+ All Categories
Home > Documents > ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations...

ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations...

Date post: 23-Apr-2018
Category:
Upload: buidang
View: 219 times
Download: 4 times
Share this document with a friend
32
Page 1 of 32 District Council of Coober Pedy ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS 1 st July 2015 to 30 th June 2016
Transcript
Page 1: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 1 of 32

District Council of Coober Pedy

ANNUAL COMPLIANCE REPORT

ELECTRICITY OPERATIONS

1st July 2015 to 30th June 2016

Page 2: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 2 of 32

ANNUAL REPORT OF ELECTRICITY OPERATIONS FROM 1st JULY 2015 - to - 30th JUNE 2016

INDEX LISTING

Page 2 Index

Page 3 Licence Information:

Name of the Officer of the Licensee Name of Licensee GENERATION OPERATIONS

Page 4 Description of Generating Plant including Installed Capacity (MW) Wind Turbine Information Diesel Litres Usage

Page 5 Outages – planned and unplanned

Page 6 Energy Produced Plant Availability DISTRIBUTION OPERATIONS

Page 7 Length of Network Lines & Cables by voltage category

Distribution Assets: Page 8 Street lighting Page 8 - 9 Transformers – SWER & Town

Page 9 - 10 Outages - Planned and Unplanned Power Quality Complaints Page 11 - 12 Work Completed by Power Line Personnel and Electricians Page 13 Customers disconnected for non-payment of accounts Quotations for New Supplies and Alterations

Non-compliant installations Page 14 Removal and Installation of Electricity Meters

RETAIL OPERATIONS

Page 15 Number of customers by customer category Electricity Sales: Consumer Category, kWhs and Sales Revenue Page 16 Employees and Qualifications Page 17 - 28 Graphs showing Station Daily Loads for each month. Page 29 Additional Information Page 30 - 31 Statement regarding Licence Obligations

Page 3: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 3 of 32

LICENCE - Information regarding the electricity operations in Coober Pedy – Generation / Distribution / Retail Licence (Combined Licence effective from 1st July 2007) Officer: Mr Neil Brown, Acting Chief Executive Officer District Council of Coober Pedy Licensee: This has been issued to the District Council of Coober Pedy

Page 4: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 4 of 32

GENERATION OPERATIONS

GENSETS – Generating Plant – OWNED BY ENERGY DEVELOPMENTS

EIGHT (8) in total:

• DEUTZ DIESEL GENSETS • TBD – 616 – V12 • 514 KW (site rating) • Each in a separate container

• Control Room – in a separate container adjacent to the gensets

INSTALLED CAPACITY: • 4.112 MW (Mega watts)

WIND TURBINE – OWNED BY COUNCIL AND LEASED BY

ENERGY DEVELOPMENTS

MAKER

RATING kW H.P.

R.P.M. ANNUAL PRODUCTION

kW hours

NORDEX WIND TURBINE

150

27 / 35

360,000

DIESEL LITRES USED

YEAR

LITRES

From: 1st July 2015 to 30th June 2016

3,118,392

The District Council of Coober Pedy has a contractual relationship with Energy Developments with the details of that relationship documented in a Power Purchase Agreement.

To date the District Council of Coober Pedy has been most satisfied with the performance of Energy Developments with all generation obligations being met.

Page 5: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 5 of 32

GENERATION PLANNED OUTAGES

1st July 2015 to 30th June 2016 No planned outages during this financial year.

GENERATION OUTAGES

1st July 2015 - 30th June 2016

Generation Outages

Type of Outage

Amount of

Outages

Minutes Seconds

Customers Per

Outage

Total CustomersAffected

UNPLANNED High Voltage 5 66 125 700 3500

Low Voltage

PLANNED High Voltage

Low Voltage

TOTALS 5 66 125 700 3500

GENERATION UNPLANNED OUTAGES

1st July 2015 - 30th June 2016

Date Reason Hospital Feeder

CustomersPer Outage

Town Feeder

Customers Per Outage

Total Duration

Min Sec Min Sec Mins Secs

9/09/2015 Generation failure with Gen 2

11 02 700 11 2

3/10/2015 Generation failure with Gen 2

5 37 700 5 37

17/11/2015 Gen 2 tripped on a reverse power fault

8 30 700 8 30

9/12/2015

Gen 2 tripped on a high crankcase pressure fault

16 52 700 16 52

4/6/2016

Hospital Feeder opened on UFLS due to an AVR issue on Gen 2

26 48 700 26 48

TOTALS 66 125 66 125

Page 6: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 6 of 32

Page 7: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 7 of 32

ENERGY PRODUCED - KwHS

From: 1st July 2015 to 30th June 2016

MONTH GENERATION PRODUCED AUXILIARIES NET

PRODUCED WIND

TURBINE TOWN

CONSUMPTION

JULY 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

AUG 958,887.00 1,411.00 957,476.00 30,000.00 987,476.00

SEPT 831,342.00 1,319.00 830,023.00 30,000.00 860,023.00

OCT 951,891.00 983.00 950,908.00 30,000.00 980,908.00

NOV 961,790.00 956.00 960,834.00 30,000.00 990,834.00

DEC 1,055,165.00 1,067.00 1,054,098.00 30,000.00 1,084,098.00

JAN 2016 1,054,269.00 1,013.00 1,053,256.00 30,000.00 1,083,256.00

FEB 1,006,603.00 927.00 1,005,676.00 30,000.00 1,035,676.00

MAR 1,084,787.00 1,019.00 1,083,768.00 30,000.00 1,113,768.00

APR 818,983.00 983.00 818,000.00 30,000.00 848,000.00

MAY 859,112.00 1,152.00 857,960.00 30,000.00 887,960.00

JUNE 2016 989,863.00 1,295.00 988,568.00 30,000.00 1,018,568.00

TOTALS

11,555,081.00 

13,662.00 

11,541,419.00 360,000

11,901,419.00

Note: 1. All hours are kilowatt hours

2. Units as indicated from Energy Developments 3. Total produced = 11.9 MWhs

PLANT AVAILABILITY: With eight gensets available to come on-line to suit load requirements, each individual genset is taken off-line for a minimal amount of time when scheduled servicing is due and when the electrical checks and maintenance have to be carried out.

Page 8: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 8 of 32

DISTRIBUTION OPERATIONS

LENGTH OF NETWORK LINES & CABLES

OVERHEAD LINES

VOLTAGE

BETWEEN PHASES

LENGTH (KM) TOWN & DISTRICT SUPPLIED

19 kV SWER

38

COOBER PEDY - LOCAL AREA

L.V.

59

COOBER PEDY - TOWNSHIP

6.6 kV

19.27

COOBER PEDY - TOWNSHIP

UNDERGROUND CABLES

VOLTAGE

BETWEEN PHASES

LENGTH (KM) TOWN & DISTRICT SUPPLIED

6.6 KV Includes PLEC Scheme

4

TOWN AREA

415 V Includes PLEC Scheme

8.4

TOWN AREA

Note: Undergrounding of cables is carried out on a needs basis. Cables crossing major roadways are gradually being placed underground

to allow passage for the over-height mining machinery prevalent in the township.

Page 9: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 9 of 32

STREET LIGHTING

SIZE

DESCRIPTION

TOTAL

80W MERCURY 290

90W SODIUM 5

100W SODIUM 113

250W SODIUM 13

400W MERCURY 25

1000W SODIUM 14

TOTAL 460

Note: All streetlights are assets of the District Council of Coober Pedy; with repairs

and maintenance being completed as soon as possible.

TRANSFORMERS

SWER

Potch Gully 5kVA = 1 10kVA = 55 20kVA = 16

25kVA = 8

50kVA = 2

Hopeful Hills 5kVA = 2 10kVA = 43 20kVA = 10

25kVA = 3

50kVA = 2

TOTAL 142

Page 10: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 10 of 32

TOWN – 3 ∅

DESCRIPTION AMOUNT 25 kVA 1 50 kVA 3 90 kVA 1 100 kVA 3 150 kVA 3 200 kVA 30

300 kVA Pad Mount 2 315 kVA 4 450 kVA 1 500 kVA 3

TOTAL 51

DISTRIBUTION NETWORK OUTAGES

1st July 2015 - 24th June 2016

Distribution Outages

Type of Outage

Amount ofOutages

Minutes Seconds

Total Customers Affected

UNPLANNED High Voltage 4 94 2106

Low Voltage 3 255 3

PLANNED High Voltage 77 3127 458

Low Voltage 41 3236 56

TOTALS 125 6712 2623

Page 11: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 11 of 32

Unplanned power outages - below outlines causes:

High Voltage

• Hospital feeder fault • Repair earthing grid for 50kVA transformer upgrade • CB opened then closed and restored Hospital feeder to normal • Hospital feeder opened on a UFLS fault.

Low Voltage

• Replaced blown fuse on Transformer # 8 • Blown fuse on SWER Transformer bushing • Lost two phases in pit.

Planned power outages – below outlines causes:

High Voltage • 70 while SWER earth testing was carried-out • Replacing damaged HV tap on Transformer # 39 • Upgrading Transformer # 47 to 50 kVA • Upgrading Transformer # 8 to 200 kVA • Upgrading Transformer # 43 to 315 kVA • Upgrading Transformer # 32 to 200 kVA • Removed Transformer # 10 from Distribution System • Removed Transformer # 33 from Distribution System.

Low Voltage

• Isolate consumer mains for new cable run • Meter testing carried-out • Connected 150mm2 A1 ring feed into service pillar • Changed meter – suspected meter tamper • 29 meter replacement – upgrading • Meter tested • 2 meters sent away for testing • 2 changed meters from 1 to 3 phase • Isolation for switchboard upgrade • Replaced faulty meter • Installed 95 mm2 ABC feeding Thrower Close from Transformer # 24 to # 25 • Extended Transformer # 35 LV area

Note: All customers were notified with a hand delivered notice a few days prior when planned outages were necessary.

THERE WERE NO POWER QUALITY COMPLAINTS RECEIVED WORK COMPLETED BY LINESMEN INCLUDED:

Page 12: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 12 of 32

The following outlines some of the work completed: • Vehicle and depot maintenance is carried-out during the year • Crane is used for various reasons including lifting septic tanks for the water supply • Installation of public light columns and repairs and replacement to lights as required • Call-out to properties when reported they have no supply • Changing overhead to underground services • Removal of temporary service • Repairs to and installation of cameras installed for Council • Airport lighting inspection • Repairs and maintenance to solar lights on walking track • Upgrading and relocation of services • Stobie poles erected • Checked switching sheets for transformer changes • Changeover of transformers • SWER maintenance • Removal of birds nest around town • Installed one phase over/under service • Installed three phase over/under service • Removed debris from transformers • Carried out night street light patrols • Pre-treatment upgrade at desalination plant • Assisting with fires at properties • Carried out maintenance on switching cubicles • Driving the EWP to Port Augusta twice a year for mandatory electrical testing • Driving crane to Adelaide for annual service • Patrolling SWER lines and removing any foreign objects from the lines • Trimming trees around town to prevent touching lines • Connections and disconnections of meters around town • Removal of services as required • Repaired lights at the basketball court • Escorting of high load into Lia Street • Assisted members of the public with blower moves • Low voltage rescue training • Working at Heights training • Delivered water to the Bore • Installed Christmas banners on poles along Hutchison Street in December and were

removed again in January • Installed Australia Day banners on poles along Hutchison Street in January and were

removed again in January

Page 13: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 13 of 32

WORK COMPLETED BY ELECTRICIANS INCLUDED:

• Carried-out tag, RCD, fire exit and emergency lighting testing for all Council equipment throughout the year and entered information to upgrade register

• Compiled letters of non-conformance • Installed new emergency lighting at various locations • Continued with removing meters and replacing with the new digital ones as part of

Council’s metering upgrade plan • Installation and removing single and three phase meters as necessary • Changed new light fittings at Council Chambers • Changed lighting tubes at various locations • Serviced and repaired air conditioners at various locations • Installed smoke alarms at various locations • Installed socket outlets at the Triangle Pumping Station • Youth Shed Installations:

o Electric stove o Ceiling fans o Range hood o Exhaust fan

• Desalination Plant repairs and maintenance: o Replaced faulty UPS o Repaired faulty dosing pumps o Reset and recalibrated dosing pumps o Found fault alarm in PLC o Recalibrated chlorine sensor o Assisted with server issues o Rectified fault on Citec and automated valves for storage tanks o Found and rectified pump faults

• Exeloo repairs and maintenance: o Diagnosed electric door fault and fitted new power supply o Installed new sewerage pump, floats switches and controller o Fabricated a door to the switchboard frame

• Airport repairs and maintenance: o Completed lighting inspection at the Airport, quarterly and annually as well as

annual report generated o Replaced door striker o Tested cable for apron lighting o Rectified programming issue in security system o Determined vending machine fault and organised repairs o Repaired and resecured departure door o Found fault and rebooted fee recorder o Rectified issues with PA system

Page 14: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 14 of 32

CUSTOMERS DISCONNECTED FOR NON-PAYMENT:

The total number of customers disconnected for non-payment of electricity accounts during this financial year was 33.

QUOTATIONS GIVEN FOR NEW INSTALLATIONS / ALTERATIONS A quotation letter is supplied to each property owner stating charges - quotation is valid for one month – after that time a new quotation is required due to escalating prices of materials and electricity meters.

REASON QUANTITY

Three Phase in town area 1

Single Phase change over to Three Phase 3

Single phase on SWER supply 2

Single phase in town area 5

Removal of Single Phase in town area 1

Supply and install a SWER transformer 1

TOTAL 13

NON-COMPLIANCE INSTALLATIONS AND MEASURES

TAKEN TO RECTIFY:

There were 15 Notices of Faulty Electrical Installation forms forwarded to property owners – listed below outline some of the reasons:

• Properties requiring Certificate of Compliances for solar installation • The main earth electrode could not be located • The main earthing conductor and main earth electrode was not accessible for visual

inspection • The MEN connection needed to be installed in the main switchboard • The MEN connection needed to be removed from sub boards to the main switchboard • There was a missing earthing connection to the earth electrode • Safety Compliance check was required • The service mains were to be redirected onto the allotment.

Receipted person-to-person delivery confirmation letters were posted out to all of the property owners with a Notice of Faulty Electrical Installation form attached advising requirements to rectify each situation.

Owners were also advised that an Electrical Certificate of Compliance form is to be supplied to Council by a Licensed Electrical Contractor who holds a current licence outlining the work as detailed in the Notice of Faulty Electrical Installation had been rectified.

An owner who does not comply is given a date when their supply will be disconnected.

Page 15: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 15 of 32

REMOVAL AND INSTALLATION OF ELECTRICITY METERS

REASON QUANTITY

Meters Installed – New Consumers Single Phase 2 Three Phase 1

Removed old meters and replaced with digital

Single Phase 48 Three Phase 4

Removed meters only Single Phase 11 Three Phase 2 Installed meters only Single Phase Nil Three Phase Nil Defective or tampered with meters changed only Single Phase 1 Three Phase 2 Changed from single to three phase meter 1 Meters removed and replaced included: Faulty meters, damaged meters, damaged or

tampered with meters, Council’s meter upgrading program service upgrades and burnt out terminals.

Meters removed only were due to: Supply no longer required; demolition of homes or

fire damage. Meters installed only were due to: Service upgrades.

Page 16: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 16 of 32

RETAIL OPERATIONS

Number of Customers by Customer Category

DOMESTIC 1111

DOMESTIC PENSIONERS 189

COMMERCIAL 189

STATE 12

COMMONWEALTH 2

TOTAL 1503

TOTAL ELECTRICITY SALES

From: 1st July 2015 to 30th June 2016

CONSUMER kWh INCOME ($)

DOMESTIC 3,507,694 1,118,723

DOMESTIC PENSIONER 728,170 236,985

COMMERCIAL 3,921,975 1,345,246

STATE GOVT. 818,114 557,805

COMMONWEALTH GOVT. 3,174 2,164

COUNCIL USE 818,747 310,207

SUPPLY CHARGES: Domestic - 265,986

SUPPLY CHARGES: Commercial - 80,327

TOTALS

9,797,874 3,917,443

Page 17: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 17 of 32

EMPLOYEES AND QUALIFICATIONS:

Employee Position Current Licence No. Expiry Date Qualifications Scope of Licence/Registration

Graeme Norton Distribution Supervisor (on leave)

PGE188971 Workers Registration -Electrical

Electrical Worker: Limited to work on overhead lines, limited to cable jointing and underground distribution systems up to consumer terminals (excluding lead)

Pierre Strzabala

Acting Distribution Supervisor / Lines Person

PGE182504 31 May 2019Workers Registration -Electrical

Electrical Worker: Limited to work on overhead lines limited to cable jointing & underground distribution systems up to consumer terminals (excluding lead)

Martin Grava

Lines Person PGE214026

28 Feb 2018

Workers Registration – Electrical

Electrical Worker: Limited to work on overhead lines limited to cable jointing and underground distribution systems up to consumer terminals (excluding lead)

Electrician – for all departments

Workers Registration – Electrical

Electrical Worker: Can perform any electrical work

Gavin Talbot Electrician – for all departments

PGE142481 30 Nov 2017Workers Registration – Electrical

Electrical Worker: Can perform any electrical work.

Grant Maxwell

Electrician – for all departments

PGE202733 2 Feb 2019 Workers Registration -Electrical

Electrical Worker: Can perform any electrical work.

Lines Person Electrical Worker: Limited to work on overhead lines limited to cable jointing and underground distribution systems up to consumer terminals (excluding lead)

Grant Grayson Lines Person PGE204739 31 July 2017Workers Registration -Electrical

Electrical Worker: Limited to work on overhead lines limited to cable jointing and underground distribution systems up to consumer terminals (excluding lead)

Brett Gardiner Apprentice Lines Person 3rd Year

PGE259381 31 Aug 2017Workers Registration – Electrical

Electrical Worker: Overhead & underground distribution systems up to consumers terminals. Valid only while employed under a Contract of Training. Must work under supervision of a registered Electrical Worker

Hire Staff Lines Person One staff member from Electel, Adelaide is on site in Coober Pedy two weeks in every four weeks to assist in the distribution duties

Neil Brown Acting C.E.O. Duties are for all Council operations

Khuram Saleem

Acting Finance Administration Manager/Accountant

Duties are for all Council operations

Richard Blobel Meter Reader Half Time meter reader for electricity and water

Brendan Lamont Meter Reader Half Time meter reader for electricity and water

Vonnie Ferguson

Administration Officer Duties are for Electricity, Water and Works Departments

Kylie-Anne Child Administration Assistant Duties are for Electricity, Water and Works Departments

Emily Natt Utilities Clerk Duties are for both Electricity and Water

Lauren Palmer Receptionist Duties are for all Council operations

Page 18: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 18 of 32

Page 19: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 19 of 32

Page 20: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 20 of 32

Page 21: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 21 of 32

Page 22: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 22 of 32

Page 23: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 23 of 32

Page 24: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 24 of 32

Page 25: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 25 of 32

Page 26: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 26 of 32

Page 27: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 27 of 32

Page 28: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 28 of 32

Page 29: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 29 of 32

Page 30: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 30 of 32

Additional Information As previously reported, there have been a number of issues identified during past audits of Council’s Safety, Reliability, Maintenance & Technical Management Plan. The manner in which these issues have been and/or are to be addressed is subject to Council Electricity Supply Budget determination on a yearly basis. I am able to advise that Council has proposed to Energy Division that an allocation of $450,000 be included in the 2013 / 2014 Electricity Supply Budget for the replacement of 16 x 6.6/11kv transformers that have been identified as containing PCB’s. These were delayed in production and have now arrived. The installations were due to be completed in the 2014 / 15 year, but to-date 11 have been replaced and the balance will be completed in the 2016 / 2017 year. Additionally Council received an allocation of $130,000 in the 2014 / 2015 Electricity Supply Budget for the removal (5) and replacement (9) of Stobie poles that are located on dugout (underground homes) roofs. The first stage of placement of new Stobie poles to re-route the conductor around the dugouts has commenced.

Page 31: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 31 of 32

Statement Regarding Licence Obligations To: Essential Services Commission of South Australia

Level 8 50 Pirie Street Adelaide SA 5000

The District Council of Coober Pedy (the Licensee) reports as follows: 1. This Report is an Annual Compliance Report for the period 1st July 2015 to 30th June 2016

and has been prepared in a manner that meets the requirements of the Compliance Systems and Reporting Energy Industry Guideline No. 4 (“the Guideline).

2. The Licensee, having made appropriate and due enquiry, is not aware of any breach of any

of the obligations listed in Schedule A to this Report (“Applicable Obligations”), other than as detailed in Schedule B.

3. The Licensee has maintained a robust compliance program during the relevant period that

ensures that:

(a) it has identified all Applicable Obligations that apply to the Licensee (and not simply reported against the indicative list of obligations set out in Schedule A);

(b) it has a “Responsible Officer” who has operational control over the activity or

work area where each of the relevant Applicable Obligations arise;

(c) it has ensured that the “Responsible Officer” has programmed the relevant Applicable Operation into operational procedures for the relevant activity or work area, and is accountable to the Council through the Chief Executive Officer for ensuring compliance with that Applicable Obligation;

(d) the Chief Executive Officer (or equivalent) and, where relevant the Council

(Licensee), will be made aware of any breaches of Applicable Obligations without delay and the process for the remediation of a breach;

(e) remedial action is taken as soon as possible to rectify breaches of Applicable

Obligations, and that the breach of the Applicable Obligation, and the completion of the remedial action, is reported to the Council;

(f) the compliance system is reviewed every two years with a view to improve it,

and also where:

• continued breaches indicate systemic failure to ensure that the compliance system is effective and relevant; and

• there is a significant change to the regulatory regime, in order to update the

system to accommodate the change. 4. The Licensee has established a process for signing this Compliance Report that is in

accordance with clause 3.6.3 of the Guideline.

Page 32: ANNUAL COMPLIANCE REPORT ELECTRICITY OPERATIONS · annual compliance report electricity operations ... avr issue on gen 2 ... july 2015 982,389.00 1,537.00 980,852.00 30,000.00 1,010,852.00

Page 32 of 32

5. Both the Mayor and Chief Executive Officer, who have signed the Report below state that:

“We certify that we have made all necessary inquiries of appropriate officers in this organisation to confirm that management has developed a robust compliance system that meets the regulatory arrangements relating to the electricity / gas industry in South Australia, and that the system has been implemented and is being appropriately used by the organisation.”

Dated the day of 2016. SIGNED, in accordance with clause 3.6.3 of the Guideline, by: ……………………………………….. ………………………………………….

Signature Signature

……………………………………….. …………………………………………. Name (Please Print) Name (Please Print)

………………………………………. …………………………………………

Designation (Please Print) Designation (Please Print) 6. This signed Annual Compliance Report has been approved by the District Council of

Coober Pedy at its meeting on 16th August 2016 as required by clause 3.6.3 of the Guideline.


Recommended