+ All Categories
Home > Documents > AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Date post: 20-Jan-2016
Category:
View: 219 times
Download: 1 times
Share this document with a friend
Popular Tags:
49
AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011
Transcript
Page 1: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

AN INTRODUCTION TO MICROPILES

CIVL 141Spring 2011

Page 2: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

A Local Situation:5

to 1

2 fe

et(v

arie

s)

35

fee

t

Fill (SM /SP-SM /SW -SM ) = 101 pcf'C S = 32°c = 0

F ine sand w ith s ilt(SP-SM ) = 95 pcf'C S = 32°c = 0

S urface (E levation = 1200 ft m sl)

W ater Table(as observed at the tim e of drilling)

Page 3: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

A Shallow FootingDefinition:

B

D f

Df/B < 2

Page 4: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Capacity of Spread Foundations(cohesionless soils)

F

qq ult

allow

γγqqult CNBγ0.5CNσq

Page 5: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Capacity of Spread Foundations(cohesionless soils)

F

qq ult

allow

γγqqult CNBγ0.5CNσq

THIS ONLY CONSIDERS THE SHEAR STRENGTH OF THE SOIL;WHAT ABOUT SETTLEMENTS?

Page 6: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Settlement-Based Capacity

• Use a bearing pressure that results in meeting some allowable settlement.– Less than 1 inch of total settlement; or

– Less than ½ inch of differential settlement.

Page 7: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Settlement-Based Capacity

• Use a bearing pressure that results in meeting some allowable settlement.– Less than 1 inch of total settlement; or

– Less than ½ inch of differential settlement.FOR COHESIONLESS SOILS (SANDS),

THIS CRITERIA GENERALLY CONTROLS. THE LOST CAPACITY FROM

SHEAR STRENGTH CAN BE SIGNIFICANT.

Page 8: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

FOR MANY PROJECTS, THERE IS MOTIVATION TO INCREASE THE BEARING LOAD WITHOUT ADDITIONAL

SETTLEMENTS

OR SIMPLY REDUCE THE EXPECTED SETTLEMENTS ALTOGETHER.

Page 9: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

FOR MANY PROJECTS, THERE IS MOTIVATION TO INCREASE THE BEARING LOAD WITHOUT ADDITIONAL

SETTLEMENTS

OR SIMPLY REDUCE THE EXPECTED SETTLEMENTS ALTOGETHER.

HOWEVER, A CHALLENGE EXISTS TO DO SOWHILE MAINTAINING CONSTRUCTION BUDGETS

Page 10: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Lower the Bearing Pressure

Page 11: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Lower Bearing Pressures Do Not Always Provide Less Settlement

2B

Hard bearing layer

Com pressib le layer

Hard bearing layer

B

qallow = 2,000 psf

Page 12: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Lower Bearing Pressures Do Not Always Provide Less Settlement

B2B

Hard bearing layer

Com pressib le layer

Hard bearing layer

qallow = 4,000 psf

Page 13: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

More-Often, This is the Observed Design Situation

2B

Com pressib le layer

Hard bearing layer

B

Page 14: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Currently Available Alternatives For Reducing Settlement

• Densify Bearing Soils– Over-Excavate and Recompact– Rapid Impact Compaction

• Deep Foundations (drilled shafts or piles)• Intermediate Solutions

– Rammed Aggregate Piers– Helical Piers – Micropiles

Page 15: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Over-Ex and Recompact

3 '

2 '5 '5 '

Page 16: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.
Page 17: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.
Page 18: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Micropiles

Page 19: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Micropiles

• Micropiles are high capacity, small diameter (typically 5" to 12") drilled and grouted in-place piles designed with steel reinforcement to primarily resist structural loading.

Page 20: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Micropiles

• Micropiles are high capacity, small diameter (typically 5" to 12") drilled and grouted in-place piles designed with steel reinforcement to primarily resist structural loading.

• Micropiles do not necessarily use hollow-core bars but this is what I will present today.

Page 21: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Micropile Types

Page 22: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Hollow-Core Bar (Fy = 75 ksi)

Page 23: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Pressure-Grouted Micropiles

• This discussion will be limited to hollow-core, pressure-grouted micropiles because they can be readily adapted to shallow foundations.

• Too, flow of grout is ensured over the complete length of the micropile.

Page 24: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Structural Limitations

Ref: FHWA Manual, Section 5

(Through full-scale tests, elastic buckling does not appear to be a design concern and is not considered by FHWA.

(note: IBC uses 0.33 and 0.40 instead of 0.40 and 0.47, respectively)

Compression:

BARBARyGROUTGROUTC AreaFAreaf ,, .. 470400P AllowC,

Page 25: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Structural Limitations

Ref: FHWA Manual, Section 5

(note: IBC uses 0.6 instead of 0.55)

Tension:

BARBARy AreaF ,.550P AllowT,

Page 26: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Geotechnical Limitations

Page 27: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Capacity of a Micropile

TIPLult PPP

Page 28: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Capacity of a Micropile

Ldiam.bit3.141

F

αP soilgrout

L

grout-soil can be 3 to 10 kips per square foot, found from a test;

F typically taken as 2.5;

bit diameter is conservative; and

L = bond length of micropile.

Page 29: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Capacity of a Micropile

qtip; taken as 32 ksf (Reese et al. 1976)

F typically taken as 3;

Rf = 0.6B

2

f

tipTIP diam.bit

4

3.141

RF

qP

Page 30: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Example

qtip = 32 ksf for medium dense sands;

Bit diameter = 0.5 feet;

L = 10 feet

F is 3 for end bearing and 2.5 for side friction; and

Rf = 0.6(0.5 feet);

grout-soil = 7 ksf

Page 31: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Example

kips44feet 10feet 0.53.1412.5

ksf 7PL

kips7feet 0.54

3.141

feet50*60*3

ksf32P 2

TIP

..

Pult = 51 kips

Page 32: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Estimating grout-soil

20 f

t

PV C sleeve

10

ft lo

ng

bon

ded

zo

ne

grout

e lectron ic load ce ll

d ia l gaugereference beam

hydrau lic ram

1-in th ick bearing p la te

1-in th ick bearing p la te

nutR 38 m icrop ile

load ing beam

w ood cribb ing as support

Page 33: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Estimating grout-soil

Page 34: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Estimating grout-soil

BARBARy AreaF ,AllowT,P

BARBARyGROUTGROUTC AreaFAreaf ,,. 850P AllowC,

Structural Limitations During Testing

Page 35: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Grout-Soil Shear Strength from a Vertical Tension Test

10-ft long bonded zone

0 10 20 30 40 50 60 70

L o a d (k ip s)

-0 .2

0

0.2

0 .4

0 .6

0 .8

De

form

atio

n (

inch

es)

Page 36: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Grout-Soil Shear Strength from a Vertical Tension Test

;ft10ft 0.53.141

2.5

αkips50 soilgrout

psi55kips/ft8α 2soilgrout or

Page 37: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Word of Caution (or a Strong Reason to Use Hollow-Core Bars)

Page 38: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.
Page 39: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.
Page 40: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Example situation

0 10 20 30

-80

-40

0

40

80

Sh

ea

r (k

ips)

0 10 20 30

-300

-200

-100

0

100

200

300

Mo

me

nt (

kip

-fe

et)

0 10 20 30

w = 7 kips/foot

35 k ips 35 k ips

70 k ips

Loa

d

Page 41: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Example situation

0 10 20 30

-80

-40

0

40

80

Sh

ea

r (k

ips)

0 10 20 30

-300

-200

-100

0

100

200

300

Mo

me

nt (

kip

-fe

et)

0 10 20 30

w = 7 kips/foot

35 k ips 35 k ips

70 k ips

Loa

d

Assumes no support from soil

Page 42: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Example situation

0 10 20 30

-80

-40

0

40

80

Sh

ea

r (k

ips)

0 10 20 30

-300

-200

-100

0

100

200

300

Mo

me

nt (

kip

-fe

et)

0 10 20 30

w = 7 kips/foot

35 k ips 35 k ips

70 k ips

Loa

d

Shear in concrete – acceptable?

Page 43: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Example situation

0 10 20 30

-80

-40

0

40

80

Sh

ea

r (k

ips)

0 10 20 30

-300

-200

-100

0

100

200

300

Mo

me

nt (

kip

-fe

et)

0 10 20 30

w = 7 kips/foot

35 k ips 35 k ips

70 k ips

Loa

d

Negative moment

Page 44: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Connection to Spread Footing

South Mountain Community College,Phoenix, AZ

Double-reinforced footing (grade beam)

Page 45: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Connection to Spread Footing

Page 46: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

• Proof loading is typically completed on about 5% of the production micropiles.

• Loading is completed to 167% of the Design Test Load.

• Creep test may or may not be completed.

Proof Loading

Page 47: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Proof Loading Mt. Lemmon HighwayMilepost 9.8

Tucson, ArizonaDec. 2009

Page 48: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Proof Loading Mt. Lemmon HighwayMilepost 9.8

Tucson, ArizonaDec. 2009

Page 49: AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011.

Proof Loading Mt. Lemmon HighwayMilepost 9.8

Tucson, ArizonaDec. 2009


Recommended