Reactor Specs
• Single Primary Reactor– 4.5 GW peak power (4.1 average)– Allows measurement of backgrounds
• Approval from the reactor company– Site access– Reactor company is providing detailed civil
construction cost estimates
Summary
• Approval from Reactor Company– 4.1 GW single reactor complex
• A Civil Construction Design Exists– Well known granite structure– Sent out to Local Contractors for detailed Cost
Estimate (expected by March 20)
• Possible Detector Locations are restricted by local geology– Far site can have 600-700 mwe– Near site has to be shallow