Annunciation Greek Orthodox
Church of Sacramento
Parish Campus Master Plan Update
1/27/13
Planning & Vision Update
• Planning Department Approval • Site & Floor Plans – Refinements – Site Plan Input/comments from City – Service Corridor to support two functions in
the Hall – Classroom refinements to support Preschool
• Architecture – Refinements • Next Steps
• Schedule
1st Floor Plan
Site Plan Refinement
1st Floor Plan
2nd Floor Plan
Architecture- Aerial View
View from Alhambra & F
View from 30th Street
View from 30th and G
View from McKinley Park
View from Alhambra & G
View of Plateia
View from McKinley Park
Evening Event in the Plateia
Next Steps
• Design Development Process
– Further Floor Plan refinements
– Follow up meetings with Ministry Groups
– System Development (site infrastructure, structural,
electrical, mechanical, plumbing, low voltage, etc.)
– Interior Architecture and Design
• Cost Estimating & Analysis
• Capital Campaign
• Always – input, input, input
Schedule
• Design Development: 2-2.5 months
• Construction Documents: 2-2.5 months
• Permitting: 6-8 weeks
• Concurrent Capital Campaign
• Construction: 8-12 months depending on
fundraising (1 or 2 phases)