Home >Documents >Appendix E - Capital Construction Report Febuary 2011

Appendix E - Capital Construction Report Febuary 2011

Date post:24-Nov-2014
Category:
View:110 times
Download:3 times
Share this document with a friend
Description:
Library Services and Facilities Report appendix; capital report
Transcript:

The District of Columbia Public Library Capital Construction Report February 17, 2011

Document #2 Facilities Committee Meeting February 17, 2011

Appendix E

Anacostia Library New Building Construction

ContactsCouncilmember Ward 7 Architect YvetteAlexander 202.724.8068 Freelon Group Philip Freelon 919.941.9790 Project Manager Dedric Boyd 202.727.1127 Forrester Construction Tom Willerton 301.816.1700

Progress

Opened to the public April 26, 2010

Contractor

New State of the Art Library on Good Hope Road SE is open.

DCPL PM Firm

Hill International

Benning Library New Building Design

ContactsCouncilmember Ward 7 YvetteAlexander 202.724.8068 Davis, Brody, Bond &Aedas Peter Cook 202.449.1190 Project Manager Contractor Kim Fuller 202.442.6069 Forrester Jon McGee 301.255.1750

Progress

Architect

Opened to the public April 5, 2010

New State of the Art Library located at 3935 Benning Road NE is open.

DCPL PM Firm

A-1 Consulting

2

ClevelandPark New Ceiling and Lighting

ContactsCouncilmember Ward 3 Architect Mary Cheh 202.724.8062N/A

Progress

Project Manager

Ed Hampton 202.442.6067 Eagle Construction

Project Complete

Contractor Project consists of installing a new ceiling and lighting system.

Deanwood New Community Center and Library

ContactsCouncilmember Ward 7 Architect YvetteAlexander 202.724.8068 EEK Sean ODonnell

Progress

Project Manager Contractor

Opened to the public June 25, 2010

Project is a partnership with the Department of Parks and Recreation to co-locate a 10,000 square foot library within a 54,000 square foot aquatic center and community center. Library and Community Center would share such space as computer lab, senior rooms, tutor rooms and community meeting rooms. Project location is 49th and Quarles St. NE

3

Energy Enhancement Projects Various Locations

ContactsCouncilmember Various

Progress

Capitol View, ClevelandPark, ShepherdPark, Lamond Riggs, Palisades, Southwest, West End and Woodridge

Architect

T.B.D

Project Manager Contractor The Library has received Federal Stimulus Money for energy enhancements. Projects will take place at the above locations, focusing on window replacements, energy efficient lighting, and automated building heating and cooling controls

Ed Hampton 202.442.6067

Contracts awarded: Coordination of implementation and potential closing dates underway.

DCPL PM Firm

Francis A. Gregory Library New Library

ContactsCouncilmember Ward 7 Architect YvetteAlexander 202.724.8068 Wiencek/Adjaye Scott Knudson 301.948.6220 Project Manager Contractor Lisa Deanes 202.727.5181 Hess Construction

Progress

Demolition work is complete. Sorting of materials for recycling is underway. Foundation work is underway.

Design of the new Francis Gregory Library will include community input on planning and programming phase. Project is fully funded.

DCPL PM Firm

Jair Lynch Development Partners

4

Francis A. Gregory Library Interim Library

ContactsCouncilmember Ward 7 Architect YvetteAlexander 202.724.8068

Progress

Project Manager

Lisa Deanes 202.727.5181

Opened June 10, 2010

Contractor Project consists of building a 4,200 square foot interim library to serve the community during construction; the interim will have 30 computers, books on CD as well as traditional collection material for all age sets

William Scotsman Greg Bichell

DCPL PM Firm

Georgetown Library Building Renovation

ContactsCouncilmember Ward 2 Architect Jack Evans 202.724.8058Martinez & Johnson

Progress

Tom Johnson 202.333.4480 Project Manager Contractor Chris Wright 202.272.4913 T.B.D.

Opened to the Public October 18, 2010

Design of the new Georgetown Library will include community input on planning and programming phase. Design phase is fully funded.

DCPL PM Firm

Smoot Construction

5

Mount Pleasant Interior Restoration

ContactsCouncilmember Ward 1 Architect Jim Graham 202.724.8181

Progress

Core Architects

Dale Stewart 202.466.6116 Project Manager Contractor Phase II of Mount Pleasant Renovation. Interior work will consist of total upgrade and modernization of all mechanical equipment as well as provide additional and functional library program space. Chris Wright 202.727.4913 T.B.D

Selective demolition and construction work is underway.

DCPL Project Management

Smoot Construction

Mount Pleasant Interim Library

ContactsCouncilmember Ward 1 Architect Jim Graham 202.724.8181

Progress

Core Architects

Dale Stewart 202.466.6116 Project Manager Contractor Project consists of building a 3,600 square foot interim library to serve the community during construction; the interim will have 30 computers, books on CD as well as traditional collection material for all age sets Dedric Boyd 202.727.1127 MCN Build Bassem Boustany 202.333.3424

Opened to the public April 26, 2010 Re-opened to the public May 15, 2010

6

Northeast Library Exterior Restoration

ContactsCouncilmember Ward 6 Architect Tommy Wells 202.724.8072

Progress

Bell Architects

David Bell 202.548.7570 Project Manager Chris Wright 202.727.4913 Monarc Construction C. McDermott, 703.201.1747

Construction y Substantial completion May 15, 2010

Contractor

Project consists of Exterior Improvements to windows, doors, security lighting, masonry restoration, landscaping and signage.

Northeast Library Pre-design Due Diligence

ContactsCouncilmember Ward 6 Architect Tommy Wells 202.724.8072

Progress

N/A

Pre-design due diligence work includes a hazardous materials survey, a Phase 1 and Phase 2 Environmental Site Assessment and a Cost Benefit Analysis Study.

Project Manager

Chris Wright 202.727.4913

Cost Benefit Analysis and Pre-design Due Diligence Reports - Complete No funding for design or construction

Consultant

McKissack & McKissack Ellen Wright 202.347.1446

7

Northwest One New Co-location Facility

ContactsCouncilmember Ward 6 Architect Tommy Wells

Progress

HordCort Plan

Project Manager Contractor

Reagan Assoc

Library Open December 7, 2009 Open to the Public

Forrester

Project consists of 6,500 SQ FT Library facility as part of Elementary School and RecreationCenter. This facility replaces the Sursum Corda kiosk.

Parklands-Turner New Storefront Library

ContactsCouncilmember Ward 8 Architect Marion Barry 202.724.8045

Progress

Mood Nolan - DC

Patrick Williams 202.244.4199 Project Manager Contractor Project to fit out approximately 5,000 Sq Ft of storefront space to replace the existing Parklands-Turner kiosk. The storefront library is similar in size, scope, computers, and collections to the Georgetown Interim and Tenley-Friendship Interim Libraries. Dedric Boyd 202.727.1129 Lexx Group Ken Postell 202.393.3085

Ribbon Cutting October 5, 2009 OPEN TO THE PUBLIC

8

Petworth Library Interim Library

ContactsCouncilmember Ward 4 Architect MurielBowser 202.724.8052 N/A

Progress

Project Manager Contractor Project consists of building a 4,200 square foot interim library to serve the community during construction; the interim will have 30 computers, books on CD as well as traditional collection material for all age sets

Lisa Deanes 202.727.5181 Sigal Construction Sarah Norman

Opened to public on January 11, 2010 Closed February 5, 2011

DCPL PM Firm

Petworth Interior Renovations

ContactsCouncilmember Councilmember Ward 4 Architect MurielBowser 202.724.8052Frank and Loshen

Progress

Fletcher Farr Anoyte Project Manager Contractor Project will update the interior of the Petworth Library to be a fully functional state of the art 21st Century Library, while still being respectful of the buildings historic character.

Chris Wright 202.727.4913 Sigal Construction Sarah Norman

Main Library closed December 20, 2009 Construction Complete. Move-in underway. Library will open February 28, 2011

DCPL PM Firm

McKissack and McKissack

9

Tenley Friendship New Building

ContactsCouncilmember Ward 3 Architect Mary Cheh 202.724.8062 Freelon Group Philip Freelon 919.941.9790 Project Manager Contractor Dedric Boyd 202.727.1113 Forrester. Joe Ockershausen 301.255.1794 DCPL PM Firm Hill International

Progress

Opened January 24, 2011

Design of the new Tenley Branch Library will include community input on planning and programming phase. Design and construction is fully funded.

Washington Highlands New Building Design

ContactsCouncilmember Ward 8 Architect Marion Barry 202.724.8045 Wiencek/Adjaye Scott Knudson 301.948.6220 Project Manager Contractor Lisa Deanes 202.727.5181 Coakley-Williams

Progress

Concrete Structure work underway

Design of the new Washington Highlands will include community input on planning and programming phase. Project is fully funded. DCPL is partnering with the DC Department of Housing and Community Development.

DCPL PM Firm

Jair Lynch Development Partners

10

Washington Highlands Interim Library

ContactsCouncilmember Ward 8 Architect Marion Barry 202.724.8045 Cooper Carry

Progress

Project Manager Contractor Pr

Popular Tags:

Click here to load reader

Embed Size (px)
Recommended