1
Application for Environmental Clearance
of
“545 Bedded Hospital”
Site no. 2, Zone H-4/5, Facility Centre
Pitampura, New Delhi
For: -
Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Regd. Off. -823, DLF Tower-A, Jasola District Centre, New Delhi-110025
PREPARED BY:
M/S PERFACT ENVIRO SOLUTIONS PVT. LTD. (NABET Registered Vide list of accredited consultants organizations/ Rev.78 /10th July, 2019 at S.No.-112)
(An ISO 9001:2008 & ISO 14001:2004 Certified Company)
5th Floor, NN Mall, Sector 3, Rohini, New Delhi-110085
Phone: +91-11-49281360
TABLE OF CONTENTS
ENCLOSURE 1. FORM-I & IA ......................................................................................................................... 4
ENCLOSURE 2: CONCEPTUAL PLAN ......................................................................................................... 41
INTRODUCTION .......................................................................................................................................................... 42
ACTIVITIES/ AMENITIES ............................................................................................................................................. 42
SITE LOCATION .......................................................................................................................................................... 42
TYPE OF PROJECT ...................................................................................................................................................... 42
PROJECT DETAILS ...................................................................................................................................................... 42
POPULATION DETAILS ............................................................................................................................................... 45
WATER MANAGEMENT .............................................................................................................................................. 45
RAIN WATER COLLECTION DETAILS ........................................................................................................................... 45
POWER REQUIREMENT & BACK-UP ........................................................................................................................... 45
SOLID & HAZARDOUS WASTE MANAGEMENT ........................................................................................................... 46
PARKING MANAGEMENT ........................................................................................................................................... 46
GREEN AREA DEVELOPMENT .................................................................................................................................... 46
ENCLOSURE 3. ENVIRONMENT MANAGEMENT PLAN ......................................................................... 47
3.1 PROJECT DETAILS .................................................................................................................................... 49
3.1.1 . AREA DETAILS: ........................................................................................................................................... 50
3.1.2 POPULATION DETAILS ................................................................................................................................... 51
3.1.3 PARKING MANAGEMENT ............................................................................................................................... 51
3.1.4 POWER REQUIREMENT AND BACKUP DETAILS .............................................................................................. 52
3.1.5 WASTE WATER, RAIN WATER AND SOLID WASTE DETAILS ......................................................................... 52
3.2 LAND USE AND OWNERSHIP OF THE SITE LAND ............................................................................................. 53
3.3 LAND USE ..................................................................................................................................................... 53
3.4 LOCATION OF THE PROJECT WITH CONNECTIVITY .......................................................................................... 54
3.4.1 GEOGRAPHICAL INFORMATION OF SITE......................................................................................................... 54
3.4.2 TOPOGRAPHICAL MAP................................................................................................................................... 55
3.5 CONNECTIVITY OF THE PROJECT ................................................................................................................... 55
3.6 CENTRALLY PROTECTED MONUMENTS UNDER DELHI CIRCLE ...................................................................... 56
3.7 LAYOUT PLAN ............................................................................................................................................... 56
3.8 WATER MANAGEMENT ................................................................................................................................. 57
3.8.1 SOURCE OF WATER ....................................................................................................................................... 57
3.8.2 PRESENT QUALITY ........................................................................................................................................ 57
3.8.3 WATER REQUIREMENT .................................................................................................................................. 57
3.8.4 DISPOSAL ...................................................................................................................................................... 58
3.9 AIR AND NOISE MANAGEMENT ..................................................................................................................... 59
3.9.1 DURING CONSTRUCTION PHASE .................................................................................................................... 59
3.9.2 DURING OPERATION PHASE .......................................................................................................................... 59
3.10 ENERGY CONSERVATION MEASURES ............................................................................................................ 59
3.11 ENVIRONMENT MANAGEMENT ...................................................................................................................... 59
3.11.1 ENVIRONMENT MANAGEMENT DURING CONSTRUCTION PHASE ............................................................... 60
3.11.1.1 AIR ENVIRONMENT ......................................................................................................................... 60
ANNUAL WINDROSE DIAGRAM.................................................................................................................................. 60
3.11.1.2 NOISE ENVIRONMENT ........................................................................................................................... 61
3.11.1.3 WATER ENVIRONMENT ......................................................................................................................... 62
3.11.1.4 SOLID WASTE MANAGEMENT ............................................................................................................... 62
1
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
3.11.2 ENVIRONMENT MANAGEMENT DURING OPERATION PHASE ...................................................................... 63
3.11.2.1 AIR ENVIRONMENT ......................................................................................................................... 63
3.11.2.2 NOISE ENVIRONMENT .................................................................................................................... 63
3.11.2.3 WATER MANAGEMENT .................................................................................................................. 64
3.11.2.3.1 WASTE WATER TREATMENT................................................................................................................. 64
3.1.1.1.1 SCHEME OF EFFLUENT TREATMENT PLANT............................................................................. 67
3.11.2.3.2 RAIN WATER HARVESTING ................................................................................................................... 68
3.11.2.4 WASTE MANAGEMENT .................................................................................................................. 71
3.11.2.4.1 MUNICIPAL SOLID WASTE .................................................................................................................... 71
3.11.2.4.2 BIOMEDICAL WASTE MANAGEMENT .................................................................................................... 72
3.11.2.4.3 HAZARDOUS WASTE MANAGEMENT: - ................................................................................................. 72
3.11.2.5 PLANTATION .................................................................................................................................... 72
3.11.3 ANTICIPITATED IMPACT & MITIGATION MEASURES ................................................................. 73
3.11.3.1 DURING CONSTRUCTION PHASE ................................................................................................. 73
3.11.3.2 DURING OPERATION PHASE ......................................................................................................... 74
3.12 ENVIRONMENT MONITORING PLAN ................................................................................................... 76
3.13 ENVIRONMENT MANAGEMENT COST ............................................................................................................ 77
3.13.1 CAPITAL COST .......................................................................................................................................... 77
3.13.2 RECURRING EXPENDITURE ........................................................................................................................ 77
3.14 CORPORATE ENVIRONMENT RESPONSIBILITY ............................................................................................... 77
ENCLOSURE 4. RISK ASSESSMENT ............................................................................................................ 79
4.1 RISK ASSESSMENT ................................................................................................................................... 80
4.1 DISASTER MANAGEMENT PLAN .......................................................................................................... 80
4.2 SAFETY MEASURES: ................................................................................................................................ 82
ENCLOSURE 5. DISCLOSURE OF THE CONSULTANT ............................................................................. 88
ENCLOSURE 6. EARLIER ENVIRONMENTAL CLEARANCE ................................................................... 91
ENCLOSURE 7. CERTIFIED COMPLIANCE REPORT ............................................................................... 99
ENCLOSURE 8. CENTRALLY PROTECTED MONUMENTS AROUND DELHI CIRCLE ........................104
ENCLOSURE 9. LAND PAPERS .....................................................................................................................106
ENCLOSURE 10. DUAC APPROVAL ............................................................................................................117
ENCLOSURE 11. WATER PERMISSION ..................................................................................................... 119
ENCLOSURE 12. AIRPORT AUTHORITY OF INDIA APPROVAL ........................................................... 121
ENCLOSURE 13. POWER ASSURANCE .......................................................................................................124
ENCLOSURE 14. TEST REPORTS .................................................................................................................126
ENCLOSURE 15. AIR DISPERSION REPORT ..............................................................................................136
ENCLOSURE 16. TRAFFIC ASSESSMENT REPORT ..................................................................................148
ENCLOSURE 17. LANDSCAPE REPORT ................................................................................................... 162
ENCLOSURE 18. TOPOGRAPHICAL MAP ................................................................................................ 164
ENCLOSURE 19. LAYOUT PLAN ................................................................................................................166
2
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
ENCLOSURE 20. TYPICAL BASEMENT PARKING PLAN ...................................................................... 168
ENCLOSURE 21. FIRE FIGHTING PLAN .................................................................................................. 170
ENCLOSURE 22: STORM WATER DRAINAGE PLAN .............................................................................. 172
ENCLOSURE 23. SEWERAGE LAYOUT PLAN ......................................................................................... 174
3
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
ENCLOSURE 1. FORM-I & IA
4
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
APPENDIX I
(See paragraph – 8.9)
FORM 1
I. Basic Information
S.No. Item Details
1. Name of the project/s “545 Bedded Hospital”
2. S. No. in the schedule 8(a)
3. Proposed capacity/ area/length/
tonnage to be handled/ command area/
lease area/ number of wells to be drilled
Total Plot area: 29999.34 m2 (2.999934 ha.)
Total Built up area: 94956.31 m2
4. New/ Expansion/ Modernization New
The project has already been granted Environmental
Clearance for the construction of Hospital vide letter
no. 21-1114/2207-IA.III dated 14.11.2008 for plot
area 29999.34 m2 and built-up area 96740.19 m2.
However, only excavation & part basement
construction has been done after the grant of
Environmental Clearance and no construction has
been carried out after that. Environmental Clearance
has also been expired.
Now, due to change in planning, the built-up area
shall be revised to 94956.31 m2.
5. Existing Capacity/ Area etc. Not Applicable
6. Category of Project i.e. ‘A’ or ‘B’ B
However, the tenure of SEAC (Delhi Committee) has
been completed so the application is being applied to
MoEF & CC.
7. Does it attract the general condition? If
yes, please specify.
No
8. Does it attract the specific condition? If
yes, please specify.
No
9. Location
Plot/ Survey/ Khasra No. Site No. – 2, Zone H-4/5, Facility Centre
Village Pitampura
Tehsil Saraswati Vihar
District North West Delhi
State New Delhi
5
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
10. Nearest railway station/ airport along
with distance in kms.
Nearest Railway Station:
Shakur Basti Railway Station, 1.83 km SE
Nearest Airport:
Indira Gandhi International Airport, 14.72 km SSW
11. Nearest Town, city, District
Headquarters along with distance in
kms.
Project is in Delhi Itself.
12. Village Panchayats, Zilla Parishad,
Municipal Corporation, Local body
(complete postal addresses with
telephone nos. to be given)
North Delhi Municipal Corporation at Pitampura
Village, Saraswati Vihar, Pitampura, New Delhi-
110034.
13. Name of the applicant Dr. Narayan Dutt Shrimali Foundation International
Charitable Trust Society
14. Registered Address 823, DLF Tower - A, Jasola District Center, New
Delhi - 110025
15. Address for correspondence:
Name Mr Harsh Vardhan Bansal
Designation (Owner/Partner/CEO) Secretary
Address 823, DLF Tower - A, Jasola District Center, New
Delhi
Pin Code 110025
E-mail [email protected]
Telephone No. 9811612189
011-20218668
Fax no. -
16. Details of Alternative Sites examined,
if any. Location of these sites should be
shown on a Topo sheet.
No alternative site has been chosen. The land has
been given on lease by DDA to Dr. Narayan Dutt
Shrimali Foundation International Charitable Trust
Society for development of Integrated Hospital.
17. Interlinked Projects No
18. Whether separate application of
interlinked project has been submitted?
Not Applicable
19. If yes, date of submission Not Applicable
20. If no, reason Not applicable
6
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
21. Whether the proposal involves
approval/clearance under: if yes, details
of the same and their status to be given.
(a) The Forest (Conservation) Act,
1980?
(b) The Wildlife (Protection) Act,
1972?
(c) The C.R.Z. Notification, 1991?
Not Applicable
Not Applicable
Not Applicable
22. Whether there is any Government
Order/ Policy relevant/ relating to the
site?
Not Applicable
23. Forest land involved (hectares) No forest land is involved.
24. Whether there is any litigation pending
against the project and/ or land in which
the project is propose to be set up?
(a) Name of the Court
(b) Case No.
(c) Orders/ directions of the Court,
if any and its relevance with the
proposed project.
Not Applicable
Not Applicable
Not Applicable
II. Activity
1. Construction, operation or decommissioning of the Project involving actions, which will
cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate quantities /rates,
wherever possible) with source of information data
1.1 Permanent or temporary
change in land use, land
cover or topography
including increase in
intensity of land use
(with respect to local
land use plan)
No As per the Master Plan Delhi 2021, the site has already been
earmarked for Hospital. Hence, there will be no change in
Land Use.
However, land cover shall change to Hospital Building.
7
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
1.2 Clearance of existing
land, vegetation and
buildings?
No At proposed site, excavation & part basement construction has
already been done after the grant of Environmental Clearance
and no other construction has been carried out after that. Also,
around 70-80 trees are present at the site which shall be
transplanted within the site during construction.
1.3 Creation of new land
uses?
No Since, the land of the proposed project has already been
earmarked for Hospital building as allowed according to the
Master Plan of Delhi 2021.
Hence, there will be no creation of new land uses.
1.4 Pre-construction
investigations e.g. bore
houses, soil testing?
Yes Pre-construction Geo-technical investigation have been done.
1.5 Construction works? Yes
Construction will be done as per approved Building Plan/
Master Plan.
1.6 Demolition works? No There will be no demolition works.
1.7 Temporary sites used
for construction works
or housing of
construction workers?
No Not Applicable.
1.8 Above ground
buildings, structures or
earthworks including
linear structures, cut and
fill or excavations
Yes The building will be elevated to height of maximum height of
45 m at terrace level. At proposed site excavation & part
basement construction has already been done after the grant of
Environmental Clearance. The maximum level of basement is
two.
1.9 Underground works
including mining or
tunnelling?
No Not applicable
1.10 Reclamation works? No Not applicable
1.11 Dredging? No Not applicable
1.12 Offshore structures? No Not applicable
1.13 Production and
manufacturing
processes?
No No production or manufacturing will be done as the proposed
land will be used for Hospital and for development of hospital
related infrastructures.
1.14 Facilities for storage of
goods or materials?
Yes During Construction Phase:
8
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Separate raw material yard will be made within the project
site.
Cement will be separately stored under cover in bales.
Sand will be stacked nearby under tarpaulin cover.
Bricks and steel will be laid in open.
During Operation Phase:
As the proposed project is a Hospital, hence, the material will
be chemicals, medicines, other biomedical materials,
radioactive material etc. which will be stored in respective labs
or storage rooms. The chemicals within threshold limit will be
stored properly as per MHISC rules.
1.15 Facilities for treatment
or disposal of solid
waste or liquid
effluents?
Yes During Construction phase:
Approx. 150 labours shall be hired during the construction
phase. Hence, the solid waste of 23 kg/day shall be generated
from labours which shall be disposed off to municipal solid
waste management site.
Construction debris like Concrete will be reused for backfilling
& waterproofing for terrace, toilets etc. Tiles will be used in
creating pathways in the landscape area, & rest will be sent to
the construction & demolition facility.
Total 6 KLD waste water shall be generated from construction
labours which will be discharged to septic tank followed by
soak pit.
During operation phase:
The biodegradable waste shall be disposed to organic waste
converter for conversion to manure. The recyclable solid waste
shall be sent to approved recycler for disposal. While, the
biomedical waste shall be sent to approved biomedical waste
service provider for disposal.
The waste water generated in the complex will be 422 KLD
(Laboratory Waste water-18 KLD and Sewage- 404 KLD).
The laboratory waste water of 18 KLD shall be treated in
Effluent Treatment Plant of capacity 25 KLD. 16 KLD treated
water shall be generated from ETP which shall be retreated in
STP. The 404 KLD of sewage generated & 16 KLD treated
water generated from ETP shall be treated in STP of 500 KLD.
399 KLD of treated water shall be generated from STP which
shall be completely reused in flushing, gardening, cooling and
misc. purposes. It will be zero discharge complex.
Details are given in Environmental Management Plan.
9
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
1.16 Facilities for long term
housing of operational
workers?
Yes During Construction phase:
Approx. 150 no. of labours will be hired during construction
phase. Separate housing in the form of hutments shall be
provided on the site for around 100 labours. Other labour will
come from nearby areas. There shall be provision of crèche
facility, kitchen, temporary toilets & bathrooms, drinking
facility, rest room and first aid facility within the hutments.
During Operation Phase:
As the proposed project is Hospital hence staff will only be
needed in the hospital which will be from the nearby areas.
Separate housing will not be provided.
1.17 New road, rail or sea
traffic during
construction or
operation?
No No new road, rail or sea traffic is proposed. Existing
transportation facilities will be used during construction or
operation phase.
1.18 New road, rail, air
waterborne or other
transport infrastructure
including new or altered
routes and stations,
ports, airports etc?
No No new road, rail, or sea traffic is proposed. Exiting facilities
shall be used
Existing transport facilities near site are given below:
Nearest Railway Station:
Shakur Basti Railway Station, 1.83 km SE
Nearest Airport:
Indira Gandhi International Airport, 15.21 km SSE
Nearest Highway:
NH-10, 1.21 km S
Nearest Metro Station:
Paschim Vihar East Metro Station, 1.55 km SW
1.19 Closure or diversion of
existing transport routes
or infrastructure leading
to changes in traffic
movements?
No No such closure or diversion of existing transport is required.
1.20 New or diverted
transmission lines or
pipelines?
No No new or diversion of transmission lines or pipelines would
be done.
10
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
1.21 Impoundment,
damming, culverting,
realignment or other
changes to the
hydrology of
watercourses or
aquifers?
No No impoundment, damming, culverting, realignment or other
changes to the hydrology of surface watercourse is required.
1.22 Stream crossings? No No stream crosses the project site.
1.23 Abstraction or transfers
of water from ground or
surface waters?
No
No abstraction of ground water is proposed.
1.24 Changes in water bodies
or the land surface
affecting drainage or
run-off?
No There will be no changes in water bodies on the land and
drainage or run-off.
1.25 Transport of personnel
or materials for
construction, operation
or decommissioning?
Yes During Construction phase:
Materials during construction phase will be transported by
truck, trolley etc. Parking of trucks will be provided in case of
emergency.
During Operation Phase:
Ambulances, Cars, two – wheeler etc. will be used during
operation phase.
1.26 Long-term dismantling
or decommissioning or
restoration works?
No Not Applicable
1.27 Ongoing activity during
decommissioning
which could have an
impact on the
environment?
No Not Applicable
11
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
1.28 Influx of people to an
area in either
temporarily or
permanently?
Yes During Construction phase
Temporary but a long-term influx of people in the form of
labours will be there till construction is done. Approx. 150 no.
of local labour shall be employed.
During operation phase
Influx of people will be as follows:
Particulars Proposed Details
No. of IPD Patients 545
No of OPD Patients 2000
Staff 1635
Visitor 2000
Total Population 6180
1.29 Introduction of alien
species?
No As on date, there is no history of alien species at the proposed
site.
1.30 Loss of native species or
genetic diversity?
No There shall not be any cutting of existing tree species. Around
70-80 trees are present on the site which shall be transplanted
within the site during construction. Hence, there will not be
any loss of native species or genetic diversity.
1.31 Any other actions? No Not Applicable
2. Use of Natural resources for construction or operation of the Project (such as land, water,
materials or energy, especially any resources which are non-renewable or in short supply):
S.No. Information/checklist
confirmation
Yes/
No
Details thereof (with approximate quantities
/rates, wherever possible) with source of
information data
2.1 Land especially undeveloped or
agricultural land (ha)
Yes 29999.34 m2 of undeveloped land shall be
developed into Hospital Building. The land has
been given on lease by DDA to Dr. Narayan Dutt
Shrimali Foundation International Charitable Trust
Society for development of Integrated Hospital
Building. Excavation & part basement construction
has been done after the grant of Environmental
Clearance vide letter no. 21-11114/2007-IA-III
dated 14.11.2008 and no construction has been
carried out after that.
2.2 Water (expected source &
competing users) unit: KLD
Yes Source & Quantity During Construction phase:
For construction purpose: Water during
construction phase will be taken from tanker water
12
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
supplier which supply treated water from STP of
nearby area.
For drinking purpose: Tanker supply
Source & Quantity During Operation Phase:
The total water requirement of the project will be
759 KLD. Out of which, fresh water requirement
will be 360 KLD. The fresh water requirement shall
be met by Delhi Jal Board.
Detailed Water Management & Water Balance are
given in Environment Management Plan.
2.3 Minerals (MT) No Not Applicable
2.4 Construction material – stone,
aggregates, sand / soil
(expected source – MT)
Yes Building materials will be sourced from indigenous
supply. The major materials required for
construction of the project will be steel, tiles, glass,
cement, agate, bricks, flooring tiles/stones, sanitary
and hardware items, electrical fittings etc.
2.5
Forests and timber (source –
MT)
Yes Wood for Doors shutters/ furniture will be used as
per the requirement.
2.6 Energy including electricity and
fuels (source, competing users)
Unit: fuel (MT), energy (MW)
Yes Source of power supply: TATA Power DDL
Power requirement: 5500 kVA
DG Sets: 2 x 1010 kVA and 2 x 1500 kVA
Fuel: Low Sulphur Diesel
2.7 Any other natural resources
(use appropriate standard units)
No Not Applicable
3. Use, storage, transport, handling or production of substances or materials, which could be
harmful to human health or the environment or raise concerns about actual or perceived
risks to human health.
S.No. Information/Checklist
confirmation
Yes/
No
Details there of (with approximate
quantities/rates, wherever possible) with source of
information data
3.1 Use of substances or
materials, which are
hazardous (as per MSIHC
rules) to human health or the
environment (flora, fauna,
and water supplies)
Yes As proposed project involves Hospital, chemicals
shall be used. The chemicals within threshold limit
will be stored properly as per MHISC rules.
13
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
3.2 Changes in occurrence of
disease or affect disease
vectors (e.g. insect or water
borne diseases)
No Since the proposed project is a hospital, there would
be generation of bio-medical wastes which could lead
to infections.
Suitable drainage and waste management measures
including bio-medical waste will be adopted during
operational phase. There will be no stagnation of
water or accumulation of water outside or within the
complex.
3.3 Affect the welfare of people
e.g. by changing living
conditions?
Yes During Construction phase:
This project shall provide employment to approx. 150
no. of local labours during construction phase which
shall lead to better quality of life & also set a standard
for future developments in the area.
During Operation Phase:
There would be generation of employment
opportunities after the development of hospital as
nurses, doctors & staff and other consultants will be
required.
Type Population
Working Staff & employee 1635
The hospital will have a positive impact as it will be
used for treatment of patients. No adverse changes in
living conditions are anticipated as land is earmarked
for development of Hospital building.
3.4 Vulnerable groups of people
who could be affected by the
project e.g. hospital patients,
children, the elderly etc.
No No, vulnerable group of people are seen near the
project site.
3.5 Any other causes Yes There will be generation of Bio-medical waste,
which will be given to State Approved Biomedical
Waste Service Provider for final disposal.
Radioactive waste will be generated from the
Oncology department which shall be disposed off in
accordance with the Atomic Energy (Safe disposal of
radioactive waste) rules.
14
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
4. Production of solid wastes during construction or operation or decommissioning
(MT/month)
S.No Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities/rates, wherever possible) with source of
information data
4.1 Spoil, overburden or mine
wastes
No Not applicable
4.2 Municipal waste (domestic
and or commercial wastes)
Yes During construction
Domestic waste –23 kg/day shall be generated from
150 no. of labours which shall be disposed off to
municipal solid waste management site.
During operation
Total Solid Waste generation will be 1091 kg/day.
Out of which 654 kg/day biodegradable waste will
be treated in Organic Waste convertor while 218
kg/day recyclable waste and 218 kg/day plastic
waste will be given to approved recycler.
Detailed Solid Waste Description is given in
Environment Management Plan.
4.3 Hazardous wastes (as per
Hazardous Waste
Management Rules)
Yes Production of hazardous wastes in form of
radioactive wastes and chemical waste shall be there.
Proper management & disposal of chemical waste
and radioactive waste will be done. 48 lt/month of
used oil shall be given to Approved vendor
Hazardous & other waste (Management & Handling)
Rules, 2016
4.4 Other industrial process
wastes
No Not applicable
4.5 Surplus product No Not applicable
4.6 Sewage sludge or other sludge
from effluent treatment
Yes About 30.5 kg/day dried sludge will be generated
from STP of capacity 500 KLD. This sludge will be
passed through filter press where it will be
dewatered/ dried & form a cake and then it shall be
used as manure in green areas and excess shall be
given to farmers/ nurseries.
4.7 Construction or demolition
wastes
No Not Applicable since it is a new project
4.8 Redundant machinery or
equipment
No Not applicable
15
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
4.9 Contaminated soils or other
materials
No Not applicable
4.10 Agricultural wastes No Not applicable
4.11 Other solid wastes Yes During operation phase, E-Waste of approx. 3-4
kg/month shall be generated from the project which
shall be given to approved recycler.
Radioactive waste will be generated from the
Oncology department which shall be disposed off in
accordance with the Atomic Energy (Safe disposal of
radioactive waste) rules of 1987 promulgated by the
Indian Central Government Atomic Energy Act
1962.
5. Release of pollutants or any hazardous, toxic or noxious substances to air (kg/hr)
S. No Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate quantities/rates,
wherever possible) with source of information data
5.1 Emissions from
combustion of fossil fuels
from stationary or mobile
sources.
Yes During Construction phase:
DG sets of capacities 1×125 kVA shall be installed
acoustically enclosed with adequate stack height.
During Operation Phase:
The only source of emission from combustion of fossil
fuels will be DG sets of 2×1010 kVA and 2×1500 kVA
Hence, to avoid the emissions, stack height of 6 m above
roof level for the DG set shall be provided. The DG set
shall meet all the norms prescribed by CPCB.
5.2 Emissions from
production processes
No Not Applicable
5.3 Emissions from materials
handling including
storage or transport Yes
Dust shall be generated during construction from the
movement of transport vehicles and other construction
activities. The effect will be restricted to construction
phase only.
Water sprinklers shall be used for dust suppression.
Material will be stored under tarpaulin cover.
5.4 Emissions from
construction activities
Yes Batching Plant shall be installed during construction
phase for which necessary approval shall be taken. Dust
& emissions shall be generated during construction
activities which shall be reduced by sprinkling of water
16
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
including plant and
equipment
in a specific time interval & timely maintenance schedule
for machinery. Also, the machines shall be kept shut
down during idle period.
5.5 Dust or odours from
handling of materials
including construction
materials, sewage and
waste
Yes During Construction phase:
During loading and unloading of construction material
dust is likely to be generated during construction phase.
Water shall be sprinkled and tarpaulin cover shall be
provided over stored raw material to reduce dust
emission.
During Operation Phase:
The sewage generated will be treated in STP of 500 KLD
and effluent generated from laboratory shall be treated in
ETP of 25 KLD & then retreated in STP. Proper
ventilation will be provided to control odour from STP
& ETP.
Biomedical waste shall be segregated and sent to State
Approved Biomedical Waste Service Provider for final
disposal.
Organic waste shall be treated in Organic Waste
Convertor & converted into manure.
5.6 Emissions from
incineration of waste.
No Not applicable
5.7 Emissions from burning
of waste in open air (e.g.
slash materials,
construction debris).
No Not applicable
5.8 Emissions from any other
sources.
No None
6. Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No. Information/Checklist
confirmation Yes/
No
Details thereof (with approximate quantities/rates,
wherever possible) with source of information data
with source of information data
6.1 From operation of equipment
e.g. engines, ventilation
plant, crushers.
Yes During Construction phase:
Due to operation of machinery and equipment during
construction of proposed project.
17
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
During construction, the equipment such as mixer
machines, bulldozers, cranes, compactors will be used
which is of highest standard and adhered to international
standards. These standards itself will take care of noise
pollution control/ vibration control and air emission
control. Hence, an insignificant impact due to
construction machinery will be envisaged.
Apart from this, the construction activities will be
restricted to daytime only.
During Operation phase:
The DG Sets of capacity 2×1010 kVA and 2×1500 kVA
shall be installed in acoustically treated room on Surface.
Vibration pads in DG sets shall be provided to minimize
the vibration effect.
6.2 From industrial or similar
processes
No Not applicable
6.3 From construction or
demolition
Yes Due to the various activities, there will be short-term
noise impacts in the immediate vicinity of the project site.
This shall be restricted to day time only.
It has been estimated that during the construction period
the average noise level will be 70-75 dB (A) during peak
construction hours.
Barricading of site shall be done in order to reduce noise
impacts outside the project boundary.
6.4 From blasting or piling No Not Applicable
6.5 From construction or
operational traffic
Yes Some amount of noise will be generated from vehicular
movement in construction and operational phase around
the boundary wall shall be done to reduce noise from
traffic.
6.6 From lighting or cooling
systems
No Not Applicable
6.7 From any other sources No None
18
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
7. Risks of contamination of land or water from releases of pollutants into the ground or
into sewers, surface waters, groundwater, coastal waters or the sea:
S.No. Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate quantities/rates,
wherever possible) with source of information data
7.1 From handling, storage,
use or spillage of
hazardous materials
Yes
As the proposed project is a Hospital, chemicals will be
used which may be hazardous in nature. The chemicals
within threshold limit will be stored properly as per
MHISC rules.
Used oil from DG sets will be stored in HDPE drums and
kept in covered rooms under lock & key. Special care shall
be taken to prevent leakages and spills.
7.2 From discharge of sewage
or other effluents to water
or the land (expected
mode and place of
discharge)
Yes The waste water generated in the complex will be 422
KLD (Laboratory Waste water-18 KLD and Sewage- 404
KLD). The laboratory waste water of 18 KLD shall be
treated in Effluent Treatment Plant of capacity 25 KLD.
16 KLD treated water shall be generated from ETP which
shall be retreated in STP. The 404 KLD of sewage
generated & 16 KLD treated water generated from ETP
shall be treated in STP of 500 KLD. 399 KLD of treated
water shall be generated from STP which shall be
completely reused in flushing, gardening, cooling and
misc. purposes. It will be zero discharge complex.
7.3 By deposition of
pollutants emitted to air
into the land or into water
Yes The only source of air emission will be DG sets &
vehicular emissions. The DG sets adhering to CPCB
standards will be installed with adequate stack height. The
emission from DG sets will be dispersed in the air & will
not create any contamination to land or water.
7.4 From any other sources Yes Risk of occurrence of disease from biomedical waste can
be observed.
204 kg/day of biomedical waste shall be generated from
the Hospital complex. The Biomedical wastes shall be
disposed as per Bio medical waste (management &
handling) rules, 2016.
Radioactive waste will be generated from the Oncology
department which shall be disposed off in accordance with
the Atomic Energy (Safe disposal of radioactive waste)
rules of 1987 promulgated by the Indian Central
Government Atomic Energy Act 1962.
7.5 Is there a risk of long-term
build-up of pollutants in
the environment from
these sources?
No None
19
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
8. Risk of accidents during construction or operation of the Project, which could affect
human health or the environment.
S.No Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate quantities/rates,
wherever possible) with source of information data
8.1 From explosions, spillages,
fires etc. from storage,
handling, use or production
of hazardous substances
Yes The possible sources of accidents from explosions,
spillages, fires etc. from storage, handling would be diesel,
chemicals from laboratory, pharmaceutical wastes etc.
Proper care shall be taken and fire-fighting system shall be
installed within the complex to avoid any accident.
8.2 From any other causes Yes During Construction Phase
The possible sources of accidents would be mis
happenings due to other sources from the complex can be
electrical shocks, mechanical damages etc. PPE shall be
provided to the labours.
During Operation Phase:
The possible sources of accidents from the other sources
in the complex would be radiation leaks, mechanical
accidents, chemical/biomedical hazards etc. Proper care
shall be taken to avoid it.
8.3 Could the project be
affected by natural disasters
causing environmental
damage (e.g. floods,
earthquakes, landslides,
cloudburst etc)?
Yes The area under study falls in Zone-IV, according to the
Indian Standard Seismic Zoning Map. Suitable seismic
coefficients in horizontal and vertical directions
respectively has been adopted while designing the
structure.
For reasons of earthquake: Earthquake measures has been
incorporated in the building design. However, the area is
not prone to flood and landslide etc.
9. Factors which should be considered (such as consequential development) which could lead to
environmental effects or the potential for cumulative impacts with other existing or planned
activities in the locality.
S. No. Information/Checklist
confirmation
Yes/No Details there of (with approximate
quantities/rates, wherever possible) with source
of information data
9.1 Lead to development of
supporting facilities, ancillary
development or development
20
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
stimulated by the project
which could have impact on
the environment e.g.:
• Supporting infrastructure
(roads, power supply, waste
or waste water treatment,
etc.)
• Housing development
• Extractive industries
• Supply industries
• Other
No
No
No
No
No
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
9.2 Lead to after-use of the site,
which could have an impact
on the environment
No Proper care shall be taken to avoid any adverse
impact on the environment
9.3 Set a precedent for later
developments
Yes It will attract people to develop organized and
environment friendly Hospital.
9.4 Have cumulative effects due
to proximity to other existing
or planned projects with
similar effects
No No impact
III. Environmental Sensitivity
S. No Areas Name/
Identity
Aerial distance
(within 15 km.) from
Proposed project
location boundary
1 Areas protected under
international conventions,
national or local legislation
for their ecological,
landscape, cultural or other
related value
Ancient Mosque (Babur’s Period)
together with adjacent area comprised
in part of Survey plot No. 177
Delhi fort or Lal Qila, NaubatKhana,
Diwan-i-am, Mumtaz Mahal' Rang
Mahal, Baithak,MaseuBurj, diwan-i-
Khas' Moti Masjid, sawanBhadon
,Shah Burj, Hammam with all
surrounding including the gardens,
paths, terraces and water courses.
Salimgarh Fort, comprising the main
gate on North, Ancient structure near
the main gate and the entire
fortification wall
11.10 km SSW
13.20 km SEE
13.31 km SEE
21
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Fortification Wall AsadBurj, Water
gate, Delhi Gate, Lahori Gate,
Jahangiri Gate, Chhattra Bazar, Baoli
13.70 km SEE
2 Areas which are important or
sensitive for ecological
reasons - Wetlands,
watercourses or other water
bodies, coastal zone,
biospheres, mountains,
forests
Water Bodies
Lake near Madipur
Najafgarh Drain
Japanese Park Lake
Swarna Jayanti Lake
Delhi Tail Distributary (Western
Yamuna Canal)
Nangloi Distributary
Distributary near Nithari
Pond near Ambedkar Nagar
Supplimetary Drain
Bhalswa Lake
Pond near Model Town
Mundka Minor
Nalni Lake
Santokh Sarover
Madanpur Distributary
Sultanpur Minor
Drain near Kamalpur
Drain near Chandpur Kalan
Yamuna River
Reserve Forest
Central Ridge Reserve Forest
Northern Ridge Reserve Forest
2.14 km SSE
2.95 km S
3.07 km NNE
4.05 km NNE
4.18 km NE
4.28 km NNW
5.22 km NWW
5.43 km NE
6.69 km NNE
7.61 km NE
7.85 km NE
8.14 km NW
8.16 km NEE
9.31 km NE
9.55 km NWW
9.78 km NWW
10.17 km NE
10.57 km NW
11.32 km NE
8.48 km SE
9.48 km SEE
3 Areas used by protected,
important or sensitive
species of flora or fauna for
breeding, nesting, foraging,
resting, over wintering,
migration
None within 15 km Radius None within 15 km
Radius
4 Inland, coastal, marine or
underground waters
None None
5 State, National boundaries
U.P State Boundary 14.01 km NE
6 Routes or facilities used by
the public for access to
recreation or other tourist,
pilgrim areas
Roads
NH-10
NH-1
NH-8
Railway Station
Shakur Basti Railway Station
Nangloi Railway Station
Adarsh Nagar Railway Station
Daya Basti Railway Station
1.21 km S
6.52 km NEE
11.67 km SSE
1.83 km SE
5.27 km SWW
5.85 km NEE
6.19 km SE
22
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Badli Railway Station
Sarai Rohilla Railway Station
Mundka Railway Station
Khera Kalan Railway Station
Subzi Mandi Railway Station
Kisanganj Railway Station
Sadar Bazar Railway Station
Ghevra Railway Station
New Delhi Railway Station
Airport
Indira Gandhi International Airport
Metro Station
Paschim Vihar West Metro Station
Paschim Vihar West Metro Station
Madipur Metro Station
Rohini East Metro Station
Peeragarhi Metro Station
Pitampura Metro Station
Kohat Enclave Metro Station
Netaji Subhash Place Metro Station
6.65 km NNE
7.73 km SE
8.01 km W
8.69 km N
8.83 km SE
8.96 km SE
10.70 km SE
11.11 km W
11.54 km SE
15.21 km SSE
1.30 km S
1.55 km SW
1.58 SSE
2.14 km SW
2.17 km SSE
2.47 km NE
2.90 km ENE
3.94 km E
7 Defence installations
None within 15 km Radius None within 15 km
Radius
8 Densely populated or built-
up area
Mangolpuri S Block 1.93 km NWW
23
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
9 Areas occupied by sensitive
man-made land uses
(hospitals, schools, places of
worship, community
facilities)
Hospital
Bhagwan Mahavir Hospital, H-45,
Pitampura
Navjeevan Hospital, A-12
Pushpanjali Enclave, Pitampura
Saransh Hospital,2949, Sant
Nagar,Pitampura
Post Office
Post Office Saraswti Vihar, C-Block,
Main Market, Pitampura
Post Office Rani Bagh, 927 Rishi
Nagar, Pitampura
Post Office, 2876 Sant NagarRani
Bagh Pitampura
Place of Worship
Sankat Mochan Shiv Shakti Mandir,
Guru Sandeepan Marg,Saraswati
Vihar, Pitampura
Shiv Mandir, Multani Mohalla,
Pitampura
Shri Sheetla Devi Mndir, Block-L,
Raj Nagar, Pitampura
School
Maxfort School, Zone H-4&5,
CHBS Moulana Azad Society,
Pitampura
Bal Bharti Public School, Parwana
Rd, Pitampura
Apeejay School, Plot No.-10, Road
No.-42, Sanik Viha, Pitampura
Bank
HDFC Bank, Community Centre,
NN Tower, 23A, Rani Bagh,
Pitampura
Nainital Bank, Shatabdi House,
Commercial Complex, Rohit Kunj,
Pitampura
Induslnd Bank, CHBS Ltd. Society,
Kohat Enclave, Pitampura
0.51 km SEE
0.59 km NNW
1.94 km E
1.58 km NE
1.63 km SEE
1.89 km E
1.78 km NE
1.99 km SEE
2.90 km E
0.21 km NW
0.39 km NW
0.81 km E
2.16 km SEE
2.70 km NEE
2.71 km NEE
24
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
10. Areas containing important,
high quality or scarce
resources
(Ground water resources,
surface resources, forestry,
agriculture, fisheries,
tourism, minerals)
Ancient Mosque (Babur’s Period)
together with adjacent area comprised
in part of Survey plot No. 177
Delhi fort or Lal Qila, NaubatKhana,
Diwan-i-am, Mumtaz Mahal' Rang
Mahal, Baithak,MaseuBurj, diwan-i-
Khas' Moti Masjid, sawanBhadon
,Shah Burj, Hammam with all
surrounding including the gardens,
paths, terraces and water courses.
Salimgarh Fort, comprising the main
gate on North, Ancient structure near
the main gate and the entire
fortification wall
Fortification Wall Asad Burj, Water
gate, Delhi Gate, Lahori Gate,
Jahangiri Gate, Chhattra Bazar, Baoli
11.10 km SSW
13.20 km SEE
13.31 km SEE
13.70 km SEE
11 Areas already subjected to
pollution or environmental
damage. (Those where
existing legal environmental
standards are exceeded)
Wazirpur Critically Polluted Area
Anand Parvat Critically Polluted
Area
5.15 km NEE
6.54 km SE
12 Areas susceptible to natural
hazard which could cause
the project to present
environmental problems
(Earthquakes, subsidence,
landslides, erosion, flooding
or extreme or adverse
climatic conditions)
Area falls in Seismic
Zone IV
25
26
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
APPENDIX II
(See paragraph 8.9)
FORM-1 A (only for construction projects listed under item 8 of the Schedule)
CHECK LIST OF ENVIRONMENTAL IMPACTS
(Project proponents are required to provide full information and wherever necessary attach
explanatory notes with the Form and submit along with proposed environmental
management plan & monitoring programme)
1. LAND ENVIRONMENT
(Attach panoramic view of the project site and the vicinity)
1.1 Will the existing land use get
significantly altered from the project
that is not consistent with the
surroundings? (Proposed land use must
conform to the approved Master Plan /
Development Plan of the area. Change
of land use if any and the statutory
approval from the competent authority
be submitted).
Attach Maps of
(i) Site location
(ii) Surrounding features of the
proposed site (within 500 meters)
(iii) The site (indicating levels &
contours) to appropriate scales. If not
available attach only conceptual plans.
The proposed project will be located at Site no. 2, Zone-
H 4/5, Facility Centre, Pitampura, New Delhi.
Since, the site has already been earmarked for Hospital
Complex. Hence, there will be no change in land use of
the proposed site.
However, land cover shall change to Hospital Building.
Yes, the proposed development conforms to the Master
Plan of Delhi, 2021.
The site location is given in Environment Management
Plan.
Location Map is given Environment Management Plan.
Layout Plan is enclosed in Environment Management
Plan.
1.2 List out all the major project
requirements in terms of the
Land area,
Built up area
Water consumption
Power requirement
Community Facility
Connectivity
Plot Area: - 29999.34 m2
Built-Up Area: - 94956.31m2
759 KLD
5500 kVA
None
Nearest Highway: - NH-10, 1.21 km S
Nearest Railway Station: - Shakur Basti Railway
Station, 1.83 km SE
Nearest Airport :- Indira Gandhi International Airport,
14.72 km SSW
27
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Parking needs etc.
Nearest Metro Station- Rohini East metro Station, 2.45
km NE
Parking Required: - 1046 ECS
Parking Provided: - 1116 ECS
1.3 What are the likely impacts of the
proposed activity on the existing
facilities adjacent to the proposed site?
(Such as open spaces, community
facilities, details of the existing land
use, and disturbance to the local
ecology).
During construction of hospital building proper care will
be taken to minimize the dust effects during construction
phase as well as Operation Phase of the project, will
generate direct and indirect employment opportunities
for a large section of society. The employment will have
positive impact thereby increasing the quality of life.
1.4 Will there be any significant land
disturbance resulting in erosion,
subsidence & instability?
(Details of soil type, slope analysis,
vulnerability to subsidence, seismicity
etc may be given).
Soil Type: Silt loam
Slope Analysis: The project area possesses fairly plain
terrain.
Erosion / Subsidence: Proper greening & paving of area
will not cause any soil erosion problem and subsidence.
Seismicity: Seismic Zone-IV, for which appropriate
safety measures shall be taken.
1.5 Will the proposal involve alteration of
natural drainage systems?
(Give details on a contour map showing
the natural drainage near the proposed
project site)
Yes, there will be any alterations of natural drainage
system due to construction of the proposed Hospital.
Artificial contour shall be maintained and proper
drainage system shall be provided.
1.6 What are the quantities of earthwork
involved in the construction activity
cutting, filling, reclamation etc.
(Give details of the quantities of
earthwork involved, transport of fill
materials from outside the site etc.)
During construction phase-
Excavation & part basement construction has already
been done as per the grant of Environmental Clearance
granted. During part basement (2 level) construction, soil
was excavated which was used for backfilling purposes
in nearby areas & out of it, top soil generated was used
for landscaping purpose in nearby areas.
There shall be done further excavation for foundation and
basement. The further excavated soil will be used for
backfilling purposes within the site and out of it, top soil
shall be preserved separately and will be used for
landscaping purpose only.
In total Approx. 112332 m3 of soil excavation is involved
for providing foundation and 2 levels of basement
completely.
C& D waste shall be disposed as per C&D Rules. Hence,
no immediate adverse impacts on the land environment
are envisaged.
28
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
1.7 Give details regarding water supply,
waste handling etc during the
construction period.
Water Supply:
During construction stage, water will be sourced through
STP treated water for construction activities & tanker
suppliers for drinking purpose.
Waste Generation / Handling:
The solid waste of 23 kg/day shall be generated from
labours which shall be disposed off to municipal solid
waste management site.
For construction labour, proper sanitary facilities & wash
areas shall be constructed and good hygienic conditions
shall be maintained.
1.8 Will the low-lying areas & wetlands get
altered?
(Provide details of how low lying and
wetlands are getting modified from the
proposed activity)
No low lying and wetland area exist in and around the
project site.
1.9 Whether construction debris & waste
during construction cause health
hazard? (Give quantities of various
types of wastes generated during
construction including the construction
labour and the means of disposal)
Construction debris like Concrete will be reused in
backfilling & for levelling of land/ back filling. Tiles will
be used in creating pathways in the landscape area etc.
Recyclable waste like aluminium, steel, wood pieces,
cement bags, plastic containers, cartons, glass etc. will be
sold to authorized recyclers.
The solid waste of 23 kg/day shall be generated from
labours which shall be disposed off to municipal solid
waste management site. Temporary toilets & drinking
water facility for construction labour will be provided.
The waste water generated during construction phase will
be 6 KLD sewage which will be discharged into septic
tank followed by soak pit.
2. WATER ENVIRONMENT
2.1 Give the total quantity of water
requirement for the proposed project
with the breakup of requirements for
various uses.
How will the water requirement have
met?
State the sources & quantities and
furnish a water balance statement.
The total quantity of water requirement will be 759
KLD. Out of which, fresh water requirement will be 360
KLD. The break-up details are given in Environment
Management Plan.
Fresh Water requirement will be met by Delhi Jal Board
(DJB)
Water Balance Diagram is given in Environment
Management Plan.
29
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
2.2 What is the capacity (dependable
flow or yield) of the proposed source
of water?
Delhi Jal Board (DJB) which is the dependable source
of water is the proposed source of supply.
2.3 What is the quality of water required,
in case, the supply is not from a
municipal source? (Provide physical,
chemical, biological characteristics
with class of water quality)
The quality of water complying with IS 10500 is
required. In case, if municipal water is not available,
quality of water complying with IS 10500 will be
arranged.
2.4 How much of the water requirement
can be met from the recycling of
treated wastewater?
(Give the details of quantities,
sources and usage)
399 KLD of treated water shall be generated from STP
which shall be completely reused in flushing, gardening,
cooling and misc. purposes. It will be zero discharge
complex.
Hence 52.56 % of total water requirement will be met
from recycled water.
2.5 Will there be diversion of water from
other users?
(Please assess the impacts of the
project on other existing uses and
quantities of consumption)
There will not be any substantial effect on water demand
of this region as the development will be done as per the
development plan.
2.6 What is the incremental pollution
load from wastewater generated from
the proposed activity?
(Give details of the quantities and
composition of wastewater generated
from the proposed activity)
There is no incremental pollution load from the complex
as no waste water shall be discharged outside the
complex. It will be zero discharge complex.
2.7 Give details of the water requirements
met from water harvesting? Furnish
details of the facilities created.
No water requirement shall be met from rain water
harvesting however, 7 no. of rain water harvesting pits
shall be installed in the complex for recharging of
ground water only.
2.8 What would be the impact of the land
use changes occurring due to the
proposed project on the runoff
characteristics (quantitative as well as
qualitative) of the area in the post
construction phase on a long-term
basis?
There will be no impact of the proposed construction on
the run-off characteristics as runoff from the
construction site shall not be allowed into the roadside.
It will be collected in a tank & after pre-treatment it will
be reused for sprinkling, etc.
30
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Would it aggravate the problems of
flooding or water logging in any way?
No, it will not aggravate the problem of flooding or
water logging in any way, rather will reduce the same.
2.9 What are the impacts of the proposal
on the ground water?
(Will there be tapping of ground
water; give the details of ground
water table, recharging capacity, and
approvals obtained from competent
authority, if any).
Ground water extraction is not proposed in the complex.
However, 7 no. of rain water harvesting pits will be
provided for ground water recharge. Ground water
extraction, if required will be done with prior
permission from CGWA.
Thus, there will be no adverse impact on the ground
water.
2.10 What precautions/measures are taken
to prevent the run-off from
construction activities polluting land
& aquifers?
(Give details of quantities and the
measures taken to avoid the adverse
impacts)
During the construction phase of the proposed site,
runoff from the construction site shall not be allowed
into the roadside. It will be collected in a tank & after
pre-treatment it will be reused for sprinkling, etc.
2.11 How is the storm water from within
the site managed?
(State the provisions made to avoid
flooding of the area, details of the
drainage facilities provided along
with a site layout indication contour
levels).
During construction phase
Adequate measures shall be taken to channelize storm
water and the same shall be collected in a tank & after
pre-treatment it will be reused for sprinkling etc.
During operation phase
Storm water, will be channelized to 7 no. of rainwater
harvesting pits to be installed within the complex.
2.12 Will the deployment of construction
labourers particularly in the peak
period lead to unsanitary conditions
around the project site (Justify with
proper explanation)
Approx. 6 KLD of waste water will be discharged from
labours employed during construction phase.
Temporary toilets will be provided for labourers during
construction period. The waste water shall be disposed
off to septic tank followed by soak pit.
2.13 What on-site facilities are provided
for the collection, treatment & safe
disposal of sewage?
(Give details of the quantities of
wastewater generation, treatment
capacities with technology &
facilities for recycling and disposal)
During Construction Phase-
Approx. 6 KLD Waste water will be discharged during
construction phase from labours. The waste water shall
be disposed off to septic tank followed by soak pit.
During Operation Phase-
The waste water generated in the complex will be 422
KLD (Laboratory Waste water-18 KLD and Sewage-
404 KLD). The laboratory waste water of 18 KLD shall
be treated in Effluent Treatment Plant of capacity 25
31
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
KLD. 16 KLD treated water shall be generated from
ETP which shall be retreated in STP. The 404 KLD of
sewage generated & 16 KLD treated water generated
from ETP shall be treated in STP of 500 KLD.
Details of STP & ETP are given in Environment
Management Plan.
2.14 Give details of dual plumbing system
if treated waste used is used for
flushing of toilets or any other use.
Dual Plumbing line for using treated water will be
provided in the Hospital.
3. VEGETATION
3.1 Is there any threat of the project to the
biodiversity?
(Give a description of the local
ecosystem with its unique features, if
any)
Core Zone:
There exist, around 70-80 trees at the site which shall
be transplanted within the site during construction
after getting prior permission.
Buffer Zone:
Ashok Kikar Neem
Eucalyptus Peepal Gulmohar
Amaltas Kachnar Kadam
3.2 Will the construction involve extensive
clearing or modification of vegetation?
(Provide a detailed account of the trees
& vegetation affected by the project)
There exist, around 70-80 trees at the site which shall
be transplanted within the site during construction
after getting prior permission.
3.3 What are the measures proposed to be
taken to minimize the likely impacts on
important site features?
(Give details of proposal for tree
plantation, landscaping, creation of
water bodies etc along with a layout plan
to an appropriate scale)
The Shelter belt for the proposed project has been
planned to provide a clean, healthy and beautiful
green environment for the people to live in within the
proposed project site.
To minimize the impact, the provision of total
plantation area 5999.87 m2 (i.e. 20.00 % of total plot
area), with lawns, ornamental plants and trees shall be
provided.
4. FAUNA
4.1 Is there likely to be any displacement of
fauna- both terrestrial and aquatic or
creation of barriers for their movement?
Provide the details.
Core Zone: This place is not a common habitat for
local fauna. However, fauna such as squirrel, Indian
Chameleon etc were commonly found.
There will not be any type of displacement or any
other effect on the local fauna due to proposed project
activities.
32
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Buffer Zone:
There will not be any type of displacement or any
other effect on the local fauna due to proposed project
activities. No threat to the biodiversity as there is no
national park/wildlife sanctuary within 10 km radius
of the site.
4.2 Any direct or indirect impacts on the
avifauna of the area? Provide details.
At present, there exist, around 70-80 trees at the site
which shall be transplanted within the site during
construction after getting prior permission. However,
proper landscaping has been planned to provide a
clean, healthy and beautiful green environment for
the population.
Common native variety of trees and ornamental
flowering species will be planted in the green space
which will attract avifauna & hence will have direct
positive impact on the local avifauna & this will
provide shelter to local birds.
4.3 Prescribe measures such as corridors,
fish ladders etc to mitigate adverse
impacts on fauna
Not Applicable
5. AIR ENVIRONMENT
5.1 Will the project increase atmospheric
concentration of gases & result in heat
islands?
(Give details of background air quality
levels with predicted values based on
dispersion models taking into account the
increased traffic generation as a result of
the proposed constructions)
The present air quality of the area has been measured.
Test reports are Enclosure along with EMP.
The traffic will increase due to the proposed Hospital.
Increased traffic generation of vehicles due to Hospital
will not cause increase in atmospheric concentration
of gases and will not result in the heat island
formation.
Tree plantation in the complex shall minimize the
impact of air pollution.
D.G. sets will be provided with adequate stack for
better dispersion of the flue gases.
5.2 What are the impacts on generation of
dust, smoke, odorous fumes or other
hazardous gases? Give details in relation
to all the meteorological parameters.
During construction phase sprinkling will be done so
no dust and odour will be generated at site. The only
source of dust generation at the site during the
operation phase will be traffic movement. However,
regular cleaning of dust from roads shall be taken care
of.
33
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Smoke will be generated from the operation of DG
sets. Proper emission standards will be maintained as
per CPCB guidelines.
5.3 Will the proposal create shortage of
parking space for vehicles? Furnish
details of the present level of transport
infrastructure and measures proposed for
improvement including the traffic
management at the entry & exit to the
project site.
The optimum parking provision is proposed at
Basement-1, Basement-2 and Surface Parking. Hence
there will be no shortage of parking space for vehicles.
The total parking requirement of the project will be
1046 ECS. Total parking provision of complex will be
1116 ECS.
5.4 Provide details of the movement patterns
with internal roads, bicycle tracks,
pedestrian pathways, footpaths etc., with
areas under each category.
In the proposed Hospital project, separate entry drive
way will be provided for private vehicles and
Emergency Ambulances.
5.5 Will there be significant increase in
traffic noise & vibrations? Give details of
the sources and the measures proposed
for mitigation of the above.
To reduce/ avoid traffic following steps will be taken:
1. One-way traffic movement
2. No honking zones
3. No vehicle movement in specified areas.
Shelter belt within the complex will further mitigate
the traffic noise.
The foundation will be made very hard and paved with
rubber flooring to minimize the vibration, also all
other measures to reduce vibration will be adopted
during designing of new buildings.
5.6 What will be the impact of DG sets &
other equipment on noise levels &
vibration in & ambient air quality around
the project site? Provide details.
There would be slight impact of D.G. Sets on noise
levels, vibration and in ambient air quality around the
project site.
1. All the D.G. Sets shall be kept in acoustically treated
room on Surafce.
2. Stack height as per C.P.C.B. norms to reduce the
impacts on air quality around the project site shall be
provided.
3. The noise from D.G. Sets will meet the desired
standard as per C.P.C.B guidelines. Low Sulphur fuel
is being used to run these D.G. Sets and the same shall
be followed after expansion also.
4. Vibration pads in DG sets to minimize the vibration
effect.
34
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
6. AESTHETICS
6.1 Will the proposed constructions in any way
result in the obstruction of a view, scenic
amenity or landscapes?
Are these considerations taken into
account by the proponents?
No, the proposed project in any way will not cause any
obstruction.
Yes, all the considerations have been taken into
account.
6.2 Will there be any adverse impacts from
new constructions on the existing
structures? What are the considerations
taken into account?
The construction of proposed building will be done as
per approved building plan. Hence no adverse impact
is anticipated.
6.3 Whether there are any local considerations
of urban form & urban design influencing
the design criteria? They may be explicitly
spelt out.
Are there any anthropological or
archaeological sites or artefacts nearby?
State if any other significant features in the
vicinity of the proposed site have been
considered.
None
Yes, there are archaeological sites situated at a distance
from project site. The list of ASI sites has been
attached as Enclosure-8.
None.
7. SOCIO-ECONOMIC ASPECTS
7.1 Will the proposal result in any
changes to the demographic structure
of local population? Provide the
details.
As it is a hospital, during the operation of the project,
patients will come for treatment and go back hence there
will be no change to the demographic structure of local
population.
7.2 Give details of the existing social
infrastructure around the proposed
project.
Social infrastructures exist near the site:
Hospital
Bhagwan Mahavir Hospital, H-
45,
Pitampura
Navjeevan Hospital, A-12
Pushpanjali Enclave, Pitampura
Saransh Hospital,2949, Sant
Nagar,Pitampura
Post Office
Post Office Saraswti Vihar, C-
Block, Main Market, Pitampura
Post Office Rani Bagh, 927
Rishi Nagar, Pitampura
0.51 km SEE
0.59 km NNW
1.94 km E
1.58 km NE
1.63 km SEE
35
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Post Office, 2876 Sant
NagarRani Bagh Pitampura
Place of Worship
Sankat Mochan Shiv Shakti
Mandir, Guru Sandeepan
Marg,Saraswati Vihar,
Pitampura
Shiv Mandir, Multani Mohalla,
Pitampura
Shri Sheetla Devi Mndir, Block-
L, Raj Nagar, Pitampura
School
Maxfort School, Zone H-4&5,
CHBS Moulana Azad Society,
Pitampura
Bal Bharti Public School,
Parwana Rd, Pitampura
Apeejay School, Plot No.-10,
Road No.-42, Sanik Vihar,
Pitampura
Bank
HDFC Bank, Community
Centre, NN Tower, 23A, Rani
Bagh, Pitampura
Nainital Bank, Shatabdi House,
Commercial Complex, Rohit
Kunj, Pitampura
Induslnd Bank, CHBS Ltd.
Society, Kohat Enclave,
Pitampura
1.89 km E
1.78 km NE
1.99 km SEE
2.90 km E
0.21 km NW
0.39 km NW
0.81 km E
2.16 km SEE
2.70 km NEE
2.71 km NEE
7.3 Will the project cause adverse effects
on local communities, disturbance to
sacred sites or other cultural values?
What are the safeguards proposed?
There are the following sacred sites present in the vicinity
of the proposed project site: -
Place of Worship
Sankat Mochan Shiv Shakti Mandir, Guru Sandeepan
Marg,Saraswati Vihar, Pitampura- 1.78 km NE
Shiv Mandir, Multani Mohalla, Pitampura-1.99 km SEE
Shri Sheetla Devi Mndir, Block-L, Raj Nagar, Pitampura-
2.90 km E
Measures shall be considered so that no negative impact is
envisaged due to construction of the project.
36
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
8. BUILDING MATERIALS
8.1 May involve the use of building materials
with high-embodied energy.
Is the construction materials produced
with energy efficient processes?
(Give details of energy conservation
measures in the selection of building
materials and their energy efficiency
The major materials required for construction of the
project are steel, cement, bricks, flooring tiles / stones,
sanitary and hardware items, electrical fittings, water,
etc.
Energy efficient Building material will be used.
Details of Energy Conservation measures given in
Environment Management Plan.
8.2 Transport and handling of materials
during construction may result in
pollution, noise & public nuisance.
What measures are taken to minimize the
impacts?
Yes, transportation and handling of material results in
air pollution and noise however will be minimized by
covering material by the tarpaulin and ensuring PUC
certificate of vehicles and good condition silencers.
8.3 Are recycled materials used in roads and
structures?
State the extent of savings achieved?
The debris of construction material will be also used in
backfilling, roads etc. The rest of the waste shall be sent
to C & D facility. Recyclable waste like aluminium,
steel, wood pieces, cement bags, plastic containers,
cartons, glass etc. will be sold to authorized recyclers.
8.4 Give details of the methods of collection,
segregation & disposal of the garbage
generated during the operation phases of
the project.
This solid waste will be disposed off as per municipal
solid waste management and handling norms. Details
of collection, segregation and disposal of the
biomedical waste is given in the Environment
Management Plan.
9. ENERGY CONSERVATION
9.1 Give details of the power
requirements, source of supply,
backup source etc.
What is the energy consumption
assumed per square foot of built-
up area?
How have you tried to minimize
energy consumption?
Power Requirement: 5500 kVA
Source of Power: TATA Power DDL
Back-up Source:
DG Sets: 2 x 1010 kVA and 2 x 1500 kVA
Fuel: Low sulphur Diesel
DG Sets shall be placed in acoustically treated room on
Surface.
Appropriate energy conservation measures & management
plan have been adopted in order to minimize the
consumptions of non-renewable fuel. Details are given in
Environment Report.
9.2 What type of and capacity of
power back-up do you plan to
provide?
DG Sets: 2 x 1010 kVA and 2 x 1500 kVA
Fuel: Low sulphur Diesel
37
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
All have been installed to provide power backup during
power failures.
9.3 What are the characteristics of the
glass you plan to use?
Provide specifications of its
characteristics related to both
short wave and long wave
radiatio
S.
No
BUILDING
MATERIAL
PROPOSED
WITH U & R
VALUES
‘R’ Values
(in Sq m.
Deg K/
Watts)
‘U’
Values
(in Watts/
Sq m.
Deg K)
1. Glass
(High-
performance
double-glazed
glass unit)
0.71 1.4
9.4 What passive solar architectural
features will be used in the
building?
Illustrate the applications made in
the proposed project.
Building design and envelope shall be optimized through
selection of appropriate wall and roof construction and
through adoption of solar measures.
Yes, the layout of building shall be designed to maximize the
potential for use of solar lighting per day devices.
9.5 Does the layout of streets &
buildings maximize the potential
for solar energy devices?
Have you considered the use of
street lighting, emergency
lighting and solar hot water
systems for use in the building?
Substantiate with details.
Yes, the layout of building shall be designed to maximize the
potential for use of solar lighting.
Yes, solar power-based street, common area light and solar
water heaters shall be used.
9.6 Is shading effectively used to
reduce cooling/heating loads?
What principles have been used
to maximize the shading of Walls
on the East and the West and the
Roof? How much energy saving
has been affected?
Architectural measures shall be adopted to provide shading
devices for windows and roof which would effectively
reduce heating up of building envelope. Louvers and
sunshades will be used around windows in order to protect
from direct sunlight.
9.7 Do the structures use energy-
efficient space conditioning,
lighting and mechanical systems?
Provide technical details.
Provide details of the
transformers and motor
efficiencies, lighting intensity and
Suitable energy optimization will be adopted during the
calculation of energy load of the proposed project. The space
heating load will be minimized by using solar structure and
suitable buildings envelop material.
The details of the transformers and motor efficiencies,
lighting intensity and air-conditioning load assumptions will
be given in the Environment Management Plan.
38
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
air-conditioning load
assumptions?
Are you using CFC and HCFC
free chillers? Provide
specifications
Uses of incandescent lamp and halogen lamps will be
avoided and energy efficient LED will be used for all
common area.
CFC & HCFC free chillers will be used.
9.8 What are the likely effects of the
building activity in altering the
micro-climates?
Provide a self-assessment on the
likely impacts of the proposed
construction on creation of heat
island & inversion effects?
No significant effect is envisaged on the surrounding
environment of project. Increased traffic generation and use
of D.G. Sets in the project will not cause significant increase
in atmospheric concentration of gases and will not result in
heat island formation.
9.9 What are the thermal
characteristics of the building
envelope? (a) roof; (b) external
walls; and (c) fenestration?
Give details of the material used
and the U-values or the R values
of the individual components.
Brickwork, plaster, stone work, double insulated glass for
external façade
S. No BUILDING
MATERIAL
PROPOSED
WITH U & R
VALUES
‘R’ Values
(in Sq m.
Deg K/
Watts)
‘U’ Values
(in Sq m. Deg
K/ Watts)
1. Exterior Wall
Brick & AAC Blocks
wall (230 mm thick),
both side thick sand
cement plaster (20
mm) with insulation.
1.33 0.749
2. Exterior Roof
150 mm RCC slab
with 50 mm Cement
sand screed, 80 mm
Brick Batt Coba and
50 mm thick Puff)
2.84 0.352
3. Glass
(High-performance
double-glazed glass
unit)
0.71
1.4
9.10 What precautions & safety
measures are proposed against
fire hazards? Furnish details of
emergency plans.
Fire storage tank with fire pumps like Hydrant pump, Jockey
Pump, Pressure vessel & Diesel Engine Driven Pump have
already been installed in the plant room.
Fire Hydrant System:
The hydrant ring main from fire pumps header are running
all around the buildings with yard hydrants at suitable
intervals. Wet risers are tapped from ring main and run along
39
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
the shaft. Fire hose cabinet is provided on all floors with
accessories.
Sprinkler System:
It is provided on all floor areas except electrical rooms,
server rooms.
Overhead water storage tank at roof is connected to sprinkler
system.
Fire Extinguishers:
Portable type class A, B & C fire extinguishers will be
provided at all fire sensitive places.
9.11 If you are using glass as wall
material provides details and
specifications including emissive
and thermal characteristics.
All fenestration with U-factors, SHGC, or visible light
transmittance determined, certified, and labelled in
accordance ISO-15099 shall be adopted.
9.12 What is the rate of air infiltration
into the building?
Provide details of how you are
mitigating the effects of
infiltration.
The air inflow and outflow shall be maintained as per norms.
All the window and door will be airtight quality; hence we
don’t foresee any air infiltration. Proper inflow and outflow
of air shall be maintained and proper dilution shall be
provided by using air exhaust to maintain air quality.
9.13 To what extent the non-
conventional energy technologies
are utilized in the overall energy
consumption?
Provide details of the renewable
energy technologies used.
Solar energy will be used. It is proposed to install solar
panels on the roof.
The details of the renewable technologies used will be given
in the Environment Management Plan.
10. ENVIRONMENT MANAGEMENT PLAN
10.1 The Environment Management Plan would consist
of all mitigation measures for each item wise
activity to be undertaken during the construction,
operation and the entire life cycle to minimize
adverse environmental impacts as a result of the
activities of the project. It would also delineate the
environmental monitoring plan for compliance of
various environmental regulations. It will state the
steps to be taken in case of emergency such as
accidents at the site including fire.
Detailed Management Plan along with
Monitoring Plan has been given in
Environment Management Plan given at
Enclosure-3.
40
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
ENCLOSURE 2: CONCEPTUAL PLAN
41
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Introduction The proposed project titled “545 Bedded Hospital” will be located at Site no. 2, Zone H-4/5, Facility
Centre, Pitampura. New Delhi- 110034. The land has been given on lease by Delhi Development
Authority to Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society vide
letter no. F (8)94/IL dated 02.06.2015 for the development of Integrated Hospital Building. The
project has earlier been granted Environmental Clearance vide letter no. 21-11114/2007-IA-III
dated 14.11.2008. However, only excavation & part basement construction (2 level of basement
each having area 9179.21 sqm) has been done after the grant of Environmental Clearance and no
construction has been carried out after that.
The total plot area of the project is 29999.34 m2 and the built-up area of the project is 94956.31
m2. As, the built-up area of the project will be less than 1,50,000 m2, hence it falls under Category
‘B’, Activity 8(a) of Schedule of the EIA notification, 2006 and its subsequent amendments.
Since the tenure of SEAC (Delhi Committee) has been completed, the application is being applied
to MoEF&CC. The cost of the project is 130 Cr.
Activities/ Amenities The activities proposed in the project are the following-:
• IPD
• OPD
• Day Care
• Emergency (casualty)
• Laboratories
• Operation theatres (OT),
• Intensive care units (ICU)
Site Location The proposed project titled “545 Bedded Hospital” will be located at Site no. 2, Zone H-4/5, Facility
Centre, Pitampura. New Delhi - 110034. The location of site is given in Environment Management
Plan.
Type of Project The proposed project is a new Hospital to be developed at built-up area 94956.31 m2. Since, the
built-up area of the project will be less than 1,50,000 m2. Hence, it falls under category B, Item 8(a)
of schedule of EIA notification, 2006 and its subsequent amendments.
Project Details
Project details are given in Table 1.
42
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Table 1: Project Details
Particulars
Unit Details as per
Earlier
Environmental
Clearance granted
dated 14-11-2008
Proposed
Details
Change
Plot Area m2 29999.34 No change
Ground Coverage (Permissible)
(40 % of total plot area)
m2 - 11999.736 -
Ground Coverage (Achieved)
(30 % of total plot area)
m2 - 8999.802 -
FAR AREA
FAR Permissible
(3.75 of total plot area)
m2 - 112497.53 -
FAR proposed
(1.74 of total plot area)-A
m2 - 52285.16 -
Free from FAR AREA
Permissible waiting area (Free
from FAR) (10% of proposed
FAR)
m2 - 5228.5 -
Proposed waiting area (Free
from FAR) -B
m2 - 4767.7 -
NON-FAR AREA
Service Floor m2 - 4820.39
-
Other Non-FAR area m2 - 5000
-
Total Non-FAR area-C m2 - 9820.39
-
BASEMENT AREA
Basement -I m2 - 12467.32 -
Basement -II m2 - 15615.72
-
Total basement Area-D m2 - 28083.04
-
Built-up Area (A+B+C+D) 96740.19
94956.31
Decrease-
1783.88
Total Green Area (20% of plot
area)
m2 - 5999.87 -
Surface Parking area m2 - 5911.00 -
Total Open & Road Area m2 - 9088.67
-
No of block No. 3
(Hospital block:
B+G+9
Research Block:
1
(Hospital block:
B+G+10)
Decrease-
2 blocks
43
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
G+10
Parking block;
2B+G+3)
Number of Basements No. 2 2 No change
Maximum No. of Floors No. G+10 G+10 No change
Max. height of building m - 45 -
No. of IPD Beds No. - 545 -
POPULATION IN HOSPITAL
No of IPD Patients No. - 545 -
No of OPD Patients No. - 2000 -
Staff in Hospital No. - 1635 -
Visitors in Hospital No. - 2000 -
Total Population No. - 6180 -
SERVICE DETAILS
Total Power load kVA 5500 5500 No change
No. of DG sets kVA - 2 x 1010 KVA
& 2 x 1500
KVA
-
No. of Rain water Harvesting
pits
No. - 7 -
Total Water Requirement KLD 883 759 Decrease-
125
Fresh Water Requirement KLD - 360 -
Treated Water reuse KLD 755 399 Decrease-
357
Waste Water Generation KLD - 422 -
STP capacity KLD 794.5 500 Decrease-
294.5
ETP capacity KLD - 25 -
Total Solid waste Generation kg/day 770 1091 Increase-
321
Total Biomedical Waste
Generation
kg/day 185 204 Increase-
19
Parking Requirement ECS - 1046 -
Parking Provision ECS 1753 1116 Decrease-
637
44
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Population Details During Construction phase-: 150 no. of labours shall be employed for the construction of the
project.
During Operation Phase-: The total population of the project has been estimated to be 6180 persons
including IPD Patients, OPD Patients, Staff and Visitors.
The population details are given in Table below-:
Table 2- Population Details
Particulars Unit Proposed Details
No. of IPD Patients No. 545
No of OPD Patients No. 2000
Staff No. 1635
Visitor No. 2000
Total Population No. 6180
Water Management
During Construction Phase
Approx. 12 KLD of water will be required which will be arranged on temporary basis through the
tankers. 7 KLD or water will be required for domestic purposes while 5 KLD of water will be used
for construction purposes. The waste water generated during construction phase will be 6 KLD
sewage which will be discharged into septic tank followed by soak pit.
During Operation Phase
The total water requirement of the project will be 759 KLD. Out of which, fresh water requirement
will be 360 KLD. The fresh water requirement shall be met by Delhi Jal Board. The waste water
generated in the complex will be 422 KLD (Laboratory Waste water-18 KLD and Sewage- 404
KLD). The laboratory waste water of 18 KLD shall be treated in Effluent Treatment Plant of
capacity 25 KLD. 16 KLD treated water shall be generated from ETP which shall be retreated in
STP. The 404 KLD of sewage generated & 16 KLD treated water generated from ETP shall be
treated in STP of 500 KLD. 399 KLD of treated water shall be generated from STP which shall be
completely reused in flushing, gardening, cooling and misc. purposes. It will be zero discharge
complex.
Rain water collection Details To recharge the ground water, 7 no. rain water harvesting pits shall be provided within the project
area.
Power Requirement & Back-up Power requirement during Construction Phase will be met by DG set of 1×125 kVA which shall be
used for construction works.
45
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Total Power Requirement during Operation Phase will be 5500 kVA which will be sourced through
TATA Power DDL. In case of power failure, power backup will be provided through DG sets of 2
x 1010 kVA and 2 x 1500 kVA. The DG sets will be kept in acoustically treated room on Surface.
Solid & Hazardous Waste Management During Construction Phase- Solid waste generation will be approx. 23 kg/day from labourers.
Excavation & part basement construction has already been done as per the grant of Environmental
Clearance granted. During part basement (2 level) construction, soil was excavated which was used
for backfilling purposes in nearby areas & out of it, top soil generated was used for landscaping
purpose in nearby areas.
There shall be done further excavation for foundation and basement. The further excavated soil will
be used for backfilling purposes within the site and out of it, top soil shall be preserved separately
and will be used for landscaping purpose only. In total Approx. 112332 m3 of soil excavation is
involved for providing foundation and 2 levels of basement completely.
C& D waste shall be disposed as per C&D Rules. Hence, no immediate adverse impacts on the land
environment are envisaged.
During operation phase- Total Solid Waste generation will be 1091 kg/day. Out of which 654
kg/day biodegradable waste will be treated in Organic Waste convertor while 218 kg/day recyclable
waste and 218 kg/day plastic waste will be given to approved recycler.
204 kg/day of Biomedical Waste shall be generated from the Hospital Complex which shall be
segregated properly and sent to State Approved Biomedical Waste Service Provider for final
disposal.
48 kl/month used oil shall be generated and 3-4 kg/month E-waste will be generated.
Battery waste shall be generated mainly from inverters & UPS.
Parking Management During construction phase- Proper parking provisions of trucks and other construction vehicles
shall be made. Proper spaces for loading and unloading shall be defined.
During operation phase- Total parking requirement for the project will be 1046 ECS. Total Parking
Provision for the Project will be 1116 ECS which shall be provide in Basements -1,2 and on Surface.
Green Area Development Green Area shall be developed on 5999.87 m2 i.e (20.00 % of total plot area) with trees and
plantation.
46
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
ENCLOSURE 3. ENVIRONMENT MANAGEMENT PLAN
47
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
ENVIRONMENT MANAGEMENT
PLAN
of
“545 BEDDED HOSPITAL”
Site no. 2, Zone H-4/5, Facility Centre
Pitampura, New Delhi
For: -
Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Regd. Off. -823, DLF Tower-A, Jasola District Centre, New Delhi-110025
PREPARED BY:
M/S PERFACT ENVIRO SOLUTIONS PVT. LTD. (NABET Registered Vide list of accredited consultants organizations/ Rev.78 /10th July, 2019 at S.No.-112)
(An ISO 9001:2008 & ISO 14001:2004 Certified Company)
5th Floor, NN Mall, Sector 3, Rohini, New Delhi-110085
Phone: +91-11-49281360
48
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
3.1 PROJECT DETAILS
The proposed project titled “545 Bedded Hospital” will be located at Site no. 2, Zone H-4/5, Facility
Centre, Pitampura. New Delhi- 110034. The land has been given on lease by Delhi Development
Authority to Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society vide
letter no. F (8)94/IL dated 02.06.2015 for the development of Integrated Hospital Building. The
project has earlier been granted Environmental Clearance vide letter no. 21-11114/2007-IA-III
dated 14.11.2008. However, only excavation & part basement construction (2 level of basement
each having area 9179.21 sqm) has been done after the grant of Environmental Clearance and no
construction has been carried out after that.
The total plot area of the project is 29999.34 m2 and the built-up area of the project is 94956.31
m2. As, the built-up area of the project will be less than 1,50,000 m2, hence it falls under Category
‘B’, Activity 8(a) of Schedule of the EIA notification, 2006 and its subsequent amendments.
Since the tenure of SEAC (Delhi Committee) has been completed, the application is being applied
to MoEF&CC. The cost of the project is 130 Cr.
The activities proposed in the project are the following-:
• IPD
• OPD
• Day Care
• Emergency (casualty)
• Laboratories
• Operation theatres (OT),
• Intensive care units (ICU)
The total plot area of the project is 29999.34 m2 and the built-up area of the project will be 94956.31
m2. 8999.802 m2 shall be utilized as Ground Coverage. Total FAR proposed of the project will be
52285.16 m2, proposed waiting area (Free from FAR) will be 4767.7 m2, total Non-FAR Area will
be 9820.39 m2 and total Basement area will be 28083.04 m2. The maximum no. of floors will be
G+10.
49
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
3.1.1. Area Details: Table 3: Detailed Project Information
Particulars
Unit Details as per
Earlier
Environmental
Clearance granted
dated 14-11-2008
Proposed
Details
Change
Plot Area m2 29999.34 No change
Ground Coverage (Permissible)
(40 % of total plot area)
m2 - 11999.736 -
Ground Coverage (Achieved)
(30 % of total plot area)
m2 - 8999.802 -
FAR AREA
FAR Permissible
(3.75 of total plot area)
m2 - 112497.53 -
FAR proposed
(1.74 of total plot area)-A
m2 - 52285.16 -
Free from FAR AREA
Permissible waiting area (Free
from FAR) (10% of proposed
FAR)
m2 - 5228.5 -
Proposed waiting area (Free
from FAR) -B
m2 - 4767.7 -
NON-FAR AREA
Service Floor m2 - 4820.39
-
Other Non-FAR area m2 - 5000
-
Total Non-FAR area-C m2 - 9820.39
-
BASEMENT AREA
Basement -I m2 - 12467.32 -
Basement -II m2 - 15615.72
-
Total basement Area-D m2 - 28083.04
-
Built-up Area (A+B+C+D) 96740.19
94956.31
Decrease-
1783.88
Total Green Area (20% of plot
area)
m2 - 5999.87 -
Surface Parking area m2 - 5911.00 -
Total Open & Road Area m2 - 9088.67
-
No of block No. 3
(Hospital block:
B+G+9
1
(Hospital block:
B+G+10)
Decrease-
2 blocks
50
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Research Block:
G+10
Parking block;
2B+G+3)
Number of Basements No. 2 2 No change
Maximum No. of Floors No. G+10 G+10 No change
Max. height of building m - 45 -
No. of IPD Beds No. - 545 -
3.1.2 Population Details During Construction phase-: 150 no. of labours shall be employed for the construction of the
project. Separate housing in the form of hutments shall be provided on the site for around 100
labours. Other labour will come from nearby areas. There shall be provision of creche facility,
kitchen, temporary toilets & bathrooms, drinking facility, rest room and first aid facility within the
hutments.
During Operation Phase-: The total population of the project has been estimated to be 6180 persons
including IPD Patients, OPD Patients, Staff and Visitors.
The population details are given in Table below-:
Table 4- Population Details
Particulars Unit Proposed Details
No. of IPD Patients No. 545
No of OPD Patients No. 2000
Staff No. 1635
Visitor No. 2000
Total Population No. 6180
3.1.3 Parking Management Parking Required:
Table 5: Parking Requirement Details
Particulars Factor Parking Required (in ECS)
Parking Required 2 ECS/100 m2 1046 ECS
51
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Parking Provision:
Table 6: Parking provision details
Particulars
Total
Area
Service
area
Parking
area
Factor Parking
provision
(in ECS)
Basement -1 12467.32 601.72 11865.6 32 371
Basement -2 15615.72 2.92 15612.8 32 488
Surface Parking - - 5911 23 257
Total Parking
1116 ECS
3.1.4 Power Requirement and Backup Details During Construction Phase-: DG sets of 1×125 kVA will be used for construction works.
During Operation Phase-: The total power requirement of the project will be 5500 kVA which will
be met by TATA Power DDL. In case of failure, power backup will be provided through DG sets
of 2 x 1010 kVA and 2 x 1500 kVA.
Table 7- Electric Details
Power Source TATA Power DDL
Total Power Load 5500 KVA
No. of DG Sets 2 x 1010 kVA and 2 x 1500 kVA
3.1.5 Waste Water, Rain Water and Solid Waste Details Table 8- Waste Water, Rain Water and Solid Waste Details
Particulars
Unit Details as per
Earlier
Environmental
Clearance granted
dated 14-11-2008
Proposed
Details
Change
No. of Rain water Harvesting
pits
No. - 7 -
Total Water Requirement KLD 883 759 Decrease-
125
Fresh Water Requirement KLD - 360 -
Treated Water reuse KLD 755 399 Decrease-
357
Waste Water Generation KLD - 422 -
52
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
STP capacity KLD 794.5 500 Decrease-
294.5
ETP capacity KLD - 25 -
Total Solid waste Generation kg/day 770 1091 Increase-
321
Total Biomedical Waste
Generation
kg/day 185 204 Increase-
19
Parking Requirement ECS - 1046 -
Parking Provision ECS 1753 1116 Decrease-
637
3.2 Land Use and Ownership of the site land The proposed project “545 Bedded Hospital” will be located at Site no. 2, Zone H-4/5, Facility
Centre, Pitampura. New Delhi - 110034. The land has been given on lease by Delhi Development
Authority to Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society vide
letter no. F (8)94/IL dated 02.06.2015 for the development of Integrated Hospital Building. The
project has earlier been granted Environmental Clearance vide letter no. 21-11114/2007-IA-III
dated 14.11.2008.
Since, the land has already been earmarked for Hospital Building as per Master Plan of Delhi,2021.
Hence, there shall be no change in Land Use.
3.3 Land Use The land use proposed at the site is given in Table below.
Table 9: Land use of the project Site
Land use Area (m2) Percentage (%)
Ground Coverage 8999.802 30.00
Green Area 5999.87 20.00
Surface Parking Area 5911.00 20.00
Road and Open Area 9088.67 30.00
Total Plot Area 29999.34 m2 100.00 %
53
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Figure 1: Land use
3.4 Location of the project with connectivity
3.4.1Geographical Information of Site Table 10: Geographical information of project site
Latitude Longitude Elevation
28°41'22.60"N 77° 6'42.92"E 217 m
Location map is shown in Figure 2.
Figure 2. Location of Project Site on Google Map
30%
20%20%
30%
Land Use
Ground Coverage
Green Area
Surface Parking Area
Road and Open Area
N
54
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
3.4.2 Topographical Map
3.5 Connectivity of the Project Details of connectivity are shown in Table below-:
Table-11 – Details of Connectivity around the Project Site
S. No. Accessibility Description Distance & Direction
1. Highway/ Road NH-10 1.21 km S
2. Railway Station Shakur Basti Railway Station 1.83 km SE
3. Airport Indira Gandhi International Airport 14.72 km SSW
55
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
3.6 Centrally Protected Monuments under Delhi Circle The list of Centrally Protected Monuments under Delhi Circle is the following-:
Ancient Mosque (Babur’s Period) together with adjacent area comprised
in part of Survey plot No. 177
Delhi fort or Lal Qila, NaubatKhana, Diwan-i-am, Mumtaz Mahal' Rang
Mahal, Baithak,MaseuBurj, diwan-i-Khas' Moti Masjid, sawanBhadon
,Shah Burj, Hammam with all surrounding including the gardens, paths,
terraces and water courses.
Salimgarh Fort, comprising the main gate on North, Ancient structure
near the main gate and the entire fortification wall
Fortification Wall Asad Burj, Water gate, Delhi Gate, Lahori Gate,
Jahangiri Gate, Chhattra Bazar, Baoli
11.10 km SSW
13.20 km SEE
13.31 km SEE
13.70 km SEE
3.7 Layout Plan
N
56
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
3.8 Water Management
3.8.1 Source of Water The water will be resourced through Delhi Jal Board.
3.8.2 Present Quality The present quality of Surface Water of nearby site canal has been accessed, the summarised results
with prescribed standards has been tabulated below-:
Sample Code Unit Nearby site canal Class
pH - 7.2 E
Total Dissolved Solids mg/l 216.9
Total Hardness mg/l 212
Biochemical Oxygen Demand mg/l 37.4
Chemical Oxygen Demand mg/l 112
The detailed studies have been done by M/s Perfact Researchers Pvt. Ltd.
3.8.3 Water Requirement During construction phase- Treated water will be arranged on temporary basis through the tankers
water supply. For construction activities, water will be sourced through nearby STP and will be
retreated on site before use. Drinking water will be sourced through the tankers.
Total water requirement during construction phase will be 12 KLD.
During operation phase-: The total water requirement of the project will be 759 KLD. Out of
which, fresh water requirement will be 360 KLD. The fresh water requirement shall be met by Delhi
Jal Board.
Table 12: Water Requirement
Particulars Population Factor
Water
Requirement
(in KLD)
Domestic
(in KLD)
Flushing
(in KLD)
Waste
Discharge
(in KLD)
IPD patients 545 450 245 164 81
OPD patients 2000 15 30 10 20
Staff and
employee 1635 45 74 41 33
Visitors 2000 15 30 10 20
Sub total 6180 379 225 154
Waste Discharge 158 154 312
Lab 20 18
Kitchen 35 28
57
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Café 15 12
Dialyses 25 22
De-ionized water for medical use 10 8
Cooling 217 11
Gardening 18 0
Filter Backwash 30 6
Misc. 10 5
Total Water
Requirement 759 422
Water Balance: -
Figure 3 Water Balance
3.8.4 Disposal The waste water generated in the complex will be 422 KLD (Laboratory Waste water-18 KLD and
Sewage- 404 KLD). The laboratory waste water of 18 KLD shall be treated in Effluent Treatment
Plant of capacity 25 KLD. 16 KLD treated water shall be generated from ETP which shall be
retreated in STP. The 404 KLD of sewage generated & 16 KLD treated water generated from ETP
shall be treated in STP of 500 KLD. 399 KLD of treated water shall be generated from STP which
shall be completely reused in flushing, gardening, cooling and misc. purposes. It will be zero
discharge complex.
.
Total Water Requirement(759 KLD)
Fresh Water(360 KLD)
Flushing(154 KLD)
Treated Water Re Used(399 KLD)
Gardening(18 KLD)
Waste Water directly to STP(404 KLD)
STP (500 KLD)
RECYCLED
WATER
Waste waterNIL
Treated Water(399 KLD)
Waste water
(154 KLD)
Reuse(399 KLD)
Cooling(217 KLD)
Lab(20 KLD)
To ETP(25 KLD)
Waste water
(18 KLD)
Treated water(16 KLD)
Misc.(10 KLD)
Domestic(225 KLD)
Waste water
(158 KLD)
Waste water
(106 KLD)
Waste water
(8 KLD)
Wastewater
(28 KLD)
Waste water
(12 KLD)
Waste water
(6 KLD)
Dialysis(31 KLD)
De-ionized water for
medical use(10 KLD)
Kitchen(35 KLD)
Cafe(15 KLD)
Filter Backwash(30 KLD)
Total Waste Water to STP(420 KLD)
Waste water
(5 KLD)
Waste water
(11 KLD)
To STP (16 KLD)
58
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
3.9 Air and Noise Management
3.9.1 During Construction Phase DG sets of 1×125 kVA with adequate stack height shall be used for Power supply during the
construction phase.
3.9.2 During Operation Phase During operation phase 5500 kVA of power load from TATA Power DDL shall be supplied to the
project. Power backup shall be provided by DG sets of capacity 2 x 1010 kVA and 2 x 1500 kVA.
3.10 Energy Conservation Measures
Following are the measures adopted to conserve the energy:
• Energy efficient lighting fixtures in parking and above grade floors.
• Basement lighting is controlled by alternate circuit switch for reducing energy consumption
during peak hours, by switching off the alternate lighting fixtures.
• Energy efficient pumps and motors (BEE star rated).
• Energy efficient water-cooled screw chillers with VSD drive.
• AAC blocks proposed for external wall construction.
• High performance double glazing for hospital building.
• Voltage drop for feeders shall not exceed 2% at design load and voltage drop for branch
circuit shall not exceed 3% at design load.
• Losses of transformer shall not be exceeding than ECBC requirement.
• All 3 phase shall maintain 0.95 power factor at the point of connection.
• Uses of incandescent lamp and halogen lamps shall be avoided and energy efficient LEDs
shall be used for all common area.
Solar Measures:
• External street lighting shall be provided by standalone solar panel.
• Solar Water Heater will be used to meet hot water requirement of the project.
• Hot water shall be taken from solar power generation.
• Solar panels shall be installed on the roof. 1 % of total load shall be met by solar power
generation.
• The layouts of buildings are designed to maximize the potential for use of solar lighting per
day devices.
• The space heating load will be minimized using solar structure and suitable buildings
envelop material.
3.11 Environment Management
The Environment Management Plan (EMP) is a site-specific plan developed to ensure that the
project is implemented in an environmentally sustainable manner where all stakeholders including
59
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
the project proponents, contractors and subcontractors, including consultants, understand the
potential environmental risks arising from the proposed project and take appropriate actions to
properly manage that risk. Adequate environmental management measures need to be incorporated
during the entire planning, construction and operating stages of the project to minimize any adverse
environmental impact and assure sustainable development of the area.
The EMP presented below should be followed and regular monitoring of relevant parameters as
stated in post project-monitoring schedule shall be carried out. The EMP is to be proactive in nature
and will be upgraded if new facilities or modification of existing facilities, with environmental
concerns, come up at a later stage.
3.11.1 Environment Management During Construction Phase
3.11.1.1 AIR ENVIRONMENT INDIAN METEROOGICAL DATA
Indian Meteorological Data conditions of the Project area can be summarised in the table below-:
S.no. Particulars Unit Details
1. Temperature ˚C 21.1-29.3
2. Relative Humidity % 43
3. Annual Rainfall mm 799
4. Wind Direction - North East to South West
5. Predominant Wind Direction - East to West
Annual Windrose Diagram
The Windrose Diagram of Annual AVERAGE (2002-2013) is given in figure below-:
Figure 4 Annual Windrose Diagram
(Source- IMD, Safdarjung)
Air quality around the project will be adversely impacted during the construction stage. Various
construction activities especially related to lose material likely to cause generation of dust that
60
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
adversely impacts the air quality of the surrounding area of the project site. To minimize such
impact, following measures will be taken:
• Dust mitigation measures shall be taken as per Environment (Protection) Amendment Rules,
2018.
• Metallic Roads leading to or at construction sites shall be paved and blacktopped.
• No excavation of soil shall be carried out without prior barricading of the project site &
other adequate dust mitigation measures in place.
• No loose soil or sand or Construction & Demolition Waste or any other construction
material that causes dust shall be left uncovered.
• Wind-breaker around the project site shall be provided.
• Water sprinkling system shall be put in place using spraying Nozzles.
• Sprinkling shall be done every hour by fixed sprinkling system.
• Proper barricading up to 10 m shall be provided.
• Grinding and cutting of building materials in open area shall be prohibited.
• Construction and Demolition waste shall be stored only within earmarked area and road side
storage of construction material and waste shall be prohibited.
• Only covered vehicles carrying construction material and waste shall be permitted inside
the complex.
• Construction and Demolition Waste processing and disposal site shall be identified and
required dust mitigation measures be notified at the site.
• DG sets shall be installed with adequate stack heights.
Maximum Ground Level Concentration of PM10 due movement of tankers and operation of DG Set
shall be maintained.
3.11.1.2 Noise Environment
During the construction stage, expected noise levels will be in the range of 80-100 dB(A), which
will decrease with increase in distance. Hence all the construction activities shall be carried out
during the daytime.
Due to the construction activities undertaken for the project, there will be some noise generation
due to the movement of vehicles carrying construction materials and as this will be only a temporary
phenomenon, it shall be managed by properly regulating the movement of vehicular traffic so that
the ambient noise quality will not be adversely affected.
To prevent any occupational hazard, ear muff / ear plug shall be given to the workers working
around or operating the plant and machinery emitting high noise levels. Operation of such plant or
machinery shall be strictly prohibited during night hours. Careful planning of machinery operation
and scheduling of operations shall be taken to minimize such impact. Furthermore, following
measures shall also be adopted:
• All the machinery and equipment shall be regularly maintained to reduce the noise level.
• DG sets of capacity 125 kVA shall be installed acoustically enclosed.
61
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
• Noise barriers shall be installed to reduce traffic noise & vibrations.
• Plantation shall be developed along the periphery of the site.
3.11.1.3 Water Environment
During the construction of the proposed project, the services required like water supply and sewage
facilities shall be arranged on a temporary basis and the same shall be maintained without any
adverse impact on the environment. Following are the measures required to manage the water
environment at site:
• Approx. 12 KLD of water will be required which will be arranged on temporary basis. 7 KLD
or water will be required for domestic purposes which will be supplied by tankers while 5 KLD
of water will be used for construction purposes which shall be taken from STP treated water of
nearby area.
• The waste water generated during construction phase will be 6 KLD sewage which will be
discharged into septic tank followed by soak pit.
• Runoff from the construction site shall not be allowed to stand (water logging) or enter into the
roadside or nearby drain. Adequate measures shall be taken to collect such run off and either
are reused or disposed off at the designated construction waste disposal location.
3.11.1.4 Solid Waste Management Excavation & part basement construction has already been done as per the grant of Environmental
Clearance granted. During part basement (2 level) construction, soil was excavated which was used
for backfilling purposes in nearby areas & out of it, top soil generated was used for landscaping
purpose in nearby areas. There shall be done further excavation for foundation and basement. The
further excavated soil will be used for properly stacked under tarpaulin cover and will be reused for
back filling purpose and road construction, etc. and out of total excavated soil, top soil shall be
preserved separately and will be used for landscaping purpose only. As soon as proposed green area
will be ready the top soil will be transferred and seeding will be done with regular sprinkling.
In total Approx. 112332 m3 of soil excavation is involved for providing foundation and 2 levels of
basement completely.
Construction debris like Concrete will be recycled and will be used in lean concrete, brick work
wastage will be used waterproofing for terrace, toilets etc. Tiles will be used in creating pathways
in the landscape area etc. Recyclable water like aluminium, steel, wood pieces, cement bags, plastic
containers, cartons, glass etc. will be sold to recyclers.
Approximately, 23 kg/day of Municipal solid waste shall be generated from temporary labours
which shall be disposed off at Municipal Landfill site.
Used oil whenever generated from the DG sets shall be kept in a secured place and in leak prof
container and shall be sent to approved recycler.
62
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
3.11.2 Environment Management during Operation Phase
3.11.2.1 AIR ENVIRONMENT DG set of 2 x 1010 kVA and 2 x 1500 kVA will be installed as power backup for emergency use
during power failure. Hence, to avoid the emissions, the DG sets shall be kept in acoustically treated
room on Surface. Stack height of 6 m above roof level for each D.G. sets shall be provided to reduce
the air emissions, meeting all the norms prescribed by CPCB.
Table 13: DG set & stack Height
As per the specifications from D.G. Set manufacturer following emissions shall be maintained, as
given in Table 12.
Table 14: DG Set emission standards
D.G Sets No. PM
mg/Nm3
Nox
mg/Nm3
HC
mg/Nm3
CO
mg/Nm3
1010 kVA 2 75 887.5 100 150
1500 kVA 2 75 887.5 100 150
3.11.2.2 NOISE ENVIRONMENT
The main sources of the noise pollution will be D.G sets. of 2 x 1010 kVA and 2 x 1500 kVA will
be installed in the project.
DG sets shall be kept in acoustically treated room on surface and shall meet the norms prescribed
by CPCB. Planting of the trees at the boundary of the project will help in reducing the level of the
noise within the project.
Location of DG sets: Surface
Insulation of air inlet and outlet points
The sound travels along with air therefore it is necessary to control the travelling sound with the
help of insulated ducts [2” glass wool pads and perforated sheets] and louvers at inlet and outlet air
points. The ducts have S-type shape to prevent any direct escape of noise Insulated service door
The maintenance and servicing of D.G. set is done using a suitable service door of 5’ x 7’ size. The
door is made of MS sheet and frames fully insulated with 3” thick glass wool pad followed by
perforated aluminium sheets.
D. G. Set. Capacity No Stack Height
1010 kVA 2 6 m above roof level
1500 kVA 2 6 m above roof level
63
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
3.11.2.3 WATER MANAGEMENT The total water requirement of the project will be 759 KLD. Out of which, fresh water requirement
will be 360 KLD. The fresh water requirement shall be met by Delhi Jal Board. The waste water
generated in the complex will be 422 KLD (Laboratory Waste water-18 KLD and Sewage- 404
KLD). The laboratory waste water of 18 KLD shall be treated in Effluent Treatment Plant of
capacity 25 KLD. 16 KLD treated water shall be generated from ETP which shall be retreated in
STP. The 404 KLD of sewage generated & 16 KLD treated water generated from ETP shall be
treated in STP of 500 KLD. 399 KLD of treated water shall be generated from STP which shall be
completely reused in flushing, gardening, cooling and misc. purposes. It will be zero discharge
complex.
3.11.2.3.1Waste Water Treatment
The Sewage Treatment Plant of 500 KLD based on MBBR technology offered has some distinct
advantages over conventional activated sludge processes. The scheme is proven, under a variety of
operating conditions, and is highly flexible in operation.
The characteristics of Raw sewage and the characteristics required for the treated water will be as
given in Table below.
Table 15: RAW SEWAGE CHARACTERISTICS
The Sewage Treatment Plant (STP) will give treated water, which will be reused for Flushing,
Gardening & Tower Cooling purposes.
Flow m3 / day 404 KLD
pH - 7.5 – 8.0
BOD mg / l 200 - 350
COD mg / l 400 - 500
TSS mg / l 100
Oil & Grease mg / l 10
Figure 5: Anti-vibration pads
64
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Table 16: TREATED SEWAGE CHARACTERISTICS
pH - 6.5-9.0
BOD mg / l <10
COD mg / l <50
TSS mg / l <20
Oil & Grease mg / l NIL
TREATMENT PROCESS:
It is proposed to treat the complete wastewater in a scientific manner through a properly planned
treatment plant. The objective is to stabilize the decomposable organic matters present in sewage
so as to get an effluent and sludge having characteristics which are within safe limits. To have an
efficient treatment system, this aeration system is proposed consisting of MBBR Technology. The
sewerage treatment plant can be constructed in such a way that it becomes viable by providing
Treated water for reuse and sludge that can be used as for manure for further use.
Different Components of the Plant
In the proposed treatment scheme, the following component unit shall be provided:
➢ Screen chamber
➢ Bar screen /Grit chamber within effluent collection sump.
➢ Submersible type raw effluent re-lift pumps
➢ Equalization tank
➢ MBBR tank/ Aeration tank
➢ Tube settler
➢ Clarified Water, Filtered Water & Soft Water Storage Tanks
➢ Filter feed pump
➢ Tertiary Treatment Units (Filtration, U.V treatment)
➢ Treated Water Supply Pumps
➢ Sludge return pump
➢ Sludge holding tank
➢ Centrifuge for solid waste management
➢ Sludge loading pumps
➢ Sludge drying beds, Centrifuge/Filter Press
65
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
PROCESS DESCRIPTION
a) Raw sewage from main sewer line shall be collected through gravity pipes into the screen
chamber. This manually cleaned screen shall be provided to remove floating and big size
particles which may otherwise choke the pumps and pipe lines.
b) After screening, the waste water shall be allowed to pass through a grit chamber to remove the
grit material. The screens and grit chambers shall be accessible so that they may be manually
cleaned from time to time.
c) The screened waste water from the Grit chamber shall be then passed into the equalization tank
to homogenize the waste water quality and also even out flow fluctuations and feed waste water
of uniform quality at constant rate to subsequent treatment units. Air mixing shall be provided
to mix the contents of the equalization tank. A coarse bubble aeration grid shall be provided to
mix the contents of the equalization tank and also to avoid septic conditions in the tank. From
the equalization tank the wastewater will be pumped into an MBBR Tank.
d) The MBBR process uses small plastic carrier elements to provide growth sites for bacteria
attachment in a suspended growth medium. The carrier elements shall allow a higher biomass
concentration to be maintained in the reactor. This shall increase the biological treatment
capacity for the given reactor volume.
e) The carrier elements shall be continuously kept in suspension by the aeration system. The
agitation pattern in the reactor shall be designed to provide an upward movement of the carriers
across the surface of the retention screen which creates a scrubbing effect to prevent clogging.
Combination of fine & coarse bubbles may be provided to provide oxygen as per detailing.
f) From the MBBR tank mixed liquor shall flow by gravity into the Tube settler. The solids will
settle in the tank. The sludge that settles down shall be transferred to sludge holding tank via
sludge loading pumps, with provision of sludge return to the bioreactor if necessary.
g) From the tube settler, treated wastewater will be fed by means of filter/softener feed pump sets
to pass through dual media filters, activated carbon filters and softeners and stored in the filtered
water and soft water storage tanks. The activated carbon filters shall ensure removal of all
coloration and odours present in the treated effluent.
h) The filtered, clean and odourless water from filtered water tank is then fed through a variable
frequency drive hydro-pneumatic system to the external treated effluent rings as per the master
plan, from where connections are taken to the garden hydrant system and to each unit for
flushing water as per detailing.
66
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
i) Excess sludge from the tube settler will be taken periodically into sludge holding tank. In this
tank sludge will be aerated for self-stabilization. Air will be shut off periodically and
superannuate water will be transferred to the aeration tank creating stabilized sludge. The final
sludge shall be de-watered through a centrifuge mechanism. Sludge loading arrangements shall
also be provided for direct disposal of sludge to sludge tankers / trolleys.
Hydraulic Flow Diagram of STP based on MBBR Technology
Figure 6. Hydraulic Flow Diagram of STP (MBBR Technology)
3.1.1.1.1 SCHEME OF EFFLUENT TREATMENT PLANT
Approx. 18 KLD effluent will be generated from the laboratory which will be treated in the ETP of
25 KLD.
Details of ETP are given as follows:
The waste water firstly passes through the oil and grease tank to remove excess oil from the
wastewater. The waste water after removal of oil and grease will collected in equalization tank to
holding the wastewater for some pre-determined time in a continuously mixed basin to produce a
uniform wastewater. The wastewater then subjected to Flocculation tank. In a flocculation tank, the
water is stirred or otherwise moved around so that the particles move around, bump into other
particles. Chemicals (most commonly "alum"/ polyelectrolyte) are often added to the water going
into a flocculation tank to help aid particle formation. The next step in the process is to separate the
solid sludge with the wastewater hence the wastewater will be transfer to Tube settlers which
capture the settleable fine floc that escapes the clarification zone beneath the tube settlers and allows
the larger floc to travel to the tank bottom in a more settleable form. The tube settler’s channel
collects solids into a compact mass which promotes the solids to slide down the tube channel to
INCOMIN
G
SEWAGEBAR
SCREEN BAFFLE
WALL
OIL &
GREASE EQUALIZATION
TANK
MBBR-1 MBBR-2 TUBE
SETTLER
CLEAR
WATER
TANK MGF ACF
TREATED
WATER
TANK
TREATED
WATER
USED
UV
FILTER
PRESS
SLUDGE
HOLDING
TANK FINAL
DISPOSAL
TO
EQUALIZATION
TANK
MBBR STP TECHNOLOGY
LEGENDS
Mark Descriptions
Air Line
Sludge Line
Effluent line
Air Blowers
Air Diffusers
Butter Fly Valv
Non Return
Valv
Pump
67
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
sludge drying beds and the water content will be goes into the carbon filter to remove contaminants
and impurities, utilizing chemical adsorption. Finally, the water will be retreated in STP.
Schematic diagram of ETP is given below:
3.11.2.3.2Rain Water Harvesting
The main source of ground water recharging in the study area is rainwater, which infiltrates into the
ground through various lithological units present in the study area. In the proposed complex there
will be 7 no. of Rainwater Harvesting pits. The runoff from the rooftop and storm water shall go to
the recharge pits.
Scheme for Ground Water Recharging
The rainwater is diverted from the rooftop using rain water pipes to the surface / underground
drainage network. The entire campus is sub divided for recharging structures. The rainwater is
diverted into the desilting tank to remove inorganic impurities and the outflow of the desilting tank
is taken into the recharge well.
Desilting Tank
The desilting tanks are used to remove silt and other floating impurities from rainwater. Desilting
tank is like an ordinary container having provision for the inflow, outflow and overflow. Apart from
removing silt it holds the excess amount of water till it is soaked up by the recharge structure. The
bottom of tank will have unpaved surface (layers of coarse sand) to allow standing water to
percolate into the soil. The rainwater collected in these desilting chambers shall be utilized for
horticulture.
Recharge well
The recharge well consists of percolation pits with boreholes in the middle of the pit. UPVC pipe
perforated will be lowered in the middle of the boreholes and the pit will be filled with gravel and
pebbles in three layers consisting of boulders, gravel and coarse sand. The mouth of the UPVC pipe
Treated
water to
STP
68
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
shall be protected to avoid silt getting into it. The depth of the bore will depend on the soil
condition/water strata. The schematic diagram is enclosed.
It should be therefore concluded that there is no significant impact on surface water quality &
hydrology of the area. The proposed rainwater-harvesting scheme will stabilize the groundwater
table in the area.
RAIN WATER HARVESTING CALCULATIONS: -
Soil Quality Silt loam
Infiltration Rate 36 mm/hr
Porosity 35 %
Annual Rainfall 794 mm
Peak Hourly Rainfall 90 mm/hr
No. of Rainwater Collecting Pits 7
Size of Pits Diameter- 4.9 m, Depth- 4.5 m
Table 17: detailed calculation of rain water harvesting calculation
S.No. Type of surface Catchment
area (m2)
Runoff
coefficient
Intensity of
rainfall
(mm/20 min)
Water
Discharge
(runoff)
(in m3) Peak hourly
90 mm
1 Roof top area 8999.802 0.9 30 242.99
2
Paved surface, Roads &
other built up area
(including Surface
Parking Area) 14999.67 0.7 30 314.99
3 Lawns, Garden & all
other Open area 5999.87 0.2 30 36.00
Grand Total 29999.34
m2 594 m3
69
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
RWH Pit Diagram: -
4900
70
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
3.11.2.4 WASTE MANAGEMENT
3.11.2.4.1 Municipal Solid Waste
For 6180 persons, around 1091 kg/day of municipal solid waste will be generated from the proposed
site.
The solid waste categories and disposal method detail is shown is given in Table 17:
Table 18: Municipal Waste Management
Type of Waste Colours of
Bins
Category Disposal Method Total Waste
(kg/day)
Bio Degradable Green Organic
waste
The waste shall be treated
in organic waste converter
and converted to manure
654
Non-
Biodegradable
Blue Recyclable Recycler 218
Plastic Blue Recyclable Recycler 218
Total
1091 kg/day i.e.
398 tons/annum
DETAILS OF ORGANIC WASTE CONVERTER
Tentative details of the Organic Waste Converter are as follows:
Model no. No. of OWC
provision
Capacity per
batch
Power Dimension
(l x w x h)
RN-125 1 no. 125 kg/batch 5.6 kW; 3 Phase
440 V, 50 Hz
4 m x 1.28 m
Biodegradable Waste Batch Capacity No of Batch
654 kg/day 125 kg/batch 6 batch/day
• No. of organic waste converter = 1 Nos.
• Volume of waste = 1.308 m3
• Space for organic waste converter= 4 m x 1.28 m = 5.12 m2
• Area required for storage and management of solid waste = 10 m2
• Area provided for storage and management of solid waste = 30 m2
71
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
3.11.2.4.2 Biomedical Waste Management Type of Waste No of Beds Disposal Method Total Waste
Biomedical No of IPD Beds- 545 Hospital will handover duly
segregated and disinfected
waste to State Approved
Biomedical Waste Service
Provider for final disposal
204 kg/day
75 tons/annum
3.11.2.4.3 Hazardous Waste Management: - Hazardous waste is a waste with properties that make it dangerous or potentially harmful to human
health or the environment. The universe of hazardous wastes is large and diverse. Hazardous wastes
can be liquids, solids, contained gases, or sludge. They can be the by-products of manufacturing
processes or simply discarded commercial products, like cleaning fluids or pesticides. All
hazardous wastes are required to be treated and disposed off in the prescribed manner.
The main objective is to promote safe management and use of hazardous substances including
hazardous chemicals and hazardous wastes, in order to avoid damage to health and environment.
Table 2: Hazardous & E-Waste Management
Battery waste will be generated from inverters & UPS, which shall be treated as per the Batteries
(Management & Handling) Rules, 2001.
3.11.2.5 PLANTATION
Green belt planning will be done with ecological perspectives for the project taking into
consideration and availability of space and other aspects. This will help in increasing the aesthetic
effect of the environment.
Since tree trunks are devoid of foliage, scrub should form there to give coverage to the trunks. The
trees maintain the regional ecological balance and conform to soil and hydrological conditions.
Indigenous species would be preferred.
Green belt/greenery has been developed along most of the periphery of the project area as well as
along roads. Area under plantation/greenery will be 5999.87 m2 (20% of plot area) which shall be
maintained with trees and plants. The trees planted are of adequate height.
Type of Waste Disposal Method Total Waste
Used Oil
Used oil shall be given to Approved vendor
Hazardous & other waste (Management &
Handling) Rules, 2016
48 lt/month
E-waste Shall be given to Approved vendor as per E-
Waste (Management & Handling) Rules, 2016 3-4 kg/month
72
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Total No. of trees required = Total plot area/80
= 29999.34/80
= 375 nos.
No of existing at site = 70-80
No of trees to be cut = 0
No of trees to be Transplant = 70-80
No. of trees proposed = 305
Total No of trees (Transplant +Proposed) = 375
Table 19: Total no. of Species proposed
S. No. Scientific Name Common Name Number of Trees
1. Wodyetia bifurcate Foxtail Palm 50
2. Polyalthia longifolia Pseudo Ashoka 75
3. Mimusops elengi Maulsari 40
4. Azadirachta indica Neem 64
5. Neolamarckia kadamba Kadamb 40
6. Plumeria alba White firangipani 46
Total 305
3.11.3 ANTICIPITATED IMPACT & MITIGATION
MEASURES
3.11.3.1 DURING CONSTRUCTION PHASE S. No. Description Impacts Mitigation Measures
1. Air & Noise
Environment
Dust will be generated due to
Site clearance and emissions
may be generated due to
vehicles, DG sets and
machinery/equipment etc.
Loading and unloading of
construction materials like,
cement, sand, stones, bricks, etc.
will result in dust generation.
Procurement and transport of
construction materials such as
sand, cement etc. will also result
in dust generation.
Water sprinkling shall be done
to reduce the dust during
construction of buildings.
D.G. set of 1×125 kVA shall be
provided with adequate stack
height to avoid emissions.
Trees will be planted along the
construction site to reduce dust
& emissions.
73
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
2. Water
Environment
Soil runoff from the site leading
to off – site contamination
(Particularly during rainy
season).
Improper disposal of
construction debris leading to
off-site contamination of water
resources.
Disposal of domestic waste
water from temporary labour
rest rooms.
Spillage of oil and grease from
the vehicle and waste water
stream generated from on-site
activities.
During construction phase,
water will be provided from
the nearby STP/tanker water
supplier.
The rain water from the
construction site shall be
collected, treated & reused for
sprinkling.
Approx. 6 KLD of sewage
from labours shall be
discharged into septic tank
followed by soak pit.
3. Solid Waste The waste from labour rest
rooms/sheds would be mainly
household domestic waste
The solid waste generated
during construction phase used
oil from DG sets.
Approx. 23 kg/day municipal
solid waste shall be generated
from 150 labours which shall
be disposed off in MSW site.
Used oil whenever generated
from the DG sets shall be kept
in an isolated area and in leak
proof container and sent to
approved recycler.
3.11.3.2 DURING OPERATION PHASE S. No. Description Impacts Mitigation Measures
1. Air & Noise
Environment
Running of DG sets of capacities
2 x 1010 kVA & 2 x 1500 kVA
during power failure will result into
air emissions.
DG sets shall be provided with
stack height of 6 m above roof
level for 2 x 1010 kVA & 2 x
1500 kVA as per CPCB norms
and shall be kept in
acoustically treated room.
2. Water
Environment
During the operation phase
abstraction of water is not proposed
for project. Fresh water
requirement of 360 KLD shall be
met by municipal supply of Delhi
Jal Board.
Fresh water requirement shall
be reduced by using 399 KLD
treated water.
399 KLD of treated water shall
be generated from STP which
shall be completely reused in
flushing, gardening, cooling
74
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
In the proposed project, water will
be used for domestic use, flushing,
laboratory, Kitchen, Café,
Dialyses, De-ionized water for
medical use, Cooling, Filter
Backwash, gardening & misc.
purposes etc. The waste water
generated in the complex will be
422 KLD (Laboratory Waste water-
18 KLD and Sewage- 404 KLD).
The laboratory waste water of 18
KLD shall be treated in Effluent
Treatment Plant of capacity 25
KLD. 16 KLD treated water shall
be generated from ETP which shall
be retreated in STP. The 404 KLD
of sewage generated & 16 KLD
treated water generated from ETP
shall be treated in STP of 500 KLD.
and misc. purposes. It will be
zero discharge complex.
Rain water shall be recharged
into the ground water by 7 no.
of rain water harvesting pits.
3. Solid Waste Bio-degradable and recyclable
waste from households’ activities.
Used oil from DG sets and e- waste.
E- waste & battery waste
generation.
Bio-degradable waste of 654
kg/day shall be disposed in
Organic waste convertor.
Biomedical Waste of quantity
204 kg/day shall be duly
segregated and given to
approved Biomedical Waste
Service Provider.
Used oil of 48 lt/month will be
generated from the DG sets
which shall be kept in an
isolated area and in leak proof
container and shall be given to
authorised recycler.
The generated E-waste of 3-4
kg/month shall be given to
Authorized vendor.
Battery waste shall be treated
as per the Batteries (Handling
& Management) Rules, 2001.
75
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
3.12 ENVIRONMENT MONITORING PLAN During Construction
Sr. No. Type of Monitoring Frequency of
Monitoring
Parameter Location
1 Ambient Air Quality Six Monthly Particulate Matter (PM 2.5)
Particulate Matter (PM 10)
Sulphur Dioxide (SO2)
Nitrogen Oxides (NOx)
Two Locations in
and around the
project site
2 Stack Monitoring Six Monthly Particulate Matter, Sulphur
Dioxide (SO2), Nitrogen
Oxides (NOx)
DG sets of capacity
125 KVA installed
for construction
purposes
3 Water Quality Monitoring for
drinking water
Six Monthly All parameters mentioned in
IS:10500
One drinking water
sample
4 Water Quality Monitoring for
Construction purpose
Six Monthly All parameters mentioned in
IS:456
One construction
water sample
5 Noise Level Monitoring Six Monthly Day and Night noise level Two locations
6 Soil Quality Monitoring Six Monthly All parameters to check soil
Fertility
Two Locations in
and around the
project site
7 Monitoring of waste
generation and other pollution
control aspects
Six Monthly _ _
During Operation Phase
Sr. No. Type of Monitoring Frequency of
Monitoring
Parameter Location
1 Ambient Air Quality Annually Particulate Matter (PM 2.5),
Particulate Matter (PM 10),
Sulphur Dioxide (SO2),
Nitrogen Oxides (NOx)
Two Locations in
and around the
project site
2 Stack Monitoring Annually Particulate Matter, Sulphur
Dioxide (SO2), Nitrogen
Oxides (NOx)
DG sets (2 x 1010
kVA & 2 x 1500)
installed for backup
purposes
3 Water Quality Monitoring
for drinking water
Annually All parameters mentioned in
IS:10500
One drinking water
sample
4 Sewage Treatment Plant &
Effluent Treatment Plant
Monitoring
Annually BOD, COD, TSS, Oil and
Grease and pH
Inlet and Outlet of
STP & Inlet and
Outlet of ETP
5 Ambient Noise Level
Monitoring
Annually Day and Night noise level Two locations
6 DG Set Room Noise
Monitoring
Annually Inside and Outside of DG Set
Room
One Locations
7 Soil Quality Monitoring Annually All parameters to check soil
Fertility
Two Locations in
and around the
project site
76
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
8 Monitoring of Waste
Generation and other
pollution control aspects
Annually _ _
3.13 Environment Management Cost
3.13.1 Capital Cost
S No. Description Total Cost
(In Lacs)
01. Landscaping 30.0
02. STP & ETP 110.0
03. DG Stack & Acoustic Treatment 7.2
04. Solid Waste Management 30.0
05. RWH 10.5
06. Miscellaneous 5.0
Total 192.7
3.13.2 Recurring Expenditure
S No. Description Total Cost
(In Lacs/ year)
01. Landscaping 3.0
02. Water Management 12.0
03. Air Management 1.0
04. Environment Management 1.5
05. Solid Waste Management 3.0
06. Miscellaneous 2.0
Total 22.5
3.14 Corporate Environment Responsibility As per CER office memorandum of MOEF dated 1.5.2018, the project cost for project is
Rs 130 Cr, hence the industry has to spend 1.5 % of the cost of the project (Rs 195 lacs) on CER
activities.
As per the Office Memorandum some of the activities which can be carried out in CER, are
infrastructure creation for drinking water supply, sanitation, health, education, skill development,
roads, cross drains, electrification including solar power, solid waste management facilities,
scientific support and awareness to local farmers to increase yield of crop and fodder, rain water
harvesting, soil moisture conservation works, avenue plantation, plantation in community areas,
etc.).
77
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
The following provisions shall be contributed under Corporate Environment Responsibility-:
S.No Activity Provision 1st
year 2nd year
3rd year
4th year
5th year
Total Cost
(Lakhs)
1
Conservation of water body in Jheel Park Lake (Pitampura) and Native Plantation
Water level Restoration of Jheel in consultation with local NGO for Conservation and plan to develop green belt with native species, ornamental plants
12 35 40 35 30 152
2 Solar Light in Jheel Park Pitampura
Provision of streetlight powered by photovoltaic panels with rechargeable battery, LED lamps.
7.5 5 10 10 5 37.5
3 Waste Management
Providing coloured dust bins and collection of segregated waste and their disposable.
2 2 0.5 0.5 0.5 5.5
Total Rs in Lakhs 22 42 50.5 45.5 35.5 195
78
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
ENCLOSURE 4. RISK ASSESSMENT
79
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
4.1 RISK ASSESSMENT
Hazard identification is the process used to identify all possible situations in the hospital where
people (patient, staff, visitors etc.) may be exposed to injury, infections or disease.
The risk hazards may be of two types:
1. Natural disasters
Earthquake
Cyclone / Storm
Flood / Draught
Landslides etc
2. Technological disasters
Gas leakages, Rupture of Gas cylinders / Pressurized Vessels / Pipe lines
Chemical, Biological, Radiological, Nuclear & Explosion Emergencies
Failure of Machines / Production
Human Error / Nuisance / Maniac
Terrorist Act
Fire Emergencies
The objectives of risk assessment are:
• To achieve a level of preparedness to safeguard the public and mitigate the impact of the
disaster.
• To prompt an effective disaster management strategy without causing panic among the patients,
visitors and the public.
4.1 DISASTER MANAGEMENT PLAN
Hospital Disaster Management provides the opportunity to plan, prepare and when needed enables
a rational response in case of disasters/ mass casualty incidents (MCI). Disasters and mass casualties
can cause great confusion and inefficiency in the hospitals. They can overwhelm the hospitals
resources, staffs, space and or supplies. Lack of any tangible plan to fall back upon in times of
disaster leads to a situation where there are many sources of command, many leaders, and no
concerted effort to solve the problem.
80
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
A disaster planning shall be done in a way that the quality of care to the serious/ critical patients is
not compromised. The plan should aim at the survival and recuperation of as many patients as
possible.
An internal risk management authority is formed which may undertake periodic evaluation of safety
precautions to be followed by each department for hazard recognition with the following steps:
1. Both Clinical and Non-clinical audits will be undertaken on a periodical basis to identify
the measures taken to prevent/reduce the impact of the potential hazards.
2. All the staff of the hospital will be encouraged to routinely assess all activities to identify
potential hazards.
3. Departmental Heads and Managers will identify hazards within their specific area of control.
The same should be notified to the appropriate hospital authorities for immediate corrective
actions.
To make the proceedings easier, the hospital administrators will embark upon disaster planning
using a phase plan. The hospital emergency planning is divided into three phases:
1) Pre-disaster phase
(a) Planning: Risk assessment and planning for preparedness will be done, the hospital plans
will be formulated and then discussed in a suitable forum for approval.
(b) The disaster manual: The hospital disaster plan shall be written down in a document form
and copies of the same should be available in all the areas of the hospital.
(c) Staff education and training: Regular staff training by suitable drills shall be undertaken in
this phase.
2) Disaster Phase
(a) Phase of activation: Alter and notification of emergency.
(b) Activation of the chain of command in the hospital.
(c) Operational phase: This is the phase in which the actual tackling of mass casualties will be
performed according to the disaster/emergency plan.
(d) Phase of deactivation: When the administration/ command of the hospital will be satisfied
that the influx of mass casualty victims is not continuing to overwhelm the hospital facilities.
3) Post Disaster Phase
This is an important phase of disaster planning where the activities of the disaster/ emergency phase
will be discussed and the inadequacies will be noted for future improvements.
81
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
4.2 SAFETY MEASURES:
Fire Safety
All the arrangements shall be made as per National Building Code Part-IV: 2016.
FIRE safety is so important to all hospital administrators, employees and designers that the
leadership in the hospital field should make every effort to keep abreast of current developments in
the fire safety field.
The basic principles of fire safety shall be kept in mind during the design, construction, operation
and maintenance of each hospital facility. Planning for fire safety can be divided into five steps:
• Minimizing the chance of fire,
• Early discovery,
• Restricting fire spread,
• Extinguishing the fire, and
• Evacuating the building.
Fire Prevention:
To prevent the incidence of fire, appropriate measure to control fire hazards in the building and
maintenance of the building facilities shall be practiced. The preventive measures taken for fire
safety are as follows:
➢ The hospital shall be declared ‘No Smoking’ zone.
➢ Fire Detection & Alarm Systems are to be installed in different parts of the hospital, in-case
of the fire, on detecting fire the devices are activated and hooter is alarmed in the security
office.
➢ Fire Extinguisher: As per IS- 2190 Fire extinguishers, in appropriate sizes and types, are to
be provided throughout the hospital in every floor of the hospital. The maintenance, Testing
& inspection of Extinguishers as per schedule to be carried out by a qualified person. The
theft of or tampering with an extinguisher should be reported immediately to the
Maintenance concerned In-charge.
➢ Emergency Exits shall be provided at places and no obstructions may be placed in front of
or upon any exit door.
Class of Fire Description Suitable Type of Appliances
A Fire in ordinary combustibles
(wood, fibers, rubber plastics,
paper and the like)
Gas Expelled Water Type
82
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Electrical Safety:
The following measures are required to be undertaken to ensure Electrical safety:
1. Routine Inspection of the power outlets throughout the hospital by the electrician.
2. Trip Switches are to be installed in different parts of the hospital to prevent short circuits.
3. Periodic inspection of wires to ensures that they are in appropriate conditions.
4. Before any electrical appliance is brought into Hospital, a safety inspection is necessary.
5. Electrical equipment not required during night is to be switched off.
6. Areas around electrical switchboards must be kept clear for a distance of at least 1 meter.
7. ABC type fire extinguisher is to be installed adjacent to electrical switchboards.
Bomb Threat:
Bomb threats are delivered in a variety of ways with the majority of threats being called in to the
target. In the event of a bomb threat, all personnel will follow the following procedures:
i. The staff member receiving the call should make reasonable efforts to gain as much
information as possible. Keep the caller on the line as long as possible. Ask who is calling,
and have the caller repeat the message. Write down every word spoken by the person making
the call.
ii. If the caller does not indicate the location of the bomb or the time of the possible detonation,
the person receiving the call should ask the caller to provide this information.
iii. Pay close attention to any strange or peculiar background noises such as motors running,
background music, or other noises that might give some clue concerning the origin of the call.
iv. Immediately call the local Police Department regarding the threat & the caller.
v. Evacuation notification procedures will be activated to evacuate the buildings.
vi. The staff should direct and assist patients to exit the buildings consistent with fire evacuation
procedures
vii. The police and assigned staff (security Personal) will conduct an extensive search of the
building and remove the bomb with the help of Bomb Disposal Squad.
B Fires in flammable liquids, paints,
grease, solvents.
Fire extinguishers of CO2, Foam
type, Dry powder type and
buckets.
C Fire in gaseous substances under
pressure including liquefied gases
Fire extinguishers of carbon
dioxide and dry powder type
Electrical /
Electronics
Installations
IT & Server Rooms, Electrical
Panels
And equipment.
Dry Chemical Powder, CO2 and
FM -200 or Clean agent type
83
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
viii. The Director or authorized representative will approve re-entry into the building after the
search is completed and after consultation with the police for bomb removal confirmation.
MOCK DRILL
a) Evacuation drills shall be conducted at established intervals not exceeding 12 months, at the
start of each new season, and with new staff. Drills shall be recorded in the operational log.
b) When the evacuation plan involves use of emergency services, they should be involved in the
preparation of the plan and should be accorded every opportunity to undertake training or drills
at least once per year for continuously operating installations and prior to each opening for
seasonal operations.
HOSPITAL SAFETY COMMITTEE:
The Hospital Safety Committee is a multidisciplinary committee consisting of five members. It
meets at least six times in a year to evaluate the various safety aspects of the hospital. The
Committee undertakes detail analysis of the ongoing monitoring activities and gives its feedback
on the same. The Committee submits its report to the Chief Medical Superintendent of the hospital.
The Hospital Safety Committee evaluates the ongoing monitoring activities on various aspects of
the following problems:
• Injuries to patients/ visitors
• Property damage.
• Occupational illnesses and injuries to staff
• Hazardous materials and waste spills, exposures, and other related incidents
• Security incidents involving patients, staff, students and visitors at Hospital.
• Fire-safety management problems, deficiencies, and failures.
• Medical equipment-management problems, failures, and user errors
• Utility systems management problems, failures, or user errors.
• Staff Unavailability (such as Weather Emergencies, natural disasters)
• Mass Casualty Patient Influx (such as Infectious Disease Outbreaks).
Role of the Hospital Safety Committee:
a. Provide guidance and direction in all phases of the Safety Management Program.
b. Pro-active safety risk assessments of the clinical and clinical support areas of hospital.
c. Facilitates the Environmental Monitoring Rounds.
d. Advising management of unsafe conditions or of non-compliance with regulations and
standards.
e. Conducts on-going safety education classes.
f. Responsible for proposing/revising safety policies.
84
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
GENERAL OUTLINE OF EMERGENCY PLANNING
➢ On site Emergency Plan
Role of Security I/C and Shift I’s/C
Emergency Control room with Emergency telephone numbers
Fire Wardens for each complex
Medical Aid / Hospital Available, Distance
Rehearsal / Training / SOP
➢ Off - site Emergency Plan
Local Fire Brigade at Distance
Disaster Management / Specialized Teams
Dog Squad / Explosion Detective Teams
Hospital, Number of Doctors and Staff, Distance Availability round o’ clock Resources Available
District / Police Authorities
Rehearsal / Training / SOP
ROLES, DUTIES & RESPONSIBILITIES AT THE TIME OF EMERGENCY
The emergency services provided are integrated with other departments of the hospital.
Administrative In-charges, O.T- They will arrange operation theatres & adequate staff and
supervise the smooth movement of patients in & out of OTs. They will act as an overall coordinator
between medical & paramedical staff & ensure the functionality of the OT & take care of the
condition of their patients.
Duty Administrator- Coordinates with store in-charges & ensure the availability of all the
desirable items. Allot the priorities to the casualties. Interact with CSO & police to maintain calm
in the hospital & instruct the staff to control any unwanted crowd. Keep the interaction for mortuary
& ice requirement.
Nursing Superintendent- Makes immediate arrangements for nursing staff in OTs, Casualty &
wherever needed and supervise the cwill be delivered by them. Check for availability of medicine.
HOD, Department of Anaesthesia- Arranges adequate no. of anaesthetist. Organize OT teams by
name comprising of anaesthetist, OT technicians, Nursing staff, bearers, safai karamchari and allot
their duties. Instruct & ensure that any bullets, arms, missile recovered from the patient & hand
over ultimately to the police after due signatures from the operating surgeon. Keep chief coordinator
informed on hourly basis.
85
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
Pharmacy & Central store- take immediate actions to replenish all the items used in various
wards/ areas. Regularly contact the local suppliers for emergency supply if needed. They keep a
sufficient inventory of vital & essential items as a part of preparedness.
HOD, Imaging Services/ laboratories- check for availability of material like chemicals, films, etc.
look after the maintenance of the equipments & machines like X-ray machine. Prepare CT/ MRI
and immediate investigation as per the needs.
HOD Blood transfusion- ensures adequate availability of all elements of blood. Liase with OT &
casualty for blood demand. Arrange staff for blood grouping & cross matching in Causality/ OT.
Chief Engineer- ensures availability of all maintenance staff (electrician, plumber, masoon, pump
operator, carpenter, etc.) throughout the emergency period. Ensures uninterrupted supply of water,
power & gases.
Chief security officer- controls sudden rush or traffic. Keep a watch that no unwanted elements
are present in the treating area. Instructs his staff to assist casualty staff in unloading & transporting
patients direct the visitors to control room. Coordinate with police & help them in carrying out their
duties.
EXTERNAL AGENCIES ENGAGED
External agencies engaged for risk assessment as well as risk management are:
• Government agencies (for eg. Hospitals, Fire, Police, civil administration, Bomb disposal
squad)
• Non-Government Organizations,
• Private Hospitals,
• International relief agencies etc.
CHAIN OF COMMAND
A chain of command to be followed at the time of Emergency is as follows:
86
“545 Bedded Hospital” at Site no. 2, Zone H-4/5, Facility Centre, Pitampura. New Delhi
By Dr. Narayan Dutt Shrimali Foundation International Charitable Trust Society
Prepared by:-M/s Perfact Enviro Solutions Pvt. Ltd.
SAFETY INSPECTION AND RECORDS:
The Safety Management Officer or Committee may require periodic assessment of the following
inventory:
a. Environmental (lighting, dusts, gases, sprays, noises).
b. Hazardous materials (flammable and caustic).
c. Equipment (biomedical equipment etc.).
d. Power equipment (motors, etc.).
e. Electrical equipment (switches, breakers, fuses, outlets, connections).
f. Hand tools.
g. Personal protective equipment (safety glasses, ventilators, radiation safety aprons etc).
h. Personal service/first aid supplies (Medical Check Up).
i. Fire protection equipment (alarms and extinguishers).
j. Walkways/roadways (sidewalks, roadways).
k. Transportation equipment (Ambulances, lifts).
l. Containers (hazardous waste bags).
m. Structural openings (windows, doors, stairways).
n. Buildings/structures (floors, roofs, planter walls, fences
87