AMS-02 tracker mechanicsstatus of assembly and integration at
UniGe
Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop Inner tracker integration: - Assembly and cabling - Temperature and magnetic field sensors - Shells closing and flanges mounting - Tests of evaporator integration (pre-assembly)Preparations: - Pre-assembly of outer planes + inner tracker - TAS tests - Transport and storage at CERN
Divic RAPIN, UniGe
General view of Silicon tracker
• 5 planes, 8 layers
• Plane 1, layer 1
• Plane 2, layers 2&3
• Plane 3, layers 4&5
• Plane 4, layers 6&7
• Plane 5, layer 8
• 192 ladder modules
Ladder Assembly (Perugia-Geneva)
• ASSEMBLY• ~ 210 ladders build
• PHASE 2 hybrid box & legs gluing
• ~ completed
• EMI SHIELDING ( kapton foil wrapping)• ~ 31 ready for process
• Full test at each step with RA source and noise control
Installation of ladders on support planes (UniGe clean room)
Plane 3 being stored (under Nitrogen)
Details of fixation on both sides
FINISHED
Complete installation and assembly jigOuter ring assembly
and installation jig
Inner ring assembly and installation jig
Cooling loops are fragile and not self supporting. They need to be kept in jigs for
fabrication, storage, transport and assembly
Upper cooling loops (build at NIKHEF) were delivered for pre-assembly tests at UniGe
The outer loop can be mounted-The fabrication jig is not well suited for installation
- Need to develop an new tool for installation of outer planes to tracker and vacuum case (compatible with cables and TAS).
- Need information from TAS about patch panel dimensions
Assembly of the inner tracker
• Set-up for storage & insertion into the magnet.
• Cables must be installed before the supporting shells and extra length must be attached to temporary supports.
• Further integration works delayed by cosmic and TAS tests
• UniGe manpower resources are decreasing
Inner cabling is finalized
Clamps to fix the cables on the back of the hybrids
Extra length of cables is stored on top and bottom temporary supports
Temperature sensors for inner tracker
Four double Dallas sensors will measure temperature at the center of inner tracker. (not foreseen from beginning of project)
Integration constraints lead us to join inner
measurement chain with upper loops
measurement chain.
Difficult locations (2 mm clearance from the edges of the bars to the shell)
Difficult locations
~Free apertures
Shown previously
T-measurement chain installation
Pieces were developed and built to support and guide the wires of the Dallas sensors chains through difficult locations.
Near future integration operations at UniGe•Design of storage and transport jigs for inner tracker and outer planes (re-use of Alu frame used for AMS01 beam test) (in progress)
•Design and construction of outer plane installation jig (info from TAS needed).
•Supporting shells installation and remove inner tracker from Durga.
•Pre-assembly of inner evaporator on inner tracker (check mountability).
•Pre-assembly of outer planes (check mountability) on inner tracker.
•Time requested by TAS for laser beam alignment/installation.
•Orbital welding of new connectors is needed for upper/lower inner/outer evaporators (on critical path)