+ All Categories
Home > Documents > Analysis of Wastewater

Analysis of Wastewater

Date post: 14-Apr-2018
Category:
Upload: aikaless
View: 218 times
Download: 0 times
Share this document with a friend

of 35

Transcript
  • 7/30/2019 Analysis of Wastewater

    1/35

    April 29, 2013 1

    DRAFTAnalysis of Wastewater Management Sector in

    Palestine

    Nidal Mahmoud+ and Adel Yasin++

    +Institute of Environmental and Water Studies, Birzeit University

    ++ Director of Sanitary Department/ Palestinian Water Authority PWA

  • 7/30/2019 Analysis of Wastewater

    2/35

    April 29, 2013 2

    Presentation Outline

    Background about past

    situation

    present situation

    Challenge1:WaterSupply

    Challenge 2: Fund

    Challenge3: Israeli

    Conditions Challenge4: WWTP

    Criteria

    Challenge5: Upgrade old

    WW Network

    Challenge 6: EffluentDisposal

    Challenge 7: Policy &

    Laws

    Challenge 8: CapacityBuilding

    Looking for the Future

  • 7/30/2019 Analysis of Wastewater

    3/35

    April 29, 2013 3

    The Past situation for

    wastewater system During the occupation period, wastewater Sector

    used to be a very neglected issue

    There are collection networks in the main cities

    and refugee camp (served 28-32% ofpopulation) remaining population uses cesspits

    Many of these networks are old and poorlydesigned established before 1967 through

    Jordanian Administration and stayed withoutdevelopment

  • 7/30/2019 Analysis of Wastewater

    4/35

    April 29, 2013 4

    The Past situation for

    wastewater system-continued 40-50 MCM/Y of ww is generated, around

    15 MCM/Y is collected by network thendischarged into open areas (wadis)

    Around 400 locations for vacuum tankersfor discharging ww

    There are very few un-functional

    wastewater treatment plant (94% of ww isdischarged to wadies)

  • 7/30/2019 Analysis of Wastewater

    5/35

    April 29, 2013 5

    The Past situation for

    wastewater system-continued The un-treated Wastewater flows into the

    wadis

    Some farmers use the mixture of both

    untreated wastewater and spring water in

    irrigation specially in Nablus and AlFara

    area

  • 7/30/2019 Analysis of Wastewater

    6/35

    April 29, 2013 6

    No. Main cities % of ww

    services

    Treatment services

    1 Jenin 55 Not function

    2 Tulkarem 75 Primarily stage

    3 Qalqilya 70 No4 Nablus 80 No

    5 Salfit 80 On going

    6 Ramallah 75 Low efficiency

    7 El Bireh 88 High efficiency8 Jerusalem 95 Under Israeli control

    9 Bethelem 85 No

    10 Hebron 80 On going

    11 Jericho Zero No

    Wastewater status in WB

  • 7/30/2019 Analysis of Wastewater

    7/35

    April 29, 2013 7

    Percentage of Households that

    Use Cesspits

    Percentage of Households that Use Cesspits by

    Type of Locality and Region, 1997

    (http://www.pcbs.org)

  • 7/30/2019 Analysis of Wastewater

    8/35

    April 29, 2013 8

    Status of WW management in

    Palestine !?

  • 7/30/2019 Analysis of Wastewater

    9/35

    April 29, 2013 9

    Israeli Colonies effects on the

    Environment Israel is controlling the Palestinians for 40 years

    but they did nothing to protect the environment

    Israel moved most of internationally forbidden

    industries to the West Bank and disposes alltoxic effluents into Palestinian land without

    tratment

    95% of the industry in the sraeli settlements is

    considered toxic & dangerous industries

  • 7/30/2019 Analysis of Wastewater

    10/35

    April 29, 2013 10

    Israeli Colonies effects on the

    Environment Total effluent seawage discharged to the

    Wadis by Israeli Settlements is around 50

    MCM

    Palestinian Agricultural lands around the

    settlements were destroyed by untrated effluent

  • 7/30/2019 Analysis of Wastewater

    11/35

    April 29, 2013 11

    Israeli Colonies effects on the

    Environmentthe last 10 years, The Palestinians allocated

    250Millin USD for WWT projects but theIsraelis stopped us by one way or

    anotherHOW!!!:

    Security Areas

    Connection of Illegal settlements High Standards & Specifications

  • 7/30/2019 Analysis of Wastewater

    12/35

    April 29, 2013 12

    Existing and near future WWTP

    Projects

  • 7/30/2019 Analysis of Wastewater

    13/35

    April 29, 2013 13

    WW ProjectsStatusTreatment nameNo.1

    Overload and not functionExisting Jenin TP1

    Needs fundProposed Jenin regional TP2

    Needs fundProposed Tubas TP3

    Tendering processProposed Nablus west TP4

    Needs fundProposed Nablus east TP5

    Pre-treatmentExisting Tulkarem ponds6

    Design phaseProposed Tulkarem TP7

    Waiting for notice to proceedProposed Salfeet TP8

    Function at 2003Existing of El-Bireh TP9

    OverloadExisting of Ramallah TP10

    Preparing the feasibility studyProposed of Ramallah TP11

    Needs fundProposed Jericho TP12

    Preparing feasibility studyProposed Wadi Al-Nar TP13

    Tendering processProposed Hebron regional TP14

    Needs fundProposed Ad Dahrriya TP15

  • 7/30/2019 Analysis of Wastewater

    14/35

    April 29, 2013 14

    Regional Sewerage Project

    Jenin Project: Regional Sewerage Jenin

    Total Investment:40 Million USD

    Donor: Germany KFW

    Start Implementation: not yet

    Period of Implemntation:

    Status: TOR prepared needs approval from JWC

    Obstacles: Feasibility study could not betendered before approval

  • 7/30/2019 Analysis of Wastewater

    15/35

    April 29, 2013 15

    Regional WW Disposal Tulkarm

    Project: Regional Sewerage Tulkarm

    Total Investment:45 Million USD

    Donor: Germany-KFW Start Implemntation:2008

    Period of Implemntation: 3 years

    Status: Feasibility Study ready Obstacles:

  • 7/30/2019 Analysis of Wastewater

    16/35

    April 29, 2013 16

    Sewerage Nablus West

    Project: Sewerage Nablus-west

    (investment/Infrastructure restortion Measures

    Total Investment:

    Donor:Germany -KFW

    Start Implemntation:1998

    Period of Implemntation: 37.8 Million USD

    Status: Final Design ready Obstacles:

  • 7/30/2019 Analysis of Wastewater

    17/35

    April 29, 2013 17

    Ramallah Sewerage Treatment

    Project Project: Ramallah Sewerage Treatment

    Total Investment:

    Donor: Germany KFW

    Start Implemntation:Not yet

    Period of Implemntation: Status: Feasibility study Ready

    Obstacles: TP Location

  • 7/30/2019 Analysis of Wastewater

    18/35

    April 29, 2013 18

    Al-Bireh Wastewater Treatment

    Plant Project: Sewerage Al-Bireh

    Objectives

    Total Investment: 12 Million USD

    Donor: Germany - KFW

    Start Implemntation:1998

    Period of Implemntation: 2.5 Years

    Status: Functional TP

    Obstacles:

  • 7/30/2019 Analysis of Wastewater

    19/35

    April 29, 2013 19

    Salfeet Sewerage

    Project: Sewerage Salfeet

    (investment/Infrastructure restortion Measures

    Total Investment:11 Million USD

    Donor: Germany KFW

    Start Implemntation: 1995

    Period of Implemntation:

    Status: postponded Obstacles:JWU approval

  • 7/30/2019 Analysis of Wastewater

    20/35

    April 29, 2013 20

    Hebron WWTP

    Project:

    Total Investment: 45 Million USD

    Donor: USAID Start Implemntation: Not Yet

    Period of Implemntation:

    Status: Postponded Obstacles: Regulation of USAID

  • 7/30/2019 Analysis of Wastewater

    21/35

    April 29, 2013 21

    Jericho WW collection System

    Project:

    Total Investment: () Million USD

    Donor: JICA

    Start Implemntation: Not Yet

    Period of Implemntation: 3 years

    Status: Feasibility Study is Ready

    Obstacles: Location of WWTP, JWCApprovement

  • 7/30/2019 Analysis of Wastewater

    22/35

    April 29, 2013 22

    Abu-Dis WW collection System

    Project: Abu-Dis, Al-Izarita & Az-Zaim WW

    Total Investment: (25) Million USD

    Donor: Submitted to AFD Start Implemntation: Not Yet

    Period of Implemntation:

    Status: Obstacles: Not Funded yet

  • 7/30/2019 Analysis of Wastewater

    23/35

    April 29, 2013 23

    Despite all what have been done, still

    huge efforts are needed to properly

    manage the wastewater in Palestine

  • 7/30/2019 Analysis of Wastewater

    24/35

    April 29, 2013 24

    Challenges1: Water Supply

    Priorities Providing drinking water systems takes the

    priority where still more than 220thousands in around 220 communities

    without networks Chaleenge2:

    Raising huge amount of fund to improve

    WW sector services more than billion USDollar are needed

  • 7/30/2019 Analysis of Wastewater

    25/35

    April 29, 2013 25

    Challenge2: Limitation of fund

    and donor regulations and

    requirements

    Challenge3: unsustainability & stability of

    External DonationDonor funds only to have sustainable &

    sanitation infrastructures, PWA policy and

    strategies should carefully considers theaffordability of beneficiaries to pay for this

    service

  • 7/30/2019 Analysis of Wastewater

    26/35

    April 29, 2013 26

    Challenges

    Israeli conditions through JWC that affect,postponds, stop projects for unreasonableaspects

    Connection of illegal Israeli Settlementeffluent to Palestinian Sewerage Systems

    Specifications and standars of effluents

    and treated ww imposed by Israelis Security aspects

  • 7/30/2019 Analysis of Wastewater

    27/35

    April 29, 2013 27

    Challenges

    Challenges4: selection of Appropriate treatment

    systems and technologies

    that leads to WW management driving forces and

    treatment technologies that achieve specificcriterias by utilizing all type of technologies that

    help to minimize the running cost, example:

    produce gas CH4, incineration of sludge and

    available solid waste

  • 7/30/2019 Analysis of Wastewater

    28/35

    April 29, 2013 28

    Driving Forces for WW

    Management Public health risks: waterborne diseases

    Environmental protection: water resources andsoil

    National and regional policies: standards andguidelines

    Adequate sanitation services: life qualitystandards

    Economical benefits: reuse and recreation

    Political issues: regional stability

  • 7/30/2019 Analysis of Wastewater

    29/35

    April 29, 2013 29

    Criteria for WWT selection

    Satisfactory treatment efficiency towards: COD/BOD, suspendedsolids, N, P, etc.

    Robust technology: high stability towards power cut, peak loads,toxicants, etc.

    Flexible with respect to future amendments (extensions,improvement)

    Simple in operation maintenance and control

    Limited number of treatment steps

    Absence of disposal problems (e.g. sludge)

    No malodour nuisance

    Availability of local experience

    Designed for (by) product recovery

  • 7/30/2019 Analysis of Wastewater

    30/35

    April 29, 2013 30

    Challenges

    Challenge 5: Upgrading of the West Bank

    old urban sewage works

    Odor nuisance:

    -Overloaded pond systems

    -Misconception in design

    Land availability:- No space for extension

  • 7/30/2019 Analysis of Wastewater

    31/35

    April 29, 2013 31

    Challenge 6: Final effluent

    disposal

    Reuse in agriculture: where, this was one of the maintarget of Master Plan started in 1996

    Treated ww recycling and reuse is considered a very

    important option for generating additional waterresources to replace fresh water used foragricultural and industrial purposes

    Artificail Recharge through Disposal final effluent inWadis: environmental impact; compliance with

    political agreements

  • 7/30/2019 Analysis of Wastewater

    32/35

    April 29, 2013 32

    Challenge 7: Enforcement of

    policy and lawsPWA policy:

    Based on Polluter Pays Principle and

    envisages a full cost recovery based on

    affordability basis, water-tariff models should bedeveloped to assure cost recovery

    Palestinian Water Law:

    - Set of regulations and rules entailing pollutionfees for environmental pollution handlings

  • 7/30/2019 Analysis of Wastewater

    33/35

    April 29, 2013 33

    Challenge 8: Capacity building

    Building and maintaining a core staff formanaging and regulating the wastewaterprojects: review of documents andformulation of future plans

    Prepare for all training and capacity buildingprogram that required to support sustainable

    operation of the WWTP, and to achieve valuefrom reuse of the treated wastewater.

  • 7/30/2019 Analysis of Wastewater

    34/35

    April 29, 2013 34

    Look into the Future

    Sustainable planning of WWTPWW treatment facilities

    Realistic planning and management?

    Affordable CAPEX and OPEX?Political issues

    Sovereignty?

    Political power? Commitment?

  • 7/30/2019 Analysis of Wastewater

    35/35

    April 29 2013 35

    Look into the Future

    Sustainable Operation SmallWWTPFinancial Resources

    Effective financial management Socio-cultural aspects

    Public awareness and cleaner production tools

    Institutional issues

    Establishment of wastewater associations?

    Private sector involvement in sanitation services

    Pollution control & reuse guidelines?

    Water quality & public health protection?


Recommended