ANASAGAR. Water Purification System The Lake water purification system by Aeration & floating fountains (4 Nos) were installed and is functioning since 23.01.2009. 10 more floating fountains have been installed in 2013 for beautification and aeration of Anasagar Lake. - PowerPoint PPT Presentation
Popular Tags:
18
ANASAGAR
Transcript
Page 1: ANASAGAR

ANASAGAR

Page 2: ANASAGAR

Water Purification System The Lake water purification system by Aeration

& floating fountains (4 Nos) were installed and is functioning since 23.01.2009. 10 more floating fountains have been installed in 2013 for beautification and aeration of Anasagar Lake.

Page 3: ANASAGAR

Water Purification System

Page 4: ANASAGAR

Bio-Remediation Bio-remediation of drains terminating into Anasagar lake has been taken up since Feb-2013 for treatment of waste water flowing through drains before entering in to the lake. At present work is under Progress In 7 drains are as under : Nagphani(near Mahaveer colony) Ramnagar(near R.K marble)RamnagarKazi ka nallahShantipuraApsara Mension Choursiawas Drain

Page 5: ANASAGAR

Bio-Remediation

CHAURASIAWAS DRAIN RAM NAGAR II (NEAR R.K. MARBLE)

KAZI KA NALLAH SHANTIPURA DRAIN

Page 6: ANASAGAR

Jetty Platform & Walkway

The work of Jetty Platform near Chaupati and walkway along the hillock below the circuit house with lighting has been completed.

Page 7: ANASAGAR

Jetty Platform near Chaupati & Walkway

Page 8: ANASAGAR

Fixing of Steel Grill-Jali to check entry of Floating impurities into the Lake is

being done .

Grill at Shantipura Drain

Jali at Anasagar Lake

Page 9: ANASAGAR

Fixing of Steel Grill-Jali

Grill at Ram Nagar II Drain

Grill at Chauarsiawas Drain

Page 10: ANASAGAR

Different IEC has been taken up to create public awareness & participation which includes showcase of Jhanki of Anasagar lake on republic day function. Distribution of pamphlets and cards for awareness of lake conservation

Page 11: ANASAGAR
Page 12: ANASAGAR

WATER PURIFICATION

Page 13: ANASAGAR

JALI FIXED AT ANASAGAR

Page 14: ANASAGAR

Bio-Remediation

Page 15: ANASAGAR

JETTY PLATFORM & WALKWAY

Page 16: ANASAGAR

• The sanctioned desilting work of the lake in 2,15,000 cum has been completed, The work of Desilting in 20000 cum on Anted Nallah, Chaurasiyawas Nallah, Kazi ka Nallah & Bandi Nadi has been completed.

• Pucca works for construction work of a pilot channel with cement concrete bed in about 308 m length in Anted Nallah has been completed behind the Press club on the Gaurav Path.

WORKS PERFORMED UNDER NLCP- ANASAGAR LAKE

Page 17: ANASAGAR

• The fencing and Afforestation in 206 Ha & construction of check dam 31 nos have been completed by the forest Dept.

• Water Quality Monitoring by testing of sample monthly is being done regularly in lake and drains.