+ All Categories
Home > Documents > [American Society of Civil Engineers Proceedings of the Fourth International Conference on Grouting...

[American Society of Civil Engineers Proceedings of the Fourth International Conference on Grouting...

Date post: 04-Dec-2016
Category:
Upload: sam
View: 220 times
Download: 6 times
Share this document with a friend
8
Compaction Grouting - A Half-Century Review Sam Bandimere, Aff.M.ASCE 1 1 Grouting Consultant, Broomfield, CO. [email protected] INTRODUCTION It has been approximately 50 years since Jim Warner and Ed Graf started using low-mobility grouts for geotechnical grouting applications. The purpose of this paper will be to review technical advances and lessons learned over this period of time and the future possibilities for this ground treatment application. Compaction grouting is no different than any other technological discovery. When reviewed over time, there are a lot of advances made for numerous reasons. With proper research came a better understanding of the technical issues involved as the application relates to soil mechanics. Also, the technological advances of other issues such as equipment, instrumentation, computer monitoring, contractors’ experience, and most of all, case histories, played a major role in the advancements of the compaction grouting application. Ed Graf was the first to document the term of “Compaction Grouting” in describing the use of a “stiff” grout to densify soils, but Jim Warner was the one who took the compaction grouting spokesman’s position by publishing the most articles and technical papers over the years. Over-time, numerous spin-off applications have required the term “Low-Mobility Grout” be used to describe and measure the effectiveness of newer applications which will be mentioned later. A half century of compaction and low-mobility grouting applications have brought exciting opportunities to the future of ground treatment methods that have well-established engineering methodologies for pre- and post- construction applications. EQUIPMENT DEVELOPMENT When Jim Warner and Ed Graf developed the concept of pumping a very stiff grout for the purpose of densifying and/or stabilizing soils, it was a very controversial and unique approach to “Grouting.” Because both of them had to develop the technique over a period of time, there is really no definite date that can be attributed to the systems’ real start, but generally can be tied to documented projects as early as the mid-to-late 1950’s. Due to the fact that the approach was discovered and developed by two separate contractors at about the same time is a testament to the fact that the American free-enterprise system works best when there is a competitive spirit for the development of any new idea or approach to an established industries’ mode of operandi. 1664 Grouting and Deep Mixing 2012 Downloaded from ascelibrary.org by GEORGE MASON UNIVERSITY on 03/15/13. Copyright ASCE. For personal use only; all rights reserved.
Transcript
  • Compaction Grouting - A Half-Century Review

    Sam Bandimere, Aff.M.ASCE1

    1 Grouting Consultant, Broomfield, CO. [email protected]

    INTRODUCTION

    It has been approximately 50 years since Jim Warner and Ed Graf started using low-mobility grouts for geotechnical grouting applications. The purpose of this paper will be to review technical advances and lessons learned over this period of time and the future possibilities for this ground treatment application.

    Compaction grouting is no different than any other technological discovery. When reviewed over time, there are a lot of advances made for numerous reasons. With proper research came a better understanding of the technical issues involved as the application relates to soil mechanics. Also, the technological advances of other issues such as equipment, instrumentation, computer monitoring, contractors experience, and most of all, case histories, played a major role in the advancements of the compaction grouting application. Ed Graf was the first to document the term of Compaction Grouting in describing the use of a stiff grout to densify soils, but Jim Warner was the one who took the compaction grouting spokesmans position by publishing the most articles and technical papers over the years. Over-time, numerous spin-off applications have required the term Low-Mobility Grout be used to describe and measure the effectiveness of newer applications which will be mentioned later.

    A half century of compaction and low-mobility grouting applications have brought exciting opportunities to the future of ground treatment methods that have well-established engineering methodologies for pre- and post- construction applications.

    EQUIPMENT DEVELOPMENT

    When Jim Warner and Ed Graf developed the concept of pumping a very stiff grout for the purpose of densifying and/or stabilizing soils, it was a very controversial and unique approach to Grouting. Because both of them had to develop the technique over a period of time, there is really no definite date that can be attributed to the systems real start, but generally can be tied to documented projects as early as the mid-to-late 1950s. Due to the fact that the approach was discovered and developed by two separate contractors at about the same time is a testament to the fact that the American free-enterprise system works best when there is a competitive spirit for the development of any new idea or approach to an established industries mode of operandi.

    5

    9

    2

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    C

    y

    a

    n

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    2

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    M

    a

    g

    e

    n

    t

    a

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    2

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    Y

    e

    l

    l

    o

    w

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    2

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    B

    l

    a

    c

    k

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    1664

    Compaction Grouting - A Half-Century Review

    Sam Bandimere, Aff.M.ASCE1

    1 Grouting Consultant, Broomfield, CO. [email protected]

    INTRODUCTION

    It has been approximately 50 years since Jim Warner and Ed Graf started using low-mobility grouts for geotechnical grouting applications. The purpose of this paper will be to review technical advances and lessons learned over this period of time and the future possibilities for this ground treatment application.

    Compaction grouting is no different than any other technological discovery. When reviewed over time, there are a lot of advances made for numerous reasons. With proper research came a better understanding of the technical issues involved as the application relates to soil mechanics. Also, the technological advances of other issues such as equipment, instrumentation, computer monitoring, contractors experience, and most of all, case histories, played a major role in the advancements of the compaction grouting application. Ed Graf was the first to document the term of Compaction Grouting in describing the use of a stiff grout to densify soils, but Jim Warner was the one who took the compaction grouting spokesmans position by publishing the most articles and technical papers over the years. Over-time, numerous spin-off applications have required the term Low-Mobility Grout be used to describe and measure the effectiveness of newer applications which will be mentioned later.

    A half century of compaction and low-mobility grouting applications have brought exciting opportunities to the future of ground treatment methods that have well-established engineering methodologies for pre- and post- construction applications.

    EQUIPMENT DEVELOPMENT

    When Jim Warner and Ed Graf developed the concept of pumping a very stiff grout for the purpose of densifying and/or stabilizing soils, it was a very controversial and unique approach to Grouting. Because both of them had to develop the technique over a period of time, there is really no definite date that can be attributed to the systems real start, but generally can be tied to documented projects as early as the mid-to-late 1950s. Due to the fact that the approach was discovered and developed by two separate contractors at about the same time is a testament to the fact that the American free-enterprise system works best when there is a competitive spirit for the development of any new idea or approach to an established industries mode of operandi.

    5

    9

    2

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    C

    y

    a

    n

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    2

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    M

    a

    g

    e

    n

    t

    a

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    2

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    Y

    e

    l

    l

    o

    w

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    2

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    B

    l

    a

    c

    k

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    1664

    Compaction Grouting - A Half-Century Review

    Sam Bandimere, Aff.M.ASCE1

    1 Grouting Consultant, Broomfield, CO. [email protected]

    INTRODUCTION

    It has been approximately 50 years since Jim Warner and Ed Graf started using low-mobility grouts for geotechnical grouting applications. The purpose of this paper will be to review technical advances and lessons learned over this period of time and the future possibilities for this ground treatment application.

    Compaction grouting is no different than any other technological discovery. When reviewed over time, there are a lot of advances made for numerous reasons. With proper research came a better understanding of the technical issues involved as the application relates to soil mechanics. Also, the technological advances of other issues such as equipment, instrumentation, computer monitoring, contractors experience, and most of all, case histories, played a major role in the advancements of the compaction grouting application. Ed Graf was the first to document the term of Compaction Grouting in describing the use of a stiff grout to densify soils, but Jim Warner was the one who took the compaction grouting spokesmans position by publishing the most articles and technical papers over the years. Over-time, numerous spin-off applications have required the term Low-Mobility Grout be used to describe and measure the effectiveness of newer applications which will be mentioned later.

    A half century of compaction and low-mobility grouting applications have brought exciting opportunities to the future of ground treatment methods that have well-established engineering methodologies for pre- and post- construction applications.

    EQUIPMENT DEVELOPMENT

    When Jim Warner and Ed Graf developed the concept of pumping a very stiff grout for the purpose of densifying and/or stabilizing soils, it was a very controversial and unique approach to Grouting. Because both of them had to develop the technique over a period of time, there is really no definite date that can be attributed to the systems real start, but generally can be tied to documented projects as early as the mid-to-late 1950s. Due to the fact that the approach was discovered and developed by two separate contractors at about the same time is a testament to the fact that the American free-enterprise system works best when there is a competitive spirit for the development of any new idea or approach to an established industries mode of operandi.

    5

    9

    2

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    C

    y

    a

    n

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    2

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    M

    a

    g

    e

    n

    t

    a

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    2

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    Y

    e

    l

    l

    o

    w

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    2

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    B

    l

    a

    c

    k

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    1664

    Compaction Grouting - A Half-Century Review

    Sam Bandimere, Aff.M.ASCE1

    1 Grouting Consultant, Broomfield, CO. [email protected]

    INTRODUCTION

    It has been approximately 50 years since Jim Warner and Ed Graf started using low-mobility grouts for geotechnical grouting applications. The purpose of this paper will be to review technical advances and lessons learned over this period of time and the future possibilities for this ground treatment application.

    Compaction grouting is no different than any other technological discovery. When reviewed over time, there are a lot of advances made for numerous reasons. With proper research came a better understanding of the technical issues involved as the application relates to soil mechanics. Also, the technological advances of other issues such as equipment, instrumentation, computer monitoring, contractors experience, and most of all, case histories, played a major role in the advancements of the compaction grouting application. Ed Graf was the first to document the term of Compaction Grouting in describing the use of a stiff grout to densify soils, but Jim Warner was the one who took the compaction grouting spokesmans position by publishing the most articles and technical papers over the years. Over-time, numerous spin-off applications have required the term Low-Mobility Grout be used to describe and measure the effectiveness of newer applications which will be mentioned later.

    A half century of compaction and low-mobility grouting applications have brought exciting opportunities to the future of ground treatment methods that have well-established engineering methodologies for pre- and post- construction applications.

    EQUIPMENT DEVELOPMENT

    When Jim Warner and Ed Graf developed the concept of pumping a very stiff grout for the purpose of densifying and/or stabilizing soils, it was a very controversial and unique approach to Grouting. Because both of them had to develop the technique over a period of time, there is really no definite date that can be attributed to the systems real start, but generally can be tied to documented projects as early as the mid-to-late 1950s. Due to the fact that the approach was discovered and developed by two separate contractors at about the same time is a testament to the fact that the American free-enterprise system works best when there is a competitive spirit for the development of any new idea or approach to an established industries mode of operandi.

    5

    9

    2

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    C

    y

    a

    n

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    2

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    M

    a

    g

    e

    n

    t

    a

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    2

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    Y

    e

    l

    l

    o

    w

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    2

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    B

    l

    a

    c

    k

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    1664

    306B_PB_4out_Same_50836_ASCE_Final_Print.job_Process Cyan_08/01/2012_16:17:32306B_PB_4out_Same_50836_ASCE_Final_Print.job_Process Magenta_08/01/2012_16:17:32306B_PB_4out_Same_50836_ASCE_Final_Print.job_Process Yellow_08/01/2012_16:17:32306B_PB_4out_Same_50836_ASCE_Final_Print.job_Process Black_08/01/2012_16:17:32

    Grouting and Deep Mixing 2012

    D

    o

    w

    n

    l

    o

    a

    d

    e

    d

    f

    r

    o

    m

    a

    s

    c

    e

    l

    i

    b

    r

    a

    r

    y

    .

    o

    r

    g

    b

    y

    G

    E

    O

    R

    G

    E

    M

    A

    S

    O

    N

    U

    N

    I

    V

    E

    R

    S

    I

    T

    Y

    o

    n

    0

    3

    /

    1

    5

    /

    1

    3

    .

    C

    o

    p

    y

    r

    i

    g

    h

    t

    A

    S

    C

    E

    .

    F

    o

    r

    p

    e

    r

    s

    o

    n

    a

    l

    u

    s

    e

    o

    n

    l

    y

    ;

    a

    l

    l

    r

    i

    g

    h

    t

    s

    r

    e

    s

    e

    r

    v

    e

    d

    .

  • THE PAST

    Until the Compaction Grouting approach was conceived, the standard methods of grouting were to utilize fluid grouts that could penetrate cracks and/or permeate a medium such as soil or gravels. The unique approach of the Compaction Grouting method was that the grout did not penetrate nor permeate, but actually created an interface between it and the medium being treated, thereby displacing and creating an advancing mass made with the incoming grout. The main advantage to this method was the control the injection had over the grouts travel-index. This had huge implications for their ability to accurately estimate grout quantities, but they also found that the pressures required to place these stiff grouts far exceeded the grouting industries standards of 1 psi. per foot of depth as established by agencies such as the Bureau of Reclamation, TVA, and the engineering community as a whole. This meant that they had to establish a whole new train of thought throughout an industry that was well-established and entrenched with specifications and requirements that did not allow for such pressures, flow rates and volume restraints. However, they found that with proper mix designs, injection rates, and volume controls, for the first time in the grouting industries history, they could actually control the lifting and re-leveling of structures. This caught the attention of some very innovative and forward thinking engineers in the California area. As Warner and Graf and their collegian engineers strove to get a better understanding of why this grouting method seemed to do things the industry had never been able to do before, they committed themselves to extensive before-and-after on-site tests as well as numerous independent tests to establish its credibility and validity. Thus were written the first two technical papers for which the industry will forever be indebted (Graf, 1969; Warner, 1974). Because this approach required mixing and pumping equipment that did not exist (at that time), Jim Warner and Ed Graf had to make and/or modify their slabjacking equipment that was never intended to mix and pump such a stiff grout. Ed Graf chose to modify an old Koehring Mudjack (1930s era) machine and Jim Warner modified a (1960s era) plaster pump which he named a G-1200. Both of these systems were of the more labor intensive batch mixing methods for mixing and pumping grout. Both of these pumps had their limitations due to the fact that they were simply modified machines of their era, but the fact remains, these were the machines that established the basics of the compaction grouting application.

    593A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Cya

    n_07

    /31/20

    12_0

    7:54:3

    459

    3A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess M

    agen

    ta_07

    /31/20

    12_0

    7:54:3

    459

    3A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess Y

    ellow

    _07/3

    1/201

    2_07

    :54:34

    593A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Blac

    k_07

    /31/20

    12_0

    7:54:3

    4

    GROUTING AND DEEP MIXING 2012 1665

    THE PAST

    Until the Compaction Grouting approach was conceived, the standard methods of grouting were to utilize fluid grouts that could penetrate cracks and/or permeate a medium such as soil or gravels. The unique approach of the Compaction Grouting method was that the grout did not penetrate nor permeate, but actually created an interface between it and the medium being treated, thereby displacing and creating an advancing mass made with the incoming grout. The main advantage to this method was the control the injection had over the grouts travel-index. This had huge implications for their ability to accurately estimate grout quantities, but they also found that the pressures required to place these stiff grouts far exceeded the grouting industries standards of 1 psi. per foot of depth as established by agencies such as the Bureau of Reclamation, TVA, and the engineering community as a whole. This meant that they had to establish a whole new train of thought throughout an industry that was well-established and entrenched with specifications and requirements that did not allow for such pressures, flow rates and volume restraints. However, they found that with proper mix designs, injection rates, and volume controls, for the first time in the grouting industries history, they could actually control the lifting and re-leveling of structures. This caught the attention of some very innovative and forward thinking engineers in the California area. As Warner and Graf and their collegian engineers strove to get a better understanding of why this grouting method seemed to do things the industry had never been able to do before, they committed themselves to extensive before-and-after on-site tests as well as numerous independent tests to establish its credibility and validity. Thus were written the first two technical papers for which the industry will forever be indebted (Graf, 1969; Warner, 1974). Because this approach required mixing and pumping equipment that did not exist (at that time), Jim Warner and Ed Graf had to make and/or modify their slabjacking equipment that was never intended to mix and pump such a stiff grout. Ed Graf chose to modify an old Koehring Mudjack (1930s era) machine and Jim Warner modified a (1960s era) plaster pump which he named a G-1200. Both of these systems were of the more labor intensive batch mixing methods for mixing and pumping grout. Both of these pumps had their limitations due to the fact that they were simply modified machines of their era, but the fact remains, these were the machines that established the basics of the compaction grouting application.

    593A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Cya

    n_07

    /31/20

    12_0

    7:54:3

    459

    3A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess M

    agen

    ta_07

    /31/20

    12_0

    7:54:3

    459

    3A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess Y

    ellow

    _07/3

    1/201

    2_07

    :54:34

    593A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Blac

    k_07

    /31/20

    12_0

    7:54:3

    4

    GROUTING AND DEEP MIXING 2012 1665

    THE PAST

    Until the Compaction Grouting approach was conceived, the standard methods of grouting were to utilize fluid grouts that could penetrate cracks and/or permeate a medium such as soil or gravels. The unique approach of the Compaction Grouting method was that the grout did not penetrate nor permeate, but actually created an interface between it and the medium being treated, thereby displacing and creating an advancing mass made with the incoming grout. The main advantage to this method was the control the injection had over the grouts travel-index. This had huge implications for their ability to accurately estimate grout quantities, but they also found that the pressures required to place these stiff grouts far exceeded the grouting industries standards of 1 psi. per foot of depth as established by agencies such as the Bureau of Reclamation, TVA, and the engineering community as a whole. This meant that they had to establish a whole new train of thought throughout an industry that was well-established and entrenched with specifications and requirements that did not allow for such pressures, flow rates and volume restraints. However, they found that with proper mix designs, injection rates, and volume controls, for the first time in the grouting industries history, they could actually control the lifting and re-leveling of structures. This caught the attention of some very innovative and forward thinking engineers in the California area. As Warner and Graf and their collegian engineers strove to get a better understanding of why this grouting method seemed to do things the industry had never been able to do before, they committed themselves to extensive before-and-after on-site tests as well as numerous independent tests to establish its credibility and validity. Thus were written the first two technical papers for which the industry will forever be indebted (Graf, 1969; Warner, 1974). Because this approach required mixing and pumping equipment that did not exist (at that time), Jim Warner and Ed Graf had to make and/or modify their slabjacking equipment that was never intended to mix and pump such a stiff grout. Ed Graf chose to modify an old Koehring Mudjack (1930s era) machine and Jim Warner modified a (1960s era) plaster pump which he named a G-1200. Both of these systems were of the more labor intensive batch mixing methods for mixing and pumping grout. Both of these pumps had their limitations due to the fact that they were simply modified machines of their era, but the fact remains, these were the machines that established the basics of the compaction grouting application.

    593A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Cya

    n_07

    /31/20

    12_0

    7:54:3

    459

    3A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess M

    agen

    ta_07

    /31/20

    12_0

    7:54:3

    459

    3A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess Y

    ellow

    _07/3

    1/201

    2_07

    :54:34

    593A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Blac

    k_07

    /31/20

    12_0

    7:54:3

    4

    GROUTING AND DEEP MIXING 2012 1665

    THE PAST

    Until the Compaction Grouting approach was conceived, the standard methods of grouting were to utilize fluid grouts that could penetrate cracks and/or permeate a medium such as soil or gravels. The unique approach of the Compaction Grouting method was that the grout did not penetrate nor permeate, but actually created an interface between it and the medium being treated, thereby displacing and creating an advancing mass made with the incoming grout. The main advantage to this method was the control the injection had over the grouts travel-index. This had huge implications for their ability to accurately estimate grout quantities, but they also found that the pressures required to place these stiff grouts far exceeded the grouting industries standards of 1 psi. per foot of depth as established by agencies such as the Bureau of Reclamation, TVA, and the engineering community as a whole. This meant that they had to establish a whole new train of thought throughout an industry that was well-established and entrenched with specifications and requirements that did not allow for such pressures, flow rates and volume restraints. However, they found that with proper mix designs, injection rates, and volume controls, for the first time in the grouting industries history, they could actually control the lifting and re-leveling of structures. This caught the attention of some very innovative and forward thinking engineers in the California area. As Warner and Graf and their collegian engineers strove to get a better understanding of why this grouting method seemed to do things the industry had never been able to do before, they committed themselves to extensive before-and-after on-site tests as well as numerous independent tests to establish its credibility and validity. Thus were written the first two technical papers for which the industry will forever be indebted (Graf, 1969; Warner, 1974). Because this approach required mixing and pumping equipment that did not exist (at that time), Jim Warner and Ed Graf had to make and/or modify their slabjacking equipment that was never intended to mix and pump such a stiff grout. Ed Graf chose to modify an old Koehring Mudjack (1930s era) machine and Jim Warner modified a (1960s era) plaster pump which he named a G-1200. Both of these systems were of the more labor intensive batch mixing methods for mixing and pumping grout. Both of these pumps had their limitations due to the fact that they were simply modified machines of their era, but the fact remains, these were the machines that established the basics of the compaction grouting application.

    593A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Cya

    n_07

    /31/20

    12_0

    7:54:3

    459

    3A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess M

    agen

    ta_07

    /31/20

    12_0

    7:54:3

    459

    3A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess Y

    ellow

    _07/3

    1/201

    2_07

    :54:34

    593A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Blac

    k_07

    /31/20

    12_0

    7:54:3

    4

    GROUTING AND DEEP MIXING 2012 1665

    307A_PB_4out_Same_50836_ASCE_Final_Print.job_Process Cyan_08/01/2012_16:17:32 307A_PB_4out_Same_50836_ASCE_Final_Print.job_Process Magenta_08/01/2012_16:17:32 307A_PB_4out_Same_50836_ASCE_Final_Print.job_Process Yellow_08/01/2012_16:17:32 307A_PB_4out_Same_50836_ASCE_Final_Print.job_Process Black_08/01/2012_16:17:32

    Grouting and Deep Mixing 2012

    Dow

    nloa

    ded

    from

    asc

    elib

    rary

    .org

    by

    GEO

    RGE

    MA

    SON

    UN

    IVER

    SITY

    on

    03/1

    5/13

    . Cop

    yrig

    ht A

    SCE.

    For

    per

    sona

    l use

    onl

    y; al

    l rig

    hts r

    eser

    ved.

  • In 1976-1977, Jim Warner sold his company, at which time, Wally Baker (founder of the Hayward Baker Company) and Richard Berry (founder of Rembco Engineering) purchased some of Jim Warners G-1200 pumps which started a national interest (and competition) for the compaction grouting application. There were some major projects performed with these machines that continued to establish the credibility of the compaction grouting application on a national level. This established a second generation of compaction grouting applicators.

    Fig 1. Warner G-1200 Grout Plant

    In 1979, Dr. Wally Baker, Jim Warner and Dr. Norbert Schmidt of The University of Rolla decided to hold a one-week Fundamentals of Grouting continuing education course in St. Louis, MO. In attendance at that course was a young slabjacking contractor, Sam Bandimere, who happened to have a project which really needed the controls of this compaction grouting application that Jim Warner presented. Upon finding out that there were no more G-1200 machines available, Mr. Bandimere decided to look at the developing concrete pumping industry to see if there would be a way to modify and apply the technologies of that industry to the compaction grouting application. Mr. Bandimere made an official presentation of that equipment at the 1982 New Orleans specialty ASCE Conference.

    Throughout the 1980s, Mr. Bandimere continued developing what later became known as the Denver System. Some of the unique capabilities developed by this system were:

    1. The continuous and automated mix system for mixing the grout. 2. The integration and use of bulk materials. 3. Pumps that allowed the grout envelope to be opened up for the inclusion

    of gravels in the mix designs. 4. Drilling and casing systems that allowed for more accurate placement of

    grout in both the up-stage and down-stage placement procedures. 5

    9

    4

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    C

    y

    a

    n

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    4

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    M

    a

    g

    e

    n

    t

    a

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    4

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    Y

    e

    l

    l

    o

    w

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    4

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    B

    l

    a

    c

    k

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    1666 GROUTING AND DEEP MIXING 2012

    In 1976-1977, Jim Warner sold his company, at which time, Wally Baker (founder of the Hayward Baker Company) and Richard Berry (founder of Rembco Engineering) purchased some of Jim Warners G-1200 pumps which started a national interest (and competition) for the compaction grouting application. There were some major projects performed with these machines that continued to establish the credibility of the compaction grouting application on a national level. This established a second generation of compaction grouting applicators.

    Fig 1. Warner G-1200 Grout Plant

    In 1979, Dr. Wally Baker, Jim Warner and Dr. Norbert Schmidt of The University of Rolla decided to hold a one-week Fundamentals of Grouting continuing education course in St. Louis, MO. In attendance at that course was a young slabjacking contractor, Sam Bandimere, who happened to have a project which really needed the controls of this compaction grouting application that Jim Warner presented. Upon finding out that there were no more G-1200 machines available, Mr. Bandimere decided to look at the developing concrete pumping industry to see if there would be a way to modify and apply the technologies of that industry to the compaction grouting application. Mr. Bandimere made an official presentation of that equipment at the 1982 New Orleans specialty ASCE Conference.

    Throughout the 1980s, Mr. Bandimere continued developing what later became known as the Denver System. Some of the unique capabilities developed by this system were:

    1. The continuous and automated mix system for mixing the grout. 2. The integration and use of bulk materials. 3. Pumps that allowed the grout envelope to be opened up for the inclusion

    of gravels in the mix designs. 4. Drilling and casing systems that allowed for more accurate placement of

    grout in both the up-stage and down-stage placement procedures.

    5

    9

    4

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    C

    y

    a

    n

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    4

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    M

    a

    g

    e

    n

    t

    a

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    4

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    Y

    e

    l

    l

    o

    w

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    4

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    B

    l

    a

    c

    k

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    1666 GROUTING AND DEEP MIXING 2012

    In 1976-1977, Jim Warner sold his company, at which time, Wally Baker (founder of the Hayward Baker Company) and Richard Berry (founder of Rembco Engineering) purchased some of Jim Warners G-1200 pumps which started a national interest (and competition) for the compaction grouting application. There were some major projects performed with these machines that continued to establish the credibility of the compaction grouting application on a national level. This established a second generation of compaction grouting applicators.

    Fig 1. Warner G-1200 Grout Plant

    In 1979, Dr. Wally Baker, Jim Warner and Dr. Norbert Schmidt of The University of Rolla decided to hold a one-week Fundamentals of Grouting continuing education course in St. Louis, MO. In attendance at that course was a young slabjacking contractor, Sam Bandimere, who happened to have a project which really needed the controls of this compaction grouting application that Jim Warner presented. Upon finding out that there were no more G-1200 machines available, Mr. Bandimere decided to look at the developing concrete pumping industry to see if there would be a way to modify and apply the technologies of that industry to the compaction grouting application. Mr. Bandimere made an official presentation of that equipment at the 1982 New Orleans specialty ASCE Conference.

    Throughout the 1980s, Mr. Bandimere continued developing what later became known as the Denver System. Some of the unique capabilities developed by this system were:

    1. The continuous and automated mix system for mixing the grout. 2. The integration and use of bulk materials. 3. Pumps that allowed the grout envelope to be opened up for the inclusion

    of gravels in the mix designs. 4. Drilling and casing systems that allowed for more accurate placement of

    grout in both the up-stage and down-stage placement procedures.

    5

    9

    4

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    C

    y

    a

    n

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    4

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    M

    a

    g

    e

    n

    t

    a

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    4

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    Y

    e

    l

    l

    o

    w

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    4

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    B

    l

    a

    c

    k

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    1666 GROUTING AND DEEP MIXING 2012

    In 1976-1977, Jim Warner sold his company, at which time, Wally Baker (founder of the Hayward Baker Company) and Richard Berry (founder of Rembco Engineering) purchased some of Jim Warners G-1200 pumps which started a national interest (and competition) for the compaction grouting application. There were some major projects performed with these machines that continued to establish the credibility of the compaction grouting application on a national level. This established a second generation of compaction grouting applicators.

    Fig 1. Warner G-1200 Grout Plant

    In 1979, Dr. Wally Baker, Jim Warner and Dr. Norbert Schmidt of The University of Rolla decided to hold a one-week Fundamentals of Grouting continuing education course in St. Louis, MO. In attendance at that course was a young slabjacking contractor, Sam Bandimere, who happened to have a project which really needed the controls of this compaction grouting application that Jim Warner presented. Upon finding out that there were no more G-1200 machines available, Mr. Bandimere decided to look at the developing concrete pumping industry to see if there would be a way to modify and apply the technologies of that industry to the compaction grouting application. Mr. Bandimere made an official presentation of that equipment at the 1982 New Orleans specialty ASCE Conference.

    Throughout the 1980s, Mr. Bandimere continued developing what later became known as the Denver System. Some of the unique capabilities developed by this system were:

    1. The continuous and automated mix system for mixing the grout. 2. The integration and use of bulk materials. 3. Pumps that allowed the grout envelope to be opened up for the inclusion

    of gravels in the mix designs. 4. Drilling and casing systems that allowed for more accurate placement of

    grout in both the up-stage and down-stage placement procedures.

    5

    9

    4

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    C

    y

    a

    n

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    4

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    M

    a

    g

    e

    n

    t

    a

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    4

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    Y

    e

    l

    l

    o

    w

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    4

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    B

    l

    a

    c

    k

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    1666 GROUTING AND DEEP MIXING 2012

    307B_PB_4out_Same_50836_ASCE_Final_Print.job_Process Cyan_08/01/2012_16:17:32307B_PB_4out_Same_50836_ASCE_Final_Print.job_Process Magenta_08/01/2012_16:17:32307B_PB_4out_Same_50836_ASCE_Final_Print.job_Process Yellow_08/01/2012_16:17:32307B_PB_4out_Same_50836_ASCE_Final_Print.job_Process Black_08/01/2012_16:17:32

    Grouting and Deep Mixing 2012

    D

    o

    w

    n

    l

    o

    a

    d

    e

    d

    f

    r

    o

    m

    a

    s

    c

    e

    l

    i

    b

    r

    a

    r

    y

    .

    o

    r

    g

    b

    y

    G

    E

    O

    R

    G

    E

    M

    A

    S

    O

    N

    U

    N

    I

    V

    E

    R

    S

    I

    T

    Y

    o

    n

    0

    3

    /

    1

    5

    /

    1

    3

    .

    C

    o

    p

    y

    r

    i

    g

    h

    t

    A

    S

    C

    E

    .

    F

    o

    r

    p

    e

    r

    s

    o

    n

    a

    l

    u

    s

    e

    o

    n

    l

    y

    ;

    a

    l

    l

    r

    i

    g

    h

    t

    s

    r

    e

    s

    e

    r

    v

    e

    d

    .

  • One of the major issues that had to be dealt with was the fact that everything in the concrete pumping and mixing industry was (and is) geared to the volume that can be produced. This of course was counterproductive and violates every technical aspect of the Compaction Grouting application. Mr. Bandimere spent years fighting that mindset and would caution that those two concepts are not mutually compatible yet to this day. One of the major dangers of falling for a sales pitch that a standard concrete pump can be used to do compaction grouting is still a fallacy and most certainly will produce project failures. However, there are now several concrete pump manufactures who make low volume- high pressure pumps that are readily available. As a general rule, if a pump has a capacity of more than 20 cu. yds/hr. and pressure capability of less than 1,500 psi., it is not a pump recommended for compaction grouting applications.

    Due to Mr. Bandimeres involvement in the Grouting Industries educational, professional and academia forums, in 1989, Mr. Bandimere started shipping rigs to international destinations which took the compaction grouting technology to an international level. By the mid-to-late 1990s, compaction grouting was being performed regularly on just about every continent. In 1997 at the ASCE GeoLogan Conference, Mr. Bandimere presented the first Compaction Grouting State of The Practice paper (Bandimere 1997).

    Technological Developments

    As the equipment side of the compaction grouting application rose to new levels, so did the technological and educational understandings come to the fore-front. Starting with the 1979 Fundamentals of Grouting Course, the era of contractors holding their Black Magic solutions to grouting applications came to an end. The 1982, 1992, 2003 and now the 2012 New Orleans Grouting Conferences, the annual ASCE (GeoInstitute), ACI, DFI and numerous

    Fig 2. Typical Denver System

    Fig 3. Cross Section Before Grouting

    595A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Cya

    n_07

    /31/20

    12_0

    7:54:3

    459

    5A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess M

    agen

    ta_07

    /31/20

    12_0

    7:54:3

    459

    5A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess Y

    ellow

    _07/3

    1/201

    2_07

    :54:34

    595A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Blac

    k_07

    /31/20

    12_0

    7:54:3

    4

    GROUTING AND DEEP MIXING 2012 1667

    One of the major issues that had to be dealt with was the fact that everything in the concrete pumping and mixing industry was (and is) geared to the volume that can be produced. This of course was counterproductive and violates every technical aspect of the Compaction Grouting application. Mr. Bandimere spent years fighting that mindset and would caution that those two concepts are not mutually compatible yet to this day. One of the major dangers of falling for a sales pitch that a standard concrete pump can be used to do compaction grouting is still a fallacy and most certainly will produce project failures. However, there are now several concrete pump manufactures who make low volume- high pressure pumps that are readily available. As a general rule, if a pump has a capacity of more than 20 cu. yds/hr. and pressure capability of less than 1,500 psi., it is not a pump recommended for compaction grouting applications.

    Due to Mr. Bandimeres involvement in the Grouting Industries educational, professional and academia forums, in 1989, Mr. Bandimere started shipping rigs to international destinations which took the compaction grouting technology to an international level. By the mid-to-late 1990s, compaction grouting was being performed regularly on just about every continent. In 1997 at the ASCE GeoLogan Conference, Mr. Bandimere presented the first Compaction Grouting State of The Practice paper (Bandimere 1997).

    Technological Developments

    As the equipment side of the compaction grouting application rose to new levels, so did the technological and educational understandings come to the fore-front. Starting with the 1979 Fundamentals of Grouting Course, the era of contractors holding their Black Magic solutions to grouting applications came to an end. The 1982, 1992, 2003 and now the 2012 New Orleans Grouting Conferences, the annual ASCE (GeoInstitute), ACI, DFI and numerous

    Fig 2. Typical Denver System

    Fig 3. Cross Section Before Grouting

    595A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Cya

    n_07

    /31/20

    12_0

    7:54:3

    459

    5A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess M

    agen

    ta_07

    /31/20

    12_0

    7:54:3

    459

    5A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess Y

    ellow

    _07/3

    1/201

    2_07

    :54:34

    595A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Blac

    k_07

    /31/20

    12_0

    7:54:3

    4

    GROUTING AND DEEP MIXING 2012 1667

    One of the major issues that had to be dealt with was the fact that everything in the concrete pumping and mixing industry was (and is) geared to the volume that can be produced. This of course was counterproductive and violates every technical aspect of the Compaction Grouting application. Mr. Bandimere spent years fighting that mindset and would caution that those two concepts are not mutually compatible yet to this day. One of the major dangers of falling for a sales pitch that a standard concrete pump can be used to do compaction grouting is still a fallacy and most certainly will produce project failures. However, there are now several concrete pump manufactures who make low volume- high pressure pumps that are readily available. As a general rule, if a pump has a capacity of more than 20 cu. yds/hr. and pressure capability of less than 1,500 psi., it is not a pump recommended for compaction grouting applications.

    Due to Mr. Bandimeres involvement in the Grouting Industries educational, professional and academia forums, in 1989, Mr. Bandimere started shipping rigs to international destinations which took the compaction grouting technology to an international level. By the mid-to-late 1990s, compaction grouting was being performed regularly on just about every continent. In 1997 at the ASCE GeoLogan Conference, Mr. Bandimere presented the first Compaction Grouting State of The Practice paper (Bandimere 1997).

    Technological Developments

    As the equipment side of the compaction grouting application rose to new levels, so did the technological and educational understandings come to the fore-front. Starting with the 1979 Fundamentals of Grouting Course, the era of contractors holding their Black Magic solutions to grouting applications came to an end. The 1982, 1992, 2003 and now the 2012 New Orleans Grouting Conferences, the annual ASCE (GeoInstitute), ACI, DFI and numerous

    Fig 2. Typical Denver System

    Fig 3. Cross Section Before Grouting

    595A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Cya

    n_07

    /31/20

    12_0

    7:54:3

    459

    5A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess M

    agen

    ta_07

    /31/20

    12_0

    7:54:3

    459

    5A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess Y

    ellow

    _07/3

    1/201

    2_07

    :54:34

    595A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Blac

    k_07

    /31/20

    12_0

    7:54:3

    4

    GROUTING AND DEEP MIXING 2012 1667

    One of the major issues that had to be dealt with was the fact that everything in the concrete pumping and mixing industry was (and is) geared to the volume that can be produced. This of course was counterproductive and violates every technical aspect of the Compaction Grouting application. Mr. Bandimere spent years fighting that mindset and would caution that those two concepts are not mutually compatible yet to this day. One of the major dangers of falling for a sales pitch that a standard concrete pump can be used to do compaction grouting is still a fallacy and most certainly will produce project failures. However, there are now several concrete pump manufactures who make low volume- high pressure pumps that are readily available. As a general rule, if a pump has a capacity of more than 20 cu. yds/hr. and pressure capability of less than 1,500 psi., it is not a pump recommended for compaction grouting applications.

    Due to Mr. Bandimeres involvement in the Grouting Industries educational, professional and academia forums, in 1989, Mr. Bandimere started shipping rigs to international destinations which took the compaction grouting technology to an international level. By the mid-to-late 1990s, compaction grouting was being performed regularly on just about every continent. In 1997 at the ASCE GeoLogan Conference, Mr. Bandimere presented the first Compaction Grouting State of The Practice paper (Bandimere 1997).

    Technological Developments

    As the equipment side of the compaction grouting application rose to new levels, so did the technological and educational understandings come to the fore-front. Starting with the 1979 Fundamentals of Grouting Course, the era of contractors holding their Black Magic solutions to grouting applications came to an end. The 1982, 1992, 2003 and now the 2012 New Orleans Grouting Conferences, the annual ASCE (GeoInstitute), ACI, DFI and numerous

    Fig 2. Typical Denver System

    Fig 3. Cross Section Before Grouting

    595A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Cya

    n_07

    /31/20

    12_0

    7:54:3

    459

    5A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess M

    agen

    ta_07

    /31/20

    12_0

    7:54:3

    459

    5A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess Y

    ellow

    _07/3

    1/201

    2_07

    :54:34

    595A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Blac

    k_07

    /31/20

    12_0

    7:54:3

    4

    GROUTING AND DEEP MIXING 2012 1667

    308A_PB_4out_Same_50836_ASCE_Final_Print.job_Process Cyan_08/01/2012_16:17:32 308A_PB_4out_Same_50836_ASCE_Final_Print.job_Process Magenta_08/01/2012_16:17:32 308A_PB_4out_Same_50836_ASCE_Final_Print.job_Process Yellow_08/01/2012_16:17:32 308A_PB_4out_Same_50836_ASCE_Final_Print.job_Process Black_08/01/2012_16:17:32

    Grouting and Deep Mixing 2012

    Dow

    nloa

    ded

    from

    asc

    elib

    rary

    .org

    by

    GEO

    RGE

    MA

    SON

    UN

    IVER

    SITY

    on

    03/1

    5/13

    . Cop

    yrig

    ht A

    SCE.

    For

    per

    sona

    l use

    onl

    y; al

    l rig

    hts r

    eser

    ved.

  • other conferences have well established and documented the compaction grouting technological developments.

    While the original compaction grouting application was (and still is) to stabilize and re-level structures, in 1997 Michael Byle presented a paper at the GeoLogan conference asserting that the term of Compaction Grouting needed to be changed to Low Mobility Grouting (Byle 1997). This was a result of the fact that pumping stiff and low mobility grouts had taken on other applications. By the early 1990s, there were case histories of projects being performed where the Low Mobility grouts were being used for water control, Karst formations were being stabilized, abandoned mines were being filled and stabilized with the precise control of low mobility grouts. It was soon discovered that a properly placed compaction pile could be used for bearing and restraining elements. Most if not all of these applications really had very little if anything to

    Fig 5. Typical Mine Fill

    Fig 6. Typical Earth Retention

    Fig 4. Cross Section After Grouting

    5

    9

    6

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    C

    y

    a

    n

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    6

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    M

    a

    g

    e

    n

    t

    a

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    6

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    Y

    e

    l

    l

    o

    w

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    6

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    B

    l

    a

    c

    k

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    1668 GROUTING AND DEEP MIXING 2012

    other conferences have well established and documented the compaction grouting technological developments.

    While the original compaction grouting application was (and still is) to stabilize and re-level structures, in 1997 Michael Byle presented a paper at the GeoLogan conference asserting that the term of Compaction Grouting needed to be changed to Low Mobility Grouting (Byle 1997). This was a result of the fact that pumping stiff and low mobility grouts had taken on other applications. By the early 1990s, there were case histories of projects being performed where the Low Mobility grouts were being used for water control, Karst formations were being stabilized, abandoned mines were being filled and stabilized with the precise control of low mobility grouts. It was soon discovered that a properly placed compaction pile could be used for bearing and restraining elements. Most if not all of these applications really had very little if anything to

    Fig 5. Typical Mine Fill

    Fig 6. Typical Earth Retention

    Fig 4. Cross Section After Grouting

    5

    9

    6

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    C

    y

    a

    n

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    6

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    M

    a

    g

    e

    n

    t

    a

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    6

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    Y

    e

    l

    l

    o

    w

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    6

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    B

    l

    a

    c

    k

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    1668 GROUTING AND DEEP MIXING 2012

    other conferences have well established and documented the compaction grouting technological developments.

    While the original compaction grouting application was (and still is) to stabilize and re-level structures, in 1997 Michael Byle presented a paper at the GeoLogan conference asserting that the term of Compaction Grouting needed to be changed to Low Mobility Grouting (Byle 1997). This was a result of the fact that pumping stiff and low mobility grouts had taken on other applications. By the early 1990s, there were case histories of projects being performed where the Low Mobility grouts were being used for water control, Karst formations were being stabilized, abandoned mines were being filled and stabilized with the precise control of low mobility grouts. It was soon discovered that a properly placed compaction pile could be used for bearing and restraining elements. Most if not all of these applications really had very little if anything to

    Fig 5. Typical Mine Fill

    Fig 6. Typical Earth Retention

    Fig 4. Cross Section After Grouting

    5

    9

    6

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    C

    y

    a

    n

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    6

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    M

    a

    g

    e

    n

    t

    a

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    6

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    Y

    e

    l

    l

    o

    w

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    6

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    B

    l

    a

    c

    k

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    1668 GROUTING AND DEEP MIXING 2012

    other conferences have well established and documented the compaction grouting technological developments.

    While the original compaction grouting application was (and still is) to stabilize and re-level structures, in 1997 Michael Byle presented a paper at the GeoLogan conference asserting that the term of Compaction Grouting needed to be changed to Low Mobility Grouting (Byle 1997). This was a result of the fact that pumping stiff and low mobility grouts had taken on other applications. By the early 1990s, there were case histories of projects being performed where the Low Mobility grouts were being used for water control, Karst formations were being stabilized, abandoned mines were being filled and stabilized with the precise control of low mobility grouts. It was soon discovered that a properly placed compaction pile could be used for bearing and restraining elements. Most if not all of these applications really had very little if anything to

    Fig 5. Typical Mine Fill

    Fig 6. Typical Earth Retention

    Fig 4. Cross Section After Grouting

    5

    9

    6

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    C

    y

    a

    n

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    6

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    M

    a

    g

    e

    n

    t

    a

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    6

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    Y

    e

    l

    l

    o

    w

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    5

    9

    6

    A

    _

    5

    0

    8

    3

    6

    _

    A

    S

    C

    E

    _

    V

    o

    l

    _

    0

    2

    _

    R

    e

    s

    i

    z

    e

    _

    A

    A

    .

    j

    o

    b

    _

    P

    r

    o

    c

    e

    s

    s

    B

    l

    a

    c

    k

    _

    0

    7

    /

    3

    1

    /

    2

    0

    1

    2

    _

    0

    7

    :

    5

    4

    :

    3

    4

    1668 GROUTING AND DEEP MIXING 2012

    308B_PB_4out_Same_50836_ASCE_Final_Print.job_Process Cyan_08/01/2012_16:17:32308B_PB_4out_Same_50836_ASCE_Final_Print.job_Process Magenta_08/01/2012_16:17:32308B_PB_4out_Same_50836_ASCE_Final_Print.job_Process Yellow_08/01/2012_16:17:32308B_PB_4out_Same_50836_ASCE_Final_Print.job_Process Black_08/01/2012_16:17:32

    Grouting and Deep Mixing 2012

    D

    o

    w

    n

    l

    o

    a

    d

    e

    d

    f

    r

    o

    m

    a

    s

    c

    e

    l

    i

    b

    r

    a

    r

    y

    .

    o

    r

    g

    b

    y

    G

    E

    O

    R

    G

    E

    M

    A

    S

    O

    N

    U

    N

    I

    V

    E

    R

    S

    I

    T

    Y

    o

    n

    0

    3

    /

    1

    5

    /

    1

    3

    .

    C

    o

    p

    y

    r

    i

    g

    h

    t

    A

    S

    C

    E

    .

    F

    o

    r

    p

    e

    r

    s

    o

    n

    a

    l

    u

    s

    e

    o

    n

    l

    y

    ;

    a

    l

    l

    r

    i

    g

    h

    t

    s

    r

    e

    s

    e

    r

    v

    e

    d

    .

  • do with the original concept of compacting in-situ soils for the purpose of stabilizing and re-leveling structures. It was also noted that for most of these applications, the use of high volume concrete pumps was acceptable, and in fact, almost required.

    The Present

    In 2010, the Geo-Institutes Grouting Committee published a Compaction Grouting Consensus Guide, to promote good practice in compaction grouting. The

    purpose of this guide is an attempt to separate the specific application of Compaction Grouting from the others, because it has always been a consensus of the industry as a whole, that the term Compaction Grouting really does have a specific meaning and should be retained as such.

    Compaction Grouting continues to set new records in terms of the size of projects being performed. This can be quantitatively expressed in the size of the average contract amounts and also in the size of structures being stabilized and re-leveled. In 2009, a 655 ft. tall power- plant chimney (Fig. 7) was stabilized and re-leveled without adversely affecting any of the adjacent and adjoining structures. Yet, there is still a huge home-owner market and small projects that continue to demand contractors maintain an ability to do quality work on a wide spectrum of project sizes both contractually and technically.

    While it may have taken some years to persuade and convince government agencies and engineering communities that the use of low mobility grouts at higher pressures did not violate basic soil mechanic principals, once the concept caught on, the use of its application took off. It seems that the Fig 8. Typical Home Owner Project

    Fig 7. Power Plant Chimney

    597A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Cya

    n_07

    /31/20

    12_0

    7:54:3

    459

    7A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess M

    agen

    ta_07

    /31/20

    12_0

    7:54:3

    459

    7A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess Y

    ellow

    _07/3

    1/201

    2_07

    :54:34

    597A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Blac

    k_07

    /31/20

    12_0

    7:54:3

    4

    GROUTING AND DEEP MIXING 2012 1669

    do with the original concept of compacting in-situ soils for the purpose of stabilizing and re-leveling structures. It was also noted that for most of these applications, the use of high volume concrete pumps was acceptable, and in fact, almost required.

    The Present

    In 2010, the Geo-Institutes Grouting Committee published a Compaction Grouting Consensus Guide, to promote good practice in compaction grouting. The

    purpose of this guide is an attempt to separate the specific application of Compaction Grouting from the others, because it has always been a consensus of the industry as a whole, that the term Compaction Grouting really does have a specific meaning and should be retained as such.

    Compaction Grouting continues to set new records in terms of the size of projects being performed. This can be quantitatively expressed in the size of the average contract amounts and also in the size of structures being stabilized and re-leveled. In 2009, a 655 ft. tall power- plant chimney (Fig. 7) was stabilized and re-leveled without adversely affecting any of the adjacent and adjoining structures. Yet, there is still a huge home-owner market and small projects that continue to demand contractors maintain an ability to do quality work on a wide spectrum of project sizes both contractually and technically.

    While it may have taken some years to persuade and convince government agencies and engineering communities that the use of low mobility grouts at higher pressures did not violate basic soil mechanic principals, once the concept caught on, the use of its application took off. It seems that the Fig 8. Typical Home Owner Project

    Fig 7. Power Plant Chimney

    597A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Cya

    n_07

    /31/20

    12_0

    7:54:3

    459

    7A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess M

    agen

    ta_07

    /31/20

    12_0

    7:54:3

    459

    7A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess Y

    ellow

    _07/3

    1/201

    2_07

    :54:34

    597A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Blac

    k_07

    /31/20

    12_0

    7:54:3

    4

    GROUTING AND DEEP MIXING 2012 1669

    do with the original concept of compacting in-situ soils for the purpose of stabilizing and re-leveling structures. It was also noted that for most of these applications, the use of high volume concrete pumps was acceptable, and in fact, almost required.

    The Present

    In 2010, the Geo-Institutes Grouting Committee published a Compaction Grouting Consensus Guide, to promote good practice in compaction grouting. The

    purpose of this guide is an attempt to separate the specific application of Compaction Grouting from the others, because it has always been a consensus of the industry as a whole, that the term Compaction Grouting really does have a specific meaning and should be retained as such.

    Compaction Grouting continues to set new records in terms of the size of projects being performed. This can be quantitatively expressed in the size of the average contract amounts and also in the size of structures being stabilized and re-leveled. In 2009, a 655 ft. tall power- plant chimney (Fig. 7) was stabilized and re-leveled without adversely affecting any of the adjacent and adjoining structures. Yet, there is still a huge home-owner market and small projects that continue to demand contractors maintain an ability to do quality work on a wide spectrum of project sizes both contractually and technically.

    While it may have taken some years to persuade and convince government agencies and engineering communities that the use of low mobility grouts at higher pressures did not violate basic soil mechanic principals, once the concept caught on, the use of its application took off. It seems that the Fig 8. Typical Home Owner Project

    Fig 7. Power Plant Chimney

    597A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Cya

    n_07

    /31/20

    12_0

    7:54:3

    459

    7A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess M

    agen

    ta_07

    /31/20

    12_0

    7:54:3

    459

    7A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess Y

    ellow

    _07/3

    1/201

    2_07

    :54:34

    597A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Blac

    k_07

    /31/20

    12_0

    7:54:3

    4

    GROUTING AND DEEP MIXING 2012 1669

    do with the original concept of compacting in-situ soils for the purpose of stabilizing and re-leveling structures. It was also noted that for most of these applications, the use of high volume concrete pumps was acceptable, and in fact, almost required.

    The Present

    In 2010, the Geo-Institutes Grouting Committee published a Compaction Grouting Consensus Guide, to promote good practice in compaction grouting. The

    purpose of this guide is an attempt to separate the specific application of Compaction Grouting from the others, because it has always been a consensus of the industry as a whole, that the term Compaction Grouting really does have a specific meaning and should be retained as such.

    Compaction Grouting continues to set new records in terms of the size of projects being performed. This can be quantitatively expressed in the size of the average contract amounts and also in the size of structures being stabilized and re-leveled. In 2009, a 655 ft. tall power- plant chimney (Fig. 7) was stabilized and re-leveled without adversely affecting any of the adjacent and adjoining structures. Yet, there is still a huge home-owner market and small projects that continue to demand contractors maintain an ability to do quality work on a wide spectrum of project sizes both contractually and technically.

    While it may have taken some years to persuade and convince government agencies and engineering communities that the use of low mobility grouts at higher pressures did not violate basic soil mechanic principals, once the concept caught on, the use of its application took off. It seems that the Fig 8. Typical Home Owner Project

    Fig 7. Power Plant Chimney

    597A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Cya

    n_07

    /31/20

    12_0

    7:54:3

    459

    7A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess M

    agen

    ta_07

    /31/20

    12_0

    7:54:3

    459

    7A_5

    0836

    _ASC

    E_Vo

    l_02

    _Res

    ize_A

    A.job

    _Proc

    ess Y

    ellow

    _07/3

    1/201

    2_07

    :54:34

    597A

    _508

    36_A

    SCE_

    Vol_

    02_R

    esize

    _AA.

    job_P

    roces

    s Blac

    k_07

    /31/20

    12_0

    7:54:3

    4

    GROUTING AND DEEP MIXING 2012 1669

    309A_PB_4out_Same_50836_ASCE_Final_Print.job_Process Cyan_08/01/2012_16:17:32 309A_PB_4out_Same_50836_ASCE_Final_Print.job_Process Magenta_08/01/2012_16:17:32 309A_PB_4out_Same_50836_ASCE_Final_Print.job_Process Yellow_08/01/2012_16:17:32 309A_PB_4out_Same_50836_ASCE_Final_Print.job_Process Black_08/01/2012_16:17:32

    Grouting and Deep Mixing 2012


Recommended