+ All Categories
Home > Documents > AME POWER PLANT REFERENCES

AME POWER PLANT REFERENCES

Date post: 15-Feb-2017
Category:
Upload: carlo-avanzini
View: 87 times
Download: 0 times
Share this document with a friend
26
ISSUE 2006
Transcript
Page 1: AME POWER PLANT REFERENCES

ISSUE 2006

Page 2: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016

SUMMARY OF MAJOR INTERVENTIONS ON DESIGN AND SUPERVISION OF POWER PLANTS

It has been followed by interventions of different complexity, at Unimar TPP inAmbarli (TR); Bandirma Natural Gas Combined Cycle Power Plant, 936.5 MW (TR);Aliağa Thermal Power Plant, 350 MW (TR); Mesaieed (Qatar) ; Bekirli Coal-firedThermal Power Plant - 2x600 MW (TR); Al-Khalij Thermal Power Plant, 4x350 MW(Libya); El Ain El Sokhna Supercritical Thermal PP - 2x650 MW (Egypt); SamsunCombined Cycle Power Plant, 870 MW (TR); Atlas Iskenderun Coal-fired Thermal PowerPlant - 2x600 MW

Apart earlier interventions on the design of marine pipelines and intake structures, a “full immersion” in the power plant sealine design and supervision started with the Sugözü - 2x605 MW Power Plant in Turkey

The presentation does not include all other sealine projects, ie. outfalls, pipelines for desalination plants and collateral activities, which are covered by a more general presentation of Avanzini Middle East.

Page 3: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016

SUGÖZÜ POWER PLANT - İSKEN İSKENDERUN ENERJI ÜRETIM VE TICARET A.Ş. - 2 X 605 MW TURKEY, 2000

Sealine data: Intake: GRP, 4 x ND2800, length 415m with 4 separate concrete intake structures Discharge: GRP, 4 x ND2400, length 1280m , 4 diffusers with 3 ports each

CONTRACTING: SIEMENS – GAMA - TEKFEN

Page 4: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016

Main tasks have been: assessment/revision of the base

design prepared by Siemens of the intake and discharge sealines

evaluation, design and specifications for GRP (FW continuous mandrel type) -assistance in the qualification of the supplier and control and testing of the pipe production

Executive design and specifications for the sealines and coastal scour protection

Design of the intake structures and of the flexible connection to the pipelines

part time supervision in assistance to the main contractor's team in the pipeline installation phase

[SÜGÖZU 2]

Page 5: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016

Phase 1 – at producer’s factory

Consultant for pipe qualification Supervision of production Witnessing of production tests Supervision of the production of fittings Supervision of shipments

Main Contractor : GAMA (TR)

Pipe Supplier : SUBOR (TR)

Onshore cooling water circuit, GRP ND 2500, length ≈6000m

AL-KHALIJ THERMAL POWER PLANTGECOL - GENERAL ELECTRICAL COMPANY

OF LIBYA 4x350 MW – LIBYA (2000-2001)

Page 6: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016

Phase 2 – in the field Supervision of pipe laminations and curing Assistance in verification of installation drawings Supervision of installation and backfilling Assistance to hydraulic testing

[AL KHALIJ 2]

Page 7: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016

Main Contractor : GAMA (TR)Pipe Supplier : AMITECH SPAIN (ES) Marine Contractor Geocean FR

AL-KHALIJ THERMAL POWER PLANT SEALINES

Observation of installation during the presence on site

Page 8: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016

AMBARLI, UNIMAR THERMAL P0WER PLANT (2005)

Construction of new tapered diffuser, removal of the existing one and connection of the new one to the main line.

Contractor: STFA (TR)

The need of the substitution of the original diffuser with a new one to be connected to the main GRP pipeline ND2500 was originated by updated thermal discharge requirements

While the construction of the new diffuser on piling did not present in itself particular problems, the removal of the old from the main line and the connetion of the new was “space and time limited”

Page 9: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016

It was requested to perform the connection respecting the existing alignment and executing the intervention in less than 12 hours to ovoid the interruption of the production.

The SOW was the study, together with the client’s and contractors engineering team, of the necessary connection tolerances and of the pipe spools and accessories to compensate such tri-dimensional tolerances

A combination of GRP short spools and of tailor-made steel bolted Compression Couplings, designed with ±200 mm longitudinal insertion tolerance and ± 3° allowable angular deflection has been used to compensate the installation misalignment.

The arrangement permitted the realization of the tie-in in ≈8 hrs, practically without disturbance to the TPP operation.

[UNIMAR 2]

Page 10: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016

MESAIEED A (QATAR) 2009LAND SECTION OF INTAKE LINE GRP ND 1800

ND 1800, 6 km long intake line on land under water table level

The request of expertise had two main aspects. The first was the peer-review of the main calculation

aspects, i.e. hydraulics, deflection, ovalization etc. and the analysis of the possible tolerances.

The second aspect was the analysis of the leaks which appeared after backfill and of their repair with internal lamination using a technique and

materials proposed by the pipe supplier.

With a few exceptions, all measured data of gap, deflection and ovalization were well within the design limits.

In a dewatered pipe, the system is acceptable and has proven leakproof.

Page 11: AME POWER PLANT REFERENCES

BANDIRMA NATURAL GAS CCTPENERJISA ENERJI ÜRETIM A.Ş 1 x 936.5 MW – TR (2010)

Cooling water GRP pipelines – 2 x 2200 intake lines 200m long to -23 m depth and 1 x 2400 outfall 350m long with diffuser at -29m depth.

CONTRACTING: ATEC (AUSTRIA)

SOWAnalysis of the contractor’s design of a twin intake pipelines and related offshore intake structures, and of the discharge line and diffuserPeer-Review of the executive design executed by the marine contractor

POWER PLANT PRESENTATION 2016

Analysis and control of the diffuser installation in soft bottom area

Page 12: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016

After start-up: evaluation of the reasons of the displacement and disconnection of the discharge pipe on the slope, study of the stabilization and assistance in the repairs of pipeline.

[BANDIRMA 2]

Page 13: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016

BEKİRLİ COAL-FIRED THERMAL POWER PLANT –İÇDAŞ ELEKTRİK ENERJİSİ ÜRETİM ve YATIRIM A.Ş. 2 X 600 MW – TR (2010)

GRP ND 3500, 450 mm long intake line with a 90m semi-buried diffuser at -35m

The SOW included several stages• The coordination and assistance in the field to the

surveyor and assistance in the reporting• Hydraulic and diffuser calculations and outline

design • Preparation of the documents for the Ministerial

approval

• Analysis of the seismic profiles to define the safest route and choice of

the centre line

Page 14: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016

After the choice, it was studied a safe stabilization system along the 27% slope.

The risk was not only the sliding downwards of the pipe, but also the eventual settlement.

The solution was found by using 6 lateral marine lugs and pipes with anti-sliding ribs.The upper bend was connected with a steel compression coupling permitting a ±3° angular deflection and the lower one was anchored by a thrust block.

[BEKIRLI 2]

Page 15: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016

GRP 3 x ND 3000, 2 x 1280 + 1 x 1350 mm long

EL AIN EL SOKHNA SUPERCRITICAL THERMAL PP EAST DELTA ELECTRICITY PRODUCTION Co - 2X650 MW – EGYPT

Phase 1 – at FPI Factory in Cairo Consultant for pipe qualification Supervision of production Witnessing of production tests Supervision of the production of fittings, chlorination pipes and of the double chamber manholes

Main Contractor : ORASCOM-BESIXPipe Supplier : FUTURE PIPE INDUSTRY EgyptSupervision requested by PGESCo -Egypt

Control of shipments

Page 16: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016[SOKHNA 2]

The second part of the SOW has been the peer review of the design “for construction”, the evaluation and assessment of the installation method, a part time installation control and the verification of the pipe joints .

Page 17: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016[SOKHNA 3]

The pipes were connected across the joint with marine lugs. Part of them were kept tight and part released after installation.A 16mm gap inside and a maximum 0.5° was specified at each joint by the client. However, the couplings tightness had been tested in the factorywith a 63mm gap and 1.2°at 9 bar without leaks.

The measure of gaps in different stages of installation brought to an animated discussion and to the definition of limits agreed between client, pipe producer and contractor and accepted by us.The study about the tolerances was the most interesting part of the supervision.

The values of gaps in 4 points at each couplinghave been recorded immediately after each pipe’s installation and after the completion of 100-120m sections before the backfill. Only minor changes due to local settlements have been found and eventually corrected,

Page 18: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016

After the examination of the geometric parameters with the pipe supplier, it was presented to the client a revision of the acceptable values (after backfill) proposing 90 mm gap and 0,9°as “safe”. In theory, larger gaps could be exceptionally accepted, provided that the position of the gasket from the coupling edge was at least 25mm (defined as “gasket not visible”)

[SOKHNA 4]

It must be noted however that the value of tolerances depend from the diameter, the geometry of pipe spigot and of the double bell coupling.

The comparison of the values “before and after” demonstrated that with the enhanced safe value of the tolerances only 3% of the joints needed a repair, mostly due to the displacement of the gasket.

Page 19: AME POWER PLANT REFERENCES

ALIAĞA THERMAL POWER PLANT IZDEMIR ENERJI ELEKTRIK URETIM A.S. -350 MW – TR (2013)

SOWAssistance during the environmental studies and preliminary route choice assistance during the third-party executive design and peer-review of the issue for construction Part-time inspection of workmanship and supervision during installation

POWER PLANT PRESENTATION 2016

Construction of the 900m long HDPE ND 1200 intake line with GRP intake structure and of the 700m long discharge ND 900 with 90m diffuser

Page 20: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016

SAMSUN COMBINED CYCLE POWER PLANTOMV GAS & POWER - 870 MW – TR (2011)

Main Contractor: METKA – Power Project – Costantinidis (GR)Pipe Producer : SUBOR (TR)Intake Structures Producer : ARMAPLAST (TR)

GRP Pipelines 3 x ND 2400 x 860m intake lines with GRP intake

structures with OD 14m 2 x ND 3200 x 600m discharge lines with diffusers

SOW Peer review of the basic design and

hydraulic calculations Executive design and specifications Outline design of Intake Structure Installation tender specs

Page 21: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016[SAMSUN 2]

Design of the connection to the pump chamber and discharge pit with the use of steel compression couplings

Supervision to the pipe productionand testing

Page 22: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016[SAMSUN 3]

The 3 GRP intake structures have been stabilized after installation with grout poured inside the body

Page 23: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016

ISKENDERUN COAL-FIRED THERMAL POWER PLANT ATLAS POWER GENERATION INC.2 X 600 MW -TR (2014)

Pipe Producer : SUPERLIT (TR)

GRP, ND 4000, length 700 m discharge line with 4 parallel diffuser branches, each with 7 ports

Pipe supplied with Double Bell Couplings with full-face embedded gasket and rotating marine lugs

Page 24: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016

Discharge line 1 x ND 4000 with complex diffuser with 6 parallel ND 2300 branches, each with 7 ports

Page 25: AME POWER PLANT REFERENCES

POWER PLANT PRESENTATION 2016

Peer-review of the outline design, executive hydraulic and diffuser calculations, outline design, executive design for construction

KARABIGA COAL-FIRED THERMAL POWER PLANT CENAL ELECTRIC POWER GENERATION INC.2 X 660 MW -TR (2014)

Pipe Producer : SUBOR (TR)

GRP 3 x ND4000 Intake lines (lengths 630, 615, 600 m) each with a Ø18m intake structure

1 x ND3800 intake 485m long with Ø14,2 intake structure

3 x ND3800 discharge lines with multiport diffuser (length 920, 965, 1015 m)

Page 26: AME POWER PLANT REFERENCES

AVANZINI MIDDLE EAST FZEMarine pipeline design and consultingSaif Zone POBox 121256 SharjahMob. +971.50.9391572 (UAE) E-mail [email protected]

Independent Professional EngineerCemil Topuzlu Cad. Bal Apt. 26-134726 Ciftehavuzlar, Istanbul, TurkeyTel 0090.216.3692011 / Mob. 0090.542.3580445E-mail [email protected]

CV SUMMARY

Name Carlo Avanzini, Dr. Engr.Born Trieste ( Italy ) 31.10.1939Nationality ItalianDegree Naval Architecture,& Naval and Mechanical

Engineering, University of Genova,1963Languages Italian ( mother tongue), English (excellent,

written and spoken), German (fluent), French (fair), Spanish (fair), Turkish (elements)

Registrations Chamber of Engineers, Genova, Nr. 8679A

Personal specializations• Consulting, preliminary design, studies and investigations, Hydraulic studies on pipelines intake structures, design of land and marine pipelines (oil & gas, aqueducts, sewerage lines), outfalls and intake/discharge lines for cooling water systems and desalination plants

• Preparation of installation manuals; qualification and testing of tubular materials; engineering assistance in development and application of products for marine installation, qualification of marine Contractors• Preparation of specifications and contracts, project coordination and planning, project management, Executive engineering and design for construction, Construction , testing and commissioning supervision


Recommended