Date post: | 24-Nov-2014 |
Category: | Documents |
View: | 110 times |
Download: | 3 times |
The District of Columbia Public Library Capital Construction Report February 17, 2011
Document #2 Facilities Committee Meeting February 17, 2011
Appendix E
Anacostia Library New Building Construction
ContactsCouncilmember Ward 7 Architect YvetteAlexander 202.724.8068 Freelon Group Philip Freelon 919.941.9790 Project Manager Dedric Boyd 202.727.1127 Forrester Construction Tom Willerton 301.816.1700
Progress
Opened to the public April 26, 2010
Contractor
New State of the Art Library on Good Hope Road SE is open.
DCPL PM Firm
Hill International
Benning Library New Building Design
ContactsCouncilmember Ward 7 YvetteAlexander 202.724.8068 Davis, Brody, Bond &Aedas Peter Cook 202.449.1190 Project Manager Contractor Kim Fuller 202.442.6069 Forrester Jon McGee 301.255.1750
Progress
Architect
Opened to the public April 5, 2010
New State of the Art Library located at 3935 Benning Road NE is open.
DCPL PM Firm
A-1 Consulting
2
ClevelandPark New Ceiling and Lighting
ContactsCouncilmember Ward 3 Architect Mary Cheh 202.724.8062N/A
Progress
Project Manager
Ed Hampton 202.442.6067 Eagle Construction
Project Complete
Contractor Project consists of installing a new ceiling and lighting system.
Deanwood New Community Center and Library
ContactsCouncilmember Ward 7 Architect YvetteAlexander 202.724.8068 EEK Sean ODonnell
Progress
Project Manager Contractor
Opened to the public June 25, 2010
Project is a partnership with the Department of Parks and Recreation to co-locate a 10,000 square foot library within a 54,000 square foot aquatic center and community center. Library and Community Center would share such space as computer lab, senior rooms, tutor rooms and community meeting rooms. Project location is 49th and Quarles St. NE
3
Energy Enhancement Projects Various Locations
ContactsCouncilmember Various
Progress
Capitol View, ClevelandPark, ShepherdPark, Lamond Riggs, Palisades, Southwest, West End and Woodridge
Architect
T.B.D
Project Manager Contractor The Library has received Federal Stimulus Money for energy enhancements. Projects will take place at the above locations, focusing on window replacements, energy efficient lighting, and automated building heating and cooling controls
Ed Hampton 202.442.6067
Contracts awarded: Coordination of implementation and potential closing dates underway.
DCPL PM Firm
Francis A. Gregory Library New Library
ContactsCouncilmember Ward 7 Architect YvetteAlexander 202.724.8068 Wiencek/Adjaye Scott Knudson 301.948.6220 Project Manager Contractor Lisa Deanes 202.727.5181 Hess Construction
Progress
Demolition work is complete. Sorting of materials for recycling is underway. Foundation work is underway.
Design of the new Francis Gregory Library will include community input on planning and programming phase. Project is fully funded.
DCPL PM Firm
Jair Lynch Development Partners
4
Francis A. Gregory Library Interim Library
ContactsCouncilmember Ward 7 Architect YvetteAlexander 202.724.8068
Progress
Project Manager
Lisa Deanes 202.727.5181
Opened June 10, 2010
Contractor Project consists of building a 4,200 square foot interim library to serve the community during construction; the interim will have 30 computers, books on CD as well as traditional collection material for all age sets
William Scotsman Greg Bichell
DCPL PM Firm
Georgetown Library Building Renovation
ContactsCouncilmember Ward 2 Architect Jack Evans 202.724.8058Martinez & Johnson
Progress
Tom Johnson 202.333.4480 Project Manager Contractor Chris Wright 202.272.4913 T.B.D.
Opened to the Public October 18, 2010
Design of the new Georgetown Library will include community input on planning and programming phase. Design phase is fully funded.
DCPL PM Firm
Smoot Construction
5
Mount Pleasant Interior Restoration
ContactsCouncilmember Ward 1 Architect Jim Graham 202.724.8181
Progress
Core Architects
Dale Stewart 202.466.6116 Project Manager Contractor Phase II of Mount Pleasant Renovation. Interior work will consist of total upgrade and modernization of all mechanical equipment as well as provide additional and functional library program space. Chris Wright 202.727.4913 T.B.D
Selective demolition and construction work is underway.
DCPL Project Management
Smoot Construction
Mount Pleasant Interim Library
ContactsCouncilmember Ward 1 Architect Jim Graham 202.724.8181
Progress
Core Architects
Dale Stewart 202.466.6116 Project Manager Contractor Project consists of building a 3,600 square foot interim library to serve the community during construction; the interim will have 30 computers, books on CD as well as traditional collection material for all age sets Dedric Boyd 202.727.1127 MCN Build Bassem Boustany 202.333.3424
Opened to the public April 26, 2010 Re-opened to the public May 15, 2010
6
Northeast Library Exterior Restoration
ContactsCouncilmember Ward 6 Architect Tommy Wells 202.724.8072
Progress
Bell Architects
David Bell 202.548.7570 Project Manager Chris Wright 202.727.4913 Monarc Construction C. McDermott, 703.201.1747
Construction y Substantial completion May 15, 2010
Contractor
Project consists of Exterior Improvements to windows, doors, security lighting, masonry restoration, landscaping and signage.
Northeast Library Pre-design Due Diligence
ContactsCouncilmember Ward 6 Architect Tommy Wells 202.724.8072
Progress
N/A
Pre-design due diligence work includes a hazardous materials survey, a Phase 1 and Phase 2 Environmental Site Assessment and a Cost Benefit Analysis Study.
Project Manager
Chris Wright 202.727.4913
Cost Benefit Analysis and Pre-design Due Diligence Reports - Complete No funding for design or construction
Consultant
McKissack & McKissack Ellen Wright 202.347.1446
7
Northwest One New Co-location Facility
ContactsCouncilmember Ward 6 Architect Tommy Wells
Progress
HordCort Plan
Project Manager Contractor
Reagan Assoc
Library Open December 7, 2009 Open to the Public
Forrester
Project consists of 6,500 SQ FT Library facility as part of Elementary School and RecreationCenter. This facility replaces the Sursum Corda kiosk.
Parklands-Turner New Storefront Library
ContactsCouncilmember Ward 8 Architect Marion Barry 202.724.8045
Progress
Mood Nolan - DC
Patrick Williams 202.244.4199 Project Manager Contractor Project to fit out approximately 5,000 Sq Ft of storefront space to replace the existing Parklands-Turner kiosk. The storefront library is similar in size, scope, computers, and collections to the Georgetown Interim and Tenley-Friendship Interim Libraries. Dedric Boyd 202.727.1129 Lexx Group Ken Postell 202.393.3085
Ribbon Cutting October 5, 2009 OPEN TO THE PUBLIC
8
Petworth Library Interim Library
ContactsCouncilmember Ward 4 Architect MurielBowser 202.724.8052 N/A
Progress
Project Manager Contractor Project consists of building a 4,200 square foot interim library to serve the community during construction; the interim will have 30 computers, books on CD as well as traditional collection material for all age sets
Lisa Deanes 202.727.5181 Sigal Construction Sarah Norman
Opened to public on January 11, 2010 Closed February 5, 2011
DCPL PM Firm
Petworth Interior Renovations
ContactsCouncilmember Councilmember Ward 4 Architect MurielBowser 202.724.8052Frank and Loshen
Progress
Fletcher Farr Anoyte Project Manager Contractor Project will update the interior of the Petworth Library to be a fully functional state of the art 21st Century Library, while still being respectful of the buildings historic character.
Chris Wright 202.727.4913 Sigal Construction Sarah Norman
Main Library closed December 20, 2009 Construction Complete. Move-in underway. Library will open February 28, 2011
DCPL PM Firm
McKissack and McKissack
9
Tenley Friendship New Building
ContactsCouncilmember Ward 3 Architect Mary Cheh 202.724.8062 Freelon Group Philip Freelon 919.941.9790 Project Manager Contractor Dedric Boyd 202.727.1113 Forrester. Joe Ockershausen 301.255.1794 DCPL PM Firm Hill International
Progress
Opened January 24, 2011
Design of the new Tenley Branch Library will include community input on planning and programming phase. Design and construction is fully funded.
Washington Highlands New Building Design
ContactsCouncilmember Ward 8 Architect Marion Barry 202.724.8045 Wiencek/Adjaye Scott Knudson 301.948.6220 Project Manager Contractor Lisa Deanes 202.727.5181 Coakley-Williams
Progress
Concrete Structure work underway
Design of the new Washington Highlands will include community input on planning and programming phase. Project is fully funded. DCPL is partnering with the DC Department of Housing and Community Development.
DCPL PM Firm
Jair Lynch Development Partners
10
Washington Highlands Interim Library
ContactsCouncilmember Ward 8 Architect Marion Barry 202.724.8045 Cooper Carry
Progress
Project Manager Contractor Pr