www.huawei.com Analisis Swap Downtime Project HCPT 2G HCPT Project wireless team 2009-12-28
Transcript
Page 1: Analisa Downtime Project HCPT 2G Swap

Slide title :40-47pt

Slide subtitle :26-30pt

Color::white

Corporate Font :

FrutigerNext LT Medium

Font to be used by customers and

partners :

Arial

www.huawei.com

Analisis Swap Downtime Project HCPT 2G

HCPT Project wireless team

2009-12-28

Page 2: Analisa Downtime Project HCPT 2G Swap

Slide title :32-35pt Color: R153 G0 B0

Corporate Font :FrutigerNext LT Medium

Font to be used by customers and

partners : Arial

Slide text :20-22ptBullets level 2-5:

18pt Color:Black

Corporate Font :FrutigerNext LT Medium

Font to be used by customers and

partners : Arial

Huawei Confidential Page 2

Katalog

• Deskripsi Skenario• Analisis Downtime Skenario• Prosedur Standar Operasi dari HCPT 2G SWAP Outdoor site

Page 3: Analisa Downtime Project HCPT 2G Swap

Slide title :32-35pt Color: R153 G0 B0

Corporate Font :FrutigerNext LT Medium

Font to be used by customers and

partners : Arial

Slide text :20-22ptBullets level 2-5:

18pt Color:Black

Corporate Font :FrutigerNext LT Medium

Font to be used by customers and

partners : Arial

Huawei Confidential Page 3

Deskripsi Skenario

Empat Skenario Utama yang perlu diperhatikan dalam Project 2G

SWAP

• Skenario1: 2G/3G colo, 3G done

• Skenario2: Hanya 2G, power dan tempat memadai tersedia

• Skenario3: Hanya 2G, power tersedia, tanpa ada tempat memadai

• Skenario4: Hanya 2G, tanpa power maupun tempat yang memadaiPeringatan: Slide ini hanyalah ilustrasi kondisi normal untuk swapping. Jika dalam keadaan di site tidak menentu, atau sesuatu keadaan pengecualian yang terjadi ketika swapping, proses downtime akan terkendala/waktu yang lama.

Page 4: Analisa Downtime Project HCPT 2G Swap

Slide title :32-35pt Color: R153 G0 B0

Corporate Font :FrutigerNext LT Medium

Font to be used by customers and

partners : Arial

Slide text :20-22ptBullets level 2-5:

18pt Color:Black

Corporate Font :FrutigerNext LT Medium

Font to be used by customers and

partners : Arial

Huawei Confidential Page 4

Katalog

• Deskripsi Skenario• Analisis Downtime Skenario • Prosedur Standar Operasi dari HCPT 2G SWAP Outdoor site

Page 5: Analisa Downtime Project HCPT 2G Swap

Slide title :32-35pt Color: R153 G0 B0

Corporate Font :FrutigerNext LT Medium

Font to be used by customers and

partners : Arial

Slide text :20-22ptBullets level 2-5:

18pt Color:Black

Corporate Font :FrutigerNext LT Medium

Font to be used by customers and

partners : Arial

Huawei Confidential Page 5

Scenario 1: 2G/3G colo,3G done

Dalam Skenario ini, untuk 2G ste menggunakan kabin 3G. Jadi papan 2G harus diinstalkan dalam kabin 3G, dan dihidupkan sebelum downtime.

RF TEST

CheckTransmission

VSWR Test

Check the battery

Cek transmisi ke BSC HW

Kumpulkan jumper baru ke feeder, dan sambungkan jumper ke RFU

RF TEST

Cek batera

i

Page 6: Analisa Downtime Project HCPT 2G Swap

Slide title :32-35pt Color: R153 G0 B0

Corporate Font :FrutigerNext LT Medium

Font to be used by customers and

partners : Arial

Slide text :20-22ptBullets level 2-5:

18pt Color:Black

Corporate Font :FrutigerNext LT Medium

Font to be used by customers and

partners : Arial

Huawei Confidential Page 6

Skenario 2: hanya 2G, daya dan ruang tersedia

Pada skenario ini, terdapat ruang yang cukup untuk perangkat 2G huawei. Site 2G dapat diinstal dan diaktifkan sebelum downtime.Cek

Transmisi

RF TEST

VSWR Test

Kumpulkan jumper baru ke feeder, dan sambungkan jumper ke RFU

RF TEST

Cek baterai

Cek Transmisi degnan BSC HW

Cek Baterai

Page 7: Analisa Downtime Project HCPT 2G Swap

Slide title :32-35pt Color: R153 G0 B0

Corporate Font :FrutigerNext LT Medium

Font to be used by customers and

partners : Arial

Slide text :20-22ptBullets level 2-5:

18pt Color:Black

Corporate Font :FrutigerNext LT Medium

Font to be used by customers and

partners : Arial

Huawei Confidential Page 7

Skenario 3: hanya 2G, daya tersedia, tidak ada ruang

RF TEST (NSN NOC)

VSWR Test

Matikan rak Base

Cek Baterai Pada skenario ini, terdapat cukup ruang

untuk peralatan 2G Huawei. Site 2G dapat diinstal dan dinyalakan sebelum downtime

Tes rantai transmisi (dengan baterai), jika step ini tidak dapat selesai dalam 2 jam, maka SWAP akan dihentikan!

Cek Transmisi dengan BSC HW

Kumpulkan jumper baru ke feeder, dan sambungkan jumper ke RFU

RF TEST

Ganti jumper E1

Cek baterai

Instal alarm

eksternal

ATP Site

Page 8: Analisa Downtime Project HCPT 2G Swap

Slide title :32-35pt Color: R153 G0 B0

Corporate Font :FrutigerNext LT Medium

Font to be used by customers and

partners : Arial

Slide text :20-22ptBullets level 2-5:

18pt Color:Black

Corporate Font :FrutigerNext LT Medium

Font to be used by customers and

partners : Arial

Huawei Confidential Page 8

Skenario 4: hanya 2G, daya dan ruang tidak tersedia

Pada skenario ini, tidak terdapat ruang yang cukup untuk perangkat 2G huawei . Site 2G dapat diinstal dan diaktifkan selama downtime.

Matikan Rak Base

Cek baterai

Cek Transmisi

RF TEST

Bongkar base rak sesuai standar. Copot jumper, kabel power dan ground dari tempat kabel. Instal BTS HUAWEI 3900A BBUdan kabinet RFC sesuai standar.

VSWR Test Kumpulkan jumper baru ke feeder

Matikan rak servis

Masukkan kabel ke port NSN

Instal BTS HUAWEI 3900A BBU dan kabinet RFC

sesuai standa

Sambungkan jumper ke RFU

Sambungkan kabel power. Nyalakan. Cek transmisi

Cek baterai

Page 9: Analisa Downtime Project HCPT 2G Swap

Slide title :32-35pt Color: R153 G0 B0

Corporate Font :FrutigerNext LT Medi

umFont to be used by c

ustomers and partners :

Arial

Slide text :20-22ptBullets level 2-5:

18pt Color:Black

Corporate Font :FrutigerNext LT Medi

umFont to be used by c

ustomers and partners :

Arial

Huawei Confidential Page 9

Katalog

• Deskripsi Skenario

• Analisis Downtime Skenario

• Prosedur Operasi Standar SWAP site outdoor 2G HCPT

Page 10: Analisa Downtime Project HCPT 2G Swap

Slide title :32-35pt Color: R153 G0 B0

Corporate Font :FrutigerNext LT Medium

Font to be used by customers and

partners : Arial

Slide text :20-22ptBullets level 2-5:

18pt Color:Black

Corporate Font :FrutigerNext LT Medium

Font to be used by customers and

partners : Arial

Huawei Confidential Page 10

Prosedur Operasi Standar SWAP site outdoor 2G HCPT

Standard Operation Procedure of HCPT 2G

Page 11: Analisa Downtime Project HCPT 2G Swap