+ All Categories
Home > Documents > AMA D A ND OC PROJECT (4 .0 0 MTY) - Welcome to...

AMA D A ND OC PROJECT (4 .0 0 MTY) - Welcome to...

Date post: 10-Aug-2018
Category:
Upload: ngoanh
View: 220 times
Download: 0 times
Share this document with a friend
414
REVISED PROJECT REPORT FOR AMADAND OC PROJECT (4.00 MTY) OF SOUTH EASTERN COALFIELDS LIMITED (A MINI RATNA COMPANY) (JAMUNA-KOTMA AREA) UPDATED JULY 2015 REGIONAL INSTITUTE - V CENTRAL MINE PLANNING & DESIGN INSTITUTE LIMITED (An ISO 9001 & A Mini Ratna Company) (A Subsidiary of Coal India Limited) SECL COMPLEX, SEEPAT ROAD BILASPUR - (C.G.) 495006 STRICTLY RESTRICTED For Company use only The information given in this report is not to be communicated either directly or indirectly to the press or to any person not holding an official position in the CIL / Government. APPROVED ON 05.03.2016
Transcript

REVISED PROJECT REPORT FOR

AMADAND OC PROJECT (4.00 MTY)

OF

SOUTH EASTERN COALFIELDS LIMITED (A MINI RATNA COMPANY)

(JAMUNA-KOTMA AREA)

UPDATED JULY 2015

REGIONAL INSTITUTE - V

CENTRAL MINE PLANNING & DESIGN INSTITUTE LIMITED

(An ISO 9001 & A Mini Ratna Company) (A Subsidiary of Coal India Limited)

SECL COMPLEX, SEEPAT ROAD

BILASPUR - (C.G.) 495006

STRICTLY RESTRICTED

For Company use only

The information given in this report is not to be communicated either directly or indirectly to the press or to any person not holding an official position in the CIL / Government.

APPROVED ON

05.03.2016

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Contents / i of iv

REVISED PROJECT REPORT FOR AMADAND OC PROJECT (4.00 MTY)

CONTENTS Sl. No. Subject Page No.

List of Appendices ii – iii

List of Plates Board Approval Pre-Presentation

iv App1-App2

P-1

Summarised Data S1-S5

Executive summary ES1 – ES39

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

Chapter-I (Introduction) Chapter-II (Marketability & Justification) Chapter-III (Project Site Information) Chapter-IV (Geology and Deposit Appraisal) Chapter-V (Mine Boundary, Reserves & Mine Life) Chapter-VI (Method of Mining) Chapter-VII (Mining & Dumping Strategy) Chapter-VIII (Mining Schedule & Equipment Phasing) Chapter-IX (Coal Quality) Chapter-X (Pumping & Drainage) Chapter-XI (Coal Handling & Despatch Arrangement) Chapter-XII (Workshop, Store and Magazine) Chapter-XIII (Power Supply, Illumination & Communication) Chapter-XIV (Civil Construction) Chapter-XV (Safety and Conservation) Chapter-XVI (Environment Management) Chapter-XVII (Land Requirement) Chapter-XVIII (Mine Closure Planning) Chapter-XIX (Manpower, Productivity & Training) Chapter-XX (Project Implementation Schedule) Chapter-XXI (Financial Evaluation) Chapter-XXII (A Chapter on Outsourcing)

1 – 11 1 – 2 1 – 2 1 - 81 1 – 5 1 – 9 1 – 8 1 – 6 1 – 18 1 – 10 1 – 10 1 – 4 1 - 6 1 – 7 1 – 21 1 – 24 1 – 2 1 – 29 1 – 2 1 – 3 1 – 9 1 – 7

APPENDICES

Appendices A to F App. A to F

ANNEXURES

I Minutes of Planning committee meeting of SECL Dated 4/6.9.2013 An 1 - An 2

II

III IV

V

VI

VII VIII

IX

X

Minutes of Planning committee meeting of CMPDI Hq Dated 16.7.2013 Minutes of Planning committee meeting of SECL Dated 12.07.2013 Minutes of Planning Committee meeting to discuss the Revised Project Report of Amadand Opencast (4.0 Mty) held in the Conference Hall of DT(O), SECL,on dated 5th March 2014

Minutes of TSC Meeting of SECL (54th ) held on 16.06.2014 in the Conference Room of DT(P&P), SECL to discuss RPR for Amadand Opencast (4.0 Mty) List of existing HEMM as on 30.09.20104 showing ‘To be retain in project” and “To be transferred from Project” Minutes of 310th CIL Board meeting regarding costing norms Minutes of TSC Meeting of SECL (65th ) held on 31.07.2015 in the Conference Room of DT(P&P), SECL Note on RPR for Amadand OCP(4.0Mty) on Revised Financial parameters as per revised Costing Norms of CIL Extract of the 236th meeting of the Board of Directors of SECL held on Friday the 4th September 2015 at Raipur.

An 3 - An 4

An 5 - 6 An 7 - 8

An 9 - 10

An 11

An 12 An 13

An 14 -15

An 16

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Contents / ii of iv

REVISED PROJECT REPORT FOR AMADAND OC PROJECT (4.00 MTY)

LIST OF APPENDICES

OUTSOURCING OPTION

SL.

NO. PARTICULARS APPENDIX

NUMBER

1 ESTIMATED CAPITAL & COMPLETION CAPITAL ON VARIABLE COST BASIS ALONGWITH PHASING

A

2 ESTIMATED CAPITAL INVESTMENT FOR LAND A.1

3 ESTIMATED CAPITAL INVESTMENT ON CIVIL WORK A.2

4 ESTIMATED CAPITAL INVESTMENT FOR SERVICE BUILDING (PERMANENT SPECIFICATIONS)

A.2.1

5 ESTIMATED CAPITAL INVESTMENT FOR RESIDENTIAL BUILDING

A.2.2

6 BUILDING COST INDEX AT JAMUNA-KOTMA AREA (WITH REF. TO 100 BASE IN DELHI AS ON 1.10.76)

A.2.3

7 ESTIMATED CAPITAL INVESTMENT FOR PLANT & MACHINERY WITH PHASING

A.3

8 STATEMENT SHOWING THE ESTIMATED CAPITAL REQUIREMENT FOR HEMM

A3.1

8A STATEMENT SHOWING THE ITEMWISE REPLACEMENT CAPITAL FOR HEMM

A3.1.1

9 ESTIMATED CAPITAL INVESTMENT FOR ELECTRICAL PLANT & MACHINARY

A.3.2

10 ESTIMATED CAPITAL INVESTMENT FOR EXCAVATION & E&M WORKSHOP

A.3.3

11 ESTIMATED CAPITAL INVESTMENT FOR PUMPS, PIPES AND FITTINGS

A.3.4

12 ESTIMATED CAPITAL EXPENDITURE FOR COAL HANDLING PLANT

A.3.5

13 ESTIMATED CAPITAL INVESTMENT FOR OTHER P&M A.3.6

15 ESTIMATED CAPITAL INVESTMENT FOR FURNITURE AND FITTINGS

A.4

16 ESTIMATED CAPITAL REQUIREMENT FOR COAL STOCKING, DESPATCH & RAILWAY SIDING

A.5

17 ESTIMATED CAPITAL INVESTMENT FOR VEHICLES A.6

18 ESTIMATED CAPITAL INVESTMENT FOR PROSPECTING & BORING

A.7

19 ESTIMATED CAPITAL INVESTMENT ON CAPITAL OUTLAY IN MINES

A.8.1

20 ESTIMATED CAPITAL INVESTMENT FOR ROADS AND CULVERTS

A.8.2

21 ESTIMATED CAPITAL INVESTMENT FOR WATER SUPPLY ARRANGEMENTS

A.8.3

22 ESTIMATED CAPITAL INVESTMENT FOR SEWAGE DISPOSAL SCHEME

A.8.3(A)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Contents / iii of iv

SL.

NO. PARTICULARS APPENDIX

NUMBER

23 THE JOB/CATEGORYWISE INVESTMENT OF MANPOWER

B

24 SUMMARY OF MANPOWER SCALE/GRADE CATEGORY WISE AND CALCULATION OF ANNUAL SALARY WAGES & BENEFITS

B.1

25 ESTIMATED COST OF PRODUCTION PER TONNE OF COAL AT 100% CAPACITY INCLUDING COST OF EMP

C

26 COST & PROFITABILITY AT DIFFERENT LEVELS OF PRODUCTION

C.1

27 ANNUAL EXPENDITURE FOR EMP & IMPACT OF COST/TE ON COAL

C.2

28 SENSITIVITY ANALYSIS AT DIFFERENT LEVEL OF CAPACITY UTILISATION

C.3

29 SENSITIVITY ANALYSIS OF THE PR C.4

30 IRR OF THE PROJECT i) AT 100% LEVEL OF PRODUCTION ii) AT 85% LEVEL OF PRODUCTION

D1 D2

31 THE CALCULATION OF REVENUE CASH OUTFLOW AT 100% LEVEL OF PRODUCTION

E1

32 THE CALCULATION OF REVENUE CASH OUTFLOW AT 85% LEVEL OF PRODUCTION

E2

33 THE ESTIMATED CAPITAL INVESTMENT FOR REHABILITATION AND ENVIRONMENTAL MANAGEMENT

F

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Contents / iv of iv

REVISED PROJECT REPORT FOR AMADAND OC PROJECT (4.00 MTY)

LIST OF PLATES

Plate

No. Particulars Drawing No. Scale

1 Location Plan R5/MOC/X00 NTS

2 Topographic-cum-Geological Plan R5/MOC/X00 1:5000

3 Final Stage Quarry Plan R5/MOC/X00 1:5000

4 Final Stage Dump Plan R5/MOC/X00 1:5000

5 Mining System R5/MOC/X00 1:5000

6 Seam extent Plan of Seam LK-2 (Bottom) & LK2(Comb) R5/MOC/X00 1:5000

7 Seam extent Plan of Seam LK-2 (Top) R5/MOC/X00 1:5000

8 Seam extent Plan of Seam L-1 R5/MOC/X00 1:5000

9 Seam extent Plan of Seam LK-1 R5/MOC/X00 1:5000

10 Seam extent Plan of Seam MK (Bottom) & MK(Comb) R5/MOC/X00 1:5000

11 Seam extent Plan of Seam MK (Top) R5/MOC/X00 1:5000

12 Seam extent Plan of Seam L-3 (Bottom) & L3(Comb) R5/MOC/X00 1:5000

13 Seam extent Plan of Seam L-3 (Top) R5/MOC/X00 1:5000

14 Seam extent Plan of Seam L-4 R5/MOC/X00 1:5000

15 Seam extent Plan of Seam UK (Top) R5/MOC/X00 1:5000

16 Seam extent Plan of Seam UK (Bottom) & UK(Comb) R5/MOC/X00 1:5000

17 Iso-parting between Seams LK-2 (Top) & LK-2 (Bottom) R5/MOC/X00 1:5000

18 Iso-parting between Seams LK-2 (T/C) & L-1 R5/MOC/X00 1:5000

19 Iso-parting between Seams L-1 & LK-1 R5/MOC/X00 1:5000

20 Iso-parting between Seams LK-1 & MK (B/C) R5/MOC/X00 1:5000

21 Iso-parting between Seams MK-B & MK-T R5/MOC/X00 1:5000

22 Iso-parting between Seams MK(T/C) & L-3 (B/C) R5/MOC/X00 1:5000

23 Iso-parting between Seams L-3 (B) & L-3 (T) R5/MOC/X00 1:5000

24 Iso-parting between Seams L-3 (T/C) & L-4 R5/MOC/X00 1:5000

25 Iso-parting between Seams L-4 & UK (B/C) R5/MOC/X00 1:5000

26 Iso-parting between Seams UK (B) & UK (T) R5/MOC/X00 1:5000

27 Top OB Plan R5/MOC/X00 1:5000

28 Total excavation on floor of Seam LK-2(B/C) R5/MOC/X00 1:5000

29 Cross-section 1-1’ to 5-5’’ R5/MOC/X00 1:2000

30 Before Mining Land Use Plan R5/MOC/X00 1:5000

31 After Mining Land Use Plan R5/MOC/X00 1:5000

32 Fifth year stage plan R5/MOC/X00 1:5000

33 Tength year stage plan R5/MOC/X00 1:5000

34 Fifteenth year stage plan R5/MOC/X00 1:5000

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 App/ 1 of 2

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 App/ 2 of 2

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 P / 1 of 1

REVISED PROJECT REPORT

FOR AMADAND OPENCAST PROJECT (4.00 MTY)

PRE-PLANNING INTERACTIVE PROCESSING

Sl.No. Particulars Date of Record

Notes

1. Draft Project Report prepared and circulated on

29st May,2013

2. Minutes of Planning Committee Meeting held on 12.07.2013 in the Board Room of DT(O), SECL to discuss the draft PR of Amadand OC(4.0 Mty)

12th July, 2013

3. Re Record Note of discussions held on 16.07.2013 during the presentation of draft PR for Amadand OC (4.0 Mty) at CMPDI, HQ, Ranchi.

16th July, 2013

4. Final Project Report prepared and submitted.

7th January, 2014.

5. Planning Committee meeting to discuss the Revised Project Report of Amadand Opencast (4.0 Mty) held in the Conference Hall of DT(O), SECL,on dated 5th March 2014

5th March, 2014

6. TSC Meeting of SECL (54th ) held on 16.06.2014 in the Conference Room of DT(P&P), SECL to discuss RPR for Amadand Opencast (4.0 Mty)

16th June, 2014

7. Final Revised Project Report Updated and re-submitted.

October 2014

8. Final Revised Project Report Updated and re-submitted.

July 2015

9. TSC Meeting of SECL (65th ) held on 31.07.2015 in the Conference Room of DT(P&P), SECL to discuss RPR for Amadand Opencast (4.0 Mty)

31 July 2015

10 RPR recommended by 236th SECL Board on dated 4th September 2015 for onward submission to CIL Board

4th Sept 2015

11 RPR approved by 325th CIL Board on dated 5th March 2016 held at CIL Headquarter, Kolkata.

5th March 2016

SUMMARISED DATA

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 SD / 1 of 5

REVISED PROJECT REPORT FOR AMADAND OPENCAST PROJECT (4.00 MTY)

SUMMARISED DATA

Sl. No. Particulars Unit Value

A. GENERAL

1 Name of Project AMADAND OPENCAST

2 Name of Area / Company Jamuna-Kotma Area

3 Nearest Railway Station from project Name

km

Manendragarh

15

4 Nearest National / State Highway / Approach Road Name

km

Manendragarh - Pendra Road

B. GEOLOGICAL

1 Name of geological blocks considered Name Amadand OC Block 2 Area of the geological blocks(part area) sq. km. 15.061

3 Borehole Density within blocks BHs

/ Sq.km. 15.20

C. TECHNICAL

1 Area of the proposed mine boundary Ha 715.02

2 Borehole density within mine area BHs

/sq. km 14.12

3 Mine parameters (Quarry-wise)

Extent along strike (min. – max.)

Extent along dip (min. - max.)

m

m

2560-3220

2600

4 Description of coal seams proposed to be worked

along with the parting details

Coal Seam Name/Parting

Generalised thickness range(m)

Av. Grade

Av.

gradient

(in

degrees)

Depth

range (m)

Mineable

Reserves (Mt)

As on

01.04.2015

Volume of

OB (Mcum)

As on

01.04.2015

Top OB 20.00-40.00 144.05

Seam-UKTOP & UK comb

0.80-1.65 C - D 1 in 30 10-37 21.85

Parting 1.00-3.00 1.18

Seam-UKBOT 0.40-1.00 C 1 in 30 15-33 0.80

Parting 10.0-17.0 140.10

Seam-L4 0.10-0.40 B 1 in 30 17-60 0.77

Parting 10.00-20.00 116.36

Seam-L3T & L3 0.10-0.60 C - D 1 in 30 30-80 2.10

Parting 1.00-4.50 8.45

Seam-L3B 0.15-0.55 C 1 in 30 23-80 0.42

Parting 1.50-4.00 36.40

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 SD / 2 of 5

Coal Seam Name/Parting

Generalised thickness range(m)

Av. Grade

Av.

gradient

(in

degrees)

Depth

range (m)

Mineable

Reserves (Mt)

As on

01.04.2015

Volume of

OB (Mcum)

As on

01.04.2015

MKTOP & MK Comb 0.25-1.70 F - G 1 in 30 15-90 22.04

Parting 1.00-6.75 4.45

MKBOT 0.30-1.25 C 1 in 30 15-90 1.86

Parting 13.50-23.00 163.75

LK1 0.10-0.80 D 1 in 30 34-122 4.47

Parting 11.00-19.00 123.96

L1 0.15-0.80 C 1 in 30 45-137 1.13

Parting 3.00-25.00 23.44

LKIITOP & LK2 comb 0.40-1.00 B - C 1 in 30 65-147 12.31

Parting 2.26

LKIIBOT 0.18-1.20 B 1 in 30 69-152 2.70

Total Coal/OB

70.46 764.40

5 Av. Stripping Ratio cum/t 10.85

6 Method of Mining Coal with Surface Miner

OB with Shovel – Dumper

7

Target Output

Nominal production capacity (at

100%)

Peak production capacity (at 135%)

Production capacity (at 85%)

Mt

Mt

Mt

4.0

5.40

3.40

8 Year of achieving Target Production

(from zero date)

3rd

9 Year of start of Internal Dumping 4th

10 Production Phasing (from zero date

upto target year) Mt

Year / Coal Seam Year 1 Year 2

Year

3 Year 4 Year 5

Coal 2.00 3.00 4.00 4.00 4.00

OB 20.59 36.91 52.54 52.54 52.54

Sl. No. Particulars Unit Outsourcing

11 Total Mine Life (at Nom. production

capacity)

Pre-construction period

Construction period

Production build-up period

Production period

Tapering / mine closure period

Years

Years

Years

Years

Years

19

-

-

3

15

1

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 SD / 3 of 5

Sl. No. Particulars Unit Outsourcing

12 Major HEMM Deployed for Coal

Surface miner

Dumper

Dozer

Nos. &

Capacity

Outsourced

13 Major HEMM Deployed for OB

Dragline

Shovel

Dumper

Drill

Dozer

Nos. &

Capacity Outsourced

14 Total Manpower

Existing

Additional

Nos

Nos.

Nos.

244

462

(-) 218

15 a) OMS excluding outsourcing manpower Tonnes 39.11

16 Seam-wise weighted average grade of

coal (non-coking LF)

Mean GCV

Kcal/Kg

G-8

4933

17 Presence of Major Surface Constraints

(Nallas, road, power line, etc.)

(type) Diversion of

HT line

18 Coal Transport within the mine

(In-pit belt conveying system or by

Truck)

Inpit Belt

19 Surface Coal Transport to

Siding/Despatch Point and Mode of

Despatch

By Belt

20 Any Railway Siding and distance Upcoming

Amadand

siding (1.5Km)

21 Name of any Specific

Customer/Industry

Miscellaneous

D. ENVIRONMENTAL & OTHERS

1 Civil Construction Residential houses

Existing Additional

Nos. Nos. Nos.

135

135

2 Water Demand Total Total

Colony Industrial

MLD MLD

0.717 0.123 0.594

3 Additional Land to be acquired Total Government land

Tenancy land Forest land (type of forest)

Ha Ha Ha Ha

740.63 129.79 610.84 0.00

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 SD / 4 of 5

Sl. No. Particulars Unit Outsourcing

4 Additional Land to be acquired within mine area (excavation area)

Government land Tenancy land

Forest land (type of forest)

Ha

Ha Ha Ha

141.71

50.461 91.245 0.00

5 Additional Land to be acquired outside mine area (Beyond Excavation Area, such as, Approach Road, Infrastructure, Colony, etc.)

Ha

598.92

6 Land to be acquired for external

dumping

Ha 356.70

7 Net Present Value of Forest Land Total Area

Total Value

Rs.Lakhs/Ha Ha

Rs.Lakhs

10.0 0.00 0.00

8 Rehabilitation & Resettlement

No. of villages within mine boundary

No. of PAFs to be rehabilitated

Nos.

Four

1100 9 Cost of land & Rehabilitation

Total Cost

R&R only

Rs. crores

7821.89

10 Total EMP Capital Rs. Lakhs 10199.03

11 Average annual rainfall mm 1200

12 Max. Make of Water Cu.m/day 503336

13 Total installed pumping capacity lps 1490

14 Drainage of the Area Through Kewai

River

15 Any proposed diversion of road or

power line

Diversion of

HT line, Road

E. FINANCIAL

1 Total Capital Investment Existing

Additional

Total Rs. crores

108.83

760.61

869.44

2 Specific Investment Rs. /tonne 2173.60

3 Total Capital Investment on P&M

Existing

Additional

Total

Rs. crores

74.08

324.68

398.76

4 Specific Investment on P&M Rs. / tonne 996.90

5 Capital requirement upto target year Rs. crores 389.43

6 Earnings per manshift (EMS) Rs. 3384.01

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 SD / 5 of 5

Sl. No. Particulars Unit Outsourcing

7 Estimated Cost of Production

At 100% production level

At 85% production level

Rs. / tonne

1074.40

1120.68

8 Estimated average selling price

(at 95% sales realization)(power sector

price)

Rs. / tonne

1298.22

9 Estimated Profit

At 100% production level

At 85% production level

Rs. / tonne

223.82

177.54

10 Financial Internal rate of return (FIRR)

At 100% production level

At 85% production level

%

21.33

13.55

11 Economic rate of return (only for

projects to be approved by Govt.)

At 100% production level

At 85% production level

%

-

-

12 Break-even point

Production

Production level

Mty

%

2.16

53.95

13 Cost of Outsourcing (average)(Excl ST)

OB

Coal

(Coal cost includes surface miner

cutting, loading and transport cost)

Rs/cum

Rs/tonne

52.53

69.81

14 Mine Closure Cost (for corpus fund) Rs./t 26.84

15 Expected Completion Capital Rs. crores 912.28

*******

EXECUTIVE

SUMMARY

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 1 of 39

EXECUTIVE SUMMARY

1.1 INTRODUCTION

The Amadand Opencast Block is located in the Eastern part of South

Sohagpur Coalfield and is flanked by working mines of Hasdeo and

Jamuna & Kotma areas of South Eastern Coalfields Limited (SECL) to the

east and west respectively. Chronology of last approved reports of

Amadand OC are as follows.

SL NO

Particulars Capacity (Mty)

Vertical Bound

Option Approval Remarks

1 Amadand OC (1.15 Mty)

1.15 UK seam Departmental Approved on Sept 1997

As Replacement of Jamuna OC with Dragline

2 Amadand OC (1.15 Mty)

1.15 UK seam Departmental Approved on Sept 2003

With Revised working norms and with Dragline

Project Report for Amadand OC (1.15 Mty) was prepared with an average

stripping ratio of 4.58 cum/t considering only upper seam i.e UK seam and

submitted to SECL in August 2003 and approved in Sept 2003 with a

capital of 83.39 Crores. Presently, Amadand OC (1.15 Mty) is operating as

per this approval of the project report.

1.1.1 SALIENT FEATURES OF LAST APPROVED REPORT

Annual Capacity of the mine (Mty) : 1.15

Initial Capital Investment (Rs. Crs.) : 83.39

Specific investment (Rs./t) : 725.09

Investment on HEMM (Rs. Crs.) : 24.45

(Rs. per tonne of Annual Output) : 212.61

Investment on P&M (Rs. Crs.) : 37.05

(Rs. per tonne of Annual Output) : 322.17

Cost of Completion (Rs. Crs.) : 92.85

Net Extractable Reserve (Mt) : 36.04

Average Grade of Coal : ‘D’(L/F)

Total Volume of Overburden (MCum) : 165.00

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 2 of 39

Average Stripping Ratio : 4.58

Total Life of Mine (years) : 34

Year of Achieving Target : 4th

Total Manpower Required : 679

Overall OMS (t) : 6.41

Estimated Cost of Production (Rs./t)

at 100% Capacity Utilisation : 522.14

at 85% Capacity Utilisation : 585.18

Average selling price (Rs/t) : 751.50

Profit at ruling sale price (Rs/t)

at 100% Capacity Utilisation : 229.36

at 85% Capacity Utilisation : 166.32

BEP of the project (%) : 60.90

FIRR (%)

at 100% Capacity Utilisation : 36.17

at 85% Capacity Utilisation : 20.82

1.2.2 PAST PERFORMANCE OF THE EXISTING MINES

Past performance of the mine showing yearwise coal, OB removal, cost of

production and profitability of mine for last few years are as given in the table.

YEAR COAL (MT)

OB (Mcum)

YEARWISE SR

COST OF PROD

SELLING PRICE

PROFIT / LOSS

(Rs/Per Te) Rs/Per Te (Rs/PerTe)

2009-10 0.13 1.07 8.23 522.54 91.33 (-)431.20

2010-11 0.48 1.23 2.56 1211.58 1365.15 153.57

2011-12 0.63 2.28 3.62 1226.24 1688.96 462.71

2012-13 1.15 5.92 5.15 1059.34 2006.13 946.79

2013-14 1.15 4.87 4.23 261.19 1949.62 1688.42

2014-15 1.15 6.17 5.36 1557.55 1971.96 414.42

1.2 EXPLORATION STATUS

The area was identified by CMPDI for scout drilling in March 1989 on the

basis of some boreholes drilled close to some of the GSI boreholes,

namely, SM-4, 6&8 etc. in the eastern part of the Amadand tract and

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 3 of 39

DGM (MP) was entrusted for scout drilling. The results of the scout

drilling conducted by DGM (MP) revealed presence of good quality

workable coal deposit in an area of about 60 sq.km of the intervening

Amadand tract between the working mines of SECL.

Detailed exploration of the area was taken up by CMPDI in August 1990

and comprehensive geological information was provided in Geological

reports on Bartarai Block in December 1993, Amadand Opencast area in

December 1995, Bakulmuni Block in July 1997, Amadand East U/G Block

in January 1998 and Amadand West U/G Block in November 1999. The

block measures 15.061 sq.km. which includes 14.154 sq.km. free area

and 0.907 sq.km. forest area.

The borehole density within the block is 15.20 BH / sq km.

1.4 JUSTIFICATION OF PREPARATION OF RPR

Amadand OC (1.15 Mty) was prepared with an average stripping ratio of

4.58 cum/t considering only upper seam i.e UK. Later on, decisions were

taken to extract coal from bottom seams upto bottom most LK-II seam.

Accordingly, this report is formulated considering all the seams upto bottom

most LK-II seam for mining with outsourcing option.

Liberalisation of power sector by Government of India has generated

wide spread interests for private and public sector investments in power

generation and other industrial development. As such, there is an

appreciable increase in the number of upcoming new projects in both

private and public sectors. The demand projection from SECL for the

year 2015-16 is 269.97 Mt, as given in Table 2.1. It will cater to the needs

of the upcoming industries like power, Cement, Fertilizers, other

industries etc. The demand projection from SECL for the year 2016-17

is 270.37 Mt. The projected availability in the year 2016-17 is 150.00 Mt

and there will be shortage of 120.37 Mt.To meet the demand of coal, it is

required to open new projects.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 4 of 39

Average grade of coal of Amadand Opencast is grade ‘G-8’ with mean

GCV is 4933 Kcal/Kg. RPR for Amadand Opencast (4.0 Mty) prepared to

enhance coal production to fulfill the above indicated growth in demand.

1.5 SALIENT FEATURES OF PRESENT PR (CAPACITY, CAPITAL, ETC.)

Sl. No. Particulars Unit Quantity

I. Coal Seams

1 Dominant Thickness of Seams

UK Top m 0.80-1.65

UK Bottom m 0.50-1.00

UK (Comb) m 0.80-4.00

L-4 m 0.50-0.60

L-3 Top m 0.50-0.60

L-3 Bottom m 0.50-0.60

L-3 (Comb) m 0.50-1.50

MK Top m 0.50-1.70

MK Bottom m 0.50-1.25

MK (Comb) m 0.70-4.00

LK-1 m 0.50-0.80

L-1 m 0.50-0.80

LK-2 Top m 0.50-1.00

LK-2 Bottom m 0.50-1.20

LK-2 (Comb) m 0.50-2.25

Average Dip Degree 1 in 30

2 Av. Specific gravity of coal in seams t/cum 1.52

II. Overburden / partings

3 Dominant Thickness

Top OB m 20.00-40.00

Between UK Top & UK Bottom m 1.00-3.00

Between UK Bottom, UK & L-4 m 10.00-18.00

Between L-4 & L-3 m 10.00-20.00

Between L-3 Top & L-3 Bottom m 1.00-4.50

Between L-3 & MK Top m 1.50-8.00

Between MK Top & MK Bottom m 1.00-6.75

Between MK & LK-1 m 15.00-35.00

Between LK-1 & L-1 m 11.00-19.00

Between L-1 & LK-2 Top m 3.00-25.00

Between LK-2 Top & LK-2 Bottom m 1.00-4.00

4 Seamwise Mineable Reserves

UK Top & UK Comb Mt 21.85

UK Bottom Mt 0.80

L-4 Mt 0.77

L-3 Top & L-3 Comb Mt 2.10

L-3 Bottom Mt 0.42

MK Top & MK Comb Mt 22.04

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 5 of 39

Sl. No. Particulars Unit Quantity

MK Bottom Mt 1.86

LK-1 Mt 4.47

L-1 Mt 1.13

LK-2 Top & LK-2 Comb Mt 12.31

LK-2 Bottom Mt 2.70

Total (as on 01.04.2015) Mt 70.46

5 Av.Specific Gravity of OB t/cum 2.40

6 Volume of OB (as on 01.04.2015) Mcum 764.40

7 Stripping Ratio (Av.) cum/t 10.85

8 Target Output Mt/Yr. 4.0

9 Peak OBR(based on natural OB) Mcum/yr. 52.54

10 Project life Year 19

Financial Parameters

OUTSOURCING

OPTION

11

a) Total capital investment b) Capital outlay per te of annual output

Rs. Crores

Rs./t

869.44

2173.60

12 a) Capital requirement of P&M b) Per tonne of annual output

Rs. crores Rs./t

398.76 996.90

13 Selling price (95% of notified selling price) )(power sector price)

Rs./ t 1298.22

14 Estimated cost of production a) at 100% level of production b) at 85% level of production

Rs./t Rs./t

1074.40 1120.68

15 Profit per tonne a) at 100% level b) at 85% level

Rs./t Rs./t

223.82 177.54

16 Break-even-point (%) (Mty)

53.95 2.16

17 No. of personnel 244

18 OMS excluding contractor workers t 59.17

19 EMS Rs. 3384.01

20 Anticipated year of achieving target Year 3rd

21 IRR at 100% level of production % 21.33

22 IRR at 85% level of production % 13.55

23 Completion capital of the project Rs.

crores 912.28

The PR has been formulated to win coal by Surface Miner with FEL and

trucks/dumpers & OB by Shovel Dumper combination. Transport of coal from

face to railway siding will be done by inpit belt conveyor & surface belt

conveyor.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 6 of 39

Both winning of coal and extraction of OBR will be done through outsourced

HEMM. PR is giving IRR 13.55% at 85% level of production. The overall grade

of coal is “grade G-8” with GCV 4933 Kcal/Kg, which is easily marketable. As

per the guidelines, a Project is economically viable when it achieves more than

12% IRR at 85% level of Production. Since, this Project is having Internal Rate

of Return more than 12% at 85% level of target production i.e. 13.55% and

hence Outsourcing Option of this project is economically viable project.

The outsourcing option of RPR for Amadand Opencast Project (4.00Mty)

was placed before SECL Board’s 236th meeting held at Raipur on dated

04.09.2015 for a total capital of Rs 869.44 Crores and SECL Board directed to

submit the same to CIL, since capital provision in the RPR exceeds Rs 500

Crores.

Accordingly, RPR for Amadand Opencast Project (4.00Mty) was placed

before 325th CIL Board meeting held at Kolkata on dated 05.03.2016 for a total

capital of Rs 869.44 Crores. CIL Board accorded its approval to Project Report

for Amadand Opencast Project for a rated capacity of 4.00 Mty at an estimated

capital investment of Rs 869.44 Crores for implementation of the project with

total outsourcing variant i.e both coal and OB outsourcing.

1.5 DIFFICULTIES AND CONSTRAINTS IN MINING WITH ASSOCIATED RISK

(i) The nearest railway siding is Govinda Railway siding which is

situated at a distance of about 5.0Km from the mine. The railway

line extension from Bhaiyatola station is required to connect the

upcoming Amadand siding.

(ii) Rehabilitation & resettlement of four villages namely Nimha,

Timkitola-Amadand, Harratola-Kuhka and Majholi are involved in

the project. Acquisition of land alongwith R&R of PAP is a critical

activity and should be taken up on top priority.

1.6 PEAK CAPACITY Sometimes with favorable geo-mining conditions and improved

productivity of the HEMM, the project may produce coal upto 1.35 times of

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 7 of 39

the planned capacity. So, EMP should be prepared for 5.40 Mty,

accordingly approval from the Competent Authority is to be sought.

1.7 FLEXIBILITY IN IMPLEMENTATION The flexibility in the implementation stage may be exercised within the

approved cost estimates to respond to improvements in technology and

equipment which would result in improved profitability and productivity

measures. Following points may be considered under the flexibility: -

a) Re-alignment of project working for better working layout / dump etc.

b) Change in the specification of HEMM, for techno-economic consideration,

to higher capacity at the time of procurement of new equipment or

replacement of the equipment.

c) To procure state-of-the-art safety equipment, whenever they are

introduced, even if the same is not provided in approved Project Report.

d) Relocation of site for infrastructure facilities depending upon techno-

economic reasons and availability of land / forest area etc.

e) Hiring of equipment for loading, transportation etc., at a competitive price,

so as to cater to the needs of increased demand of coal and subsequent

removal of higher OB and for augmentation of coal production.

f) For upgradation of new technology in mining method for improving

performance and reduction in manpower, at a subsequent date after

project completion.

g) In this PR it is proposed that coal would be mined by surface miner.

However, in circumstances where Operational/Geotechnical difficulties

persist small quantity of coal may be mined out by alternative technology

such as ripping/drilling etc. Prior approval may be obtained for use of

alternative technology citing the circumstances/operational difficulties.

1.8 CRITICAL ACTIVITIES PRIOR TO ENVIRONMENT CLEARENCE

Critical activities, which could be taken up prior to environmental, forestry

and other statutory clearances to expedite project implementation are as given

below.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 8 of 39

a) Northern boundary of quarry is to be exposed upto UK seam along the

full strike length of the quarry. This is required to reach quarry floor of 4.0

Mty report to create internal dumping space at the earliest.

b) The acquisition of R&R site should be processed to take possession of

the R&R site to rehabilitate the project affected family at the earliest.

c) The northern side garland drain is to be constructed first to prevent inrush

of water from northern side. As quarry advances towards the south, the

other garland drains will be constructed as per requirement.

d) Preliminary study about extension of railway line and its tentative

alignment from Bhaiyatola rail station or other suitable location is to be

done to connect Amadand Siding.

2.1 DEMAND AND SUPPLY SCENARIO (COMPANY) The demand projection from SECL for the year 2014-15 is 269.67 Mt,

as given in Table 2.1. It will cater to the needs of the upcoming industries like

power, Cement, Fertilizers, other industries etc. The projected availability in

the year 2014-15 is 131.00 Mt and there is shortage of 138.67 Mt. The

demand projection from SECL for the year 2016-17 is 270.37 Mt. The

projected availability in the year 2016-17 is 150.00 Mt and there will be

shortage of 120.37 Mt as shown in Table 2.1.

3.1 LOCATION

The Amadand Opencast Block (Plate 1) located 8 km SE of Kotma town

is bounded by latitudes 23O07'28" & 23O09'46" N and longitudes

82O02'04" & 82O04'53" E (approx.). It falls on the Survey of India Topo-

sheet No.64 I/4 (RF1:50,000) within Anuppur district of Madhya Pradesh.

The Baihatola railway station on the Anuppur-Chirimiri/ Bisrampur section

of SE Central Railway is located at a distance of 8 km. due north. The crow

fly distances from Rajnagar colliery railway siding and Kotma colliery

railway siding from the opencast area are about 8km and 7km respectively.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 9 of 39

3.1.1 Limiting boundaries of proposed Quarry area

The quarriable area for the opencast mining is shown on Plate No. 3. The

boundary of Amadand Opencast Project is as follows:

North : Incrop of Upper Kotma Seam. South : Incrop of Upper Kotma Seam. East : A line keeping 100 m barrier from boundary of Amadand

Village. West : Incrop of Upper Kotma Seam.

4.1.2 Geological Block Boundaries

The geographical boundary of Amadand Opencast block is as follows:

North : Floor of incrop of Upper Kotma Seam and E-W

trending Fault F1-F1 (Southern boundary of Khodri

Block).

South : Floor Incrop of seam MKB.

East : A line connecting common boundary of Bakulmuni

and Bartarai blocks passing through borehole

CMAD-235A.

West : Floor Incrop of Upper Kotma Seam along boreholes

CMAD-638, 539, 262 and line passing through

boreholes CMAD-112 & 511.

The block measures 15.061 sq. km which includes 14.154 Sq. km free

area and 0.907sq.km forest area.

4.1.2 DESCRIPTION OF GEOLOGICAL RESERVES

A total of 160.57 Mt of proved geological reserves of coal have been estimated

in Amadand OC Block. These includes 68.27 Mt (42.52%) superior grade

coal of (A, B, C) grade and 90.30 Mt (57.48%) coal of inferior grade (D, E,

F,G).

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 10 of 39

Out of the total Net Proved Geological Reserves of 160.57 Mt of coal

6.19% is of ‘A’ Grade, 11.45% is of ‘B’ Grade and the bulk of the reserves, i.e.

24.87% falls under ‘C’ Grade, 23.40% is of ‘D’ Grade, 9.53% is of ‘E’ Grade,

11.53% is of ‘F’ Grade and 13.03% in ‘G’ Grade. The quarriable reserves

falling in the total proved category are within 170.00m depth.

NET GEOLOGICAL RESERVES WITHIN THE BLOCK AREA

Seam-wise, Grade-wise ‘Net’ Proved Geological Reserves within Forest and Non-Forest areas, Amadand OC Block, Sohagpur Coalfield

(Figures in million tones)

Coal seams

<----------------------GRADE-----------------------> TOTAL A B C D E F G

UKT 0.986 1.108 0.288 0.018 0.019 2.419

UKB 0.062 0.712 0.681 0.029 0.017 0.121 1.622

UK 0.698 14.488 18.614 3.606 0.712 0.133 38.250

L4 0.241 1.056 0.520 1.818

L3T 0.636 0.563 0.376 0.280 0.179 0.078 2.113

L3B 0.202 0.268 0.461 0.290 1.222

L3 0.136 1.202 2.729 1.664 0.542 0.065 6.339

MKT 0.024 0.080 0.152 0.335 1.890 16.532 19.012

MKB 0.025 2.492 6.391 3.521 0.318 0.096 0.029 12.871

MKC 0.560 2.175 6.175 14.120 3.931 26.961

LKI 0.039 0.428 3.409 3.225 1.274 0.343 0.005 8.724

L1 0.162 0.419 0.746 0.843 0.187 0.046 0.061 2.466

LKIIT 0.464 0.790 1.020 0.984 0.115 3.372

LKIIB 0.685 2.104 0.781 0.124 3.695

LKII 8.254 7.709 8.128 4.059 1.019 0.453 0.082 29.703

GRAND TOTAL

9.932 18.392 39.945 37.581 15.298 18.522 20.917 160.587

% 6.19 11.45 24.87 23.40 9.53 11.53 13.03 100.000

5.1 MINE BOUNDARIES

The quarriable area for the opencast mining is shown on Plate No.3 &

Figure-5.1. One quarry on floor of Seam LK-II has been planned. The

boundary of quarry has been fixed as follows: -

North : Incrop of Upper Kotma Seam

Reason- Beyond UK seam incrop the stripping ratio is

high (more than 20).

South : Incrop of Upper Kotma Seam

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 11 of 39

Reason- Beyond UK seam incrop the stripping ratio is

high (more than 20).

East : A line keeping 100 m barrier from boundary of Amadand

Village and Pendra-Manendragarh road.

Reason-. Amadand UG and Bartarai UG mine is operating

on the other side of road.

West : Incrop of Upper Kotma Seam

Reason- Beyond UK seam incrop the stripping ratio is high

(more than 20).

Khodri Block has not been included in the proposed mine area. The

incrop of coal seams also exists in the northern side of Khodri Block.

Thus, Khodri Block can be extracted from the northern side of the block

as a separate mine.

5.2 MINEABLE RESERVES

As on 01.04.2015, the total mineable reserves within the quarry have

been estimated as 70.46 Mt with a corresponding OB volume of 764.40

Mcum. The already extracted coal & OB removal has been deducted to

get the balance remaining coal & OB quantity. While, calculating

mineable reserves, a geological loss of 10% and a mining loss of 10%

have been considered.

6.1 MINE PARAMETERS The geological and mining characteristics of both the quarries have been

summarised in the following table: -

Geological and Mining Characteristics

Sl. No. Particulars Unit Quantity

I. Coal Seams

1 Dominant Thickness of Seams

UK Top m 0.80-1.65

UK Bottom m 0.50-1.00

UK (Comb) m 0.80-4.00

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 12 of 39

Sl. No. Particulars Unit Quantity

L-4 m 0.50-0.60

L-3 Top m 0.50-0.60

L-3 Bottom m 0.50-0.60

L-3 (Comb) m 0.50-1.50

MK Top m 0.50-1.70

MK Bottom m 0.50-1.25

MK (Comb) m 0.70-4.00

LK-1 m 0.50-0.80

L-1 m 0.50-0.80

LK-2 Top m 0.50-1.00

LK-2 Bottom m 0.50-1.20

LK-2 (Comb) m 0.50-2.25

Average Dip Degree 1 in 30

2 Av. Specific gravity of coal in seams t/cum 1.52

II. Overburden / partings

3 Dominant Thickness

Top OB m 20.00-40.00

Between UK Top & UK Bottom m 1.00-3.00

Between UK Bottom, UK & L-4 m 10.00-18.00

Between L-4 & L-3 m 10.00-20.00

Between L-3 Top & L-3 Bottom m 1.00-4.50

Between L-3 & MK Top m 1.50-8.00

Between MK Top & MK Bottom m 1.00-6.75

Between MK & LK-1 m 15.00-35.00

Between LK-1 & L-1 m 11.00-19.00

Between L-1 & LK-2 Top m 3.00-25.00

Between LK-2 Top & LK-2 Bottom m 1.00-4.00

4 Seamwise Mineable Reserves (As on 1.4.2015)

UK Top & UK Comb Mt 21.85

UK Bottom Mt 0.80

L-4 Mt 0.77

L-3 Top & L-3 Comb Mt 2.10

L-3 Bottom Mt 0.42

MK Top & Bottom Mt 22.04

MK Bottom Mt 1.86

LK-1 Mt 4.47

L-1 Mt 1.13

LK-2 Top & LK-2 Comb Mt 12.31

LK-2 Bottom Mt 2.70

Total Mt 70.46

5 Av. Specific Gravity of OB t/cum 2.40

6 Volume of OB (As on 1.4.2015) Mcum 764.40

7 Stripping Ratio (Av.) cum/t 10.85

8 Target Output Mt/Yr. 4.0

9 Peak OBR Mcum/yr. 52.54

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 13 of 39

Sl. No. Particulars Unit Quantity

10 Project life Year 21

III. Quarry Parameters

1 Maximum width along strike

- at surface m 3220

- at floor m 2880

2 Minimum width along strike

- at surface m 2560

- at floor m 1890

3 Maximum length along dip

- at surface m 2600

- at floor m 2250

4 Maximum depth m 152.50

5 Minimum depth m 120

6 Maximum lift m 158

7 Area of excavation

- at surface Ha 694.80

- at floor Ha 515.35

6.2 HAUL ROAD

Haul roads have been planned at a maximum gradient of 1 in 16, the width

of the haul road has been kept as 30 m for two way dumpers transport. Two

batter road of 50m width will be maintained along UK seam & MK seam for

laying side road and inpit belt conveyor.(details given in chapter 11)

6.3 EQUIPMENT SELECTION

In this PR, Coal and OB is proposed to be worked by outsourced

equipment. OB is proposed to be excavated by shovel dumper

combination. It is envisaged that coal would be mined by surface miner. In

this PR it is proposed that coal would be mined by surface miner. However,

in circumstances where Operational/Geotechnical difficulties persist small

quantity of coal may be mined out by alternative technology such as

ripping/drilling etc. Prior approval may be obtained for use of

alternative technology citing the circumstances/operational difficulties.

In the outsourcing option blasting will be done departmentally and

both OB and coal will be worked by outsourcing. To handle the larger OB

quantity optimum no. of equipment with optimum capacity is proposed be

used. Due to flexibility of operation, Shovel-Dumper combination will be

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 14 of 39

suitable for OB removal for working multiple seams and partings.

Considering huge volume of OB removal higher size of HEMM like 10

cum Shovels with 100T rear dumpers may be used for OBR by

outsourcing agency. For thin partings, smaller backhoe may be used.

Few auxiliary HEMM has been given for mine development and

reclamation related work. Transport of coal from face to railway siding

will be done by inpit belt conveyor & surface belt conveyor.

The property is free from any major geological disturbances. Average

gradient of quarry floor is 1 in 30. The average strike length of the quarry

is 3.0 km. Thus, sufficient face length will be available for optimum

efficiency of surface miner.

The bottom most seams LK-2 have been splitted into LK-2 Top and LK-2

Bottom. Both of the splits have varying thickness from 0.7 m to 1.50m.

Above LK-2 Seam, Seam L-1 exists having seam thickness 0.70m to

0.90m. Parting thickness between Seam LK-2 and L-1 varies 6 m to 18

m. Thus, dragline horizon changing will be required for operation of

dragline and dragline productivity will be less. Besides, the bottom coal

bench may be diluted as low thickness coal seam may be mixed with OB

during dragline operation. Considering multi-seam working and wide

variation of parting OB, dragline has not been proposed in this Project

Report.

6.4 MINING SYSTEM & SYSTEM PARAMETERS

Surface miner has been proposed for extraction of coal.

The salient features of mining system are as follows:-

i) Height of bench in OB will depend on the size of equipment.

Coal bench height will depend on the thickness of the coal seams.

The provision of coal mine regulations and related circulars shall be

strictly followed for designing bench parameters in coal and OB.

ii) Average Seam gradient – 1 in 30.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 15 of 39

iii) Total dump height – Internal dump height is 230 m from quarry

floor but it will be 90m from surface. External dump height is 120m

from surface.

7.1 CONSTRAINTS ON MINE DEVELOPMENT (i) The nearest railway siding is Govinda Railway siding which is

situated at a distance of about 5.0Km from the mine. The railway

line extension from Bhaiyatola station is required to connect the

upcoming Amadand siding.

(ii) Rehabilitation & resettlement of four villages namely Nimha,

Timkitola-Amadand, Harratola-Kuhka and Majholi are involved in

the project. Acquisition of land alongwith R&R of PAP is a critical

activity and should be taken up on top priority.

7.2 MINING STRATEGY / MINING SEQUENCE

At present Amadand OC is a running mine with a peak coal production of

1.15Mty and it is already extracting coal from UK seam.

It is proposed to expose MK seam in the 2nd year of mine operation by

grading properly the access trench and making its width 30 m wide and

gradient at 1 in 16. Then sufficient area to be exposed in the MK seam

floor. In the 3rd year of mine operation, the access trench is to be graded

at 1 in 16 to touch the mine floor at LKII seam of about 405 m R.L.

The quarry floor is developed in such a manner so as to facilitate

the proper drainage of water towards the sump. This would also facilitate

extension of coal and OB bench for full development of mine. After

creation of sufficient decoaled area, internal backfilling of OB will be

started in the 4th year. The coal production will continue from the 1st year

of mine life and the target coal production of 4.00 Mty will be achieved in

the 3rd year.

Two batter road of 50m width will be maintained along eastern side

batter. One batter road along floor of UK seam will be used to place inpit

belt conveyor to carry coal from UK & L4 seam as shown in plate 3.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 16 of 39

Other batter road along floor of MK seam will be used to place inpit

belt conveyor to carry coal from MK, L3 & LK1 seam. One another

inclined inpit belt conveyor will be placed upto floor of LKII seam to carry

coal from LKII & L1 seam.

Finally, through inclined belt conveyor all the coal will be transported to

surface as shown in the plate-3. From pit top coal will be transported to

upcoming Amadand siding through surface belt conveyor. .(details given

in chapter 11)

For reducing the external dump area and healthy operation of mine, 2

plans i.e. final stage of mine excavation and final dump plan showing

backfilling, Plate No. 3 & 4 are enclosed. The life of mine will be 19 years.

7.3 TOP SOIL MANAGEMENT Initially, the soil/alluvium from top bench of OB will be stacked and stored

separately. The stock piling of topsoil will be as follows:

i) Top soil removed shall be stock-piled till sufficient area is making

available to spread such materials immediately on re-graded

areas.

ii) Stock-piled Top soil shall be selectively placed on a stable area,

not disturbed, and protected from wind and water erosion,

unnecessary compaction, and contaminants which lessen the

capability of the materials to support vegetation when redistributed.

iii) After the final grading the stacked top soil would be redistributed

in a manner that achieves an approximate uniform stable

thickness consistent with the post mining land uses, contours,

and surface water drainage system.

The top soil quantity will be about 3.0Mcum. Provision of placing of

top soil over final dump has been considered in project costing.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 17 of 39

7.4 DUMPING STRATEGY In the initial years i.e. upto 4th year, entire OB will go to the external

dumps. For project implementation and aquision of land for external

dump may take 3 to 4 years. During this period about 20 Mcum OB will

be dumped internally. Provision of rehandling of this internal dump to

external dump site has been considered in the project costing.

Internal dumping will start from the 4th year onwards. The parting OB in

case of older seams may be transported partly through central haul road,

while mining in the multi seam zone.

Initially, the soil/alluvium from top bench of OB will be stacked and stored

separately. The spoil dump benches in the internally backfilled OB will be

in the form of benches. With the sufficient advance of coal production

bench, the backfilled OB will be leveled with dozer.. Dumper/Tipper will

transport soil/alluvium OB from the top OB bench and will dump the soil

directly on the leveled backfilled OB. The barrier distance between

internal dump and coal production bench will be 100 m to have smooth

functioning of machineries.

The slope stability study should be done. According to study report, the

dump design like dump bench height, total dump height & slope etc.

should be modified to avoid dump failure. In addition to that proper

precautions should be taken to avoid sliding of internal OB bench. is

estimated that 238.02 Mcum OB will be externally dumped outside quarry

area from 1st year to 10th year for which 356.50 Ha land will be required.

The northern boundary of Amadand OC block is along the Fault F1-F1

having throw of 20m to 80m. On the other side of Fault F1-F1 Khodri

Block exists where UK seam occurs at a minimum depth of about 21m.

So external dump has not proposed in the Khodri Block.

External dump has been made near southern boundary as shown in

Plate No.4. The break-up of OB quantity to be accommodated in various

dumps is as follows:-

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 18 of 39

Dump OB accommodated in Mcum 1. Internal dump 526.38 2. External dump outside Quarry area 238.02

Top soil will be removed and stored separately. This soil will be directly

spread over the leveled graded backfilled spoil for reclamation of the

quarried out land.

Possibility of external dump within quarry boundary and rehandling back

into the quarry has been examined. Considering the high quantity of

external OB placing of external dump within quarry boundary will not to

be feasible. So placing of external dump proposed outside the quarry

area.

Amadand OC may be expanded in the east direction. Quarry planning

and dump plan has been proposed accordingly such that quarry can be

expanded in east directions in future. At the end of quarry life, if required,

the void left will be filled to reduce the depth of void to 60m. Necessary

filling of the void will be done from mine closure cost. Initially the height of

internal dump is 90m from surface. After ffteenth year of mine life the

internal dump height will be kept upto surface level. Thus after mining is

over, about 228.18 Ha land will be levelled to surface level and can be

utilized for agricultural purposes.

7.5 SEQUENCE OF DUMPING OPERATIONS & STAGE-WISE DETAILS

Sl.No. Particulars of working Total

1. Coal mined (Mt) 74.09

2. OBR (Mcum) 764.40

3. Stripping ratio (Mcum/t) 10.85

4. Excavated quarry area (Ha) 694.80

5. Internal dump (Mcum) 526.38

6. External dump (Mcum) 238.02

7.6 DUMPING ARRANGEMENTS & PRECAUTIONS Maximum height of internal dump will be upto 230m from quarry floor

(90m above surface level) (refer Plate No.4). Maximum height of external

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 19 of 39

dump will be upto 120m from surface. The slopes of external & internal

dumps are as follows: -

External dump - 37 degrees

Internal dump - 37 degrees

30 m will be the height of individual bench.

30 m will be width of berm.

The slope stability study should be done. According to study report

necessary mitigative measure will be taken for the dump design like

dump bench height, total dump height & slope etc. In addition to that

proper precautions / observations should be taken to avoid sliding of

internal and external dump.

8.1 ANNUAL PRODUCTIVITY OF HEMM

The PR has been formulated to win coal by Surface Miner & OB by

Shovel Dumper combination. In Outsourcing Option both winning of coal

and extraction of OB will be done through outsourced HEMM. For OB

removal year wise lead has been estimated and based on that average

lead for OB removal is estimated to 3.0 Km.

Transport of coal from face to railway siding will be done by inpit

belt conveyor & surface belt conveyor. The Annual productivity of

outsourced HEMM will depends on the size of deployed HEMM.

8.4 EXISTING HEMM POPULATION

Details of Existing HEMM are as given below. Few existing HEMM will be

used as auxiliary HEMM for mine development and reclamation related

work and rest of HEMM will be transferred elsewhere as given in

Annexure.

SL.No. PARTICULARS CAPACITY No of HEMM

OVERBURDEN

1 ELE. ROPE SHOVEL 4,6/5.0 CuM 4

2 ELE. HYD SHOVEL 4/4.2 CuM 1

3 REAR DUMPER 35T 21

4 RBH DRILL 250 MM 3

5 RBH DRILL 160 MM 3

6 DOZER 320/410 HP 8

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 20 of 39

7 Grader 280 HP 1

8 Crane 8-10 T 1

9 Crane 30/60T 2

10 Hyd Back-hoe 0.9-1.3 CuM 1

11 Water Sprinkler 20 KL 1

8.5 CALENDAR PROGRAMME OF EXCAVATION

The mine is proposed for peak coal production of 4.00 Mty and peak OB

removal based on natural OB removal is of 52.54 Mty. The total mineable

reserves within the quarries have been estimated as 70.46 Mt as on

01.04.2015 with a corresponding OB volume of 764.40 Mcum. While,

calculating mineable reserves, a geological loss of 10% and a mining loss

of 10% have been considered.

Production build-up period - 3 years

Production period - 15 years

Tapering period - 1 year

Total period - 19 years

YEAR COAL (Mt) OB

PLANNED (Mcum)

REHANDLING OF OB (Mcum)

REHANDLING OF TOP SOIL

(Mcum)

1 2.00 20.59 8.00

2 3.00 36.91 11.00

3 4.00 52.54

4 4.00 52.54

5 4.00 52.54

6 4.00 47.32

7 4.00 39.38

8 4.00 39.91

9 4.00 40.87

10 4.00 40.89

11 4.00 40.89

12 4.00 40.61

13 4.00 40.37

14 4.00 40.86 0.50

15 4.00 41.16 0.50

16 4.00 44.43 0.50

17 4.00 40.64 0.50

18 4.00 38.10 0.50

19 1.46 13.85 0.50

TOTAL 70.46 764.40 19.00 3.00

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 21 of 39

9.1 PROJECTED COAL QUALITY

The seamwise mean GCV of coal seams within Quarry area has been

calculated by explorartion division and based on that seamwise mean

GCV of coal seams within Quarry area has been calculated. The

seamwise mean GCV and mean GCV of coal within Quarry area are as

follows.

NAME OF SEAM GCV (in Kcal/Kg)

Seam UKT 5726

Seam UKB 5725

Seam UKC 5052

Seam L4 5967

Seam L3T 5681

Seam L3B 5224

Seam L3C 4750

Seam MKT 3568

Seam MKB 5385

Seam MKC 4151

Seam LK1 5327

Seam L1 5712

Seam LK2T 5633

Seam LK2B 6037

Seam LK2C 5592

TOTAL

MEAN GCV VALUE (Kcal/kg) 4933

The weighted average Grade of coal is G-8 having Gross Calorific value

of 4933 Kcal/Kg within quarry boundary of Amadand OC(4.00 Mty).

10.1 MAKE OF WATWR CALCULATIONS:

SL.NO. DESCRIPTION UNIT 5 th Year

10th year

15th Year

Final Year

1

Inflow due to direct rainfall in exposed area

cu.m.

290712 397921 409540 317886

2

Inflow due to direct rainfall on internal dump area

cu.m.

0 11514 42500 86994

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 22 of 39

3

Inflow due to direct rainfall on area beyond excavation

cu.m.

2423 3892 5538 6999

4 Seepage from ground water cu.m. 29313 41333 45758 41188

5 Total water collected in a day cu.m. 322448 454660 503336 453066

6

Sump capacity provided 10% probability(rain fall 172mm)

cu.m.

268707 375358 415545 374043

7

Water lying out side the sump

cu.m.

53741 79301 87791 79023

8

Pumping capacity to dewater the water lying outside the sump in 18 hrs.including 10% pump losses

lps

912 1346 1490 1341

9

Pump capacity to dewater entire water including 10% pump losses in 100 hrs. pumps

lps

896 1263 1398 1259

10

No.of 225 lps capacity pumps required to dewater lying outside the sump in 18 hrs.

No.

4 6 7 6

11

No. of 225 lps capacity pumps required to dewater entire water in 100 hrs.

No.

4 6 6 6

10.2. SUMP

A sump will be provided at the deep most point of the mine. The sump

will be shifted as the mine advances. The layout of quarry provides

suitable gradient along the floor of the benches to facilitate self drainage

of water into the sump.

Water from the sump will be pumped to surface which will pass through

sedimentation ponds before finally discharged into natural drainage

system. Sump will be cleaned periodically to avoid silting and mud

accumulation.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 23 of 39

10.3 PUMPS

Nine numbers of main pumps each of 225lps, 160m head (along with

energy efficient motor) will be provided to meet the requirements up to 19

years. Out of nine pumps six nos. will be working & three will be standby.

Some of the stages of the main pumps may be blanked when they have

to operate at shallow depths. This has been provided to reduce the

capital investment and utilize the pumps till the end of life. Provisions

have been made considering the peak demand which is occasional.

Further the pumps may be repaired and kept ready for use in rainy

season. Main pumps will be installed on pontoons. Provision of pontoons

for each main pump has been given in the estimate. After 10th year of

mine operation the depth of mine would be around 145m, so proper care

has to be taken to arrest water at upper seam. Thus stage pumping could

be avoided.

Three nos. of Intermediate pump of 80 lps capacity, 100 m head,

110kw have also been provided to be used at low head. Two nos. of

diesel engine operated pump of 80lps capacity, 80m head has been

provided for operation in the initial period and then as standby for use in

case of emergency.

11.1 COAL HANDLING PLANT AND DISPATCH:

11.4.1 Coal from inpit conveyor will feed to Surge Bunker with the help of

conveyors IC8 and IC9. From 1000t surge bunker coal will be discharged on

to belt conveyor C1 or C2 of main CHP with the help of Vibratory feeder. The

belt conveyor C1 or C2 will discharge the coal to a series of belt conveyor C3 or

C4 and C5 or C6. The conveyor C5 or C6 will receive coal from conveyor C3

or C4. The conveyor C5 or C6 will also act as tripper conveyor and spread coal

over 15000t overhead bunker.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 24 of 39

11.4.2 The conveyors C7/C8 will be of 1600 mm wide and of 2200 tph

capacity. The belt conveyor C7/C8 will installed bellow the 20,000te bunker.

These conveyors will elevate coal and discharge onto 500t bunker over rail.

11.4.3 The overhead bunker will be of twin slit type. At each slit two numbers

(one working & one standby) plough feeders of 2200 tph capacity (av.) will be

provided for reclaiming coal from the bunker at a regulated rate and

discharge on reclaim cum loading belt conveyors C7/C8.

11.4.4 Ultrasonic type level switches will be provided on the carriage of the

traveling tripper of the conveyors C5/C6 to monitor the high level of coal in the

bunker. In case high level is reached in the bunker, it gives signals so that

tripper can move to the next place for discharging coal in the bunker. Similarly

low level switches will also be provided in bunker to stop the plough feeder

provided at the bunker opening in case a pre-determined low level is reached.

Two numbers of partition walls will be provided in the bunker which will be

helpful during maintenance and repair. The floor of the bunker will be provided

with proper slopes for easy drainage of water. The slanting surface of the

bunker will be provided with suitable liners for smooth flow of coal.

11.4.8 SAMPLING: Automatic sampling system with primary sample

collector, belt feeder, secondary sampler, crusher, tertiary sampler, bag

collector, bucket elevator will be provided near 500t bunker. The primary

sample collector will collect coal from the belt conveyor C7 and C8 discharging

into the bunker.

11.0 RAILWAY SIDING

A new railway siding has been proposed for the Amadand OC project.

Coal from Inpit will be brought to the proposed railway siding and will be

loaded into the railway wagons with the help of Rapid loading system.

12.1 E&M WORKSHOP The shop wise function are as follows.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 25 of 39

i) MACHINE SHOP The shop will have necessary machine tools for repair/restoration of

parts, manufacture of spares to a limited ii) ELECTRICAL REPAIR SHOP The repair facilities are limited to the replacement of parts, facilities have

also been provided to undertake winding of motors to a limited extent. 12.2.3 EQUIPMENT REPAIR / STRUCTURAL REPAIR SHOP This shop will undertake minor repairs and maintenance of the

equipments like pumps, couplings etc. 12.2 STORE A small store for the workshop is provided for day-to-day requirement of

spares and consumables.

13.0 POWER SUPPLY

The project shall receive power at 33kV by two independent over head lines

from Kotma Sub Station of CSEB. The power will be received at Quarry Sub

Station located near quarry. From this substation power will be fed to quarry &

other surface loads.

For outsourcing option the maximum Demand of Quarry Sub Station after

correcting pf to 0.98 comes to 6409 kVA for which 2 nos. 5MVA 33/6.6kV

Transformers have been provided. In order to maintain high system power factor

of around 0.98 two sets of 1500 kVAr capacity have been envisaged in Quarry

Sub Station for outsourcing option.

Adequate provision has been kept in the project for Earthing, Lightning

Protection, Illumination & for safety & fire fighting. Adequate provision has been

kept for tele-communication system for both voice & data communication.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 26 of 39

Provision has been kept in the project for township electrification & for power

supply to surface loads. Specific Energy Consumption of the project comes to

the tune of 7.91 kWh/T for outsourcing option.

14.1 COST INDEX & SPECIFICATION OF BUILDING:

The preparation of cost estimates for civil infrastructures is based on prevailing

cost index of the area in July '2015. The cost index value has been calculated

from market rate of the area. The same was provided by the staff officer (Civil)

of the area. Standard guidelines provided by B.P.E have been adopted for

arriving at cost index value. Considering the prevalent rates of materials and

labour in Jamuna & Kotma Area, the cost index works out to 2926 in July '2015

with reference to 100 base in Delhi as on 1.10.76. The detailed calculation for

Cost Index is shown in Appendix A.2.3. As the life of the mine is 19 years &

more, civil construction has predominantly been envisaged to be of permanent

specification.

15.1 DEGREE OF GASSINESS

Since it is an opencast mine, degree of gassiness is of no relevance at present.

15.2 SAFETY MEASURES AGAINST INUNDATION OF RAIN WATER

Adequate pumping capacity has been provided to deal with strata and surface

water. At the same time, one diesel pump set has also been provided to pump

out those waters logged which can not flow to the sump. Intermittent capacity

pump has also been provisioned to deal with average pumping load.

15.3 DUST SUPPRESSION

Major source of dust in opencast mine operation have been identified to be

from haul roads, due to spillage from dumpers and abrasion by their wheels.

Provision of adequate nos. of water sprinklers have been made for spraying of

water on haul roads to prevent emission of dust. All along life, haul roads and

other heavy duty roads likely to be negotiated by heavy vehicles and

equipment have been proposed to be metalled and coated to facilitate control

of emission of dust.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 27 of 39

The drills to be engaged is to be equipped with dust arrester so that dust

emission is minimum. As the blasting is not continuous one and while blasting,

persons will be removed to the safe zone, chances of exposure to dust due to

blasting are less. At siding, sufficient arrangements have been provided to

suppress coal dust at vulnerable points.

16.1 Environment Management System

Environment Management System involves two factors:

i) The protective measures to be taken and system to be developed to control the

pollution during the operation of the mine itself and also for the other operations

related to the mine as well as after closer of the mine.

ii) To comply with the above protective measures and to implement the systems

the capital and revenue provisions involved.

The capital provision made for environment protection; land reclamation measures

and other revenue cost per annum on environmental obligations are to be given.

16.2 Capital Provision

The capital provision made for environment protection and land reclamation

measures on environmental obligations are given in Appendix-F.

17.1 LAND REQUIREMENT The topography of the quarry area is almost flat with surface elevation varying from

530m to 550m above MSL. The total land involved for the project is 1443.01 Ha

including land for industrial development, colony, approach road, coal transport

road & road diversion, magazine and quarry safety zone. Out of this, 702.38Ha is

already acquired and 740.63 Ha of land is additionally required. Out of additional

land 740.63 ha, the tenancy land is 610.84 Ha and Govt. land is 129.79Ha. Within

the mine area four villages exists. The break-up of land for the purpose of this

report is as follows: -

(Land in Ha)

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 28 of 39

SL. PARTICULARS ADDITIONAL LAND TO BE ACQUIRED

NO. Already

Acquired as

31.03.2015

FOREST

LAND

TOTAL

AGRICUL-

TURE LAND

SURFACE

WATER

BODY

SURFACE

WATER

BODY

WASTE

LAND

OTHER

GOVT LAND

1. QUARRY AREA 573.31 91.245 1.622 48.839 141.71 715.02

2. SAFETY ZONE 90.71 22.855 2.431 25.29 116.00

3. REHABILITATION 50.798 50.80 50.80

4 COLONY 15.170 15.17 15.17

5 EXTERNAL DUMP 20.00 343.962 1.688 11.046 356.70 376.70

6 INFRASTRUCTURE 18.35 56.784 0.830 0.765 2.197 60.58 78.93

7 SERVICE ROAD 15.610 15.61 15.61

8 CHP, SILO, SIDING 41.660 0.404 42.06 42.06

9 MAGAZINE 10.000 10.00 10.00

OTHERS 22.720 22.72 22.72

GRAND TOTAL 702.38 610.01 0.83 4.08 125.72 740.63 1443.01

TOTAL LAND

REQUIRE

MENT

Land

TENANCY LAND GOVT LAND

Break-up of land use has been estimated on the basis of updated revenue

plan/ land use plan supplied by area authority. It is estimated that total

1443.01 Ha land will be involved for Amadand Opencast including land for

industrial development, colony, approach road, coal transport road & road

diversion, magazine and quarry safety zone.

The estimated capital requirement for land acquisition of the quarry has been

given in Appendix-A.1.

17.3 STATUS OF LAND ACQUISITION

The total land involved for the project is 1443.01 Ha including land for

industrial development, colony, approach road, coal transport road & road

diversion, magazine and quarry safety zone. Thus, total land to be acquired

for the project is 1443.01 Ha. Out of this, 702.38Ha is already acquired and

740.63 Ha of land is additionally required. Out of additional land 740.63 ha, the

tenancy land is 610.84 Ha and Govt. land is 129.79Ha. As per supplied

landuse plan no forest involved in this project, so no forest land is to be

acquired for implementation of this project report.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 29 of 39

18.11 MINE CLOSURE COST

The mine closure cost will cover the various related activities for which a

corpus escrow account @ Rs. 6.0 lakh per Ha for Opencast mine of the

project area shall be opened with the coal controller organization. The

above amount is as per the mine closure guidelines issued in August

2009, which will be updated for the present financial year based on the

cost index value.

18.11.1 Mine Closure Cost for OC mine

As per the guidelines of the MoC, the cost of the mine closure is to be

computed on the basis of the project area involved in the project. In

Amadand OCP total land area involved is 1443.005 Ha. The updated

cost of the mine closure as on March’15 is estimated to be Rs. 8.15 lakh

per hectare (considering the admissible escalation over Rs. 6.00 lakh per

Ha as on August 2009).

Final mine closure cost @ Rs = W.P.I of March 2015 176.10 /W.P.I of

Aug.09 129.60 x 6= Rs.8.15 Lakh/ Ha. for 1443.005 Ha = Rs.11760.491

lakhs.

The balance life of the mine is 19 years. Hence, the management of

funds in the Escrow Account would be as follows:

Table

Year-wise Fund for Escrow Account

Year Fund Deposited in

Escrow Fund Fund to be Reimbursed (Maximum)

1 618.973 Nil

(+) accrued interest as applicable

2 649.922 Nil

3 682.418 Nil

4 716.539 Nil

5 752.366 Nil

1st phase 3420.218 2736.174

6 789.984 Nil

7 829.483 Nil

8 870.957 Nil

9 914.505 Nil

10 960.230 Nil

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 30 of 39

2nd phase 4365.159 3492.127

11 1008.242 Nil

12 1058.654 Nil

13 1111.587 Nil

14 1167.166 Nil

15 1225.524 Nil

3rd phase 5571.173 4456.938

16 1286.800 Nil

17 1351.140 Nil

18 1418.697 Nil

19 1489.632 Nil

final phase 5546.269 8217.579

Total 18902.819 18902.819

*The interest will be as per the existing rates for the period.

Table

Total escalation of escrow fund of March’15 from the base year of

Aug’09 is given below

Year Amount (As of August’09)

Escalation

Total amount to be deposited in escrow account (As of March 15)

1 455.686 163.287 618.973

2 455.686 194.236 649.922

3 455.686 226.732 682.418

4 455.686 260.853 716.539

5 455.686 296.680 752.366

Phase 1 2278.430 1141.788 3420.218

6 455.686 334.298 789.984

7 455.686 373.797 829.483

8 455.686 415.271 870.957

9 455.686 458.819 914.505

10 455.686 504.544 960.230

Phase 2 2278.430 2086.729 4365.159

11 455.686 552.556 1008.242

12 455.686 602.968 1058.654

13 455.686 655.901 1111.587

14 455.686 711.480 1167.166

15 455.686 769.838 1225.524

Phase 3 2278.430 3292.743 5571.173

16 455.686 831.114 1286.800

17 455.686 895.454 1351.140

18 455.686 963.011 1418.697

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 31 of 39

19 455.686 1033.946 1489.632

Final phase 1822.744 3723.525 5546.269

TOTAL 8658.034 10244.785 18902.819

19.1 MANPOWER ASSESSMENT The requirement of manpower at the rated capacity of 4.00Mt of coal per

year has been estimated. Total departmental manpower estimated as 244

numbers resulting in an overall OMS of 59.17t. While estimating the total

manpower an additional provision of 25% has been made for leave and sick

considering 330 days working. In addition to that 122 nos outsourcing

manpower also has been considered in project costing for working in CHP,

security and workshop etc.

19.2 The details of estimated manpower with scale/category wise are given in

Appendix-B. The break-up of total manpower in outsourcing option in

groups’ viz., workers, monthly paid staff and officers are given below:-

Sl. No

Particular No. Percentage of

total Manpower

1 Workers 145 59.43%

2 Monthly paid staff

70 28.69%

3 Officers 29 11.88%

Total 244 100%

20.1 PROJECT IMPLEMENTATION SCHEDULE

It is well known fact that for timely implementation of a project, it is

essential that all the activities related with project construction are

properly planned, closely monitored and effectively supervised.

All implementing departments have their own implementation manuals

which are followed for monitoring and construction of the project, so that,

man, materials and money are made available to the project in time as

spelt in the project report, with a view to prevent cost and time over-run.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 32 of 39

Responsibility, power for each executive has also been included in the

implementation manual to prevent overlapping of operational areas.

Sufficient administrative and financial power has been defined for key

executive to take timely and effective decisions for the implementation of

the project.

Time estimates are broad and indicative only, necessary modifications to

suit local site conditions are to be incorporated subsequently.

1.1 CAPITAL INVESTMENT

21.1.1 Capital investment and its phasing

Phasing of Additional Capital (Rs. In Lakhs) Total Additional

Capital 1st 2nd 3rd 4th 5th 6th to 15th

5119.98 11578.31 22244.91 24457.52 12102.15 558.21 76061.08

Existing Capital as on 01.04.2015 is 10882.52 Lakhs and Net block capital is

6009.91 Lakhs. Some existing HEMM will be transferred to other mine as in this

report both coal and OB removal is proposed to be done by outsourcing. As on

31.03.2015, Net block of HEMM which are to be transferred from this project is

Rs 3528.71 Lakhs. Net block considered for project costing = Rs (6009.91-

3528.71) Lakhs = 2481.20 Lakhs

21.1.2 Basis of price of P&M, Civil works & hiring rate

Price of P&M has been taken from the standard price list published by

CMPDI, HQ on May 2014. Prices have been updated upto July 2015 as

per escalation rate given in the price list.

The preparation of cost estimates for civil infrastructure is based on

prevailing cost index of the area in July 2015. The cost index value has

been calculated from the market rate of the area. Considering the

prevailing rates of materials and labour in Jamuna-Kotma Area, the cost

index works out to 2926 w.r.t. 100 base in Delhi as on 1.10.1976.

21.1.3 Foreign Capital

No foreign capital investment has been envisaged.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 33 of 39

21.1.4 Capital upto target year - Rs. 38943.20 Lakhs

Capital requirement beyond target year - Rs. 37117.88 Lakhs

Specific investment - Rs. 2173.60 tonne

Specific investment for P&M - Rs. 996.90 tonne

21.2 OPENING OF REVENUE ACCOUNT

The Amadand Opencast project is an ongoing project with a target

production of 1.15 Mty and the project is already in operation. This RPR

is being prepared to enhance the production from 1.15Mty to 4.0 Mty.

Considering the ongoing project, the Revised Project Report would

be brought under revenue account w.e.f. the beginning of 1st year of

operation. Thus the revenue expenditure of the project has not been

capitalized during the initial years.

21.3 REPLACEMENT CAPITAL

Year-wise phasing of replacement capital is given in Appendix-D.1 column No.3.

21.4 SOURCES OF FINANCE

The project will be financed completely by internal resources.

21.5 COMPLETION COST

As per the latest guidelines, the completion cost of a project will qualify all

the following conditions:

- Achievement of coal production capacity of 80% of the rated output.

- Completion of all major facilities and initial mine development work.

- Procurement of major and essential plant & machinery.

Completion cost of the project is estimated as Rs. 912.28 Crores.

21.6 METHOD OF ESTIMATION OF CAPITAL COST: a) Land

Rate of revenue, forest and tenancy land are provided by SECL.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 34 of 39

b) Civil Construction (alongwith Cost Index)

The preparation of cost estimates for civil infrastructure is based on prevailing

cost index of the area in July 2015. The cost index value has been calculated

from the market rate of the area. Considering the prevailing rates of materials

and labour in Jamuna-Kotma Area, the cost index works out to 2926 w.r.t. 100

base in Delhi as on 1.10.1976.

c) P&M

Price of P&M has been taken from the standard price list published by CMPDI,

HQ on May 2014. Prices have been updated upto July 2015 as per escalation

rate given in the price list.

21.7 COST OF PRODUCTION AT DIFFERENT LEVEL OF PRODUCTION a) Salaries & Wages Cost

The detail of category-wise / scale-wise manpower requirement and year-wise estimated wages cost is given in Appendix-B.1.

Estimated salaries & wages cost is worked out as Rs. 57.20/Te.

b) Stores Cost

Stores Cost has been estimated taking into account provision for Repair &

Maintenance, POL, Explosive and miscellaneous stores cost. The estimated

Stores Cost has been worked out to Rs.114.40/Te.

c) Power Cost

Estimated Energy Consumption is given in the relevant chapter for Power

Supply. The power cost has been taken as Rs.6.0/unit. The average power cost

per tonne of coal production works out to Rs.44.93 at 100% level of operation.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 35 of 39

d) Misc. Expenditure

This cost has been estimated to cover expenditure on Printing & Stationary,

Postage, Telephone, repair & Maintenance of assets other than P&M, Workshop

Workshop Debit, and Insurance & Taxes for vehicles and other repairs and a

further provision has been made for deterioration of coal stock. Miscellaneous

expenditure per tonne works out to Rs.30.80.

Provision has been considered to meet cost of environmental related activities

at the rate of Rs 5/tonne and it is also included in the miscellaneous head.

e) Administrative Charges

A provision has been made in total revenue cost estimate for Administrative

charges based on the Admn. Cost per tonne of coal production as was

appearing in the last Annual Report of SECL. Total Admn. Cost has been

calculated at 100% level and treated as fixed cost. Based on the

recommendations of 310th meeting of CIL Board held on 8-11-14 only 10% of

Administrative charges have been considered . The Admn. Cost works out toto

Rs. 6.40/Te (10% of Administration cost considered as per CIL proposal).

f) Interest on Working Capital

Interest on Working Capital has been calculated on the basis of 4 months

operating expenditure. Rate of interest is taken as 14.50%. The Interest on

Working Capital comes to Rs. 45.08/Te.

g) Depreciation

Straight line method of depreciation has been provided to arrive at depreciation

cost per tonne of coal production. The depreciation Cost comes to Rs. 96.57/Te.

h) Interest on Loan Capital

Interest @ 11.5% on loan capital is to be considered for computation based on

given Debt Equity Mix. However, loan capital in this project is NIL.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 36 of 39

i) Environment related Cost

Rs 120.27 /Te of coal has been provided to absorb environmental related cost in

the project.

j) Mine Closure Cost

Rs.26.84 /Te has been provided in the project against Mine Closure Cost.

k) Cost of Production - Cost of production per tonne at 100%, 85% and 80%

level of production works out to Rs.1074.40, Rs.1120.68 & Rs.1139.96.

l) CSR Cost - CSR cost as per latest CIL’s CSR Policy communicated vide

CGM (Welfare), CIL, letter No.CIL/C-5C/231(CSR)/269 dated 3.12.2009, source

of fund under this head will be 5% of the retained earning of the previous year

subject to minimum Rs.5/- per tonne of coal production of previous year.

However, this fund is not a part of project costing and the same will be spent by

company as per CSR activities.

21.7.1 OUTSOURCING RATES

Coal extraction and OB removal is proposed to be done by outsourcing.

The rates have been considered based on the escalated rates table received

from SECL.

The outsourcing cost of OB for average lead of 3.0 Km is considered are

Rs.52.53 per cum with current diesel price Rs 57.84 per litre. Rehandling cost

considered Rs 40.00 per cum of OB to be rehandled. The outsourcing cost of

Coal for surface miner cutting, loading and transport from face to inpit belt

conveyor are follows:-

Particulars (Rs./t)

Coal Cutting (by Surface Miner) 23.91

Loading 14.29

Ave Transportation from face to in pit belt conveyor 1 to 2 km (and surface transport 5Km upto 3rd year)

31.61

Total (Say) 69.81

Service Tax has not been considered in estimating outsourcing rate of

the project as CENVAT credit is available to the extent of Service Tax rate.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 37 of 39

The scope of work by outsourcing will include drilling, loading and

transportation, dozing and maintenance of haul roads. All statutory rules,

regulations and applicable laws are to be followed.

21.8 SELLING PRICE The weighted average selling price of coal for this coal project has

been taken as Rs.1298.22 per tonne(considering coal price of power sector

consumer) for ROM processed coal (-100 mm). The weighted average grade of

coal is ‘G-8’. The mean GCV of Amadand OC is 4933 Kcal/Kg.

CALCULATION OF SELLING PRICE

(a) Price of GCV 4933Kcal/Kg coal per tonne* = Rs.1250.00

(b) Price taken in PR coal per tonne** = Rs.1187.50

(c) Sizing charges (-100 mm) per tonne*** = Rs.79.00

(d) Ave. of transport & Rapid loading **** = Rs.31.72

Weighted average selling price = Rs.1298.22 /t

*As per price notification No. CIL:S&M:GM(F):Pricing:1965 dated 31.01.2012

**95% of the grade based on borehole data as per norms.

***As per price notification No. CIL:S&M:GM(F):Pricing:2784 dated 16.12.2013

**** Average Transport & Rapid Loading charge includes Rs 57 per tonne upto

3rd year and rapid loading charge Rs. 26 per tonne beyond 3rd year. As per

price notification No. CIL:S&M:GM(F):Pricing:2340 dated 13.11.2013

21.9 Profitability

Profit/Loss at 100% = Rs 223.82./t

at 85% = Rs 177.54./t

21.10 Manpower, OMS, EMS

Manpower - 244,

OMS - 59.17,

EMS - Rs. 3384.01

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 38 of 39

21.11 Financial IRR -

Financial IRR at 100% level of production = 21.33 %

at 85% level of production = 13.55 %

21.12 BREAK-EVEN PRODUCTION It is estimated that the project will achieve break-even point at 2.16 Mty of

production which is 53.95 % of rated capacity.

21.13 Sensitivity Analysis - given in the Appendix-C.4.

21.14 CONCLUSION AND APPROVAL

In this report both coal and OB removal is proposed to be done by

outsourcing. In this outsourcing option, total capital investment works out to Rs.

869.44 Crores. (Addl. Capital investment of Rs. 760.61Crs.). The project report

for Amadand OC(1.15 Mty) may be treated as dovetailed with project report for

Amadand OC (4.00 Mty) for the purpose of implementation as all the required

activities and financial provisions of Amadand OC(1.15 Mty) have been included

in Amadand OC (4.0 Mty) Report.

In this report recommendations of 310th meeting of CIL Board (held on 8-11-14)

regarding modification of cost provisioning in PR for CIL projects have been

incorporated.

The project is yielding an IRR of 13.55% at 85% level of production. As per the

guidelines, a Project is economically viable when it achieves more than 12%

IRR at 85% level of Production. Since, this Project is having Internal Rate of

Return more than 12% at 85% level of target production i.e. 13.55% the

Outsourcing Option of this project is economically viable project.

The outsourcing option of RPR for Amadand Opencast Project (4.00Mty)

was placed before SECL Board’s 236th meeting held at Raipur on dated

04.09.2015 for a total capital of Rs 869.44 Crores and SECL Board directed to

submit the same to CIL, since capital provision in the RPR exceeds Rs 500

Crores.

RPR for Amadand OCP (4.0 Mty) (Updated July’2015) CMPDI

JOB NO.-515126 ES / 39 of 39

Accordingly, RPR for Amadand Opencast Project (4.00Mty) was placed

before 325th CIL Board meeting held at Kolkata on dated 05.03.2016 for a total

capital of Rs 869.44 Crores. CIL Board accorded its approval to Project Report

for Amadand Opencast Project for a rated capacity of 4.00 Mty at an estimated

capital investment of Rs 869.44 Crores for implementation of the project with

total outsourcing variant i.e both coal and OB outsourcing.

*******

TEXT

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 1 / 1 of 11

CHAPTER – I INTRODUCTION

1.1 BACKGROUND OF THE PROJECT REPORT

The Amadand Opencast Block is located in the eastern part of south Sohagpur

Coalfield and is flanked by working mines of Hasdeo and Jamuna & Kotma

areas of South Eastern Coalfields Limited (SECL) to the east and west

respectively.

The detailed exploration of the area was taken up by CMPDI in August 1990

and comprehensive geological information were provided in Geological Reports

on Bartarai Block in December 1993, Amadand Opencast area in December

1995, Bakulmuni Block in July 1997, Amadand East U/G Block in January 1998

and Amadand West U/G Block in November 1999.

Project Report for Amadand OC (1.15 Mty) was prepared with an average

stripping ratio of 4.58 cum/t considering only upper seam i.e UK seam and

submitted to SECL in August 2003 and approved in Sept 2003. During

preparation of Amadand OC (1.15 Mty) report, lower seams e.g. MK (Top) and

MK (Bottom) and LK-II were also considered for extraction by opencast

method. But, due to high stripping ratio, the quarriability of lower seam were not

feasible for departmental option. So seams below UK seam were not

considered in the 1.15 Mty PR.

Latter on, decisions were taken to extract coal from bottom seams.

Accordingly, Revised Geological Report have been prepared, considering

workable coal seams upto bottom most LK-II seam which has not taken into

account for opencast mining earlier. In the area under consideration seams, L-

6, L-5, UK (Top), UK (Bottom), UK, L-4, L-3(Top), L-3 (Bottom), L-3, MK (Top),

MK (Bottom), MKC, L-2, LK-I, L-1, LK-II (Top), LK-II (Bottom) & LK-II have

encountered in descending order.

The present report is formulated considering all the seams upto bottom most

LK-II seam for mining with outsourcing option.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 1 / 2 of 11

1.1.1 SALIENT FEATURES OF LAST APPROVED REPORT

Annual Capacity of the mine (Mty) : 1.15

Initial Capital Investment (Rs. Crs.) : 83.39

Specific investment (Rs./t) : 725.09

Investment on HEMM (Rs. Crs.) : 24.45

(Rs. per tonne of Annual Output) : 212.61

Investment on P&M (Rs. Crs.) : 37.05

(Rs. per tonne of Annual Output) : 322.17

Cost of Completion (Rs. Crs.) : 92.85

Net Extractable Reserve (Mt) : 36.04

Average Grade of Coal : ‘D’(L/F)

Total Volume of Overburden (MCum) : 165.00

Average Stripping Ratio : 4.58

Total Life of Mine (years) : 34

Year of Achieving Target : 4th

Total Manpower Required : 679

Overall OMS (t) : 6.41

Estimated Cost of Production (Rs./t)

at 100% Capacity Utilisation : 522.14

at 85% Capacity Utilisation : 585.18

Average selling price (Rs/t) : 751.50

Profit at ruling sale price (Rs/t)

at 100% Capacity Utilisation : 229.36

at 85% Capacity Utilisation : 166.32

BEP of the project (%) : 60.90

FIRR (%)

at 100% Capacity Utilisation : 36.17

at 85% Capacity Utilisation : 20.82

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 1 / 3 of 11

1.2 EXPLORATION STATUS

The area was identified by CMPDI for scout drilling in March 1989 on the basis of

some boreholes drilled close to some of the GSI boreholes, namely, SM-4, 6&8

etc. in the eastern part of the Amadand tract and DGM (MP) was entrusted for

scout drilling. The results of the scout drilling conducted by DGM (MP) revealed

presence of good quality workable coal deposit in an area of about 60 sq.km of

the intervening Amadand tract between the working mines of SECL.

Detailed exploration of the area was taken up by CMPDI in August 1990 and

comprehensive geological information was provided in Geological reports on

Bartarai Block in December 1993, Amadand Opencast area in December 1995,

Bakulmuni Block in July 1997, Amadand East U/G Block in January 1998 and

Amadand West U/G Block in November 1999.

The block measures 15.061 sq.km. which includes 14.154 sq.km. free area

and 0.907 sq.km. forest area. The borehole density within the block is 15.20 BH /

sq km.

1.2.1 History of the Block

Project Report for Amadand OC (1.15 Mty) was prepared with an average

stripping ratio of 4.58 cum/t considering only upper seam i.e UK seam and

submitted to SECL in August 2003 and approved in Sept 2003.

At present Amadand OC is a running mine with a peak coal production of

1.15Mty to extract coal from UK seam.

1.2.2 PAST PERFORMANCE OF THE EXISTING MINES

Past performance of the mine showing yearwise coal, OB removal, cost of

production and profitability of mine for last few years are as given in the table.

YEAR COAL (MT)

OB (Mcum)

YEARWISE SR

COST OF PROD

SELLING PRICE

PROFIT / LOSS

(Rs/Per Te) Rs/Per Te (Rs/PerTe)

2009-10 0.13 1.07 8.23 522.54 91.33 (-)431.20

2010-11 0.48 1.23 2.56 1211.58 1365.15 153.57

2011-12 0.63 2.28 3.62 1226.24 1688.96 462.71

2012-13 1.15 5.92 5.15 1059.34 2006.13 946.79

2013-14 1.15 4.87 4.23 261.19 1949.62 1688.42

2014-15 1.15 6.17 5.36 1557.55 1971.96 414.42

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 1 / 4 of 11

1.2.3 ADJOINING WORKING MINES

The status of mine workings adjoining this mine are given below.

Sl.No.

Mine/ its location with respect to Amadand Block

Coal Seam Status of Mine workings

1 Amadand UG (adjacent to Amadand East U/ G Block)

Lower Kotma II Development in progress

2 Bartarai UG (Adjacent to Amadand East U/ G Block)

Middle Kotma Top & Middle

Kotma Bot.

Development in progress

3 Kotma (11km west) Middle Kotma Fully developed & depillared

Lower Kotma-I Fully developed & depillared

Lower Kotma-II Largely developed & depillared, nearing exhaustion

4 Radha Incline (11km.) north-west

Middle Kotma Development/ depillaring in progress

5 Govinda 7 & 8 Incline (12 km north-west)

Middle Kotma Largely developed & depillared nearing exhaustion

6 Amritdhara( 3km SE) Seam 5/ Middle Kotma Top

Mining yet to commence

Seam-4/ Middle Kotma Bot.

Mining yet to commence

7 Ramnagar (Jhiria)(5km ENE) Seam-4/Middle Kotma Bot&

Seam-5/Middle kotma top.

Development in progress

1.2.4 BACKGROUND OF PREPARATION OF PRESENT REPORT

To meet the increased growth of demand, later on it was decided, to

formulate a project report of higher capacity considering all the coal seams

upto bottom most LK-II seam. Accordingly, the present report is formulated

considering all the coal seams upto bottom most LK-II seam. Chronology of

preparation of reports considering all the coal seams upto bottom most LK-II

seam are as follows.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 1 / 5 of 11

SL NO CAPACITY PARTICULARS Vertical Boundary

Horizontal Boundary

Option Remarks

1 5.00 DPR Dec 2011 LKII seam Incrop of UK considering diversion of road

Outsourcing Viable with Non-power Price

2 4.00 Final June 2012 LKII seam Incrop of UK considering diversion of road

Outsourcing Peak reduced to 4 Mty as OB is high

3 4.00 Planning meeting Sept 2012

LKII seam Incrop of UK considering diversion of road

Outsourcing Quarry extent to be as per approved boundary

4 4.00 DPR with modified boundary present at SECL July 2013

LKII seam Quarry boundary nearly as per approved boundary

Outsourcing Rehandling of OB to be accorded in PR

5 4.00 Final PR Dec 2013 by incorporating Rehandling of OB

LKII seam Incrop UK Quarry boundary nearly as per approved boundary

Outsourcing Viable with Non-power Price

6 4.00 TSC held on 16.6.2014 LKII seam Quarry boundary nearly as per approved boundary

Outsourcing Power price of coal and CENVAT to be considered

7 4.00 UCE Submitted in October 2014 considering power price and CENVAT

LKII seam Quarry boundary nearly as per approved boundary

Outsourcing IRR is below 12%

8 4.00 UCE Submitted in July 2015 considering recommendation of 310th CIL Board for revised costing Norms

LKII seam Quarry boundary nearly as per approved boundary

Outsourcing IRR is more than 12%.

Based on above observations, the horizontal boundary of quarry area is

mostly same as proposed in Amadand OC 1.15 Mty report and vertical

boundary proposed upto the bottom most LKII(Bot) seam. From environmental

point of view Inpit belt conveyor and surface belt conveyor to transport coal

from pit top to siding has been considered in this Amadand OC Opencast (4.0

Mty) report. Rapid loading system has also been considered. Thus increasing

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 1 / 6 of 11

production capacity from 1.15Mty to 4.0Mty is justified to meet the increased

growth of demand.

To consider all the coal seams upto bottom most LK-II seam, a Revised

Geological Report have been prepared, considering all workable coal seams in

this area which has not taken into account for opencast mining earlier. In the

area under consideration, four main coal seams UK, MK, LKI & LKII exists and

in addition to that three local coal seams L1, L3 & L4 exists. The seams UK,

MK, LKII & L3 are splitted into top and bottom within the proposed quarry area.

1.2.2 Exploration Design

A total of 228 boreholes involving 27121.07m of drilling have been

considered for preparation of this report. Core recovery in coal and non coal

is generally above 85% & 70% respectively except in few boreholes e.g.

CMAD-72, 153, 164, 177, 184 etc. Boreholes have been spaced generally

400m apart except in case of structure proving boreholes. Depth range of

boreholes is from 17m to 206m. Density of boreholes per sq. km. is 15.20.

1.3 MINING ACTIVITIES

1.3.1 PRESENT STATUS OF THE MINE/PROJECT

Project Report for Amadand OC (1.15 Mty) was prepared with an

average stripping ratio of 4.58 cum/t considering only upper seam i.e UK seam

and submitted to SECL in August 2003 and approved in Sept 2003.

At present Amadand OC is a running mine with a peak coal production of

1.15Mty to extract coal from UK seam.

The Amadand UG & Bartarai UG are adjoining working mines of

Amadand Opencast mine. Both Amadand UG & Bartarai UG property are

situated on other side of the Pendra-Manendragarh state highway road and

area of these mines are not included within quarry boundary of this 4.0 Mty

RPR Report.

1.4 JUSTIFICATION OF PREPARATION OF RPR

Amadand OC (1.15 Mty) was prepared with an average stripping ratio of 4.58

cum/t considering only upper seam i.e UK. Later on, decisions were taken to

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 1 / 7 of 11

extract coal from bottom seams upto bottom most LK-II seam. Accordingly, this

report is formulated considering all the seams upto bottom most LK-II seam for

mining with outsourcing option.

Liberalisation of power sector by Government of India has generated wide

spread interests for private and public sector investments in power generation

and other industrial development. As such, there is an appreciable increase in

the number of upcoming new projects in both private and public sectors. The

demand projection from SECL for the year 2015-16 is 269.97 Mt, as given in

Table 2.1. It will cater to the needs of the upcoming industries like power,

Cement, Fertilizers, other industries etc. The demand projection from SECL

for the year 2016-17 is 270.37 Mt. The projected availability in the year 2016-

17 is 150.00 Mt and there will be shortage of 120.37 Mt.To meet the demand of

coal, it is required to open new projects.

Average grade of coal of Amadand Opencast is grade ‘G-8’ with mean

GCV is 4933 Kcal/Kg. RPR for Amadand Opencast (4.0 Mty) prepared to

enhance coal production to fulfill the above indicated growth in demand.

1.5 SALIENT FEATURES OF PRESENT PR (CAPACITY, CAPITAL, ETC.)

Sl. No. Particulars Unit Quantity

I. Coal Seams

1 Dominant Thickness of Seams

UK Top m 0.80-1.65

UK Bottom m 0.50-1.00

UK (Comb) m 0.80-4.00

L-4 m 0.50-0.60

L-3 Top m 0.50-0.60

L-3 Bottom m 0.50-0.60

L-3 (Comb) m 0.50-1.50

MK Top m 0.50-1.70

MK Bottom m 0.50-1.25

MK (Comb) m 0.70-4.00

LK-1 m 0.50-0.80

L-1 m 0.50-0.80

LK-2 Top m 0.50-1.00

LK-2 Bottom m 0.50-1.20

LK-2 (Comb) m 0.50-2.25

Average Dip Degree 1 in 30

2 Av. Specific gravity of coal in seams t/cum 1.52

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 1 / 8 of 11

Sl. No. Particulars Unit Quantity

II. Overburden / partings

3 Dominant Thickness

Top OB m 20.00-40.00

Between UK Top & UK Bottom m 1.00-3.00

Between UK Bottom, UK & L-4 m 10.00-18.00

Between L-4 & L-3 m 10.00-20.00

Between L-3 Top & L-3 Bottom m 1.00-4.50

Between L-3 & MK Top m 1.50-8.00

Between MK Top & MK Bottom m 1.00-6.75

Between MK & LK-1 m 15.00-35.00

Between LK-1 & L-1 m 11.00-19.00

Between L-1 & LK-2 Top m 3.00-25.00

Between LK-2 Top & LK-2 Bottom m 1.00-4.00

4 Seamwise Mineable Reserves

UK Top & UK Comb Mt 21.85

UK Bottom Mt 0.80

L-4 Mt 0.77

L-3 Top & L-3 Comb Mt 2.10

L-3 Bottom Mt 0.42

MK Top & MK Comb Mt 22.04

MK Bottom Mt 1.86

LK-1 Mt 4.47

L-1 Mt 1.13

LK-2 Top & LK-2 Comb Mt 12.31

LK-2 Bottom Mt 2.70

Total (as on 01.04.2015) Mt 70.46

5 Av.Specific Gravity of OB t/cum 2.40

6 Volume of OB (as on 01.04.2015) Mcum 764.40

7 Stripping Ratio (Av.) cum/t 10.85

8 Target Output Mt/Yr. 4.0

9 Peak OBR(based on natural OB) Mcum/yr. 52.54

10 Project life Year 19

Financial Parameters OUTSOURCING

OPTION

11 a) Total capital investment b) Capital outlay per te of annual

output

Rs. Crores

Rs./t

869.44

2173.60

12 a) Capital requirement of P&M b) Per tonne of annual output

Rs. crores Rs./t

398.76 996.90

13 Selling price (95% of notified selling price) )(power sector price)

Rs./ t 1298.22

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 1 / 9 of 11

Sl. No. Particulars Unit Quantity

14 Estimated cost of production a) at 100% level of production b) at 85% level of production

Rs./t Rs./t

1074.40 1120.68

15 Profit per tonne a) at 100% level b) at 85% level

Rs./t Rs./t

223.82 177.54

16 Break-even-point (%) (Mty)

53.95 2.16

17 No. of personnel 244

18 OMS excluding contractor workers t 59.17

19 EMS Rs. 3384.01

20 Anticipated year of achieving target Year 3rd

21 IRR at 100% level of production % 21.33

22 IRR at 85% level of production % 13.55

23 Completion capital of the project Rs. crores 912.28

The PR has been formulated to win coal by Surface Miner with FEL and

trucks/dumpers & OB by Shovel Dumper combination. Transport of coal from face

to railway siding will be done by inpit belt conveyor & surface belt conveyor.

Both winning of coal and extraction of OBR will be done through outsourced

HEMM. PR is giving IRR 13.55% at 85% level of production. The overall grade of

coal is “grade G-8” with GCV 4933 Kcal/Kg, which is easily marketable. As per the

guidelines, a Project is economically viable when it achieves more than 12% IRR

at 85% level of Production. Since, this Project is having Internal Rate of Return

more than 12% at 85% level of target production i.e. 13.55% and hence

Outsourcing Option of this project is economically viable project.

The outsourcing option of RPR for Amadand Opencast Project (4.00Mty) was

placed before SECL Board’s 236th meeting held at Raipur on dated 04.09.2015 for

a total capital of Rs 869.44 Crores and SECL Board directed to submit the same to

CIL, since capital provision in the RPR exceeds Rs 500 Crores.

Accordingly, RPR for Amadand Opencast Project (4.00Mty) was placed before

325th CIL Board meeting held at Kolkata on dated 05.03.2016 for a total capital of

Rs 869.44 Crores. CIL Board accorded its approval to Project Report for Amadand

Opencast Project for a rated capacity of 4.00 Mty at an estimated capital

investment of Rs 869.44 Crores for implementation of the project with total

outsourcing variant i.e both coal and OB outsourcing.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 1 / 10 of 11

1.6 DIFFICULTIES AND CONSTRAINTS IN MINING WITH ASSOCIATED RISK

(i) The nearest railway siding is Govinda Railway siding which is situated

at a distance of about 5.0Km from the mine. The railway line extension

from Bhaiyatola station is required to connect the upcoming Amadand

siding.

(ii) Rehabilitation & resettlement of four villages namely Nimha, Timkitola-

Amadand, Harratola-Kuhka and Majholi are involved in the project.

Acquisition of land alongwith R&R of PAP is a critical activity and

should be taken up on top priority.

1.7 PROJECT OBJECTIVES AND TARGET BENEFICIARIES The demand projection from SECL for the year 2016-17 is 270.37 Mt. It will cater

to the needs of the upcoming industries like Cement, Fertilizers, other industries

etc. The projected availability in the year 2016-17 is 150.00 Mt and there will be

shortage of 120.37 Mt as shown in Table 2.1. .

1.8 PEAK CAPACITY Sometimes with favorable geo-mining conditions and improved productivity of the

HEMM, the project may produce coal upto 1.35 times of the planned capacity. So,

EMP should be prepared for 5.40 Mty, accordingly approval from the Competent

Authority is to be sought.

1.9 FLEXIBILITY IN IMPLEMENTATION The flexibility in the implementation stage may be exercised within the approved

cost estimates to respond to improvements in technology and equipment which

would result in improved profitability and productivity measures. Following points

may be considered under the flexibility: -

a) Re-alignment of project working for better working layout / dump etc.

b) Change in the specification of HEMM, for techno-economic consideration, to

higher capacity at the time of procurement of new equipment or replacement of

the equipment.

c) To procure state-of-the-art safety equipment, whenever they are introduced,

even if the same is not provided in approved Project Report.

d) Relocation of site for infrastructure facilities depending upon techno-economic

reasons and availability of land / forest area etc.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 1 / 11 of 11

e) Hiring of equipment for loading, transportation etc., at a competitive price, so as

to cater to the needs of increased demand of coal and subsequent removal of

higher OB and for augmentation of coal production.

f) For upgradation of new technology in mining method for improving

performance and reduction in manpower, at a subsequent date after project

completion.

g) In this PR it is proposed that coal would be mined by surface miner. However,

in circumstances where Operational/Geotechnical difficulties persist small

quantity of coal may be mined out by alternative technology such as

ripping/drilling etc. Prior approval may be obtained for use of alternative

technology citing the circumstances/operational difficulties.

1.10 CRITICAL ACTIVITIES PRIOR TO ENVIRONMENT CLEARENCE

Critical activities, which could be taken up prior to environmental, forestry and

other statutory clearances to expedite project implementation are as given below.

a) Northern boundary of quarry is to be exposed upto UK seam along the full

strike length of the quarry. This is required to reach quarry floor of 4.00 Mty

report to create internal dumping space at the earliest.

b) The acquisition of R&R site should be processed to take possession of the

R&R site to rehabilitate the project affected family at the earliest.

c) The northern side garland drain is to be constructed first to prevent inrush of

water from northern side. As quarry advances towards the south, the other

garland drains will be constructed as per requirement.

d) Preliminary study about extension of railway line and its tentative alignment

from Bhaiyatola rail station or other suitable location is to be done to connect

Amadand Siding.

*******

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 2 / 1 of 2

CHAPTER - II

MARKETABILITY & JUSTIFICATION 2.1 DEMAND AND SUPPLY SCENARIO (COMPANY)

Liberalisation of power sector by Government of India has generated

wide spread interests for private and public sector investments in power

generation and other industrial development. As such, there is an appreciable

increase in the number of upcoming new projects in both private and public

sectors. The demand projection from SECL for the year 2015-16 is 269.97 Mt,

as given in Table 2.1. It will cater to the needs of the upcoming industries like

power, Cement, Fertilizers, other industries etc. The projected availability in the

year 2015-16 is 135.00 Mt and there is shortage of 134.97 Mt. The demand

projection from SECL for the year 2016-17 is 270.37 Mt. The projected

availability in the year 2016-17 is 150.00 Mt and there will be shortage of

120.37 Mt as shown in Table 2.1.

*TABLE No. 2.1 : Demand and availability for South Eastern Coalfields Ltd ( Figures in Mt)

Sl. No. Sector/Group XII Plan

(2015-16) XII Plan

(2016-17)

A. COKING

1. Steel (Indigenous) 0.17 0.17

B. NON-COKING

1. Power (Utilities) 209.25 209.25

2. Power (Captive) 24.56 24.56

3. Sponge Iron / CDI 8.68 8.68

4. BRQ & Others / LTC / SSF 15.38 15.78

5. Soft Coke - -

6 Cement 11.06 11.06

7 Fertilizer 0.85 0.85

8 Colliery consumption 0.02 0.02

Total Demand (SECL) 269.97 270.37

Availability 135.00 150.00

Balance (-) 134.97 (-) 120.37

NOTE: * Source Long Term Plan Report of SECL

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 2 / 2 of 2

2.2 UTILITY OF MARKET FOR THE COAL FROM MINE / PROJECT

Liberalisation of power sector by Government of India has generated wide

spread interests for private and public sector investments in power

generation and other industrial development. As such, there is an

appreciable increase in the number of upcoming new projects in both

private and public sectors.

Amadand OC is a existing ongoing project & grade of coal is grade ‘G-8’

with GCV 4933 Kcal/Kg. Preparation of RPR for Amadand Opencast with

enhance coal production is, therefore, proposed with a view to fulfill the

above indicated growth in demand.

2.3 AVAILABLE LINKAGE OR FIRM FUEL SUPPLY AGREEMENT (FSA) Amadand OC is an existing ongoing project & grade of coal is grade ‘G-8’

with GCV 4933 Kcal/Kg can be used for basket linkage to various

industries.

From Table No-2.1, it can be seen that in the year 2015-16, there is a

need of opening of new Projects to bridge the gap in demand. Preparation

of Revised Project Report for Amadand Opencast is therefore proposed

with a view to fulfill part of the above indicated growth in demand.

*******

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 3 / 1 of 2

CHAPTER-III

PROJECT SITE INFORMATION

3.1 LOCATION

The Amadand Opencast Block (Plate 1) located 8 km SE of Kotma town is

bounded by latitudes 23O07'28" & 23O09'46" N and longitudes 82O02'04" &

82O04'53" E (approx.). It falls on the Survey of India Topo-sheet No.64 I/4

(RF1:50,000) within Anuppur district of Madhya Pradesh.

The Baihatola railway station on the Anuppur-Chirimiri/ Bisrampur section of

SE Central Railway is located at a distance of 8 km. due north. The crow fly

distances from Rajnagar colliery railway siding and Kotma colliery railway

siding from the opencast area are about 8km and 7km respectively.

3.1.1 Limiting boundaries of proposed Quarry area

The quarriable area for the opencast mining is shown on Plate No. 3. The

boundary of Amadand Opencast Project is as follows:

North : Incrop of Upper Kotma Seam. South : Incrop of Upper Kotma Seam. East : A line keeping 100 m barrier from boundary of Amadand

Village. West : Incrop of Upper Kotma Seam.

3.2 ACCESSIBILITY AND COMMUNICATION

Amadand Opencast Block has a good road communication. The State

highway connecting Manendragarh and Pendra passes through the east of

the block. A few fair weather roads, branching off from the state highway

provide accessibility to different parts of the area

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 3 / 2 of 2

3.3 CLIMATE AND RAINFALL DATA

The area is characterised by tropical climate with well defined Summer from

April to June, monsoon from July to September and winter from November

to February. May is the hottest month when the temperature rises to 46oC

and during winter temperature falls as low as 7oC to 8oC. The relative

humidity during monsoon ranges from 76% to 90% and in summer 26% to

42%. The average annual rainfall is about 1200.00 mm.

3.4 TOPOGRAPHY WITH DRAINAGE PATTERN OF AREA

The Amadand Opencast Block has a gentle rolling topography with a

general slope in all directions from the central part of the area. The

variation in surface elevation is from 530m to 550m above MSL (Plate II).

The area has a radial drainage pattern while the major part of the area is

being drained by channels of Kewai River, a tributary to Son, the channels

in the north eastern part of the area discharge its water into Hasdeo river, a

tributary to Mahanadi. There are also a number of ponds in the area.

The villages falling within the Amadand Opencast Block are Timki Tola,

Manjhouli, Nimha and Kuhaka Village. The entire report area including the

villages and Pasture land is covered by cultivated field.

*******

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 1 of 81

CHAPTER - IV

GEOLOGY AND DEPOSIT APPRAISAL

4.1 INTRODUCTION

4.1.1 The Amadand Opencast Block is located in the eastern part of south Sohagpur

Coalfield and is flanked by working collieries of Hasdeo and Jamuna & Kotma

areas of the SECL to the east and west respectively.

The area was identified by CMPDI for scout drilling in March 1989 on the basis

of some boreholes drilled close to some of the GSI boreholes, namely, SM-4,

6&8 etc. in the eastern part of the Amadand tract and DGM (MP) was entrusted

for scout drilling. The results of the scout drilling conducted by DGM (MP)

revealed presence of good quality workable coal deposit in an area of about

60sq.km. of the intervening Amadand tract between the working collieries of

SECL.

A detailed proving of the area was taken up by CMPDI in Aug.1990 and a

comprehensive geological information was provided in Geological Reports on

Bartarai Block in Dec.'93, Amadand Opencast area in Dec.'95, Bakulmuni Block

in July'97, Amadand East U/G Block in January 1998 and Amadand West U/G

Block in Nov.’99.

The Amadand Opencast Area has been prepared after considering the Upper

Kotma seam only. However, the present report is prepared at the behest of

Mining Department, considering the area of aforesaid 4 reports in part or total

from the opencast stand point considering all the seams. Accordingly the data

have been re-processed, boreholewise from underground norms to opencast

norm and many coal seams and/coal bands intersected in boreholes, earlier not

taken into account, have been considered along with their naming. Wherever

necessary, earlier splits of seams have been merged, as per the revised norms

considered for opencast mine. In the area of present seams, L-6, L-5, UK (Top),

UK (Bottom), UK, L-4, L-3(Top), L-3 (Bottom), L-3, MK (Top), MK (Bottom),

MKC, L-2, LK-I, L-1, LK-II (Top), LK-II (Bottom) & LK-II have encountered in

descending order.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 2 of 81

4.1.2 Block Boundaries

The geographical boundary of Amadand Opencast block is as follows:

North : Floor of incrop of Upper Kotma Seam and E-W trending

Fault F1-F1 (Southern boundary of Khodri Block).

South : Floor Incrop of seam MKB.

East : A line connecting common boundary of Bakulmuni and

Bartarai blocks passing through borehole CMAD-235A.

West : Floor Incrop of Upper Kotma Seam along boreholes CMAD-

638, 539, 262 and line passing through boreholes CMAD-

112 & 511.

The block measures 15.061 sq. km which includes 14.154 Sq. km free area and

0.907sq.km forest area.

4.1.3 It is not a virgin block. The mining activity is in progress based on reports

submitted earlier.

4.2 EXPLORATION STATUS

4.2.1 Summary of Exploratory Boreholes

Financial year wise break up of drilling in Amadand OC Block is given below:

Agencywise, periodwise No. of boreholes drilled, Amadand O/C Block, Sohagpur Coalfield.

Agency Period Drilling Source of

Funding From To No.of Bhs. Meterage

CMPDI 1990 1991 17 2423.45 CIL

1991 1992 27 3792.20

1992 1993 27 3931.65

1993 1994 36 4593.45

1994 1995 27 3458.85

1995 1996 33 1858.25

1997 1998 7 991.7

1998 1999 1 133.00

Total CMPDI 175 21182.55

DGM(M.P.) 1988 1989 1 105.85

1989 1990 10 1532.79

Total DGM(M.P.) 11 1638.64

GRAND TOTAL 186 22821.19

Thus, a total of 186 boreholes have been considered in this chapter.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 3 of 81

4.2.2 Overall borehole density in the geological block is 13.68 per sq. km.

Seam Number of intersections

UK TOP 31

UK BOT 31

UK 139

L4 113

L3 TOP 60

L3 BOT 53

L3 72

MK TOP 96

MK BOT 94

MKC 66

L2 69

LKI 143

L1 81

LKII TOP 31

LKII BOT 31

LKII 117

4.2.3 Status of analysis

Seam-wise, band-by-band, overall proximate analysis and other tests are

tabulated below

Seam Number of intersections

Band by band

analysis

Overall proximate analysis on 60% RH & 40oC

GCV K.cal./

kg.

Ultimate analysis

AFT HGI

Determined Calculated

L5 58 7 4 4 - - -

UKTOP 31 136 25 25 1 1 1

UKBOT 31 27 27 1 2 2

UK 139 105 105 7 8 5

L4 113 17 17 17 1 1 1

L3TOP 60 75 17 17 - - -

L3BOT 53 11 11 - - -

L3 72 54 54 2 4 3

MKTOP 96 163 74 74 6 7 4

MKBOT 94 80 80 2 4 4

MKC 66 66 66 - 1 1

L2 69 2 - - L2

LKI 143 77 66 58 - 1 1

L1 81 17 15 15 - - -

LKIITOP 31 161 21 21 - - -

LKIIBOT 31 18 18 1 - -

LKII 117 108 108 6 7 2

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 4 of 81

4.2.4 Reliability of data and degree of confidence (based on statistical analysis)

1) In the absence of any surface exposure of the strata, the report is based

entirely on the data obtained from 228 boreholes drilled by CMPDI and

DGM (MP) falling within Amadand OC Block.

2) The area shows variable dip, and the area is devoid of fault. However, the

possibility of faults of smaller magnitude cannot be entirely ruled out in the

area. Though all care has been taken to precisely delineate the incrops of

seams on the basis of borehole data, there is a possibility of minor

variation as the exact pattern of local weathering is not known.

3) The statistical analysis of borehole data has been carried out separately for

different seams for estimating Mean and Standard Deviation of different

parameters is given below:

Particular S e a m s

L6 L5 U

K

T

U

K

B

U

K

L

4

L

3

T

L

3

B

L

3

MK

T

MK

B

M

K

C

L

2

L

K

I

L

1

L

K IIT

L

K IIB

L

K

II

T h i c k n e s s (m)

No. 2

2

5

8

3

1

3

1

1

3

9

1

1

3

6

0

5

3

7

2

9

6

9

4

6

6

6

9

1

4

3

8

1

3

1

3

1

1

1

7

Min. .

0

9

.

0

5

.

3

0

.

2

4

.1

5

.0

5

.0

8

.0

7

.

2

5

.

0

4

.

2

1

.

5

3

.

0

2

.

0

5

.

1

0

.

3

3

.

1

0

.

2

4

Max. 1

.

3

7

.

8

8

2

.

8

2

.

2

6

6.

8

7

1.

7

3

1.

2

0

0

.8

0

3

.

8

0

3

.

4

4

2

.

7

4

6

.

1

8

.

7

1

1

.

9

6

2

.

5

7

2

.

7

6

2

.

6

8

5

.

6

2

M o i s t u r e ( M % )

No. 2

5

2

7

1

0

6

1

8

1

7

1

7

5

8

8

7

9

0

6

1

6

1

1

5

2

1

1

8

1

1

9

Min. 5

.

0

3

.

8

4.

6

7.

5

4.

7

6.

5

5

.

0

4

.

2

4

.

1

4

.

5

4

.

8

4

.

5

5

.

6

5

.

6

5

.

2

Max. 1

4

.

1

1

0

.

5

1

1.

0

1

0.

3

7.

6

8.

7

8

.

7

7

.

4

9

.

8

9

.

1

9

.

7

8

.

7

9

.

4

9

.

2

9

.

7

Mean 8

.

5

7

.

9

7.

4

8.

6

6.

4

7.

8

6

.

6

5

.

4

7

.

3

5

.

9

7

.

5

7

.

5

7

.

1

7

.

5

7

.

5

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 5 of 81

Particular S e a m s

STD 1

.

8

1

.

3

1.

0

0.

7

0.

9

.8

0

.

9

0

.

8

0

.

8

9

1.

0

0

0.

9

9

1.

0

0.

9

8

0.

9

9

1

.

0

A s h ( A% )

No. 2

5

2

7

1

0

6

1

8

1

7

1

7

5

8

8

7

9

0

6

1

6

1

1

5

2

1

1

8

1

1

9

Min. 1

0.

8

1

0

.

4

1

4.

9

9.

7

1

2.

2

1

2.

2

1

2.

3

1

4.

1

9

.

1

1

5

.

5

5

.

2

8

.

7

5

.

5

7

.

6

5

.

3

Max. 3

9

.

6

3

8

.

1

4

9.

2

1

9.

3

4

3.

0

3

2.

5

4

4.

7

5

0

.

2

7

0

.

6

4

9

.

8

4

7

.

9

4

8

.

6

3

4

.

3

3

1

.

4

5

1

.

0

Mean 1

8

.

1

1

7

.

2

2

5.

1

1

3.

9

2

3.

0

2

0.

3

2

9.

4

4

3

.

8

2

0

.

6

3

7

.

5

2

2

.

2

1

9

.

9

1

9

.

2

1

5

.

6

1

6

.

3

STD 5

.

7

6

.

9

6.

4

2.

9

1

0.

1

7.

4

8.

5

6

.

5

8

.

3

8

.

6

7

.

6

1

0.

0

8

.

1

6

.

3

8

.

1

U H V

No. 2

5

2

7

1

0

6

1

8

1

7

1

7

5

8

8

7

9

0

6

1

6

1

1

5

2

1

1

8

1

1

9

Min. 2

6

0

6

2

9

8

7

1

4

2

0

5

1

2

8

2

3

2

0

3

5

6

2

2

0

4

5

1

3

3

2

1

1

2

7

1

0

8

9

1

6

3

0

1

5

7

4

3

3

7

3

3

7

3

9

1

1

3

0

Max. 6

0

4

3

6

3

3

0

5

7

8

1

6

3

1

9

6

1

5

9

6

0

1

5

6

0

4

1

5

9

3

3

6

4

4

8

5

5

4

6

6

8

7

2

6

5

0

4

6

9

4

3

6

7

6

1

7

1

3

3

Mean 5

2

2

7

5

4

5

8

4

4

0

9

5

7

7

6

4

8

6

5

5

0

2

7

3

9

2

4

2

1

0

9

5

0

8

3

2

9

0

2

4

7

7

7

5

1

1

9

5

2

1

5

5

6

9

4

5

5

6

5

STD 7

3

8

8

2

2

7

9

6

3

8

5

1

2

5

0

9

0

8

1

0

5

1

8

0

1

8

4

4

1

0

8

0

9

5

6

1

2

4

0

1

0

2

4

7

7

0

1

0

4

9

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 6 of 81

4.3 GEOLOGY AND STRUCTURE OF BLOCK AREA

4.3.1 Brief geological setting along with generalized sequence within the

block/coalfield

Stratigraphic Sequence of Sohagpur Coalfield

Age Formation Thickness(m) Lithology

Recent/Sub-Recent

Alluvium & soil

^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ Unconformity ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^

Eocene-Upper Cretaceous

Deccan Trap Effusive and intrusive rocks, mostly basalt & dolerite

^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ Unconformity ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^

Upper Cretaceous

Lameta Reddish & greyish sandstone & nodular limestones

^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ Unconformity ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^

Upper Triassic Supra Barakars (Mahadeva?)

Pink, buff and red sandstones and red shale

^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ Unconformity ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^

Lower Permian

Barakar +320m Coarse to medium grained sand-stones,subordinate shales and coal seam, thin & moderately thick

Upper Carboniferous

Talchir +430m Diamictite, siltstone, sandstone & needle shales.

^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ Unconformity ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^

Precambrian Porphyritic granite gneisses with pigmatite veins.

4.3.2 Coal bearing formations

The coal bearing Barakar Formation is mainly composed of greyish white, fine to

medium grained loosely compact sandstone with occasional coarse grained

sandstone. Moreover, grey shale, sandy shale and carbonaceous shale with coal

bands are found to occur in the Formation. The thickness of preserved section of

Barakar in the area is about +224m. The potential workable coal horizons are

restricted to the top 140m while the lower 110m of Barakar strata is devoid of

workable coal horizons.

Eighteen coal seams viz. Seam L6, L5, UKT, UKB, UK, L4, L3T,L3B, L3, MKT,

MKB, MKC, L2, LKI, L1, LKIIT, LKIIB and LKII in descending order occur in

Barakar Formation.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 7 of 81

Sequence of coal seams and partings within the block area

Seam Surface Cover (m)

Area of Developmen

t (sq. km.) [As per GR]

Thickness Range (m)

Grade Range

(Dominant Grade)

Borehole Intersection (As per GR)

Borehole Density/ sq. Km.

Geological Reserves

(Mt) [As per GR]

L6 Incrop-27.32 - 0.09-1.37 22 -

Parting - 4.11-11.56

L5 Incrop-32.35 - 0.05-0.88 F-B(D) 58 -

Parting - 0.60-4.39

UKTOP Incrop-28.40 1.128 0.30-2.80 F-B(C) 31 27 2.419

Parting 1.03-5.41

UKBOT Incrop-33.76 1.201 0.24-2.26 F-A(C) 31 26 1.622

Parting with L4

9.95-22.25

UK Incrop-37.35 7.258 0.45-6.87 G-B(D) 139 19 38.250

Parting 8.74-28.65

L4 Incrop-59.60 1.966 0.05-1.73 C-A(B) 113 57 1.818

Parting 13.35-27.05

L3T Incrop-80.75 2.271 0.08-1.25 G-B(D) 60 26 2.113

Parting 1.01-6.88

L3B Incrop-81.91 1.517 0.07-0.80 E-B(C) 53 35 1.222

Parting with MKTOP

1.46-11.91

L3 Incrop-77.15 4.198 0.25-3.80 G-B(D) 72 17 6.339

Parting with MKTOP

1.25-6.08

MKTOP Incrop-87.15 6.750 0.04-3.44 G-B(G) 96 14 19.012

Parting 0.94-16.23

MKBOT Incrop-90.06 8.112 0.21-2.74 G-A(C) 94 12 12.871

Parting with L2

2.85-27.55

MKC Incrop-89.87 5.309 0.53-6.18 G-C(F) 66 12 26.961

Parting 12.00-29.45

L2 28.75-111.78 - 0.02-0.71 69 -

Parting 1.55-13.78

LKI 34.04-122.39 7.809 0.05-1.96 F-A(D) 143 18 8.724

Parting 10.40-32.16

L1 45.14-137.78 2.508 0.10-2.57 G-A(C) 81 32 2.466

Parting 2.11-21.90

LKIIT 65.28-147.07 2.799 0.36-2.76 E-A(C) 31 11 3.372

Parting 1.05-4.21

LKIIB 69.54-150.26 2.240 0.10-2.68 D-A(B) 31 14 3.695

LKII 66.20-150.40 11.592 0.24-5.62 UG-A(B) 117 10 29.703

4.3.4 Structural setting within the project area

The featureless rolling topography and a thick soil cover in and around Amadand

Open Cast Block have completely masked the surface expression of the

structural elements. The entire structural set-up of the area, therefore, has been

worked out on the sub-surface data obtained through boreholes. It shows that

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 8 of 81

the Amadand Open Cast Block is located in the central part of the broad

basinal structure in the Amadand sub-basin intervening Jamuna & Kotma and

Jhagrakhand sub-basin and the same is presented in the form of Geological Map

(Plate-II).

4.3.5 STRIKE AND DIP

In the southern part of the block the strike is roughly E-W with 1o-2o northerly dip.

In the north-eastern part of the block the strike is roughly NW-SE with 2o-4o

south westerly dip. In the north eastern part of the block the strike is roughly E-

W with 1o to 3o southerly dip. In the western part of the block the dip of the strata

is less than a degree to almost flat. The overall structure may be attributed to the

depositional rolling nature of basin configuration.

4.3.6 PATTERN OF FAULT

The considered area is devoid of any fault. Earlier while preparing Amadand

Opencast area report, faults were interpreted but in due course after receipt of

more data of boreholes the possibility of faults was ruled out.

4.3.7 INTRUSIVES

Dolerite has been intersected in borehole no AMD-8 at the depths of 168.60m &

172.50m, located in the northern part of the block. From intersection it has been

surmised that the intrusive body has a discordant relation with the host rock. The

magnetic survey conducted in the area has confirmed the above postulate and

has delineated a single E-W trending, 24m-60m thick dyke. From the magnetic

intensity data, the dyke has been inferred to occur at a shallow depth in the

northern part of the block. Either the dyke occurs at a considerable depth or it is

highly weathered near the surface. No other dolerite body has been picked up in

the magnetic survey scanning in the balance part of the area.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 9 of 81

4.4 DESCRIPTION OF INDIVIDUAL COAL SEAMS 4.4.1 SEAM-L6

Seam L6 is the top most from the surface within the Barakar Formation.

No splitting in this seam is observed in the block area.

This seam is intersected in 22 boreholes restricted in the central part of the block

area. The thickness range varies between 0.09m to 1.37m with more than 0.50m

thickness in 12 boreholes. The average thickness is 0.62m. Minimum parting in

respect of Seam L5, down below is 4.11m (CMAD-340) whereas the maximum

parting is 11.56 m (CMAD-271).

As the seam is having low thickness, not covering the considerable area in the

block and paucity of analytical data, Seam L6 is not considered for reserve

estimation as well as for structural interpretation.

4.4.2 SEAM-L5

This seam is second from the surface. This Seam is intersected in 58 boreholes.

The minimum thickness of 0.05m is observed in borehole No.CMAD-15 and

maximum thickness of 0.88m is observed in borehole No.CMAD-36. The seam is

having more than 0.50m thickness in 10 boreholes only. Though the Seam L5 is

more persistent than Seam L6, the workable area is distributed in patches. The

band-by-band analysis and proximate analysis are available for seven and four

boreholes respectively .The seam is not considered for reserve estimation.

4.4.3 SEAM-UPPER KOTMA TOP (UKT)

A. STATUS OF MINING

Mining activity is in developmental stage for Upper Kotma and its splits Seam in

Amadand OC block.

B. DETAILS OF BOREHOLES INTERSECTION

A. Intersections Nos.

i) No. of full seam intersections in boreholes 31

ii) No. of outcrop proving boreholes with part thickness Nil

iii) No. of boreholes with part thickness due to faulting Nil

iv) No. of boreholes where seam is totally omitted due to fault Nil

v) No. of boreholes where seam is merged with lower seam Nil

vi) No. of boreholes where seam is not encountered due to non-development of seam and presence of dyke

Nil

vii) No. of boreholes not deepened to encounter the seam Nil

viii) No. of boreholes beyond incrop Nil

TOTAL 31

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 10 of 81

a. Depth of intersection (Roof)

i) Shallowest : 10.15m (CMAD-152, 332, 339)

ii) Deepest : 28.40m (CMAD-63)

b. Minimum & Maximum FRLs

i) Minimum : 508.07m (CMAD-334)

ii)Maximum : 530.15m (CMAD-152)

C. STRATIGRAPHIC POSITION

Seam-UK Top being the top most split of Seam Upper Kotma is the third from

surface within the Barakar Formation.

D. PARTING In the block area this is the topmost workable coal seam. The seam occurs at a

minimum depth of 10.15m (CMAD-152, 332, 339) from the surface in the north

eastern and south western parts of the block and at a maximum depth of 28.40m

(CMAD-63) in the south central part of the block.

The parting between UKT & UKB seams predominantly consists of arenaceous

facies represented by sandstone. Since coal seams UKT & UKB are merged at

places, parting between them ranges between 0.00m to 5.36m (CMAD-343).

E. THICKNESS

It is observed that the minimum thickness of 0.30m is intersected in borehole

No.CMAD-63 and maximum thickness of 2.80m is intersected in borehole

No.CMAD-62. The average thickness of seam is 1.65m. Since Seam UKT is

having workable thickness in patches in major part of the block area, it is

described in detail and also considered for assessment of availability of coal

reserves.

F. SPLITTING

This seam does not show splitting in the block area.

G. OUTCROP/INCROP

The seam incrops to represent a broad basinal structure with its E-W longer axis

alongwith corresponding centripetal dip. The position of incrop is below the

weathered mantle.

H. ROOF & FLOOR

The immediate roof of Seam-UKT consists predominantly of coarse grained

sandstone, at places it is clay and sandy soil also. The immediate floor consists

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 11 of 81

of predominantly sandstone and sandy shale. At places, occasionally fine

grained to medium grained sandstone and carbonaceous shale are also found.

I. DIRT BANDS

This seam, barring a few boreholes, is generally devoid of dirt bands. Dirt bands in Seam UKT (on I10 basis)

Thickness range of seam

(m)

Effective thickness range (m)

Carbonaceous shale bands

Non-Combustible bands Total bands

No.of bands/ No.

of BHs

Thick. range (m)

No.of bands/ No. of BHs

Thickness range (m)

No.of bands/ No.

of BHs

Thick. range (m)

0.30-2.80 0.30-2.80 - - 1/1 0.02 1/1 0.02

J. PROXIMATE ANALYSIS

Grades on I10 samples show the grade variation between F-B. But in major part

of the block, the general grade is “C”.

Range of proximate analysis & grade of Seam-UKT, Amadand OC Block

Parameters Range

Bcs Sample I10 Sample I100 Sample Full Seam

Boreholes considered : 25 25 25 Thickness/Range (m) Mean STD.DEV

0.30-2.80 (CMAD-63) (CMAD-62)

1.71 0.82

0.30-2.80 (CMAD-63) (CMAD-62)

1.71 0.82

0.30-2.80 (CMAD-63) (CMAD-62)

1.71 0.82

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.30-2.80 (CMAD-63) (CMAD-62)

1.71 0.82

0.30-2.80 (CMAD-63) (CMAD-62)

1.71 0.82

0.30-2.80 (CMAD-63) (CMAD-62)

1.71 0.82

Proximate analysis in 60% RH & 400 C

M% Mean STD.DEV.

5.0–14.1 (CMAD-315) (CMAD-273)

5.5 1.80

5.0–14.1 (CMAD-315) (CMAD-273)

8.5 1.80

5.0–14.1 (CMAD-315) (CMAD-273)

8.5 1.80

Ash% Mean STD.DEV

10.80-39.60 (CMAD-30) (CMAD-55)

18.1 5.7

10.80-39.60 (CMAD-30) (CMAD-55)

18.1 5.7

10.80-39.60 (CMAD-30) (CMAD-55)

18.1 5.7

VM% Mean STD.DEV

26.5 – 31.3 (CMAD-37) (CMAD-273)

28.7 1.4

26.5 – 31.3 (CMAD-37) (CMAD-273)

28.7 1.4

26.5 – 31.3 (CMAD-37) (CMAD-273)

28.7 1.4

FC% Mean STD.DEV

35.9 – 49.8 (CMAD-273) (CMAD-315)

45.2 3.7

35.9 – 49.8 (CMAD-273) (CMAD-315)

45.2 3.7

35.9 – 49.8 (CMAD-273) (CMAD-315)

45.2 3.7

UHV (Kcal/kg) Mean STD.DEV

2606 - 6043 (CMAD-55) (CMAD-315)

5227 738

2606 - 6043 (CMAD-55) (CMAD-315)

5227 738

2606 - 6043 (CMAD-55) (CMAD-315)

5227 738

Grade Avg. Grade

F-B C

F-B C

F-B C

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 12 of 81

K. GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam-UKT, Amadand OC Block

Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg)

Bcs I10 I100

25 0.30-2.80 3954 - 6350 (CMAD-55) (CMAD-315)

3954 - 6350 (CMAD-55) (CMAD-315)

3954 - 6350 (CMAD-55) (CMAD-315)

L. ULTIMATE ANALYSIS

Range of Ultimate Analysis for Seam-UKT, Amadand OC Block

Parameters Range of content %

Ultimate Analysis on Bcs/Ex-band sample (dmmf basis) (No. of samples 1) (Borehole No.CMAD-56).

C% 79.29

H% 4.84

N% 1.57

S% 0.65

M. ASH FUSION TEMPERATURE RANGE

Ash Fusion Temperature Range for Seam-UKT (including bands), Amadand OC

Block, Sohagpur Coalfield.

Borehole considered

Thickness range (m) Ash fusion range oC(under mildly reducing atmosphere)

IDT HT FT

1 2.39 (CMAD-56) 1170 >1400 >1400

N. HARDGROVE GRINDABILITY INDEX (HGI) HGI of 1 borehole of Seam UKT of Amadand OC Block sample is given as

under:

H.G.I. for Seam-UKT, Amadand OC Block, Sohagpur Coalfield

No. of boreholes

Nature of Sample

Range

Minimum Maximum 1 (CMAD-56) Bcs/I10/I100 50

O. ASH ANALYSIS

ASH ANALYSIS (on In band basis)

Borehole No.

Constituents %

SiO2 Al2O3 Fe2O3 TiO2 P2O5 SO3 MnO CaO MgO Alkalies by diff.

CMAD-56 58.90 31.70 5.1 1.10 0.02 0.40 0.12 0.96 0.98 0.72

4.4.4 SEAM-UPPER KOTMA BOTTOM (UKB)

A. STATUS OF MINING

Mining activity is in developmental stage for Upper Kotma Seam and its splits in

Amadand OC block.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 13 of 81

B. DETAILS OF BOREHOLES INTERSECTION

A. Intersections Nos.

i) No. of full seam intersections in boreholes 31

ii) No. of outcrop proving boreholes with part thickness Nil

iii) No. of boreholes with part thickness due to faulting Nil

iv) No. of boreholes where seam is totally omitted due to fault Nil

v) No. of boreholes where seam is merged with lower seam Nil

vi) No. of boreholes where seam is not encountered due to non-development of seam and presence of dyke

Nil

vii) No. of boreholes not deepened to encounter the seam -

viii) No. of boreholes beyond incrop -

TOTAL 31

a. Depth of intersection (Roof)

i) Shallowest : 11.94m (CMAD-339)

ii) Deepest : 33.76m (CMAD-521)

b. Minimum & Maximum FRLs

i) Minimum : 506.02 (CMAD-334)

ii) Maximum : 525.14m (CMAD-152)

C. STRATIGRAPHIC POSITION

Seam-UKB is the second split of UK seam and is the fourth from the top in the

Barakar Formation in the block.

D. PARTING

In the block area this seam occurs at a minimum depth of 11.94m (CMAD-339)

from the surface in the south western part of the block and at a maximum depth

of 33.76m (CMAD-521) in the north eastern part of the block.

The parting between UKB and L-4 seams predominantly consists of arenaceous

facies represented by sandstone. Its parting with Seam L4 ranges between

9.95m (CMAD-152) and 22.25m (CMAD-36).

E. THICKNESS

It is observed that the minimum coal seam thickness of 0.24m is intersected in

borehole No.CMAD-133 and maximum thickness of 2.26m in B.H. No.CMAD-62.

The general thickness of seam varies between 0.40m to 1.00m. Seam UKB has

attained workable thickness in patches in the block. Therefore, it is described in

detail and also considered for assessment of availability of coal reserves.

F. SPLITTING

This seam does not show splitting in the block area.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 14 of 81

G. OUTCROP/INCROP

The seam incrops and represent a broad basin like structure with its E-W longer

axis along with corresponding centripetal dip. The position of incrop is below the

weathered mantle.

H. ROOF & FLOOR

The immediate roof of Seam-UKT consists predominantly of coarse grained

sandstone, at places it is clay and sandy soil also. The immediate floor consists

of predominantly sandstone, sandy shale. At places, occasionally fine grained to

medium grained sandstone and carbonaceous shale are also found.

J. DIRT BANDS

This seam, barring a few boreholes, is generally devoid of dirt bands.

Dirt bands in Seam UKB (on I10 basis) Thickness

range of seam (m)

Effective thickness range (m)

Carbonaceous shale bands

Non-Combustible bands Total bands

No.of bands/ No.

of BHs

Thick. range (m)

No.of bands/ No. of BHs

Thickness range (m)

No.of bands/ No.

of BHs

Thick. range (m)

0.24-2.26 0.24-2.26 1/2 0.06-0.08 1/1 0.03 1/2 0.03-0.08

K. PROXIMATE ANALYSIS

Grades on I10 samples show the grade variation between F-A. But in major part

of the block, the general grade is “C”.

Range of proximate analysis & grade of Seam-UKB, Amadand OC Block

Parameters Range

Bcs Sample I10 Sample I100 Sample Full Seam

Boreholes considered : 27 27 27

Thickness (m)/ Range (m) Mean STD.DEV

0.24-2.26 (CMAD-133) (CMAD-62)

1.09 0.39

0.24-2.26 (CMAD-133) (CMAD-62)

1.09 0.39

0.24-2.26 (CMAD-133) (CMAD-62)

1.09 0.39

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.24-2.26 (CMAD-133) (CMAD-62)

1.08 0.39

0.24-2.26 (CMAD-133) (CMAD-62)

1.09 0.39

0.24-2.26 (CMAD-133) (CMAD-62)

1.09 0.39

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

3.8 –10.5 (CMAD-55) (CMAD-30)

7.9 1.30

3.8 –10.5 (CMAD-55) (CMAD-30)

7.9 1.30

3.8 –10.5 (CMAD-55) (CMAD-30)

7.9 1.30

Ash% Mean STD.DEV

10.4-37.4 (CMAD-28) (CMAD-36)

17.1 6.5

10.4-38.1 (CMAD-28) (CMAD-152)

17.2 6.9

10.4-38.1 (CMAD-28) (CMAD-152)

17.2 6.9

VM% Mean STD.DEV

23.5 – 32.0 (CMAD-62) (CMAD-63)

28.7 2.3

23.5 – 32.0 (CMAD-62) (CMAD-63)

28.7 2.3

23.5 – 32.0 (CMAD-62) (CMAD-63)

28.7 2.3

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 15 of 81

Parameters Range

Bcs Sample I10 Sample I100 Sample FC% Mean STD.DEV

42.2 -53.3 (CMAD-63) (AMD-2)

48.0 2.4

42.2 -53.3 (CMAD-63) (AMD-2)

48.0 2.4

42.2 -53.3 (CMAD-63) (AMD-2)

48.0 2.4

UHV (Kcal/kg) Mean STD.DEV

2987 - 6330 (CMAD-36) (CMAD-28)

5458 777

2987 - 6330 (CMAD-36) (CMAD-28)

5458 823

2987 - 6330 (CMAD-36) (CMAD-28)

5458 822

Grade Avg. Grade

F-A C

F-A C

F-A C

L. GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam-UKB, Amadand OC Block.

Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg)

Bcs I10 I100

27 0.24 – 2.26 4243 -6381 (CMAD-36) (CMAD-28)

4243 -6381 (CMAD-36) (CMAD-28)

4243 -6381 (CMAD-36) (CMAD-28)

M. ULTIMATE ANALYSIS

Range of Ultimate Analysis for Seam- UKB, Amadand OC Block

Parameters Range of content %

Ultimate Analysis on Bcs/Ex-band sample (dmmf basis)(No. of samples 1) (Borehole No. CMAD-56)

C% 79.52

H% 4.80

N% 1.64

S% 0.76

N. ASH FUSION TEMPERATURE RANGE

Ash Fusion Temperature Range for Seam- UKB (including bands),

Amadand OC Block, Sohagpur Coalfield.

Borehole considered

Thickness range (m) Ash fusion range oC(under mildly reducing atmosphere)

IDT HT FT

2 1.04 - 1.89 (CMAD-55)(CMAD-56)

1160 - >1230 1400->1400 1400->1400

O. HARDGROVE GRINDABILITY INDEX (HGI) HGI of 2 boreholes of Seam UKB of Amadand OC Block samples is given as

under:-

H.G.I. for Seam- UKB, Amadand OC Block

No. of boreholes

Nature of Sample

Range

Minimum Maximum 2 (CMAD-55 & 56) Bcs/I10/I100 49 59

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 16 of 81

P. ASH ANALYSIS

ASH ANALYSIS (on In band basis)

Borehole No.

Constituents %

SiO2 Al2O3 Fe2O3 TiO2 P2O5 SO3 MnO CaO MgO Alkalies by diff.

CMAD-55 58.36 31.40 5.6 1.33 0.04 0.44 0.12 1.00 0.94 0.77

CMAD-56 60.46 30.46 4.7 1.12 0.03 0.41 0.10 0.95 0.98 0.79

4.4.5 SEAM: UPPER KOTMA (UK)

A. STATUS OF MINING

Mining activity is in developmental stage for Upper Kotma and its splits Seam in

Amadand OC block.

B. DETAILS OF BOREHOLES INTERSECTION

A. Intersections Nos.

i) No. of full seam intersections in boreholes 139

ii) No. of outcrop proving boreholes with part thickness 2

iii) No. of boreholes with part thickness due to faulting Nil

iv) No. of boreholes where seam is totally omitted due to fault Nil

v) No. of boreholes where seam is merged with lower seam Nil

vi) No. of boreholes where seam is not encountered due to non-development of seam and presence of dyke

NIL

vii) No. of boreholes not deepened to encounter the seam NIL

vii) No. of boreholes beyond incrop 14 TOTAL 155

a. Depth of intersection (Roof)

i) Shallowest : 3.05m (CMAD-523)

ii) Deepest : 37.35m (CMAD-35)

b. Minimum & Maximum FRLs

i) Minimum : 502.03m (CMAD-340)

ii) Maximum : 534.75m (AMD-005)

C. STRATIGRAPHIC POSITION

This is the third workable seam and fifth from the surface within the Barakar

Formation in the block.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 17 of 81

D. PARTING

In the block area seam occurs at a minimum depth of 3.05m (CMAD-523) from

surface in the western part of the block and maximum at a depth of 37.35m

(CMAD-35) also in the western part of the block.

The parting between Seam UK and Seam L4 predominantly consists of

arenaceous facies represented by sandstone. The parting between Seam UK

and Seam L4 ranges between 8.74m (CMAD-8) and 28.65M (CMAD-12) in the

eastern part of the block.

E. THICKNESS

It is observed that the coal seam thickness ranges between 0.45m (CMAD-51)

and 6.87m (CMAD-325). The seam exhibits a general reduction in its thickness

from east to west. The seam deteriorates into clay and carbonaceous shale in 22

and 2 boreholes respectively.

F. SPLITTING

The seam shows splitting into two seams (UKT & UKB) at various places, mostly

near incrop region. The splitting is due to development of parting ranging from

1.03m to 5.36m.

G. OUTCROP/INCROP

The seam’s incrop is in elliptical fashion in conformity to the basinal configuration

of the deposits. In the incrop regions, the seam in general has been observed to

deteriorate into clay in 22 boreholes and into carbonaceous shale in 2 boreholes.

The incrop shown is generally below the weathered mantle except near borehole

nos. AMD-05, CMAD-72, 80, 101, 172, 192, 282, 283 & 328 in which seam has

deteriorated and occurrence is within weathered zone. The incrop is shown upto

the borehole to avoid the confusion of up dip position of boreholes

H. ROOF & FLOOR

The immediate roof is generally sandy soil or clay. The floor of seam consists of

mainly sandstone.

I. DIRT BANDS

This seam contains impersistent dirt band. The lithology of dirt band is either

carbonaceous shale or shale. In the northern and central part of the area dirt

band is closer to the roof whereas in the southern part of the area it is located

closer to the seam floor.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 18 of 81

Dirt bands in Seam UK (on I10 basis) Thickness

range of seam (m)

Effective thickness range (m)

Carbonaceous shale bands

Non-Combustible bands Total bands

No.of bands/ No.

of BHs

Thick. range (m)

No.of bands/ No. of BHs

Thickness range (m)

No.of bands/ No.

of BHs

Thick. range (m)

0.15-6.87 0.15-6.45 1/1 0.10 - - 1/1 0.10

J. PROXIMATE ANALYSIS

Grades on I10 samples show the grade variation between G-B. But in major part of

the block, the general grade is “D”.

Range of proximate analysis & grade of Seam-UK, Amadand OC Block.

Parameters Range

Bcs Sample I10 Sample I100 Sample

Full Seam

Boreholes considered :

106 106 106

Thickness (m)/Range (m) Mean STD.DEV

0.15-6.87 (CMAD-282) (CMAD-325)

4.34 1.40

0.15-6.87 (CMAD-282) (CMAD-325)

4.34 1.40

0.15-6.87 (CMAD-282) (CMAD-325)

4.34 1.40

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.15-6.45 (CMAD-282) (CMAD-12)

4.11 1.34

0.15-6.45 (CMAD-282) (CMAD-12)

4.11 1.34

0.15-6.87 (CMAD-282) (CMAD-325)

4.34 1.40

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

3.5 –11.0 (CMAD-319) (CMAD-4)

7.6 1.20

3.5 –11.0 (CMAD-319) (CMAD-4)

7.6 1.10

4.6 –11.0 (CMAD-34) (CMAD-4)

7.4 1.0

Ash% Mean STD.DEV

6.7-49.1 (CMAD-320) (CMAD-274)

22.1 6.6

13.6-49.1 (CMAD-17) (CMAD-274)

22.3 6.4

14.9-49.2 (CMAD-71) (CMAD-34)

25.1 6.4

VM% Mean STD.DEV

18.3 –58.6 (CMAD-274) (CMAD-115)

26.5 4.3

18.3 –58.6 (CMAD-274) (CMAD-115)

26.4 4.3

18.3 –34.1 (CMAD-274) (CMAD-156)

25.7 2.3

FC% Mean STD.DEV

14.0 -61.4 (CMAD-15) (CMAD-320)

44.5 5.4

14.0 -51.9 (CMAD-15) (CMAD-338)

44.3 5.1

26.3 -49.5 (CMAD-156) (CMAD-71)

43.1 4.2

UHV (Kcal/kg) Mean STD.DEV

1420 - 7368 (CMAD-274) (CMAD-320)

4804 854

1420 - 6084 (CMAD-274) (CMAD-319)

4772 816

1420 - 5781 (CMAD-274) (AMD-25)

4409 796

Grade Avg. Grade

G-A D

G-B D

G-B D

K. GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam UK, Amadand OC Block, Sohagpur Coalfield.

Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

106 0.15 – 6.45 3240 - 7184

(CMAD274) (CMAD320) 3240- 6455

(CMAD274) (CMAD319) 3240- 6100

(CMAD274) (AMD-25)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 19 of 81

L. ULTIMATE ANALYSIS

Range of Ultimate Analysis for Seam UK, Amadand OC Block.

Parameters Range of content %

Ultimate Analysis on Bcs/Ex-band sample (dmmf basis)(No. of samples 7)

C% 78.19 - 81.64 (CMAD-52) (AMD-8)

H% 4.73 - 5.01 (CMAD-163) (AMD-6)

N% 1.31 - 1.87 (CMAD-134) (AMD-15)

S% 0.45 - 0.98 (CMAD-134) (CMAD-163)

M. ASH FUSION TEMPERATURE RANGE

Ash Fusion Temperature Range Seam UK(including bands), Amadand OC Block

Borehole considered

Thickness range (m)

Ash fusion range oC(under mildly reducing atmosphere)

IDT HT FT

8 3.50-6.05 1150->1370 1280->1400 1270->1400

N. HARD GROVE GRINDABILITY INDEX (HGI) FOR SEAM VIIIB

HGI of 5 boreholes of Seam UK of Amadand OC Block samples is given as under:

H.G.I. for Seam UK, Amadand OC Block, Sohagpur Coalfield

No. of boreholes

Nature of Sample Range

Minimum Maximum

5 Bcs/I10/I100 46 57

O. ASH ANALYSIS

ASH ANALYSIS (on In band basis) Borehole

No. Constituents %

SiO2 Al2O3 Fe2O3 TiO2 P2O5 SO3 MnO CaO MgO Alkalies by diff.

CMAD-14 57.80 28.20 4.10 2.20 0.01 0.92 - 2.94 2.35 1.48

CMAD-52 60.40 30.10 4.90 1.20 0.02 0.38 0.10 0.98 0.96 0.96

CMAD-134 In-band

51.20 36.82 5.20 1.55 0.10 0.15 0.20 1.76 1.60 1.42

CMAD-134 Ex-band

50.60 37.97 5.98 1.50 0.05 0.10 0.10 1.40 1.20 1.10

CMAD-163 59.24 29.76 3.95 1.50 0.08 0.20 0.10 1.47 1.65 2.05

CMAD-164 58.26 31.00 4.16 1.50 0.08 0.10 0.10 1.67 1.44 1.69

4.4.6 SEAM-L4

A. STATUS OF MINING

The seam is devoid of mining activity in the block.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 20 of 81

B. DETAILS OF BOREHOLES INTERSECTION

A. Intersections Nos.

i) No. of full seam intersections in boreholes 113

ii) No. of outcrop proving boreholes with part thickness Nil

iii) No. of boreholes with part thickness due to faulting Nil

iv) No. of boreholes where seam is totally omitted due to fault

Nil

v) No. of boreholes where seam is merged with lower seam

Nil

vi) No. of boreholes where seam is not encountered due to non-development of seam and presence of dyke

36

vii) No. of boreholes not deepened to encounter the seam 27

viii) No. of boreholes beyond incrop 10

TOTAL 186

a. Depth of intersection (Roof)

i) Shallowest : 18.00m (AMD-16)

ii) Deepest : 59.60m (CMAD-39)

b. Minimum & Maximum FRLs

i) Minimum : 481.58m (CMAD-340)

ii) Maximum : 524.25 (AMD-16)

C. STRATIGRAPHIC POSITION

This is the fourth workable seam and sixth from the surface within the Barakar

Formation in the block.

D. SPLITTING

The seam does not show splitting in the block area.

E. PARTING

The seam occurs at a minimum depth of 18.00m (AMD-16) from the surface in

the northern part and at a maximum depth of 59.60m (CMAD-39) in the north

western part of the block.

The parting between L4 and L3T & L3 seams predominantly consists of

arenaceous facies represented mainly by sandstone. The parting between

aforesaid seams varies in the range of 13.35m (CMAD-45) to 27.050m (AMD-9).

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 21 of 81

F. THICKNESS

It is observed that minimum thickness of 0.05m in borehole No.CMAD-18 is

intersected and maximum thickness of 1.73m in borehole No.CMAD-112. The

general thickness of seam varies between 0.40m to 0.70m.

Though the seam is widely spread in distribution in the block, the workable

thickness of 0.50m and above is found only in 33 boreholes. The main workable

patch is developed in the south western part.

Therefore, this seam is described in detail and also considered for assessment

of availability of coal reserves.

G. OUTCROP/INCROP

The seam incrops along the southern and north eastern parts of the block area.

The position of incrop is below the weathered mantle.

H. ROOF & FLOOR

The immediate roof and floor of the seam consists mainly medium to coarse

grained sandstone.

I. DIRT BANDS

This seam barring two boreholes (CMAD-314, 315) is devoid of dirt bands. Dirt bands in Seam L4 (on I10 basis)

Thickness range of seam

(m)

Effective thickness range (m)

Carbonaceous shale bands

Non-Combustible bands Total bands

No.of bands/ No.

of BHs

Thick. range (m)

No.of bands/ No. of BHs

Thickness range (m)

No.of bands/ No.

of BHs

Thick. range (m)

0.45 - 1.73 0.45 -

1.73

- - 1/2 0.03-0.03 1/2 0.03-0.03

J. PROXIMATE ANALYSIS

Grades on I10 samples show the grade variation between C to A. The general

grade is B.

Range of proximate analysis & grade of Seam L4, Amadand OC Block.

Parameters Range

Bcs Sample I10 Sample I100 Sample Full Seam

Boreholes considered :

17 17 17

Thickness (m)/Range (m) Mean STD.DEV

0.45 - 1.73 (CMAD-190)(CMAD-112)

0.84 0.30

0.45 - 1.73 (CMAD-190)(CMAD-112)

0.84 0.30

0.45 - 1.73 (CMAD-190)(CMAD-112)

0.84 0.30

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 22 of 81

Parameters Range

Bcs Sample I10 Sample I100 Sample Effect. Thickness (m)/Range (m) Mean STD.DEV

0.45 - 1.73 (CMAD-190)(CMAD-112)

0.84 0.30

0.45 - 1.73 (CMAD-190)(CMAD-112)

0.84 0.30

0.45 - 1.73 (CMAD-190)(CMAD-112)

0.84 0.30

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

7.5 – 10.3 (AMD-25) (CMAD-24)

8.6 0.7

7.5 – 10.3 (AMD-25) (CMAD-24)

8.6 0.7

7.5 – 10.3 (AMD-25) (CMAD-24)

8.6 0.7

Ash% Mean STD.DEV

9.7 - 19.3 (CMAD-56) (AMD-9)

13.9 2.9

9.7 - 19.3 (CMAD-56) (AMD-9)

13.9 2.9

9.7 - 19.3 (CMAD-56) (AMD-9)

13.9 2.9

VM% Mean STD.DEV

25.6 – 32.4 (CMAD-22) (AMD-25)

29.4 2.0

25.6 – 32.4 (CMAD-22) (AMD-25)

29.4 2.0

25.6 – 32.4 (CMAD-22) (AMD-25)

29.4 2.0

FC% Mean STD.DEV

45.0 - 53.8 (AMD-9) (CMAD-22)

48.7 2.7

45.0 - 53.8 (AMD-9) (CMAD-22)

48.7 2.7

45.0 - 53.8 (AMD-9) (CMAD-22)

48.7 2.7

UHV (Kcal/kg) Mean STD.DEV

5128 - 6319 (AMD-9) (CMAD-56)

5789 367

5128 - 6319 (AMD-9) (CMAD-56)

5789 367

5128 - 6319 (AMD-9) (CMAD-56)

5776 385

Grade Avg. Grade

C-A B

C-A B

C-A B

K. GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam L4, Amadand OC Block, Sohagpur Coalfield.

Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

17 0.45-1.73 5570 - 6400 (AMD-9) (AMD-25)

5570 - 6400 (AMD-9) (AMD-25)

5570 - 6400 (AMD-9) (AMD-25)

L. RANGE OF ULTIMATE ANALYSIS

Range of Ultimate Analysis for Seam L4, Amadand OC Block.

Parameters Range of content %

Ultimate Analysis on Bcs/Ex-band sample (dmmf basis)(No. of samples 1) (Borehole No.CMAD-56)

C% 79.42

H% 4.85

N% 1.62

S% 0.75

M. ASH FUSION TEMPERATURE RANGE

Ash Fusion Temperature Range for Seam L4(including bands), Amadand OC Block, Sohagpur Coalfield.

Borehole considered

Thickness range (m) Ash fusion range oC(under mildly reducing atmosphere)

IDT HT FT

1 0.90 (CMAD-56) 1130 >1400 >1400

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 23 of 81

N. HARDGROVE GRANDABILITY INDEX (HGI)

HGI of 1 borehole of Seam L4 of Amadand OC Block sample is given as under:

H.G.I. for Seam L4, Amadand OC Block, Sohagpur Coalfield.

No. of boreholes Nature of Sample Range

Minimum Maximum

1 (CMAD-56 ) Bcs/I10/I100 48

O. ASH ANALYSIS ASH ANALYSIS (on In-band basis)

Borehole No.

Constituents %

SiO2 Al2O3 Fe2O3 TiO2 P2O5 SO3 MnO CaO MgO Alkalies by diff.

CMAD-14 58.60 31.80 5.20 1.20 0.02 0.40 0.11 0.98 0.99 0.70

4.4.7 SEAM-L3 TOP (L3T)

A. STATUS OF MINING

The seam is devoid of mining activity in the block.

B. DETAILS OF BOREHOLES INTERSECTION

A. Intersections Nos.

i) No. of full seam intersections in boreholes 60

ii) No. of outcrop proving boreholes with part thickness Nil

iii) No. of boreholes with part thickness due to faulting Nil

iv) No. of boreholes where seam is totally omitted due to fault Nil

v) No. of boreholes where seam is merged with lower seam Nil

vi) No. of boreholes where seam is not encountered due to non-development of seam and presence of dyke

11

vii) No. of boreholes not deepened to encounter the seam -

viii) No. of boreholes beyond incrop - TOTAL 71

a. Depth of intersection (Roof)

i) Shallowest : 30.30m (CMAD-6)

ii) Deepest : 80.75m (CMAD-340)

b. Minimum & Maximum FRLs

i) Minimum : 459.85m (CMAD-340)

ii) Maximum : 503.60m (CMAD-6)

C. STRATIGRAPHIC POSITION

Seam L3T being the top most split of seam L3 is the seventh from the surface

and the fifth workable seam within the Barakar Formation in the block.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 24 of 81

D. SPLITTING

The seam is the split of L3 seam. This splitting is observed in the eastern,

northern and western parts of the block. The seam itself does not further split in

the block.

E. PARTING

The seam occurs at a minimum depth of 30.30m (CMAD-6) from the surface in the

southern part and at a maximum depth of 80.75m (CMAD-340) in the north-

western part of the block,

The parting between L3T and L3B seams predominantly consists of arenaceous

facies The parting between aforesaid seams ranges between 1.01m (CMAD-144)

and 6.88m (CMAD-63).

F. THICKNESS

It is observed that minimum thickness of 0.08m is observed in borehole

No.CMAD-48 and maximum thickness of 1.20m in borehole No.CMAD-188. The

average thickness is 0.45m.

The seam is described in detail and also considered for assessment of availability

of coal reserves.

G. OUTCROP/INCROP

The seam incrops along the southern and north-eastern parts of the block area.

The position of incrop is below the weathered mantle.

H. ROOF & FLOOR

The immediate roof and floor of the seam consists mainly medium to coarse

grained sandstone.

I. DIRT BANDS

This seam barring a few boreholes is devoid of dirt bands.

Dirt bands in Seam L3T (on I10 basis) Thickness range of seam (m)

Effective thickness range (m)

Carbonaceous shale bands

Non-Combustible bands Total bands

No.of bands/ No.

of BHs

Thick. range (m)

No.of bands/ No. of BHs

Thickness range (m)

No.of bands/ No.

of BHs

Thick. range (m)

0.35 - 1.25 0.35 - 1.20 1/1 0.08 1/1 0.10 1/2 0.08-0.10

J. PROXIMATE ANALYSIS

Grades on I10 samples show the grade variation between G to B. The general

grade is D.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 25 of 81

Range of proximate analysis & grade of Seam L3T, Amadand OC Block Parameters Range

Bcs Sample I10 Sample I100 Sample Full Seam

Boreholes considered :

17 17 17

Thickness (m)/Range (m) Mean STD.DEV

0.35 - 1.20 (CMAD-101)(CMAD-188)

0.75 0.23

0.35 - 1.20 (CMAD-101)(CMAD-188)

0.75 0.23

0.35 - 1.20 (CMAD-101)(CMAD-188)

0.75 0.23

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.35 - 1.20 (CMAD-101)(CMAD-188)

0.75 0.23

0.35 - 1.20 (CMAD-101)(CMAD-188)

0.75 0.23

0.35 - 1.20 (CMAD-101)(CMAD-188)

0.75 0.23

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

4.7 – 7.6 (CMAD-20) (CMAD-23)

6.4 0.9

4.7 – 7.6 (CMAD-20) (CMAD-23)

6.4 0.9

4.7 – 7.6 (CMAD-20) (CMAD-23)

6.4 0.9

Ash% Mean STD.DEV

12.2 - 43.0 (CMAD-66) (CMAD-20)

22.4 10.0

12.2 - 43.0 (CMAD-66) (CMAD-20)

22.4 10.0

12.2 - 43.0 (CMAD-66) (CMAD-20)

22.8 10.1

VM%5 Mean STD.DEV

20.7 – 31.8 (CMAD-83) (CMAD-66)

26.3 4.1

20.7 – 31.8 (CMAD-83) (CMAD-66)

26.5 4.3

20.7 – 31.8 (CMAD-83) (CMAD-66)

26.5 4.3

FC% Mean STD.DEV

40.1 - 51.9 (CMAD-115) (CMAD-152)

47.0 4.1

40.1 - 51.9 (CMAD-115) (CMAD-152)

47.3 4.3

40.1 - 51.9 (CMAD-115) (CMAD-152)

47.3 4.3

UHV (Kcal/kg) Mean STD.DEV

2320 - 6159 (CMAD-20) (CMAD-66)

4865 1250

2320 - 6159 (CMAD-20) (CMAD-66)

4865 1250

2320 - 6159 (CMAD-20) (CMAD-66)

4865 1250

Grade Avg. Grade

G-B D

G-B D

G-B D

K. GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam L3T, Amadand OC Block.

Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

17 0.35-1.20 3829 - 6293 (CMaD-20) (CMAD-66)

3829 - 6293 (CMaD-20) (CMAD-66)

3829 - 6293 (CMaD-20) (CMAD-66)

L. RANGE OF ULTIMATE ANALYSIS

Data not available.

M. ASH FUSION TEMPERATURE RANGE

Data not available.

N. HARDGROVE GRANDABILITY INDEX (HGI)

Data not available .

O. ASH ANALYSIS

Data not available.

4.4.8 SEAM-L3 BOTTOM (L3B)

A. STATUS OF MINING

The seam is devoid of mining activity in the block.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 26 of 81

B. DETAILS OF BOREHOLES INTERSECTION

A. Intersections Nos.

i) No. of full seam intersections in boreholes 53

ii) No. of outcrop proving boreholes with part thickness Nil

iii) No. of boreholes with part thickness due to faulting Nil

iv) No. of boreholes where seam is totally omitted due to fault Nil

v) No. of boreholes where seam is merged with lower seam Nil

vi) No. of boreholes where seam is not encountered due to non-development of seam and presence of dyke

18

vii) No. of boreholes not deepened to encounter the seam Nil

viii) No. of boreholes beyond incrop NIL TOTAL 71

a. Depth of intersection (Roof)

i) Shallowest : 23.25m (CMAD-157)

ii) Deepest : 81.91m (CMAD-68)

b. Minimum & Maximum FRLs

i) Minimum : 460.29m (AMD-9)

ii) Maximum : 502.61m (CMAD-91)

C. STRATIGRAPHIC POSITION

This is the sixth workable seam and eighth from the surface within the Barakar

Formation in the block.

D. SPLITTING The seam is the split of L3 seam. The splitting is observed in the eastern,

northern and western parts of the block. The seam itself does not further split in

the block

E. PARTING

The seam occurs at a minimum depth of 23.25m (CMAD-157) from the surface

in the north eastern part and at a maximum depth of 81.31m (CMAD-68) from

the surface in the northern part of the block.

The parting between L3B and MKT & MKC predominantly consists of

arenaceous facies mainly. The parting between aforesaid seams ranges

between 1.46m (CMAD-36) and 11.91m (CMAD-94).

F. THICKNESS

It is observed that minimum thickness of 0.06m is found in borehole No.CMAD-

101 and maximum thickness of 0.80m in borehole No.CMAD-245. The average

thickness is 0.42m.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 27 of 81

The seam is described in detail and also considered for assessment of

availability of coal reserves.

G. OUTCROP/INCROP

The seam incrops along the southern and north eastern parts of the block area.

The position of incrop is below the weathered mantle.

H. ROOF & FLOOR

The immediate roof and floor of the seam consists mainly medium to coarse

grained sandstone.

I. DIRT BANDS

This seam barring a few boreholes is devoid of dirt bands.

Dirt bands in Seam L3B (on I10 basis)

Thickness range of seam

(m)

Effective thickness range (m)

Carbonaceous shale bands

Non-Combustible bands Total bands

No.of bands/ No.

of BHs

Thick. range (m)

No.of bands/ No. of BHs

Thickness range (m)

No.of bands/ No.

of BHs

Thick. range (m)

0.06 - 0.80 0.06 - 0.80 1/2 0.06-0.07 1/3 0.02-0.04 1/5 0.02-0.07

J. PROXIMATE ANALYSIS

Grades on I10 samples show the grade variation between E to B. The general

grade is c.

Range of proximate analysis & grade of Seam L3B, Amadand OC Block Parameters Range

Bcs Sample I10 Sample I100 Sample

Full Seam

Boreholes considered :

11 11 11

Thickness (m)/Range (m) Mean STD.DEV

0.06 - 0.75 (CMAD-101)(CMAD-85)

0.48 0.20

0.06 - 0.75 (CMAD-101)(CMAD-85)

0.48 0.20

0.06 - 0.75 (CMAD-101)(CMAD-85)

0.48 0.20

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.06 - 0.75 (CMAD-101)(CMAD-85)

0.48 0.20

0.06 - 0.75 (CMAD-101)(CMAD-85)

0.48 0.20

0.06 - 0.75 (CMAD-101)(CMAD-85)

0.48 0.20

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

6.5 – 8.7 (CMAD-6) (CMAD-190)

7.7 0.79

6.5 – 8.7 (CMAD-6) (CMAD-190)

7.7 0.79

6.5 – 8.7 (CMAD-6) (CMAD-190)

7.7 0.79

Ash% Mean STD.DEV

12.2 - 32.2 (CMAD-190) (CMAD-6)

20.1 7.2

12.2 - 32.2 (CMAD-190) (CMAD-6)

20.1 7.2

12.2 - 32.2 (CMAD-190) (CMAD-6)

20.1 7.2

VM% Mean STD.DEV

24.6 – 32.3 (CMAD-85) (CMAD-98)

28.8 2.8

24.6 – 32.3 (CMAD-85) (CMAD-98)

28.8 2.8

24.6 – 32.3 (CMAD-85) (CMAD-98)

28.8 2.8

FC% Mean STD.DEV

40.7 - 51.5 (CMAD-115) (CMAD-188)

46.4 4.1

40.7 - 51.5 (CMAD-115) (CMAD-188)

46.4 4.1

40.7 - 51.5 (CMAD-115) (CMAD-188)

46.4 4.1

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 28 of 81

Parameters Range

Bcs Sample I10 Sample I100 Sample

UHV (Kcal/kg) Mean STD.DEV

3562 - 6015 (CMAD-6) (CMAD-190)

5025 906

3562 - 6015 (CMAD-6) (CMAD-190)

5025 906

3562 - 6015 (CMAD-6) (CMAD-190)

5025 906

Grade Avg. Grade

E-B C

E-B C

E-B C

K. GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam L3B, Amadand OC Block, Sohagpur Coalfield

Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

11 0.06-080 4581- 6141 (CMaD-6) (CMAD-190)

4581- 6141 (CMaD-6) (CMAD-190)

4581- 6141 (CMaD-6) (CMAD-190)

L. RANGE OF ULTIMATE ANALYSIS

Data not available. M. ASH FUSION TEMPERATURE RANGE

Data not available.

N. HARDGROVE GRANDABILITY INDEX (HGI)

Data not available.

O. ASH ANALYSIS Data not available.

4.4.9 SEAM-L3 (L3)

A. STATUS OF MINING

The seam is devoid of mining activity in the block.

B. DETAILS OF BOREHOLES INTERSECTION

DETAILS OF BOREHOLES INTERSECTION

A. Intersections Nos.

i) No. of full seam intersections in boreholes 72

ii) No. of outcrop proving boreholes with part thickness Nil

iii) No. of boreholes with part thickness due to faulting Nil

iv) No. of boreholes where seam is totally omitted due to fault

Nil

v) No. of boreholes where seam is merged with lower seam

Nil

vi) No. of boreholes where seam is not encountered due to non-development of seam and presence of dyke

1

vii) No. of boreholes not deepened to encounter the seam 26

viii) No. of boreholes beyond incrop 2

TOTAL 101

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 29 of 81

a. Depth of intersection (Roof)

i) Shallowest : 39.05m (CMAD-60)

ii) Deepest : 77.15m (CMAD-45)

b. Minimum & Maximum FRLs

i) Minimum : 468.55m (AMD-6)

ii) Maximum : 502.56m (AMD-16)

C. STRATIGRAPHIC POSITION

This is the seventh workable seam and ninth from the surface within the Barakar

Formation in the block.

D. SPLITTING

The composite L3 seam having two splits L3T & L3B is mainly developed in the

central part and in patches in north western part of the block.

E. PARTING

The seam occurs at a minimum depth of 39.05m (CMAD-60) from the surface in

the northern part and at a maximum depth of 77.15m (CMAD-45) from the

surface also in the northern part of the block.

The parting between L3 and MKT, MKC predominantly consists of arenaceous

facies mainly. The parting between aforesaid seams ranges between 1.25m

(CMAD-60) and 6.08m (AMD-6).

F. THICKNESS

It is observed that minimum thickness of 0.25m is found in borehole No.CMAD-

34 and maximum thickness of 3.80m in borehole No.CMAD-168. The average

thickness is 1.23m.

The seam is described in detail and also considered for assessment of

availability of coal reserves.

G. OUTCROP/INCROP

The seam incrops along the southern and northeastern parts of the block area.

The position of incrop is below the weathered mantle.

H. ROOF & FLOOR

The immediate roof and floor of the seam consists mainly medium to coarse

grained sandstone.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 30 of 81

I. DIRT BANDS

The seam is having 1 to 3 dirt bands of both combustible and non-combustible

nature in seam in a few boreholes. However, in maximum boreholes seam is

devoid of dirt bands.

Dirt bands in Seam L3 (on I10 basis) Thickness

range of seam (m)

Effective thickness range (m)

Carbonaceous shale bands

Non-Combustible bands Total bands

No.of bands/ No.

of BHs

Thick. range (m)

No.of bands/ No. of BHs

Thickness range (m)

No.of bands/ No.

of BHs

Thick. range (m)

0.44 - 2.51 0.44 - 2.47 1/4 0.04-0.10 1-2/5 0.06-0.10 1-2/9 0.04-0.10

J. PROXIMATE ANALYSIS

Grades on I10 samples show the grade variation between G to B. The general

grade is E.

Range of proximate analysis & grade of Seam L3, Amadand OC Block

Parameters Range

Bcs Sample I10 Sample I100 Sample Full Seam

Boreholes considered :

54 54 54

Thickness (m)/Range (m) Mean STD.DEV

0.44 - 2.51 (CMAD-111)(CMAD-163)

1.27 0.50

0.44 - 2.51 (CMAD-111)(CMAD-163)

1.27 0.50

0.44 - 2.51 (CMAD-111)(CMAD-163)

1.27 0.50

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.44 - 2.47 (CMAD-111)(CMAD-51)

1.12 0.42

0.44 - 2.47 (CMAD-111)(CMAD-51)

1.13 0.43

0.44 - 2.51 (CMAD-111)(CMAD-163)

1.27 0.50

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

5.0 – 8.7 (CMAD-16) (CMAD-148)

7.0 0.90

5.0 – 8.7 (CMAD-16) (CMAD-148)

7.0 0.90

5.0 – 8.7 (CMAD-16) (CMAD-148)

6.6 0.90

Ash% Mean STD.DEV

12.3 - 44.7 (CMAD-162) (CMAD-520)

25.4 8.2

12.3 - 44.7 (CMAD-162) (CMAD-520)

25.6 8.1

12.3 - 44.7 (CMAD-162) (CMAD-520)

29.4 8.5

VM% Mean STD.DEV

19.7 – 30.3 (CMAD-245) (CMAD-7)

25.3 2.5

22.0 – 30.3 (CMAD-52) (CMAD-7)

25.6 2.3

21.7 – 30.3 (CMAD-135) (CMAD-7)

25.4 2.4

FC% Mean STD.DEV

31.5 - 48.2 (CMAD-52) (CMAD-60)

41.4 4.3

31.5 - 48.2 (CMAD-52) (CMAD-60)

41.1 4.6

31.5 - 48.2 (CMAD-52) (CMAD-60)

40.2 5.1

UHV (Kcal/kg) Mean STD.DEV

2045 - 6041 (CMAD-520) (CMAD-162)

4426 1016

2045 - 6041 (CMAD-520) (CMAD-162)

4393 1001

2045 - 6041 (CMAD-520) (CMAD-162)

3924 1051

Grade Avg. Grade

G-B D

G-B D

G-B E

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 31 of 81

K. GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam L3, Amadand OC Block.

Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

54 0.44-2.47 3626 - 6172

(CMAD-520) (CMAD-162) 3626 - 6172

(CMAD-520) (CMAD-162) 3626 - 6172

(CMAD-520) (CMAD-162)

L. RANGE OF ULTIMATE ANALYSIS

Range of Ultimate Analysis for Seam L3, Amadand OC Block

Parameters Range of content %

Ultimate Analysis on Bcs/Ex-band sample (dmmf basis)(No. of samples 2)

C% 78.97 - 79.03 (CMAD-51) (CMAD-52)

H% 4.75 - 4.61 (CMAD-51) (CMAD-52)

N% 1.58 - 1.62 (CMAD-51) (CMAD-52)

S% 0.61 - 0.95 (CMAD52) (CMAD-51)

M. ASH FUSION TEMPERATURE RANGE

Ash Fusion Temperature Range for Seam L3(including bands), Amadand OC

Block, Sohagpur Coalfield.

Borehole considered

Thickness range (m)

Ash fusion range oC(under mildly reducing atmosphere)

IDT HT FT

4 1.11-2.47 1130-1220 >1400->1400 >1400->1400

N. HARDGROVE GRANDABILITY INDEX (HGI)

HGI of 3 boreholes of Seam L3 of Amadand OC Block sample is given as under:

H.G.I. for Seam L3, Amadand OC Block, Sohagpur Coalfield.

No. of boreholes Nature of Sample Range Minimum Maximum

3 Bcs/I10/I100 54 65

O. ASH ANALYSIS ASH ANALYSIS (on In band basis)

Borehole No.

Constituents %

SiO2 Al2O3 Fe2O3 TiO2 P2O5 SO3 MnO CaO MgO Alkalies by diff.

CMAD-135 58.80 33.14 2.39 1.40 0.07 0.10 0.15 1.40 1.00 1.55

4.4.10 SEAM- MIDDLE KOTMA TOP (MKT)

A. STATUS OF MINING

The mining developmental activity is in progress in Bartarai block.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 32 of 81

B. DETAILS OF BOREHOLES INTERSECTION

A. Intersections Nos.

i) No. of full seam intersections in boreholes 96

ii) No. of outcrop proving boreholes with part thickness Nil

iii) No. of boreholes with part thickness due to faulting Nil

iv) No. of boreholes where seam is totally omitted due to fault

Nil

v) No. of boreholes where seam is merged with lower seam

Nil

vi) No. of boreholes where seam is not encountered due to non-development of seam and presence of dyke

Nil

vii) No. of boreholes not deepened to encounter the seam Nil

viii) No. of boreholes beyond incrop TOTAL 96

a. Depth of intersection (Roof)

i) Shallowest : 17.98m (CMAD-88)

ii) Deepest : 87.15m (CMAD-39)

b. Minimum & Maximum FRLs

i) Minimum : 454.42m (CMAD-39)

ii) Maximum : 509.58m (CMAD-88)

C. STRATIGRAPHIC POSITION

This is the eighth workable seam and tenth from the surface within the Barakar

Formation in the block.

D. SPLITTING This seam is the split of MKC seam. The splitting is observed in southern,

eastern and north western parts of the block. In addition splitting is also

observed in patches. The seam itself does not further split in the block

E. PARTING

The seam occurs at a minimum depth of 17.98m (CMAD-88) from the surface in

the south eastern part and at a maximum depth of 87.15m (CMAD-39) from the

surface also in the north eastern part of the block.

The parting between MKT and MKB predominantly consists of arenaceous

facies. It is also carbonaceous shale, sandy shale occasionally. The parting

between aforesaid seams ranges between 0.94m (CMAD-91) and 16.23m

(AMD-2). It is generally observed that the parting between MKT & MKB seams

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 33 of 81

increases from west to east in the northern part. In borehole no CMAD-91,

parting between MKT & MKB is 0.94m and the seam is taken as split because

MKT is carbonaceous shale and its merger with seam MKB will deteriorate the

quality of the seam MKC.

F. THICKNESS

It is observed that minimum thickness of 0.04m is found in borehole No.AMD-15

and maximum thickness of 3.44m in borehole No.CMAD-273. The seam is

deteriorated into carbonaceous shale in 21 boreholes.

The seam is described in detail and also considered for assessment of

availability of coal reserves.

G. OUTCROP/INCROP

The seam incrops along the southern part of the block area. The position of

incrop is below the weathered mantle.

H. ROOF & FLOOR

The immediate roof and floor are predominantly coarse to medium grained

sandstone. At place carbonaceous shale is also at roof and floor. I. DIRT BANDS

The seam is having 1 to 3 dirt bands of both combustible and non-combustible

nature in seam in a few boreholes. However, in maximum boreholes seam is

devoid of dirt band.

Dirt bands in Seam MKT (on I10 basis) Thickness

range of seam (m)

Effective thickness range (m)

Carbonaceous shale bands

Non-Combustible bands Total bands

No.of bands/ No.

of BHs

Thick. range (m)

No.of bands/ No. of BHs

Thickness range (m)

No.of bands/ No.

of BHs

Thick. range (m)

0.47 - 3.46 0.13 - 3.20 2/1 0.07 1/4 0.04-0.09 1-2/4 0.04-0.09

J. PROXIMATE ANALYSIS

Grades on I10 samples show the grade variation between G to B. The general

grade is G.

Range of proximate analysis & grade of Seam MKT, Amadand OC Block,

Sohagpur Coalfield.

Parameters Range

Bcs Sample I10 Sample I100 Sample Full Seam

Boreholes considered :

74 74 74

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 34 of 81

Parameters Range

Bcs Sample I10 Sample I100 Sample Thickness (m)/Range (m) Mean STD.DEV

0.47 - 3.44 (CMAD-60)(CMAD-273)

1.83 0.68

0.47 - 3.44 (CMAD-60)(CMAD-273)

1.83 0.68

0.47 - 3.44 (CMAD-60)(CMAD-273)

1.83 0.68

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.0 - 3.20 (AMD-2)(CMAD-198)

1.71 0.61

0.0 - 3.20 (AMD-2)(CMAD-198)

1.71 0.61

0.0 - 3.20 (AMD-2)(CMAD-198)

1.71 0.61

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

4.2 – 7.4 (CMAD-85) (CMAD-103)

5.0 0.77

4.2 – 7.4 (CMAD-85) (CMAD-103)

5.0 0.77

4.2 – 7.4 (CMAD-85) (CMAD-103)

5.0 0.77

Ash% Mean STD.DEV

14.1 - 50.2 (CMAD-103) (CMAD-521)

43.5 6.4

14.1 - 50.2 (CMAD-103) (CMAD-521)

43.6 6.4

14.1 - 50.2 (CMAD-103) (CMAD-521)

43.7 6.4

VM% Mean STD.DEV

16.5 – 30.7 (CMAD-85) (CMAD-103)

20.2 2.9

16.5 – 30.7 (CMAD-85) (CMAD-103)

20.2 3.0

16.5 – 30.7 (CMAD-85) (CMAD-103)

20.2 3.0

FC% Mean STD.DEV

25.7 - 72.2 (CMAD-163) (AMD-27)

32.2 7.4

25.7 - 72.2 (CMAD-163) (AMD-27)

32.1 7.5

25.7 - 72.2 (CMAD-163) (AMD-27)

32.1 7.5

UHV (Kcal/kg) Mean STD.DEV

1332 - 5933 (CMAD-521) (CMAD-103)

2134 797

1332 - 5933 (CMAD-521) (CMAD-103)

2121 800

1332 - 5933 (CMAD-521) (CMAD-103)

2109 801

Grade Avg. Grade

G-B G

G-B G

G-B G

K. GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam MKT, Amadand OC Block, Sohagpur Coalfield.

Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

74 0.13-3.20 2655 - 6120

(CMAD-6) (CMAD-103) 2655 - 6120

(CMAD-6) (CMAD-103) 2655 - 6120

(CMAD-6) (CMAD-103)

L. RANGE OF ULTIMATE ANALYSIS

Range of Ultimate Analysis for Seam MKT, Amadand OC Block

Parameters Range of content %

Ultimate Analysis on Bcs/Ex-band sample (dmmf basis)(No. of samples 6)

C% 78.81 - 83.35 (CMAD-55) (CMAD-135)

H% 4.52 - 4.89 (CMAD-135) (CMAD-52)

N% 1.53 - 2.00 (CMAD-165) (CMAD-137)

S% 0.48 - 1.56 (CMAD-135) (CMAD-137)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 35 of 81

M. ASH FUSION TEMPERATURE RANGE Ash Fusion Temperature Range for Seam MKT(including bands), Amadand OC

Borehole considered

Thickness range (m)

Ash fusion range oC(under mildly reducing atmosphere)

IDT HT FT

7 1.05-2.70 1240-1320 >1400->1400 >1400->1400

N. HARDGROVE GRANDABILITY INDEX (HGI)

HGI of 4 boreholes of Seam MKT of Amadand OC Block sample is given as

under:

H.G.I. for Seam MKT, Amadand OC Block, Sohagpur Coalfield.

No. of boreholes Nature of Sample Range Minimum Maximum

4 Bcs/I10/I100 52 59

O. ASH ANALYSIS

ASH ANALYSIS (on In band basis)

Borehole No.

Constituents %

SiO2 Al2O3 Fe2O3 TiO2 P2O5 SO3 MnO CaO MgO Alkalis by diff.

CMAD-52 59.40 30.90 5.00 1.30 0.03 0.40 0.12 0.98 0.97 0.90

CMAD-55 60.20 30.80 4.40 1.25 0.03 0.42 0.10 0.99 0.97 0.84

CMAD-163 60.34 29.00 4.96 1.60 0.10 0.20 0.10 1.54 1.46 0.70

4.4.11 SEAM- MIDDLE KOTMA BOTTOM (MKB)

A. STATUS OF MINING

The mining activity is in progress in Bartarai block.

B. DETAILS OF BOREHOLES INTERSECTION

A. Intersections Nos.

i) No. of full seam intersections in boreholes 94

ii) No. of outcrop proving boreholes with part thickness Nil

iii) No. of boreholes with part thickness due to faulting Nil

iv) No. of boreholes where seam is totally omitted due to fault Nil

v) No. of boreholes where seam is merged with lower seam Nil

vi) No. of boreholes where seam is not encountered due to non-development of seam and presence of dyke

1

vii) No. of boreholes not deepened to encounter the seam 1

viii) No. of boreholes beyond incrop Nil TOTAL 96

a. Depth of intersection (Roof)

i) Shallowest : 23.68m (CMAD-88)

ii) Deepest : 90.06m (CMAD-39)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 36 of 81

b. Minimum & Maximum FRLs

i) Minimum : 450.77m (CMAD-39)

ii) Maximum : 503.74m (CMAD-88)

C. STRATIGRAPHIC POSITION

This is the ninth workable seam and eleventh from the surface within the Barakar

Formation in the block.

D. SPLITTING This seam is the split of MKC seam. The splitting is observed in southern,

eastern and north western parts of the block. In addition splitting is also

observed in patches. The seam itself does not further split in the block

E. PARTING

The seam occurs at a minimum depth of 23.68m (CMAD-88) from the surface in

the south eastern part and at a maximum depth of 90.06m (CMAD-39) from the

surface also in the western part of the block.

The parting between MKB and LKI predominantly consists of arenaceous facies.

The parting between aforesaid seams ranges between 2.85m (AMD-9) and

27.55m (CMAD-21).

F. THICKNESS

It is observed that minimum thickness of 0.21m is found in borehole No.CMAD-

86 and maximum thickness of 2.74m in borehole No.CMAD-69. The seam is

deteriorated into carbonaceous shale and clay in 1 and 2 boreholes respectively.

The seam is described in detail and also considered for assessment of

availability of coal reserves.

G. OUTCROP/INCROP

The seam incrops along the southern part of the block area. The position of

incrop is below the weathered mantle.

H. ROOF & FLOOR

The immediate roof and floor are predominantly coarse to medium grained

sandstone. At places carbonaceous shale is also at roof and floor.

I. DIRT BANDS

The seam is having 1 to 3 dirt bands of both combustible and non-combustible

nature in seam in a few boreholes. However, in maximum boreholes seam is

devoid of dirt bands.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 37 of 81

Dirt bands in Seam MKB (on I10 basis) Thickness

range of seam (m)

Effective thickness range (m)

Carbonaceous shale bands

Non-Combustible bands Total bands

No.of bands/ No.

of BHs

Thick. range (m)

No.of bands/ No. of BHs

Thickness range (m)

No.of bands/ No.

of BHs

Thick. range (m)

0.36 - 2.74 0.00 - 2.51 1/3 0.01-0.09 1/3 0.01-0.09

J. PROXIMATE ANALYSIS

Grades on I10 samples show the grade variation between G to A. The general

grade is C.

Range of proximate analysis & grade of Seam MKB, Amadand OC Block, Sohagpur Coalfield.

Parameters Range

Bcs Sample I10 Sample I100 Sample

Full Seam

Boreholes considered :

80 80 80

Thickness (m)/Range (m) Mean STD.DEV

0.36 - 2.74 (CMAD-102)(CMAD-69)

1.35 0.48

0.36 - 2.74 (CMAD-102)(CMAD-69)

1.35 0.48

0.36 - 2.74 (CMAD-102)(CMAD-69)

1.35 0.48

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.00 - 2.51 (CMAD-147)

1.33 0.47

0.00 - 2.51 (CMAD-147)

1.33 0.47

0.00 - 2.74 (CMAD-69)

1.36 0.51

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

4.1 – 9.1 (CMAD-153) (CMAD-33)

7.3 0.89

4.1 – 9.1 (CMAD-153) (CMAD-33)

7.3 0.89

4.1 – 9.1 (CMAD-153) (CMAD-33)

7.3 0.89

Ash% Mean STD.DEV

9.1 - 70.6 (CMAD-52) (CMAD-165)

20.1 7.8

9.1 - 70.6 (CMAD-52) (CMAD-165)

20.1 7.8

9.1 - 70.6 (CMAD-52) (CMAD-165)

20.6 8.3

VM% Mean STD.DEV

13.7 – 38.1 (CMAD-165) (CMAD-135)

27.5 3.1

13.7 – 38.1 (CMAD-165) (CMAD-135)

27.5 3.1

13.7 – 38.1 (CMAD-165) (CMAD-135)

27.5 3.3

FC% Mean STD.DEV

11.6 - 59.1 (CMAD-165) (CMAD-87)

44.9 5.8

11.6 - 59.1 (CMAD-165) (CMAD-87)

44.9 5.8

11.6 - 59.1 (CMAD-165) (CMAD-87)

44.7 6.0

UHV (Kcal/kg) Mean STD.DEV

1917 - 6448 (CMAD-20) (CMAD-52)

5145 755

1917 - 6448 (CMAD-20) (CMAD-52)

5145 755

1127 - 6448 (CMAD-153) (CMAD-52)

5083 844

Grade Avg. Grade

G-A C

G-A C

UG-A C

K. GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam MKB, Amadand OC Block, Sohagpur Coalfield.

Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

80 0.00-2.51 1314 - 7655

(CMAD-165) (CMAD-163) 1314 - 7655

(CMAD-165) (CMAD-163) 1314 - 7655

(CMAD-165) (CMAD-163)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 38 of 81

L. RANGE OF ULTIMATE ANALYSIS

Range of Ultimate Analysis for Seam MKB, Amadand OC Block

Parameters Range of content %

Ultimate Analysis on Bcs/Ex-band sample (dmmf basis)(No. of samples 2)

C% 79.75 - 80.16 (CMAD-139) (CMAD-163)

H% 4.80 - 5.15 (CMAD-163) (CMAD-135)

N% 1.60 - 1.86 (CMAD-163) (CMAD-135)

S% 0.57 - 0.73 (CMAD-135) (CMAD-163)

M. ASH FUSION TEMPERATURE RANGE

Ash Fusion Temperature Range for Seam MKB(including bands), Amadand OC

Borehole considered

Thickness range (m)

Ash fusion range oC(under mildly reducing atmosphere)

IDT HT FT

4 1.00-1.79 1180->1400 >1400->1400 >1400->1400

N. HARDGROVE GRANDABILITY INDEX (HGI)

HGI of 4 boreholes of Seam MKB of Amadand OC Block sample is given as

under:

H.G.I. for Seam MKB, Amadand OC Block, Sohagpur Coalfield.

No. of boreholes Nature of Sample Range

Minimum Maximum

4 Bcs/I10/I100 46 52

O. ASH ANALYSIS ASH ANALYSIS (on In band basis)

Borehole No.

Constituents %

SiO2 Al2O3 Fe2O3 TiO2 P2O5 SO3 MnO CaO MgO Alkalies by diff.

AMD-15 58.62 27.83 3.94 2.14 0.01 0.88 - 2.65 2.57 1.30

CMAD-135 51.40 37.84 4.58 1.50 0.08 0.20 0.15 1.68 1.20 1.37

CMAD-163 58.24 30.60 4.62 1.50 0.08 0.10 0.10 1.65 1.57 1.54

4.4.12 SEAM- MIDDLE KOTMA COMBINED (MKC)

A. STATUS OF MINING

The mining activity is in progress in Bartarai block.

B. DETAILS OF BOREHOLES INTERSECTION

A. Intersections Nos.

i) No. of full seam intersections in boreholes 66

ii) No. of outcrop proving boreholes with part thickness Nil

iii) No. of boreholes with part thickness due to faulting Nil

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 39 of 81

iv) No. of boreholes where seam is totally omitted due to fault Nil

v) No. of boreholes where seam is merged with lower seam Nil

vi) No. of boreholes where seam is not encountered due to non-development of seam and presence of dyke

Nil

vii) No. of boreholes not deepened to encounter the seam 24

viii) No. of boreholes beyond incrop Nil TOTAL 90

a. Depth of intersection (Roof)

i) Shallowest : 49.15m (CMAD-192)

ii) Deepest : 89.87m (CMAD-35)

b. Minimum & Maximum FRLs

i) Minimum : 446.45m (CMAD-340)

ii) Maximum : 482.15m (CMAD-198)

C. STRATIGRAPHIC POSITION

This is the tenth workable seam and twelfth from the surface within the Barakar

Formation in the block.

D. SPLITTING

The composite MKC seam having two splits MKT & MKB is mainly in central and

western parts of the block.

E. PARTING

The seam occurs at a minimum depth of 49.15m (CMAD-192) from the surface

in the south eastern part and at a maximum depth of 89.87m (CMAD-35) from

the surface in the north western part of the block.

The parting between MKC and LKI seams predominantly consists of arenaceous

facies. The parting between aforesaid seams ranges between 12.00m (CMAD-

340) and 29.45m (CMAD-47).

F. THICKNESS

It is observed that minimum thickness of 0.53m is found in borehole No.CMAD-

50 and maximum thickness of 6.18m in borehole No.CMAD-54. The average

thickness is 3.74m. The seam is deteriorated into carbonaceous shale and clay

in one borehole each.

The seam is described in detail and also considered for assessment of

availability of coal reserves.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 40 of 81

G. OUTCROP/INCROP

The seam incrops along the southern part of the block area. The position of

incrop is below the weathered mantle.

H. ROOF & FLOOR

The immediate roof and floor are predominantly coarse to medium grained

sandstone. At places, carbonaceous shale is also at roof and floor.

I. DIRT BANDS

The seam is having 1 to 3 dirt bands of both combustible and non-combustible

nature in seam in a few boreholes. However, in maximum boreholes seam is

devoid of dirt bands.

Dirt bands in Seam MKC (on I10 basis)

Thickness range of seam

(m)

Effective thickness range (m)

Carbonaceous shale bands

Non-Combustible bands Total bands

No.of bands/ No.

of BHs

Thick. range (m)

No.of bands/ No. of BHs

Thickness range (m)

No.of bands/ No.

of BHs

Thick. range (m)

1.50 - 6.18 0.19 - 5.29 1/6 0.07-0.08 1/4 0.04-0.08 1/10 0.04-0.08

J. PROXIMATE ANALYSIS

Grades on I10 samples show the grade variation between G to C. The general

grade is F.

Range of proximate analysis & grade of Seam MKC, Amadand OC Block

Parameters Range

Bcs Sample I10 Sample I100 Sample Full Seam

Boreholes considered :

61 61 61

Thickness (m)/Range (m) Mean STD.DEV

1.50 - 6.18 (AMD-6)(CMAD-54)

3.85 1.22

1.50 - 6.18 (AMD-6)(CMAD-54)

3.85 1.22

1.50 - 6.18 (AMD-6)(CMAD-54)

3.85 1.22

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.19 - 5.29 (CMAD-29)(CMAD-512)

3.47 1.64

0.19 - 5.29 (CMAD-29)(CMAD-512)

3.47 1.64

0.19 - 6.18 (CMAD-29)(CMAD-54)

3.80 1.30

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

4.5 – 9.1 (CMAD-68) (CMAD-33)

6.2 1.00

4.5 – 9.1 (CMAD-68) (CMAD-33)

6.2 1.00

4.5 – 9.1 (CMAD-68) (CMAD-33)

5.9 1.00

Ash% Mean STD.DEV

15.5 - 48.7 (CMAD-33) (CMAD-276)

34.9 8.7

15.5 - 48.7 (CMAD-33) (CMAD-276)

35.0 8.7

15.5 - 49.8 (CMAD-33) (CMAD-53)

37.5 8.6

VM% Mean STD.DEV

17.7 – 28.3 (CMAD-68) (CMAD-267)

23.4 3.4

17.7 – 28.3 (CMAD-68) (CMAD-267)

23.5 3.7

17.7 – 26.6 (CMAD-68) (CMAD-33)

22.9 3.8

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 41 of 81

Parameters Range

Bcs Sample I10 Sample I100 Sample FC% Mean STD.DEV

27.5 - 49.9 (CMAD-13) (CMAD-45)

38.3 7.2

27.5 - 49.9 (CMAD-13) (CMAD-45)

38.7 7.5

27.5 - 70.3 (CMAD-13) (CMAD-267)

40.7 11.5

UHV (Kcal/kg) Mean STD.DEV

1516 - 5546 (CMAD-276) (CMAD-45)

3234 1082

1516 - 5546 (CMAD-276) (CMAD-45)

3216 1078

1089 - 5546 (CMAD-53) (CMAD-45)

2902 1080

Grade Avg. Grade

G-C F

G-C F

UG-C F

K. GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam MKC, Amadand OC Block, Sohagpur Coalfield.

Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

61 0.19-5.29 3255 - 5903 (CMAD-13) (CMAD-45)

3255 - 5903 (CMAD-13) (CMAD-45)

2881 - 5903 (CMAD-53) (CMAD-45)

L. RANGE OF ULTIMATE ANALYSIS

Data not available. M. ASH FUSION TEMPERATURE RANGE

Ash Fusion Temperature Range for Seam MKC(including bands), Amadand OC Block, Sohagpur Coalfield.

Borehole considered

Thickness range (m)

Ash fusion range oC(under mildly reducing atmosphere)

IDT HT FT

1 4.90 1210 >1400 >1400

N. HARDGROVE GRANDABILITY INDEX (HGI)

Data not available.

O. ASH ANALYSIS

Data not available.

4.4.13 SEAM-L2

Seam L2 is the 13th seam from the surface within the Barakar Formation. This

seam is intersected in 72 boreholes. The minimum thickness of 0.02m observed

in borehole CMAD-45 and maximum thickness is observed in 0.71m in

boreholes CMAD-51 & 111. The average thickness is 0.27m. The seam

thickness above 0.50m is found in 17 boreholes in the block.

Since sufficient analytical data are not available, the seam L2 is not considered

for reserve estimation.

4.4.14 SEAM- LOWER KOTMA I (LKI)

A. STATUS OF MINING

The mining activity is in progress in Bartarai block.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 42 of 81

B. DETAILS OF BOREHOLES INTERSECTION

A. Intersections Nos.

i) No. of full seam intersections in boreholes 143

ii) No. of outcrop proving boreholes with part thickness Nil

iii) No. of boreholes with part thickness due to faulting Nil

iv) No. of boreholes where seam is totally omitted due to fault Nil

v) No. of boreholes where seam is merged with lower seam Nil

vi) No. of boreholes where seam is not encountered due to non-development of seam and presence of dyke

12

vii) No. of boreholes not deepened to encounter the seam 31

viii) No. of boreholes beyond incrop Nil TOTAL 186

a. Depth of intersection (Roof)

i) Shallowest : 51.07m (CMAD-88)

ii) Deepest : 122.39m (CMAD-35)

b. Minimum & Maximum FRLs

i) Minimum : 418.57m (CMAD-340)

ii) Maximum : 477.57m (CMAD-88)

C. STRATIGRAPHIC POSITION

This is the eleventh workable seam and fourteenth from the surface within the

Barakar Formation in the block.

D. SPLITTING

The seam does not split in the block.

E. PARTING

The seam occurs at a minimum depth of 51.07m (CMAD-88) from the surface in

the southern part and at a maximum depth of 122.39m (CMAD-35) from the

surface also in the north western part of the block.

The parting between LKI and L1 seams predominantly consists of arenaceous

facies. The parting between aforesaid seams ranges between 10.40m (CMAD-

245) and 32.16m (CMAD-175).

F. THICKNESS

It is observed that minimum thickness of 0.05m is found in borehole Nos.CMAD-

62 & 175 and maximum thickness of 1.96m in borehole No.CMAD-340. The

average thickness is 0.60m.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 43 of 81

The seam is described in detail and also considered for assessment of availability

of coal reserves.

G. OUTCROP/INCROP

The seam does not incrop in the block.

H. ROOF & FLOOR

The immediate roof and floor consist of coarse to medium grained sandstone.

Sometimes carbonaceous shale is also observed as roof and floor.

I. DIRT BANDS

The seam is having dirt bands of both combustible and non-combustible nature in

seam in a few boreholes. However, in maximum boreholes seam is devoid of dirt

bands.

Dirt bands in Seam LKI (on I10 basis) Thickness

range of seam (m)

Effective thickness range (m)

Carbonaceous shale bands

Non-Combustible bands Total bands

No.of bands/ No.

of BHs

Thick. range (m)

No.of bands/ No. of BHs

Thickness range (m)

No.of bands/ No.

of BHs

Thick. range (m)

0.13 - 1.78 0.13 - 1.70 1/4 0.03-0.07 1/6 0.02-0.06 1/12 0.02-0.07

J. PROXIMATE ANALYSIS

Grades on I10 samples show the grade variation between F to A. The average

grade is D.

Range of proximate analysis & grade of Seam LKI, Amadand OC Block, Sohagpur Coalfield.

Parameters Range

Bcs Sample I10 Sample I100 Sample

Full Seam

Boreholes considered :

58 58 58

Thickness (m)/Range (m) Mean STD.DEV

0.13 - 1.78 (CMAD-512)(CMAD-269)

0.93 0.36

0.13 - 1.78 (CMAD-512)(CMAD-269)

0.93 0.36

0.13 - 1.78 (CMAD-512)(CMAD-269)

0.93 0.36

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.13 - 1.70 (CMAD-512)(CMAD-54)

0.91 0.34

0.13 - 1.70 (CMAD-512)(CMAD-54)

0.91 0.34

0.13 - 1.78 (CMAD-512)(CMAD-269)

0.93 0.36

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

4.9 – 9.7 (AMD-6) (CMAD-41)

7.6 0.89

4.9 – 9.7 (AMD-6) (CMAD-41)

7.6 0.89

4.8 – 9.7 (CMAD-30) (CMAD-41)

7.5 0.99

Ash% Mean STD.DEV

5.2 - 39.7 (CMAD-28) (CMAD-267)

21.3 6.4

5.2 - 39.7 (CMAD-28) (CMAD-267)

21.3 6.4

5.2 - 47.9 (CMAD-28) (CMAD-30)

22.2 7.6

VM% Mean STD.DEV

21.2 – 31.7 (CMAD-103) (CMAD-94)

26.5 2.2

21.2 – 31.7 (CMAD-103) (CMAD-94)

26.6 2.2

21.2 – 31.7 (CMAD-103) (CMAD-94)

26.6 2.2

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 44 of 81

Parameters Range

Bcs Sample I10 Sample I100 Sample

FC% Mean STD.DEV

34.7 - 55.0 (CMAD-103) (CMAD-312)

45.0 4.5

34.7 - 55.0 (CMAD-103) (CMAD-312)

44.9 4.5

34.7 - 55.0 (CMAD-103) (CMAD-312)

45.0 4.6

UHV (Kcal/kg) Mean STD.DEV

2640 - 6872 (CMAD-267) (CMAD-28)

4886 812

2640 - 6872 (CMAD-267) (CMAD-28)

4870 816

1630 - 6872 (CMAD-30) (CMAD-28)

4777 956

Grade Avg. Grade

F-A D

F-A D

F-A D

K. GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam LKI, Amadand OC Block.

Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

58 0.13-1.70 3995 - 6685

(CMAD-267) (CMAD-28) 3995 - 6685

(CMAD-267) (CMAD-28) 3553 - 6685

(CMAD-30) (CMAD-28)

L. RANGE OF ULTIMATE ANALYSIS

Data not available.

M. ASH FUSION TEMPERATURE RANGE

Ash Fusion Temperature Range for Seam LKI (including bands), Amadand OC

Borehole considered

Thickness range (m)

Ash fusion range oC(under mildly reducing atmosphere)

IDT HT FT

1 1.20 >1400 >1400 >1400

N. HARDGROVE GRANDABILITY INDEX (HGI)

HGI of 2 boreholes of Seam LKI of Amadand OC Block sample is given as

under:

H.G.I. for Seam LKI, Amadand OC Block, Sohagpur Coalfield.

No. of boreholes Nature of Sample Range

Minimum Maximum

1 Bcs/I10/I100 53 53

O. ASH ANALYSIS

Data not available.

4.4.15 SEAM- LOCAL-1(L1)

A. STATUS OF MINING

The mining activity is in progress in Bartarai block.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 45 of 81

B. DETAILS OF BOREHOLES INTERSECTION

A. Intersections Nos.

i) No. of full seam intersections in boreholes 81

ii) No. of outcrop proving boreholes with part thickness Nil

iii) No. of boreholes with part thickness due to faulting Nil

iv) No. of boreholes where seam is totally omitted due to fault

Nil

v) No. of boreholes where seam is merged with lower seam

Nil

vi) No. of boreholes where seam is not encountered due to non-development of seam and presence of dyke

73

vii) No. of boreholes not deepened to encounter the seam 32

viii) No. of boreholes beyond incrop NiL TOTAL 186

a. Depth of intersection (Roof)

i) Shallowest : 66.36m (CMAD-88)

ii) Deepest : 137.78m (CMAD-58)

b. Minimum & Maximum FRLs

i) Minimum : 403.92m (CMAD-41)

ii) Maximum : 462.09m (CMAD-88)

C. STRATIGRAPHIC POSITION

This is the twelfth workable seam and fifteenth from the surface within the

Barakar Formation in the block.

D. SPLITTING

The seam does not split in the block.

E. PARTING

The seam occurs at a minimum depth of 66.36m (CMAD-88) from the surface in

the north-eastern part and at a maximum depth of 137.78m (CMAD-58) from the

surface also in the north central part of the block.

The parting between L1 and LKIIT and LKII seams predominantly consists of

arenaceous facies. The parting between aforesaid seams ranges between

2.11m (CMAD-44) and 21.90m (CMAD-245).

F. THICKNESS

It is observed that minimum thickness of 0.10m is found in borehole No.CMAD-

128 and maximum thickness of 2.57m in borehole No.CMAD-41. The average

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 46 of 81

thickness is 0.51m. The thickness above 0.50m is found in 40 boreholes only

mainly restricted in north-eastern and south central parts of the block.

The seam is described in detail and also considered for assessment of availability

of coal reserves.

G. OUTCROP/INCROP

The seam does not incrop in the block.

H. ROOF & FLOOR

The immediate roof and floor consists of coarse to medium grained sandstone.

Sometimes carbonaceous shale is also observed as roof and floor.

I. DIRT BANDS

The seam is having 1 to 3 dirt bands of both combustible and non-combustible

nature in seam in a few boreholes. However, in maximum boreholes seam is

devoid of dirt bands.

Dirt bands in Seam L1 (on I10 basis)

Thickness range of seam

(m)

Effective thickness range (m)

Carbonaceous shale bands

Non-Combustible bands Total bands

No.of bands/ No.

of BHs

Thick. range (m)

No.of bands/ No. of BHs

Thickness range (m)

No.of bands/ No.

of BHs

Thick. range (m)

0.25 - 1.12 0.25 - 1.12 3/1 0.64- 1-2/3 0.03-0.13 1-2/4 0.03-0.13

J. PROXIMATE ANALYSIS

Grades on I10 samples show the grade variation between G to A. The average

grade is C.

Range of proximate analysis & grade of Seam L1, Amadand OC Block

Parameters Range

Bcs Sample I10 Sample I100 Sample Full Seam

Boreholes considered :

14 14 14

Thickness (m)/Range (m) Mean STD.DEV

0.25 - 1.12 (CMAD-7)(CMAD-20)

0.73 0.24

0.25 - 1.12 (CMAD-7)(CMAD-20)

0.73 0.24

0.25 - 1.12 (CMAD-7)(CMAD-20)

0.73 0.24

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.25 - 1.12 (CMAD-7)(CMAD-20)

0.73 0.24

0.25 - 1.12 (CMAD-7)(CMAD-20)

0.73 0.24

0.25 - 1.12 (CMAD-7)(CMAD-20)

0.73 0.24

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

4.5 – 8.7 (CMAD-512) (CMAD-42)

7.5 1.00

4.5 – 8.7 (CMAD-512) (CMAD-42)

7.5 1.00

4.5 – 8.7 (CMAD-512) (CMAD-42)

7.5 1.00

Ash% Mean STD.DEV

8.7 – 48.6 (CMAD-265) (CMAD-512)

19.3 10.00

8.7 – 48.6 (CMAD-265) (CMAD-512)

19.9 10.00

8.7 – 48.6 (CMAD-265) (CMAD-512)

19.9 10.00

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 47 of 81

Parameters Range

Bcs Sample I10 Sample I100 Sample VM% Mean STD.DEV

24.6 – 32.6 (CMAD-1) (CMAD-314)

27.6 2.8

24.6 – 32.6 (CMAD-1) (CMAD-314)

27.6 2.8

24.6 – 32.6 (CMAD-1) (CMAD-314)

27.6 2.8

FC% Mean STD.DEV

36.8 - 55.0 (CMAD-314) (CMAD-312)

45.0 5.8

36.8 - 55.0 (CMAD-314) (CMAD-312)

45.0 5.8

36.8 - 55.0 (CMAD-314) (CMAD-312)

45.0 5.8

UHV (Kcal/kg) Mean STD.DEV

1574 - 6504 (CMAD-512) (CMAD-265)

5195 1241

1574 - 6504 (CMAD-512) (CMAD-265)

5119 1240

1574 - 6504 (CMAD-512) (CMAD-265)

5119 1240

Grade Avg. Grade

G-A C

G-A C

G-A C

K. GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam L1, Amadand OC Block, Sohagpur Coalfield.

Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

14 0.25-1.12 3330 - 6475 (CMAD-512) (CMAD-265)

3330 - 6475 (CMAD-512) (CMAD-265)

3330 - 6475 (CMAD-512) (CMAD-265)

L. RANGE OF ULTIMATE ANALYSIS

Data not available.

M. ASH FUSION TEMPERATURE RANGE

Data not available. N. HARDGROVE GRANDABILITY INDEX (HGI)

Data not available.

O. ASH ANALYSIS

Data not available.

4.4.16 SEAM- LOWLER KOTMA II TOP (LKIIT)

A. STATUS OF MINING

The mining activity of this seam is in progress in Amadand U/G block.

B. DETAILS OF BOREHOLES INTERSECTION

A. Intersections Nos.

i) No. of full seam intersections in boreholes 31

ii) No. of outcrop proving boreholes with part thickness Nil

iii) No. of boreholes with part thickness due to faulting Nil

iv) No. of boreholes where seam is totally omitted due to fault

Nil

v) No. of boreholes where seam is merged with lower seam

Nil

vi) No. of boreholes where seam is not encountered due to non-development of seam and presence of dyke

Nil

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 48 of 81

vii) No. of boreholes not deepened to encounter the seam Nil

viii) No. of boreholes beyond incrop Nil TOTAL 31

a. Depth of intersection (Roof)

i) Shallowest : 108.96m (CMAD-112)

ii) Deepest : 147.07m (CMAD-340)

b. Minimum & Maximum FRLs

i) Minimum : 392.17m (CMAD-340)

ii) Maximum : 421.42m (CMAD-112)

C. STRATIGRAPHIC POSITION

This is the thirteenth workable seam and sixteenth from the surface within the

Barakar Formation in the block.

D. SPLITTING

The seam is the upper split of the Seam LKII in the western part of the block.

The seam itself does not further split in the block.

E. PARTING

The seam occurs at a minimum depth of 108.96m (CMAD-112) from the surface

in the southern part and at a maximum depth of 147.07m (CMAD-340) from the

surface also in the north western part of the block.

The parting between LKIIT and LKIIB seams predominantly consists of

arenaceous facies. The parting between aforesaid seams ranges between

1.05m (CMAD-270) and 4.21m (CMAD-54).

F. THICKNESS

It is observed that minimum thickness of 0.36m is found in borehole No.CMAD-

33 and maximum thickness of 2.76m is found in borehole No.CMAD-309. The

average thickness is 0.94m.

The seam is described in detail and also considered for assessment of

availability of coal reserves.

G. OUTCROP/INCROP

The seam does not incrop in the block.

H. ROOF & FLOOR

The immediate roof and floor consists of coarse to medium grained sandstone.

Sometimes carbonaceous shale is also observed as roof and floor.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 49 of 81

I. DIRT BANDS

The seam is having 1 to 3 dirt bands of both combustible and non-combustible

nature in seam in a few boreholes. However, in maximum boreholes seam is

devoid of dirt bands.

Dirt bands in Seam LKIIT (on I10 basis)

Thickness range of seam

(m)

Effective thickness range (m)

Carbonaceous shale bands

Non-Combustible bands Total bands

No.of bands/ No.

of BHs

Thick. range (m)

No.of bands/ No. of BHs

Thickness range (m)

No.of bands/ No.

of BHs

Thick. range (m)

0.60 - 2.76 0.60 - 2.76 1/1 0.10 1/1 0.09 1/2 0.09-0.10

J. PROXIMATE ANALYSIS

Grades on I10 samples show the grade variation between E to A. The average

grade is C.

Range of proximate analysis & grade of Seam LKIIT, Amadand OC Block.

Parameters Range

Bcs Sample I10 Sample I100 Sample Full Seam

Boreholes considered :

21 21 21

Thickness (m)/Range (m) Mean STD.DEV

0.60 - 2.76 (CMAD-638)(CMAD-309)

1.11 0.55

0.60 - 2.76 (CMAD-638)(CMAD-309)

1.11 0.55

0.60 - 2.76 (CMAD-638)(CMAD-309)

1.11 0.55

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.60 - 2.76 (CMAD-638)(CMAD-309)

1.11 0.55

0.60 - 2.76 (CMAD-638)(CMAD-309)

1.11 0.55

0.60 - 2.76 (CMAD-638)(CMAD-309)

1.11 0.55

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

5.6 – 9.4 (CMAD-315) (CMAD-21)

7.1 0.98

5.8 – 9.4 (AMD-23) (CMAD-21)

7.1 0.98

5.6 – 9.4 (AMD-23) (CMAD-21)

7.1 0.98

Ash% Mean STD.DEV

5.5 – 34.3 (CMAD-37) (AMD-23)

18.6 8.0

5.5 – 34.3 (CMAD-37) (AMD-23)

18.2 7.5

5.5 – 34.3 (CMAD-37) (AMD-23)

19.2 8.1

VM% Mean STD.DEV

17.0 – 28.8 (AMD-23 (CMAD-21)

25.2 3.8

17.0 – 28.8 (AMD-23 (CMAD-21)

25.2 3.8

17.0 – 28.8 (AMD-23 (CMAD-21)

25.9 3.4

FC% Mean STD.DEV

42.6 - 53.0 (CMAD-269) (AMD-07)

48.7 4.9

42.6 - 53.0 (CMAD-269) (AMD-07)

48.7 4.9

33.6 - 53.0 (CMAD-118) (AMD-07)

47.3 6.4

UHV (Kcal/kg) Mean STD.DEV

3373 - 6943 (AMD-23) (CMAD-37)

5285 1004

3373 - 6943 (AMD-23) (CMAD-37)

5335 945

3373 - 6943 (AMD-23) (CMAD-37)

5215 1024

Grade Avg. Grade

E-A C

E-A C

E-A C

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 50 of 81

K. GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam LKIIT, Amadand OC Block, Sohagpur Coalfield. Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

21 0.60-2.76 4489 - 6773 (AMD-23) (CMAD-37)

4489 - 6773 (AMD-23) (CMAD-37)

4435 - 6773 (AMD-23) (CMAD-37)

L. RANGE OF ULTIMATE ANALYSIS

Data not available

M. ASH FUSION TEMPERATURE RANGE

Data not available

N. HARDGROVE GRANDABILITY INDEX (HGI)

Data not available

O. ASH ANALYSIS

Data not available

4.4.17 SEAM- LOWLER KOTMA II BOTTOM (LKIIB)

A. STATUS OF MINING

The mining activity of this seam is in progress in Amadand U/G block.

B. DETAILS OF BOREHOLES INTERSECTION

A. Intersections Nos.

i) No. of full seam intersections in boreholes 31

ii) No. of outcrop proving boreholes with part thickness Nil

iii) No. of boreholes with part thickness due to faulting Nil

iv) No. of boreholes where seam is totally omitted due to fault Nil

v) No. of boreholes where seam is merged with lower seam Nil

vi) No. of boreholes where seam is not encountered due to non-development of seam and presence of dyke

Nil

vii) No. of boreholes not deepened to encounter the seam Nil

viii) No. of boreholes beyond incrop TOTAL 31

a. Depth of intersection (Roof)

i) Shallowest : 111.85m (CMAD-112)

ii) Deepest : 150.26m (CMAD-340)

b. Minimum & Maximum FRLs

i) Minimum : 388.51m (CMAD-340)

ii) Maximum : 418.04m (CMAD-112)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 51 of 81

C. STRATIGRAPHIC POSITION

This is the fourteenth workable seam and seventeenth from the surface within

the Barakar Formation in the block.

D. SPLITTING

The seam is the upper split of the Seam LKII in the western part of the block.

The seam itself does not further split in the block.

E. PARTING

The seam occurs at a minimum depth of 111.85m (CMAD-112) from the surface

in the southern part and at a maximum depth of 150.26m (CMAD-340) from the

surface also in the northwestern part of the block.

The parting between LKIIT and LKIIB seams predominantly consists of

arenaceous facies. The parting between aforesaid seams ranges between

1.05m (CMAD-270) and 4.21m (CMAD-54).

F. THICKNESS

It is observed that minimum thickness of 0.10m is found in borehole No.AMD-23

and maximum thickness of 2.68m is found in borehole No.CMAD-53. The

average thickness is 1.01m. The seam is deteriorated into carbonaceous shale

in one borehole CMAD-95.

The seam is described in detail and also considered for assessment of

availability of coal reserves.

G. OUTCROP/INCROP

The seam does not incrop in the block.

H. ROOF & FLOOR

The immediate roof and floor consists of coarse to medium grained sandstone.

Sometimes carbonaceous shale is also observed as roof and floor.

I. DIRT BANDS

The seam is having 1 to 2 dirt bands of both combustible and non-combustible

nature in seam in a few boreholes. However, in maximum boreholes seam is

devoid of dirt bands and no dirt band has been found less than 0.10m thickness

in any borehole.

J. PROXIMATE ANALYSIS

Grades on I10 samples show the grade variation between D to A. The average

grade is B.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 52 of 81

Range of proximate analysis & grade of Seam LKIIB, Amadand OC Block

Parameters Range

Bcs Sample I10 Sample I100 Sample Full Seam

Boreholes considered :

18 18 18

Thickness (m)/Range (m) Mean STD.DEV

0.55 - 2.68 (CMAD-309)(CMAD-53)

1.35 0.70

0.55 - 2.68 (CMAD-309)(CMAD-53)

1.35 0.70

0.55 - 2.68 (CMAD-309)(CMAD-53)

1.35 0.70

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.55 - 2.68 (CMAD-309)(CMAD-53)

1.30 0.70

0.55 - 2.68 (CMAD-309)(CMAD-53)

1.30 0.70

0.55 - 2.68 (CMAD-309)(CMAD-53)

1.35 0.70

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

5.6 – 9.7 (CMAD-270) (CMAD-24)

7.6 1.0

5.6 – 9.7 (CMAD-270) (CMAD-24)

7.6 1.0

5.6 – 9.2 (CMAD-270) (CMAD-33)

7.5 0.99

Ash% Mean STD.DEV

7.5 – 26.6 (CMAD-24) (CMAD-334)

14.6 5.3

7.5 – 26.6 (CMAD-24) (CMAD-334)

14.6 5.3

7.6 – 31.4 (CMAD-24) (CMAD-36)

15.6 6.3

VM% Mean STD.DEV

22.3 – 30.9 (CMAD-334) (CMAD-54)

26.7 2.6

22.3 – 30.9 (CMAD-334) (CMAD-54)

26.7 2.6

22.3 – 30.9 (CMAD-334) (CMAD-54)

26.9 2.6

FC% Mean STD.DEV

44.4 - 58.5 (CMAD-334) (CMAD-22)

51.0 4.3

44.4 - 58.5 (CMAD-334) (CMAD-22)

51.0 4.3

44.4 - 58.5 (CMAD-334) (CMAD-22)

51.3 4.1

UHV (Kcal/kg) Mean STD.DEV

4304 - 6761 (CMAD-334) (CMAD-22)

5802 635

4304 - 6761 (CMAD-334) (CMAD-22)

5802 635

3739 - 6761 (CMAD-36) (CMAD-22)

5694 770

Grade Avg. Grade

D-A B

D-A B

E-A B

K. GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam LKIIB, Amadand OC Block, Sohagpur Coalfield.

Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

18 0.36-2.68 5076 - 7748 (CMAD-334) (CMAD-54)

5076 - 7748 (CMAD-334) (CMAD-54)

4727- 7748 (CMAD-36) (CMAD-54)

L. RANGE OF ULTIMATE ANALYSIS

Range of Ultimate Analysis for Seam LKIIB, Amadand OC Block.

Parameters Range of content %

Ultimate Analysis on Bcs/Ex-band sample (dmmf basis)(No. of samples 1)

C% 79.35 (CMAD-54))

H% 4.84 (CMAD-54)

N% 1.61 (CMAD-54)

S% 0.75 (CMAD-54)

M. ASH FUSION TEMPERATURE RANGE

Data not available

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 53 of 81

N. HARDGROVE GRANDABILITY INDEX (HGI)

Data not available

O. ASH ANALYSIS

ASH ANALYSIS (on In band basis)

Borehole No. Constituents %

SiO2 Al2O3 Fe2O3 TiO2 P2O5 SO3 MnO CaO MgO Alkalis by diff.

CMAD-54 Ex-band

59.60 31.70 4.20 1.15 0.03 0.42 0.11 0.96 0.98 0.85

4.4.18 SEAM- LOWLER KOTMA II (LKII)

A. STATUS OF MINING

The mining activity of this seam is in progress in Amadand U/G block.

B. DETAILS OF BOREHOLES INTERSECTION

A. Intersections Nos.

i) No. of full seam intersections in boreholes 117

ii) No. of outcrop proving boreholes with part thickness Nil

iii) No. of boreholes with part thickness due to faulting Nil

iv) No. of boreholes where seam is totally omitted due to fault Nil

v) No. of boreholes where seam is merged with lower seam Nil

vi) No. of boreholes where seam is not encountered due to non-development of seam and presence of dyke

Nil

vii) No. of boreholes not deepened to encounter the seam

viii) No. of boreholes beyond incrop 38 TOTAL 155

a. Depth of intersection (Roof) i) Shallowest : 83.84m (CMAD-88)

ii) Deepest : 150.40m (CMAD-58)

b. Minimum & Maximum FRLs

i) Minimum : 392.16m (CMAD-35)

ii) Maximum : 461.37m (CMAD-107)

C. STRATIGRAPHIC POSITION

This is the fifteenth workable seam and eighteenth from the surface within the

Barakar Formation in the block.

D. SPLITTING

The composite seam is splitting into LKIIT & LKIIB in the western part of the

block.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 54 of 81

E. PARTING

The seam occurs at a minimum depth of 83.84m (CMAD-88) from the surface in

the south eastern part and at a maximum depth of 150.40m (CMAD-58) from the

surface also in the northern part of the block.

F. THICKNESS

It is observed that minimum thickness of 0.24m is found in borehole No.CMAD-

264 and maximum thickness of 5.62m is found in borehole No.CMAD-46. The

average thickness is 1.97m. The seam is deteriorated into shale and

carbonaceous shale in one and two boreholes respectively.

The seam is described in detail and also considered for assessment of

availability of coal reserves.

G. OUTCROP/INCROP

The seam does not incrop in the block.

H. ROOF & FLOOR

The immediate roof and floor consists of coarse to medium grained sandstone.

Sometimes carbonaceous shale is also observed as roof and floor.

I. DIRT BANDS

The seam is having 1 to 3 dirt bands of both combustible and non-combustible

nature in seam in a few boreholes. However, in maximum boreholes seam is

devoid of dirt bands.

Dirt bands in Seam LKII (on I10 basis) Thickness

range of seam (m)

Effective thickness range (m)

Carbonaceous shale bands

Non-Combustible bands Total bands

No.of bands/ No.

of BHs

Thick. range (m)

No.of bands/ No. of BHs

Thickness range (m)

No.of bands/ No.

of BHs

Thick. range (m)

0.32 - 5.62 0.32 - 5.17 1/3 0.06-0.09 1/6 0.06-0.10 1/9 0.06-0.10

J. PROXIMATE ANALYSIS

Grades on I10 samples show the grade variation between UG to A. The average

grade is B.

Range of proximate analysis & grade of Seam LKII, Amadand OC Block Parameters Range

Bcs Sample I10 Sample I100 Sample Full Seam

Boreholes considered :

108 108 108

Thickness (m)/Range (m) Mean STD.DEV

0.32 - 5.62 (CMAD-58)(CMAD-46)

2.03 0.74

0.32 - 5.62 (CMAD-58)(CMAD-46)

2.03 0.74

0.32 - 5.62 (CMAD-58)(CMAD-46)

2.03 0.74

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 55 of 81

Parameters Range

Bcs Sample I10 Sample I100 Sample Effect. Thickness (m)/Range (m) Mean STD.DEV

0.32 - 5.17 (CMAD-58)(CMAD-46)

1.97 0.69

0.32 - 5.17 (CMAD-58)(CMAD-46)

1.99 0.69

0.32 - 5.62 (CMAD-58)(CMAD-46)

2.00 0.76

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

3.9 – 9.7 (CMAD-60) (CMAD-14)

7.5 1.0

3.9 – 9.7 (CMAD-60) (CMAD-14)

7.5 1.0

5.2 – 9.7 (CMAD-283) (CMAD-24)

7.5 1.0

Ash% Mean STD.DEV

5.3 – 51.0 (CMAD-44) (CMAD-515)

15.4 7.5

5.3 – 51.0 (CMAD-44) (CMAD-515)

15.5 7.5

5.3 – 51.0 (CMAD-44) (CMAD-515)

16.3 8.3

VM% Mean STD.DEV

16.2 – 31.2 (CMAD-515) (CMAD-156)

26.4 2.2

16.2 – 31.2 (CMAD-515) (CMAD-156)

26.4 2.2

16.2 – 31.2 (CMAD-515) (CMAD-156)

26.4 2.2

FC% Mean STD.DEV

27.5 - 59.8 (CMAD-515) (AMD-6)

51.4 5.8

27.5 - 59.8 (CMAD-515) (AMD-6)

51.5 5.8

27.5 - 59.8 (CMAD-515) (AMD-6)

51.4 6.0

UHV (Kcal/kg) Mean STD.DEV

1130 - 7133 (CMAD-515) (AMD-6)

5697 961

1130 - 7133 (CMAD-515) (AMD-6)

5680 963

1130 - 7133 (CMAD-515) (AMD-6)

5565 1049

Grade Avg. Grade

UG-A B

UG-A B

UG-A C

K. GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam LKII, Amadand OC Block, Sohagpur Coalfield.

Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

108 0.32-5.17 2984 - 7073

(CMAD-515) (AMD-6) 2984 - 7073

(CMAD-515) (AMD-6) 2984 - 7073

(CMAD-515) (AMD-6)

L. RANGE OF ULTIMATE ANALYSIS

Range of Ultimate Analysis for Seam LKII, Amadand OC Block

Parameters Range of content %

Ultimate Analysis on Bcs/Ex-band sample (dmmf basis)(No. of samples 6)

C% 78.83 - 82.04 (CMAD-52) (CMAD-165)

H% 4.72 - 5.01 (CMAD-164) (AMD-8)

N% 1.55 - 1.63 (CMAD-51) (CMAD-165)

S% 0.63 - 1.03 (AMD-08) (CMAD-165)

M. ASH FUSION TEMPERATURE RANGE

Ash Fusion Temperature Range for Seam LKII (including bands), Amadand OC

Block, Sohagpur Coalfield.

Borehole considered

Thickness range (m)

Ash fusion range oC(under mildly reducing atmosphere)

IDT HT FT

8 1.55-2.36 1100->1400 >1400->1400 >1400->1400

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 56 of 81

N. HARDGROVE GRANDABILITY INDEX (HGI)

HGI of 3 boreholes of Seam LKII of Amadand OC Block sample is given as

under:

H.G.I. for Seam LKII, Amadand OC Block, Sohagpur Coalfield.

No. of boreholes Nature of Sample Range

Minimum Maximum

2 Bcs/I10/I100 39 42

O. ASH ANALYSIS ASH ANALYSIS (on In band basis)

Borehole No.

Constituents %

SiO2 Al2O3 Fe2O3 TiO2 P2O5 SO3 MnO CaO MgO Alkalis by diff.

AMD-8 60.36 26.80 3.88 2.10 0.01 0.86 - 2.74 1.87 1.32

CMAD-51 59.10 30.66 5.40 1.30 0.03 0.40 0.14 1.00 0.98 0.99

CMAD-52 56.80 33.40 5.20 1.35 0.02 0.39 0.10 0.99 0.95 0.80

4.5 SPECIALIZED STUDY

4.5.1 Physico mechanical properties The drill core samples of borehole No.CMAD-340 was sent to Mining laboratory

of CMPDI at Ranchi for physico-mechanical tests. The report received from the

mining laboratory is reproduced below:

4.5.1.1TEST RESULTS Summarised data in respect of bulk density, unconfined compressive strength,

tensile strength, shear strength and Young’s modulus of elasticity are given in table –I.

The triaxial test results are given in Table II. Mohr’s diagram drawn from triaxial test

results is also enclosed for reference.

TABLE 4.5.1.1A

TEST RESULTS OF PHYSICO-MECHANICAL PROPERTIES ON DRILL CORE

SAMPLES OF BOREHOLE NO.CMAD-340 OF AMADAND OC BLOCK, SOHAGPUR COALFIELD

Sampl

e No.

Rock type Depth (m)

Density

gm/cc

Compressive strength

(Mpa)

Tensile strengt

h (Mpa)

Shear strength

(Mpa)

Young’s modulus

(Gpa)

Mean,Std.Deviation & No.of specimen tested

1 Sludge 0.00-25.40

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 57 of 81

Sample

No.

Rock type Depth (m)

Density

gm/cc

Compressive strength

(Mpa)

Tensile strengt

h (Mpa)

Shear strength

(Mpa)

Young’s modulus

(Gpa)

Mean,Std.Deviation & No.of specimen tested

2 CGD SST grey coloured

25.40-25.42 2.70

3 Grey SH 25.42-25.76 2.06

4 Carb.SH 25.76-25.96 1.96

5 Sandy SH 25.96-26.30 2.21 3.344 0.841

4

6 Coal 26.30-26.40 1.33

7 Sandy SH 26.40-27.32 2.19 32.065 5.266

2

8 Coal 27.32-28.16 1.33

9 Sandy SH 28.16-28.25 2.08 1.929 - 1

10 FGD SST grey coloured

28.25-28.45 2.25 14.147 - 1

2.541 - 1

11 FGD to MGD SST shaly patches at top

28.45-29.95 2.30 14.681 5.991

3

1.964 0.269

4

3.625 0.715

2

12 Sandy SH 29.95-30.06 2.19 3.429 1

13 FGD SST with shaly patches

30.06-30.44 2.25 14.081 2.253 0.208

2

14 Grey SH 30.44-30.65 1.77

15 Carb.SH 30.65-30.71 1.80

16 FGD SST with shaly patches

30.71-31.11 2.20 6.172 1.275

3

17 Sandy SH 31.11-31.50 2.28 7.256 - 1

18 Sandy SH 31.50-32.10 2.18 5.260 - 1

19 Carb.SH 32.10-32.27 1.94

20 Coal Broken 32.27-32.37 1.32

21 FGD SST 32.37-33.32 2.34 34.183 5.234

3

4.963 1.090

4

22 Sandy SH 33.32-34.10 2.24 43.545 - 1

0.419 1.702

2

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 58 of 81

Sample

No.

Rock type Depth (m)

Density

gm/cc

Compressive strength

(Mpa)

Tensile strengt

h (Mpa)

Shear strength

(Mpa)

Young’s modulus

(Gpa)

Mean,Std.Deviation & No.of specimen tested

23 Grey SH 34.10-34.60 2.02

24 Coal 34.60-36.05 1.32 33.300 -

1

2.716 -

1

25 Grey SH 36.05-36.35 2.14

26 Coal 36.35-39.02 1.40

27 Sandy SH 39.02-39.35 2.24

28 MGD SST grey coloured

39.35-40.65 2.27 27.789 7.064

5

2.226 0.403

5

5.997 0.764

3

3.856 0.215

2

29 CGD SST grey coloured poor sorting

40.65-43.70 2.29 13.988 4.065

6

2.160 0.542

5

3.965 0.496

4

3.654 0.929

3

30 --do-- 43.70-49.80 2.29 14.063 2.976

5

1.285 0.372

5

3.478 0.364

4

3.133 0.333

2

31 Grottu SST friable

49.80-52.85 2.32 7.806 0.898

5

0.609 0.342

5

2.826 - 1

1.875 - 1

32 CGD SST friable poor sorting

52.85-55.90 2.24 13.085 3.627

6

1.898 0.162

5

2.397 0.482

3

3.372 0.193

2

33 VCGD SST friable pebbly at places

55.90-58.95 2.28 12.041 4.330

6

1.197 0.251

5

3.549 0.960

3

2.918 0.574

2

34 CGD SST friable

58.95-59.12 2.29 1.651 0.102

2

35 Coal broken 59.12-59.47 1.25

36 Sandy SH 59.47-61.48 2.17 37.567 3.375 0.360

5

37 FGD SST shaly patches at places

81.48-62.00 2.23 22.354 2.188

2

3.697 0.243

2

38 CGD SST 62.00-62.50 2.23 12.100 1.863

2

1.099 - 1

39 FGD SST 62.50-63.00 2.40 14.546 - 1

2.495 0.336

3

40 CGD SST friable

63.00-65.05 2.28 13.232 1.972

6

2.004 0.317

5

3.299 0.077

2

41 Highly friable CGD SST

65.05-74.20 2.27 7.068 0.845

7

0.822 0.158

5

1.440 0.325

3

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 59 of 81

Sample

No.

Rock type Depth (m)

Density

gm/cc

Compressive strength

(Mpa)

Tensile strengt

h (Mpa)

Shear strength

(Mpa)

Young’s modulus

(Gpa)

Mean,Std.Deviation & No.of specimen tested

42 Highly friable CGD SST

74.20-80.75 2.26 6.976 1.035

5

0.891 0.139

5

1.104 - 1

1.482 - 1

43 Shaly coal broken

80.75-81.00 1.77

44 Carb.sh. 81.00-81.08 1.95

45 Coal 81.08-81.20 1.29

46 Sandy SH broken sub vertically at bottom

81.20-82.65 2.32 22.541 2.973

4

2.624 0.789

5

1.825 0.364

2

47 MGD SST broken sub vertically at places from top

82.65-83.35 2.26 7.488 - 1

2.819 0.156

3

48 CGD SST 83.35-85.14 2.26 10.438 2.423

4

1.414 0.668

3

1.572 0.009

2

2.114 0.022

2

49 Sandy SH broken

85.14-85.58 2.21

50 CGD SST friable

85.58-86.40 2.25 9.376 - 1

1.102 0.180

5

51 CGD SST 86.40-89.45 2.33 8.996 1.015

5

1.129 0.155

5

2.069 0.569

3

1.778 0.073

2

52 CGD SST shaly patch at middle

89.45-89.68 2.38 1.505 0.108

2

53 Sandy SH 89.68-89.74 2.30

54 Coal 89.74-89.90 1.31

55 Shaly coal 89.90-91.65 1.65 3.327 0.085

2

56 Carb.SH 91.65-92.25 1.72 4.444 0.511

5

57 Shaly Coal 92.25-92.34 1.93

58 Coal 92.34-94.60 1.36

59 MGD SST grey coloured

94.60-95.55 2.35 22.387 5.739

4

3.089 0.443

5

3.149 0.157

2

60 MGD to CGD SST

95.55-98.60 2.26 17.220 4.785

6

1.378 0.350

3

2.850 0.385

4

2.517 0.371

2

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 60 of 81

Sample

No.

Rock type Depth (m)

Density

gm/cc

Compressive strength

(Mpa)

Tensile strengt

h (Mpa)

Shear strength

(Mpa)

Young’s modulus

(Gpa)

Mean,Std.Deviation & No.of specimen tested

61 CGD SST friable

98.60-101.65 2.33 10.493 1.484

6

2.185 0.557

5

3.203 0.758

2

2.560 0.109

2

62 CGD SST friable poor sorting

101.65-104.70 2.13 11.534 4.081

5

1.726 0.107

4

3.935 - 1

63 Gritty SST highly friable

104.70-106.60 2.36 6.146 - 1

0.967 0.139

4

3.935 - 1

64 Coal 106.60-106.74 1.25

65 Gritty SST highly friable

106.74-107.75 2.27 7.372 1.223

3

0.884 0.091

3

66 VCGD SST friable

107.75-110.80 2.28 10.544 0.903

5

1.330 0.285

4

2.261 0.361

3

1.873 0.297

2

67 VCGD SST friable

110.80-117.05 2.25 10.074 3.435

5

1.300 0.134

5

1.986 0.595

5

68 Shaly coal broken

117.05-117.30 1.87

69 Sandy SH 117.30-118.00 2.31

70 --do-- 118.00-119.50 2.33 37.117 - 1

2.687 - 1

71 MGD SST 119.50-119.95 2.27 11.762 - 1

72 FGD SST 119.95-120.10 2.26 2.918 0.055

3

73 CGD SST 120.10-120.47 2.15 1.154 0.205

5

74 FGD SST 120.47-120.52 2.32

75 Coal 120.52-121.02 1.94

76 Sandy SH 121.02-121.33 2.30

77 Coal 121.33-122.48 1.29

78 FGD SST 122.48-123.00 2.41 15.887

79 MGD to CGD SST

123.00-126.05 2.21 11.143 4.363

5

1.534 0.369

5

2.407 0.560

5

3.223 0.617

2

80 CGD SST 126.05-132.15 2.22 11.407 2.206

5

1.466 0.136

5

2.203 0.417

5

2.699 0.532

2

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 61 of 81

Sample

No.

Rock type Depth (m)

Density

gm/cc

Compressive strength

(Mpa)

Tensile strengt

h (Mpa)

Shear strength

(Mpa)

Young’s modulus

(Gpa)

Mean,Std.Deviation & No.of specimen tested

81 --do-- 132.15-138.25 2.21 6.567 1.494

5

1.124 0.150

4

1.934 0.504

5

2.085 0.315

2

82 Gritty SST friable

138.25-139.13 2.23 7.671 1.358 - 1

83 CGD to VCGD SST

139.13-141.30 2.19 9.379 2.259

4

1.150 0.221

4

2.453 - 1

1.678 0.129

2

84 CGD SST friable

141.30-143.55 2.26 14.870 3.891

4

1.655 0.252

5

3.350 - 1

85 Gritty SST friable

143.55-147.07 2.24 7.607 3.149

6

1.250 - 1

1.128 0.011

2

2.441 - 1

86 Coal 147.07-147.53 1.35

87 Grey SH 147.53-147.81 2.13

88 Coal 147.81-148.88 1.25

89 Sandy SH 148.88-150.01 2.29

90 Grey SH 150.01-150.26 2.28 47.197 2.629

91 Coal 150.26-152.54 1.68

92 Sandy SH 152.54-155.10 2.39 26.689 5.641

3

5.191 0.871

5

3.472 0.600

4

2.983 1.312

2

93 FGD SST shaly patches at places

155.10-155.71 2.35 11.928 0.716

4

2.293 0.283

2

94 Sandy SH 155.71-155.90 2.25

95 Coal 155.90-156.05 1.30

96 Sandy SH 156.05-156.11 2.34

97 FGD SST 156.11-156.10 2.33 15.404 5.080

2

TABLE 4.5.1.1B

TRIAXIAL TEST RESULTS ON DRILL CORE SAMPLES OF BOREHOLE NO.CMAD-

340 OF AMADAND OC BLOCK, SOHAGPUR COALFIELD Sampl

e No.

Rock type Depth (m)

Compressive strength (MPa) Mean Std.Deviation & No.of specimen tested

Angle of internal friction

Cohesion

"C"

At 0 MPa Confining

At 5 MPa Confining

At 10 MPa Confining

(degree) (MPa)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 62 of 81

Sample

No.

Rock type Depth (m)

Compressive strength (MPa) Mean Std.Deviation & No.of specimen tested

Angle of internal friction

Cohesion

"C"

At 0 MPa Confining

At 5 MPa Confining

At 10 MPa Confining

(degree) (MPa)

29 CGD SST grey coloured poor sorting

40.65-43.70

13.988 4.065

6

59.65 4.053

2

76.937 2.653

2

24 2.5

30 --do-- 43.70-49.80

14.063 2.976

5

53.970 2.970

3

63.168 - 1

31.5 2.0

31 Gritty SST friable

49.80-52.85

7.806 0.898

5

31.691 2.875

2

40.201 1.281

2

26.5 1.5

32 CGD SST friable poor sorting

52.85-55.90

13.085 3.627

6

28.405 5.837

2

54.585 2.102

2

24\ 2.5

33 VCGD SST friable pebbly at places

55.90-58.95

12.041 4.330

6

40.675 6.656

2

80.322 16.710

2

28 2.0

40 CGD SST friable

63.00-65.05

13.232 1.972

6

49.790 64.325 16.454

2

21 2.0

42 Highly friable CGD SST

74.20-80.75

6.976 1.035

5

36.123 7.872

2

52.636 - 1

24.5 1.5

48 CGD SST 83.35-85.14

10.438 2.423

4

27.513 4.918

2

38.701 8.583

2

28.6 2.5

51 CGD SST 86.40-89.45

8.996 1.015

5

23.25 39.907 0.247

2

21.5 2.0

60 MGD to CGD SST

95.55-98.60

17.220 4.785

6

61.563 8.257

2

24.5 2.0

62 CGD SST friable poor sorting

101.65-104.70

11.534 4.081

5

47.226 1.902

2

63.194 0.081

2

25 2.0

66 VCGD SST friable

107.75-110.80

10.544 0.903

5

55.255 2.882

2

74.709 0.496

2

30 2.0

67 VCGD SST friable

110.80-117.05

10.074 3.435

5

26.931 8.820

2

55.075 7.648

2

27.5 2.0

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 63 of 81

Sample

No.

Rock type Depth (m)

Compressive strength (MPa) Mean Std.Deviation & No.of specimen tested

Angle of internal friction

Cohesion

"C"

At 0 MPa Confining

At 5 MPa Confining

At 10 MPa Confining

(degree) (MPa)

80 CGD SST 126.05-132.15

11.407 2.206

5

37.749 0.046

2

49.492 6.920

2

33 2.0

81 --do-- 132.15-138.25

6.567 1.494

5

43.343 0.513

2

45.461 2.515

2

35 1.4

83 CGD to VCGD SST

139.13-141.30

9.379 2.259

4

27.291 5.780

2

50.919 9.400

2

26 2.0

84 CGD SST friable

141.30-143.55

14.870 3.891

4

42.429 13.496

2

55.519 20.217

2

20.5 3.0

4.5.2 Hydro-geological details:

Surface water:

Regionally, the Son River and its tributaries mainly control the drainage system

in the area. Kewai River, a major tributary of Son River flowing close to the

western boundary of the mine, in a north east to south west direction, is the

master drainage of the study area.

The block area is traversed by a small first order stream Banki Nala in the south-

west. Bhirwa Nala is flowing along the south eastern part of the project. Both

Banki Nala and Bhirwa nala is flowing towards south west direction and finally

they merge and discharge into Son River as Bhirwa nala.

Another important river close to the eastern boundary of the mine is Jhiria Nala

which is flowing in the North-east to East direction and finally merges with

Kulhariya Nala. Kulhariya nala is draining the north eastern part of the study

area. It is flowing form north to east and finally discharge into Hasdeo River.

The other streams which drain the buffer zone are Hendri Nala in north,

Bukbuka Nala, Bathi Dhar, Khari and Jhimar Dhar in east, Neori nala and

Keraha Dhar in south east. The drainage pattern in the area is mostly dendritic in

nature.

Groundwater:

The formations within the study area are Gondwanas and Talchirs. Major portion

of the area is occupied by Gondwanas and the rest by Talchirs. The project area,

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 64 of 81

situated on Barakar sand stone formation, comprises soil cover, weathered

mantle and sand stone of different grain sizes with shale beds and coal seams.

The weathered mantle and sand stone beds are saturated, and behave as

aquifers whereas the shale beds and coal seams as aquicludes. Due to

stratification and with the presence of aquicludes (shale/coal), a multi-aquifer

system is developed.

Eleven coal seams developed in the block and all the seams are selected for

opencast mining. The seams are centrally dipping and the gradient of the seams

area 1 in 30.

The alluvium formation and weathered Barakar formation comprising mainly of

loosely cemented and poorly consolidated grey coloured medium to coarse

grained sandstone lying above the Upper Kotma (Top) & Upper Kotma Combine

coal seams with a thickness varying from 20.0 m to 40.0 m behave as

unconfined aquifer. This unconfined aquifer is potential and prolific. The lower

formations, consisting of compact and fine to medium grained sandstone with

occasional sandy shale, carbonaceous shale and shale intercalation, with

secondary porosity, behave as semi-confined to confine in nature.

The general hydro-geological units developed in the Amadand block area are as

follows:

Hydrogeological Unit

Formation Thickness

Phreatic aquifer (A)

Soil & Alluvium, loosely cemented, poorly consolidated medium to coarse grained weathered sandstone & intercalation of shale and sandstone.

20.0 m – 40.0 m

Aquiclude Coal seam Upper Kotma (Top) & Upper Kotma Combine (Working)

0.80m – 1.65 m

Aquifer (B)

Medium to coarse grained sandstone, with occasional sandy shale, carbonaceous shale and shale intercalation

1.00 m – 3.00 m

Aquiclude Coal seam Upper Kotma (Bottom) (Working)

0.40 m – 1.00 m

Aquifer (C) Fine to medium grained sandstone 10.00 m – 17.00 m

Aquiclude Coal seam L4 (Working) 0.10 m – 0.40 m

Aquifer (D) Medium to coarse grained sandstone 10.00 m – 20.00 m

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 65 of 81

Aquiclude Coal seam L3 Top & L3 (Working) 0.10 m – 0.60 m

Aquifer (E) Medium to coarse grained sandstone 1.00 m – 4.50 m

Aquiclude Coal seam L3 Bottom (Working) 0.15 m – 0.55 m

Aquifer (F) Medium to coarse grained sandstone 1.50 m – 4.00 m

Aquiclude Coal seam Middle Kotma Top (Working)

0.25 m – 1.70 m

Aquifer (G) Medium to coarse grained sandstone, occasional sandy shale, carbonaceous shale intercalation

1.00 m – 6.75 m

Aquiclude Coal seam Middle Kotma Bottom (Working)

0.30 m – 1.25 m

Aquifer (H) Medium to coarse grained sandstone 13.50 m – 23.00 m

Aquiclude Coal seam Lower Kotma I (Working) 0.10 m – 0.80 m

Aquifer (I) Medium to coarse grained sandstone 11.00 m – 19.00 m

Aquiclude Coal seam L1 (Working) 0.15 m – 0.80 m

Aquifer (J) Medium to coarse grained sandstone 3.00 m – 25.00 m

Aquiclude Coal seam Lower Kotma II Top & Lower Kotma II Combine (Working)

0.40 m – 1.00 m

Aquifer (K) Medium to coarse grained sandstone 1.00 m – 4.00 m

Aquiclude Coal seam Lower Kotma II Bottom (Working)

0.18 m – 1.20 m

Aquifer Parameters

No detailed hydrogeological investigation has been carried out in the present

mine block. However, hydrogeological investigations were carried out by

CGWB & CMPDI in Jamuna coalfield, where the mine is situated, under S&T

project," Studies on Groundwater Flow into Coal Mines." The aquifer parameters

for the formation lying above the working seam (i.e. multi-aquifer) were reported

as:

Transmissivity (T) : 175 m2/day

Permeability (k) : 5 m/day

Storage coefficient : 5.0 x 10-4

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 66 of 81

So also, detailed hydrogeological investigations were carried out at Bartarai UG

project just adjacent to Amadand OC Project, located in Jamuna-Kotma Area,

the aquifer parameters for lower aquifer were evaluated by SECL and reported

the permeability as 0.25 m/day.

Ground water levels:

Village groundwater levels:

Mainly 8 villages is present in the Amadand Block and the water levels

monitored in the villages during pre monsoon (May 2010 and May 2012) are

furnished below. The water levels in the block during pre-monsoon (May 2012)

observed to vary from 4.06m (Malga) to more than 9.80 m (Baratrai).

DETAILS OF WELL INVENTORY & GROUNDWATER LEVELS, AMADAND EXPLORATION BLOCK

Sl. No.

Place/ Location

Owner Well Depth (m)

Well Dia (m)

Height of Parapet (m)

Water Level, may '10 bgl (m)

Water Level, may '12 bgl (m)

Remarks

1 Amadand O.P.Vishwakarma 7.15 1.25 0.70 5.95 5.45 Rd side, close to chowk, inside house premises

2 Baratrai Govt Well 9.80 2.85 0.85 >8.95 Dry Near Primary School

3 Bhalwahi Hiralal 12.18 2.50 1.10 10.95 7.60 Nr to temple of (Late) Hira Singh, Bamboo grooves, brick lined

4 Kuhka Kare lal s/o Bahbal Singh

8.3 1.4 0.55 7.45 6.75 main road, 100 behind temple, centre of village, pucca well, brick lined

5 Manjhauli Sudama Prasad Mishra s/o Ramdas Mishra

10.05 1.30 0.80 9.15 7.87 Rd side, inside house

6 Malga Govt Well Near School

6.6 2.20 0.00 3.05 4.06 inside school premises, abandoned, brick lined

7 Nimha Pakshu 7.1 1.50 0.00 6.60 5.80 Nr temple, house premises, kuchcha well

8 Timkiitola Gore Lal 6.2 1.20 0.00 6.05 6.28 Opp. school, rd side, in front of house

Historical groundwater levels:

The District Groundwater Survey Unit, Shadol district, Madhya Pradesh, has

been monitoring the ground water levels in the region. The pre-monsoon and

post-monsoon historical groundwater levels for the last 22 years (1990 - 2011)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 67 of 81

recorded at the nearest permanent observation wells Khodri (POW-08) and

Payari (POW-89) located close to the block were collected and are given below:

(in meters) b.g.l.

Hydrograph

Stn / Year

Khodri (POW -08) Payari (POW-89)

Pre -

Monsoon

Post -

Monsoon Fluctuation

Pre -

Monsoon

Post -

Monsoon Fluctuation

1990 6.13 2.98 3.15 9.15 2.90 6.25

1991 6.05 3.80 2.25 9.30 4.10 5.20

1992 7.05 3.08 3.97 7.60 4.00 3.60

1993 8.27 3.75 4.52 8.05 4.41 3.64

1994 8.10 2.05 6.05 8.60 2.55 6.05

1995 7.95 3.40 4.55 8.51 2.61 5.90

1996 8.55 3.73 4.82 9.64 5.42 4.22

1997 9.06 2.77 6.29 12.53 3.05 9.48

1998 8.27 3.88 4.39 12.48 3.68 8.80

1999 9.08 3.95 5.13 12.50 4.00 8.50

2000 9.20 4.45 4.75 12.36 5.40 6.96

2001 9.28 4.50 4.78 12.30 5.50 6.80

2002 9.80 5.10 4.70 8.35 6.60 1.75

2003 11.00 3.00 8.00 8.20 3.00 5.20

2004 7.25 4.00 3.25 7.10 3.60 3.50

2005 7.65 3.75 3.90 9.00 3.55 5.45

2006 7.55 3.98 3.57 8.40 3.70 4.70

2007 7.70 4.40 3.30 7.40 4.00 3.40

2008 7.72 5.10 2.62 8.00 3.90 4.10

2009 7.92 6.35 1.57 6.90 4.65 2.25

2010 8.00 6.35 1.65 9.00 5.89 3.11

2011 8.11 4.85 3.26 9.05 3.22 5.83

Average 8.17 4.06 4.11 9.29 4.08 5.21

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 68 of 81

The above mentioned data shows that the pre-monsoon water levels vary from

6.05m (1991, Khodri) to 12.53 m (1997, Payari) with an average of 8.73 m and

Post monsoon water level data vary from 2.05 m ( 1994, Khodri) to 6.60 m

(2002, Payari) with an average of 4.07 m. The average water level fluctuation

varies from 1.57 m (2009, Khodri) to 9.48 m (1997, Payari) with an average of

4.66 m in the Buffer zone.

Water level trends:

The Pre-monsoon and Post-monsoon water level trends of the above

hydrograph stations are given in Fig. (a) and (b).

Pre and Post-monsoon Water Level Trends,

Station: KHODRI (POW-08)

0

4

8

12

1990

1991

1992

1993

1994

1995

1996

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

Year

Wa

ter

lev

el (m

)

0

500

1000

1500

2000

2500

Ra

infa

ll (

mm

)

Rainfall Pre-Monsoon Post-Monsoon

Fig. (a)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 69 of 81

Pre and Post-monsoon Water Level Trends,

Station: PAYARI (POW-89)

0

4

8

12

16

1990

1991

1992

1993

1994

1995

1996

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

Year

Wa

ter

lev

el (m

)

0

500

1000

1500

2000

2500

Ra

infa

ll (

mm

)

Rainfall Pre-Monsoon Post-Monsoon

Fig. (b)

The pre and post-monsoon water levels of Khodri station show decreasing

trends whereas the pre monsoon water level trend at Payari shows increasing

trend and post-monsoon water level trends at Payari station show marginal

decline. This upward trend may be attributed to the water conservation and

utilization of surface water for irrigation use in the area. The decline in pre and

post-monsoon water level at Khodri village may be attributed to increase in

ground water utilization due to increase in the local population and the irrigation

draft and .decrease in rainfall.

Groundwater Stage of Development:

Except for coal mining, no major industrial development activity is located in the

area. Due to dominant forest area and backwardness the groundwater

development in the area is very insignificant. As per CGWB, NCC Region, Raipur,

the total annual replenishable ground water resource in the Anuppur Development

Block, Shahdol district (where Amadand Block exists), was assessed as 68.20

M.Cum. It was also reported that the ground water development in the block is as

1.99 % and falls within category "Safe". As such, the entire Madhya Pradesh &

Chhattisgarh States are covered under the category “Safe”.

Water Quality:

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 70 of 81

Under routine environmental monitoring, the surface, groundwater and mine

water quality, for all the operating mines in the area, have been monitored and

found to be well within the permissible limits of stipulated standards. Mine water

and other effluents have been treated before disposal and usage.

Mine Drainage:

In sedimentary rocks, due to stratification, the horizontal permeability (KH) is

many folds higher than the vertical permeability (KV). The permeable beds act as

individual hydrogeological units and develop a multi-aquifer system. Thereby, the

groundwater velocity / flow along the bedding plane are higher than across the

plane. The opencast mine can be simulated as a large diameter well and the

inflows are contributed mainly from the saturated formation lying above. Thus,

the mine inflow is directly proportional to the aquifer and mine parameters.

In the initial stage the mine inflow is in proportion to the rate of mine expansion.

With the presence of low permeable formations, the inflow is significantly small.

In due course of mining, due to partial de-saturation of the aquifer, the inflow

reduces and gets stabilized.

Presently, in Amadand Opencast mine, the permeable formations lying above

the deepest working seam (Lower Kotma II Bottom) are mainly composed of

sandstone with occasional intercalation of shale, sandstone and sandy shale.

The present depth of workings is about 35m against an ultimate planned depth

of 150m. The present mine discharge during dry period is estimated as 3,928

m3/d, which can be considered as the ground water inflow into the mine.

Disposal of Mine water:

To meet the safety of the mine and create good working conditions, it is necessary

to discharge the mine water collection onto surface. To collect the present mine

water inflow from the operating two quarries (Departmental Patch and Contractual

Patch), three sumps with a total holding capacity of about 65,000 cum. (i.e.

Departmental Patch = 24,000 + 9,000 cum & Contractual Patch = 32,000 cum) are

existing and equipped with suitable sumps. The main sump floor RL in

Departmental Patch is 510.00 m. whereas, the sump floor RL in Contractual Patch

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 71 of 81

is 505.00 m. As the mine is in the starting phase and because of lack of adequate

storage space within active mine area, so, most of the monsoon water collection

has been discharged on the surface. As such the entire industrial water demand

has been met from mine water only.

To handle the inflow 9 pumps (3 Nos. @ 1000 gpm, 6 Nos. @ 700 gpm), including

standby, with a total discharge capacity of about 7,200 gpm (545 LPs) are

operating in both the working quarries. As such, the monsoon water collection has

been stored in the sumps and only the overflow of these sumps has been

discharged.

The present mine water discharge varies from about 21,210m3/day during peak

monsoon period to about 3,928 m3/day in lean period. Thereby, the average

pumping (120 days rainy period + 245 days lean period) from Amadand OCP is

9,610m3/day. This discharge includes both rainwater collection and groundwater

seepage into the mine.

Sl. No. Mine Mine discharge

during non-

monsoon period

(Cum/day)

Mine discharge

during monsoon

period (Cum/day)

1 Amadand OC 3,928 21,210

This stored water has been effectively utilized for industrial purposes within mine

premises, such as, mine operation, dust suppression, CHP, workshop, greenbelt

development and fight fighting uses. Most of the mine water has been discharged

after sufficient settling time. Thereby, the discharged water is almost clean with

very less TSS load. The mine water after settling in mine sumps has been

discharged to various utility points and excess water / overflow has been

discharged into the adjacent ponds and irrigation land for local users.

During monsoon, part of the mine water has been discharged on down dip for

irrigation use, the overflow of which will ultimately reach the adjacent Banki Nala

flowing in the southern part of the mine. Because of clean water in sufficient

quantity is available for local irrigation, the crops in these villages are protected.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 72 of 81

4.6 GEOLOGICAL RESERVES

4.6.1 BRIEF METHODOLOGY FOR RESERVE ESTIMATION

Estimation of quarriable reserves has been made on the following considerations:

(i) The effective thickness of the seams considered for quarriable reserves

includes all combustible and non-combustible bands upto 0.10m,

(ii) All bands of more than 0.10m thickness irrespective of their lithology have been

excluded from seam thickness for arriving at effective seam thickness in the

case of quarriable proposition.

(iii) All the unworkable coal bands/coal sections occurring above/below the

delineated roof/floor of the seam sections and also those occurring within the

seam partings have been added to the overburden.

(iv) The cumulative thickness of all bands excluded from the seam thickness has

been added to the seam burden.

(v) For estimation of quarriable reserves, thickness ranges of 0.50 to 0.90m, 0.90

to 1.20m, 1.20 to 1.50m, 1.50 to 2.00m, 2.00 to 2.5m and 2.5m to 3.00m and so

on, have been considered.

(vi) The minimum thickness considered for reserve estimation has been taken as

0.50m as desired by Mine Planners.

(vii) The influence area around the borehole in which seam has deteriorated to

carb.shale, shale or clay has not been considered for reserve estimation.

(viii) Thickness and quality values of seams in boreholes have not been considered

wherever values are not in conformity of surrounding boreholes. For instance,

in case of MKT Seam values of boreholes AMD-15, CMAD-62, 115, 121, 127

and 243 and for Seam L-1, values of borehole CMAD-64 has not been

considered

CATEGORAIZATION OF RESERVES

The entire reserves of fifteen coal seams viz. UKT, UKB, L4, L3T, L3B, L3,

MKT, MKB, MKC, LKI, L1, LKIIT, LKIIB & LKII, have been placed under 'Proved'

category as per Indian Standard Procedure.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 73 of 81

Although, forest area has been shown to occur nearly at southern and in the

north-eastern part of the block, where drilling could not be possible, there is

hardly any difference between two boreholes of around 50-100m after

considering the area of influence of 200m to satisfy the norms of indicated

reserves. Therefore, all the reserves are considered to be covered under

“Proved” category.

To obtain net in-situ geological reserves, a total deduction of 10% has been

made from the estimated gross reserves to compensate for loss on account of

faults and other unforeseen geological conditions.

METHODOLOGY

The volume of coal reserves has been calculated by volumetric method.

Volume (mm3) = Area (in sq.km.) x thickness (m) considered.

The seam thickness and grade between various borehole points have been

extrapolated and depicted by drawing isochores & isogrades.

SPECIFIC GRAVITY

For the purpose of converting volume of coal into tonnage, specific gravity of

1.40, 1.42, 1.47, 1.52, 1.58, 1.67 and 1.70 has been assumed for grades A, B,

C, D, E, F and G respectively.

COMPUTATION OF COAL RESERVES

The isochore method has been used for estimation of reserves. The following

formula has been used for this purpose:

R= A x Th.x Sp.Gr.

Where R= Gross reserves in million tonnes

A=Area in sq.km.

Th.= Thickness in meter

Sp. gr.= Specific gravity

As stated earlier, a 10% deduction from the gross reserves has been made to

arrive at the net in situ ‘proved’ reserves available in the block.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 74 of 81

METHODOLOGY OF OVERBURDEN ESTIMATION

The following procedure has been adopted for the estimation of overburden in

Amadand OC Block.

A total excavation (iso depth) plan has been prepared at 5m interval after

intersecting the surface contour with the floor contour of Seam LKIIB & LKII (the

lower most workable coal seam) to arrive at the total depth of excavation.

Isochores on I10 basis of the total coal of the seams considered for opencast

mining viz. Seams UKT, UKB,UK, L4,L3T, L3B, L3,MKT, MKB, MKC, LKI,

L1,LKIIT,LKIIB & LKII were intersected with each other to arrive at the

thickness of the total coal present. Isochores of the total coal, thus drawn, in the

respective area of occurrence of the seam(s), were intersected with the iso-

depth lines to arrive at the thickness and volume of total overburden in the

area. Different Coal: OB cut-off ratio lines were accordingly arrived at. The iso-

depth lines at 5m interval and the coal to OB cut-off ratio lines were transferred

onto the seam folio plans.

- The volume of overburden has been estimated by the volumetric method, i.e.

Volume (mm3) = Area (sq. km.) x thickness (m) considered.

- The volume of overburden has been estimated, depth wise and Coal: OB cut-

off ratio-wise.

- To arrive at stripping ratio, the total volume of overburden within the block area

has been divided by the corresponding coal reserves.

Depthwise Overburden and Quarriable ‘Net’ Proved Geological Reserves with

Resultant Stripping Ratio, Amadand OC Block, Sohagpur Coalfield.

Particulars Volume of OB (mm3)

Quarriable Reserves (mt)

Stripping Ratio

Upto 170.0 Depth Line 1706.00 160.57 1:10.62

TOTAL 1706.00 160.57 1:10.62

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 75 of 81

DEPTH OF EXCAVATION

The maximum depth of excavation would be about 152.54m (CMAD-340) which

is found locally in borehole no. CMAD-340 up to the floor of Seam LKIIB due to

topographic high, surface RL of borehole CMAD-340 is 541.05m in the north

western part of the block. However, The coal reserves for all the coal seams viz.

UKT, UKB, UK, L4, L3T, L3B, L3, MKT, MKB, MKC, LKI, L1, LKIIT, LKIIB & LKII

are available within 170.00m average depth of excavation.

4.6.2 DESCRIPTION OF RESERVES

SUMMARY

A total of 160.57 Mt of proved reserves of coal have been estimated in Amadand

OC Block.

These includes 68.27 Mt (42.52%) superior grade coal of (A, B, C) grade and

90.30 Mt (57.48%) coal of inferior grade (D, E, F,G).

Out of the total Net Proved Reserves of 160.57 Mt of coal 6.19% is of ‘A’ Grade,

11.45% is of ‘B’ Grade and the bulk of the reserves, i.e. 24.87% falls under ‘C’

Grade, 23.40% is of ‘D’ Grade, 9.53% is of ‘E’ Grade, 11.53% is of ‘F’ Grade

and 13.03% in ‘G’ Grade. The quarriable reserves falling in the total proved

category are within 170.00m depth. Since the reserves are to be extracted by

opencast method, all the coal seams reserves have been assessed for coal

seams having thickness more than 0.50m (>0.50m), as desired by mine

planners.

NET GEOLOGICAL RESERVES WITHIN THE BLOCK AREA

Seam-wise, Grade-wise ‘Net’ Proved Geological Reserves within Forest and Non-

Forest areas, Amadand OC Block, Sohagpur Coalfield

(Figures in million tones)

COAL SEAM

<---------------------------GRADE---------------------> TOTAL

A B C D E F G

(A) FOREST AREA (0.907 SQ.KM.)

UKT 0.016 0.016

UKB 0.001 0.006 0.007

UK 0.001 0.001

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 76 of 81

COAL SEAM

<---------------------------GRADE---------------------> TOTAL

A B C D E F G

L4 0.006 0.059 0.065

L3T 0.114 0.016 0.009 0.043 0.040 0.222

L3B 0.005 0.019 0.027 0.071 0.122

L3 0.004 0.004

MKT 0.018 0.037 0.050 0.104 0.840 1.049

MKB 0.227 0.301 0.147 0.675

MKC 0.015 0.016 0.030

LKI 0.010 0.071 0.199 0.280

L1 0.001 0.049 0.046 0.000 0.095

LKIIT 0.007 0.007

LKIIB 0.004 0.003 0.001 0.009

LKII 0.005 0.569 0.959 0.393 0.253 0.082 2.261

SUB-TOTAL FOREST AREA

0.006 0.431 1.028 1.198 0.631 0.611 0.938 4.844

(B) NON- FOREST AREA (14.154 SQ.KM.)

UKT 0.970 1.108 0.288 0.018 0.019 2.403

UKB 0.061 0.706 0.681 0.029 0.017 0.121 1.615

UK 0.698 14.488 18.613 3.606 0.712 0.133 38.250

L4 0.241 1.051 0.461 1.753

L3T 0.522 0.547 0.367 0.238 0.139 0.078 1.891

L3B 0.197 0.249 0.434 0.219 1.100

L3 0.136 1.202 2.729 1.660 0.542 0.065 6.335

MKT 0.024 0.062 0.114 0.285 1.785 15.692 17.963

MKB 0.025 2.265 6.090 3.374 0.318 0.096 0.029 12.196

MKC 0.560 2.175 6.175 14.106 3.916 26.931

LKI 0.039 0.428 3.409 3.215 1.202 0.144 0.005 8.444

L1 0.162 0.371 0.701 0.843 0.187 0.046 0.061 2.371

LKIIT 0.464 0.790 1.020 0.977 0.115 3.365

LKIIB 0.681 2.101 0.779 0.124 3.686

LKII 8.254 7.703 7.559 3.100 0.626 0.200 27.442

SUB-TOTAL NON-FOREST AREA

9.926 17.961 38.917 36.383 14.667 17.911 19.980 155.744

TOTAL RESERVE ALL SEAMS

9.932 18.392 39.945 37.581 15.298 18.522 20.917 160.587

Seam-wise, Grade-wise ‘Net’ Proved Geological Proved Reserves for seam thickness between 0.50m to 0.90m, Amadand OC Block, Sohagpur Coalfield

(Figures in million tones)

SEAM -------------------------GRADE-------------------------- TOTAL

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 77 of 81

A B C D E F G

UKT 0.019 0.019

UK 0.003 0.003

L4 0.241 1.056 0.520 1.818

L3T 0.522 0.547 0.364 0.280 0.179 0.078 1.970

L3B 0.202 0.265 0.461 0.290 1.219

L3 0.101 0.004 0.145 0.022 0.000 0.059 0.331

MKT 0.008 0.022 0.030

MKB 0.023 0.294 0.025 0.045 0.118 0.505

LKI 0.039 0.428 3.333 0.444 0.261 0.236 0.005 4.747

L1 0.162 0.419 0.260 0.331 0.058 0.046 0.061 1.338

LKIIT 0.114 0.092 0.010 0.157 0.014 0.386

LKIIB 0.162 0.128 0.291

LKII 0.000 0.000

TOTAL 0.740 3.243 4.972 1.972 1.044 0.481 0.204 12.657

Since Amadand block reserves are to be extracted by opencast method, as

desired by Mine Planners, the reserves have been assessed for seam thickness

between 0.50m to 0.90m.

Seam-wise, Thickness-wise, Grade-wise ‘Net’ Proved Geological Reserves, Amadand OC Block, Sohgpur Coalfield

(Figures in millon tonnes)

Seam

Thick.Range (m)

--------------GRADE--------- TOTAL

A B C D E F G

UKT INCROP 0.238 0.238

UKT 0.5-0.9 0.019 0.019

UKT 1.2-1.5 0.018 0.018

UKT 1.5-2.0 0.099 0.823 0.288 1.210

UKT 2.0-2.5 0.887 0.047 0.934

SUB TOTAL 0.986 1.108 0.288 0.018 0.019 2.419

UKB INCROP 0.266 0.266

UKB 0.9-1.2 0.062 0.712 0.293 0.017 0.121 1.205

UKB 1.2-1.5 0.122 0.022 0.144

UKB 2.0-2.5 0.008 0.008

SUB TOTAL 0.062 0.712 0.681 0.029 0.017 0.121 1.622

UK INCROP 0.275 0.275

UK 0.5-0.9 0.003 0.003

UK 0.9-1.2 0.009 0.009

UK 1.5-2.0 0.015 0.021 0.035

UK 2.5-3.0 0.067 0.056 0.008 0.158 0.028 0.317

UK >3.00 0.631 14.418 18.307 3.448 0.675 0.133 37.611

SUB TOTAL 0.698 14.488 18.614 3.606 0.712 0.133 38.250

L4 0.5-0.9 0.241 1.056 0.520 1.818

SUB TOTAL 0.241 1.056 0.520 1.818

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 78 of 81

Seam

Thick.Range (m)

--------------GRADE--------- TOTAL

A B C D E F G

L3T INCROP 0.003 0.003

L3T 0.5-0.9 0.522 0.547 0.364 0.280 0.179 0.078 1.970

L3T 0.9-1.2 0.114 0.016 0.009 0.140

SUB TOTAL 0.636 0.563 0.376 0.280 0.179 0.078 2.113

L3B INCROP 0.003 0.003

L3B 0.5-0.9 0.202 0.265 0.461 0.290 1.219

SUB TOTAL 0.202 0.268 0.461 0.290 1.222

L3 INCROP 0.020 0.020

L3 0.5-0.9 0.101 0.004 0.145 0.022 0.000 0.059 0.331

L3 0.9-1.2 0.024 0.472 0.746 1.335 0.459 3.036

L3 1.2-1.5 0.726 0.851 0.307 0.056 0.006 1.947

L3 1.5-2.0 0.011 0.967 0.027 1.005

SUB TOTAL 0.136 1.202 2.729 1.664 0.542 0.065 6.339

MKT INCROP 0.002 0.002

MKT 0.5-0.9 0.008 0.022 0.030

MKT 0.9-1.2 0.024 0.020 0.031 0.110 0.184

MKT 1.2-1.5 0.053 0.073 0.140 0.796 0.472 1.533

MKT 1.5-2.0 0.057 0.195 1.062 5.589 6.903

MKT 2.0-2.5 0.001 10.359 10.360

SUB TOTAL 0.024 0.080 0.152 0.335 1.890 16.532 19.012

MKB INCROP 0.020 0.020

MKB 0.5-0.9 0.023 0.294 0.025 0.045 0.118 0.505

MKB 0.9-1.2 0.623 0.515 0.425 0.200 0.029 1.791

MKB 1.2-1.5 1.219 4.739 2.995 0.096 9.049

MKB 1.5-2.0 0.002 0.350 1.067 0.056 1.475

MKB 2.0-2.5 0.006 0.024 0.031

SUB TOTAL 0.025 2.492 6.391 3.521 0.318 0.096 0.029 12.871

MKC 0.9-1.2 0.003 0.003

MKC 1.5-2.0 0.004 0.014 0.018

MKC 2.0-2.5 0.560 0.031 0.591

MKC 2.5-3.0 2.031 2.031

MKC >3.00 0.144 6.144 14.113 3.917 24.318

SUB TOTAL 0.560 2.175 6.175 14.120 3.931 26.961

LKI 0.5-0.9 0.039 0.428 3.333 0.444 0.261 0.236 0.005 4.747

LKI 0.9-1.2 0.034 2.772 1.013 3.818

LKI 1.2-1.5 0.043 0.010 0.107 0.159

LKI >3.00 0.001 0.001

SUB TOTAL 0.039 0.428 3.409 3.225 1.274 0.343 0.005 8.725

L1 0.5-0.9 0.162 0.419 0.260 0.331 0.058 0.046 0.061 1.338

L1 0.9-1.2 0.486 0.451 0.033 0.970

L1 1.2-1.5 0.061 0.061

L1 1.5-2.0 0.096 0.096

SUB TOTAL 0.162 0.419 0.746 0.843 0.187 0.046 0.061 2.465

LKIIT 0.5-0.9 0.114 0.092 0.010 0.157 0.014 0.386

LKIIT 0.9-1.2 0.351 0.695 1.010 0.827 0.101 2.984

LKIIT 1.2-1.5 0.002 0.002

SUB TOTAL 0.464 0.790 1.020 0.984 0.115 3.372

LKIIB 0.5-0.9 0.162 0.128 0.291

LKIIB 0.9-1.2 0.004 0.099 0.104

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 79 of 81

Seam

Thick.Range (m)

--------------GRADE--------- TOTAL

A B C D E F G

LKIIB 1.2-1.5 0.003 0.681 0.124 0.808

LKIIB 1.5-2.0 0.519 1.873 2.392

LKIIB 2.0-2.5 0.099 0.099

SUB TOTAL 0.685 2.104 0.781 0.124 3.695

LKII 0.5-0.9 0.000 0.000

LKII 0.9-1.2 0.032 0.032

LKII 1.2-1.5 0.009 0.294 0.007 0.200 0.082 0.592

LKII 1.5-2.0 5.366 3.422 1.986 1.359 0.561 12.693

LKII 2.0-2.5 2.879 3.960 0.945 0.211 0.253 8.248

LKII 2.5-3.0 5.196 0.451 5.648

LKII >3.00 2.489 2.489

SUB TOTAL 8.254 7.709 8.128 4.059 1.019 0.453 0.082 29.703

GRAND TOTAL 9.932 18.392 39.945 37.581 15.298 18.522 20.917 160.587

4.6.3 GEOLOGICAL LOSSES / SURFACE CONSTRAINTS

COAL RESERVES UNDER SURFACE CONSTRAINTS

The distribution of opencast reserves in the block under various surface

constraints is given in table.

Seam-wise ‘Net’ Proved Geological Reserves within different areas, Amadand OC Block, Sohagpur Coalfield

(Figures in million tones)

SEAM PROVED RESERVES

TOTAL INCROP FREE BLOCKED

UKT 0.238 1.879 0.302 2.419

UKB 0.266 1.181 0.176 1.622

UK 0.275 29.211 8.765 38.250

L4 1.515 0.303 1.818

L3T 0.003 1.576 0.534 2.113

L3B 0.003 0.932 0.287 1.222

L3 0.020 4.656 1.663 6.339

MKT 0.002 13.996 5.014 19.012

MKB 0.020 9.048 3.803 12.871

MKC 24.432 2.530 26.961

LKI 7.557 1.167 8.724

L1 1.681 0.785 2.466

LKIIT 3.055 0.318 3.372

LKIIB 3.381 0.314 3.695

LKII 22.359 7.344 29.703

TOTAL 0.826 126.458 33.304 160.587

% 0.515 78.747 20.739 100.000

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 80 of 81

NET GEOLOGICAL RESERVES WITHIN THE BLOCK AREA

Seam-wise, Grade-wise ‘Net’ Proved Geological Reserves within Forest and Non-Forest areas, Amadand OC Block, Sohagpur Coalfield

(Figures in million tones)

Coal seams

<----------------------GRADE-----------------------> TOTAL A B C D E F G

UKT 0.986 1.108 0.288 0.018 0.019 2.419

UKB 0.062 0.712 0.681 0.029 0.017 0.121 1.622

UK 0.698 14.488 18.614 3.606 0.712 0.133 38.250

L4 0.241 1.056 0.520 1.818

L3T 0.636 0.563 0.376 0.280 0.179 0.078 2.113

L3B 0.202 0.268 0.461 0.290 1.222

L3 0.136 1.202 2.729 1.664 0.542 0.065 6.339

MKT 0.024 0.080 0.152 0.335 1.890 16.532 19.012

MKB 0.025 2.492 6.391 3.521 0.318 0.096 0.029 12.871

MKC 0.560 2.175 6.175 14.120 3.931 26.961

LKI 0.039 0.428 3.409 3.225 1.274 0.343 0.005 8.724

L1 0.162 0.419 0.746 0.843 0.187 0.046 0.061 2.466

LKIIT 0.464 0.790 1.020 0.984 0.115 3.372

LKIIB 0.685 2.104 0.781 0.124 3.695

LKII 8.254 7.709 8.128 4.059 1.019 0.453 0.082 29.703

GRAND TOTAL

9.932 18.392 39.945 37.581 15.298 18.522 20.917 160.587

% 6.19 11.45 24.87 23.40 9.53 11.53 13.03 100.000

4.7 RECOMMENDATION 1. The reserves estimated and geological interpretation made could be regarded as

fairly accurate within the limits of available data. A few boreholes along

proposed entry alignment are recommended to ascertain the point of disposition

of the coal seams and incrops.

2. Although not a single fault has been delineated in the block, but possibility of

some minor slips of small magnitude may not be ruled out.

3. Though the incrops have been proved on the basis of boreholes drilled, few

boreholes may be taken up, if suggested by the Planners in view of the

variable/rolling nature of the dips.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 4 / 81 of 81

4.7.1 Mining & Utilization

The coals available in Amadand OC Block are low to high moisture, low to

medium ash, low rank, non-coking coals of major part inferior in quality D, E, F & G

92.03mt ( 57.58%) and minor part superior in quality A, B & C 68.27 mt (42.52%). The

seam-wise quality is given in Table below.

Quality of Coal Seams (I100 basis) Coal

Seam/ Section

At 60% RH & 40oC UHV (K. cal./ kg.)

Grade Dominant Grade M% A%

Min. Max. Min. Max. Min. Max.

UKT 5.0 14.1 10.8 39.6 2606 6043 F-B C

UKB 3.8 10.5 10.4 38.1 2895 6330 F-A C

UK 4.6 11.0 14.9 49.2 1420 5781 G-B D

L4 7.5 10.3 9.7 19.3 5128 6319 C-A B

L3T 4.7 7.6 12.2 43.0 2320 6159 G-B D

L3B 6.5 8.7 12.2 32.5 3521 6015 E-B C

L3 5.0 8.7 12.3 44.7 2045 6041 G-B D

MKT 4.2 8.9 14.1 50.2 1332 5933 G-B G

MKB 4.1 9.1 9.1 70.6 1127 6448 UG-A C

MKC 4.5 9.1 15.5 49.8 1089 5546 UG-C F

LKI 4.8 9.7 5.2 47.9 1630 6872 F-A D

L1 4.5 8.7 8.7 48.6 1157 6504 G-A C

LKIIT 5.8 9.4 5.5 34.3 3373 6943 E-A C

LKIIB 5.6 9.2 7.6 31.4 3739 6761 E-A B

LKII 3.9 9.7 5.3 51.0 1130 7133 UG-A B

The coals of medium ash, non-coking coals especially of inferior grade from

seams UKT, UKB, UK, L4, L3T, L3B, L3, MKB, MKC, LKI, L1, LKIIT, LKIIB & LKII can

be of use in the thermal power, fertilizer, refractory, ceramic and cement industries and

coal liquefaction process.

*******

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 5 / 1 of 5

CHAPTER - V

MINE BOUNDARY, RESERVES AND MINE LIFE

5.1 INTRODUCTION

The Amadand Opencast Block is located in the eastern part of south

Sohagpur Coalfield and is flanked by working mines of Hasdeo and Jamuna

& Kotma areas of SECL to the east and west respectively.

Project Report for Amadand OC (1.15 Mty) was prepared with an average

stripping ratio of 4.58 cum/t considering only upper seam i.e UK seam and

submitted to SECL in August 2003 and approved in Sept 2003. During

preparation of Amadand OC (1.15 Mty) report, lower seams e.g. MK (Top)

and MK (Bottom) and LK-II were also considered for extraction by opencast

method. But, due to high stripping ratio, the quarriability of lower seam were

not feasible for departmental option. So seams below UK seam were not

considered in the 1.15 Mty PR.

Latter on, decisions was taken to extract coal from bottom seams.

Accordingly, Revised Geological Report have been prepared, considering

workable coal seams upto bottom most LK-II seam which has not taken into

account for opencast mining earlier. In the area under consideration seams,

L-6, L-5, UK (Top), UK (Bottom), UK, L-4, L-3(Top), L-3 (Bottom), L-3, MK

(Top), MK (Bottom), MKC, L-2, LK-I, L-1, LK-II (Top), LK-II (Bottom) & LK-II

have encountered in descending order.

The present report is formulated considering all the seams upto bottom

most LK-II seam for mining with outsourcing option.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 5 / 2 of 5

5.2 PIT FORMULATION STRATEGY

It is proposed to extract all the seams UK (Top), UK (Bottom), UK, L-4, L-

3(Top), L-3 (Bottom), L-3, MK (Top), MK (Bottom), MKC, L-2, LK-I, L-1, LK-

II (Top), LK-II (Bottom) & LK-II as they can be mined techno-economically

by opencast method. Quarry floor has been proposed on the floor of Seam-

LK-II. Access trench & Haul Road is proposed to touch seam LK-II at floor

RL of 420m. Haul roads have been planned at a maximum gradient of 1 in

16, the width of the haul road has been kept as 30 m for two way dumpers

movement.

This PR has been formulated mainly considering the following details:-

1. Increased demand of superior grade coal from CIC Coalfields.

2. Sufficient mineable reserves

3. Workable strike and dip length

5.3 MINE BOUNDARIES

The quarriable area for the opencast mining is shown on Plate No.3 &

Figure-5.1. One quarry on floor of Seam LK-II has been planned. The

boundary of quarry has been fixed as follows: -

North : Incrop of Upper Kotma Seam.

Reason- Beyond UK seam incrop the stripping ratio is high

(more than 20).

South : Incrop of Upper Kotma Seam.

Reason- Beyond UK seam incrop the stripping ratio is

high (more than 20).

East : A line keeping 100 m barrier from boundary of Amadand

Village.

Reason-. The major state highway Pendra to Manendragarh

is passing along the middle of the Amadand Village. Two UG

mines namely, Amadand UG & Bartarai UG are situated on

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 5 / 3 of 5

other side of the Pendra-Manendragarh state highway road

and area of these mines are not included within quarry

boundary of this 4.0 Mty RPR Report.

West : Incrop of Upper Kotma Seam

Reason- Beyond UK seam incrop the stripping ratio is high

(more than 20).

Khodri Block has not been included in the proposed mine area. The

incrop of coal seams also exists in the northern side of Khodri Block.

Thus, Khodri Block can be extracted from the northern side of the block as

a separate mine.

5.4 MINEABLE RESERVES

As on 01.04.2015, the total mineable reserves within the quarries have

been estimated as 70.46 Mt with a corresponding OB volume of 764.40

Mcum. The already extracted coal & OB removal has been deducted to

get the balance remaining coal & OB quantity. While, calculating mineable

reserves, a geological loss of 10% and a mining loss of 10% have been

considered. The estimation of mineable reserves is based on a minimum

mineable thickness of 0.5 m. The mineable reserves have been estimated

by iso-chore method from the seam extent plan of individual seams.

Similarly, OB has been estimated based on iso-parting and Top OB plan.

The plan showing seam extent of individual seams under consideration

are given at Plate No. 6 to 16. The top OB and the iso-parting plan

between seams under consideration are given at Plate No. 17 to 27.

5.5 TARGET OUTPUT & MINE LIFE

The mine is proposed for peak coal production of 4.00 Mty and peak OB

removal is of 52.54 Mty.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 5 / 4 of 5

Mine Life The mine life for nominal production is 19 years. The break-up is as under:

Production build-up period - 3 years

Production period - 15 years

Tapering period - 1 year

Total period - 19 years

5.6 FUTURE EXPANSION POTENTIAL It is proposed to extract upto the bottom most seam LK-II of the area.

Thus, mine does not have the scope to expand further in vertical direction.

In northern side, Khodri Block has not been included in the proposed mine

area. There is high stripping ratio zone(more than 20) between present

quarry boundary and Khodri block boundary. The incrop of coal seams

also exists in the northern side of Khodri Block. Thus, Khodri Block can be

extracted from the northern side of the block as a separate mine. In

western and southern side, beyond UK seam incrop, the stripping ratio

is high (more than 20). Thus, mine does not have the scope to expand

further under the present condition to north, south and west directions.

In eastern side, the quarry boundary fixed along a line keeping 100 m

barrier from boundary of Amadand Village. The state highway Pendra to

Manendragarh is passing along the middle of the Amadand Village. Two

UG mines namely, Amadand UG & Bartarai UG are situated on other side

of the Pendra-Manendragarh state highway road and area of these mines

are not included within quarry boundary of this 4.0 Mty RPR Report. In

future, if diversion of major state highway Pendra to Manendragarh can be

undertaken, decisions taken to extract UG property by opencast method

and shifting of Amadand village can be undertaken, in that case the

Amadand OC can be expanded in the east direction. Quarry planning and

dump plan has been proposed accordingly such that quarry can be

expanded in east directions in future.

RP

R fo

r Am

adand O

CP

(4.0

Mty

) (Update

d J

uly

’ 2015) C

MP

DI

. . JO

B N

O.-515126 C

hapter 5 / 5 of 5 5

.7

SE

CT

OR

& M

INE

AB

LE

RE

SE

RV

ES

The

se

cto

rwis

e q

ua

rry w

ise m

ine

ab

le re

se

rve

s, v

olu

me

of O

BR

and

strip

pin

g ra

tio a

re s

um

ma

rise

d in

the

follo

win

g ta

ble

: -

CO

AL

S

EA

MS

T

OT

AL

U

K&

UK

T

UK

B

L4

L3&

L3T

L

3B

M

K&

MK

T

MK

B

LK

1

L1

LK

2&

LK

2T

L

K2B

SE

C-1

2.8

9

2.8

9

SE

C-2

16.5

1

3.0

1

0.0

5

0.0

5

1.2

7

0.2

6

6.1

9

1.2

0

0.9

8

0.3

0

3.2

0

SE

C-3

8.1

8

2.8

9

0.2

3

0.0

1

2.7

3

0.4

3

0.1

1

1.7

8

SE

C-4

7.8

3

2.8

6

0.0

1

0.0

1

0.1

8

0.0

5

2.4

9

0.3

8

0.1

2

1.6

7

0.0

6

SE

C-5

7.5

7

2.8

4

0.0

7

0.0

1

0.1

6

0.0

5

2.4

1

0.0

6

0.2

9

0.0

5

1.4

6

0.1

7

SE

C-6

7.4

3

2.6

8

0.0

2

0.0

8

0.1

0

0.0

2

2.4

5

0.0

6

0.4

7

0.0

3

1.2

6

0.2

6

SE

C-7

6.6

9

2.3

2

0.0

1

0.0

6

0.0

7

0.0

1

1.9

8

0.0

4

0.5

2

0.1

0

1.0

0

0.5

8

SE

C-8

5.3

4

1.3

1

0.2

5

0.1

5

0.0

4

0.0

1

1.4

7

0.1

3

0.4

4

0.1

2

0.7

5

0.6

7

SE

C-9

4.6

8

0.7

2

0.3

3

0.2

3

0.0

4

0.0

1

1.4

1

0.1

6

0.4

8

0.2

6

0.5

8

0.4

6

SE

C-1

0

3.3

4

0.3

3

0.0

6

0.1

8

0.0

1

0.0

1

0.9

1

0.2

1

0.4

8

0.0

4

0.6

1

0.5

0

TO

TA

L

70.4

6

21.8

5

0.8

0

0.7

7

2.1

0

0.4

3

22.0

4

1.8

6

4.4

7

1.1

3

12.3

1

2.7

0

PA

RT

ING

S

TO

TA

L

TO

P O

B

UK

T-

UK

B

UK

B-L

4

L4-

L3&

L3T

L

3T

-L

3B

L

3B

-M

K&

MK

T

MK

T-

MK

B

MK

B-

LK

1

LK

1-

L1

L1-L

K2

&

LK

2T

L

K2T

-L

K2B

SE

C-1

29.9

0

29.9

SE

C-2

216.8

8

17.6

4

0.1

3

59.5

2

37.4

6

1.4

10.1

1

3.4

6

49.2

2

30.8

9

7.0

5

SE

C-3

80.5

5

17.9

6

14

11.3

9

0.7

6

3.3

0.0

1

17.2

1

13.6

2.3

2

SE

C-4

80.0

0

17.6

4

12.2

9

12.7

9

1

3.2

9

17.5

6

12.9

8

2.4

2

0.0

3

SE

C-5

77.3

9

16.5

1

0.0

9

11.6

1

12.3

6

0.7

6

4.0

8

0.0

4

16.5

9

13.2

9

1.9

3

0.1

3

SE

C-6

74.9

6

15.1

3

0.0

3

11.2

1

11.7

6

0.9

6

4.7

0.0

4

15.7

8

13.6

1

1.5

9

0.1

5

SE

C-7

68.8

4

12.3

3

0.1

11.2

3

10.4

3

1.0

2

4.1

5

0.0

7

14.8

8

11.4

4

2.8

4

0.3

5

SE

C-8

59.4

3

9.5

3

0.3

9.0

9

9.5

1

0.8

1

3.3

7

0.2

5

13.2

4

10.8

3

2.3

0.2

SE

C-9

44.9

9

5.8

1

0.4

5

7.7

1

6.0

8

0.8

5

2.1

1

0.2

4

10.4

7

8.6

7

2.1

4

0.4

6

SE

C-1

0

31.4

6

1.6

0.0

8

3.4

4

4.5

8

0.8

9

1.2

9

0.3

4

8.8

8.6

5

0.8

5

0.9

4

TO

TA

L

764.4

0

144.0

5

1.1

8

140.1

0

116.3

6

8.4

5

36.4

0

4.4

5

163.7

5

123.9

6

23.4

4

2.2

6

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 6 / 1 of 9

CHAPTER-VI

METHOD OF MINING

6.1 GENERAL The PR has been formulated to win coal by Surface Miner with FEL and

coal body trucks & OB by Shovel Dumper combination.

In Outsourcing Option both winning of coal and extraction of OBR will be

done through outsourced HEMM. Transport of coal from face to railway

siding will be done by inpit belt conveyor & surface belt conveyor.

It is proposed that mine will be operated for 330 days in a year. In a day,

there will be 3 shifts and each shift is of 8 hours.

6.2 GEO-MINING CHARACTERISTICS

6.2.1 Seam Gradient - Variation, average gradient of quarry floor 1 in 30.

6.2.2 Geological Disturbances -

Only one normal fault F1F1, trending E-W and having a maximum throw of

80m, have been deciphered in the area at the northern boundary of block.

Within mine area no fault exists. However, the occurrence of faults of

small lesser magnitude cannot be entirely ruled out in the area.

6.2.3 Presence of In-seam band seam-wise The in-seam of all the seams is composed mainly of carbshale, shale,

sandy shale and sandstone.

6.2.4 Details of sequence of coal seam and parting

The sequence of coal seams with their thickness and parting range,

average grade & UHV range, Mineable coal and volume of OB within the

proposed mine area are as shown in table below:-

Coal Seam Name/Parting

Thickness range(m) Generalised thickness range(m)

Remarks

From To

Seam-L6 0.09 (CMAD-69)

1.37 (CMAD-512)

0.15-0.55 Not considered

Parting 4.11 (CMAD-340)

11.56 (CMAD-271)

5.00-7.00

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 6 / 2 of 9

Coal Seam Name/Parting

Thickness range(m) Generalised thickness range(m)

Remarks

From To

Seam-L5 0.05 (CMAD-15)

0.88 (CMAD-36)

0.10 - 0.30 Not Considered

Parting 0.60 (CMAD-271)

4.39 (CMAD-35)

1.00-3.00

Seam-UKTOP 0.30 (CMAD-63)

2.80 (CMAD-521)

0.80-1.65 Considered workable.

Parting 1.03 (CMAD-317)

5.41 (AMD-2)

1.00-3.00

Seam-UKBOT 0.24 (CMAD-133)

2.26 (CMAD-62)

0.40-1.00 Considered workable.

Parting with L4 9.95 (CMAD-152)

22.25 (CMAD-36)

10.0-17.0

Seam-UK 0.45 (CMAD-51)

6.87 (CMAD-325)

0.80-4.00 Considered workable.

Parting with L4 8.74 (CMAD-8)

28.65 (CMAD-12)

8.00-18.00

Seam-L4 0.05 (CMAD-172)

1.73 (CMAD-112)

0.10-0.40 Considered workable.

Parting 13.35 (CMAD-45)

27.05 (AMD-9)

10.00-20.00

Seam-L3T 0.08 (CMAD-48)

1.25 (CMAD-148)

0.10-0.60 Considered workable.

Parting 1.01 (CMAD-144)

6.88 (CMAD-63)

1.00-4.50

Seam-L3B 0.10 (CMAD-315)

0.90 (CMAD-167)

0.15-0.55 Considered workable.

Parting with MKTOP

1.46 (CMAD-30)

11.91 (CMAD-94)

1.50-8.00

Seam-L3 0.25 (CMAD-34)

3.80 (CMAD-168)

0.30-1.50 Considered workable.

Parting with MKTOP

1.25 (CMAD-60)

6.08 (AMD-6)

1.50-4.00

MKTOP 0.15 (CMAD-257)

3.46 (CMAD-172)

0.25-1.70 Considered workable.

Parting 0.94 (CMAD-91)

16.23 (AMD-2)

1.00-6.75

MKBOT 0.21 (CMAD-86)

2.74 (CMAD-69)

0.30-1.25 Considered workable.

Parting with L2 2.85 (AMD-9)

27.55 (CMAD-21)

3.50-19.00

MKC 0.53 (CMAD-50)

6.18 (CMAD-54)

0.70-4.00 Considered workable.

Parting 12.00 (CMAD-340)

29.45 (CMAD-47)

13.50-23.00

L2 0.02 (CMAD-45)

0.71 (CMAD-111,51)

0.05-0.30 Not considered

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 6 / 3 of 9

Coal Seam Name/Parting

Thickness range(m) Generalised thickness range(m)

Remarks

From To

Parting 1.55 (CMAD-30)

13.78 (CMAD-340)

LK1 0.05 (CMAD-175,

62)

1.96 (CMAD-340)

0.10-0.80 Considered workable.

Parting 10.40 (CMAD-245)

32.16 (CMAD-175)

11.00-19.00

L1 0.10 (CMAD-128)

2.57 (CMAD-41)

0.15-0.80 Considered workable.

Parting 2.11 (CMAD-44)

31.47 (CMAD-186)

3.00-25.00

LKIITOP 0.33 (CMAD-95)

2.76 (CMAD-118)

0.40-1.00 Considered workable.

Parting 1.05 (CMAD-270)

4.21 (CMAD-54)

LKIIBOT 0.10 (AMD-23)

2.68 (CMAD-53)

0.18-1.20 Considered workable.

LKII 0.24 (AMD-264)

5.62 (CMAD-46)

0.30-2.25 Considered workable.

6.3 MINE PARAMETERS

The geological and mining characteristics of both the quarries have been

summarised in the following table: -

Geological and Mining Characteristics

Sl. No.

Particulars Unit Quantity

I. Coal Seams

1 Dominant Thickness of Seams

UK Top m 0.80-1.65

UK Bottom m 0.50-1.00

UK (Comb) m 0.80-4.00

L-4 m 0.50-0.60

L-3 Top m 0.50-0.60

L-3 Bottom m 0.50-0.60

L-3 (Comb) m 0.50-1.50

MK Top m 0.50-1.70

MK Bottom m 0.50-1.25

MK (Comb) m 0.70-4.00

LK-1 m 0.50-0.80

L-1 m 0.50-0.80

LK-2 Top m 0.50-1.00

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 6 / 4 of 9

Sl. No.

Particulars Unit Quantity

LK-2 Bottom m 0.50-1.20

LK-2 (Comb) m 0.50-2.25

Average Dip Degree 1 in 30

2 Av. Specific gravity of coal in seams t/cum 1.52

II. Overburden / partings

3 Dominant Thickness

Top OB m 20.00-40.00

Between UK Top & UK Bottom m 1.00-3.00

Between UK Bottom, UK & L-4 m 10.00-18.00

Between L-4 & L-3 m 10.00-20.00

Between L-3 Top & L-3 Bottom m 1.00-4.50

Between L-3 & MK Top m 1.50-8.00

Between MK Top & MK Bottom m 1.00-6.75

Between MK & LK-1 m 15.00-35.00

Between LK-1 & L-1 m 11.00-19.00

Between L-1 & LK-2 Top m 3.00-25.00

Between LK-2 Top & LK-2 Bottom m 1.00-4.00

4 Seamwise Mineable Reserves

UK Top & UK Comb Mt 21.85

UK Bottom Mt 0.80

L-4 Mt 0.77

L-3 Top & L-3 Comb Mt 2.10

L-3 Bottom Mt 0.42

MK Top & Bottom Mt 22.04

MK Bottom Mt 1.86

LK-1 Mt 4.47

L-1 Mt 1.13

LK-2 Top & LK-2 Comb Mt 12.31

LK-2 Bottom Mt 2.70

Total (as on 01.04.2015) Mt 70.46

5 Av. Specific Gravity of OB t/cum 2.40

6 Volume of OB (as on 01.04.2015) Mcum 764.40

7 Stripping Ratio (Av.) cum/t 10.85

8 Target Output Mt/Yr. 4.0

9 Peak OBR Mcum/yr. 52.54

10 Project life Year 19

III. Quarry Parameters

1 Maximum width along strike

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 6 / 5 of 9

Sl. No.

Particulars Unit Quantity

- at surface m 3220

- at floor m 2880

2 Minimum width along strike

- at surface m 2560

- at floor m 1890

3 Maximum length along dip

- at surface m 2600

- at floor m 2250

4 Maximum depth m 152.50

5 Minimum depth m 120

6 Maximum lift m 158

7 Area of excavation

- at surface Ha 694.80

- at floor Ha 515.35

.CHOICE OF TECHNOLOGY

Surface miner has been proposed for extraction of coal. The salient

feature of the mining system is as follows: -

(i) Height & width of the benches in OB will depend upon the size

of the leased equipment. However, for Surface Miner height

restriction is not there. The provision of Coal Mine Regulation

and related circulars shall be strictly followed for designing

bench parameters in coal and OB.

(ii) Dump bench height - 30m (Internal dump has 7 benches and

total dump height 230 m from quarry floor & 90m from surface,

External dump height is 120m from surface).

(iii) Bench Slope

Coal / OB - 700

Spoil - 370

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 6 / 6 of 9

Considering the average mine floor gradient of about 1 in 30, the coal

benches are proposed parallel to seam floor and self-draining. The mining

system is shown at Plate No. 6.

DRILLING & BLASTING

Pattern for drilling of blast holes will depend upon the height of the bench

and may design as follows: -

Height of Bench = H

Burden (B) ~ H/2

Spacing (S) ~ B*1.25

The suggested drilling pattern is for average mining conditions. These

may be suitably modified during actual mining operations as per the site

conditions.

HAUL ROAD

Haul roads have been planned at a maximum gradient of 1 in 16, the

width of the haul road has been kept as 30 m for two way dumpers

transport. Two batter road of 50m width will be maintained along UK seam

& MK seam for laying side road and inpit belt conveyor. (details given in

chapter 11)

6.5 EQUIPMENT SELECTION

The PR has been formulated to win coal by Surface Miner with FEL and

coal body trucks & OB by Shovel Dumper combination.

In Outsourcing Option both winning of coal and extraction of OBR will be

done through outsourced HEMM. Few auxiliary HEMM has been given for

mine development and reclamation related work. Transport of coal from

face to railway siding will be done by inpit belt conveyor & surface belt

conveyor. To handle the larger OB quantity optimum no. of equipment with

required capacity is proposed be used. Minimum 10 cum Shovels with

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 6 / 7 of 9

100T rear dumpers will be used for OBR by outsourcing agency. For thin

partings, smaller backhoe may be used.

As depth of OB increases the annual OB removal will also increased. To

handle the larger OB quantity optimum no. of equipment with required

capacity is proposed be used. Due to flexibility of operation, Shovel-

Dumper combination will be suitable for OB removal for working multiple

seams and partings.

The property is free from any major geological disturbances. Average

gradient of quarry floor is 1 in 30. The average strike length of the quarry

is 3.0 km. Thus, sufficient face length will be available for optimum

efficiency of surface miner.

The bottom most seams LK-2 have been splitted into LK-2 Top and LK-2

Bottom. Both of the splits have varying thickness from 0.7 m to 1.50m.

Above LK-2 Seam, Seam L-1 exists having seam thickness 0.70m to

0.90m. Parting thickness between Seam LK-2 and L-1 varies 6 m to 18 m.

Thus, dragline horizon changing will be required for operation of dragline

and dragline productivity will be less. Besides, the bottom coal bench may

be diluted as low thickness coal seam may be mixed with OB during

dragline operation. Considering multi-seam working and wide variation of

parting OB, dragline has not been proposed in this Project Report.

6.6 MINING SYSTEM & SYSTEM PARAMETERS

Surface miner has been proposed for extraction of coal.

The salient features of mining system are as follows:-

i) Height of bench in OB will depend on the size of equipment.

Coal bench height will depend on the thickness of the coal seams.

The provision of coal mine regulations and related circulars shall be

strictly followed for designing bench parameters in coal and OB.

ii) Average Seam gradient – 1 in 30.

iii) Total dump height – Internal dump height is 230 m from quarry floor

but it will be 90m from surface. External dump height is 120m from

surface.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 6 / 8 of 9

iv) Bench slope –

Coal/OB - 70 degree

Spoil - 37 degree

Keeping the geo-mining characteristics of the deposit, in view, optimum

number of equipment with optimum capacity is proposed be used.

6.7 SCOPE OF WORK PROPOSED TO BE OUTSOURCED i) Drilling

The external agency will prepare the site and carry out blast hole

drilling as per the pattern decided by the project authorities according

to strata conditions and stipulations of DGMS

ii) Coal cutting by surface miner

Surface miner has been proposed for extraction of coal. The external

agency will prepare the site decided by the project authorities

according to strata conditions and stipulations of DGMS for working of

surface miner.

iii) Loading and Transportation of coal

The work involves loading and transportation of coal to dumping site

as per guidelines of the project authorities or otherwise to suit local

conditions. All activities involving the loading and transportation have

been proposed to be done by outside agencies. All statutory rules ,

regulation and applicable laws are to be followed including those

related to Govt. licenses, workmen compensation , insurance etc. by

the agency to whom the job has been awarded. Coal has to be

transported to and from the site as decided by the project authorities

from time to time in accordance with the requirement of the project.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 6 / 9 of 9

iv) OB Removal

The work involves excavation of OB and dumping of the same to

different dump locations. This includes construction and maintenance

of haul roads for plying of dumpers/tippers with suitable number of

graders and dozers. The leveling of the dumps is to be carried out by

the agency to which the work has been awarded for OB removal.

The site of excavation and dumping is to be decided by the project

authorities in accordance with the requirement of the project. All

statutory rules, regulation and applicable laws are to be followed

including those related to Govt. licenses, workmen compensation,

insurance etc. by the agency to whom the job has been awarded.

v) Accommodation, Site Office, Electricity etc.

Site office may be provided by the company on availability basis,

which will be chargeable. Electricity to the site office may be provided

on chargeable basis.

*******

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 7 / 1 of 8

CHAPTER-VII

MINING & DUMPING STRATEGY

7.1 CONSTRAINTS ON MINE DEVELOPMENT (i) The nearest railway siding is Govinda Railway siding which is

situated at a distance of about 5.0Km from the mine. The railway

line extension from Bhaiyatola station is required to connect the

upcoming Amadand siding.

(ii) Rehabilitation & resettlement of four villages namely Nimha,

Timkitola-Amadand, Harratola-Kuhka and Majholi are involved in

the project. Acquisition of land alongwith R&R of PAP is a critical

activity and should be taken up on top priority.

7.2 MINING STRATEGY / MINING SEQUENCE

At present Amadand OC is a running mine with a peak coal production of

1.15Mty and it is already extracting coal from UK seam.

It is proposed to expose MK seam in the 2nd year of mine operation by

grading properly the access trench and making its width 30 m wide and

gradient at 1 in 16. Then sufficient area to be exposed in the MK seam

floor. In the 3rd year of mine operation, the access trench is to be graded

at 1 in 16 to touch the mine floor at LKII seam of about 405 m R.L.

The quarry floor is developed in such a manner so as to facilitate

the proper drainage of water towards the sump. This would also facilitate

extension of coal and OB bench for full development of mine. After

creation of sufficient decoaled area, internal backfilling of OB will be

started in the 5th year. The coal production will continue from the 1st year

of mine life and the target coal production of 4.00 Mty will be achieved in

the 5th year.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 7 / 2 of 8

Two batter road of 50m width will be maintained along eastern side

batter. One batter road along floor of UK seam will be used to place inpit

belt conveyor to carry coal from UK & L4 seam as thown in plate 3. Other

batter road along floor of MK seam will be used to place inpit belt

conveyor to carry coal from MK, L3 & LK1 seam. One another inclined

inpit belt conveyor will be placed upto floor of LKII seam to carry coal from

LKII & L1 seam. Finally, through inclined belt conveyor all the coal will be

transported to surface as shown in the plate-3. From pit top coal will be

transported to upcoming Amadand siding through surface belt conveyor.

.(details given in chapter 11)

For reducing the external dump area and healthy operation of mine, 2

plans i.e. final stage of mine excavation and final dump plan showing

backfilling, Plate No. 3 & 4 are enclosed. The life of mine will be 21 years.

7.3 DUMPING STRATEGY In the initial years i.e. upto 4th year, entire OB will go to the external

dumps. For project implementation and aquision of land for external

dump may take 3 to 4 years. During this period about 20 Mcum OB

will be dumped internally. Provision of rehandling of this internal dump

to external dump site has been considered in the project costing.

Internal dumping will start from the 5th year onwards. The parting OB in

case of older seams may be transported partly through central haul road,

while mining in the multi seam zone.

Initially, the soil/alluvium from top bench of OB will be stacked and stored

separately. The spoil dump benches in the internally backfilled OB will be

in the form of benches. With the sufficient advance of coal production

bench, the backfilled OB will be leveled with dozer..

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 7 / 3 of 8

Dumper/Tipper will transport soil/alluvium OB from the top OB bench and

will dump the soil directly on the leveled backfilled OB. The barrier

distance between internal dump and coal production bench will be 80 m to

have smooth functioning of machineries.

The slope stability study should be done. According to study report, the

dump design like dump bench height, total dump height & slope etc.

should be modified to avoid dump failure. In addition to that proper

precautions should be taken to avoid sliding of internal OB bench.

238.02 Mcum OB will be externally dumped outside quarry area from 1st

year to 10th year for which 356.50 Ha land will be required.

The northern boundary of Amadand OC block is along the Fault F1-F1

having throw of 20m to 80m. On the other side of Fault F1-F1 Khodri Block

exists where UK seam occurs at a minimum depth of about 21m. So

external dump has not proposed in the Khodri Block.

External dump has been made near southern boundary as shown in Plate

No.4. The break-up of OB quantity to be accommodated in various dumps

is as follows:-

Dump OB accommodated in Mcum 1. Internal dump 526.38 2. External dump outside Quarry area 238.02

Top soil will be removed and stored separately. This soil will be directly

spread over the leveled graded backfilled spoil for reclamation of the

quarried out land. Possibility of external dump within quarry boundary and

rehandling back into the quarry has been examined. Considering the high

quantity of external OB placing of external dump within quarry boundary

will not to be feasible. So placing of external dump proposed outside the

quarry area.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 7 / 4 of 8

Amadand OC can be expanded in the east direction. Quarry planning

and dump plan has been proposed accordingly such that quarry can be

expanded in east directions in future. At the end of quarry life, if required,

the void left will be filled to reduce the depth of void to 60m. Necessary

filling of the void will be done from mine closure cost. Initially the height of

internal dump is 90m from surface. After fifteenth year of mine life the

internal dump height will be kept upto surface level. Thus about 228.18 Ha

land will be levelled to surface level and can be utilized for agricultural

purposes.

7.4 SEQUENCE OF DUMPING OPERATIONS & STAGE-WISE DETAILS

Sl.No. Particulars of working Total

1. Coal mined (Mt) 70.46

2. OBR (Mcum) 764.40

3. Stripping ratio (Mcum/t) 10.85

4. Excavated quarry area (Ha) 694.80

5. Internal dump (Mcum) 526.38

6. External dump (Mcum) 238.02

7.5 DUMPING ARRANGEMENTS & PRECAUTIONS Maximum height of internal dump will be upto 230m from quarry floor

(90m above surface level) (refer Plate No.4). Maximum height of external

dump will be upto 120m from surface. The slopes of external & internal

dumps are as follows: -

External dump - 37 degrees

Internal dump - 37 degrees

30 m will be the height of individual bench.

30 m will be width of berm.

The slope stability study should be done. According to study report

necessary mitigative measure will be taken for the dump design like dump

bench height, total dump height & slope etc. In addition to that proper

precautions / observations should be taken to avoid sliding of internal and

external dump.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 7 / 5 of 8

7.6 TOP SOIL MANAGEMENT

1.0 INTRODUCTION

The topsoil at Amadand block comprises of rich humus with minerals and

nutrients. Proper handling and management is necessary for future

vegetation growth in the mine reclaimed area. The thickness of the top soil

varies between 25 cm to 35 cm.

1.1 Objectives of the Soil Stripping management plan

The objectives of Top Soil Management are to:

Maintain a topsoil balance that achieves rehabilitation objectives during

the life of Mine.

Ensure effective topsoil removal techniques are employed to maximise

volumes of suitable topsoil removed and minimise wastage.

Maintain topsoil viability during stripping, spreading, and stockpiling,

through best practice technique and effective stockpile design and

treatment .

In accordance with the objective of providing sufficient stable soil material

for rehabilitation and to optimise soil recovery, the following strategies will

be adopted during the mining operation at Mahan opencast mines.

1.2 Stripping Prior to the commencement of stripping, areas will be cleared of

vegetation. Soil stripping will be undertaken by dozers and hydraulic backhoe

excavators to maximise the preservation of the quality of the soil. The HEMM

operators and supervisors should be trained and made aware for the same. This

will ensure that all suitable topdressing material resources are salvaged and that

the quality of the stripped top dressing material is not reduced through

contamination with unsuitable soils. Care will be taken during stripping,

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 7 / 6 of 8

stockpiling, and re-spreading to ensure that structural degradation of the soil is

avoided and that excessive compaction does not occur during stockpiling.

1.3 Stock piling

Where possible, topdressing material will be re-spread directly from

stripped areas onto areas being rehabilitated. Where this is not possible,

topdressing material will be stored in stockpiles.

Stock piles will be dumped at places where they would not be disturbed by

future mining. Sediment fences or other barriers can be used where

necessary to retain sediment.

The overall topography for the graded surface should be designed to

minimize the uncontrolled flow of runoff.

Dispersed sheet flow should be broken up by terraces or benches along

the slope that also follow topographic contours.

On a fine scale the ground surface can be roughened by the tracks of a

bulldozer perpendicular to the slope. Construction of stockpiles with a

“rough” surface condition will reduce erosion hazard, improve drainage

and promote revegetation.

1.4 Stockpile preservation

Stockpiling topsoil may result in disruption & loss of beneficial soil

microorganisms and nutritional values, hence needs the following amendments

during preservation:-

1) Re-vegetation of the stockpile will be done as scheduled below to protect the

soil from erosion, discourage weeds and maintain active populations of beneficial

soil microbes.

Temporary Seeding- To protect topsoil stockpiles by temporarily

seeding as soon as possible, within 30 days after the formation of

the stockpile.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 7 / 7 of 8

Permanent Vegetation- If stockpiles will not be used within 12

months they will be stabilized with permanent vegetation to control

erosion and weeds. Likely grass species for revegetating top soil

stock piles are green panic, Japanese millet (spring sowing), Oats

(winter sowing), Dryland Lucerne, Seaton park sub-clover.

Topsoil can be mixed with organic material or manufactured soil

amendments to improve the growing capability.

2) To the extent practicable, above ground vegetation, including tree litter

should be mixed or otherwise incorporated into the topsoil.

3) Soil amendments: Soil amendments should be applied before seeding or

planting. Common soil amendments used are biosolids, compost, manure, lime

and coal combustion byproducts.

Prior to the placement, the top 0.30 cm of stockpile material should be

mixed with the remainder of stockpile to ensure that living organisms are

distributed throughout the topsoil material at the time of final placement. In case,

the material has been stockpiled for over nine month period, use of

microorganisms inoculates may be necessary to re-establish microorganisms in

the topsoil material. The quantity should be 200 ml for one Heactare area in case

of Azatobactor and Rhizobium.

1.5 Site Preparation

Before spreading topsoil, establish erosion and sedimentation control

structures such as diversions, berms, dikes, waterways and sediment

basins.

Adjust grades and elevations for receipt of topsoil.

Roughening - Immediately prior to spreading the topsoil, loosen the

subgrade to ensure bonding of the topsoil and subsoil.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 7 / 8 of 8

Soil horizons will be replaced in the same order that they were removed.

Top soil will be uniformly distributed to pre-mining thickness. Topsoil will

not be spread while it is frozen or muddy .

The topsoil will be compacted to ensure good contact with the underlying

soil, but excessive compaction will be avoided, as it increases runoff and

inhibits seed germination. Light compaction with roller will be done where

turf is to be established.

On slopes and areas that will not be mowed, the surface will be left rough

after spreading topsoil.

1.6 Monitoring

Specific team / manpower is to be deployed for this most important step of

topsoil management. The team will monitor the area and quantum of top soil

management with the authorities of mine on quarterly basis and regularly monitor

the given points of significant importance:

Monitoring Erosion Control: This step is necessary during stock

piling as well as reclamation stage of topsoil management. Take corrective

measure in areas showing evidence of erosion, sedimentation or slope

failure. This is a serious problem, because erosion causes fertile farmland

to lose nutrients and water retention ability.

Regular monitoring of top soil management should be done until

vegetation is demonstrated to be successfully established.

Reseeding: Take appropriate measures to address evidence of

invasive species or poorly established vegetation. Reseeding should be

done, if germination is not uniform or poor.

*******

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 8 / 1 of 6

CHAPTER - VIII

MINING SCHEDULE & EQUIPMENT PHASING

8.1 DESIGN CRITERIA

Transport of coal from face to railway siding will be done by inpit belt conveyor

& surface belt conveyor. The mine has been planned for 330 days with 3 shifts

working per day. Duration of shift hours will be eight.

Excavation category assumed

i) Coal - - III

ii) Alluvial OB - Cat.I/II : Assumed

iii) Hard OB - 50% cat.III + 50% cat.IV Insitu volume weight t/cum i) Coal - 1.52 t/cum ii) Overburden - 2.40 t / cum

8.2 ANNUAL PRODUCTIVITY OF HEMM

The PR has been formulated to win coal by Surface Miner & OB by Shovel

Dumper combination. For OB removal year wise lead has been estimated and

based on that average lead for OB removal is estimated to 3.0 Km.

Transport of coal from face to railway siding will be done by inpit belt

conveyor & surface belt conveyor. The Annual productivity of outsourced

HEMM will depends on the size of deployed HEMM.

8.3 EQUIPMENT SELECTION

The PR has been formulated to win coal by Surface Miner with FEL and coal

body trucks/dumpers & OB by Shovel Dumper combination. In Outsourcing

Option both winning of coal and extraction of OBR will be done through

outsourced HEMM. Due to flexibility of operation, Shovel-Dumper combination

will be suitable for OB removal for working multiple seams and partings. As

coal production increased, the annual OB removal will also increased. To

handle the larger OB quantity optimum no. of equipment with required capacity

is proposed be used. Minimum 10 cum Shovels with 100T rear dumpers will be

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 8 / 2 of 6

used for OBR by outsourcing agency. For thin partings, smaller backhoe may

be used.

The property is free from any major geological disturbances. Average gradient

of quarry floor is 1 in 30. The average strike length of the quarry is 3.0 km.

Thus, sufficient face length will be available for optimum efficiency of surface

miner.

The bottom most seams LK-2 have been splitted into LK-2 Top and LK-2

Bottom. Both of the splits have varying thickness from 0.7 m to 1.50m. Above

LK-2 Seam, Seam L-1 exists having seam thickness 0.70m to 0.90m. Parting

thickness between Seam LK-2 and L-1 varies 6 m to 18 m. Thus, dragline

horizon changing will be required for operation of dragline and dragline

productivity will be less. Besides, the bottom coal bench may be diluted as low

thickness coal seam may be mixed with OB during dragline operation. So

dragline has not been proposed in this Project Report.

8.4 EXISTING HEMM POPULATION

In Outsourcing Option both winning of coal and extraction of OBR will be done

through outsourced HEMM. Few auxiliary HEMM has been proposed for mine

development and reclamation related work. In outsourcing option, few existing

HEMM will be used as auxiliary HEMM for mine development and reclamation

related work and rest of HEMM will be transferred elsewhere.

8.5 DRILLING & BLASTING

OB will be loosened by drilling and blasting to facilitate their excavation. The

actual pattern for drilling and blasting will be decided after field trials. For

secondary blasting 10% of additional explosives will be required for OB. The

drilling will be done carefully to keep at least 1.0m to 1.5m OB parting above

coal seam to reduce contamination of coal with fragmented OB. Whenever

required Ripper will be used reduce contamination of coal with fragmented OB.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 8 / 3 of 6

SMS explosives should be used wherever possible. The pattern for drilling of

blast holes will depend upon the height of the bench and may be designed as

follows: -

Height of bench = H

Burden (B) - H/2

Spacing (S) - B*1.25

The suggested drilling pattern is for average mining conditions. These may

suitably be modified during actual mining operations as per the site conditions.

The explosives consumption has been envisaged as 0.30 - 0.35 kg/cum of

excavation.

The ground vibration due to blasting can be controlled by:-

i) Optimising the amount of explosives charged per delay,

ii) Optimising spacing and burden of blast holes,

iii) Optimising the amount of explosives charged per blast,

iv) Proper strata movement during blast by using suitable initiating sequence.

Since above parameters are site specific, the exact blasting pattern will be

designed by conducting field trials.

8.6 CALENDAR PROGRAMME OF EXCAVATION

The mine is proposed for peak coal production of 4.00 Mty and peak OB

removal is of 52.54 Mty. The total mineable reserves within the quarries have

been estimated as 70.46 Mt with a corresponding OB volume of 764.40 Mcum.

While, calculating mineable reserves, a geological loss of 10% and a mining

loss of 10% have been considered.

Production build-up period - 3 years

Production period - 15 years

Tapering period - 1 year

Total period - 19 years Considering the average width of quarry and annual advance of quarry floor,

the calendar programme has been prepared and given in the following table: -

RP

R fo

r Am

adand O

CP

(4.0

Mty

) (Update

d J

uly

’ 2015) C

MP

DI

. . JO

B N

O.-515126 C

hapter 8 / 4 of 6 Y

ea

rwis

e c

oa

l from

diffe

ren

t co

al s

ea

ms

YE

AR

T

OT

AL

C

OA

L

UK

&

UK

T

UK

B

L4

L

3 &

L

3T

L

3B

M

K &

M

KT

M

KB

L

K1

L

1

LK

2 &

L

K2

T

LK

2B

1

2.0

0

2.0

0

2

3.0

0

1.8

5

0.0

1

0.0

1

0.1

6

0.0

3

0.7

9

0.1

5

3

4.0

0

0.1

6

0.0

1

0.0

1

0.3

1

0.0

6

1.5

0

0.2

9

0.3

6

0.1

1

1.1

9

4

4.0

0

0.7

3

0.0

1

0.0

1

0.3

1

0.0

6

1.5

0

0.2

9

0.2

4

0.0

7

0.7

8

5

4.0

0

0.7

3

0.0

1

0.0

1

0.3

1

0.0

6

1.5

0

0.2

9

0.2

4

0.0

7

0.7

8

6

4.0

0

0.9

9

0.0

1

0.0

1

0.2

3

0.0

4

1.4

3

0.1

8

0.2

3

0.0

7

0.8

1

7

4.0

0

1.4

1

0.1

3

1

.33

0

.21

0.0

5

0.8

7

8

4.0

0

1.4

4

0.1

1

0.0

1

1.3

1

0

.20

0.0

6

0.8

6

0.0

1

9

4.0

0

1.4

6

0.0

1

0.0

1

0.0

9

0.0

3

1.2

7

0

.19

0.0

6

0.8

5

0.0

3

10

4.0

0

1.4

8

0.0

1

0.0

1

0.0

9

0.0

3

1.2

7

0.0

1

0.1

8

0.0

5

0.8

2

0.0

5

11

4.0

0

1.5

0

0.0

4

0.0

1

0.0

8

0.0

3

1.2

7

0.0

3

0.1

5

0.0

3

0.7

7

0.0

9

12

4.0

0

1.4

7

0.0

2

0.0

2

0.0

7

0.0

2

1.3

1

0.0

3

0.2

0

0.0

2

0.7

2

0.1

2

13

4.0

0

1.4

4

0.0

1

0.0

4

0.0

5

0.0

1

1.3

3

0.0

3

0.2

5

0.0

2

0.6

8

0.1

4

14

4.0

0

1.4

1

0.0

1

0.0

4

0.0

5

0.0

1

1.2

3

0.0

3

0.2

9

0.0

4

0.6

2

0.2

7

15

4.0

0

1.3

9

0.0

1

0.0

3

0.0

4

0.0

1

1.1

8

0.0

2

0.3

1

0.0

6

0.6

0

0.3

5

16

4.0

0

0.9

9

0.1

8

0.1

1

0.0

3

0.0

1

1.1

0

0.1

0

0.3

3

0.0

9

0.5

6

0.5

0

17

4.0

0

0.7

5

0.2

5

0.1

7

0.0

3

0.0

1

1.1

7

0.1

2

0.3

8

0.1

7

0.5

2

0.4

3

18

4.0

0

0.5

1

0.1

8

0.2

1

0.0

1

0.0

1

1.1

5

0.2

0

0.4

9

0.1

4

0.6

1

0.4

9

19

1.4

6

0.1

4

0.0

3

0.0

7

0.4

0

0.0

9

0.2

2

0.0

2

0.2

7

0.2

2

TO

TA

L

70

.46

21

.85

0.8

0

0.7

7

2.1

0

0.4

3

22

.04

1.8

6

4.4

7

1.1

3

12

.31

2.7

0

RP

R fo

r Am

adand O

CP

(4.0

Mty

) (Update

d J

uly

’ 2015) C

MP

DI

. . JO

B N

O.-515126 C

hapter 8 / 5 of 6 Y

ea

rwis

e O

B re

mo

va

l from

pa

rting

s o

f diffe

ren

t co

al s

ea

ms

TO

P O

B

NA

TU

RA

L

TO

P O

B

PL

AN

NE

D

UK

T-

UK

B

UK

B-

L4

L4-

L3&

L3T

L

3T

- L

3B

L

3B

-M

K&

MK

T

MK

T-

MK

B

MK

B-

LK

1

LK

1-

L1

L1-

LK

2

&L

K2T

L

K2T

-L

K2B

TO

TA

L

OB

N

AT

UR

AL

TO

TA

L

OB

P

LA

NN

ED

S

R

20.5

9

20.5

9

20.5

9

20.5

9

10.3

0

15.6

5

15.6

5

0.0

2

14.5

7

4.7

6

0.1

8

1.2

9

0.4

4

36.9

1

36.9

1

12.3

0

0.1

8

0.1

8

0.0

3

7.4

2

9.0

8

0.3

4

2.4

5

0.8

4

18.1

8

11.4

1

2.6

1

52.5

4

52.5

4

13.1

4

4.2

7

4.2

7

0.0

3

14.4

2

9.0

8

0.3

4

2.4

5

0.8

4

11.9

2

7.4

8

1.7

1

52.5

4

52.5

4

13.1

4

4.2

7

4.2

7

0.0

3

14.4

2

9.0

8

0.3

4

2.4

5

0.8

4

11.9

2

7.4

8

1.7

1

52.5

4

52.5

4

13.1

4

6.0

7

6.0

7

0.0

2

11.4

1

7.6

8

0.3

5

2.1

2

0.5

1

10.5

3

7.1

5

1.4

8

47.3

2

47.3

2

11.8

3

8.7

8

8.7

8

6.8

5

5.5

7

0.3

7

1.6

1

8.4

2

6.6

5

1.1

3

39.3

8

39.3

8

9.8

5

8.8

6

8.8

6

6.6

5

5.9

1

0.4

2

1.6

4

8.6

1

6.6

4

1.1

7

0.0

1

39.9

1

39.9

1

9.9

8

9.0

1

9.0

1

6.2

8

6.5

3

0.5

1

1.6

8

8.9

7

6.6

3

1.2

4

0.0

2

40.8

7

40.8

7

10.2

2

8.9

0

8.9

0

0.0

2

6.2

2

6.5

3

0.4

7

1.8

7

0.0

1

8.8

9

6.7

9

1.1

5

0.0

4

40.8

9

40.8

9

10.2

2

8.7

2

8.7

2

0.0

5

6.1

3

6.5

3

0.4

0

2.1

6

0.0

2

8.7

7

7.0

2

1.0

2

0.0

7

40.8

9

40.8

9

10.2

2

8.4

3

8.4

3

0.0

3

6.0

8

6.4

3

0.4

6

2.3

4

0.0

2

8.6

3

7.1

8

0.9

4

0.0

7

40.6

1

40.6

1

10.1

5

8.1

5

8.1

5

0.0

2

6.0

3

6.3

3

0.5

2

2.5

3

0.0

2

8.5

0

7.3

3

0.8

6

0.0

8

40.3

7

40.3

7

10.0

9

7.6

5

7.6

5

0.0

4

6.4

7

6.2

7

0.5

8

2.5

0

0.0

3

8.7

5

7.0

1

1.4

0

0.1

6

40.8

6

40.8

6

10.2

2

7.3

7

7.3

7

0.0

6

6.7

1

6.2

4

0.6

1

2.4

8

0.0

4

8.9

0

6.8

4

1.7

0

0.2

1

41.1

6

41.1

6

10.2

9

7.1

5

7.1

5

0.2

2

6.8

1

7.1

0

0.6

1

2.5

2

0.1

8

9.8

9

8.0

8

1.7

2

0.1

5

44.4

3

44.4

3

11.1

1

5.7

5

5.7

5

0.3

3

6.6

7

5.9

0

0.6

8

2.0

6

0.2

0

9.3

0

7.6

6

1.7

9

0.3

0

40.6

4

40.6

4

10.1

6

3.5

4

3.5

4

0.2

5

5.4

4

5.3

3

0.8

9

1.6

8

0.3

0

9.6

9

8.7

9

1.4

5

0.7

4

38.1

0

38.1

0

9.5

3

0.7

1

0.7

1

0.0

4

1.5

1

2.0

2

0.3

9

0.5

7

0.1

5

3.8

7

3.8

1

0.3

7

0.4

1

13.8

5

13.8

5

9.4

9

144.0

5

144.0

5

1.1

9

140.0

9

116.3

7

8.4

6

36.4

0

4.4

4

163.7

4

123.9

5

23.4

5

2.2

6

764.4

0

764.4

0

10.8

5

RP

R fo

r Am

adand O

CP

(4.0

Mty

) (Update

d J

uly

’ 2015) C

MP

DI

. . JO

B N

O.-515126 C

hapter 8 / 6 of 6 S

um

ma

rise

d c

ale

nd

ar p

rogra

mm

e c

on

sid

erin

g re

ha

nd

le o

f OB

are

as g

ive

n in

the fo

llow

ing ta

ble

YE

AR

C

OA

L (M

t) O

B P

LA

NN

ED

(M

cu

m)

RE

HA

ND

LIN

G O

F

OB

(Mc

um

) R

EH

AN

DL

ING

OF

T

OP

SO

IL (M

cu

m)

1

2.0

0

20

.59

8.0

0

2

3.0

0

36

.91

11

.00

3

4.0

0

52

.54

4

4.0

0

52

.54

5

4.0

0

52

.54

6

4.0

0

47

.32

7

4.0

0

39

.38

8

4.0

0

39

.91

9

4.0

0

40

.87

10

4.0

0

40

.89

11

4.0

0

40

.89

12

4.0

0

40

.61

13

4.0

0

40

.37

14

4.0

0

40

.86

0.5

0

15

4.0

0

41

.16

0.5

0

16

4.0

0

44

.43

0.5

0

17

4.0

0

40

.64

0.5

0

18

4.0

0

38

.10

0.5

0

19

1.4

6

13

.85

0.5

0

TO

TA

L

70

.46

76

4.4

0

19

.00

3.0

0

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 9 / 1 of 18

CHAPTER - IX

COAL QUALITY 9.1 INTRODUCTION

On the basis of moisture and ash percentage different litho units are

defined as under: -

Coal : Ash + Moisture upto 40%. Shaly Coal : Ash + Moisture from 40% to 55%. Carbonaceous shale/

combustible dirt band : Ash + Moisture from 55% to 75%. Obvious dirt bands : Ash + Moisture more than 75%.

Initially, the band by band analysis of the coal cores were obtained and

subsequently special tests and the proximate analysis at 60% RH and

400C were advised for Bcs, I30, I10, I100 and Ip basis which are defined as

under: -

Bcs Sample: only coal and shaly coal. I30 Sample: including combustible bands upto a thickness of 30cm. This

type of analysis has been asked only for assessing under ground

reserves. Dirt bands upto 5 cm irrespective of lithology have been

included in the seam for quality assessment. Carbonaceous shale bands

having thickness more than 30cm have been excluded from the seam

thickness.

I10 Sample: including both combustible and non-combustible bands upto

0.10m thickness. This analysis has been carried out for the seams having

quarriable potentiality.

I100 Sample : 'Bcs' sample + carbonaceous shale (ash + moisture upto

75%) bands upto 1m in thickness + grey shale (ash + moisture >75%)

bands upto 1m in thickness and excluding all other obvious bands such as

sandy shale, shaly sandstone, sandstone etc. irrespective of their

thickness.

Ip Sample: I100 Sample + carbonaceous and grey shale bands irrespective

of their thickness and excluding all other obvious bands as in I100 Sample.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 9 / 2 of 18

9.2 QUALITY ANALYSIS SEAM-UPPER KOTMA TOP (UKT)

PROXIMATE ANALYSIS

The iso-grade lines drawn on I10 samples show the grade variation

between F-B. But in major part of the block, the general grade is “C”.

Range of proximate analysis & grade of Seam-UKT, Amadand OC Block Parameters Range

Bcs Sample I10 Sample I100 Sample Full Seam

Boreholes considered :

25 25 25

Thickness (m)/Range (m) Mean STD.DEV

0.30-2.80 (CMAD-63) (CMAD-62)

1.71 0.82

0.30-2.80 (CMAD-63) (CMAD-62)

1.71 0.82

0.30-2.80 (CMAD-63) (CMAD-62)

1.71 0.82

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.30-2.80 (CMAD-63) (CMAD-62)

1.71 0.82

0.30-2.80 (CMAD-63) (CMAD-62)

1.71 0.82

0.30-2.80 (CMAD-63) (CMAD-62)

1.71 0.82

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

5.0–14.1 (CMAD-315) (CMAD-273)

5.5 1.80

5.0–14.1 (CMAD-315) (CMAD-273)

8.5 1.80

5.0–14.1 (CMAD-315) (CMAD-273)

8.5 1.80

Ash% Mean STD.DEV

10.80-39.60 (CMAD-30) (CMAD-55)

18.1 5.7

10.80-39.60 (CMAD-30) (CMAD-55)

18.1 5.7

10.80-39.60 (CMAD-30) (CMAD-55)

18.1 5.7

VM% Mean STD.DEV

26.5 – 31.3 (CMAD-37) (CMAD-273)

28.7 1.4

26.5 – 31.3 (CMAD-37) (CMAD-273)

28.7 1.4

26.5 – 31.3 (CMAD-37) (CMAD-273)

28.7 1.4

FC% Mean STD.DEV

35.9 – 49.8 (CMAD-273) (CMAD-315)

45.2 3.7

35.9 – 49.8 (CMAD-273) (CMAD-315)

45.2 3.7

35.9 – 49.8 (CMAD-273) (CMAD-315)

45.2 3.7

UHV (Kcal/kg) Mean STD.DEV

2606 - 6043 (CMAD-55) (CMAD-315)

5227 738

2606 - 6043 (CMAD-55) (CMAD-315)

5227 738

2606 - 6043 (CMAD-55) (CMAD-315)

5227 738

Grade Avg. Grade

F-B C

F-B C

F-B C

GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam-UKT, Amadand OC Block Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg)

Bcs I10 I100

25 0.30-2.80 3954 - 6350 (CMAD-55) (CMAD-315)

3954 - 6350 (CMAD-55) (CMAD-315)

3954 - 6350 (CMAD-55) (CMAD-315)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 9 / 3 of 18

SEAM-UPPER KOTMA BOTTOM (UKB)

PROXIMATE ANALYSIS The iso-grade lines drawn on I10 samples show the grade variation between

F-A. But in major part of the block, the general grade is “C”.

Range of proximate analysis & grade of Seam-UKB, Amadand OC Block Parameters Range

Bcs Sample I10 Sample I100 Sample Full Seam

Boreholes considered :

27 27 27

Thickness (m)/Range (m) Mean STD.DEV

0.24-2.26 (CMAD-133) (CMAD-62)

1.09 0.39

0.24-2.26 (CMAD-133) (CMAD-62)

1.09 0.39

0.24-2.26 (CMAD-133) (CMAD-62)

1.09 0.39

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.24-2.26 (CMAD-133) (CMAD-62)

1.08 0.39

0.24-2.26 (CMAD-133) (CMAD-62)

1.09 0.39

0.24-2.26 (CMAD-133) (CMAD-62)

1.09 0.39

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

3.8 –10.5 (CMAD-55) (CMAD-30)

7.9 1.30

3.8 –10.5 (CMAD-55) (CMAD-30)

7.9 1.30

3.8 –10.5 (CMAD-55) (CMAD-30)

7.9 1.30

Ash% Mean STD.DEV

10.4-37.4 (CMAD-28) (CMAD-36)

17.1 6.5

10.4-38.1 (CMAD-28) (CMAD-152)

17.2 6.9

10.4-38.1 (CMAD-28) (CMAD-152)

17.2 6.9

VM% Mean STD.DEV

23.5 – 32.0 (CMAD-62) (CMAD-63)

28.7 2.3

23.5 – 32.0 (CMAD-62) (CMAD-63)

28.7 2.3

23.5 – 32.0 (CMAD-62) (CMAD-63)

28.7 2.3

FC% Mean STD.DEV

42.2 -53.3 (CMAD-63) (AMD-2)

48.0 2.4

42.2 -53.3 (CMAD-63) (AMD-2)

48.0 2.4

42.2 -53.3 (CMAD-63) (AMD-2)

48.0 2.4

UHV (Kcal/kg) Mean STD.DEV

2987 - 6330 (CMAD-36) (CMAD-28)

5458 777

2987 - 6330 (CMAD-36) (CMAD-28)

5458 823

2987 - 6330 (CMAD-36) (CMAD-28)

5458 822

Grade Avg. Grade

F-A C

F-A C

F-A C

9.2.1 GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam-UKB, Amadand OC Block Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg)

Bcs I10 I100

27 0.24 – 2.26 4243 -6381 (CMAD-36) (CMAD-28)

4243 -6381 (CMAD-36) (CMAD-28)

4243 -6381 (CMAD-36) (CMAD-28)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 9 / 4 of 18

9.2.3 SEAM : UPPER KOTMA (UK)

PROXIMATE ANALYSIS

The iso-grade lines drawn on I10 samples show the grade variation between

G-B. But in major part of the block, the general grade is “D”.

Range of proximate analysis & grade of Seam-UK, Amadand OC Block Parameters Range

Bcs Sample I10 Sample I100 Sample

Full Seam

Boreholes considered :

106 106 106

Thickness (m)/Range (m) Mean STD.DEV

0.15-6.87 (CMAD-282) (CMAD-325)

4.35 1.41

0.15-6.87 (CMAD-282) (CMAD-325)

4.35 1.41

0.15-6.87 (CMAD-282) (CMAD-325)

4.35 1.41

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.15-6.45 (CMAD-282) (CMAD-12)

4.12 1.35

0.15-6.45 (CMAD-282) (CMAD-12)

4.12 1.35

0.15-6.87 (CMAD-282) (CMAD-325)

4.35 1.41

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

3.5 –11.0 (CMAD-319) (CMAD-4)

7.6 1.20

3.5 –11.0 (CMAD-319) (CMAD-4)

7.6 1.10

4.6 –11.0 (CMAD-34) (CMAD-4)

7.4 1.0

Ash% Mean STD.DEV

6.7-49.1 (CMAD-320) (CMAD-274)

22.1 6.6

13.6-49.1 (CMAD-17) (CMAD-274)

22.3 6.4

14.9-49.2 (CMAD-71) (CMAD-34)

25.1 6.4

VM% Mean STD.DEV

18.3 –58.6 (CMAD-274) (CMAD-115)

26.5 4.3

18.3 –58.6 (CMAD-274) (CMAD-115)

26.4 4.3

18.3 –34.1 (CMAD-274) (CMAD-156)

25.7 2.3

FC% Mean STD.DEV

14.0 -61.4 (CMAD-15) (CMAD-320)

44.5 5.4

14.0 -51.9 (CMAD-15) (CMAD-338)

44.3 5.1

26.3 -49.5 (CMAD-156) (CMAD-71)

43.1 4.2

UHV (Kcal/kg) Mean STD.DEV

1420 - 7368 (CMAD-274) (CMAD-320)

4804 854

1420 - 6084 (CMAD-274) (CMAD-319)

4772 816

1420 - 5781 (CMAD-274) (AMD-25)

4409 796

Grade Avg. Grade

G-A D

G-B D

G-B D

GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam UK, Amadand OC Block Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

106 0.15 – 6.45 3240 - 7184 (CMAD274) (CMAD320)

3240- 6455 (CMAD274) (CMAD319)

3240- 6100 (CMAD274) (AMD-25)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 9 / 5 of 18

9.3 SEAM-L4 9.3.1 PROXIMATE ANALYSIS

The isochores and isograde of the seam are depicted in seam folio plan.

The isochore lines drawn on I10 samples show the grade variation between

C to A. The average grade is B. The seam folio plan is given in

Range of proximate analysis & grade of Seam L4, Amadand OC Block Parameters Range

Bcs Sample I10 Sample I100 Sample

Full Seam

Boreholes considered :

18 18 18

Thickness (m)/Range (m) Mean STD.DEV

0.45 - 1.73 (CMAD-190)(CMAD-112)

0.85 0.31

0.45 - 1.73 (CMAD-190)(CMAD-112)

0.85 0.31

0.45 - 1.73 (CMAD-190)(CMAD-112)

0.85 0.31

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.45 - 1.73 (CMAD-190)(CMAD-112)

0.85 0.31

0.45 - 1.73 (CMAD-190)(CMAD-112)

0.85 0.31

0.45 - 1.73 (CMAD-190)(CMAD-112)

0.85 0.31

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

7.5 – 10.3 (AMD-25) (CMAD-24)

8.6 0.7

7.5 – 10.3 (AMD-25) (CMAD-24)

8.6 0.7

7.5 – 10.3 (AMD-25) (CMAD-24)

8.6 0.7

Ash% Mean STD.DEV

9.7 - 19.3 (CMAD-56) (AMD-9)

13.9 2.9

9.7 - 19.3 (CMAD-56) (AMD-9)

13.9 2.9

9.7 - 19.3 (CMAD-56) (AMD-9)

13.9 2.9

VM% Mean STD.DEV

25.6 – 32.4 (CMAD-22) (AMD-25)

29.4 2.0

25.6 – 32.4 (CMAD-22) (AMD-25)

29.4 2.0

25.6 – 32.4 (CMAD-22) (AMD-25)

29.4 2.0

FC% Mean STD.DEV

45.0 - 53.8 (AMD-9) (CMAD-22)

48.7 2.7

45.0 - 53.8 (AMD-9) (CMAD-22)

48.7 2.7

45.0 - 53.8 (AMD-9) (CMAD-22)

48.7 2.7

UHV (Kcal/kg) Mean STD.DEV

5128 - 6319 (AMD-9) (CMAD-56)

5789 367

5128 - 6319 (AMD-9) (CMAD-56)

5789 367

5128 - 6319 (AMD-9) (CMAD-56)

5776 385

Grade Avg. Grade

C-A B

C-A B

C-A B

9.3.2 GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam L4, Amadand OC Block Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

18 0.45-1.73 5570 - 6400 (AMD-9) (AMD-25)

5570 - 6400 (AMD-9) (AMD-25)

5570 - 6400 (AMD-9) (AMD-25)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 9 / 6 of 18

9.4 SEAM-L3 TOP (L3T) PROXIMATE ANALYSIS

The isochores and isograde of the seam are depicted in seam folio plan.

The isochore lines drawn on I10 samples show the grade variation between

G to B. The average grade is D.

Range of proximate analysis & grade of Seam L3T, Amadand OC Block Parameters Range

Bcs Sample I10 Sample I100 Sample

Full Seam

Boreholes considered :

20 20 20

Thickness (m)/Range (m) Mean STD.DEV

0.35 - 1.25 (CMAD-101)(CMAD-148)

0.77 0.25

0.35 - 1.25 (CMAD-101)(CMAD-148)

0.77 0.25

0.35 - 1.25 (CMAD-101)(CMAD-148)

0.77 0.25

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.35 - 1.20 (CMAD-101)(CMAD-188)

0.75 0.23

0.35 - 1.20 (CMAD-101)(CMAD-188)

0.75 0.23

0.35 - 1.25 (CMAD-101)(CMAD-148)

0.75 0.25

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

4.7 – 7.6 (CMAD-20) (CMAD-23)

6.6 1.0

4.7 – 7.6 (CMAD-20) (CMAD-23)

6.6 1.0

4.7 – 7.6 (CMAD-20) (CMAD-23)

6.6 1.0

Ash% Mean STD.DEV

12.2 - 43.0 (CMAD-66) (CMAD-20)

22.6 10.1

12.2 - 43.0 (CMAD-66) (CMAD-20)

22.6 10.1

12.2 - 43.0 (CMAD-66) (CMAD-20)

23.0 10.3

VM%5 Mean STD.DEV

20.7 – 31.8 (CMAD-83) (CMAD-66)

26.3 4.1

20.7 – 31.8 (CMAD-83) (CMAD-66)

26.5 4.3

20.7 – 31.8 (CMAD-83) (CMAD-66)

26.5 4.3

FC% Mean STD.DEV

40.1 - 51.9 (CMAD-115) (CMAD-152)

47.0 4.1

40.1 - 51.9 (CMAD-115) (CMAD-152)

47.3 4.3

40.1 - 51.9 (CMAD-115) (CMAD-152)

47.3 4.3

UHV (Kcal/kg) Mean STD.DEV

2320 - 6159 (CMAD-20) (CMAD-66)

4868 1252

2320 - 6159 (CMAD-20) (CMAD-66)

4868 1252

2320 - 6159 (CMAD-20) (CMAD-66)

4868 1252

Grade Avg. Grade

G-B D

G-B D

G-B D

GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam L3T, Amadand OC Block Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

20 0.35-1.20 3829 - 6293 (CMaD-20) (CMAD-66)

3829 - 6293 (CMaD-20) (CMAD-66)

3829 - 6293 (CMaD-20) (CMAD-66)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 9 / 7 of 18

9.5 SEAM-L3 BOTTOM (L3B)

PROXIMATE ANALYSIS

The isochores and isograde of the seam are depicted in seam folio plan.

The isochore lines drawn on I10 samples show the grade variation between

E to B. The average grade is C.

Range of proximate analysis & grade of Seam L3B, Amadand OC Block Parameters Range

Bcs Sample I10 Sample I100 Sample

Full Seam

Boreholes considered :

17 17 17

Thickness (m)/Range (m) Mean STD.DEV

0.06 - 0.80 (CMAD-101)(CMAD-166)

0.48 0.20

0.06 - 0.80 (CMAD-101)(CMAD-166)

0.48 0.20

0.06 - 0.80 (CMAD-101)(CMAD-166)

0.48 0.20

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.06 - 0.80 (CMAD-101)(CMAD-166)

0.48 0.20

0.06 - 0.80 (CMAD-101)(CMAD-166)

0.48 0.20

0.06 - 0.80 (CMAD-101)(CMAD-166)

0.48 0.20

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

6.5 – 8.7 (CMAD-6) (CMAD-148)

7.8 0.80

6.5 – 8.7 (CMAD-6) (CMAD-148)

7.8 0.80

6.5 – 8.7 (CMAD-6) (CMAD-148)

7.8 0.80

Ash% Mean STD.DEV

12.2 - 32.5 (CMAD-190) (CMAD-336)

20.3 7.4

12.2 - 32.5 (CMAD-190) (CMAD-336)

20.3 7.4

12.2 - 32.5 (CMAD-190) (CMAD-336)

20.3 7.4

VM% Mean STD.DEV

24.6 – 32.3 (CMAD-85) (CMAD-98)

28.8 2.8

24.6 – 32.3 (CMAD-85) (CMAD-98)

28.8 2.8

24.6 – 32.3 (CMAD-85) (CMAD-98)

28.8 2.8

FC% Mean STD.DEV

40.7 - 51.5 (CMAD-115) (CMAD-188)

46.4 4.1

40.7 - 51.5 (CMAD-115) (CMAD-188)

46.4 4.1

40.7 - 51.5 (CMAD-115) (CMAD-188)

46.4 4.1

UHV (Kcal/kg) Mean STD.DEV

3521 - 6015 (CMAD-336) (CMAD-190)

5027 908

3521 - 6015 (CMAD-336) (CMAD-190)

5027 908

3521 - 6015 (CMAD-336) (CMAD-190)

5027 908

Grade Avg. Grade

E-B C

E-B C

E-B C

GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam L3B, Amadand OC Block Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

17 0.06-080 4555- 6141 (CMaD-336) (CMAD-190)

4555- 6141 (CMaD-336) (CMAD-190)

4555- 6141 (CMaD-336) (CMAD-190)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 9 / 8 of 18

9.6 SEAM-L3 (L3)

PROXIMATE ANALYSIS

The iso-chores and iso-grade of the seam are depicted in seam folio plan.

The iso-chore lines drawn on I10 samples show the grade variation between

G to B. The average grade is D.

Range of proximate analysis & grade of Seam L3, Amadand OC Block Parameters Range

Bcs Sample I10 Sample I100 Sample Full Seam

Boreholes considered :

58 58 58

Thickness (m)/Range (m) Mean STD.DEV

0.44 - 2.51 (CMAD-111)(CMAD-163)

1.27 0.50

0.44 - 2.51 (CMAD-111)(CMAD-163)

1.27 0.50

0.44 - 2.51 (CMAD-111)(CMAD-163)

1.27 0.50

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.44 - 2.47 (CMAD-111)(CMAD-51)

1.12 0.42

0.44 - 2.47 (CMAD-111)(CMAD-51)

1.13 0.43

0.44 - 2.51 (CMAD-111)(CMAD-163)

1.27 0.50

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

5.0 – 8.7 (CMAD-16) (CMAD-148)

7.0 0.90

5.0 – 8.7 (CMAD-16) (CMAD-148)

7.0 0.90

5.0 – 8.7 (CMAD-16) (CMAD-148)

6.6 0.90

Ash% Mean STD.DEV

12.3 - 44.7 (CMAD-162) (CMAD-520)

25.4 8.2

12.3 - 44.7 (CMAD-162) (CMAD-520)

25.6 8.1

12.3 - 44.7 (CMAD-162) (CMAD-520)

29.4 8.5

VM% Mean STD.DEV

19.7 – 30.3 (CMAD-245) (CMAD-7)

25.3 2.5

22.0 – 30.3 (CMAD-52) (CMAD-7)

25.6 2.3

21.7 – 30.3 (CMAD-135) (CMAD-7)

25.4 2.4

FC% Mean STD.DEV

31.5 - 48.2 (CMAD-52) (CMAD-60)

41.4 4.3

31.5 - 48.2 (CMAD-52) (CMAD-60)

41.1 4.6

31.5 - 48.2 (CMAD-52) (CMAD-60)

40.2 5.1

UHV (Kcal/kg) Mean STD.DEV

2045 - 6041 (CMAD-520) (CMAD-162)

4426 1016

2045 - 6041 (CMAD-520) (CMAD-162)

4393 1001

2045 - 6041 (CMAD-520) (CMAD-162)

3924 1051

Grade Avg. Grade

G-B D

G-B D

G-B E

GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam L3, Amadand OC Block Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

58 0.44-2.47 3626 - 6172 (CMAD-520) (CMAD-162)

3626 - 6172 (CMAD-520) (CMAD-162)

3626 - 6172 (CMAD-520) (CMAD-162)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 9 / 9 of 18

9.7 SEAM- MIDDLE KOTMA TOP (MKT) PROXIMATE ANALYSIS

The iso-chores and iso-grade of the seam are depicted in seam folio plan.

The iso-chore lines drawn on I10 samples show the grade variation between

G to B. The average grade is G.

Range of proximate analysis & grade of Seam MKT, Amadand OC Block Parameters Range

Bcs Sample I10 Sample I100 Sample Full Seam

Boreholes considered :

93 93 93

Thickness (m)/Range (m) Mean STD.DEV

0.47 - 3.46 (CMAD-60)(CMAD-172)

1.83 0.68

0.47 - 3.46 (CMAD-60)(CMAD-172)

1.83 0.68

0.47 - 3.46 (CMAD-60)(CMAD-172)

1.83 0.68

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.13 - 3.20 (CMAD-243)(CMAD-198)

1.75 0.64

0.13 - 3.20 (CMAD-243)(CMAD-198)

1.75 0.64

0.13 - 3.20 (CMAD-243)(CMAD-172)

1.75 0.64

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

4.2 – 8.9 (CMAD-85) (CMAD-179)

5.4 0.80

4.2 – 8.9 (CMAD-85) (CMAD-179)

5.4 0.80

4.2 – 8.9 (CMAD-85) (CMAD-179)

5.4 0.80

Ash% Mean STD.DEV

14.1 - 50.2 (CMAD-103) (CMAD-521)

43.6 6.5

14.1 - 50.2 (CMAD-103) (CMAD-521)

43.7 6.5

14.1 - 50.2 (CMAD-103) (CMAD-521)

43.8 6.5

VM% Mean STD.DEV

16.5 – 30.7 (CMAD-85) (CMAD-103)

20.2 2.9

16.5 – 30.7 (CMAD-85) (CMAD-103)

20.2 3.0

16.5 – 30.7 (CMAD-85) (CMAD-103)

20.2 3.0

FC% Mean STD.DEV

25.7 - 72.2 (CMAD-163) (AMD-27)

32.2 7.4

25.7 - 72.2 (CMAD-163) (AMD-27)

32.1 7.5

25.7 - 72.2 (CMAD-163) (AMD-27)

32.1 7.5

UHV (Kcal/kg) Mean STD.DEV

1332 - 5933 (CMAD-521) (CMAD-103)

2137 799

1332 - 5933 (CMAD-521) (CMAD-103)

2124 804

1332 - 5933 (CMAD-521) (CMAD-103)

2112 804

Grade Avg. Grade

G-B G

G-B G

G-B G

GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam MKT, Amadand OC Block Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

93 0.13-3.20 2655 - 6120 (CMAD-6) (CMAD-103)

2655 - 6120 (CMAD-6) (CMAD-103)

2655 - 6120 (CMAD-6) (CMAD-103)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 9 / 10 of 18

9.8 SEAM- MIDDLE KOTMA BOTTOM (MKB) PROXIMATE ANALYSIS

The iso-chores and iso-grade of the seam are depicted in seam folio plan.

The iso-chore lines drawn on I10 samples show the grade variation between

G to A. The average grade is C.

Range of proximate analysis & grade of Seam MKB, Amadand OC Block Parameters Range

Bcs Sample I10 Sample I100 Sample

Full Seam

Boreholes considered :

100 100 100

Thickness (m)/Range (m) Mean STD.DEV

0.36 - 2.74 (CMAD-102)(CMAD-69)

1.38 0.49

0.36 - 2.74 (CMAD-102)(CMAD-69)

1.38 0.49

0.36 - 2.74 (CMAD-102)(CMAD-69)

1.38 0.49

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.00 - 2.51 (CMAD-172)

1.33 0.47

0.00 - 2.51 (CMAD-172)

1.33 0.47

0.00 - 2.74 (CMAD-69)

1.36 0.51

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

4.1 – 9.8 (CMAD-153) (CMAD-179)

7.5 0.90

4.1 – 9.8 (CMAD-153) (CMAD-179)

7.5 0.90

4.1 – 9.8 (CMAD-153) (CMAD-179)

7.5 0.90

Ash% Mean STD.DEV

9.1 - 70.6 (CMAD-52) (CMAD-165)

20.2 7.9

9.1 - 70.6 (CMAD-52) (CMAD-165)

20.2 7.9

9.1 - 70.6 (CMAD-52) (CMAD-165)

20.7 8.4

VM% Mean STD.DEV

13.7 – 38.1 (CMAD-165) (CMAD-135)

27.5 3.1

13.7 – 38.1 (CMAD-165) (CMAD-135)

27.5 3.1

13.7 – 38.1 (CMAD-165) (CMAD-135)

27.5 3.3

FC% Mean STD.DEV

11.6 - 59.1 (CMAD-165) (CMAD-87)

44.9 5.8

11.6 - 59.1 (CMAD-165) (CMAD-87)

44.9 5.8

11.6 - 59.1 (CMAD-165) (CMAD-87)

44.7 6.0

UHV (Kcal/kg) Mean STD.DEV

1917 - 6448 (CMAD-20) (CMAD-52)

5149 757

1917 - 6448 (CMAD-20) (CMAD-52)

5149 757

1127 - 6448 (CMAD-153) (CMAD-52)

5086 847

Grade Avg. Grade

G-A C

G-A C

UG-A C

GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam MKB, Amadand OC Block Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

100 0.00-2.51 1314 - 7655 (CMAD-165) (CMAD-163)

1314 - 7655 (CMAD-165) (CMAD-163)

1314 - 7655 (CMAD-165) (CMAD-163)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 9 / 11 of 18

9.9 SEAM- MIDDLE KOTMA COMBINED (MKC) PROXIMATE ANALYSIS

The isochores and isograde of the seam are depicted in seam folio plan.

The isochore lines drawn on I10 samples show the grade variation between

G to C. The average grade is F.

Range of proximate analysis & grade of Seam MKC, Amadand OC Block Parameters Range

Bcs Sample I10 Sample I100 Sample

Full Seam

Boreholes considered :

61 61 61

Thickness (m)/Range (m) Mean STD.DEV

1.50 - 6.18 (AMD-6)(CMAD-54)

3.85 1.22

1.50 - 6.18 (AMD-6)(CMAD-54)

3.85 1.22

1.50 - 6.18 (AMD-6)(CMAD-54)

3.85 1.22

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.19 - 5.29 (CMAD-29)(CMAD-512)

3.47 1.64

0.19 - 5.29 (CMAD-29)(CMAD-512)

3.47 1.64

0.19 - 6.18 (CMAD-29)(CMAD-54)

3.80 1.30

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

4.5 – 9.1 (CMAD-68) (CMAD-33)

6.2 1.00

4.5 – 9.1 (CMAD-68) (CMAD-33)

6.2 1.00

4.5 – 9.1 (CMAD-68) (CMAD-33)

5.9 1.00

Ash% Mean STD.DEV

15.5 - 48.7 (CMAD-33) (CMAD-276)

34.9 8.7

15.5 - 48.7 (CMAD-33) (CMAD-276)

35.0 8.7

15.5 - 49.8 (CMAD-33) (CMAD-53)

37.5 8.6

VM% Mean STD.DEV

17.7 – 28.3 (CMAD-68) (CMAD-267)

23.4 3.4

17.7 – 28.3 (CMAD-68) (CMAD-267)

23.5 3.7

17.7 – 26.6 (CMAD-68) (CMAD-33)

22.9 3.8

FC% Mean STD.DEV

27.5 - 49.9 (CMAD-13) (CMAD-45)

38.3 7.2

27.5 - 49.9 (CMAD-13) (CMAD-45)

38.7 7.5

27.5 - 70.3 (CMAD-13) (CMAD-267)

40.7 11.5

UHV (Kcal/kg) Mean STD.DEV

1516 - 5546 (CMAD-276) (CMAD-45)

3234 1082

1516 - 5546 (CMAD-276) (CMAD-45)

3216 1078

1089 - 5546 (CMAD-53) (CMAD-45)

2902 1080

Grade Avg. Grade

G-C F

G-C F

UG-C F

GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam MKC, Amadand OC Block Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

61 0.19-5.29 3255 - 5903 (CMAD-13) (CMAD-45)

3255 - 5903 (CMAD-13) (CMAD-45)

2881 - 5903 (CMAD-53) (CMAD-45)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 9 / 12 of 18

9.10 SEAM- LOWER KOTMA I (LKI) PROXIMATE ANALYSIS

The isochores and isograde of the seam are depicted in seam folio plan.

The isochore lines drawn on I10 samples show the grade variation between

F to A. The average grade is D.

Range of proximate analysis & grade of Seam LKI, Amadand OC Block Parameters Range

Bcs Sample I10 Sample I100 Sample

Full Seam

Boreholes considered :

69 69 69

Thickness (m)/Range (m) Mean STD.DEV

0.13 - 1.78 (CMAD-512)(CMAD-269)

0.94 0.37

0.13 - 1.78 (CMAD-512)(CMAD-269)

0.94 0.37

0.13 - 1.78 (CMAD-512)(CMAD-269)

0.94 0.37

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.13 - 1.70 (CMAD-512)(CMAD-54)

0.92 0.35

0.13 - 1.70 (CMAD-512)(CMAD-54)

0.92 0.35

0.13 - 1.78 (CMAD-512)(CMAD-269)

0.94 0.37

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

4.9 – 9.7 (AMD-6) (CMAD-41)

7.7 0.90

4.9 – 9.7 (AMD-6) (CMAD-41)

7.7 0.90

4.8 – 9.7 (CMAD-30) (CMAD-41)

7.6 1.00

Ash% Mean STD.DEV

5.2 - 39.7 (CMAD-28) (CMAD-267)

21.4 6.5

5.2 - 39.7 (CMAD-28) (CMAD-267)

21.4 6.5

5.2 - 47.9 (CMAD-28) (CMAD-30)

22.3 7.7

VM% Mean STD.DEV

21.2 – 31.7 (CMAD-103) (CMAD-94)

26.5 2.2

21.2 – 31.7 (CMAD-103) (CMAD-94)

26.6 2.2

21.2 – 31.7 (CMAD-103) (CMAD-94)

26.6 2.2

FC% Mean STD.DEV

34.7 - 55.0 (CMAD-103) (CMAD-312)

45.0 4.5

34.7 - 55.0 (CMAD-103) (CMAD-312)

44.9 4.5

34.7 - 55.0 (CMAD-103) (CMAD-312)

45.0 4.6

UHV (Kcal/kg) Mean STD.DEV

2640 - 6872 (CMAD-267) (CMAD-28)

4889 814

2640 - 6872 (CMAD-267) (CMAD-28)

4872 818

1630 - 6872 (CMAD-30) (CMAD-28)

4778 958

Grade Avg. Grade

F-A D

F-A D

F-A D

GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam LKI, Amadand OC Block Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

69 0.13-1.70 3995 - 6685 (CMAD-267) (CMAD-28)

3995 - 6685 (CMAD-267) (CMAD-28)

3553 - 6685 (CMAD-30) (CMAD-28)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 9 / 13 of 18

9.11 SEAM- LOCAL-1(L1) PROXIMATE ANALYSIS

The isochores and isograde of the seam are depicted in seam folio plan.

The isochore lines drawn on I10 samples show the grade variation between

G to A. The average grade is C.

Range of proximate analysis & grade of Seam L1, Amadand OC Block Parameters Range

Bcs Sample I10 Sample I100 Sample

Full Seam

Boreholes considered :

15 15 15

Thickness (m)/Range (m) Mean STD.DEV

0.25 - 1.12 (CMAD-7)(CMAD-20)

0.73 0.24

0.25 - 1.12 (CMAD-7)(CMAD-20)

0.73 0.24

0.25 - 1.12 (CMAD-7)(CMAD-20)

0.73 0.24

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.25 - 1.12 (CMAD-7)(CMAD-20)

0.73 0.24

0.25 - 1.12 (CMAD-7)(CMAD-20)

0.73 0.24

0.25 - 1.12 (CMAD-7)(CMAD-20)

0.73 0.24

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

4.5 – 8.7 (CMAD-512) (CMAD-42)

7.5 1.00

4.5 – 8.7 (CMAD-512) (CMAD-42)

7.5 1.00

4.5 – 8.7 (CMAD-512) (CMAD-42)

7.5 1.00

Ash% Mean STD.DEV

8.7 – 48.6 (CMAD-265) (CMAD-512)

19.3 10.00

8.7 – 48.6 (CMAD-265) (CMAD-512)

19.9 10.00

8.7 – 48.6 (CMAD-265) (CMAD-512)

19.9 10.00

VM% Mean STD.DEV

24.6 – 32.6 (CMAD-1) (CMAD-314)

27.6 2.8

24.6 – 32.6 (CMAD-1) (CMAD-314)

27.6 2.8

24.6 – 32.6 (CMAD-1) (CMAD-314)

27.6 2.8

FC% Mean STD.DEV

36.8 - 53.0 (CMAD-314) (CMAD-186)

45.1 5.8

36.8 - 53.0 (CMAD-314) (CMAD-186)

45.1 5.8

36.8 - 53.0 (CMAD-314) (CMAD-186)

45.1 5.8

UHV (Kcal/kg) Mean STD.DEV

1574 - 6504 (CMAD-512) (CMAD-265)

5195 1241

1574 - 6504 (CMAD-512) (CMAD-265)

5119 1240

1574 - 6504 (CMAD-512) (CMAD-265)

5119 1240

Grade Avg. Grade

G-A C

G-A C

G-A C

GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam L1, Amadand OC Block Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

15 0.25-1.12 3330 - 6475 (CMAD-512) (CMAD-265)

3330 - 6475 (CMAD-512) (CMAD-265)

3330 - 6475 (CMAD-512) (CMAD-265)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 9 / 14 of 18

9.12 SEAM- LOWLER KOTMA II TOP (LKIIT) PROXIMATE ANALYSIS

The isochores and isograde of the seam are depicted in seam folio plan.

The isochore lines drawn on I10 samples show the grade variation between

E to A. The average grade is C.

Range of proximate analysis & grade of Seam LKIIT, Amadand OC Block Parameters Range

Bcs Sample I10 Sample I100 Sample

Full Seam

Boreholes considered :

25 25 25

Thickness (m)/Range (m) Mean STD.DEV

0.60 - 2.76 (CMAD-638)(CMAD-309)

1.12 0.56

0.60 - 2.76 (CMAD-638)(CMAD-309)

1.12 0.56

0.60 - 2.76 (CMAD-638)(CMAD-309)

1.12 0.56

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.60 - 2.76 (CMAD-638)(CMAD-309)

1.12 0.56

0.60 - 2.76 (CMAD-638)(CMAD-309)

1.12 0.56

0.60 - 2.76 (CMAD-638)(CMAD-309)

1.12 0.56

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

5.6 – 9.4 (CMAD-315) (CMAD-21)

7.3 1.0

5.8 – 9.4 (AMD-23) (CMAD-21)

7.4 1.0

5.6 – 9.4 (AMD-23) (CMAD-21)

7.4 0.9

Ash% Mean STD.DEV

5.5 – 34.3 (CMAD-37) (AMD-23)

18.8 8.1

5.5 – 34.3 (CMAD-37) (AMD-23)

18.4 7.6

5.5 – 34.3 (CMAD-37) (AMD-23)

19.3 8.2

VM% Mean STD.DEV

17.0 – 28.8 (AMD-23 (CMAD-21)

25.2 3.8

17.0 – 28.8 (AMD-23 (CMAD-21)

25.2 3.8

17.0 – 28.8 (AMD-23 (CMAD-21)

25.9 3.4

FC% Mean STD.DEV

42.6 - 56.8 (CMAD-269) (CMAD-121)

48.7 4.9

42.6 - 56.8 (CMAD-269) (CMAD-121)

48.7 4.9

33.6 - 56.5 (CMAD-118) (CMAD-121)

47.3 6.4

UHV (Kcal/kg) Mean STD.DEV

3373 - 6943 (AMD-23) (CMAD-37)

5288 1006

3373 - 6943 (AMD-23) (CMAD-37)

5337 947

3373 - 6943 (AMD-23) (CMAD-37)

5217 1026

Grade Avg. Grade

E-A C

E-A C

E-A C

GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam LKIIT, Amadand OC Block Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

25 0.60-2.76 4489 - 6773 (AMD-23) (CMAD-37)

4489 - 6773 (AMD-23) (CMAD-37)

4435 - 6773 (AMD-23) (CMAD-37)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 9 / 15 of 18

9.13 SEAM- LOWLER KOTMA II BOTTOM (LKIIB) PROXIMATE ANALYSIS

The isochores and isograde of the seam are depicted in seam folio plan.

The isochore lines drawn on I10 samples show the grade variation between

D to A. The average grade is B.

Range of proximate analysis & grade of Seam LKIIB, Amadand OC Block Parameters Range

Bcs Sample I10 Sample I100 Sample

Full Seam

Boreholes considered :

23 23 23

Thickness (m)/Range (m) Mean STD.DEV

0.36 - 2.68 (CMAD-539)(CMAD-53)

1.36 0.71

0.36 - 2.68 (CMAD-539)(CMAD-53)

1.36 0.71

0.36 - 2.68 (CMAD-539)(CMAD-53)

1.36 0.71

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.36 - 2.68 (CMAD-539)(CMAD-53)

1.31 0.71

0.36 - 2.68 (CMAD-539)(CMAD-53)

1.31 0.71

0.36 - 2.68 (CMAD-539)(CMAD-53)

1.36 0.71

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

5.6 – 9.7 (CMAD-270) (CMAD-24)

7.7 1.1

5.6 – 9.7 (CMAD-270) (CMAD-24)

7.7 1.1

5.6 – 9.2 (CMAD-270) (CMAD-33)

7.6 1.0

Ash% Mean STD.DEV

7.5 – 26.6 (CMAD-24) (CMAD-334)

14.7 5.4

7.5 – 26.6 (CMAD-24) (CMAD-334)

14.7 5.4

7.6 – 31.4 (CMAD-24) (CMAD-36)

15.7 6.4

VM% Mean STD.DEV

22.3 – 30.9 (CMAD-334) (CMAD-54)

26.7 2.6

22.3 – 30.9 (CMAD-334) (CMAD-54)

26.7 2.6

22.3 – 30.9 (CMAD-334) (CMAD-54)

26.9 2.6

FC% Mean STD.DEV

44.4 - 58.5 (CMAD-334) (CMAD-22)

51.0 4.3

44.4 - 58.5 (CMAD-334) (CMAD-22)

51.0 4.3

44.4 - 58.5 (CMAD-334) (CMAD-22)

51.3 4.1

UHV (Kcal/kg) Mean STD.DEV

4304 - 6761 (CMAD-334) (CMAD-22)

5804 637

4304 - 6761 (CMAD-334) (CMAD-22)

5804 637

3739 - 6761 (CMAD-36) (CMAD-22)

5697 773

Grade Avg. Grade

D-A B

D-A B

E-A B

GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam LKIIB, Amadand OC Block Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

23 0.36-2.68 5076 - 7748 (CMAD-334) (CMAD-54)

5076 - 7748 (CMAD-334) (CMAD-54)

4727- 7748 (CMAD-36) (CMAD-54)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 9 / 16 of 18

9.14 SEAM- LOWLER KOTMA II (LKII) PROXIMATE ANALYSIS

The isochores and isograde of the seam are depicted in seam folio plan.

The isochore lines drawn on I10 samples show the grade variation between

UG to A. The average grade is B.

Range of proximate analysis & grade of Seam LKII, Amadand OC Block Parameters Range

Bcs Sample I10 Sample I100 Sample

Full Seam

Boreholes considered :

130 130 130

Thickness (m)/Range (m) Mean STD.DEV

0.32 - 5.62 (CMAD-58)(CMAD-46)

2.05 0.75

0.32 - 5.62 (CMAD-58)(CMAD-46)

2.05 0.75

0.32 - 5.62 (CMAD-58)(CMAD-46)

2.05 0.75

Effect. Thickness (m)/Range (m) Mean STD.DEV

0.32 - 5.17 (CMAD-58)(CMAD-46)

1.99 0.70

0.32 - 5.17 (CMAD-58)(CMAD-46)

2.00 0.70

0.32 - 5.62 (CMAD-58)(CMAD-46)

2.04 0.77

Proximate analysis in 60% RH & 400 C

M% Mean STD.Dev..

3.9 – 9.7 (CMAD-60) (CMAD-14)

7.7 1.0

3.9 – 9.7 (CMAD-60) (CMAD-14)

7.7 1.0

5.2 – 9.7 (CMAD-283) (CMAD-24)

7.7 1.0

Ash% Mean STD.DEV

5.3 – 51.0 (CMAD-44) (CMAD-515)

15.5 7.5

5.3 – 51.0 (CMAD-44) (CMAD-515)

15.6 7.5

5.3 – 51.0 (CMAD-44) (CMAD-515)

16.4 8.3

VM% Mean STD.DEV

16.2 – 31.2 (CMAD-515) (CMAD-156)

26.4 2.2

16.2 – 31.2 (CMAD-515) (CMAD-156)

26.4 2.2

16.2 – 31.2 (CMAD-515) (CMAD-156)

26.4 2.2

FC% Mean STD.DEV

27.5 - 59.8 (CMAD-515) (AMD-6)

51.4 5.8

27.5 - 59.8 (CMAD-515) (AMD-6)

51.5 5.8

27.5 - 59.8 (CMAD-515) (AMD-6)

51.4 6.0

UHV (Kcal/kg) Mean STD.DEV

1130 - 7133 (CMAD-515) (AMD-6)

5699 962

1130 - 7133 (CMAD-515) (AMD-6)

5683 965

1130 - 7133 (CMAD-515) (AMD-6)

5570 1051

Grade Avg. Grade

UG-A B

UG-A B

UG-A C

GROSS CALORIFIC VALUE (K.cal./kg.)

Range of Gross CV, Seam LKII, Amadand OC Block Boreholes considered

Thickness Range (m)

Range of Gross CV (K.cal/kg) on dmmf basis

Bcs I10 I100

130 0.32-5.17 2984 - 7073 (CMAD-515) (AMD-6)

2984 - 7073 (CMAD-515) (AMD-6)

2984 - 7073 (CMAD-515) (AMD-6)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 9 / 17 of 18

9.15 MINEABLE COAL RESERVES

As on 01.04.2015, the total mineable reserves within the quarries have

been estimated as 70.46 Mt with a corresponding OB volume of 764.40

Mcum. The estimation of mineable reserves is based on a minimum

mineable thickness of 0.5 m. The mineable reserves have been

estimated by iso-chore method from the seam extent plan of individual

seams. Seamwise mineable coal reserves are as given are as given

below.

NAME OF COAL SEAMS MINEABLE COAL RESERVE (MT)

UK&UKT 21.85

UKB 0.8

L4 0.77

L3&L3T 2.1

L3B 0.43

MK&MKT 22.04

MKB 1.86

LK1 4.47

L1 1.13

LK2&LK2T 12.31

LK2B 2.7

TOTAL 70.46

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 9 / 18 of 18

9.16 PROJECTED COAL QUALITY

The seamwise mean GCV of coal seams within Quarry area has been

calculated by explorartion division and based on that seamwise mean

GCV of coal seams within Quarry area has been calculated. The

seamwise mean GCV and mean GCV of coal within Quarry area are as

follows.

NAME OF SEAM GCV (in Kcal/Kg)

Seam UKT 5726

Seam UKB 5725

Seam UKC 5052

Seam L4 5967

Seam L3T 5681

Seam L3B 5224

Seam L3C 4750

Seam MKT 3568

Seam MKB 5385

Seam MKC 4151

Seam LK1 5327

Seam L1 5712

Seam LK2T 5633

Seam LK2B 6037

Seam LK2C 5592

TOTAL

MEAN GCV VALUE (Kcal/kg) 4933

The weighted average Grade of coal is G-8 having Gross Calorific value

of 4933 Kcal/Kg within quarry boundary of Amadand OC(4.00 Mty).

*******

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 10 / 1 of 10

CHAPTER –X

WATER MANAGEMENT (PUMPING AND DRAINAGE)

10.1 GENERAL

The general surface topography in the project is such that that surface

drainage is not likely to pose any major problems as no major nallah do

not traverse quarriable area. The area drainage is by Kewai River and

Hasdeo River.

Garland drains will be provided around the mine to keep the runoff water

away from the quarry. Fresh drains will be made as mine advances. The

drains will be connected to the natural drainage of the area. The drains

will be cleaned periodically to avoid overflow of the same. Embankments

will be provided around the mine wherever necessary to protect the mine

from flooding.

Efforts will be made to lay the benches and haul roads in such a way that

water will gravitate towards the main sump located at the deep most point

available at the current workings. The slope of the floor of benches will

be made such a way that water flows down to the sump to keep the

benches dry.

10.2 SOURCE OF WATER In general the sources of water inside the quarry are as given below:- - Direct rainfall in the excavated area

- Inflow of water from back filled area due to rain fall on it

- Inflow of water from area beyond excavation due to rainfall on it

- Seepage of water from strata water/Ground water

10.2.1 Direct rain fall in excavated area:-

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 10 / 2 of 10

The rain water falling directly in the excavated area will flow down and

collected in the sump. It is assumed that 90% of water falling in this area

will be collected in the sump.

10.2.2 Inflow from back filled area:-

A part of rainwater falling on the Internal dumping area will flow down into

the mine. As the internal dump will be relatively loose so run off

coefficient into the mine has been considered as 0.1.

10.2.3 Inflow from area beyond excavation:-

A part of the rain water falling in the area beyond excavation will find its

way into the mine. Garland drains will be provided around the mine to

arrest the outside water so it is assumed that 10% of rain falling in this

area will flow down into the mine and collected in the sump.

10.2.4 Seepage from strata: / Ground water

There will be some seepage from Strata/ Ground water. This seepage

during dry season say November-June is expected to be low. During

monsoon and post monsoon period i.e. July-October the seepage will be

more. This is assumed as 10% of make of water in the mine.

10.3. MAKE OF WATER

10.3.1 General considerations

The general parameters considered for calculating the pumping

requirements and make of water are as given below:-

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 10 / 3 of 10

(i) Geographical location of the opencast workings.

(ii) Life of the mine

(iii) Surface features of the area surrounding the opencast workings

(iv) Total annual rainfall, maximum rain in a day (assumed)

(v) Catchments area – Exposed area, area beyond excavation, internal

dump area etc.

(vi) Depth of quarry – Initial, final etc.

(vii) Run –off characteristic of the area

(viii) Inflow /Seepage from underground water into the mine

(ix) Sump location and capacity

(x) Desired location on surface where the mine water can be

discharged, surface drainage system.

(xi) Dewatering time for the water collected due to maximum rainfall in

a day.

(xii) Standby capacity required.

(xiv) Size of pipe, piping layout etc.

(xv) Ph value of water.

10.3.2 BASIC DATA The basic data considered for calculating make of water and pumping capacity is as given below:- (i) Yearly rainfall (on average) mm 1200 (ii) Maximum rainfall in a day mm 203 (From probability curve) (iii) Monsoon season (july to Oct) days 120

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 10 / 4 of 10

(iv) Life of the quarry 21 (v) Depth of the mine - Initial m 85 - Final m 140 (vi) Quarry excavation area (year) 5th 10th 15th Final stage -Open excavation H.A. 238.68 326.7 326.24 260.99 - Back filled Area H.A. 0 56.72 209.36 428.54 - Area beyond H.A. 11.93 19.17 27.28 34.48

(vii) Run-off co-efficient for inflow of water into the mine - Open excavation 0.60 - Area beyond excavation 0.10 - Internal dump area 0.10

(viii) Seepage/Inflow of water into the 10% of water accumulated mine due to strata water in the mine due o rainfall

(ix) Time required to dewater the entire Water including 10% pump losses 100 hours (x) Pumping losses 10% 10.3.3 Assessment of maximum rainfall in a day

The assessment of maximum rainfall in a day during the life of the project

has been made by drawing a probability curve (fig 10.1) based on

calculated/theoretical values and observed values of the maximum rainfall

in a day, life of the project etc.

i) Probability based on observed values:-

The maximum rainfall in a day at J&K Area for the period 2001-2011 has

been arranged in the descending order and the probability of the same

was calculated and tabulated below in the descending order :-

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 10 / 5 of 10

Observation Year Highest Rainfall %P=(N-0.3)*

No.(N) in one day(mm) 100/(M+0.4)

1 2008 195.00 6.14

2 2003 175.00 14.91

3 2009 150.00 23.68

4 2004 150.00 32.46

5 2011 109.00 41.23

6 2010 103.00 50.00

7 2007 88.00 58.77

8 2001 86.00 67.54

9 2006 75.00 76.32

10 2005 54.00 85.09

11 2002 37.00 93.86

Where N = observation Number M = Total number of observations

ii) Probability based on calculated/theoretical values:-

The probability of calculated/Theoretical rainfall based on the observed data is shown below:-

Observation Highest K=hn/ham K-1 (K-1)^2

No.(N) Rainfall in

one day

(mm) hn

1 195.00 1.76 0.76 0.58

2 175.00 1.58 0.58 0.34

3 150.00 1.35 0.35 0.12

4 150.00 1.35 0.35 0.12

5 109.00 0.98 -0.02 0

6 103.00 0.93 -0.07 0

7 88.00 0.79 -0.21 0.04

8 86.00 0.77 -0.23 0.05

9 75.00 0.68 -0.32 0.1

10 54.00 0.49 -0.51 0.26

11 37.00 0.33 -0.67 0.45

Sigma hn= 1222.00 Sigma(K-1)^2=2.06

Whereas N = Observation Number M = Total number of observations haM = Mean Value of recorded maximum rainfall haM = haN = 1222.00 = 111.09 mm N 11

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 10 / 6 of 10

Cv = Co efficient of variation = ∑√ ((k-1)2 / (M-1)) =0.4539 Cs = Asymmetrical ratio = 3Cv = 3 x 0.5712 = 1.3616 h = Calculated rainfall The values of (Cs) the “Deviation of ordinates of Binomial curve of probability

from “RIBKIN CHART” at the Cs value as calculated above have been selected

for different probabilities. By using f (Cs) value the maximum rainfall and its

probability will be calculated as given in the table below:-

Probability f(Cs)=Phai Ms=Phai*Cv Ks=Ms+1 h=Ks*ham

Percentage (from R.C).

0.1 5.09 2.31 3.31 367.71

1 3.27 1.48 2.48 275.51

5 1.94 0.88 1.88 208.85

10 1.34 0.61 1.61 178.86

20 0.71 0.32 1.32 146.64

25 0.49 0.22 1.22 135.53

30 0.31 0.14 1.14 126.64

40 0.02 0.01 1.01 112.20

50 -0.02 -0.01 0.99 109.98

60 -0.44 -0.20 0.80 88.87

70 -0.64 -0.29 0.71 78.87

80 -0.83 -0.38 0.62 68.88

90 -1.04 -0.47 0.53 58.88

95 -1.17 -0.53 0.47 52.21

99 -1.32 -0.60 0.40 44.44

A rainfall probability curve Fig. 10.1 will be drawn taking into consideration the

calculated values and observed values. The maximum daily rainfall at

probabilities of 10% and 4.76% which corresponds to 10 years and 21 years (life

of the project) respectively will be found out from the above curve and they are

approximately 172 mm and 203 mm :-

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 10 / 7 of 10

10.3.4 CALCULATIONS:

SL.NO. DESCRIPTION UNIT 5 th Year

10th year

15th Year

Final Year

1

Inflow due to direct rainfall in exposed area

cu.m.

290712 397921 409540 317886

2

Inflow due to direct rainfall on internal dump area

cu.m.

0 11514 42500 86994

3

Inflow due to direct rainfall on area beyond excavation

cu.m.

2423 3892 5538 6999

4 Seepage from ground water cu.m. 29313 41333 45758 41188

5 Total water collected in a day cu.m. 322448 454660 503336 453066

6

Sump capacity provided 10% probability(rain fall 172mm)

cu.m.

268707 375358 415545 374043

7

Water lying out side the sump

cu.m.

53741 79301 87791 79023

8

Pumping capacity to dewater the water lying outside the sump in 18 hrs.including 10% pump losses

lps

912 1346 1490 1341

9

Pump capacity to dewater entire water including 10% pump losses in 100 hrs. pumps

lps

896 1263 1398 1259

10

No.of 225 lps capacity pumps required to dewater lying outside the sump in 18 hrs.

No.

4 6 7 6

11

No. of 225 lps capacity pumps required to dewater entire water in 100 hrs.

No.

4 6 6 6

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 10 / 8 of 10

10.4. SUMP

A sump will be provided at the deep most point of the mine. The sump will

be shifted as the mine advances. The layout of quarry provides suitable

gradient along the floor of the benches to facilitate self drainage of water

into the sump.

During heavy monsoon period, the work in the lower most benches may

be drowned as it will not be possible to pump out the entire make of water

in the wettest day. Therefore, it is proposed to drown a part of the lower

most bench which will work as a sump to accommodate the required

quantity of water which will be equivalent to the water accumulated due to

a rainfall of 172 mm in a day (at 10% probability).

Water from the sump will be pumped to surface which will pass through

sedimentation ponds before finally discharged into natural drainage

system. Sump will be cleaned periodically to avoid silting and mud

accumulation.

10.5.0 PUMPS

Nine numbers of main pumps each of 225lps, 160m head (along

with energy efficient motor) will be provided to meet the requirements up

to 21 years. Out of nine pumps six nos. will be working & three will be

standby. Some of the stages of the main pumps may be blanked when

they have to operate at shallow depths. This has been provided to reduce

the capital investment and utilize the pumps till the end of life. Provisions

have been made considering the peak demand which is occasional.

Further the pumps may be repaired and kept ready for use in rainy

season. Main pumps will be installed on pontoons. Provision of pontoons

for each main pump has been given in the estimate. After 10th year of

mine operation the depth of mine would be around 145m, so proper care

has to be taken to arrest water at upper seam. Thus stage pumping could

be avoided.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 10 / 9 of 10

Three nos. of Intermediate pump of 80 lps capacity, 100 m head,

110kw have also been provided to be used at low head. Two nos. of

diesel engine operated pump of 80lps capacity, 80m head has been

provided for operation in the initial period and then as standby for use in

case of emergency.

All the main pumps will be provided with pressure gauges on

delivery side and suction side for measuring the head developed so that

corrective action will be taken for operating the pump at the duty point.

The main pumps have been provided considering life of the mine.

The requirement of pumps has been shown for entire life of the mine;

however procurement shall be made as per requirement.

During heavy rainfall, overburden may be washed away from edges

of slopes and internal dumps, pumps capable of slurry handling will be

required. Pumping of clear water and slurry will be from upper and lower

part of sump respectively.

10.6 PIPING ERW pipes of 355.6mm outer diameter will be used for carrying the

discharge from 225lps capacity pumps. Similarly, ERW pipes of 273mm

outside diameter will be provided for carrying the discharge from 80lps

capacity main pump / diesel engine operated pumps and 219mm diameter

pipe will be provided for discharge from 38lps submersible pumps. Initially

the delivery pipes from each pumping stations are proposed to be taken

out through haul road and then through access trench and through side

batters of quarry at a later date. Provision for crossways are made on the

floor of the side batters for crossing the haul road so that dumper

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 10 / 10 of 10

transportation is not affected. These pipes are evenly brought to the

surface from where water will be discharged to the sedimentation ponds

and then water will be discharged to natural drainage system. Provision

will be provided at pump house for connecting the delivery of the pumps to

at least two numbers of delivery ranges. Flow meters will be provided in

each 355.6mm diameter pipe for measuring the discharges.

10.7 CAPITAL INVESTMENT

The details of the proposed pumps, pipes and pipe fittings along

with estimated cost and brief specifications are shown in Appendix A.3.4.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 11 / 1 of 10

CHAPTER-XI

COAL HANDLING PLANT AND DESPATCH 11.1.0 INTRODUCTION:

There are numbers of overlying workable seams in the proposed quarry

area. Due to the above reason in-pit conveyor system has been

proposed. It is proposed to produce (-) 100 mm coal by using surface

miners and then transport the same up to CHP by using Inpit conveyor

system. It is proposed to dispatch (-) 100mm size coal to distant

consumers by rail. To meet the above requirement a CHP with coal

storage in 15000Te bunker and rapid loading system with 500Te Bunker

has been provided for dispatch of coal to the distant consumers by rails.

Road dispatch facility has also been provided to meet the requirements of

distant customers. Capacity of this CHP is 4.0 Mty.

11.2.0 BASIC DATA:

i. Target out put 4.0 mty ii. Life of the mine 21years iii. Quality of coal Grade G-8 (GCV 5335 Kcal/Kg) iv. Mine operation 3 shifts/day v. CHP operation 3 shifts/day vi. Customer Power houses & Misc. vii. Mode of transport to CHP By Inpit Conveyors viii. Dispatch of coal

- to distant consumers through rail - to local consumers by trucks ix. Storage facility 1) Over head RCC Bunker of 15000te

2) Bunker500te

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 11 / 2 of 10

x. Loading arrangement Rapid loading system @ 3600-4400 tph xi. Weighing arrangement of coal

- to distant consumers Pre-weigh hopper below 500t bunker & rail weighbridge.

- to local consumers Road weigh bridges xii. End product for dispatch (-) 100 mm 11.3.0 INPIT CONVEYING SYSTEM 11.3.1 i) Coal mined by surface miner will be transported to inpit by 60te

trucks/dumpers to coal receiving station, where reclaim feeder will be

installed.

ii) Reclaim feeder will receive the coal and feed to Inpit belt conveyors.

iii) Installation of conveyor of Inpit will start from 2nd year onwards.

iv) In initial period Inpit conveyors will be laid along the haul road directly from

the surface after getting the proper gradiant.

v) In final stage of Inpit Conveying System there will be 9 nos.of conveyors

IC1 to IC9 will be of 1200mm to 1400 mm wide and 800 to 1600 tph

capacity.

vi) Inpit conveyor will discharge the coal to a surge bunker at surface. The

surge bunker be connected with the main CHP at surface.

vii) Each Inpit conveyor will be fed by one no. of Reclaim feeder which in turn

fed to another Inpit conveyor.

11.4.0 COAL HANDLING PLANT (CHP) 11.4.1 Coal from inpit conveyor will feed to Surge Bunker with the help of

conveyors IC8 and IC9. From 1000t surge bunker coal will be discharged on to

belt conveyor C1 or C2 of main CHP with the help of Vibratory feeder. The belt

conveyor C1 or C2 will discharge the coal to a series of belt conveyor C3 or C4

and C5 or C6. The conveyor C5 or C6 will receive coal from conveyor C3 or

C4. The conveyor C5 or C6 will also act as tripper conveyor and spread coal

over 15000t overhead bunker.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 11 / 3 of 10

11.4.2 The conveyors C7/C8 will be of 1600 mm wide and of 2200 tph

capacity. The belt conveyor C7/C8 will installed bellow the 15,000te bunker.

These conveyors will elevate coal and discharge onto 500t bunker over rail.

11.4.3 The overhead bunker will be of twin slit type. At each slit two numbers

(one working & one standby) plough feeders of 2200 tph capacity (av.) will be

provided for reclaiming coal from the bunker at a regulated rate and discharge on

reclaim cum loading belt conveyors C7/C8.

11.4.4 Ultrasonic type level switches will be provided on the carriage of the

traveling tripper of the conveyors C5/C6 to monitor the high level of coal in the

bunker. In case high level is reached in the bunker, it gives signals so that

tripper can move to the next place for discharging coal in the bunker. Similarly

low level switches will also be provided in bunker to stop the plough feeder

provided at the bunker opening in case a pre-determined low level is reached.

Two numbers of partition walls will be provided in the bunker which will be helpful

during maintenance and repair. The floor of the bunker will be provided with

proper slopes for easy drainage of water. The slanting surface of the bunker will

be provided with suitable liners for smooth flow of coal.

11.4.5 The overhead bunker will be of 500 t capacity and of RCC construction.

The bunker will be designed and constructed on mass flow concept to reduce the

possibilities of rat holing/arching taking place during evacuation process.

Provision for air blasters/air cannons along with suitable air compressor have

been made to avoid rat holing/arching inside the bunker so that continuous coal

flow is assured. The air blasters will be located at different levels. Ultrasonic

type high level limit switches will be provided in 500Te bunker to stop the Plough

feeder below 15,000te bunker, if a predetermined high level reached in the

bunker. Similarly low level limit switches will be provided to close 500te bunker

discharge gates if a predetermined low level is reached in the 500te bunker.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 11 / 4 of 10

The conical portion of the bunker will be provided with 10 mm thick stainless

steel liners and up to a height of 1 m in the vertical walls. The vertical walls will

be lined with 40 mm thick epoxy based ironite lining. There will be 4 numbers

outlets below the 500te bunker. At each outlet one number of hydraulically

operated emergency gate will be installed. These will be used in emergency

cases during the maintenance of the equipment below the bunker and will be

operated through independent hydraulic power pack. Further, one number

hydraulically operated bunker discharge gate will be installed below each

emergency gate. The coal will fall into a steel hopper of flush capacity of 115

cum through bunker discharge gates. The hopper walls will be lined with 10 mm

thick stainless steel liners. The pre-weigh hopper will be mounted on four

numbers of load cells each of 60 t capacity to weigh the coal before it is

discharged .Below the pre weigh hopper a hydraulically operated swing chute

with a flow control gate will be provided by which the wagons will be choke

loaded. The wagons will be moved by means of creep controlled diesel

locomotive while they are being loaded. Track logic system will be provided on

the rail lines to identify the wagons and send signal to the central processing unit

for operating the swing chute. The loading system will have print out facilities to

have records of dispatch.

11.4.6 2x100t capacity overhead steel hoppers will be installed to dispatch

coal by trucks. For this purpose, a belt conveyor C9 of 1200 mm wide and 400

tph capacity will be installed to receive coal from the two pockets of over head

bunker & carry to discharge coal into the 2 x 100 t capacity hopper. Coal will be

reclaimed from these Surge hoppers with the help of 400 tph capacity vibratory

feeders provided at the discharge opening of the Surge hopper for loading into

customers’ trucks. Rod gates will be provided at the discharge opening to arrest

the coal in case of repair and maintenance of the vibratory feeders. The hoppers

will be lined with 10 mm thick manganese steel liners.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 11 / 5 of 10

11.4.7 Coal dispatches through rail will be weighed in the pre-weigh hopper

located below the bunker before loading into the wagons. At the same time Coal

dispatches by rail will be weighed on 100 t capacity rail weigh bridge (1 no.)

installed on rail line. Coal dispatches by trucks through road will be weighed on

100 t capacity road weigh bridge .

11.4.8 SAMPLING: Automatic sampling system with primary sample

collector, belt feeder, secondary sampler, crusher, tertiary sampler, bag

collector, bucket elevator will be provided near 500t bunker. The primary sample

collector will collect coal from the belt conveyor C7 and C8 discharging into the

500te bunker.

11.5.0 DUST SUPPRESSION ARRANGEMENT: Dust suppression

arrangement has been provided to suppress dust at all transfer points, truck

receiving station, over the RCC bunker below the over head RCC bunker, below

truck loading hoppers etc. The dust suppression arrangement will be by spraying

plain water in atomized/mist form to have better dust suppression. Necessary full

cone type nozzles, valves, pipes, pumps, sump, pump house etc. will be

provided.

11.6.0 FIRE FIGHTING ARRANGEMENT: Fire fighting arrangement as per

statutory requirements will be provided. Fire detection and alarm system will be

provided. Fire extinguishers, sand buckets will be provided in control room,

substation/MCC rooms, compressor room, hydraulic power pack room, pump

house, drive houses etc. to put-off minor nature of fires.

11.7.0 CHUTES: Closed chutes will be provided at all the transfer points to

avoid dust nuisance and for proper flow of material. The chutes will be properly

lined.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 11 / 6 of 10

11.8.0 LIFTING TACKLES: Electric hoist blocks suitable for mounting on

mono rails will be provided at the drive houses of belt conveyors, maintenance

bay of plough feeders to lift the equipment during erection, repairing and

maintenance. Traveling type pulley blocks suitable for mounting on mono rails

will be provided at transfer points, sampler house, pump house, compressor

room etc. to lift the equipment . Fixed type pulley blocks of suitable capacity will

be provided in the towers of the counter weights provided for H-loop take up of

the belt conveyors. Passenger lift of 1 t. capacity will be provided near 500 te

RCC bunker for transport of material and men in the bunker complex. Two nos.

of inspection trolley with cage will be provided over 15000te and 500 te bunkers

for inspection of outer and inner surfaces of bunkers.

11.9.0 HARD STAND: Three numbers of hard stands will be provided one

each near 500 te bunker and drive house of conveyor C3/C4 and C5/C6 for

maintenance of equipment.

11.10.0 CONDITION MONITORING: Suitable condition monitoring system to

monitor the condition of motor winding and bearing temperatures of the HT

motors, oil and bearing temperatures of the gear boxes will be provided.

11.11.0 BELT VULCANIZING: Belt vulcanizing units suitable for vulcanizing

of steel card/N-N belting will be provided. Belt handling device will also be

provided to pull the belting during erection and jointing of belting.

11.12.0 Heat sensors will be provided at various levels in the bunker to

monitor the temperature inside the bunker to take proper steps in case of

emergency.

11.13.0 The control room near the weigh bridge will be of modular construction

and located very near to the weighbridge and on right hand side of the road for

communication with the driver. The control room will be air conditioned. Proper

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 11 / 7 of 10

illumination, earthling system, lightning protection system will be provided near

the weigh bridge. The weigh bridges are of pit less electronics type. The weigh

bridges will be provided with required electronics, printout facilities. The print out

facility will facilitate in keeping records of weighment.

11.14.1 POWER SUPPLY ARRANGEMENT:

Four numbers of 6.6 kV Double Circuit Overhead lines from the project

substation will be drawn up to 4 nos. of substations, out of which 2 nos. will be

located in inpit conveying section & 2 nos. will be located in CHP & silo section

and will be strategically located to cater to the inpit & CHP loads.

All the equipment in the CHP will be operated at 6.6 kV/415V/230V, 50 Hz

supply.

At each substation required 6.6 kV switch boards, power transformers, lighting

transformers, 415V MCC, lighting switch boards, auxiliary power distribution

boards etc. will be provided.

All the required protections for over current, short circuit, earth fault and earth

leakage will be provided.

11.14.2 ILLUMINATION: The conveyor gantries, transfer houses, drive

houses, various floors in silo/bunker/truck loading hoppers, will be illuminated by

70W HPSV lamps with well glass fittings. For illumination of CHP, outdoor yard

high masts 15/30 m with 400W metal halide lamps will be provided at suitable

location. The service buildings such as MCC room, transfer room, control room

and other buildings will be illuminated with help of CFL lamps of suitable rating.

Service roads will be illuminated by means of 250W HPSV lamps in street light

fittings mounted on poles.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 11 / 8 of 10

11.15.0 CENTRAL CONTROL SYSTEM:

All the equipment working in the coal flow other than overhead RCC bunker will

be operated and controlled sequentially from central place. For this purpose one

control room will be provided over the substation located near the bunker (15,000

te cap.). All the equipment in coal flow will be controlled from the control room.

The other equipment which are not in the coal flow will also be controlled from

the control room. A second control room will be provided at silo for control of the

reclaim section. The control system will be of PLC type. Local control switches

will be provided to facilitate for repair and maintenance of the equipment. PLC

system will be provided along with mimic panel, enunciator panel in the control

room.

11.16.0 Required earthing system, lightning protection system, safety

equipment, communication equipment will be provided. The substations will be

pressurized and control room will be air conditioned.

11.17.0 MANPOWER REQUIREMENT

The detail manpower requirement for operation and maintenance of CHP are

shown in Appendix B.

11.18.0 CAPITAL REQUIREMENT

The capital requirement with year wise phasing & brief specification of the

equipment are shown at Appendix A.3.5.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 11 / 9 of 10

RAILWAY SIDING

(ALL OPTIONS) 11.19.0 INTRODUCTION

A study has been made for comparison of cost between Coal handling

plant and Railways siding. It was gathered that cost of CHP would be

much more higher than Railways siding for a distance of 8 km. Moreover

the silo/500Te bunker has to be provided on main rail line near Bhaiyatola

railway station which would not be proper. As such railways line has been

proposed.

A railway line will be constructed up to Amadand open cast project from

the Bhaiyatola railway station which is about 8 km.. This will consist of

permanent way, culverts, bridges, electrification, signaling, block stations

etc. A railway siding consisting of one load standage line (suitable for 58

box N wagons), one empty standage line (suitable for 58 box-N-wagons),

engine escape line, one loading station, crossovers, turnouts,

electrification, signaling etc. will be constructed at a suitable location near

the project for loading of coal through a 500te Bunker over railways.

11.19.1 WEIGHMENT

Weighment of coal will be done by pre-weigh hopper installed below the

500te Bunker over railway & rail weighbridge 100Te installed over the

loading line.

11.19.2 MAINTENANCE AND ILLUMINATION

A maintenance shed has been provided near the siding for maintenance

of diesel locomotive engine. It is proposed to outsource the maintenance

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 11 / 10 of 10

of diesel engine. So no provision of equipment has been made for

maintenance, however an E.O.T. crane has been provided in the shed.

Proper illumination arrangement will be provided near the siding and loco

shed for easy operation at site.

11.19.3 CAPITAL REQUIREMENT

The capital requirement for railway siding including the 8km incoming line from,

the existing nearby railway station which with phasing is shown at Appendix A-5.

The estimated cost for construction.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 12 / 1 of 4

CHAPTER-XII

UNIT WORKSHOP AND STORES

12.1.1 INTRODUCTION

In this project report it is envisaged to produce coal and overburden by Coal

and OB outsourcing .

Accordingly unit workshop have been proposed for outsourcing option.

12.2.0 WORKSHOP FOR OUTSOURCING OPTION(Fig. 12.1)

12.2.1 INTRODUCTION

In the present report it is envisaged that the production of coal and over

burden removal in will be outsourced. The mine dewatering and power

supply will be departmental. The required light vehicles will also be hired.

For maintaining departmental equipment it is necessary to provide a small

work shop to cater the needs of daily maintenance, schedule maintenance,

lubrication, routine inspection, minor repair and replacement of parts/sub-

assemblies of equipment such as- pumps, electrical equipment etc.

deployed in the project.

Any major repairs, overhaul of equipment, major repairs and manufacturing

of spares on large scale are beyond the scope of this workshop. These

works will be carried out at Regional workshop of the Jamuna-Kotma area

or Central workshop Korba / Gevra.

12.2.2 SCOPE OF WORKSHOP

This workshop will undertake the following jobs:-

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 12 / 2 of 4

i) Repair/restoration of parts, manufacture of spares to a limited extent

which are in short supply.

ii) Minor and medium repair of switch gears, motors, self-starters and

other electrical equipment, motor rewinding, battery charging

facilities etc.

iii) Minor repairs and maintenance of the equipment like Reclaim

feeders, Belt conveyors, pumps, couplings, pulleys etc.

iv) Structural fabrication to a limited extent.

v) Power supply, illumination etc.

12.2.3 FACILITIES

The unit workshop will consist of the following shops for undertaking the

jobs within Main Workshop shed as envisaged above.

i) Machine shop ii) Electrical repair shop iii) Equipment repair/structural repair shop

12.2.4 SHOP FUNCTIONS The shop wise functions are as follows:- i) Machine shop:- The shop will have necessary machine tools for repair/restoration of

parts, manufacture of spares to a limited extent which are in short

supply.

ii) Electrical repair shop:- The repair facilities are limited to the replacement of parts, facilities

have also been provided to undertake winding of motors to a limited

extent.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 12 / 3 of 4

iii) Equipment repair/structural repair shop:-

This shop will undertake minor repairs and maintenance of the

equipments like pumps, couplings etc. The equipment/components

will be dismantled into individual sub-assemblies for through

checking. The parts/ sub-assemblies which are completely worn-out

or damaged beyond repair will be replaced by new parts/sub-

assemblies. The worn-out /damaged parts which are repairable will

be re-conditioned for further use.

iv) Power supply:

A switching station will be established for installing 415 V switch

board to receive power from the projects main substation. Sub

distribution boards will be provided in the respective shops for

feeding power to different equipment. The shops will be properly

illuminated.

12.2.5 STORES

A small unit stores will be provided in the work shop premises or at adjacent

area for storage of equipment, consumables, spares etc. In this stores

required racks, bins, steel cabinets, wheel barrows, hangers etc will be

provided. Motorised electrical hoist and chain pulley blocks will be provided

for lifting of heavy masses.

12.3.0 MANPOWER

Details of manpower required for manning work shop and stores are given

Appendix-B.

12.4.0 CAPITAL REQUIREMENT

The details of Plant and machinery provided, estimated cost along with

phasing are given in Appendix-A.3.3.

******

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 12 / 4 of 4

S.

No.

Part

icula

rs

S

ize (

m x

m)

1.

Main

Work

shop s

hed.

6m

ht.

1

8 x

42

2.

Equip

ment

Repair s

hop

30 x

20

4.

Off

ice r

oom

15 x

15

5.

Sw

itch R

oom

4 x

10

6.

Batt

ery

room

4 x

8

7.

Car

park

ing

5 x

30

8.

Hard

sta

nd

570 s

q. m

.

9.

Securi

ty p

ost

1N

o.

10.

Boundary

wall w

ith g

ate

380 R

m.

Note

s ;-

1.

All d

imensio

ns a

re in m

.

2.

Lay o

ut

is t

enta

tive a

nd m

ay

change d

uri

ng d

eta

il d

esig

n.

SCH

EM

ATIC

LAYO

UT O

F

UN

IT W

ORK S

HO

P

Fig

.12.1

9

10

Gate

8

(O

UT S

OU

RC

ING

OPTIO

N)

AM

AD

AN

D O

CP

(Job N

o.

(515126)

13

11

11.

Moto

r C

ycle

sta

nd

5x30

12.

Sto

re s

hed

20x20

12

13.

Scra

p y

ard

20x20

3.

Machin

e s

hop

18 x

30

14.

Sub s

tation

15x12

14

2

16

7

RO

AD

15

15.

Cante

en

12x12

8

(O

PTIO

N -

I O

UTSO

URCIN

G)

8

3

41

56

9 x

30

9 x

20

8 x

12

16.

W.C

.6x6

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

JOB NO. 515126 Page No. XIII- 1/ 5

CHAPTER - XIII

POWER SUPPLY, ILLUMINATION AND COMMUNICATION

Source of Power

Amadand opencast project is located in the J&K Area of SECL. This project will

receive power at 33 kV by means of two numbers overhead lines drawn from

Chachai feeder of MPEB by tapping it at Kotma MPEB substation. The distance

of the opencast project from MPEB substation is approximately 22 km.

Main Substation

It is proposed to establish a main substation at Surface to feed all loads of

Quarry and colony loads. This Substation will consist of 2 numbers of 33/6.6 kV,

5000 kVA transformers for pumping, CHP, Workshop, surface and quarry

lighting loads etc.

Outdoor Installations for both Substations

a) 33 kV Isolators

b) 33 kV Bus Section

c) 33 kV VCB Circuit Breakers

d) (i) 33 kV/6.6 kV, 2x5000 kVA transformers

(ii) 33 kV/6.6 kV, 1X1000 kVA transformer- for colony

e) 33 kV Current transformer and potential transformer

f) 33 kV Lightning arrestors

g) 33/0.240 kV (L-L), 100 kVA lighting transformer

h) 6.6 /0.433 kV, 160 kVA station transformer

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

JOB NO. 515126 Page No. XIII- 2/ 5

Indoor Installations

a) 33 kV Remote Control Panel for 33 kV circuit breakers.

b) 6.6 kV Switch Board for 5 MVA & 1 MVA transformers.

c) 415 V Switch board.

d) 6.6 kV Capacitor Banks.

6.6 kV Indoor Type Switch Board

In the substation, one number 12 panel 6.6 kV indoor type switch board will be

installed for secondary control of the main transformers, control of power supply

to the quarry pumps and other load centers of the project. The capacitor bank

controlling panel will incorporate automatic power factor controlling equipment.

The 6.6 kV indoor type switch board will comprise 12 numbers of vacuum

circuit breakers for following functions:

Incoming feeder control 2 nos.

Sectionaliser 1 no.

Capacitor Bank control 2 nos.

Quarry Lighting feeder control 1 no.

Workshop feeder control 1 no.

Quarry Pump feeder control 2 Nos.

CHP feeder control 1 Nos.

Primary control of 250 kVA,3.3/0.433kV Station transformer

1 no.

Reserve 1 nos.

Total 12nos.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

JOB NO. 515126 Page No. XIII- 3/ 5

160 kVA, 6.6/0.433 kV Transformer and 415 V Switch Board

It is proposed to install one number 160 kVA, 6.6/0.433 kV station

transformer at the substation. A five panel 415 V indoor type switch board will

be installed in the substation building which will receive power from the

secondary side of the transformer. Five numbers of moulded case circuit

breakers will be used in the switch board for the following functions-

- 1 no. MCCB for incomer control

- 4 nos. MCCB for outgoing control

100 kVA, 33 kV/ 230 V (L-L) lighting transformer and Lighting Main

Distribution Board

It is proposed to install one no. 100 kVA, 33 kV/ 230 V (L-L) lighting

transformer each for meeting the lighting loads on the surface. It will feed

power to 12 panel 230 V (L-L) indoor type switch board. This distribution

board consists of 1 no. 400 A MCCB (incomer), 2 nos. 3 pole 100 A MCCB,

5 nos. 2 pole 63A MCBs and 2 nos. 2 pole 40A MCBs.

Conncted Load and Maximum Demand

Electrically operated equipments like shovels, drills, pumps, CHP,

workshop, surface and quarry lighting and residential colony have been

proposed in the project for which power will be required. The maximum

demand of the substation (Including colony loads) has been assessed as

10982 kW & 6409 kVA with a corrected power factor of 0.98 (lagging).

Energy Consumption:-

The energy consumption has been calculated considering active power,

Annual number of working hours of equipment/ installation wise. The details

of the year wise energy consumption including colony loads are given in

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

JOB NO. 515126 Page No. XIII- 4/ 5

Table 13.2. The specific energy consumption will be approximately 7.91 kWh

per ton of coal produced at the targeted production of 4 Mt/yr.

Power Factor Improvement

In order to maintain a high system power factor of around 0.98 even during

maximum demand hours, two sets of 6.6kV capacitors each of 1500 kVAr

capacity have been provided in the 6.6 kV switch board of substation.

COMMUNICATION

For effective management of different production, service units and for ensuring safety the adequate communication facilities have been envisaged for the project.

Township Electrification

Suitable provision has been made for external electrification and

illumination of residential colony. This includes 6.6 kV and L.T overhead

lines, transformers, street light fittings etc required for external

electrification of township. It is proposed to draw a 6.6 kV overhead line

from project substation up to colony.

`

Power Balance and Annual Energy Consumption, yearwise Energy

Consumption

The details of power balance for substation is given at Table-13.1. The

annual energy consumption and year wise energy consumption are shown

in Table 13.2.

RP

R fo

r Am

ada

nd

OC

P (4

.0 M

ty) (U

pda

ted

Ju

ly’ 2

01

5) C

MP

DI

. . JO

B N

O.-515126 Page N

o XIII / 5 of 6

Sl,n

o.

Eq

uip

me

nt D

eta

ilsTO

TA

LD

EM

AN

DTO

TA

L

CO

NN

EC

TE

DF

AC

TO

RW

OR

KIN

GTO

TA

L P

OW

ER

TO

TA

L P

OW

ER

TO

TA

L P

OW

ER

TO

TA

L P

OW

ER

TO

TA

L P

OW

ER

LO

AD

LO

AD

CO

NS

N.

LO

AD

CO

NS

N.

LO

AD

CO

NS

N.

LO

AD

CO

NS

N.

LO

AD

CO

NS

N.

(kW

)H

RS

./ YE

AR

(kW

)(k

Wh)

(kW

)(k

Wh)

(kW

)(k

Wh)

(kW

)(k

Wh)

(kW

)(k

Wh)

AO

ve

r Bu

rde

n

Sub

To

tal

00

0

0

0

Ad

d L

ine

los

se

s @

4%

00

00

0

Ene

rgy c

ost fo

r OB

in R

s. L

akhs

00

00

0

BC

oa

l

1C

HP

45

50

0.6

49

50

10

00

29

70

00

01

50

04

45

50

00

20

00

59

40

00

04

55

01

35

13

50

04

55

01

35

13

50

0

20

00

.00

49

50

50

00

10

00

01

50

00

20

00

03

00

00

Ad

d L

ine

los

se

s @

4%

30

88

80

04

63

32

00

61

77

60

01

40

54

04

01

40

54

04

0

Ene

rgy c

ost fo

r Co

al in

Rs. L

akhs

18

5.3

32

77

.99

37

0.6

68

43

.24

84

3.2

4

CC

om

mo

n

1W

ork

sho

p

30

00

.50

16

50

50

41

25

01

00

82

50

01

50

12

37

50

20

01

65

00

03

00

24

75

00

2M

ain

Pum

ps,

54

00

0.6

04

56

01

20

03

28

32

00

24

00

65

66

40

03

60

09

84

96

00

48

00

13

13

28

00

54

00

14

77

44

00

3S

ub

me

rsib

le P

um

ps

33

00

.60

33

00

90

17

82

00

90

17

82

00

18

03

56

40

02

40

47

52

00

33

06

53

40

0

4C

entrifu

ga

l Pum

ps

80

0.6

03

30

04

07

92

00

40

.07

92

00

80

15

84

00

80

15

84

00

80

15

84

00

5F

ace

Pum

ps

72

.00

.60

33

09

.01

78

21

8.0

35

64

27

.05

34

64

5.0

89

10

72

.01

42

56

6Illu

min

atio

n (S

urfa

ce

)1

00

0.9

04

38

05

01

97

10

01

00

39

42

00

10

03

94

20

01

00

39

42

00

10

03

94

20

0

7Illu

min

atio

n (Q

ua

rry)

50

0.9

04

38

02

59

85

50

30

11

82

60

40

15

76

80

50

19

71

00

50

19

71

00

8C

olo

ny a

nd

wa

ter S

up

ply

10

00

.90

52

56

50

23

65

20

60

28

38

24

60

28

38

24

70

33

11

28

10

04

73

04

0

Sub

To

tal

41

15

80

27

70

61

48

1

13

29

20

0

14

86

27

38

1

69

12

29

6

Ad

d L

ine

los

se

s 4

%

42

80

43

48

01

43

94

11

78

23

68

15

45

72

48

17

58

87

88

Ene

rgy c

ost fo

r Co

mm

on in

Rs.

La

khs

25

6.8

34

80

.86

70

6.9

49

27

.43

10

55

.33

E

To

tal e

ne

rgy

co

ns

um

ptio

n o

f

item

s A

to C

73

69

23

41

26

47

59

41

79

59

96

82

95

11

28

83

16

42

82

8

Sp

ecific

Ene

rgy C

onsum

ptio

n (k

Wh/T

) for ta

rge

tted

pro

ductio

n o

f 4.0

Mty

7.9

1

Sp

ecific

Ene

rgy C

ost (R

s/T

) for ta

rge

tted

pro

ductio

n o

f 4.0

Mty

47

.46

Es

tima

ted

ye

ar w

ise

en

erg

y c

on

su

mp

tion

of A

ma

da

nd

OC

P(4

Mty

), Ou

tso

urc

ing

Op

tion

Ta

ble

13

.2

6th

YE

AR

onw

ard

s

4 th

YE

AR

3rd

YE

AR

1st &

2nd Y

EA

R 5

th Y

EA

R

RP

R fo

r Am

ada

nd

OC

P (4

.0 M

ty) (U

pda

ted

Ju

ly’ 2

01

5) C

MP

DI

. . JO

B N

O.-515126 Page N

o XIII / 6 of 6

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 14 / 1 of 7

Chapter – XIV

CIVIL CONSTRUCTION

14.1 GENERAL:

Amadand open cast project is situated in Jamuna and Kotma area of SECL.

The location and general topography of the proposed block has been elaborated

elsewhere in this report.

14.1.1 Life & Type of Specification:

The planned life of the proposed block is more than 20 years and as per

B.P.E guidelines permanent specifications have been envisaged for all civil

structures. All civil structures should preferably be constructed over non-coal bearing

area. Residential colony and service infrastructures should preferably be located at

distant locations/ existing township.

14.1.2 Nature of soil:

In general poor soil is available in this area. As such necessary provision

wherever required has been made.

14.1.3 External Services:

Coal transportation from the mine and CHP has been dealt separately.

14.2 COST INDEX & SPECIFICATION OF BUILDING:

The preparation of cost estimates for civil infrastructures is based on

prevailing cost index of the area in July 2015. The cost index value has been

calculated from market rate of the area. The same was provided by the staff officer

(Civil) of the area. Standard guidelines provided by B.P.E have been adopted for

arriving at cost index value. Considering the prevalent rates of materials and labour

in Jamuna & Kotma Area, the cost index works out to 2926 in July 2015 with

reference to 100 base in Delhi as on 1.10.76. The detailed calculation for Cost

Index is shown in Appendix A.2.3. All civil construction has predominantly been

envisaged to be of permanent specification.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 14 / 2 of 7

14.3 SERVICE BUILDINGS:

14.3.1 Provision of Service/Welfare Building:

Considering the requirement of the project and its operational criteria,

assessment of service and welfare buildings have been finalised with the planners

and the same has been provided in this report. The provisions has been finalised

considering the existing available services and the requirement for enhanced

production capacity. Provision has been made for new excavation workshop

complex and E&M workshop complex to cater the future requirement. Part of the

existing service buildings and welfare buildings will require expansion and some

additional service buildings and welfare buildings have been proposed to cater the

future need of the enhanced production.

14.3.2 Site of Service Building:

All the proposed service buildings will be located close to the mine and

preferably in non-coal bearing area where as the utility buildings will be located in

the demarcated area as indicated in the relevant plate.

14.3.3 Salient features of important service buildings:

To meet the daily requirement workshop complex area has been assessed

by E&M department with required facilities which have been elaborated elsewhere.

The detail provision along with their cost estimates have been indicated in Appendix-

A.2.1.

The salient features of some of the important service buildings are as follows:-

14.3.3.1 Workshop:

This workshop will provide support services for regular activity of the mine.

Workshop layout has been provided by E&M department considering requirements

as per deployment of departmental machineries. The proposed workshop should be

located at a suitable place near the operation activities and with due consideration of

non coal bearing area / minimum coal blockage.

Workshop structure has been envisaged predominantly with structural steel

construction i.e. structural frame with columns, bracing, trusses, purlins, louvers etc.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 14 / 3 of 7

Roofing is suggested with 0.8mm CGI sheeting and side covering with 0.63mm CGI

sheeting.

For natural lighting within the sheds thick translucent sheets of area up to

10% of covered area is to be provided in a staggered fashion. Other detailing within

the sheds will have to be finalised during detailed design with due considerations of

equipments and supporting services.

14.3.3.2 Store:

For the storage of essential materials required for the operational

requirement store complex has been provided. The store structure has been

envisaged predominantly to be structural steel framing and brick work construction

i.e. structural frame with columns, bracing, trusses, purlins, louvers etc. and covered

with brick walls. For natural lighting translucent sheets of area up to 10% of covered

area is to be provided in a staggered fashion. Detailing within the store has to be

finalised during detailed design considering the utilities.

14.3.3.3 Sub Station:

As per requirement of power supply, 132kV and 33kV substations with

outdoor structures have been provided which includes substation building to

accommodate various electrical equipments. The Substation buildings will be R.C.C

framed structure with well ventilation. Cable ducts are to be covered with steel

chequered plates. Foundation for heavy equipment is part of substation flooring and

the same are to be finalised with equipment load during detailed design.

For other structures following type of construction have been envisaged.

1. Project office: - RCC framed structure

2. Other buildings : - - do -

3. Dispensary : - - do -

4. Canteen: - - do -

5. Garage, Scooter & Cycle shed : - Steel structure with CGI roofing

6. Under ground reservoir: - RCC structure

7. Security post: - Brick masonry structure

8. Overhead tank : - RCC structure

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 14 / 4 of 7

14.3.4 Cost Estimate:

The details of cost estimate, as per prevalent cost index, against

service buildings have been elaborated in appendix A.2.1.

14.4 RESIDENTIAL BUILDINGS:

14.4.1 Provision of Houses:

The total manpower has been planned for different operational

combinations and the same has been indicated in different options. Considering the

existing houses, additional quarters as per B.P.E. guidelines has been provided. For

optimum utilisation of land all quarters should be of G+3 configuration.

14.4.2 Type of Construction:

Permanent specification for R.C.C. framed structure in poor soil has been

considered. All type quarters will preferably be (G+3) i.e., four storied in order to

reduce the land requirement. Garage provision has been provided for 50% of ‘C’

type quarters.

14.4.3 Site of Township:

The location of the additional quarters will be decided as per land availability

and non coal bearing area within the existing township.

14.4.4 Rain Water Harvesting

The concept of rain water harvesting involves ‘tapping the rain water where

it falls’. A major portion of rain water that falls on the earth’s surface runs off into

streams and rivers and finally into the sea.

The technique of rain water harvesting involves collecting the rain from

localized catchments surfaces such as roofs, plain/sloping surfaces etc., either for

direct use or to augment the ground water resources depending on conditions.

Among various techniques of water harvesting, roof rain water harvesting is

one of the appropriate options for augmenting ground water recharge/ storage.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 14 / 5 of 7

In a typical domestic roof top rain water harvesting system, rain water from

the roof is collected in storage vessel or tank for use during periods of scarcity. Such

systems are usually designed to support the drinking water and cooking needs

during the scarcity time and comprise a roof, a storage tank and guttering to

transport water from the roof to the storage tank. In addition, a flush system to divert

the dirty water, which contains debris, collected on the roof during non-rainy period

and a filter unit to remove debris and contaminants before water enters the storage

tank are also provided. The roof top rain water can also be used for recharging of

the ground water through recharge pits or putting into the dried bore wells/ open dug

wells.

14.4.5 Unit cost and Cost Estimate:

The details of cost estimate, as per unit cost with prevalent cost index,

against residential buildings have been elaborated in appendix A.2.2.

14.5 ROAD AND CULVERTS:

14.5.1 Colony Roads & Culverts:

Colony roads as per prevalent norms on the basis of additional houses have

been provided. Single lane bituminous road has been considered. Tentative cost in

respect of total road length including provision of culverts and tree guards etc. as per

norms have been elaborated in Appendix- A.8.2.1.

14.5.2 Haul Roads & Culverts:

As per mine lay out 4.6 Km haul road with culverts as per prevalent norms

have been envisaged for the departmental option. The detail cost estimates along

with tentative specifications have been elaborated in the Appendix A.8.2.3.

14.5.3 Approach Roads & Culverts:

To cater to the need of enhanced production 3.0 Km. long new approach

road has been envisaged in this report. The proposed approach road will be of

bituminous road and 7.5m wide. Culverts and drains have been proposed as per the

norm. The detail cost estimates along with tentative specifications have been

elaborated in the Appendix A.8.2.2.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 14 / 6 of 7

14.5.4 Service Roads & Culverts:

Provision has been made for 23m wide service road in the outsourcing

options only. A total length of 4.6Km service road has been proposed in this report.

Culverts and drains have been proposed as per the norm. The detail cost estimates

along with tentative specifications have been elaborated in the Appendix A.8.2.3.

14.5.5 Diversion of Non CIL Roads:

One major road namely the State Highway falls within the quarry boundary.

So, provision has been made for diversion of this road. A total length of 6.0Km road

diversion has been proposed in this report. The detail cost estimates along with

tentative specifications have been elaborated in the Appendix A.8.2.4.

14.5.6 Coal Transportation Road & Culverts:

Provision has been made for 7.5m wide coal transportation road in this

report. A total length of 5.0Km road has been proposed in this report. Culverts and

drains have been proposed as per the norm. The detail cost estimates along with

tentative specifications have been elaborated in the Appendix A.8.2.5.

Capital requirement against different roads have been elaborated in

appendix A.8.2.1 to A.8.2.5.

14.6 WATER SUPPLY AND SEWERAGE DISPOSAL

ARRANGEMENT:

14.6.1 Colony water supply and sewage:

Based on conventional norm for water supply, the total water demand for

this Project has been assessed. For domestic requirement 135 litres of water per

head for a family comprising of 5 members and for non-resident persons 45 litres

per head has been adopted. Detailed calculation of water demand has also been

provided.

The water demand has been envisaged to be met from deep bore wells.

Accordingly provision has been made for deep bore wells with under ground water

reservoir, pump house, over head water reservoir, pumps etc.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 14 / 7 of 7

In this report provision has been made for sewerage treatment plant. The

sewage from individual houses will be collected by conventional sewerage disposal

system which will be ultimately connected to the sewerage treatment plant.

14.6.2 Industrial water supply & sewage:

Total industrial water requirement for the mine has been assessed for

incremental production. Water for dust suppression, fire fighting and water sprinkling

on mine transport road has been considered.

This water demand has been envisaged to be met from quarry water.

Quarry water will be pumped and delivered to ground reservoir at different suitable

locations near industrial site. From ground reservoir water will be distributed to the

desired locations through pumping.

Industrial sewerage will be collected at a centrally located settling tank and

after settlement of industrial waste the supernatant liquid is to be disposed of in

nearest natural water course.

Provision has been made for Effluent treatment plant for treating the total

effluent generated.

14.6.3 Capital Requirement:

Capital requirement against colony water supply and industrial water supply

has been elaborated in appendix A.8.3.

Capital requirement against colony sewerage and industrial sewerage has

been elaborated in appendix A.8.3a.

14.7 SURFACE REORGANISATION AND REHABILITATION, IF

ANY:

This aspect has been dealt separately in the Mining write-up portion.

14.8 CONSTRUCTION MANPOWER :

For different options essential manpower required to run regular mining

activity has been considered.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 1 of 21

CHAPTER-XV

SAFETY AND CONSERVATION

15.1 DEGREE OF GASSINESS

Since it is an opencast mine, degree of gassiness is of no relevance at

present.

15.2 SAFETY MEASURES AGAINST INUNDATION FROM RAIN WATER Adequate pumping capacity has been provided to deal with strata and

surface water. At the same time, diesel pump set has also been provided

to pump out water to the sump from temporary accumulated site.

15.3 DUST SUPPRESSION

Major source of dust in opencast mine operation have been identified in

haul roads due to traffic, due to spillage from dumpers and abrasion by

their wheels. Provision of adequate nos. of water sprinklers and adequate

lengh fixed type of water sprinkler have been made for spraying of water

on haul roads to prevent emission of dust. Haul roads and other heavy

duty roads likely to be negotiated by heavy vehicles and equipment have

been proposed to be metalled and coated to facilitate control of emission

of dust.

The drills to be engaged is to be equipped with dust arrester so that dust

emission is minimum. As the blasting is not continuous one and while

blasting, persons will be removed to the safe zone to reduce exposure to

dust created due to blasting. At siding, sufficient arrangements have been

provided to suppress coal dust at vulnerable points.

15.4 SLOPE STABILITY

SPOIL DUMP

The spoil will be stacked in the external and internal dump space at the

natural angle of repose to avoid the sliding of OB bench. The OB dump

will be terraced at the height of 30m. The barrier distance between internal

dump and coal production bench will be 100 m to have smooth functioning

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 2 of 21

of machineries. The surface of OB dump will be leveled and graded.

Plantation will be made on the slope of OB heap to avoid the sliding of

spoil once OB heap becomes non-active.

The slope stability study should be done. According to study report the

dump design like dump bench height, berm width, total dump height &

slope etc. should be modified to avoid internal dump failure. In addition to

that proper precautions / observations should be taken to avoid sliding of

internal OB bench.

Dumping of soil and clayey material should be on the top of dump.

Final regrading of internal dumps is done in such a way that rain water is

drained outside the mine through drains and culverts. Proper monitoring

system shall be used for internal dump stabilization to avoid sliding of OB

dump.

15.5 HAUL ROAD MAINTENANCE

Haul road for dumper / tipper has been designed double lane with

shoulders on both side for movement of dumper and ancillary equipment.

Sharp turnings to be avoided to reduce the chance of any accident. The

access trench is graded to 6% slope. The ramp from one bench to another

bench is graded at 1 in 10 slopes.

15.6 BLASTING

For blasting crews, the blasting shelter has been provided. To reduce the

chance of fly rock and misfire, the optimum blasting pattern is to be

developed by trial. In view of the safety of the villages / public / mine

infrastructure against blasting hazards like fly rocks, ground vibrations etc.

proper safe distance has been kept from the mine working.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 3 of 21

However, when the mine working reaches near to the village

boundaries/mine infrastructure, controlled blasting will be adopted

alongwith other necessary precautions laid down by the DGMS. Misfire if

any, should be handled cautiously

15.7 CONSERVATION OF COAL

The coal recovery within panel excluding barriers is 60% and 80% to 85%

of extractable coal by Bord & Pillar Method and Longwall Method of

underground mining respectively. On the other hand, coal recovery is

almost 100% by opencast mining method. And so wastage of natural

resource is almost nil in opencast mining method.

The OB bench cut working will be kept sufficiently advanced in respect to

the coal bench working to avoid mixing of OB into the coal during blasting.

At the same time, the coal bench surface will be cleaned initially by dozer

and thereafter by surface miner to avoid dilution and contamination of

coal.

15.8 ADDITIONAL PERMISSION / RELAXATIONS REQUIRED FROM DGMS SAFETY ASPECTS FOR OUTSOURCING / HIRING OF HEMM /

EQUIPMENT Outside agency deploying HEMM or any equipment in the mine for

excavation of coal shall plan their activities in confirmation with the

prevailing statutory provisions as per Mines Act 1952 and CMR 1957

applicable for safety in opencast mines.

However, all statutory rules, regulations, applicable laws etc. and statutory

requirement related to Govt. licenses, workers compensation, insurance,

etc., including minimum wage act for workers employed by the outside

agency shall have to be adhered to.

Rules if any imposed by local / state / central authorities should also be

complied by leaser of HEMM / equipment and then shall have to supply

various protective equipment viz., helmet, shoes etc. to the workmen at

their cost.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 4 of 21

All the regulations and schedules of Coal Mines Regulations 1957 relating

to opencast mining have to be adhered to and implemented in order to

maintain day to day safety precautions as per stature.

Special precaution should be taken while deploying workers in the mine.

Before employing any worker to the mine proper vocation training should

be imparted and recommendations of VIII Safety Conference should be

strictly followed. Terms and conditions shall be fixed by management for

deployment of workers by outside agency. Some of the major aspects are

as follows: -

A) For Persons :

i) No persons shall be deployed unless he is trained at VTC.

ii) Records in Form-B, Form-D shall be maintained.

iii) Records of Vocational Training Certificate and driving license of

operators shall be kept by HEMM outsourcing agency and shall be

made readily available for inspection by management.

iv) Salaries shall be distributed in front of management

representative.

v) No person shall be employed unless person holds VTC certificate

and management is informed. A record of it shall be maintained.

vi) Adequate supervision shall be maintained by qualified competent

persons.

vii) Outside agency shall follow safety guidelines and safety

instructions from project authorities.

B) For Machineries as recommended by DGMS Cir. (Tech.) 1 of 1999 :

i) All the machineries to be deployed in mines should be checked

before deployment by competent authority.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 5 of 21

ii) Regular checking of m/c deployed by outside agency shall be

done. No unfit machine shall be deployed before the defect is

rectified.

iii) A proper record of repair and maintenance along with inspection

done by management and defect pointed out shall be maintained

and signed by authorized person.

iv) The trucks deployed outside agency shall be provided with audio

visual alarms, proper light for use at night and period when

natural light is not sufficient. Also audiovisual alarms for

reversing on trucks shall be provided.

Other precautions for machines

i) RTO certificate photocopies of all vehicles shall be submitted to

management.

ii) Daily welding, monitoring, inspection shall be done by the

agency’s mechanic as directed by management.

iii) Machine manufacturers should be asked to give risk analysis

details in respect of machines deployed by outside agencies.

iv) Suitable type of the fire extinguishers shall be provided in every

machine.

C) General :

i) No person / vehicle shall be deployed at any place other than authorized place.

ii) All workers should obey lawful instruction of mine management.

iii) Risk Management Plan of tipper / pay loader shall be made and implemented.

iv) All drivers shall obey systematic traffics rules prepared by management.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 6 of 21

v) Before deploying workers, they must be trained and briefed about

safety aspects in opencast mine. However, during course of

execution of the work, if any accident occurs whether major or

minor, the matter shall have to be immediately informed to mine

management i.e. Colliery Manager / Agent / GM of Area, so that,

notices of accidents in accordance of (Reg.9 of CMR 1957) and

Section 23 of Mines Act 1952 may be given and other necessary

steps may be taken in accordance with the Mines Act 1952.

vi) Outside Agency shall operate transport system in such a way so

as to minimize pollution in the mine.

Recommendations of 11th conference on Safety in Mines held on 4th & 5th July, 2013 at New Delhi.

The related recommendation of XIth Conference on safety in mines is to

be followed while implementation of project report.

1. Review of status of implementation of recommendations of 10th

Conference on Safety in Mines.

The committee unanimously decided to carry forward the following Para of the

recommendations of the 10th Conference on Safety in Mines, namely:-

1.1(a) Necessary facilities for monitoring the environmental parameters in

respect of Methane and Carbon Monoxide should be provided at

mines. Facilities of continuous type monitoring should be installed

within two years in all degree III gassy COAL and in such other mines

having active underground fire.

1.1(b) Indigenous manufacturers should be encouraged to manufacture

necessary equipments.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 7 of 21

1.1(c) Time bound programme is to be made, which should be decided in a

tripartite committee at company level.

1.2 In underground specified mines where long or arduous travel is

involved, arrangement for transport of men should be made with a

target of 20 % every year.

1.3(a) In respect of small-mechanised mines, which are operating in NON-

COAL sector, it may not be feasible for a small organization to create

a special department on Occupational Health Services. For such small

mines, it is suggested that an Association of small mines operators

creates common facilities and infrastructure for occupational health

services. Creation of such facilities are specially needed for asbestos,

manganese and mica mines.

1.4 Development of a portable instrument for detecting hidden slips in

roof of COAL mines should be taken up on priority by R&D

organizations. The instrument should be developed by S&T project

which should be guided by a committee consisting of an officer from

DGMS and others from COAL Industry and Research Organisations.

1.8(a) Before the valid gate pass is issued for entry of trucks and other

vehicles not belonging to management into the mine, the mine

engineer should check the road-worthiness of such vehicles.

1.8(b) In order to check entry of un-authorized vehicles in mine premises,

each mine should establish property manned check gate(s) at the

entrance(s) where record of entry and exist of each such vehicle

should be maintained.

1.9(a) All persons engaged at any work within the mine premises through

the contractors have received relevant training and other job-related

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 8 of 21

briefings and that the drivers of vehicles belonging to contractors

entering the mine premises have additionally been explained the

salient provisions of "traffic rules".

1.9(b) Each mining company should draw up appropriate training schedules

and modalities in this regard and implement the same.

1.9(c) In case of smaller mines, such arrangement may be made by

association of mine operators.

1.11.1 Considering the risk of fire, all COAL mine companies shall rank its

COAL mines on a uniform scale according to its risk from fire on

scientific basis. Guidelines may be framed by DGMS and circulated to

all mining companies.

2.0 Contractor work vis-à-vis safety

2.0 Contractor work vis.-a-vis. safety

2.1 Employer's responsibilities

2.1(a) Suitable clauses (in consistence with risk of the work allotted) shall be

included in tender document (including NITs) stating how the risk

arising to men and material from the mining operation/operations to

be done by the contractors shall be managed.

2.1(b) Ensure that contractors are familiar with the relevant parts of the

statutes, health and safety management system and are provided

with copies of such documents prior to commencing work.

2.1(c) Ensure that contractor's arrangements for health and safety

management are consistent with those for the mine owner. All the

rules, regulations and bye-laws as applicable to the mine owner are

also applicable to the contractor. Details of the contractor's workmen

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 9 of 21

should be maintained in the owners Form-B register. Whereas as C, D

& E registers for contractor men may be maintained independently by

the owner and shall be kept in the mine office of the manager.

2.1(d) Ensure that contracts should preferably of longer period (3 years), so

that there is adequate scope of management of safety by the

contractor.

2.1(e) Ensure that contractors provide the machinery, operator and other

staff with written safe work procedures for the work to be carried out,

stating clearly the risk involved and how it is to be managed.

2.1(f) Monitor all activities of the contractors to ensure that contractors are

complying with all the requirements of statute and the system related

to safety. If found non-compliance of safety laws directing the

contractors to take action to comply with the requirements and for

non-compliance, the contractor may be suitably penalized. Clause to

this affect may be a part of the agreement between the employer and

the contractor.

2.1(g) Where a risk to health or safety of a person arises because of a

non-compliance directing the contractor to cease work until the non-

compliance is corrected.

2.2 Contractor's responsibilities:

2.2(a) Prepare written Safe Operating Procedure (SOP) for the work to be

carried out, including an assessment of risk, wherever possible and

safe methods to deal with it/them.

2.2(b) Provide copy of the SOP to the person designated by the mine owner

who shall be supervising the contractor's work.

2.2(c) Keep an up to date SOP and provide a copy of changes to a person

designated by the mine owner

2.2(d) Ensure that all work is carried out in accordance with the Statue and

SOP and for the purpose he may deploy adequate qualified and

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 10 of 21

competent personnel for the purpose of carrying out the job in a safe

manner.

2.2(e) For work of a specify scope/nature, develop and provide to the mine

owner a site specific Code of Practice (COP).

2.2(f) Ensure that all sub-contractors hired by him comply with the same

requirement as the contractor himself and shall be liable for ensuring

the compliance all safety laws by the sub or sub-sub contractors.

2.2(g) All persons deployed by the contractor for working in mine must

undergo vocational training, initial medical examination, PME. They

should be issued cards stating the name of the contractor and the

work and its validity period, indicating status of VT & IME.

2.2(h) Every person deployed by the contractor in a mine must wear safety

gadgets to be provided by the contractor. If contractor is unable to

provide, owner, agent and manager of the mine shall provide the

same.

2.2(i) The contractor shall submit to DGMS returns indicating -Name of his

firm, Registration number, Name and address of person heading the

firm, Nature of work, type of deployment of work persons, Number of

work persons deployed, how many work persons hold VT Certificate,

how many work persons undergone IME and type of medical coverage

given to the work persons. The return shall be submitted quarterly (by

10th of April, July, October and January) for contracts of more than

one year. However, for contracts of less than one year, returns shall

be submitted monthly.

2.3 Employees Responsibilities

2.3(a) An employee must, while at work, take reasonable care for the health

and safety of people who are at the employee's place of work and

who may be affected by the employee's act or omissions at work.

2.3 (b) An employee must, while at work, co-operate with his or her

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 11 of 21

employer or other persons so far as is necessary to enable compliance

with any requirement under the act or the regulations that is imposed

in the interest of health, safety and welfare of the employee or any

other person.

3.0 Safety issues in mines in un-organised sector

3.2 In case of stone quarried on hillocks, whole of the hillock should be

given out as a single lease so that necessary development could be

done from top-downwards after making approach road to reach to top

of the hillock before starting extraction of stone. A condition to this

effect may be incorporated before granting such leases.

3.3 In the lease document, reference should be made to the Mines Act

and the Rules and Regulations made there under for compliance. The

DGMS may prepare, in consultation with Ministry of Mines a model

document for grant of leases by the state governments so that the

conditions of leases are such that there is a uniformity and compliance

with central laws.

3.4 A copy of the lease document should be sent to the DGMS and lessees

explicitly asked to send notice of opening of mine to DGMS in

accordance to the Provisions of the Mines Act.

3.5 The Conference has noted that there have been instances in some

States where leases have been granted in close proximity of inhabited

area and within 45 m. of Railway acquired land and land acquired for

National and State highways, public works without consulting the

appropriate statutory authority. The conference recommends that the

States may grant mining leases in conformity of Central Laws.

3.6 DGMS should organize Orientation Programmes for officers of State

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 12 of 21

Mines and Geology Departments to inform them about safety laws.

4.0 Occupational Health surveillance and Notified Diseases

4.1 Noise mapping should be made mandatory of various workplaces in

the mine premises based on the various machines being used in

concerned mines along with personal noise dosimetry of individual

workmen exposed to noise level above 85 dB(A).

4.2 Vibration studies of various mining machineries before their

introduction in mining operation should be done as per ISO

Standards.

4.3 Ergonomical assessment of all latest machines, before their

introduction into mining operation as per ISO standards. Ergonomical

assessment should include:

* Assessment of work process.

* Assessment of working Aids/tools

* Assessment of working posture.

4.5 Portability tests of drinking water supplied to the mine employees, to

be made mandatory once in a year irrespective of its source,

preferably after Rainy seasons, the sample of water should be

collected from the points of consumption.

4.7(a) In addition to measurement of blood pressure, detailed cardiovascular

assessment of employees should be done. This should be include 12

leads electrocardiogram and complete lipid profile.

4.7(b) Detailed neurological examinations including testing of all major

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 13 of 21

superficial and deep reflexes and assessment of peripheral circulation

to diagnose vibrational syndromes.

4.7(c) In addition to routine urine, fasting and post-prandial blood sugar

should be included for early diagnosis of diabetes mellitus.

4.7(d) Serum Urea Creatinine should be included for assessment of Renal

function.

4.8 Special tests should be included in the PME for employees exposed to

specific health hazard:

4.8(a) For employees exposed to manganese, special emphasis should be

given to behavioural and neurological disturbances such as speech

defect, tremor, impairment of equilibrium, adiadochokinesia H2S and

emotional changes.

4.8(b) For persons exposed to lead, PME should include blood lead analysis

and delta aminolevulinic acid in urine, at least once in a year.

4.8(c) Employees engaged in food handling and preparation and handling of

stemming material activities should undergo routine stool examination

once in a every six months and sputum for AFB and chest radiograph

once in a year.

4.8(d) Employees engaged in driving/HEMM operation jobs should undergo

eye refraction test at least once in a year.

4.8(e) Employees exposed to ionizing radiation should undergo blood count

at least once in a year.

4.9(a) All other types of Pneumoconiosis excluding Coal workers

pneumoconiosis, silicosis and asbestosis. This include Siderosis &

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 14 of 21

Berilllyosis

4.10 For smaller mines where PME facilities are not existing, medical

examinations can be done through other competent agencies.

5.0 Mechanisation with view to phase out manual loading etc.

5.1 Keeping in view the objective of phasing out manual loading, all COAL

companies shall identify appropriate technology suitable for the

prevailing geo-mining conditions and introduce the same in such a

manner so as to phase out manual loading operation completely within

a period of five years in COAL seams with gradient of 1 in 5 or less,

within a period of seven years where gradient steeper than 1 in 5.

5.2 While formulating the strategies for face mechanization in

underground workings, it shall be ensured that back facilities like

COAL evacuation, support system, ventilation arrangements etc. are

compatible with face mechanization.

5.3 The scheme of face mechanization shall be based on proper scientific

investigation. The scheme shall also include arrangements for

monitoring strata behaviour and environmental conditions.

5.4 Possibility of deployment of multi-skilled miners in the face shall be

explored to reduce the exposure at hazardous areas without

affecting employment.

5.5 Suitable training for efficient and safe operation of machinery shall be

imparted to all concerned.

5.6 While planning for face mechanization, due considerations shall be

given for long term sustainability of the technology.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 15 of 21

6.0 Reduction from risk from roof and sides falls in coal mines

6.1 In every Coal mining company, STRATA CONTROL CELL shall be

established at corporate and area levels within a period of one year, to

assist mine managers, for formulation of Systematic Support Rules,

monitoring strata control measure in a scientific way to ensure

efficacy of support system and for procurement/supply of quality

supporting materials. Such cell shall be manned by adequate number

of technical personnel headed by a senior official not below the rank of

General Manager at Corporate level and Dy. General Manager at Area

level.

6.2 Roof bolting shall be used as a primary means of support for freshly

exposed roof in development as well as depillaring districts. For the

roof category Poor, having value of RMR of 40 or less, or where there

is excessive seepage of water from the roof strata, roof bolts

exclusively with resin capsules shall be used to ensure adequate &

immediate reinforcement of the strata.

6.5 To ensure proper drilling for roof bolting in all types of roof strata,

suitable fit-for-use roof bolting machines shall be introduced in all

mines within a period of one year. Such machines shall be capable of

being operated from a distance or be provided with suitable canopy to

protect the supporting personnel during drilling or bolting operations.

6.6 Risk assessment exercise shall be carried out in the mines for

assessing for risk from the hazards of roof and sides falls and

identifying the control mechanism with specific responsibility for

implementation. This exercise shall be reviewed at regular intervals

not exceeding a year.

6.7 Each company shall take steps to impart structured training to officers,

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 16 of 21

supervisors and support personnel on roof bolting.

8.0 Below ground communication and tracking system

8.2 Mining companies in collaboration with research institutions/equipment

manufacturers shall initiate and fund for, suitable research initiatives

for establishment of appropriate communication system for below

ground mines including to locate the trapped miners.

8.3 Mine management in collaboration with equipment manufacturers shall

evolve a system of proximity warning device in HEMM and initiate

measures for its implementation.

9.0 Safety Management system” Strategies for implementation and

path forward.

9.1 Every mine should employ a sound risk analysis process, should

conduct a risk assessment, and should develop a safety management

plan to address the significant hazards identified by the analysis /

assessment.

9.2 The managements of every mining company should adopt the process

of safety management system and commit itself for proper formulation

and implementation of the same in totality. Necessary resources

should be allocated for implementation of the control measures

identified by the risk assessment process.

9.3 Necessary training of all employees of Mining Companies should be

organized with the help of experts, both national and international, for

optimal adoption of safety management system.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 17 of 21

10.0 Implementation of ILO convention No. 176 in Mines

10.0 The committee decided that a separate discussion be held by the

Govt. of India in a tripartite forum to deliberate on the implications

arising out of ILO Convention No. 176.

Small Scale Mining

(1) The concerned authority in State Government may grant prospecting

lease/mining lease/ mining right after ascertaining technical feasibility of

mineral extraction in pursuance with provisions of the mining law, so that

the lessee can make medium to long-term plan for investment in

infrastructure and work the mines in a safe and scientific manner. While

conduct of mining operations, it should be ensured that the Central Laws,

including the Mines Act are complied with.

(2) The State Governments may explore the feasibility of demarcation of

mining zones to avoid problems of growing habitation encroaching into

the mining area, thereby creating unsafe and unhealthy conditions.

However, the State Government may take efforts to relocate the

habitation already existing near mining zones.

(3) The lease granting authority of State Government may assign a unique

identification number, which will serve as a common reference for all

central and state authorities responsible for administration of central and

state laws.

The details of lease may be displayed in a board of permanent nature in a

prominent place in the lease hold are showing following:

a. Name of lessee:

b. Lease number:

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 18 of 21

c. Period of lease:

d. Unique identification number:

(4) The lease granting authority of State Government may insert a clause in

the lease document requiring the lessee to submit a notice of (i)

commencement of any mining operation, and (ii) appointment of a

manager, prescribed under the Mines Act, 1952 and Rules and

Regulations framed there under.

(5) The concerned authorities of State Government may be requested to

explore the possibility of introducing a course in Mining at Industrial

Training Institutes in consultation with DGMS to augment the requirement

of Mining Mates.

(6) Orientation Programmes may be organized for officers of State Mine and

Geology Departments on OSH Laws.

(7) Organized mines of public and private sector may consider extending their

facilities in Vocational Training, Occupational Health Surveillance and other

Safety Awareness Programmes for workers engaged in small scale mining

sector.

(8) As a promotional initiative, social dialogue and deliberations at appropriate

level may be initiated to facilitate formation of Cooperative Society/Mine

Owners Association to tackle issues of resource and logistics management

essential for safe and healthy mining.

(9) The Conference appreciates the efforts made by Ministry of Labour &

Employment and Directorate General of Mines Safety for encouraging and

adopting innovative means to create awareness about OSH issues and

improving compliance in small scale mining sector with public private

interventions. It is recommended to continue with such initiatives

vigorously and in enhanced manner.

(10) The concerned authorities may explore possibilities of setting up of Mine

Workers Welfare Boards for minerals like sandstone, marble and granite.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 19 of 21

Safety, Health and Welfare of Contractual Workers.

(1) The recommendations made in the 10th conference on Safety in Mines

regarding safety, health and welfare of contractor’s workers shall be

complied within two years. Owner, Agent and Manager shall be

responsible for ensuring compliance at the their respective mines.

(2) There shall be provisions for modifications in Notice Inviting Tenders

(NITs) to fulfill the requirement of statute/circulars issued by DGMS from

time to time subsequent to the finalization of NITs also.

(3) The contractor shall not employ or terminate his worker without the

knowledge of the mine management.

(4) Payment to contractor’s workers including leave with wages shall be made

through bank only.

(5) In case of non-routine type of work in the mine a Work-Permit system,

outlining the precautions to be adopted, SOPs, supervision, persons

responsible for the job etc., shall be adopted.

(6) Each company shall frame a safety, health and welfare policy for their

contractor’s workers keeping in view the requirement of Mines Act and

Rules & Regulations made there-under. The details of the policy shall be

included in the tender document which will be a binding clause for the

contractor.

(7) Each mining company shall extend all benefits including medical facilities

and payment of wages, to contractor’s workers receiving injury whilst on

duty. Owner, Agent and Manager shall be responsible for ensuring

compliance at their respective mines.

(8) Medical facilities shall be extended to contractor workers.

(9) Central Government should take steps against non-compliance of the

recommendations of the National Safety Conferences.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 20 of 21

Surface and Underground Transportation Machinery:

(A) MACHINERY FOR SURFACE OR OPENCAST OPERATIONS

(a) Mine Planning & Design

The provisions of requirements of HEMMs and their installations,

operations, maintenance and training shall be included in the project at

planning stage.

(b) Safety Features in HEMMs

(i) Audio-Visual Alarm

The sound level of AVA should be at least 5 to 20% higher than the

ambient noise level; and

The audio frequency and its amplitude band should be increasing and

uniquely heard to keep persons alert in the blind zone during reversal.

AVA should be of IP 67 compliance.

(ii) Anti-Skid and Tail-End Protection System

The provision of tail end protection, bumper extension or any other device

shall be provided in dumpers/tippers to prevent collision both head on and

head to tail conditions.

(iii) GPS-GSM Based Navigation System

The GPM-GSM based vehicle navigation system shall be used in large

mines in a phased manner.

(c) Risk Control and Management

Risk Assessment and Control of Risks should be conducted by the mine

management quarterly and annually.

(d) Skill Development and Training

General Skill Development programme should be undertaken for training of

operators and all other associated staffs using state of the art technique

including simulation and 3D Virtual Reality system.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 15 / 21 of 21

(e) Protection against Fatigue

(i) Long or Extended Hours of driving beyond 8 continuous hours with a rest

interval of half an hour after four hours of continuous operation, shall not

be permitted, for which biometric system of check-in & check-out system of

attendance associated with suitable software shall be introduced in the

mine.

(ii) Additional warning system for operator’s fatigue should be provided in the

machine.

(iii) Operator’s Seat in the Vehicle/HEMMs should be ergonomically designed to

have adequate comforts while driving continuously.

(B) TRANSPORTATION MACHINERYIN UNDERGROUND:-

(a) All steam winders should be replaced with electric winders in phased

manner within a period of five years.

OR

Alternate access to the mine in the form of Inclines or Shafts may be

considered and implemented within the same period.

(b) Safety Features in Winding

Detail survey of all winding installation completed 20 years shall be carried

out by committee of experts and its recommendations shall be

implemented.

(c) Man-Riding System

DGMS should initiate necessary steps to frame suitable standard for man

riding system within a period of 18 months through an expert committee.

(d) Use of Diesel Equipment belowground in Coal Mines

An expert committee may be appointed to examine and frame standards

and safety provisions for diesel equipment in belowground both coal and

non-coal mines.

*******

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 1 of 24

CHAPTER-XVI

ENVIRONMENT MANAGEMENT

16.1 Existing Environment Quality

Amadand OCP Expansion is located in the south-eastern part of Sohagpur

Coalfields (J&K area) of South Eastern Coalfields Limited (SECL). This area consists of

Bartarai, Balkuni, Amadand East U/G and Amadand West U/G blocks in Anuppur district

of Madhya Pradesh. These blocks cover an area of 15.061 sq km and are bounded by

North latitudes 23O07'28" & 23O09'46" N and East longitudes 82O02'04" & 82O04'53" and

included in Survey of India Toposheet No. 64 I/4 (RF1:50,000). Environmental base line

data for Amadand OC Expansion, generated in the year of 2014, are utilized for

preparation of this Chapter.

16.1.1Ambient Air quality in core and buffer zone

To assess the ambient air quality, six monitoring stations were fixed on the basis

of physiography of the area, meteorological parameters like predominant wind direction,

wind speed etc. The air quality data generated for the period December 2013 -March

2014 indicates that the SPM, RPM, SO2, & NO2 values in respect of the stations given

in table below.

Table 16.1 (a) Locations for observation & reasons for selection

Sl.No Location Distance,Km Direction

Reasons for selection (W.r.t centre of core zone)

1.0 Amadand

OCP, Mine office – (A1)

- Within

mine area

To assess pollution levels in the mining area.

2.0 Amadand –

(A2) -

Within mine area

To assess pollution levels in the village within the mining area

3.0 Dadaibahra–

(A3) 5.0 Northwest

To assess the pollution levels in the village area.

4.0 Phulwaritola

– (A4) 4.0 Northeast

To assess the pollution levels in the village area in the up-wind direction.

5.0 Chhapratola

– (A5) 5.0 Southeast

To assess pollution levels in the village area.

6.0 Bhad – (A6) 5.0 Southwest

To assess the pollution levels in the village area in the down-wind direction as control

station.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 2 of 24

Table 16.1 (b) AIR QUALITY STATUS

Period: Dec’13- March’14 (In µg / cum)

Category Location Name

&

Code

Min. Max. 98th %

Value AM GM SD

MoEF/

CPCB

Limits

Suspended Particulate Matter (SPM) Concentration

Industrial Mine Office – A1 441 480 472 461.92 461.84 8.77 500

Residential

Amadand – A2 178 190 189 184.42 184.38 3.50

200

Dadaibahra – A3 163 185 180 172.25 172.19 5.00

Phulwaritola – A4 165 186 185 180.42 180.34 5.35

Chhapratola – A5 175 188 187 182.54 182.51 3.67

Bhad – A6 178 190 189 184.67 184.64 3.38

Respire able Particulate Matter (PM10) Concentration

Industrial Mine Office – A1 213 230 227 221.75 221.71 4.08 250

Residential

Amadand – A2 83 91 90 87.79 87.76 2.26

100

Dadaibahra – A3 78 88 86 83.43 83.40 2.31

Phulwaritola – A4 75 88 87 84.63 84.57 2.98

Chhapratola - A5 83 90 90 87.21 87.18 2.08

Bhad – A6 83 91 90 87.96 87.93 2.20

Respire able Particulate Matter (PM2.5) Concentration

Industrial Mine Office – A1 123 134 132 129.08 129.06 2.60 -

Residential

Amadand – A2 48 54 53 51.04 51.01 1.76

60

Dadaibahra – A3 45 51 50 48.11 48.08 1.49

Phulwaritola – A4 47 53 52 50.33 50.31 1.52

Chhapratola - A5 48 53 52 50.54 50.52 1.41

Bhad – A6 48 54 53 51.21 51.18 1.64

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 3 of 24

Category Location Name &

Code

Min. Max. 98th % Value

AM GM SD MoEF/ CPCB Limits

Sulphur Dioxide (SO2) Concentration

Industrial Mine Office – A1 16.6 22.3 21.5 20.48 20.44 1.19 120

Residential Amadand – A2 12.6 18.3 17.5 16.48 16.43 1.19 80

Dadaibahra – A3 10.7 16.2 16.0 14.69 14.59 1.61

Phulwaritola – A4 11.2 16.2 16.1 15.01 14.96 1.20

Chhapratola - A5 13.5 17.8 17.7 16.57 16.53 1.13

Bhad – A6 13.8 17.8 17.7 16.61 16.57 1.09

Nitrogen Dioxide (NOx) Concentration

Industrial Mine Office – A1 23.2 29.2 28.7 27.40 27.37 1.31 120

Residential Amadand – A2 20.3 26.3 25.8 24.50 24.20 1.31 80

Dadaibahra – A3 20.3 25.8 25.7 24.36 24.20 1.63

Phulwaritola – A4 21.3 25.8 25.7 24.48 24.20 1.31

Chhapratola - A5 23.8 27.1 26.9 25.89 24.20 0.97

Bhad – A6 23.5 27.1 27.0 25.77 24.20 1.11

In general, all SPM, RPM, SO2 and NOx values are found to be within the prescribed

limits of CPCB for Residential and rural area.

16.1.2 Water Quality

The general topography of the block has a gentle rolling topography with a general

slope in all directions from the central part of the area. The variation in surface elevation

is from 530 m to 550.01 m above MSL. The area has a radial drainage pattern while the

major part of the area is being drained by channels of Kewai River, a tributary to Son, the

channels in the north eastern part of the area discharge its water into Hasdeo River, a

tributary to Mahanadi. There are also a number of ponds in the area.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 4 of 24

Table 16.2 (a)

SAMPLING LOCATION AND THEIR RATIONALE

Sl. No.

Location Reasons for selection

1. Amadand, Bore Well

To assess the ground water quality near mine area.

2. Phulwaritola, Hand Pump

To assess the ground water quality near mine area.

3. Amadand OCP, Sump water

To assess mine water quality

4. Amadand OCP, Discharge water

To assess mine water quality

5. Bakkhi nala U/S To assess the river water quality

6. Bakkhi nala D/S To assess the river water quality after contamination with mine discharge.

Water quality status of surface and ground water

The summarized water quality data for the period Dec’13 – March’14 is given

below in table 16.2(b) & (c). The water quality data of different locations are found to be

within the permissible limit of CPCB.

Table 16.2(b) SURFACE WATER AT A GLANCE Period: Dec’13 – March’14

Sl. No.

Parameters

Concentration Range & Norms

Result IS: 2296-1982

(Inland Surface Water) Class C

1 pH 7.26 - 7.34 6.5 - 8.5

2 Total Dissolved solids, mg/l 772 - 780 1500

3 Dissolved Oxygen, mg/l 5.4 - 5.5 4 (minimum)

4 BOD, 5 Days @ 20OC, mg/l 2.7 - 2.8 3.0

5 Chloride (as Cl), mg/l 72 - 76 600

6 Fluorides (as F) ,mg/l 0.58 - 0.60 1.5

7 Sulphate (as SO4), mg/l 26 - 28 400

8 Nitrate (as NO3) ,mg/l 11.4 - 12.2 50

9 Zinc (as Zn) ,mg/l 0.10 - 0.12 15

10 Iron (as Fe ) , mg/l 0.38 - 0.40 50

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 5 of 24

Table 16.2(c) Period: Dec’13 – March’14

GROUND WATER QUALITY AT A GLANCE

(In comparison to drinking water standard)

At all locations, well within the prescribed norms of IS: 2296 and IS: 10500.

Sl. No.

Parameter

Result IS: 10,500 - 1991 Norms*

Amadand Borewell

Phulawaritola hand pump

1 pH 7.32 6.86 6.5 – 8.5

2 Colour, Hazen 5.0 4.0 5/25*

3 Odour Unobjectionable Unobjectionable

4 Turbidity, NTU 5.0 4.0 5/10*

5 Total Dissolved Solids, mg/l 118 106 500/2000*

6 Residual free Chlorine, mg/l <0.04 <0.04 0.2 (Minimum)

7 Chloride (as CI), mg/l 12 17 250/1000*

8 Fluoride (as F), mg/l 0.56 0.42 1.0/1.5*

9 Sulphate (as SO4), mg/l 8 6 200/400*

10 Cyanide (as CN), mg/l <0.01 <0.01 0.05

11 Phenols (as C6H5OH), mg/l <0.001 <0.001 0.001/0.002*

12 Chromium (as Cr 6+), mg/l <0.01 <0.01 0.05

13 Copper (as Cu), mg/l 0.03 0.03 0.05/1.5*

14 Selenium (as Se), mg/l <0.01 <0.01 0.01

15 Arsenic (as As), mg/l <0.05 <0.05 0.05

16 Cadmium (as Cd), mg/l <0.01 <0.01 0.01

17 Mercury (as Hg), mg/l <0.001 <0.001 0.001

18 Lead (as Pb), mg/l < 0.01 < 0.01 0.05

19 Zinc (as Zn), mg/l 0.02 0.03 5/15*

20 Alkalinity (as CaCO3), mg/l 52 46 200/600*

21 Iron (as Fe), mg/l 0.08 0.10 0.30/1.0*

22 Hardness (as CaCO3), mg/l 49.80 27.33 300/600*

23 Calcium (as Ca), mg/l 15.0 6.0 75/200*

24 Magnesium (as Mg), mg/l 3.0 3.0 30/100*

25 Nitrate (as NO3), mg/l 10.36 8.28 45/100*

26 Manganese (as Mn), mg/l 0.04 0.03 0.10/ 0.30*

27 Boron (as B), mg/l <0.10 < 0.10 1 / 5*

28 Aluminum (as Al), mg/l < 0.02 < 0.02 0.03/0.20*

29 E. Coli, MPN/100ml Absent Absent Absent

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 6 of 24

16.1.3 Noise level

The day and night noise level data (Leq Values) at mine area and villages around

are given below

Table 16.3 (a)

SAMLING LOCATION AND REASONS FOR SELECTION

Sl.No Location Distance,Km Direction

Reasons for selection (W.r.t centre of core zone)

1.0 Amadand

OCP, Mine office – (A1)

- Within mine

area

To assess Noise levels in the mining area.

2.0 Amadand –

(A2) -

Within mine area

To assess Noise levels in the village within the mining area

3.0 Dadaibahra–

(A3) 5.0 Northwest

To assess the Noise levels in the village area.

4.0 Phulwaritola

– (A4) 4.0 Northeast

To assess the Noise levels in the village area in the up-wind

direction.

5.0 Chhapratola

– (A5) 5.0 Southeast

To assess Noise levels in the village area.

6.0 Bhad – (A6) 5.0 Southwest

To assess the Noise levels in the village area in the down-

wind direction as control station.

Table 16.3 (b)

NOISE QUALITY STATUS Period: Dec’13 – March’14

Ca

tego

ry

Sl. No.

Location Name & Code

Average Noise Level

MOEF LIMITS

Day Time (06.00 AM to 10.00 PM)

Night Time (10.00 PM to 06.00 AM)

Day Time

Night Time

Indus-trial

1 Mine Office – N1 72.1 67.8 75 70

Re

sid

en

tia

l

2 Amadand – N2 53.1 42.9

55 45

3 Dadaibahra – N3

53.6 42.9

4 Phulwaritola – N4

53.1 43.1

5 Chhapratola – N5

52.1 41.4

6 Bhad – N6 53.1 42.9

The values are under permissible limit in dB (A).

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 7 of 24

16.1.4 Flora and Fauna

As per one season environmental baseline data generated (year: 2014) for preparation

of EMP of Amadand OCP, Flora & Fauna data has been taken into reference. Summary

of the flora and fauna study is given below.

The study area comprises of Tropical Moist Deciduous vegetation. Several tropical

elements can be seen scattered in the area. Shorea robusta, Anogeissus latifolia,

Tectona grandis were the most common species in forest. Acacia auriculiformis, Alstonia

scholaris, Bauhinia spp. and Cassia fistula were common in avenue plantation. Tree

species viz Mangifera indica, Dillenia aurea, Messua ferrera, Syzigium cumini, Terminalia

arjuna , Treama aurientalis, Diospyrous malabarica, Ficus racemosa, , Anogeissus

latifolia, etc. are found planted along the boundary of the agricultural lands and along the

road sides. Amadand mine lease area has running mine quarries and does not support

healthy vegetation. Main flora of the region includes plantation along the road side and

avenue plantation. The tree species observed in the area are, Albizia procera, Albizia

lebbek, Leucaena leucocephala, Delonix regia, Bauhinia variegate, Syzigium cumini, etc.

The major part of the study area lies under agriculture field and human settlements which

restrict the wildlife habitat significantly. Most of the mammalian species reported in the

study area are domesticated animals. There is neither any wildlife sensitive area nor any

corridor for the movement of wildlife is present in the study areas. Common Myna,

Kingfisher, Spotted dove and Pintail are some dominant bird species present in the study

area. Migratory movement of birds in the study area has not been reported. As far as the

reptile community was concerned, rat, snake, and house lizard are reported from the

study area.

Biodiversity conservation plan is developed with the aim to reduce the anthropogenic

pressure on natural resources due to accelerated pace of habitat change and natural

resource utilization. It needs a sustainable use and management of resources, identifying

and conserving critical habitats of wildlife and conservation of endangered and Schedule-

I species. Conservation plan also include the active participation of local communities.

The biodiversity management and conservation plan has been formulated considering

the wildlife (fauna and flora) profile of the region, customs, cultures & traditional rights of

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 8 of 24

locals, conservation significance of the area, and Biological Diversity Act (2002). Indian

Peafowl is present in study area having high conservation value.

16.1.5 Socio-economic Status

The project envisages 1443.01 Ha of land for quarry, infrastructure, residential

complex, safety zone and external dumps etc. This includes 702.379 Ha of land already

acquired for the existing Amadand OCP (1.15 Mty). Remaining 740.626 Ha land has to

be acquired for Amadand OC Expansion (1.15 to 4 Mty). The approximate number of

Project affected families likely to be rehabilitated is 1100. The families going to be affected

by acquisition of tenancy land / agricultural land are to be compensated economically and

jobs to the eligible land oustees / losers have to be provided as per M.P R and R Norms.

The Socio-economics data as per 2011 census are presented in table below

Parameters Total Study Area

Population 182549

Male (% of total population) 93504 (51.22%)

Female (% of total population) 89045 (48.78%)

Scheduled Caste ( % of total population)

25444 (13.94%)

Scheduled Tribes (% of total population) 47082 (25.79%)

Others (% of total population) 110023 (60.27%)

Literates (% of total population) 121110 (66.34%)

Illiterates (% of total population) 61439 (33.66%)

Main workers (% of total population) 44565 (24.41%)

Cultivators (% of main worker ) 6216 (13.95%)

Agricultural labourers(% of main worker ) 3862 (8.66%)

Household Industries Workers(% of main worker ) 912 (2.05%)

Others(% of main worker ) 33575 (75.34%)

Marginal workers (% of total population) 17042 (9.34%)

Non-workers (% of total population) 120942 (66.25%)

16.2 Environment Impact

16.2.1 Air Quality:

Impact assessment on air quality has been shown in table 16.4.

Table 16.4

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 9 of 24

Sl. No.

Parameters Impact Assessment

1.00 Meteorological Condition

Coal dumps are susceptible to fire, and Spontaneous combustion may occur therein; hence, there may be a likely change in ambient temperature, wind speed and direction to somewhat extent.

2.00 Ambient air quality

Type Impact

2.01 Direct Minimal increase in dust & noxious emission to the air owing to transport vehicles, Blasting, coal & dump handling causing to slight increase in the ambient SPM levels.

2.02 Indirect Surface coal transport & dump handling & Workshop will generate indirect impact in the long run

2.03 Short term

Drilling and Blasting may be attributed to slight increase in the ambient SPM levels

2.04 Long term

Surface coal transport, dump handling & Workshop will produce long term impact upon the air quality

16.2.2 Water Quality

Impact assessment on water is shown in table 16.5 below.

Table 16.5

Sl. No.

Parameters Impacts Assessment

1.00 Hydro-geological-Ground water

1.01 Topography & drainage

Topography and drainage by developing micro basins

1.02 Aquifer geometry Changes in aquifer geometry, water level in the vicinity of the mine and disturb ground water flow direction. This can also create secondary fractures and higher permeability zones within the aquifer. After the mining activity, the aquifer restores its original water level and mined out area acts as a good reservoir.

1.03 Water levels The project is an opencast mine, the impact of mining on local water levels will be limited to few hundred meters.

2.00 Water Quality- Physico-Chemical and Bacteriological ones

2.01 Ground Water Quality

Acceptable; No abnormality.

2.02 Surface Water Quality

-Do-

16.2.3 Ground Water Resource

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 10 of 24

Except for coal mining, no major industrial development activity is located in the

area. As per CGWB, NCC Region, Raipur, the total annual replenishable ground water

resource in the Anuppur Development Block, Shahdol district (where Amadand UG

proposed mine exists), was assessed as 68.20 M.cum. It was also reported that the ground

water development in the block is as 1.99 % and falls within category "Safe". As such, the

entire Madhya Pradesh & Chhattisgarh States are covered under the category “Safe”.

Fig 16.1

16.2.4 Noise Impact

Noise impact assessment has been shown in the following table 16.6.

Table -16.6

Sl. No

Parameters Impacts Assessment

1.00 Increase in Noise Levels at drilling and blasting

May have impact upon the workers and the nearby habitants. The impact of noise more than permissible dosage may cause Annoyance and irritation, Mental and Physical fatigue, Interference in normal activities, Health hazards resulting from impaired hearing. In extreme cases, cardio-vascular diseases etc., Task interference, Interference with communication i.e., masking.

2.00 Increase in Noise Levels at Operation of HEMMs like shovel, dumper, dozer, excavator etc.

Same as above

Natural losses 8.04

15.00%

Irrigation 5.36

10.00%

Domestic7.27

13.57%

Mine Discharge21.10

39.37%

Balance11.82

22.06%

Net Annual Groundwater Recharge Balance, Study Area Amadand OCP Expansion, Jamuna Kotma Area, SECL

(M.Cum, %)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 11 of 24

Sl. No

Parameters Impacts Assessment

3.00 Increase in Noise Levels at Operation of equipment in CHP, workshop etc

Same as above

4.00 Increase in Noise Levels due to transport system

Same as above

16.2.5 Flora and Fauna

Impact assessment on flora & fauna has been shown below in Table 16.7.

Table 16.7

Sl.No Parameters Impact Assessment

1.00 Negative

1.01 Vegetation Cover

Except the area such as used for quarry excavation, erection & development of plants, service & allied structures, colony, roads, diversions, culverts, etc, no other area is going to affected directly or indirectly by mining activities . Hence, impact on flora and fauna will not be of appreciable level.

1.02 Forests degradation

Forest areas are not going to be affected due to mining activities. Except the agricultural area used for quarry excavation, erection & development of plants, service & allied structures, colony, roads, drains, culverts, etc. Against this, 980.84 Ha of area will be generated by way of reclamation of dump areas, plantation in other available areas etc. By coal & OB transportation air pollution may affect photosynthesis and transpiration in plants by plugging their leaves pores. SO2 causes Necrosis disease in plants. Hence, no major impact on flora and fauna.

1.03 Ecological change

Being an opencast project, there is minor change expected in ecological parameters on which survival of flora and fauna depends directly or indirectly, and hence, expected impact on flora and fauna are not going to an appreciable level.

1.04 Hydro-geological aspects

Owing to opencast project, water level and draw down are likely to be affected to a nominal value; ground water and surface water on which the flora and fauna of the area directly or indirectly depend upon are not going to be affected to an appreciable level. After mine closure, the Mine void will act a stable water source for the flora & fauna.

2.00 Positive

2.01 Plantation work and forest & wild life conservation

Plantation work and forest & wild life conservation in a scientific way by project authorities in mine area will increase aestheticism of the area.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 12 of 24

16.2.6 Land Use

Impact assessment on land use has been shown below in Table 16.8.

Table 16.8

Sl. No.

Parameters Impact Assessment

Within mining area Outside mining area

1.0 Topography In the quarry area, the dump area and the mining equipment area, there will be a marked change in topography.

No appreciable damage is envisaged.

2.0 Change in Landscape and Land use pattern than pre-mining scenario such as visual impact-loss of aesthetic beauty, ugly scar on land; deforestation-loss of surface soil and vegetation cover

Total scenario of landscape land use pattern will undergo a stark change.

Landscape and land use pattern will change where erection and development of plants, service /allied services buildings are established.

3.0 Change in Surface Drainage.

There will be a stark change in surface drainage; rather new pattern of drainage will be developed.

Surface drainage is likely to change where construction of colony, roads and drainage are to be executed.

16.2.7 Impact on Socio-Economic Status

In the core zone there are four villages viz. Nimha, Timkitola, Kuhka and Majholi

located. The population predominantly comprises agriculture labour and non- workers.

The no. of PAFs is 1100. Rehabilitation & Resettlement of the PAFs will be done following

the State R & R Provisions & CIL R&R policies. The involved homesteads will be suitably

shifted in rehabilitation site of 50.80 Ha land. The population of the study area are

predominantly comprises with agriculture labor and marginal workers. The probable

impact on Socio-Economic Status of the study area is assessed below in table – 16.9.

Table-16.9

Sl.No Impact on Socio- Economic Status

1 Population Growth & In-migration

2 Human Settlement & Resettlement / Rehabilitation

3 Transport & Communication

4 Income & Employment

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 13 of 24

5 Civic Amenities& Community Development

6 Educational facilities & Literacy Drive

7 Economic growth

8 Growth of Financial Revenues (State & Central)

9 Social status growth

16.3 Environment Management

16.3.1 Air Quality Management

Following air pollution control measures are practiced within the mining area and at

coal handling plants and railway siding.

1. Water spraying is done regularly on approach roads within the mining area to minimise

the dust generation.

2. Dust suppression has been proposed at mine, with an additional provision of Rs.155

Lakh for the purpose. This includes provision of 6.0 km long Fixed Water Spraying

Arrangement. For siding, an additional amount of Rs.10 lakh has been provided for mist

water spraying at the siding.

3. Adequate plantation will be done along the width of the haul road and other road to

minimize transport generated pollutants. The distance of haul road provided is 4.6 Km.

4. Coal transportation to pit-top will be done by belt conveyors. Amadand railway siding

is proposed near pit-top.

5. Exposed overburden dumps will be covered through an appropriate plantation.

6. The drills are equipped with dust arresting devices or wet drilling arrangement.

7. Optimum blast-hole geometry is being followed to reduce the dust during blasting.

8. Regular monitoring of ambient air quality of project area.

16.3.2 Water Quality Management

Management of surface water drainage: -

Garland drains will be made around the periphery of the quarry to drain out the

water of catchment area into the reservoir. In the workings, heavy duty pumps will be

deployed in rainy season which after passing through settling ponds will throw the

accumulated water from the working face into these garland drains, which in turn will be

delivered into the reservoir.

Mine Water Discharge

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 14 of 24

The water quantity at the floor of mine sump to be collected in different stages

has been assessed at 10% probability. The maximum mine sump capacity is 415545

Cu.m. The sump water will be pumped out and discharged to the settling tank where

suspended solids will get settled. The clear water after sedimentation & treatment will be

recycled for water sprinkling, plantation & agriculture purpose, ground water recharge &

for use by the local villagers etc. Collected water, after settling tank will also be discharged

into the surface drain which in turn will deliver into the reservoir. Workshop effluents will

be recycled through Oil and Grease trap and sedimentation tank.

Domestic Effluent Treatment: -

The sewerage disposal system for the colony exists with conventional septic tank

and a soak pit arrangement. As a part of Environmental Control Measures in township

the money to be spent for Sewerage Disposal in Colony is 29.63 lakhs and for Sewerage

Treatment Plant is 400 lakhs.

Water Conservation: -

The waste water recycling after due treatment will enable conservation of water.

The clear water after sedimentation & treatment will be reused for water sprinkling,

plantation & agriculture purpose, ground water recharge & for use by the local villagers

etc. Workshop effluents will be discharged and treated through Oil and Grease trap and

sedimentation tank.

Storage of conserved water in mine pits would be given due emphasis to provide

water round the year and the quality of water would be maintained. The balance left mined

out area of 250.41 Ha would be treated as water body after mine closure. The maximum

depth of the void is 130 m from ground level. The water body would serve as a

considerable source of water for the use of local population after final closure.

Control measures adopted against impact on ground water regime:-

i) The impact will be limited to a smaller distance and for a temporary period. The effected

habitation will be provided with suitable drinking water supply by sinking hand pumps in

the habitat.

ii) The entire mine industrial water demand, would be met from the treated mine

discharge. The wastage of water will be minimized.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 15 of 24

iii) The surplus treated mine water will be discharge into the agricultural fields. Thereby,

the mine water will behave as constant source of recharge and improves the water levels

in the mine area. This will also become a resource for the local public and increase

agriculture output.

iv) So also, after cessation of mining, part of the quarry area will be reclaimed with highly

permeable OB material. The final void would be converted into a water reservoir. Thus,

in post-mining, the recharge and source potential in core zone will be much higher than

the existing.

v) With the increase in secondary porosity, a significant improvement in the rainfall

infiltration rate, close to the mine area can be anticipated.

16.3.3 Noise Management

The present noise levels are below the prescribed limits. If the impulsive noise

levels increase due to mining operation, suitable measures will be adopted to maintain

the noise level within permissible limits at working zone. The following measures are

adopted and will be continued:

1. Planting of rows of trees with thick foliage along roads and other noise generating

centers to act as acoustic barriers.

2. Isolating/enclosing the noisy machines/sources by using resilient mounting/altering

structures.

3. Routine maintenance schedules for HEMM and other machineries to eliminate noise

as far as possible.

4. Balanced and properly aligned conditioning of machines to reduce vibration.

5. Provision of ear muffs/ear plugs to workers subjected to noise level above

recommended limits.

6. Controlled blasting.

7. Regular monitoring of noise level of project area.

16.3.4 Flora and Fauna Management

The location of Amadand OCP does not have any importance as a holiday resort.

The surface to be disturbed by open cast mining operation does not contain any rare

variety of flora or fauna. As such, consequent to the opencast mining operation,

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 16 of 24

deterioration in quality of life or loss of amenity is not envisaged. Conservation plans of

schedule I & II animals, if any, will be prepared and implemented.

Compensatory afforestation and Strengthening of safety zone will be done.

The reclaimed and afforested internal dump and external dump of 841.31 Ha will

form one integral unit at the cessation of the mining activity. SECL will develop this

integrated area, as habitat for the fauna. The following steps will be taken for development

of habitat.

Reclamation of mine void:

In the core zone, after the cessation of mining activity a void will be created. This

void will be used as a water body. This will be graded to a gentle slope so that it acts as

a safe approach / access to the water body for the faunal species.

Through CSR activities in villages existing in the buffer zone, existing water

sources particularly the village tanks will be improved to provide drinking water to the

local community so that biotic pressure on water resources present in the forest areas

and used by fauna is gradually reduced.

Control of forest fire, fire in coal seam and coal stock:

Fire can destroy the entire habitats (micro and macro) and its life supporting

potential in a forest area. Fire does not spare fauna also. SECL will implement the

existing DGMS stipulated fire protection norms on coal seams and coal stock. This will

ensure that a congenial atmosphere is created and fire does not affect the fauna and flora

as well.

16.3.5 Land Resource Management

The project involves 715.02 Ha of land for the quarry area. This includes 70.46 Mt

(as on 01.04.2015) of mineable coal and 764.40 Mcum of OB. In the initial years i.e. upto

4th year, entire OB will go to the external dumps. Internal dumping will start from the 5th

year onwards. The parting OB in case of older seams may be transported through central

haul road, while mining in the multi seam zone.

Initially, the soil/alluvium from top bench of OB will be stacked and stored

separately. The spoil dump benches in the internally backfilled OB will be in the form of

benches. With the sufficient advance of coal production bench, the backfilled OB will be

leveled with dozer.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 17 of 24

Dumper/Tipper will transport soil/alluvium OB from the top OB bench and will dump

the soil directly on the leveled backfilled OB. The barrier distance between internal dump

and coal production bench will be 70 m to have smooth functioning of machineries. The

slope stability study should be done. According to study report, the dump design like

dump bench height, total dump height & slope etc. should be modified to avoid dump

failure. In addition to that proper precautions should be taken to avoid sliding of internal

OB bench.

238.02 Mcum OB will be externally dumped outside quarry area from 1st year to

10th year for which 356.50 Ha land will be required.

External dump has been made near southern boundary. The break-up of OB

quantity to be accommodated in various dumps is as follows

Table 16.10 Dump Volume (Mcum)

A. External 238.02 B. Internal 526.38

Grand Total (A+B) 764.40

Present land use would be converted into internal dump, external dump, green

belt, built up area, surface infrastructure, final void/water body & other surface water body

etc. after the cessation of mining operation. Out of 715.02 Ha. of quarry area, plantation

would be done in 464.61 Ha. The dump surface would be maintained flat and top soil

would be sprayed over it as a part of final reclamation.

Plantation would be done on reclaimed internal dump, external dump, safety zone

and around the mine, infrastructure, etc. The no. of plantation is given as under.

a. Mine, infrastructure, colony etc. 58825 Nos, in 23.53 Ha.

b. Internal Dump after backfilling: 1161525 No.s, in 464.61 Ha

c. External Dump: 941750 Nos in 376.70 Ha

d. Safety zone* : 290000 No.s in 116.00 Ha

Total Plantation = 2452100 Nos.

RP

R fo

r Am

adand O

CP

(4.0

Mty

) (Update

d J

uly

’ 2015) C

MP

DI

Job N

o.5

15

126

Chapte

r 16 / 1

8 o

f 24

Ta

ble

16

.11

Pre

se

nt L

an

d U

se

Sl.

No

. P

artic

ula

rs

Alre

ad

y a

ward

ed

(1.1

5 M

ty)

Ad

ditio

nal la

nd

to b

e a

cq

uire

d(4

.0 M

ty)

To

tal la

nd

re

qu

irem

en

t A

gri

lan

d

Su

rface

wate

r b

od

y

Oth

er

go

vt

lan

d

To

tal

Ag

ri la

nd

Su

rface

wate

r b

od

y

Oth

er

go

vt

lan

d

To

tal

1.

Quarry

are

a

567.5

4

5.7

8

- 573.3

1

91.2

5

1.6

2

48.8

4

141.7

1

715.0

2

2.

Safe

ty z

one

87.9

4

2.7

7

- 90.7

1

22.8

6

- 2.4

3

25.2

9

116.0

0

3.

Rehabilita

tion

-

- -

- -

- 50.8

0

50.8

0

50.8

0

4

Colo

ny

- -

- -

15.1

7

- -

15.1

7

15.1

7

5

Exte

rnal d

um

p

20.0

0

- -

20.0

0

343.9

6

1.6

9

11.0

5

356.7

0

376.7

0

6

Infra

stru

ctu

re

18.3

5

- -

18.3

5

57.6

1

0.7

7

2.2

0

60.5

8

78.9

3

7

Serv

ice ro

ad

- -

- -

15.6

1

- -

15.6

1

15.6

1

8

CH

P, s

ilo, s

idin

g

- -

- -

41.6

6

- 0.4

0

42.0

6

42.0

6

9

Mag

azin

e

- -

- -

- -

10.0

0

10.0

0

10.0

0

10

O

thers

-

- -

- 22.7

2

-

22.7

2

22.7

2

Gra

nd

tota

l 693.8

3

8.5

5

Nil

702.3

8

610.8

4

4.0

8

125.7

2

740.6

3

1443.0

1

Ta

ble

16

.12

Po

st M

inin

g L

an

d U

se

Sl.

No

P

artic

ula

rs

Q

uarry

Are

a

(Afte

r backfillin

g

& re

cla

matio

n)

Exte

rnal

Du

mp

(A

fter

Recla

matio

n)

Safe

ty

zo

ne a

s

gre

en

belt*

Infra

stru

ctu

re,

Exp

losiv

e

mag

azin

e e

tc.

R&

R s

ite

Gra

nd

To

tal

1

Affo

reste

d a

rea

464.6

1

376.7

0

116.0

0

18.4

5

5.0

8

980.8

4

2

Cultiv

ab

le L

and

0.0

0

0.0

0

0.0

0

0.0

0

0.0

0

0.0

0

3

Fin

al V

oid

/ Wate

r Body

250.4

1

0.0

0

0.0

0

0.0

0

0.0

0

250.4

1

4

Oth

er W

ate

r Bodie

s

0.0

0

0.0

0

0.0

0

0.0

0

0.0

0

0.0

0

5

Built-U

p A

rea.

0.0

0

0.0

0

0.0

0

166.0

4

45.7

2

211.7

6

To

tal L

an

d

715.0

2

376.7

0

116.0

0

184.4

9

50.8

0

1443.0

1

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 19 of 24

16.4 Environment Management System

16.4.1 Monitoring Schedule

Environmental monitoring will be carried out following the monitoring schedule for

Air, Water, and Noise levels as per Standards of MOEF (Vide GSR 742 (E) dated

25.9.2000).

16.4.2 Plantation Monitoring

The project authority at field level will continuously monitor the growth and

survival/mortality rates of the plantations till the end of 3 years. Once trees attain desired

growth, no further monitoring will be required.

16.4.3 Action Plan for Land Reclamation and Plantation

The estimated life of the mine is 19 years. Maximum height of internal dump would

be 90 m from the ground level. The dump surface would be maintained flat and top soil

would be sprayed over it as a part of final reclamation. The maximum depth of quarry 150

m from the ground level. Approximate total no. of plants is estimated as 2452100 Nos. An

area of 250.41 Ha would be left as final void/water body after mine closure.

Year wise tentative programme of OB removal, dumping, plantation and the stage

dumping and reclamation programme are given below in table 16.18. Stage reclamation

plan thereof are shown in figures -18.2 for 5th year, 18.3 for 10th year, 18.4 for 15th year

and 18.5 for final stage reclamation plan respectively of Chapter - 18. X-section of final

stage reclamation is shown in figure 18.6 of Chapter - 18.

The action programme for EMP implementation is given in figure-16.2.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 16 / 20 of 24

Table 16.13

PROGRAMME OF O.B. REMOVAL, DUMPING & PLANTATION:

Year

Coal produc-tion

OB removal

Dump plan Dump area Dump area available for

reclamation (Ha.)

No of plantatio

n

(MTes)

(Mcum )

( Mcum) (Ha.) /2500 Nos / Ha. Externa

l Interna

l Externa

l Interna

l Externa

l Interna

l

1 2.00 20.59 20.59 0.00 65.00 0.00 0.00 0.00 0

2 3.00 36.91 36.91 0.00 117.00 0.00 0.00 0.00 0

3 4.00 52.54 52.54 0.00 38.00 0.00 3.00 0.00 7500

4 4.00 52.54 52.54 0.00 30.00 0.00 5.00 0.00 12500

5 4.00 52.54 35.54 17.00 30.00 18.05 7.00 0.00 17500

6 4.00 47.32 22.32 25.00 16.00 26.54 36.17 0.00 90425

7 4.00 39.38 9.38 30.00 15.00 31.85 36.17 0.00 90425

8 4.00 39.91 3.44 36.47 15.00 38.72 36.17 0.00 90425

9 4.00 40.87 2.87 38.00 15.00 40.35 36.17 0.00 90425

10 4.00 40.89 1.89 39.00 15.50 41.41 36.17 0.00 90425

11 4.00 40.89 0.00 40.89 0.00 43.42 36.17 0.00 90425

12 4.00 40.61 0.00 40.61 0.00 43.12 36.17 15.51 129200

13 4.00 40.37 0.00 40.37 0.00 42.86 36.17 17.00 132925

14 4.00 40.86 0.00 40.86 0.00 43.39 36.17 19.00 137925

15 4.00 41.16 0.00 41.16 0.00 43.70 36.17 19.00 137925

16 4.00 44.43 0.00 44.43 0.00 47.18 0.00 50.00 125000

17 4.00 40.64 0.00 40.64 0.00 43.15 0.00 50.00 125000

18 4.00 38.10 0.00 38.10 0.00 40.45 0.00 50.00 125000

19 1.46 13.85 0.00 13.85 0.00 14.71 0.00 50.00 125000

MC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 64.70 161750

MC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 64.70 161750

MC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 64.70 161750

Total 70.46 764.40 238.02 526.38 356.50 558.91 376.70 464.61 2103275

*Note: This calendar program is tentative and plantation may vary according to mine conditions and actual area available for reclamation.

P.R

for A

madand O

CP

(4.0

0 M

ty)

CM

PD

I

Job N

o.5

15

126

C

hapte

r 16 / 2

1 o

f 24

AC

TIO

N P

RO

GR

AM

ME

FO

R E

MP

IMP

LE

ME

NT

AT

ION

A

ma

da

nd

OC

P (4

Mty

), J&

K A

rea

.

N

O.

DU

RA

TIO

N/ A

CT

IVIT

IES

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

M1

M2

M3

1

RE

HA

BIL

ITA

TIO

N &

RE

SE

TT

LE

ME

NT

OF

PR

OJ

EC

T A

FF

EC

TE

D F

AM

ILIE

S/ P

ER

SO

NS

2

AN

TIC

IPA

TO

RY

AF

FO

RE

ST

AT

ION

/ PL

AN

TA

TIO

N

3

CO

MP

EN

SA

TO

RY

AF

FO

RE

ST

AT

ION

4

DU

MP

RE

CL

AM

AT

ION

A

Exter

na

l Du

mp

a

. Fillin

g(D

um

pin

g)

b

. Rec

lam

atio

n(T

ech

nica

l)

c. P

lan

tatio

n

B

Inte

rna

l Du

mp

a

. Fillin

g

b

. Rec

lam

atio

n(T

ech

nica

l)

c. P

lan

tatio

n

5

EN

V.M

ON

ITO

RIN

G / H

EA

LT

H M

ON

ITO

RIN

G

6

OP

ER

AT

ION

/ MA

INT

EN

AN

CE

OF

OIL

, GR

EA

SE

TR

AP

D

ET

P.

7

WA

TE

R S

PR

INK

LIN

G O

N H

AU

L R

OA

DS

, CH

P

8

CO

MM

UN

ITY

DE

VE

LO

PM

EN

T IN

VIL

LA

GE

S

9

FIN

AL

MIN

E C

LO

SU

RE

AC

TIV

ITY

F

igu

re 1

6.2

P.R

for A

madand O

CP

(4.0

0 M

ty)

CM

PD

I

Job N

o.5

15

126

C

hapte

r 16 / 2

2 o

f 24

16

.4.4

Org

an

iza

tion

al S

truc

ture

Fo

r imp

lem

en

ting th

e e

nviro

nm

en

t ma

na

gem

en

t pla

n (E

MP

) of th

e p

roje

ct, th

e o

rga

niz

atio

na

l stru

ctu

re h

as b

ee

n s

ho

wn

in

figu

re-1

6.3

P.R for Amadand OCP (4.00 Mty) CMPDI

Job No.515126 Chapter 16 / 23 of 24

16.5 Capital Provision:

Table 16.14

Statement showing the estimated capital requirement for Environmental and Social Measures

S.N. PARTICULARS NUMBER

1. COST OF REHABILITATION

i) Total No. of families likely to be rehabilitated 1100

CAPITAL ESTIMATE In Lakhs

A. For quarry as recommended in PR a) Total homestead 1100. Compensation for 1100 nos. of

homestead @ Rs. 3,00,000/-*(50% will be given cash compensation, 50% will be given land for house) 1650.00

(given in Appendix A-8.1)

b) Land for R&R site for 1100 home stead etc (50.798 Ha). 507.98 c) Compensation to 50% land oustees in lieu of not providing job.

For additional Tenancy land to be acquired 610.84 Ha and cash compensation given for 305.42 Ha land

@ Rs. 5,00,000/- per Acre for 305.42 Ha Land 3771.91

(App.-A.8.1)

d) Subsistence Allowance @Rs 240 per day for 25 days in a month for 1100 homestead for one year 792.00

e) Development of rehabilitation colony for total 1100 homestead including school, hospitals, road etc. 1100.00

(Appendix-A.8.1)

Sub-total of (1) 7821.89

Note: Considerin 50% land oustees will be provided job and 50% will be given cash compensation in lieu of Job.

2 CAPITAL FOR RESTORATION

a Housing for Reclamation personnel 17.57

(Appendix-A.2.2)

b Piezometers for measuring water level (6 Nos) 20.00

c Hydrogeological study including drilling, study etc.

(App. - A.8.1) 35.00 d Scientific study like slope stability study for internal & external

OB dump, monitoring and other study etc. 20.00

e Green belt fencing 15m width along safety zone of the Project (approx.12.0 km)

6.42

Sub-Total (2) 98.99

3. CAPITAL FOR ANTI-POLLUTION MEASURE

IN MINE & INDUSTRIAL AREA

a Settling tank for mine water disposal 40.00

(Appendix-A.8.3.(A)

c Other development measures in industrial

site viz. drains & tree guards etc. 85.73

P.R for Amadand OCP (4.00 Mty) CMPDI

Job No.515126 Chapter 16 / 24 of 24

(Appendix-A.8.2)

d Oil & Grease Trap (Appendices A.2.1) 5.00

d Garland drains (Appendix-A.8.1) 500.00

e Arboriculture/plantation in industrial

area (Appendix-A.8.1.) 2.50

f Dust suppression at Mine,CHP (Appendix-A.3.5,A.3.6 ) 155.00

g Dust suppression at Siding (Appendix-A5) 10.00

h Slope Stability Radder 700.00

Sub-Total(3) 1498.23

S.N. PARTICULARS AMOUNT

4. ENVIRONMENTAL CONTROL MEASURES IN TOWNSHIP

a Sewerage disposal in colony(Appendix-A.8.3(A) 29.63

b Storm water drains & culverts(Appendix-A.8.2) 8.43

c Aboriculture/plantation (Appendix-A.8.1) 2.50

d Other development measures in township to 10.36

improve cleanliness & aesthetics parks-play-

grounds & tree guards (App-A.8.2)

e Severage Treatment Plant (Appendices A8.3(A) 400.00

f Land development & Horticulture(App A22) 23.00

g Rain Water Harvesting (App A22) 6.00

Sub Total (4) 479.92

5. Steps for Prevention of Possible 200.00

mine inundation(Embankments) (App.-A.8.1)

6. Cost of EMP preparation(Appendix-A.8.4) 50.00

7. Community development in surrounding 50.00

villages (Appendix-A.8.1)

Total capital from 1 to 7 10199.03

B. Different type of Revenue nature cost to be considered

in cost of production per tonne of Coal:-

1. Land reclamation/restoration

@1.25 lakhs/Ha for technical and biological 94.93

& Hydro seeder for reclamation (lakhs/annum)

2. Environment Audit @ 0.60 lakhs/annum 0.60

3. Environment [email protected] lakhs/annum 10.00

4 Monitoring of landuse through satellite surveillance lakhs/annum 8.00

5 Mine Closure Cost lakhs/annum 618.97

6 Monitoring of CSR and RR plan lakhs/annum 2.00

Total Revenue nature cost per annum 734.50

*CSR provision is subjected to CIL’s norms, i.e. 5% of net profit or at least Rs. 5.00 per

tonne of coal production.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 17 / 1 of 2

CHAPTER - XVII

LAND REQUIREMENT

17.1 GENERAL The topography of the quarry area is almost flat with surface elevation varying from

530m to 550m above MSL.

The total land involved for the project is 1443.01 Ha including land for industrial

development, colony, approach road, coal transport road & road diversion, magazine

and quarry safety zone. Out of this, 702.38Ha is already acquired and 740.63 Ha of

land is additionally required. Out of additional land 740.63 ha, the tenancy land is

610.84 Ha and Govt. land is 129.79Ha. Within the mine area four villages exists. The

project area is free from forest land as per landuse plan supplied by area authority.

The break-up of land for the purpose of this report is as follows: -

The break-up of land for the purpose of this report is as follows: -

(Land in Ha)

SL. PARTICULARS ADDITIONAL LAND TO BE ACQUIRED

NO. Already

Acquired as

31.03.2015

FOREST

LAND

TOTAL

AGRICUL-

TURE LAND

SURFACE

WATER

BODY

SURFACE

WATER

BODY

WASTE

LAND

OTHER

GOVT LAND

1. QUARRY AREA 573.31 91.245 1.622 48.839 141.71 715.02

2. SAFETY ZONE 90.71 22.855 2.431 25.29 116.00

3. REHABILITATION 50.798 50.80 50.80

4 COLONY 15.170 15.17 15.17

5 EXTERNAL DUMP 20.00 343.962 1.688 11.046 356.70 376.70

6 INFRASTRUCTURE 18.35 56.784 0.830 0.765 2.197 60.58 78.93

7 SERVICE ROAD 15.610 15.61 15.61

8 CHP, SILO, SIDING 41.660 0.404 42.06 42.06

9 MAGAZINE 10.000 10.00 10.00

OTHERS 22.720 22.72 22.72

GRAND TOTAL 702.38 610.01 0.83 4.08 125.72 740.63 1443.01

TOTAL LAND

REQUIRE

MENT

Land

TENANCY LAND GOVT LAND

Break-up of land use has been estimated on the basis of updated revenue plan/

land use plan supplied by area authority.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 17 / 2 of 2

Break-up of land use has been estimated on the basis of updated revenue plan/

land use plan supplied by area authority. It is estimated that total 1443.01 Ha

land will be involved for Amadand Opencast including land for industrial

development, colony, approach road, coal transport road & road diversion,

magazine and quarry safety zone. Within the mine area four villages exists

namely Nimha, Timkitola-Amadand, Harratola-Kuhka and Majholi which are to

be rehabilitated.

The estimated capital requirement for land acquisition of the quarry has been

given in Appendix-A.1.

17.3 STATUS OF LAND ACQUISITION

The total land involved for the project is 1443.01 Ha including land for

industrial development, colony, approach road, coal transport road & road

diversion, magazine and quarry safety zone. Thus, total land to be acquired for

the project is 1443.01 Ha. Out of this, 702.38Ha is already acquired and 740.63

Ha of land is additionally required. Out of additional land 740.63 ha, the tenancy

land is 610.84 Ha and Govt. land is 129.79Ha. As per supplied landuse plan no

forest involved in this project, so no forest land is to be acquired for

implementation of this project report.

*******

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 1 of 29

CHAPTER - 18

MINE CLOSURE PLANNING

18.1 Closure Planning details of mine

Amadand OCP is an operating mine under Jamuna & Kotma Area, SECL and

comprises mostly (i.e. 1313.22 Ha, 91 %) of tenancy land. The expansion project area is

not involved with any industrial and mining activities for which require regular

environmental monitoring/audit. Environmental base line data for Amadand OC

Expansion, generated in the year of 2014, are utilized for preparation of this Chapter.

This data will enable to obtain a comprehensive idea of environmental quality in

and around the proposed project area in respect of air quality, water quality, noise level,

flora fauna, socio economic data etc. The project has been planned for a target capacity

of 4.0 Mty for 19 years life, to meet power grade coal. Beyond this life, the mine will be

closed if no further expansion towards the above adjoining blocks is considered. The

closure details are described below.

18.1.1 Mined out Land & proposed final land use;--

The proposed pre-mining and the tentative post mining land use plan has been

given below in table 18.1(a), (b) & 18.2 (a), (b).

RP

R fo

r Am

adand O

CP

(4.0

Mty

) (Update

d J

uly

’ 2015) C

MP

DI

Job N

o.5

15

126

C

hapte

r 18 / 2

of 2

9

Ta

ble

18

.1 P

res

en

t Lan

d U

se

Sl.

No

. P

artic

ula

rs

Alre

ad

y a

ward

ed

(1.1

5 M

ty)

Ad

ditio

nal la

nd

to b

e a

cq

uire

d(4

.0 M

ty)

To

tal la

nd

re

qu

irem

en

t A

gri la

nd

S

urfa

ce

wate

r b

od

y

Oth

er

go

vt

lan

d

To

tal

Ag

ri lan

d

Su

rface

wate

r b

od

y

Oth

er

go

vt

lan

d

To

tal

1.

Quarry

are

a

567.5

4

5.7

8

- 573.3

1

91.2

5

1.6

2

48.8

4

141.7

1

715.0

2

2.

Safe

ty z

one

87.9

4

2.7

7

- 90.7

1

22.8

6

- 2.4

3

25.2

9

116.0

0

3.

Rehabilita

tion

-

- -

- -

- 50.8

0

50.8

0

50.8

0

4

Colo

ny

- -

- -

15.1

7

- -

15.1

7

15.1

7

5

Exte

rnal d

um

p

20.0

0

- -

20.0

0

343.9

6

1.6

9

11.0

5

356.7

0

376.7

0

6

Infra

stru

ctu

re

18.3

5

- -

18.3

5

57.6

1

0.7

7

2.2

0

60.5

8

78.9

3

7

Serv

ice ro

ad

- -

- -

15.6

1

- -

15.6

1

15.6

1

8

CH

P, s

ilo, s

idin

g

- -

- -

41.6

6

- 0.4

0

42.0

6

42.0

6

9

Mag

azin

e

- -

- -

- -

10.0

0

10.0

0

10.0

0

10

Oth

ers

-

- -

- 22.7

2

-

22.7

2

22.7

2

Gra

nd

tota

l 693.8

3

8.5

5

Nil

702.3

8

610.8

4

4.0

8

125.7

2

740.6

3

1443.0

1

Ta

ble

18

.2 P

os

t-min

ing

lan

d u

se

Sl.

No

P

artic

ula

rs

Q

uarry

Are

a

(Afte

r backfillin

g

& re

cla

matio

n)

Exte

rnal

Du

mp

(A

fter R

ecla

matio

n)

Safe

ty z

on

e

as g

reen

b

elt*

Infra

stru

ctu

re,

Exp

losiv

e

mag

azin

e e

tc.

R&

R s

ite

Gra

nd

To

tal

1

Affo

reste

d a

rea

464.6

1

376.7

0

116.0

0

18.4

5

5.0

8

980.8

4

2

Cultiv

ab

le L

and

0.0

0

0.0

0

0.0

0

0.0

0

0.0

0

0.0

0

3

Fin

al V

oid

/ Wate

r Body

250.4

1

0.0

0

0.0

0

0.0

0

0.0

0

250.4

1

4

Oth

er W

ate

r Bodie

s

0.0

0

0.0

0

0.0

0

0.0

0

0.0

0

0.0

0

5

Built-U

p A

rea.

0.0

0

0.0

0

0.0

0

166.0

4

45.7

2

211.7

6

To

tal L

an

d

715.0

2

376.7

0

116.0

0

184.4

9

50.8

0

1443.0

1

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 3 of 29

18.5 Water Management: -

a) Physiography & Drainage

The Amadand Opencast Block has a gentle rolling topography with a general slope

in all directions from the central part of the area. The variation in surface elevation is from

530 m to 550.01m above MSL. The area has a radial drainage pattern while the major

part of the area is being drained by channels of Kewai River, a tributary to Son, the

channels in the north eastern part of the area discharge its water into Hasdeo river, a

tributary to Mahanadi. There are also a number of ponds in the area. The entire report

area including the villages and Pasture land is covered by cultivated field.

b) Water quality status of surface and ground water

The water quality data generated for the period Dec’13 – March’14 is given below

in table 18.3 and 18.4.

Table 18.3 Surface Water at a Glance Period: Dec’13 – March’14

Sl. No. Parameters

Concentration Range & Norms

Result IS: 2296-1982

(Inland Surface Water) Class C

1 pH 7.26 - 7.34 6.5 - 8.5

2 Total Dissolved solids, mg/l 772 - 780 1500

3 Dissolved Oxygen, mg/l 5.4 - 5.5 4 (minimum)

4 BOD, 5 Days @ 20OC, mg/l 2.7 - 2.8 3.0

5 Chloride (as Cl), mg/l 72 - 76 600

6 Fluorides (as F) ,mg/l 0.58 - 0.60 1.5

7 Sulphate (as SO4), mg/l 26 - 28 400

8 Nitrate (as NO3) ,mg/l 11.4 - 12.2 50

9 Zinc (as Zn) ,mg/l 0.10 - 0.12 15

10 Iron (as Fe ) , mg/l 0.38 - 0.40 50

Table 18.4

Peak Values of Ground Water Quality at a Glance in Comparison To Drinking Water Standard Period: Dec’13 – March’14

Sl. No.

Parameter

Result IS: 10,500 - 1991 Norms*

Amadand Borewell

Phulawaritola hand pump

1 pH 7.32 6.86 6.5 – 8.5

2 Colour, Hazen 5.0 4.0 5/25*

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 4 of 29

3 Odour Unobjectionable Unobjectionable

4 Turbidity, NTU 5.0 4.0 5/10*

5 Total Dissolved Solids, mg/l 118 106 500/2000*

6 Residual free Chlorine, mg/l <0.04 <0.04 0.2 (Minimum)

7 Chloride (as CI), mg/l 12 17 250/1000*

8 Fluoride (as F), mg/l 0.56 0.42 1.0/1.5*

9 Sulphate (as SO4), mg/l 8 6 200/400*

10 Cyanide (as CN), mg/l <0.01 <0.01 0.05

11 Phenols (as C6H5OH), mg/l <0.001 <0.001 0.001/0.002*

12 Chromium (as Cr 6+), mg/l <0.01 <0.01 0.05

13 Copper (as Cu), mg/l 0.03 0.03 0.05/1.5*

14 Selenium (as Se), mg/l <0.01 <0.01 0.01

15 Arsenic (as As), mg/l <0.05 <0.05 0.05

16 Cadmium (as Cd), mg/l <0.01 <0.01 0.01

17 Mercury (as Hg), mg/l <0.001 <0.001 0.001

18 Lead (as Pb), mg/l < 0.01 < 0.01 0.05

19 Zinc (as Zn), mg/l 0.02 0.03 5/15*

20 Alkalinity (as CaCO3), mg/l 52 46 200/600*

21 Iron (as Fe), mg/l 0.08 0.10 0.30/1.0*

22 Hardness (as CaCO3), mg/l 49.80 27.33 300/600*

23 Calcium (as Ca), mg/l 15.0 6.0 75/200*

24 Magnesium (as Mg), mg/l 3.0 3.0 30/100*

25 Nitrate (as NO3), mg/l 10.36 8.28 45/100*

26 Manganese (as Mn), mg/l 0.04 0.03 0.10/ 0.30*

27 Boron (as B), mg/l <0.10 < 0.10 1 / 5*

28 Aluminum (as Al), mg/l < 0.02 < 0.02 0.03/0.20*

29 E. Coli, MPN/100ml Absent Absent Absent

c) Measures for control of water pollution

i) An amount of Rs 40 Lakh has been provided in the PR for Construction of Settling

tank for treatment of mine effluent.

ii) Adequate provision has been made for the construction of the workshop ETP (Oil

& grease trap) and other effluent generated in the industrial as well as residential

areas.

iii) Mine water after settlement will be used for industrial use like road watering, fire

fighting etc.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 5 of 29

iv) Provision of Rs. 35 Lakh has been made for hydro-geological study.

v) Amount of 20 Lakhs has been provided in the PR for provision of 6 nos. of

Piezometers

vi) Provision of Rs.29.63 lakhs has been made for the colony sewage disposal.

vii) Money amounting to Rs.400 Lakh has been provided in the PR for construction of

Sewerage Treatment Plant.

viii)Environmental monitoring work will be continued as per the legal requirements and

will continue after subsequent three years post closure.

d) Water Conservation

The effluent generated in the workshop will be recycled for washing of vehicles. Steps

will be taken to maximise the reuse of effluent generated from the mine and colony.

Rainwater harvesting structure will be provided in the office/ colony at suitable place for

water conservation. The waste water recycling after due treatment for the purpose

mentioned above will enable conservation of water. Storage of conserved water in mine

pits will be given due emphasis to provide water round the year and quality of water will

be maintained before and after storage. An amount of 6.00 lakhs has been provided for

the rain water harvesting in the colony areas.

e) Water balance of the area (from EMP)

Except for coal mining, no major industrial development activity is located in the area.

As per CGWB, NCC Region, Raipur, the total annual replenishable ground water resource

in the Anuppur Development Block, Shahdol district (where Amadand UG proposed mine

exists), was assessed as 68.20 M.cum. It was also reported that the ground water

development in the block is as 1.99 % and falls within category "Safe". As such, the entire

Madhya Pradesh & Chhattisgarh States are covered under the category “Safe”. On

analysis, the net groundwater recharge and draft for the buffer zone were

estimated as 45.55 MCum and 33.73 MCum respectively. Thus, about 11.82

MCum groundwater recharge would be available annually in the area to meet any

future demand.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 6 of 29

Figure-18.1

f) Acid mine drainage source, the existing practice of control and future plan

The existing mine water quality of Amadand & nearby mines are not acidic and it is

expected the acid mine drainage problem will not arise in Amadand OCP also. If however

acid mine drainage problem arises suitable measures will be taken as per standard.

g) Underground water/ quarry water management after closure (Specifying its

usage like domestic water supply, irrigation, and pisciculture or stabilizing the

ground water regime).

The final void (250.41 Ha) left after the completion of mining activity will act as a

water recharge basin for the area and may be utilized by the local community.

h) Water quality monitoring for three years after closure

The number of sampling stations shall be one with the quarterly sampling frequency

and two numbers ground water samples in core and buffer zone with quarterly frequency.

A monitoring schedule for Water levels will be as per Standards of MOEF (Vide

GSR 742 (E) dated 25.9.2000)

Water : For effluent & surface water the parameters to be monitored are pH, Chemical

Oxygen Demand, Total Suspended Solid, Oil & Grease at every fortnight and all

parameters once in a year. For drinking water, monitoring will be done as per

IS.10500 once in a month.

Natural losses 8.04

15.00%

Irrigation 5.36

10.00%

Domestic7.27

13.57%

Mine Discharge21.10

39.37%

Balance11.82

22.06%

Net Annual Groundwater Recharge Balance, Study Area Amadand OCP Expansion, Jamuna Kotma Area, SECL

(M.Cum, %)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 7 of 29

18.6 Air quality management

a) Air quality (Monitored data) Monitoring for next three years will be done. 3 samples at

every fortnightly basis for 3 years will be taken. The frequency of sampling will be

according to the time to time requirement by the statute. One sample will be at core zone

and one sample each in upwind and downwind direction of the project.

A monitoring schedule for Air as per Standards of MOEF (Vide GSR 742 (E) dated

25.9.2000). The Parameters to be monitored are SPM, RPM, SO2, and NOx at every

fortnight.

b) Description of the air quality scenario of the core and buffer zone area

(monitoring data in tabular form for SPM, RPM, SO2 and NOX).

Air quality in core and buffer zone

The air quality data generated for the period Dec’2013 – March’2014 indicates that

the SPM, RPM, SO2, & NO2 values in respect of the station given in table below.

Table 18.5

AIR QUALITY STATUS

Period: Dec 2013 - March 2014 (in µg / cum)

Category Location Name

&

Code

Min. Max.

98th

%

Value

AM GM SD

MoEF/

CPCB

Limits

Suspended Particulate Matter (SPM) Concentration

Industrial Mine Office – A1 441 480 472 461.92 461.84 8.77 500

Residential

Amadand – A2 178 190 189 184.42 184.38 3.50

200

Dadaibahra – A3 163 185 180 172.25 172.19 5.00

Phulwaritola – A4 165 186 185 180.42 180.34 5.35

Chhapratola – A5 175 188 187 182.54 182.51 3.67

Bhad – A6 178 190 189 184.67 184.64 3.38

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 8 of 29

Respire able Particulate Matter (PM10) Concentration

Industrial Mine Office – A1 213 230 227 221.75 221.71 4.08 250

Residential

Amadand – A2 83 91 90 87.79 87.76 2.26

100

Dadaibahra – A3 78 88 86 83.43 83.40 2.31

Phulwaritola – A4 75 88 87 84.63 84.57 2.98

Chhapratola - A5 83 90 90 87.21 87.18 2.08

Bhad – A6 83 91 90 87.96 87.93 2.20

Respire able Particulate Matter (PM2.5) Concentration

Industrial Mine Office – A1 123 134 132 129.08 129.06 2.60 -

Residential

Amadand – A2 48 54 53 51.04 51.01 1.76

60

Dadaibahra – A3 45 51 50 48.11 48.08 1.49

Phulwaritola – A4 47 53 52 50.33 50.31 1.52

Chhapratola - A5 48 53 52 50.54 50.52 1.41

Bhad – A6 48 54 53 51.21 51.18 1.64

Category Location Name &

Code

Min. Max. 98th

% Value

AM GM SD MoEF/ CPCB Limits

Sulphur Dioxide (SO2) Concentration

Industrial Mine Office – A1 16.6 22.3 21.5 20.48 20.44 1.19 120

Residential Amadand – A2 12.6 18.3 17.5 16.48 16.43 1.19 80

Dadaibahra – A3 10.7 16.2 16.0 14.69 14.59 1.61

Phulwaritola – A4 11.2 16.2 16.1 15.01 14.96 1.20

Chhapratola - A5 13.5 17.8 17.7 16.57 16.53 1.13

Bhad – A6 13.8 17.8 17.7 16.61 16.57 1.09

Nitrogen Dioxide (NOx) Concentration

Industrial Mine Office – A1 23.2 29.2 28.7 27.40 27.37 1.31 120

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 9 of 29

Residential Amadand – A2 20.3 26.3 25.8 24.50 24.20 1.31 80

Dadaibahra – A3 20.3 25.8 25.7 24.36 24.20 1.63

Phulwaritola – A4 21.3 25.8 25.7 24.48 24.20 1.31

Chhapratola - A5 23.8 27.1 26.9 25.89 24.20 0.97

Bhad – A6 23.5 27.1 27.0 25.77 24.20 1.11

Regular monitoring is being done in & around the mine on the above monitoring

stations and will continue up to 3 years after closure of the mine. The data under different

category are within the permissible limit of CPCB.

c) Air Quality Management

Following air pollution control measures are and will be practiced within the mining

area and at coal handling plants and railway siding site.

1. Dust suppression has been proposed at mine, with an additional provision of

Rs.155 Lakh for the purpose. This includes provision of 6.0 km long Fixed Water

Spraying Arrangement. For siding, an additional amount of Rs.10 lakh has been

provided for mist water spraying at the siding.

2. Road has been black topped & further black topping will be done as per

requirement

3. Water sprinkling arrangement will be provided at the transfer point of coal.

4. Water spraying will be done regularly on approach roads within the mining area

to minimise the dust generation.

5. Intensive plantation of adequate width all along the transportation road will be

raised to minimise transport generated pollutants.

6. Green belt fencing has been proposed for 12 km length in the safety zone.

7. Extensive plantation carried out in mine & other areas.

8. Biological reclamation & plantation over overburden dump has been

Proposed in an area of approximately 841.31 Ha. in a phased manner.

9. Exposed overburden dumps will be covered through an appropriate plantation

10. Optimum blast hole geometry will be followed to reduce the dust during blasting.

11. Regular monitoring of ambient air quality of project area.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 10 of 29

18.7 Waste disposal

a) External OB dump & internal backfilling details (specifying the reclaimed

backfilled area, area of voids for water reservoir and also the OB dump area height

and volume) prior to closure of mine or during progressive mine closure

The project involves 715.02 Ha of land for the quarry area. This includes 70.46 Mt

(as on 01.04.2015) of mineable coal and 764.40 Mcum of OB. In the initial years i.e. upto

4th year, entire OB will go to the external dumps. Internal dumping will start from the 5th

year onwards. The parting OB in case of older seams may be transported through central

haul road, while mining in the multi seam zone.

Initially, the soil/alluvium from top bench of OB will be stacked and stored

separately. The spoil dump benches in the internally backfilled OB will be in the form of

benches. With the sufficient advance of coal production bench, the backfilled OB will be

leveled with dozer.

Dumper/Tipper will transport soil/alluvium OB from the top OB bench and will dump

the soil directly on the leveled backfilled OB. The barrier distance between internal dump

and coal production bench will be 70 m to have smooth functioning of machineries. The

slope stability study should be done. According to study report, the dump design like dump

bench height, total dump height & slope etc. should be modified to avoid dump failure. In

addition to that proper precautions should be taken to avoid sliding of internal OB bench.

238.02 Mcum OB will be externally dumped outside quarry area from 1st year to

10th year for which 356.50 Ha land will be required.

External dump has been made near southern boundary. The break-up of OB

quantity to be accommodated in various dumps is as follows

Table 18.6 Dump Volume (Mcum)

A. External 238.02 B. Internal 526.38 Grand Total (A+B) 764.40

Present land use would be converted into internal dump, external dump, green belt,

built up area, surface infrastructure, final void/water body & other surface water body etc.

after the cessation of mining operation. Out of 715.02 Ha. of quarry area, plantation would

be done in 464.61 Ha. There would be a final void/water body of 250.41 Ha left in the

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 11 of 29

project after mine closure The dump surface would be maintained flat and top soil would

be sprayed over it as a part of final reclamation.

Plantation would be done on reclaimed internal dump, external dump, safety zone

and around the mine, infrastructure, etc. The no. of plantation is given as under.

a. Mine, infrastructure, colony etc. 58825 Nos, in 23.53 Ha.

b. Internal Dump after backfilling: 1161525 No.s, in 464.61 Ha

c. External Dump: 941750 Nos in 376.70 Ha

d. Safety zone* : 290000 No.s in 116.00 Ha

Total Plantation = 2452100 Nos.

b) Stabilization of external O.B. dumps and backfilled area (Technical Reclamation)

Technical reclamation would involve breaking and levelling the top of OB dumps,

filling of gulleys and terracing etc. The maximum depth of the project will be 152.50 m. In

the initial years i.e. upto 4th year, entire OB will go to the external dumps. Internal dumping

will start from the 5th year onwards. The parting OB in case of older seams may be

transported through central haul road, while mining in the multi seam zone.

The height of each waste bench is restricted to only 30 m. The decoaled area after

simultaneous backfilling will be levelled by means of dozers keeping a mild slope of about

1 in 200 for surface water drainage for plantation and other purposes.

To the extent possible, top soil will be removed and stored separately. This soil

will be directly spread over the levelled graded external & backfilled OB for reclamation

Biological reclamation work will follow in next progressive year.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 12 of 29

Table 18.7 PROGRAMME OF O.B. REMOVAL, DUMPING & PLANTATION:

Year

Coal produc

-tion

OB removal

Dump plan Dump area Dump area available for

reclamation (Ha.)

No of plantatio

n

(MTes)

(Mcum )

( Mcum) (Ha.) /2500 Nos / Ha. Externa

l Interna

l Externa

l Interna

l Externa

l Interna

l

1 2.00 20.59 20.59 0.00 65.00 0.00 0.00 0.00 0

2 3.00 36.91 36.91 0.00 117.00 0.00 0.00 0.00 0

3 4.00 52.54 52.54 0.00 38.00 0.00 3.00 0.00 7500

4 4.00 52.54 52.54 0.00 30.00 0.00 5.00 0.00 12500

5 4.00 52.54 35.54 17.00 30.00 18.05 7.00 0.00 17500

6 4.00 47.32 22.32 25.00 16.00 26.54 36.17 0.00 90425

7 4.00 39.38 9.38 30.00 15.00 31.85 36.17 0.00 90425

8 4.00 39.91 3.44 36.47 15.00 38.72 36.17 0.00 90425

9 4.00 40.87 2.87 38.00 15.00 40.35 36.17 0.00 90425

10 4.00 40.89 1.89 39.00 15.50 41.41 36.17 0.00 90425

11 4.00 40.89 0.00 40.89 0.00 43.42 36.17 0.00 90425

12 4.00 40.61 0.00 40.61 0.00 43.12 36.17 15.51 129200

13 4.00 40.37 0.00 40.37 0.00 42.86 36.17 17.00 132925

14 4.00 40.86 0.00 40.86 0.00 43.39 36.17 19.00 137925

15 4.00 41.16 0.00 41.16 0.00 43.70 36.17 19.00 137925

16 4.00 44.43 0.00 44.43 0.00 47.18 0.00 50.00 125000

17 4.00 40.64 0.00 40.64 0.00 43.15 0.00 50.00 125000

18 4.00 38.10 0.00 38.10 0.00 40.45 0.00 50.00 125000

19 1.46 13.85 0.00 13.85 0.00 14.71 0.00 50.00 125000

MC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 64.70 161750

MC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 64.70 161750

MC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 64.70 161750

Total 70.46 764.40 238.02 526.38 356.50 558.91 376.70 464.61 2103275

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 13 of 29

Figure 18.2 5th year dump plan (1st Stage)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 14 of 29

Figure 18.3 10th year dump plan (2nd Stage)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 15 of 29

Figure 18.4 15th year dump plan (3rd Stage)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 16 of 29

Figure 18.5 (Final stage dump reclamation plan)

RP

R fo

r Am

adand O

CP

(4.0

Mty

) (Update

d J

uly

’ 2015) C

MP

DI

Job N

o.5

15

126

C

hapte

r 18 / 1

7 o

f 29

Fig

ure

18.6

(Cro

ss

-sec

tion

of th

e fin

al s

tag

e d

um

p re

cla

ma

tion

pla

n)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 18 of 29

a) Top soil Preservation & Management

The objectives of Top Soil Management are to-

Maintain a topsoil balance that achieves rehabilitation objectives during the life

of mine.

Ensure effective topsoil removal techniques are employed to maximize volumes

of suitable topsoil removed and minimize wastage.

Maintain topsoil viability during stripping, spreading, and stockpiling, through

best practice techniques and effective stockpile design and treatment.

In accordance with the objective of providing sufficient stable soil material for

rehabilitation and to optimize soil recovery, the top soil management the stock

piling of topsoil will be practiced as follows:

i) Top soil and other materials removed shall be stock-piled only when it is

impractical to promptly redistribute such materials on re-graded areas.

ii) Stock-piled materials shall be selectively placed on a stable area, not disturbed,

and protected from wind and water erosion, unnecessary compaction, and

contaminants which lessen the capability of the materials to support vegetation

when redistributed.

iii) The stockpiled top soil is preserved by adding–up organic material, manure and

other similar amendments.

iv) Uniformly distribute topsoil to suitable thickness. If sufficient topsoil is available,

a minimum compacted depth of a half meter on 3:1 slopes and one meter on flatter

slopes is suggested.

v) Specific team / manpower are to be deployed for this most important step of

topsoil management. The team will monitor the area and quantum of top soil

management with the authorities of mine on quarterly basis and regularly monitor

the given points of significant importance.

vi) Organic or inorganic fertilizer should be applied periodically if vegetation growth

is poor.

vi) Regular monitoring of top soil management should be done until vegetation is

demonstrated to be successfully established.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 19 of 29

b) Plantation on external & backfilled area, avenue and block plantation with

type of plantation i.e local/native species. Name the local species for

plantation.

Green belt on dumps:-

After technical reclamation of external & internal OB dumps and redistribution of top

soil over it, the dumps will be made biologically reclaimed. The above activities will be

carried out in a phased manner.

Green Belt around Mine: - In the directions where natural forest does not exist, there is need for creating green

belt of adequate width as an effective dust and sight curtain in the periphery of mining area,

residential areas/villages including those areas which are falling in the downwind direction.

There will be three tier plantations in the green belt area of 12 km length that shall act as

buffers and shock absorber against dusts, noise and stone flying. The trees in the green

belt will be wind firm, broad leaved and evergreen and of three different heights planted in

three tiers.

Haul Roads & other avenue Plantation: -

A green belt of adequate width on either side of the haul road will be raised and

the existing vegetation will be protected. The plants will be raised at spacing of 2.0x2.0

m. The roads available in the mine and other project areas will be provided with avenue

plantation as far as practicable.

c) Infrastructural Facilities (Nursery):-

A nursery is a pre-requisite for supply of seedlings of suitable species of right size

to the extent required. Rajya Van Vikas Nigam has already raised a nursery to grow

saplings and related activities in the administrative area of SECL.

Species for plantation.-

• Fruit bearing trees

– Jamun, Mango, Imli, Sitaphal, Bel, Ganga Imli, etc.

• Medicinal trees

– Neem, Karanj, Harra, Behara, Aonla, Arjun, Shikakai, Mahua, Kusum.

• Timber value trees

– Teak, Shivan / Ghamar, Sissoo, Sisham, Safed Sirus, Bamboo, Peltaforum,

Babool,

• Ornamental trees

– Gulmohur, Kachnar, Amaltas, Saptaparni, Grevelia, Peepal, Palm tree

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 20 of 29

18.8 Details of surface structures proposed for dismantling

The matter related with dismantling of the surface structures would be taken-up

extensively in the Final Mine Closure Plan. However, the different structures are

tentatively being discussed below:

a) Industrial / mine structures

Workshop (E&M and Excavation), Managers & Pit Offices are to be dismantled.

b) Residential Buildings

It will be handed over to closest project.

c) Service buildings

Dispensary, Telephone Exchange, Sub area Manager’s Office, Store are to be

handed over to closest project.

d) Telephone Cables

Telephone cables to be removed for re-use in other projects of the area, if

possible.

e) Sub-stations

It would be dismantled, if not used by local authority

f) Transformers

It will be sent to the place of requirement.

g) Community Services

It will be handed over to the local authorities.

h) Water line

It will be handed over to the local authorities.

i) Water Treatment Plants

It will be handed over to the local authorities.

j) Rly Siding

It will be handed over to closest project.

k) ETP/STP

It will be handed over to the local authorities.

l) Power line

It would be dismantled and re-used if not used by local authority.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 21 of 29

18.8.1 Disposal of Plants & Machineries

a) Disposal or reuse of existing HEMM, workshop and railway siding for OC.

The items will be provided to the mines of the company having requirement for

the items. If there is no such requirement the items will be auctioned.

b) Disposal or reuse of haulage system, ventilation, CHP, workshop, and

railway siding for UG.

Not applicable

c) Disposal or reuse of transmission and sub-station.

The items will be provided to the mines of the company having requirement for

the items. If there is no such requirement the items will be auctioned.

18.9 Safety and security arrangement

a) Details of fencing around abandoned quarry indicating the length of the

fencing.

About 12 Km fencing in the form of trench cutting 3.00 m wide, 2.0 m deep, & earth

from the trench will be stacked on the mine void side. The entire periphery will be

planted.

b) Mine entry sealing arrangements and subsidence management for UG mines.

Sealing details and dimensions shall also be provided. The thickness of mine

sealing will be 100 cm RCC (M20) with nominal reinforcement. For incline

entry, the mine entry path of 5 m will be filled with debris and clay before

sealing the mine.

- Not applicable.

c) Providing One Time Lighting Arrangement.

It would be provided.

d) Slope stability arrangement for high wall and back filled dumps.

The Slope stability analysis for high wall and backfilled dumps and related studies

would be carried out.

NOTE: However, possibility shall be explored for handing over the residential &

non-residential buildings and other infrastructures including the reclaimed land to

state govt. for the benefit of local villagers and strengthening the area

infrastructures. The end use of these facilities shall be decided by State Govt. with

the help of local govt. and Village Panchayat.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 22 of 29

18.10 Economic Repercussions of closure of mine

18.10.1Manpower of the Project- Departmental: 244

Outsourcing: 122

18.10.2Assessment of Income Scenario of local people

a) 440 numbers of local employees will be redeployed in other projects of the

company till their superannuation.

b) Approximate no. of 2500 people engaged in indirect employment / ancillary activities

will find no financial loss due to the mine closure as their activities will be shifted in

the new or expansion mines located in the coalfield area.

(c) Resettlement / Redeployment of (a) & (b)

It will be decided before the final closure and shall be covered in the Final Mine

Closure plan.

(d) Views of society and expectation on closure of mine.

Views of the society should be positive and they should be satisfied with the facts

stated in the note below.

NOTE: It is proposed that reclaimed and afforested land will be handed over to

State Forest Dept for the benefit of local ecosystem. The forest wealth can also be

utilized by local people or tribal in the form of fruits and fodders. The water reservoir

in the mine voids will be utilized for pisciculture, irrigation, domestic drinking water

or stabilizing the ground water regime. Landscaping during closure of mine will

make the spot for tourist attraction.

18.11 Time Schedule

The closure of mines involves environmental, technical, social aspects and

financial assurance for implementing the post closure activities as per guidelines of

Ministry of Coal.

The time scheduling is being provided on the basis of time interval of five year as

required in the MoC guidelines. This period of 5 years is considered as one phase of five

years and reclamation of one phase must be taken-up before commencement of mining

activity in the subsequent phase. The action plan for reclamation activities has been

provided in Figure 18.7.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 23 of 29

Figure 18.7

Sl.No Activities in Reclamation

Phase

1st 2nd 3rd 4th Mine closure

1 Backfilling & Grading of dump

2 Leveling of Dump

3 Toe Walling

4 Provision of Water Coursing Channels

5 Provision of Sedimentation Pond

6 Provision of Garland Drains

7 Provision of Check dams at high velocity points

8 Top soil Application

9 Provision of Jute Netting over steep slopes

10 Provision of Grass Legumes

11 Terracing of slopes

12 Pit digging

13 Plantation

The post closure implementing activities will run for three years. The activities will

be implemented as per bar chart provided in Figure 18.8.

Figure 18.8

Sl. No.

Activities Time Frame

Half Yearly

1 2 3 4 5 6

1. Preparation of Survey & Disposal Report

1 month

2. Slope Stability study for high walls and internal backfilled dumps

1 month

3. Disposal of P&M including HEMM, CHP, W/S, Siding

2 and half

years

4. Backfilling of mined out Area ( OC ) 2 years

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 24 of 29

5. Dismantling of Industrial structure 2 years

6. Grading & dozing of high walls for OC 2 years

7. Fencing of quarry 2 years

8. Clearing of Coal Stock and Infrastructural Area.

2 years

9. Disposal / Dismantling of Residential colony

2 &1/2 years

10. Plantation & landscaping on backfilled area.

3 years

11. Plantation over cleaned land of Infrastructure.

from 2nd year

12 Sealing of mine entries for UG mine from 2nd year

Not Applicable

13. Environmental Monitoring 3 years

14. Subsidence Management for U/G 3 years Not Applicable

15. Post closure subsidence monitoring for UG

3 years Not Applicable

16 Any project specific activities Nil

The manpower for implementing the above activities with time bound manner would

be provided.

18.12 MINE CLOSURE COST

The mine closure cost will cover the various related activities for which a corpus

escrow account @ Rs. 6.0 lakh per Ha for Opencast mine of the project area shall be

opened with the coal controller organization. The above amount is as per the mine closure

guidelines issued in August 2009, which will be updated for the present financial year

based on the cost index value.

18.11.1 Mine Closure Cost for OC mine

As per the guidelines of the MoC, the cost of the mine closure is to be computed

on the basis of the project area involved in the project. In Amadand OCP total land area

involved is 1443.005 Ha. The updated cost of the mine closure as on March’15 is

estimated to be Rs. 8.15 lakh per hectare (considering the admissible escalation over Rs.

6.00 lakh per Ha as on August 2009).

Final mine closure cost @ Rs = W.P.I of March 2015 176.10 /W.P.I of Aug.09

129.60 x 6= Rs.8.15 Lakh/ Ha. for 1443.005 Ha = Rs.11760.491 lakhs.

The balance life of the mine is 19 years. Hence, the management of funds in the

Escrow Account would be as follows:

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 25 of 29

Table 18.8

Year-wise Fund for Escrow Account

Year Fund Deposited in

Escrow Fund Fund to be Reimbursed (Maximum)

1 618.973 Nil

(+) accrued interest as applicable

2 649.922 Nil

3 682.418 Nil

4 716.539 Nil

5 752.366 Nil

1st phase 3420.218 2736.174

6 789.984 Nil

7 829.483 Nil

8 870.957 Nil

9 914.505 Nil

10 960.230 Nil

2nd phase 4365.159 3492.127

11 1008.242 Nil

12 1058.654 Nil

13 1111.587 Nil

14 1167.166 Nil

15 1225.524 Nil

3rd phase 5571.173 4456.938

16 1286.800 Nil

17 1351.140 Nil

18 1418.697 Nil

19 1489.632 Nil

final phase 5546.269 8217.579

Total 18902.819 18902.819

*The interest will be as per the existing rates for the period.

Table 18.9

Total escalation of escrow fund of March’15 from the base year of Aug’09 is given below

Year Amount (As of August’09)

Escalation

Total amount to be deposited in escrow account (As of March 15)

1 455.686 163.287 618.973

2 455.686 194.236 649.922

3 455.686 226.732 682.418

4 455.686 260.853 716.539

5 455.686 296.680 752.366

Phase 1 2278.430 1141.788 3420.218

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 26 of 29

6 455.686 334.298 789.984

7 455.686 373.797 829.483

8 455.686 415.271 870.957

9 455.686 458.819 914.505

10 455.686 504.544 960.230

Phase 2 2278.430 2086.729 4365.159

11 455.686 552.556 1008.242

12 455.686 602.968 1058.654

13 455.686 655.901 1111.587

14 455.686 711.480 1167.166

15 455.686 769.838 1225.524

Phase 3 2278.430 3292.743 5571.173

16 455.686 831.114 1286.800

17 455.686 895.454 1351.140

18 455.686 963.011 1418.697

19 455.686 1033.946 1489.632

Final phase 1822.744 3723.525 5546.269

TOTAL 8658.034 10244.785 18902.819

The break-up of final mine closure cost, activities-wise is given in Table-18.10 below.

Table 18.10

Major Activity-wise Break-up of Mine Closure Cost Type of mine: Open cast Size of the mine: 1443.01 Ha. Production: 4.0 MTY

Sl. No.

Activity MC Cost (% Weightage)

Remarks

A Dismantling of Structures To be included in final mine closure plan

- Service Buildings 0.20

- Residential Buildings, 2.67

- - Industrial Structures like CHP, workshop, Field Sub -Station etc.

0.30

B Permanent Fencing of mine void and other dangerous area

To be included in final mine closure plan Random rubble masonry of height 1.2

metre including levelling up in cements concrete 1:6:12 in mud mortar.

1.50

C Grading of highwall Slopes To be included in final mine closure plan.

Levelling & Grading of highwall slopes. 1.77

D OB Dump Reclamation

Handling/Dozing of external OB dump into mine void.

88.66 71% for progressive & 17.66% for Final mine closure.

Bio-reclamation including soil spreading, plantation & maintenance.

0.40 Equal Weightage throughout the life of the mine

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 27 of 29

E Landscaping

Landscaping of the cleared land for improving its aesthetic.

0.30 To be included in final mine closure plan.

F Plantation

Plantation over area obtained after dismantling.

0.50 To be included in final mine closure plan.

Plantation around fencing. 0.20 To be included in progressive mine closure plan.

Plantation over the cleared off external OB dump

0.00 To be included in progressive mine closure plan.

G Monitoring / testing of environmental parameters for three years.

For three years after mine closure.

- Air quality 0.22

- Water quality. 0.20

H Entrepreneurship development (vocational and skill development training for sustainable income of affected people).

0.26 Equal Weightage throughout the life of the mine

I Miscellaneous & other mitigation measures.

2.02 Equal Weightage throughout the life of the mine

J Manpower cost for Supervision 0.80 To be included in final mine closure plan.

Total 100

NOTE: The above cost expenditure will be met from the corpus escrow account deposited

by the mine operator. However, the additional amount beyond the escrow account will be

provided by the mine operator after estimating the final mine closure cost five years prior

to mine closure (as per the mine closure guideline).

The progressive mine closure will deal the land reclamation as per the calendar plan of

project report given in table 18.4. The cost of progressive land reclamation is already part

of the project cost. Therefore, the escrow account for mine closure will deal only the final

mine closure.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 28 of 29

18.12 Implementation Protocol

For implementing the mine closure activities, the following organisational structure has

been proposed:

Director (Tech.)

Environmental monitoring for three years after closure of mine will be carried out to

evaluate the environmental quality of the area. If need be, proper mitigation measures will

be taken up after evaluating the environmental quality. The funds for this have been

provided in the cost estimate. Before closure of the mine, Area GM will prepare survey

and disposal report and the same will be submitted to DGMS for acceptance.

GM (Env) CGM /GM (Area)

Land

reclamation &

Employee

Redistribution

Disposal of

plant &

machinery,

CHP,

Workshop etc.

Project

Manager

Plantation &

dismantling of

civil structures,

environmental

monitoring

Area Engineer

(E&M)

Area Civil

Engineer

Monitoring &

Overall co-

ordination

Sr.Mana-

ger(Env)

Sr.Mana-

ger(Mine

Closure)

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

Job No.515126 Chapter 18 / 29 of 29

18.13 MINE CLOSURE MONITORING & AUDITING

The mine authority shall comply with the closure plan approved. Monitoring of the plan

will be carried out at the project site during the life of the project and at each stage of the

closure.

The mine authority has an ongoing responsibility for rehabilitation of its mine site to the

point where the site can be returned to the concerned authorities

The company should create organisation at mine, area and headquarter level to monitor

the operation of mine closure.

There will be an organisation / team of supervisory officers / staff and workman for

implementing and carrying out various activities of mine closure.

A team of employees will continue at the mine site even after the mine is closed, to see

that completion criteria are met or not.

The last phase of the closure may take 4 to 5 years of time even after production of coal

is stopped.

The mine authority will finally withdraw from the area after the implementation of closure

plan.

*******

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 19 / 1 of 2

CHAPTER - XIX

MANPOWER, PRODUCTIVITY AND TRAINING

19.1 MANPOWER ASSESSMENT

The requirement of manpower at the rated capacity of 4.00Mt of coal per year

has been estimated. Total departmental manpower estimated as 244 numbers

resulting in an overall OMS of 59.17t.

While estimating the total manpower an additional provision of 25% has been

made for leave and sick considering 330 days working. In addition to that 122

nos outsourcing manpower also has been considered in project costing for

working in CHP, security and workshop etc.

19.2 The details of estimated manpower with scale/category wise are given in

Appendix-B. The break-up of total manpower in outsourcing option in

groups’ viz., workers, monthly paid staff and officers are given below:-

Sl. No

Particular No. Percentage of

total Manpower

1 Workers 145 59.43%

2 Monthly paid staff

70 28.69%

3 Officers 29 11.88%

Total 244 100%

19.3 In outsourcing option, total 122 manpower including 30 nos related

security is proposed to be outsourced and its impact has been envisaged in

the IRR calculations.

19.4 PRODUCTIVITY

Total departmental manpower requirement estimated for the project is 244

numbers. Considering 244 departmental manpower, the overall OMS of

project will be 59.17.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 19 / 2 of 2

19.6 TRAINING

It is proposed that all the workers who will operate the HEMM etc. will be

given proper training, so that, they are able to operate these equipment

efficiently and safely. Refresher training will also be given to these workers

at regular interval. For safe and proper operation of the project, an

executive of higher rank has been proposed to be the chief of the project.

Adequate no. of executives has been provided in the report to look after

different activities. These executives have also been proposed to be given

training in their fields at regular intervals, so that; they will be updated with

the advancement in their respective field of operation.

*******

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 20 / 1 of 3

CHAPTER - XX

PROJECT IMPLEMENTATION SCHEDULE

20.1 INTRODUCTION

It is well known fact that for timely implementation of a project, it is essential

that all the activities related with project construction are properly planned,

closely monitored and effectively supervised. All implementing departments

have their own implementation manuals which are followed for monitoring and

construction of the project, so that, man, materials and money are made

available to the project in time as spelt in the project report, with a view to

prevent cost and time over-run. Responsibility, power for each executive has

also been included in the implementation manual to prevent overlapping of

operational areas. Sufficient administrative and financial power has been

defined for key executive to take timely and effective decisions for the

implementation of the project.

Time estimates are broad and indicative only, necessary modifications to suit

local site conditions are to be incorporated subsequently.

20.2 PROJECT SCHEDULE

The life of the proposed mine will be 19 years including construction period.

The maximum quarry depth will be around 152.0 m. The Production Program

proposed is as given below:-

Year Coal Production (Mt) OB Removal (M.Cum)

1 2.00 20.59

2 3.00 36.91

3 4.00 52.54

4 4.00 52.54

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 20 / 2 of 3

20.3 Technically, zero date has been adopted as the date of approval and/or date

of environmental clearance or the date of the land acquisition whichever is

later.

Some of the preliminary activities as enumerated below may be initiated as

advance action.

1. Posting of key personnel.

2. Proceedings of land acquisition for the proposed quarry complex.

3. Survey and marking of the road alignment, dumping area, site for service building etc.

4. Alignment of power line and sub-station.

5. Arrangement of water supply and sub-station

6. Construction of approach roads and culverts.

7. Processing indent for principal HEMMs to be used during development period.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 20 / 3 of 3

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 21 / 1 of 9

CHAPTER - XXI

FINANCIAL EVALUATION 21.1 CAPITAL INVESTMENT

21.1.1 Capital investment and its phasing

Phasing of Additional Capital (Rs. In Lakhs) Total Additional

Capital 1st 2nd 3rd 4th 5th 6th to 15th

5119.98 11578.31 22244.91 24457.52 12102.15 558.21 76061.08

Existing Capital as on 01.04.2015 is 10882.52 Lakhs and Net block capital is 6009.91

Lakhs. Some existing HEMM will be transferred to other mine as in this report both coal

and OB removal is proposed to be done by outsourcing. As on 31.03.2015, Net block of

HEMM which are to be transferred from this project is Rs 3528.71 Lakhs. Net block

considered for project costing = Rs (6009.91-3528.71) Lakhs = 2481.20 Lakhs

21.1.2 Basis of price of P&M, Civil works & hiring rate

Price of P&M has been taken from the standard price list published by CMPDI, HQ on

May 2014. Prices have been updated upto July 2015 as per escalation rate given in the

price list.

The preparation of cost estimates for civil infrastructure is based on prevailing cost

index of the area in July 2015. The cost index value has been calculated from the

market rate of the area. Considering the prevailing rates of materials and labour in

Jamuna-Kotma Area, the cost index works out to 2926 w.r.t. 100 base in Delhi as on

1.10.1976.

21.1.3 Foreign Capital

No foreign capital investment has been envisaged.

21.1.4 Capital upto target year - Rs. 38943.20 Lakhs

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 21 / 2 of 9

Capital requirement beyond target year - Rs. 37117.88 Lakhs

Specific investment - Rs. 2173.60 tonne

Specific investment for P&M - Rs. 996.90 tonne

21.2 OPENING OF REVENUE ACCOUNT The norms for bringing coal projects into revenue account as decided in the meeting

held under the chairmanship of JS&FA on 9.6.04 are as follows:-

1) Revenue expenditure to be capitalized should be net of sales receipts of coal

produced during the construction period.

2) The period of construction has to be defined to determine the commercial readiness

of the project to yield on a sustainable basis.

3) In case of opencast projects, the volume of stripping of OB and in case of UG

projects, the completion of required development activities during the above period of

construction have to be clearly defined.

4) Based on the above, the capitalization of revenue expenses / opening of revenue

account will be decided.

Accordingly, a definition of the term ’commercial readiness of a project has been drafted

and based on this a norm for capitalization of revenue expense / opening of revenue

expenditure of a project has been suggested as under:-

A. Commercial Readiness: A project will be treated to have reached the stage of commercial readiness to yield

production on sustainable basis from the year when all the following criteria have been

achieved –

(i) 30% of the total volume of excavation (Coal and OB) envisaged in the target year.

(ii) The land required for the project upto target year has been acquired.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 21 / 3 of 9

(iii)Construction of CHP and railway siding have been completed or adequate

alternative arrangement for sizing and dispatch of coal have been commissioned for the

Project.

B. Capitalisation of Revenue Expenses based on commercial readiness:

For the preparation of Feasibility Reports, the revenue expenditure of a project can be

capitalized till the year the project achieves commercial readiness as per the plan

envisaged.

The capitalization of revenue expenditure, in no case, shall extend beyond the year the

Project achieves the status of commercial readiness.

The Amadand Opencast project is on going project with a target production of 1.15 Mty

and the project is already in operation. This RPR is being prepared to enhance the

production from 1.15Mty to 4.0 Mty.

Considering the on going project, the Revised Project Report would be brought

under revenue account w.e.f. the beginning of 1st year of operation. Thus the revenue

expenditure of the project has not been capitalized during the initial years.

21.3 REPLACEMENT CAPITAL

Year-wise phasing of replacement capital is given in Appendix-D.1 column No.3. 21.4 SOURCES OF FINANCE

The project will be financed completely by internal resources.

21.5 COMPLETION COST

As per the latest guidelines, the completion cost of a project will qualify all the following

conditions:

- Achievement of coal production capacity of 80% of the rated output.

- Completion of all major facilities and initial mine development work.

- Procurement of major and essential plant & machinery.

Completion cost of the project is estimated as Rs. 912.28 Crores.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 21 / 4 of 9

21.6 METHOD OF ESTIMATION OF CAPITAL COST: a) Land

Rate of revenue, forest and tenancy land are provided by SECL.

b) Civil Construction (alongwith Cost Index)

The preparation of cost estimates for civil infrastructure is based on prevailing cost

index of the area in July 2015. The cost index value has been calculated from the

market rate of the area. Considering the prevailing rates of materials and labour in

Jamuna-Kotma Area, the cost index works out to 2926 w.r.t. 100 base in Delhi as on

1.10.1976.

c) P&M

Price of P&M has been taken from the standard price list published by CMPDI, HQ on

May 2014. Prices have been updated upto July 2015 as per escalation rate given in the

price list.

21.7 COST OF PRODUCTION AT DIFFERENT LEVEL OF PRODUCTION a) Salaries & Wages Cost

The detail of category-wise / scale-wise manpower requirement and year-wise estimated wages cost is given in Appendix-B.1.

Estimated salaries & wages cost is worked out as Rs. 57.20/Te.

b) Stores Cost

Stores Cost has been estimated taking into account provision for Repair &

Maintenance, POL, Explosive and miscellaneous stores cost. The estimated Stores

Cost has been worked out to Rs.114.40/Te.

c) Power Cost

Estimated Energy Consumption is given in the relevant chapter for Power Supply. The

power cost has been taken as Rs.6.0/unit. The average power cost per tonne of coal

production works out to Rs.44.93 at 100% level of operation.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 21 / 5 of 9

d) Misc. Expenditure

This cost has been estimated to cover expenditure on Printing & Stationary, Postage,

Telephone, repair & Maintenance of assets other than P&M, Workshop Workshop

Debit, and Insurance & Taxes for vehicles and other repairs and a further provision has

been made for deterioration of coal stock. Miscellaneous expenditure per tonne works

out to Rs.30.80.

Provision has been considered to meet cost of environmental related activities at the

rate of Rs 5/tonne and it is also included in the miscellaneous head.

e) Administrative Charges

A provision has been made in total revenue cost estimate for Administrative charges

based on the Admn. Cost per tonne of coal production as was appearing in the last

Annual Report of SECL. Total Admn. Cost has been calculated at 100% level and

treated as fixed cost. As such for all other estimated level of operation the absolute

Admn. Cost has been taken as it worked out for 100% level of operation. The Admn.

Cost comes to Rs. 6.40/Te (considering the recommendation of 310th CIL Board for

revised costing Norms 10% of Administration cost considered).

f) Interest on Working Capital

Interest on Working Capital has been calculated on the basis of 4 months operating

expenditure. Rate of interest is taken as 14.50%. The Interest on Working Capital

comes to Rs. 45.08/Te.

g) Depreciation

Straight line method of depreciation has been provided to arrive at depreciation cost per

tonne of coal production. The depreciation Cost comes to Rs. 96.57/Te.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 21 / 6 of 9

h) Interest on Loan Capital

Interest @ 11.5% on loan capital is to be considered for computation based on given

Debt Equity Mix. However, loan capital in this project is NIL.

i) Environment related Cost

Rs 120.27 /Te of coal has been provided to absorb environmental related cost in the

project.

j) Mine Closure Cost

Rs.26.84 /Te has been provided in the project against Mine Closure Cost.

k) Cost of Production - Cost of production per tonne at 100%, 85% and 80% level of

production works out to Rs.1074.40, Rs.1120.68 & Rs.1139.96.

l) CSR Cost - CSR cost as per latest CIL’s CSR Policy communicated vide CGM

(Welfare), CIL, letter No.CIL/C-5C/231(CSR)/269 dated 3.12.2009, source of fund under

this head will be 5% of the retained earning of the previous year subject to minimum

Rs.5/- per tonne of coal production of previous year. However, this fund is not a part of

project costing and the same will be spent by company as per CSR activities.

21.7.1 OUTSOURCING RATES

Coal extraction and OB removal is proposed to be done by outsourcing. The

rates have been considered based on the escalated rates table received from SECL.

The outsourcing cost of OB for average lead of 3.0Km is considered are

Rs.52.53 per cum with current diesel price Rs 57.84 per litre. Rehandling cost

considered Rs 40.00 per cum of OB to be rehandled. The outsourcing cost of Coal for

surface miner cutting, loading and transport from face to inpit belt conveyor are follows:-

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 21 / 7 of 9

Particulars (Rs./t)

Coal Cutting (by Surface Miner) 23.91

Loading 14.29

Ave Transportation from face to in pit belt conveyor 1 to 2 km (and surface transport 5Km upto 3rd year)

31.61

Total (Say) 69.81

Service Tax has not been considered in estimating outsourcing rate of the

project as CENVAT credit is available to the extent of Service Tax rate. The scope of

work by outsourcing will include drilling, loading and transportation, dozing and

maintenance of haul roads. All statutory rules, regulations and applicable laws are to be

followed.

21.8 SELLING PRICE The weighted average selling price of coal for this coal project has been taken

as Rs.1298.22 per tonne(considering coal price of power sector consumer) for ROM

processed coal (-100 mm). The weighted average grade of coal is ‘G-8’. The mean

GCV of Amadand OC is 4933 Kcal/Kg.

CALCULATION OF SELLING PRICE

(a) Price of GCV 4933Kcal/Kg coal per tonne* = Rs.1250.00

(b) Price taken in PR coal per tonne** = Rs.1187.50

(c) Sizing charges (-100 mm) per tonne*** = Rs.79.00

(d) Average of transport **** = Rs.31.72

Weighted average selling price -Rs.1298.22 /tonne

*As per price notification No. CIL:S&M:GM(F):Pricing:1965 dated 31.01.2012

**95% of the grade based on borehole data as per norms.

***As per price notification No. CIL:S&M:GM(F):Pricing:2784 dated 16.12.2013

**** Average Transport charge includes Rs 57 per tonne upto 3rd year and rapid loading charge Rs. 26 per tonne beyond 3rd year. As per price notification No. CIL:S&M:GM(F):Pricing:2340 dated 13.11.2013

21.9 Profitability Profit/Loss Rs./t at 100% = 223.82

85% = 177.54

21.10 Manpower, OMS, EMS Manpower - 244, OMS - 59.17, EMS - 3384.01

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 21 / 8 of 9

21.11 Financial IRR -

Financial IRR at 100% level of production = 21.33 %

At 85% level of production = 13.55 %

21.12 BREAK-EVEN PRODUCTION It is estimated that the project will achieve break-even point at 2.16 Mty of production

which is 53.95 % of rated capacity.

21.13 Sensitivity Analysis - given in the Appendix-C.4.

21.14 CONCLUSION

In this report both coal and OB removal is proposed to be done by outsourcing.

In this outsourcing option, total capital investment works out to Rs. 869.44 Crores.

(Addl. Capital investment of Rs. 760.61Crs.). The project report for Amadand OC(1.15

Mty) may be treated as dovetailed with project report for Amadand OC (4.00 Mty) for the

purpose of implementation as all the required activities and financial provisions of

Amadand OC(1.15 Mty) have been included in Amadand OC (4.0 Mty) Report.

In this report recommendations of 310th meeting of CIL Board (held on 8-11-14)

regarding modification of cost provisioning in PR for CIL projects have been

incorporated.

The project is yielding an IRR of 13.55% at 85% level of production. As per the

guidelines, a Project is economically viable when it achieves more than 12% IRR at

85% level of Production. Since, this Project is having Internal Rate of Return more than

12% at 85% level of target production i.e. 13.55% the Outsourcing Option of this project

is economically viable project.

The outsourcing option of RPR for Amadand Opencast Project (4.00Mty) was

placed before SECL Board’s 236th meeting held at Raipur on dated 04.09.2015 for a

total capital of Rs 869.44 Crores and SECL Board directed to submit the same to CIL,

since capital provision in the RPR exceeds Rs 500 Crores.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 21 / 9 of 9

Accordingly, RPR for Amadand Opencast Project (4.00Mty) was placed before

325th CIL Board meeting held at Kolkata on dated 05.03.2016 for a total capital of Rs

869.44 Crores. CIL Board accorded its approval to Project Report for Amadand

Opencast Project for a rated capacity of 4.00 Mty at an estimated capital investment of

Rs 869.44 Crores for implementation of the project with total outsourcing variant i.e

both coal and OB outsourcing.

*******

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 22 / 1 of 7

CHAPTER - XXII

A CHAPTER ON OUTSOURCING 22.1 INTRODUCTION

Outsourcing has become increasingly attractive for many organizations in

recent past. Businesses irrespective of its size, skill, knowledge and

technology are finding outsourcing mechanism most befitting in terms of

cost reduction as well as quality improvement .With globalization and

removal of barriers, outsourcing has created new opportunities for

generation of employment. Today whether it is a canteen services or

security services or courier services or gardening, is no longer one man

providing service to one organization. These are just examples and we

can go on listing them but essentially they are contractor or organizations

which provide a specialized service at a competitive price. The service

itself is much better than what an entrepreneur if he engages workmen on

his roll would be able to provide. Further, the quality of the service is much

better and it leaves the entrepreneur to concentrate on its core activity.

Outsourcing will remain in the four front of every business executive mind

as a business strategy that will let their organization to create and sustain

business value in the competitive global market for reduced cost, focus on

core business processes, improve services, enhance skills, and increase

competitive advantages.

Growth in outsourcing is expanding to include not only IT functions, but

critical business processes, as well as evolving application areas like

enterprise resource planning and re-business initiatives. Successful

companies are incorporating outsourcing as a key strategy for growth and

differentiation. No longer considered merely a tactic for cutting costs and

adding temporary staff, outsourcing is being accepted in board rooms

around the world as a critical success factor for business survival. We

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 22 / 2 of 7

need to give as much attention to managing processes as we have in the

past to managing products.

For years, outsourcing was more a matter of “out asking” – hiring outside

vendors to perform specific jobs or manage specific projects within a

department of a large organization. Many things that are done inside the

companies are labour intensive. Those are the kind of work where human

being have to intervene in a process and use decision – making skills –

such as interpretation, validation, translation, transliteration or

transformation.

22.2 SCOPE OF WORK PROPOSED TO BE OUTSOURCED i) Drilling

The external agency will prepare the site and carry out blast hole

drilling as per the pattern decided by the project authorities according

to strata conditions and stipulations of DGMS

ii) Coal cutting by surface miner

Surface miner has been proposed for extraction of coal. The external

agency will prepare the site decided by the project authorities

according to strata conditions and stipulations of DGMS for working of

surface miner.

iii) Loading and Transportation of coal

The work involves loading and transportation of coal to dumping site

as per guidelines of the project authorities or otherwise to suit local

conditions. All activities involving the loading and transportation have

been proposed to be done by outside agencies. All statutory rules ,

regulation and applicable laws are to be followed including those

related to Govt. licenses, workmen compensation , insurance etc. by

the agency to whom the job has been awarded. Coal has to be

transported to and from the site as decided by the project authorities

from time to time in accordance with the requirement of the project.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 22 / 3 of 7

iv) OB Removal

The work involves excavation of OB and dumping of the same to

different dump locations. This includes construction and maintenance

of haul roads for plying of dumpers/tippers with suitable number of

graders and dozers. The leveling of the dumps is to be carried out by

the agency to which the work has been awarded for OB removal.

The site of excavation and dumping is to be decided by the project

authorities in accordance with the requirement of the project. All

statutory rules, regulation and applicable laws are to be followed

including those related to Govt. licenses, workmen compensation,

insurance etc. by the agency to whom the job has been awarded.

v) Accommodation, Site Office, Electricity etc.

Site office may be provided by the company on availability basis,

which will be chargeable. However, regarding accommodation and

other facilities to persons engaged by the outside agency Barrack type

residential complex has been provided in this Project Report.

Electricity to the site office may be provided on chargeable basis.

22.4 ANNUAL WORK LOAD FOR EXTERNAL AGENCY

The total Coal and OB will be outsourced. Peak coal and OB production

will be 4.00 Mty and 41.50 Mcum. The annual work load for the external

agency will be 44.13 Mcum (approx.).

22.5 OUTSOURCING RATES

Coal extraction and OB removal is proposed to be done by outsourcing.

The rates have been considered based on the escalated rates table received

from SECL.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 22 / 4 of 7

The outsourcing cost of OB for average lead of 3.0Km is considered are

Rs.52.53 per cum with current diesel price Rs 57.84 per litre. Rehandling

cost considered Rs 40.00 per cum of OB to be rehandled. The outsourcing

cost of Coal for surface miner cutting, loading and transport from face to inpit

belt conveyor are follows:-

Particulars (Rs./t)

Coal Cutting (by Surface Miner) 23.91

Loading 14.29

Ave Transportation from face to in pit belt conveyor 1 to 2 km (and surface transport 5Km upto 3rd year)

31.61

Total (Say) 69.81

Service Tax has not been considered in estimating outsourcing rate of

the project as CENVAT credit is available to the extent of Service Tax rate.

The scope of work by outsourcing will include drilling, loading and

transportation, dozing and maintenance of haul roads. All statutory rules,

regulations and applicable laws are to be followed.

22.6 SAFETY ASPECTS FOR OUTSOURCING OF HEMM

Outside agency deploying HEMM or any equipment in the mine for

excavation of coal shall plan their activities in confirmation with the prevailing

statutory provisions as per Mines Act 1952 and CMR 1957 applicable for

safety in opencast mines. However, all statutory rules, regulations, applicable

laws etc. and statutory requirement related to Govt. licenses, workers

compensation, insurance, etc., including minimum wage act for workers

employed by the outside agency shall have to be adhered to.

Rules if any imposed by local / state / central authorities should also be

complied by leaser of HEMM / equipment and then shall have to supply

various protective equipment viz., helmet, shoes etc. to the workmen at their

cost.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 22 / 5 of 7

All the regulations and schedules of Coal Mines Regulations 1957 relating

to opencast mining have to be adhered to and implemented in order to

maintain day to day safety precautions as per stature.

Special precaution should be taken while deploying workers in the mine.

Before employing any worker to the mine proper vocation training should

be imparted and recommendations of VIII Safety Conference should be

strictly followed. Terms and conditions shall be fixed by management for

deployment of workers by outside agency. Some of the major aspects are

as follows: -

A) For Persons:

i) No persons shall be deployed unless he is trained at VTC.

ii) Records in Form-B, Form-D shall be maintained.

iii) Records of Vocational Training Certificate and driving license of

operators shall be kept by HEMM outsourcing agency and shall be

made readily available for inspection by management.

iv) Salaries shall be distributed in front of management

representative.

v) No person shall be employed unless person holds VTC certificate

and management is informed. A record of it shall be maintained.

vi) Adequate supervision shall be maintained by qualified competent

persons.

vii) Outside agency shall follow safety guidelines and safety

instructions from project authorities.

B) For Machineries as recommended by DGMS Cir. (Tech.) 1 of

1999 :

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 22 / 6 of 7

i) All the machineries to be deployed in mines should be checked

before deployment by competent authority.

ii) Regular checking of m/c deployed by outside agency shall be

done. No unfit machine shall be deployed before the defect is

rectified.

iii) A proper record of repair and maintenance along with inspection

done by management and defect pointed out shall be maintained

and signed by authorized person.

iv) The trucks deployed outside agency shall be provided with audio

visual alarms, proper light for use at night and period when

natural light is not sufficient. Also audiovisual alarms for reversing

on trucks shall be provided.

Other precautions for machines

i) RTO certificate photocopies of all vehicles shall be submitted to

management.

ii) Daily welding, monitoring, inspection shall be done by the

agency’s mechanic as directed by management.

iii) Machine manufacturers should be asked to give risk analysis

details in respect of machines deployed by outside agencies.

iv) Suitable type of the fire extinguishers shall be provided in every

machine.

C) General :

i) No person / vehicle shall be deployed at any place other than

authorized place.

ii) All workers should obey lawful instruction of mine management.

RPR for Amadand OCP (4.0 Mty) (Updated July’ 2015) CMPDI

. . JOB NO.-515126 Chapter 22 / 7 of 7

iii) Risk Management Plan of tipper / pay loader shall be made and

implemented.

iv) All drivers shall obey systematic traffic rules prepared by

management.

v) Before deploying workers, they must be trained and briefed about

safety aspects in opencast mine. However, during course of

execution of the work, if any accident occurs whether major or

minor, the matter shall have to be immediately informed to mine

management i.e. Colliery Manager / Agent / GM of Area, so that,

notices of accidents in accordance of (Reg.9 of CMR 1957) and

Section 23 of Mines Act 1952 may be given and other necessary

steps may be taken in accordance with the Mines Act 1952.

vi) Outside Agency shall operate transport system in such a way so

as to minimize pollution in the mine.

*******

APPENDICES

OUTSOURCING OPTION

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

1

AP

PE

ND

IX-A

RE

VIS

ED

PR

OJ

EC

T R

EP

OR

T F

OR

AM

AD

AN

D O

PE

NC

AS

T P

RO

JE

CT

(4.0

Mty

)Life

(yrs

) :19

Capacity

(Mty

) :4.0

0

STA

TE

ME

NT S

HO

WIN

G T

HE

ES

TIM

ATE

D T

OTA

L C

AP

ITA

L IN

VE

STM

EN

T A

ND

ITS

PH

AS

ING

ALO

NG

WIT

H C

ALC

ULA

TIO

N O

F D

EP

RE

CIA

TIO

N

(Ou

tso

urc

ing

Op

tion

)(A

mount in

Rs L

akhs)

Sa

nctio

ne

d

TO

TA

LA

nnual

Depr.

Annual

Depr.

(1.1

5 M

ty)

CA

PIT

AL

12

34

510

15

%A

mount

1.

LA

ND

773.3

01821.9

416568.8

018390.7

4507.9

82500.0

03000.0

03000.0

04000.0

04068.8

00.0

00.0

0

2.

BU

ILD

ING

:-

a) S

ER

VIC

E232.3

1331.0

9664.0

4995.1

35.0

0100.0

0120.0

0150.0

0150.0

0144.0

45.2

634.9

5

b) R

ES

IDE

NTIA

L788.7

862.7

2898.7

2961.4

446.5

7150.0

0150.0

0200.0

0200.0

0198.7

21.6

915.1

9

3.

PLA

NT &

MA

CH

INE

RY

3705.2

17407.9

132468.1

739876.0

8155.0

00.0

05502.9

610638.9

111880.2

43887.8

5279.4

5278.7

65.1

5-3

3.3

32434.3

3

4.

FU

RN

ITU

RE

& F

ITTIN

GS

21

13.6

2115.5

0129.1

230.0

030.0

030.0

025.5

05.1

55.9

5

5.

RA

ILW

AY

SID

ING

00.0

08019.2

88019.2

810.0

00.0

00.0

04002.0

04017.2

80.0

00.0

00.0

05.1

5412.9

9

6.

VE

HIC

LE

S116.3

962.5

288.5

6151.0

80.0

035.3

753.1

90.0

00.0

011.3

110.0

2

7.

PR

OS

PE

CTIN

G &

BO

RIN

G60.2

561.7

040.8

1602.5

120.0

020.8

15.0

02.0

4

8.

DE

VE

LO

PM

EN

T

8.1

CA

P. O

UTLA

Y IN

MIN

ES

1782.8

204.3

410399.8

910604.2

38850.3

31000.0

01000.0

03000.0

03000.0

02399.8

95.0

0519.9

9

8.2

RO

AD

S &

CU

LV

ER

TS

214.9

3196.2

44901.6

05097.8

418.7

9700.0

01000.0

01000.0

01000.0

01201.6

05.0

0245.0

8

8.3

WA

TE

R S

UP

PLY

& S

EW

ER

AG

E147.0

720.3

9755.7

5776.1

4555.3

6100.0

0150.0

0150.0

0180.0

0175.7

55.0

037.7

9

DIS

PO

SA

L

8.4

PR

PR

EP

AR

ATIO

N C

OS

T &

49.2

11139.9

61139.9

650.0

0569.9

8569.9

85.0

057.0

0

SC

IEN

TIF

IC R

ES

EA

RC

H C

OS

T.

0.0

0

TO

TA

L O

F 8

2194.0

1420.9

717197.2

017618.1

79474.4

82369.9

82719.9

84150.0

04180.0

03777.2

40.0

00.0

0859.8

6

TO

TA

L C

AP

ITA

L IN

VE

ST

ME

NT

7891.2

010682.4

776061.0

886743.5

510199.0

35119.9

811578.3

122244.9

124457.5

212102.1

5279.4

5278.7

63775.3

2

9(A

)O

TH

ER

EXP

EN

SE

S O

F R

EV

EN

UE

5.0

0

NA

TU

RE

CA

PIT

ALIS

ED

DU

RIN

G

DE

VE

LO

PM

EN

T P

ER

IOD

207.2

5200.0

5200.0

5

9(B

)O

BR

E-D

RE

335.2

5

TO

TA

L O

F 1

TO

98433.7

010882.5

276061.0

886943.6

010199.0

35119.9

811578.3

122244.9

124457.5

212102.1

5279.4

5278.7

60.0

03775.3

2

10.

LE

SS

-DE

PR

EC

IATIO

N

CA

PIT

ALIS

ED

DU

RIN

G

DE

VE

LO

PM

EN

T P

ER

IOD

95.1

7

TO

TA

L C

AP

ITA

L IN

VE

ST

ME

NT

8338.5

310882.5

276061.0

886943.6

010199.0

35119.9

811578.3

122244.9

124457.5

212102.1

5279.4

5278.7

60.0

03775.3

2

PH

AS

ING

OF

AD

DIT

ION

AL

CA

PIT

AL

S

L.

NO

PA

RT

ICU

LA

RS

EM

P

Ca

pita

l

Inve

stme

nt

EX

IST

ING

CA

PIT

AL

as

on

1.4

.2015

Ad

ditio

na

l

Ca

pita

l

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

2

AP

PE

ND

IX-A

1

(Ou

tso

urc

ing

Op

tion

)(L

an

d in

Ha)

SL.

PA

RTIC

ULA

RS

AD

DIT

ION

AL

LA

ND

TO

BE

AC

QU

IRE

D

NO

.F

OR

ES

T

LA

ND

Alre

ady

Acquire

d a

s

31.0

3.2

015

FO

RE

ST

LA

ND

TO

TA

L

AG

RIC

UL-

TU

RE

LA

ND

SU

RF

AC

E W

ATE

R

BO

DY

WA

STE

LA

ND

OTH

ER

GO

VT

LA

ND

AG

RIC

UL-

TU

RE

LA

ND

SU

RF

AC

E

WA

TE

R

BO

DY

SU

RF

AC

E

WA

TE

R

BO

DY

WA

STE

LA

ND

OTH

ER

GO

VT L

AN

D

1.

QU

AR

RY

AR

EA

567.5

39

5.7

75

573.3

191.2

45

1.6

22

48.8

39

141.7

1715.0

2

2.

SA

FE

TY

ZO

NE

87.9

42

2.7

71

90.7

122.8

55

2.4

31

25.2

9116.0

0

3.

RE

HA

BIL

ITA

TIO

N50.7

98

50.8

050.8

0

4C

OLO

NY

15.1

70

15.1

715.1

7

5E

XTE

RN

AL D

UM

P20.0

00

20.0

0343.9

62

1.6

88

11.0

46

356.7

0376.7

0

6IN

FR

AS

TR

UC

TU

RE

18.3

52

18.3

556.7

84

0.8

30

0.7

65

2.1

97

60.5

878.9

3

7S

ER

VIC

E R

OA

D-

15.6

10

15.6

115.6

1

8C

HP

, SIL

O, S

IDIN

G41.6

60

0.4

04

42.0

642.0

6

9M

AG

AZIN

E10.0

00

10.0

010.0

0

OTH

ER

S22.7

20

22.7

222.7

2

GR

AN

D T

OT

AL

693.8

38.5

5702.3

8610.0

10.8

34.0

8125.7

2740.6

31443.0

1

CO

ST

OF

LA

ND

( A

RE

A in

Ha)

(AM

OU

NT IN

RS

.LA

KH

S)

SL

.P

AR

TIC

UL

AR

S

NO

.

Ex

istin

g

La

nd

acq

uire

d

EX

IST

ING

CA

PIT

AL

as

on

31.0

3.1

5

AR

EA

TO

BE

AC

QU

IRE

D

AD

DIT

ION

A

L A

MO

UN

T

TO

TA

L

LA

ND

RE

QU

IRE

ME

NT

TO

TA

L

AM

OU

NT

 

1

TE

NA

NC

Y /

AG

RIC

ULTU

RE

LA

ND

702.3

8610.8

415270.9

01313.2

215270.9

0

2F

OR

ES

T L

AN

D

5G

OV

T. L

AN

D129.7

91297.9

0129.7

91297.9

0

To

tal

702.3

81821.9

4740.6

316568.8

01443.0

118390.7

45000

5000

5000

5000

5000

5000

-13431.2

0

Note

:

2. L

and d

eta

ils g

iven a

re te

nta

tive b

ased o

n L

anduse P

lan s

upplie

d b

y a

rea a

uth

ority

.

3. M

inor c

hanges in

figure

s o

f additio

nal la

nd to

be a

cquire

d m

ay ta

ke p

lace a

t the tim

e o

f actu

al a

cquis

ition

d

ue to

unfo

reseen d

iscrip

encie

s/a

nom

alie

s in

diffe

rent re

cord

s w

ith d

iffere

nt d

epartm

ents

of S

tate

Gove

rnm

ent.

4. F

or R

&R

50.7

98H

a la

nd re

com

mended b

y s

tate

auth

ority

and a

lready fo

rward

ed fo

r appro

val.

RE

VIS

ED

PR

OJ

EC

T R

EP

OR

T F

OR

AM

AD

AN

D O

PE

NC

AS

T P

RO

JE

CT

(4.0

Mty

)

ES

TIM

AT

ED

CA

PIT

AL

INV

ES

TM

EN

T F

OR

LA

ND

TO

TA

L L

AN

D

RE

QU

IRE

ME

NT

La

nd

Alre

ad

y A

cq

uire

d a

s p

er (1

.15 M

ty)(a

s 3

1.0

3.2

015)

TE

NA

NC

Y L

AN

DG

OV

T L

AN

DTE

NA

NC

Y L

AN

DG

OV

T L

AN

D

1. T

enancy la

nd - @

25 la

kh p

er H

a, F

ore

st la

nd- @

10.0

lakhs p

er H

a, G

ovt. la

nd @

10.0

lakhs p

er H

a.

AD

DIT

ION

AL

T

OT

AL

PR

OV

ISIO

N

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

3

AP

PE

ND

IX-A

.2

(Am

ou

nt in

Rs

. La

kh

s)

Sl.N

o.

Pa

rticu

lars

As

pe

r Ap

pro

ve

d

PR

Pro

vis

ion

Ex

pe

nd

iture

up

to

31

.03

.20

15

Re

vis

ed

/ Ad

ditio

na

l

Pro

vis

ion

To

tal P

rov

isio

nR

efe

ren

ce

s

1.

Se

rvice

Build

ing

s2

32

.31

33

1.0

96

64

.04

99

5.1

3A

pp

end

ix-A.2

.1

2.

Re

sid

entia

l Build

ing

s7

88

.78

62

.72

89

8.7

29

61

.44

Ap

pe

nd

ix-A.2

.2

3.

Ro

ad

s a

nd

Culve

rts2

14

.93

19

6.2

44

90

1.6

05

09

7.8

4A

pp

end

ix-A.8

.2

4.

Wa

ter S

up

ply a

rrang

em

ent

76

.88

20

.39

17

5.3

51

95

.74

Ap

pe

nd

ix-A.8

.3

5.

Se

we

rag

e S

yste

m7

0.1

90

.00

58

0.4

05

80

.40

Ap

pe

nd

ix-A.8

.3a

To

tal

13

83

.09

61

0.4

47

22

0.1

17

83

0.5

5

UC

E o

f Re

vis

ed

Pro

jec

t Re

po

rt for A

ma

da

nd

Op

en

Ca

st P

roje

ct (4

.0 M

ty)

Sta

tem

ent s

ho

win

g th

e C

ap

ital In

ve

stm

ent o

n C

ivil W

ork

s

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

4

Ap

pe

nd

ix- A

.2.1

.

(Am

ou

nt in

Rs

. La

kh

s)

Sl.

Pa

rticu

lars

To

tal

No

.U

nit

Am

ou

nt

Ra

te a

tR

ate

at

Am

ou

nt

Am

ou

nt

Qty

.(la

kh

s)

Qty

.A

mo

un

tQ

ua

ntity

10

0C

I (Rs

.)2

92

6 C

I(Rs

.)(la

kh

s)

(lak

hs

)

1O

ffice

of th

e P

roje

ct O

ffice

r/S

q.m

.4

61

21

.57

50

.39

50

.39

Ma

na

ge

r's o

ffice

2B

ound

ary w

all w

ith G

ate

RM

13

51

.59

20

01

12

.00

32

77

.12

6.5

56

.55

3i) S

tore

she

dS

q.m

.1

92

11

.08

20

.87

20

85

50

.00

16

09

3.0

03

3.4

75

4.3

4

ii) Bo

und

ary w

all w

ith g

ate

RM

20

01

12

.00

32

77

.12

6.5

56

.55

iii) Se

curity p

ost

Sq

.m.

10

.53

80

.00

11

11

8.8

01

.17

1.1

7

iv) Scra

p ya

rd/C

oncre

te p

ave

me

nt

Sq

.m.

40

04

5.0

01

31

6.7

05

.27

5.2

7

4W

ork

sho

p

i) Dum

pe

r she

dS

q.m

.6

72

38

.77

35

.27

35

.27

ii) Exc

ava

tion e

quip

me

nt b

uild

ing

Sq

.m.

38

42

2.1

63

0.7

53

72

55

0.0

01

60

93

.00

59

.87

90

.62

iii) E&

M e

quip

me

nt b

uild

ing

Sq

.m.

28

81

6.6

21

9.4

03

12

55

0.0

01

60

93

.00

50

.21

69

.61

iv) Do

zer s

ho

pS

q.m

.8

04

.62

10

.04

10

.04

v) LM

V s

ho

pS

q.m

.4

82

.77

0.0

0

vi) Dum

pe

r pa

rkin

g s

pa

ce

Sq

.m.

48

61

.68

48

63

3.0

09

65

.58

4.6

94

.69

(Bitu

min

ous p

ave

me

nt)

vii) Dum

pe

r wa

shin

g p

latfo

rmS

q.m

.2

25

1.9

6L

S2

0.0

02

0.0

0

viii) LM

V w

ashin

g p

latfo

rmS

q.m

.2

00

.17

5.4

05

.40

ix) Co

ncre

te p

ave

me

nt

Sq

.m.

21

00

9.9

13

1.3

03

1.3

0

x) Bitu

min

ous p

ave

me

nt

Sq

.m.

50

01

.73

10

00

33

.00

96

5.5

89

.66

9.6

6

xi) Bo

und

ary w

all

RM

45

05

.29

12

.32

12

.32

xii) Ga

teL

S0

.30

LS

1.0

01

.00

xiii) Se

curity p

ost

Sq

.m.

7.5

0.3

51

.44

1.4

4

xiv) Sub

-sta

tion

Sq

.m.

90

.52

40

55

0.0

01

60

93

.00

6.4

46

.44

xv) Wa

ter ta

nk

Litre

75

00

05

.12

0.0

0

xvi) Pum

p h

ouse

Sq

.m.

6.2

50

.29

15

38

0.0

01

11

18

.80

1.6

71

.67

xvii) Ma

chin

e s

ho

pS

q.m

.5

40

55

0.0

01

60

93

.00

86

.90

86

.90

xviii) Wo

rksho

p o

ffice

Sq

.m.

22

55

50

.00

16

09

3.0

03

6.2

13

6.2

1

xix) Ba

ttery R

oo

mS

q.m

.3

25

50

.00

16

09

3.0

05

.15

5.1

5

xx) W.C

.S

q.m

.3

66

85

.00

20

04

3.1

07

.22

7.2

2

31

.03

.20

15

As

pe

r Ap

pro

ve

d P

.R.

Re

vis

ed

/Ad

ditio

na

l Pro

vis

ion

Re

vis

ed

Pro

jec

t Re

po

rt for A

ma

da

nd

Op

en

ca

st P

roje

ct (4

.0 M

ty)

Sta

tem

ent S

ho

win

g th

e E

stim

ate

d C

ap

ital R

eq

uire

me

nt o

n S

ervic

e B

uild

ing

s

Ex

istin

g u

pto

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

5

Ap

pe

nd

ix- A

.2.1

. (Co

ntd

.)

(Am

ou

nt in

Rs

. La

kh

s)

Sl.

Pa

rticu

lars

To

tal

No

.U

nit

Am

ou

nt

Ra

te a

tR

ate

at

Am

ou

nt

Am

ou

nt

Qty

.(la

kh

s)

Qty

.A

mo

un

tQ

ua

ntity

10

0C

I (Rs

.) 2

92

6 C

I(Rs

.)(la

kh

s)

(lak

hs

)

xxi) Ha

rd s

tand

Sq

.m.

57

01

90

.00

55

59

.40

31

.69

31

.69

xxii) Mo

tor c

ycle

sta

nd

Sq

.m.

15

02

00

.00

58

52

.00

8.7

88

.78

xxiii) Ca

nte

en

Sq

.m.

14

43

80

.00

11

11

8.8

01

6.0

11

6.0

1

xxiv) Oil a

nd

Gre

ase

trap

LS

5.0

05

.00

xxv) Ca

r pa

rkin

gS

q.m

.1

50

20

0.0

05

85

2.0

08

.78

8.7

8

5S

ub

-Sta

tion

i) Build

ing

Sq

.m.

28

81

6.6

25

2.1

35

2.1

3

ii) Ma

inte

na

nce

Ba

yS

q.m

.4

02

.31

0.0

0

iii) Ba

rbe

d w

ire fe

ncin

gR

M3

00

0.5

70

.00

6S

ervic

e M

ag

azin

eS

q.m

.8

64

.96

16

.48

16

.48

7C

ante

en (2

5 s

ea

ter)

Sq

.m.

10

64

.23

7.6

57

.65

8D

isp

ensa

ry S

q.m

.1

47

7.2

01

47

46

7.0

01

36

64

.42

20

.09

20

.09

9L

ava

torie

s &

Urin

als

Sq

.m.

30

2.1

63

06

85

.00

20

04

3.1

06

.01

6.0

1

10

Offic

er's

Clu

bS

q.m

.1

58

6.3

01

58

38

0.0

01

11

18

.80

17

.57

17

.57

11

Wo

rke

rs' In

stitu

teS

q.m

.1

48

5.9

01

48

38

0.0

01

11

18

.80

16

.46

16

.46

12

Firs

t Aid

ce

ntre

Sq

.m.

17

0.8

32

.55

2.5

5

13

Prim

ary s

cho

ol

Sq

.m.

20

48

.13

20

43

80

.00

11

11

8.8

02

2.6

82

2.6

8

14

Re

st s

he

lter

Sq

.m.

39

1.5

54

.46

39

38

0.0

01

11

18

.80

4.3

48

.80

15

Ga

rag

eS

q.m

.1

00

2.4

71

00

23

5.0

06

87

6.1

06

.88

6.8

8

16

Sco

ote

r and

Cyc

le S

he

dS

q.m

.1

00

2.1

02

00

20

0.0

05

85

2.0

01

1.7

01

1.7

0

17

Che

ck p

ost

Sq

.m.

15

0.3

70

.00

18

Pa

rks &

pla

ygro

und

s fo

r tow

nship

LS

2.5

01

0.0

01

0.0

0

19

Extra

pro

visio

n fo

r found

atio

n in

33

86

5.3

2

po

or s

oil fo

r all b

uild

ing

s o

the

r tha

n

bo

und

ary w

all/ b

arb

ed

wire

fencin

g,

ga

rag

e, c

ycle

she

d &

pa

vem

ent.

20

Extra

pro

visio

n fo

r found

atio

n in

po

or

3.5

2

so

il for b

ound

ary w

all, g

ara

ge

,

pa

vem

ent @

10

% o

f it's c

ost

21

So

il inve

stig

atio

nL

S2

.00

5.0

05

.00

22

Offic

er's

Re

st h

ouse

Sq

.m.

27

6.0

03

80

.00

11

11

8.8

03

0.6

93

0.6

9

23

Se

curity R

oo

m - 4

no

s.

Sq

.m.

42

.00

38

0.0

01

11

18

.80

4.6

74

.67

As

pe

r Ap

pro

ve

d P

.R.

Ex

istin

g u

pto

Re

vis

ed

/Ad

ditio

na

l Pro

vis

ion

31

.03

.20

15

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

6

Ap

pe

nd

ix- A

.2.1

. (Co

ntd

.)

(Am

ou

nt in

Rs

. La

kh

s)

Sl.

Pa

rticu

lars

To

tal

No

.U

nit

Am

ou

nt

Ra

te a

tR

ate

at

Am

ou

nt

Am

ou

nt

Qty

.(la

kh

s)

Qty

.A

mo

un

tQ

ua

ntity

10

0C

I (Rs

.)2

92

6 C

I(Rs

.)(la

kh

s)

(lak

hs

)

25

La

bo

rato

ry Build

ing

Sq

.m.

50

.00

44

6.0

01

30

49

.96

6.5

26

.52

26

Ma

inte

na

nce O

ffice

Sq

.m.

50

.00

44

6.0

01

30

49

.96

6.5

26

.52

27

Bo

und

ary w

all fo

r colo

ny

RM

60

0.0

01

12

.00

32

77

.12

19

.66

19

.66

28

Se

curity B

arra

ck (tw

in s

ha

ring

)N

o.

15

.00

99

38

.50

29

08

00

.51

43

.62

43

.62

29

Ba

rbe

d W

ire F

encin

g

RM

30

.64

30

.64

Sub

-To

tal

22

5.5

43

31

.09

64

4.7

09

75

.79

Ad

d fo

r contin

ge

ncie

s @

3%

6.7

71

9.3

41

9.3

4

To

tal

23

2.3

13

31

.09

66

4.0

49

95

.13

31

.03

.20

15

As

pe

r Ap

pro

ve

d P

.R.

Ex

istin

g u

pto

Re

vis

ed

/Ad

ditio

na

l Pro

vis

ion

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

7

Ap

pe

nd

ix - A

.2.2

Re

vis

ed

Pro

jec

t Re

po

rt for A

ma

da

nd

Op

en

Ca

st P

roje

ct (4

.0 M

ty)

Sta

tem

en

t sh

ow

ing

Ca

pita

l Inv

es

tme

nt o

n R

es

ide

ntia

l Bu

ildin

g

(Am

ou

nt in

Rs

. La

kh

s)

Sl.

Ca

teg

ory

/Sc

ale

Ty

pe

Ad

ditio

na

lT

ota

l

No

.o

f M

an

po

we

rN

o. o

fA

mo

un

tM

an

po

we

r%

No

. of

Ne

tU

nit C

os

t U

nit C

os

t A

mo

un

tP

rov

isio

nA

mo

un

t

Qtrs

.Q

trs.

Ma

np

ow

er

No

. of

Am

ou

nt

s

atis

-Q

ua

rters

Qu

arte

rsa

t 10

0C

Ia

t 29

26

CI

Am

ou

nt

Qtrs

.

fac

tion

Re

qd

.R

eq

d.

1C

at-I to

VI a

nd

M

Q4

80

23

03

61

.91

86

42

36

36

0.1

50

4.3

89

15

8.0

0

Gra

de

s B

,C,D

&E

28

57

1.7

9 to

87

57

.06

A1

25

8.0

10

10

00

00

.15

74

.59

40

.00

*(72

- 19

)

38

97

9.9

7 to

15

19

9.0

8B

13

56

11

43

.66

13

15

5.0

72

53

0.2

24

6.5

54

34

7.3

6

Gra

de

A a

nd

Sp

l.Gra

de

E1

and

E2

4E

3 to

E5

C4

64

61

73

.23

22

10

02

22

20

.35

91

0.5

04

23

1.1

0

5E

6 a

nd

Ab

ove

D6

64

8.5

95

10

05

50

.77

22

2.5

89

11

2.9

4

6H

oste

l type

93

0.4

21

90

.09

92

.89

75

5.0

4

Acco

mm

od

atio

n

7P

rovis

ion fo

r land

de

velo

pm

ent

LS

23

.00

and

Ho

rticultu

re

8P

rovis

ion fo

r rain

wa

ter

LS

6.0

0

ha

rvestin

g

Su

b - T

ota

l6

79

35

77

65

.82

00

62

.72

24

45

5.3

31

35

13

59

33

.44

Ad

d 3

% c

ontin

ge

ncie

s

22

.96

28

.00

To

tal

78

8.7

86

2.7

29

61

.44

89

8.7

29

61

.44

No

te: 1

. * 19

no

s. T

ype

qua

rters

ha

s b

ee

n c

onsid

ere

d a

s h

oste

l type

acco

mo

da

tion.

2

. All q

ua

rters

will b

e o

f (G+

3) c

onfig

ura

tion o

r hig

he

r co

nsid

erin

g o

ptim

al u

tilisa

tion o

f land

.

As

pe

r Ap

pro

ve

d P

.R.

Re

vis

ed

Pro

vis

ion

Ex

istin

g u

pto

31

.03

.20

15

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

8

Ap

pe

nd

ix-A

.2.3

UC

E o

f Re

vis

ed

Pro

jec

t Re

po

rt fo

r A

ma

da

nd

Op

en

Ca

st P

ro

jec

t (4.0

Mty

)

Sta

tem

en

t sh

ow

ing

the

Bu

ildin

g C

os

t Ind

ex

at J

am

un

a K

otm

a a

re

a w

ith

re

fere

nc

e to

10

0 B

as

e in

De

lhi a

s o

n 1

.10

.76

in J

uly

20

15

SL

.U

NIT

SR

AT

ES

AS

RA

TE

SP

ER

CE

NT

AG

E

WE

IGH

-C

OS

T

NO

.D

ES

CR

IPT

ION

ON

A

T

INC

RE

AS

E T

AG

EIN

DE

X

1.1

0.7

6A

RE

A(R

AT

IO

AT

DE

LH

IB

ET

WE

EN

CO

L.5

&4

)

1.

2.

3.

4.

5.

6.

7.

8.

1.

BR

ICK

S1

00

01

06

.15

24

00

22

.61

16

.03

61

.76

2.

SA

ND

67

% C

OA

RS

E, 3

3 %

FIN

EC

u.M

21

.92

61

52

8.0

65

.01

40

.30

3.

CE

ME

NT

QU

INT

AL

35

.28

54

01

5.3

12

1.0

32

1.5

1

4.

ST

ON

ES

|50

% - 4

0m

m

AG

GR

EG

AT

E |5

0%

- 20

mm

Cu.M

27

.10

15

05

55

.54

6.5

36

1.0

1

5.

TIM

BE

R (S

AL

/BIJ

A S

AL

)C

u.M

20

21

.00

45

00

02

2.2

71

8.0

40

0.8

6

6.

MIL

D/T

OR

ST

RU

CT

UR

AL

ST

EE

LQ

UIN

TA

L1

83

.20

46

70

25

.49

10

.02

54

.90

7.

LA

BO

UR

:

a) M

AS

ON

EA

CH

9.8

93

85

38

.93

8.5

33

0.9

1

b) C

AR

PE

NT

ER

EA

CH

9.8

93

85

38

.93

4.0

15

5.7

2

c) U

NS

KIL

LE

DE

AC

H4

.41

24

05

4.4

21

1.0

59

8.6

2

TO

TA

L2

92

5.5

9

S

AY

2926

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

9

AP

PE

ND

IX- A

.3

(Ou

tso

urc

ing

Op

tion

)A

mount in

Rs. L

akhs

Pa

rticu

lars

Ra

te O

fA

nn

ua

l

1st Y

ea

r2n

d Y

ea

r3rd

Ye

ar

4th

Ye

ar

5th

Ye

ar

10th

yr

15th

yr

De

prn

.(%)

De

pre

cia

tion

HE

MM

A.

OV

ER

BU

RD

EN

(Ap

p-A

.3.1

)2022.2

7

B.

CO

AL

(Ap

p-A

.3.1

)327.7

6

7058.4

9

C.

RE

CL

AM

AT

ION

(Ap

p-A

.3.1

)6.4

2

D.

CO

MM

ON

(Ap

p-A

.3.1

)88.7

644.0

044.0

044.0

04.8

9

E.

SP

AR

ES

& C

ON

TIN

GE

NC

Y2.2

02.2

02.2

00.2

4

Su

b-T

ota

l HE

MM

(A+

B+

C+

D+

E)

2445.2

17058.4

946.2

07104.6

946.2

05.1

3

F.

Oth

er th

an

HE

MM

1E

lectric

al P

&M

(App-A

.3.2

)485.0

075.4

9599.1

1674.6

0411.0

873.4

6114.5

75.1

530.8

5

2W

ork

shop P

&M

(App-A

.3.3

)172.3

4121.7

5118.7

2240.4

727.4

049.6

927.7

613.8

75.1

56.1

1

3P

um

ps P

ipes &

Fittin

gs (A

pp-A

.3.4

)145.9

939.3

51150.4

41189.7

9280.5

6311.6

7279.4

5278.7

65.1

559.2

5

4C

oal H

andlin

g P

lant (A

pp-A

.3.5

)399.2

78.6

929865.7

029874.3

94982.2

89984.2

011486.9

13412.3

15.1

5- 3

3.3

32256.5

4

5O

ther P

&M

(App-A

.3.6

)57.4

0104.1

4688.0

0792.1

436.0

0251.0

0251.0

0150.0

011.1

176.4

4

Su

b-T

ota

l(F)

1260.0

0349.4

232421.9

732771.3

95456.7

610638.9

111880.2

43887.8

5279.4

5278.7

62429.1

9

GR

AN

D T

OT

AL

(A+

B+

C+

D+

E+

F)

3705.2

17407.9

132468.1

739876.0

85502.9

610638.9

111880.2

43887.8

5279.4

5278.7

62434.3

3

2. A

ll other existing H

EM

M w

hich are not m

entioned

in A3

1 o

n com

pletio

n of their life w

ill be surveyed

off and

will no

t be rep

laced o

r will b

e transferred elsew

here.

Sta

tem

ent s

ho

win

g th

e e

stim

ate

d c

ap

ital in

vestm

ent fo

r Pla

nt a

nd

Ma

chin

ery

Ph

asin

g O

f Ad

ditio

na

l Ca

pita

l

RE

VIS

ED

PR

OJ

EC

T R

EP

OR

T F

OR

AM

AD

AN

D O

PE

NC

AS

T P

RO

JE

CT

(4.0

Mty

)

Sa

nctio

ne

d

(1.1

5 M

ty)

Sl.

No

.

Ad

ditio

na

l

Pro

visio

n

To

tal

Pro

visio

n

EX

IST

ING

CA

PIT

AL

as

on

31.0

3.1

5

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

10

Ap

pe

nd

ix- A

3.1

Am

ount in

Rs. L

akhs

Sl.

No

.P

artic

ula

rsU

nit

Siz

e/

Ca

pa

city

Ad

ditio

na

l Pro

vis

ion

Ph

as

ing

of e

qu

ipm

en

ts

No

.N

o.

Unit P

rice

Am

ount

No

.1

st ye

ar

2nd

yea

r3

rd ye

ar

No

.A

mo

unt

No

.A

mo

unt

No

.A

mo

unt

(%)

Am

ount

A.

OV

ER

BU

RD

EN

Su

b-T

ota

l (A)

B.

CO

AL

Su

b-T

ota

l (B)

C.

RE

CL

AM

AT

ION

1D

oze

rsH

P4

20

11

11

.11

2W

ate

r Sp

rinkle

rK

L2

81

11

1.1

1

Su

b-T

ota

l (C)

D.

CO

MM

ON

3M

oto

r Gra

de

rH

P2

80

11

11

.11

4R

ipp

er a

ttachm

ent

14

4.0

04

4.0

01

14

4.0

01

1.1

14

.89

11

.11

5H

ydra

ulic

Ba

ckho

e

Cum

0.9

-1.3

11

11

.11

6C

rane

T8-1

01

11

1.1

1

11

.11

Su

b-T

ota

l (D)

44

.00

44

.00

4.8

9

To

tal (A

+B

+C

+D

)4

4.0

04

4.0

04

.89

ES

PA

RE

S &

CO

NT

ING

EN

CY

8F

loa

t asse

mb

lies fo

r Dum

pe

rs &

Do

zers

@ 1

2.5

%

11

.11

9C

ontin

ge

ncie

s @

5%

2.2

02

.20

11

.11

0.2

4

Su

b-T

ota

l (E)

2.2

02

.20

0.2

4

To

tal (A

+B

+C

+D

+E

)5

46

.20

64

6.2

05

.13

No

te : 1

. All H

EM

M s

ho

uld

be

AC

fitted

.

2. A

ll other existing H

EM

M o

n com

pletio

n of their life w

ill be surveyed

off and

will no

t be rep

laced o

r will b

e transferred elsew

here.

4. D

etails of E

xisting HE

MM

has been given in the A

nnexure.

3 : A

s o

n 3

1.0

3.2

01

5, N

et b

lock o

f HE

MM

to b

e tra

nfe

red

is R

s 3

52

8.7

1 L

akhs. N

et b

lock c

onsid

ere

d fo

r pro

ject c

ostin

g =

Rs (6

00

9.9

1-3

52

8.7

1) L

akhs =

24

81

.20

La

khs

EX

IST

ING

no

s as o

n

31.0

3.1

5

To

tal

Pro

vis

ion

RE

VIS

ED

PR

OJ

EC

T R

EP

OR

T F

OR

AM

AD

AN

D O

PE

NC

AS

T P

RO

JE

CT

(4.0

Mty

)

Sta

tem

ent s

ho

win

g th

e e

stim

ate

d c

ap

ital re

quire

me

nt fo

r HE

MM

(Outs

ourc

ing

Op

tion)

Ra

te o

f

de

pre

ci

atio

n

An

nu

al

De

pre

cia

tion

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

11

AP

PE

ND

ICE

S A

32

(A

mount in

Rs' la

khs)

Sl.N

o.

Pa

rticu

lars

Ex

isting

as

Am

ou

nt

on

31.0

3.1

52n

d3rd

4th

1S

urfa

ce

Su

bsta

tion

4.9

9161.7

3101.2

310.2

250.2

8

2Q

ua

rry P

ow

er S

up

ply

3.7

3100.3

542.1

325.9

332.2

9

3O

/H L

ine

an

d C

ab

les ( in

km

)66.1

0270.3

1241.0

01.3

128.0

0

4Illu

min

atio

n0.2

832.7

210.7

222.0

00.0

0

5T

ow

nsh

ip E

lectrific

atio

n22.0

010.0

08.0

04.0

0

6S

afe

ty,T

estin

g a

nd

ma

int.in

clu

din

g te

lsco

pic

0.3

90.0

00.0

00.0

0

lad

de

r

7C

om

mu

nic

atio

n12.0

06.0

06.0

0

To

tal o

f item

s 1 to

875.4

9599.1

1411.0

873.4

6114.5

7

RP

R fo

r Am

ad

an

d O

pe

n C

as

t Pro

jec

t (4.0

0 M

ty) (O

UT

SO

UR

CIN

G O

PT

ION

)

Estim

ate

d S

um

maris

ed C

apita

l Require

ment fo

r Ele

ctric

al a

nd C

om

munic

atio

n P

lant a

nd M

achin

ery

Ye

arw

ise P

ha

sing

of C

ap

ital R

eq

uire

me

nt

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

12

Ap

pen

dix

- A.3

.2.1

RP

R fo

r Am

ad

an

d O

CP

(4 M

ty) O

utso

urcin

g

Estim

ated

Cap

ital Req

uire

men

t for E

lectrical, Co

mm

unicatio

n, P

lant an

d M

achin

ery

(Am

t in R

s lak

hs)

Sl.N

o.

Pa

rticula

rs E

xist Q

ty

as o

n

31

.03.1

5

Exist A

mt

as o

n

31

.03.1

5

Qty

as

per P

R

Ba

l Qty

Un

it Ra

te B

al A

mt

Yea

rwise p

ha

sing

cap

ital r

eq.

2

nd

3

rd

4th

on

ward

1

2

3

4

5

6

7

8

9

10

11

12

1.0

S

UR

FA

CE

SU

BS

TA

TIO

N

1.1

Iso

lator, 3

3 k

V, 3

po

le, outd

oor ty

pe, g

an

g o

perated

, 12

50

amp

s,

3

0.6

5

1.9

5

1.3

0

0

.65

co

nfo

rmin

g to

IS:1

81

8 (C

urren

t)

1.2

Iso

lator, 3

3 k

V, 3

po

le, outd

oor ty

pe, g

an

g o

perated

,125

0 am

ps

2

0

.65

1.3

0

1.3

0

w

ith earth

switc

h co

nfirm

ing to

IS:1

818

(curren

t)

1.3

Iso

lator, 3

3 k

V, 3

po

le, outd

oor ty

pe, g

an

g o

perated

,630

amp

s

3

0.4

5

1.3

5

1.3

5

w

ith earth

switc

h co

nfirm

ing to

IS:1

818

(curren

t)

1.4

-D

O--b

ut w

ith earth

switc

h an

d D

.O. F

uses.

2

0.4

37

4

2

0

.68

1.3

6

1.3

6

1.5

L

igh

tnin

g arresto

r,station cla

ss, 30

kV

,10

kA

for 3

3 k

V sy

stem

7

0.3

3

2.3

1

2.3

1

1.6

S

ingle p

hase cu

rrent tra

nsfo

rmer ,o

utd

oo

r typ

e with

CT

ratio o

f

4

1.2

6

5.0

4

5.0

4

2

00

/5 A

for 3

3 k

V sy

stem

for m

etering a

nd

pro

tection (1

set

co

nsists o

f 3 n

os fo

r 3 p

hase su

pp

ly)

1.7

P

oten

tial transfo

rmer ,o

utd

oo

r typ

e 33

kV

, 10

0 V

A each

4

0.9

8

3.9

2

1.9

6

1

.96

3

3 k

V/ 1

10

V w

ith tw

o co

res for m

etering a

nd

pro

tection

1.8

V

accum

Circ

uit B

reaker, 3

3kV

,12

50

A, o

utd

oo

r typ

e, 75

0 M

VA

4

8.5

0

34

.00

17

.00

1

7.0

0

sy

mm

etrical break

ing cap

acity w

ith re

mo

te contro

l pan

el

hav

ing ID

MT

L rela

y fo

r O/L

and

E/F

pro

tection, D

igital ty

pe

m

icrop

rocer b

ased p

ow

er meter, b

attery,b

attery c

harg

ing

sy

stem

etc.

1.9

T

ransfo

rmer o

utd

oo

r typ

e con

form

ing to

IS:2

02

6 (cu

rrent) h

avin

g

2

2

6.0

6

52

.12

26

.06

2

6.0

6

O

N-L

OA

D tap

chan

ger o

n H

V sid

e with

all accesso

ries as per

IS

:36

39

(Curren

t) with

the ratin

ga a

s follo

ws:

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

13

Ap

pen

dix

- A.3

.2.1

R

ated k

VA

:50

00

R

ated V

oltag

e(prim

ary):3

30

00

V

R

ated V

oltag

e(second

ary): 6

60

0V

C

on

nectio

n a

nd

vecto

r gro

up

:Dy1

1

1.1

0

12

- pan

el ,6.6

kV

switch

-bo

ard, in

do

or ty

pe, w

ith 1

7vacu

um

1

17

.40

17

.40

17

.40

circu

it break

ers, 12

50

amp

s for in

com

er and

sectionaliser,

Set

6

30

A fo

r outg

oin

g, 1

50

MV

A sy

mm

etrical break

ing cap

acity.

T

he fu

nctio

n o

f each p

anel is as fo

llow

s:

-2

no

s inco

min

g feed

er contro

l circuit b

reaker p

anel

hav

ing C

T ratio

of 5

00

/5

-1

no

sectionliser co

ntro

l circuit b

reaker p

anel

hav

ing C

T ratio

of 5

00

/5

-2

no

s capacito

r ban

k co

ntro

l circuit b

reaker p

anel w

ith

au

tom

atic po

wer facto

r contro

l facility h

avin

g C

T ratio

100

/5 .

-1

no

outg

oin

g feed

er contro

l circuit b

reaker p

anel fo

r

w

ork

sho

p h

avin

g C

T ratio

of 3

0/5

-2

no

s outg

oin

g feed

er contro

l circuit b

reaker p

anel fo

r CH

P

hav

ing C

T ratio

of 3

00

/5

-1

no

outg

oin

g feed

er contro

l circuit b

reaker p

anel fo

r Quarry

lig

htin

g h

avin

g C

T ratio

of 3

0/5

-2

no

s outg

oin

g feed

er contro

l circuit b

reaker p

anel fo

r pu

mp

s

hav

ing C

T ratio

of 1

50

/5

-1

no

s. reserve circ

uit b

reaker p

anel h

avin

g C

T ratio

of

hav

ing C

T ratio

of 3

00

/5 &

15

0/5

A

ll panels w

ill con

form

to IS

:34

27

(curren

t) and

relev

ent p

arts to IS

:25

16

. These w

ill be p

rovid

ed

w

ith cab

le end

bo

xes. T

he in

co

min

g p

anels w

ill be

p

rovid

ed w

ith restricted

earth fau

lt Pro

tection.

A

ll panels w

ill be p

rovid

ed w

ith ID

MT

L rela

ys fo

r

o

ver cu

rrent an

d earth

fault p

rotectio

n. A

ll inco

min

g

co

ntro

l circuit b

reaker sh

all be p

rovid

ed w

ith D

igital

ty

pe m

icrop

rocer b

ased P

ow

er meter an

d o

utg

oin

g

co

ntro

l circuit b

reaker sh

all be p

rovid

ed w

ith D

igital

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

14

Ap

pen

dix

- A.3

.2.1

ty

pe a

mm

eter & en

ergy m

eter.

1.1

1

Neu

tral Gro

und

ing R

esista

nce

with

pro

tection sy

stem

2

set

LS

3

.50

1.7

5

1

.75

1.1

2

Lig

htin

g T

ransfo

rmer,o

utd

oo

r typ

e rated as

1.0

0

1.9

6

1

0

fo

llow

s:

R

ated k

VA

: 10

0

R

ated V

oltag

e(prim

ary):3

30

00

V

R

ated V

oltag

e(second

ary):2

40

V (L

-L)

1.1

3

Tran

sform

er,ind

oo

r typ

e rated as fo

llow

s

1

1.7

2

1.7

2

1

.72

R

ated k

VA

: 16

0

R

ated V

oltag

e(prim

ary):6

60

0 V

R

ated V

oltag

e(second

ary):4

33

V

1.1

4

41

5V

switc

h b

oard

, ind

oor ty

pe w

ith 4

no

s AC

B h

avin

g O

/L,

1

2

.26

2.2

6

2.2

6

S

/C an

d E

/L p

rotec. 2

5 M

VA

sym

metrical b

reakin

g .cap

acity

(A

ll out g

oin

g p

anels w

ill be p

rovid

ed w

ith E

nerg

y

m

eter & a

mm

eter. The in

com

min

g p

anel w

ill be

p

rovid

ed E

nerg

y m

eter, a

mm

eter an

d v

oltm

eter)

T

he fu

nctio

n o

f each p

anel w

ill be as fo

llow

s:

- 1

no

, AC

B, 8

00

A, C

TR

of 3

00

/5 A

, as contro

ler for

in

com

ing feed

er.

- 3

no

s , AC

Bs, 4

00

A, C

TR

of 1

00

/5 A

, as contro

ler for

o

ut g

oin

g feed

ers.

1.1

5

23

0 V

(L-L

) Lig

htin

g sw

itch b

oard

with

the fo

llow

ing :

1

2

.50

2.5

0

2.5

0

--1

no

. MC

CB

, 3 p

ole,4

00 am

ps fo

r contro

l of in

com

ing feed

er.

--2

no

s. MC

CB

, 3 p

ole,1

00

A fo

r contro

l of o

utg

oin

gin

g fee

ders.

-2

no

s.,MC

Bs, 3

po

le,63

amp

s for co

ntro

l of o

ut g

oin

g feed

ers.

-3

no

s.,MC

Bs, 2

po

le,63

amp

s for co

ntro

l of o

ut g

oin

g feed

ers.

-3

no

s.,MC

Bs, 2

po

le, 40

amp

s for co

ntro

l of o

ut g

oin

g feed

ers.

1.1

6

Cap

acitor b

ank , 6

.6 k

V in

do

or ty

pe 2

16

3 k

VA

R in

clud

ing A

PF

C.

2.0

0

2.5

9

2

0

1.1

7

11

0 V

Battery

and

battery

charg

ing set fo

r em

ergency lig

htin

g

LS

3

.00

1.5

0

1.5

0

in

side S

witch

ing statio

n b

uild

ing.

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

15

Ap

pen

dix

- A.3

.2.1

1.1

8

Sub

station earth

ing an

d L

ightn

ing p

rotectio

n arran

gem

ent.

LS

6

.00

1.5

0

3.0

0

1.5

0

1.1

9

Cab

les(Po

wer,L

ightin

g a

nd

Co

ntro

l)

L

S

12

.00

12

.00

1.2

0

Misc ite

ms fo

r 33

kV

bus b

ar,Insu

lators , n

ut ,b

olts etc

L

S

10

.00

6.0

0

4.0

0

S

ub

To

tal (1

.1 to

1.2

0)

4

.99

1

61

.73

10

1.2

3

10

.22

50

.28

0.0

0

2.0

Q

UA

RR

Y P

OW

ER

SU

PP

LY

:

2.1

5

pan

el, 6.6

kV

switc

h b

oard

, outd

oo

r typ

e, with

5 V

CB

, 630

A,

3

7

.19

21

.57

7.1

9

7.1

9

7.1

9

7

5 M

VA

sym

metrical b

reakin

g cap

acity.

T

he fu

nctio

n o

f each p

anel w

ill be as fo

llow

s:

- 1

no

, VC

B, 8

00

A, C

TR

of 2

00

/5 A

, as contro

ler for

in

com

ing feed

er.

- 4

no

s , VC

Bs, 4

00

A, C

TR

of 6

0/5

A, as co

ntro

ler for

p

um

p feed

ers.

2.2

U

nitised

Sub

station, 4

00

kV

A,6

.6kV

/41

5 V

1

14

.88

14

.88

14

.88

w

ith 6

.6 k

V, 4

00

amp

s, 15

0 M

VA

, VC

B (1

no

) and

43

3V

,

8

00

A, 5

0 M

VA

, AC

B (2

no

s)

2.3

L

igh

ting tran

sform

er, single p

hase, p

ole m

ou

nted

4

0.4

0

1.6

0

0.8

0

0.8

0

1

0 k

VA

, 6.6

kV

/23

0 V

(L-L

)

2.4

F

ield sw

itch, 6

.6 k

V, 4

00

A

4.0

0

3.7

3

11

5

.02

55

.22

15

.06

15

.06

25

.10

2.5

Iso

lator, 6

.6 k

V, 3

po

le, outd

oor ty

pe, g

an

g o

perated

,

1

2

0

.19

2.2

8

1.8

0

0.4

8

6

30

amp

s con

form

ing to

IS:1

81

8 (C

urren

t)

2.6

L

igh

tnin

g arresto

r 6 k

V d

istributio

n ty

pe fo

r 6.6

kV

syste

m

12

0

.40

4.8

0

2.4

0

2.4

0

S

ub

To

tal 2

.1 to

2.6

)

3.7

3

1

00

.35

42

.13

25

.93

32

.29

0.0

0

3.0

O

/H L

INE

AN

D C

AB

LE

S

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

16

Ap

pen

dix

- A.3

.2.1

3.1

3

3 k

V O

/H lin

e with

all accesso

ries in k

m(D

og A

CS

R co

nd

.) 1

2.0

0

18

.12

2

2

10

22

.50

22

5.0

0

22

5.0

0

(d

oub

le circuit lin

e)

3.2

6

.6 k

V O

/H lin

e with

all accessories in

km

(Do

g A

CS

R co

nd

.) 8

.00

47

.98

3.3

C

ables P

VC

DW

A m

inin

g ty

pe, 3

core, co

pp

er cond

ucto

rs

L

S

28

.00

28

.00

6

.6kV

grad

e of size 3

5 sq

.mm

3.4

C

ables P

VC

DW

A m

inin

g ty

pe, 3

core, co

pp

er cond

ucto

rs

0

.5

1

0.6

2

5.3

1

4.0

0

1.3

1

6

.6kV

grad

e of size 3

5 sq

.mm

3.5

C

ables,P

VC

DW

A, m

inin

g ty

pe, 3

core, co

pp

er

L

S

12

.00

12

.00

co

nd

ucto

rs, 11

00

V g

rade o

f sizes 95

sq.m

m, 7

0 sq

.

m

m,3

5 sq

.mm

, 25

sq.m

m.,1

6 sq

.mm

.& 1

0 sq

. mm

.

S

ub

To

tal (3

.1 to

3.5

)

66

.10

27

0.3

1

24

1.0

0

1.3

1

28

.00

0.0

0

4.0

Illu

min

atio

n S

yste

m

0

.28

LS

3

2.7

2

10

.72

22

.00

5.0

T

ow

nsh

ip E

lectrificatio

n

2

2.0

0

10

.00

8.0

0

4.0

0

LS

L

S

6.0

S

afety

,Testin

g a

nd

ma

int.in

clu

din

g m

ini tru

ck

mo

un

ted

0.3

90

telesco

pic la

dd

er etc.

T

ota

l (item

s 1 to

7)

7

5.4

9

5

87

.11

40

5.0

8

67

.46

11

4.5

7

0.0

0

8.0

C

OM

MU

NIC

AT

ION

L

S

12

.00

6.0

0

6.0

0

G

ran

d T

ota

l

75

.49

59

9.1

1

41

1.0

8

73

.46

11

4.5

7

0.0

0

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

17

Sl.n

o.

De

sc

riptio

n

Ex

istin

g a

s o

n

31

/03

/15

Qty

Un

it pric

eA

mo

un

t1

st Y

ea

r2

nd

Ye

ar

3rd

Ye

ar

4th

Ye

ar

5th

Ye

ar

1U

nit W

ork

Sho

p

(Ap

pe

nd

ix A.3

.3.1

)2

2.7

31

06

.72

27

.40

44

.69

24

.26

10

.37

2U

nit S

tore

s

(Ap

pe

nd

ix A.3

.3.2

)0

12

.00

0.0

05

.00

3.5

03

.50

3O

the

r P&

M9

9.0

2

T

ota

l1

21

.75

11

8.7

22

7.4

04

9.6

92

7.7

61

3.8

7

Pro

jec

t Re

po

rt Fo

r AM

AD

AN

D O

C (4

.0M

TY

)

Pro

vis

ion

Sta

tem

ent S

ho

win

g th

e E

stim

ate

d C

ap

ital In

vestm

ent o

n u

nit W

ork

sho

p a

nd

Sto

res P

lant a

nd

Ma

chin

ery

Ye

ar w

ise

Ph

as

ing

(Am

ou

nt in

Rs

. 'lak

hs

)

( Op

tion-I C

oa

l & O

B O

ut s

ourc

ing

)

Ap

pe

nd

ix A

.3.3

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

18

Pro

ject Rep

ort F

or A

MA

DA

ND

OC

P(4

.0M

TY

)

Statem

ent S

how

ing th

e Estim

ated C

apital In

vestm

ent o

n u

nit W

ork

shop P

lant an

d M

achin

ery

Appen

dix

A.3

.3.1

(Am

ou

nt in

Rs.'la

kh

s)

Sl.n

o

.

Descrip

tion

E

xistin

g a

s on

31/0

3/1

5

Qty

U

nit

price

Am

ou

nt

Yea

r wise P

hasin

g

Qty

. co

st

1st

Yea

r

2n

d

Yea

r

3rd

Yea

r

4th

Yea

r

5th

Yea

r

A

MA

CH

INE

SH

OP

1

Lig

ht d

uty

Cen

tre Lath

e, CH

: 250

-270 m

m,

DB

C:2

000

-2500m

m alo

ngw

ith accesso

ries.

1

7.7

6

1

6.4

7

6.4

7

6.4

7

2

Lig

ht d

uty

Cen

tre Lath

e,Cen

tre heig

ht:

200-2

20 m

m, C

entre d

istance:1

400

-

1600m

m alo

ngw

ith accesso

ries.

1

4.8

4

4.8

4

4.8

4

3

Pillar d

rilling m

achin

e, cap to

drill in

steel:

38 m

m.

1

0.4

6

1

2.1

5

2.1

5

2.1

5

4

Ped

estal grin

der, w

heel d

ia-300 m

m.

1

0.4

7

1

1.0

5

1.0

5

1.0

5

5

Pow

er hack

saw su

itable fo

r 300 m

m

rounds

1

1.9

9

1

1.3

6

1.3

6

1.3

6

6

Measu

ring g

auges,to

ols,w

ork

man

tables,tack

les etc.

Ls

0.3

7

Ls

1.7

0

0.4

0

0.4

0

0.5

0

0.4

0

S

ub

Tota

l A

11.0

5

17.5

7

10.3

8

5.2

4

1.5

5

0.4

0

B

EL

EC

TR

ICA

L R

EP

AIR

SH

OP

1

Man

ually

op

erated co

il win

din

g m

/c

1

0.3

4

0.3

4

0.0

0

0.0

0

0.0

0

0.3

4

0.0

0

2

Moto

r dry

ing h

eating ch

amber

1

2.3

6

2.3

6

2.3

6

3

Cab

le fault d

etecter 1

0.8

4

1

0.8

9

0.8

9

0.8

9

4

Cab

le vulcan

iser

2

0.9

4

1.8

8

0.9

4

0.9

4

5

Cab

le crimpin

g m

/c, hyd

raulic o

perated

1

0.6

9

0.6

9

0.6

9

6

H V

break

doun tester, test v

oltag

e: 0.5

kv.

1

0.7

9

1

0.9

7

0.9

7

0.9

7

7

Portab

le relay testin

g eq

uip

men

t

2

0.9

8

1.9

6

0.9

8

0.9

8

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

19

8

Electro

nic b

attery o

perated

portab

le Moto

r

check

er with

testing lead

s, clips, leath

er

carryin

g case &

batteries.

2

0.2

0

0.4

0

0.2

0

0.2

0

9

Tran

sform

er oil d

ie electric strength

kit

with

glass test cell.

2

3.2

2

6.4

4

3.2

2

3.2

2

10

Tran

sform

er oil filteratio

n m

achin

e 500

gph

capacity

1

3.3

2

3.3

2

3.3

2

11

Earth

tester

2

0.1

1

0.2

2

0.1

1

0.1

1

12

Tran

sform

er prim

ary in

jection k

it

1

2.8

5

2.8

5

2.8

5

13

Bearin

g p

uller, 5

0t cap

., hydrau

lic

1

1.3

4

0

0.0

0

0.0

0

0.0

0

14

Misc. item

s inclu

din

g to

ols,testin

g

instru

men

ts, sold

ering ro

d,tack

les,work

man

tables etc.

LS

1.3

0

0.4

5

0.2

5

0.2

0

0.4

0

S

ub

tota

l B

2.9

7

23.6

2

3.3

7

7.6

8

8.9

5

3.6

2

C

EQ

UIP

ME

NT

RE

PA

IR

/ST

RU

CT

UR

AL

SH

OP

1

Hyd

raulic p

ress, 50 t cap

acity

1

2.1

2

2.1

2

2.1

2

2

Tran

sform

er weld

ing set, 4

00A

2

1.1

3

2.2

6

1.1

3

1.1

3

3

Ox

yacety

lene g

as cuttin

g an

d w

eldin

g set

2

0.4

0

0.8

0

0.4

0

0.4

0

4

Electric h

and to

ols

i) H

and d

rill,drillin

g cap

25m

m

1

0.4

7

2

0.4

9

0.9

8

0.4

9

0.4

9

ii) H

and g

rinder,1

00 m

m w

heel d

ia.

2

0.3

1

0.6

2

0.3

1

0.3

1

iii) E

lectric blo

wer

1

0.5

9

2

0.0

8

0.1

6

0.0

8

0.0

8

5

Indu

ction ty

pe b

earing h

eater 1

1.3

6

1

6.5

0

6.5

0

6.5

0

6

Hyd

raulic p

ress, 100 t cap

acity

1

3.0

8

3.0

8

3.0

8

7

Steam

jenn

y fo

r wash

ing o

f the

equip

men

t,2.7

kW

1

0.3

9

1

2.8

8

2.8

8

2.8

8

8

Misc. item

s inclu

din

g

tools,tack

les,work

man

tables etc.

Ls

0.7

6

Ls

3.3

0

0.6

0

0.7

0

0.8

0

1.2

0

S

ub

tota

l C

3.5

7

22.7

0

1.4

8

15.5

7

2.3

3

3.3

2

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

20

D

CO

MM

ON

EQ

UIP

ME

NT

1

Moto

rised electric h

oist, m

ono rail

mounted

, 6t class IV

3

4.0

4

12.1

2

4.0

4

4.0

4

4.0

4

2

Chain

pulley

blo

ck,3

/5 t cap

acity

3

0.3

4

1.0

2

0.3

4

0.3

4

0.3

4

3

Carp

entry

tools

Ls

- 0.3

2

0.1

5

0.1

7

4

Fire fig

htin

g an

d v

entilatio

n eq

uip

men

t L

s 5.1

4

Ls

- 1.2

0

0.2

0

0.3

0

0.2

0

0.5

0

5

Siren

1

0.1

8

0.1

8

0.1

8

S

ub

tota

l D

5.1

4

14.8

4

4.7

3

4.8

5

4.7

6

0.5

0

E

Tota

l(A to

D)

22.7

3

78.7

3

19.9

6

33.3

4

17.5

9

7.8

4

F

Electricals in

cludin

g p

ow

er

supply

,illum

inato

in etc. at 1

5 %

of item

E

11.8

1

2.9

9

5.0

0

2.6

4

1.1

8

G

Contin

gen

cies at 5%

of item

s E &

F

4.5

3

1.1

5

1.9

2

1.0

1

0.4

5

H

Installatio

n ch

arges at 1

0%

of item

s E &

F

9.0

5

2.3

0

3.8

3

2.0

2

0.9

0

I G

rease and o

il trap

Ls

2.6

0

1.0

0

0.6

0

1.0

0

J

Gra

nd

Tota

l of item

s E to

I

22.7

3

106.7

2

27.4

0

44.6

9

24.2

6

10.3

7

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

21

2n

d Y

ea

r3

rd Y

ea

r4

th Y

ea

r5

th Y

ea

r

1S

TO

RA

GE

RA

CK

S

1.1

Sto

re ra

cks, b

ins, c

ab

ine

ts, a

lmira

hs, ta

ble

s, tro

lleys

,

pa

llet tru

cks, c

ard

ex, ve

ntilla

tion e

qp

t., we

ighin

g

ma

chin

e, P

C, c

ha

in p

ulle

y blo

ck e

tc.

LS

12

.00

5.0

03

.50

3.5

0

To

tal

12

.00

5.0

03

.50

3.5

0

Sl.n

o.

Ap

pe

nd

ix A

.3.3

.2

Pro

jec

t Re

po

rt Fo

r AM

AD

AN

D O

CP

(4.0

MT

Y)

Sta

tem

ent s

ho

win

g e

stim

ate

d c

ap

ital re

quire

me

nt o

f P&

M fo

r unit s

tore

s

(Op

tion-I C

oa

l & O

B O

uts

ourc

ing

)

De

sc

riptio

nQ

ty.

Un

it rate

Am

ou

nt

Ye

ar w

ise

Ph

as

ing

(Am

ou

nt in

Rs

lak

hs

)

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

22

Sl N

o.

Pa

rticu

lars

Qty

.C

os

tQ

tyU

nit R

ate

Am

ou

nt

3rd

ye

ar

5th

ye

ar

10

th y

ea

r1

5th

ye

ar

20

th y

ea

r

& a

fter

AP

um

ps

1C

entrifu

ga

l pum

p-m

oto

r se

t, multi s

tag

e, 2

25

lps, 1

60

m

He

ad

, 50

0 k

W, 6

.6 k

V, N

FL

P e

lectric

als

alo

ng

with

no

n-

retu

rn va

lve, fo

ot va

lve ,s

luic

e va

lve a

nd

acce

sso

ries (s

uch

as b

ase

pla

te, c

oup

ling

, co

up

ling

gua

rd, fo

und

atio

n b

olts

)

etc

.

1

25

.59

93

4.7

73

12

.93

69

.54

10

4.3

16

9.5

46

9.5

4

2C

entrifu

ga

l pum

p-m

oto

r se

t, multi s

tag

e, 8

0lp

s, 1

00

m

He

ad

, 11

0 k

W, 4

15

V, N

FL

P e

lectric

als

.3

8.8

72

6.6

18

.87

8.8

78

.87

3D

iese

l eng

ine

op

era

ted

Pum

p o

f 80

lps, 8

0m

he

ad

12

0K

W w

ith a

ll acce

sso

ries.

2

13

.76

19

.23

9.2

39

.23

4S

ub

me

rsib

le p

um

p fo

r ha

nd

ling

slu

rry 49

0cum

./hr, 4

0m

he

ad

24

.12

8.2

44

.12

4.1

2

5P

rimin

g p

um

p o

f 40

cum

/hr, 1

6m

he

ad

, with

all

acce

sso

ries.

40

.89

3.5

60

.89

0.8

91

.78

6F

ace

pum

ps,d

iese

l eng

ine

op

era

ted

, 11

lps, 3

0m

he

ad

alo

ng

with

req

uire

d va

lves

40

.87

3.4

80

.87

0.8

71

.74

7sub

tota

l of ite

ms 1

to 6

36

4.0

58

7.6

41

19

.06

75

.42

81

.93

0.0

0

BP

ipe

s a

nd

pip

e fittin

gs

1E

RW

pip

e, 3

55

.6 m

m o

ut s

ide

dia

., 7.1

4 m

m w

all

thic

kne

ss, in

km

1

23

6.1

94

34

.28

10

8.5

71

08

.57

10

8.5

71

08

.57

2E

RW

pip

e, 2

73

mm

out s

ide

dia

., 6.3

5 m

m w

all th

ickne

ss,

in k

m

5.0

01

8.0

69

0.3

02

7.0

91

8.0

61

8.0

62

7.0

9

3G

I pip

es m

ed

ium

duty, 1

00

mm

dia

, in k

m0

.50

6.4

53

.23

1.2

91

.94

4G

I pip

es m

ed

ium

duty, 8

0 m

m d

ia., in

km

2.5

04

.89

12

.23

4.8

94

.89

2.4

5

5 P

ipe

fitting

s s

uch a

s b

end

s,t jo

ints

,elb

ow

s, fla

ng

es,

valve

s e

tc.

LS

54

.00

13

.57

13

.28

13

.35

13

.80

6S

ub

tota

l of ite

ms 1

to5

59

4.0

41

49

.23

14

6.0

91

46

.81

15

1.9

10

.00

CC

ivil co

st fo

r pro

vidin

g c

ause

wa

ysL

S2

0.0

05

.00

5.0

05

.00

5.0

0

D P

onto

ons fo

r mo

untin

g p

um

ps

97

.50

67

.50

15

.00

15

.00

30

.00

7.5

0

EIn

sta

llatio

n c

ha

rge

sL

S9

5.8

12

3.6

92

6.5

22

2.2

22

3.3

80

.00

FT

ruck m

ounte

d c

rane

, 8T

ca

pa

city

19

.04

9.0

49

.04

GR

AN

D T

OT

AL

OF

ITE

MS

A T

O F

39

.35

11

50

.44

28

0.5

63

11

.67

27

9.4

52

78

.76

0.0

0

Ap

pe

nd

ix - A

.3.4

PR

OJ

CT

RE

PO

RT

FO

R A

MA

DA

ND

(4.0

0M

TY

)S

tate

me

nt s

ho

win

g e

stim

ate

d c

ap

ital re

qu

irem

en

t for p

um

ps

, pip

es

an

d p

ipe

fitting

s

(Fo

r All o

ptio

ns

)

Ex

istin

g a

s o

n

31

/03

/20

15

RP

R R

rqu

irem

en

tP

ha

sin

g (A

mo

unt in

Rs. L

akhs)

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

23

S.n

oP

articulars

% L

ifeA

nn

ual

Qty

Unit R

ateT

otal Am

ount1st Y

ear2nd Y

ear3rd Y

ear4th Y

ear5th Y

earD

ep

.

1P

lant & M

achinery (Mechanical &

Electrical)

LS16279.66

2486.834752.87

6240.232799.73

5.15%878.17

2Idlers &

Loading pointLS

1932.76276.80

636.94732.32

286.7033.33%

644.19

3S

teel cord beltingLS

1815.73251.14

659.37579.34

325.8814.28%

227.55

4C

ivil & S

tructuralsLS

9837.561967.51

3935.033935.03

0.005.15%

506.63

To

tal8.69

29865.704982.28

9984.2011486.91

3412.312256.54

Ap

pe

nd

ix- A.3.5.1

Am

ou

nt R

s.'lakhs

PR

req

uire

me

nt

Yr. w

ise p

hasin

g o

f capital re

qt.

Su

mm

arised

she

et fo

r CH

P

Ex

isting

as o

n

31/03/2013

PR

FO

R A

MA

NA

ND

OC

P (4.0M

TY

)

(Fo

r all Op

tion

s)

State

me

nt sh

ow

ing

estim

ated

Ad

ditio

nal C

apital R

eq

uire

me

nt fo

r CH

P

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

24

A

pp

end

ix- A

.3.5

.1

PR

FO

R A

MA

DA

ND

OC

P

Sta

tem

ent sh

ow

ing

estima

ted

Ca

pita

l Req

uire

men

t for C

HP

Am

ou

nt R

s.'lak

hs

S.n

o

Pa

rticula

rs

Existin

g a

s

on

01

/04

/20

15

PR

req

uire

men

t Y

r. wise p

ha

sing

of ca

pita

l reqt.

% L

ife

An

nu

al

Qty

. C

ost

Qty

U

nit R

ate T

otal

Am

ou

nt

1st Y

ear 2nd

Year 3

rd Y

ear 4th

Year

5th

Year

&

On

ward

D

ep.

1

Belt co

nv.IC

1 1

20

0m

m w

ide,4

40

m lo

ng,8

00

tph,2

.5m

/s

sp

eed, 2

X2

25

kW

multid

rive, w

ith 6

.6K

V electricals,

3

phase, 5

0 H

z sup

ply

a. D

rive h

ead ,tail en

d an

d stru

cturals

1

18

8.9

2

18

8.9

2

18

8.9

2

5.1

5%

9

.73

b

. Idlers an

d lo

adin

g p

oin

t

1

7

3.4

2

73

.42

73

.42

33

.33

% 2

4.4

7

2

Belt co

nv.IC

2 &

IC3

12

00

mm

wid

e,52

0 m

long,8

00

tph,2

.5m

/s

sp

eed, 2

X1

10

kW

multid

rive, w

ith 6

.6K

V electricals,

3

phase, 5

0 H

z sup

ply

a. D

rive h

ead ,tail en

d an

d stru

cturals

2

15

7.9

0

31

5.8

0

1

57

.90

1

57

.90

5.1

5%

1

6.2

6

b

. Idlers an

d lo

adin

g p

oin

t

2

9

1.1

8

18

2.3

6

9

1.1

8

91

.18

33

.33

% 6

0.7

8

3

Belt co

nv.IC

4 &

IC5

14

00

mm

wid

e, 22

5 m

long,1

60

0tp

h, 3

m/s

sp

eed, 2

X2

25

kW

multid

rive, w

ith 6

.6K

V electricals,

3

phase, 5

0 H

z sup

ply

a. D

rive h

ead ,tail en

d an

d stru

cturals

2

24

3.2

6

48

6.5

2

48

6.5

2

5.1

5%

2

5.0

6

b

. Idlers an

d lo

adin

g p

oin

t

2

5

4.9

1

10

9.8

2

10

9.8

2

33

.33

% 3

6.6

0

4

Belt co

nv.IC

6 &

IC7

12

00

mm

wid

e, 72

0 m

long,8

00

tph,2

.5m

/s

sp

eed, 2

X1

50

kW

multid

rive, w

ith 6

.6K

V electricals,

3

phase, 5

0 H

z sup

ply

a. D

rive h

ead ,tail en

d an

d stru

cturals

2

20

5.6

7

41

1.3

4

2

05

.67

20

5.6

7

5.1

5%

2

1.1

8

b

. Idlers an

d lo

adin

g p

oin

t

2

1

22

.10

2

44

.20

1

22

.10

12

2.1

0

33

.33

% 8

1.3

9

5

Belt co

nv.IC

8 &

IC9

14

00

mm

wid

e, 34

5 m

long,1

60

0tp

h,3

.0m

/s

sp

eed, 2

X3

00

kW

multid

rive, w

ith 6

.6K

V electricals,

3

phase, 5

0 H

z sup

ply

a. D

rive h

ead ,tail en

d an

d stru

cturals

2

26

3.9

1

52

7.8

2

5

27

.82

5

.15

%

27

.18

b

. Idlers an

d lo

adin

g p

oin

t

2

7

7.3

5

15

4.7

0

1

54

.70

3

3.3

3%

51

.56

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

25

Ap

pen

dix

- A.3

.5.1

6

Belt co

nv.C

1 &

C2

,12

00

mm

wid

e,10

00

m lo

ng, 8

00

tph,2

.5m

/s

speed

, 2X

150

kW

with

6.6

kV

electricals,3 p

hase, 5

0 H

z sup

ply

a. D

rive h

ead ,tail en

d an

d stru

cturals

2

22

6.5

2

45

3.0

4

45

3.0

4

5.1

5%

2

3.3

3

b

. Idlers an

d lo

adin

g p

oin

t

2

1

65

.40

3

30

.80

33

0.8

0

33

.33

% 1

10

.26

7

Belt co

nv.C

3 &

C4

,12

00

mm

wid

e,10

00

m lo

ng, 8

00

tph,2

.5m

/s

speed

, 2X

150

kW

with

6.6

kV

electricals,3 p

hase, 5

0 H

z sup

ply

a. D

rive h

ead ,tail en

d an

d stru

cturals

2

22

6.5

2

45

3.0

4

4

53

.04

5.1

5%

2

3.3

3

b

. Idlers an

d lo

adin

g p

oin

t

2

1

60

.00

3

20

.00

3

20

.00

33

.33

% 1

06

.66

8

Belt co

nv.C

5 &

C6

,12

00

mm

wid

e,60

0m

long, 8

00

tph,2

.5m

/s

speed

, 2X

150

kW

with

6.6

kV

electricals,3 p

hase, 5

0 H

z sup

ply

a. D

rive h

ead ,tail en

d an

d stru

cturals

2

19

8.2

7

39

6.5

4

39

6.5

4

5.1

5%

2

0.4

2

b

. Idlers an

d lo

adin

g p

oin

t

2

9

8.1

6

19

6.3

2

19

6.3

2

33

.33

% 6

5.4

3

9

Belt co

nv.C

7 &

C8

,16

00

mm

wid

e,30

0m

long, 2

20

0tp

h,3

.5m

/s

speed

, 2X

400

kW

with

6.6

kV

electricals,3 p

hase, 5

0 H

z sup

ply

a. D

rive h

ead ,tail en

d an

d stru

cturals

2

29

4.8

4

58

9.6

8

5

89

.68

5.1

5%

3

0.3

7

b

. Idlers an

d lo

adin

g p

oin

t

2

1

60

.57

3

21

.14

3

21

.14

33

.33

% 1

07

.04

10

Belt co

nv.C

9,1

20

0m

m w

ide,1

15

m lo

ng, 4

00

tph,2

.5m

/s speed

,

1X

75

kW

with

41

5V

electricals,3 p

hase, 5

0 H

z sup

ply

a. D

rive h

ead ,tail en

d an

d stru

cturals

1

58

.61

5

8.6

1

5

8.6

1

5

.15

%

3.0

2

b

. Idlers an

d lo

adin

g p

oin

t

1

2

8.5

7

28

.57

2

8.5

7

3

3.3

3%

9.5

2

11

Beltin

g

a. B

elting (S

T-1

00

0) w

idth

12

00

mm

(In m

)

1

69

00

0.0

869

1

46

8.6

1

2

51

.14

52

1.4

0

37

0.1

9

32

5.8

8

14

.28

% 2

09

.72

b

. Beltin

g (S

T-1

00

0) w

idth

14

00

mm

(In m

)

2

40

0

0.0

926

2

22

.24

13

7.9

7

84

.27

14

.28

% 3

1.7

4

c. B

elting (S

T-1

00

0) w

idth

16

00

mm

(In m

)

1

25

0

0.0

999

1

24

.88

1

24

.88

14

.28

% 1

7.8

3

12

Plo

ugh F

eeder 2

20

0 tp

h 6

5K

W

4

14

2.3

1

56

9.2

4

28

4.6

2

28

4.6

2

5

.15

%

29

.32

13

Reclaim

Feed

er 80

0tp

h, 9

0K

W

3

28

5.6

4

85

6.9

2

2

85

.64

2

85

.64

2

85

.64

5.1

5%

4

4.1

3

14

Vib

ratory

Feed

er Cap

acity 8

00

tph

4

4

4.3

4

17

7.3

6

88

.68

88

.68

5.1

5%

9

.13

15

Vib

ratory

Feed

er Cap

acity 4

00

tph

2

2

9.7

5

59

.50

29

.75

29

.75

5.1

5%

3

.06

16

Electro

nic, p

it less , Ro

ad w

eig

h b

ridge, 1

00

te/50

te with

dig

ital 2

8.6

9

2

11

.66

2

3.3

2

11

.66

1

1.6

6

5.1

5%

1

.2

d

ispla

y w

ith p

rinter n

ear CH

P (ex

clud

ing civ

il wo

rks)

17

Dust su

pp

ression sy

stem

L

S

3

5.0

0

15

.00

20

.00

5.1

5%

1

.80

18

Fire fig

htin

g eq

uip

men

t.

L

S

2

5.0

0

8.0

0

9.0

0

8.0

0

5.1

5%

1

.29

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

26

Ap

pen

dix

- A.3

.5.1

19

Airco

nd

itionin

g sy

stem

& P

ressurisatio

n sy

stem

L

S

1

2.0

0

5

.00

7

.00

5.1

5%

0

.62

20

Sh

un

ting L

OC

O 9

0T

for fu

ll rake 5

8 b

ox

1

3

29

.98

3

29

.98

32

9.9

8

5.1

5%

1

6.9

9

21

Wag

on w

eigh b

ridge, 1

00

t, 6.2

5X

4.5

5m

with

dig

ital & v

idu

al

d

ispla

y w

ith p

rinter u

nit w

ith w

eigh h

ouse

1

1

6.8

6

16

.86

1

6.8

6

0.0

0

5.1

5%

0

.87

22

Rap

d L

oad

-out sy

stem

consistin

g 5

00

Te o

f Bunker o

n railw

ay

sidin

g w

ith P

rew

eigh h

op

pers, lo

ad cells, d

ischarg

e gate

s,track

logic sy

stem

, contro

l syste

m h

igh &

low

lrvel in

dicato

r,

tem

peratu

re senso

r etc.

1

47

9.5

1

47

9.5

1

4

79

.51

0

.00

5.1

5%

2

4.6

9

23

Air ca

nno

ns, air co

mp

ressors, alo

ng w

ith req

uired

pip

ing etc

.

L

S

5

0.0

0

10

.00

20

.00

2

0.0

0

5.1

5%

2

.58

24

Sam

pler u

nit alo

ng w

ith req

uired

chutes &

lifting tack

les

LS

30

.00

1

5.0

0

15

.00

5.1

5%

1

.55

25

Insp

ection w

inches o

ver b

un

kers

2

3.7

1

7.4

2

3

.71

3

.71

5.1

5%

0

.38

26

Ch

ute w

ith lin

ers

26

.1

Tran

sfer chu

te with

liners

LS

40

.00

15

.00

15

.00

1

0.0

0

5.1

5%

2

.06

26

.2

Tw

o w

ay c

hute w

ith m

oto

rised

flap g

ate & lin

ers

L

S

2

0.0

0

1

0.0

0

10

.00

5.1

5%

1

.03

26

.3

Ch

ute b

elow

feeder w

ith lin

ers

L

S

2

5.0

0

5.0

0

10

.00

1

0.0

0

5.1

5%

1

.29

27

Co

nd

ition m

on

itorin

g sy

stem

L

S

1

5.0

0

5.0

0

5.0

0

5.0

0

5.1

5%

0

.77

28

Ho

isting d

evice

s,too

ls, tackle

s, instru

ments, etc.

LS

23

.00

1

0.0

0

13

.00

5.1

5%

1

.18

29

Tru

ck m

ou

nted

crane 1

0 t cap

.

1

9

.09

9.0

9

9

.09

5.1

5%

0

.47

30

Belt p

ullin

g d

evice

1

12

.37

1

2.3

7

12

.37

5.1

5%

0

.64

31

Belt v

ulca

nisin

g u

nit

1

28

.36

2

8.3

6

2

8.3

6

5

.15

%

1.4

6

32

Su

b to

tal m

ech

an

ical (ite

m 1

to 2

7)

8

.69

10

503

.30

0.0

0

15

47

.07

31

05

.12

39

44

.68

1

90

6.4

3

12

59

.39

33

Electricals at 2

0%

of ite

m 3

2 (P

ow

er sup

ply

, Illum

inatio

n,

contro

l, earthin

g, lig

htn

ing p

rotectio

n etc.)

LS

21

00

.66

0.0

0

30

9.4

1

62

1.0

2

78

8.9

4

38

1.2

9

5.1

5%

1

08

.18

34

Erectio

n an

d co

mm

issionin

g ch

arges @

10

% o

f item

s 32

& 3

3

LS

12

60

.40

0.0

0

18

5.6

5

37

2.6

1

47

3.3

6

22

8.7

8

5.1

5%

6

4.9

1

35

Civ

il and

structu

ral wo

rks

LS

98

37

.56

1

96

7.5

1

39

35

.03

39

35

.03

0

.00

5.1

5%

5

06

.63

36

Desig

n &

En

gin

eering ch

arges @

5%

of ite

m 3

2,3

3 &

34

L

s

11

22

.08

1

91

.20

38

3.0

6

43

3.4

3

11

4.3

9

5.1

5%

5

7.7

9

37

Overh

ead co

nstru

ction co

st @1

5%

of ite

m 3

2,3

3,3

4 &

36

L

S

2

24

7.9

6

3

35

.00

67

2.2

7

84

6.0

6

39

4.6

3

5.1

5%

1

15

.77

38

Insu

rance @

0.7

5%

of ite

m 3

2,3

3 &

34

L

S

1

03

.98

1

5.3

2

30

.74

39

.05

1

8.8

7

5.1

5%

5

.35

39

Co

ntin

gen

cies @

3%

of ite

m 3

2, 3

3, 3

4,3

6 &

37

L

S

5

17

.03

7

7.0

5

15

4.6

2

19

4.5

9

90

.77

5.1

5%

2

6.6

3

40

Wo

rks co

ntract tax

(2%

/as app

licable) o

f item

32

to 3

8

LS

54

3.5

2

9

1.0

2

18

2.4

0

20

9.2

1

60

.89

5.1

5%

2

7.9

9

41

Train

ing o

n O

&M

staff @ 0

.05

% o

f item

32

,33

& 3

4

LS

69

.32

1

0.2

1

20

.49

26

.03

1

2.5

9

5.1

5%

3

.57

42

Sp

ares @3

% o

f item

32

& 3

3

LS

37

8.1

2

5

5.6

9

11

1.7

8

14

2.0

1

68

.64

5.1

5%

1

9.4

7

43

Serv

ice tax @

4.1

2%

of (S

um

item

32

to 4

2)

LS

11

81

.78

1

97

.15

39

5.0

7

45

4.5

3

13

5.0

3

5.1

5%

6

0.8

6

G

ran

d T

ota

l

8.6

9

29

865

.70

0.0

0

49

82

.28

99

84

.20

11

486

.91

34

12

.31

22

56

.54

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

27

AP

PE

ND

IX-A

.3.6

(Ou

tso

urc

ing

Op

tion

)

(R

S. IN

LA

KH

S)

Sa

nctio

ne

d

(1.1

5 M

ty)

Siz

e/

ca

pa

city

Un

it

Co

st

To

tal

Pro

visio

n

1st y

ea

r%

Am

t

1E

xplo

der w

ith C

ontin

uity

Teste

r0.2

00.0

8 2

5 S

hots

15

3.0

03.0

81.0

01.0

01.0

011.1

10.3

3

2S

urve

y In

stru

ment

5.0

0LS

040.0

040.0

010.0

010.0

010.0

010.0

011.1

14.4

4

3S

afe

ty E

qip

ments

0.4

4LS

30.0

030.4

45.0

05.0

010.0

010.0

011.1

13.3

3

4N

ear fie

lds b

last d

esig

n a

ssessm

ent,

Vib

ratio

n M

onito

ring E

quip

ment &

geom

etry

package

LS

15.0

015.0

010.0

05.0

011.1

11.6

7

5P

erm

anent w

ate

r sprin

klin

g a

rrangem

ent

on h

aul ro

ad &

belt lo

adin

g s

ite(6

Km

)103.6

280.0

0183.6

220.0

020.0

020.0

020.0

011.1

18.8

9

6F

ire F

ightin

g E

quip

ments

2.0

0LS

20.0

020.0

05.0

05.0

010.0

011.1

12.2

2

7M

iscella

neous(F

or

incorp

ora

tion

of

late

st

technolo

gy

inm

ine

Safe

ty,

Surve

illance

&

contro

llsyste

mfo

rcolo

ny,

offic

e,

despatc

hnetw

ork

,m

agazin

eand

atte

ndance c

aptu

ring e

tc.)

LS

500.0

0500.0

0200.0

0200.0

0100.0

011.1

155.5

5

8O

thers

50.2

0

To

tal

57.4

0104.1

415.0

0688.0

0792.1

40.0

036.0

0251.0

0251.0

0150.0

076.4

4

4th

ye

ar

5th

ye

ar

RE

VIS

ED

PR

OJ

EC

T R

EP

OR

T F

OR

AM

AD

AN

D O

PE

NC

AS

T P

RO

JE

CT

(4.0

Mty

)

ST

AT

EM

EN

T S

HO

WIN

G T

HE

ES

TIM

AT

ED

CA

PIT

AL

RE

QU

IRE

ME

NT

ON

OT

HE

R P

LA

NT

AN

D M

AC

HIN

ER

Y

Sl.

No

.D

esc

riptio

n

Ad

ditio

na

l

pro

visio

n

Ph

asin

g o

f Ca

pita

l Pro

visio

n

De

pre

cia

tion

EX

IST

ING

CA

PIT

AL

as

on

31.0

3.1

52n

d y

ea

r3rd

ye

ar

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

28

AP

PE

ND

IX-A

.4

(O

uts

ou

rcin

g O

ptio

n)

(A

mount R

s.in

lakhs)

Sl.

Pa

rticu

lars

Sa

nctio

ne

d (1

.15 M

ty)

Ad

ditio

na

l Pro

visio

nT

ota

l

No

.P

rovisio

n

1G

enera

l Furn

iture

& F

ittings

5.0

02.9

230.0

032.9

2

2A

ir conditio

ners

and A

ir coole

rs1.0

01.9

410.0

011.9

4

3R

efe

rigera

tors

and W

ate

r coole

rs1.0

00.5

32.5

03.0

3

4O

ffice e

quip

ment

5.5

02.5

110.0

020.0

0

5C

ante

en E

quip

ment

3.0

01.9

63.0

05.0

0

6C

om

pute

rs(M

ine P

lannin

g S

oftw

are

,

E-C

onfe

rencin

g S

yste

m,e

tc)

3.7

650.0

070.0

0

7M

iscella

neous

5.5

010.0

010.0

0

To

tal

21

.00

13

.62

11

5.5

01

29

.12

RE

VIS

ED

PR

OJ

EC

T R

EP

OR

T F

OR

AM

AD

AN

D O

PE

NC

AS

T P

RO

JE

CT

(4.0

Mty

)

Sta

tem

ent s

ho

win

g e

stim

ate

d c

ap

ital re

quire

me

nt fo

r Furn

iture

& F

itting

s

EX

IST

ING

CA

PIT

AL

as

on

31.0

3.1

5

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

29

2n

d y

ea

r3

rd y

ea

r4

th y

ea

r

1.0

Ra

ilwa

y s

idin

g

1.1

Ra

il wa

y sid

ing

co

nsis

ting

of o

ne

loa

d s

tand

ag

e lin

es,

(suita

ble

for 5

8 b

ox-N

-wa

go

ns), o

ne

em

pty s

tand

ag

e

line

(suita

ble

for 5

8 b

ox-N

-wa

go

ns), c

ross o

vers

, turn

outs

,

ele

ctrific

atio

n s

igna

lling

etc

. in k

m1

.50

84

0.0

01

26

0.0

06

30

.00

63

0.0

0

1.2

Exte

nsio

n o

f railw

ay lin

e fro

m e

xistin

g B

ha

iyato

la ra

ilwa

y

sta

tion to

Am

ad

and

OC

P c

onsis

ting

of ra

il line

s, c

ulve

rts,

brid

ge

s, e

letrific

atio

n, s

igna

lling

etc

. (KM

)8

84

0.0

06

72

0.0

03

36

0.0

03

36

0.0

0

1.3

Ra

il we

igh b

ridg

e,1

00

Te

in m

otio

n.

11

6.7

81

6.7

81

6.7

8

1.4

Po

we

r sup

ply a

nd

illum

ina

tion

LS

5.0

03

.00

2.0

0

1.5

Mis

ce

llane

ous

LS

2.5

01

.50

1.0

0

1.6

Sid

ing

offic

eL

S5

.00

2.5

02

.50

1.7

Dust s

up

pre

ssio

n a

rrang

em

ent a

t sid

ing

LS

10

.00

5.0

05

.00

To

tal

80

19

.28

40

02

.00

40

17

.28

Qty

.U

nit ra

teA

mo

un

t

(Fo

r all O

ptio

ns

)

Ap

pe

nd

ix-A

.5

Ye

arw

ise

Ph

as

ing

Pro

jec

t Re

po

rt for A

MA

DA

ND

OC

P (4

.0M

TY

)

Sta

tem

en

t sh

ow

ing

es

tima

ted

ca

pita

l req

uire

me

nt fo

r Ra

ilwa

y s

idin

g

Am

ou

nt in

Rs

La

kh

s

Sl .n

oD

es

crip

tion

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

30

Sl.

De

scrip

tion

No

.N

os

.U

nit

Ad

ditio

na

lN

os

.T

ota

l1

st ye

ar

2nd

yea

r3

rd ye

ar

4th

yea

r5

th ye

ar

CA

PIT

AL

Co

st

Co

st

Co

st

No

.A

mo

unt

No

.A

mo

unt

No

.A

mo

unt

No

.A

mo

unt

No

.A

mo

unt

A. O

UT

SO

UR

CE

D V

EH

EC

LE

1D

iese

l Je

ep

/Lig

ht V

ehe

cle

98

.05

9

2S

cho

ol B

us

2

3P

ick-u

p B

us

2

4T

ruck

2

5C

ante

en va

n1

6W

ate

r Ta

nke

r (10

KL

)2

TO

TA

L(O

uts

ou

rcin

g)

18

B. D

EP

AR

TM

EN

TA

L V

EH

EC

LE

1D

iese

l Je

ep

/Lig

ht V

ehe

cle

37

.73

23

.20

32

3.2

01

7.7

32

15

.47

2E

xplo

sive

Va

n(1

0T

e)

12

1.5

92

1.5

91

21

.59

12

1.5

9

3A

mb

ula

nce

16

.04

6.0

41

6.0

41

6.0

4

4M

oto

r cyc

le1

0.7

80

.78

10

.78

10

.78

5T

ruck

21

9.0

02

1.4

82

19

.00

6F

ue

l Tru

ck

14

3.5

22

5.4

21

43

.52

7F

ire F

ightin

g T

ruck(1

4K

L)

13

6.9

53

6.9

51

36

.95

13

6.9

5

GR

AN

D T

OT

AL

36

2.5

27

88

.56

10

15

1.0

83

5.3

75

3.1

9

(Outs

ourc

ing

Op

tion)

(Am

ount R

s. in

lakhs)

No

s

EX

IST

ING

CA

PIT

AL

as

on

31.0

3.1

5

No

te:-C

ap

ital fo

r ou

tso

urc

ed

ve

hic

le a

re n

ot p

rov

ide

d. T

he

sa

me

ma

y b

e a

rran

ge

d o

n le

as

ed

.

AP

PE

ND

IX-A

.6

Ph

as

ing

of A

dd

ition

al e

qu

ipm

en

tsA

dd

ition

al p

rovisio

nT

ota

l pro

visio

n

RE

VIS

ED

PR

OJ

EC

T R

EP

OR

T F

OR

AM

AD

AN

D O

PE

NC

AS

T P

RO

JE

CT

(4.0

Mty

)

Sta

tem

ent s

ho

win

g th

e e

stim

ate

d c

ap

ital re

quire

me

nt o

n ve

hic

les

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

31

AP

PE

ND

IX-A

.7

Sta

tem

ent s

ho

win

g th

e c

ap

ital e

xpe

nd

iture

on p

rosp

ectin

g a

nd

bo

ring

(Ou

tso

urc

ing

Op

tion

)

(Am

ount in

Rs. la

khs)

Sl.

Se

ctio

n/

Existin

g C

apita

lT

ota

l

No

.A

rea

for E

xplo

ratio

nP

rov

isio

n

As o

n 3

1.0

3.2

015

Ad

ditio

na

l

me

tera

ge

Ad

ditio

na

l

Ca

pita

l

1.

EX

PL

OR

AT

ION

IN T

HE

AM

AD

AN

D B

LO

CK

60

.20

27

12

1.0

7561.7

05

00

.00

40

.81

60

2.5

1

No

te : P

rovis

ion fo

r ad

ditio

na

l 50

0m

drillin

g k

ep

t to d

rill ne

ar A

cce

ss T

rench a

nd

oth

er p

lace

s

RE

VIS

ED

PR

OJ

EC

T R

EP

OR

T F

OR

AM

AD

AN

D O

PE

NC

AS

T P

RO

JE

CT

(4.0

Mty

)

To

tal M

ete

rag

e

of A

ma

da

nd

Blo

ck

(Mts

.)

Ad

ditio

na

l Ex

pe

nd

iture

Sa

nc

tion

ed

(1.1

5 M

ty)

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

32

AP

PE

ND

IX-A

.8.1

(Ou

tso

urc

ing

Op

tion

)

(Am

ount in

Rs L

akhs.)

Sl.N

o.

P A

R T

I C U

L A

R S

Sa

nc

tion

ed

(1.1

5 M

ty)

EX

IST

ING

CA

PIT

AL

as

on

31.0

3.1

5

To

tal C

ap

ital

1.

Co

mm

unity

De

ve

lop

me

nt in

the

surro

und

ing

villa

ge

s1

0.0

05

0.0

0

2L

eve

lling

, De

ve

lop

me

nt o

f ind

ustria

l site

& c

olo

ny s

ite

4.0

01

2.3

02

0.0

0

3G

arla

nd

dra

ins

3.0

05

0.0

65

00

.00

4S

tone

wa

ll/Bric

kw

all a

round

the

Pro

ject (a

pp

rox.1

2.0

km

)2

.00

24

9.9

8

5E

mb

ankm

ents

10

.00

20

0.0

0

6S

tone

pitc

hin

g5

0.0

0

7.

Hyd

rog

eo

log

ica

l stu

dy in

clu

din

g d

rilling

, stu

dy e

tc.

35

.00

8

Scie

ntific

stu

dy lik

e s

lop

e s

tab

ility s

tud

y fo

r inte

rna

l & e

xte

rna

l OB

dum

p,

mo

nito

ring

and

oth

er s

tud

y e

tc.

20

.00

9G

ree

n b

elt fe

ncin

g 1

5m

wid

th a

long

sa

fety

zo

ne

of th

e P

roje

ct (a

pp

rox.1

2.0

km

)6

.42

10

Shiftin

g o

f HT

line

(14

.0K

m)

5.6

05

60

11

Ab

oric

ultu

re/p

lanta

tion in

Co

lony &

in In

dustria

l Site

10

.00

5.0

0

12

Flo

ra &

Fa

una

Stu

dy

5.0

0

13

Mis

c fo

r mo

de

rnis

atio

n o

f min

e lik

e m

onito

ring

of la

nd

use

thro

ug

h s

ate

llite

surv

eyilla

nce

etc

.

50

0.0

0

14

Pie

zo

me

ters

for m

ea

surin

g w

ate

r leve

l (6 N

os)

10

.64

20

.00

15

Re

tain

ing

wa

ll aro

und

exte

rna

l dum

p b

esid

e d

ive

rted

roa

d (5

.50

Km

)1

14

.58

16

Wa

ter T

rea

tme

nt P

lant (L

S)

12

.27

50

.00

17

Slo

pe

sta

bility

Ra

dd

er

70

0.0

0

RE

VIS

ED

PR

OJ

EC

T R

EP

OR

T F

OR

AM

AD

AN

D O

PE

NC

AS

T P

RO

JE

CT

(4.0

Mty

)

ES

TIM

AT

ED

CA

PIT

AL

OU

TL

AY

IN M

INE

S

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

33

App A

81

(Contd

)

(Am

ount in

Rs L

akhs.)

Sl.N

o.

P A

R T

I C U

L A

R S

Sa

nc

tion

ed

(1.1

5 M

ty)

EX

IST

ING

CA

PIT

AL

as

on

31.0

3.1

5

To

tal C

ap

ital

R

& R

PA

CK

AG

E IN

QU

AR

RY

18

Co

mp

ensa

tion to

50

% la

nd

ouste

es in

lieu o

f no

t pro

vidin

g jo

b.F

or a

dd

itiona

l

Te

na

ncy la

nd

to b

e a

cq

uire

d 6

10

.84

Ha

and

ca

sh c

om

pe

nsa

tion g

iven fo

r

30

5.4

2 H

a la

nd

@ R

s. 5

,00

,00

0/- p

er A

cre

for 3

05

.42

Ha

La

nd

21

1.2

03

77

1.9

1

19

To

tal h

om

este

ad

11

00

. Co

mp

ensa

tion fo

r 11

00

no

s. o

f ho

me

ste

ad

@ R

s.

3,0

0,0

00

/-*(50

% w

ill be

give

n c

ash c

om

pe

nsa

tion)

47

1.5

01

65

0.0

0

20

Sub

sis

tence

Allo

wa

nce

@R

s 2

40

pe

r da

y for 2

5 d

ays

in a

mo

nth

for 1

10

0

ho

me

ste

ad

for o

ne

yea

r 7

92

.00

21

De

velo

pm

ent o

f reha

bilita

tion c

olo

ny fo

r tota

l 11

00

ho

me

ste

ad

inclu

din

g s

cho

ol,

ho

sp

itals

, roa

d e

tc.

11

00

.00

22

Oth

ers

10

55

.50

11

9.0

7

TO

TA

L1

78

2.8

02

04

.34

10

39

9.8

9

No

te: C

onsid

erin

g 5

0%

land

ouste

es w

ill be

pro

vide

d jo

b a

nd

50

% w

ill be

give

n c

ash c

om

pe

nsa

tion in

lieu o

f Jo

b.

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

34

Ap

pe

nd

ix.A

.8.2

.

UC

E o

f Re

vis

ed

Pro

jec

t Re

po

rt Am

ad

an

d O

pe

n C

as

t Pro

jec

t (4.0

Mty

) S

tate

me

nt s

ho

win

g T

he

Ca

pita

l Inv

es

tme

nt o

n R

oa

ds

an

d C

ulv

erts

(Am

ou

nt in

Rs

. La

kh

s.)

Sl.N

o.

Pa

rticu

lars

Ex

pe

ditu

reT

ota

lR

em

ark

s

Le

ng

th(k

m)

Am

ou

nt

up

toL

en

gth

(km

)A

mo

un

tA

mo

un

t

31

.03

.20

15

1C

olo

ny R

oa

ds a

nd

Culve

rts2

.50

39

.06

0.0

01

.00

89

.73

89

.73

Ap

p - A

.8.2

.1

2A

pp

roa

ch R

oa

d a

nd

Culve

rts3

.00

10

5.8

22

1.1

42

.00

47

9.9

75

01

.11

Ap

p - A

.8.2

.2

3S

ervic

e R

oa

d/H

aul R

oa

d a

nd

Culve

rts1

.00

70

.05

17

5.1

01

.60

68

3.5

98

58

.69

Ap

p - A

.8.2

.3

4D

ivers

ion o

f Ro

ad

with

Culve

rts0

.00

0.0

00

.00

6.0

01

05

1.8

81

05

1.8

8A

pp

- A.8

.2.4

5C

oa

l Tra

nsp

ort R

oa

d w

ith C

ulve

rts0

.00

0.0

00

.00

5.0

02

59

6.4

32

59

6.4

3A

pp

- A.8

.2.5

To

tal

21

4.9

31

96

.24

49

01

.60

50

97

.84

As

pe

r Ap

pro

ve

d P

.R.

Re

vis

ed

/Ad

ditio

na

l Pro

vis

ion

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

35

Ap

pe

nd

ix-A

.8.2

.1.

(Am

ou

nt in

Rs. L

akh

s)

Sl.N

o.

Pa

rticu

lars

Un

itE

xp

en

ditu

reT

ota

l

Qu

an

tityA

mo

un

tu

pto

Qu

an

tityC

ost

Co

stT

ota

lA

mo

un

t

31.0

3.2

015

a

t 100C

Ia

t 2926 C

IC

ost

(Rs.)

(Rs.)

(La

kh

s)

1C

olo

ny R

oa

ds

3.7

5 M

Wid

e R

oa

d (In

term

ed

iate

Wid

th R

oa

d)

M.

2500.0

0

18.7

3

1000.0

0-

6802.0

068.0

2

Sp

ecific

atio

ns:

i)20cm

th.G

rade- I o

ver 4

0cm

th.m

ooru

m fillin

g a

s s

ub-b

ase.

ii)15cm

th.G

rade - II &

7.5

cm

th.G

rade-III W

BM

as b

ase

iii)5.0

cm

th.b

itum

inous m

acadam

with

2cm

thic

k s

eal c

oat

Rate

estim

ate

d o

n th

e b

asis

of C

PW

D D

SO

R'2

007

(equiva

lent C

ost In

dex 1

727) =

Rs.4

015/R

M

2C

ulv

erts:(7

.5m

wid

e)

i)4.5

7m

span R

CC

sla

b c

ulve

rtN

o.

1.0

03.9

3

ii)3.0

5m

span R

CC

sla

b c

ulve

rtN

o.

1.0

02.6

21.0

025000.0

0731500.0

07.3

2

iii)1.8

3m

span R

CC

sla

b c

ulve

rtN

o.

1.0

01.6

8

iv)0.6

1m

dia

mete

r hum

e p

ipe c

ulve

rtN

o.

3.0

00.9

81.0

03100.0

090706.0

00.9

1

3P

ucca

Dra

ins:

i)22.5

cm

X 3

0cm

RM

.625.0

01.8

4250.0

028.0

0819.0

02.0

5

ii)30cm

X 4

5cm

RM

.500.0

02.9

9200.0

057.0

01668.0

03.3

4

iii)60cm

X 9

0cm

RM

.250.0

02.7

3100.0

0104.0

03043.0

03.0

4

4T

ree

Gu

ard

s:N

o.

100.0

00.3

340.0

031.0

0907.0

00.3

6

5R

CC

slab

for d

rain

cro

ssing

: N

o.

151.0

0

0.4

1

54.0

026.0

0761.0

00.4

1

(1.5

3m

X 0

.61m

X 7

.5cm

)

6E

xtra

for p

oor /B

.C. s

oil o

n ite

ms 2

& 3

only

1.6

8

1.6

7

@ 1

0%

To

tal

37.9

287.1

2

Contin

gencie

s @

3%

1.1

42.6

1

Gra

nd

To

tal

39.0

60.0

089.7

389.7

3

As p

er a

pp

rove

d P

.R.

Re

vise

d/A

dd

ition

al P

rovisio

n

Re

vis

ed

Pro

jec

t Re

po

rt for A

ma

da

nd

Op

en

Ca

st P

roje

ct (4

.0 M

ty)

Sta

tem

ent s

ho

win

g th

e E

stim

ate

d C

ap

ital In

vestm

ent o

n C

olo

ny R

oa

ds

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

36

Ap

pe

nd

ix-A

.8.2

.2

(Am

ou

nt in

Rs. L

akh

s)

Sl.N

o.

Pa

rticu

lars

Un

itT

ota

l

Q

ua

ntity

Am

ou

nt

Qu

an

tityA

mo

un

tQ

ua

ntity

Ra

teR

ate

A

mo

un

t

at 1

00 C

Ia

t 2926 C

IA

mo

un

t

(Rs.)

(Rs.)

(La

kh

s)(L

akh

s)

15.0

M W

ide

Ro

ad

(Inte

rme

dia

te W

idth

Ro

ad

)R

M3000

90.1

3

Sp

ecific

atio

ns:

i)40cm

th.m

ooru

m fillin

g a

s s

ub-b

ase.

ii)30cm

th.G

rade - I &

15cm

th.G

rade-II W

BM

as b

ase.

iii)15cm

th.G

rade - III a

long w

ith 5

.0cm

th.b

itum

inous

macadam

with

seal c

oat.

Rate

estim

ate

d o

n th

e b

asis

of C

PW

D D

SO

R'2

007

(equiva

lent C

ost In

dex 1

727) =

Rs.6

380/R

M

27.5

M W

ide

Ro

ad

(Inte

rme

dia

te W

idth

Ro

ad

)R

M2000

-16214.1

4324.2

8

Sp

ecific

atio

ns:

i)40cm

th.m

ooru

m fillin

g a

s s

ub-b

ase.

ii)30cm

th.G

rade - I &

15cm

th.G

rade-II W

BM

as b

ase.

iii)15cm

th.G

rade - III a

long w

ith 5

.0cm

th.b

itum

inous

macadam

with

seal c

oat.

Rate

estim

ate

d o

n th

e b

asis

of C

PW

D D

SO

R'2

007

(equiva

lent C

ost In

dex 1

727) =

Rs.9

570/R

M

3C

ulv

erts:

i)4.5

7m

span R

CC

sla

b c

ulve

rtE

ach

27.8

61

126750.0

03708705.0

037.0

9

ii) 3.0

5m

span R

CC

sla

b c

ulve

rtE

ach

12.6

21

84500.0

02472470.0

024.7

2

ii)0.6

1m

dia

mete

r hum

e p

ipe c

ulve

rtE

ach

30.9

82

10525.0

0307962.0

06.1

6

4P

ucca D

rain

s : 6

0 x

90 c

mR

M2000

104.0

03043.0

460.8

6

5E

xtra

for p

oor/B

.C s

oil o

n ite

m 2

& 3

of a

bove

@ 1

0%

1.1

512.8

8

Su

b T

ota

l102.7

424.0

8465.9

9

Contin

gencie

s(3

%)

3.0

813.9

8

To

tal

105.8

224.0

8479.9

7504.0

5

Re

vise

d/A

dd

ition

al P

rovisio

nA

s pe

r Ap

pro

ve

d P

.R.

Re

vis

ed

Pro

jec

t Re

po

rt for A

ma

da

nd

Op

en

Ca

st P

roje

ct (4

.0 M

ty)

Sta

tem

ent s

ho

win

g th

e E

stim

ate

d C

ap

ital In

vestm

ent o

n A

pp

roa

ch R

oa

d

Ex

pe

nd

iture

up

to 3

1.0

3.1

5

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

37

Ap

pe

nd

ix-A

.8.2

.3

(Am

ou

nt in

Rs. L

akh

s)

Sl.N

o.

Pa

rticu

lars

Un

itT

ota

l

Qu

an

tityA

mo

un

tQ

ua

ntity

Am

ou

nt

Qu

an

tityR

ate

Ra

teT

ota

lA

mo

un

t

a

t 100 C

Ia

t 2926 C

IC

ost

1S

erv

ice

Ro

ad

/ Ha

ul R

oa

d

Tota

l wid

th o

f Road -2

3m

(Double

Lane)

M.

1000.0

061.6

8

1600.0

033260.0

0532.1

6

Wid

th o

f carria

ge w

ay-1

4m

Wid

th o

f Dozer tra

ck- 5

m

Wid

th o

f should

er o

n e

ach s

ide-2

m

Specific

atio

ns:(F

or C

BR

valu

e 4

)

i) 500m

m th

. Mooru

m

ii) 300m

m th

. WB

M G

rade I

iii) 300m

m th

.WB

M G

rade II

Rate

estim

ate

d o

n th

e b

asis

of C

PW

D D

SO

R'0

7

(equiva

lent C

ost In

dex 1

727) =

Rs.1

9631/R

M

2C

ulv

erts:

i)4.5

7m

span R

CC

sla

b c

ulve

rtN

o.

1.0

05.3

11.0

0169110.0

04948158.6

049.4

8

ii)0.6

1m

dia

mete

r hum

e p

ipe c

ulve

rtN

o.

1.0

00.4

41.0

014000.0

0409640.0

04.1

0

iii)3.0

5m

span R

CC

sla

b c

ulve

rtN

o.

2.0

0112750.0

03299065.0

065.9

8

3E

xtra

for p

oor /B

.C. s

oil o

n ite

ms 2

only

@10%

0.5

8

11.9

6

To

tal

68.0

1172.1

5663.6

8

Contin

gencie

s(3

%)

2.0

419.9

1

Gra

nd

To

tal

70.0

5172.1

5683.5

9855.7

4

As p

er A

pp

rove

d P

.R.

Re

vise

d/ A

dd

ition

al P

rovisio

n

Re

vis

ed

Pro

jec

t rep

ort fo

r Am

ad

an

d O

pe

n C

as

t Pro

jec

t (4.0

Mty

)S

tate

me

nt s

ho

win

g th

e E

stim

ate

d C

ap

ital In

vestm

ent o

n S

ervic

e R

oa

d/H

aul R

oa

d

Ex

pe

nd

iture

up

to 3

1.0

3.2

015

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

38

Ap

pe

nd

ix-A

.8.2

.4

(Am

ou

nt in

Rs. L

akh

s)

Sl.N

o.

Pa

rticu

lars

Un

itE

xp

en

ditu

reT

ota

l

Q

ua

ntity

Am

ou

nt

up

toQ

ua

ntity

Ra

te a

tR

ate

at

Am

ou

nt

Am

ou

nt

31.0

3.2

015

100 C

I (Rs.)

2926 C

I (Rs.)

(La

kh

s)

17.5

M W

ide

Ro

ad

(Inte

rme

dia

te W

idth

Ro

ad

)R

M6000

-15155.2

2909.3

1

Sp

ecific

atio

ns: (C

BR

Va

lue

=4)

i) 50.0

cm

th.m

ooru

m fillin

g a

s s

ub-b

ase.

ii)30cm

th.G

rade - I &

22.5

cm

th.G

rade- II W

BM

as b

ase.

iii)15cm

th.G

rade - III a

long w

ith 5

.0cm

th.b

itum

inous

macadam

with

seal c

oat.

Rate

estim

ate

d o

n th

e b

asis

of C

PW

D D

SO

R'0

7

(equiva

lent C

ost In

dex 1

727) =

Rs.8

945/R

M

2C

ulv

erts:(1

3.0

m w

ide

)

i)4.5

7m

span R

CC

sla

b c

ulve

rtE

ach

267300.0

01969198.0

039.3

8

ii)3.0

5m

span R

CC

sla

b c

ulve

rtE

ach

444900.0

01313774.0

052.5

5

iii)0.6

1m

dia

mete

r hum

e p

ipe c

ulve

rtE

ach

65600.0

0163856.0

09.8

3

3E

xtra

for p

oor/ B

.C. s

oil o

n ite

m n

o.2

only

@ 1

0%

10.1

8

Su

b T

ota

l1021.2

5

Contin

gencie

s(3

%)

30.6

4

To

tal

0.0

00.0

01051.8

81051.8

8

As p

er A

pp

rove

d P

.R.

Re

vise

d/A

dd

ition

al P

rovisio

n

UC

E o

f Re

vis

ed

Pro

jec

t Re

po

rt for A

ma

da

nd

Op

en

Ca

st P

roje

ct (4

.0 M

ty)

Sta

tem

ent s

ho

win

g th

e E

stim

ate

d C

ap

ital In

vestm

ent o

n D

ivers

ion o

f Ro

ad

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

39

Ap

pe

nd

ix-A

.8.2

.5

(Am

ou

nt in

Rs. L

akh

s)

Sl.N

o.

Pa

rticu

lars

Un

itE

xp

en

ditu

reT

ota

l

Q

ua

ntity

Am

ou

nt

up

toQ

ua

ntity

Ra

te a

tR

ate

at

Am

ou

nt

Am

ou

nt

31.0

3.2

015

100 C

I (Rs.)

2926 C

I (Rs.)

(La

kh

s)

17.5

M W

ide

Ro

ad

(Inte

rme

dia

te W

idth

Ro

ad

)R

M5000

-15155.2

2757.7

6

Sp

ecific

atio

ns: (C

BR

Va

lue

=4)

i) 50.0

cm

th.m

ooru

m fillin

g a

s s

ub-b

ase.

ii)30cm

th.G

rade - I &

22.5

cm

th.G

rade- II W

BM

as b

ase.

iii)15cm

th.G

rade - III a

long w

ith 5

.0cm

th.b

itum

inous

macadam

with

seal c

oat.

Rate

estim

ate

d o

n th

e b

asis

of C

PW

D D

SO

R'0

7

(equiva

lent C

ost In

dex 1

727) =

Rs.8

945/R

M

2C

ulv

erts:(1

3.0

m w

ide

)

i)4.5

7m

span R

CC

sla

b c

ulve

rtE

ach

267300.0

01969198.0

039.3

8

ii)3.0

5m

span R

CC

sla

b c

ulve

rtE

ach

344900.0

01313774.0

039.4

1

iii)0.6

1m

dia

mete

r hum

e p

ipe c

ulve

rtE

ach

55600.0

0163856.0

08.1

9

3B

ridge : (1

3.0

m w

ide)

RM

300

LS

1500.0

0

4P

ucca D

rain

s : 6

0 x

90 c

mR

M5000

104.0

03043.0

4152.1

5

3E

xtra

for p

oor/ B

.C. s

oil o

n ite

m n

o.2

& 4

only

@ 1

0%

23.9

1

Su

b T

ota

l2520.8

0

Contin

gencie

s(3

%)

75.6

2

To

tal

0.0

00.0

02596.4

32596.4

3

As p

er A

pp

rove

d P

.R.

Re

vise

d/A

dd

ition

al P

rovisio

n

UC

E o

f Re

vis

ed

Pro

jec

t Re

po

rt for A

ma

da

nd

Op

en

Ca

st P

roje

ct (4

.0 M

ty)

Sta

tem

ent s

ho

win

g th

e E

stim

ate

d C

ap

ital In

vestm

ent o

n C

oa

l Tra

nsp

ort R

oa

d

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

40

A

pp

en

dix

- A.8

.3

(Am

ou

nt in

Rs

.La

kh

s)

Sl.N

o.

Pa

rticu

lars

Un

itT

ota

l

Qu

an

tityA

mo

un

tQ

ua

ntity

Ra

te a

tR

ate

at

To

tal

Am

ou

nt

Qu

an

tityA

mo

un

t1

00

CI

29

26

CI

Co

st

(Rs

.)(R

s.)

(La

kh

s)

Fo

r Do

me

stic

wa

ter re

qu

irem

en

t

1.

Bo

re w

ell in

clu

din

g s

ub

me

rssib

le p

um

p ,G

I co

nne

ctio

ns

No

s4

12

.00

5.5

12

LS

10

.00

up

to G

round

Wa

ter R

ese

rvoir in

clu

din

g e

lectric

als

.

2G

round

wa

ter re

se

rvoir

Litre

s1

75

00

04

.00

65

00

00

.65

19

.02

12

.36

3C

lea

r wa

ter p

um

ps (c

entrifu

ga

l type

) 10

HP

.N

os

20

.75

2L

S4

.00

4P

um

p H

ouse

S

q.m

.2

00

.80

25

38

0.0

01

11

18

.80

2.7

8

5C

lea

r wa

ter ris

ing

ma

in :

i) 15

0 m

m.d

ia.

RM

20

03

.01

30

01

43

.45

41

97

.35

12

.59

ii) Ad

d 7

.5%

for s

ad

dle

sup

po

rts va

lves,b

end

s,e

tc.

0.2

30

.94

6Z

on

al s

tora

ge

:

a) R

CC

Ove

rhe

ad

tank:

i) Fo

r cle

ar w

ate

r in to

wnship

. |L

itres

17

50

00

20

.20

45

00

01

.10

32

.19

14

.49

ii) Fo

r cle

ar w

ate

r in s

ervc

e b

ldg

. |

7D

istrib

utio

n s

ys

tem

:

A.F

or C

olo

ny :

i) 10

0 m

m d

ia m

ain

.R

M5

00

4.6

65

00

88

.80

25

98

.29

12

.99

ii) 80

mm

dia

.R

M5

00

3.5

85

00

68

.25

19

97

.00

9.9

9

iii) Ad

d 7

.5%

for s

ad

dle

sup

po

rts,va

lves,b

end

s e

tc.

0.6

21

.72

Fo

r Ind

us

trial w

ate

r req

uire

me

nt

8G

round

wa

ter re

se

rvoir fo

r Ind

ustry

Litre

s7

50

00

1.5

02

25

00

00

.65

19

.02

42

.80

9C

entrifu

ga

l Pum

p fo

r Ind

ustria

l wa

ter

No

s.

20

.50

4L

S8

.00

10

Zo

na

l sto

rag

e :

b) R

CC

Ove

rhe

ad

tank fo

r ind

st.w

ate

r |L

itres

75

00

08

.66

9.9

0

11

Dis

tribu

tion

sy

ste

m :

B)F

or In

dustry:

i) 10

0 m

m d

ia m

ain

.R

M6

00

5.5

94

.98

50

08

8.8

02

59

8.2

91

2.9

9

ii) 80

mm

dia

.ma

in.

RM

40

02

.86

50

06

8.2

51

99

7.0

09

.99

iii) Ad

d 7

.5%

for s

ad

dle

sup

po

rts, va

lves, b

end

s e

tc.

0.6

31

.72

12

Inv

es

tiga

tion

s fo

r :

Hyd

ro-g

eo

log

ica

l & G

eo

- Te

chnic

al d

ata

1.5

05

.00

13

Ele

ctric

al in

sta

llatio

ns

:

A) T

ransfo

rme

r and

sw

itchg

ea

r |

B) O

verh

ea

d lin

e. |

5%

of th

e

3.5

57

.87

C) In

stru

me

nts

, too

ls e

tc. |

ab

ove

D) S

witc

h ro

om

. |

Su

b-T

ota

l7

4.6

42

0.3

91

70

.24

Ad

d c

ontin

ge

ncie

s @

3%

2.2

45

.11

Gra

nd

To

tal

76

.88

20

.39

17

5.3

51

95

.74

31

.03

.20

15

As

pe

r Ap

pro

ve

d P

.R.

Re

vis

ed

/Ad

ditio

na

l Pro

vis

ion

UC

E o

f Re

vis

ed

Pro

jec

t Re

po

rt for A

ma

da

nd

Op

en

Ca

st P

roje

ct (4

.0 M

ty)

Sta

tem

ent S

ho

win

g th

e C

ap

ital In

vestm

ent in

Wa

ter S

up

ply A

rrang

em

ent

Ex

istin

g u

pto

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

41

Ap

pe

nd

ix - A

.8.3

(a)

(Am

ou

nt in

Rs

.La

kh

s)

Sl.N

o.

Pa

rticu

lars

Un

itE

xp

ed

iture

To

tal

Qu

an

tityA

mo

un

tu

pto

Qty

Ra

te (R

s.)

Co

st a

t A

mo

un

t

31

.03

.20

15

at 1

00

CI

29

26

CI

1.

Co

lon

y

To

tal N

o. o

f ho

use

s in

the

co

lony

No

s.

37

72

9.6

61

35

Co

st o

f se

wa

ge

dis

po

sa

l sche

me

pe

r ho

use

Rs.

75

02

9.6

3

(Fo

r co

nve

ntio

na

l se

we

rag

e d

isp

osa

l arra

ng

em

ent)

The

refo

re, to

tal c

ost o

f se

wa

ge

dis

po

sa

l sche

me

of

Rs.

co

lony

2.

Se

rvic

e b

uild

ing

s

i) To

tal c

ost o

f se

rvice

build

ing

sR

s.la

kh

16

2.7

7

ii) Co

st o

f se

wa

ge

dis

po

sa

l sche

me

5%

of a

bo

ve3

4.5

38

.14

3.

Dis

po

sa

l of m

ine

wa

ter s

ettlin

g ta

nk ( 2

no

s.)

LS

6.0

04

0.0

0

4P

uc

ca

Dra

ins

for in

du

stria

l se

we

rag

e

i)22

.5cm

X 3

0cm

RM

.1

00

0.0

02

8.0

08

.19

ii)30

cm

X 4

5cm

RM

.1

00

0.0

05

7.0

01

6.6

8

iii)60

cm

X 9

0cm

RM

.2

00

0.0

01

04

.00

60

.86

5S

ew

ag

e T

rea

tme

nt P

lant

LS

40

0.0

0

Su

b-T

ota

l7

0.1

95

63

.50

Co

ntin

ge

ncie

s @

3%

01

6.9

0

Gra

nd

To

tal

70

.19

0.0

05

80

.40

58

0.4

0

As

pe

r Ap

pro

ve

d P

.R.

Re

vis

ed

/Ad

ditio

na

l Pro

vis

ion

UC

E o

f Re

vis

ed

Pro

jec

t Re

po

rt for A

ma

da

nd

Op

en

Ca

st P

roje

ct (4

.0 M

ty)

Sta

tem

ent S

ho

win

g th

e C

ap

ital In

vestm

ent in

Se

we

rag

e D

isp

osa

l Sche

me

.

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

42

A

pp

end

ix - A

.8.3

(Co

ntd

.)

Re

vis

ed

Pro

jec

t Re

po

rt for A

ma

da

nd

Op

en

Ca

st P

roje

ct (4

.00

Mty

)

Wa

ter D

em

an

d C

alc

ula

tion

s

DA

TA

AV

AIL

AB

LE

i)Ma

np

ow

er=

36

6

ii)To

tal N

o.o

f ho

use

s re

quire

d=

13

5

iii)To

tal N

o.o

f exis

ting

ho

use

s=

0

iv)T

ota

l No

.of h

ouse

s to

be

co

nstru

cte

d=

13

5

Po

pula

tion:

1.R

esid

entia

l po

pula

tion @

5 p

ers

ons p

er h

ouse

=6

75

2.N

on - R

esid

entia

l wo

rke

rs=

23

1

Wa

ter D

em

an

d:

A.P

ota

ble

Wa

ter D

em

an

d:

i)Wa

ter re

quire

me

nt fo

r resid

entia

l po

pula

lion @

13

5 litre

s p

er c

ap

ita

pe

r da

y=

91

12

5ii)W

ate

r req

uire

me

nt fo

r no

n - re

sid

entia

l po

pula

tion @

45

litres p

er

ca

pita

pe

r da

y=

10

39

5

iii)Wa

ter re

qure

me

nt fo

r se

rvic

e b

uild

ing

s 1

0%

of ite

m A

(i)& (ii)

10

15

2

iv)S

ub

- tota

l of a

bo

ve

(i),(ii) & (iii)

11

16

72

v)P

roce

ss a

nd

oth

er lo

sse

s 1

0%

of (iv

)1

11

67

To

tal

12

28

39

Litre

s p

er d

ay

Sa

y0

.12

3M

LD

B.In

du

stria

l Wa

ter D

em

an

d in

Op

en

ca

st P

roje

cts

:

i)To

tal N

o o

f Se

rvic

ea

ble

Dum

pe

rs a

nd

Do

ze

rs0

ii)Wa

ter re

quire

d fo

r wa

shin

g o

f Dum

pe

rs a

nd

Do

ze

rs @

22

50

litres

pe

r dum

pe

r0

iii)Wa

ter re

quire

d fo

r dust s

up

pre

ssio

n in

CH

P &

oth

er in

dustria

l

pre

mis

es 2

25

00

litres p

er d

ay fo

r millio

n to

nne

of c

oa

l pro

ductio

n p

er

annum

90

00

0iv

)Wa

ter re

quire

d fo

r fire fig

htin

g in

co

al 4

50

00

LP

D fo

r eve

ry m

illion

tonne

of c

oa

l pro

ductio

n p

er a

nnum

18

00

00

v)W

ate

r req

uire

d fo

r roa

d w

ate

ring

inclu

din

g w

ate

ring

of h

aul ro

ad

s

67

50

0 L

PD

for e

ve

ry m

illion to

nne

co

al p

rod

uctio

n p

er a

nnum

27

00

00

vi)A

dd

for lo

sse

s 1

0%

of (ii) to

(v)

54

00

0

59

40

00

Litre

s p

er d

ay

Sa

y,

0.5

94

ML

DT

ota

l Wa

ter D

em

an

d (P

ota

ble

Wa

ter D

em

an

d

& In

du

stria

l Wa

ter D

em

an

d)

0.7

17

ML

D

R.P.R for Amadand OCP (4.00 Mty), Updated’ July 2015 CMPDI

Job No.515126 Total Outsourcing Option Page-X43

APPENDIX-B

REVISED PROJECT REPORT FOR AMADAND OPENCAST PROJECT (4.0 Mty)

STATEMENT SHOWING JOB/CATEGORYWISE REQUIREMENT OF MANPOWER

SL.No. PARTICULARS CATEGORY/SCALE DEPARTMENTAL OUTSOURCED TOTAL

A. OB MANPOWER CAT dep con TOT

1 MINING

SIRDAR/SHORTFIRER/OVERMAN 21891.41 24 24

2 MAZDOOR INCLUDING

BLASTING I/II 12 12

3 PITMAN/DUMPMAN/TRIPMAN GRADE-E 11 11

SUB-TOTAL(OB) 47 0 47

B. COAL MANPOWER

A. COAL DIRECT MANPOWER

1 MINING SIRDAR 21891.41 11 11

2 PITMAN/DUMPMAN/TRIPMAN GRADE-E 11 11

SUB-TOTAL

22 0 22

C. COAL HANDLING PLANT

2 Sr. Manager/Manager(E& M) E5/E6 1 1

3 Deputy Manager/Asst Manager (E&

M) E4/E3 3 3

4 FORMAN INCHARGE(E&M) 25472.49 1 1

5 FOREMAN(E&M) 23638.06 3 3

6 WEIGH BRIDGE CLERK(Road) 21891.41 5 5

7 MECHANICAL FITTER IV/V 8 8

8 ELECTRICAL FITTER IV/V 6 6

9 MECHANIC ELECTRONIC IV/V 1 1

10 WELDER V 1 1

11 CONTROL ROOM /SUBSTATION

ATTENDENT IV/V 4 4

12 CONVEYOR OPERATOR III/IV 7 7

13 FIRESTATION ATTENDENT III/IV 0

14 HELPERS FOR

FITTERS,WELDERS II 15 15

15 FEEDER OPERATOR III 3 3

16 PLOUGH FEEDER OPERATOR III 0

17 FEEDER OPERATOR III 0

18 TYNDALS IV/V 2 2

19 RECLAIM FEEDER OPERATOR III 10 10

20 GENERAL MAZDOORS/BELT

CLEANERS I 5 5

21 DOZER OPERATOR EXCV-A 0

22 CRANE OPERATOR EXCV-A 1 1

23 LOCO OPERATOR EXCV SPL 3 3

SUB-TOTAL 17 62 79

SUB-TOTAL(COAL) 39 62 101

D. E&M SUPERVISION

1 DY. CHIEF ENGINEER (E&M) E7 1 1

2 SENIOR MANAGER (E&M) E4/E5 1 1

3 ASST. MANAGER (E&M) E3 1 1

5 SR. OFFICERS(E&M) E2 1 1

6 SR.PA GRADE-E 1 1

7 LDC/TYPIST GRADE-D 1 1

8 PEON GRADE-H 0 1 1

R.P.R for Amadand OCP (4.00 Mty), Updated’ July 2015 CMPDI

Job No.515126 Total Outsourcing Option Page-X44

SUB-TOTAL

6 1 7

APPENDIX-B(CONTD.)

SL. PARTICULARS CATEGORY/ DEPTT. CONTRACTUAL TOTAL

NO. SCALE

E. WORKSHOP & E&M

MAINTENANCE

1 FOREMAN INCHARGE(E&M) 25472 1 1

2 ELECTRICAL SUPERVISOR 25472 1 1

3 FOREMAN (E&M) 23638.06 2 2

4 FOREMAN (E&T) 23638.06 1 1

5 CONTROL ROOM ATTENDENT III/IV 4 4

6 ELECTRICIAN IV/V 0

7 PUMP KHALASI/OPERATOR III 7 7

8 TELEPHONE MECHANIC IV/V 1 1

9 TELEPHONE LINEMAN II 0

10 TURNER/MACHINIST IV/V 5 5

11 MECHANICAL FITTER IV/V 5 5

12 ELECTRICAL FITTER IV/V 3 3

13 PIPE FITTER IV/V 3 3

14 ELECTRICAL

FITTER/ARMATURE WINDER IV/V 0

15 WELDER IV/V 5 5

16 HELPER II 9 9

17 TYNDALS I 0

18 CABLE JOINTER III 0

19 GENERAL MAZDOORS,

GREASING ETC. I 4 4

SUB-TOTAL 35 16 51

F. OTHER OPERATOR

2 VEHICLE DRIVER V/VI 22 22

3 HEMM OPERATORS EXCV-B/C 15 15

SUB-TOTAL 37 0 37

G. MINING SAFETY DESPATCH

AND

QUALITY CONTROL

1 PROJECT OFFICER E8 1 1

2 MINE MANAGER E7 1 1

3 ASSTT. COLLIERY MANAGER E4 2 2

4 ASST. MANAGER E3 4 4

5 OVERMAN 25472.49 3 3

6 MINING SIRDARS 21891.41 5 5

7 PA./JR.STENOGRAPHER GRADE-E 1 1

8 LDC/TYPIST GRADE-D 1 1

9 MTK/REGISTER KEEPER GRADE-D 4 4

10 PEON GRADE-H 1 1

QUALITY CONTROL &

DESPATCH

11 LOADING SUPERVISOR 23638.06 3 3

12 SAMPLING ASST. 20249.47 1 1

13 SAMPLING MAZDOOR II 1 1

14 DATA ENTRY OPERATOR 21891.41 1 1

15 LABORATORY ASST. 20249.47 0 0

16 TECH.INSPECTOR 20249.47 1 1

SUB-TOTAL 30 0 30

H. ACCOUNTS

R.P.R for Amadand OCP (4.00 Mty), Updated’ July 2015 CMPDI

Job No.515126 Total Outsourcing Option Page-X45

1 SR. FINANCE OFFICER/FINANCE

OFFICER E6 1

1

APPENDIX-B(CONTD.)

2 MANAGER (FINANCE) E5 1 1

3 Dy MANAGER (FINANCE) E4 1 1

4 ACCOUNTANT 25472.49 2 2

5 ACCOUNTS CLERK GRADE-D 2 2

6 LDC/TYPIST GRADE-D 1 1

7 CASHIER GRADE-C 1 1

SUB-TOTAL 9 0 9

SL. PARTICULARS CATEGORY/ DEPTT. CONTRACTUAL TOTAL

NO. SCALE

I. PERSONNEL AND WELFARE

1 ASST MANAGER(PERSONEL) E3 1 1

2 LDC/TYPIST GRADE-D 1 1

3 GENERAL MAZDOOR I 1 1

SUB-TOTAL

3 0 3

J. MEDICAL AND SANITATION

1 MEDICAL OFFICER E5 1 1

2 COMPOUNDER GRADE-D 1 1

3 DRESSER GRADE-E 1 1

4 NURSE/MIDWIFE GRADE-D 1 1

5 CLERK CUM STORE KEEPER GRADE-D 1 1

SUB-TOTAL

5 0 5

K. STORES

1 STORE KEEPER/ASSTT. STORE

KEEPER GRADE-D 2 2

2 MAZDOOR I 3 3

3 MAGAZINE CLERK GRADE-D 4 4

SUB-TOTAL

9 0 9

L. CIVIL

1 SENIOR MANAGER (CIVIL) E6 1 1

2 MANAGER (CIVIL) E4/E5 1 1

3 ASST. MANAGER (CIVIL) E3 1 1

4 SR. OFFICERS(CIVIL) E2 1 1

5 OVERSEER 23638.06 2 2

6 PUMP ATTENDANT III 7 7

7 PIPE FITTER

HELPER/VALVEMAN II 4 4

SUB-TOTAL

6 11 17

M. SURVEY

2 MANAGER (SURVEY) E4 1 1

3 ASST. MANAGER (SURVEY) E3 1 1

3 SURVEYOR 25472.49 2 2

R.P.R for Amadand OCP (4.00 Mty), Updated’ July 2015 CMPDI

Job No.515126 Total Outsourcing Option Page-X46

4 DRAFTSMAN GRADE-E 2 2

5 CHAINMAN GRADE-F 2 2

6 MAZDOOR I 2 2

SUB-TOTAL 10 0 10

APPENDIX-B(CONTD.)

N. SECURITY

2 MANAGER (SECURITY) E4 1 1

2 ARMED GUARD GRADE-F 4 30 34

SUB -TOTAL 5 30 35

SUB -TOTAL(COMMON) 155 58 213

O. EMP & REHABILAITATION

2 MANAGER (ENVIRONMENT) E4 1 1

2 MINING SIRDARS 21891.41 1 1

3 LDC/TYPIST GRADE-D 1 1

4 MAZDOOR I 0 2 2

SUB-TOTAL(EMP)

3 2 5

GRAND TOTAL

244 122 366

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

47

RP

R F

OR

AM

AD

AN

D O

C P

RO

JE

CT

[4.0

0 M

ty]

Appendix

B-1

Ste

me

nt S

ho

win

g W

ag

es &

Be

ne

fits C

ost

Op

tion

-II(Ou

tsou

rce

) R

S. IN

LA

KH

S.

PA

RT

ICU

LA

RS

Annua

l

Ea

rnin

g N

O.

AM

T.

NO

. A

MT

. N

O.

AM

T.

NO

. A

MT

. N

O.

AM

T.

NO

. A

MT

. N

O.

AM

T.

DA

ILY

RA

TE

D E

MP

LO

YE

ES

Excav

atio

n

1 S

PL.G

RA

DE

9.2

70

93

0.0

03

27

.81

0.0

00

.00

32

7.8

10

.00

32

7.8

1

2 G

RA

DE

-A8

.83

60

40

.00

18

.84

0.0

00

.00

18

.84

0.0

01

8.8

4

3 G

RA

DE

-B8

.33

67

80

.00

0.0

00

.00

86

6.6

98

66

.69

0.0

08

66

.69

4 G

RA

DE

-C7

.99

15

80

.00

0.0

00

0.0

07

55

.94

75

5.9

40

.00

75

5.9

4

5 G

RA

DE

-D7

.28

50

50

.00

0.0

00

.00

0.0

00

0.0

00

.00

00

.00

6 G

RA

DE

-E6

.82

48

50

.00

0.0

00

.00

0.0

00

0.0

00

.00

00

.00

Cate

go

ry

7 C

AT

-I6

.41

50

86

38

.49

0.0

00

.00

63

8.4

91

27

6.9

80

.00

12

76

.98

8 C

AT

-II6

.55

41

96

39

.33

0.0

00

.00

16

.55

74

5.8

80

.00

74

5.8

8

9 C

AT

-III6

.74

43

30

.00

0.0

00

.00

96

0.7

09

60

.70

0.0

09

60

.70

10

CA

T-IV

6.8

78

26

0.0

00

.00

0.0

01

17

5.6

61

17

5.6

60

.00

11

75

.66

11

CA

T-V

7.1

54

30

0.0

00

.00

0.0

02

11

50

.24

21

15

0.2

40

.00

21

15

0.2

4

12

CA

T-V

I7

.90

06

90

.00

0.0

00

.00

11

86

.91

11

86

.91

0.0

01

18

6.9

1

MO

NT

HL

Y P

AID

EM

PL

OY

EE

S

13

A1

10

.75

39

40

.00

0.0

00

.00

22

1.5

12

21

.51

0.0

02

21

.51

14

A9

.47

54

30

.00

19

.48

0.0

09

85

.28

10

94

.75

0.0

01

09

4.7

5

15

B8

.81

05

80

.00

32

6.4

30

.00

87

0.4

81

19

6.9

20

.00

11

96

.92

16

C8

.18

08

62

41

96

.34

16

13

0.8

90

.00

75

7.2

74

73

84

.50

18

.18

48

39

2.6

8

17

D7

.14

84

40

.00

0.0

00

.00

19

13

5.8

21

91

35

.82

17

.15

20

14

2.9

7

18

E6

.86

95

11

17

5.5

61

17

5.5

65

34

.35

27

18

5.4

80

.00

27

18

5.4

8

19

F6

.79

15

60

.00

0.0

06

40

.75

64

0.7

50

.00

64

0.7

5

20

G6

.70

13

90

.00

0.0

00

.00

00

.00

0.0

00

0.0

0

21

H6

.56

61

00

.00

0.0

01

6.5

71

6.5

70

.00

16

.57

EX

EC

UT

IVE

S:

22

E-1

14

.09

55

70

.00

0.0

00

.00

0.0

00

0.0

00

.00

00

.00

23

E-2

15

.80

78

00

.00

0.0

00

.00

23

1.6

22

31

.62

0.0

02

31

.62

24

E-3

17

.34

94

80

.00

23

4.7

00

.00

81

38

.80

10

17

3.4

90

.00

10

17

3.4

9

25

E-4

18

.62

17

10

.00

11

8.6

20

.00

61

11

.73

71

30

.35

11

8.6

28

14

8.9

7

26

E-5

19

.00

71

20

.00

11

9.0

10

.00

35

7.0

24

76

.03

0.0

04

76

.03

27

E-6

20

.19

40

90

.00

0.0

00

.00

24

0.3

92

40

.39

0.0

02

40

.39

28

E-7

22

.82

14

20

.00

0.0

00

.00

24

5.6

42

45

.64

0.0

02

45

.64

29

E-8

24

.61

78

90

.00

0.0

00

.00

12

4.6

21

24

.62

0.0

01

24

.62

47

34

9.7

23

93

51

.34

00

.00

15

51

44

3.0

22

41

21

44

.08

33

3.9

52

44

21

78

.03

E . M

. S. (R

s.)

.3

38

4.0

1

Pro

d (P

ea

k) In

La

kh to

nne

.4

0.0

0

O . M

. S. (t)

59

.17

CO

ST

/T (R

s.)

57

.20

L.R

& E

MP

GR

AN

D T

OT

AL

SU

B-T

OT

AL

O.B

. C

OA

L C

OM

MO

NC

HP

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

48

.R

PR

FO

R A

MA

DA

ND

OC

PR

OJ

EC

T [4

.00

Mty

]

Sta

tem

en

t Sh

ow

ing

Un

it Co

st E

stim

ate

. A

PP

-C

S.R

10.8

5

Op

tion

-II(Ou

tso

urce

)S

P.G

RV

1.5

2

To

tal

Fix

ed

Va

riab

le

Sl.N

o P

artic

ula

rsC

ost

Co

st

Co

st

(Rs./t)

(Rs./t)

(Rs./t)

1 S

ala

ries,W

ag

es &

Be

ne

fits5

7.2

05

7.2

0

2 S

tore

s1

14

.40

11

.75

10

2.6

5

3 P

ow

er

44

.93

33

.69

11

.23

4 M

isc. e

xp

. incl.w

/s d

eb

its3

0.8

02

2.1

88

.62

5M

ine

Clo

sure

Co

st

26

.84

26

.84

6 A

dm

n. E

xp

ense

s6

.40

6.4

0

7 In

t. on w

kg

. ca

p @

1

4.5

0%

13

.56

7.6

45

.92

8 In

t. on lo

an c

ap

@ *

11

.50

%0

.00

0.0

0

9 D

ep

recia

tion

96

.57

96

.57

Sub

-To

tal

39

0.6

92

62

.27

12

8.4

2

10

OB

Outs

ourc

e C

ost

56

9.8

85

69

.88

11

Co

al O

uts

ourc

e C

ost

69

.81

69

.81

12

OB

Re

ha

nd

ling

Co

st

12

.49

12

.49

13

Int. o

n w

kg

. ca

p @

1

4.5

0%

31

.52

31

.52

All In

clu

siv

e C

ost

10

74

.40

26

2.2

78

12

.13

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

49

RP

R F

OR

AM

AD

AN

D O

C P

RO

JE

CT

[4.0

0 M

ty]

Sta

tem

en

t Of C

os

t an

d P

rofita

bility

At V

ario

us

Le

ve

ls

Op

tion

-II(Ou

tsou

rce

) A

PP

-C.1

Sl.N

oLE

VE

L O

F P

RO

DU

CTIO

N (%

)75

80

85

90

100

1P

rod

uctio

n(m

t)3

3.2

03

.40

3.6

04

.00

2V

aria

ble

co

st/t(R

s.)

81

2.1

38

12

.13

81

2.1

38

12

.13

81

2.1

3

3F

ixed

co

st/t(R

s.)

34

9.6

93

27

.84

30

8.5

52

91

.41

26

2.2

7

4T

ota

l co

st/t(R

s.)

11

61

.82

11

39

.96

11

20

.68

11

03

.54

10

74

.40

5C

ap

.inve

stm

ent/a

nnua

l2

61

8.0

82

45

4.4

52

31

0.0

72

18

1.7

31

96

3.5

6

outp

ut(R

s.)

6P

rese

nt s

.p/t (R

s.)

12

98

.22

12

98

.22

12

98

.22

12

98

.22

12

98

.22

7P

rofit/t (R

s.)

13

6.4

01

58

.26

17

7.5

41

94

.68

22

3.8

2

8R

.O.I.(g

ross b

efo

re c

ha

rgin

g

int.o

n lo

an c

ap

ital)(%

)5

.21

6.4

57

.69

8.9

21

1.4

0

9B

.E.P

. (%)

53

.95

%

(Mt.)

2.1

6

Capita

l Em

plo

yed R

s.in

lakhs

78

54

2.2

8

Equity

Capita

l Rs.in

lakhs

78

54

2.2

8

Loan C

apita

l Rs.in

lakhs

0.0

0

Sale

Pric

e P

er T

n. R

s.

12

98

.22

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

50

Sta

tem

ent s

ho

win

g E

MP

Co

st p

er/t

Ap

p- C

2

SL

.No

Pa

rticula

rsR

s./t

1 S

ala

ries,W

ag

es &

Be

ne

fits0

.92

2 S

tore

s1

3.3

3

3 P

ow

er

3.6

7

4 M

isc. e

xp. in

cl.w

/s d

eb

its5

.40

5M

ine

Clo

sure

Co

st

26

.84

6 A

dm

n. E

xpe

nse

s6

.98

7 In

t. on w

kg

. ca

p @

14

.50

%2

.76

8 D

ep

recia

tion

60

.37

To

tal

12

0.2

7

RP

R F

OR

AM

AD

AN

D O

C P

RO

JE

CT

[4.0

0 M

ty]

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

51

RP

R F

OR

AM

AD

AN

D O

C P

RO

JE

CT

[4.0

0 M

ty]

Sta

tem

ent S

ho

win

g E

co

no

mic

s a

t diffe

rent C

ap

acity U

tilisa

tionA

pp

en

dix

-C.3

Op

tion-II(O

uts

ourc

e)

10

0%

90

%8

5%

80

%7

5%

1O

utp

ut(M

ty)4

.00

3.6

03

.40

3.2

03

.00

2C

ost/te

(`.)

10

74

.40

11

03

.54

11

20

.68

11

39

.96

11

61

.82

3S

ellin

g P

rice

(`./te

)1

29

8.2

21

29

8.2

21

29

8.2

21

29

8.2

21

29

8.2

2

4P

rofit(`

./te)

22

3.8

21

94

.68

17

7.5

41

58

.26

13

6.4

0

5IR

R (%

)2

1.3

3%

16

.06

%1

3.5

5%

11

.06

%8

.58

%

Ca

pa

city

Utilis

atio

n L

ev

el

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

52

RP

R F

OR

AM

AD

AN

D O

C P

RO

JE

CT

[4.0

0 M

ty]

Sta

tem

ent s

ho

win

g s

ensitivity o

f NP

VA

pp

en

dix

-C.4

Op

tion-II(O

uts

ourc

e)

10

0%

90

%8

5%

80

%7

5%

AB

ase

ca

se

21

.33

%1

6.0

6%

13

.55

%1

1.0

6%

8.5

8%

BIn

cre

ase

in C

ap

ital

i) 5%

19

.73

%1

4.7

8%

12

.39

%1

0.0

2%

7.6

4%

ii) 10

%1

8.3

0%

13

.62

%1

1.3

4%

9.0

7%

6.7

7%

iii) 15

%1

7.0

0%

12

.55

%1

0.3

7%

8.1

8%

5.9

7%

CIn

cre

ase

in o

p. c

ost

i) 5%

15

.29

%1

0.9

9%

8.8

3%

6.6

4%

4.3

8%

ii) 10

%1

0.0

7%

6.3

3%

4.3

8%

2.3

3%

0.1

5%

iii) 15

%5

.25

%1

.79

%N

eg

ative

Ne

ga

tiveN

eg

ative

DD

ecre

ase

in S

ale

s

i) 5%

13

.72

%9

.66

%7

.61

%5

.51

%3

.33

%

ii) 10

%7

.08

%3

.66

%1

.84

%N

eg

ative

Ne

ga

tive

iii) 15

%0

.58

%N

eg

ative

Ne

ga

tiveN

eg

ative

Ne

ga

tive

EIn

cre

ase

in b

oth

Ca

pita

l & o

p. c

ost

i) 5%

14

.11

%9

.99

%7

.92

%5

.80

%3

.61

%

ii) 10

%8

.31

%4

.80

%2

.94

%0

.99

%N

eg

ative

iii) 15

%3

.21

%N

eg

ative

Ne

ga

tiveN

eg

ative

Ne

ga

tive

Ca

pa

city u

tilisa

tion le

vel

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

53

RP

R F

OR

AM

AD

AN

D O

C P

RO

JE

CT

[4.0

0 M

ty]

AP

P-D

.1

Ca

sh

flow

sta

tem

en

t at 1

00 %

ca

pa

city

& D

CF

Co

st / tn

. @ d

iffere

nt r

ate

s

Op

tion

-II(Ou

tso

urce

) R

s. in

Lakhs.

YE

AR

Ca

pita

l R

ep

l. R

EV

. T

ota

l S

ale

s P

rod

. N

et

Exp

. C

ap

. E

xp

. O

utflo

w R

ece

ipt

lakh te

. F

low

(1)

(2)

(3)

(4)

(5)

(6)

(7)

(8)

Ne

tblo

ck a

s o

n

31

.03

.15

24

81

00

24

81

00

.00

-24

81

Yr 1

51

20

02

11

34

26

25

42

64

70

20

.00

21

6

Yr 2

11

57

80

34

87

54

64

53

39

70

53

0.0

0-6

74

8

Yr 3

22

24

50

42

36

76

46

12

52

94

04

0.0

0-1

16

72

Yr 4

24

45

80

43

39

86

78

55

52

94

04

0.0

0-1

49

15

Yr 5

12

10

22

77

44

38

25

67

61

51

70

04

0.0

0-5

06

1

Yr 6

06

37

40

81

04

14

47

51

70

04

0.0

01

02

53

Yr 7

07

32

35

76

63

64

98

51

70

04

0.0

01

52

02

Yr 8

02

87

36

15

03

64

37

51

70

04

0.0

01

52

63

Yr 9

05

28

36

81

03

73

38

51

70

04

0.0

01

43

62

Yr 1

02

79

12

96

36

87

83

84

54

51

70

04

0.0

01

32

46

Yr 1

10

13

55

36

92

93

82

84

51

70

04

0.0

01

34

16

Yr 1

20

61

33

68

02

37

41

55

17

00

40

.00

14

28

5

Yr 1

30

27

73

67

04

36

98

15

17

00

40

.00

14

71

9

Yr 1

40

63

73

72

86

37

92

35

17

00

40

.00

13

77

7

Yr 1

52

79

73

23

75

46

38

55

75

17

00

40

.00

13

14

3

Yr 1

60

53

83

97

05

40

24

35

17

00

40

.00

11

45

7

Yr 1

70

93

63

73

45

38

28

15

17

00

40

.00

13

41

9

Yr 1

80

12

16

35

78

93

70

05

51

70

04

0.0

01

46

95

Yr 1

90

10

58

18

29

81

93

56

18

87

11

4.6

0-4

86

RE

S.V

ALU

E-5

04

7-5

04

70

05

04

7

78

54

26

07

26

88

97

47

73

58

99

14

72

67

05

14

11

37

IRR

21.3

3%

NP

V a

t12%

(Rs. C

rore

)193.4

9

Co

st o

f pro

ductio

n d

isco

unte

d @

12%

(Rs./tn

.)1222.1

4

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

54

RP

R F

OR

AM

AD

AN

D O

C P

RO

JE

CT

[4.0

0 M

ty]

AP

P-D

.2

Ca

sh

flow

sta

tem

en

t at 8

5 %

ca

pa

city

& D

CF

Co

st / tn

. @ d

iffere

nt ra

tes

Op

tion

-II(Ou

tso

urc

e)

Rs. in

Lakhs.

YE

AR

Incre

me

nta

l R

ep

l. R

EV

. T

ota

l S

ale

s P

rod

. N

et

Ca

pita

l C

ap

. E

xp

. O

utflo

w R

ece

ipt

lakh te

. F

low

Exp

.

(1)

(2)

(3)

(4)

(5)

(6)

(7)

(8)

Ne

tblo

ck a

s o

n

31

.03

.15

24

81

00

24

81

00

-24

81

Yr 1

51

20

01

83

82

23

50

22

25

00

17

.00

-10

02

Yr 2

11

57

80

30

22

14

17

99

33

74

92

5.5

0-8

05

0

Yr 3

22

24

50

36

74

75

89

92

44

99

93

4.0

0-1

39

93

Yr 4

24

45

80

37

72

96

21

87

44

99

93

4.0

0-1

71

88

Yr 5

12

10

22

77

38

67

85

10

58

43

94

53

4.0

0-7

11

3

Yr 6

06

37

35

63

93

62

76

43

94

53

4.0

07

66

9

Yr 7

07

32

31

35

83

20

90

43

94

53

4.0

01

18

55

Yr 8

02

87

31

69

03

19

77

43

94

53

4.0

01

19

68

Yr 9

05

28

32

25

93

27

87

43

94

53

4.0

01

11

58

Yr 1

02

79

12

96

32

32

43

39

00

43

94

53

4.0

01

00

45

Yr 1

10

13

55

32

37

53

37

30

43

94

53

4.0

01

02

15

Yr 1

20

61

33

22

75

32

88

84

39

45

34

.00

11

05

7

Yr 1

30

27

73

22

00

32

47

74

39

45

34

.00

11

46

8

Yr 1

40

63

73

27

03

33

34

04

39

45

34

.00

10

60

5

Yr 1

52

79

73

23

29

35

33

94

54

39

45

34

.00

10

00

0

Yr 1

60

53

83

47

80

35

31

84

39

45

34

.00

86

27

Yr 1

70

93

63

27

83

33

71

94

39

45

34

.00

10

22

6

Yr 1

80

12

16

31

47

13

26

87

43

94

53

4.0

01

12

58

Yr 1

90

10

58

16

59

01

76

48

16

04

01

2.4

1-1

60

8

RE

S.V

ALU

E-5

04

7-5

04

70

50

47

78

54

26

07

26

03

14

06

87

75

57

77

51

75

98

.91

89

76

2

IRR

13.5

5%

NP

V a

t12%

(Rs. C

rore

)33.2

5

Co

st o

f pro

ductio

n d

isco

unte

d @

12%

(Rs./tn

.)1287.1

8

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

55

Ca

pa

city100%

RP

R F

OR

AM

AD

AN

D O

C P

RO

JE

CT

[4.0

0 M

ty]

AP

P-E

.1

Re

venue

exp

end

iture sta

tem

ent a

t 10

0 %

cap

acity

Op

tion-II(O

utsource

)R

s.lakhs

Ye

ar

M.C

los

ure

OB

O/S

Co

st

Co

al o

/s

Co

st

OB

RE

H

CO

ST

Int o

n w

/c

@T

ota

l

OB

CO

AL

CO

MN

TO

TA

LFix

ed

var.

TO

TA

LFix

ed

var.

TO

TA

LFix

ed

var.

26.8

452.5

369.8

140.0

0TO

TA

LF

ixed

14.5

0%

Re

v.E

xp

.

11

86

14

41

12

12

17

41

42

20

31

22

71

71

57

14

81

46

16

19

10

81

61

39

63

20

01

28

12

89

74

21

13

4

22

31

18

91

40

23

69

52

09

34

86

66

65

00

16

73

58

29

56

36

50

19

38

92

09

44

40

01

92

19

21

60

83

48

75

33

50

35

11

47

75

25

03

38

49

12

98

57

39

24

66

70

48

61

85

68

32

75

99

27

92

02

56

25

61

95

34

23

67

43

50

35

11

47

75

48

74

80

50

07

12

98

97

43

25

10

70

74

63

24

71

72

75

99

27

92

02

56

25

62

00

14

33

98

53

50

35

11

47

75

56

55

27

50

39

18

99

14

24

47

51

29

49

28

36

67

53

27

59

92

79

20

25

62

56

20

46

44

38

2

63

50

35

11

47

74

86

24

67

43

95

18

99

14

24

47

51

29

59

29

36

67

90

24

85

72

79

20

25

62

56

18

82

40

81

0

73

50

35

11

47

74

18

04

67

37

14

18

99

14

24

47

51

29

69

30

36

68

30

20

68

62

79

20

25

62

56

16

49

35

76

6

83

50

35

11

47

74

22

64

67

37

59

18

99

14

24

47

51

29

69

30

36

68

71

20

96

52

79

20

25

62

56

16

67

36

15

0

93

50

35

11

47

74

30

84

67

38

41

18

99

14

24

47

51

29

69

30

36

69

15

21

46

92

79

20

25

62

56

16

97

36

81

0

10

35

03

51

14

77

43

15

47

03

84

51

89

91

42

44

75

12

97

93

03

67

96

12

14

80

27

92

02

56

25

61

70

03

68

78

11

35

03

51

14

77

43

15

47

03

84

51

89

91

42

44

75

12

97

93

03

67

10

09

21

48

02

79

20

25

62

56

17

03

36

92

9

12

35

03

51

14

77

42

91

47

03

82

11

89

91

42

44

75

12

97

93

03

67

10

59

21

33

22

79

20

25

62

56

16

97

36

80

2

13

35

03

51

14

77

42

71

47

03

80

11

89

91

42

44

75

12

97

93

03

67

11

12

21

20

62

79

20

25

62

56

16

92

36

70

4

14

35

03

51

14

77

43

13

47

03

84

31

89

91

42

44

75

12

97

93

03

67

11

68

21

46

42

79

22

00

25

62

56

17

19

37

28

6

15

35

03

51

14

77

43

44

47

33

87

11

89

91

42

44

75

12

99

93

13

68

12

26

21

62

12

79

22

00

25

62

56

17

31

37

54

6

16

35

03

51

14

77

46

25

47

34

15

11

89

91

42

44

75

12

99

93

13

68

12

87

23

33

92

79

22

00

25

62

56

18

31

39

70

5

17

35

03

51

14

77

43

00

47

33

82

61

89

91

42

44

75

12

99

93

13

68

13

52

21

34

82

79

22

00

25

62

56

17

22

37

34

5

18

35

03

51

14

77

40

82

47

33

60

81

89

91

42

44

75

12

99

93

13

68

14

19

20

01

42

79

22

00

25

62

56

16

50

35

78

9

19

35

03

51

14

77

20

01

47

31

52

81

89

91

42

44

75

12

99

93

13

68

14

90

72

75

10

19

20

09

39

38

44

18

29

8

Ad

mn

. Ex

pe

nce

sW

ag

es

ST

OR

ES

Mis

c. E

xp

en

ce

sP

OW

ER

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

56

Ca

pa

city

85

%R

PR

FO

R A

MA

DA

ND

OC

PR

OJ

EC

T [4

.00

Mty

]

Re

venue

exp

end

iture sta

tem

ent a

t 85

% ca

pa

cityA

PP

-E.2

Op

tion

-II(Ou

tso

urc

e)

M.C

lo

su

re

OB

O/S

Co

st

Co

al

o/s

Co

st

OB

RE

H

CO

ST

Int o

n w

/c

@T

ota

l

Ye

ar

OB

CO

AL

CO

MN

TO

TA

LFix

ed

var.

TO

TA

LFix

ed

var.

TO

TA

LFix

ed

var.

TO

TA

LFix

ed

14.5

0%

Rev.E

xp.

11

86

14

41

12

11

86

91

42

17

26

.72

19

17

14

81

47

14

61

61

99

19

41

18

72

72

01

28

12

88

47

18

38

2

22

31

18

91

40

23

17

22

09

29

63

.46

41

50

01

42

34

92

95

54

65

01

64

80

17

80

37

40

19

21

92

13

93

30

22

1

33

50

35

11

47

74

51

33

38

41

75

.59

48

73

92

09

64

34

86

15

76

83

23

45

92

37

40

25

62

56

16

94

36

74

7

43

50

35

11

47

74

73

64

80

42

56

.11

24

99

74

27

61

02

17

46

27

57

17

23

45

92

37

40

25

62

56

17

40

37

72

9

53

50

35

11

47

74

81

05

27

42

82

.81

82

71

42

44

03

12

39

92

83

11

75

32

34

59

23

74

02

56

25

61

78

33

86

78

63

50

35

11

47

74

20

24

67

37

35

.61

82

71

42

44

03

12

40

92

93

11

79

02

11

29

23

74

02

56

25

61

64

33

56

39

73

50

35

11

47

73

62

34

67

31

56

.61

82

71

42

44

03

12

41

93

03

11

83

01

75

83

23

74

02

56

25

61

44

63

13

58

83

50

35

11

47

73

66

24

67

31

95

.21

82

71

42

44

03

12

41

93

03

11

87

11

78

20

23

74

02

56

25

61

46

13

16

90

93

50

35

11

47

73

73

24

67

32

65

.21

82

71

42

44

03

12

41

93

03

11

91

51

82

49

23

74

02

56

25

61

48

73

22

59

10

35

03

51

14

77

37

39

47

03

26

8.6

18

27

14

24

40

31

24

29

30

31

29

61

18

25

82

37

40

25

62

56

14

90

32

32

4

11

35

03

51

14

77

37

39

47

03

26

8.6

18

27

14

24

40

31

24

29

30

31

21

00

91

82

58

23

74

02

56

25

61

49

33

23

75

12

35

03

51

14

77

37

18

47

03

24

8.2

18

27

14

24

40

31

24

29

30

31

21

05

91

81

33

23

74

02

56

25

61

48

83

22

75

13

35

03

51

14

77

37

01

47

03

23

0.7

18

27

14

24

40

31

24

29

30

31

21

11

21

80

25

23

74

02

56

25

61

48

53

22

00

14

35

03

51

14

77

37

37

47

03

26

6.4

18

27

14

24

40

31

24

29

30

31

21

16

81

82

44

23

74

17

02

56

25

61

50

83

27

03

15

35

03

51

14

77

37

64

47

33

29

0.1

18

27

14

24

40

31

24

49

31

31

31

22

61

83

78

23

74

17

02

56

25

61

51

83

29

35

16

35

03

51

14

77

40

02

47

33

52

8.6

18

27

14

24

40

31

24

49

31

31

31

28

71

98

38

23

74

17

02

56

25

61

60

43

47

80

17

35

03

51

14

77

37

26

47

33

25

2.2

18

27

14

24

40

31

24

49

31

31

31

35

21

81

46

23

74

17

02

56

25

61

51

13

27

83

18

35

03

51

14

77

35

40

47

33

06

71

82

71

42

44

03

12

44

93

13

13

14

19

17

01

22

37

41

70

25

62

56

14

51

31

47

1

19

35

03

51

14

77

17

72

47

31

29

8.4

18

27

14

24

40

31

24

49

31

31

31

49

06

18

48

66

17

09

39

37

65

16

59

0

Wa

ge

sS

TO

RE

SP

OW

ER

Mis

c. E

xp

en

ce

sA

dm

n. E

xp

en

ce

s

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

57

A

PP

EN

DIX

-F

(Ou

tso

urc

ing

Op

tion

)

S.N

.P

AR

TIC

UL

AR

SN

UM

BE

R

1.

CO

ST

OF

RE

HA

BIL

ITA

TIO

N

i)T

ota

l No

. of fa

milie

s lik

ely

to b

e re

ha

bilita

ted

11

00

CA

PIT

AL

ES

TIM

AT

E

Am

t. Rs

.in L

ak

hs

A.

Fo

r qua

rry a

s re

co

mm

end

ed

in P

R

a)

To

tal h

om

este

ad

11

00

. Co

mp

ensa

tion fo

r 11

00

no

s. o

f ho

me

ste

ad

@ R

s.

3,0

0,0

00

/-*(5

0%

will b

e g

ive

n c

ash c

om

pe

nsa

tion)

16

50

.00

(giv

en in

Ap

pe

nd

ix A

-8.1

)

b)

La

nd

for R

&R

site

for 1

10

0 h

om

e s

tea

d e

tc (5

0.7

98

Ha

). 5

07

.98

c)

Co

mp

ensa

tion to

50

% la

nd

ouste

es in

lieu o

f no

t pro

vid

ing

job

.Fo

r ad

ditio

na

l

Te

na

ncy la

nd

to b

e a

cq

uire

d 6

10

.84

Ha

and

ca

sh c

om

pe

nsa

tion g

ive

n fo

r

30

5.4

2 H

a la

nd

@ R

s. 5

,00

,00

0/- p

er A

cre

for 3

05

.42

Ha

La

nd

37

71

.91

(Ap

p.-A

.8.1

)

d)

Sub

sis

tence

Allo

wa

nce

@R

s 2

40

pe

r da

y fo

r 25

da

ys in

a m

onth

for 1

10

0

ho

me

ste

ad

for o

ne

ye

ar

79

2.0

0

e)

De

ve

lop

me

nt o

f reha

bilita

tion c

olo

ny fo

r tota

l 11

00

ho

me

ste

ad

inclu

din

g

scho

ol, h

osp

itals

, roa

d e

tc.

11

00

.00

(Ap

pe

nd

ix-A

.8.1

)

Su

b-to

tal o

f (1)

78

21

.89

No

te: C

onsid

erin

50

% la

nd

ouste

es w

ill be

pro

vid

ed

job

and

50

% w

ill be

giv

en c

ash c

om

pe

nsa

tion in

lieu o

f Jo

b.

RE

VIS

ED

PR

OJ

EC

T R

EP

OR

T F

OR

AM

AD

AN

D O

PE

NC

AS

T P

RO

JE

CT

(4.0

Mty

)

Sta

tem

en

t sh

ow

ing

the

es

tima

ted

ca

pita

l re

qu

ire

me

nt fo

r E

nv

iro

nm

en

tal

Pro

tec

tion

Me

as

ure

s.

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

58

AP

PE

ND

IX-F

(CO

NT

D.)

Am

t.Rs.in

La

khs

S.N

.P

AR

TIC

UL

AR

SA

MO

UN

T

2C

AP

ITA

L F

OR

RE

ST

OR

AT

ION

aH

ousin

g fo

r Re

cla

ma

tion p

ers

onne

l 1

7.5

7

(Ap

pe

nd

ix-A

.2.2

)

bP

iezo

me

ters

for m

ea

surin

g w

ate

r leve

l (6 N

os)

20

.00

c

Hyd

rog

eo

log

ica

l stu

dy in

clu

din

g d

rilling

, stu

dy e

tc.

(Ap

p. - A

.8.1

)3

5.0

0

dS

cie

ntific

stu

dy lik

e s

lop

e s

tab

ility s

tud

y fo

r inte

rna

l & e

xte

rna

l OB

dum

p,

mo

nito

ring

and

oth

er s

tud

y e

tc.

20

.00

eG

ree

n b

elt fe

ncin

g 1

5m

wid

th a

long

sa

fety

zo

ne

of th

e P

roje

ct (a

pp

rox.1

2.0

km

)

6.4

2

Su

b-T

ota

l (2)

98

.99

3.

CA

PIT

AL

FO

R A

NT

I-PO

LL

UT

ION

ME

AS

UR

E

IN M

INE

& IN

DU

ST

RIA

L A

RE

A

aS

ettlin

g ta

nk fo

r min

e w

ate

r dis

po

sa

l4

0.0

0

(Ap

pe

nd

ix-A

.8.3

.(A)

cO

the

r de

ve

lop

me

nt m

ea

sure

s in

ind

ustria

l

site

viz

. dra

ins &

tree

gua

rds e

tc.

85

.73

(Ap

pe

nd

ix-A

.8.2

)

dO

il & G

rea

se

Tra

p (A

pp

end

ice

s A

.2.1

)5

.00

dG

arla

nd

dra

ins (A

pp

end

ix-A

.8.1

)5

00

.00

eA

rbo

ricultu

re/p

lanta

tion in

ind

ustria

l

are

a (A

pp

end

ix-A

.8.1

.)2

.50

fD

ust s

up

pre

ssio

n a

t Min

e,C

HP

(Ap

pe

nd

ix-A

.3.5

,A.3

.6 )

15

5.0

0

gD

ust s

up

pre

ssio

n a

t Sid

ing

(Ap

pe

nd

ix-A

5)

10

.00

hS

lop

e S

tab

ility R

ad

de

r7

00

.00

Su

b-T

ota

l(3)

14

98

.23

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

59

AP

PE

ND

IX-F

(CO

NT

D.)

Am

t.Rs.in

La

khs

S.N

.P

AR

TIC

UL

AR

SA

MO

UN

T

4.

EN

VIR

ON

ME

NT

AL

CO

NT

RO

L M

EA

SU

RE

S IN

TO

WN

SH

IP

aS

ew

era

ge

dis

po

sa

l in c

olo

ny(A

pp

end

ix-A

.8.3

(A)

29

.63

bS

torm

wa

ter d

rain

s &

culv

erts

(Ap

pe

nd

ix-A

.8.2

)8.4

3

cA

bo

ricultu

re/p

lanta

tion (A

pp

end

ix-A

.8.1

)2

.50

dO

the

r de

ve

lop

me

nt m

ea

sure

s in

tow

nship

to1

0.3

6

imp

rove

cle

anlin

ess &

ae

sth

etic

s p

ark

s-p

lay-

gro

und

s &

tree

gua

rds (A

pp

-A.8

.2)

eS

eve

rag

e T

rea

tme

nt P

lant (A

pp

end

ice

s A

8.3

(A)

40

0.0

0

fL

and

de

ve

lop

me

nt &

Ho

rticultu

re(A

pp

A2

2)

23

.00

gR

ain

Wa

ter H

arv

estin

g (A

pp

A2

2)

6.0

0

Su

b T

ota

l (4)

47

9.9

2

5.

Ste

ps fo

r Pre

ve

ntio

n o

f Po

ssib

le2

00

.00

min

e in

und

atio

n(E

mb

ankm

ents

) (Ap

p.-A

.8.1

)

6.

Co

st o

f EM

P p

rep

ara

tion(A

pp

end

ix-A

.8.4

)5

0.0

0

7.

Co

mm

unity

de

ve

lop

me

nt in

surro

und

ing

50

.00

villa

ge

s (A

pp

end

ix-A

.8.1

)

To

tal c

ap

ital fr

om

1 to

71

01

99

.03

B.

Diffe

re

nt ty

pe

of R

ev

en

ue

na

ture

co

st to

be

co

ns

ide

re

d

in

co

st o

f pro

du

ctio

n p

er to

nn

e o

f Co

al:

-

1.

La

nd

recla

ma

tion/re

sto

ratio

n

@1

.25

lakhs/H

a fo

r technic

al a

nd

bio

log

ica

l 9

4.9

3

& H

yd

ro s

ee

de

r for re

cla

ma

tion (la

khs/a

nnum

)

2.

Enviro

nm

ent A

ud

it @ 0

.60

lakhs/a

nnum

0.6

0

3.

Enviro

nm

ent m

onito

ring

@8

.00

lakhs/a

nnum

10

.00

4M

onito

ring

of la

nd

use

thro

ug

h s

ate

llite s

urv

eilla

nce

lakhs/a

nnum

8.0

0

5M

ine

Clo

sure

Co

st la

khs/a

nnum

61

8.9

7

6M

onito

ring

of C

SR

and

RR

pla

n la

khs/a

nnum

2.0

0

To

tal R

ev

en

ue

na

ture

co

st p

er a

nn

um

73

4.5

0

R.P

.R fo

r Am

ada

nd O

CP

(4.0

0 M

ty), U

pdate

d’ J

uly

2015

CM

PD

I

Job N

o.5

15

126 T

ota

l Outs

ourc

ing

Optio

n

Pa

ge-X

60

R

PR

FO

R A

MA

DA

ND

OC

PR

OJ

EC

T [4

.00

Mty

]

Op

tion

-II(Ou

tso

urc

e)

Re

pla

ce

me

nt S

ch

ed

ule

Ye

ar

12

34

56

78

91

01

11

21

31

41

51

61

71

81

9

To

tal

277

637

732

287

528

1296

1355

613

277

637

732

538

936

1216

1058

YEA

R R

IPP

ER

AT

TA

CH

MEN

T

Unit p

rice

44.0

01

23

45

67

89

10

11

12

13

14

15

16

17

18

19

INV

ST.

Targ

et+

Addl.

no

11

Life

94

4

REPLA

CEM

EN

Tn

o1

Am

t.4

4

DEPR

.

YEA

RO

ther H

EM

MU

nit p

rice

11

23

45

67

89

10

11

12

13

14

15

16

17

18

19

INV

ST.

Targ

et+

Addl.

no

2555

47

36

55

39

34

76

27

92

79

Life

18

47

36

55

39

34

76

27

92

79

REPLA

CEM

EN

Tn

o

Am

t.

DEPR

.6

19

34

93

97

15

57

8

YEA

Rch

p 1

8 y

rs life

Unit p

rice

1.0

01

23

45

67

89

10

11

12

13

14

15

16

17

18

19

INV

ST.

Targ

et+

Addl.

no

26117

44

55

86

88

10

17

52

79

9

Life

18

44

55

86

88

10

17

52

79

9

REPLA

CEM

EN

Tn

o

Am

t.

DEPR

.8

20

59

04

42

33

3

YEA

Rch

p 3

yrs

lifeU

nit p

rice

11

23

45

67

89

10

11

12

13

14

15

16

17

18

19

INV

ST.

Targ

et+

Addl.

no

1933

27

76

37

73

22

87

Life

32

77

63

77

32

28

7

REPLA

CEM

EN

Tn

o2

77

63

77

32

28

72

77

63

77

32

28

72

77

63

77

32

28

72

77

63

77

32

Am

t.2

77

63

77

32

28

72

77

63

77

32

28

72

77

63

77

32

28

72

77

63

77

32

DEPR

.4

25

24

4

YEA

Rch

p 7

yrs

life1

12

34

56

78

91

01

11

21

31

41

51

61

71

81

9

INV

ST.

1815

25

16

59

57

93

26

Life

72

51

65

95

79

32

6

25

16

59

57

93

26

25

16

59

57

93

26

REPL.

Am

t.2

51

65

95

79

32

62

51

65

95

79

32

6

DEPR

.1

43

28

21

65

47

ANNEXURES

P a g e - A n 1 |

P a g e - A n 2 |

P a g e - A n 3 |

P a g e - A n 4 |

P a g e - A n 5 |

P a g e - A n 6 |

P a g e - A n 7 |

P a g e - A n 8 |

P a g e - A n 9 |

P a g e - A n 10 |

Pa

ge

-A

n 11

|

A

NN

EX

UR

E-V

I

P

RO

JE

CT

RE

PO

RT

FO

R A

MA

DA

ND

OC

P (4

.00

Mty

)

L

ist o

f Exis

ting H

EM

M a

s o

n 3

1.0

3.2

01

5

SL

.No

. P

AR

TIC

UL

AR

S

CA

PA

CIT

Y

No

of

HE

MM

T

OT

AL

T

O B

E R

ET

AIN

ED

IN

PR

OJ

EC

T

TO

BE

TR

AN

SF

ER

RE

D

Gro

ss B

lock

as o

n

31.0

3.2

015

No

s

Gro

ss

Blo

ck a

s

on

31.0

3.2

015

Net B

lock

as

31.0

3.2

015

No

s

Gro

ss B

lock

as o

n

31.0

3.2

015

Net B

lock

as

31.0

3.2

015

cap

ital in

L

akh

s

cap

ital in

L

akh

s

1

EL

E. R

OP

E

SH

OV

EL

4,6

/5.0

CuM

4

1132

.83

4

1132

.83

949.0

9

2

EL

E. H

YD

S

HO

VE

L

4/4

.2 C

uM

1

718.5

8

1

718.5

8

503.9

5

3

RE

AR

DU

MP

ER

35T

21

2781

.35

21

2781

.35

1241

.59

4

RB

H D

RIL

L

250 M

M

3

536.7

7

3

536.7

7

215.2

5

5

RB

H D

RIL

L

160 M

M

3

163.4

8

3

163.4

8

8.1

7

6

DO

ZE

R

420/3

20 H

P

7

975.7

8

7

975.7

8

377.7

2

7

DO

ZE

R

320 H

P

1

144.7

8

144.7

8

40.4

4

8

Gra

der

280 H

P

191.4

2

191.4

2

145.3

2

9

Cra

ne

8-1

0 T

1

7.8

5

1

7.8

5

5.7

3

10

C

rane

30/6

0T

2

306.5

8

2

306.5

8

232.9

4

11

F

EL

0.9

-1.3

Cu

M

1

24.3

1

24.3

0

17.9

9

12

W

ate

r Sprin

kle

r 20 K

L

1

74.7

6

1

74.7

6

3.7

4

A

mo

un

t in L

akh

s.

7058

.48

443.1

1

213.2

2

6615

.37

3528

.71

Note

1: P

art o

f the

ab

ove ta

bula

ted

HE

MM

are

pro

pose

d to

be d

ep

loyed in

Am

ada

nd O

CP

as s

ho

wn a

bo

ve a

s 'T

o b

e R

eta

ine

d in

pro

ject". T

he lis

t of H

EM

M to

be d

ep

loyed in

Am

adand O

CP

als

o p

rovid

ed in

AP

P. A

31. It is

pro

posed a

ll oth

er e

xis

ting H

EM

M th

at a

re s

ho

wn a

s "T

o b

e T

ransfe

rred"

may e

ither b

e s

urv

eyed

-off a

nd n

ot to

be re

pla

ced

or tra

nsfe

red to

oth

er m

ine fo

r gain

ful u

tilisatio

n.

Note

2 : A

s o

n 3

1.0

3.2

015

, Net b

lock o

f HE

MM

to b

e tra

nfe

red is

Rs 3

55

1.7

6 L

akhs. N

et b

lock o

f Am

adand O

C c

onsid

ere

d fo

r pro

ject c

ostin

g =

Rs

(6009.9

1-3

528.7

1) L

akhs =

248

1.2

0 L

akhs

P a g e - A n 12 |

ANNEXURE VII

P a g e - A n 13 |

ANNEXURE VIII

P a g e - A n 14 |

ANNEXURE - IX

NOTE ON RPR FOR AMADAND OCP (4.00Mty)

REVISED FINANCIAL PARAMETERS AS PER REVISED COSTING NORMS OF CIL

The revised project report for Amadand OCP (Capacity 4.00 Mty) has been presented in the

65thth meeting of TSC of SECL Board on 31st July, 2015. The RPR for Amadand OCP had

been recommended by TSC on 31-07-2015 for a capital investment of Rs. 869.44 Crores to

put up before SECL Board for approval.

Meanwhile after the TSC meeting, new guideline issued by 317th CIL board held on 4th

July,2015 regarding cost provisioning in project report of CIL projects has been received. The

financial parameters of RPR has been reworked considering the new guidelines.

The Revised Financial Parameters are as tabulated below

Sl.No. Particular Base RPR As per Revised

Costing Norms

1 Mineable coal Mt. (as on 01.04.2015) 70.46 70.46

2 OB Mm3 (as on 01.04.2015) 764.40 764.40

3 SR m3 / t 10.85 10.85

4 Quality, GCV G-8, 4933 G-8, 4933

5 Initial Capital (Rs.Crore ) 869.44 869.44

6 Capital for Land (Rs.Crore ) 183.91 183.91

7 Capital for R&R (Rs.Crore ) 78.22 78.22

8 CPT (Rs./ t) @100% 1074.40 1113.69

9 Selling Price (Rs./ t) 1298.22 1298.22

10 Profit (Rs./ t) 223.82 184.53

11 IRR @ 85% (%) 13.55 16.18

The above table shows that the reworked Financial Parameter are showing better results

than the Financial Parameter submitted in the RPR for consideration.

P a g e - A n 15 |

A tentative exercise to work out IRR with different rates of Tenancy land (with revised norms

of cost provisioning in RPR) has also been done and tabulated as below:-

Sl

No. Rate of Tenancy land

IRR (%)

@ 100% Capacity @ 85% Capacity

1. @ 25 lakhs/ha 24.66 16.18

2. @ 30 lakhs/ha 22.99 15.08

3. @ 35 lakhs/ha 21.52 14.07

4. @ 40 lakhs/ha 20.20 13.15

P a g e - A n 16 |

ANNEXURE X

PLAN

IN FIGURE

FIG - 1

: LOC

ATIO

N P

LAN

AM

RITDH

ARA

N

OC PRO

JECT

AM

ADAN

D

OC PRO

JECT

FIG - 2

: FINA

L STAG

E QU

AR

RY

PLA

N

FIG - 3

: FINA

L STAG

E DU

MP

PLA

N


Recommended