+ All Categories
Home > Documents > Appendix B SI

Appendix B SI

Date post: 16-Sep-2015
Category:
Upload: andres2563
View: 15 times
Download: 0 times
Share this document with a friend
Description:
trabajo de obras
Popular Tags:
21
B SI Unit Highway Bridge Bid-Item Summary Sheets 323
Transcript
  • BSI Unit HighwayBridge Bid-ItemSummarySheets

    323

  • Job: Highway Bridge Bid Item No. 1: Excavation, unclassifed

    32220.10 Excavation, unclassified

    1,275 m3 Laborforeman 1 @ $34.00 = $34.00operator 1 @ $33.00 = $33.00laborer 2 @ $22.00 = $44.00

    Crew hourly rate = $111.00production rate = 53.5 m3/hr

    1,275 53.5 x $111.00 = $2,643 $2,643 $925 $3,569Equipmentdozer 1 @ $39.00 per hr

    1,275 54 x $39.00 = $929 $929 $929Total this account $2,643 $925 $929 $0 $4,497

    $2,643 $925Total Bid Item No. 1 $3,569 $929 $0 $4,497

    Estimator: GAS Equipment

    CostMaterial

    CostTotalCost

    Summary Sheet

    CostCode

    Labor CostWork Type Quantity Unit Calculations Direct Indirect

    324

  • Job: Highway Bridge Bid Item No. 2: Excavation, structural

    32222.10 Excavation, structural

    92 m3 Laborforeman

    1 @

    $34.00 = $34.00operator $33.00 = $33.00laborers $22.00 = $132.00

    Crew hourly rate = $199.00production rate = 6.1 m3/hr

    92 6.1

    6

    x $199.00 = $2,985 $2,985 $746 $3,731Equipmentbackhoe $37.00 per hr

    92 x $37.00 = $555 $555 $555Total this account $2,985 $746 $555 $0 $4,286

    $2,985 $746Total Bid Item No. 2 $3,731 $555 $0 $4,286

    Estimator: GAS Equipment

    CostMaterial

    CostTotalCost

    Summary Sheet

    CostCode

    Labor CostWork Type Quantity Unit Calculations Direct Indirect

    1 @1 @

    6 @

    325

  • Job: Highway Bridge Bid Item No. 3: Backfill, compacted

    32226.10 Backfill,compacted

    260 m3 Laborlabor unit cost = $11.05 per m3

    260 x $11.05 = $2,872 $2,872 $718 $3,591Equipmentequipment unit cost = $2.55 per m3

    260 x $2.55 = $663 $663 $663Total this account $2,872 $718 $663 $0 $4,254

    $2,872 $718Total Bid Item No. 3 $3,591 $663 $0 $4,254

    Estimator: GAS Equipment

    CostMaterial

    CostTotalCost

    Summary Sheet

    CostCode

    Labor CostWork Type Quantity Unit Calculations Direct Indirect

    326

  • 327

  • 328

  • 329

  • 330

  • 22

    2

    331

  • 332

  • Job: Highway Bridge Bid Item No. 8a: Reinforcing steel

    03200.00 Steel, reinforcing, place

    40,823 kg Labor:labor unit cost = $0.64 per kg40,823 x $0.64 = $26,100 $26,100 $11,745 $37,844

    Equipment:equipment unit cost = $0.13 per kg40,823 x $0.13 = $5,400 $5,400 $5,400

    Materials:material unit cost = $0.93 per kg40,823 x $0.93 = $37,798 $37,798 $37,798

    Total this account $26,100 $11,745 $5,400 $37,798 $81,042$26,100 $11,745

    Total Bid Item No. 8a $37,844 $5,400 $37,798 $81,042

    Job: Highway Bridge Bid Item No. 8b: Reinforcing steel (Subcontracted)

    03200.00 Steel, reinforcing,place

    40,823 kg Subcontractsubbid quotation = $66,240 $0 $0 $0 $66,240

    $0 $0Total Bid Item No. 8b $0 $0 $0 $66,240

    Estimator: GAS Equipment

    CostMaterial

    CostTotalCost

    Summary Sheet

    CostCode

    Labor CostWork Type Quantity Unit Calculations Direct Indirect

    Estimator: GAS Equipment

    CostMaterial

    CostTotalCost

    Summary Sheet

    CostCode

    Labor CostWork Type Quantity Unit Calculations Direct Indirect

    333

  • Job: Highway Bridge Bid Item No. 9: Steel, structural

    05120.00 Steel, structural, place

    29,710 kg Labor:labor unit cost = $0.068 per kg29,710 x $0.07 = $2,030 $2,030 $914 $2,944

    16 hours of 50-ton crane timeoperator 1 @

    @$33.00

    oiler 1 $22.00Crew hourly r = $55.00

    16 x $55.00 = $880.00 $880 $396 $1,276Equipment:

    16 hours of 50-ton crane time16 x $105 = $1,680 $1,680 $1,680

    Material:material unit cost = $2,480.20 per tn29,710 1,000 x $2,480 = $73,687 $73,687 $73,687

    Total this account $2,910 $1,310 $1,680 $73,687 $79,588$2,910 $1,310

    Total Bid Item No. 9 $4,220 $1,680 $73,687 $79,588

    Estimator: GAS Equipment

    CostMaterial

    CostTotalCost

    Summary Sheet

    CostCode

    Labor CostWork Type Quantity Unit Calculations Direct Indirect

    334

  • Job: Highway Bridge Bid Item No. 10: Bearing plates

    05812.00 Bearing plates 1,451 kg Laborlabor unit cost = $0.77 per kg

    1,451 x $0.77 = $1,119.97 $1,120 $504 $1,6244 hours of 50-ton crane time

    operator 1 @ $33.00oiler 1 @ $22.00

    Crew hourly rate = $55.004 x $55.00 = $220.00 $220 $99 $319

    Equipment4 hours of 50-ton crane time4 x $105 = $420.00 $420 $420

    Materialsprice quotation = $3,250 $3,250 $3,250Total this account $1,340 $603 $420 $3,250 $5,613

    $1,340 $603Total Bid Item No. 10 $1,943 $420 $3,250 $5,613

    Estimator: GAS Equipment

    CostMaterial

    CostTotalCost

    Summary Sheet

    CostCode

    Labor CostWork Type Quantity Unit Calculations Direct Indirect

    335

  • Job: Highway Bridge Bid Item No. 11: Guardrails

    05520.00 Guardrails 37 m Laborlabor unit cost = $27.23 per m

    37 x $27.23 = $996 $996 $349 $1,3454 hours of 50-ton crane time

    operator 1 @ $33.00oiler 1 @ $22.00

    Crew hourly rate = $55.004 x $55.00 = $220.00 $220 $99 $319

    Equipment4 hours of 50-ton crane time4 x $105 = $420.00 $420 $420

    Materialsprice quotation = $5,650 $5,650 $5,650anchor bolts 64 @ $2.75 = $176 $176 $176Total this account $1,216 $448 $420 $5,826 $7,910

    $1,216 $448Total Bid Item No. 11 $1,664 $420 $5,826 $7,910

    Job: Highway Bridge Bid Item No. 12: Painting

    Painting job ls subbid quotation = $8,550 $0 $0 $0 $8,550$0 $0

    Total Bid Item No. 12 $0 $0 $0 $8,550

    Estimator: GAS Equipment

    CostMaterial

    CostTotalCost

    Summary Sheet

    CostCode

    Labor CostWork Type Quantity Unit Calculations Direct Indirect

    Estimator: GAS Equipment

    CostMaterial

    CostTotalCost

    Summary Sheet

    CostCode

    Labor CostWork Type Quantity Unit Calculations Direct Indirect

    336

  • Summary Sheet

    Job: Highway Bridge Field Overhead: Move in & Cleanup Estimator: GASCost Labor Cost Equipment Material TotalCode Work Type Quantity Unit Calculations Direct Indirect Cost Cost Cost

    01500.00 Move In 1 ls Laborforeman 1 @ $34.00 = $34.00carpenters 2 @ $31.00 = $62.00laborers 4 @ $22.00 = $88.00operator 2 @ $33.00 = $66.00truck drivers 4 @ $22.00 = $88.00Crew hourly rate $338.00Three 8-hour days required

    3 x 8 x $338.00 = $8,112 $8,112 $2,839 $10,951Equipment50-ton crane 1 @ $105.00 = $105.0025-ton crane 1 @ $62.00 = $62.00atbed trucks 4 @ $25.00 = $100.00Equipment hourly rate $267.0012 hours required

    12 x $267.00 = $3,204 $3,204 $3,204Total this account $8,112 $2,839 $3,204 $0 $14,155

    01700.00 Cleanup 1 ls Laborforeman 1 @ $34.00 = $34.00laborers 6 @ $22.00 = $132.00Crew hourly rate $166.00Two 8-hour days required

    2 x 8 x $166.00 = $2,656 $2,656 $664 $3,320foreman 1 @ $34.00 = $34.00laborers 3 @ $22.00 = $66.00operator 1 @ $33.00 = $33.00Oiler 1 @ $22.00 = $22.00truck drivers 2 @ $22.00 = $44.00Crew hourly rate $199.00One 8-hour day required

    8 x $199.00 = $1,592 $1,592 $557 $2,149Equipment50-ton crane 1 @ $105.00 = $105.00Flatbed trucks 2 @ $25.00 = $50.00Equipment hourly rate $155.00One 8-hour day required

    8 x $155.00 = $1,240 $1,240 $1,240Total this account $4,248 $1,221 $1,240 $0 $6,709

    $12,360 $4,060Total Move In & Cleanup $16,420 $4,444 $0 $20,864

    337

  • 338 B SI Unit Highway Bridge Bid-Item Summary Sheets

    CFixed

    Bearing

    60-0 (18288 mm) c.c. bearings

    Presentground surface

    28 - 12 54 steel H piles,each 40 ft.(12192 mm) long

    Abut.no. 1

    Abut.no. 2

    CExpansion

    bearing

    Figure B.1Highway bridge, prole

    Bridge 150(4572 mm)

    16(457 mm)

    Guardrail

    W 36150typical

    10 (254 mm) reinforced concrete pavement

    46(1372 mm)

    C

    46(1372 mm)

    46(1372 mm)

    10(254 mm)

    Figure B.2Highway bridge, transverse section

  • B SI Unit Highway Bridge Bid-Item Summary Sheets 339

    Work QuantitiesCostCode WorkType Unit Quantity

    Sitework:02220.10 Excavation, unclassied m3 1,274.502222.10 Excavation, structural m3 91.702226.10 Backfill, compacted m3

    m

    259.902350.00 Piledriving rig, mobilization & demobilization ls job02361.10 Piling, steel, driving 682.8

    Concrete03150.10 Footing forms, fabricate m2 33.403150.20 Abutment forms, prefabricate m2 168.203157.10 Footing forms, place m2 66.903159.10 Footing forms, strip m2 66.903157.20 Abutment forms, place m2 336.303159.20 Abutment forms, strip m2 336.303157.30 Deck forms, place m2 167.203159.30 Deck forms, strip m2 167.203200.00 Steel, reinforcing, place kg 40,823.403251.30 Concrete, deck, saw joints m 18.303311.10 Concrete, footings, place m3 91.703311.20 Concrete, abutments, place m3 214.103311.30 Concrete, deck, place & screed m2 167.203345.30 Concrete, deck, nish m2 167.203346.20 Concrete, abutments, rub m2 182.103370.20 Concrete, abutments, curing m2 354.903370.30 Concrete, deck, curing m2 167.2

    Metals05120.00 Steel, structural, place kg

    m29,710.3

    05520.00 Guardrail 36.605812.00 Bearing plates kg 1,451.5

    Figure B.3Highway bridge, work quantities

    1 Excavation, unclassied m3 1,274.52 Excavation, structural m3 91.73 Backfill, compacted m3 259.94 Piling, steel m 682.85 Concrete, footings m3 91.76 Concrete, abutments m3 214.17 Concrete, deck slab, 10 in. m2 167.28 Steel, reinforcing kg 40,823.39 Steel, structural kg 29,710.0

    10 Bearing plates kg 1,451.511 Guardrail m 36.612 Paint ls job

    Total Estimated Amount =

    Unit Price ScheduleItemNo.[1]

    EstimatedQuantity

    [4]UnitPrice

    [5]EstimatedAmount

    [6]Description

    [2]Unit[3]

    Figure B.4Highway bridge, bid form

  • 340 B SI Unit Highway Bridge Bid-Item Summary Sheets

    / mo x/ mo x

    / mo mox/ mo x

    Project Overhead EstimateJob: Highway Bridge Estimator: GAS

    Overhead Item Calculations Amount TotalsProject manager $5,500 x 3.5

    x 3.5mo x 0.5 time = $9,625.00

    Project superintendent $5,000 mo = $17,500.00Utilities

    Electricity $225 / mo

    / mo/ mo/ mo

    / mo

    / mo

    / mo/ mo

    / mo

    Telephone $350Fax $100

    $675 x

    x

    x

    3.5 mo $2,362.50Utility installation charges (job) $1,520.00Facilities

    Job office $3502 ea. tool sheds $600Toilet $125

    $1,075 3.5 mo. = $3,762.50Travel expense $212 / wk x 15 wk = $3,180.00Water tank & water service $80 / wk x 15 wk =

    =

    $1,200.00Soil & concrete testing $600 3.5 $2,100.00Scaffolding $480 1 mo = $480.00Trash removal $190 3.5 mo = $665.00Tire repair $100 3.5 mo = $350.00Photographs $130 / mo x 3.5 mo = $455.00Computer $140 / mo x 3.5 mo = $490.00

    Subtotal of time variable overhead expenses = $43,690.00Surveys (job) $1,600.00Project insurance (job) $1,164.00First aid (job) $220.00Sign (job) $570.00Reproductions (job) $400.00Fence $6.56 / m 207 m = $1,360.00Move In See calculations, Appendix A $14,155.20Clean Up See calculations, Appendix A $6,709.20

    Subtotal of time constant overhead expenses = $26,178.40Total project overhead = $69,868.40

    =

    x

    Figure B.5Highway bridge, overhead estimate

  • Recap SheetBid Date: April 25, 20

    Job: Highway Bridge Estimator: GASItemNo.

    EstimatedQuantity

    LaborCost

    EquipmentCost

    MaterialCost

    SubcontractCost

    DirectCost

    BidTotalBid Item Unit Unit

    1 Excavation, unclassified $3,569 $929 $0 $0 $4,497 $6,386 $5.012 Excavation, structural $3,731 $555 $0 $0 $4,286 $6,086 $66.343 Backfill, compacted $3,591 $663 $0 $0 $4,254 $6,040 $23.234 Piling, steel $21,390 $11,176 $72,281 $0 $104,847 $148,876 $218.055 Concrete, footings $3,661 $685 $12,185 $0 $16,531 $23,473 $255.856 Concrete, abutments $37,458 $7,104 $30,541 $0 $75,103 $106,641 $498.157 Concrete, deck slab, 10 in. $11,745 $1,790 $8,020 $0 $21,554 $30,606 $183.028 Steel, reinforcing $0 $0 $0 $66,240 $66,240 $94,056 $2.3049 Steel, structural $4,220 $1,680 $73,687 $0 $79,588 $113,009 $3.804

    10 Bearing plates $1,943 $420 $3,250 $0 $5,613 $7,970 $5.4911 Guardrail $1,664 $420 $5,826 $0 $7,910 $11,231 $307.0612 Paint job $0 $0 $0 $8,550 $8,550 $12,140 $12,140.39

    Totals $92,972 $25,422 $205,790 $74,790 $398,974 $566,514Job overhead $69,868

    $468,842Small tools (5% of labor) $4,649

    $473,491Tax 3% $14,205

    Factor = $566,514 = 1.4199 $487,695$398,974 Markup 15% $73,154

    $560,850Bonds $5,665Total Project Bid $566,514

    m3 1,275m3 92m3 260m 683m3 92m3 214m2 167kg 40,823kg 29,710kg 1,451

    37lsm

    Note: Values change slightly from U.S. units in Figure 3.8 due to rounding errors.

    Figure B.6Highway bridge, recap sheet

    341

  • 342 B SI Unit Highway Bridge Bid-Item Summary Sheets

    Unit Price ScheduleItemNo.[1]

    EstimatedQuantity

    [4]UnitPrice

    [5]EstimatedAmount

    [6]1 Excavation, unclassified m3

    m3

    m3

    m

    m3

    m3

    m2

    kgkgkg

    lsm

    1,275 $5.01 $6,385.312 Excavation, structural 92 $66.34 $6,086.173 Backfill, compacted 260 $23.34 $6,038.614 Piling, steel 683 $218.05 $148,874.075 Concrete, footings 92 $255.85 $23,473.366 Concrete, abutments 214 $498.15 $106,641.647 Concrete, deck slab, 10 in. 167 $183.02 $30,605.618 Steel, reinforcing 40,823 $2.304 $94,056.919 Steel, structural 29,710 $3,804 $113,016.84

    10 Bearing plates 1,451 $5.49 $7,968.7111 Guardrail 37 $307.06 $11,231.0312 Paint job $12,140.39 $12,140.39

    Total Estimated Amount = $566,518.65

    Description[2]

    Unit[3]

    Note: Values change slightly from U.S. units in Figure 3.9 due to rounding errors.

    Figure B.7Highway bridge, complete bid form

  • General Requirements01500.00 Move In ls 1 $8,112 $8,112 $3,204 $3,204 $001700.00 Clean Up ls 1 $4,248 $4,248 $1,240 $1,240 $0

    Subtotals $12,360 $4,444 $0Sitework

    02220.10 Excavation, unclassified 1,275 m3 $2,643 $2.07 $929 $0.73 $002222.10 Excavation, structural 92 m3 $2,985 $32.54 $555 $6.05 $002226.10 Backfill, compacted 260 m3 $2,872 $11.05 $663 $2.55 $002350.00 Piledriving rig, mobilization & demobilization job ls $6,528 $6,528.00 $5,448 $5,448.00 $30002361.10 Piling, steel, driving 683 m $8,224 $12.05 $5,728 $8.39 $71,981

    Subtotals $23,253 $13,323 $72,281Concrete

    03150.10 Footing forms, fabricate 33 m2 $936 $27.99 $0 $0.00 $39203150.20 Abutment forms, prefabricate 168 m2 $3,548 $21.10 $0 $0.00 $2,15303157.10 Footing forms, place 67 m2 $360 $5.38 $0 $0.00 $20103159.10 Footing forms, strip 67 m2 $158 $2.37 $0 $0.00 $003157.20 Abutment forms, place 336 m2 $7,311 $21.74 $2,520 $7.49 $1,01403159.20 Abutment forms, strip 336 m2 $3,511 $10.44 $840 $2.50 $003157.30 Deck forms, place 167 m2 $3,190 $19.08 $420 $2.51 $1,89003159.30 Deck forms, strip 167 m2 $1,460 $8.73 $210 $1.26 $003251.30 Concrete, deck, saw joints 18 m $360 $19.68 $110 $6.01 $003311.10 Concrete, footings, place 92 m3 $1,200 $13.08 $685 $7.47 $11,59203311.20 Concrete, abutments, place 214 m3 $9,088 $42.45 $3,744 $17.49 $27,04803311.30 Concrete, deck, place & screed 167 m2 $1,200 $7.18 $980 $5.86 $5,41003345.30 Concrete, deck, finish 167 m2 $2,250 $13.45 $70 $0.42 $63003346.20 Concrete, abutments, rub 182 m2 $3,763 $20.66 $0 $0.00 $23503370.20 Concrete, abutments, curing 355 m2 $244 $0.69 $0 $0.00 $9203370.30 Concrete, deck, curing 167 m2 $108 $0.65 $0 $0.00 $90

    Subtotals $38,688 $9,579 $50,746Metals

    05120.00 Steel, structural, place 29,710 kg $2,910 $0.10 $1,680 $0.06 $73,68705520.00 Guardrail 37 m $1,216 $33.25 $420 $11.48 $5,82605812.00 Bearing plates 1,451 kg $1,340 $0.92 $420 $0.29 $3,250

    Subtotals $5,466 $2,520 $82,763

    Project BudgetJob: Highway Bridge Estimator: GAS

    CostCode

    DirectLabor Cost

    LaborUnit Cost

    EquipmentCost

    EquipmentUnit Cost

    MaterialCostWork Type Quantity Unit

    Note: Values change slightly from U.S. units in Figure 3.10 due to rounding errors.

    Figure B.8Highway bridge, project budget343


Recommended