AMATHOLE DISTRICT MUNICIPALITY
To : The Municipal Manager
Date : 27 October 2015
Subject : Report on Performance Information Management
PERFORMANCE INFORMATION RESULTS
JULY - SEPTEMBER
FIRST QUARTER PERFORMANCE REPORT FOR 2015/2016
FINANCIAL YEAR
2 | P a g e
Contents
1. INTRODUCTION ............................................................................................................................................. 3
2. STRATEGIC (INSTITUTIONAL / ORGANISATIONAL) LEVEL LINKED TO THE IDP ..................................................................... 3
3. EARLY WARNING MECHANISMS .......................................................................................................................... 3
3.1 DEPARTMENTAL REVIEWS (MONTHLY) .............................................................................................................. 3
3.2 MUNICIPAL MANAGERS REVIEWS (QUARTERLY) ................................................................................................... 3
3.3 MANAGEMENT TEAM REVIEWS ....................................................................................................................... 3
3.4 EXCO REVIEWS ........................................................................................................................................ 4
4. CONCLUSION ........................................................................................................................................ 23
3 | P a g e
1. Introduction
Section 39 of the Municipal Systems Act 32 of 2000 requires municipalities to manage the development of the municipality’s Performance Management System (PMS); assign responsibilities in this regard to the Municipal Manager and submit the proposed system to the Municipal Council for adoption. Amathole District Municipality (ADM) Performance Management Framework was first adopted in 2001 and has since been reviewed yearly as part of the IDP Review process.
2. Strategic (Institutional / Organisational) Level linked to the IDP
It is important at the Municipality, that the Council and management should have access to the appropriate information for considering and making timeous interventions to uphold or improve the capacity of its delivery systems. The performance of any municipality as a service delivery mechanism is fundamentally determined by factors enabling it to perform its Constitutional and statutory mandates. It is important that these causal and contributory factors for performance excellence at the municipality be measured to determine performance gaps timeously with the objective to respond with appropriate remedial interventions.
At a strategic level the five-year IDP of a municipality forms the basis for performance management, whilst at operational level it is the annual SDBIP. The IDP is a long-term plan and by its nature the performance measures associated with it will have a long-term focus, measuring whether a municipality is achieving its IDP objectives.
3. Early warning mechanisms
One of the key functions of a PMS is to serve as an early warning system to indicate so-called “gaps” in the levels of service delivery to the community. It is therefore imperative that the processes of regular monitoring, measurements and reviews are executed, to timeously identify those areas within which performance levels are to be found below satisfactory.
Reporting and review process is listed below:
3.1 Departmental Reviews (Monthly)
It is intended that departments review their performance at least monthly. Decision-makers should be immediately warned of any emerging failures to service delivery such that they can intervene if necessary. It is important that departments use these reviews as an opportunity for reflection on their goals and programmes and whether these are being achieved.
3.2 Municipal Managers Reviews (Quarterly)
Departments will then need to report on their performance in the required format to the municipal manager. Additional indicators that occur in the strategic and operational plans will also be reviewed. The formulation of a strategic scorecard and the process of review will be co-ordinated by the Performance Management team. The Municipal Manager’s Review Panel will need to reflect on whether targets are being achieved, what are the reasons for targets not being achieved where applicable and corrective action that may be necessary.
3.3 Management Team Reviews
Each portfolio committee will be required to review the performance of their respective services against their service scorecard. The portfolio committee should appraise the performance of the service against committed targets. Where targets are not being met, portfolio committees should ensure that the reasons for poor performance are satisfactory and sufficient, and the corrective strategies proposed are sufficient to address the reasons for poor performance.
4 | P a g e
3.4 EXCO Reviews
On a quarterly basis, the Executive Mayoral Committee should engage in an intensive review of municipal performance against both the service scorecards and the strategic scorecard, as reported by the municipal manager.
Many of the indicators in the strategic scorecard will only be measurable on an annual basis. The quarterly reviews should thus culminate in a comprehensive annual review of performance in terms of both scorecards. The review should reflect on the performance of services and the strategic scorecard. The Executive Committee will need to ensure that targets committed to in the strategic scorecard are being met, where they are not, that satisfactory and sufficient reasons are provided and that the corrective action being proposed is sufficient to address the reasons for poor performance. The review should also focus on reviewing the systematic compliance to the performance management system, by departments, portfolio committees and the Municipal Manager.
3.5 Council and Community Oversight (Through Rep Forum Meetings)
The cycle of performance management requires Council and community oversight in each of the stages of the cycle. Oversight is exercised in the interests of society in general and should ensure that the considerable powers that government executives and administrations assume are monitored to avoid abuse and under-performance.
It is important to note that reporting on performance as provided for in the framework will not in itself enable Councillors to fully exercise their internal oversight role effectively. Not everything a Department does would be reflected in quarterly performance reports or lends itself to review through key performance indicators and targets. In addition to the required performance reports; monthly progress reports are submitted to the relevant Portfolio Committee of Council dealing with the broader activities of each Department during the preceding month.
Below is the performance report for the month starting from July to September 2015
5 | P a g e
SUMMARY OF ORGANISATIONAL PERFORMANCE FOR QUARTER 1 (TOP LAY SDBIP 2015/16)
KEY PERFORMANCE AREAS Outstanding Performance
(5)
Performance Significantly
above expectation
(4)
Fully Effective
(3)
Performance Not fully
Effective (2)
Unacceptable Performance(1)
Not Applicable
TOTAL
Municipal Transformation and Organisational/Institutional Development
2 0 3 0 0 1 6
Good Governance and Public Participation 0 2 18 0 0 0 20
Municipal Financial Viability 4 1 8 0 0 1 14
Local Economic Development 2 1 12 0 0 0 15
Basic Service Delivery 1 5 7 0 1 1 15
TOTAL 9 9 48 0 1 3 70
6 | P a g e
Detailed Performance Results INDI REF
IDP REF
INDICATOR TARGET REASONS/EVIDENCE SCORE REMEDIAL ACTIONS DEPARTMENT
KPI 1
MTI 1/1
Turnaround time in filling all vacant and budgeted posts
3 months turnaround time in filling all vacant and budgeted posts
A request for condoning reporting on this target
for the entire year has been approved. This
target has been affected by the decision taken by
the EMC to place a moratorium on all recruitment
processes due to limited funding for vacancies.
The target is therefore condoned as not
applicable for reporting.
N/A None- as the target is not
applicable
Corp Serv
KPI 2
MTI 1/2
Percentage increase in female representation in line with the Employment Equity Plan
Progress report on the appointment of females by each department
Progress report on the appointment of females by each department is submitted showing 5 percent increase by quarter 1 which is above the annual target. A copy of new engagements is submitted.
5 None- Target met Corp Serv
KPI 3
MTI 1/3
Percentage Increase of Disabled employees employed in line with the Employment Equity Plan targets
Progress report on the appointment of disabled employees by each department
Progress report on the appointment of disabled employees by each department is submitted showing 3 percent increase by quarter 1 which is above the annual target. A copy of new engagements is submitted.
5 None- Target met Corp Serv
KPI 4
MTI 2/1
Implemented Information kiosk and Management tools as per ICT Master Plan
Appointment of 3 Service providers
Signed quarterly report on the activities undertaken by information management unit and appointment letters of MLG group (Pty)Ltd for supply, delivery and installation of 8 freestanding information kiosk units dated 22/09/15, First technology for Solar winds module for Log analyser purposes dated 04/09/13 and Dimension data (Pty)Ltd dated 30/09/15 are provided
3 None- Target met STRAT
7 | P a g e
KPI 5
MTI 3/1
No. of Quarterly organisational performance assessment reports
Q4 2014/15 Performance Assessment report
Q4 performance report, HOD’s review minutes and attendance register dated 23/07/15 are provided
3
None- Target met STRAT
KPI 6
MTI 3/2
No. of Quarterly Individual performance assessment reports
Q4 2014/15 Individual Performance Assessment report 2014/15
Quarterly report on activities undertaken, Q4 consolidated institutional individual assessment, departmental checklist together with certificates of assurance
3 None- Target met STRAT
KPI 7
SDI 1/1
No. of households with new water connection
969 Households with new water connections
The Completion Certificate for 3 service providers for households water connections are submitted all together proving 1008 households connected within quarter 1 of 2015/16. Expenditure report is also submitted.
4 None- Target met ENG
KPI 8
SDI 1/2
No. of dams and Waste Water Treatment Works refurbished as per the Refurbishment Plan
Appointment of 3 Service Providers and compile a progress report on Dutywa dam
A progress report on refurbishment of Dutywa dam is submitted with a service provider`s progress report. Also an appointment letter dated 30/09/2015 for the service provider Ceenex Ltd on the refurbishment of Waste Water Treatment Works is availed.
3 None- Target met ENG
KPI 9
SDI 1/3
No of Households provided with interim water supply
112 Household provided with interim water supply
A signed confirmation letter reflecting 137 households benefitting from interim water supply is submitted together with expenditure report
4 None- Target met ENG
KPI 10
SDI 1/4
Percentage of indigent House Hold with access to free basic potable water
100 percent of indigent Households with access to free basic potable water
Indigent report on subsidy paid is submitted together with lists of registered indigents during the quarter.
3 None- Target met BTO
KPI 11
SDI 1/5
Percentage reduction of water losses within the district
Appointment of a service provider
A copy of the signed contract for the appointment of a service provider is submitted to.
3 None- Target met ENG
8 | P a g e
KPI 12
SDI 1/6
No of drinking water samples taken to determine compliance with SANS 241
380 drinking water samples tested
Amatola water report is submitted with 502 drinking water samples tested, confirmed through recalculation by PME unit. A signed quarterly report on drinking water quality and expenditure report are submitted.
5 None- Target met Comm Serv
KPI 13
SDI 2/1
No of household supplied with new VIP Toilets
2000 household supplied with new VIP Toilets
A request for condoning reporting on this target in Q1 and Q2 has been approved. The current predicament of shortage of funds in the institution led to a decision taken to suspend the sanitation projects. As soon as the cashflow situation normalizes suspended projects will continue. The target is therefore condoned as not applicable for reporting.
N/A
None- as the target is not applicable
ENG
KPI 14
SDI 2/2
No. of waste water samples taken to determine compliance with General Authorisation Standards
47 waste water samples tested
Amatola waste water report is submitted with 51 waste water samples confirmed after recalculation by PME unit. A signed quarterly report on drinking water quality and expenditure report are also submitted.
4 None- Target met Comm Serv
KPI 15
SDI 3/1
No. of Local Municipalities with business licences registration forms complying with MHS legislation
Progress report on 3 Local Municipalities license registration complying with Municipal Health Services requirement
Progress report on 4 Local Municipalities license registration complying with Municipal Health Services requirement. Attendance registers are submitted for sessions held in Great Kei, Nkonkobe, Amahlathi, Ngqushwa on 22/07/2015, 26/08/2015, 01/09/2015, and 28/09/2015 respectively.
4 None- Target met Comm Serv
KPI 16
SDI 4/1
No. of fire safety and emergency facilities constructed
Appointment of a Contractor
Target is not met. The variance report states that the contractor could not be appointed as the matter of gaining access through neighbouring sites is still pending. Also a Memo to the Municipal Manager motivating the application of co-use of the area restricted to Eskom for the ADM to have access and contruct Butterworth fire station and Mquma training centre.
1 The contractor will be appointed once the access to the neighbouring sites is obtained
ENG
9 | P a g e
KPI 17
SDI 4/2
No. of fire safety compliance inspections undertaken
17 fire compliance inspections undertaken
23 Fire compliance inspections were undertaken this quarter. Reports indicating compliance and non-compliance are submitted.
4 None- Target met Comm Serv
KPI 18
SDI 5/1
No. of Local Municipalities provided with Disaster relief material
Delivery of Relief material in Mbhashe Mnquma Ngqushwa and Nkonkobe
A signed quarterly report on delivery of relief material in Mbhashe, Mnquma Ngqushwa and Nkonkobe is submitted with delivery notes.
3 None- Target met
Comm Serv
KPI 19
SDI 6/1
Phase 2 of solid waste transfer stations built in Amahlathi
Appointment of a Service Provider
A copy of the signed contract of Appointment for the Service Provider MattMacDonald PDNA is submitted and dated 30/09/2015
3 None- Target met ENG
KPI 20
SDI 7/1
No.of Public Transport facilities upgraded
Appointment of 2 Contractors
A signed quarterly report is submitted stating the renewal of existing contractors which are available on site for, IDutywa public transport facility and Willowvale Public Transport facilities.
3 None- Target met ENG
KPI 21
SDI 8/1
No. of Preliminary design reports developed for Settlements
Appointment of 5 Service Providers
A copy of the signed contract of Appointment for the Service Provider Iliso Consulting is submitted and dated 30/09/2015 covering all 5 projects.
3 None- Target met ENG
KPI 22
LED 1/1
No. of AREDS construction projects implemented in Alice
Quarterly progress report on the Construction of (Pedestrian bridge CBD Upgrade and Transport hub facilities in Alice
Quarterly report from ASPIRE on the construction of pedestrian bridge and CBD upgrade in Nkonkobe, minutes of the site meetings held in July, Aug and Sept together with the expenditure report.
3 None- Target met
LHSED
10 | P a g e
KPI 23
LED 1/2
No. of Tourism events supported as per Tourism master plan
Progress report on Tourism development Tourism marketing and promotion craft development tourism trade shows and exhibitions
Quarterly report on the provision of Tourism development support: (a) 1 LTO in Ngqushwa to participate in the Gauteng Gataway Show with attendance register dated 28-30/08/15, (b) attendance register of 3 tour guides that participated in the ADM Mayors challenge held on the 23-26/09/15, 2 tourism grading certificates for Mantsundu and Primestone B&B, attendance registers of the VIC's for Nkonkobe LM, Amahlathi LM, Mnquma LM, Nxuba LM, Great Kei LM and Mbhashe for July and Aug, (c) report on the participation and support towards wild coast jikeleza, Grahamstown national arts festival X-mas in July, attendance register for GANF, XMAS, WCJF dated 6-12/07/15, 24-26/07/15 and 07-10/08/15, (d) report on the development of needs analysis for craft development, needs analysis template, minutes of the meeting and attendance register dated 11/08/15
3 None- Target met LHSED
KPI 24
LED 1/3
No of film makers supported in 3 Local Municipalities
Identification of beneficiaries in Mnquma Nxuba and Amahlathi
Quarterly report on the profiled beneficiaries for film development equipment, profiling forms for the 3 beneficiaries in Nxuba, Amahlathi and Mnquma, attendance register for profiling meeting of 3 ADM emerging film makers dated 06/08/15 and the minutes of the meeting held for profiling dated 06/08/15 together with the expenditure report
3
None- Target met LHSED
11 | P a g e
KPI 25
LED 1/4
No. of Heritage management plan projects implemented
Progress report on Early African intellectuals legacy Support towards Commercialisation of heritage resources and Armed Struggle History
Summation report on implementation of 4 heritage projects: a) Early African Intellectuals conference, agenda, attendance register and minutes of PSC meeting dated 23/07/15, programme and attendance register of the conference - Nongqawuse and the Xhosa cattle killing episode dated 03-04/09/15, b) Signed terms of reference for Commercialization of Heritage resources, (c) agenda, minutes and attendance register for conversation of Armed Struggle History dated 26/08/15 and d) agenda, minutes and attendance for district geographical name change committee meeting held on the 21/09/15
3 None- Target met LHSED
KPI 26
LED 1/5
No. of Agricultural development plan programmes implemented
Progress report on implementation of Input Supply Livestock improvement Emerging farmers support Sorghum and Macadamia production
a) Progress report on input supply programme, list of beneficiaries, profiling forms, attendance register for discussion of MOA and signing of project profiling dated 02/09/15, profiling of vegetables seedlings dated 03/09/15, b) progress report on implementation of livestock improvement programme: profiling forms, attendance registers for community profiling, list of beneficiaries and acknowledgement of receipt, c) progress report on implementation of emerging farmers support programme, profiling forms, attendance registers for profiling, 1st quarter ADM agricultural stakeholders forum dated 23/09/15, d) progress report on implementation of Sorghum production, profiling forms, attendance registers and acknowledgement of receipt and e) progress report on the implementation of Macadamia production, terms of reference for Macadamia production, attendance register dated 27/07/15, 26/08/15 and 28/08/15
3
None- Target met
LHSED
12 | P a g e
KPI 27
LED 1/6
Developed feasibility study on the establishment of the abattoir submitted to Council
Appointment of a Service provider
Quarterly report on the development of feasibility study for an abattoir and appointment letter of Urban-fun development economists to conduct an Abattoir feasibility study dated 09/09/15
3 None- Target met LHSED
KPI 28
LED 1/7
No. of infrastructure rural development projects implemented
Progress report on the Infrastructural projects implemented
progress report on implementation of rural development programme, appointment letter of Tsaba (Pty)Ltd for supply and delivery of boundry fencing materials for Ngqushwa dated 14/09/15, profiling forms and attendance register for profiling dated 13/09/15 and expenditure report provided, quarterly report on the development of needs analysis for furnishing of Bawa falls and expenditure report
3 None- Target met
LHSED
13 | P a g e
KPI 29
LED 1/8
No. of Environmental management plan programs implemented
Progress report on the implementation of the Biosphere Renewable energy Air quality Climate change Blue Flag and Awareness programme
Quarterly progress report on the implementation of environmental projects: (a) report on the Amathole mountain biosphere reserve and attendance register of the meeting dated 17/08/15, (b) progress report on implementation of renewable energy where social facilitation has been conducted in Phandulwazi agricultural high in Nkonkobe LM, Baxton SPS in Nxuba LM and Byletts combined high school in Great Kei, site identification attendance register dated 31/07/15, attendance register for installation of Biogas digester plenary meeting dated 01/09/15, (c) report on implementation of integrated air quality management plan, appointment letter of CBM consulting Eng dated23/09/15 for supply and delivery of standard PM.2.5 minivol Tas portable air sample, (d) progress report on implementation of climate change adaptation programme, attendance register for site visit in Mbashe LM dated 13/08/15, (e) report on the implementation of the integrated environmental management plan , expenditure report, water testing results , proof of application submission, attendance register and programme held in Ngqushwa dated 23/09/15 and (f) progress report on the Arbour week celebration, attendance register for arbour week celebrations in Nxuba dated 11/09/15, 10/09/15, 02/09/15, 06/08/15 and minutes and attendance register of the environmental forum dated 17/09/15
3
None- Target met
LHSED
14 | P a g e
KPI 30
LED 1/9
No. of Cooperatives supported within the district
Develop a Quarterly Progress report on the implementation of 3 Cooperatives projects (Annual cooperative Indaba Co-ops support Cooperative Development Centre)
Summation report on implementation of 3 programs: (a) quarterly report on stakeholder engagement meeting held in Amahlathi LM, attendance refgister dated 01/09/15, (b) need analysis conduction, list of the cooperatives to be supported, cooperative site visit form, attendance register for needs analysis conduction dated 20/08/15, (c) appointment letter of Azile financial services for development of Baseline study for Co-operatives dated 23/09/15 and expenditure reports provided
3 None- Target met LHSED
KPI 31
LED
1/10
Percentage of SMME that have benefited from an SMME support program within the district
10 percent of SMMEs that have benefited from an SMME support program within the district
Quarterly report on the SMME's that have been supported, awarded register for SMME’s for the quarter under review, expenditure report of the supported and database SMME list: total number of database 764 and 131 SMME’s have been supported(764/131=17%) making it 17% SMME’s supported
5 None- Target met LHSED
15 | P a g e
KPI 32
LED 1/11
No. of Enterprises supported as per development strategy
Progress report on Implementation of three (3) Enterprise Development Projects ( SMME support Informal trade and Business Support structures)
Summation report on the implementation of 3 enterprise development projects: (a) progress report on support provided to 2 fashion designers, attendance register for grahamstown arts festival dated 01-05/07/15, (b) report on the informal traders with hawker inputs, appointment letter of Slwane for supply and delivery of working material for informal traders in Ngqushwa dated 23/09/15, minutes, attendance register of the business forum meeting held on the 28/07/15, (c) report on hosting of 1 business forum for the enterprise development unit, attendance register for 1 business forum in Nxuba dated 30/09/15, and additional capacity building for women dated 26/08/15 and attendance register of forum client capacitation dated 06/08/15
4 None- Target met
LHSED
KPI 33
LED 1/12
No. of jobs created using EPWP programme
Identification of 3500 beneficiaries for EPWP programme
Signed quarterly report on the lists of identified beneficiaries for EPWP programme, list of identified beneficiaries from Nxuba, Great Kei, Mbhashe, Amahlathi, Nkonkobe and Ngqushwa totalling up to 3500 beneficiaries identified are provided
3 None- Target met LHSED
KPI 34
LED 1
No of jobs created by ASPIRE using EPWP programme
Progress reports on removal of invasive alien vegetation
Signed quarterly report on the activities undertaken by ASPIRE, site meeting minutes for July, August and September, environmental audit checklist for the construction activities for July, Aug and Sept, expenditure report for Aug and Sept
3 None- Target met LHSED
16 | P a g e
KPI 35
LED 1/13
No. of informal traders supported in creative and beauty industry
Develop needs analysis report on Informal Traders to be supported
Report on informal trade needs analysis, Amahlathi hawkers needs, Great Kei informal trade needs, Amahlathi informal traders commodity group database and Nxuba LM informal traders needs are provided
3 None- Target met LHSED
KPI 36
LED 1/14
No. of candidates participating in the intership programme created through HRD strategy
Enrolment of 70 interns The report is submitted on interns enrolled as follows: 2 under National Treasury funded programme, 1 under LGSETA, 35 under Discretionary Grant funding and 69 under Expanded Public Works Programme. The list of interns is also submitted.
5 None- Target met Corp Serv
KPI 37
MFV 1/1
Financial viability expressed by Debt Coverage ratio
2 Copy of 4th quarter Financial dashboard is submitted
3 None- Target met BTO
KPI 38
MFV 1/2
Financial viability expressed by Outstanding service debtors to revenue ratio
346 percent Copy of 4th quarter Financial dashboard is submitted
3 None- Target met BTO
KPI 39
MFV 1/3
Financial viability expressed by Cost Coverage ratio
1 Copy of 4th quarter Financial dashboard is submitted
3 None- Target met BTO
KPI 40
MFV 1/4
Percentage billing of billable metered households
98 percent reading on billable meters
1. BP421 Report is submitted with a summary showing 98 percent billable meters
3 None- Target met BTO
KPI 41
MFV 1/5
Percentage budget spent on MIG funding
Spending on MIG funded budget not less than 100 percent
A signed quarterly report on spending on MIG funded is R 214 071 752 and therefore 189%
5 None- Target met ENG
17 | P a g e
KPI 42
MFV1 Percentage budget spent on MSIG funding
Appointment of service provider
Progress report of spending of MSIG and appointment letters of DL & associates and Zuzisa consulting for implementation of data alignment and cleansing for Ngqushwa LM and data integration and implementation of revenue enhancement strategy for Nkonkobe LM both dated 30/09/15
3
None- Target met STRAT
KPI 43
MFV 1/7
Percentage of invoices paid within 30 days of receipt
100 percent of Invoices paid within 30 days of receipt
A request for condoning reporting on this target in Q1 and Q2 has been approved. The current financial situation wherein there is a cash-flow predicament due to funds utilized on MIG projects whilst waiting for NT allocation, is causing delays in payment of invoices. The target is therefore condoned as not applicable for reporting.
N/A None- as the target is not applicable
BTO
KPI 44
MFV 1
Percent budget spent on implementing Workplace Skills Plan
15 percent spent on the WSP Budget allocated to ADM
A quarterly report is availed on 26% spent on the WSP Budget allocated to ADM. An expenditure report is also submitted
4 None- Target met Corp Serv
KPI 45
MFV 1/9
Percentage collected on outstanding debts per debtor category (A B and C)
20 percent collected on outstanding debts per debtor category (A B and C)
Quarterly report on debt collection with supporting evidence and Financial system report is submitted showing 47% of outstanding debt collected.
5
None- Target met BTO
KPI 46
MFV 1/10
Percentage Collected on leased ADM Buildings
100 percent Collected on leased ADM Buildings
Receipts of amounts collected from ADM leased buildings is submitted to PME proving that all amounts were received and some tenants have paid in advance.
3 None- Target met Corp Serv
KPI 47
MFV 1/11
Percentage collected on billed Municipal fire services
80 percent collected on billed Municipal fire services
A report on 95 percent collected on billed Municipal fire services is submitted together with receipts documents form the clients.
5 None- Target met BTO
18 | P a g e
KPI 48
MFV 1/12
Percentage Updated and accurate Move -able Asset Register with additions and disposals
100 percent Updated and accurate Move -able Asset Register with addittions and disposals
Copy of the Asset register dated 30/09/2015 is submitted. Financial Systems report for additions and disposals is also submitted.
3 None- Target met BTO
KPI 49
MFV 1/13
Percentage of infrastructure assets layout plans developed
Appointment of service provider and 10 percent Infrastructure Assets Layout Plans developed
1. Copy of signed memo of deviation by the Municipal Manager for the re-appointment of A2A Kopano currently appointed to provide services the ADM 2. Copies of developed Layout plans Service provider report dated 25/09/2015 are submitted
3 None- Target met ENG
KPI 50
MFV 1/14
Percentage reduction in the number of deviations
Reduction in number of deviations by 1 percent
Signed quarterly report on deviations is submitted stating 5.3 percent deviations. Also a deviations register and Proof of submission to Council dated 21/08/2015 is submitted
5 None- Target met BTO
KPI 51
GGP 1/1
Percentage Implementation of Internal Audit action plans submitted to EMC
Progress report on Implementation of Internal Audit action plans submitted to EMC
Signed quarterly report on the activities undertaken, Internal audit tracking document, and the EMC agenda dated 28/09/15 are provided
3 None- Target met STRAT
KPI 52
GGP 1/2
Percentage Implementation of Auditor General action plans submitted to EMC
Percentage implementation of Auditor General action plans submitted to EMC
Signed quarterly report submitted to EMC on the 14/15 AG findings raised is availed accompanied by a copy of action plans/ Dashboard with the status of actions. A proof of submission submitted is dated 28/09/2015
3 None- Target met
BTO
19 | P a g e
KPI 53
GGP 1/3
No. of Activities implemented as per Risk Master Plan
Implement 4 activities as per the Risk Master Plan
Approved implementation plan dated 10/09/15, minutes and attendance register of the risk and audit committee dated 21/07/15, 06/08/15, screen shots from Barn owl system, institutional strategic risk register, departmental risk registers, agenda for risk and IT steering committee date 27/07/15 are provided
3 None- Target met STRAT
KPI 54
GGP 1/4
Financial statements compliant with MFMA and GRAP submitted to Auditor-General by 31st August annually
Develop AFS and consolidated AFS (Aspire) and submit to AG and PT
The documents are submitted to PME : Copies of signed June 2014/15 AFS submitted to the office of AG and PT, Copies of consolidated signed 2014/15 AFS submitted to the office of AG and PT Copies of acknowledgement from AG and PT ,and Copies of consolidated acknowledgement from AG and PT
3 None- Target met BTO
KPI 55
GGP 1/5
Annual Report with Financial statements submitted to Auditor-General and Council
Develop draft unaudited Annual Report submitted to AG and PT
Consolidated draft 14/15 unaudited annual report, proof of submission, acknowledgement of receipt from PT and proof of submission to AG dated 31/08/15 are provided
3 None- Target met STRAT
KPI 56
GGP 1/6
Monthly budget statement and Mid-year budget assessment reports submitted to Mayor Provincial & National Treasuries
3 monthly reports on S71 reporting submitted within 10 working days after the end of the month to the Executive Mayor Provincial Treasury and National Treasury
Copies of the quarterly reports and proof of submission to Executive Mayor, National and Provincial Treasury are submitted together with a Municipal Managers Quality certificate.
3 None- Target met BTO
KPI 57
GGP 1/7
Percentage of Council resolutions implemented annually
Quarterly progress report on the Council resolutions implemented
Signed quarterly report on the implementation of the ADM Council resolutions for May, June and July together with the tracking document on the implementation
3 None- Target met
LESS
20 | P a g e
KPI 58
GGP 1/8
Turn-around time taken in handling grievances lodged
3 months taken in handling disciplinary hearings
The report on disciplinary hearings is submitted. Together with the list register of disciplinary hearings and the register of grievances.
3 None- Target met Corp Serv
KPI 59
GGP 2/1
Integrated Development Plan submitted to Council for approval
District IDP Framework and IDP Process Plan submitted to Council
16/17 IDP and Budget process plan and district framework and Council minutes dated 21/08/15 and the expenditure report are provided
3 None- Target met STRAT
KPI 60
GGP 2/2
Budget & Adjustment budget submitted to Council for approval
Budget Process Plan submitted to Council
Signed quarterly report with a copy of Budget Process Plan for 2015/16 and council agenda dated 21/08/2015 are submitted.
3 None- Target met BTO
KPI 61
GGP 2/3
Developed ADM Long term Vision submitted to Council for approval
Appointment of a Service Provider
Quarterly report and appointment letter for PDT management consulting dated 30/09/15 to conduct a comprehensive situational analysis report for ADM are provided
3 None- Target met STRAT
KPI 62
GGP 2/4
No. of Municipalities with functional IGR structures
Coordination of IGR forum meetings in Mbhashe and Ngqushwa
Quarterly report on the functionality of the IGR structures and attendance registers for IGR forum meetings at Mbhashe LM and Ngqushwa LM dated 08/10/15 as stated in the report that it was postponed from the initial date and 09/09/15
3 None- Target met STRAT
KPI 63
GGP 3/1
No. of designated groups capacitated on socio political issues as per Special Programs Strategy
Conduct Capacity building for women in 1 LM
Signed quarterly report indicates 2 capacity building conducted for women, attendance registers for women in business in Mbhashe LM dated 31/08/15, Nkonkobe LM dated 26/08/15 and women’s day event dated 28/08/15 together with the expenditure reports are provided
4 None- Target met LESS
KPI 64
GGP 4/1
No. of Quarterly municipal support reports submitted to EMC
1 Quarterly municipal support report submitted to EMC
Quarterly report on the support provided by line departments to local municipalities and proof of submission to EMC date 28/09/15 are provided
3 None- Target met STRAT
21 | P a g e
KPI 65
GGP 5/1
Turnaround time for registering complaints and forwarded to the relevant departments and acknowledgement to clients
3 working days for registering complaints forwarded to relevant departments and acknowledgement to clients
Signed quarterly report on the activities undertaken by communication and customer care unit, issues handling report for the LM’s, acknowledgement and referrals to relevant departments with 3 working days are provided
3 None- Target met STRAT
KPI 66
GGP 5/2
Conduct Customer satisfaction survey
Appointment of a Service Provider
Signed quarterly report on activities undertaken by communication and customer care and appointment letter of Core Function Concepts dated 30/09/15 for customer survey for ADM
3 None- Target met STRAT
KPI 67
GGP 5/3
No. of communication programmes conducted
Appointment of a Service Provider
Signed quarterly report on the activities undertaken by communications unit, appointment letter of The Big Concept Company dated 23/09/15 for the Procurement of services for the Video production events of ADM
3 None- Target met STRAT
KPI 68
GGP 6/1
Turnaround time taken to respond to Petitions received from customers
30 working days for responding to Petitions received from the communities
Signed quarterly report on the petitions received for 14/15 financial year, list of received queries and letters of response are provided
3 None- Target met LESS
KPI 69
GGP 6/2
No. of programmes implemented as per Public Participation and Petition Framework Policy
Mayoral Outreach Signed quarterly report on the 2 mayoral outreach programmes held, attendance registers for Ngqushwa and Nxuba LM dated 20/08/15 and 18/08/15 together with the expenditure report have been provided
4 None- Target met LESS
KPI 70
GGP 7/1
No. of reports on the nature of punitive measures taken on By law infringements
Develop a quarterly report on notices issued and documents for any punitive measures taken
A quarterly report on notices issued and documents for any punitive measures taken is submitted. Also copies of notices issued and documents on punitive measures taken
3 None- Target met Comm Serv
22 | P a g e
SUMMARY OF DEPARTMENTAL PERFORMANCE FOR QUARTER 1 (BOTTOM LAYER SDBIP 2015/16)
DEPARTMENTS Outstanding Performance
(5)
Performance Significantly
above expectation
(4)
Fully Effective
(3)
Performance Not fully
Effective (2)
Unacceptable Performance(1)
Not Applicable
TOTAL
Community Services 3 7 9 0 0 0 19
Corporate Services 4 1 15 0 0 1 21
Engineering 1 1 19 1 1 1 24
Budget and Treasury 2 2 17 2 0 1 24
LHSED 1 1 23 0 0 1 26
LESS 0 6 11 0 0 0 17
Strategic planning and management 3 6 33 0 0 0 42
TOTAL 12 25 128 3 1 4 173
23 | P a g e
4. CONCLUSION The Institution performed very well this quarter when looking at the number of targets that are not achieved. Out of 70 KPIs set in the Institutional SDBIP (Top Layer) only 1 target was not achieved. Furthermore, the departments’ performance has significantly improved as compared to 2014/15 Quarter 1 performance results. Out of 132 KPIs set in the 14/15 SDBIP, 30 targets were not achieved in the first quarter, whereas in 2015/16 only 4 target were not achieved out of 173 Departmental (Bottom Layer) KPIs. There are 3 KPIs not applicable for reporting this quarter. These have been condoned due to financial problems affecting the institution currently. These will be resumed once the cash-flow situation is addressed. This report will be presented in the next Performance Audit Committee meeting.