+ All Categories
Home > Documents > An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

Date post: 02-Oct-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
108
An Internship Report by ATHAR JABBAR QURESHI Submitted to the College of Engineering of Texas A&M University partial fulfillment of the requirement for the degree of DOCTOR OF ENGINEERING August 1982 Major Subject: Chemical Engineering
Transcript
Page 1: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

An Internship Report

by

ATHAR JABBAR QURESHI

Submitted to the College of Engineering of Texas A&M University

partial fulfillment of the requirement for the degree of

DOCTOR OF ENGINEERING

August 1982

Major Subject: Chemical Engineering

Page 2: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

An Internship Report

by

ATHAR JABBAR QURESHI

Approved as to style and content by:

(Head/of Department)

(Member)

/ 6 .

(Member)

r'1II

(Member)

(Member)

August 1382

Page 3: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

This report describes the internship performed in the slurry

group of the pipeline and production facilities division of the

Bechtel Corporation in San Francisco, during the period February, 1981

to January, 1982.

The intern worked as a slurry engineer in the slurry systems

group of the pipeline and production facilities division. The intern

supervisor was Mr. Ramesh L. Gandhi, chief engineer for the slurry sys­

tems group.

The intership objectives included two aspects; tangibles and

intangibles. In the tangible phase,the intern participated in the de­

velopment of slurry technology-related projects.. The intangible as­

pects of the internship were more subjective, yet were invaluable.

These included such things as learning to see engineering problems as

a whole and translating this knowledge to obtain specific technical

objectives whenever it was appropriate.

Almost half of the internship time was spent in the technical de­

velopment projects pertaining to the design and development of

slurry pipelines, and the other half of the time was spent doing

feasibility studies, engineering studies, and preparing cost estimates

for slurry pipelines-related projects. In addition to this, the intern

reviewed design work done by other engineers and made recommendations

to improve the quality of designs and studies.

During the technical development phase of the internship, two

major projects were performed. First, a computer program was developed

Page 4: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

for the optimum economic design of slurry pipelines. Second, a

study was performed wherein various slurry thmners were evaluated

to transport a very highly concentrated limestone slurry. In addition,

feasibility and engineering studies were performed to evaluate

different alternatives to transport coal, copper and phosphate slurry

pipelines.

Page 5: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

ACKNOWLEDGEMENT

The author would like to express his gratitude to Dr. Ronald

Darby for his worthy advice during the course of this program, for

his efforts in handling the many details associated with a doctoral

program and, above all, instilling a sense of professionalism. My

sincere appreciation goes to Mr. Ramesh Gandhi, intern supervisor,

for his guidance and encouragement throughout various assignments

I undertook during the course of my internship which has helped me

become a better engineer. I would like to give my special thanks to

Mr. Peter Snoek for his leadership and understanding which helped me

conclude this internship successfully.

Page 6: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

TABLE OF CONTENTS

Page

ABSTRACT ................................................ iii

ACKNOWLEDGEMENT ......................................... v

LIST OF FIGURES ......................................... vii

LIST OF TABLES .......................................... viii

CHAPTER 1 - INTRODUCTION ............................... 1

Objectives ................................. 1

Internship Organization .................... 1

Intership Position ......................... 4

CHAPTER 2 - TECHNICAL DEVELOPMENT PROJECTS ............. 9

Development of Computer Program for the Optimum Economic Design of SlurryPipelines .............................. 9

Development of a Slurry Thinner ............. 20

CHAPTER 3 - ENGINEERING PROJECTS ......................... 47

Feasibility of a Phosphate Slurry Pipeline___ 47

Feasibility of a Coal Slurry Pipeline ....... 62

Feasibility of a Copper Concentrate SlurryPipeline ........ ....................... 62

Prediction of Friction Losses for a CoalSlurry Pipeline ........................ 69

CHAPTER 4 - SUMMARY AND CONCLUSIONS ..................... 72

APPENDIX I Pipeline Route Profile Data for IronOre Pipeline ........................... 73

APPENDIX II Optimization Output for Iron Ore Pipeline.... 76

APPENDIX III Computer Certificate Courses ................ 95

VITA ...................................................... 100

Page 7: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

LIST OF FIGURES

Figures Page

1. Reporting Relationship In Bechtel PetroleumSan Francisco Office ................................... 5

2. Reporting Relationship In Pipeline and Production Facilities Division .................................... 6

3. Slurry System Position In Pipeline and Production Facilities Division .................................... 7

4. Generalized Logic of Optimization Program ............. 14

5. General Pipeline Route Profile with Hydraulic Design Constraints ............................................ 15

6. Effect of Lime Stone Slurry Concentration onViscosity .............................................. 27

7. Lime Stone Slurry Yield Stress vs. Concentration ...... 28

8. Rheological Properties of Shale Slurries TreatedWith Thinner E ......................................... 29

9. Effect of Thinner E On The Rheological Properties of60% by Weight Shale Slurry ............................. 31

10. Rheological Properties of Clay Slurries Treated With2 lb/Ton Thinner E ..................................... 32

11. Friction Loss vs. Velocity Test Loop Data for 74%Weight Lime Stone Slurry ............................... 33

12. Effect of Thinner E on the Yield Stress of 75% WeightLime Stone Slurry ...................................... 37

13. Effect of Thinner E On The Viscosity of 75% WeightLime Stone Slurry ...................................... 39

14. Effect of Ph on Viscosity of 75% Weight Lime StoneSlurry .................................................. 40

15. Effect of Ph on the Yield Stress of 75% Weight LimeStone Slurry ........................................... 41

16. Operating Chart for Lime Stone Slurry .................. 44

17. Friction Loss vs. Velocity Data for 75% Weight Limet Stone Slurry ........................................... 46

Page 8: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

LIST OF TABLES

Tables Page

1. System Input Parameters for Optimization Program ...... 11

2. Optimum Economic Design of Iron Ore Pipeline .......... 13

3. Effect of Thinners on Limestone Slurry Rheology ....... 25

4. Rheology of Limestone Slurry During Field Tests ....... 35

5. Operating Limits Chart for Limestone Slurry ........... 36

6. Rheology of Limestone Slurry During Field Tests ....... 43

7. Major Hydraulic Parameters for the Phosphate Slurry Pipelines (original study) ............................. 48

8. Evaluation of Throughputs for Phosphate SlurryPipeline ............................................... 50

9. Sensitivity of 8-inch and 10-inch Pipe Hydraulic Designto Route Changes........................................ 51

10. Evaluation of Routes for Phosphate Slurry Pipeline .... 53

11. Evaluation of Combined Routes for a 10-inch Pipe Size Phosphate Slurry Pipeline .............................. 54

12. Major Equipment Listing for Phosphate Slurry Pipelinefor Route B Plus Original Route ........................ 56

13. Major Equipment Listing for Phosphate Slurry Pipelinefor Route D Plus Original Route ........................ 58

14. Annual Operating Cost for Phosphate Slurry Pipeline.... 50

15. Hydraulic Design for Coal Slurry Pipeline ............. 53

16. Capital Cost Estimates for Coal Slurry Pipeline ....... 54

17. Hydraulic Design Parameters for Copper ConcentrateSlurry Pipeline ........................................ 55

18. Capital Cost for Copper Concentrate Slurry Pipeline ___ 57

19. Operating Cost for Copper Concentrate Slurry Pipeline .. 58

20. Prediction of friction Losses for Coal Slurry ......... 70

Page 9: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

CHAPTER 1

INTRODUCTION

OBJECTIVES:

The purpose of this report is to document the accomplishment of

the following general internships objectives:

1. To demonstrate the ability to carry out planning, organizing,

executing, reporting and correcting the procedures encountered

during the course of an engineering problem.

2. To perceive a specific engineering problem in a systems

approach as a whole and see its interaction with other

components of the system.

INTERNSHIP ORGANIZATION:

History of the Organization:

Bechtel Corporation is a leading Engineering-Construction Company

which is also involved in investment activities. The Bechtel Company

was founded by W.A. Bechtel in 1898. Initially it started as a

small railroad construction firm but in 1906, became a full contracting

construction firm, with work on highways, bridges and water tunnels.

Under the guidance of Steve Bechtel, Sr., president from the mid 1930's

to 1960, the company grew rapidly. Engineering was added to its

capabilities, and new fields included refinery and chemical plants.

In 1940*the company began its first international project when it

began work on a pipeline system in Venezuela. In the late 1950's,

Page 10: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

Bechtel began building commercial scale nuclear plants. Near the

end of 1960, the third generation of the Bechtel family assumed the

leadership of the company when Steve Bechtel, Jr. was named president.

During this period, Bechtel moved into many new fields; rapid transit,

master planning and urban development, underground hydro power sta­

tions, slurry pipelines, airports, hotels and water treatment plants,

among others.

Types of Services:

Bechtel companies provide three types of services:

(1) Engineering: Complete engineering and design services are

performed through technical staffs within different divisions

Services include:

a. Project Evaluation and Preliminary Planning

b. Preliminary Engineering

c. Process Planning and Design

d. Plant Layout

e. Final Detailed Engineering

(2) Construction: Bechtel companies perform construction for

clients under either of two basic arrangements:

a. As part of an overall contract, including engineering

design and furnishing materials.

b. As a separate assignment, based upon engineering plans

specifications and materials supplied by the owner,

by the contractor or partly by both. The companies

provide a complete construction service with all or

major portion of the work performed by Bechtel.

Page 11: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

(3) Management: The Bechtel companies provide three kinds of

management services:

a. Engineering Management

b. Construction Management

c. Total project Management

Structure of the Organization:

Bechtel is structured to provide its services through three

principal operating companies:

a. Bechtel Civil and Minerals, Inc.

This company offers services for projects including

hydroelectric power, water projects, community

facilities, and all types of mining and metals

projects.

b. Bechtel Power Corporation

All Bechtel activities involving nuclear, fossil fuel

and geothermal power plants, and electrical trans­

mission and distribution facilities around the world,

are the responsibility of the Bechtel Power Corpora-

ti on.

c. Bechtel Petroleum Inc.

The full range of engineering, construction and

management services for projects in petroleum, oil

field, pipelining, petrochemical, LNG, tar sands and

synthetic fuels fields is provided by Bechtel

Petroleum, Inc.

Page 12: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

In addition the Bechtel Group, Inc., through its Research and

Engineering operation, offers engineering services in advanced

and emerging technologies. Bechtel's investments are handled by a

wholly owned subsidiary, Bechtel Investments, Inc.

INTERNSHIP POSITION:

The intern was employed by the slurry systems group in San

Francisco. The slurry department is a part of the pipeline and produc­

tion facilities division which is headquartered in Houston. This in

turn is one of the divisions of Bechtel Petroleum, Inc.. 'with the home

office in San Francisco. Bechtel has two slurry systems groups, one

in San Francisco and another in Houston. The San Francisco office of

the slurry systems group is the head office with a well equipped

laboratory, data base for slurry pipelines and various computer design

programs.

Figure 1 shows the hierarchy of management with reporting relation­

ships of Bechtel Petroleum's San Francisco office. Figure 2 shows the

reporting relationship of the Pipeline and Production Facilities

Division. Figure 3 shows the relationship of slurry systems group and

the position of the intern to the P&PF Division.

The intern supervisor was Mr. Ramesh L. Gandhi who is the chief

engineer of the slurry systems group. Mr. Gandhi has extensive

experience in slurry pipeline systems design. He has supervised

many feasibility studies, engineering studies, conceptual designs and

is in charge of technical development projects. He has co-authored a

book with E.J. Wasp which is considered a major source book for slurry

pipeline technology.

Page 13: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

aas I>c e

iic s su. u, a

|?ais2i HEUjZ C a *“ui * * u £ >• u E 3< 0.03

f j j IOS a

il

ut 5 a** 3 d ? *

h- <J

« £ SoZ <3= ua. <a— u5> 21!<?u UIc(9ZKoe2

Page 14: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

35lo .

<2 I 2 « >1 ss =| sS $2 j O 3> < 5

2 P |2 X “* 35 “! * 2si < ua > -j <ud ̂ ̂ ̂* J o . &</j UJ £ 04< s < s

z «- u v: 5> 2

i i ii< * « • j3fiC s

c < s

PRO

DU

CT

ION

FA

CIL

ITIE

S D

IVIS

ION

Page 15: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

ENG

INEE

RIN

G

W.L

. Te

isar

MA

NA

GER

O (Az « lh| e uE UJ UJ

uiSOz 5 c

i i iUJ W

Q •

? <3s i H*n<3ns * -i o zUi

ocao -g 3 %id< u i«

2|| -i 3 3| i §

5 zs

> £ 052 *s2i3d So<§ i *‘ 2

C/Ja: S ® SO 0tr f- is * i l l

2 w* a? < x *“& u . u.

I : s “5 5 <c ^ w z 0

e l 5 h z 81 3j a.

< = <=' g i « IS < i «*S 5 H §' S(j2

I j i f - g " I ffl U- * * • - U4 “ X 2 I U

I *o s SLU UJ >

u j C§ 5 5£ 0 5

2 v>

3 a3 *z a a. s- 2vi Ui

CIV

IL/S

TR

UC

T7

A

RC

H.

& V

ES

SE

LS

S.

H.

T«n

g C

HIE

F E

NG

R.

CO

NT

RO

L S

YS

TE

M!

L.H

. C

han

g C

HIE

F E

NG

R.

EL

EC

TR

ICA

L

R.J.

A

uil

in

CH

IEF

EN

GR

.

PLA

NT

L

AY

OU

T

* P

IPIN

G

P.A.

M

cL

«m

i

CH

IEF

EN

GR

.

acwg2 J is>tr* -j «j h J O u5i“ m u .isjo

2*5 2 § 1 £

“ 5 >5 ̂<hQ2<Cs;

< § £2 u £ 2 | 2 j * ==SoI

SLU

RRY

SYST

EMS

POSI

TION

IN

PIPE

LIN

E AN

D

PRO

DUCT

ION

FACI

LITI

ES

DIV

ISIO

N

Page 16: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

The intern, in the capacity of slurry engineer, participted in

five projects during the internship period, starting February, 1981

and lasting through January, 1982. These are described in detail

later.

The specific objectives which were established for this Intern­

ship were:

1. Learn and practice route location of slurry pipelines.

2. Learn and practice laboratory testing of slurry samples.

3. Learn and practice hydraulic design of the pipelines based

on the laboratory results.

4. Learn and practice sizing of major equipment involved in

slurry pipeline systems. This equipment includes:

a. Selection and sizing of pipelines.

b. Selection and rating of pumps.

c. Rating of flanges.

d. Sizing of agitated storage tanks.

e. Rating of pump motor h.p. and agitator motor h.p.

f. Sizing of slurry ponds.

g. Sizing of orifice station.

5. Perform operating cost estimates on slurry pipeline systems.

6. Perform order of magnitude capital cost estimates on slurry

pipeline systems.

7. Write, debug, modify, and test a preliminary optimization

computer program for slurry pipeline systems.

Page 17: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

CHAPTER 2

Technical Development Projects

Development of Computer Program for the

Optimum Economic Design of Slurry Pipelines

INTRODUCTION

As a part of the technical development programs of the slurry

systems group, a computer program was developed for the preliminary

optimum design of pseudo-homogeneous solid-liquid pipelines. A

preliminary logic chart of the computer program was provided initially.

The logic was cod&i in Fortran V programming language, and

the program was run on Uni vac 1100/80 computer system for an iron

ore slurry pipeline. Hand calculations were performed to diagnose

the syntax and logical errors. The logic was then modified and

extended to increase the flexibility and capacity of the program.

The program development work was later discontinued due to

the depletion of funds allocated to the project for the year 1981-

1982. However, the computer program was developed to the stage

that it can be used to optimize a conventional slurry pipeline,

and it was used to optimize m iron ore slurry pipeline for an

arbitrary pipeline route. The program has been documented for

other users.

OBJECTIVE:

For a slurry pipeline, when a feasibility study, engineering

study or conceptual design of a project is undertaken, many technical

Page 18: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

alternatives are available, and the final selection of an alternative

depends upon the economics. Thus the objective of this computer

program is to select a technical design which yields minimum trans­

portation cost.

Basis of the Program:

This computer program deals with the pipeline aspect of slurry

systems. Table 1 shows the input variables fed into the program.

The slurry is assumed to behave as psuedo-homogeneous suspensions

and follows the Bingham-Plastic rheological mode. For a given

concentration (by wt.) of the desired slurry, the yield stress

and viscosity are measured in a concentric cylinder type viscometer,

and is input into the program.

The program also contains a separate subroutine for commercial

pipeline diameter selection. Normally the commercial pipe sizes

are available in even sizes (nominal sizes; 4, 6, 8 inches, etc.);

however, Sometimes hydraulic design dictate the selection of the

odd seize pipes (nominal sizes; 5, 7, 9 inches, etc.). Odd

pipe sizes are not readily available commercially, and are relatively

expensive compared to even pipe sizes. This program incorporates

both odd and even pipe sizes.

The pipeline route profile is supplied in a separate subroutine.

It is added by the user, outside the main program as a separate

data file. It lists elevation of the pipeline as a function of

distance, as the pipeline traverses from the mine site to the slurry

pipeli ne dewateri ng:faci1i ty.

Page 19: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

TABLE 1

System Input Parameters for Optimization Program

Technical Input Parameters

pipe roughness = inches

number of pipeline route profile points slurry concentration in weight percent viscosity for given concentration = centipoise particle size below which 95 percent of particles lie = in micron equilibrium moisture content = % specific gravity of solid specific gravity of carrier liquid

maximum pump discharge pressure = PSI minimum slurry concentration by wt. = % maximum slurry concentration by wt. = % increment in concentration = % minimum pipe wall thickness = inches pressure safety factor = flow safety factor =

number of pump station cases to be considered number of diameter cases to be considered pipe grade = PSI solids throughput = Tons/hr. pipeline operating time/year = hours maximum velocity = ft/sec. pump efficiency = in fraction maximum horsepower/pump = Hp first length of the pipe = mile or kilometer corrosion allowance for first length of pipe = inches corrosion allowance for remainder pipe length = inches

Economic Input Parameters

steel cost = $/Ton construction cost = $/in-ft. base cost of pump station = $ cost/pump/station = $ cost per Hp = $/Hp labor cost/pump station/year = $ supplies cost/pump/year = $ power cost = $/kwh

cost premium factor for odd pipe size amortization period = years cost of debt = %fraction of capital financed by debt corporate tax = fraction advalorem tax = percentage of capital average inflation rate = % cost of equity = %

Page 20: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

A corrosion allowance, which is also fed into the program

as an input, is measured in the laboratory using a corrosometer.

The maximum velocity limit is set by the corrosion - erosion charac­

teristics of the slurry and is also determined through data on

corrosion - erosion.

Analysis of the alternative designs revealed an optimum design

which is presented in Table 2.

Logic Description '

Figure 4 shows a very generalized flow chart for the optimi­

zation program. For a chosen concentration, rheological properties

are calculated. The deposition velocity is calculated using rheo­

logical properties and concentration. Bechtel's model for deposition

velocity prediction was used in the program. An operating velocity

is selected above the deposition velocity but below maximum velocity

which depends on the abrasivity of the slurry. Then a commercial

size pipe diameter is selected. The selection of the pipe size

is based on outside diameter since inside diameter changes for

tapered wall pipe. The friction losses are calculated by a model

developed by Bechtel. The hydraulic gradient is checked for slack

flow conditions. Typically slack flow occurs when the pipeline

operating pressure is less than atmospheric pressure, and is usually

encountered at the peaks of the pipeline route profile. Slack

flow is avoided by lifting the hydraulic gradient line above the

peak of the pipeline profile as shown in Figure 5. Sometimes

avoiding slack flow results in excess head at the terminal, which

Page 21: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

TABLE 2

Optimum economic Design of Iron Ore Pipeline

concentration by wt. = 54% outside pipe diameter = 9.625 inches slurry flow rate = 1325 gpm average operating velocity =6.5 ft/sec. number of pumps/station = 2 (1 operating, 1 spare) total required horsepower = 6367 Hp

number of pump stations = 3 horsepower/pump = 1061 Hp power consumption = 15 million kwh/yr steel weight for API-5LX52 = 2062 Tons direct capital cost t)f; pipeline = 15.615 million dollars operating cost of pipeline = 0.907 million dollars/year transportation cost = 1.1294 $/Ton

Pump Station Location:

Pump Station

1

Distance From Elevation (ft.) Pipeline Mouth (1000 ft.)

1345 0

2 2414 36.27

3 1368 225.98

Page 22: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

VARIABLES

CHOOSECONCENTRATION

DATA

CHOOSE VELOCITY A80VE DEPOSITION

VELOCITY

1 PIPELINEPROFILE----

CHOOSE DESIGN ANDCOMMERCIAL PIPE LOCATE ORIFICE

DIAMETER STATION

DESIGN A DESIGN AND CALCULATETAPERED LOCATE A CAPITAL ANDPIPELINE PUMP STATION OPERATING COST

GENERALIZED LOGIC OF OPTIM IZATION PROGRAM

Page 23: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

EL

EV

AT

ION

NOTE:1 -P IPEL IN E GROUND PROFILE2 - HYDRAULIC GRADIENT LINE AT WHICH SLACK

FLOW CONDITION 5 OCCURS3 -N E W HYDRAULIC GRADIENT LINE4 - ORIFICE STATION TO CHOKE THE EXCESS HEAD5 - SLACK FLOW CONDITION WHEN 1 AND 2 COINCIDE6 - HYDRAULIC GRADIENT FOR REDUCED PIPE DIAMETER

7 -H Y D R A U L IC GRADIENT AFTER CHOKING8 -S T A R T OF A REDUCED PIPE DIAMETER

DISTANCE

GENERAL PIPELINE ROUTE PROFILE WITH HYDRAULIC DESIGN CONSTRAINTS

Page 24: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

should be dissipated either by a selection of a smaller diameter

pipe or an orifice station. If the reducer diameter is selected

to dissipate the excess head, the resulting operating velocity

should be such that it does not exceed maximum velocity, since

at higher velocities the wear rate of the pipe increases at an

increasing rate.

Once the hydraulic design criteria has been established,

the tapered wall pipe is designed along with pump stations. Finally,

capital and operating costs are calculated. The procedure is

repeated for different concentrations.

Capabilities of the Program:

The program has been developed primarily to compare several

technical alternatives available within given design limits, so

that the most economical technical design could be selected. Follow­

ing are some major features performed by the program;

(1) For different concentrations, it selects a commercial

pipe diamater for a tapered wall pipeline.

(2) For the number of stations as specified in the input, It

sizes up pump stations and establishes their exact

location.

(3) It avoids slack flow and makes necessary design changes

to avoid it during operation.

(4) It considers both regular (e.g., nominal pipe sizes 4, 6,

8 inches, etc.) and premium (e.g., nominal pipe sizes 5, 7,

9 inches, etc.) pipe sizes.

Page 25: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

(5) It sizes orifice station and establishes the location.

(6) If a hydraulic design criteria establishes slack flow

condition somewhere along the pipeline route,it selects

a lower diameter pipe for the remaining length of the pipe.

Thus,it can calculate two diameters for one pipeline system

with the exact location and length for each pipe size.

(7) It considers different economic parameters for the calcula­

tion of transportation cost, e.g., time value of money,

cost of debt and equity, income tax, advalorem tax, capital

financing structure, rate of inflation, amortization

period, etc.

(8) It calculates installed capital cost of the tapered

pipeline.

(9) It calculates power cost, labor cost, cost of supplies and

maintenance.

(10) It can be used to perform sensitivity analysis on

any input technical parameter or economic parameter.

(11) The major variables which can be optimized are concen­

tration, diameter, number of pump stations, pipeline route,

pipp grade, etc. The optimum values are obtained at

minimum transportation cost.

Example Case: A previously designed iron ore slurry pipeline was

tested on the optimization program. The input pipeline route

profile data is given in Appendix I. Appendix II shows the various

alternate designs for this pipeline.

Page 26: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

Shortcomi ngs:

Two kinds of shortcomings were encountered during the develop­

ment of the optimization program. The first was due to personal

limitations and the second was program related.

Personal Limitations:

I first joined the slurry group of the Bechtel petroleum's

pipeline and production facilities division on February 9, 1981,

and was assigned the responsibility for the development of the

slurry pipeline optimization program. Most of the computer programs

in Bechtel are developed and used on Uni vac 1100/80 Computer System

with Fortran V Compiler. I had marginal familiarity with the Fortran

V Compiler and none on the operation aspects of Uni vac 1100/80

Computer System. The deficiency was corrected through the following:

1. Self Study

2. Bechtel sponsored computer courses

3. Computer services group

4. Users support group

1. Self Study:

Through self study the use of Fortran V as a programming

language and operation of Uni vac Computer System was made possible.

The books used were: Bechtel Reference Manual for the Univac Computer

System, an introduction to Bechtel Data Processing Service and

Fortran V (level 4R1) local inventions.

2. Bechtel Sponsored Courses:

To learn the operation of the Univac Computer System, computer

Page 27: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

program generation on it and the Text editor, four certificate

courses were completed. Copies of the certificates are given

in Appendix III.

3. Computer Services Groupi

The Computer Services Group typically does production runs

on existing computer programs for the slurry group. Also during

the development of any computer program, they are responsible

for coding the program in Fortran V language and loading it on

the Uni vac Computer System. Frequent interaction with the Computer

Services Group during the development of the optimization computer

program was necessary.

4. Users Support Group:

The Users Support Group services were sought during the debug­

ging of the program. The intern learned to diagnose different

system related and program related error messages through their

help.

In addition to this, occasional interaction with the Time-

Share support services group and Engineering Support services

group was necessary.

Program Related:

When the intern was assigned the responsibility for the develop­

ment of the computer program, there was no separate allocation

of funds for the project. The development cost incurred was charged

to another ongoing technical development project. After the deple­

tion of funds, the work on the program development was discontinued.

Page 28: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

The program has been documented with appropriate instructions

to help the user to use it. The computer program is developed

to the stage that it can be used* to optimize a conventional slurry

pipeline. There are still some bugs left in it so that slack

flow calculations, orifice station calculations and two diameters

case for one line cannot be handled by it at the moment.

Recommendations have been made for future work on the program.

DEVELOPMENT OF A SLURRY THINNER:

Long distance slurry pipelines are designed to transport

solids under turbulent flow conditions. In the case of a limestone

slurry, the yield stress increases quite rapidly as the solids

content is increased. The laminar-turbulent transition velocity

increases as the slurry yield stress increases. Dispersing agents

can be used to reduce the yield stress of a slurry. In cement

plants, it is advantageous to deliver a limestone slurry at the

maximum possible solids concentration. Dispersing agents (slurry

thinners) are used to reduce the yield stress and make the slurry

pumpable at high concentrations.

A client-sponsored research program was carried out by Bechtel

to evaluate the effectiveness of various types of slurry thinners

on a limestone slurry, shale slurry and clay slurry.

Objectives:

(1) Evaluate the effectiveness of various slurry thinners on

liimestone, shale and clay slurries.

Page 29: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

(2) Produce the maximum concentration pumpable slurries with

the aid of the most effective thinner.

Duration of Study:

The slurry thinner study took about 5 months to complete. The

study was divided into two parts:

(1) Lab Testing and Engineering Analysis

(2) Field Testing.

Both lab testing and field testing had to be repeated. The

initial results obtained through lab testing and engineering anal­

ysis was found to be encouraging. Recommendation for field testing

was made to the client. However, the results obtained during field

testing were not as encouraging as the laboratory results. More

extensive laboratory tests were performed to determine the effect

of variations in slurry properties on the effectiveness of slurry

thinners. A subsequent field test under more controlled conditions

confirmed the predictions based on laboratory evaluations.

Types of Experiments:

Five types of experiments were performed on slurries in Bechtel1

slurry laboratory.

1. Size Analysis: Particle size distribution was measured

on limestone solids using Tyler mesh screen. The original

design particle size was -65 Tyler mesh. For the current

study, the same particle size was maintained.

2. Specific Gravity of Solids: Specific gravity was de­

termined for limestone, shale and clay solids using

Page 30: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

pycnometer method, where the specific gravity is measured

by weighing the material in the air, compared to the

weight in the water.

3. Penetration Tests: Penetration tests were performed on

the limestone slurry to determine the extent of settled

bed compaction. This is done by dropping a previously

weighed conical bob on the settled slurry. The weight

required to penetrate the bed is the measure of slurry

packing characteristics. This indicates the relative

difficulty which may be encountered in attempting to

resuspend a slurry which has settled in a pipeline

during shut down.

4. Settling Rate: Settling tests were performed on limestone

slurry. This determines the slurry-liquid interface settling

rate and terminal solids concentration under static con­

ditions. This helps to eatablish a safe shut down period,

also this is an indirect measure of slurry packing density,

i.e., if the slurry-liquid interface is closer to the top

of the pipe, the slurry is less compact and easier to

resuspend during start-up of the pipeline.

5. Rheology Tests: Rheology tests were the most important

tests and they were performed extensively on the three

slurries using a concentric cylinder type viscometer.

This viscometer consists of a cylindrical bob and a cy­

linder. The bob rotates inside the cylinder containing

the slurry. For a preset shear rate the shear stress is

Page 31: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

recorded. The data are used to characterize the rheological

model. The limestone slurries obey the Bingham plastic

rheological model, which is

T = XQ + ji00 Y

where t q = yield stress of the slurry

y» = viscosity at infinite shear rate

y = shear rate

x = shear stress

The rheological parameters tq and are used to predict

transition critical velocities and friction losses in the pipe. The

transitional velocity is an important criteria, which is used

to define the laminar and turbulent flow regions. An operating

velocity below critical transition velocity means the slurry will

operate in laminar flow. Similarly, an operating velocity above

the critical transition velocity indicates a slurry flow regime

in the turbulent region. Almost all the pipelines are designed

in the turbulent region.

Types of Thinners:

Seven different thinning agents were evaluated during

this study. These will be designated as A, B, C, D, E, F and

Orzan AL-50.

Evaluation of Thinners:

Since the limestone slurry contributed the major portion

of the solids going to kiln for cement production, the selection

Page 32: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

of thinner was based on the sole criteria of its effectiveness

in reducing the yield stress and viscosity of limestone slurry.

The same thinner was used for the determination of rheological

properties for shale and clay slurries.

The thin limestone slurry was filtered and various samples

in concentration range from 74-75 percent by weight were prepared

using the filtrate. The thinners were added to the samples on

the weight basis (lb. of thinner per ton of dry limestone) as recom­

mended by the suppliers. The rheological measurements were made

in the viscometer at room temperature. Table 3 shows the effect

of various thinners on the rheological properties of limestone

slurries. It shows that the thinner E was the best among all

the thinners evaluated. For a 75 percent weight limestone slurry

2the yield stress was found to be 20 dynes/cm and limiting viscosity,

120 centipoise. Further rheological measurements were made on

limestone, shale and clay slurries with this thinner.

Establishment of Maximum Concentration Limestone Slurry:

The maximum concentration for the limestone slurry was

determined for pumping purposes using 2 pounds of thinner E per

torn of dry limestone. For comparison purposes rheological measure­

ments were made for limestone slurry without any additive and

with 3 pounds Orzan per ton of dry limestone which is currently

being used for the production of 70 percent weight limestone slurry.

The concentric cylinder type viscometer was used to measure the

rheological properties at room temperature. Several samples of

Page 33: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

TABLE 3

Effect of Thinners on Limestone Slurry Rheology

Thinner Slurry Yield Viscosity Dosage AdditiveCone. Stress «

Wt. % Dynes/cm

A 75.5 544

B 75.5 462

C 74.25 721.4

D 74.25 334

E 75 20

F 75.5 721

ORZANAL-50 75 200

Rate CostCP lb/Ton $/Ton Limestone

377 1 0.56

316 1 0.56

411 1.4 0.59

190 1.2 0.59

120 2 0.60

571 6 0.15

425 3 0.20

Page 34: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

limestone slurries were prepared in the concentration range of

70-79 percent by weight of solids. Figure 6 shows the variation

in viscosity of the slurry with the concentration of limestone

solids in a slurry. The limestone slurry without any additive

had the highest viscosities and the lowest viscosities were observed

with 2 pounds of thinner E per ton of limestone. The Orzan treated

limestone slurry had an intermediate viscosity.

Figure 7rshows the change in yield stresses of limestone

slurries as a function solids concentration. The limestone slurry

without any additive had the highest yield stresses while the

thinner E treated slurry shows the lowest yield stresses.

The existing limestone slurry pipeline system had been designed

to transport solids in the turbulent region. Bechtel's computer

model was used to predict the minimum operating velocity in the

turbulent region. Analysis of the results revealed that a maximum

of 75 percent limestone slurry is possible without over-pressuring

the existing pipeline and pump.

Establishment of Maximum Concentration for Shale Slurry:

The thin shale slurry sample was filtered. Various samples

of different concentrations were prepared. For comparison purposes,

a base concentration of 50 percent by weight was selected. Figure

8 shows the viscosity and yield stress versus shale slurry concentra­

tion relationship for 2 lb/ton, 4 lb/ton thinner E and without

any additive. It was decided that a higher maximum concentration

can be achieved by increasing the thinner E dosage. Thus a 60

Page 35: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

VISC

OSI

TY

(cp)

EFFECT OF LIMESTONE SLURRY CONCENTRATION ON VISCOSITY

Page 36: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

YIEL

D ST

RESS

(D

ynes

/cm

2)

LIMESTONE SLURRY YIELD STRESS VS. CONCENTRATION

Figure 7

Page 37: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

SLU

RRY

VISC

OSI

TY

(cp)

OR

YI

ELD

STRE

SS

(Dyn

es/c

m2)

RHEOLOGICAL PROPERTIES OF SHALE SLURRY TREATED WITH THINNER E

Page 38: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

percent maximum concentration was selected and rheological properties

were measured for various thinner E dosages. Figure 9 shows the

effect of change in thinner E dosages on viscosity and yield stress

of a 60 percent weight shale slurry. At about 6 lb/ton of thinner

E, the desired viscosity and yield stress were obtained.

Establishment of Maximum Concentration for Clay Slurry:

Figure 10 shows the variation in yield stresses and viscosities

of the clay slurry as a function of concentration of thinner E.

However, at the request of the client, additional tests on the

clay slurry were discontinued.

Field Test:

A field test was carried out at the client's slurry preparation

and pump station facility, to demonstrate the feasibility of the

project. However, due to some unavoidable circumstances, which

will be discussed later, only 74 percent weight limestone slurry

could be produced through the mills. The diaphragm pressure cell

at the test loop was not functioning, so a mercury monometer was

installed for pressure drop measurement at the test loop. For

various flow rates pressure drop measurements were recorded. Figure

11 shows the change in friction!losses in psi/mile for various

flow rates. It had been observed in the past that the slope of

the pressure drop vs. velocity line in a logarithmic plot for

turbulent region was about 1.75; however, analysis of Figure 11

revealed that all the data points lie in laminar region. Rheological

tests were performed at the test site on slurry samples collected

Page 39: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

YIELD STRESS

2 4 6 8

lb. PER TON OF THINNER E

EFFECT OF THINNER E ON THE RHEOLOGICAL PROPERTIES OF 60% Wt. SHALE SLURRY

Page 40: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

VISC

OSI

TY

(cp)

OR

YI

ELD

STRE

SS

(Dyn

es/c

m2

)

SLURRY CONCENTRATION (% by weight)

RHEOLOGICAL PROPERTIES OF CLAY SLURRIES TREATED WITH 2 !b/ton THINNER E

Page 41: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

200 i -

1S0

100 c 90

aa

C/3COO

zoHo

80

70

60

50

40

30

20

10

MAXIMUM DESIGN

© FRICTION LOSS - 125 psi per mila

NOTE: All points indicate laminar flow

J__L9 8 7 6 5 4 3 2

VELOCITY {ft. per sec.)

FRICTION LOSS VS. VELOCITY TEST LOOP DATA FOR 74% Wt. LIMESTONE SLURRY

Page 42: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

from the ball mill, storage tank and test loop at various concen­

trations. Table 4 shows the rheological properties and laminar-

turbulent transition velocity at various concentrations. The Bechtel

model was used to predict the transition velocity.

The slurry was diluted to about 73.5 percent concentration

and rheological properties measured as shown in Table 4. The slurry

could have been pumped at 73.5 percent concentration. However,

since the mainline pump speed reducer was not working, the slurry

was further diluted to about 71 percent concentration and pumped.

Effect of Thinner on Varying Rock Properties:

Additional tests were carried out on limestone slurry to de­

termine the effect of thinner on changing limestone rock properties.

Rheological tests were performed on different batches of limestone

slurries collected on different dates at the mine. Table 5 shows

the rheological properties, transition velocities and minimum and

maximum flow rates for different batches of limestone slurries.

Batches 1, 2, 3 could be pumped at 75 percent concentration with

pounds of thinner E per tone of dry limestone, whereas for Batch

4 only 73.5 percent concentration limestone slurry could be pumped

with 2 pounds of thinner E per tone of dry limestone. However,

it was noted that by varying the thinner amount to 10 lb/ton, it

was possible to pump the 75 percent concentration limestone slurry.

Figure 12 shows the effect of cnanging thinner dosages on

yield stress of a 75 percent weight limestone slurry for Batches

Page 43: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

TABLE 4

Rheology of Limestone Slurry During Field Tests

Material Slurry Viscosity Yield Stress CalculatedCone. Wt.% CP Dynes/cm^ Laminar-Turbulent

Transition Velocity Ft/S.

MillProduct 75.5 300 160 11.2

StorageTank 74 240 74 8.0

Test Loop 73,8 190 110 8.6

Test Loop-Mainline 73.6 150 60 6.5

Test Loop-Mainline 71.0 100 50 5.4

Page 44: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

Operating

Limits

Chart

for

Limestone

Slur

ry

Cl- CCTiZJos-

C 5 •i— o 2 : I—

inOucn

to*o 00 1— <uV s-•1- 4->

> - CO

s-<u

to-o■M t-OCO

u+■>«o

CQ

eo

•Xr0 a .

<v 2 : CD

ass-3 : X—X0 • 2 :

p— C Q.Ll-1 •r» O

_J 2 :

cjn 0 > >s- •r “ +->3 +-> O

t— •1— O <Ul <S> O to

•r— c r—E <0 CD +Jas s- > M-

_ l h -

Q_O

CM

in0)sz£

ot-

UD U0 1"* O tocn CD CO <3- LOCM CM CM CM CM

O in to CDVO to in 0 CMCM CM CM CM CM

O 0 in in CMCM CM CD to CM00 00 r>>. to r->»

CM <3 - CM CM inCM CO i~t

r̂. in to

coCM

CM

in

COCM

CM

inI '*

CM

CM

LO

CO

CO

*3"

in

00

in toCM CM cn

« • • • •CM CO 00to in 00 iH

CMCO «—t

CO 00 CMr—t *3" O in• • • • ■CM CO CM 00rH rH CO CM

CM

incol"s.

Page 45: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

YIEL

D ST

RESS

(D

ynes

/cm

2)

EFFECT OF THINNER EON THE YIELD STRESS OF 75% Wt. LIMESTONE SLURRY

Page 46: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

1, 2, 3 and 4. For Batches 1, 2, 3 it can be seen that 2 lb/ton

of thinner produced a minimum yield stress for a 75 percent weight

of limestone slurry. However, for Batch 4 the yield stress of the

slurry decreased as the thinner dose in the slurry was increased.

Similarly, Figure 13 shows the viscosity variation in a 75 percent

weight limestone slurry as the thinner dosage was changed. It can

be seen that for 2 pounds thinner/ton of dry limestone, all the

four batches exhibited minimum viscosity.

The pH of the slurry was also found to be an effective measure

of changing limestone rock properties. Figure 14 and Figure 15

show the viscosity and yield stress of slurry respectively for all

four Batches 1, 2, 3, and 4 as the pH was increased. Between pH

9.5-10 all the batches appeared to have lowest yield stresses and

viscosities except for Batch 4, which showed a significant drop

in viscosity as the pH increased from 7.5-8. However, further in­

crease in pH did not produce any significant change in the vis­

cosity of Batch 4 slurry. Thus, the effect of varying dosages of

thinner E on the changing rock properties was established. The

recommendations were made to the client for field testing.

Field Test:

About 3500 tons of limestone was processed through the ball

mills and stored in slurry holding tanks. The thinner was added

in the mill, initially at a lower rate. The pH of the ball mill

processed slurry was about 8-8.5 at 75 percent concentration during

the thinner addition rate of 1.6 lb/ton. The rheology of the

Page 47: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

VISC

OSI

TY

(cp)

lb. THINNER E PER TON OF DRY LIMESTONE

EFFECT OF THINNER E ON VISCOSITY OF 75% Wt. LIMESTONE SLURRY

Page 48: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

VISC

OSI

TY

(cp)

EFFECT OF pH ON VISCOSITY OF 75% Wt. LIMESTONE SLURRY

Page 49: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

DO “

00 -

00 -

90 -80 -70 ■

60 -

50 -

40 ■

30 ■

20 ■

10 i i i i i i _ i 5 6 7 8 9 10 11

pH

EFFECT OF pH ON THE YIELD STRESS OF 75% Wt. LIMESTONE SLURRY

Page 50: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

slurry indicated that the yield stress and viscosity of the slurry

was high at this pH. The estimated laminar-turbulent transition

velocity was also found to be quite high so that the 75 percent

weight slurry could not have been pumped in turbulent region. The

thinner rate was increased to about 2.5 lb/ton of limestone. The

pH of the slurry at this thinner rate was found to be 9-9.5. The

rheological properties were measured which indicated lower transi­

tion velocity.

When the processing of the limestone slurry was complete, it

was pumped through the pipeline test loop. The differential pres­

sure transducer cell on the test loop was out of service, so a mer­

cury monometer was installed to measure the friction losses. The

friction losses of the slurry were measured at various flow rates.

The critical transition velocity was calculated using Bechtel's

model for transitional velocity.

Table 6 shows the rheological properties at different pH for

processed limestone slurry at various concentrations. Based on

the test loop data, engineering calculations were made to pump the

75 percent weight limestone slurry at a flow rate such that it did

not exceed the maximum design discharge pressure of the pump station.

Based on the data collected during the test loop operation

and mainline pumping of the slurry, operating, charts were prepared

to account for the variable rheological properties of the limestone

rock. Figure 16 shows the minimum operating velocity, maximum

flow rate and the maximum discharge pressure as a function of

Page 51: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

TABLE 6

Rheology of Limestone Slurry During Field Test

Average Temperature = 26° C

Material Slurry pH Viscosity Yield Laminar-Turbulent Cone. CP Stress Transition VelocityWt.% Dynes/cm2 ft/s

MillProduct (A) 76.3 8.0 237 94 6.9

9.5 181 64 5.6

(B) 75.5 8.09.5

194206*

30595

9.76.7

HoldingTank 75 8.5 102 47 4.3

9.0 111 47 4.49.5 77 12 2.5

MainlinePump 75 9.0 125 54 4.7

* Viscosity and yield stress higher than 76.3 wt.% due to variation in limestone rock properties.

Page 52: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

SLURRY CONCENTRATION RANGE = 73 to 75 PERCENT WT.

VELOCITY (ft/sec) FL0W RATE <9Pm)

20 40 60 80 100 120 140 160 180 200 220 240 260 280 300

VISCOSITY (cp)

Note: Min. Operating Velocity = Laminar - Turbulent Transition Velocity.

OPERATING CHART FOR LIMESTONE SLURRY Figure 16

Page 53: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

rheological properties for the limestone slurry in the concentration

range of 73-75 percent weight. Figure 17 shows the friction losses

for safety"loop and mainline as the operating velocity was varied

in the pipeline.

Page 54: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

FRIC

TIO

N

LOSS

(p

si pe

r m

ile)

900 800 700

600

500

400 h

300

200

150

50

20

MAXIMUM DESIGN

^ FRICTION LOSS = 125 psi per mile1001- •

90 807 0 1- h

6 0 h oHI > Z

40 h 2c/5 z

30 \ - <trKQ . NOTATION:uiH i 9 Safety Loop Data

▲ Mainline Data

Note: All points indicate turbulent flow

9 8 7 6 5 4 3 2

VELOCITY (ft. per sec.)

FRICTION LOSS VS. VELOCITY DATA FOR 75% Wt. LIMESTONE SLURRY

Page 55: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

CHAPTER 3

Engineering Projects

Feasibility of a Phosphate Slurry Pipeline

INTRODUCTION:

A feasibility study of a phosphate slurry pipeline was under­

taken. The original study was performed by Bechtel in 1979 for

the client. The pipeline was designed for an 8 inch nominal size

pipe with design concentration of 65 percent by weight and top parti­

cle size of -65 mesh. The original study was performed for

a pipeline route length of about 25.58 miles. Table 7 shows the

major hydraulic design parameters for the original study.

At the request of the client, hydraulic design was performed

with a 10 inch pipeline on the original pipeline route. The ori­

ginal study on 8 inch pipe had recommended a positive displace­

ment pump, it was anticipated that a 10 inch pipe size might result

in the selection of a centrifugal pump which is quite cheap compared

to the positive displacement pump. To realize this design change,

the design velocity was reduced by adjusting the particle size.

The particle size was decreased from minus 65 mesh to minus 100

mesh which resulted in a decrease in operating velocity from 5.3

feet per second to about 5 feet per second. However, it was found

that a lower pump discharge pressure could not be achieved because

the pipeline system has a large static head to overcome. The

ground elevation rises from 7430 feet at the pump: station site

to about 8450 feet elevation at mile post 8. The client further.

Page 56: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

Major Hydraulic Parameters for the

Phosphate Slurry Pipelines (Original Study)

Nominal Pipeline Diameter

Slurry Concentration

Particle Size Distribution

Flow Velocity

Throughput

Pump Discharge Pressure

Choke Pressure

8 inches

65 percent by weight

-65 mesh

5.3 feet per second

2.0 million short tons per year

1613 PSI

1082 feet

Page 57: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

asked for a sensitivity of the 10 inch pipe design to solid concen­

tration to determine &ny possible economy of scale. This was

done by relaxing the 2 million ton per year design throughput

constraint. Table 8 shows the sensitivity of pump station discharge

pressure to various solid concentrations for a 10 inch size pipeline.

The results were discussed with the client who has taken them

under consideration. No operating and capital cost estimates

were performed.

An additional sensitivity analysis was performed on both

8 inch and 10 inch pipe size design with respect to two route

changes from the original route profile. The length of the changed

routes were approximately the same as the original route length,

but the elevation profiles were different. Table 9 shows the

sensitivity of both 8 inch and 10 inch pipe hydraulic design to

route changes. For an 8 inch pipe!ine the.route changes did

not result in any significant changes in the hydraulic design,

except for route change 1, where the slack flow choke pressure

requirement is only 736 feet compared to 1082 feet for both the

original route and route change 2' Similarly for a 10 inch diameter

pipe the hydraulic design for route change 1 differed from the

original profile^, Whereas route change 2 did not affect the hydraulic

design at all compared to original profile. The result of this

study was also forwarded to client.

Later on, the client came up with a new terminal station

site which was about seventy miles away from the terminal site

used in the original study. Four routes were analyzed to reach

Page 58: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

Evaluation of Throughputs for Phosphate Slurry Pipeline

50 55 60 65Concentration

by weight

DesignParameters

Particle Size (Mesh) -100 -100 -100 -100

Operating (ft/sec)Velocity ^Tt'secJ 5.0 5.0 5.0 5.0

Flow rate(gallon/minute) 1,286 1,286 1,286 1,286

Solids Throughput(million tons per year) 2.0 2.3 2.6 3.0

Pump Station Discharge Pressure(PSI) 924 1010 1090 1190

Page 59: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

TABLE

9

Sensitivity

of

Both

8 Inch

and

10 Inch

Pipe

Hydraulic

Design

to

Route

Chang

es

Route

Change

2OrH 50

oorH1

5.0

2.0

924 CM

rH

ld in CO LO o oCO CO . 1—1 CO CM

'i LO • CM 00CO H

rH -<u o o o o O

CD CD H o . • CM O+-> C o H in CM CT> rH3 tO in 1 rHO SZ/V t ̂UL w

in in O oCO rH o ini • . CT> o

in CM rH

rO O)C r—•r“ T—o>u- o o o O■i— o o in o • • CM CM&- s- »"H r—H in CM a»o Q- 1 rH

CM<U<u cn+J C 00 in CO CO O CO CM

3 <0 CO in • • T—H COo -c i in CM CO Oa: o i—l i-1

rH(U

a) cn +J c 00 in in CO O CO CO3 <a CO CO • • rH COo sz i in CM CO r-*oc o rH

r-(T3 (UC i—•r- •!■—CJ)4- 00 in in CO O CO CM•I— o co CO . • rH 00s_ S- i in CM co oO CL- rH rH

-oco CU CLL

C -—■ 0) >) o CO cn S-O -P N C +-> cu sz s. 3

<o ■r— SZ •r- o ■i— CO o «3 to(/) c +j cn CO *r- o +-> +J sz i/)i. •r— (O *r- +J o s- 3 u cu<D E S- CU CD 3 1— <u CL C S> tS) CU+-> O <L) CO +-> s r— JO CU Q. SI O «3 •r— S— Q-cu Z -M d) >, C CJ t- > crvr- cu O 3g cu x: S- CU >> •r- S- JZ +J 3r— >, CO CU(O cu e o S. OJ3 4-> +-> CO 5 <u O r— Q. CO •—i ^ •i. a (O c 3 C S- CO CU o cu i- ’1- S- E <v <S) O+JfO ■r" •!— *r— r— O to *r- E «—1+- sz E cu 3 S- D_ SZ M-D_ Q- O'—' cou-— Cl. Q — - --------- 1—̂ Q. | Cl. --- ' o —

Page 60: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

the new terminal site from the old terminal site. The client

requested Bechtel to perform a sensitivity analysis of the 8

inch pipeline system to these new routes. The pipeline was designed

for a throughput of 240 tons of solid phosphate per hour (2 million

short tons per year) as used in the original design. The design

concentration was selected to be 65 percent by weight and particle

size -65 mesh as used in the original design. The design operating

velocity was selected to be about 5.2 feet per second based upon

the estimated deposition velocity. Table 10 shows the hydraulic

design parameters for an''8 inch pipeline system, obtained through

the Bechtel's computer program. The pump discharge pressure,

pump station horsepower, number of pump stations and the steel

requirement for the API-5LX60 grade pipe with tapered wall thickness

were also calculated by the Bechtel computer program. The difference

between the design and operating discharge pressure is due to

the fact that an 8 percent design flow safety factor had been

used, i.e. the operating flow rate is 8 percent less than the

design flow rate. After consultation with the client, two routes

were selected for additional study. Routes B and D were selected

based on fewer required pump stations, lower horsepower, and

lower steel tonnage requirement. Routes B and D were each combined

with the original route length of about 25.58 miles. An engineering

analysis was performed on these combined routes for a 10 inch

pipeline at the request of the client. Table 11 shows the hydraulic

design for a 10 inch pipeline system for the combined routes.

For the combined route B plus the original route, it was calculated

Page 61: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

Evaluation of Routes for Phosphate Slurry Pipeline

Aj B CRoutes

Design Parameters

Length, miles 77.8 66.6 67.3 68.<

Throughput, TPH 240 240 240 240

Slurry conc. Wt% 65 56 65 65

Flow rate, gpm 920 920 920 920

Pipe Diameter, inch 8 8 8 8

Average Velocity 5.3 '5.3 5.3 5.:

Number of pump stations 3 2 2 2

Discharge Pressure

Design 1477 1827 1627 1950Operati ng 1196 1479 1318 1579

HP required per station

Design 933 1154 1027 1231Operating 755 934 832 997

Tons of Steel 3891 3585 4050 3932

Page 62: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

Evaluation of Combined Routes

For a 10 Inch Pipe Size Phosphate Slurry Pipeline

Design Parameters Original OriginalRoute + Route B Route + Route D

Length of the pipeline(miles) 92.18 94.48

Throughput(million short tons per year) 3.22 3.22

Slurry concentration(percent by weight) 65 65

Particle size distribution(mesh) -65 -65

Flow rate(gallons per minute) 1480 1480

Pipe Diameter 10-88 miles 10(inches) 8-4.18 miles

Number of pprnp stations 2 2

Plimp discharge pressure (PSI)

(1) pump station one 1600 1600

(2) pump station two 1230 634

Choke station (feet) 300 —

Page 63: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

that slack flow will occur at mile post 88. An 8 inch pipe size

was selected for the iremaining length (4.13 mile) of the pipe

to avoid slack flow. The choke requirement for this station

was found to be about 300 feet. Following instructions from

the client, further work on the 10 inch pipe system was discontinued.

Equipment Sizing:

A detailed design was performed for an 8 inch pipeline system

for both the original route plus route B and original route plus

route D.

Table 12 shows the quantity, size and description of the

major components of the 8 inch pipeline system for combined route

B and original route.

Similarly, Table 13 shows the listing of major components

of the pipeline system for route B plus the original route.

Operating Cost:

The operating cost estimates were made for the 8 inch system

for both the combined routes, following sizing of equipment.

The capital cost estimates were performed by the capital estimating

group and they are not reported here.

The operating cost was estimated using Bechtel's in-house

information. Table 14 shows the operating cost for Routes B and D for

an 8 inch system. The components of the operating costs are

power, labor, maintenance supplies, and corrosion inhibitor.

The operating cost comprises power required to operate the mainline

pumps at the pipeline mouth and intermediate stations as well

Page 64: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

LOCATION

Pump station at mill site

Pump Station No. 2

EQUIPMENT QUANTITY SIZE

Slurry tanks 2 321x321 dia. x ht.

Agitators 2 125 ph each

Mainline pumps 2 1700 p

Variable speed drive 2

Motor 2 1400 hp each

Centrifugal pumps and driver 2 75 hp each

Station building 1 601xl501

Control room 1 151x401

Corrosion inhibitor system 1

Slurry Tank 1 321x321 dia. x ht.

Agitator 1 125 hp

Mainline 2 1700 p

Variable speed drive

2

Motors 2 1000 hp each

Centrifugal pump and driver 1 75 hp

Water pond 1 1021xl021xl3.51

Station Bldg. 1 60'x901

DESCRIPTION

4600 bbl. each

Piston pumps

With gear reducer

920 gpm @ 80 ft.

Heated and ventilated

Heated and ventilated

4600 bbl'i. each

Piston pumps

With gear reducer

920 gpm @ 80 ft.

Heated and ventilated

Page 65: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

LOCATION EQUIPMENT QUANTITY SIZE DESCRIPTION

Pump Station No. 3

Terminal at Dewatering plant site

CommunicationSystem

Pipeline(ExternallyCoated)

Slurry tank

Agitator

Mainline pumps

Variable speed drive

Motors

Centrifugal pumps and driver

Water pond

Station Bldg.

Slurry tanks

Agitators

Slurry emergency pond

Choke Station

Leased telephone 1 i nes

Microwave radjo system

Steel Tonnage

Plug Valves

Ball Valves

>5608tons

1383

321

321x321

125 hp

1700 p

1200 hp each

75 hp

85'x85'xl3.5'

60'x90‘

4600 bbl. each

Piston pumps

With gear reducer

920 gpm @ 80 ft.

Heated and ventilated

561x481 2200bbl. each

250 hp each

132'xl32'xl3.5

2 chokes Cerami c- Design Head Drop 230 ft.

O.D. = 8.625" APIM5LX60

pipelength =95.8 miles

900 ANSI600 ANSI300 ANSI

900600300

ANSIANSIANSI

Page 66: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

LOCATION

Pliffip Station at mill site

Pump Station No. 2

EQUIPMENT QUANTITY SIZE DESCRIPTION

Slurry tanks 2 32'x32' 4600 bbl. each

Agitators 2 125 hp each

Mainline pumps 2 1700 p each Piston pumps

Variable speed drive

2 With gear reducer

Motors 2 1300 hp each

Centrifugal pumps and driver 2 75 hp each

920 gpm @ 80 ft.

Station Bldg. 1 601xl501 Headed and ventilated

Control Room 1 151x401 Heated and ventilated

Corrosion inhibitor System 1

Slurry tank )1 32'x32‘ 4600 bbl. each

Agitator 1 125 hp each

Mainline pumps 2 1700 p each Piston pumps

Variable speed drive 2

With gear reducer

Motors 2 1000 hp each

Centrifugal pump and driver 1 75 p each

920 gpm @ 80 ft.

Water tank 1 93 'x93'xl3.5'

Station Bldg. 1 60'x90x Heated andventi1ated

Page 67: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

(Table 13 continued)

LOCATION

Pump Station No. 3

Terminal at plant site

CommunicationSystem

Pi pelineExternallyCoated

EQUIPMENT QUANTITY SIZE DESCRIPTION

Slurry tank 1 321x32 * 4600 bbl. each

Agitator 1 125 hp

Mainline pumps 2‘ 1700 p Piston pumps

Variable speed drive 2

With gear reducer

Motors 2 1000 hp each

Centrifugal pumps and driver 1 75 hp

920 gpm @ 80 ft.

Water tank 1 85'x85'xl3.5'

Station Bldg. 1 601x901 Heated and ventilated

Slurry tanks 4 561x481 22000 bbl. each

Agitators 4 250 hp each

Slurry emergency pond 1 134,xl34'xl3.5l

Leased telephone 1 i nes 1

Microwave radio system 1

Steel tonnage 5708tons

O.D. = 8.625" Pipelength =

98.3 miles

GradeAPI-5LX60

Cathodic protection system 1

Plug Valves 1383

900600300

ANSIANSIANSI

Ball Valves 3 900 2 600 1 300

ANSIANSIANSI

Page 68: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

ITEM

Annual Operating Cost for Phosphate Slurry Pipeline

(Thousand Dollars)

ROUTE B Plus Orginal Route

Power

Labor

Mai ntenance Supplies

CorrosionInhibitor

SUB-TOTAL

CONTINGENCY

370.0

451.0

501.0

16.5

1338.5

201.0

1539.5

ROUTE D Plus Original Route

384.0

451.0

501.0

16.5

1352.5

203.0

1555.5

BASIS: 1st quarter 1981

Page 69: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

as agitated slurry tanks, and charge pumps, skilled and semiskilled

people to operate and maintain the pipeline and pump stations

and the central control system at the pipeline mouth. Lime is

used for corrosion inhibition inside the pipeline. The maintenance

and supplies include the pump parts and other parts annually

to keep the pump station and pipeline running smoothly. Finally,

a contingency allowance of 15 percent is added.

Page 70: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

FEASIBILITY OF A COAL SLURRY PIPELINE:

A short feasibility study was undertaken for the design

of a coal slurry pipeline for throughputs of 3 million short

tons per year and 5 million short tons per year.

The pipeline was designed for a flat terrain.

Hydraulic Design:

Table 15 shows the major hydraulic design parameters and

equipment sizing. Due to the very preliminary nature of the

study, ho rheological tests or tests to determine the operational

characteristics of the slurry were performed. The rheological

data used was from inhouse data.

Capital Cost Estimate:

Table 16 shows the capital cost for the major components

of the pipeline systems. It gives rough order of magnitude capital

cost estimates and no input was sought from the cost estimating

group.

Feasibility of a copper concentrate slurry pipeline:

A preliminary feasibility study was undertaken for the design

of a copper concentrate slurry pipeline. The pipeline was designed

to transport three thousand tons per day of copper concentrate

along a 52 kilometer long route.

Hydraulic Design:

Table 17 shows the hydraulic design parameters and major

Page 71: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

Throughput (million tons/year) 5 3

Design Parameters

Length (miles) 250 250

Specific gravity of slurry 1.184 1.184

Concentrating solids (wt%) 50 50

Outside diameter (inches) 18 14

Number of pumps (including 1 spare) 4 3

Number of pump stations 4 5

Horsepower per pump 1300 1350

Average wall thickness (inch) (including corrosion allowance) 0.50 0.45

Type of pumps Positive PositiveDisplacement Displacement

Grade of pipe API-5LX60 API-5LX60

Weight of steel (tons) 61794 43062

)

Page 72: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

TABLE 16

Capital Cost Estimates for Coal Slurry Pipeline

(Million Dollars)

Throughput (million tons/year) 3 5

Installed pipeline 63.0 86.0

Installed pump stations 38.0 41.0

Slurry preparation andDewatering facilities 45.0 60.0

Indirect costs 49.0 60.0

Total 195.0 247.0

Page 73: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

TABLE 17

Hydraulic Design Parameters for

Copper Concentrate Slurry Pipeline

Throughput(metric tons per day)

Length of the line (kilometers)

Particle size distribution

Solid concentration (wt%)

Outside diameter (mm)

Average wall thickness (nm)

Number of pumps (including one spare pump)

Pump discharge pressure (kgm/square cm.)

Type of pump

Grade of pipe

Weight of steel (tons)

Number of slurry tanks

Size of slurry tanks

3000

52

-65 mesh, 80%through -325 mesh

60

168.275

6.35

2

115

Plunger type reciprocating pump

API 5LX-52

1455

4

10 m diameter 8 m high

Page 74: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

equipments listing for this study. The slurry enters at an elevation

of 400 meters and discharges: at an elevation of 45 meters. The

pipeline has been designed as a tapered wall pipeline taking

into account the changing operating pressure due to friction

losses and changing static heads along the pipeline route.

Capital and operating costs:

The major equipment listing for capital cost estimates

are given in Table 18. Some of the cost figures were acquired

from the vendor over the telephone. The other cost figures were

developed through in-house information without getting a detailed

input from the cost estimating group. The labor cost and power

cost have not been included in the operating cost Table 19 due

to the nonavailability of unit cost for labor and power at the

time of the study. However, the total power requirement was calculated

to be 7.2 million kwh per year, and the labor requirements were

estimated to be 8 operators and one pipeline superintendent.

Page 75: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

TABLE 18

Capital Cost for Copper Concentrate Slurry Pipeline

(Million Dollars)

Installed Pipeline 2.9

Installed Pump Station 3,8

Indirect Costs 3.3

Total 10.0

Page 76: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

TABLE 19

Operating Cost for Copper Concentrate Slurry Pipeline

(Dollars Per Year)

Pump Maintenance Supplies $ 52,000

Other Maintenance Supplies 93,000

TOTAL $145,000

Page 77: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

PREDICTION OF FRICTION LOSSES FOR A COAL SLURRY PIPELINE

Friction losses were calculated for a coal slurry for various

concentrations. The information was needed bV a project group

to size the pumps for the under flow slurry obtained from the

slurry thickener in the separation plant. A 2-inch diameter

pipe was supposed to be used. The coal slurry obtained from

the bottom of the thickener was observed to be highly stable

and homogeneous. The calculated transitional velocity was estimated

to be higher than the desired operating velocity. Thus the concerned

auxiliary equipments were designed to pump the slurry in the

laminar region. The rheological data were obtained through labora­

tory testing and indicated that slurry behaved as a Bingham

plastic slurry. Theoretical equations given in Govier and Aziz

were used to predict theoretical friction losses.

Table 20 shows the measured Bingham viscosities, yield stresses,

calculated transitional velocities and predicted friction losses

for different concentrations of slurry.

The procedure used to estimate friction losses is given

as follows:

(1) Calculate Bingham Reynold number

NRe = ^n

(2) Calculate Hedstrom number

n

Page 78: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

Prediction of

Friction Losses

for

Coal

Slurry

<DC r— O *r-*r- u) £+■> <UU Ifl f•f w wS- O Q.

<TJC >y—'o +->o•r— -r— dj-M O i/I •r— O *''** (flr- <P C <U 4 - <0 > —- s-

C ME </> u

</» ">s.CU </)s. 0)

I-a'aj>• oo >,

o

>,CD+JC•r— t/1 Q_ -t-> O O •r- U — 'S </>

OO4 - 4-> > , •r— -i— S-a > s-QJ «J 3 Q. i- i— OO O VI

co

S- + J -M .C e cn <u •*- o cu §* o >, .a

s-^-*

oo

CT» 00 CMO in o\CM r** CM

00 r—• • •un CM 00r— CVJ

o oCVJ

oo©

03CVJ

C Min

00 UO CSJC* r—o o r—• • •r-~ r— r—

inC M

OcnLficn

Page 79: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

(3) Get Y = f(eo) using

NRe = i Heltl8 eo

(4) Calculate f u s i n g Newton-Raphson technique

V ».1 = 4/3 £0 + 1/3 e04

where NRe = Bingham Reynold number

v = Slurry velocity

D = Pipe diameter

n = Bingham viscosity

p = Slurry density

t = Yield stresso

NHd = Hedstrom number

Page 80: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

CHAPTER 4

SUMMARY AND CONCLUSIONS

This report serves the purpose of explaining the various aspects

of my internship at Bechtel Petroleum Inc. at San Francisco. The

internship was served in the slurry systems group of the pipeline and

production facilities division.

The specific objectives outlined in Chapter One have been met.

The requirements for internship in the Doctor of Engineering program

are two fold: first, an intern is supposed to make an identifiable

technical contribution to the company; second, to enable the student

to work in a nonacademic environment where he can see the organizational

approach to the industrial problems. It was the second objective which

I believe proved most beneficial to me. I think the training I have

received in the Doctor of Engineering program,especially one pertain­

ing to economics, business law, systems engineering, communications,

management, human interaction, reward-punishment motivation, conflict

resolution in a project environment has helped me understand and

perceive things during my internship in a logical manner.

Page 81: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

APPENDIX - I

Pipeline Route Profile Data for Iron Ore Pipeline.

Page 82: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

PIPELINE

ROUTE

PROFILE

DATA

S TI— <U < +-> > aLjJ E _l—' UJ

o o o o o o o o o o o o o o o o( • • • • • • • • • • • • • a *L O O O O O i n a o o m i n i n o o c M i n i n o i noor**ra> » L O i o ^ r c o i o i O L n c M O O r — cQLQ

inz s- o a>H-• +->I— aj <C E o oO I—

o o o o o oCMr- o

p>. LOO O O O O O *3-

o o o % o « — c M c o c o ^ - ’̂’ L O v o r v . c o t n o o c M C M C O c o c o o o c o c Q o o e o c o c o c o c o ^ ^

I—• s. h— a» c -M > <u

o o o o o o o o o o o o o o o oO O O O 00 O LO O O LO O O LO LO LO LO OLOOLOOLOO^LOOCDr— LO'SfLOLOO CO CM CM c— r— r-r—r— r— f— r— r— r— »— CM

</)2= S- O CU ►—i +-> h-> cu <C E o o O r—

LOLO

r*̂co o00

00 LO i—CM00

CO 00 00 o cm m O O CM O O O O

COOOOOCT*CT»CT>Or— i— CM fO «t r-r- r - r - r— r— CMCMCMCMCMCML OCM

0 -~ *1—I S- t— (U < +-* > a

o o o o o o o o o o o o o o o oO LO o r— co in

CM CMO L O O O O O L O O O O O O Oc o L O i n r ^ c ^ o ^ f L n o L O O L O i nC M C M C M L O i n i o v o r ^ r ^ L O i O L O L O

uj

inZ s- o tt) ►-« +-> h- a < E o o o <—

r— in in cm p*» in lo o co in cm c o o i n c o o ^ - a r > n ^ } - i — r^.cMcocooo

O i — c M c o i n o o a % o * o O r — <— c m c v i c m *̂ 16.0

450.0

25

.7 29

5.0

40.55

65

.0

16.74

40

0.0

26.0

270.0

41

.0 75

.0

17.13

35

0.0

27.0

190.0

42

.0 90

.0

Page 83: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

PIPELINE

ROUTE

PROFILE

DATA

CONT

INUED

2 T5 2> a> u i e

o o o O o O o O o• • • • • • • • •

IX) CM CM in m o CO CM in<x> CT» r— i— CM CM in inin in lO VO <£> VO lO io io

tnz s- o <u

• +j

< i o S o •—

o o o o o<T> I—

CM CO

00o o o CM

in in 1000 00 00 00

2 Ti— cu <C -M > a>

O O o o O o o O O o o o o o O o o o o• • • • • • • • • • • • • 9 • • • • •

CM in in 00 in 00 in in o o CM in CO o o in in m inCM in CM r>. 1— r". CT> CM f— CM CM in <3- r>. 00 cx>CO CO CO ro CM CO CO CO in in in in in in in in in

UJ

</iz i- o a •—i +-> i— <u < E o o o >—

CMo O o o r>. o o o o o o o o O o o o o• • • • • • • • • • • • • • • • • • •CM CO in in io 00 cn o r— CM CO CO un io 00<£> 10 10 10 10 (0 10 10 i0 r>. r*. r-. r*. r** 1̂ p*. r-'* !■*«.

o - —*HI U o o oh- <u • • •< o o in> <u o CO cnLU E r— f—_ J — ' U J

O O O O OO O LO O CMo ^ if) O'

r - r— I— CM

o o o o o oCM LO CM CO O LDU3 r>. CO r̂ . I— LOCM CM CM CM CO CO

o o o o ocm o o in os s m io nCM CM CO CO CO

COZ j-o <vt—4 +J o o o o1-- <D • • • •< c = cn m VOo oo r—

o o o o o o o o o o o o o o on co

^ •3’oin

r - M n - f i n k O N O Di n i n i n m i n i n i n i n

cnin o i—10 vo

Page 84: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

APPENDIX - II

Optimization Output for Iron Ore Pipeline

Page 85: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

a. z«/> a 09Z H H- o< l/J-'* aa o <* CMk y

< Het </) ui a a o a

tm i/ia. o< u y

z§5

o<t- CLO X aK

az z0 3 1 -Z 0. u» CM

>m a f*-U Ulo </l ▼j ' v •UI t- r*> u.

CM3a s in-i a *•Ik (9

X< in►H U) CMO ui (0XUI U 0)a z

UzO H* O 3

m ao i- z li.

UI Oa w

8

zo ~m in oH ■«-> V CM< k n id> Ik *■UI w

8 2H* O< z

Page 86: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

a. z«/> oZ K K *< to \ 00a o <*K O

(— «* •< K O r»B V ) Q 0)w O Oa. U —o

-1 .< <* in* - 1 - 0 CMH i / i g Ofa. a o 0>< o *-u

a & 3 Z a.

h a a z

3 K- CL (/)

> Z UlH < QM O r- h QU UI I/I oO Ui ►«J S • oUi 1- t-> u.

3CN

zo z in o-j a Mu. a H •*»•

z

< K > U. Ui w

< in Ui►1 in CNO ui <0

XUi u 0)a z

Na Z

u s *8 o

M •K Oz o < z

O H in H-O 3 V)

n CN<0 a>

J.n CO na

0) O(0 (0— ow *“

« n

Page 87: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

Q. Zui a nZ »- H t-< IflN 09a o «» toH (J

H- W< h O f*BIAO 10ui O O PJQ. U —a_i< «* VH- t- o wM«ig (00.0 0 Cl< (J CMo

CLN Xa. 3 aZ a.

Z in8 •”Z «/>

. j<h- a.a x

0.z z0 3 K z a. </>

>O Hz u .

H < Q>-• O r - QU UI (/> oO </> *J N • Q wUJ K p*> u .

Scm

zo z in o- i a . Mu . (9 H ^

Z

< H> U. Ui w - J

< in UiN V) CMO u i (0

X •Ui U o>& zM <-» Na . z

o *«8 o

H O*z o < zO t - m HO 3 1/)

r*> CN r- (0n OCM (0 oPJ (0 OCl Cl

in n CM « P>CM 0) o in

n 01 f " CM r«*

cn n

Page 88: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

a zcn a nZ t*h <0< WN. «a o «* CM»- u

< h Oat tn q Ui o oOl U —o

w WQa o o< o u

aN Z COa. a coX a

z cs8 •“Z «/>

k a a x

a.z z3 t-aiA n

> Z U.H < QM O o K QU ui in oa <n a*

• QUi H- (0> Ik

3in

Za z * O-j a. MIk o t- —*

z< K> Ik Ul w -J

< in UlM (/) CMQ ui <0X •Ul o 0>a. zM M \

o* o *-U 3

Page 89: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

a. zcn aZ l - H 00< (/> N ona o » »•H- O J.

H- «»< K O 10 OCIAQ <0 WOO <J> 0 .0 '- o

0. N z& 3 Z a.

<h a a x

o.z z3 Ka v)

>O H 2 tH < Q

i- O O ►- ocj ui (/) oO Ui 0> t— ̂

Q wUi t- (0> U.

3in

za z oj a. Mu. (9 H ̂

Z

< H > U. Ui w •J

< in Uim in CMa ui (0

X •ui u a>Q. ZM M \Q. Z

O S * .OO o

MH O

z CM < zO H in HO 3 V)

Page 90: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

a. ztf) oZ H K< l/J-v oa o ** Vh- U

K «* ,< h O 10B V I O CMUi O O ••0. u — o

-J .< «* 0)H H O oM (/) Q0 . 0 0 0>< O —U

aN X& 3 x a

zO t- Z tn

-j< a a x

a.z z§3 t- a «i

>h

Z U.< O S5 <0 «* 0>

)-i CJ O H Q <5 CM <0 nCJ Ui v V) O • • •O in 0) M ^ CM <N

• O W n 00 nUi K > UL

(0 CM

o z-i a. ik oo . . • •M in 00 10 0>H « O n< K n * (0> U. Ui w

CM

z< in UlM l/t «a ui (0x •Ui CJ 0>a. ZM Ma. zo * .

8 cH •t- oz CM < zo t- in H*O 3 (/)

cn m

Page 91: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

a. zto o ASZ t*h I"< C/»N <oa o <*K o

h~ «* •

< H* Q f*ac in Qui a o a>a o —a

_» .< * (0H K O o•-I/JQ 0)Q. O O n< U —O

& N X & 3 Z 0.

z

<H O. O X

az zO 3 H Z 0. U) «

hM U Oa u Oo <n inj \ •UJ K 10> U.

in3 CNO X n-i a.u. a

z< • in*■* (A MO UJ (0XUJ CJ ona. zM Ma.

OO

z •»O h- inU 2

8

< H n > u. ~

*- o < z

Page 92: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

a. zoZ K K 01< U»N Ola o «»h- U

t- * .

< k o p*k i a q ou O O ©a u —a

-i .

< «* inK h OM i A O (0a. o O in< u ~u

0. \ S & 3 Z a

ZIS

<►* a o z

az z3 H0. l/J Cl

h»M o OU W OO V) in-IN •UJ K (0> U.

ins CMo z «-I (LIk (9

Z< inN V) CMO ui (0

zUJ (J o>a. za

o

OJ«o

zO h- inU 3

o »- Z li. < QH Q (/) OM **"o W

►- o < z

o • • •M in * 09h (0< 1- n ▼ m> u. CMUJ w

■»" cv n

Page 93: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

a zin o t-Z 1“ h< na o nt- o

a mN Ja. 3 COX a.

zS •“z </>

<H Q. O X

a.s z0 3 H Z Q. (/>

O H> Z U.H < O O r«» <0 (0M CJ O H O O O (0 t»*U Ul O </> O • •O «/» in tx »• 'T CN CM

O ' W 0> nUi H <0 CM> u.

ID3 CN za z n a • • • •-i a M ID CN o (0ik a •v ID (0

< k- n O o 10> u. CNUi ws -1

< ID Ulw V)Q Ui (0Xui u o»a. z

sa zg oo *4 •o x H O •r- CM nz < zO 1- . ID 1-O 3 10

Page 94: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

CL Zl/J -Q— 00Z K t- 0)< I/IN CMB O » nt- (J

H< HOC I/I Ui O & U O

J< t-M I/ia. o< (j u

a. P-s z 10a 3z az no *-z </>

-1 p»< oH Q. 00o z 00H

§Q.z z3 Ha v)

> Z u.H < Q** (J CM H QO Ui 00 t/» oa v> (0JN • O ̂Ui ►» f*> u.

3 zO Z CN o-1 0.ib a h ̂

z< >- > u.Ui w -1< in UiM (/) CMa u (0z iUi u 00a. zM M Va. z

.00 oH►- oz (0 < zO H in HO 3 i/i

8to a> *- cm

Page 95: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

0. zV) o2 1 - K<«/)>* nB O < * 10H CJ

t - * .< h OK Ul QW O Oa o * .o

,< * 101-H O On i/iq Va. o O 00< uu

a. s z & 3 z a.

z§ in

<*- a o x

a.x z3 Ha. (/) cn

M CJ U Ul O V) -1>«* Ui t—> u.

a x _i a.Ik <3

ui ̂ O H< Q Q Cl a

CN H Q O (0 01CO V) o • • •(0 M IO a o

Q w n t - nr* CN

zCN o • * • •

M in 01 cn CDH ̂ Cl< H m CJ 01 IO> u. CN *•

X< IO UiM U> CNO ui (0XUl U COa zM M sa. zO oO ►« ■o x H Oz CO* < zO *- in HCJ 3 Ul

cn cn

Page 96: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

Q. ZV) O (0Z H K P>< W » N mKOW p*H- U

H- «* •< h OCL M Q oui O 0 ’T0. U —o

-J .< «*H t-O o» «/» Q COCL O O< o CMu

z § £

<h- a. o x

&X z0 3 1 -zaviUiu>H 2 fc „ < O C3 N<-• O CM h o 25 o>

U ui CO in o • •O </> V M ^ nJ \ Ui K > u.

p*Q w m

« 10t- os

O cn (0 O ex

o Zmi a.ib <a < H-

> u.

ID in eM o 01«* O CM CO CMn O (0 o*“ CM

<m cna uui oQ. Z

o»-U 3

o < z— <n n

Page 97: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

a. zvi oZ H H (0< i/jv . Va o ** CMH (J

a.N SCL 3z a.

-i

h> a o z

a.z z3 H-a. i/i d

•- ou uio wUJ H > U.

o z_j a. u. (9

8. a w CM

r«» CM

(0 za • • •M in <0H r*< H m in CM>'U. *• **

X -1< in Ul1-1 </> CMa ui (0i •Ul CJ ®0. z«-H M sa z

u X 8 o«

I- oz CO < zO K W HCJ 3 l/J

Page 98: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

G. Zui o 0)Z H H p-< w v .C£ O ¥* *H CJ

t- *< h O ata u t o (Oui a Oa. (J —a

,< «* <0H H O aom i/i u piL O O 00< « ’•u

a. s a a 3 X a.

z a h z V)

<h a. o x

OLz zO 3 Hz a ui

>H

O H Z U.< 2 5S 0) toM O H O c5 - <o

U Ul O v> O • •O V) w H *■ in at

• O w n I** nUl H CM> ik

3 *<0 Zo z o-J Q. MIk o H '**

z< H > Ik Ul w

< IO Ul1-1 V) <NO ui <0

XUl u 00a z

Na. z

O X .OO o

HH O

z 00 < zO H IO HO 3 Ui

10 CM •» 910 0) (0« CM at IOCM

— <n re

Page 99: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

a zin aZ h t- 9< IflScc a «* (0*- u

H «» •< t- O o>B I A Q CMU O O n0. u —o

-1 ,< <*H l - Q COix (/) 6 (0a o o< <j ~ CMu

0. r-s z oa. 3 00z a.

Z ino *-z in

<H- O.o z

OLz zO 3 h Z a. </>

>h»

O H2 t -< O C5 0» I** 0>

<-> O K O <5 in ao «U UJ O V) O • •a i/i CM M —■ n CM 01j \ • O w n 10 O ntu t— r» CM CM> u.

*a z- j a. u. (9

z< in11 l/l CMa in 10ziu v 00a. za.

g

o ̂O

z soO 1- inu »

a • • • • •IX in n 10 m CM(- (0 0> n n< h- n 0) 10> u.UJ w

H* O < Z ' N O

Page 100: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

0. zin a CMZ h l - (0< W S r»a a1- o

1- .< 1 - 0 oae i/i Q inw o o ata. u —o

-1 ,< «* oH H O 0>m W O p*a. o O< u *■a

a. «S I (0a. sz a

z no t-Z V)

_J ui<K CL Cf»o Z (0H*

a.s z03 1-Z L V I «N

>HM CJ nO Ul ino </> r*»-JV. •Ui (0> U.

3 a»O Z o-i a.u. 0

z< in>-* in «a w (0X •Ul O 00a zM *4a. QO X Oz oO H (0U 3

8

M in o»h* **** n «**< h> <n (0 n> u.Ui w-1Ui

H O< z

Page 101: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

0. z1/1 o P)Z H K p*< lfl\ r-K O «• p>H O

i- •» •< H- O 01KVIQ oUi O OOL y ^a

-j .< 4» 10H H O aohIAQa a o so« o ■»-y

Q. f*S Z aa 3 az o.z ▼

O t-Z in

-I O< OH Q.a z f»H

z z3 H Q. 1/1

>

«-• CJ P>U Ui inO VI r-J N •Ui H (0> u.

3 01O Z o-t alb <9

z< in*■* «/> «O ui 10

z •Ui u 00CL Za.

o

U XO

z oO H- (0U 3

Q w

01 in01 COO

pi 09 p»CM

Zo . . . . m m « 01 al » ^ V 01 09 01< i- « — o in > lb o» *• —Ui w .J 111

t- o — < z

Page 102: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

CL ZUl o UlZ K h 00< ui-v r«»0£ O <* UlH O

.< 1 - 0 000E Ul Q 10uj O O CMa. u »-o

-1< *H K O 00<-. U> © UlL O O »•< o CMo

0. \ s & 3 Z 0.

zO H- Z Ul

J<t- Q.a z

ax z3 Ha. ui

M CJO ui o uiUJ h- (0> u.

9 at zO X o o-i a. Mu. a H» '

X

< K> U. UJ w _J

< Ul UJ►* Ul CMa uj (0

Xu cj 00a. zM M \0. Z

O X8 a

h* • H O

z o < Zo t- (0 HO 3t U)

UJ «“»o *- Z U.28 8 ui OQ w

O a o> Ulr* 01

CM pi Ul oipi <0 o PI

CM CM

(0 * CM <0CO (0 00 ̂0> P» ^

Page 103: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

APPENDIX - III

Computer C ertificate Courses

Page 104: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...
Page 105: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

I

l

£

>s*

«S3

'52

6 ?

< 3

“3Q£

1

*«5 IJ; .0

I " U* I

s §I ^v$* Vj

§ 1 :

IV J k i

£ ^ i

' ^ 1

^ v>

L Ueae?

xL U

Page 106: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

I

1 U

5

‘53

GOU JC£zsg j

!

£ | *N %

6n u

* I

' I ^ ^ 1

I ^Vj

§\ & S ' S* &

'c: &

C/3> -CO

ts

UJ

OOcn

CSJcnjU J

Page 107: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

CO

- 3 i

I*•5 1

$ -. I

^ §

' S y

8 1

$ 1s ^§ « 5

$ vs

a ^< 1 V

«=cC£UJ

VD

^ «4o §os * a .

UJ

oUi

Page 108: An Internship Report ATHAR JABBAR QURESHI Submitted to the ...

VITA

NAME: Athar Jabbar Qureshi

DATE OF BIRTH: June 8, 1951

PLACE OF BIRTH: Hyderabad, Pakistan

PARENTS: Abdul Jabbar and Hamidunnisa Jabbar

EDUCATION: Bachelor of Engineering in Chemical Engineering from the University of Karachi, Pakistan, 1974. Master of Science in Chemical Engineering from Oklahoma State University,1977.

EXPERIENCE: Engineer, Bechtel Petroleum Inc., San Francisco, California 1981-1982

Department of Chemical Engineering, Texas A&M University, College Station, Texas, 1979-1980

Hoechst International Company, Karachi, Pakistan, 1975- 1976

This report was typed by Virginia Woods and Dianne Wauters


Recommended