Date post: | 23-Dec-2015 |
Category: |
Documents |
Upload: | kerry-phillips |
View: | 219 times |
Download: | 0 times |
Angie Templeton & Nicole Cobb
Grants & Contracts Administrators
Sponsored Programs Administration
Overview: Building Your Budget
OMB Circular A-21 General Principles
Direct vs Indirect Costs
Allowability of Costs
Mechanics of Building a Budget
Sample Problems
Overview
Provides allowability principles for the reimbursement of costs associated with federally sponsored projects
Provides guidance for determining direct and indirect costs
http://www.whitehouse.gov/omb/circulars_a021_2004
*Note: Circular A-21 will be included in the OMB Uniform Guidance that will take effect on December 26, 2014, so the references at A-21 in this presentation will likely be different when that begins.
OMB Circular A-21
Direct vs Indirect Costs
DIRECTOMB A-21 D.1.Can be identified
specifically with a particular project
Can be directly assigned to projects relatively easily with a high degree of accuracy
INDIRECTOMB A-21 E.1.aka “F&A” or
“Overhead”Incurred for
common or joint objectives
Cannot be identified readily and specifically with a particular project
SalariesFringeTravel
Commodities/SuppliesContractuals/Services/Subcontracts
Equipment
Direct Costs
Indirect Costs (F&A/Overhead)
FacilitiesDepreciation and Use
AllowancesInterest of Debt
associated with certain buildings
Equipment and Capital Improvements
Operation and Maintenance Expenses
Library Expenses
AdministrativeGeneral Administration
and ExpensesDepartmental
AdministrationPresident’s OfficeGeneral CounselProvostBudget & PlanningProcurementCompliance
Sponsored Programs Administration
Basic Costing PrinciplesOMB A-21, C.2. (a.b.c.d.)
ReasonableAllocable
ConsistentAllowable
REASONABLE“Prudent Person Test”Determining Reasonableness:
Necessary to the projectComplies with Federal and State Laws
and RegulationsDid the individuals make good
judgements?Were the actions taken consistent with
institutional policies and procedures?
Basic Costing Principles (cont’d)
ALLOCABLEExpenses are incurred solely for the project
OR
Expenses benefit both the project and other work in a proportion that can be approximatedSplit purchases are allowed, and are often the most
appropriate way to allocate expenses to projects
Basic Costing Principles (cont’d)
CONSISTENTCost Accounting Standard (CAS) 502 requires
consistent allocation of costsIncurred for the same purpose, in like
circumstances, and are either only direct costs or only indirect costs
REMEMBER:Cannot charge the same cost both directly and
indirectly when it is incurred for the same purpose and circumstance
Basic Costing Principles (cont’d)
ALLOWABLEMust follow requirements from:
OMB Circulars (soon to be Uniform Guidance)Sponsor GuidelinesAward DocumentInstitutional Policies
Applies to both direct and indirect costsCertain costs may only be allowable as indirect
Example: Sponsored Programs expenses are not allowable as a direct costs, but are allowable as indirect
Basic Costing Principles (cont’d)
Costs must be treated consistently as either direct costs or indirect costs, when in like circumstances
“Like costs in like manner”Disclosure Statement (DS-2) also provides
guidance:http://www.controller.msstate.edu/cas/cdst/ Example:
Travel costs incurred while performing the function of general university activity such as travel by executive officers meeting with the State Board of Trustees to discuss general university business would be classified as indirect costs.
Travel by a university employee related to carrying out the functions of a specific contract or grant would be classified as a direct charge to that contract or grant.
Basic Costing Principles (cont’d)
Can I charge a computer to my project?IT DEPENDS!
Yes, if being used in a programmatic wayComputer needed to be connected to a scientific
piece of equipment for data collectionComputer needed to run simulations, analyze data,
etc
No, if being used in a general wayCheck email, browse internet,
word processing, etc
Allowability as a Direct Cost
Can I charge office supplies to my project?Typically no, due to lack of allocability
OMB A-21 F.6.b.(3).- normally treated as Indirect Costs
Allowable in unlike circumstancesUsed in programmatic way (conference materials,
pamphlets, etc)
Allowability as a Direct Cost
Can I charge my administrative assistant to my project?Typically no, due to lack of allocability
OMB A-21 F.6.b.(2).- salaries of administrative and clerical staff normally treated as Indirect Costs
Appropriate on a “Major Project”OMB A-21 Exhibit C
Allowability as a Direct Cost
Anything necessary for the completion of the project that is not paid for by the sponsor
Source of funds is irrelevant:MSU- E&G (Educational and General) FundsMSU- Designated FundsThird Party ContributionOther
Cost Share
Cost Share CategoriesCommitted
Must be tracked
Required by sponsorNot required, but
committed in proposal
Not required, but implied through regulation
UncommittedDoesn’t need to be
tracked
Typically after the fact “volunteering” of MSU resources
As a PI, do I have to charge my time to the project?No- BUT your time will be considered cost
share, and some portion of it must be committed and trackedDoing so will require division approval on the IAS
in the Cost Share portionOMB Memo 01-06
http://www.whitehouse.gov/omb/memoranda_m01-06/
All projects must have some committed effort, and therefore must be tracked
Note: we do not encourage cost sharing if it is not required by the sponsor
Cost Share
To be allowable as a cost share expense, it must be allowable as a direct costMust be incurred during project periodCan only be used as cost share onceCannot be already charged to the feds (F&A
costs)
Allowability of Cost Share
The sponsor does not allow me to charge F&A on the project. Can I use this unrecovered F&A to meet my cost share requirement?Only if you have prior approval of the Federal awarding
agency (see OMB A-110 C.23.(b).)
If I have two related federal projects, can I use my NSF funds as cost share for my USDA project?No- unless authorized by federal statute to be used
as cost share (very rare to happen)- OMB A-110 C.23.(a).(5).
**Cannot cost share Federal funds with Federal funds.**
Allowability of Cost Share
I bought a piece of equipment a few years ago that I plan to use on this project. Can I use that as cost share?
1- Was it purchased with Federal funds?2- Are the feds already paying for this (as F&A)? Is it in the F&A pool?3- Is it fully depreciated?
If you answer “no” to all of these, then you could use the depreciation value as cost share.
Questions to Ask About Cost Share
Budget MechanicsBasic Principles
All costs must follow the principles we’ve discussed:Reasonable, Allocable,
Allowable, and ConsistentProperly budgeted as Direct
or Indirect Costs
All costs should be viewed in relation to the project’s needs
Specific RFP’s may prohibit or require certain classes of expenses- be sure to read carefully!
PersonnelPI, Project Team, Students
Establish this section first to help determine expenses for other categories
Calculations:% effort or person months
Person Months recommended
9 mo. Vs 12 mo. employeesUse current salaries-
escalations allowed for future budget periods
Sometimes sponsors (particularly industries) will ask for an hourly rate.
Hourly Rate for 12 month: Salary / 2,080 Hourly Rate for 9 month: Salary / 1,560
Because MSU uses level of effort percentage instead, hourly rates are not auditable.
We can provide these rates if required, but we need to add a disclaimer. SPA can work with the PI on what verbiage to use.
Hourly Rates vs Effort Percentage
Budget MechanicsFringe Benefits
Treated as a Direct Cost
Effective August 31, 2014
CalculationsRates are applied to
budgeted salariesFaculty/Staff (based on $40,000 average salary)
Enrolled Students
Retirees Other Intermittent Employees and Non-Enrolled Students
36.09% 0.73% 24.23% 8.48%
Graduate Student Tuition Calculation is based on student’s budgeted
effort
Note: Effective Fall 2015 (FY16), all GRA’s will have the 100% rate charged in budgets. GTA’s and GSA’s will remain at 71%. (Kevin Edelblute)
Budget Mechanics
Budget MechanicsTravel
Project related conferences, meetings, data collection, etc
For budgeted personnel
Per Diemhttp://www.travel.m
sstate.edu/hcma/plhcma.php $41/day (min) $46/day (max)
Mileagehttp://www.travel.m
sstate.edu/mileage/mileage.pdf
$.56/mile if State owned vehicle not available
$.235/mile if State owned vehicle available
EquipmentNon-expendableTangibleUseful life of more than
one yearAcquisition cost of
$5,000 or more per unit
Note: just because it can be inventoried, does not necessarily make it equipment for budgeting purposes
Budget Mechanics
Commodities/Materials and Supplies
Items to be used for the project
Examples: Molecular Biology Supplies (enzymes, tubes, etc) to be used for DNA sequencing
Contractuals/Subcontracts
Services to be performed by another entity to complete the project
Example: Third-party vendor will perform DNA sequencing samples
Participant CostsBroad definition:
Support provided when a sponsor funds a project or activity in connection with formal meetings, conferences, or training programs
Specific definition:Costs paid to (or on behalf of) participants in such
eventsTreatment of participant costs vary from
sponsor to sponsor- check the RFP and sponsor requirements!
Budget Mechanics
Facilities and Administrative Costs (F&A)
Research45.5% MTDC On Campus26% MTDC Off Campus
Instruction50% MTDC On Campus26% MTDC Off Campus
Public Service/Other27.2% MTDC On Campus22.8% MTDC Off Campus
(MTDC = Modified Total Direct Costs)
Budget Mechanics
*Current Federally-
negotiated rates, effective:
July 1, 2014-June 30, 2017
Modified Total Direct Cost (MTDC)
Exclusions:TuitionEquipmentPatient CareOff-site RentalsScholarships/
FellowshipsAll Subaward Costs
Exceeding $25,000
Sponsor may further restrict the F&A Rate
The maximum that can be charged is our federally negotiated rate
Total Direct Costs
ExclusionsModified
Total Direct Costs
Sample Problems
Angie Templeton: [email protected]
Nicole Cobb: [email protected]
Sponsored Programs Administration133 Etheredge Hall
325-7404
QUESTIONS?