Page 1 of 32
District Council of Coober Pedy
ANNUAL COMPLIANCE REPORT
ELECTRICITY OPERATIONS
1st July 2015 to 30th June 2016
Page 2 of 32
ANNUAL REPORT OF ELECTRICITY OPERATIONS FROM 1st JULY 2015 - to - 30th JUNE 2016
INDEX LISTING
Page 2 Index
Page 3 Licence Information:
Name of the Officer of the Licensee Name of Licensee GENERATION OPERATIONS
Page 4 Description of Generating Plant including Installed Capacity (MW) Wind Turbine Information Diesel Litres Usage
Page 5 Outages – planned and unplanned
Page 6 Energy Produced Plant Availability DISTRIBUTION OPERATIONS
Page 7 Length of Network Lines & Cables by voltage category
Distribution Assets: Page 8 Street lighting Page 8 - 9 Transformers – SWER & Town
Page 9 - 10 Outages - Planned and Unplanned Power Quality Complaints Page 11 - 12 Work Completed by Power Line Personnel and Electricians Page 13 Customers disconnected for non-payment of accounts Quotations for New Supplies and Alterations
Non-compliant installations Page 14 Removal and Installation of Electricity Meters
RETAIL OPERATIONS
Page 15 Number of customers by customer category Electricity Sales: Consumer Category, kWhs and Sales Revenue Page 16 Employees and Qualifications Page 17 - 28 Graphs showing Station Daily Loads for each month. Page 29 Additional Information Page 30 - 31 Statement regarding Licence Obligations
Page 3 of 32
LICENCE - Information regarding the electricity operations in Coober Pedy – Generation / Distribution / Retail Licence (Combined Licence effective from 1st July 2007) Officer: Mr Neil Brown, Acting Chief Executive Officer District Council of Coober Pedy Licensee: This has been issued to the District Council of Coober Pedy
Page 4 of 32
GENERATION OPERATIONS
GENSETS – Generating Plant – OWNED BY ENERGY DEVELOPMENTS
EIGHT (8) in total:
• DEUTZ DIESEL GENSETS • TBD – 616 – V12 • 514 KW (site rating) • Each in a separate container
• Control Room – in a separate container adjacent to the gensets
INSTALLED CAPACITY: • 4.112 MW (Mega watts)
WIND TURBINE – OWNED BY COUNCIL AND LEASED BY
ENERGY DEVELOPMENTS
MAKER
RATING kW H.P.
R.P.M. ANNUAL PRODUCTION
kW hours
NORDEX WIND TURBINE
150
27 / 35
360,000
DIESEL LITRES USED
YEAR
LITRES
From: 1st July 2015 to 30th June 2016
3,118,392
The District Council of Coober Pedy has a contractual relationship with Energy Developments with the details of that relationship documented in a Power Purchase Agreement.
To date the District Council of Coober Pedy has been most satisfied with the performance of Energy Developments with all generation obligations being met.
Page 5 of 32
GENERATION PLANNED OUTAGES
1st July 2015 to 30th June 2016 No planned outages during this financial year.
GENERATION OUTAGES
1st July 2015 - 30th June 2016
Generation Outages
Type of Outage
Amount of
Outages
Minutes Seconds
Customers Per
Outage
Total CustomersAffected
UNPLANNED High Voltage 5 66 125 700 3500
Low Voltage
PLANNED High Voltage
Low Voltage
TOTALS 5 66 125 700 3500
GENERATION UNPLANNED OUTAGES
1st July 2015 - 30th June 2016
Date Reason Hospital Feeder
CustomersPer Outage
Town Feeder
Customers Per Outage
Total Duration
Min Sec Min Sec Mins Secs
9/09/2015 Generation failure with Gen 2
11 02 700 11 2
3/10/2015 Generation failure with Gen 2
5 37 700 5 37
17/11/2015 Gen 2 tripped on a reverse power fault
8 30 700 8 30
9/12/2015
Gen 2 tripped on a high crankcase pressure fault
16 52 700 16 52
4/6/2016
Hospital Feeder opened on UFLS due to an AVR issue on Gen 2
26 48 700 26 48
TOTALS 66 125 66 125
Page 6 of 32
Page 7 of 32
ENERGY PRODUCED - KwHS
From: 1st July 2015 to 30th June 2016
MONTH GENERATION PRODUCED AUXILIARIES NET
PRODUCED WIND
TURBINE TOWN
CONSUMPTION
JULY 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00
AUG 958,887.00 1,411.00 957,476.00 30,000.00 987,476.00
SEPT 831,342.00 1,319.00 830,023.00 30,000.00 860,023.00
OCT 951,891.00 983.00 950,908.00 30,000.00 980,908.00
NOV 961,790.00 956.00 960,834.00 30,000.00 990,834.00
DEC 1,055,165.00 1,067.00 1,054,098.00 30,000.00 1,084,098.00
JAN 2016 1,054,269.00 1,013.00 1,053,256.00 30,000.00 1,083,256.00
FEB 1,006,603.00 927.00 1,005,676.00 30,000.00 1,035,676.00
MAR 1,084,787.00 1,019.00 1,083,768.00 30,000.00 1,113,768.00
APR 818,983.00 983.00 818,000.00 30,000.00 848,000.00
MAY 859,112.00 1,152.00 857,960.00 30,000.00 887,960.00
JUNE 2016 989,863.00 1,295.00 988,568.00 30,000.00 1,018,568.00
TOTALS
11,555,081.00
13,662.00
11,541,419.00 360,000
11,901,419.00
Note: 1. All hours are kilowatt hours
2. Units as indicated from Energy Developments 3. Total produced = 11.9 MWhs
PLANT AVAILABILITY: With eight gensets available to come on-line to suit load requirements, each individual genset is taken off-line for a minimal amount of time when scheduled servicing is due and when the electrical checks and maintenance have to be carried out.
Page 8 of 32
DISTRIBUTION OPERATIONS
LENGTH OF NETWORK LINES & CABLES
OVERHEAD LINES
VOLTAGE
BETWEEN PHASES
LENGTH (KM) TOWN & DISTRICT SUPPLIED
19 kV SWER
38
COOBER PEDY - LOCAL AREA
L.V.
59
COOBER PEDY - TOWNSHIP
6.6 kV
19.27
COOBER PEDY - TOWNSHIP
UNDERGROUND CABLES
VOLTAGE
BETWEEN PHASES
LENGTH (KM) TOWN & DISTRICT SUPPLIED
6.6 KV Includes PLEC Scheme
4
TOWN AREA
415 V Includes PLEC Scheme
8.4
TOWN AREA
Note: Undergrounding of cables is carried out on a needs basis. Cables crossing major roadways are gradually being placed underground
to allow passage for the over-height mining machinery prevalent in the township.
Page 9 of 32
STREET LIGHTING
SIZE
DESCRIPTION
TOTAL
80W MERCURY 290
90W SODIUM 5
100W SODIUM 113
250W SODIUM 13
400W MERCURY 25
1000W SODIUM 14
TOTAL 460
Note: All streetlights are assets of the District Council of Coober Pedy; with repairs
and maintenance being completed as soon as possible.
TRANSFORMERS
SWER
Potch Gully 5kVA = 1 10kVA = 55 20kVA = 16
25kVA = 8
50kVA = 2
Hopeful Hills 5kVA = 2 10kVA = 43 20kVA = 10
25kVA = 3
50kVA = 2
TOTAL 142
Page 10 of 32
TOWN – 3 ∅
DESCRIPTION AMOUNT 25 kVA 1 50 kVA 3 90 kVA 1 100 kVA 3 150 kVA 3 200 kVA 30
300 kVA Pad Mount 2 315 kVA 4 450 kVA 1 500 kVA 3
TOTAL 51
DISTRIBUTION NETWORK OUTAGES
1st July 2015 - 24th June 2016
Distribution Outages
Type of Outage
Amount ofOutages
Minutes Seconds
Total Customers Affected
UNPLANNED High Voltage 4 94 2106
Low Voltage 3 255 3
PLANNED High Voltage 77 3127 458
Low Voltage 41 3236 56
TOTALS 125 6712 2623
Page 11 of 32
Unplanned power outages - below outlines causes:
High Voltage
• Hospital feeder fault • Repair earthing grid for 50kVA transformer upgrade • CB opened then closed and restored Hospital feeder to normal • Hospital feeder opened on a UFLS fault.
Low Voltage
• Replaced blown fuse on Transformer # 8 • Blown fuse on SWER Transformer bushing • Lost two phases in pit.
Planned power outages – below outlines causes:
High Voltage • 70 while SWER earth testing was carried-out • Replacing damaged HV tap on Transformer # 39 • Upgrading Transformer # 47 to 50 kVA • Upgrading Transformer # 8 to 200 kVA • Upgrading Transformer # 43 to 315 kVA • Upgrading Transformer # 32 to 200 kVA • Removed Transformer # 10 from Distribution System • Removed Transformer # 33 from Distribution System.
Low Voltage
• Isolate consumer mains for new cable run • Meter testing carried-out • Connected 150mm2 A1 ring feed into service pillar • Changed meter – suspected meter tamper • 29 meter replacement – upgrading • Meter tested • 2 meters sent away for testing • 2 changed meters from 1 to 3 phase • Isolation for switchboard upgrade • Replaced faulty meter • Installed 95 mm2 ABC feeding Thrower Close from Transformer # 24 to # 25 • Extended Transformer # 35 LV area
Note: All customers were notified with a hand delivered notice a few days prior when planned outages were necessary.
THERE WERE NO POWER QUALITY COMPLAINTS RECEIVED WORK COMPLETED BY LINESMEN INCLUDED:
Page 12 of 32
The following outlines some of the work completed: • Vehicle and depot maintenance is carried-out during the year • Crane is used for various reasons including lifting septic tanks for the water supply • Installation of public light columns and repairs and replacement to lights as required • Call-out to properties when reported they have no supply • Changing overhead to underground services • Removal of temporary service • Repairs to and installation of cameras installed for Council • Airport lighting inspection • Repairs and maintenance to solar lights on walking track • Upgrading and relocation of services • Stobie poles erected • Checked switching sheets for transformer changes • Changeover of transformers • SWER maintenance • Removal of birds nest around town • Installed one phase over/under service • Installed three phase over/under service • Removed debris from transformers • Carried out night street light patrols • Pre-treatment upgrade at desalination plant • Assisting with fires at properties • Carried out maintenance on switching cubicles • Driving the EWP to Port Augusta twice a year for mandatory electrical testing • Driving crane to Adelaide for annual service • Patrolling SWER lines and removing any foreign objects from the lines • Trimming trees around town to prevent touching lines • Connections and disconnections of meters around town • Removal of services as required • Repaired lights at the basketball court • Escorting of high load into Lia Street • Assisted members of the public with blower moves • Low voltage rescue training • Working at Heights training • Delivered water to the Bore • Installed Christmas banners on poles along Hutchison Street in December and were
removed again in January • Installed Australia Day banners on poles along Hutchison Street in January and were
removed again in January
Page 13 of 32
WORK COMPLETED BY ELECTRICIANS INCLUDED:
• Carried-out tag, RCD, fire exit and emergency lighting testing for all Council equipment throughout the year and entered information to upgrade register
• Compiled letters of non-conformance • Installed new emergency lighting at various locations • Continued with removing meters and replacing with the new digital ones as part of
Council’s metering upgrade plan • Installation and removing single and three phase meters as necessary • Changed new light fittings at Council Chambers • Changed lighting tubes at various locations • Serviced and repaired air conditioners at various locations • Installed smoke alarms at various locations • Installed socket outlets at the Triangle Pumping Station • Youth Shed Installations:
o Electric stove o Ceiling fans o Range hood o Exhaust fan
• Desalination Plant repairs and maintenance: o Replaced faulty UPS o Repaired faulty dosing pumps o Reset and recalibrated dosing pumps o Found fault alarm in PLC o Recalibrated chlorine sensor o Assisted with server issues o Rectified fault on Citec and automated valves for storage tanks o Found and rectified pump faults
• Exeloo repairs and maintenance: o Diagnosed electric door fault and fitted new power supply o Installed new sewerage pump, floats switches and controller o Fabricated a door to the switchboard frame
• Airport repairs and maintenance: o Completed lighting inspection at the Airport, quarterly and annually as well as
annual report generated o Replaced door striker o Tested cable for apron lighting o Rectified programming issue in security system o Determined vending machine fault and organised repairs o Repaired and resecured departure door o Found fault and rebooted fee recorder o Rectified issues with PA system
Page 14 of 32
CUSTOMERS DISCONNECTED FOR NON-PAYMENT:
The total number of customers disconnected for non-payment of electricity accounts during this financial year was 33.
QUOTATIONS GIVEN FOR NEW INSTALLATIONS / ALTERATIONS A quotation letter is supplied to each property owner stating charges - quotation is valid for one month – after that time a new quotation is required due to escalating prices of materials and electricity meters.
REASON QUANTITY
Three Phase in town area 1
Single Phase change over to Three Phase 3
Single phase on SWER supply 2
Single phase in town area 5
Removal of Single Phase in town area 1
Supply and install a SWER transformer 1
TOTAL 13
NON-COMPLIANCE INSTALLATIONS AND MEASURES
TAKEN TO RECTIFY:
There were 15 Notices of Faulty Electrical Installation forms forwarded to property owners – listed below outline some of the reasons:
• Properties requiring Certificate of Compliances for solar installation • The main earth electrode could not be located • The main earthing conductor and main earth electrode was not accessible for visual
inspection • The MEN connection needed to be installed in the main switchboard • The MEN connection needed to be removed from sub boards to the main switchboard • There was a missing earthing connection to the earth electrode • Safety Compliance check was required • The service mains were to be redirected onto the allotment.
Receipted person-to-person delivery confirmation letters were posted out to all of the property owners with a Notice of Faulty Electrical Installation form attached advising requirements to rectify each situation.
Owners were also advised that an Electrical Certificate of Compliance form is to be supplied to Council by a Licensed Electrical Contractor who holds a current licence outlining the work as detailed in the Notice of Faulty Electrical Installation had been rectified.
An owner who does not comply is given a date when their supply will be disconnected.
Page 15 of 32
REMOVAL AND INSTALLATION OF ELECTRICITY METERS
REASON QUANTITY
Meters Installed – New Consumers Single Phase 2 Three Phase 1
Removed old meters and replaced with digital
Single Phase 48 Three Phase 4
Removed meters only Single Phase 11 Three Phase 2 Installed meters only Single Phase Nil Three Phase Nil Defective or tampered with meters changed only Single Phase 1 Three Phase 2 Changed from single to three phase meter 1 Meters removed and replaced included: Faulty meters, damaged meters, damaged or
tampered with meters, Council’s meter upgrading program service upgrades and burnt out terminals.
Meters removed only were due to: Supply no longer required; demolition of homes or
fire damage. Meters installed only were due to: Service upgrades.
Page 16 of 32
RETAIL OPERATIONS
Number of Customers by Customer Category
DOMESTIC 1111
DOMESTIC PENSIONERS 189
COMMERCIAL 189
STATE 12
COMMONWEALTH 2
TOTAL 1503
TOTAL ELECTRICITY SALES
From: 1st July 2015 to 30th June 2016
CONSUMER kWh INCOME ($)
DOMESTIC 3,507,694 1,118,723
DOMESTIC PENSIONER 728,170 236,985
COMMERCIAL 3,921,975 1,345,246
STATE GOVT. 818,114 557,805
COMMONWEALTH GOVT. 3,174 2,164
COUNCIL USE 818,747 310,207
SUPPLY CHARGES: Domestic - 265,986
SUPPLY CHARGES: Commercial - 80,327
TOTALS
9,797,874 3,917,443
Page 17 of 32
EMPLOYEES AND QUALIFICATIONS:
Employee Position Current Licence No. Expiry Date Qualifications Scope of Licence/Registration
Graeme Norton Distribution Supervisor (on leave)
PGE188971 Workers Registration -Electrical
Electrical Worker: Limited to work on overhead lines, limited to cable jointing and underground distribution systems up to consumer terminals (excluding lead)
Pierre Strzabala
Acting Distribution Supervisor / Lines Person
PGE182504 31 May 2019Workers Registration -Electrical
Electrical Worker: Limited to work on overhead lines limited to cable jointing & underground distribution systems up to consumer terminals (excluding lead)
Martin Grava
Lines Person PGE214026
28 Feb 2018
Workers Registration – Electrical
Electrical Worker: Limited to work on overhead lines limited to cable jointing and underground distribution systems up to consumer terminals (excluding lead)
Electrician – for all departments
Workers Registration – Electrical
Electrical Worker: Can perform any electrical work
Gavin Talbot Electrician – for all departments
PGE142481 30 Nov 2017Workers Registration – Electrical
Electrical Worker: Can perform any electrical work.
Grant Maxwell
Electrician – for all departments
PGE202733 2 Feb 2019 Workers Registration -Electrical
Electrical Worker: Can perform any electrical work.
Lines Person Electrical Worker: Limited to work on overhead lines limited to cable jointing and underground distribution systems up to consumer terminals (excluding lead)
Grant Grayson Lines Person PGE204739 31 July 2017Workers Registration -Electrical
Electrical Worker: Limited to work on overhead lines limited to cable jointing and underground distribution systems up to consumer terminals (excluding lead)
Brett Gardiner Apprentice Lines Person 3rd Year
PGE259381 31 Aug 2017Workers Registration – Electrical
Electrical Worker: Overhead & underground distribution systems up to consumers terminals. Valid only while employed under a Contract of Training. Must work under supervision of a registered Electrical Worker
Hire Staff Lines Person One staff member from Electel, Adelaide is on site in Coober Pedy two weeks in every four weeks to assist in the distribution duties
Neil Brown Acting C.E.O. Duties are for all Council operations
Khuram Saleem
Acting Finance Administration Manager/Accountant
Duties are for all Council operations
Richard Blobel Meter Reader Half Time meter reader for electricity and water
Brendan Lamont Meter Reader Half Time meter reader for electricity and water
Vonnie Ferguson
Administration Officer Duties are for Electricity, Water and Works Departments
Kylie-Anne Child Administration Assistant Duties are for Electricity, Water and Works Departments
Emily Natt Utilities Clerk Duties are for both Electricity and Water
Lauren Palmer Receptionist Duties are for all Council operations
Page 18 of 32
Page 19 of 32
Page 20 of 32
Page 21 of 32
Page 22 of 32
Page 23 of 32
Page 24 of 32
Page 25 of 32
Page 26 of 32
Page 27 of 32
Page 28 of 32
Page 29 of 32
Page 30 of 32
Additional Information As previously reported, there have been a number of issues identified during past audits of Council’s Safety, Reliability, Maintenance & Technical Management Plan. The manner in which these issues have been and/or are to be addressed is subject to Council Electricity Supply Budget determination on a yearly basis. I am able to advise that Council has proposed to Energy Division that an allocation of $450,000 be included in the 2013 / 2014 Electricity Supply Budget for the replacement of 16 x 6.6/11kv transformers that have been identified as containing PCB’s. These were delayed in production and have now arrived. The installations were due to be completed in the 2014 / 15 year, but to-date 11 have been replaced and the balance will be completed in the 2016 / 2017 year. Additionally Council received an allocation of $130,000 in the 2014 / 2015 Electricity Supply Budget for the removal (5) and replacement (9) of Stobie poles that are located on dugout (underground homes) roofs. The first stage of placement of new Stobie poles to re-route the conductor around the dugouts has commenced.
Page 31 of 32
Statement Regarding Licence Obligations To: Essential Services Commission of South Australia
Level 8 50 Pirie Street Adelaide SA 5000
The District Council of Coober Pedy (the Licensee) reports as follows: 1. This Report is an Annual Compliance Report for the period 1st July 2015 to 30th June 2016
and has been prepared in a manner that meets the requirements of the Compliance Systems and Reporting Energy Industry Guideline No. 4 (“the Guideline).
2. The Licensee, having made appropriate and due enquiry, is not aware of any breach of any
of the obligations listed in Schedule A to this Report (“Applicable Obligations”), other than as detailed in Schedule B.
3. The Licensee has maintained a robust compliance program during the relevant period that
ensures that:
(a) it has identified all Applicable Obligations that apply to the Licensee (and not simply reported against the indicative list of obligations set out in Schedule A);
(b) it has a “Responsible Officer” who has operational control over the activity or
work area where each of the relevant Applicable Obligations arise;
(c) it has ensured that the “Responsible Officer” has programmed the relevant Applicable Operation into operational procedures for the relevant activity or work area, and is accountable to the Council through the Chief Executive Officer for ensuring compliance with that Applicable Obligation;
(d) the Chief Executive Officer (or equivalent) and, where relevant the Council
(Licensee), will be made aware of any breaches of Applicable Obligations without delay and the process for the remediation of a breach;
(e) remedial action is taken as soon as possible to rectify breaches of Applicable
Obligations, and that the breach of the Applicable Obligation, and the completion of the remedial action, is reported to the Council;
(f) the compliance system is reviewed every two years with a view to improve it,
and also where:
• continued breaches indicate systemic failure to ensure that the compliance system is effective and relevant; and
• there is a significant change to the regulatory regime, in order to update the
system to accommodate the change. 4. The Licensee has established a process for signing this Compliance Report that is in
accordance with clause 3.6.3 of the Guideline.
Page 32 of 32
5. Both the Mayor and Chief Executive Officer, who have signed the Report below state that:
“We certify that we have made all necessary inquiries of appropriate officers in this organisation to confirm that management has developed a robust compliance system that meets the regulatory arrangements relating to the electricity / gas industry in South Australia, and that the system has been implemented and is being appropriately used by the organisation.”
Dated the day of 2016. SIGNED, in accordance with clause 3.6.3 of the Guideline, by: ……………………………………….. ………………………………………….
Signature Signature
……………………………………….. …………………………………………. Name (Please Print) Name (Please Print)
………………………………………. …………………………………………
Designation (Please Print) Designation (Please Print) 6. This signed Annual Compliance Report has been approved by the District Council of
Coober Pedy at its meeting on 16th August 2016 as required by clause 3.6.3 of the Guideline.