2017
1 | P a g e
ANNUAL REPORT: 2016-17 PIPELINE DEPARTMENT
Commissioned in 1962, the 1157 KM long fully automated crude oil pipeline is the lifeline of
OIL. Along with an additional network of 63 Km, OIL Pipelines operates a total network of
1220 Km of Crude Oil Pipelines. At present the main pipeline has two segments, one
segment of 401 km, 406 mm (16”) with built in capacity of 5.38 MMTPA for NE crude oil,
both from OIL and ONGCL. The second segment of 756 km, 356 mm (14”) has a built in
capacity of 3.0 MMTPA in the reverse direction from Barauni to Bongaigaon. In addition to
above, 0.65 MMTPA of OIL’s crude is transported from Duliajan field to Digboi refinery
through 200 mm diameter 30 km long pipeline. The system has a network of 11 crude oil
pumping stations and 18 repeater stations.
This 5.38 MMTPA capacity pipeline transports crude oil produced from oilfields in Upper
Assam to the public sector refineries at Numaligarh, Guwahati and Bongaigaon. The pipeline
runs through the states of Assam, West Bengal and Bihar traversing hostile terrain, dense
forests and cuts across 78 rivers including the mighty Brahmaputra.
The 600 KM pipeline segment between Bongaigaon and Barauni has been re-engineered to
enable oil flow in either direction and is now transporting imported crude from Barauni to
Bongaigaon.
A 660 km long 406 mm diameter cross country Pipeline was constructed by Oil India Limited
for evacuation of 1.72 MMTPA of products from Numaligarh Refinery in Assam to Siliguri
terminal in west Bengal at a project cost of Rs. 469 crores.
The department has carried out various activities during the year to achieve its desired goal
and few of them are summarised below:
i) Round the clock operation and maintenance of crude oil Pipeline Operation including
support services like electrical, telecommunication, instrumentation etc.
ii) Round the clock operation and maintenance of product pipeline to evacuate product
from Numaligarh Refinery to Marketing terminal at Rangapani.
iii) Customer satisfaction through timely delivery of crude oil under strict quality control
and also product delivery.
iv) Compliance of all statutory, safety rules and practices, implementation of new safety
recommendations made by relevant bodies.
2 | P a g e
v) Liaison with external bodies like IOCL, NRL, CCoE, PESO, Oil Industry Safety Directorate
(OISD), authorities for implementation of Factories Act, State Administration of Assam,
West Bengal and Bihar etc.
vi) Training of students from Engineering Colleges, Institutes & Universities, Apprentice
trainees etc. and training of own employees through internal trainers.
vii) Periodic medical examination of all the employees of the department as per schedule.
viii) The ISO/ OHSAS certification under ISO9001, ISO14001: and OHSAS 18001 which was
valid up to 03.09.2016 was revalidated/re-certified by M/s BV, Kolkata. Now ISO 9001
& ISO 14001 is valid up to 14.09.2018 and OHSAS 18001 is valid up to 03.09.2019
II. PIPELINE OPERATIONS, UPLIFTMENT AND DELIVERY:
During the period overview, OIL’s Crude Oil Pipeline transported a total of 6.56 MMT
out of which Naharkatia-Bongaingaon sector transported 3.21 MMT of OIL crude and
0.94 MMT of ONGC crude. Barauni-Bongaigaon sector transported 2.41 MMT of
Imported Crude.
We have transported 1.78MMT of products through NSPL with Pipeline utilization
103.42%
The total deliveries of OIL & ONGC crude oil vis-à-vis off take are given below:
OFF TAKE
(in tonnes)
Delivery to
Refineries in
tonnes
Crude oil consumed
by pump engines &
generators
(in Pump-stations)
Percentage of
Achievement
OIL + JVC 3262761 3244544 3060 `99.44
ONGC 930856 939741 - 100.95
TOTAL 4193617 4184285 3060 99.78
The total IMPORTED crude oil delivery vis-à-vis off take is shown below:
Offtake of
Imported crude
oil at Barauni
(Wet tonnes)
Delivery of
Imported crude
oil at BRPL
(wet tonnes)
Line stock of
Imported crude
oil in the line
(tonnes)
Crude oil
consumed in the
pump stations
(tonnes)
Percentage
of
achievements
%
2407349 2398468 45663 4493 99.63
3 | P a g e
The deliveries to the four refineries against yearly allocation are given below:
REFINERIES/
CAPACITY
ACTUAL DELIVERY
(TONNES)
MoPNG
Allocation
MMT (16-
17)
%AGE OF
ACHIEVEMENT
(wrt MoPNG)
OCC
Allocation
MMT
(2016-17)
%Age of
Achievement
(w.r.t. OCC)
DIGBOI
0.65 MMT
EX/PL:479709
D/FLD+JVC: 49263
TOTAL: 528972
0.643 82.27 0.489 108.17
NRL
3.00 MMT
OIL: 2044006
ONGC: 706587
TOTAL: 2750593
2.968 92.67 2.769 99.34
GUWAHATI
1.MMT
OIL: 620957
ONGC: 232139
TOTAL: 835479
0.989 84.48 0.806 103.66
BONGAIGAON
0.497 MMT
(Assam Crude)
OIL: 50611
ONGC: 18632
TOTAL: 69243
NIL N/A 0.24
288.51
Delivery to Numaligarh, Bongaigoan and Digboi Refinery was less than the allocation
due non-availability of sufficient crude.
RECONCILIATION DIFFERENCE:
The reconciliation difference in the main line and the Duliajan-Digboi line for the
period 2015-16 to 2016-17 is given below:
YEAR MAIN LINE
DLJ-DIG 8” DEL/DIFF OIL (Ton) ONGC (Ton) TOTAL (Ton)
2015-16
Del 2687411 930048 3617459 511822
Diff 10804 3720 14524 4549
%Diff 0.40 0.40 0.40 0.88
2016-17
Del 2715572 939741 3655313 479709
Diff 6788 2349 9138 222
%Diff 0.25 0.25 0.25 0.046
Delivered quantity of OIL & ONGCL crude and transported quantity of IMPORTED
crude are comparatively shown below:
DESCRIPTION OF SERVICE
2011-12
(MMT)
2012-13
(MMT)
2013-14
(MMT)
2014-15
(MMT)
2015-16
(MMT)
2016-17
(MMT)
OIL CRUDE
DELLIVERED 3.80 3.62 3.42 3.40 3.20
3.20
ONGC CRUDE
DELLIVERED 1.19 1.18 1.20 1.08 0.93
0.94
IMP. CRUDE
TRANSPORTED 1.64 1.52 1.96 2.33 2.23
2.41
TOTAL 6.63 6.32 6.58 6.81 6.36 6.55
4 | P a g e
PIPELINE STOCK:
The inventory of crude oil in the pipeline at 0700 hrs on 01/04/2017 was 39245
tonnes of OIL crude out of which 1003 tones was in the DIGBOI line. The total ONGC
stock with OIL is 19072 tones. The total line stock of imported crude oil in the 14”
sector is 45663 tonnes.
NSPL:
The NSPL line operated smoothly during the period. Below product wise quantities
dispatch from Numaligarh and Received at Rangapani Terminal are shown.
Despatch from Receipt at
Numaligarh Rangapani Terminal
MS 03 287684 306823
SKO 01 61261 48072
HSD 03 880835 926453
HSD 04 427309 390466
MS 04 115621 109723
HSD 02 8048 -
TOTAL 1780758 1781537
III. ACHIEVEMENTS AND HIGHLIGHTS:
The department earned revenue of about Rs. 367.67 crores during the financial
year from Crude Oil and Product transportation.
Out of 605 Nos. of safety recommendation given by OISD through their external
safety audits, so far 495 Nos. of recommendations have been completed. The
percentage of completion at the end of the year was 81.82%.
Monthly departmental safety meetings, monthly central safety meetings, annual
internal safety inspection of pump and repeater stations, tool box meetings, pit
level safety meetings, weekly fire drill in Pipeline department etc. were regularly
carried out with adequate attention to safety standard upgradation.
IV. MAINTENANCE:
A: Mechanical:
During the year under review, the plant and machineries in all the Pump & Repeater
stations along the Pipeline were maintained in good running condition, and
uninterrupted pumping operation was maintained achieving 100% of the MOU
target of Crude delivery. The Preventive Maintenance schedules of the pumping and
5 | P a g e
generating units were carried out as per plan as per availability of the units.
The overall achievement as against planned targets for scheduled maintenance of
pumping and generating units of all the three bases is as follows:
ALLEN-ALDRICH Pumping units: 115.56%
ALLEN alternator units: 88.46 %
DG set at repeater stations: 103.45 %
B: Telecom:
Telecommunication:
Average Link Availability OFC System: 99.76 %
Instrumentation:
16" Sector Instrumentation Availability: 99.31 %
14" Sector Instrumentation Availability: 99.84 %
NSPL Instrumentation Availability: 99.60 %
Telemetry:
16 inch Sector Telemetry Availability: 99.15 %
14 inch Sector Telemetry Availability: 96.88 %
NSPL Telemetry Availability: 98.78 %
C: Electrical:
Power Availability: The power supply to various installations was monitored
throughout the year. As a result over 99.8 % of power availability was maintained for
all the pump stations and over 98% for repeater stations below.
V. PROJECT JOBS:
A. TENGAKHAT-SHALMARI PIPELINE (TSPL):
Electronic Geometry Pigging (EGP) of TSPL Pipeline from Tengakhat PS to
Fetengbor (Shalmari) hook up point carried out successfully on 07.03.2015.
Preliminary report submitted reveals no reductions observed above 5% of pipe
ID during survey.
B. UP-GRADATION PROJECTS:
During the year 2016-17, the Pipeline Project section was primarily engaged for
managing 3 projects namely
UP-GRADATION OF PUMP STATIONS/TERMINALS (Phase I)
UP-GRADATION OF PUMP STATIONS/TERMINALS (Phase II)
PIPELINE REHABILITATION PROJECT (Phase I).
6 | P a g e
The status of project activities being undertaken by Project section are given
below
UGPS (Phase-I)
Project Scope: Up-gradation Project for replacement and optimization of
eight (08) Pumping Stations and all Receipt Terminals including replacement of
50 years old Mainline Pumping units along with Engine drives and auxiliary
equipment’s.
Consultant: Engineers India Limited (EIL)
EIL Scope of Work: Engineering, Procurement, Tendering, Construction,
Management and Commissioning assistance
Date of Award: 14.12.2012
Project cost: Rs. 1200.00 Crore
Project key date:
- Effective start date: 14.12.2012
- Revised Schedule for Mechanical completion: 31.08.2015
- Revised schedule for Commissioning: 31.05.2017
Revised schedule for Project closure: 31.08.2017
Time elapsed: 51 ½ Months
Overall progress: 63.8%
C. DIGITIZED MAP OF TOWNSHIP:
For preparation of concept master plan of PHQ Township through School of
Planning and Architecture (SPA) the topographical survey of the township was
carried out by latest technology. A digitized map of the township has been
prepared on the basis of actual coordinate in reference to Survey on India and
Satellite data. With the help of this map one can easily find out the existing
properties, services, different facilities, installation, fire hydrant line, piping
network, electrical layout, contour lines etc. for planning and other development
purpose.
D. K.D. MALAVIYA NATIONAL OIL MUSEUM, GUWAHATI:
To showcase the involvement oil industry, an OIL Museum project at Guwahati is
being coordinated by Civil Engineering Section of PHQ. At this inception stage
liaising with the different PSUs of Petroleum Industries is being done for
preparing the detailed project report with the help of National Council of
Science Museums (NCSM).
7 | P a g e
E. HOOK-UP OF MICRO-TUNNEL SECTIONS:
Haruaputa-Sankosh- Hookup (PLKM 629-632):
Diversion of Crude oil pipeline from the railway bridges to submerged mode by
laying approximately 4.2 km length of pipeline and Hook up with Micro-
Tunneling sections. Approximately 2000 m pipe laying was completed in July
2013 and 1200 m pipe laying completed in Jan 2015 (700 m in Assam side and
500 m in Bengal side). Laying of the remaining 1000 m pipeline and the hook-up
job could not be completed on schedule due to non-clearance of RoU land.
F. HDD IN 10 RIVER CROSSINGS:
GOURANG River HDD (PLKM- 590):
Diversion of Crude oil pipeline from suspension crossing to underground mode
by HDD: Out of 1300 m new pipeline construction, fabrication and hydro-testing
of HDD string and railway track crossing string as well as fabrication of 450 m
string for normal terrain completed. Wrapping/coating of 350 m length in D/S
site with cold applied tape completed and lowered. Fabrication and hydro-test of
the 350m HDD segment completed; fabrication and coating of 100m Segment for
normal terrain completed in June 2015. Pilot boring started on 10.12.2016.
Pulling of 438 m of 3LPE pipe completed on 29.12.2016. Boring under railway
track started on 23.01.2017. PRs has been processed for HDD jobs for river
locations, namely, MAHANANDA-I, MAHANANDA-II, KOSI, BURIGANDHAK,
BURIDIHING & DHANSIRI. Work commencement is expected during the financial
year 2017-18
Status of Remaining 8 River Locations:
Necessary permissions from River Body authorities of Assam, West Bengal Bihar
as well as from NF Railway and East Central Railway obtained. Procurement of
land except river Donk completed.
G. 65 KM COATING REBURBISHMENT UNDER SR BUDGET:
● 15 km coating refurbishment: Starting date as per Work Order is 6.03.2015.
Total coating refurbishment done as on 31.03.2017 is 7837.87 meter.
50 km coating refurbishment: Starting date as per Work Order is 1.11.2015.
Total Coating refurbishment done as on 31.03.2017 is 45232.6 meter
8 | P a g e
VI. TECHNOLOGY UP-GRADATION:
Post-Earthquake study of storage tanks: Chief Scientist, CMERI, Durgapur
visited PS3 on 28.06.2015 for preliminary seismic study of the and delivered one
presentation on seismic excitation of storage tanks on 02.07.2015 at PHQ. LOA
has been issued to CMERI for Post-Earthquake study of storage tanks from PS-3
to PS-5 in Phase-I as per directives of Ministry of Petroleum and Natural Gas,
Govt. of India.
Mutual aid agreement has been signed between OIL Pipeline Department;
IOCL, Guwahati Refinery and NRL on 00.03.2017. This will cover Pipeline and
its Installations from PS3 to PS6.
After prolonged study and trial through field use, Butyle rubber Polyethylene
cold applied tape has been inducted as the coating material for pipeline and Coal
Tar Enamel has been phased out. Coating refurbishment with Cold applied tape
and visco-elastic material carried out at different locations.
New methodology for strengthening of the live pipeline by application of cold
applied composite material has been inducted.
New state-of-the art insulating flange joint kit has been inducted and effectively
applied in repairing shorted insulating flanges.
Digitized MAP of Township:
For preparation of concept master plan of PHQ Township through School of
Planning and Architecture (SPA) the topographical survey of the township was
carried out by latest technology.
Establishment of GIS based pipeline assets management system:
With an objective for better management of OIL’s Pipeline asset from Duliajan to
Barauni, it was decided to develop a Geographic Information System (GIS) based
asset management by preparation of a Pipeline base map encompassing the
entire RoW of OIL with Geo-referencing and overlaying the pipeline asset details
over the map so that the entire network could be viewed and managed
efficiently on one platform. The system should also be able to track the line
walkers with the help of Global Positioning System (GPS).
9 | P a g e
VII. GENERATION, CONSUMPTION AND SALE OF ELECTRICITY:
Power Generation:
A total of 8257570 KWh of energy was generated in the Pump Stations and Repeater
Stations along the pipeline.
LOCATION 2014 - 15 2015 - 16 2016-17
Pump Stations 7,848,394 7,581,250 7,783,713
Repeater Stations 517199 501,155 473,857
TOTAL(KWh) 8,365,593 8,082,405 8257570
Energy Consumption
The power consumption in all the installations in the last three years is shown below
LOCATION 2014- 15 2015- 16 2016 – 17
Pump Stations 16,813,172 16,1,79,907 16,670,605
Repeater Stations 545,519 515,315 473,857
TOTAL(KWH) 17,358,691 16,695,222 17,144,462
Power Sale to other Organization:
The total units of power supplied to other organizations in the FY 2016-17
amounted to 47,553 KWh. Organization wise break-up for the last three years is
shown in the following table.
ORGANISATION LOCATION 2014 – 15 2015 - 16 2016 – 17
ONGC PS-3 10,775 15660 `13604
IOC PS-7 12,891 14969 15118
Contractors PS-5 -- 351 4715
Contractors PS-8 -- 58,389 27720
TOTAL(KWH) 23,666 89,369 47,553
VIII. Highlights of Cathodic Protection Jobs:
Pipeline 65 Km refurbishment work (PS9-RS16 & RS4-RS5) - Carried out Holiday
testing of the 2ply/3ply Tape coating work and installation of 1 Km TLPs.
ON-OFF PSP survey of all pipelines in OIL ROW/ROU is carried out
CAT survey of mainline from PS1 to PS5 carried out
CIPL survey of NSPL between NDT-RS3, RS5-PS5 and RS9-508.4km carried out.
10 | P a g e
NEW PROJECTS AND INFRASTRUCTURE
20KWp PV Solar Power Plant at RS-14, Kishanganj:
20KWp P V Solar Power Plant has been installed & commissioned at RS-14,
Kishanganj on 27th May, 2015 as another achievement in the field of renewable
energy by Pipeline Department of Oil India Limited. In addition to the above, RS-8,
RS-10, RS-11, RS-15 & RS-16 is being taken up for installation of Solar Power Plants of
20 KW capacity each.
ENERGY CONSERVATION AND ENVIRONMENTAL PROTECTION MEASURES
Measures adopted
Efficient maintenance & operation of 20 KWp Solar PV Power Plants installed &
commissioned at RS-5 (Jagiroad) & RS-14 (Kishanganj) is considered as a major
step towards use of renewable energy, thereby serving the cause of energy
conservation.
Replaced high energy consuming street light fitting with energy efficient &
environment friendly 25W LED light which results not only in better illumination
but also saves energy considerably & helps protecting the environment. It helps
saving energy up to 6789 units.
Replacing old electromechanical/hybrid type energy meters with new technology
digital multi-function meter. Replacing existing BC lamps, damaged 20W/40W
tube light fittings with CFL of 9W& 15W results in savings of energy up to 25754
units.
Installation of 5 KWp Solar PV system for RS-6 & RS-7(BG Hills) replacing Diesel
generator is under progress (technical scrutiny completed) and once implemented
it will save considerable amount of energy as well as help protecting the
environment.
Installation & commissioning of 20KWp Solar PV system in 5 nos. repeater station
is in progress. (materials received at RS-8, Dhramapur & others are in transit)
Impact on Energy Consumption
Efficient operation of the solar plants at RS-5 (Jagiroad) & RS-14 (Kishanganj) has led
to a total HSD Fuel savings of 34 KL (appx.) which is equivalent to ₹28,40,229/- in
monetary terms.
11 | P a g e
Contribution to Environmental Protection
By employment of solar energy, it has been possible to reduce the carbon footprint
under CDM (Clean Development Mechanism) with avoidance of good amount of CO2
(approximately 86 Tons). This type of clean energy project will help in achieving
carbon credits by OIL.
IX. ORGANIZATION:
The executive manpower strength of the department as on 31.03.2017 is as follows:
Board sanction : 157 (+12 against manning of MB Lal &
UGPS project)
Permanent Executive : 139 (Including 3 ET’s)
The work person manpower strength of the department as on 31.03.2017 is as
follows:
Sanctioned Strength (PL) : 470
Existing employees against sanctioned strength : 274
Separations during the year 2016-17:
X. TRAINING/ SEMINAR:
Diploma Holders, sponsored by Directorate of Technical Education and Trade
Apprentices had undergone training at PHQ during the year as follows:
Diploma Apprentices : 10
Trade Apprentices : 17
Students were imparted Training, in Both Summer and Winter Season:
Mechanical Stream : 78
Electronics, Telecom and Instrumentation Stream : 37
Electrical Stream : 0
HR Stream : 10
Civil Engineering Stream : 14
Moreover, 21 Company Employees attended various Training Programmes, both In-House and In-Country. On the Executive front, 52 Executives attended In-Country Training Programmes, In-House Programmes and 8 executives attended overseas training.
No of executives retired 07
No of additional executives retired 02
No of executives expired -
No of executive resigned 01
No of ETs resigned 01
12 | P a g e
XI. PROMOTION A total number of 22 executives have been promoted in Pipeline Department during the above period. ET s inducted in Grade B as probationary Officers: 3 Joining: 03
Transfer: 29 XII. AWARDS & PAPERS PUBLISHED:
● सितम्फय, 2016िे 30 सितम्फय, 2016तक विसबन्न्रतितमगिततओं केिओ िनन् ी भओनिभओयगनकओिपरतओऩिूवकआमगजनककमओतमओ।ऩओइऩरओइनभखु्मओरम,तिुओनओटीकेिओ -िओ ऩ ऩस्टेशन नन 3जगयनओटएि ऩ ऩस्टेशन नन 8िगनओऩयुभेंबीिनन् ीभओनके ौयओनकओमवक्रभोंकओआमगजनककमओतमओ।
● सितभ फय, 2016कग ऩओइऩरओइनभखु्मओरम, रईुतऩओय क्रफ िबओतओय भें ‘’राजभाषा हिन् दी र का ा ति ’’ शन ीर्वक ऩय यओजबओर्ओ ि तगष्ठी कओआमगजन ककमओ तमओ । तिुओनओटीनतययओजबओर्ओकओमओवन्िमनिसभित(उऩक्रभ)द्िओयओयओजबओर्ओभेंउत्कृष्ट्रत शन वननेतुऩओइऩरओइनभखु्मओरमकग16ि िम्फय,2016कग्रतशन स्स्तऩत्र्रत ओनककमओतमओ। ऑमर ्रतफ धन सुरमओजओन द्िओयओ ऩओइऩरओइन भखु्मओरम कग यओजबओर्ओ िनन् ी केकओमओवन्िमनभें ककमेतमेििवशे्रष्ठ्रत शन वन नेतु30सितम्फय2016कग्रत भयओजबओर्ओशन ील्ड िे निओजओ तमओ। विि त नग ऩओइऩरओइन भखु्मओरमकग िनयन्तय 13िी फओय मनशन ील्ड्रतओप्तनुआ।
XIII ACKOWLEDGEMENT I offer my sincere thanks and appreciation to all the Executives, Employees and other personnel of Pipeline Department for their invaluable contribution towards the smooth functioning of the department. On behalf of the OIL management I offer my heartfelt appreciation for their active cooperation in achieving the high standard of operation, maintenance and successful completion of all the on- going projects, in a safe and environment friendly manner. I also take this opportunity to acknowledge humbly the encouragement and guidance received from Chairman and Managing Director and all the other functional directors of OIL as well as support from Field Headquarters Duliajan which had greatly contributed to our achievements during the year. I also thank all the Sections for submitting their Annual Reports on time and also to the Planning and Coordinating Section for compiling and presenting it in such a Comprehensive manner.
(B. K. Mishra) General Manager (Pipeline Services)