+ All Categories
Home > Documents > Analysis and Visualization Approaches to Assess UDU Capability Presented at MBSW 2015 19 May 2015...

Analysis and Visualization Approaches to Assess UDU Capability Presented at MBSW 2015 19 May 2015...

Date post: 29-Dec-2015
Category:
Upload: prudence-shepherd
View: 216 times
Download: 0 times
Share this document with a friend
25
Analysis and Visualization Approaches to Assess UDU Capability Presented at MBSW 2015 19 May 2015 Jeff Hofer, Adam Rauk 1
Transcript

Analysis and Visualization Approaches to Assess UDU CapabilityPresented at MBSW 2015

19 May 2015

Jeff Hofer, Adam Rauk

1

Jeff Hofer and Adam Rauk, Eli Lilly 2

Outline

♦ Background and Motivation♦ ASTM E2810♦ Linking development results to Process

Validation and Routine testing• Bayesian analysis

♦ Visualization tool♦ Conclusions

2015 MBSW, Tuesday, May 19, 2015

Jeff Hofer and Adam Rauk, Eli Lilly 3

Motivation

♦ USP 905 is a standard that must be met whenever a product is tested … it is not a release test

♦ Increasing expectations to use ASTM E2810 (or other approach) to demonstrate ability to meet USP 905

♦ ASTM E2810 provides requirements that, if met, for the specific sample size tested provide a specified level of confidence that the USP 905 test would be met at least a specified percentage of the time if tested in the future

2015 MBSW, Tuesday, May 19, 2015

Jeff Hofer and Adam Rauk, Eli Lilly 4

True

Example OC Curves for ASTM plans and USP test from recent ISPE team publication

2015 MBSW, Tuesday, May 19, 2015

Demonstration of Conservativeness

These OC curves change based on the true batch mean

Jeff Hofer and Adam Rauk, Eli Lilly 5

Example ASTM E2810 Acceptance Table

2015 MBSW, Tuesday, May 19, 2015

Acceptance Ranges

This table changes based on the sample plan and confidence/coverage

Jeff Hofer and Adam Rauk, Eli Lilly 6

Question

How can one concisely and clearly summarize a product’s capability to meet complex criteria, such as that of ASTM E2810, from multiple Stage 1 (i.e., development) studies?

2015 MBSW, Tuesday, May 19, 2015

Jeff Hofer and Adam Rauk, Eli Lilly 7

Challenge

♦ Create a way to summarize development UDU study data that• Includes individual studies and provides an

overall summary for a given product• Enables more informed risk assessments as a

product moves from development into process validation and routine manufacture

• Allows for comparison between products, platforms, and scales

• Is readily understandable/interpretable

2015 MBSW, Tuesday, May 19, 2015

Jeff Hofer and Adam Rauk, Eli Lilly 8

Desired Attributes

♦ KISS♦ Seamlessly adjust for studies of varying size♦ Visualize the amount of uncertainty in the results♦ Leverage prior knowledge where appropriate

• Apply Bayesian methods to estimate credible intervals for variability estimates

– Some estimates using traditional random effects resulted in poor estimates. Bayesian methods provide significantly improved estimation in these cases.

• Determine reasonable priors to use for variability estimates

2015 MBSW, Tuesday, May 19, 2015

Jeff Hofer and Adam Rauk, Eli Lilly 9

Factors Impacting the Ability of a Batch to Pass the Different UDU Criteria

♦ Batch Mean♦ Location to Location Variability♦ Within Location Variability♦ Note

• Weight variability, concentration variability, and assay variability are not explicitly called out but they contribute to the above elements

2015 MBSW, Tuesday, May 19, 2015

Jeff Hofer and Adam Rauk, Eli Lilly 10

Monte Carlo Simulation to Obtain 95% Limit Contours

♦ Properties Varied • True batch mean• True location to location standard deviation• True within location standard deviation

♦ Estimates • Probability of passing the various criteria

– USP 905– ASTM 50/95 30 locations x 2 samples per location when there was either

0% or 90% of the total variance due to location to location (example Process Validation, Stage 2)

– ASTM 50/80 10/30 (example Routine Release, Stage 3)

♦ Summarize• Show contours of constant 95% probability of passing a given criteria

on a plot of within location versus between location variability

2015 MBSW, Tuesday, May 19, 2015

Jeff Hofer and Adam Rauk, Eli Lilly 11

Example OC Curves when m=100

2015 MBSW, Tuesday, May 19, 2015

0

10

20

30

40

50

60

70

80

90

100

Perc

enta

ge o

f Tim

e P

ass

Cri

teri

a

0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 5.5 6 6.5 7 7.5 8 8.5 9 9.5 10 10.5 11 11.5 12

Lot Standard Deviation (% Label Claim)

Routine 50/80 Tier 10:30 PV 50/95 0% 30X2 PV 50/95 90% 30X2 USP 10-30

12

95% Pass Contours for Mean=100

2015 MBSW, Tuesday, May 19, 2015 Jeff Hofer and Adam Rauk, Eli Lilly

Jeff Hofer and Adam Rauk, Eli Lilly 13

95% Limit Contours for Passing USP, Example Process Validation (50/95)*, and Example Routine Release (50/80)*

♦ Plots were created displaying the contours with 95% probability of meeting the specific criteria for different combinations of• True Batch Mean (96, 97, 98, 99, 100)• True Between Location Standard Deviation• True Within Location Standard Deviation

♦ Contours become more restrictive as the true mean deviates from 100%

♦ When showing multiple batches on same plot, show the contours corresponding to the worst case mean

2015 MBSW, Tuesday, May 19, 2015

*ASTM E2810

Jeff Hofer and Adam Rauk, Eli Lilly 14

Working with Product Data

2015 MBSW, Tuesday, May 19, 2015

Jeff Hofer and Adam Rauk, Eli Lilly

Product Data

♦ Data are obtained for batches• Dosage units are obtained from multiple

locations across the batch• At least two dosage units are tested from some

locations♦ Bayesian analysis is performed to estimate the

between and within location variability and associated credible limits

2015 MBSW, Tuesday, May 19, 2015 15

Jeff Hofer and Adam Rauk, Eli Lilly

Bayesian Analysis

♦ Bayesian statistical methods used to estimate the within and between standard deviations and 90% credible intervals (provides upper 95% credible limit)

♦ Can incorporate prior belief and realistic constraints♦ Relatively non-informative priors utilized

• Within location SD is Uniform(0.001,10)• Between location SD is Uniform(0.001,10)• Batch mean comes from a Normal(100,SD=10)

♦ The actual data is utilized along with the prior to obtain a posterior distribution for the parameters

2015 MBSW, Tuesday, May 19, 2015 16

Jeff Hofer and Adam Rauk, Eli Lilly

Summarizing Analysis Results

♦ Plot the point estimates (medians) and the upper 95% credible limits for the posterior distributions of the between and within location standard deviations for individual studies/batches

2015 MBSW, Tuesday, May 19, 2015 17

18

95% Pass Contours for Mean=100 & Credible Intervals for Line Segment Creation

2015 MBSW, Tuesday, May 19, 2015 Jeff Hofer and Adam Rauk, Eli Lilly

Upper 95% Credible Limit

Upper 95% Credible Limit

Median Estimate

Jeff Hofer and Adam Rauk, Eli Lilly

Summarizing Analysis Results

♦ If line lies inclusively within the contours, we have high (95%) confidence that true within and between location standard deviations are small enough for the batch mean that the corresponding criteria can be met 95% of the time

♦ If point estimates fall directly on contour, we have 50% confidence that we could meet the corresponding criteria 95% of the time

2015 MBSW, Tuesday, May 19, 2015 19

Jeff Hofer and Adam Rauk, Eli Lilly 20

Quality Statements

♦ When the line endpoint lies inclusively within the contours, there is 95% probability that the true standard deviation is small enough for the batch mean that the corresponding criteria can be met 95% of the time

♦ When a point estimate falls directly on the line, there is a 50% probability that the corresponding criteria will be met 95% of the time

2015 MBSW, Tuesday, May 19, 2015

Jeff Hofer and Adam Rauk, Eli Lilly 21

Example – Plot of Contours for 95% Pass Percentage for Different Criteria using Worst Case Batch Mean versus 95% Credible Limits for Between and Within Location Variability

2015 MBSW, Tuesday, May 19, 2015

0.00

1.00

2.00

3.00

4.00

5.00

6.00

7.00

0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00

True

SD

With

in L

ocati

ons

True SD Between Locations

USP

PV 50/95 30x2

Routine 50/8010:30

a

b

c

d

e

f

g

h

i

j

k

l

m

n

o

p

q

r

s

t

u

v

w

x

y

z

Jeff Hofer and Adam Rauk, Eli Lilly 22

Example 2 – Plot of Contours for 95% Pass Percentage for Different Criteria using Worst Case Batch Mean versus 95% Credible Limits for Between and Within Location Variability

2015 MBSW, Tuesday, May 19, 2015

0.00

1.00

2.00

3.00

4.00

5.00

6.00

7.00

0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00

True

SD

With

in L

ocati

ons

True SD Between Locations

USP

PV 50/9530x2

Routine50/8010:30

a

b

c

d

e

f

Jeff Hofer and Adam Rauk, Eli Lilly 23

Conclusion

♦ There is a desire to have a criteria that ensures that one would meet the USP 905 requirements a high percentage of the time• ASTM E2810 provides such criteria

♦ Bayesian methods provide an excellent way to summarize development content uniformity data

♦ Bayesian analysis results can be visualized to demonstrate a product’s capability to meet the USP and ASTM requirements

♦ Such a product capability evaluation is useful for assessing risk as a product transitions from development to the manufacturing stages of process validation (Stage 2) and eventually routine release (Stage 3)

2015 MBSW, Tuesday, May 19, 2015

Jeff Hofer and Adam Rauk, Eli Lilly 24

Backup Slides

2015 MBSW, Tuesday, May 19, 2015

Jeff Hofer and Adam Rauk, Eli Lilly 25

Example OC Curves when m=100

2015 MBSW, Tuesday, May 19, 2015

0

10

20

30

40

50

60

70

80

90

100

Perc

enta

ge o

f Tim

e P

ass

Cri

teri

a

100% 99% 98% 97% 96% 95% 94% 93% 92% 91% 90%Percentage of Individual Dosage Units Within 85-115% LC

Routine 50/80 Tier 10:30 PV 50/95 0% 30X2 PV 50/95 90% 30X2 USP 10-30


Recommended