+ All Categories
Home > Documents > Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of...

Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of...

Date post: 25-Sep-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
37
Annual Report Licence Term 1 15 October 2013 to 29 April 2014 Petroleum Exploration Licence (PEL) 218 South Australian Cooper Basin
Transcript
Page 1: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

Annual Report

Licence Term 1

15 October 2013 to 29 April 2014

Petroleum Exploration Licence (PEL) 218

South Australian Cooper Basin

Page 2: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

2

Contents

1 Introduction ....................................................................................................................... 3 2 Permit Summary ................................................................................................................ 3 3 Regulated Activities ........................................................................................................... 5 3.1 Drilling .......................................................................................................................... 5 3.2 Fracture Stimulation, Completions .............................................................................. 5 3.3 Extended Production Testing ....................................................................................... 7 4 Compliance Issues .............................................................................................................. 7 4.1 Licence and Regulatory Compliance ............................................................................ 7 4.2 Compliance with Statement of Environmental Objectives (SEOs) .............................. 8 4.3 Management Systems Audit ........................................................................................ 8 4.4 Reports and Data Submissions .................................................................................... 9 4.5 Incidents ..................................................................................................................... 10 4.6 Threat Prevention ...................................................................................................... 11 4.7 Future Work Program ................................................................................................ 11

5 Statement of Expenditure ................................................................................................ 12 Table 1 - Original Work Program Commitments ....................................................................... 3 Table 2 - Final Work Program Commitments ............................................................................ 4 Table 3 - Work Completed ......................................................................................................... 4 Table 4 – Summary of Wells Drilled ........................................................................................... 5 Table 5 – Summary of Fracture Stimulation .............................................................................. 6 Table 6 – Summary of Production Testing ................................................................................. 7 Table 7 – Regulatory non-compliances ...................................................................................... 7 Table 8 – Report and Data Submissions .................................................................................... 9 Table 9 – Incidents ................................................................................................................... 11 Appendix 1 – Compliance with SEO – Drilling and Well operations (Drilling) ......................... 13 Appendix 2 – Compliance with SEO – Shale Gas Fracture Stimulation ................................... 26 Appendix 3 – Compliance with SEO – Drilling and Well operations (Flow Testing) ................ 30 Appendix 4 – Expenditure (Commercial in Confidence) .......................................................... 38

Page 3: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

3

1 Introduction Petroleum Exploration Licence (PEL) 218 was granted on 1 November 2007. The Licence is located within the Nappamerri Trough in the Cooper/Eromanga Basin, South Australia. This Annual Report for PEL 218 details the work conducted during the period 15 October 2013 to 29 April 2014 which marks the end of the term and expiry of PEL 218. This Annual Report has been prepared in accordance with Regulation 33 of the Petroleum and Geothermal Energy Act 2000 (the Act). 2 Permit Summary PEL 218 was originally awarded in November 2007 to:

Adelaide Energy Limited (Adelaide) 100%

Beach Petroleum Limited (now Beach Energy Limited) farmed into the Licence on 29 May 2009. Beach Energy Limited (Beach) and Chevron Australia Exploration 1 Pty Ltd (Chevron) executed a PEL 218 Farmin Agreement on 23 February 2013. The Deed of Assignment, Assumption and Amendment between Beach, Adelaide and Chevron was registered on DMITRE’s public register on 4 September 2013. The interests in PEL 218 are now:

Beach Energy Limited 70%

Chevron Australia Exploration 1 Pty Ltd 30% The PEL 218 licensees applied for petroleum retention licences (PRLs) over the area of PEL 218. PRLs 33 to 49 were awarded effective on 29 April 2014. As a consequence of grant of PRLs 33 to 49, the PEL 218 licence term ends with effect on 29 April 2014. The original work commitments for the first term of PEL 218 are detailed in Table 1 below. Table 1: Original Work Program Commitments by Licence Year (as at 1 Nov 2007)

Permit Year

Licence Dates Minimum Work Requirements

Year 1 1 November 2007 - 31 October 2008 Drill 2 wells, acquire 180 km 2D

seismic plus G and G studies

Year 2 1 November 2008 - 31 October 2009 Drill 1 well, acquire 100 km 2D

seismic plus G and G studies

Year 3 1 November 2009 - 31 October 2010 Drill 1 well, acquire 100 km 2D

seismic plus G and G studies

Year 4 1 November 2010 - 31 October 2011 Drill two wells

Year 5 1 November 2011 - 31 October 2012 Drill two wells

Page 4: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

4

Approved variations to the licence conditions including, variations to the work program commitments and licence suspension and suspension / extension of work commitments are listed in Table 2. Table 2: Final Work Program Commitments by Licence Year (varied 26 Oct 2011)

Permit Year

Licence Dates Minimum Work Requirements

Year 1 (firm)

1 November 2007 - 31 October 2008 Acquire 218 km 2D seismic; G & G studies

Year 2 (firm)

1 November 2008 – 14 April 2010 Drill 1 well; acquire plus G & G studies

Year 3 (firm)

15 April 2010 - 14 October 2011 Drill 3 wells*; G & G studies

Year 4 (firm)

15 April 2011 – 14 October 2012 Acquire 162 km 2D seismic; Drill two wells

Year 5 15 April 2012 – 29 April 2014 Drill two wells

* Substitute third well for fracture stimulation/flow testing at Holdfast-1

Table 3: Work Completed by Licence Year (to 29 April 2014)

Permit Year Work Completed

Year 1 (firm) Acquired 218 km Wakefield 2D seismic, G & G studies

Year 2 (firm)

Drilled 1 well (1) G & G studies

Year 3 (firm)

Drilled 2 wells (2) Fracture Stimulation 2 wells (3) G & G studies

Year 4 Acquired 300 km Regius 2D seismic; Drilled 3 wells (4)

Year 5 Drilled 7 wells (5) Fracture Stimulated 8 wells (6)

(1) Wakefield-1 (2) Holdfast-1, Encounter-1 (3) Holdfast-1, Encounter-1 (4) Moonta-1, Streaky-1, Marble-1 (5) Boston-1, Nepean-1, Holdfast-2, Dashwood-1, Boston-2, Rapid-1, Boston-3 (6) Moonta-1, Streaky-1, Marble-1, Nepean-1, Holdfast-2, Dashwood-1, Boston-1, Boston-3

* Substitute third well for fracture stimulation/flow testing at Holdfast-1

Page 5: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

5

3 Regulated Activity

Pursuant to Regulations 33(2) (a), an Annual Report must include: “a summary of the regulated activities conducted during the licence year.”

3.1 Drilling

One horizontal well, Boston-3, was drilled to evaluate the basin centred gas play in the Permian Formations within the Nappamerri Trough during the reporting period. Table 4: Summary of Wells Drilled in PEL 218 in Licence Year

Well Name Boston-3

Type of well Horizontal exploration well

Contractor / Rig Ensign International - Ensign Rig 965

Date Spudded 7 September 2013

Formations Intersected Full representation of Eromanga and Cooper Basin strata was intersected. The depths at which each of the formation tops was intersected will be provided to DMITRE in the Well Completion Report.

Evaluated hydrocarbon pay

Preliminary log analysis indicates that the primary target formations from top Roseneath Shale to Patchawarra Formation are gas saturated. Quantification of hydrocarbon pay is currently ongoing.

Status Cased and Suspended

Rig release date 3 December 2013

Track and Pad construction

Earthworks for access and lease were carried out in accordance with the SEO for Drilling and Well Operations in SA Cooper Basin

Borrow Pit construction Borrow pits were constructed in accordance with the SEO for Petroleum Production Operations in SA Cooper Basin which requires borrow pits to be sited at least 10 metres from all roads and 50 m from public roads.

3.2 Fracture Stimulation, Completion Fracture stimulation of four wells was carried out during the reporting period. Table 5: Summary of Fracture Stimulation activities in PEL 218 in Licence Year

Well Name Holdfast-2

Type of well Horizontal exploration well

Start Date 30 October 2013

Surveys Cement Bond Log

End Date 19 November 2013

No. of Stages fracture stimulated

9

Page 6: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

6

Formations Stimulated Murteree Shale

Completion 2 7/8” tubing completion

Status Production Test completed. Shut-in on pressure build up.

Well Name Dashwood-1

Type of well Vertical exploration well

Start Date 26 November 2013

Surveys Cement Bond Log (pre & post frac)

End Date 1 December 2013

No. of Stages fracture stimulated

4

Formations Stimulated Patchawarra Sandstone

Completion 2 7/8” tubing completion with packer isolating annulus

Status

Production Test completed and 2-7/8” tubing string removed. All perforations isolated by bridge plug and cement. Awaiting fracture stimulation of upper intervals.

Well Name Boston-1

Type of well Vertical exploration well

Start Date 9 February 2014

Surveys Radioactive Tracer (proppant) logging, Cement Bond Log

End Date 14 February 2014

No. of Stages fracture stimulated

2

Formations Stimulated Patchawarra Sandstone

Completion Not completed

Status Downhole isolation. 2 7/8” tubing completion pending

Well Name Boston-3

Type of well Horizontal exploration well

Start Date 25 February 2013

Surveys Radioactive Tracer (proppant) logging, Cement Bond Log

End Date 25 February 2014

No. of Stages fracture stimulated

1

Formations Stimulated Murteree Shale

Completion 2 7/8” tubing completion

Status Production Test completed. Shut-in on pressure build up.

Page 7: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

7

3.3 Extended Production Testing Flow testing of wells is summarised in the below Table 6. Approval for extended production testing (EPT) was approved by DMITRE by granting an exemption under Section 27 (2) of the Act. Table 6 – Summary of Production Testing in Licence Year

Well EPT Approval Granted Date

EPT Approval Expiry EPT Commencement

Date Actual End EPT or Expected End EPT

Nepean-1 1/08/2013 13/08/2014 13/08/2013 (short

flow up casing) 18/4/2014 (EPT)

ongoing

Dashwood-1 13/03/2014 20/06/2014 20/03/2014 25/5/2014

Holdfast-2 19/12/2013 4/06/2014 4/03/2014 10/4/2014

4 Compliance Issues

4.1 Licence and Regulatory Compliance

There were cases during the current reporting period in which the PEL 218 Operator submitted technical reports later than the required timeframe pursuant to Regulation 39 and Regulation 40 of the Petroleum and Geothermal Energy Regulations 2013 (the Regulations). A summary of the non-compliance is provided in Table 7. Table 7 - Regulatory non-compliances in Licence Year

Activity Details of Non-Compliance Rectification of Non-Compliance

Submission of Wireline logs

Regulation 39 – logs for Boston-3 submitted late

Ongoing discussions with contractors regarding provision of data and resourcing issues. Operator to apply for extension of time to avoid non-compliance.

Pursuant to Regulations 33(2) (b) & (c), an Annual Report must include: “a report for the year on compliance with the Act, these regulations, the licence and any relevant statement of environmental objectives;” and “a statement concerning any action to rectify non compliance with obligations imposed by the Act, these regulations or the licence, and to minimise the likelihood of recurrence of any such non-compliances.”

Page 8: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

8

Submission of Well Completion Reports

Regulation 40 – WCR for Nepean-1, Dashwood-1, Boston-2 submitted late

Ongoing discussions with contractors regarding provision of data and resourcing issues. Operator to apply for extension of time to avoid non-compliance.

4.2 Compliance with Statement of Environmental Objectives 4.2.1 Drilling The drilling of wells was conducted in accordance with the South Australia Cooper Basin Statement of Environmental Objectives: Drilling and Well Operations November 2009 (Drilling and Well Operations SEO). Compliance with the Drilling and Well Operations SEO is reported in Appendix 1. 4.2.2 Fracture Stimulation The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture Stimulation of deep Shale Gas and Tight Gas in the Nappamerri Trough (Cooper Basin), South Australia – Statement of Environmental Objectives (Fracture Stimulation SEO). Compliance with the Fracture Stimulation SEO is reported in Appendix 2. 4.2.3 Production Testing

Extended production testing was carried out at Holdfast-2, Dashwood-1 and Nepean-1 during the reporting period in accordance with the Drilling and Well Operations SEO. Compliance with the Drilling and Well Operations SEO is reported in Appendix 3. 4.3 Management System Audits

Pursuant to Regulation 33(2) (d) under the Act, an annual report must include: “a summary of any management system audits undertaken during the relevant licence year including information on any failure or deficiency identified by the audit and any corrective actions that has, or will be taken”.

An audit of the application of Beach’s HSE system was conducted in February-March 2013. A subsequent report detailed the positive application of HSE within Beach’s operations together with some areas for improvement. Those recommendations are addressed as part of annual HSE system objectives which are reported upon quarterly.

Page 9: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

9

An environmental audit of Beach’s shale gas operations in PEL 218 was conducted between December 2013 and March 2014 to assess compliance with the Fracture Stimulation SEO.

Beach utilizes Field HSE Advisors to assess and monitor the application of HSE systems in its operations as well as the HSE systems standards of its Contractors.

Any contractors engaged to undertake activities for Beach operations have their HSE systems audited prior to commencement.

Beach has undertaken an extensive independent review of its Permit to Work (PTW) process. An updated PTW method will be launched early in 2014.

4.4 Report and Data Submissions

Pursuant to Regulation 33(2) (e) under the Act, an annual report must include: “a list of all reports and data relevant to the operation of the Act generated by the licensee during the licence year”.

A list of the reports and data generated and samples submitted in relation to the operations undertaken during the current reporting period for PEL 218 is provided in Table 8. Table 8 - List of Report, Data and Sample Submissions to DMITRE Annual Reports

Description of Report / Data Date Due Date Submitted

Submission of Annual Report for Yr 6 (15April 2013 to 14 October 2013)

13 December 2013

Quarterly Reports

Quarterly Compliance Report for Q3 2013 31 October 2013 31 October 2013

Quarterly Compliance Report for Q4 2013 31 January 2014 31 January 2014

Quarterly Compliance Report for Q1 2014 30 April 2014 30 April 2014

Quarterly Cased Hole Report for Q3 2013 31 October 2013 31 October 2013

Quarterly Cased Hole Report for Q4 2013 31 January 2014 31 January 2014

Page 10: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

10

Quarterly Cased Hole Report for Q1 2014 30 April 2014 30 April 2014

Nepean-1

Well Completion Report 26 August 2013 24 February 2014

Dashwood-1

Well Completion Report 11 November 2013 24 February 2014

Well samples 11 November 2013 28 November 2013 (1)

Boston-2

Well Completion Report 3 December 2013 10 December 2013

Well Samples 19 November 2013 5 December 2013 (1)

Rapid-1

Wireline logs 29 November 2013 8 November 2013

Well Completion Report 3 April 2014 4 April 2014

Well Samples 3 April 2014 1 April 2014

Boston-3

Wireline logs 2 February 2014 12 May 2014

Well Completion Report 7 June 2014 26 May 2014

Well Samples 7 June 2014 Not submitted as at 29

April 2014

(1) Samples at Challenger within 6 months but delivered late to core library. DMITRE advise that if samples are at Challenger, it is considered complaint under Regulation 40.

4.5 Incidents

Pursuant to Regulation 33(2) (f), an annual report must include: “in relation to any incidents reported to the Minister under the Act and these Regulations during the relevant licence year – (i) an overall assessment and analysis of the incidents, including the identification and

analysis of any trends that have emerged; and

Page 11: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

11

(ii) an overall assessment of the effectiveness of any action taken to rectify non-compliance with obligations imposed by the Act, these regulations or the licence, or to minimise the risk of recurrence of any such non-compliance

During the reporting period there were no serious incidents in PEL 218. A serious incident is defined in section 85(1) of the Act. During the reporting period there three incidents which were formally reported to DMITRE through quarterly compliance reporting and are summarised below. A reportable incident is defined in section 85(1) and regulation 32 of the Act. Table 9 - List of Incidents in PEL 218 During Licence Year

Incident Location Incident Root Cause Rectification

Reportable Well site

Potential cultural heritage incident

Communication Cultural Heritage Awareness

Reportable Well site

Potential cultural heritage incident

Induction & Training

Cultural Heritage Awareness

Reportable Well site

Environmental Work Practice Review location of effluent irrigation area

4.6 Threat Prevention

Pursuant to Regulation 33(2) (g) under the Act, an annual report must include: “a report on any reasonably foreseeable threats (other than threats previously reported on) that reasonably present, or may present, a hazard to facilities or activities under the licence, and a report on any corrective action that has, or will be taken”.

There are no foreseeable threats to the proposed exploration activities for PEL 218, other than the disruptive influence of occasional flooding of the Cooper Creek or abnormally high rainfalls in the basin itself. Flooding events in the headwaters of the Cooper Creek are closely monitored by satellite surveillance to predict well in advance the time of their arrival in the PEL 218 area. Drilling schedules will continue to be amended accordingly. 4.7 Future Work Program

Pursuant to Regulation 33(2) (h) under the Act, an annual report must include: “unless the relevant licence year is the last year in which the licence is to remain in force – a statement outlining operations proposed for the ensuing year”.

Not applicable.

Page 12: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

12

5 Statement of Expenditure

Pursuant to Regulation 33(3) under the Act, an annual report must contain: “An annual report must be accompanied by a statement of expenditure on regulated activities conducted under the licence for the relevant licence year, showing expenditure under each of the following headings:

drilling activities;

seismic activities;

technical evaluation and analysis;

other surveys;

facility construction and modification;

operating and administration expenses (not already covered under another heading)”.

The Expenditure Statement for the current reporting period is presented as Appendix 4.

Page 13: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

13

APPENDIX 1

Compliance with the SEO for Drilling and Well Operations PEL 218 (15 October 2013 to 29 April 2014)

Beach’s strategies for achieving each of the SEO objectives for the drilling of Boston-3 is outlined in the Table below. Note: The Santos SEO for Drilling and Well Operations has been adopted by Beach Energy Limited for its Drilling and Well Operations in the South Australian sector of the Cooper Basin. References to 'Appendix 1 Table A2' and 'Appendix 1 Table A3' refer to tables included in Santos' “South Australia Cooper Basin Statement of Environmental Objectives: Drilling and Well Operations November 2009”

Table A1-1 SEO for Cooper Basin Drilling Operations

Objective Assessment Criteria

Compliant

/ Non-compliant

Comments

Objective 1:

Minimise risks to the safety of the public and other third parties.

Reasonable measures implemented to ensure no injuries or health risks to the public or to third parties.

Compliant

Communication of all potential hazards to safety associated with drilling and other well site operations including the rig move to all affected parties, prior to the commencement of such activities. Beach maintained regular contact with the landholder and associated stakeholders during drilling operations. The design and operation of the PEL 218 activities was undertaken in accordance with Beach safety policies, standards and guidelines. All employees visiting or working on the rig undertook a safety induction prior to commencing work in the field and will undertake a refresher course if/when required. Beach's Permit to Work System was in operation during drilling operations to control potentially dangerous situations. Appropriate Personal Protective Equipment (PPE) was issued to all personnel involved in the drilling operations. Accident / incident reporting systems were in place as defined in the Beach Drilling Operation Manual. Records are reviewed regularly to assess trends.

Page 14: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

14

Beach Safety Management Plans are updated and reviewed on a regular basis. The Beach Emergency Response System which includes; Emergency Management Manual, Site Emergency Response Plans and Emergency Management Initial response guidelines were reviewed during 2009 with documentation being updated to meet the changing roles and responsibilities in the organisation. Signage was erected along the access road to advise that only authorised personnel are permitted on to the well site.

Page 15: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

15

Objective Assessment Criteria Compliant

/ Non-compliant

Comments

Objective 2 :

Minimise disturbance and avoid contamination to soil.

Well Site & Access Track Construction 0, +1 or +2 GAS criteria are attained for “Minimise impacts on soil" objective as listed in Appendix 1 Table A1* and "To minimise the visual impact" as listed in Appendix 1 Table A2*. No unauthorised off-road driving or creation of shortcuts. No construction activities are carried out on salt lakes or steep tableland slopes or wetlands land systems. Borrow pit construction and restoration 0, +1 or +2 GAS criteria are attained for “Minimise visual impacts" and "Minimise impact on soil" objectives as listed in Appendix 1 Table A3*

Compliant

Compliant

The well sites and the existing access track and leases were constructed in accordance with the procedures outlined in Beach's "Guidelines for Lease Construction and Restoration". Potential impacts on the environment were carefully considered prior to constructing tracks and the well site. Existing routes were utilised where feasible. Vehicle movements were strictly limited to the defined access track and well pad areas – areas which had been given cultural heritage clearance for the drilling operations. Site specific environmental assessments were conducted to assess environmental, topographical features. No leases or access tracks were constructed on salt lakes, tablelands or wetlands. Where possible, existing borrow pits will be used. Borrow pits will be rehabilitated and restored in accordance with the guidelines set down in DMITRE’s Field Guide for the Environmental Assessment of Abandoned Petroleum Wellsites in the Cooper Basin, South Australia, to attain the highest feasible GAS rating. Topsoil was stockpiled for subsequent respreading when restoration activities are conducted.

Page 16: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

16

Objective Assessment Criteria Compliant

/ Non-compliant

Comments

Production Testing / Well Blowdowns No soil contamination as a result of production testing or well blowdown operations. Fuel and Chemical Storage and Handling No spills/leaks outside of areas designed to contain them. Level of hydrocarbon continually decreasing for in-situ remediation of spills. Soils remediated to a level as determined by the Soil Health Index process Waste Disposal (domestic, sewage and sludges) All domestic wastes are disposed of in accordance with EPA licensing requirements. 0, +1 or +2 GAS criteria are attained for "Site to be left in a clean and tidy condition" objective listed in Appendix 1 Table A2*. No spills or leaks from sewage treatment processing. Refer to Assessment Criteria for Obj 11.

Compliant

Compliant

Compliant

No spills of fuels or chemicals. Beach’s Oil Spill Contingency Plan is included in the Emergency Response Plan. Domestic Wastes were managed as described in the Cooper Basin Drilling & Well Operations EIR. Wastes were collected, stored and transported in covered bins / containers. All rubbish was disposed of at a licensed waste facility. Wastewater treatment plants used for drilling operations conform to SA health requirements.

Page 17: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

17

Objective Assessment Criteria Compliant

/ Non-compliant

Comments

Objective 3 Avoid the introduction or spread of pest plants and animals and implement control measures as necessary.

No weeds or feral animals are introduced to, or spread in, operational areas as a consequence of activities.

Compliant

Rigs and associated equipment cleaned, where appropriate, as per Beach Policy.

Objective 4 Minimise disturbance to drainage patterns and avoid contamination of surface waters and shallow ground resources

Well Lease and Access Track Construction Well sites and access tracks are located and constructed to maintain pre-existing water flows (i.e. channel contours are maintained on floodplains and at creek crossings). Drilling Mud Sumps and Flare Pits No overflow of drill cuttings, muds and other drilling fluids from mud sumps. No waste material disposal to sumps and flare pits. Well Heads (Oil and Gas Systems) No leaks/spills outside of areas designed to contain them.

Compliant

Compliant

Compliant

Drill pad and access track were constructed and located to avoid diversion of flood waters from their natural direction of drainage in the event of inundation. All drill cuttings, muds, and non toxic drill fluids were contained within designated mud sumps with adequate freeboard at the completion of operations to allow for a 1m cover of clean fill at remediation. No leaks or spills. Specific oil spill containment / clean-up materials were and will be on site at all operational times. Beach’s Oil Spill Contingency Plan is included in Beach's Emergency Response Plan. Cased hole testing conducted with every effort to ensure no spills or seepages.

Page 18: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

18

Well Blowdown/Production Testing No water (surface or groundwater) contamination as a result of production testing or well blowdown operations. Fuel/Chemical Storage and Handling No water (surface or groundwater) contamination as a result of fuel or chemical storage and handling. Waste Management Refer to Assessment Criteria for Objective 11.

Compliant

Compliant

Compliant

Waste removed from the well site. Bins are covered to prevent access by wildlife and prevent spread of rubbish by wind. Non-putrescible waste material (including hazardous material) stored safely on site for later removal to an EPA approved disposal facility.

Page 19: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

19

Objective Assessment Criteria Compliant

/ Non-compliant

Comments

Objective 5

Avoid disturbance to sites of cultural

and heritage significance

Proposed well sites and access tracks have been surveyed and any sites of Aboriginal and non-Aboriginal heritage identified. Any identified cultural and heritage sites have been avoided. Note: Where a negotiated agreement or determination for heritage clearance is in place, compliance with the negotiated agreement or determination takes precedence over the above criteria.

Compliant

Beach has an agreement with the Yandruwandha / Yawarrawarrka Native Title Claimant group which specifies the requirements for scouting proposed well sites and access tracks to identify and avoid areas of heritage value and archaeological significance. Joint site visits were carried out with the Yandruwandha / Yawarrawarrka, the Native Title Claimant group. The proposed drilling location and access route were agreed and given heritage clearance for activities within PEL 218. Areas of significance were recorded and marked as exclusion zones.

Objective 6

Minimise loss of aquifer pressure

and avoid aquifer contamination

Drilling & Completion Activities There is no uncontrolled flow to surface (blow out). Sufficient barriers exist in casing annulus to prevent crossflow between separate aquifers or hydrocarbon reservoirs. Relevant Government approval obtained for abandonment of any radioactive tool left downhole. Producing, Injection, Inactive and Abandoned Wells No cross-flow behind casing between aquifers, and between aquifers and hydrocarbon reservoirs unless approved by DWLBC.

Compliant

Compliant

The Drilling Programs for wells are designed to ensure minimal loss of reservoir and aquifer pressures and minimal contamination of freshwater aquifers. Wells have been cased from total depth to surface. The cement bond log demonstrates competent cementing and the isolation of all aquifer units. When abandonment operations are undertaken cement plugs will be installed to isolate any zones that have been perforated to ensure no likelihood of cross-flow. Pressure cementing of the casing annulus will provide sufficient barriers to the potential for cross flow between aquifers to enable the requirements for the abandonment of petroleum wells to be met. A competent cement bond between and across each of the aquifers intersected by the well bore was established. Monitoring programs will be implemented in the future to assess cross-flow behind casing.

Page 20: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

20

Objective Assessment Criteria Compliant

/ Non-compliant

Comments

Objective 7

Minimise

disturbance to native

vegetation and native fauna.

Well Lease and Access Track Construction and Restoration Any sites with rare, vulnerable and endangered flora and fauna have been identified and avoided. 0, +1 or +2 GAS criteria are attained for “Minimise impact on vegetation” objective as listed in Appendix 1 Table 1A and "The revegetation of indigenous species" objective as listed in Appendix 1 Table A2, during well lease and access track site selection, construction and restoration. Borrow Pit Construction and Restoration 0, +1 or +2 GAS criteria are attained for “Minimise impacts on vegetation” objective as listed in Appendix 1 Table A3 during borrow pit site selection construction and restoration. Waste Management Refer to assessment criteria for Objective

Compliant

Compliant

An environmental assessment of the well site was undertaken prior to the commencement of lease construction activities. Although wells are located in the Innamincka Regional Reserve they lie outside the area defined as the Coongie Lakes Wetlands of International Significance, they were not located in or near an area of high biological or wilderness values and hence the drilling operations presented no long term impacts to any such areas.

National Parks and Wildlife flora/fauna databases contain no records of vulnerable or endangered species within several kilometres of the drill site.

Construction of the access tracks to the well sites required minimal clearance of vegetation and the routes were aligned to avoid clearing trees.

Well sites contained only sparse vegetation, and clearance of vegetation was minimised. Drilling sump and water dam fenced to prevent access by large fauna and stock. Any borrow pits established for building the tracks or the drill pad will be rehabilitated and restored in accordance with the guidelines set down in DMITRE’s Field Guide for the Environmental Assessment of Abandoned Petroleum Well Sites in the Cooper Basin, South Australia, to attain the highest feasible GAS rating.

Page 21: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

21

11. Fuel and Chemical Storage and Management Refer to assessment criteria for Objectives 2 and 4.

Compliant

Compliant

Page 22: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

22

Objective Assessment Criteria Compliant

/ Non-compliant

Comments

Objective 8

Minimise air pollution and

greenhouse gas emissions.

Compliance with EPA requirements.

Compliant

No open hole testing was undertaken.

Objective 9

Maintain and

enhance partnerships with the Cooper Basin

community.

No unresolved reasonable complaints from the community.

Compliant

Beach maintained regular contact with the landholder and associated stakeholders prior to, and while undertaking drilling operations. Beach enhances partnerships with the local community through various events and sponsorships. No complaints received.

Page 23: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

23

Objective Assessment Criteria Compliant

/ Non-compliant

Comments

Objective 10

Avoid or minimise

disturbance to stakeholders

and/or associated

infrastructure

No reasonable stakeholder complaints left unresolved.

Compliant

Beach maintained regular contact with the landholder and associated stakeholders prior to and while undertaking drilling at all well sites. Discussions will be undertaken with the landowner to determine whether he wishes to have any rehabilitation work undertaken on the access track. Wells are located nearby to public roads regularly used by tourists. Signs advising of no unauthorised entry to the well sites were erected at the beginning of each access track. At the completion of the operations, temporary cattle proof fencing was erected to isolate any pits or plant remaining on site. The fencing will be kept in place until rehabilitation operations on the well site resume.

Objective 11

Optimise (in

order of most to least preferable) wast avoidance, reduction, reuse,

recycling, treatment and

disposal

All wastes to be disposed of at an EPA licenced facility in accordance with criteria developed with the exception of the National Environment Protection Measure for contaminated sites, and wastewater (see below). Wastewater (sewage and grey water) disposed of in accordance with the Public and Environmental Health (Waste Control) Regulations 1995 or to the Department of Health's satisfaction.

Compliant

Compliant

Waste was removed from well sites to an EPA licenced disposal facility in accordance with Beach’s policy set out prior to final restoration. Bins are covered to prevent access track and rig site. Non-putrescible waste material (including hazardous material) was stored safely on site for later removal to an EPA approved disposal facility. Beach conducts post drilling audits to ensure drill sites and associated tracks are free of waste materials and left in a tidy and safe condition. Wastewater treatment plants used for drilling operations conform to SA health requirements.

Page 24: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

24

Attainment of GAS criteria for “Site to be left in left in clean, tidy and safe condition" objective during well site restoration (refer Appendix 1 Table A2): - “To minimise the visual impact" - “The revegetation of indigenous

species"

Compliant

Objective 12

Remediate and

rehabilitate operational areas

to agreed standards.

No unresolved reasonable stakeholder complaints. Contaminated Site Remediation Contaminated sites are remediated to a level as determined by the approved SHI process. Prior to the finalisation and approval of the SHI process, contaminated sites are remediated in accordance with criteria developed with the principles of the National Environment Protection Measure for contaminated sites, and in consultation with the EPA. Well Site and Access Track Restoration The attainment of 0, +1 or +2 GAS criteria for the objectives (refer Appendix 1 Table A2):

“To minimise the visual impact"

“The revegetation of indigenous

Compliant

Compliant

Compliant

Following testing, leases will be rehabilitated leaving a level work area for future workover requirements as part of the on-going work scope to use these wells for microseismic observation and/or water producers. Contaminated sites are remediated in accordance with Beach Guidelines and Industry Standards. Discussions will be undertaken with the landowner to determine whether he wishes to have any rehabilitation work undertaken on the access track and rig site. Post operations audits conducted on wellsites following the completion of rehabilitation works.

Page 25: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

25

species"

Borrow Pit Restoration The attainment of 0, +1 or +2 GAS criteria for (refer Appendix 1 Table A3):

"Rejuvenation of indigenous species"

"Minimise impact on soil"

“Minimise visual impacts”

"Site to be left in a clean and tidy condition"

Compliant

Borrow pits will be rehabilitated and restored using effective contouring in accordance with the guidelines set down in DMITRE’s Field Guide for the Environmental Assessment of Abandoned Petroleum Wellsites in the Cooper Basin, South Australia, to attain the highest feasible GAS rating.

Page 26: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

26

APPENDIX 2

Compliance with the Beach Shale Gas Fracture Stimulation SEO (Beach 2012) PEL 218 reporting period 15 October 2013 to 29 April 2014

Beach’s strategies for achieving each of the SEO objectives for the fracture stimulation of wells are outlined in Table below.

Environmental Objectives

Assessment Criteria Compliant / Non-compliant

Beach Management Strategy / Comment

1. Avoid aquifer contamination.

No undesired flow between geological units or to surface.

No contamination of aquifers as a result of fracture stimulation operations.

Compliant

Compliant

Geological and geomechanical settings consistent with the EIR. Stimulated zones are the deeper of the zones listed in the EIR, so the risk of propagation into aquifers above was further reduced.

Microseismic monitoring not undertaken.

2. Minimise impacts of groundwater use.

No reasonable stakeholder complaints left unresolved.

No impact on groundwater dependent ecosystems resulting from extraction of groundwater.

Compliant

Compliant

No complaints received

3. Avoid contamination of surface water and shallow groundwater.

No leaks / spills outside of areas designed to contain them.

No overflow or escape of flowback fluids from temporary ponds.

No water (surface or groundwater) contamination as a result of fracture stimulation operations.

Compliant

Compliant

Compliant

Ponds are not located in close proximity to Cooper Creek or other significant watercourses.

Pond installation as per SEO requirements. Daily water level monitoring will be used for water balance method of leak detection during active testing, reverting to weekly while equipment remains on site and fortnightly until liner is removed.

Beach has established a regional bore monitoring program.

4. Minimise disturbance and avoid contamination to

No overflow or escape of fluids from temporary ponds.

No soil contamination as a result of

Compliant

All ponds fully lines to collect fluids

Vertical flaring stack employed for testing.

A spill of fluid was rectified immediately.

Page 27: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

27

Environmental Objectives

Assessment Criteria Compliant / Non-compliant

Beach Management Strategy / Comment

soil. fracture stimulation and flowback operations.

Fuel and Chemical Storage and Handling

No spills / leaks outside of areas designed to contain them.

Level of hydrocarbon and other contaminants continually decreasing for in situ remediation of spills.

Also refer to Objective 12 for remediation of contaminated sites.

Waste Disposal

Refer to Assessment Criteria for Objective 11.

Compliant

Emergency response drills regularly carried out.

5. Minimise disturbance to native vegetation and native fauna.

No unauthorised clearing of vegetation.

Activities confined to cleared areas (e.g. access tracks and prepared well lease).

Fauna casualties reduced to as low as reasonably practicable.

Waste Management

Refer to assessment criteria for Objective 11.

Fuel and Chemical Storage and Handling

Refer to assessment criteria for Objective 4.

Compliant

Compliant

Compliant

Activities confined to pre-existing well lease and ponds.

Daily inspections for fauna incursions will be carried out during flowback and active testing, reverting to weekly while equipment remains on site and until liner is removed.

Page 28: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

28

Environmental Objectives

Assessment Criteria Compliant / Non-compliant

Beach Management Strategy / Comment

6. Avoid the introduction or spread of pest plants and animals and implement control measures as necessary.

No weeds or feral animals are introduced to, or spread in, operational areas as a consequence of activities.

Compliant Activities confined to the cleared well lease, laydown areas and access tracks.

No evidence of introduction of weeds to well sites.

7. Avoid disturbance to sites of cultural and heritage significance

Well lease and access tracks have been surveyed and any sites of Aboriginal and non-Aboriginal heritage identified.

Any identified cultural and heritage sites have been avoided.

Compliant Activities confined to the cleared well lease, laydown areas and access tracks.

8. Minimise air pollution and greenhouse gas emissions.

No reasonable stakeholder complaint left unresolved.

No unplanned gas releases.

Well production diverted to flare as soon as practicable.

Well testing curtailed when test objectives are satisfied.

Compliant Operations conducted in accordance with approved procedures, including monitoring of gas emissions during stimulation and production testing activities.

9. Minimise risks to the safety of the public, employees and other third parties.

Reasonable measures implemented to ensure no injuries or health risks as a result of the activities.

Compliant Warning signage erected on pulic roads where required to warn of restricted entry and traffic hazards and significant transportation movements.

10. Avoid or minimise disturbance to stakeholders and /

No reasonable stakeholder complaints left unresolved.

Compliant Stakeholder consultation, liaison and NOA and NOE undertaken.

Sites not located in close proximity to homesteads or Innamincka townshipPonds fenced to prevent stock access.

Page 29: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

29

Environmental Objectives

Assessment Criteria Compliant / Non-compliant

Beach Management Strategy / Comment

or associated infrastructure.

11. Optimise (in order of most to least preferable) waste avoidance, reduction, reuse, recycling, treatment and disposal.

Wastes to be disposed of at an EPA licensed facility in accordance with EPA licence conditions.

No waste material disposal to sumps and flare pits with the exception of drilling fluids, drill cuttings, other fluids disposed during well clean-up (under the Drilling and Well Operations SEO).

Compliant Wastes segregated, appropriately stored and transported and disposed of at an EPA licenced facility.

12. Remediate and rehabilitate operational areas.

No reasonable stakeholder complaints left unresolved.

Contaminated Site Remediation

Contaminated sites are remediated in accordance with criteria developed with the principles of the National Environment Protection Measure for contaminated sites, and in consultation with the EPA.

Note: Well abandonment and well site restoration issues are addressed under Objectives 6 and 12 in the Drilling and Well Operations SEO

Compliant Site rehabilitation will be undertaken in accordance with relevant Beach procedures.

Page 30: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

30

APPENDIX 3

Compliance with the SEO for Drilling and Well Operations (Flow Testing) PEL 218 (15 October 2013 to 29 April 2014)

Beach’s strategies for achieving each of the SEO objectives for the production testing of wells are outlined in Table below.

Environmental Objective

Assessment Criteria Compliant / Non-compliant

Beach Management Strategy / Comment

1. Minimise risks to the safety of the public and other third parties.

Reasonable measures implemented to ensure no injuries or health risks to the public or third parties.

Compliant Measures such as inductions, PPE, permit to work implemented.

Warning signage erected and site access restricted during testing activities.

2. Minimise disturbance and avoid contamination to soil.

Well Site and Access Track Construction

0, +1 or +2 GAS criteria are attained for “Minimise impacts on soil” objective as listed in Appendix 1 Table A1 and “To minimise the visual impact” as listed in Appendix 1 Table A2.

No unauthorised off-road driving or creation of shortcuts.

No construction activities are carried out on salt lakes or steep tableland slopes (as defined in EIR).

Compliant Production testing activities restricted to existing well lease and associated laydown and access tracks.

Borrow pit construction and restoration

0, +1 or +2 GAS criteria are attained for “Minimise visual impacts’, and “Minimise impact

N/A Additional borrow pits not required. Existing borrow pits used where required.

Page 31: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

31

Environmental Objective

Assessment Criteria Compliant / Non-compliant

Beach Management Strategy / Comment

on soil” objectives as listed in Appendix 1 Table A3.

Production Testing/Well Blowdowns

No soil contamination as a result of production testing or well blowdown operations.

Compliant Separator used with flowback to lined ponds.

Fuel and Chemical Storage and Handling

No spills/leaks outside of areas designed to contain them.

Level of hydrocarbon continually decreasing for in situ remediation of spills.

Soils remediated to a level as determined by the SHI process.

Also refer to Objective 12.

Compliant Storage and bunding of fuel and chemicals carried out to a high standard, in accordance with appropriate standards and guidelines (e.g. EPA guidelines, AS1940).

Emergency response plans and equipment will be in place.

Waste Disposal (domestic, sewage and sludges)

All domestic wastes are disposed of in accordance with EPA licensing requirements.

0, +1 or +2 GAS criteria are attained for “Site to be left in a clean and tidy condition” objective listed in Appendix 1 Table A2.

No spills or leaks from sewage treatment processing.

Compliant Waste will be collected in well covered bins prior to offsite disposal at an approved facility.

Camp sewage treatment will be via an approved system or operated to the satisfaction of the Department of Health.

Page 32: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

32

Environmental Objective

Assessment Criteria Compliant / Non-compliant

Beach Management Strategy / Comment

Refer to Assessment Criteria for Objective 11.

3. Avoid the introduction or spread of pest plants and animals and implement control measures as necessary

No weeds or feral animals are introduced to, or spread in, operational areas as a consequence of activities.

Compliant Production testing activities restricted to existing well lease and associated laydown and access tracks.Vehicles and equipment coming from outside the Cooper Basin or from a known area of weed infestation will be washed down prior to entry to site.

4. Minimise disturbance to drainage patterns and avoid contamination of surface waters and shallow ground water resources.

Well Lease and Access Track Construction

Well sites and access tracks are located and constructed to maintain pre-existing water flows (i.e. channel contours are maintained on floodplains and at creek crossings).

Compliant Production testing activities restricted to existing well lease and associated laydown and access tracks.Additional earthworks not required.

Drilling Mud Sumps and Flare Pits

No overflow of drill cuttings, muds and other drilling fluids from mud sumps.

No waste material disposal to sumps and flare pits.

Compliant Fluids contained on site in adequately sized, lined ponds. Ponds will be rehabilitated on completion.

Well Heads (Oil and Gas Systems)

No leaks/spills outside of areas designed to contain them.

Compliant

Well Blowdown/Production Testing

No water (surface or

Compliant Separator used with flowback to lined ponds.

Page 33: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

33

Environmental Objective

Assessment Criteria Compliant / Non-compliant

Beach Management Strategy / Comment

groundwater) contamination as a result of production testing or well blowdown operations.

Fuel/Chemical Storage and Handling

No water (surface or groundwater) contamination as a result of fuel or chemical storage and handling

Compliant Refer to Objective 2.

Waste Management

Refer to Assessment Criteria for Objective 11.

Compliant Refer to Objective 11.

5. Avoid disturbance to sites of cultural and heritage significance

Proposed well sites and access tracks have been surveyed and any sites of Aboriginal and non-Aboriginal heritage identified.

Any identified cultural and heritage sites have been avoided.

Compliant Production testing activities restricted to existing well lease and associated laydown and access tracks.

All activities confined to the area covered by the WAC.

6. Minimise loss of aquifer pressures and avoid aquifer contamination.

Drilling & Completion Activities

There is no uncontrolled flow to surface (Blow out).

Sufficient barriers exist in casing annulus to prevent crossflow between separate aquifers or hydrocarbon reservoirs.

Relevant government approval obtained for abandonment of any radioactive tool left downhole.

Compliant Hole casing, cementing and abandonment will be in accordance with SEO requirements.

Page 34: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

34

Environmental Objective

Assessment Criteria Compliant / Non-compliant

Beach Management Strategy / Comment

Producing, Injection, Inactive and Abandoned Wells

No cross-flow behind casing between aquifers, and between aquifers and hydrocarbon reservoirs unless approved by DWLBC. Compliant

Compliant

7. Minimise disturbance to native vegetation and native fauna

Well Lease and Access Track Construction and Restoration

Any sites with rare, vulnerable and endangered flora and fauna have been identified and avoided.

0, +1 or +2 GAS criteria are attained for “Minimise impact on vegetation” objective as listed in Appendix 1 Table A1 and “The revegetation of indigenous species” objective as listed in Appendix 1 Table A2, during well lease and access track site selection and construction and restoration.

Borrow Pits Construction and Restoration

0, +1 or +2 GAS criteria are attained for “Minimise impacts on vegetation” objectives as listed in Appendix 1 Table A3 during borrow pit site selection,

Compliant Refer to previous assessment s (RPS 2011).

Restoration of sites, ponds and borrow pits will be carried out in accordance with the SEO when they are no longer required.

Page 35: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

35

Environmental Objective

Assessment Criteria Compliant / Non-compliant

Beach Management Strategy / Comment

construction, and restoration.

Waste Management

Refer to assessment criteria for Objective 11.

Compliant Refer to Objective 2.

Fuel and Chemical Storage and Management

Refer to assessment criteria for Objectives 2 and 4.

Compliant Refer to Objective 2 and 4.

8. Minimise air pollution and greenhouse gas emissions.

Compliance with EPA requirements.

Compliant Testing carried out in accordance with industry standards (including relevant parameters established in the Beach Shale Gas Fracture Stimulation SEO – see above).

9. Maintain and enhance partnerships with the Cooper Basin community.

No unresolved reasonable complaints from the community.

Compliant Landowners have been (and will continue to be) notified in accordance with P&GE Act requirements.

10. Avoid or minimise disturbance to stakeholders and/or associated infrastructure.

No reasonable stakeholder complaints left unresolved.

Compliant Landholders have been consulted regarding the proposed activities.

Ponds fenced to prevent stock access.

11. Optimise (in order of most to least preferable) waste avoidance,

All wastes to be disposed of at an EPA licensed facility in accordance with EPA Licence conditions, with the exception of

Compliant

Waste collected in covered bins and disposed of at an appropriately licensed facility.

Camp wastewater disposal via an approved system or operated to the satisfaction of the Department of Health.

Page 36: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

36

Environmental Objective

Assessment Criteria Compliant / Non-compliant

Beach Management Strategy / Comment

reduction, reuse, recycling, treatment and disposal.

drilling fluids, drill cuttings, other fluids disposed during well clean-up and wastewater (see below).

Wastewater (sewage and grey water) disposed of in accordance with the Public and Environmental Health (Waste Control) Regulations 1995 or to the Department of Health’s satisfaction.

Attainment of GAS criteria for “Site to be left in clean, tidy and safe condition” objective during well site restoration (refer Appendix 1 Table A2).

Attainment of GAS criteria for “Site left in clean and tidy condition” objective during borrow pit restoration (refer Appendix 1 Table A3).

Compliant

Compliant

Compliant

12. Remediate and rehabilitate operational areas to agreed standards.

No unresolved reasonable stakeholder complaints.

Compliant The sites will be restored in consultation with stakeholders and according to industry standards (e.g. SEO, PIRSA (2009) Field Guide for the Environmental Assessment of Abandoned Petroleum Well sites in the Cooper Basin, South Australia).

Contaminated Site Remediation

Contaminated sites are remediated to a level as determined by the approved SHI process.

N/A

Page 37: Annual Report Licence Term 1 Petroleum Exploration Licence ... · The fracture stimulation of Holdfast-2, Dashwood-1, Boston-1 & Boston-3was conducted in accordance with the Fracture

37

Environmental Objective

Assessment Criteria Compliant / Non-compliant

Beach Management Strategy / Comment

Prior to the finalisation and approval of the SHI process, contaminated sites are remediated in accordance with criteria developed with the principles of the National Environment Protection Measure for contaminated sites, and in consultation with the EPA.

The attainment of 0, +1 or +2 GAS criteria for the objectives (refer Appendix 1 Table A2):

- “To minimise the visual impact”

- “The revegetation of indigenous species”

N/A

Borrow Pit Restoration

The attainment of 0, +1 or +2 GAS criteria for (refer Appendix 1 Table A3):

- “Revegetation of indigenous species”

- “Minimise impact on soil”

- “Minimise visual impacts”

- “Site to be left in a clean and tidy condition”

Note: Well abandonment issues are addressed under Objective 6.

N/A


Recommended