May 2015 Board Meeting May 2015 Construction Update for the Stadium Repairs ALLEN INDEPENDENT SCHOOL DISTRICT
Transcript
  • M a y 2 0 1 5

    Board Meeting May 2015 Construction Update for the Stadium Repairs

    ALLEN INDEPENDENT SCHOOL DISTRICT

  • ALLEN INDEPENDENT SCHOOL DISTRICT

    Summary of Stadium Repairs Phase Description of Work of Work Phase 1 Scoreboard Complete Phase 2 Low Rise Lateral Complete Phase 3 Retaining Walls Complete Phase 4 Press Box Repairs Complete Phase 5 Exp. Joints, Complete

    One-Story Gravity Phase 6 Concourse Structure Complete at

    Home side/In Progress Phase 7 Traffic Topping In Progress

  • Stadium Repairs Scoreboard Phase 1 - Complete

  • ALLEN INDEPENDENT SCHOOL DISTRICT

    Stadium Repairs Phase 2 One Story Lateral Load Buildings on Concourse Level. The structural repairs are complete Concession Stands complete Entry towers are reconstructed Beams over gate ramps are complete

  • Allen ISD Eagle Stadium Concession Repairs 5-2015

  • Allen ISD Eagle Stadium Towers at Ramp Entries 5-2015

  • Allen ISD Eagle Stadium Ramped Entry at D 4-2015

  • ALLEN INDEPENDENT SCHOOL DISTRICT

    Stadium Repairs Phase 3 Retaining Wall Repairs Shotcrete complete Geo-foam complete Rock Anchors complete

  • Eagle Stadium Shotcrete on Retaining Wall Phase 3

  • Eagle Stadium Retaining Wall Soil Nails Phase 3

  • ALLEN INDEPENDENT SCHOOL DISTRICT

    Stadium Repairs Phase 4 Press Box Repairs Structural Steel Repairs complete from the Press box

    to the foundation Press box repairs are complete

  • Allen ISD Eagle Stadium Press box repairs complete

  • Allen ISD Eagle Stadium Press box repairs complete

  • Allen ISD Eagle Stadium Press box repairs

  • ALLEN INDEPENDENT SCHOOL DISTRICT

    Stadium Repairs Phase 5 Expansion Joints, Transfer Girders, and One Story Gravity Repairs Structural Steel Repairs complete Water shed metal roof is complete

  • Allen ISD Eagle Stadium Phase 5

  • Allen ISD Eagle Stadium Phase 5

  • ALLEN INDEPENDENT SCHOOL DISTRICT

    Stadium Repairs Phase 6 Concourse Structural Repairs Installation of FRP Composite System to concrete

    joists on-going Home side joists and beams has been wrapped and

    installation is underway on the visitor side

  • Concrete Joists repaired with FRP Application

  • ALLEN INDEPENDENT SCHOOL DISTRICT

    Stadium Repairs Phase 7 Traffic Topping Installation of a coating over the concrete concourse

    walking surface Installation has started and we are waiting on a break

    in the weather

  • Traffic Topping Installed at home side of Stadium

  • Traffic Topping Installed at the visitor side of Stadium

  • ALLEN INDEPENDENT SCHOOL DISTRICT