Date post: | 12-Apr-2018 |
Category: |
Documents |
Upload: | duongkhanh |
View: | 220 times |
Download: | 3 times |
1
ETHEKWINI MUNICIPALITY
FIBRE OPTIC
INSTALLATION OF COMMUNICATION TUBING FOR UNDERGROUND FIBRE OPTIC
INSTALLATION OF UNDERGROUND FIBRE
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
Version 3
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
Part 1
INSTALLATION OF COMMUNICATION TUBING FOR UNDERGROUND FIBRE OPTIC
CABLE
Part 2
UNDERGROUND FIBRE OPTIC CABLE INTO COMMUNICATION
TUBING
ETHEKWINI MUNICIPALITY
ETHEKWINI MUNICIPALITY
INSTALLATION OF COMMUNICATION TUBING FOR UNDERGROUND FIBRE OPTIC
INTO COMMUNICATION
2
INSTALLATION OF COMMUNICATION TUBING FOR
UNDERGROUND FIBRE OPTIC CABLE
1. INTRODUCTION
1.1 Scope
This document details the requirements for the installation of underground communication
tubes to house fibre optic communication cables.
This includes the installation of the manholes along the route, which are required to
facilitate the future pulling
maintenance.
1.2 Order of Description
This order of description for this part of the standard is as follows:
• Definitions
• Specification of Materials
• Laying Communication Tubes for Underground Fibre Optic Links
• Handover Requirements After Laying of Communication Tubes
Specifications for these components of the Fibre Optic System follows:
2. DEFINITIONS
Communication Tubes: The underground tubing, as
through which fibre optic cable is pulled for the establishment of communication links between two
points.
Communication Manholes: The manholes, which are either designed for use within a pavement
area or for use within the roadway itself, which are situated along a route and connected by
communication tubes.
Fibre Communication Panel (FCP):
terminated into a patch tray, and made availab
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
Version 3
PART 1
TECHNICAL SPECIFICATION FOR
INSTALLATION OF COMMUNICATION TUBING FOR
UNDERGROUND FIBRE OPTIC CABLE
This document details the requirements for the installation of underground communication
tubes to house fibre optic communication cables.
This includes the installation of the manholes along the route, which are required to
facilitate the future pulling-in of fibre optic cable and for future fault finding and
This order of description for this part of the standard is as follows:
Definitions
Specification of Materials
Laying Communication Tubes for Underground Fibre Optic Links
Handover Requirements After Laying of Communication Tubes
Specifications for these components of the Fibre Optic System follows:
The underground tubing, as specified by the MetroConnect
through which fibre optic cable is pulled for the establishment of communication links between two
The manholes, which are either designed for use within a pavement
area or for use within the roadway itself, which are situated along a route and connected by
Fibre Communication Panel (FCP): The panel within a substation where the fibre optic cable is
terminated into a patch tray, and made available for optical connection to various optical
ETHEKWINI MUNICIPALITY
INSTALLATION OF COMMUNICATION TUBING FOR
This document details the requirements for the installation of underground communication
This includes the installation of the manholes along the route, which are required to
in of fibre optic cable and for future fault finding and
Laying Communication Tubes for Underground Fibre Optic Links
Handover Requirements After Laying of Communication Tubes
Specifications for these components of the Fibre Optic System follows:
MetroConnect Engineer,
through which fibre optic cable is pulled for the establishment of communication links between two
The manholes, which are either designed for use within a pavement
area or for use within the roadway itself, which are situated along a route and connected by
The panel within a substation where the fibre optic cable is
le for optical connection to various optical
3
equipment.
Manhole Ball Markers: A device which is attached to the inside of a manhole cover, which
together with a sensor carried by an operator, is used to pinpoint the exact location of the manhole
beneath the surface of the ground.
3. SPECIFICATION OF MATERIALS
The materials include Tubing, Manholes and Manhole Ball markers. Details of the materials to be
used are as follows:
3.1. Specification of Communication Tubes
Communication Tubing
underground communication route must be
(HDPE) tubing with rodent repellent additives
Sections of HDPE tubing must be joined using water
3.2. Specification of Communication Manholes
Manholes within roadways are to be of precast concrete or brick, and
constructed and installed according to
specification.
Manhole covers must be polymer
3.3. Specification of Manhole Ball Markers to Pinpoint Communication Manholes
New technology location devices/ antennae /ball markers
be hung inside each manh
completed.
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
Version 3
A device which is attached to the inside of a manhole cover, which
together with a sensor carried by an operator, is used to pinpoint the exact location of the manhole
the surface of the ground.
SPECIFICATION OF MATERIALS
The materials include Tubing, Manholes and Manhole Ball markers. Details of the materials to be
Specification of Communication Tubes
Communication Tubing installed between the last manhole positions on each side of an
underground communication route must be 110mm, cream, hard drawn polyetherlene
(HDPE) tubing with rodent repellent additives (DN110).
Sections of HDPE tubing must be joined using water-tight pipe couplers.
Specification of Communication Manholes
Manholes within roadways are to be of precast concrete or brick, and
constructed and installed according to the City Engineering Unit’
Manhole covers must be polymer in construction and be lockable.
Specification of Manhole Ball Markers to Pinpoint Communication Manholes
New technology location devices/ antennae /ball markers (3M code 14014 orange)
be hung inside each manhole and used to locate manholes after construction has been
ETHEKWINI MUNICIPALITY
A device which is attached to the inside of a manhole cover, which
together with a sensor carried by an operator, is used to pinpoint the exact location of the manhole
The materials include Tubing, Manholes and Manhole Ball markers. Details of the materials to be
installed between the last manhole positions on each side of an
, hard drawn polyetherlene
tight pipe couplers.
Manholes within roadways are to be of precast concrete or brick, and are to be located,
ing Unit’s requirements and
Specification of Manhole Ball Markers to Pinpoint Communication Manholes
(3M code 14014 orange) are to
ole and used to locate manholes after construction has been
4. INSTALLATION OF COMMUNICATION TUBING ROUTES
This includes the installation of the communication tubing itself, the communication
manholes and the ball markers.
Please read ANNEXURE A: EXCAVATION CODE OF PRACTICE
4.1. Excavation and laying of Communication Tubing
The Contractor shall be responsible for all trenching excavations unless specified to the contrary.
The Contractor shall, before trenching commsite conditions. The procedure and order of doing the work shall be planned in conjunction with the general construction program for other services and building requirements.
The Contractor shall acquaint himstorm water pipes, water mains, sewer mainnecessary Wayleaves etc.shall approach the appropriate Municipal authority and any other authority which may be involved. Special attention is drawn to GAS and PETROL pipelines that does not belong to Ethekwini Municipality.
The Contractor will be held responsible for damage to any existing services brought to his attention by the MetroConnect
The Contractor shall take all the necessary precautions Construction Regulations. The contractor shalland/or lights in accordance with the City Engineers specification for signage at roadworks to ensure that the public and/or employees on site are not endangereProvision must also be made for reasonable, continuous and all weather pedestrian access with due regard for pedestrian safety.
The Contractor shall ensure that the excavations will not endanger existing structures, roads, railways, other site construcendanger motorists or pedestrians. In such instances where it is proposed to use an existing bridge structure to carry ducting, approval in writing shall be soughtProvision Department, Structures Branch. be cut, cored, or modified in any way without prior approval from the Roads Provision Department.
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
4
INSTALLATION OF COMMUNICATION TUBING ROUTES
This includes the installation of the communication tubing itself, the communication
manholes and the ball markers.
ANNEXURE A: EXCAVATION CODE OF PRACTICE carefully.
Excavation and laying of Communication Tubing
The Contractor shall be responsible for all trenching excavations unless specified to the
The Contractor shall, before trenching commences, familiarize himself with the routes and he procedure and order of doing the work shall be planned in conjunction
with the general construction program for other services and building requirements.
The Contractor shall acquaint himself with the position of all the existing services such as storm water pipes, water mains, sewer mains, gas pipes, telephone cables
etc. before any excavations are commenced. For this purpose he shall approach the appropriate Municipal authority and any other authority which may be involved. Special attention is drawn to GAS and PETROL pipelines that does not belong to
The Contractor will be held responsible for damage to any existing services brought to his MetroConnect Engineer and shall be responsible for the cost of repairs.
The Contractor shall take all the necessary precautions in terms of thConstruction Regulations. The contractor shall provide the necessary warning signs
in accordance with the City Engineers specification for signage at to ensure that the public and/or employees on site are not endangere
Provision must also be made for reasonable, continuous and all weather pedestrian access with due regard for pedestrian safety.
The Contractor shall ensure that the excavations will not endanger existing structures, roads, railways, other site constructions or other property. Excavations should also not endanger motorists or pedestrians.
In such instances where it is proposed to use an existing bridge structure to carry ducting, approval in writing shall be sought by the ContractorProvision Department, Structures Branch. Under no circumstance shall the structure be cut, cored, or modified in any way without prior approval from the Roads Provision Department.
ETHEKWINI MUNICIPALITY
This includes the installation of the communication tubing itself, the communication
carefully.
The Contractor shall be responsible for all trenching excavations unless specified to the
ences, familiarize himself with the routes and he procedure and order of doing the work shall be planned in conjunction
with the general construction program for other services and building requirements.
self with the position of all the existing services such as s, gas pipes, telephone cables and obtain the
before any excavations are commenced. For this purpose he shall approach the appropriate Municipal authority and any other authority which may be involved. Special attention is drawn to GAS and PETROL pipelines that does not belong to
The Contractor will be held responsible for damage to any existing services brought to his Engineer and shall be responsible for the cost of repairs.
in terms of the OHS Act and provide the necessary warning signs
in accordance with the City Engineers specification for signage at to ensure that the public and/or employees on site are not endangered.
Provision must also be made for reasonable, continuous and all weather pedestrian
The Contractor shall ensure that the excavations will not endanger existing structures, Excavations should also not
In such instances where it is proposed to use an existing bridge structure to carry by the Contractor with the Roads
Under no circumstance shall the structure be cut, cored, or modified in any way without prior approval from the Roads
Trenches shall connect the points in a straight line. Any existing services will need the
The MetroConnect Engineer reserves the right to alter any cable route or portion thereof in advance of cable laying. The removal of obstructionMetroConnect Engineer. Cable trenches for one or two 110 mm Sleeves shall not be less than 300 mm wide and need not be more than 450 mm wide. These dimensions must be maintained for the entitrench depth.
The width shall be increased where more sleeves are installemm between sleeves.
Sleeves will be installed at a minimum depth of and 1metre in roadwaysthe laid sleeve. The Contractor may need to adjust trench depths to accommodate bedding where required.require written permission from the Roads Department which shall the Contractor. The padding and bedding materials will be sieved to a maximum The backfill will be excavated material, large objects may not be dumped into the trench. Removal of rubble is the respon Re-instatement of asphaltedStormwater Maintenancedocumentation by the Contractor to ensure that trenches are repaired timeously.
All trench depth measurements shall be made to the top of the sleeve when laid, ready for backfill.
The MetroConnect Engineer reserves the right to inspect the installation at any stage during the course of construction. Such inspections will, however, not deem the portions inspected as being complete or accepted and the Contractor shall remain responsible for completing the installation fully in accordance with the Contract Documents.
4.2. Laying of Communication Tubes within
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
5
Trenches shall connect the points in a straight line. Any deviations due to obstructions or need the prior approval of the MetroConnect Engineer.
Engineer reserves the right to alter any cable route or portion thereof in advance of cable laying. The removal of obstructions along the cable routes shall be subject to the approval of the
Engineer.
Cable trenches for one or two 110 mm Sleeves shall not be less than 300 mm wide and need not be more than 450 mm wide. These dimensions must be maintained for the enti
The width shall be increased where more sleeves are installed to allow for spacing of 50
Sleeves will be installed at a minimum depth of 600 mm on sidewalks and verges, and 1metre in roadways, measured from surface level to the most upper surface of the laid sleeve. The Contractor may need to adjust trench depths to accommodate bedding where required. Trench depths below the minimum specification shall
ssion from the Roads Department which shall
The padding and bedding materials will be sieved to a maximum aggregate
The backfill will be excavated material, large objects may not be dumped
Removal of rubble is the responsibility of the Contractor.
asphalted and paved areas will be done by Roads DepartmentStormwater Maintenance, unless otherwise agreed. Submission of the necessary
by the Contractor for permanent road reinstatement must bto ensure that trenches are repaired timeously.
All trench depth measurements shall be made to the top of the sleeve when laid, ready for
Engineer reserves the right to inspect the installation at any stage the course of construction. Such inspections will, however, not deem the portions
inspected as being complete or accepted and the Contractor shall remain responsible for completing the installation fully in accordance with the Contract Documents.
Laying of Communication Tubes within Electricity Substation Perimeters
ETHEKWINI MUNICIPALITY
deviations due to obstructions or Engineer.
Engineer reserves the right to alter any cable route or portion thereof in
s along the cable routes shall be subject to the approval of the
Cable trenches for one or two 110 mm Sleeves shall not be less than 300 mm wide and need not be more than 450 mm wide. These dimensions must be maintained for the entire
d to allow for spacing of 50
on sidewalks and verges, level to the most upper surface of
the laid sleeve. The Contractor may need to adjust trench depths to accommodate Trench depths below the minimum specification shall
ssion from the Roads Department which shall be acquired by
aggregate size of 10 mm.
The backfill will be excavated material, large objects may not be dumped and compacted
ill be done by Roads Department & , unless otherwise agreed. Submission of the necessary
for permanent road reinstatement must be prompt
All trench depth measurements shall be made to the top of the sleeve when laid, ready for
Engineer reserves the right to inspect the installation at any stage the course of construction. Such inspections will, however, not deem the portions
inspected as being complete or accepted and the Contractor shall remain responsible for completing the installation fully in accordance with the Contract Documents.
Substation Perimeters
Two tubes as specified in Section 3.1 are to be laid unless otherwise specified by the
MetroConnect Project Engineer.
Where communication tubes are to be installed into the same tren
laying of supply cables, the tubes must be laid at the same depth as the supply cables.
There should be some spacing between the tubes and the cables to prevent excessive
heating of the communication tubes in the event of a fault occur
Tubes may be laid together with copper pilot cables.
Where trenching is specifically for the installation of communication tubes, the two tubes as
specified in Section 3.1 must be bu
entire route.
Tubes laid within substations must be laid within the substation trenches, where practical.
Where large bending radii permit, the above HDPE tubing may also be installed from the
last manhole position into the trench inside a substation building. If the required bends into
the substation building are too tight for the HDPE, or where the route terminates into an
FCP, then corrugated 50mm diameter DN50 Kabelflex conduit mentioned in Section
must be used for the last section of the link. (Stock Code 101048
stores).
Correct water-tight pipe couplers between sections of communication tubing (Stock code
105171 available from Electricity stores
mud. Connections between HDPE and DN50 Kabelflex must also be water
4.3. Laying of Communication Tubes into same Trenches opened
services
Where communication tubes are to be installed into the
laying of other utility services (new water pipes/new electrical cables), the tubes must be
laid at the same depth as the other utility services. There should be some spacing
between the tubes and the existing cables to preven
communication tubes in the event of a fault occurring in the electrical cable. Tubes may be
laid together with copper pilot cables.
4.4. Installation of Communication Manholes
Communication manholes, as specified in Section 3.
less. Manholes are also to be installed where the cable bends beyond 30 degrees.
Communication tubes must be well sealed at entry/ exit points of the manhole. All tubing
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
6
Two tubes as specified in Section 3.1 are to be laid unless otherwise specified by the
Project Engineer.
Where communication tubes are to be installed into the same tren
laying of supply cables, the tubes must be laid at the same depth as the supply cables.
There should be some spacing between the tubes and the cables to prevent excessive
heating of the communication tubes in the event of a fault occurring in the supply cable.
Tubes may be laid together with copper pilot cables.
Where trenching is specifically for the installation of communication tubes, the two tubes as
specified in Section 3.1 must be buried not less than 0,8m deep (preferably 1m) for the
Tubes laid within substations must be laid within the substation trenches, where practical.
Where large bending radii permit, the above HDPE tubing may also be installed from the
ole position into the trench inside a substation building. If the required bends into
the substation building are too tight for the HDPE, or where the route terminates into an
FCP, then corrugated 50mm diameter DN50 Kabelflex conduit mentioned in Section
must be used for the last section of the link. (Stock Code 101048 available from Electricity
tight pipe couplers between sections of communication tubing (Stock code
available from Electricity stores) must be used to prevent ingress of moisture and
mud. Connections between HDPE and DN50 Kabelflex must also be water
Laying of Communication Tubes into same Trenches opened
Where communication tubes are to be installed into the same trenches opened for the
laying of other utility services (new water pipes/new electrical cables), the tubes must be
laid at the same depth as the other utility services. There should be some spacing
between the tubes and the existing cables to prevent excessive heating of the
communication tubes in the event of a fault occurring in the electrical cable. Tubes may be
laid together with copper pilot cables.
Installation of Communication Manholes
Communication manholes, as specified in Section 3.2 are to be placed at 200m intervals or
less. Manholes are also to be installed where the cable bends beyond 30 degrees.
Communication tubes must be well sealed at entry/ exit points of the manhole. All tubing
ETHEKWINI MUNICIPALITY
Two tubes as specified in Section 3.1 are to be laid unless otherwise specified by the
Where communication tubes are to be installed into the same trenches opened for the
laying of supply cables, the tubes must be laid at the same depth as the supply cables.
There should be some spacing between the tubes and the cables to prevent excessive
ring in the supply cable.
Where trenching is specifically for the installation of communication tubes, the two tubes as
ried not less than 0,8m deep (preferably 1m) for the
Tubes laid within substations must be laid within the substation trenches, where practical.
Where large bending radii permit, the above HDPE tubing may also be installed from the
ole position into the trench inside a substation building. If the required bends into
the substation building are too tight for the HDPE, or where the route terminates into an
FCP, then corrugated 50mm diameter DN50 Kabelflex conduit mentioned in Section 3.1
available from Electricity
tight pipe couplers between sections of communication tubing (Stock code
prevent ingress of moisture and
mud. Connections between HDPE and DN50 Kabelflex must also be water-tight.
Laying of Communication Tubes into same Trenches opened for other Utility
same trenches opened for the
laying of other utility services (new water pipes/new electrical cables), the tubes must be
laid at the same depth as the other utility services. There should be some spacing
t excessive heating of the
communication tubes in the event of a fault occurring in the electrical cable. Tubes may be
2 are to be placed at 200m intervals or
less. Manholes are also to be installed where the cable bends beyond 30 degrees.
Communication tubes must be well sealed at entry/ exit points of the manhole. All tubing
ends within the manhole must be sealed wit
4.5. Installation of Ball Markers
Communication Ball Markers as specified in Section 3.3 must be hung from the inside of
the manhole cover to facilitate the future location of all joints and manholes. The
Communication Ball Marker must be attached close to the lid where it may be detected,
with rot resistant nylon fibre string. Alternatively it may be attached via a cabletie onto a
short loop of galvanised wire made to protrude into the manhole and secured at the time
when the lids are filled with cemented.
4.6. Joining between Communication Tubing and overhead Optical ground Wire
(OPGW).
There may be instances where the route requires a sections or sections which are
overhead. This requires a joint between communication tubes and overhead Optical
Ground Wire (OPGW).
In these instances the approved stainless steel dome
top of a vertically installed 2m high, 50mm diameter stainless steel pipe buried 0,8m into
the ground. The pipe must be secured to the inside of the tower leg/ just off the gantry or
pylon leg, using an approved stainle
Sufficient additional OPGW slack is to be coiled and secured above the Anti
on the OPGW side of the joint prior to splicing, to enable the joint to be worked on at least
5m from the base of the tower/ gantry.
Where HDPE is run to the joint position and not DN kabelflex, a length of DN50 Kabelflex
tubing must be joined to the HDPE tubing, which will be inserted into the base of the
stainless steel pipe during the splicing process. Joints must be taped with self
amalgamating rubber tape to prevent the ingress of moisture and sand. Approximately 5m
of DN50 Kabelflex slack must be retained at the base of the stainless steel tube.
5. HANDOVER REQUIREMENTS AND PROCEDURES
The following paperwork must be completed and han
Engineer before handover and b
Careful attention must be made to Annexure C, which outlines the format of the GIS data
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
7
ends within the manhole must be sealed with the proper supplier's endcaps.
Installation of Ball Markers
Communication Ball Markers as specified in Section 3.3 must be hung from the inside of
the manhole cover to facilitate the future location of all joints and manholes. The
Ball Marker must be attached close to the lid where it may be detected,
with rot resistant nylon fibre string. Alternatively it may be attached via a cabletie onto a
short loop of galvanised wire made to protrude into the manhole and secured at the time
hen the lids are filled with cemented.
Joining between Communication Tubing and overhead Optical ground Wire
There may be instances where the route requires a sections or sections which are
overhead. This requires a joint between communication tubes and overhead Optical
In these instances the approved stainless steel dome jointboxes must be mounted onto the
top of a vertically installed 2m high, 50mm diameter stainless steel pipe buried 0,8m into
the ground. The pipe must be secured to the inside of the tower leg/ just off the gantry or
pylon leg, using an approved stainless steel bracket.
Sufficient additional OPGW slack is to be coiled and secured above the Anti
on the OPGW side of the joint prior to splicing, to enable the joint to be worked on at least
5m from the base of the tower/ gantry.
s run to the joint position and not DN kabelflex, a length of DN50 Kabelflex
tubing must be joined to the HDPE tubing, which will be inserted into the base of the
stainless steel pipe during the splicing process. Joints must be taped with self
g rubber tape to prevent the ingress of moisture and sand. Approximately 5m
of DN50 Kabelflex slack must be retained at the base of the stainless steel tube.
HANDOVER REQUIREMENTS AND PROCEDURES
The following paperwork must be completed and handed over to the
Engineer before handover and before payment may be authorized.
Careful attention must be made to Annexure C, which outlines the format of the GIS data
ETHEKWINI MUNICIPALITY
h the proper supplier's endcaps.
Communication Ball Markers as specified in Section 3.3 must be hung from the inside of
the manhole cover to facilitate the future location of all joints and manholes. The
Ball Marker must be attached close to the lid where it may be detected,
with rot resistant nylon fibre string. Alternatively it may be attached via a cabletie onto a
short loop of galvanised wire made to protrude into the manhole and secured at the time
Joining between Communication Tubing and overhead Optical ground Wire
There may be instances where the route requires a sections or sections which are
overhead. This requires a joint between communication tubes and overhead Optical
jointboxes must be mounted onto the
top of a vertically installed 2m high, 50mm diameter stainless steel pipe buried 0,8m into
the ground. The pipe must be secured to the inside of the tower leg/ just off the gantry or
Sufficient additional OPGW slack is to be coiled and secured above the Anti-climbing gear
on the OPGW side of the joint prior to splicing, to enable the joint to be worked on at least
s run to the joint position and not DN kabelflex, a length of DN50 Kabelflex
tubing must be joined to the HDPE tubing, which will be inserted into the base of the
stainless steel pipe during the splicing process. Joints must be taped with self
g rubber tape to prevent the ingress of moisture and sand. Approximately 5m
of DN50 Kabelflex slack must be retained at the base of the stainless steel tube.
ver to the MetroConnect Project
Careful attention must be made to Annexure C, which outlines the format of the GIS data
that needs to be submitted to the
of the ‘as-built’ documentation.
5.1 Documentation of Route
The entire tubing route, all manhole
co-ordinates marked on the associated
Office for capture into the drawing office database, to facilitate future fault location.
A copy of the final ‘as-built' drawing and the completed "Communication Tubing Handover
Form" form detailed in ANNEXURE
Engineer/ Supervisor overseeing the installation and to the
Telecommunications.
5.2 Completion of Communication Tubing Handover Form
The contractor/ cable layer is to ensure and confirm that the tubes have been laid
according to the specifications and any additional requirements stipulated by the
MetroConnect Office/Project Engineer.
The "Communication Tubing Handover Form" detailed in
completed and returned to the appointed Clerk of Works/
after completion and at handover of the work.
.
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
8
that needs to be submitted to the MetroConnect Project Engineer. This nee
built’ documentation.
Documentation of Route
The entire tubing route, all manholes and all joint positions must be properly surveyed and
ordinates marked on the associated Drawing Plans and forwarded to the
for capture into the drawing office database, to facilitate future fault location.
built' drawing and the completed "Communication Tubing Handover
Form" form detailed in ANNEXURE B must be forwarded by the
Engineer/ Supervisor overseeing the installation and to the Deputy Head: Networks and
Completion of Communication Tubing Handover Form
The contractor/ cable layer is to ensure and confirm that the tubes have been laid
according to the specifications and any additional requirements stipulated by the
MetroConnect Office/Project Engineer.
"Communication Tubing Handover Form" detailed in ANNEXURE
completed and returned to the appointed Clerk of Works/ Project leader of
after completion and at handover of the work.
ETHEKWINI MUNICIPALITY
Project Engineer. This needs to form part
and all joint positions must be properly surveyed and
and forwarded to the MetroConnect
for capture into the drawing office database, to facilitate future fault location.
built' drawing and the completed "Communication Tubing Handover
must be forwarded by the MetroConnect Project
Deputy Head: Networks and
The contractor/ cable layer is to ensure and confirm that the tubes have been laid
according to the specifications and any additional requirements stipulated by the
ANNEXURE B shall be
Project leader of MetroConnect
ETHEKWINI MUNICIPALITY
ANNEXURE A: EXCAVATION CODE OF PRACTICE
1. Excavation, Backfilling and Reinstatement of Trenches within Road Reserve Areas
1.1 Excavation of Trenches
1.2 Suitable backfill material
1.3 Use of the “Dynamic Core Penetrometer” (D.C.P) and Test Requirements
1.4 Compacting the trench bottom
1.5 Initial backfill (Blinding)
1.5.1 Initial Test using D.C.P
1.6 Final Backfilling
1.6.1 Final Test using D.CP
1.7 Trenches in verge areas
1.8 Responsibility for maintenance of the trench and final reinstatement
1.9 Surplus material
1.10 Service Related structures
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
9
ANNEXURE A: EXCAVATION CODE OF PRACTICE
Reinstatement of Trenches within Road Reserve Areas
Suitable backfill material
Use of the “Dynamic Core Penetrometer” (D.C.P) and Test Requirements
Compacting the trench bottom
Trenches in verge areas
Responsibility for maintenance of the trench and final reinstatement
Service Related structures
ETHEKWINI MUNICIPALITY
Reinstatement of Trenches within Road Reserve Areas
Use of the “Dynamic Core Penetrometer” (D.C.P) and Test Requirements
ETHEKWINI MUNICIPALITY
EXCAVATION, BACKFILLING AND REINSTATEMENT OF TRENCHES WITHIN ROAD
The procedures outlined are to be followed whenever trenches within road reserve areas are
reinstated, irrespective of the work being carried out by contract labour or by depart
personnel.
1.1 Excavation of trenches within road reserve
(a) Trench-less technology methods for road crossings shall be explored
Contractor prior to trenchin
permission must be sought
Maintenance Department
(b) Prior to any excavation taking place through hardened surfaces, the proposed
trench width shall be marked
Contractor.
(c) The minimum depth of any trench should be not less than
sidewalks and verges, and 1metre in roadways
requirement must first be authorised by the Roads & Stormwater Maintenance
Department by the
(d) In areas covered with special pavers through which trenching is required, the
existing paving shall be carefully removed and stored safely and securely for
re-use. This will minimize the need for obtaining new materials to match the
existing.
(e) In areas where the proposed trench falls within existing works that are being
undertaken by any other service provider, it shall be necessary for the
responsible official from eThekwini Municipality
interact with such servi
purposes.
(f) In areas where the proposed trench traverses through established flowerbeds,
gardens and grassed sections, it shall be necessary for the responsible official
from eThekwini Municipality
owners or relevant authority, prior to any work commencing.
(g) In developed and CBD areas, all property owners and businesses shall be
informed by the Contractor
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
10
EXCAVATION, BACKFILLING AND REINSTATEMENT OF TRENCHES WITHIN ROAD
RESERVE AREA
The procedures outlined are to be followed whenever trenches within road reserve areas are
reinstated, irrespective of the work being carried out by contract labour or by depart
within road reserve
less technology methods for road crossings shall be explored
prior to trenching. This must be considered only as a last resort and
permission must be sought by the Contractor from the Roads & Stormwater
Maintenance Department before proceeding with any work.
Prior to any excavation taking place through hardened surfaces, the proposed
trench width shall be marked and saw cut by mechanical means by the
The minimum depth of any trench should be not less than
sidewalks and verges, and 1metre in roadways. Any deviation from this
requirement must first be authorised by the Roads & Stormwater Maintenance
by the Contractor.
In areas covered with special pavers through which trenching is required, the
existing paving shall be carefully removed and stored safely and securely for
use. This will minimize the need for obtaining new materials to match the
In areas where the proposed trench falls within existing works that are being
undertaken by any other service provider, it shall be necessary for the
responsible official from eThekwini Municipality and the Contractor
interact with such service providers for co-ordination and reinstatement
In areas where the proposed trench traverses through established flowerbeds,
gardens and grassed sections, it shall be necessary for the responsible official
from eThekwini Municipality and the Contractor to liaise and interact with the
owners or relevant authority, prior to any work commencing.
In developed and CBD areas, all property owners and businesses shall be
by the Contractor of the proposed works prior to any work
ETHEKWINI MUNICIPALITY
EXCAVATION, BACKFILLING AND REINSTATEMENT OF TRENCHES WITHIN ROAD
The procedures outlined are to be followed whenever trenches within road reserve areas are
reinstated, irrespective of the work being carried out by contract labour or by department
less technology methods for road crossings shall be explored by the
be considered only as a last resort and
from the Roads & Stormwater
Prior to any excavation taking place through hardened surfaces, the proposed
and saw cut by mechanical means by the
The minimum depth of any trench should be not less than 600 mm on
Any deviation from this
requirement must first be authorised by the Roads & Stormwater Maintenance
In areas covered with special pavers through which trenching is required, the
existing paving shall be carefully removed and stored safely and securely for
use. This will minimize the need for obtaining new materials to match the
In areas where the proposed trench falls within existing works that are being
undertaken by any other service provider, it shall be necessary for the
and the Contractor to liaise and
ordination and reinstatement
In areas where the proposed trench traverses through established flowerbeds,
gardens and grassed sections, it shall be necessary for the responsible official
to liaise and interact with the
In developed and CBD areas, all property owners and businesses shall be
of the proposed works prior to any work
ETHEKWINI MUNICIPALITY
commencing.
(h) All road/lane closures must first be authorised by the Ethekwini Transport
Authority & the Durban Metro
Correct reinstatement by the Contractor
subsidence, but in the case
Footpaths etc.,) extra special attention must be paid
method of “compacted layered” backfill.
Strict adherence to the procedures given in this Section will ensure the sa
temporary reinstatement of the trench, leading to early permanent reinstatement by
the appropriate authority.
2 Suitable Backfill Material
(a) General backfill can be carried out by using the material excavated from the
trench, provided that:
(i) it is easily workable and compactable
(ii) it is free from organic material (roots, grass etc) rubbish, clay lumps and
aggregates larger than 50 mm stones in diameter.
(iii) the material is suitable, is not water saturated or too dry. Should the
material be too dry, it will be moistened prior to placing and compacting.
(b) In the immediate vicinity of the duct or cable both below and up to a height of
300mm above, stone
suitable due to their high thermal resistivity).
(c) If the site materials cannot meet these requirements suitable material must be
imported.
1.3 Use of “Dynamic Core Penetrometer” (D.C.P)
(a) To ensure that the required compaction of the trench has been achieved, tests
must be carried out
(b) The tests are carried out using a D.C.P which consists of a metal rod with a
cone-shaped end with an anvil onto whic
distance. (Drawing No.:1)
(c) The cone-shaped end of the rod is placed on the
is raised to the pre
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
11
All road/lane closures must first be authorised by the Ethekwini Transport
Authority & the Durban Metro Police by the Contractor.
by the Contractor of all trench work is necessary to prevent
subsidence, but in the case of trenches within hardened surfaces i.e. (Roadways,
Footpaths etc.,) extra special attention must be paid by the Contractor
method of “compacted layered” backfill.
Strict adherence to the procedures given in this Section will ensure the sa
temporary reinstatement of the trench, leading to early permanent reinstatement by
the appropriate authority.
Suitable Backfill Material
General backfill can be carried out by using the material excavated from the
trench, provided that:
it is easily workable and compactable
it is free from organic material (roots, grass etc) rubbish, clay lumps and
aggregates larger than 50 mm stones in diameter.
the material is suitable, is not water saturated or too dry. Should the
material be too dry, it will be moistened prior to placing and compacting.
In the immediate vicinity of the duct or cable both below and up to a height of
300mm above, stone-free material must be used. (Beach and river sand are not
o their high thermal resistivity).
If the site materials cannot meet these requirements suitable material must be
Use of “Dynamic Core Penetrometer” (D.C.P)
To ensure that the required compaction of the trench has been achieved, tests
must be carried out by the Contractor at various levels.
The tests are carried out using a D.C.P which consists of a metal rod with a
shaped end with an anvil onto which a fixed weight falls through a set
distance. (Drawing No.:1)
shaped end of the rod is placed on the area to be tested, the weight
is raised to the pre-set height and then dropped through the set distance onto
ETHEKWINI MUNICIPALITY
All road/lane closures must first be authorised by the Ethekwini Transport
of all trench work is necessary to prevent
of trenches within hardened surfaces i.e. (Roadways,
by the Contractor to the correct
Strict adherence to the procedures given in this Section will ensure the satisfactory
temporary reinstatement of the trench, leading to early permanent reinstatement by
General backfill can be carried out by using the material excavated from the
it is free from organic material (roots, grass etc) rubbish, clay lumps and
the material is suitable, is not water saturated or too dry. Should the
material be too dry, it will be moistened prior to placing and compacting.
In the immediate vicinity of the duct or cable both below and up to a height of
free material must be used. (Beach and river sand are not
If the site materials cannot meet these requirements suitable material must be
To ensure that the required compaction of the trench has been achieved, tests
The tests are carried out using a D.C.P which consists of a metal rod with a
h a fixed weight falls through a set
area to be tested, the weight
set height and then dropped through the set distance onto
ETHEKWINI MUNICIPALITY
the anvil. The force of the wei
(d) The number of blows required for the rod to penetrate to a distance of 100 mm
into the soil indicates the degree of compaction of the soil.
(e) The following test results are deemed to be acceptable, as m
requirements for compaction of trench backfill using D.C.P test method:
(i) in roadways
(ii) in footpaths, driveways and medians
(iii) in verges –
NOTE: The greater the number of blows required to penetrate the 100 mm the
better the soil compaction at the point of the test.
1.4 Compacting the Trench Bottom
(a) Compaction of suitable bedding material can be achieved by making two
passes over the whole trench bed, preferably using a Power Vibrating Rammer
or a 5 kg hand rammer as an alternative.
(b) The cable or duct can then be laid on the prepared bed.
1.5 Initial Blinding (Backfilling)
(a) After the duct(s) or cable(s) have been lai
placed around them, and the blinding material should be brought up to a level
not exceeding 150 mm.
(b) The material should be equally placed on both sides of the duct(s) or cable(s)
and each layer should then be we
complete passes over the length of the trench, using a 5 kg hand rammer.
NOTE: Do NOT use a vibrating rammer at this stage as the ducts(s) or cable(s)
could easily be damaged.
(c) Further layers, each
leveled and compacted by making five complete passes over the layer, still
using the hand rammer, until the duct or cable is covered by well compacted
blinding material to a height of 300 mm above the to
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
12
the anvil. The force of the weight will cause the rod to penetrate the soil.
The number of blows required for the rod to penetrate to a distance of 100 mm
into the soil indicates the degree of compaction of the soil.
The following test results are deemed to be acceptable, as m
requirements for compaction of trench backfill using D.C.P test method:
in roadways – 5 blows per 100 mm penetration
in footpaths, driveways and medians – 3 blows per 100 mm penetration
– 2 blows per 100 mm penetration
: The greater the number of blows required to penetrate the 100 mm the
better the soil compaction at the point of the test.
Compacting the Trench Bottom
Compaction of suitable bedding material can be achieved by making two
over the whole trench bed, preferably using a Power Vibrating Rammer
or a 5 kg hand rammer as an alternative.
The cable or duct can then be laid on the prepared bed.
Initial Blinding (Backfilling)
After the duct(s) or cable(s) have been laid, suitable blinding material should be
placed around them, and the blinding material should be brought up to a level
not exceeding 150 mm.
The material should be equally placed on both sides of the duct(s) or cable(s)
and each layer should then be well and carefully compacted by making five
complete passes over the length of the trench, using a 5 kg hand rammer.
: Do NOT use a vibrating rammer at this stage as the ducts(s) or cable(s)
could easily be damaged.
Further layers, each not exceeding 150 mm thickness should now be spread,
leveled and compacted by making five complete passes over the layer, still
using the hand rammer, until the duct or cable is covered by well compacted
blinding material to a height of 300 mm above the top of the duct(s) or cable(s).
ETHEKWINI MUNICIPALITY
ght will cause the rod to penetrate the soil.
The number of blows required for the rod to penetrate to a distance of 100 mm
The following test results are deemed to be acceptable, as minimum
requirements for compaction of trench backfill using D.C.P test method:
3 blows per 100 mm penetration
: The greater the number of blows required to penetrate the 100 mm the
Compaction of suitable bedding material can be achieved by making two
over the whole trench bed, preferably using a Power Vibrating Rammer
d, suitable blinding material should be
placed around them, and the blinding material should be brought up to a level
The material should be equally placed on both sides of the duct(s) or cable(s)
ll and carefully compacted by making five
complete passes over the length of the trench, using a 5 kg hand rammer.
: Do NOT use a vibrating rammer at this stage as the ducts(s) or cable(s)
not exceeding 150 mm thickness should now be spread,
leveled and compacted by making five complete passes over the layer, still
using the hand rammer, until the duct or cable is covered by well compacted
p of the duct(s) or cable(s).
ETHEKWINI MUNICIPALITY
NOTE: If ducts are laid in a cluster the blinding material must be brought up in
layers of 150 mm until a cover of 300 mm above the top duct is
obtained.
1.5.1 Initial Test using D.C.P
Tests carried out at this
would be considered satisfactory if at least two blows are required to penetrate
100mm.
NOTE: Tests must be carried out to one side of the duct or cable, and not
immediately above.
1.6 Final Backfilling and Temporary Capping
(a) From the level of 300 mm above the duct or cable to the top of the trench,
backfilling should proceed using suitable material (Section
thickness now being increased to 200 mm (before compaction).
(b) Each layer should be thoroughly compacted by making four complete passes
over the whole trench area with a Power Vibrating Rammer.
(c) Trenches located in roadways shall be finished off with capping of either cold
asphalt (50 mm thick) or 10 MPa strengt
and compacted to serve as a temporary riding surface.
1.7 Trenches in Verge Areas
(a) The final 75 mm -100 mm of trench backfill shall comprise of an organic/topsoil
type material, placed and leveled off flush with
No humps and bumps shall be permitted.
(b) All loose stones and other obstructions shall be removed to spoil.
(c) A suitable ground cover shall be established over the trench width.
1.8 Responsibility for Maintenance of the
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
13
: If ducts are laid in a cluster the blinding material must be brought up in
layers of 150 mm until a cover of 300 mm above the top duct is
Tests carried out at this stage, i.e. 300 mm above duct(s) or cable(s), using D.C.P,
would be considered satisfactory if at least two blows are required to penetrate
: Tests must be carried out to one side of the duct or cable, and not
immediately above.
Backfilling and Temporary Capping
From the level of 300 mm above the duct or cable to the top of the trench,
backfilling should proceed using suitable material (Section
thickness now being increased to 200 mm (before compaction).
Each layer should be thoroughly compacted by making four complete passes
over the whole trench area with a Power Vibrating Rammer.
Trenches located in roadways shall be finished off with capping of either cold
asphalt (50 mm thick) or 10 MPa strength concrete mix (100 mm thick), placed
and compacted to serve as a temporary riding surface.
Trenches in Verge Areas
100 mm of trench backfill shall comprise of an organic/topsoil
type material, placed and leveled off flush with the surrounding ground level.
No humps and bumps shall be permitted.
All loose stones and other obstructions shall be removed to spoil.
A suitable ground cover shall be established over the trench width.
Responsibility for Maintenance of the Trench and Final Reinstatement
ETHEKWINI MUNICIPALITY
: If ducts are laid in a cluster the blinding material must be brought up in
layers of 150 mm until a cover of 300 mm above the top duct is
stage, i.e. 300 mm above duct(s) or cable(s), using D.C.P,
would be considered satisfactory if at least two blows are required to penetrate
: Tests must be carried out to one side of the duct or cable, and not
From the level of 300 mm above the duct or cable to the top of the trench,
backfilling should proceed using suitable material (Section 1.2), with layer
thickness now being increased to 200 mm (before compaction).
Each layer should be thoroughly compacted by making four complete passes
Trenches located in roadways shall be finished off with capping of either cold
h concrete mix (100 mm thick), placed
100 mm of trench backfill shall comprise of an organic/topsoil
the surrounding ground level.
All loose stones and other obstructions shall be removed to spoil.
A suitable ground cover shall be established over the trench width.
Trench and Final Reinstatement
ETHEKWINI MUNICIPALITY
(a) On completion of the backfilling a requisition must be created by the
A service order will be then generated by Buying Department and forwarded to
the appropriate Local Authority, for permanent reinstatement of the trench
surface.
(b) As the responsibility for the maintenance of the trench in the period between
the initial backfilling and final reinstatement is that of the Department, failure
the Contractor to meet the compaction standards could lead to unnecessarily
long periods where a trench would be open to traffic. This could give rise to
dangerous conditions partic
attrition of heavily vehicular or pedestrian traffic.
(c) Trench Reinstatement by Contractors
undertaken by contractors, requirements of Part
Engineering Specifications shall be complied with.
NOTE: Where the excavation is carried out within the eThekwini Municipal
area, these additional clauses are applicable:
(i) The Roads
to test the trench using a D.C.P to check the compaction of differing
depths below ground level.
(ii) If the D.C.P indicates that the number of blows required to penetrate
100 mm into the soil at any zone in the trench profile is less than that
specified in Clause
Department will be notified to take the necessary remedial action. Only
after the trench has been tested and passed shall the final
reinstatement be carried out.
1.9 Surplus Material
All surplus material from trench excavation must be removed
designated spoil site. Should excavated material remain on site for backfill purposes,
it shall be adequately barricaded. Should excavated material end up in the
Municipality’s storm water infrastructure, it will be removed at the responsible party’s
expense.
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
14
On completion of the backfilling a requisition must be created by the
A service order will be then generated by Buying Department and forwarded to
the appropriate Local Authority, for permanent reinstatement of the trench
As the responsibility for the maintenance of the trench in the period between
backfilling and final reinstatement is that of the Department, failure
to meet the compaction standards could lead to unnecessarily
long periods where a trench would be open to traffic. This could give rise to
dangerous conditions particularly where the trench surface is exposed to the
attrition of heavily vehicular or pedestrian traffic.
Trench Reinstatement by Contractors – where trench reinstatements are
undertaken by contractors, requirements of Part S of the City of Durban Civil
Engineering Specifications shall be complied with.
: Where the excavation is carried out within the eThekwini Municipal
area, these additional clauses are applicable:
The Roads and Stormwater Maintenance Department reserves the right
e trench using a D.C.P to check the compaction of differing
depths below ground level.
If the D.C.P indicates that the number of blows required to penetrate
100 mm into the soil at any zone in the trench profile is less than that
specified in Clause 1.3(e), the trench will not be reinstated and the
Department will be notified to take the necessary remedial action. Only
after the trench has been tested and passed shall the final
reinstatement be carried out.
All surplus material from trench excavation must be removed by the Contractor
designated spoil site. Should excavated material remain on site for backfill purposes,
it shall be adequately barricaded. Should excavated material end up in the
y’s storm water infrastructure, it will be removed at the responsible party’s
ETHEKWINI MUNICIPALITY
On completion of the backfilling a requisition must be created by the Contractor.
A service order will be then generated by Buying Department and forwarded to
the appropriate Local Authority, for permanent reinstatement of the trench
As the responsibility for the maintenance of the trench in the period between
backfilling and final reinstatement is that of the Department, failure by
to meet the compaction standards could lead to unnecessarily
long periods where a trench would be open to traffic. This could give rise to
ularly where the trench surface is exposed to the
where trench reinstatements are
the City of Durban Civil
: Where the excavation is carried out within the eThekwini Municipal
Department reserves the right
e trench using a D.C.P to check the compaction of differing
If the D.C.P indicates that the number of blows required to penetrate
100 mm into the soil at any zone in the trench profile is less than that
, the trench will not be reinstated and the
Department will be notified to take the necessary remedial action. Only
after the trench has been tested and passed shall the final
by the Contractor to a
designated spoil site. Should excavated material remain on site for backfill purposes,
it shall be adequately barricaded. Should excavated material end up in the
y’s storm water infrastructure, it will be removed at the responsible party’s
ETHEKWINI MUNICIPALITY
1.10 Service Related Structures
(a) All structures such as manholes, chambers, earth retainers and connecting
junction boxes shall be constructed to a design approved
department.
(b) All exposed vertical surfaces above ground shall be either of a face brick or
concrete off shutter finish.
(c) Where earth retainers such as loffelstein blocks are used, it shall be erected to
the manufacturer’s guideline
(d) The finish level on manhole covers shall be true horizontal with the surrounding
levels modified to tie in.
ACKNOWLEDGEMENT
The contents of “A Practical Guide to Trench Backfilling and Compaction”, issued by the
Construction Division, City Engineer’s Department, have been used extensively in compiling
this Code of Practice.
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
15
Service Related Structures
All structures such as manholes, chambers, earth retainers and connecting
junction boxes shall be constructed to a design approved
All exposed vertical surfaces above ground shall be either of a face brick or
concrete off shutter finish.
Where earth retainers such as loffelstein blocks are used, it shall be erected to
the manufacturer’s guidelines and specifications.
The finish level on manhole covers shall be true horizontal with the surrounding
levels modified to tie in.
The contents of “A Practical Guide to Trench Backfilling and Compaction”, issued by the
ivision, City Engineer’s Department, have been used extensively in compiling
ETHEKWINI MUNICIPALITY
All structures such as manholes, chambers, earth retainers and connecting
junction boxes shall be constructed to a design approved by the relevant
All exposed vertical surfaces above ground shall be either of a face brick or
Where earth retainers such as loffelstein blocks are used, it shall be erected to
The finish level on manhole covers shall be true horizontal with the surrounding
The contents of “A Practical Guide to Trench Backfilling and Compaction”, issued by the
ivision, City Engineer’s Department, have been used extensively in compiling
DYNAMIC CONE PENETROMETER FOR TESTINGREINSTATEMENT OF TRENCHES WITHIN HARDENEDSURFACES
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
16
DYNAMIC CONE PENETROMETER FOR TESTING REINSTATEMENT OF TRENCHES WITHIN HARDENED
DRN : D.J.P.
CHK
APP :
NPA
ETHEKWINI MUNICIPALITY
Drawing 1
CP 2.051 Rev 0
ANNEXURE B: COMMUNICATION TUBING HANDOVER FORM
Preamble
This checklist is to completed and signed in sequence by the Contractor/ Consultant or installer,
once installation of the tubing has been completed, and handed to the appointed
Clerk of Works/ Supervisor.
LINK DESCRIPTION End A
Total Length of Route
Average length between manholes
Item
Description
a.
Manholes are positioned within 200m of each other.
b.
Manholes are positioned at bends greater than 30
o in the route to facilitate the pulling of
the fibre cable.
c. GPS coordinates of all Manholes and ducts to be supplied with as built documents
d.
New technology 3M code 14014" orange location devices/ antennae have been correctly installed and attached to the inside of the manhole cover with nylon string or suitable alternative.
e.
The tubing used has been approved by MetroConnect Engineer.
f.
All tubing into the manhole has been sealed with proper supplier’s end-
g.
An ‘as-built’ diagram of the entire tubing route, showing the surveyed position of all manholes, and the manholes which accommodate joints has been submitted to the MetroConnect Engineer.
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
17
: COMMUNICATION TUBING HANDOVER FORM
This checklist is to completed and signed in sequence by the Contractor/ Consultant or installer,
once installation of the tubing has been completed, and handed to the appointed
LINK DESCRIPTION: Contract No./ Order No.: .................................. End B
No. Of Manholes
Maximum length between manholes
Complies (Y/N)
Remarks
Manholes are positioned within 200m of each
Manholes are positioned at bends greater in the route to facilitate the pulling of
GPS coordinates of all Manholes and ducts to be supplied with as built documents
New technology 3M code 14014" orange location devices/ antennae have been correctly installed and attached to the inside of the manhole cover with nylon string or
The tubing used has been approved by
All tubing into the manhole has been sealed -caps.
built’ diagram of the entire tubing route, showing the surveyed position of all manholes, and the manholes which accommodate joints has been submitted to
Engineer.
ETHEKWINI MUNICIPALITY
This checklist is to completed and signed in sequence by the Contractor/ Consultant or installer,
once installation of the tubing has been completed, and handed to the appointed MetroConnect
: Contract No./ Order No.: ..................................
Completed By: Name
Company
Date
Annexure C
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
18
ETHEKWINI MUNICIPALITY
1. Introduction
This document, together with other referenced documents, defines the responsibilities and procedures to be adopted to ensure that the data and information produced as part of Project No................................. are reliable, fit for purpose and conand deliverables. It provides the details regarding the structure and specifications for all Geographic Information Systems (GIS) data supplied as part of the project deliverables.
2. Deliverables
Complete and verified Spatial Data for Fibre Installation projects shall be delivered via CD
DVD or any other method approved by the
R format, so that it cannot be modified. The deliverables must include the following:
a) Descriptive document
b) Geospatial (GIS) data with relevant attributes
c) Associated data table(s) or relational Microsoft Access database
d) Federal Geographic Data Committee (
a) Descriptive Document
A Microsoft Word document (and/or ASCII text file if specified) describing the CD/DVD contents shall accompany any submission and provide all necessary information for understanding the submittal. The document should include, but is not limited to, the fol
i. Project information including Project name, Project Number, Date of Project commencement and completion, Internal Project Manager (Service provider’s project leader and contact details, Other relevant team members include the GIS technical person.
ii. Contents of the CD/DVD and/or .zip file;iii. Description of the project, including all related deli
and drawings; iv. Version and date of the data and reports;v. Information on the use of data or data issue
appropriate) vi. Contact information for those responsible for creating the data and who have the
responsibility for maintaining the master version of the data vii. A short description of data themes or layers, reports, tables (limit
sentences for each)
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
19
GIS Data Specification
This document, together with other referenced documents, defines the responsibilities and procedures to be adopted to ensure that the data and information produced as part of Project No................................. are reliable, fit for purpose and consistent with documented objectives and deliverables. It provides the details regarding the structure and specifications for all Geographic Information Systems (GIS) data supplied as part of the project deliverables.
Spatial Data for Fibre Installation projects shall be delivered via CD
DVD or any other method approved by the MetroConnect project manager. CD/DVD should be in
R format, so that it cannot be modified. The deliverables must include the following:
Descriptive document
Geospatial (GIS) data with relevant attributes
Associated data table(s) or relational Microsoft Access database
Federal Geographic Data Committee (FGDC) compliant metadata
a) Descriptive Document
A Microsoft Word document (and/or ASCII text file if specified) describing the CD/DVD contents shall accompany any submission and provide all necessary information for understanding the submittal. The document should include, but is not limited to, the following:
Project information including Project name, Project Number, Date of Project commencement and completion, Internal Project Manager (Service provider’s project leader and contact details, Other relevant team members
he GIS technical person. Contents of the CD/DVD and/or .zip file; Description of the project, including all related deliverables, any project codes
Version and date of the data and reports; Information on the use of data or data issues to note;(if any exist or as
Contact information for those responsible for creating the data and who have the responsibility for maintaining the master version of the data A short description of data themes or layers, reports, tables (limitsentences for each)
ETHEKWINI MUNICIPALITY
This document, together with other referenced documents, defines the responsibilities and procedures to be adopted to ensure that the data and information produced as part of Project
sistent with documented objectives and deliverables. It provides the details regarding the structure and specifications for all Geographic Information Systems (GIS) data supplied as part of the project deliverables.
Spatial Data for Fibre Installation projects shall be delivered via CD-ROM or
project manager. CD/DVD should be in -
R format, so that it cannot be modified. The deliverables must include the following:-
Associated data table(s) or relational Microsoft Access database
FGDC) compliant metadata
A Microsoft Word document (and/or ASCII text file if specified) describing the CD/DVD contents shall accompany any submission and provide all necessary information for understanding the
Project information including Project name, Project Number, Date of Project commencement and completion, Internal Project Manager (MetroConnect Official), Service provider’s project leader and contact details, Other relevant team members
verables, any project codes
s to note;(if any exist or as
Contact information for those responsible for creating the data and who have the
A short description of data themes or layers, reports, tables (limited to one to two
viii. Linking fields
photographs)
b) Geospatial (GIS) Data
All Geospatial (GIS) data shall be supplied in include, at a minimum, the .SHP, .DBF, .SHX, and .PRJ files. The following projection parameters shall be used for all Geospatial data supplied:
Projection
Spheroid
False Easting
False Northing
Central Meridian
Scale Factor
Latitude of Origin
Units
In general, the standard projection for GIS layers is Universal Transverse Mercator with the parameters for the WGS84 ellipsoid.
c) Attribute Data
All related attribute data specified below shall be contained in the .dbf file. Dataset Cables Field Name TypeCableID Text LinkID Text CableType TextFibreType Text NoOfFibres Long Dataset Links Field Name TypeLinkID TextCPCodeFrom TextCPCodeTo TextLength Double Dataset Fibres Field Name TypeCableID Text
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
20
Linking fields to documents, a Microsoft Access database, and/or digital
photographs)
All Geospatial (GIS) data shall be supplied in shapefile format. The shapefile format should include, at a minimum, the .SHP, .DBF, .SHX, and .PRJ files. The following projection parameters shall be used for all Geospatial data supplied:
Universal Transverse Mercator
GRS 1980
False Easting 0
False Northing 0
Central Meridian 31.0
Scale Factor 1.0
Latitude of Origin 0 .0
Meters
In general, the standard projection for GIS layers is Universal Transverse Mercator with the parameters for the WGS84 ellipsoid.
All related attribute data specified below shall be contained in the .dbf file.
Type Size 14 12 Text 8 8 Long 8
Type Size Text 12 Text 6 Text 6 Double 19
Type Size 14
ETHEKWINI MUNICIPALITY
to documents, a Microsoft Access database, and/or digital
The shapefile format should include, at a minimum, the .SHP, .DBF, .SHX, and .PRJ files. The following projection
In general, the standard projection for GIS layers is Universal Transverse Mercator with the
All related attribute data specified below shall be contained in the .dbf file.
FibreNo Long FibreColor TextAssocCam TextUniqueNo Long
Dataset Ducts Field Name TypeUniqueNo Long Length Double Dataset Manholes Field Name TypeUniqueNo Long ImageName TextRemarks Text Dataset CCtvcablepointsField Name TypeCablePt Text GisRef TextType Text
All other additional attributes shall be delivered in a welldatabase format (.MDB file) using the latest version of Microsoft Access. Map features and database records shall share a common unique identifier or primary kfeature to the database record. d) Metadata
All data submitted shall include metadata that meets the minimum ### content standard for metadata. The metadata must be located in the same directory as the data, share the same naming prefix, and when appropriate, be attached to that data. The metadata should be delivered in extensible markup language with an .XML extension.
3. Conclusion
For any additional information regarding the specifications for GIS data, the contractor is free tconsult the the GIS Database Administration ManagerMr Dennis Bodeker on [email protected]
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
21
8 Text 8 Text 6 8
Type Size 8 Double 19
Type Size 8 Text 30 30
CCtvcablepoints Type Size 6 Text 10 Text 15
All other additional attributes shall be delivered in a well-structured database format (.MDB file) using the latest version of Microsoft Access. Map features and database records shall share a common unique identifier or primary key that relates the map feature to the database record.
All data submitted shall include metadata that meets the minimum ### content standard for metadata. The metadata must be located in the same directory as the data, share the same
prefix, and when appropriate, be attached to that data. The metadata should be delivered in extensible markup language with an .XML extension.
For any additional information regarding the specifications for GIS data, the contractor is free tconsult the the GIS Database Administration Manager
[email protected] or 031 311 4058
ETHEKWINI MUNICIPALITY
structured Microsoft Access database format (.MDB file) using the latest version of Microsoft Access. Map features and
ey that relates the map
All data submitted shall include metadata that meets the minimum ### content standard for metadata. The metadata must be located in the same directory as the data, share the same
prefix, and when appropriate, be attached to that data. The metadata should be
For any additional information regarding the specifications for GIS data, the contractor is free to
PART 2
INSTALLATION OF UNDERGROUND FIBRE OPTIC CABLE
6. INTRODUCTION
1.1 Scope
The purpose of this document is to detail the requirements for the pulling of underground
fibre optic cable into existing communication tubes, and the handing over of the completed
link.
1.2 Order of Description
This order of description for this part of the standard is as follows:
• Definitions
• Testing of Cable prior to delivery.
• Pulling in of underground fibre optic cable
• Splicing
• Handover Requirements After Laying of Communication Tubes
Specifications for these components of the Fibre Optic System follows:
7. DEFINITIONS
Communication Tubes: The underground tubing, as specified by the Engineer, through which
fibre optic cable is pulled for the establishment of communication links between two points.
Communication Manholes: The manholes, which are either designed for use within a pavement
area or for use within the roadway itself, which are situated along a route and connected by
communication tubes.
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
22
TECHNICAL SPECIFICATION FOR
INSTALLATION OF UNDERGROUND FIBRE OPTIC CABLE
INTO COMMUNICATION TUBING
The purpose of this document is to detail the requirements for the pulling of underground
fibre optic cable into existing communication tubes, and the handing over of the completed
This order of description for this part of the standard is as follows:
Definitions
Testing of Cable prior to delivery.
Pulling in of underground fibre optic cable
Handover Requirements After Laying of Communication Tubes
Specifications for these components of the Fibre Optic System follows:
The underground tubing, as specified by the Engineer, through which
fibre optic cable is pulled for the establishment of communication links between two points.
The manholes, which are either designed for use within a pavement
a or for use within the roadway itself, which are situated along a route and connected by
ETHEKWINI MUNICIPALITY
INSTALLATION OF UNDERGROUND FIBRE OPTIC CABLE
The purpose of this document is to detail the requirements for the pulling of underground
fibre optic cable into existing communication tubes, and the handing over of the completed
Handover Requirements After Laying of Communication Tubes
Specifications for these components of the Fibre Optic System follows:
The underground tubing, as specified by the Engineer, through which
fibre optic cable is pulled for the establishment of communication links between two points.
The manholes, which are either designed for use within a pavement
a or for use within the roadway itself, which are situated along a route and connected by
Fibre Communication Panel (FCP):
terminated into a patch tray, and made available
equipment.
Manhole Ball Markers: A device which is attached to the inside of a manhole cover, which
together with a sensor carried by an operator, is used to pinpoint the exact location of the manhole
beneath the surface of the ground.
Jointbox: An approved sealed enclosure used to secure and accommodate splices made
between two sections of fibre. In the case of an enclosure contained within a manhole, this will be
of high density polyethelene, (eg. Tank Techno
case of a jointbox to be positioned in the air, this is made of stainless steel (eg. Nokia Dome Joint)
8. PULLING OF UNDERGROUND FIBRE OPTIC CABLE
The pulling of cable proceeds after the installa
begin only once it has been confirmed that the communication tubing, including installation of
communication manholes and manhole ball markers, and documentation, has been completed
according to the standard set by eThekwini
3.1. Attenuation Tests prior to Pulling
Attenuation tests shall be carried out on every fibre of the cable while still on the drum to
confirm that the fibre drums are in good order after delivery and have been received b
contractor/ installer, prior to pulling.
Cables with an average attenuation at 1550nm above 0,25dB/km, or above 0,35dB/km at
1300nm, shall not be accepted. In addition, fibres with any points or steps of discontinuity
greater than 0,04dB shall
The form used to confirm the results of the attenuation test is provided in Annexure B.
3.2. Pulling of Sections
One underground fibre cable is to be used per tube. Fibre cable is to be pulled from
communication manhole to comm
Utmost care must be taken to ensure against over
in the process of pulling. It should be noted that the drawer wires/fibre supplied in the
communication tubing must not be used to pull through t
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
23
Fibre Communication Panel (FCP): The panel within a substation where the fibre optic cable is
terminated into a patch tray, and made available for optical connection to various optical
A device which is attached to the inside of a manhole cover, which
together with a sensor carried by an operator, is used to pinpoint the exact location of the manhole
surface of the ground.
An approved sealed enclosure used to secure and accommodate splices made
between two sections of fibre. In the case of an enclosure contained within a manhole, this will be
of high density polyethelene, (eg. Tank Technologies TFO B30000/0B Fibre Optic Dome. In the
case of a jointbox to be positioned in the air, this is made of stainless steel (eg. Nokia Dome Joint)
PULLING OF UNDERGROUND FIBRE OPTIC CABLE
The pulling of cable proceeds after the installation of the communication tubes. This process may
begin only once it has been confirmed that the communication tubing, including installation of
communication manholes and manhole ball markers, and documentation, has been completed
rd set by eThekwini Municipality.
Attenuation Tests prior to Pulling
Attenuation tests shall be carried out on every fibre of the cable while still on the drum to
confirm that the fibre drums are in good order after delivery and have been received b
contractor/ installer, prior to pulling.
Cables with an average attenuation at 1550nm above 0,25dB/km, or above 0,35dB/km at
1300nm, shall not be accepted. In addition, fibres with any points or steps of discontinuity
greater than 0,04dB shall also be unacceptable.
The form used to confirm the results of the attenuation test is provided in Annexure B.
One underground fibre cable is to be used per tube. Fibre cable is to be pulled from
communication manhole to communication manhole.
Utmost care must be taken to ensure against over-bending and over
in the process of pulling. It should be noted that the drawer wires/fibre supplied in the
communication tubing must not be used to pull through the actual fibre cable. Instead a
ETHEKWINI MUNICIPALITY
The panel within a substation where the fibre optic cable is
for optical connection to various optical
A device which is attached to the inside of a manhole cover, which
together with a sensor carried by an operator, is used to pinpoint the exact location of the manhole
An approved sealed enclosure used to secure and accommodate splices made
between two sections of fibre. In the case of an enclosure contained within a manhole, this will be
logies TFO B30000/0B Fibre Optic Dome. In the
case of a jointbox to be positioned in the air, this is made of stainless steel (eg. Nokia Dome Joint)
tion of the communication tubes. This process may
begin only once it has been confirmed that the communication tubing, including installation of
communication manholes and manhole ball markers, and documentation, has been completed
Attenuation tests shall be carried out on every fibre of the cable while still on the drum to
confirm that the fibre drums are in good order after delivery and have been received by the
Cables with an average attenuation at 1550nm above 0,25dB/km, or above 0,35dB/km at
1300nm, shall not be accepted. In addition, fibres with any points or steps of discontinuity
The form used to confirm the results of the attenuation test is provided in Annexure B.
One underground fibre cable is to be used per tube. Fibre cable is to be pulled from
bending and over-tensioning the cable
in the process of pulling. It should be noted that the drawer wires/fibre supplied in the
he actual fibre cable. Instead a
rope, or a more robust drawer wire which must be used to pull the actual cable. A pulling
lubricant may be used provided this has no detrimental effect on the cable or PVC pipes/
ducts.
The cables must be hand pulled, mapproval and under direct supervision of the Engineer. Every care must be taken to prevent damage to existing cables / services whilst installing new cables. The cable must be manhandled at every mdrag on existing services.
Cable lubrication may be necessary when installing in occupied ducts provided this has no
detrimental effect on the cable or PVC pipes/ ducts.
The cable should be pulled with a continuous rhythmic motion, sharp jerks must be avoided.
At least 5 metres of slack must be looped and retained within each communication
manhole.
At least 5 metres of slack should be looped at the base of the tower/ ga
Underground fibre optic cables need to join onto Optical Ground Wire (OPGW).
Self-expanding polystyrene type foam shall be injected into the communication tube
openings after the cable has been pulled to seal the ends of the tubes and to s
ingress of sand, rodents, etc.
3.3. Splicing
Splicing must only be carried out using equipment that has been approved by eThekwini
Municipality.
The identification of cores is according to an in
detailed in ANNEXURE A
Descriptions of the various splicing scenarios follow:
3.3.1 JOINTING AND SPLICING BETWEEN SECTIONS OF UNDERGROUND FIBRE
OPTIC CABLE
Fibres must be fusion spliced, and must have a
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
24
rope, or a more robust drawer wire which must be used to pull the actual cable. A pulling
lubricant may be used provided this has no detrimental effect on the cable or PVC pipes/
The cables must be hand pulled, mechanical pulling devices may only be used with explicit approval and under direct supervision of the Engineer.
Every care must be taken to prevent damage to existing cables / services whilst installing
The cable must be manhandled at every manhole along the way to prevent unnecessary drag on existing services.
Cable lubrication may be necessary when installing in occupied ducts provided this has no
detrimental effect on the cable or PVC pipes/ ducts.
The cable should be pulled with a continuous rhythmic motion, sharp jerks must be
At least 5 metres of slack must be looped and retained within each communication
At least 5 metres of slack should be looped at the base of the tower/ ga
Underground fibre optic cables need to join onto Optical Ground Wire (OPGW).
expanding polystyrene type foam shall be injected into the communication tube
openings after the cable has been pulled to seal the ends of the tubes and to s
ingress of sand, rodents, etc.
Splicing must only be carried out using equipment that has been approved by eThekwini
The identification of cores is according to an international numbering convention as
detailed in ANNEXURE A (Part 2).
Descriptions of the various splicing scenarios follow:
JOINTING AND SPLICING BETWEEN SECTIONS OF UNDERGROUND FIBRE
Fibres must be fusion spliced, and must have a loss equal or less than 0.05dB.
ETHEKWINI MUNICIPALITY
rope, or a more robust drawer wire which must be used to pull the actual cable. A pulling
lubricant may be used provided this has no detrimental effect on the cable or PVC pipes/
echanical pulling devices may only be used with explicit
Every care must be taken to prevent damage to existing cables / services whilst installing
anhole along the way to prevent unnecessary
Cable lubrication may be necessary when installing in occupied ducts provided this has no
The cable should be pulled with a continuous rhythmic motion, sharp jerks must be
At least 5 metres of slack must be looped and retained within each communication
At least 5 metres of slack should be looped at the base of the tower/ gantry leg where
Underground fibre optic cables need to join onto Optical Ground Wire (OPGW).
expanding polystyrene type foam shall be injected into the communication tube
openings after the cable has been pulled to seal the ends of the tubes and to stop the
Splicing must only be carried out using equipment that has been approved by eThekwini
ternational numbering convention as
JOINTING AND SPLICING BETWEEN SECTIONS OF UNDERGROUND FIBRE
loss equal or less than 0.05dB.
An approved fibre optic jointbox (eg. Tank’s TFOB30000/0B Fibre Optic Dome
Jointbox) must be used to contain the splices between two sections of underground
fibre optic cable. The jointbox must be accommodated within a com
manhole.
Jointing within the box must be carried out strictly according to the suppliers
specification. Joint boxes must be suitably sealed to prevent ingress of moisture,
and waterproof to a submerged depth of 2 metres.
At least 4 metres of
to allow staff to work on the joint above the ground within an enclosure or vehicle.
3.3.2 JOINTING AND SPLICING BETWEEN SECTIONS OF UNDERGOUND FIBRE
OPTIC CABLE AND OVERHEAD OPTICAL GROUND WIR
Joints between OPGW and Underground fibre optic cable sections must be housed
within a stainless steel jointbox approved by eThekwini Electricity.
The approved stainless steel jointbox must be mounted onto the top of a vertically
installed, 2 metres high, 50mm diameter stainless steel pipe buried 0,8 metres into
the ground. The pipe must be secured to the inside of the tower leg/ just off the
gantry leg or pylon using the approved stainless steel bracket supplied by
eThekwini Electricity.
DN50 Kabelflex tubing for the underground fibre cable must be inserted into the
base of the stainless steel pipe. Where the communication tubing is hard drawn
polyetherlene (HDPE), the DN50 Kabelflex and the HDPE tubing must be water
tight and taped with self
moisture and sand.
The top of the pipe must be sealed with self expanding polystyrene type foam,
(‘Sista'), to prevent ingress of water.
Jointing within the box must be carried out stri
specification. The correct cable clamping ferrules and half shells at the base of the
joint must be used. Jointboxes must be suitably sealed to prevent ingress of
moisture.
3.3.3 TERMINATION OF UNDERGROUND FIBRE OPTIC CABLE INTO FIBRE
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
25
An approved fibre optic jointbox (eg. Tank’s TFOB30000/0B Fibre Optic Dome
Jointbox) must be used to contain the splices between two sections of underground
fibre optic cable. The jointbox must be accommodated within a com
Jointing within the box must be carried out strictly according to the suppliers
specification. Joint boxes must be suitably sealed to prevent ingress of moisture,
and waterproof to a submerged depth of 2 metres.
At least 4 metres of slack from each end should be coiled neatly into the manhole
to allow staff to work on the joint above the ground within an enclosure or vehicle.
JOINTING AND SPLICING BETWEEN SECTIONS OF UNDERGOUND FIBRE
OPTIC CABLE AND OVERHEAD OPTICAL GROUND WIRE (OPGW)
Joints between OPGW and Underground fibre optic cable sections must be housed
within a stainless steel jointbox approved by eThekwini Electricity.
The approved stainless steel jointbox must be mounted onto the top of a vertically
etres high, 50mm diameter stainless steel pipe buried 0,8 metres into
the ground. The pipe must be secured to the inside of the tower leg/ just off the
gantry leg or pylon using the approved stainless steel bracket supplied by
eThekwini Electricity.
Kabelflex tubing for the underground fibre cable must be inserted into the
base of the stainless steel pipe. Where the communication tubing is hard drawn
polyetherlene (HDPE), the DN50 Kabelflex and the HDPE tubing must be water
tight and taped with self amalgamating rubber tape to prevent the ingress of
moisture and sand.
The top of the pipe must be sealed with self expanding polystyrene type foam,
(‘Sista'), to prevent ingress of water.
Jointing within the box must be carried out strictly according to the suppliers
specification. The correct cable clamping ferrules and half shells at the base of the
joint must be used. Jointboxes must be suitably sealed to prevent ingress of
TERMINATION OF UNDERGROUND FIBRE OPTIC CABLE INTO FIBRE
ETHEKWINI MUNICIPALITY
An approved fibre optic jointbox (eg. Tank’s TFOB30000/0B Fibre Optic Dome
Jointbox) must be used to contain the splices between two sections of underground
fibre optic cable. The jointbox must be accommodated within a communication
Jointing within the box must be carried out strictly according to the suppliers
specification. Joint boxes must be suitably sealed to prevent ingress of moisture,
slack from each end should be coiled neatly into the manhole
to allow staff to work on the joint above the ground within an enclosure or vehicle.
JOINTING AND SPLICING BETWEEN SECTIONS OF UNDERGOUND FIBRE
E (OPGW)
Joints between OPGW and Underground fibre optic cable sections must be housed
within a stainless steel jointbox approved by eThekwini Electricity.
The approved stainless steel jointbox must be mounted onto the top of a vertically
etres high, 50mm diameter stainless steel pipe buried 0,8 metres into
the ground. The pipe must be secured to the inside of the tower leg/ just off the
gantry leg or pylon using the approved stainless steel bracket supplied by
Kabelflex tubing for the underground fibre cable must be inserted into the
base of the stainless steel pipe. Where the communication tubing is hard drawn
polyetherlene (HDPE), the DN50 Kabelflex and the HDPE tubing must be water-
amalgamating rubber tape to prevent the ingress of
The top of the pipe must be sealed with self expanding polystyrene type foam,
ctly according to the suppliers
specification. The correct cable clamping ferrules and half shells at the base of the
joint must be used. Jointboxes must be suitably sealed to prevent ingress of
TERMINATION OF UNDERGROUND FIBRE OPTIC CABLE INTO FIBRE
COMMUNICATION PANEL (FCP)
Both the underground fibre optic cable and the communication tubing in which the
cable runs must be properly terminated at the FCP
either end of the link.
The individually coloured fibre cores must be numbered according to international
numbering convention as detailed in the physical specifi
Municipality.
The optic fibres of the fibre transmission link must
provided in the patching tray/ drawer of the Fibre Communication Panel (FCP)
the termination point, using a core aligning machine.
splices must not be greater than 0,05dB.
The connectors a
source, or source substation, and the cores numbered. This label must be black
lettering on a white background.
Singlemode fibre ends will terminated using LX.5 APC connectors and
midcouplers.
4. HANDOVER REQUIREMENTS AND PROCEDURES
Handover occurs once the contractor/ installer of a link has completed the installation, when all
splices have been completed and when the contractor has fully tested and proved the fibre link,
from termination point to termination point. A termination point is a patch panel within the Fibre
Communication Panel (FCP) at a substation, unless otherwise specified by eThekwini Electricity.
4.1 Test Equipment
The test instrument used for the testing of fibre
Domain Reflectometer (OTDR), approved by eThekwini Electricity.
4.2 Red Light-source test
A red light source must be used to check for basic continuity and to ensure that there are
no cross-overs between termin
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
26
COMMUNICATION PANEL (FCP)
Both the underground fibre optic cable and the communication tubing in which the
cable runs must be properly terminated at the FCP into designated locations
either end of the link.
The individually coloured fibre cores must be numbered according to international
numbering convention as detailed in the physical specifi
The optic fibres of the fibre transmission link must be fusion spliced to the pigtails
provided in the patching tray/ drawer of the Fibre Communication Panel (FCP)
the termination point, using a core aligning machine.. The attenuation across
splices must not be greater than 0,05dB.
The connectors at the front of the patch tray must be labelled with the name of the
source, or source substation, and the cores numbered. This label must be black
lettering on a white background.
Singlemode fibre ends will terminated using LX.5 APC connectors and
HANDOVER REQUIREMENTS AND PROCEDURES
Handover occurs once the contractor/ installer of a link has completed the installation, when all
splices have been completed and when the contractor has fully tested and proved the fibre link,
on point to termination point. A termination point is a patch panel within the Fibre
Communication Panel (FCP) at a substation, unless otherwise specified by eThekwini Electricity.
The test instrument used for the testing of fibre transmission links must be an Optical Time
Domain Reflectometer (OTDR), approved by eThekwini Electricity.
A red light source must be used to check for basic continuity and to ensure that there are
overs between termination points.
ETHEKWINI MUNICIPALITY
Both the underground fibre optic cable and the communication tubing in which the
into designated locations at
The individually coloured fibre cores must be numbered according to international
numbering convention as detailed in the physical specifications of eThekwini
be fusion spliced to the pigtails
provided in the patching tray/ drawer of the Fibre Communication Panel (FCP) at
. The attenuation across
t the front of the patch tray must be labelled with the name of the
source, or source substation, and the cores numbered. This label must be black
Singlemode fibre ends will terminated using LX.5 APC connectors and
Handover occurs once the contractor/ installer of a link has completed the installation, when all
splices have been completed and when the contractor has fully tested and proved the fibre link,
on point to termination point. A termination point is a patch panel within the Fibre
Communication Panel (FCP) at a substation, unless otherwise specified by eThekwini Electricity.
transmission links must be an Optical Time
A red light source must be used to check for basic continuity and to ensure that there are
4.3 Attenuation Tests
Attenuation tests and tests shall be carried out from end to end on every fibre after pulling
and splicing.
At handover the average attenuation for the link, at 1300nm, shall not be greater than
0,4dB/km. At 1550nm the average attenuation shall not be greater than 0,25dB/km.
4.4 Optical Time Domain Reflectometer Tests
Each core must be tested using the approved OTDR from each side of the link, at 1550nm
and at 1310nm. The report shall also inc
events of the route.
Losses and reflectances shall proved to have been
4.4 Handover Documentation
The documentation required at handover and prior to payment are as follows:
• The completed “Completion Form for Underground Optical Fibre Link” as detailed
in ANNEXURE C
• Copies of the results of the OTDR tests on
• Details of the helix factor, the index of refraction, and the Rayleigh backscatter
factor of the fibre cable used.
• Complete GIS drawing of all new fibre installed
GIS specification).
Copies of this documentation shall be provided to
MetroConnect after completion and at handover of the work.
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
27
Attenuation tests and tests shall be carried out from end to end on every fibre after pulling
At handover the average attenuation for the link, at 1300nm, shall not be greater than
4dB/km. At 1550nm the average attenuation shall not be greater than 0,25dB/km.
4.4 Optical Time Domain Reflectometer Tests
Each core must be tested using the approved OTDR from each side of the link, at 1550nm
and at 1310nm. The report shall also include labels describing the physical location of any
ances shall proved to have been minimized.
4.4 Handover Documentation
The documentation required at handover and prior to payment are as follows:
completed “Completion Form for Underground Optical Fibre Link” as detailed
in ANNEXURE C
Copies of the results of the OTDR tests on CD and on hard copy
Details of the helix factor, the index of refraction, and the Rayleigh backscatter
re cable used.
Complete GIS drawing of all new fibre installed (SEE Part 1: ANNEXURE C, for
Copies of this documentation shall be provided to Clerk of Works/ Project leader of
after completion and at handover of the work.
ETHEKWINI MUNICIPALITY
Attenuation tests and tests shall be carried out from end to end on every fibre after pulling
At handover the average attenuation for the link, at 1300nm, shall not be greater than
4dB/km. At 1550nm the average attenuation shall not be greater than 0,25dB/km.
Each core must be tested using the approved OTDR from each side of the link, at 1550nm
lude labels describing the physical location of any
The documentation required at handover and prior to payment are as follows:
completed “Completion Form for Underground Optical Fibre Link” as detailed
and on hard copy
Details of the helix factor, the index of refraction, and the Rayleigh backscatter
(SEE Part 1: ANNEXURE C, for
Clerk of Works/ Project leader of
ANNEXURE A: FIBRE NUMBERING CONVENTION The standard colours of fibres in each bundle or tube shall be as follows:
core 1
core 2:
core 3:
core 4:
core 5:
core 6:
Example.1 12 fibre core systems Two conventions are prevalent:
• In 3 tube/ bundle systems:
• Red tube • White tube • Green tube
There are 4 fibres per tube/ bundle. The individual fibre cores in each tube/ bundle are in order Blue, Orange, Green and Brown ie. Cores 1,5 & 9 are Blue, cores 2,6 & 10 are Orange, etc.
• In 4 tube/ bundle systems:
• Red tube/ bundle • White tube/ bundle • White tube/ bundle • Green tube/ bundle
There are 3 fibres per tube/ bundle. The individual fibre cores in each tube/ bundare in order Blue, Orange and Green ie. Cores 1,4,7 & 10 are Blue, cores 2,5,8 & 11 are Orange, etc.
Example 2. 24 fibre core systems
• In 4 tube/ bundle systems:
• Red tube/ bundle • White tube/ bundle • White tube/
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
28
ANNEXURE A: FIBRE NUMBERING CONVENTION
The standard colours of fibres in each bundle or tube shall be as follows:
Blue core 7:
Orange core 8:
Green core 9:
Brown core 10:
Grey core 11:
White core 12:
12 fibre core systems
Two conventions are prevalent:
In 3 tube/ bundle systems:
Red tube - cores 1 to 4, White tube - cores 5 to 8 and Green tube - cores 9 to 12.
There are 4 fibres per tube/ bundle. The individual fibre cores in each tube/ bundle are in order Blue, Orange, Green and Brown ie. Cores 1,5 & 9 are Blue, cores 2,6 & 10 are Orange, etc.
In 4 tube/ bundle systems:
Red tube/ bundle - cores 1 to 3 White tube/ bundle - cores 4 to 6 White tube/ bundle - cores 7 to 9 Green tube/ bundle - cores 10 to 12
There are 3 fibres per tube/ bundle. The individual fibre cores in each tube/ bundare in order Blue, Orange and Green ie. Cores 1,4,7 & 10 are Blue, cores 2,5,8 & 11 are Orange, etc.
24 fibre core systems
In 4 tube/ bundle systems:
Red tube/ bundle - cores 1 to 6 White tube/ bundle - cores 7 to 12 White tube/ bundle - cores 13 to 18
ETHEKWINI MUNICIPALITY
Red
Black
Yellow
Purple
Turquoise
Pink
There are 4 fibres per tube/ bundle. The individual fibre cores in each tube/ bundle are in order Blue, Orange, Green and Brown ie. Cores 1,5 & 9 are Blue, cores 2,6
There are 3 fibres per tube/ bundle. The individual fibre cores in each tube/ bundle are in order Blue, Orange and Green ie. Cores 1,4,7 & 10 are Blue, cores 2,5,8 &
• Green tube/ bundle
There are 6 fibres per tube/ bundle. The individual fibre cores in each tube/ bundle are in order Blue, Orange, Green, Brown, Grey and White ie. Cores 1,7,13 & 19 are Blue, cores 2,8,14 & 20 a
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
29
Green tube/ bundle - cores 19 to 24
There are 6 fibres per tube/ bundle. The individual fibre cores in each tube/ bundle are in order Blue, Orange, Green, Brown, Grey and White ie. Cores 1,7,13 & 19 are Blue, cores 2,8,14 & 20 are Orange, etc.
ETHEKWINI MUNICIPALITY
There are 6 fibres per tube/ bundle. The individual fibre cores in each tube/ bundle are in order Blue, Orange, Green, Brown, Grey and White ie. Cores 1,7,13 & 19 are
ANNEXURE B: ATTENUATION TESTING ON FIBRE OPTIC CABLE/ OPGW PRIOR TO
PULLING OR STRINGING
Preamble
This form is to completed and signed by the Contractor/ Consultant or installer, prior to the
pulling of fibre optic cable
completed it must be handed to the appointed
MetroConnect.
LINK DESCRIPTION: Contract No./ Order No.: .................................................. End A
Drum Manufacturer
No. Of fibres
Test Results: average dB/km Core
Average dB/km
1
2
3
4
5.
6.
7.
8.
9.
10.
11.
12.
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
30
ANNEXURE B: ATTENUATION TESTING ON FIBRE OPTIC CABLE/ OPGW PRIOR TO
This form is to completed and signed by the Contractor/ Consultant or installer, prior to the
pulling of fibre optic cable or the stringing of Optical Ground Wire (OPGW). Once
completed it must be handed to the appointed Clerk of Works/ Project leader of
: Contract No./ Order No.: .................................................. End B
Drum No.
Make & Model of Equipment used:
Test Results: average dB/km
Average dB/km Core
Average dB/km
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
ETHEKWINI MUNICIPALITY
ANNEXURE B: ATTENUATION TESTING ON FIBRE OPTIC CABLE/ OPGW PRIOR TO
This form is to completed and signed by the Contractor/ Consultant or installer, prior to the
or the stringing of Optical Ground Wire (OPGW). Once
Clerk of Works/ Project leader of
: Contract No./ Order No.: ..................................................
Average dB/km
I hereby confirm that the fibre optic cable/ OPGW has been received by me in good working order.
Completed By: Name
Company
Date
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
31
hereby confirm that the fibre optic cable/ OPGW has been received by me in good working order.
ETHEKWINI MUNICIPALITY
hereby confirm that the fibre optic cable/ OPGW has been received by me in good working order.
ANNEXURE C: COMPLETION FORM FOR UNDERGROUND OPTICAL FIBRE LINK
Preamble
This form is to completed and signed by the Contractor/ Consultant or installer, once installation of
the underground fibre optic cable is completed and fully tested. It is to be and handed to the
appointed Clerk of Works/ Project leader of
LINK DESCRIPTION: Contract No./ Order No.: .....................................................
End A
Length of route
No. Of Joint Boxes
Make & Model of Splicer used
Item
Description
1.
Pulling of cable between, and splicing at communication manholes:
a.
Precautions were taken to ensure that there was no damage to the cable during the pulling process and that there was no overor excessive strain placed on it.
b.
5m of cable slack has been retained in each manhole.
c.
The ends of the tubes at the manholes have been filled with self expanding polystyrene type foam.
d.
Approved joint boxes have been used, and been fitted according to the manufacturer’s instruction.
e.
5m of cable slack has been retained on each side of a joint box at the manhole.
g.
The standard fibre numbering system applied during splicing.
h.
‘Sista’ expanding foam was of stainless steel tube, beneath Nokia Dome Joint.
2.
Jointing of fibre cables within the FCP in the Computer Room NOTE: FCP will have been equipped by DME with a splicing tray, fitted with midcouplers, compression glands and for each fibre
a.
NEX tubing is secured to the gland plate at the base of the FCP with a 50mm male adaptor, (provided by DME).
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
32
ANNEXURE C: COMPLETION FORM FOR UNDERGROUND OPTICAL FIBRE LINK
This form is to completed and signed by the Contractor/ Consultant or installer, once installation of
the underground fibre optic cable is completed and fully tested. It is to be and handed to the
Clerk of Works/ Project leader of MetroConnect.
: Contract No./ Order No.: ..................................................... End B
No. Of Tubes
Make & model of OTDR used
Complied(Y/N)
Remarks
Pulling of cable between, and splicing at communication manholes:
Precautions were taken to ensure that there was no damage to the cable during the pulling process and that there was no over-bending
excessive strain placed on it.
5m of cable slack has been retained in each
The ends of the tubes at the manholes have been filled with self expanding polystyrene
Approved joint boxes have been used, and been fitted according to the manufacturer’s
5m of cable slack has been retained on each side of a joint box at the manhole.
The standard fibre numbering system applied
‘Sista’ expanding foam was used to seal top of stainless steel tube, beneath Nokia Dome
Jointing of fibre cables within the FCP in
NOTE: FCP will have been equipped by DME with a splicing tray, fitted with mid-couplers, compression glands and pigtails
NEX tubing is secured to the gland plate at the base of the FCP with a 50mm male adaptor, (provided by DME).
ETHEKWINI MUNICIPALITY
ANNEXURE C: COMPLETION FORM FOR UNDERGROUND OPTICAL FIBRE LINK
This form is to completed and signed by the Contractor/ Consultant or installer, once installation of
the underground fibre optic cable is completed and fully tested. It is to be and handed to the
: Contract No./ Order No.: .....................................................
Remarks
Item
Description
b.
All fibres spliced onto pigtails, and fibres on splicing tray neatly made off
c.
Standard Fibre Numbering system adopted
f.
The loss for all splices is below 0,05dB.
g.
The connectors at the front of the patch tray at the terminations have been labelled, and checked for crossovers.
h.
The average dB/km for all 0,4dB/km at 1310nm and 0,25dB/km at 1550nm.
i.
All losses and reflectances on the link have been minimised.
j.
Helix Factor: Index of refraction: Rayleigh backscatter factor:
j.
All the events on the OTDR traces have been labeled/ position described.
k.
The results of the OTDR tests, from both ends, and at both 1550nm and at 1310nm, have been provided on CD
Completed By: Name
Company
Date
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
33
Complied(Y/N)
Remarks
All fibres spliced onto pigtails, and fibres on splicing tray neatly made off
Standard Fibre Numbering system adopted
The loss for all splices is below 0,05dB.
The connectors at the front of the patch tray at the terminations have been labelled, and
The average dB/km for all cores is less than 0,4dB/km at 1310nm and 0,25dB/km at
All losses and reflectances on the link have
Rayleigh backscatter factor:
.................................................................................................................................
All the events on the OTDR traces have been / position described.
The results of the OTDR tests, from both ends, and at both 1550nm and at 1310nm,
CD and on hard copy.
ETHEKWINI MUNICIPALITY
Remarks
............................................
............................................
.........................................
Adopted at the End of December 2008:
Signature:
1. Information Technology:________________________________________________
2. ETA _______________________________________________________________
3. Roads____________________________________________________________
4. Water______________________________________________________________
5. Electricity___________________________________________________________
6. City Police__________________________________________________________
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
34
Adopted at the End of December 2008:
________________________________________________
ETA _______________________________________________________________
____________________________________________________________
Water______________________________________________________________
Electricity___________________________________________________________
City Police__________________________________________________________
ETHEKWINI MUNICIPALITY
________________________________________________
ETA _______________________________________________________________
______________________________________________________________
Water______________________________________________________________
Electricity___________________________________________________________
City Police__________________________________________________________
Customer File Index
A hardcopy customer file must be completed for each purchase order issued. Below is the index list of all information that must be supplied.expedite job completion and payments.
1. Original RFQ document and ma2. Bill of quantities and official quotation.3. Site layout plan or m4. All email correspondence from MetroConnect Planning or MetroConnect Procurement.5. Official purchase order6. Additional maps that 7. Additional work instruction8. Work instruction/variation 9. Quotes for any Variation work 10. Invoices for each purchase 11. Evidentiary photos for any work/cost varia12. Progress reports on additional work13. Contact people on site that was 14. Contact people in charge of customer building15. Contact numbers and names of persons/companies that will do the job16. Progress reports from 17. Splice tray labeling d18. Photographs of cabinet, patch panel and splice tray.19. OTDR test results. 20. GPS co-ordinates for all service points. (21. Copy of Wayleaves from all service providers.22. All email correspondence with Ethekwini Roads Department. 23. Customer Sign Off C
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
35
customer file must be completed for each purchase order issued. Below is the index list of all information that must be supplied. Please ensure that all information is supplied to expedite job completion and payments.
Original RFQ document and map. Bill of quantities and official quotation.
plan or map of completed route (as built route). All email correspondence from MetroConnect Planning or MetroConnect Procurement.
rder number from Ethekwini. aps that could relate to the area of the job. ork instructions.
ariation order for additional work. ariation work – NOT part of initial quote urchase order.
Evidentiary photos for any work/cost variance. Progress reports on additional work.
on site that was involved in the job. Contact people in charge of customer buildings or sites. Contact numbers and names of persons/companies that will do the jobProgress reports from site inspections.
diagram. Photographs of cabinet, patch panel and splice tray.
ordinates for all service points. (New Manholes, Strategic Junction Points
s from all service providers. l email correspondence with Ethekwini Roads Department.
Certificate.
ETHEKWINI MUNICIPALITY
customer file must be completed for each purchase order issued. Below is the index Please ensure that all information is supplied to
All email correspondence from MetroConnect Planning or MetroConnect Procurement.
Contact numbers and names of persons/companies that will do the job if required.
New Manholes, Strategic Junction Points, etc)
CONDITIONS PERTAINING TO APPROVAL OF WAYLEAVES
1. No obstructions to sidewalks and roadways are permitted. In this regard, Pedestrians and
motorists should be accommodated for at all times.
2. The proving of underground services and the relocation thereof, if necessary, will be their
responsibility of your organisation.
3. All re-instatements, including backfilling, compaction and testing of excavations to
departmental specifications.
The Road and Stormwater Maintenance Department will carry out the final road re
instatement and requisitions for such work must be forwarded by your organization
timeously.
4. Temporary re-instatements to be maintained by
instatements. Claims arising during the construction of the proposed works and prior to any
final reinstatements being carried out by this department will be for your organization to
resolve.
5. Finish cover levels of manholes to suit the surrounding surface levels.
6. All excavations and allied works must be suitably barricaded and maintained until final
completion or works.
7. Saw cutting of the existing surfaced layers will be required, prior to any excavations taking
place.
8. Mixing of concrete or mortar on the road or sidewalk surface is not permitted.
9. Construction materials are not to be left haphazardly on the road, sidewalk or verge at any
time during construction.
10. All rubble and other spoil generated by the prop
as the works in particular vicinity is complete.
11. Contractors carrying out work on your behalf to be adequately supervised at all times. Due
cognisance must be taken of the gazetted Occupational Health and Safety
Construction Regulations: 2003
12. The Unit reserves the right to halt progress at any time during the project should the above
requirements not be satisfactorily adhered to.
13. Adequate notice of intention to commence work must be given to prior t
commencement of the work. All work within the Council road reserve will be monitored by
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
36
CONDITIONS PERTAINING TO APPROVAL OF WAYLEAVES
No obstructions to sidewalks and roadways are permitted. In this regard, Pedestrians and
should be accommodated for at all times.
The proving of underground services and the relocation thereof, if necessary, will be their
responsibility of your organisation.
instatements, including backfilling, compaction and testing of excavations to
departmental specifications.
The Road and Stormwater Maintenance Department will carry out the final road re
instatement and requisitions for such work must be forwarded by your organization
instatements to be maintained by the excavator until completion of final re
instatements. Claims arising during the construction of the proposed works and prior to any
final reinstatements being carried out by this department will be for your organization to
of manholes to suit the surrounding surface levels.
All excavations and allied works must be suitably barricaded and maintained until final
Saw cutting of the existing surfaced layers will be required, prior to any excavations taking
Mixing of concrete or mortar on the road or sidewalk surface is not permitted.
Construction materials are not to be left haphazardly on the road, sidewalk or verge at any
time during construction.
All rubble and other spoil generated by the proposed works to be removed off site as soon
as the works in particular vicinity is complete.
Contractors carrying out work on your behalf to be adequately supervised at all times. Due
cognisance must be taken of the gazetted Occupational Health and Safety
Construction Regulations: 2003
The Unit reserves the right to halt progress at any time during the project should the above
requirements not be satisfactorily adhered to.
Adequate notice of intention to commence work must be given to prior t
commencement of the work. All work within the Council road reserve will be monitored by
ETHEKWINI MUNICIPALITY
CONDITIONS PERTAINING TO APPROVAL OF WAYLEAVES
No obstructions to sidewalks and roadways are permitted. In this regard, Pedestrians and
The proving of underground services and the relocation thereof, if necessary, will be their
instatements, including backfilling, compaction and testing of excavations to be to
The Road and Stormwater Maintenance Department will carry out the final road re-
instatement and requisitions for such work must be forwarded by your organization
the excavator until completion of final re-
instatements. Claims arising during the construction of the proposed works and prior to any
final reinstatements being carried out by this department will be for your organization to
of manholes to suit the surrounding surface levels.
All excavations and allied works must be suitably barricaded and maintained until final
Saw cutting of the existing surfaced layers will be required, prior to any excavations taking
Mixing of concrete or mortar on the road or sidewalk surface is not permitted.
Construction materials are not to be left haphazardly on the road, sidewalk or verge at any
osed works to be removed off site as soon
Contractors carrying out work on your behalf to be adequately supervised at all times. Due
cognisance must be taken of the gazetted Occupational Health and Safety Act 85/1993:
The Unit reserves the right to halt progress at any time during the project should the above
Adequate notice of intention to commence work must be given to prior to the actual
commencement of the work. All work within the Council road reserve will be monitored by
this unit.
14. The Engineering Unit is to be included in any progress meetings held by yourselves.
15. This unit reserves the right to have it’s Materials Testin
testing of any or all road layer densities. Control testing will be y our responsibility with test
results being made available to this Unit on request.
16. With regard to road markings that will be affected due to the propos
organisation is to make arrangements with the Ethekwini Transport Authority’s Traffic
Operations Branch on telephone 031 311 7093 or 031 311 7334 prior to commencement of
the works.
17. A joint final inspection of the completed works forms part
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
37
The Engineering Unit is to be included in any progress meetings held by yourselves.
This unit reserves the right to have it’s Materials Testing Laboratory carry out acceptance
testing of any or all road layer densities. Control testing will be y our responsibility with test
results being made available to this Unit on request.
With regard to road markings that will be affected due to the proposed works, your
organisation is to make arrangements with the Ethekwini Transport Authority’s Traffic
Operations Branch on telephone 031 311 7093 or 031 311 7334 prior to commencement of
A joint final inspection of the completed works forms part of this agreement.
ETHEKWINI MUNICIPALITY
The Engineering Unit is to be included in any progress meetings held by yourselves.
g Laboratory carry out acceptance
testing of any or all road layer densities. Control testing will be y our responsibility with test
ed works, your
organisation is to make arrangements with the Ethekwini Transport Authority’s Traffic
Operations Branch on telephone 031 311 7093 or 031 311 7334 prior to commencement of
of this agreement.
ENGINEERING UNIT ROADS AND STORMWATER MAINTENANCE DEPARTMENT EXCAVATION AND REINSTATEMENT OF TRENCHES IN ROADS AND SIDEWALKS IN THE EMA AREA PROJECT SPECIFICATIONS AND REQUIREMENTS EXCAVATION OF TRENCHES
• Trenches that are excavated for service provisions and upgrading purposes on roads or
sidewalks will be done so in compliance to Departmental requirements pertaining to
accommodating traffic. Both vehicular and pedestrian, thereby ensuring their s
other Health and Safety requirements to both the public and the contractors own personnel
needs to be complied with.
• The Roads Department will be kept informed in advance of all proposed excavations in
roads and sidewalks. The option of trenchl
all avenues to auger bore have been exhausted, will trenching be permitted and in writing
by the Roads Department.
• Where the proposed excavation falls within existing works being undertaken by any
department or service provider, the Excavation Department/Contractor will liaise
accordingly for ease of implementation and re
• Spoil emanating from the trench excavation will be removed to a designated spoil site soon
after the trench has been e
be adequately barricaded. Where the spoil is dumped on private properties by agreement,
the Municipality will be indemnified in writing, against any future claims or queries.
• Where the trench traverses through gardens, flower beds and neat grassed areas, the
contractor needs to liaise with the relevant authority or owner prior to the work
commencing.
• In developed and CBD areas all property owners and businesses will be informed of the
intended work prior to same commencing.
BACKFILLING OF TRENCHES
• All trenches will be backfilled with suitable material that is easily workable and
compactable, in layers not exceeding 200mm (loose) thickness. The backfill material
will be free of grass, roots,
the backfill material is too dry, it will be moistened prior to placing and compacting.
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
38
ROADS AND STORMWATER MAINTENANCE DEPARTMENT EXCAVATION AND REINSTATEMENT OF TRENCHES IN ROADS AND SIDEWALKS IN THE
PROJECT SPECIFICATIONS AND REQUIREMENTS
TRENCHES
Trenches that are excavated for service provisions and upgrading purposes on roads or
sidewalks will be done so in compliance to Departmental requirements pertaining to
accommodating traffic. Both vehicular and pedestrian, thereby ensuring their s
other Health and Safety requirements to both the public and the contractors own personnel
needs to be complied with.
The Roads Department will be kept informed in advance of all proposed excavations in
roads and sidewalks. The option of trenchless technology will be explored and only when
all avenues to auger bore have been exhausted, will trenching be permitted and in writing
by the Roads Department.
Where the proposed excavation falls within existing works being undertaken by any
r service provider, the Excavation Department/Contractor will liaise
accordingly for ease of implementation and re-instatement purposes.
Spoil emanating from the trench excavation will be removed to a designated spoil site soon
after the trench has been excavated. Should such spoil remain on site for reuse, same will
be adequately barricaded. Where the spoil is dumped on private properties by agreement,
the Municipality will be indemnified in writing, against any future claims or queries.
traverses through gardens, flower beds and neat grassed areas, the
contractor needs to liaise with the relevant authority or owner prior to the work
In developed and CBD areas all property owners and businesses will be informed of the
ed work prior to same commencing.
BACKFILLING OF TRENCHES
All trenches will be backfilled with suitable material that is easily workable and
compactable, in layers not exceeding 200mm (loose) thickness. The backfill material
will be free of grass, roots, rubbish, clay and aggregates greater than 50mm. Where
the backfill material is too dry, it will be moistened prior to placing and compacting.
ETHEKWINI MUNICIPALITY
EXCAVATION AND REINSTATEMENT OF TRENCHES IN ROADS AND SIDEWALKS IN THE
Trenches that are excavated for service provisions and upgrading purposes on roads or
sidewalks will be done so in compliance to Departmental requirements pertaining to
accommodating traffic. Both vehicular and pedestrian, thereby ensuring their safety. All
other Health and Safety requirements to both the public and the contractors own personnel
The Roads Department will be kept informed in advance of all proposed excavations in
ess technology will be explored and only when
all avenues to auger bore have been exhausted, will trenching be permitted and in writing
Where the proposed excavation falls within existing works being undertaken by any
r service provider, the Excavation Department/Contractor will liaise
instatement purposes.
Spoil emanating from the trench excavation will be removed to a designated spoil site soon
xcavated. Should such spoil remain on site for reuse, same will
be adequately barricaded. Where the spoil is dumped on private properties by agreement,
the Municipality will be indemnified in writing, against any future claims or queries.
traverses through gardens, flower beds and neat grassed areas, the
contractor needs to liaise with the relevant authority or owner prior to the work
In developed and CBD areas all property owners and businesses will be informed of the
All trenches will be backfilled with suitable material that is easily workable and
compactable, in layers not exceeding 200mm (loose) thickness. The backfill material
rubbish, clay and aggregates greater than 50mm. Where
the backfill material is too dry, it will be moistened prior to placing and compacting.
DCP TESTING OF BACKFILLING
• Each layer of 150mm thick compacted backfill shall be tested to the following
requirements using the standard 5kg DCP test method:
- Road Trenches: Minimum of 5 blows per 100mm penetration
-Sidewalk, driveways and median trenches: minimum of 3 blows per 100 mm
penetration
-Verge trenches: minimum of 2 blows per 100mm penetration
• Trenches in the verge (unhardened areas) may be backfilled and compacted in 300mm
loose layers.
• All test results will be recorded and handed to the Engineer on a weekly basis.
• The Engineer reserves the right to carry out his/her own DCP testing and should
minimum requirements not be achieved on completed work, the contractor will be
required to remove and redo the operation to ensure compliance.
ROAD CATEGORIES/ASPHALT TRENCH REINSTATEMENT
• The city’s network comprises of the following road categories
corresponding upper layer constructions:
-CATEGORY A: 150mm G2 Crusher run and 240mm mix D Asphalt
-CATEGORY B: 150mm G2 Crusher run and 160mm mix D Asphalt
-CATEGORY C: 150mm G2 Crusher run and 80mm mix D Asphalt
-CATEGORY D: 150mm G2 Crusher
-CATEGORY E: 100mm G2 Crusher run and 25mm mix A Asphalt (driveway &
sidewalks)
The onus is on the excavator department/contractor to ascertain from the Roads
Department as to what category a certain road falls under.
• Asphalt will be compacted in layers not exceeding 800mm thick (after compaction)
• G2 Crusher run will be adequately moistened and mixed prior to placing and
compacting.
• The DCP test requirements on the G2 crushed stone layer is a minimum of 15
blows per 100mm pene
• All loose material will be swept off prior to the placing and compacting of Asphalt.
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
39
DCP TESTING OF BACKFILLING
Each layer of 150mm thick compacted backfill shall be tested to the following
requirements using the standard 5kg DCP test method:
Road Trenches: Minimum of 5 blows per 100mm penetration
Sidewalk, driveways and median trenches: minimum of 3 blows per 100 mm
Verge trenches: minimum of 2 blows per 100mm penetration
renches in the verge (unhardened areas) may be backfilled and compacted in 300mm
All test results will be recorded and handed to the Engineer on a weekly basis.
The Engineer reserves the right to carry out his/her own DCP testing and should
minimum requirements not be achieved on completed work, the contractor will be
required to remove and redo the operation to ensure compliance.
ROAD CATEGORIES/ASPHALT TRENCH REINSTATEMENT
The city’s network comprises of the following road categories
corresponding upper layer constructions:
CATEGORY A: 150mm G2 Crusher run and 240mm mix D Asphalt
CATEGORY B: 150mm G2 Crusher run and 160mm mix D Asphalt
CATEGORY C: 150mm G2 Crusher run and 80mm mix D Asphalt
CATEGORY D: 150mm G2 Crusher run and 50mm mix D Asphalt
CATEGORY E: 100mm G2 Crusher run and 25mm mix A Asphalt (driveway &
The onus is on the excavator department/contractor to ascertain from the Roads
Department as to what category a certain road falls under.
ill be compacted in layers not exceeding 800mm thick (after compaction)
G2 Crusher run will be adequately moistened and mixed prior to placing and
The DCP test requirements on the G2 crushed stone layer is a minimum of 15
blows per 100mm penetration.
All loose material will be swept off prior to the placing and compacting of Asphalt.
ETHEKWINI MUNICIPALITY
Each layer of 150mm thick compacted backfill shall be tested to the following
Sidewalk, driveways and median trenches: minimum of 3 blows per 100 mm
renches in the verge (unhardened areas) may be backfilled and compacted in 300mm
All test results will be recorded and handed to the Engineer on a weekly basis.
The Engineer reserves the right to carry out his/her own DCP testing and should the
minimum requirements not be achieved on completed work, the contractor will be
required to remove and redo the operation to ensure compliance.
The city’s network comprises of the following road categories with the
CATEGORY A: 150mm G2 Crusher run and 240mm mix D Asphalt
CATEGORY B: 150mm G2 Crusher run and 160mm mix D Asphalt
CATEGORY C: 150mm G2 Crusher run and 80mm mix D Asphalt
run and 50mm mix D Asphalt
CATEGORY E: 100mm G2 Crusher run and 25mm mix A Asphalt (driveway &
The onus is on the excavator department/contractor to ascertain from the Roads
ill be compacted in layers not exceeding 800mm thick (after compaction)
G2 Crusher run will be adequately moistened and mixed prior to placing and
The DCP test requirements on the G2 crushed stone layer is a minimum of 15
All loose material will be swept off prior to the placing and compacting of Asphalt.
• All liquid emulsion will be brush applied at 0.3 l/m2 to the vertical sides of the
existing trench.
• The finish levels will be true to the surrounding existing
CONCRETE AND BRICK PAVED AREAS
• The CBD sidewalks are generally brick or concrete paved and therefore the
reinstatement of trenches in these areas will be undertaken to match existing.
• Areas covered in special type pavers where trenc
pavers will be carefully removed and stored for reuse as the availability of new
materials for reinstating these areas are minimum. The Contractor will take full
responsibility for removing, storing and safekeeping of the
reuse.
• The following mix proportions are to be used when undertaking trench
reinstatement work.
-Bedding for brick paved and concrete slabbed areas: Minimum 500mm thick riversand mixed with cement at a ratio of 10:1 i.e 5 wheelbpocket of cement. -Joints to precast slabs will comprise of a 3:1 plaster sand/cement mix i.e 1 ½ wheelbarrows o plaster sand to 1 pocket of cement. -Cast insitu concrete slabs will comprise of a full depth of 100mm, 75mm of whis concrete and 25mm Umgeni/cement topping. Both layers are required to be constructed simultaneously. -Should ready blend be used to mix the 75mm thick concrete, a mix ratio of 6:1 will be used i.e. 3 wheelbarrows of ready blend to 1 pocket of topping, a mix proportion of 2:1 will be used i.e. 1 wheelbarrow of riverpocket of cement. Cast insitu slabs in non CBD areas may be constructed with a full depth of 100mm concrete using a 6:1 ready blend/cement mix. Either option requires that the concrete be wood floated and joints formed to match existing. Should stone, sand and cement be used as separate mix materials for mixing concrete, then a mix proportion of 3:3:1 will be used i.e 3 wheelbarrows of stone, 3 wheelbarrows of river
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
40
All liquid emulsion will be brush applied at 0.3 l/m2 to the vertical sides of the
The finish levels will be true to the surrounding existing road/sidewalk levels.
CONCRETE AND BRICK PAVED AREAS
The CBD sidewalks are generally brick or concrete paved and therefore the
reinstatement of trenches in these areas will be undertaken to match existing.
Areas covered in special type pavers where trench excavation is to take place, the
pavers will be carefully removed and stored for reuse as the availability of new
materials for reinstating these areas are minimum. The Contractor will take full
responsibility for removing, storing and safekeeping of the removed materials for
The following mix proportions are to be used when undertaking trench
reinstatement work.
Bedding for brick paved and concrete slabbed areas: Minimum 500mm thick riversand mixed with cement at a ratio of 10:1 i.e 5 wheelbarrows of river sand to 1 pocket of cement.
Joints to precast slabs will comprise of a 3:1 plaster sand/cement mix i.e 1 ½ wheelbarrows o plaster sand to 1 pocket of cement.
Cast insitu concrete slabs will comprise of a full depth of 100mm, 75mm of whis concrete and 25mm Umgeni/cement topping. Both layers are required to be constructed simultaneously.
Should ready blend be used to mix the 75mm thick concrete, a mix ratio of 6:1 will be used i.e. 3 wheelbarrows of ready blend to 1 pocket of cement. For the 25mm topping, a mix proportion of 2:1 will be used i.e. 1 wheelbarrow of riverpocket of cement.
Cast insitu slabs in non CBD areas may be constructed with a full depth of 100mm concrete using a 6:1 ready blend/cement mix.
er option requires that the concrete be wood floated and joints formed to match
Should stone, sand and cement be used as separate mix materials for mixing concrete, then a mix proportion of 3:3:1 will be used i.e 3 wheelbarrows of stone, 3
barrows of river-sand and 2 pockets of cement.
ETHEKWINI MUNICIPALITY
All liquid emulsion will be brush applied at 0.3 l/m2 to the vertical sides of the
road/sidewalk levels.
The CBD sidewalks are generally brick or concrete paved and therefore the
reinstatement of trenches in these areas will be undertaken to match existing.
h excavation is to take place, the
pavers will be carefully removed and stored for reuse as the availability of new
materials for reinstating these areas are minimum. The Contractor will take full
removed materials for
The following mix proportions are to be used when undertaking trench
Bedding for brick paved and concrete slabbed areas: Minimum 500mm thick river-arrows of river sand to 1
Joints to precast slabs will comprise of a 3:1 plaster sand/cement mix i.e 1 ½
Cast insitu concrete slabs will comprise of a full depth of 100mm, 75mm of which is concrete and 25mm Umgeni/cement topping. Both layers are required to be
Should ready blend be used to mix the 75mm thick concrete, a mix ratio of 6:1 will cement. For the 25mm
topping, a mix proportion of 2:1 will be used i.e. 1 wheelbarrow of river-sand to 1
Cast insitu slabs in non CBD areas may be constructed with a full depth of 100mm
er option requires that the concrete be wood floated and joints formed to match
Should stone, sand and cement be used as separate mix materials for mixing concrete, then a mix proportion of 3:3:1 will be used i.e 3 wheelbarrows of stone, 3
TRENCHES IN VERGE AREAS
• Where trenches are excavated and required to be reinstated in unhardened or grassed
areas, the following will apply.
• The final 75-100mm of backfill will comprise of organic topsoi
off flush
with the surrounding ground level. No humps or bumps will be permitted.
• All loose stones and other obstructions will be moved to spoil.
• The establishment of suitable ground cover over the trench width will be the
of the Excavator Department/Contractor.
SERVICE RELATED STRUCTURES
• Where minor structures such as chambers, manholes, earth retainers and connecting
junction boxes are to be erected, the following requirements shall apply.
• All structures are to be constructed in accordance with an approved design detail, provided
by the Excavator Department and passed through the Roads Department.
• All exposed vertical surfaces above ground will either be of face brick (satin red) or
reinforced concrete with an off shutter class 1 finish.
• Where earth retainers such as loffestein blocks are used, same shall be erected to the
manufactures guidelines, specifications and recommendations.
• Generally manhole covers will comprise of a reinforced concrete slab whic
standard access cover and lid. The finish on the concrete covers will be to a wood floated
finish. In asphalt, brick and other special paved areas, the finish on the cover slabs will be
such that it matches the existing surface finish. The
horizontal with the surrounding surface modified to suit, so as to avoid sudden change in
levels.
• The mixing of mortar and concrete on existing paved surfaces will be avoided and where
same is unavoidable, the affe
completion of the day’s operations.
SPECIAL REQUIREMENTS
• The main contractor/project manager is required to ensure that effective and timeous
communication and interaction takes place between the civils
instating contractor
• Where excavated trench material has ended up in the stormwater inlet and catchpit, the
contractor will be required to remove, ensuring that the incoming and outgoing pipes are
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
41
TRENCHES IN VERGE AREAS
Where trenches are excavated and required to be reinstated in unhardened or grassed
areas, the following will apply.
100mm of backfill will comprise of organic topsoil material, placed and leveled
with the surrounding ground level. No humps or bumps will be permitted.
All loose stones and other obstructions will be moved to spoil.
The establishment of suitable ground cover over the trench width will be the
of the Excavator Department/Contractor.
SERVICE RELATED STRUCTURES
Where minor structures such as chambers, manholes, earth retainers and connecting
junction boxes are to be erected, the following requirements shall apply.
re to be constructed in accordance with an approved design detail, provided
by the Excavator Department and passed through the Roads Department.
All exposed vertical surfaces above ground will either be of face brick (satin red) or
h an off shutter class 1 finish.
Where earth retainers such as loffestein blocks are used, same shall be erected to the
manufactures guidelines, specifications and recommendations.
Generally manhole covers will comprise of a reinforced concrete slab whic
standard access cover and lid. The finish on the concrete covers will be to a wood floated
finish. In asphalt, brick and other special paved areas, the finish on the cover slabs will be
such that it matches the existing surface finish. The finish level on manhole covers shall be
horizontal with the surrounding surface modified to suit, so as to avoid sudden change in
The mixing of mortar and concrete on existing paved surfaces will be avoided and where
same is unavoidable, the affected area will be properly cleaned and washed off on
completion of the day’s operations.
The main contractor/project manager is required to ensure that effective and timeous
communication and interaction takes place between the civils contractor and the re
Where excavated trench material has ended up in the stormwater inlet and catchpit, the
contractor will be required to remove, ensuring that the incoming and outgoing pipes are
ETHEKWINI MUNICIPALITY
Where trenches are excavated and required to be reinstated in unhardened or grassed
l material, placed and leveled
with the surrounding ground level. No humps or bumps will be permitted.
The establishment of suitable ground cover over the trench width will be the responsibility
Where minor structures such as chambers, manholes, earth retainers and connecting
junction boxes are to be erected, the following requirements shall apply.
re to be constructed in accordance with an approved design detail, provided
by the Excavator Department and passed through the Roads Department.
All exposed vertical surfaces above ground will either be of face brick (satin red) or
Where earth retainers such as loffestein blocks are used, same shall be erected to the
Generally manhole covers will comprise of a reinforced concrete slab which incorporates a
standard access cover and lid. The finish on the concrete covers will be to a wood floated
finish. In asphalt, brick and other special paved areas, the finish on the cover slabs will be
finish level on manhole covers shall be
horizontal with the surrounding surface modified to suit, so as to avoid sudden change in
The mixing of mortar and concrete on existing paved surfaces will be avoided and where
cted area will be properly cleaned and washed off on
The main contractor/project manager is required to ensure that effective and timeous
contractor and the re-
Where excavated trench material has ended up in the stormwater inlet and catchpit, the
contractor will be required to remove, ensuring that the incoming and outgoing pipes are
free of same. Should pressure jetti
• Where trench reinstatements are undertaken by resources employed by the
Excavator/Civils Contractor, the trenches are required to be permanently reinstated within
a period of not exceeding 7 days from d
• All reinstatements undertaken will carry a maintenance guarantee period of 12 months
from the date of completion of the works being handed over to the Roads Department.
• Should the contract not comply with the Departmental requireme
the instructions from the Municipal Official to make good or comply, then the Municipality
reserves the right of requesting that such contractor be removed off site
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
42
free of same. Should pressure jetting be required to clean same, this must be arranged.
Where trench reinstatements are undertaken by resources employed by the
Excavator/Civils Contractor, the trenches are required to be permanently reinstated within
a period of not exceeding 7 days from date of final backfill.
All reinstatements undertaken will carry a maintenance guarantee period of 12 months
from the date of completion of the works being handed over to the Roads Department.
Should the contract not comply with the Departmental requirements and continue to ignore
the instructions from the Municipal Official to make good or comply, then the Municipality
reserves the right of requesting that such contractor be removed off site
ETHEKWINI MUNICIPALITY
ng be required to clean same, this must be arranged.
Where trench reinstatements are undertaken by resources employed by the
Excavator/Civils Contractor, the trenches are required to be permanently reinstated within
All reinstatements undertaken will carry a maintenance guarantee period of 12 months
from the date of completion of the works being handed over to the Roads Department.
nts and continue to ignore
the instructions from the Municipal Official to make good or comply, then the Municipality
reserves the right of requesting that such contractor be removed off site
REGIONAL CONTRACT
• Should the need arise to make contact with a Roads Department official for any reason or
clarity, the following shall apply:
Road Maintenance HQ
REGIONAL SUBURBS
1.) North Region Verulam, Tongaat, Phoenix, Inanda and Ntunzuma
2.) North Central Region Umhlanga, Durban North, KwaMashu, Newlands, Springfield, Durban, CBD, Berea, Maydon Wharf
3.) South Central Region Bellair, Catomanor, Clairwood, Bluff, Yellowood Park, Chatsworth, Umlazi, Isipingo and Prospecton
South Region Toti, Kingsburgh, Illovo, Folweni, Umkomaas
West Central Region: Pinetown, Westville, Reservoir Hills, Westmeath, Shall cross, Marianhill, Kwadengezi, Clemont, Kwadabeka
West Region Hillcrest, Kloof, Hammarsdale, Cateridge, Molweni
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
43
the need arise to make contact with a Roads Department official for any reason or
clarity, the following shall apply:
Barlla Munsamy (Admin Officer)
Tel: 031 311 7893Fax: 031 311 7691E-mail: [email protected]
MANAGER CONTACT DETAILS
Kevin Govender Tel: 031 Cell: 083 637 9266E-mail: [email protected]
Shan Govender Tel: 031 311 74 27Cell: 083 270 0234E-mail: govenderv@
Thomas Govender Tel: 031 466 8666Cell: 083 270 0234E-mail: govedertho
Peter Dally Tel: 031 311 5955Cell: 083 256 4412E-mail: [email protected]
Pinetown, Westville, Reservoir Siggie Miller Tel: 031 311 6403
Cell: 083 287 8582E-mail: [email protected]
Hillcrest, Kloof, Hammarsdale, Richard Mngoma Tel: 031 311 2736
Cell: 072 112 5030E-mail: [email protected]
ETHEKWINI MUNICIPALITY
the need arise to make contact with a Roads Department official for any reason or
Tel: 031 311 7893 Fax: 031 311 7691
CONTACT DETAILS
Cell: 083 637 9266
Tel: 031 311 74 27 Cell: 083 270 0234
Tel: 031 466 8666 Cell: 083 270 0234
Tel: 031 311 5955 Cell: 083 256 4412
Tel: 031 311 6403 Cell: 083 287 8582
Tel: 031 311 2736 Cell: 072 112 5030
Instructions To Contractors
1. Only 48 core LC patch panels must be used forMetroConnect equipment is located such as UMH fire station.
2. Use any existing patch panel that is at the PoP sites first before installing a new one. We will run out of space if every contractor uses a new patsplice trays.
3. Any new cabinet on site must be recessed 6 or 7 holes before the fibre splice trays are mounted in the cabinet
4. When a new splice tray is installed make sure enough slack is left so that future work in splice trays is not difficult.
5. At subscriber sites 24 core LC patch panels must be used.
6. Only 4-way dome joints must be used on any new dome joint installation.
7. When submitting an RFQ response, no maps are to be submitted unless your proposed route deviates from MC planned route.
8. Manholes are to be created 200m apart unless change in route direction is required or at 30 to 90 degree bend.
9. Manhole Spec (include locking mechanism) :drop-in
10. Fibre Spec : Proposed fibre is Systimax 11. As built map to be submitted on CAD and on Topographical Map.12. GPS co-ordinates to be provided in this format only : Long 30.123456
13. Completion file to be submitted as per MC
ETHEKWINI MUNICIPALITY
FIBRE OPTIC STANDARDS
44
Additional Comments.
Instructions To Contractors - 28 October 2009
Only 48 core LC patch panels must be used for any new install at a PoP site i.e. where the MetroConnect equipment is located such as UMH fire station.
Use any existing patch panel that is at the PoP sites first before installing a new one. We will run out of space if every contractor uses a new patch panel and not make use of existing
Any new cabinet on site must be recessed 6 or 7 holes before the fibre splice trays are
When a new splice tray is installed make sure enough slack is left so that future work in
At subscriber sites 24 core LC patch panels must be used.
way dome joints must be used on any new dome joint installation.
When submitting an RFQ response, no maps are to be submitted unless your proposed route deviates from MC planned route. Manholes are to be created 200m apart unless change in route direction is required or at 30 to
Manhole Spec (include locking mechanism) : Proposed manhole is the Maverick round lid,
oposed fibre is Systimax As built map to be submitted on CAD and on Topographical Map.
ordinates to be provided in this format only : Long 30.123456 Lat
Completion file to be submitted as per MC template/sample
ETHEKWINI MUNICIPALITY
PoP site i.e. where the
Use any existing patch panel that is at the PoP sites first before installing a new one. We will ch panel and not make use of existing
Any new cabinet on site must be recessed 6 or 7 holes before the fibre splice trays are
When a new splice tray is installed make sure enough slack is left so that future work in the
way dome joints must be used on any new dome joint installation.
When submitting an RFQ response, no maps are to be submitted unless your proposed route
Manholes are to be created 200m apart unless change in route direction is required or at 30 to
Proposed manhole is the Maverick round lid,
Lat -29.123456