Page 1: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

1

Page 2: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

2

This presentation contains statements that are forward-looking, such as those relating to results of operations and financial

condition, capital spending, financing sources, commodity prices, mineral resources and property evaluation plans and

programmes. Forward-looking statements are frequently characterised by words such as “plan”, “expect”, “project”, ”intend”,

”believe”, ”anticipate” and other similar words, or statements that certain events or conditions “may” or “will” occur.

Forward-looking statements are based on the opinions and estimates of management at the dates the statements are made,

and are subject to a variety of risks and uncertainties and other factors that could cause actual events or results to differ

materially from those projected in the forward-looking statements. The forward-looking statements contained in this document

are as of the date of this document, and are subject to change after this date. Readers are cautioned that the assumptions

used in the preparation of such information, although considered reasonable at the time of preparation, may prove to be

imprecise and, as such, undue reliance should not be placed on forward-looking statements. Euromax disclaims any intention

or obligation to update or revise any forward-looking statements, whether as a result of new information, future events or

otherwise.

Disclaimer

Page 3: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

3

Simple Geology, Simple Mining, Simple processing,

Simple Logistics = AISC US$372/oz

___________________________________________________________

Longevity 20+ year Mine Life = cyclical Gold & Copper exposure

___________________________________________________________

Credibility A Management Team that has done it all before

___________________________________________________________

Comprehensive National, Regional and Local backing

Received EIS Approval

The Euromax Proposition

Simplicity

Introducing the Ilovica-Shtuka Gold-Copper project in Macedonia

Support

Page 4: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

4

Logistics

Project Location

Bor

Chelopech

(Dundee Precious Metals)

Certej (Eldorado Gold)

Rosia Montana (Gabriel Resources)

Skouries (Eldorado Gold)

Timok (Nevsun Resources)

North America

South America

Europe

Africa

Ilovica - Shtuka (Euromax)

Page 5: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

5

Mining in Macedonia

North America

SASA - MK Kamenica

Lead, Zinc and Silver

FENI INDUSTRIES

Rzanovo Mine

Nickel

MINSTROY HOLDING

TORANICA – Kriva Palanka

Lead, Zinc and Silver

MINSTROY HOLDING

ZLETOVO – Probishtip

Lead, Zinc and Silver

LOJANE - Lipkovo

Antimony and Arsenic

STOGOVO - Kichevo

Manganese

Tajmiste - Kischevo

Iron ore

LUKE – Kriva Palanka

Lead, Zinc, Gold, Silver and Copper

EUROMAX RESOURCES

Ilovica-Shtuka

Copper and Gold

BUCHIM - Radovish

Copper, cold and silver mine

BOROV DOL – Konche

Copper, Gold and Silver

KADIICA – Pehchevo

Copper, Gold and Iron

KAZANDOL - Valandovo

Copper and Gold

PLAVICA – Probishtip Kratovo

Gold, Lead and Zink

Operating

Development

Page 6: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

Free Trade

agreements with EU

and EFTA

Government &

Public Support

Tax rate 10%

Excellent infrastructure

World Bank Ease

of Doing Business

6th EU, 12th World

Educated workforce

25% Unemployment

GDP USD 11 billion

Population 2 million

Macedonia

5

Page 7: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

7

Page 8: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

8

Measured &

Indicated Resources

256.8mt @

0.32g/t Au (2.6Moz)

0.21% Cu (1.2Blb)

AuEq 5.4Moz

• Base Line E & S Data Collation

• EIS Approved

• 30 Year Mining Concession Awarded

• Construction Permit Initiated

• All achieved with US$30 million of expenditure

• Inferred Resource ✓

• Preliminary Economic Analysis ✓

• M & I Resource ✓

• Pre-Feasibility Study ✓

• P & P Reserve ✓

• Feasibility Study ✓

• Front End Engineering & Design ✓

Proven &

Probable Reserve

198.1mt @

0.32g/t Au (2.01Moz)

0.21% Cu (898.9Mlb)

(AuEq 0.66 g/t)

AuEq 4.11Moz

Systematic Value Creation

Page 9: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

Mineral Reserve

- 2.01 Million oz Gold

- 898.9 Million lbs Copper

Pre-tax NPV(5%) US$ 513m

IRR: 19.8%

MINE LIFE 20+ YRS

AVG ANNUAL

PRODUCTION

83,000oz Au & 16,000t Cu (AuEq 167,000 oz)

Conc & Dore – Aurubis Offtake

Prices: USD 1,220/oz Au; USD 2.90/lb Cu

Au ADJ. OP. CASH COSTS / ALL-IN COSTS US$ 200/oz /US $372/oz

U S $ 4 7 4 . 3 mi l l ionINITIAL CAPEX ( INC. CONTINGENCY )

Cu ADJ. US$ 0.54/lb / US $0.93/lb

Post-tax NPV(5%) US$ 440m

IRR: 17.8%

9

Feasibility Study – the Value Defined

AFTER TAX PAYBACK PERIOD 4 . 3 Y R S

Page 10: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

10

Initial Capex Summary

Initial Capex Breakdown (US$m)

Mining & Fleet $75.2

Processing Plant $199.6

Owner’s Costs $33.2

Infrastructure $26.0

Tailings Management Facility $42.9

EPCM Contractor $53.2

Temporary Works $3.7

Sub-Total $433.8

Contingency $40.4

Total $474.2

Initial Capex Opportunities

• MOU with EPC Contractor agreed - 2 stage process:

Open Book to Guaranteed Maximum Price; Lump

Sum Turn Key EPC Contract.

• Received 3 bids appetite for Contract Mining,

reducing capex requirements at rates in line with the

Feasibility Study.

• Comminution equipment costs reduced from more

detailed quotes from suppliers.

• Lower infrastructure costs using local quotes and

supply together with reducing foot print.

Financing

US$240m UFK Guaranteed Project Finance

supported by Aurubis offtake

Page 11: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

11

• Resource drilling completed to nominal

50m spacing

• A total of 42,032m have been drilled for

130 drillholes

• Consistent mineralisation and grade

throughout

Measured and Indicated Fresh Mineral Resource Based upon a Dollar Equivalent cut-off of US$16/t

Classification Tonnage (Mt)

Grade Contained Metal

Au

(g/t)

Cu

(%)

Au

(Moz)

Cu

(Mlb)

Measured 147.1 0.31 0.23 1.5 729.500

Indicated 109.7 0.33 0.20 1.1 479.000

Total M & I 256.8 0.32 0.21 2.6 1,208.500

Simple Geology

Page 12: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

12

• Strip Ratio 1:1 – open pit

• Conventional drilling and blasting together

with shovel and trucks supported by a fleet

of ancillary equipment

• Two hydraulic shovels with a fleet of up to

19 rigid dump trucks

Proven and Probable Reserves

Classification Tonnage

Grade Contained Metal

Au

(g/t)

Cu

(%)

Au

(Moz)

Cu

(Mlb)

Probable 112.6 0.30 0.19 0.84 355.0

Proven 85.5 0.32 0.22 1.17 543.9

Total P & P 198.1 0.32 0.21 2.01 898.9

Simple Mining

Page 13: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

13

• 10Mt pa throughput

• Primary gyratory in pit crusher with conveyor from pit to plant

• SAG mill with two ball mills

• Bulk flotation - produces clean concentrate of 24% Cu & 24g/t Au

• CIL on scavenger tails to on-site doré

Simple Processing

Page 14: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

14

• Road Transportation (A3 Motorway) directly to the

Pirdop smelter at costs of US$26.4 per tonne of

concentrate

• 60,000 – 100,000 tpa concentrate production

using 30t trucks

• 300km / 4-5 hour Journey time

Simple Logistics

Page 15: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

15

Steve Sharpe, President & CEO

• +30 years in investment banking, focused on the mining sector in

Europe & The Americas.

• Senior management positions at European Goldfields,

Canaccord, Endeavour Financial, Standard Bank, and NM

Rothschild & Sons Ltd.

Tim Morgan-Wynne, Non-Executive Director

• Previously CFO at European Goldfields and Director of

Resources and Energy Group at HSBC Bank plc.

• Experience in financing projects: Europe, North America, Africa.

Varshan Gokool, CFO

• Extensive project finance experience.

• Corporate and banking background, including European

Goldfields, Treasurer at Katanga Mining Limited, Vice President

in Societe Generale's Mining Finance team.

Randy Matkaluk, Non-Executive Director

• CFO of privately owned oil and gas company Capio Exploration

Ltd.

• Director at Triangle Petroleum Corp.

Patrick Forward, COO

• +25 years global experience in project development and

execution: exploration, managing engineering studies up to

detailed engineering, operational management.

• Qualified Person for NI 43-101 reporting.

• Formerly VP head of projects at European Goldfields.

Bill Abel, Non-Executive Director

• +40 years of senior professional experience at major

international mining companies.

• Specialty in operations, management and project development

and implementation.

Martyn Konig, Non-Executive Chairman

• +30 years’ experience in banking and commodities.

• Non-Executive Director of New Gold Inc. and Chairman of

Nyrstar.

Raymond Threlkeld, Non-Executive Director

• +30 years’ experience in mineral industry.

• Currently Executive Chairman of Newmarket Gold Inc., Non-

Executive Director of New Gold Inc.

A Wealth of Experience

Page 16: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

16

Next Steps

Technical Development – Expected Completion end of Q3 2017

• Incorporate Ag into Resource

• Initiate stage 1 of EPC Process – Guarantee Maximum Price

• Complete Mining Contract negotiation

• Issue Optimised Technical Report – June 2017

Permitting – Expected completion Q3 2017

• International ESIA – March 2017

• Process Main Mining Project through approval steps

• Complete Land Acquisition and urbanisation process

Page 17: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

17

Production

Years 1-5 6-10 11-23

Avg Annual

Production

Au (oz/yr) 103,000 90,800 67,700

Cu (t/yr) 20,800 16,800 13,300

Total AuEq (oz/yr) 212,000 179,800 137,700

Cash Flows by Period (Au US$ 1220 /oz, Cu US$ 2.90 /lb)

Years 1-5 6-10 11-23

Average Annual

Operating Cashflow Post Tax$112 million $84 million $24 million

Total Operating Cashflow Post Tax $560 million $420 million $323 million

Cashflow Profile – Returning The Value

Food for thought: EOX Market Cap C$79 million (US$59 million)

Average Annual Operating Cashflow yrs 1-5 = US$112 million per annum

1 AuEq calculation also includes payable silver in concentrate.

2 There is no production in years 21-23 but there are cash flows incurred associated with closure and salvage.

Page 18: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

18

Value Gap: TSX Listed and Construction Ready

$0

$200,000

$400,000

$600,000

$800,000

$1,000,000

$1,200,000

0

50,000

100,000

150,000

200,000

250,000

300,000

1 2 3 4 5 6 7 8 9 10

Cu

mu

lative Op

erating C

ash Flo

w in

US'0

00

Go

ld E

qu

ival

en O

un

ces

Production vs Cumulative Operating Cash FlowGold Gold Equivalent Copper Operating Cash Flow

Market Capitalization (MC) C$79M or US$59M

Operating Cash Flow (OCF) US$98M average, Yr 1-10

Multiple: MC / OCF = 0.6x in each of years 1-10

Page 19: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

19

C$ 57 M

C$ 0.47

C$ 0.81

C$ 0.38

120.3 M

181 M

19.4%

18.6%

11.3%

7.7%

6.9%

Capitalization Overview

Market cap

Closing price (28 June 17)

52 Week High

52 Week Low

Shares Basic

Shares Fully Diluted

Major Shareholders

EBRD

Richard Griffiths

Richmond Capital

Investec Bank Plc

Management

Holding

Share price against Market Vector

Junior Gold Miners Index

GDXJEOX

Research Coverage:

CIBC, Peel Hunt, Echelon Wealth Partners, Edison

Corporate Information

Page 20: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

20

Simple Geology, Simple Mining, Simple processing,

Simple Logistics = AISC US$372/oz

___________________________________________________________

Longevity 20+ year Mine Life = cyclical Gold & Copper exposure

___________________________________________________________

Credibility A Management Team that has done it all before

___________________________________________________________

Comprehensive National, Regional and Local backing

Received EIS Approval

All Free Cash Flow Returned to Shareholders

Euromax: Executing on Value Creation at Ilovica-Shtuka

Simplicity

Support

Page 21: “plan”,“expect”,“project”,”intend”, · Certej (Eldorado Gold) Rosia Montana (Gabriel Resources) Skouries (Eldorado Gold) Timok (Nevsun Resources) North America South

21

`

Steven L C SharpePresident & CEO

[email protected]

Varshan GokoolChief Financial Officer

[email protected]

Pat ForwardChief Operating Officer

[email protected]

www.euromaxresources.com