+ All Categories
Home > Documents > Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining...

Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining...

Date post: 27-May-2020
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
31
1 MARULA PLATINUM MARULA PLATINUM Analyst Visit Analyst Visit – Tuesday, 5 October 2004 Tuesday, 5 October 2004 2 Agenda Agenda Introduction Geology Mining Mineral Processing Safety Environment Infrastructure Social Involvement
Transcript
Page 1: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

1

MARULA PLATINUMMARULA PLATINUMAnalyst Visit Analyst Visit –– Tuesday, 5 October 2004Tuesday, 5 October 2004

2

AgendaAgenda

• Introduction

• Geology

• Mining

• Mineral Processing

• Safety

• Environment

• Infrastructure

• Social Involvement

Page 2: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

2

3

INTRODUCTIONINTRODUCTION

4

Location mapLocation map

Page 3: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

3

5

BackgroundBackground

• Acquired all assets of Platexco(Winnaarshoek) – R950 million in Dec 2000

• Exchanged Hendriksplaats for Clapham and portion of Forest Hill

• Sublease of portion of Driekop

• 20% Black Economic Empowerment

• Phase 1 approved in June 2002

Hendriksplaats

Maandagshoek

Clapham

Twickenham

Hackney Forest Hill

R37Road

Driekop

Winnaarshoek

6

Capital cost (Capital cost (RmRm))

• Phase 1 FY04

Mining and infrastructure 765

Process plant 382

indirect costs 203

Total 1 350

• Total revised mining plan + 1850

Page 4: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

4

7

The owners of Marula PlatinumThe owners of Marula Platinum

Enables sustainable benefit to flow to community over life of mine and beyond

5Marula Community Trust

Long-term, committed, empowerment investor5Business consortium

BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum

10MmakauMining

Technical, managerial, financial and operational support and expertise. Reputation allows capital to be raised for Marula Platinum and BEE owners

80Implats

Role%Owner

8

Project programme Project programme

August 2002 Construction started

November 2003 Commissioning started

February 2004 First concentrate shipped

June 2004 Produced 13 280 oz Pt (in

concentrate) for financial year

June 2006 125 000 oz Pt in concentrate

Page 5: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

5

9

GEOLOGYGEOLOGY

10

GeologyGeology

MerenskyReef

400m

UG2 Reef

Dyke

Generalised section of geology

Page 6: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

6

11

Dip variation planDip variation plan

• Depicts structural interpretation

• Dip steeper in shallow/slump area

• Ave 13 degrees

• Detailed variability influenced by borehole density

• Variability expected in “clean areas”

12

UG2 horizonUG2 horizon

UG2 Main Chrome

UG2 Pegmatoid

UG2 Pyroxenite

UL1

UL2

20 cm

50 cm

60 cm

Page 7: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

7

13

Marula UG2 Marula UG2 –– PGE splitsPGE splits

Pt37%

Rh8%

Ru11%

Pd40%

Au1%Ir

3%

14

Reserves and resourcesReserves and resources

• Mineral Reserve :

UG2 41.3 Mt

• Mineral Resource:

Merensky and UG2 66.6 Mt

• Phase 1 UG2 Reef

(Merensky mined at a later stage)

• Evaluation drilling continuing on Merensky

Page 8: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

8

15

MININGMINING

16

Mine plan Mine plan –– phase onephase one

• Original mining based on trackless Bord and Pillar

• Two decline accessesClaphamDriekop

• Mine UG2 to a depth of 600 metres• 233 000 ROM tonnes per month

(103 000 oz Pt per annum)• Infrastructure designed on a modular basis to

facilitate future expansion• Life-of-mine of 22 years

Page 9: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

9

17

Typical Typical bordbord--andand--pillar methodpillar method

18

Stope layoutStope layout

Dip @ +18°Dip @ 9°

Original layout

1.6m14m

WasteDip @ 5°

3.1mTypical

Page 10: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

10

19

Effect of reef dip on dilutionEffect of reef dip on dilution

Reef Dip vs Additional % Dilution(Bord and Pillar layout)

0%

10%

20%

30%

40%

50%

60%

70%

10 12 14 16 18 20 22 24 26

Dip (degrees)

% A

dditi

onal

Dilu

tion

20

Revised mine planRevised mine plan

• Dips

• High dilution

• Poor equipment efficiencies

• Poor extraction rates at depth

65% at 500m

50% with geological losses

• Low-resource utilization

• High cost per ounce

• Long ounce buildup profile

Page 11: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

11

21

SemiSemi--mechanisedmechanised layoutlayout

22

SemiSemi--mechanisedmechanised layoutlayout

Panel 1

Panel 2Typical section showing Trackless drive with conventional panel

Drive 2

Drive 1

Page 12: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

12

23

Breast mining layoutBreast mining layout

24

Mining methods evaluatedMining methods evaluated

• Bord and pillar (1.6 or 1.8m)

• Semi-mechanised (3 or 2 shifts)

• On Reef Breast

• On Reef Dip

• Off Reef Breast (conveyors or trucks)

• Off Reef Dip(conveyors or trucks)

Page 13: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

13

25

Grade comparisonGrade comparison

5.02 5.02

3.83

3.383.76

0.00

1.00

2.00

3.00

4.00

5.00

6.00

Off Reef Breast SingleConveyor

Off Reef Breast Singletruck

Semi Mechanised Bord and pillar 1.8 Bord and pillar 1.6

Mining methods

g/t

26

Cost per Cost per tonnetonne comparisoncomparison

160 162

148

129 129

0

20

40

60

80

100

120

140

160

180

Off Reef Breast SingleConveyor

Off Reef Breast Singletruck

Semi Mechanised Bord and pillar 1.8 Bord and pillar 1.6

Mining methods

Rand

per

tonn

e

Page 14: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

14

27

Cost per ounce comparisonCost per ounce comparison

1,067 1,078

1,2921,369

1,231

0

200

400

600

800

1,000

1,200

1,400

1,600

Off Reef Breast SingleConveyor

Off Reef Breast Singletruck

Semi Mechanised Bord and pillar 1.8 Bord and pillar 1.6

Mining methods

Rand

per

oun

ce

28

Mining method selected Mining method selected -- conclusionconclusion

• Conventional breast stoping method chosen for the Life Of Mine Plan

• Footwall infrastructure and development

• Conventional stoping and strike development to be done in house

• Main development outsourced

Page 15: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

15

29

The way forwardThe way forward

• Transitional phase to full production

• Detailed design work in progress

• Initiated footwall development

• EPCM contract to manage process

• Maintain ounce profile from current workings

• Maximise semi-mechanised operations

• Opportunities for breast mining on-reef

30

Best practiceBest practice

• Use of DDT drill jigs for stope and ASG drilling

• Support drilling with Auto drill

• Support with hydrabolts on face and pre-stressed stick support

Page 16: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

16

31

DDT drill jigs DDT drill jigs -- objectivesobjectives

• To reduce the physical effort

• Improved safety through face support in the form of roof-bolts

• Improving the quality of drilling

• Improving the face advance

• Improved hanging wall control

32

Support drilling inSupport drilling in--stopestope

Page 17: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

17

33

HydraboltHydrabolt

34

Installed Installed hydrabolthydrabolt supportsupport

Page 18: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

18

35

PrePre--stressed stick supportstressed stick support

JACKPOT

36

Production outputProduction output

• Panel length 24,0m

• Face advance 22,0m

• Square meters/panel 528 m²

• Labour required 11

RDO 4

Winch operator 2

TBR/support 2

LHD 1

Miner assistant 1

PTV 1

• Efficiency 48 m²/man

Page 19: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

19

37

MINERAL MINERAL PROCESSINGPROCESSING

38

Mineral processing overviewMineral processing overview

• Design based on Mintek test work data

• Overall metallurgical recovery set at 82% of ROM

grades (after mine call factor and scalping)

• Designed on a modular basis to facilitate

future expansion

• Final concentrate transported to Mineral

Processes

Page 20: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

20

39

Commissioning datesCommissioning dates

• Plant commissioned March 2004

• Plant operating as per design expectations

• Completed on time and below budget

• DMS plant by-passed

40

Tonnage profileTonnage profile

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

Page 21: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

21

41

Ounces profileOunces profile

-

20,000

40,000

60,000

80,000

100,000

120,000

140,000

160,000

180,000

42

TonnesTonnes milledmilled

050

100150

200250

300350

B/Plan 74 71 81 87 102 105 226

Actual 120 88 84 292

Jul-04 Aug-04 Sep-04 Oct-04 Nov-04 Dec-04 YTD

Page 22: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

22

43

PGM % recoveryPGM % recovery

70

75

80

85

90

95

B/Plan 79 79 80 81 80 80 79

Actual 92 93 91 92

Jul-04 Aug-04

Sep-04

Oct-04 Nov-04 Dec-04 YTD

44

SAFETYSAFETY

Page 23: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

23

45

Safety statisticsSafety statistics

00.5

11.5

22.5

33.5

4

FY04 FY05

Lost Time Injury Frequency Rate

3,87

2,43

46

Safety initiativesSafety initiatives

• 5 Platinum rules established

• Implemented the Meerkat system

• Training Centre underground to train workers in working environment

• Road safety awareness through propoganda and photographs

• Revised support methods

• Fall of ground campaign ‘DROP THAT ROCK BEFORE IT DROPS YOU’

Page 24: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

24

47

ENVIRONMENTENVIRONMENT

48

EnvironmentEnvironment

• Water permit application submitted

• Sewerage plant in full operation

• Water treatment plant in full operation

• Slimes dam operational

• Water Management Committee established

• Ground water monitoring with SRK

Page 25: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

25

49

INFRASTRUCTUREINFRASTRUCTURE

50

InfrastructureInfrastructure

• Bulk water supply

• Power supply

• Bio-filter sewage treatment works

• Central offices, workshops, ablutions, training facilities and clinic

• Offices, change house and lamp room at each shaft

Page 26: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

26

51

LebaleloLebalelo raw water damraw water dam

52

EskomEskom powerpower

Page 27: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

27

53

SOCIAL SOCIAL INVOLVEMENTINVOLVEMENT

54

HlahlanaHlahlana primary schoolprimary school

Page 28: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

28

55

Empowerment modelEmpowerment model

BEE Ownership

Employment Equity

Elements of empowerment

Training Social/SMEDevelopment

Mmakau Community

Affirmative Procurement

Trust Local direct stakeholding

56

Marula Community trustMarula Community trust

• Trust formed 5 August 2004 after 14 months of negotiations with all stakeholders

• R1m cheque presented by Impala to the Marula Community Trust

• 11 Trustees have been appointed to represent the relevant stakeholders

Page 29: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

29

57

EmploymentEmployment

• 50.4% of workforce currently made up of local labour

• Committed to the Mining Charter, Social and Labour Plan and Implats’ submission on Employment Equity Act

• 10 local miners trained and achieved blasting certificates

• 13 local apprentices qualified• 4 local bursary students currently

at university

58

TrainingTraining

• Transfer of skills to the local community

• Skills training includes

Construction

Mining

Engineering

Page 30: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

30

59

Social involvementSocial involvement

• Preference to local contractors and suppliers

Building trades

Security

Fencing

Catering

Transport

60

Mining Charter Categories Mining Charter Categories -- procurementprocurement

Black Empowered23%

Black Owned22%

Black Influenced55%

R49m 1 July 03 – 30 June04

Page 31: Analyst - Marula Sep 2004 Ian - Impala Platinum · BEE with proven sustainability and mining expertise. Will have strategic input into Marula Platinum ... GEOLOGY 10 Geology Merensky

31

61

THANK YOUTHANK YOU


Recommended