Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
i
Table of contents
Part A Transfer of technology to the counterpart
1. Purpose of Technical transfer and training
1.1 Transfer of technology to the counterpart and development of
human resources......................................................................................................A1-1
1.1.1 Implementation of technology transfer ........................................................A1-2
1.2 Function and procedures of Power and energy demand forecasts........................A1-3
1.2.1 Structure of power demand forecasting model ............................................A1-3
2. Model building for power and energy demand forecasts
2.1 Seminar program and participants..........................................................................A2-1
2.2 Seminar style and textbook.......................................................................................A2-1
2.3 .TEXT Energy Demand Forecasting Model............................................................A2-3
3. GDP potential and Energy price estimation
3.1 Seminar program and prticipants............................................................................A3-1
3.2 Seminar style and textbook.......................................................................................A3-1
3.3 TEXT Syria Crude oil & natural gas price .............................................................A3-2
4. Technology Transfer for Power Development Plan Preparation
4.1 Technology transfer related to Power Development Plan Preparation ................A4-1
4.1.1 First Counterpart Training Seminar ............................................................A4-1
4.1.2 Second Counterpart Training Seminar ........................................................A4-7
4.2 TEXT Power Developmetn Planning on Syria Energy ..................................... A4-t1
4.3 TEXT Outline of Thermal Power Generation Energy...................................... A4-t2
4.4 TEXT PDCA Cycle for Thermal Power Plant Operation & Maintenance ..... A4-t3
4.5 TEXT Management of Equipment Failure and Human Error ........................ A4-t4
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
ii
Part B Basic Design of Terhmal Power Plants
1.1 Basic Design of Terhmal Power Plants ....................................................................................B-1
1.2 Basic Design of Combined Cycle Thermal Power Plant ........................................................B-5
1.2.1 Outline of Plants .......................................................................................................B-5
1.2.2 Operation of Power Generating Equipment ..........................................................B-5
1.2.3 Outline of Generating Equipment Control ............................................................B-7
1.2.4 Ezamnation of Basic Technical issues .....................................................................B-9
1.2.5 Optimization of bottoming Cycle .......................................................................... B-11
1.2.6 Exhaust Gas Turbine Equipment..........................................................................B-15
1.2.7 Auxiliary Steam Boiler ...........................................................................................B-17
1.2.8 Standard and Criteria ............................................................................................B-17
1.2.9 Environment ...........................................................................................................B-18
1.2.10 Gas Turbine...........................................................................................................B-19
1.2.11 HRSG.....................................................................................................................B-19
1.2.12 Steam Turbine .......................................................................................................B-19
1.2.13 Fuel Supply Equipment .......................................................................................B-20
1.2.14 Water Treatment Apparatus................................................................................B-21
1.2.15 Wastewater Treartment Unit ...............................................................................B-21
1.2.16 Firefighting Equipment........................................................................................B-21
1.2.17 Electrical Equipment ...........................................................................................B-22
1.2.18 Power Generation Equipment Protection andControl......................................B-26
1.2.19 Civil and Building Works ....................................................................................B-28
1.2.20 Construction Cost.................................................................................................B-29
1.3 Basic Plan of the Coal-fired Thermal Power Plant ..............................................................B-32
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
List of Tables
Table a-1 Detailed items to be used for technical transfer knowledge ................................................ A1-2
Table a-2 Schedule and seminar contents............................................................................................ A1-1
Table a-3 Name list of the participants................................................................................................ A2-1
Table b-1 Examination Results and Recommendations .................................................................B-2
Table b-2 Startup Time Schedule ................................................................................................B-6
Table b-3 Startup Frequency ....................................................................................................B-7
Table b-4 Vibration Control Values ..............................................................................................B-8
Table b-5 Gas Turbine Model Performance .................................................................................B-10
Table b-6 CCPP Model Performance ....................................................................................... B-11
Table b-7 Bottoming Cycle Performance .....................................................................................B-13
Table b-8 Bottoming Cycle Construction Cost ...........................................................................B-14
Table b-9 Limit Values on Concentration of Air Pollutant Emissions..........................................B-18
Table b-10 Noise Standard ...........................................................................................................B-18
Table b-11 Protected Areas and Firefighting Equipment .............................................................B-22
Table b-12 Generator Specifications ............................................................................................B-23
Table b-13 Standard Specifications of Transformers ...................................................................B-25
Table b-14 Generator Protective Circuit.......................................................................................B-26
Table b-15 Construction Cost Calculation ...................................................................................B-29
List of Figures
Figure a-1 Block flow of power demand forecasting model ............................................................... A1-1
Figure a-2 Data processing of power demand forecasting model ....................................................... A1-1
Figure b-1 Examination Flow ............................................................................................................. B-1
Figure b-2 Priority Implementation Items in the Next Plan .................................................................. B-4
Figure b-3 Combined Heat Balance ................................................................................................. B-31
iii
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A1-1
1. Technical transfer and training
1.1 Transfer of technology to the counterpart and development of human resources
After the electric power system has been worked out by the JICA Study Team, the Syrian side is
required to take charge of revision of the power development plan, periodic prediction of
electricity demand prediction and review and reexamination of the power system plan. To
achieve this objective, it is important to implement technology transfer effectively within the
limit period of time. Efforts were made to implement strategic technology transfer through a
seminar or similar events. Technology transfer is one of the major items in this survey activity.
Particularly with reference to the electricity/energy demand prediction procedure and power
development plan included in the present survey work, such basic technologies as the concept of
supply reliability, economical operation of the power supply system, and power development
planning technique are essential to the PEEGT as a counterpart organization which is responsible
for continued development of the Syrian electricity sector. Accordingly, the above-mentioned
technologies shall be transferred in such a way that the counterpart organization can use these
technologies independently after completion of this survey.
(1) Electricity/energy demand prediction procedure In the project, an electricity/energy demand prediction model is worked out to predict
the electricity demand for the power development plan. For the supply of primary energy required for power generation, it is important to ensure consistency with the amount of power generation. The technology regarding a series of the related work is transferred to the PEEGT and related organizations.
(2) Power development planning procedure For the power development planning procedure, the results of studies on optimization
of power source based on a development scenario and system reliability as well as the supply-demand operation simulation program (PDPAT II) are transferred to the counterpart organization. The data employed in the study made so far is used for instruction of the operation method and training to enhance the level of skill. Further, instruction and training will be provided regarding the method of analyzing the power development plan using a supply-demand operation simulation program.
The following shows specific implementation items:
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A1-2
Table a-1 Detailed items to be used for technical transfer knowledge
Implementation items Trainee Description
First power development plan induction course (Within the country)
Related persons of the counterpart organization Four persons
Acquisition of the concept and technique of power development plan
Concept of supply reliability Concept of economical operation of
power source Economic viability assessment
technique Hands-on training by PDPAT II Visit to thermal power plants within
the jurisdiction of TEPCO
Second power development plan induction course (Within the country)
Related persons of the counterpart organization Four persons (changed to six)
Preparation of the Syrian power development plan based on the result of field survey, and discussion
Introduction of Japanese technologies for diversification of power sources for Syria
Explanation of the result of survey made so far, and discussion on the result of study
1.1.1 Implementation of technology transfer
1) Power development planning procedure In the first technology transfer meeting, four engineers of Syrian PEEGT Planning
Bureau were invited to Tokyo during the period from July 16 (Sun) through July 31 (Sun), and training was provided regarding simulation programs and domestic power generation facilities, where a visit to manufacturers was included.
In the second technology transfer meeting, six engineers of Syrian PEEGT Planning Bureau were invited to Tokyo during the period from November 13 (Sun) through November 27 (Sun), and training was provided regarding simulation programs and domestic power generation facilities, where a visit to manufacturers was included.
2) Electricity/energy demand prediction procedure During the period from September 18, 2011 through September 20 in the third field
survey, a seminar was held for six engineers of Syrian PEEGT Planning Bureau to explain about the electricity/energy demand development program developed for this project (at the work office of TEPSCO, Amman, Jordan due to aggravating public security in Syria).
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
1.2 Power and energy demand forecasts
1.2.1 Structures of power demand forecasting model
(1) Required functions of power demand forecasting model
The following functions are required by the energy demand forecasting model in the project.
The model has to link social economic activities.
The model has to be affected by the changes of energy prices and energy efficiency and
conservation (EE&C) policies.
The model has to be able to forecast power and final energy demands by sector
(Agriculture, Industry, Commercial & Services, Public, Transportation and Residential
sectors).
The model has to be able to forecast power, final energy and primary energy demands in
whole country and those should be compared to other countries.
(2) Block flows of power demand forecasting model
At first, the energy demand forecasting model calculates sectoral power demand and final
energy demand, after that, power generation, energy resources for the power sector and
primary energies are calculated. Econometric theory is used for model building methods.
The following figure is the procedure that shows the power and energy demand forecasting
model.
Figure a-1 Block flow of power demand forecasting model
A1-3
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
Source: JICA Study Team
Figure a-2 Data processing of power demand forecasting model
(3) Procedures of power demand forecasting
The targeted sectors are Power, Industry, Commercial & Services, Public, Transportation and
Residential sectors. The forecasting procedures are as follows;
The power and energy demands of the sectors are estimated with future energy intensities per
sectoral GDP (for residential sector, energy consumption per population is used) extended
from the past trends.
The power and fossil energies are estimated by sectoral GDP, power ratio, energy price
elasticity, energy conversion policy (share functions of energies) and introduction of energy
management system (EMS).
The consumed energies in power sector are estimated under power development plan.
Finally, sectoral power demand, final energy demand, primary energy demand and energy
intensities after implementing EMS are forecasted.
A1-4
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-1
2. Model building for power and energy demand forecasts
2.1 Seminar program and Participants
(1) Seminar room
Meeting room of TEPSCO in Amman
(2) Seminar contents
The following contents are explained in two and half days. For explaining the contents, three
day are needed originally. However the seminar is implemented in two and half days due to
short time staying of the C/P in Amman.
Table a-2 Schedule and seminar contents
Date Time Contents 20th Sep 10:00~16:30 1. Growth rate, Intensity and Elasticity
2. Economic data analysis 3. Methods of energy demand forecasting
21st Sep 10:00~16:30 4. How to use Simple E 5. Energy Demand Forecasting Model on SEEX 6. Syria Demand Forecasting Model (Model structures)
22nd Sep 9:30~11:30 7. Syria Economy and GDP potential 8. Power & Energy Demand Forecasts (Simulation Results)
(3) Names of participants
Six persons participate from PEEGT as C/P
Table a-3 Name list of the participants
NO Names Title 1 Mr. Nabil Al Sharaa PEEGT Planning Director 2 Mr. Fawaz Al Dhaher PEEGT Deputy Manager of Dispatching Center 3 Mr. Sameer Ishak PEEGT Electric engineer, Planning Dept. 4 Mr.Adnan Al Hallaq PEEGT Power Plant, Construction Dept. 5 Ms.Mona Mtawej PEEGT Planning Dept 6 Ms.Fatima Hamza PEEGT Electric Engineer, Planning Dept
2.2 Seminar style and textbook
(1) The instructor explained the following PPT files to the participants. The participants use
PCs delivered by JICA Amman and practiced the exercises for their understanding
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-1
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-2
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-3
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-4
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-5
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-6
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-7
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-8
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-9
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-10
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-11
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-12
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-13
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-14
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-15
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-16
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-17
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-18
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-19
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A2-3-20
A2-3-21
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A3-1-1
3 GDP potential and Energy price estimation
3.1 Seminar program and Participants
(1) Seminar room
Meeting room of JICA Training center
(2) Seminar contents
The following contents are explained in 2.5 hour seminar in JICA training center on date
24th September 2011
Table a-4 Seminar contents
Time Contents 13:30~16:00 Crude oil & Natural gas Market in middle and long term
1. Factors for Crude Oil Price 2. Crude oil market in middle & long term 3. Natural gas market in middle & long term
(3) Names of participants
Six persons participate from PEEGT as C/P
Tablea-5 Name list of the participants
NO Names Title
1 Mr. Nabil Al Sharaa PEEGT Planning Department Planning Director
2 Mr. Maher Bakla PEEGT Dispatching Department Operator
3 Mr. Sameer Ishak PEEGT Planning Department Technical Engineer
4 Mr. Mohamad Farham Alhussen PEEGT Dispatching Department National Dispatching Center Operator
5 Ms. Nour Aldabak PEEGT Studies Department Technical Engineer
6 Ms. Reem Alhomsi PEEGT Construction Power Plant Department Technical Engineer
3.2 Seminar style and textbook
The instructor explained the following PPT files to the participants.
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A3-2-1
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A3-2-2
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A3-2-3
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A3-2-4
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A3-2-5
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A3-2-6
A3-2-7
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A4-1
4.1 Technology Transfer Related to Power Development Plan Preparation
The power development plan is not only be prepared during the present study, but even after
the end of this study, it is necessary to carry out review and optimization of the plan according
to the progress of the study. In order to proceed with the work from now on efficiently,
technology transfer to the concerned persons in the Syrian organizations is necessary since it is
essential to learn the method of using the simulation software (PDPAT-II and RETICS) used at
the time of formulating the power development plan in the present study. In view of these
purposes, in the present survey, a training seminar was conducted related to the preparation of
the power development plan (counterpart training seminar).
4.1.1 First Counterpart Training Seminar
(1) Training seminar period
July 19 to 29, 2011
(2) Schedule
The schedule of the training seminar was as shown in Table 11.1-1.
(3) Participants
The participants from the counterpart organizations were the persons listed in Table 11.1-2.
The participants were selected mainly from the planning department of PEEGT, and
constituted of a group consisting of a director, key persons in charge of technology and
finance, and the leader of the organization governing the system operation (who is actually
the head of the National Dispatching Center).
All these members were capable persons well-versed in their respective fields, and the
combination of persons was not only one that suited the intent of this training, but also
these persons were considered to be very important for spreading the technology and
knowledge acquired through this training seminar.
(4) Contents and results of training seminar
(a) Lectures and demonstrations related to power development planning
Explanation of the general theory of electric power development planning, description of
the functions of the tools (PDPAT-II and RETICS), and demonstration using the tools were
provided during the training seminar.
In the lectures on the method and general theory of preparing an electric power
development plan, there were many parts providing new knowledge or concepts to the
participants, and it is thought that they not only listened intently but also deepened their
understanding.
In the lectures and demonstrations using the tools, there were some that used material based
on the current status and plan of their country, and it appears that they obtained a more
realistic understanding. Also, they exhibited quick grasp of the details and the method of
handling the software. It was possible for them to acquire not only the basic knowledge
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A4-2
but also understanding of the more advanced functions, and the training seminar appears to
be very meaningful.
There were frequent questions from the participants during the lectures and demonstrations,
and it was possible to carry out very dynamic and interactive lectures and demonstrations.
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A4-3
Table a-6 Schedule of the first counterpart training seminar
18-Jul Mon Come to Japan
19-Jul Tue 09:00 ~ 12:00 Briefing, Orientation (JICA) JICA Tokyo
14:00 ~ 16:30 L Power Sector in Japan JICA Tokyo
20-Jul Wed 09:00 ~ 10:00 L About TEPCO JICA Tokyo
10:00 ~ 12:00 DDiscussion about Progress ReportConfirmation of discussion points
JICA Tokyo
13:30 ~ 16:00 DCurrent status and development plan of powersystem in Syria (presentation from Syria)
JICA Tokyo
21-Jul Thu 09:00 ~ 12:00 L Outline of Power Development Planning JICA Tokyo
13:30 ~ 17:00 L How to use PDPAT and RETICS JICA Tokyo
22-Jul Fri 13:30 ~ 16:30 VSite visit (factory of thermal power plant facility,MHI Takasago Works)
MHI Takasago Works
23-Jul Sat ~ Himeji - Tokyo24-Jul Sun ~ Holiday
25-Jul Mon 09:00 ~ 12:00 L,E Lecture and Exercise regarding PDPAT and RETICS JICA Tokyo
13:30 ~ 16:30 L,E Lecture and Exercise regarding PDPAT and RETICS JICA Tokyo
26-Jul Tue 09:00 ~ 12:00 L,E Lecture and Exercise regarding PDPAT and RETICS JICA Tokyo
13:30 ~ 16:30 L,E Lecture and Exercise regarding PDPAT and RETICS JICA Tokyo
27-Jul Wed 10:30 ~ 14:30 VSite visit about Renewable energy power station(solar power, micro hydropower)
Komekurayama, Hokuto, inYamanashi Pref.
28-Jul Thu 09:00 ~ 12:00 L,E Lecture and Exercise regarding PDPAT and RETICS JICA Tokyo
13:30 ~ 16:30 L,E Lecture and Exercise regarding PDPAT and RETICS JICA Tokyo
29-Jul Fri 09:30 ~ 12:00 D Confirmation about discussion items JICA Tokyo
13:30 ~ 14:00 Action plan JICA Tokyo
14:30 ~ 15:00 Close ceremony JICA Tokyo
30-Jul Sat Return to SyriaD:Discussion, L:Lecture, E:Exercise, V:Visit
Date VenueTime Item
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A4-4
Table a-7 Participants of the first counterpart training seminar
No. Name Occupation
1 Mr. Nabil Alsharaa
PEEGT (Public Establishment of Electricity for
Generation and Transmission)
Planning Department
Planning Director
2 Mr. Sameer Ishak
PEEGT
Planning Department
Technical Studies
3 Ms. Mona Mtawej
PEEGT
Planning Department
Economic Studies
4 Ms. Fawas Alzaher
PEEGT
National Dispatching Center
Head of Dispatching Department
Fig. a-3 Scenes from lectures, discussions, and demonstrations (first training seminar)
(b) Study and inspection tours of power generation facilities
With the purpose of providing an opportunity to see in person the electric power generation
facilities in Japan so that it can be used as reference material for preparing the power
development plan, this training seminar included study and inspection tours of electric
power generation facilities and equipment.
The following three locations were selected this time for the visits: the Takasago Works of
Mitsubishi Heavy Industries Ltd., which is manufacturing thermal power plant facilities
(mainly gas turbine facilities) and has the track record of having made several deliveries to
Syria; the construction site of the large scale solar electric power generation facility located
in Yamanashi Prefecture (the Konekurayama Mega Solar Power Plant), as the site of an
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A4-5
electric power generation facility of Tokyo Electric Power Company; and the
Rokkason-seki hydroelectric power plant in Hokuto City, Yamanashi Prefecture, also,
similarly, as an example of a power generation facility using renewable sources of energy, .
In the site of manufacture of gas turbines with which the participants were familiar, the
participants appeared to be surprised at the highly precise management that was beyond
their imagination. Further, even about solar power generation and small hydroelectric
power generation, they seemed to have a strong feeling that these should be introduced
aggressively in their country as well, they appeared to observe everything very keenly.
Fig. a-4 Visit to Takasago Works of Mitsubishi Heavy Industries
Fig. a-5 Visit to Konekurayama Mega Solar Power Plant Construction Site
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A4-6
Fig. a-6 Visit to Rokkason-seki micro hydroelectric power plant
(c) Discussions
Discussions were held for confirming and agreeing on the preconditions for preparing the
power development plan, the set values, the policies of the country, etc. In a broad
classification, presentations were made by the Syrian side about the organization of the
electric power sector, electric power supply conditions, etc., confirmation was made of
items about which they had been requested to prepare in advance, and confirmation and
discussions were made about some aspects that needed discussions.
Fig. a-7 Scenes from discussions
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A4-7
4.1.2 Second Counterpart Training Seminar
(1) Training seminar period
November 15 to 25, 2011
(2) Schedule
The schedule of the training seminar was as is shown in Table 11.1-3.
(3) Participants
The participants from their side were as listed in Table 11.1-4.
Except two persons, all participants were new participants who had not participated in the
first training seminar, and similar to the participants in the first training seminar, the
participants included key persons and persons in charge of technology of PEEGT, and
persons in charge of governing the system operation.
(4) Contents and results of training seminar
(a) Understanding the outlines of preparing the electric power development plan using the
simulation software (lectures and demonstrations)
The training seminar participants included two persons who participated in the previous
first training seminar (the remaining four persons came to Japan for the first time), and
since they had mastered to some extent the basic functions and the method of use of the
simulation software (PDPAT-II and RETICS) during the previous training seminar, they
appeared to proactively guiding the new participants.
In the lectures and demonstrations using the simulation software (PDPAT-II and RETICS),
after a review of the contents of the first training seminar, the data of the current status in
Syria, and the data of the electric power development plan prepared by this survey team
were used concretely, and a concrete procedure for preparing the future optimal plan was
taught in the form of a practice session. The method of selecting based on the differences
between the methods of operating gas turbine and combined cycle type power plants, future
necessity of coal fired thermal power plants which are not existing at present, differences in
whether or not pumped storage hydroelectric power plants are introduced, etc., were
explained in detail, and all participants followed the lectures and demonstrations intently,
and seem to have acquired all the knowledge presented to them. In particular, regarding
the investigation of international coordination, one of the participants had studied
international coordination during the university thesis and hence showed particularly deep
interest, and left the impression that detailed investigations will be done from now on using
the software.
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A4-8
Table a-8 Schedule of the second counterpart training seminar
14-Nov Mon Come to Japan
15-Nov Tue 09:00 ~ 12:00 Briefing, Orientation (JICA) JICA Tokyo
13:30 ~ 16:00 L,E Power Development Planning Simulation JICA Tokyo
16-Nov Wed 09:30 ~ 12:00 L,E Power Development Planning Simulation JICA Tokyo
13:30 ~ 16:00 L,E Power Development Planning Simulation JICA Tokyo
17-Nov Thu 09:30 ~ 12:00 L,EPower Development Planning Simulation(Role of pumped storage power station)
JICA Tokyo
13:30 ~ 16:00 LOperation and Maintenance of Thermal PowerStation
JICA Tokyo
18-Nov Fri 10:00 ~ 12:00 V TEPCO Chiba Thermal Power Station
14:30 ~ 16:30 V TEPCO Kawasaki Thermal Power Station
19-Nov Sat Holiday20-Nov Sun Holiday
21-Nov Mon 11:30 ~ 15:00 V TEPCO Kannagawa Hydroelectric Power Station by Bus
22-Nov Tue 11:00 ~ 16:30 V MHI Nagasaki Shipyard & Machinery Works
23-Nov Wed Nagasaki - Tokyo
24-Nov Thu 09:30 ~ 12:00 L,E Power Development Planning Simulation JICA Tokyo
13:30 ~ 16:00 L Power Demand Forecast JICA Tokyo
25-Nov Fri 09:30 ~ 12:00 DPower Development Planning SimulationConfirmation about discussion items
JICA Tokyo
14:00 ~ 14:30 Action plan JICA Tokyo
14:30 ~ 15:00 Close ceremony JICA Tokyo
26-Nov Sat Return to SyriaD:Discussion, L:Lecture, E:Exercise, V:Visit
VenueTime ItemDate
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A4-9
Table a-9 Participants of the second counterpart training seminar
No. Name 名前 Occupation 職業
1 Mr. Nabil ALSHARA
PEEGT (Public Establishment of Electricity for Generation and Transmission) Planning Department Planning Director
2 Ms. Reem ALHOMSI PEEGT Construction Power Plant Department Technical Engineer
3 Mr. Sameer ISHAK PEEGT Planning Department Technical Studies
4 Mr. Maher BAKLA PEEGT Dispatching Department Operator
5 Ms. Nour ALDABAK PEEGT Studies Department Technical Engineer
6 Mr. Mohamad Farhan ALHUSSEN
PEEGT Dispatching Department, National Dispatching Center Operator
Fig. a-8 Scenes from discussions (Second training seminar)
(b) Study and inspection tours
Actual installed facilities of combined cycle power plant and pumped-storage hydroelectric
power plant were visited because of the high probability of their being adopted from now
on in Syria. The visited locations were the Chiba thermal power station, the Kawasaki
thermal power station, and the Kannagawa power station of Tokyo Electric Power
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A4-10
Company. In addition, in continuation of the previous training seminar, a visit to
Mitsubishi Heavy Industries Limited which has the track record of having delivered several
thermal power plants to Syria, and following the visit last time to their Takasago Works
(gas turbine facilities), this time a visit was made to their Nagasaki Shipyard and
Machinery Works (HRSG and steam turbine facilities).
In the Chiba thermal power station, the participants showed interest in the operation
management organization of the existing power generation facilities, the power generation
cost, etc., and a very active question and answer session was carried out. In addition, in
the Chiba thermal power station, although at present the construction work method of
firstly installing the gas turbines and then adding thereafter the steam turbine facilities is
being made as the No. 3 system (this is the first attempt of this kind in Tokyo Electric
Power Company), since the same method is being planned to be used even in Syria, the
participants appeared to show deep interest in the methods of construction and installation
works.
In the Kawasaki thermal power station, the participants saw with their own eyes a
combined cycle thermal power generation facility which boasts the highest level of thermal
efficiency in the world, and again asked questions actively. They entered the central
operating room where the operations of running the plant are made, showed interest in the
number of operators and the method of giving power dispatching commands, etc., and
again asked various questions.
In the Kannagawa power station, it appeared that the participants obtained a real feel by
seeing the actual plant and not by theory of the construction and role of pumped-storage
hydroelectric power generation plant. They were able to go close to each of the facilities
that were operating and the facilities that were under construction, and appeared to be
satisfied.
In the Nagasaki Shipyard and Machinery Works of Mitsubishi Heavy Industries, the
participants were not only surprised by the hugeness of the factory, but also appeared to be
deeply impressed by the very detailed quality management methods adopted in spite of the
huge size of the factory.
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A4-11
Fig. a-9 Visit to Chiba thermal power station of Tokyo Electric Power Company
Fig. a-10 Visit to Kawasaki thermal power station of Tokyo Electric Power Company
Appendix Study for Updating Syrian Electricity Sector in Syrian Arab Republic
A4-12
Fig. a-12 Visit to Nagasaki Shipyard and Machinery Works of Mitsubishi Heavy Industries
Fig. a-11 Visit to Kana gawa power station of Tokyo Electric Power Company
1
Power Development Planning on Syria
November 2011Tokyo Electric Power Co.
2
2010 (Net) CapacityTotal
North 1065 450 1200 2715 35.0%Aleppo ST 1065 Zezon CC 450 Althwra 680
Albaeth 20Tishren dam 500
West 520 260 0 780 10.0%Banias ST1,2 240 Banias GT 260Banias ST3,4 280
Central 1105 600 0 1705 22.0%Refinery Homs 45 Jander CC 600Meharda ST 400Alzara ST 660
South 400 1850 0 2250 29.0%Tishren ST 400 Nasrieh CC 450
Tishren GT 200Tishren CC 450Dir-Ali-1 CC 750
East 0 315 0 315 4.1%Tayem GT 90Swedieh GT 150Swedieh Petro G 75
Total 3090 3475 1200 7765 100.0%39.8% 44.8% 15.5% 100.0%
HFO Gas Hydro
3
0
100
200
300
400
500
600
700
800
900
1,000
0 50 100 150 200 250 300 350 400
[MW]
[US$
/kW
]Construction Cost of GT
[MW] 30 60 75 100 300Equipment 360 310 290 270 220Civil 44 38 35 33 27Engineering 32 24 20 24 16Erection 44 38 35 33 27Total 480 410 380 360 290
4
0
200
400
600
800
1,000
1,200
0 200 400 600 800 1000 1200
[MW]
[US$
/kW
]Construction Cost of CC
MW 300 450 750Equipment 520 490 450Civil 50 50 50Engineering 50 50 50Erection 80 70 60Total 700 660 610
5
Annual Expense
Construction cost Annual expense (USD/kW/year)
Gas-fired thermal (C/C: 750MW) 610 USD/kW 98.0
Gas-fired thermal (GT: 150MW) 340 USD/kW 56.3
Oil-fired thermal (ST: 250MW) 1,100 USD/kW 154.8
Coal-fired thermal (ST: 250MW) 1,800 USD/kW 271.3
6
Fuel Cost
IEA forecast (2020) Fuel price
(USC/kcal) Efficiency Fuel cost (USC/kWh)
Gas C/C 12.10 USD/Mbtu 4.0 kcal/Btu 4.8 56% 7.4
Gas GT Ditto Ditto 4.8 32.5% 12.7
Oil ST 100.0 USD/bbl 9,600 kcal/kg 7.3 44% 14.3
Coal ST 104.16 USD/ton 6,000 kcal/kg 1.7 44% 3.4
7
Generating Cost - 1
0
10
20
30
40
0% 20% 40% 60% 80% 100%Capacity factor
PSPP Gas CC Gas GT Coal Oil ST
(Cent/kWh)
8
Annual Expense & Fuel cost of Old Facilities
Annual fixed cost
(USD/kW/year)
Fuel price
(USC/kcal)Efficiency
Fuel cost
(USC/kWh)
New Gas-fired C/C 98.0 4.8 56% 7.4
Old Gas-fired C/C 41.2 4.8 49.5% 8.3
Old Gas-fired GT 25.5 4.8 30% 13.8
Old Oil-fired ST 41.3 7.3 42% 14.9
9
Generating Cost - 2
0
10
20
30
0% 20% 40% 60% 80% 100%Capacity factor
New Gas CC Old Gas CCGas GT Oil ST
(Cent/kWh)
10
Relation between Reserve Capacity Rate and LOLE
0
20
40
60
80
100
-2% 0% 2% 4% 6% 8% 10%Reserve capacity rate
LOLE
(H
ours
)
11
Sensitivity Analysis - 1Demand Forecast Error
0%
2%
4%
6%
8%
10%
12%
0% 1% 2% 3% 4% 5%
Demand forecast error (%)
Rese
rve
capa
city
rat
e
LOLE=50hrs LOLE=24hrs LOLE=5hrs
12
Sensitivity Analysis - 2Forced Outage Rate
0%
2%
4%
6%
8%
10%
12%
14%
Base +1% +2% +3% +4%
Forced outage rate
Rese
rve
capa
city
rat
e
LOLE=50hrs LOLE=24hrs LOLE=5hrs
13
Peak Supply PowerGas GT Vs. Gas CC
-140-120-100-80-60-40-20
0204060
0 500 1000 1500 2000 2500 3000
Gas turbine Capacity (MW)
Fixed cost Fuel cost Total(mil. USD)
14
Peak Supply PowerGas GT Vs. Gas CC with PSPP
-120
-100
-80
-60
-40
-20
0
20
40
60
0 500 1000 1500 2000 2500
Gas turbine Capacity (MW)
Fixed cost Fuel cost Total
15
Peak Supply PowerChange in Fixed Cost
-160-140-120-100-80-60-40-20
02040
0 500 1000 1500 2000 2500 3000
PSPP Capacity (MW)
1.4 times 1.2 times Base 0.8 times
16
GT: 2100MWGT: 0MW
17
Base Supply Power
-4000
-3000
-2000
-1000
0
1000
2000
0 2000 4000 6000 8000 10000 12000 14000
Coal-fired thermal Capacity (MW)
Fixed cost Fuel cost Total(mil. USD)
18
Base Supply PowerChange in Fuel Price
-2000
-1500
-1000
-500
0
500
1000
0 2000 4000 6000 8000 10000
Coal-fired thermal Capacity (MW)
Base 0.8 times 0.6 times(mil.
19
Fuel Consumption
0
5
10
15
20
0 2000 4000 6000 8000 10000
Coal-fired thermal Capacity (MW)
(mil. toe)
12.6 million toe
20
Configuration of Capacity
0%
20%
40%
60%
80%
100%
0 2000 4000 6000 8000 10000
Coal-fired thermal Capacity (MW)
Hydro & others Oil Gas Coal
21
Unevenly Distributed Power Plants
Site location of Coal-fired thermal : West areaWest area demand : 11%Necessity of large amount of transmission lines
22
CO2 Emissions
0
20000
40000
60000
80000
0 2000 4000 6000 8000 10000
Coal-fired thermal Capacity (MW)
0
0.2
0.4
0.6
0.8
CO2 emissions Unit emission rate
(mil. kg-CO2) (kg-CO2/kWh)
2010 (present)25,000 mil. kg-CO20.5 kg-CO2/kWh
23
Effect of 1000MW development
680 million kg-CO20.28 million toe20%Solar
1,020 million kg-CO20.41 million toe30%Wind
2,700 million kg-CO21.10 million toe80%Nuclear
Reduction of CO2 emissions
Reduction of Fossil fuel consumption
Capacity factor
24
Recommendation of 2030 Configuration
MW % MW %Hydro 1,200 5 0 0PSPP 0 – 1,200 0 – 5 0 – 1,200 0 – 5HFO 2,500 10 1,000 5
Gas GT 1,500 – 2,500 5 – 10 1,000 – 2,000 5 – 10Gas CC 10,000 – 13,000 45 – 55 6,000 – 8,000 40 – 50Coal 3,000 – 4,000 15 3,000 – 4,000 20 – 25
Nuclear 0 – 2,000 0 – 10 0 – 2,000 0 – 10Renewable 500 – 1,500 2 – 5 500 – 1,500 5 – 10
Total 25,000 100 16,000 100
2030 2016 - 2030
1
Outline of Thermal Power Generation
November 20November 201111Thermal Power DepartmentThermal Power Department
TEPCOTEPCO
All Rights Reserved, Copyright TEPCO 2011 2
Contents
1. TEPCO Corporate Overview
2.TEPCO’s Thermal Power Plants
3.Characteristics of TEPCO’s Thermal
Power Generation
All Rights Reserved, Copyright TEPCO 2011 3
-- Part 1 Part 1 --TEPCO Corporate OverviewTEPCO Corporate Overview
All Rights Reserved, Copyright TEPCO 2011 4
TEPCO Corporate Overview
Okinawa
Kyushu
Chugoku
Shikoku
Kansai
Hokuriku
Tohoku
TEPCO
Hokkaido
Chubu
total898,896
GWh
ShikokuKyushu
Chugoku
Kansai
Hokuriku ChubuTohoku
Hokkaido
TEPCO293,386 GWh
Historical Data in FY2010
The The NineNine Japanese CompanyJapanese Company’’s Power Saless Power Sales
Service Area of Service Area of JapanJapan’’s Ten Power s Ten Power CompaniesCompanies
As of the end of March 2011
38,38,671671Employees:Employees:
14,255.9 billion JPY14,255.9 billion JPYTotal Assets:Total Assets:
293,386 293,386 GWhGWh4,796.5 billion JPY4,796.5 billion JPY
Power Sales:Power Sales:Sales:Sales:
900.1 billion JPY900.1 billion JPYCapital Stock: Capital Stock:
1 1 May 1951May 1951Establishment:Establishment:
TEPCO Energy SourceTEPCO Energy Source
Source : TEPCO ILLUSTRATED in 2011
New Energy etc,0%
Hydro14%
Nuclear27%
Coal2% Oil
17%
LNG, LPG40%
All Rights Reserved, Copyright TEPCO 2011 5
-- Part 2 Part 2 --TEPCOTEPCO’’s Thermal Power Plantss Thermal Power Plants
All Rights Reserved, Copyright TEPCO 2011 6
TEPCO’s Thermal Power Stations
Conventional 24,635 MW (63.2%)LN(P)G 12,285 MW(31.5%)
Oil 10,750 MW (27.6%)
Coal 1,600 MW (4.1%)
CC> 14,321 MW (36.8%)Total 38,956 MW
Hitachinaka
15 15 Thermal Power StationsThermal Power Stations889 Units9 Units
Central TPO
West TPO
East TPO
As of the end of March 2011
Source : TEPCO ILLUSTRATED in 2011
East TPO* 17,317 MW (44.5%)West TPO 10,249 MW (26.3%)Central TPO 11,390 MW (29.2%)Total 38,956 MW
*TPO = Thermal Power Office
○Generating Capacity
All Rights Reserved, Copyright TEPCO 2011 7
TEPCO Overseas IPP Plants
U.A.E.Umm Al Nar Power : 2257MW
Water : 65,000t/dTaiwan
Chang-Bin (GTCC) : 490MWFong-Der (GTCC) : 980MWStar-Buck (GTCC) : 490MW
Viet NamPhu-my2-2 (GTCC) : 715MW
IndonesiaPaiton1 (Coal) : 1,230MWPaiton3 (Coal) : 815MW (COD 2012)
AustraliaLoy Yang-A (Coal) : 2,195MW
the PhilippinesPagbilao (Coal) : 735MWSual (Coal) : 1,218MWIlijan (GTCC) : 1,251MW
Thai (EGCO)GTCC : 2,742MWLNG : 824MWCoal : 1,434MW(SPP : 512MW)(Overseas : 1,754MW)
TotalTotal16,000MW (gross) 16,000MW (gross)
3,360MW (net)3,360MW (net)
All Rights Reserved, Copyright TEPCO 2011 8
Organization Chart
Chairman
Thermal Power Department
East Thermal Power Office
Thermal Power Plant Engineering Center
Thermal Power Plant O&M Training Center
…..
HQ
BO
5 Thermal Power Stations
West Thermal Power Office
Central Thermal Power Office
5 Thermal Power Stations
5 Thermal Power Stations
President
All Rights Reserved, Copyright TEPCO 2011 9
-- Part 3 Part 3 --Characteristics of TEPCOCharacteristics of TEPCO’’ssThermal Power GenerationThermal Power Generation
All Rights Reserved, Copyright TEPCO 2011 10
A. Contribution to “Best Mix” Power Generation
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1973 1975 1985 1995 2000 2005 2007 2008 2009 2010
FY
NuclearCoalOil
Other GasesLNG, LPG
GeothermalNew Energy etc,Hydro
19851985~~1,100 1,100 degdeg--CC
CCCC
19961996~~1,300 1,300 degdeg--CC
ACCACC
20072007~~1,500 1,500 degdeg--CC
MACCMACC
1970~Introduction of LNGLNG
Source : TEPCO ILLUSTRATED in 2011
Increase in gas consumptionOil-fired : 72% (1973) → 26% (1985)Gas-fired: 9% (1973) → 26% (1985)
All Rights Reserved, Copyright TEPCO 2011 11
B. TPG as Middle & Peak Power Supply
Source : TEPCO ILLUSTRATED in 2011
All Rights Reserved, Copyright TEPCO 2011 12
C. Thermal Efficiency Trend
LHV Combined CycleCombined CyclePower PlantsPower Plants
19851985~~1,100 1,100 degdeg--CCCombined CycleCombined Cycle(CC)(CC)
19961996~~1,300 1,300 degdeg--CCAAdvanceddvanced CCCC(ACC)(ACC)
20072007~~1,500 1,500 degdeg--CCMore Advanced CCMore Advanced CC(MACC)(MACC)
Steam Steam Power PlantsPower Plants
Source : TEPCO Environment Highlights 2009
1,1,6600 deg00 deg--CCMACC IIMACC II
All Rights Reserved, Copyright TEPCO 2011 13
Typical TEPCO’s CC
1,300℃
All Rights Reserved, Copyright TEPCO 2011 14
D. Addressing Environmental Issues
Example of air pollution countermeasuresat a thermal power plant
All Rights Reserved, Copyright TEPCO 2011 15
D. Addressing Environmental Issues
Hitachinaka Power Station
(Coal-fired)
Turbine
Boiler
Fuel Gas Denitrification
Facility
Electrostatic Precipitator
Fuel Gas Desulphurization
Facility
All Rights Reserved, Copyright TEPCO 2011 16
D. Addressing Environmental Issues
Source : TEPCO Environment Highlights 2009
All Rights Reserved, Copyright TEPCO 2011 17
D. Addressing Environmental Issues
1. Shells
2. Used Generator Brush
FertilizerIntermediate treatment
Shells in the water intake
Used generator brush
Graphite particle Extra lead
- Examples of waste recycling -
All Rights Reserved, Copyright TEPCO 2011 1
PDCA Cycle for PDCA Cycle for Thermal Power Plant Thermal Power Plant
OperationOperation && MaintenanceMaintenance
November 20November 201111Thermal Power Plant Thermal Power Plant
Engineering Center, TEPCOEngineering Center, TEPCO
All Rights Reserved, Copyright TEPCO 2011 2
AgendaAgenda
1. Plant Operation
2. Daily Maintenance
3. Periodic Inspection Program
4. Plant Engineering and Plant Diagnosis
5. Maintenance Plan and Budget
6. Work Preparation / Implementation / Commissioning
All Rights Reserved, Copyright TEPCO 2011 3
Plant OperationPlant Operation
• Monitoring critical parameters
• Site inspection
• Standard operation procedure
• Thermal efficiency / condition monitoring
All Rights Reserved, Copyright TEPCO 2011 4
Daily MaintenanceDaily Maintenance
• Daily maintenance standards
Preventive maintenance
– Time based
– Condition based
Maintenance Maintenance Maintenance Maintenance
MaintenanceMaintenance
PlantOperation
1week 1week 1week 1week
2weeks2weeks
A' equipment
B' equipment
All Rights Reserved, Copyright TEPCO 2011 5
Periodic Inspection Program Periodic Inspection Program
• The electricity utilities industry law
• Voluntary preservation of safety
• Safety rule
• Principles and manuals on periodic inspection
• Scope, interval for each equipment and their reasons
2years 2years 2years 2years
?years
Inspection Inspection Inspection Inspection
PlantOperation
Major Inspection Based on… ‐ law ‐ rule ‐ manuals ‐ Principle
PlantOperation Trouble !
If no maintenance...
All Rights Reserved, Copyright TEPCO 2011 6
What is PWhat is P--DD--CC--A Cycle?A Cycle?
Plan
Do
Check
ActionThermal
Power PlantMaintenance
All Rights Reserved, Copyright TEPCO 2011 7
Plant Diagnosis Plant Diagnosis
• Plant failures in own plant/ other plant
• Results of previous inspection
• Results of plant life assessment
• Operational history / date
• Results of condition monitoring
• OEM information / recommendation
• Changes of laws/ regulations
• New technologiesPlan
Do
Check
ActionThermal
Power PlantMaintenance
All Rights Reserved, Copyright TEPCO 2011 8
Plant Engineering and Plant DiagnosisPlant Engineering and Plant Diagnosis
• Critical part of the maintenance PDCA cycle
Plant Diagnosis Procedure– Check engineering information / site condition
– Carry out hazard identification and risk assessment
– Discuss most appropriate action ;
when, where, what, how, who, why and how much
– Prepare plant diagnosis report
– Authorization
– To be followed by maintenance work plan Plan
Do
Check
ThermalPower PlantMaintenance
Action
All Rights Reserved, Copyright TEPCO 2011 9
Maintenance Plan / Annual BudgetMaintenance Plan / Annual Budget
• Prioritize all the maintenance work plan to meet budget guideline on – Thermal power plant– Thermal power office– Thermal power department
• Build up 5-year maintenance plan – Outage schedule – Optimized maintenance works
• Set up annual budget
• Design of inspection / repair / modification work Do
Check
ActionThermal
Power PlantMaintenance
Plan
All Rights Reserved, Copyright TEPCO 2011 10
Preparation of Maintenance WorkPreparation of Maintenance Work
• To manage safety, schedule and quality of work
• Preparation by TEPCO operation / maintenance team and contractors through close communication
• Hazard identification and risk assessment
Plan
Check
ActionThermal
Power PlantMaintenance
Do
All Rights Reserved, Copyright TEPCO 2011 11
Implementation of Maintenance WorkImplementation of Maintenance Work
• Daily and weekly meeting
• Change of schedule
• Supervise– Isolation
– Work and plant conditions
– Inspection data
• Commissioning– Data to be checked carefully
Plan
Check
ActionThermal
Power PlantMaintenance
Do
All Rights Reserved, Copyright TEPCO 2011 12
What we learned about maintenance PDCA?What we learned about maintenance PDCA?
Safety is always the first priority in our business
Diligent operation, daily maintenance and periodic inspection, complying with standard procedure, are fundamental
Plant engineering and plant diagnosis are key steps for maintenance PDCA cycle – Plant diagnosis report is the key document
Careful design and preparation are important for successful maintenance work
Communication between operations, maintenance and contractors is indispensable for work preparation, implementation and commissioning
Management ofManagement ofEquipment FailureEquipment Failure andand
Human ErrorHuman Error
November 2011Thermal Power Department
TEPCO
All Rights Reserved, Copyright TEPCO 2011 1
1. What is Trouble Data Base<PURPOSE>To reduce unplanned-shutdown and to improve the quality of daily work by developing preventive measures through information sharing of troubles occurred at thermal power stations.
<Basic Principle>We consider equipment failures and human errors as good opportunities for improvement.
Trouble Data Base (DB)
・Trouble which affected power output・Trouble which extended planned maintenance duration・Trouble which led to severe disasters
(e.g. Fire, Oil leakage)・Trouble caused by human error
<Troubles to be controlled>
Analysis
Utilization of the DB
・Deploy preventive measures to other power plants by:- issuance of Technical Information Letters,- revision of maintenance manuals, etc.
・Reflect to design of new power plants
・To promptly send trouble information・To share information without boundaries・To carry out preventive measures promptly
All Rights Reserved, Copyright TEPCO 2011 2
Method of
Information
Sharing
【TP Department/Office】--everyday--・Reporting troubles・Conducting supplemental investigations
and developing countermeasures ・Judging application to similar
equipment
2. Utilizing Trouble Data Base
【TP Station】--everyday--・Reporting troubles・Root cause analysis・Execution of temporally and
permanent countermeasure
TP StationTP OfficeTP DepartmentTrouble occurrence
Input trouble informationoccurred at other companies
Measures
Completion
Judgment of applicationto similar equipment
Application to similar equipment
Data input
Trouble DB
Analysis of troubles
Every1 year
Instruct all TP Offices/Stations(by Campaign)
Judgment of applicationto similar equipment
Application to similar equipment
Select priority issues
All Rights Reserved, Copyright TEPCO 2011 3
Others
BreakdownMaintenance
Deterioration
Design
MaintenanceWork
ManualOperation
Troubles related to human factor
Troubles related to equipment
• Analyze human factors not only for operation but also for maintenance.
• Decrease unplanned shutdown from the view of “What we should have done.“
TP Department analyzes the equipment failures every 1 year from the view point of “What we should have done to minimize or prevent the trouble.“ In addition, in order to further decrease such troubles, we prioritize the troubles and focus on certain incidents. The result is shared among all power plants and take certain actions.
- To revise maintenance manuals
-To carry out periodic meeting with maintenance companies to share information and thorough prevention of trouble reoccurrence
- To apply countermeasures to similar equipment and determine the scope of inspection using the Trouble DB
- To reflect to plants under construction
Maintenance Management
3. Failure Analysis
Not predictable
All Rights Reserved, Copyright TEPCO 2011 4
4. Measures against Human ErrorIn case a human error incident occurs, thorough analysis and development of recurrence prevention measures are necessary to prevent recurrence. TV conference is used to confirm and share its background and to exchange opinions among all related parties.
Occurrence of Human Error
TV conference : after 1 week passed(temporary countermeasure)
TV conference : after 1 month passed)(permanent countermeasure)
TP StationTP OfficeTP Department
Trouble DB
Temporary Measures
Completion
Judge necessity of application to other plants
Application to other plants
Judge necessity of application to other plants
Application to other plants
Permanent Measures
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―1
1. Basic Design of Thermal Power Plants
1.1 Basic Design of Thermal Power Plants
When constructing new thermal power plants, it will be necessary to conduct ample
examination on the installation sites, generating capacity, funds and environmental issues, etc.
Figure b-1 shows the examination flow, while Table b-1 shows the results of examination and
recommendations.
Source: JICA Study Team
Figure b-1 Examination Flow
Examination Flow
Confirmation of macro
Environmental trends
Politics
Economy
Technology
Resources
and energy
Population
statistics
Energy and Electric
Power Sector
Demand forecast
Power source
Network system
Electricity tariff system
Fundraising
Securing of energy
Environmental and social
consideration
Stable and economic
provision of energy
(electricity) to the
Syrian people
Best matching of
primary resources
Appropriate
power
development plans
Power sector
master plan
review
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―2
Table b-1 Examination Results and Recommendations
Item Examination Results Recommendations
Demand
forecast
Power demand growth rate: 4.6
percent between 2010~2030
Improvement of 20 percent in the
energy saving rate in industry,
commerce and the public sectors
GDP elasticity of demand:
Reduction from 1.4 to 0.9
Increase in share of the industrial
sector and commercial sector: 34
percent (2030)
Energy saving plans in the industry,
commerce and the public sectors
Building of the natural gas and coal supply
systems
Reduction of distribution losses and
building of statistics in the electric power
sector
Improvement in legal efficiency of devices
used in traffic agencies (especially
automobiles) and the domestic sector
Power
development
evaluation
Reflection in abolishment of
equipment, etc. in line with
deterioration
Estimation of supply shortage at
time of peak demand in 2012
GCC, etc. between 2012~2014
Improvement at 2,000 MW
Development of 12,200 MW
required between 2021~2030
Development of gas turbine and
pumped-storage hydroelectric power
equivalent to 10 percent of plant capacity
Development of coal thermal power
Development of renewable energy
Transmission
network
system
Confirm that the power
transmission network system is
almost integral without serious
problems.
Make the maximum possible efforts to
maintain the local supply-demand balance
in future as well
Separation of operation between 230 kV
and 400 kV systems
Increase transmission capacity of the
transmission lines
Electricity
tariff system,
Disparity in timing of fuel price
hikes and tariff hikes
Revision of electricity tariffs that
are low in international terms
Price difference between imported
gas and domestically produced gas
(see below)
Cost cutting among electric utility operators
Revision of electricity tariffs (weighted
mean of imported natural gas and domestic
natural gas)
Improvement of the time zone-based
electricity tariff system
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―3
Fundraising
for power
source
development
Deterioration in supply spare
capacity
Development of a total of 16,000
MW of power sources between
2016~2030
Increase in own funds
Utilization of international ODS funds (not
applicable to coal-fired thermal power)
Utilization of private capital (IPP, BOT,
BOOT)
Diversification of fundraising sources based
on PEEGT privatization and splitting
Also, utilization of low-interest funds
(funds from Arabian countries)
Energy
securing
Reduction in production of crude
oil
85 percent of gas is for power
generation, the remainder is
consumed domestically.
Ongoing import of gas + new
imports (Egypt, Iran, Iraq, etc.)
Energy best mix
Diversification of energy supply sources
Early implementation of renewable energy
projects
Encouragement of the early development
and utilization of confirmed reserves of
shale gas
Discussions on securing energy with
neighboring countries
Cooperation with construction of crude oil
and gas pipelines that can contribute to the
international community
Environmental
and social
consideration
Environmental standards exist but
they are not an important factor.
Formulation and implementation of
internationally acceptable EIA System and
environmental standards
Renewable
energy
Abundant resources (solar power,
wind power)
Start on small-scale projects
Continuation of sustained and phased
development
International cooperation (Japan,
surrounding countries, Europe)
Source: JICA Study Team
*In future, if imports of gas increase, price disparities with domestic gas will become a
problem. Particularly concerning gas-fired power generation, since the generating cost more
than doubles between using imported gas and domestic gas, it will be necessary to place the
burden on consumers through applying a weighted average. Such work will be carried out by
the Power Regulatory Authority, and this function will become more important in the future.
Figure b-2 shows the priority implementation items in the next plan.
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―4
Source: JICA Study Team
Figure b-2 Priority Implementation Items in the Next Plan
Priority Implementation Items in the Next Plan
b. Best mix of energy
Reexamination Items Important enforcement Items
b. Development of coal thermal power c. development renewable energy
a. Increased in own funds
b. Utilization of international ODA funds
c. Utilization of private capital (IPP)
a. Cost cutting among electric utility operators
b. Revision of electricity tariffs
c. Improvement of the time zone based Electricity tariff system
Review of demand forecast
Power sources development plan
a. Development of gas turbine and pumped storage hydroelectric power
Electricity tariff system
d. Diversification of fundraising sources based on PEEGT privatization and splitting
Fundraising
e. Encouragement of the early development and utilization of confirmed reserves of shale gas
f. Discussion on securing energy with
neighboring countries
Renewable energy
c. Improvement in legal efficiency of devices used in traffic modes (especially
automobiles) and the domestic sector
a. continuation of sustained and phased development
b. International cooperation (Japan, surrounding countries, Europe)
a. Energy saving plans in the industry, commerce and the public sectors
b. Reduction of distribution losses and building of statistics in the electric power sector
Energy Saving Securing of energy
a. Building of the natural gas and coal supplysystems
c. Diversification of energy supply sources
d. Early implementation of renewable energy projects
a. Compilation of internationally acceptable Syrian environmental evaluation criteria
a. Boosting of transmission lines in case where
The future balance cannot be maintained b. separation of operation between 230kv and
400kv systems
Environmental and social consideration Transmission network system
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―5
1.2 Basic Design of Combined Cycle Thermal Power Plant
1.2.1 Outline of Plans
The combined cycle power plant (CCPP) is planned as a high-efficiency multiaxial CCPP
comprising one F-type gas turbine generator (GT), one exhaust heat recovery boiler (HRSG), one
steam turbine generator and related instruments and possessing net output of 360 MW. For the
steam turbine condenser cooling equipment, a naturally ventilated cooling tower will be adopted.
1.2.2 Operation of Power Generating Equipment
(1) Outline
The main and auxiliary power generating equipment will be designed to have no problems when
startup and stopping and in ordinary operation throughout the service life of the equipment. The
auxiliary unit will be given ample redundancy to ensure that there is a high degree of reliability.
The main and auxiliary power generating equipment will be designed so that operation from
startup to rated load can be performed from the keyboard panel with mouse.
(2) Generating equipment operation plan
Generating equipment that can secure high efficiency and high reliability based on proven and
sophisticated technology will be adopted. In the generating equipment design, equipment shall be
able to withstand the operating plan prescribed in the basic design. Moreover, the annual average
operating factor must not fall below the figure of 86.8 percent that is defined in
ISO3977-9:1999(E) (Gas Turbine Procurement) Part 9 (Reliability, Operating Factor, Ease of
Maintenance, Safety).
(a) Schedule requirements for startup time
Startup time will be shortened as much as possible to enable responsiveness to the generating
equipment functions. The generating equipment will be designed to satisfy the startup times
indicated in the following table. Startup time is defined as the time required from selecting the
startup phase to establishment of condenser vacuum, HRSG startup, GT startup, and attainment of
the rated load state after going into parallel operation. The GT air purge and parallel time are
omitted.
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―6
Table b-2 Startup Time Schedule
Startup Process Time (minutes)
Cold startup following stoppage of 36
hours or longer Max. 240 minutes
Warm startup following stoppage of less
than 36 hours Max. 180 minutes
Hot startup following stoppage of less
than 8 hours Max. 120 minutes
Very hot startup following stoppage of
less than 1 hour Max. 60 minutes
Source: JICA Study Team
(b) Operation service life
The main and auxiliary power generating equipment will be designed and constructed based on the
following operation service life:
Operation service life = 30 years
Operation service hours = 183,960 hours at rated load (equipment utilization factor 70 percent)
The generating equipment will be designed so that it can be operated continuously for at least
6,132 hours at rated load.
Incidentally, the times required in the startup and stopping processes are not included in the above
operation time. The main and auxiliary power generating equipment will be continuously operated
with high efficiency, reliability and economy during the operation service life. Concerning
equipment in which there is a possibility that the operation service life will drop below the above
value, it will be designed with consideration given to ease of replacement and maintenance.
(3) Startup and stop times
Starting and stopping of generating equipment will be carried out automatically from the
central control room. The generating equipment will have monitoring and control functions in
order to enable safe, reliable and efficient operation.
It will be possible to carry out parallel and load change operation of the generating equipment
from the central control room. It is assumed that the generating equipment can be operated at
rated load while maintaining high efficiency and reliability over the warranty period of 30
years. The aforementioned conditions are designed based on the annual startup frequency
indicated below.
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―7
Table b-3 Startup Frequency
Startup process Number of
startups per
year
Number of startups
over the warranty
period
Cold startup (following stoppage of
36 hours or longer)
2 60
Warm startup (following stoppage of
less than 36 hours)
5 150
Hot startup (following stoppage of
less than 8 hours)
30 900
Very hot startup (following stoppage
of less than 1 hour)
5 150
Total 42 1,260
Source: JICA Study Team
A turbine bypass system will be attached to the steam turbine system in order to enhance
operating reliability at startup times, load change times, stop times and in emergencies.
1.2.3 Outline of Generating Equipment Control
(1) Scope of automation
In order to enable the operators to monitor and control the generating equipment from the
central control room, the equipment start/stop control and protection functions will be totally
automated. However, manually operated break points will be included as necessary in the
start/stop control sequence. Startup operation can be selected and automatically controlled
according to each startup condition, i.e. very hot, hot, warm and cold.
(2) Generating equipment operation
The central control room will be equipped with the latest DCS (distributed control system)
including data log system with automatic control of generating output in order to enable
demand to be satisfied. An operator’s console equipped with LCD (liquid crystal displays) for
monitoring operation conditions and a keyboard panel with mouse for operating the generating
equipment will be installed in the central control room. LCD control will be adopted in order
to simplify the interface between humans and machines and enhance the monitoring and
control and operating reliability of generating equipment. A standby redundant system
comprising a dual structure will be adopted for the central processing unit (CPU) in order to
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―8
secure reliability of the control system. Moreover, parallel and parallel-off operation based on
the generator circuit breaker will be conducted from the central control room.
(3) Operation during high and low system frequency
The GT generator and ST generator are designed to withstand continuous operation under
conditions of system frequency fluctuation of 48.5~51.5 Hz during load operation. Moreover,
loaded operation at low frequency of 46.5~48.5 Hz shall be possible on condition of limited
operating time. The control device required for loaded operation will be designed upon
considering the power system conditions.
(4) Vibration value control
In rated load operation from GT startup, the shaft vibration value of the GT and GT generator
and ST and ST generator will be limited. ISO7919 or an appropriate standard will be followed
regarding the method for measuring shaft vibration. In the bearings of the GT/ST shafts, the
unfiltered comparative shaft oscillation displacement will be measured as the vibration value.
Concerning control of the vibration value during operation, as is shown in the following table,
ISO7919-2:2001(E) part 2 (Large land stead turbine generator set) and ISO7919-4:1996(E)
part 4 (Gas turbine set) will be followed.
Table b-4 Vibration Control Values
Equipment Vibration Value
(p-p μm)
Gas turbine and gas turbine generator 80 μm or less
Steam turbine and steam turbine generator 80 μm or less
Source: JICA Study Team
The shaft vibration value in GT and GT generator and ST and ST generator must not exceed
80 μm in reliability testing. If the vibration value in any of these units exceeds this value
during two weeks of reliability testing, the testing will be suspended, countermeasures will be
taken and a new reliability test will be conducted for another two weeks. The vibration value
shall not exceed 80 μm during the defect liability period following receipt of the generating
equipment. The vibration value shall be adjusted so that it doesn’t go higher than 120 μm in
the GT and GT generator and ST and ST generator. In cases deemed permissible based on
operating experience of similar type GT and GT generator and ST and ST generator, the trip
value may be set at 240μm.
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―9
(5) Load control
The power load of generating equipment is requested to the generating equipment from the
central dispatch room based on the SCADA system. After the operator sets the power demand
of generating equipment by the DCS via the operator’s console to ensure that the demand on
power load in the generating equipment is satisfied, the generating equipment will be
automatically operated.
1.2.4 Examination of Basic Technical Issues
(1) Selection of CCPP model
On the international market, there are four models of combined cycle power generating
equipment (CCPP) composed of a 50 Hz large capacity gas turbine model in which the turbine
inlet temperature is at the F-class level. These CCPPs, which are based on abundant operating
experience, are F-class gas turbines by four manufacturing companies (OEM). According to
the Gas Turbine World 2007-2008 GTW Hand book, these four models are as follows.
GT OEM maker CCPP model No.
Alstom KA26-1 AQC
GE S109FA, S109FB
Mitsubishi Heavy Industries MPCPI (M701F)
Siemens SCC5-4000F 1x1
Alstom can supply two types of gas turbine. One of these is equipped with an air-based cold
air cooling device, and the other has a steam-based cold air cooling device. Steam is used to
cool the air that is extracted from the air compressor used for cooling the hot parts of the gas
turbine, and the equipment cannot be operated without the steam media.
(2) Rated and maximum capacity performance
Utilizing the performance particulars under gas turbine ISO conditions that are stated in the
GTW Handbook, the performance of each CCPP model is indicated in the following table.
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―10
Table b-5 Gas Turbine Model Performance
Gas turbine model GT26(AQC) PG9371(FA) M701F4 SGT5-4000F
ISO base rating (MW) 288.3 255.6 312.1 286.6
Efficiency (%) 38.1 36.9 39.3 39.5
Pressure ratio 33.9 17.0 18.0 17.9
Air flow (kg/s) 648.6 640.9 702.6 689.4
Exhaust air
temperature (℃)
616.1 602.2 596.7 577.2
Fuel gas flow (kg/s) 15.4 14.09 16.16 14.76
Source: JICA Study Team
The equipment capacity of the plant generating equipment and auxiliary units needs to be
determined according to the maximum operating capacity of the gas turbine and the
corresponding capacity of bottoming equipment (HRSG and steam turbine). The maximum
operating capacity of the gas turbine differs greatly depending on the air temperature.
Therefore, in order to decide the equipment capacity of the plant generating equipment and
auxiliary units, it is necessary to determine the site atmospheric conditions that define the
maximum operating capacity of the gas turbine. Providing that the maximum operating
capacity of the gas turbine is within the design permissible maximum capacity, it will increase
in line with the atmospheric temperature. The atmospheric temperature at which the gas
turbine reaches the design permissible maximum capacity is usually given as minus 10� or
less, although this depends on the design philosophy of the maker.
The cycle composition and parameters of the CCPP bottoming system differ according to the
design philosophy of the maker, however, the case of a similar CCPP is indicated below.
GT inlet air cooling equipment: Not used
GT outlet exhaust air gas leakage: 0.5percent
Cycle composition: Triple pressure, reheating
Cooling equipment: Mechanical ventilated cooling tower
HRSG type: Non-supporting system
HP steam conditions: Temperature 560℃ , pressure 11.8Mpa
IP steam conditions: Temperature 560℃ , pressure 2.94Mpa
LP steam conditions: Temperature LP SH and IPT outlet steam mixing temperature,
pressure 0.34 Mpa
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―11
(3) The following table shows rough performance of the four CCPPs under conditions of no
supporting combustion.
Table b-6 CCPP Model Performance
CCPP model KA26-1 S109FA M701F SCC5
Rated Max. Rated Max. Rated Max. Rated Max.
Total generating
output (MW)
374.7 433.5 344.9 396.3 403.9 465.0 365.6 421.1
Gas turbine (MW) 245.5 288.7 221.8 260.8 270.5 318.1 244.1 287.0
Steam turbine
(MW)
129.2 144.8 123.1 135.5 133.4 146.9 121.5 134.1
Total thermal
efficiency (%)
54.8 56.6 54.6 56.0 55.8 57.3 55.8 57.3
Auxiliary power
(MW)
12.4 14.2 9.9 11.4 11.6 13.4 10.5 12.1
Net generation
output (MW)
362.3 419.3 335.0 384.9 392.2 451.6 355.1 409.0
Net thermal
efficiency (%)
53.0 54.7 53.0 54.4 54.2 55.6 54.2 55.7
Source: JICA Study Team
1.2.5 Optimization of Bottoming Cycle
(1) Examination contents
Combined cycle power generation entails combining differing thermal cycles in the high
temperature zone and low temperature zone. In the high temperature zone thermal cycle, the
Brayton cycle (gas turbine cycle), in which the combustion heat of fuel is used as the heat source,
is used, while in the low temperature thermal cycle, the Rankine cycle (steam cycle), in which the
excess heat of combustion exhaust gas (that is the operating media in the high temperature thermal
cycle) is used as the heat source, is used. These two cycles are incorporated into a combined
engine in which the operating temperature range is extended to include the low temperature zone
and thus improve the overall thermal efficiency.
The performance and construction cost in combined cycle power generation differs according to
the way in which the bottoming cycle (steam cycle) is designed with respect to the given topping
cycle (gas turbine cycle). Generally speaking, if the bottoming cycle becomes complicated, the
performance and construction cost of combined cycle power generation will become higher. In the
case of combined cycle power generation based on T-type gas turbine, three types of bottoming
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―12
cycle can be considered, i.e. triple pressure reheating type, triple pressure non-reheating type, and
double pressure non-reheating type. Concerning performance, since the topping cycle incoming
heat is similar, this corresponds to the difference in generating output. The disparity in power
generating output is the disparity in the amount of sold power during operation. The triple
pressure reheating type has higher performance than the triple pressure non-reheating type and
double pressure non-reheating type. On the other hand, construction cost is higher in the triple
pressure reheating type than in the triple pressure non-reheating type and double pressure
non-reheating type. Accordingly, it can be evaluated whether the disparity in construction cost
between these three bottoming cycles can be complemented through differences in the present
value of revenue from power sales during the operating period.
(2) Examination criteria
(a) Performance conditions
Gas turbine model: Siemens SCC5-4000F
With or without reheating burner: None
Atmospheric temperature: 35℃
Atmospheric pressure: 0.1013Mpa
Cooling water temperature (condenser inlet): 26.7℃
Fuel type: Natural gas
Lower heating value 50,011kj/kg
(b) Economic conditions
Operating period 30 years
Utilization factor 70 percent
Annual operating time 6,132 hours
Load factor 100 percent
First year power sale price 3.2 US cents/kwh
Discount rate 8percent
(c) Performance
The following table indicates the performance of the triple pressure reheating type, triple pressure
non-reheating type and double pressure non-reheating type.
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―13
Table b-7 Bottoming Cycle Performance
Triple pressure
reheating type
Triple pressure
non-reheating
type
Double pressure
non-reheating
type
Gas turbine total output
(MW)
244.1 244.1 244.1
Steam turbine total
output (MW)
121.5 116.3 114.3
Total gross output (MW) 365.6 360.4 358.4
Total generating
efficiency (%)
55.8 55.0 54.7
Source: JICA Study Team
Under the same incoming heat conditions, total output in the case of the triple pressure reheating
type is 5,200 kW higher than in the triple pressure non-reheating type and 7,200 kW higher than in
the double pressure non-reheating type. Moreover, annual generated electric energy in the case of
the triple pressure reheating type is 31.9 million kwh higher than in the triple pressure
non-reheating type and 44.2 million kwh higher than in the double pressure non-reheating type.
(d) Disparity in construction cost
The following table shows the construction cost in each type of system.
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―14
Table b-8 Bottoming Cycle Construction Cost
Unit: US$ 1,000
Item
Triple pressure
reheating type
Triple pressure
non-reheating
type
Double pressure
non-reheating
type
1. Generator and installation cost
and parts procured overseas (FOB
price)
a) Gas turbine and accessories 84,865 84,865 84,865
b) HRSG and accessories 36,419 34,952 34,242
c) Steam turbine and accessories 42,216 40,515 36,692
d) Bottoming cycle equipment 66,958 64,261 62,957
e) Electrical equipment and
instrumentation and control
equipment
45,750 43,906 43,015
2. Overseas transportation and
insurance
7,312 7,018 6,876
3. Domestic transportation and
insurance
3,659 3,511 3,440
4. Construction, trial operation and
insurance
73,093 70,148 68,724
5. Construction cost (excluding
power plant, transmission line, tax
and contingency costs)
360,272 349,176 343,811
Construction cost disparity with the
triple pressure reheating type
0 11,095 16,461
Source: JICA Study Team
(e) Conclusion
From the above table it can be gathered that the disparity in the present value of power sales
revenue during the operating period is larger than the disparity in construction cost. This indicates
that the triple pressure reheating type is more economical than the triple pressure non-reheating
type and the double pressure non-reheating type.
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―15
1.2.6 Exhaust Gas Turbine Equipment
In multiaxial CCPP systems, exhaust gas turbine equipment is usually equipped in order to
enable simple cycle operation in the event where some kind of trouble arises in the bottoming
cycle. This equipment is needed when the power supply is tight and it is necessary to conduct the
commercial operation of gas turbine generating equipment (topping cycle) before the bottoming
cycle. For this reason, it is necessary to install a bypass stack and damper within the high
temperature gas flow in between the gas turbine exhaust system and waste heat recovery boiler
(HRSG). These equipment items comprise a giant mechanical unit that can withstand high
temperatures of up to 650℃; therefore, there is a possibility that operability of the generating
equipment will be reduced. In addition, there is a risk that partial leakage of gas turbine exhaust
gases into the atmosphere will lead to performance losses.
(1) Operating flexibility
The operating flexibility of the CCPP differs according to whether or not there is bypass
equipment for the exhaust gas. If there is such equipment, in the event where a problem arises in
the bottoming cycle, the system can switch to simple cycle operation without interruption.
However, depending on the type of trouble that occurs in the bottoming cycle, there may be cases
where the generating equipment needs to be stopped. For example, if a problem occurs only in the
steam turbine part, since all the generated steam is discharged into the condenser via the steam
turbine bypass line, the generating equipment can continue operation through the simple cycle.
However, since this type of operation is not viewed as normal, it should be limited to certain times
only. Even so, there is no doubt that operating flexibility can be expanded through installing
exhaust gas bypass equipment. Concerning the startup performance of power generating
equipment, in the case where exhaust gas bypass equipment is installed, high temperature steam
can be quickly generated, warming of the steam turbine is speeded up and the startup time can be
slightly shortened compared to the case where there is no exhaust gas bypass equipment.
(2) Operating reliability
In gas turbine equipment that includes HRSG, a conventional diverter or flapper type damper is
used. Dampers used in F-type gas turbines are very large with dimensions of 7 m x 7 m.
Meanwhile, exhaust gases that are exposed to the damper reach high temperatures of 650℃ . The
damper is designed to operate stably, smoothly and rapidly and with minimum losses from gas
leaks during the service life of the generating equipment. It is very difficult to design the damper
to operate under such harsh conditions in a manner that completely satisfies these contradictory
requirements. This is because the massive metal damper that is exposed to very hot gases cannot
maintain its original dimensions and shape over the service life of the generating equipment. No
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―16
specific figures concerning the operating reliability of exhaust gas bypass equipment has been
provided by power plant users, however, it is inevitable that operating reliability of the entire
power generating system will decline if this equipment is adopted.
(3) Cost impacts
Adopting the exhaust gas bypass equipment will additionally entail the following equipment
and works:
- Bypass stack fitted with silencer (top diameter 7.5 m, height 45 m)
- Diverter damper
- Guillotine damper (for maintenance of the bottoming cycle during simple cycle
operation)
- Gas damper and expansion joint
- Associated site assembly, installation and civil engineering works
- Other related costs
It is estimated that the above items will incur an additional cost of US$6.4 million.
(4) Phased construction
Through adopting exhaust gas bypass equipment, it becomes possible to conduct the phased
construction of the topping and bottoming cycles. Such phased construction is adopted in cases
where the power supply situation is tight and it is necessary to achieve power supply at an early
stage. The total works period of phased construction is longer than the case of simultaneous
construction, however, the start of commercial operation of the gas turbine generating equipment,
which constitutes the topping cycle, is speeded up by approximately six months. This advantage is
evaluated by the purchaser of the generating equipment according to the degree of necessity for
early power supply.
(5) Other perspectives
In the case of an F-type gas turbine in which wider installation space is required for the bypass
equipment, the system becomes approximately 15 meters longer in the axial direction. If the
bypass stack is not equipped with a silencer, there is concern over noise from the stack even if
bypass operation is limited to a short time.
There is concern over whether or not the silencer, which is exposed to high temperature and high
speed gases, can sustain sure and appropriate functions over the service life of the power
generating equipment. Since the exhaust gas bypass equipment is not used all the time, this is all
the more reason to conduct careful routine maintenance to ensure that it can be used normally in
emergencies.
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―17
(6) Summarization of examination
As was mentioned above, adoption of the exhaust gas bypass equipment of course enhanced the
operating flexibility of generating equipment, however, this inevitably leads to decline in
operating reliability and increase in project costs.
1.2.7 Auxiliary Steam Boiler
(1) Necessity
In a multiaxial CCPP with no auxiliary steam boiler, it is necessary to simultaneously start up the
gas turbine and HRSG. If it becomes possible to supply the steam that is required for starting the
HRSG, gland sealing of the steam turbine and so on is completed, however, oxygen concentration
in feed water at the HRSG inlet during startup time becomes higher than the concentration during
operation. In the multiaxial CCPP equipped with auxiliary steam boiler, the steam required for
gland sealing of the steam turbine is supplied from the auxiliary steam boiler before the generating
equipment is started up. Compared to the multiaxial CCPP with no auxiliary steam boiler, the
HRSG and steam turbine can be started without waiting for steam from the HRSG and the oxygen
concentration in feed water at the HRSG inlet during startup time is the same as the concentration
during operation.
(2) Examination items
It is necessary to start up the HRSG and accessories in the shortest time in the case of both gas
turbine individual operation and combined cycle operation. In the case where the auxiliary steam
boiler is not applied, it is necessary to ascertain the startup procedure, startup time, oxygen
concentration in feed water at the HRSG inlet during startup and permissible oxygen concentration
in feed water at the HRSG inlet in this case.
1.2.8 Standards and Criteria
(1) Machinery, electricity and control units
Excluding specially requested items, equipment shall be designed according to the following
international criteria and standards.
Japanese Industrial Standards (JIS)
U.S. standards (ASME, ASTM, etc.)
IEC standards
ISO standards
British standard (BS)
German standards (DIN)
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―18
1.2.9 Environment
(1) Concentrations of air pollutant emissions shall be planned not to exceed the following
levels over the range of 75~100percent output.
Table b-9 Limit Values on Concentration of Air Pollutant Emissions
Pollutant Emission concentration limit value
Gas No more than 40
ppmv NOx
Light oil No more than 100
ppmv
Gas No more than 20
ppmv CO
Light oil No more than 50
ppmv
Gas 10mg/m3N Particulates
Light oil 10mg/m3N
SO2 Light oil No more than
200ppmv
Source: JICA Study Team
(2) Noise
The noise level of all operating equipment during regular operation will be planned no higher than
85 db (A) at a distance of 1 meter (height of 1 meter) from the edge of the equipment or enclosure.
Moreover, at the site perimeter, the noise level shall be planned to exceed no more than 70 db (A).
Noise measurement and testing will be carried out according to ANSI B133.8. Also, noise
proofing equipment such as silencers and soundproof walls will be installed in order to conform to
the noise standards.
Table b-10 Noise Standard
Maximum noise
level
Distance of 1 meter (height of 1 meter) from the edge
of the equipment or enclosure
No more than
85db(A)
Site perimeter No more than
70db(A)
Source: JICA Study Team
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―19
1.2.10 Gas Turbine
The gas turbine is usually operated on natural gas, however, in the event where natural gas is
in short supply, equipment will be equipped with the function to enable operation on diesel oil
equivalent to No. 2 GT oil as designated in ASTM D 2880. In the case where it is operated on
the designated natural gas over the range of 75~100 percent load, the gas turbine shall have a
sophisticated design satisfying the NOx emission requirement of less than 40 ppm (15 percent
O2 dry volume standard) with no injection of steam or water under all atmospheric
temperature conditions. Moreover, in the case of operation on diesel oil, it shall be possible to
inject pure water and operate while satisfying the NOx emission requirement of less than 100
ppm (15 percent O2 dry volume standard).
The gas turbine must be designed and verified according to the design criteria of the
manufacturer (OEM) upon basically satisfying the ISO21789 Gas Turbine Application-Safety
requirements. In axial design of the gas turbine, the minimum bearing is used on a steel frame
or appropriate steel structure or concrete foundation with sufficient size to withstand
instantaneous maximum transfer torque in the event of either generator shorting or phase
shifting simultaneous operation, whichever one is larger.
1.2.11 HRSG
(1) Circulation method
The HRSG circulation method can either be a natural circulation system or a forced
circulation system. In the natural circulation system, circulating force is secured by means of
the density difference between boiler water in downcast pipes and the steam-water mixture in
the steam generating tubes. In the forced circulation system, circulating force is secured by
forcibly circulating the steam-water mixture from the drum to the steam generating tubes and
from the steam generating tubes. With the forced circulation system, it is possible to conduct
rapid warm or hot startup. In the natural circulation system, since no circulating pump is
required, operating costs entailed in pump breakdowns and maintenance can be economized
on. At times of cold startup, since time is required to increase the temperature of the HRSG
unit and boiler water, there is no difference in startup time between the natural circulation
system and forced circulation system.
1.2.12 Steam Turbine
The steam turbine will be a reheat, triple pressure, two-cylinder or single-cylinder condensing
type directly coupled to the generator. In this, steam is discharged to the surface condenser in
the downward or axial direction and cooled by the circulating water. The circulated water is
cooled in the naturally ventilated cooling tower. Maximum capacity of the steam turbine shall
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―20
be enough to accept the steam at the pressure, temperature and flow conditions generated by
the HRSG when the gas turbine is operated under the conditions that exhibit the maximum
capacity. When the steam turbine is operated for the designated period under the designated
conditions, the main components (cylinders and shaft) must be designed so that the level of
life consumption at the end of the operating period does not exceed 75 percent of the
remaining life of the main components.
1.2.13 Fuel Supply Equipment
(1) Fuel gas supply equipment
The gas turbine will be designed so that it can operate using the designated natural gas. The
fuel gas supply equipment will include the step-up compressor, pretreatment equipment and
pressure regulator that are required to conduct the starting, stopping and continuous operation
of the gas turbine. The pretreatment equipment is intended to pretreat the natural gas in order
to enable the gas turbine to be continuously operated.
(2) Fuel oil supply equipment
The gas turbine will be designed so that it can operate using the designated light oil. As with
the fuel supply equipment, the fuel oil supply equipment will be designed so that it is possible
to conduct the starting, stopping and continuous operation of the gas turbine. Concerning how
much emergency light oil needs to be stored, it is estimated that a light oil tank with enough
capacity to hold a seven-day supply of light oil (2,000kl/day x 7 days = 14,000 kl, however,
20,000 kl to be on the safe side) for emergencies in the event of gas equipment breakdown will
be needed.
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―21
1.2.14 Water Treatment Apparatus
Process water including pure water, potable water, cleaning water, firefighting water and
miscellaneous water will be manufactured from groundwater using a pretreatment unit.
Groundwater will be directly utilized to provide the makeup water for the cooling tower. Pure
water will be used as HRSG makeup water, auxiliary equipment cooling water, chemical
injection water and for injection to the gas turbine during oil combustion and so forth. The
pretreatment unit will comprise coagulating sedimentation tank and filter, while the pure
water unit will comprise a chemical storage tank and regeneration unit, etc. Moreover, the
question of whether or not to install a pretreatment unit and the specifications of the unit will
be determined by the quality of the groundwater.
1.2.15 Wastewater Treatment Unit
Wastewater comprises HRSG blow water, floor drainage from the gas turbine and steam
turbine house, and neutralized surface wastewater from the transformer area. Domestic
wastewater such as sanitary sewage and toilet wastewater will be treated in a septic tank,
whereas the floor drainage from the gas turbine and steam turbine house and surface
wastewater from the transformer area will be treated in a wastewater treatment unit after
passing through an oil separator.
1.2.16 Firefighting Equipment
(1) Fire safety methods
In order to protect plant employees and equipment from fires and other disasters, the facilities will
be designed and planned so that there is ample space secured between equipment units and
fireproof specifications are adopted in equipment and materials. Risk areas will be configured
separately according to types of hazardous objects and handling methods. In order to protect
equipment, zones and buildings that entail differing methods of operation, it is necessary to install
different types of firefighting equipment. The CCPP firefighting equipment will have enough
capacity to withstand fire for at least two hours (capacity 300 m3, pressure 10 bar) according to
NFPA850. Fire pumps will comprise the following equipment:
- Electric jockey pump, 100 percent capacity: 1 unit
- Main electric pump, 100 percent capacity: 1 unit
- Main diesel pump, 100 percent capacity: 1 unit
The main electric pump will secure the necessary water flow and pressure under the harshest
conditions, while the main diesel pump will be kept on standby to cover in the event where the
main electric pump breaks down. The capacity of the main diesel pump will be the same as
that of the main electric pump.
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―22
Table b-11 Protected Areas and Firefighting Equipment
Item Building and Area Firefighting Equipment
1 Gas turbine Carbon dioxide firefighting equipment
2 Steam turbine lubricating oil and
lubricating pump
Powder firefighting equipment
3 Steam turbine bearings Powder firefighting equipment
4 Steam turbine building Stand type equipment
5 Generator, main transformer and
starting transformer
Powder firefighting equipment
6 Oil tank Installation of foam firefighting
equipment and oil fence
7 Control room
Cable treatment room: sprinkler unit
Control room: argon type or similar type
8 Electric equipment and switchgear Water sprinkler or, where necessary,
mobile fire extinguishers
9 Common Protective device for detecting fire or gas
in the control room
Source: JICA Study Team
(2) Outline of firefighting equipment
Generally, NFPA specifications will be adopted for the CCPP firefighting equipment, however,
the fire control law will also be complied with. Fire extinguishers will be categorized and
arranged according to NFPA10. Moreover, according to NFPA72, building fire detectors,
automatic fire detectors and fire display panel will be installed. The firefighting system will
be designed so as to supply firefighting water for two hours according to NFPA. It will be
necessary to separately design the firefighting water supply system to ensure that firefighting
functions can be maintained even if part of the supply system breaks down.
1.2.17 Electrical Equipment
(1) Electric system
(a) Electric system from the generator to the substation
Electricity generated in the gas turbine generator will be stepped up in the gas turbine step-up
transformer, while electricity generated in the steam turbine generator will be stepped up via the
steam turbine step-up transformer, and the stepped-up electricity will be connected to the
substation for transmission to the external power transmission network. The power source for the
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―23
in-station auxiliary power, etc. will be the unit type whereby it is separated from the generator
main circuit during regular operation and power is supplied via the in-station transformer. At
startup time, when the gas turbine generator reaches the rated speed and rated voltage, it will be
connected to the external power transmission network by means of the gas turbine generator
circuit breaker. Next, when the steam turbine generator reaches the rated speed and rated voltage,
it will be connected to the external power transmission network by means of the steam turbine
generator circuit breaker.
(b) Generator main circuit
The system will be composed of the gas turbine generator and steam turbine generator. Each
generator, main transformer, excitation transformer and instrumentation transformer will be
connected to the isolated-phase bus (IPB) and eventually to the external transmission network
after passing through the secondary side generator circuit breaker and generator disconnecting
switch.
(2) Generators
The generator specifications are as indicated below.
Table b-12 Generator Specifications
Type of generator Gas turbine generator Steam turbine generator
Type Three-phase AC
synchronous generator
Three-phase AC
synchronous generator
Number of poles 2 2
Phases 3 3
Capacity 248MVA 131.6MVA
Frequency 50Hz 50Hz
Rotating speed 3.000rpm 3.000rpm
Terminal voltage 16kv 11kv
Power factor 0.8 0.8
Rotor cooling
method
Hydrogen or air Hydrogen or air
Stator cooling
method
Hydrogen or air Hydrogen or air
Source: JICA Study Team
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―24
(3) Generator cooling system
Generator cooling systems for gas turbines and steam turbines will comprise the air cooled
type and the hydrogen gas cooled type. According to IEC conditions, the generator
manufacturer (OEM) will need to have a past record of supplying at least two air cooled
generators and two hydrogen gas cooled generators.
(4) Comparison of generator cooling equipment
Recently, as a result of technological progress in cooling performance and reduction of windage
loss, air-cooled equipment is adopted in generators with output of 300 MVA or more. Compared to
hydrogen gas-cooled equipment, the air-cooled equipment is simpler, entails easier operation and
maintenance and is more cost effective. On the other hand, the hydrogen gas-cooled equipment is
more compact and is more advantageous for transportation and installation.
(5) Excitation method
In each generator, a static thyristor excitation device will adjust the field current and control
voltage at the generator terminals. The thyristor excitation device includes an excitation
transformer, automatic voltage regulator (AVR), thyristor unit and field circuit breaker.
The automatic voltage regulator adopts a generator excitation device for detecting the generator
voltage and controlling reactive power so that the voltage is at the set level.
(6) Transformer
(a) Gas turbine transformer
The gas turbine transformer, which will step up the generator voltage to the transmission voltage
level, will comprise either an oil-insulated three-phase transformer with load tap switcher or four
single-phase transformers (including one for backup), and the oil natural air forced (ONAF)
method will be adopted as the transformer cooling system. The transformer winding method will
be Δ-Y.
(b) Steam turbine transformer
The steam turbine transformer, which will step up the generator voltage to the transmission
voltage level, will comprise either an oil-insulated three-phase transformer with load tap switcher
or four single-phase transformers (including one for backup), and the oil natural air forced
(ONAF) method will be adopted as the transformer cooling system. The transformer winding
method will be Δ-Y.
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―25
(c) In-station transformer
The in-station transformer, which will step down the generator voltage to the station level, will
comprise either an oil-insulated three-phase transformer with load tap switcher or four
single-phase transformers (including one for backup), and the oil natural air forced (ONAF)
method will be adopted as the transformer cooling system. The transformer winding method will
be Δ-Y.
(d) Startup transformer
The in-station transformer, which will step down the external transmission voltage to the station
level, will comprise either an oil-insulated three-phase transformer with load tap switcher or four
single-phase transformers (including one for backup), and the oil natural air forced (ONAF)
method will be adopted as the transformer cooling system. The transformer winding method will
be Y-Y-Δ stable winding. Through adopting the Y-Y-Δ method, it will be easier to detect grounding
failure current. The following table shows the standard specifications of each transformer.
Table b-13 Standard Specifications of Transformers
Item GT transformer ST transformer In-station
transformer
Startup
transformer
Primary 16kv 11kv 16kv 132kv Rated
voltage Secondary 230kv 230kv 6.9kv 6.9kv
Primary 11,547A 8,398A 722A 87.5A Rated
current Secondary 803A 402A 1,674A 1,674A
Primary 320MVA 160MVA 20MVA 20MVA Rated
capacity Secondary 320MVA 160MVA 20MVA 20MVA
Phase wiring Δ-Y Δ-Y Δ-Y Y-Y-Δ
Cooling method ONAF (oil
natural air
forced)
ONAF (oil
natural air
forced)
ONAN (oil
natural air
natural)
ONAN (oil
natural air
natural)
Source: JICA Study Team
(e) Single-phase transformer and three-phase transformer
When it comes to replacing a single-phase portion of a transformer at times of transportation or
failure, it is more advantageous to have three single-phase transformers. Meanwhile, in cost terms,
adopting three single-phase transformers is more expensive because it is necessary to have a spare
transformer and control devices and foundations for each transformer unit. The single-phase
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―26
transformer and three-phase transformer systems are similar in terms of performance.
(7) In-station power supply
Concerning the in-station power supply, the power supply system is composed of the in-station
transformers and startup transformer. In the system used in the CCPP, power will be supplied from
the in-station transformer, while the power for common equipment (water treatment and
wastewater treatment equipment, etc.) will be supplied from the startup transformer. Also, one
three-phase diesel generator will be installed as the emergency power supply in order to enable the
protective power supply to be secured when the CCPP is entirely suspended. Power supply for C
load will be obtained from the DC distribution panel. It shall be possible to secure safe stoppage
of the generating equipment when the CCPP is entirely suspended.
1.2.18 Power Generating Equipment Protection and Control
(1) Protection of generators and transformers
The generator main circuit is composed of the GT generator, GT transformer, ST generator
and ST transformer. The relays for protecting the main circuit will be as follows.
Table b-14 Generator Protective Circuit
Name Element
GT generator operating ratio 87G1
GT transformer operating
ratio
87T1
ST generator operating ratio 87G2
ST transformer operating ratio 87T2
Reversed phase 46
Field loss 40
Generator reverse power 67
Grounding overcurrent 51GN
Over excitation 24
Generator over-voltage 59
Generator low voltage 27G
Frequency high and low 81
Source: JICA Study Team
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―27
(2) Control and monitoring system
The control and monitoring system will be designed to ensure that the maximum safety of CCPP
employees and equipment can be secured and enable the CCPP to be operated safely and
efficiently under all conditions while bearing in mind the peak potential. The control and
monitoring system to enable fully automatic operation of the generating equipment will comprise
a distributed control system (DCS) in consideration of technical and cost factors. The DCS
equipment will enable the control and monitoring of the entire generating system including the
control and monitoring of common equipment.
Basic composition of DCS:
Calculation and power source circuitry will be duplexed and the input/output circuitry will
be single line.
Dual power supply, i.e. AC and DC, will be adopted (matching system).
The core transmission network will be duplexed.
Operations will basically be carried out by mouse.
(3) Generating equipment control and monitoring unit
The generating equipment control and monitoring unit will be composed of DCS equipment,
information control system, maintenance system, transmission network system and related devices.
The DCS equipment will comprise the operator’s console, turbine control system, data collection
system, sequence control system, process I/O system and peripheral equipment all connected in a
transmission network configuration. The GT control system, ST control system, HRSG and local
control system will be connected to the DCS by redundant communications link and hard wiring
signals. Detection for carrying out protective control of the GT, ST and HRSG will be a redundant
triple composition geared to enhancing the reliability of the generating equipment. The control
system will be designed to enable the generating equipment to be operated and controlled by an
automatic system. Also, this will convey to operators information on the status of generating
equipment, start and stop operations, troubleshooting and the routine operating status. The control
logic and graphic display composition of the control system will be designed to ensure that
maintenance staff can easily and correctly make revisions and changes on the ground.
DCS equipment will be planned to possess the following functions.
(a) Turbine control and monitoring function
GT control and monitoring and GT protective circuit
HRSG control and monitoring and HRSG protective circuit
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―28
ST control and monitoring and ST protective circuit
High voltage control hydraulic system control
Generator protection, excitation control, voltage control, parallel/parallel-off control
Auxiliary unit control and monitoring
(b) Information collection and control functions
Scan and warning
Process calculation (including performance calculation)
Data log function and data display
(c) Common equipment control and monitoring function
Fuel oil equipment
Water treatment equipment
Wastewater treatment equipment, etc.
1.2.19 Civil and Building Works
The civil and building works will include geologic survey, site creation, design and construction
of rainwater and site wastewater drainage equipment, underground utilities and water intake pipes,
road works, paving and surface gravel laying and compaction, main and auxiliary buildings and
structures including foundations, foundations for indoor and outdoor equipment, building
equipment such as lighting, lightning conductor equipment, sanitary sewage equipment, air
conditioning and ventilation equipment.
The applicable international criteria and standards are indicated below:
The American Concrete Institute concerning concrete works (ACI318)
The American Institute of Steel Construction (AISC) concerning steel structures
American Iron and Steel Institute (AISI)
American Society of Civil Engineers (ASCE)
American Society For Testing and Materials (ASTM) concerning materials quality
control
American Association of State. Highway and Transportation Officials (AASHTO)
concerning road drainage
American Welding Society (AWS) concerning welding
American Water Works Association (AWWA) concerning concrete pipes and distribution
pipes
The National Fire Protection Association (NFPA)
The American Society of Mechanical Engineers (ASME)
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―29
The American National Standards Institute (ANSI)
1.2.20 Construction Cost
Table b-15 shows the results of calculating the rough cost of constructing an 800 MW class
combined cycle power plant according to the above basic plan using TEPSCO software and taking
the site conditions in Syria into consideration.
Based on the basic plan, this cost estimation assumes a multiaxial combined cycle power plant
(gas turbines x 2 units, heat recovery boilers x 2 units, steam turbine x 1 unit) of a type that is
frequently adopted in developing countries, uses gas as the main fuel and can combust auxiliary
fuel (in the event where there is a shortage of gas). For steam cooling, considering the
environment in Syria, ACC (draft direct air cooled condenser) will be adopted, the transmission
end output will be 803 MW and the efficiency will be 55.6 percent as indicated in the heat balance
given later.
Table b-15 Construction Cost Calculation
Unit: US$x1000
Description Equipment Material Labor Total
Combustion Turbine & Accessories 175,635 4,956 2,813 183,404
Inlet Filtration System 4,701 459 543 5,703
Electrical Systems - Combustion
Turbine 21,282 373 1,924 23,579
Condensate Heating System 5,002 18 915 5,935
HRSG & Accessories 64,508 1,297 12,023 77,828
Deaeration System 314 128 356 798
Steam Piping 0 14,059 9,043 23,102
Electrical Systems - HRSG 171 316 827 1,314
Steam Turbine & Accessories 52,857 3,447 2,118 58,422
Steam Bypass System 1,769 61 317 2,147
Electrical Systems - Steam Turbine 9,379 2,266 2,458 14,103
Condenser & Accessories 38,593 2,724 12,216 53,533
Water Treatment System 2,370 808 1,291 4,469
Waste Water Treatment System 1,541 61 628 2,230
Auxiliary Boiler & Accessories 2,617 663 691 3,971
Boiler Feed System 2,705 321 982 4,008
Condensate System 400 201 440 1,041
Buildings 1,613 19,570 12,786 33,969
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―30
Description Equipment Material Labor Total
Fire Protection System 1,467 56 1,146 2,669
Fuel Systems 3,805 825 1,639 6,269
Fuel Gas Compressor & Accessories 15,590 2,517 1,160 19,267
Bypass Stack & Diverter Valve 12,094 380 4,198 16,672
Main Exhaust Stack 0 3,127 2,011 5,138
Station & Instrument Air System 1,287 619 508 2,414
Closed Cooling Water System 1,019 791 528 2,338
Cranes & Hoists 225 200 224 649
Plant Control System 2,300 0 203 2,503
Continuous Emission Monitoring
System 1,556 1,003 2,033 4,592
Total Process Cost 424,800 61,246 76,021 562,067
General Facilities (Adm bldg, workshop bldg, warehouse, etc.) 21,078
Engineering Fees for plant design by EPC contractor 31,616
Consulting Fees 21,078
Physical Contingency 28,103
Total Plant Cost 663,942
Net Plant Power Output (MW) 802.3
Total Plant Cost per Net kW
(US$/kW) 828
Source: JICA Study Team
As is shown above, the total construction cost is US$663.9 million. In terms of kW unit cost, this
comes to 828US$/kW. This unit cost does not include Syrian taxation, civil engineering works in
consideration of the site conditions, spare parts required for periodic inspections, gas supply
equipment to the plant, and the construction contingency fund.
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―31
274.1 G 40.1 G 432.8 G 2,357.0 G
1.4 G 3,515.9 H 2,923.6 H 230.8 H 98.1 H275.6 G 237.7 T 13.0 P 53.8 G 0.54 P 0.71 P 93.0 P
3,503.1 H 568.0 T 3,053.7 H 232.9 T 55.0 T 93.8 T
13.0 P 3.25 P
563.0 T 326.0 T
2,357.0 G
662.7 H96.5 kPa
599.7 T
319.5 G
3,607.3 H3.15 P
568.0 T
275.6 G G t/hr3,501.5 H H kJ/kg
12.4 P 80.1 G P Mpa
1.4 G 560.0 T 2,918.3 H ToC
237.7 T 0.51 P
11.8 G 641.8 G 229.9 T Steam662.7 H 3,589.8 H Water
93.0 kPa 2,368.8 G 3.09 P Cooling Water599.7 T 662.7 H 560.0 T 740.5 G Gases
96.5 kPa 3,061.1 H599.7 T 120.7 G (Ambient Air) 265.7 G 0.49 P
15.0 T 3,162.7 H 298.1 T
3.31 P
372.0 T
*1 370.9 G
165.2 H0.81 P
39.3 T
740.5 G
300.0 T 2,455.2 H52.59 G 9.1 P(kPa)
49,348 *1 2,316.3 G 31,300 G 38.0 T
15.0 T 15.1 H 30.0 T
93.0 kPa
15.0 T
741.8 G
160.1 H0.81 P
49,790 740.5 G 38.1 T
49,518 200.0 T 159.1 H92.2 T 182.7 T 6.6 P(kPa)
38.0 T
15.0 T
Wet Bulb Temperature
49,320 kJ/kg
Ambient Pressure 93.0 kPa
Relative Humidity 50.0 %
Operating Conditions
Dry Bulb Temperature 15.0 oC
Plant Gross Power Output
kW
kW
kW Total 826,900
Gas turbine (2× 281,950 kW)
Steam turbine
563,900
263,000
57.4 Plant Gross Thermal Eff %
24,600 kW Auxiliary Power Plant Net Power Output
Type of Fuel Natural Gas
10.9 oC
Plant Net Thermal Efficienc 55.6 %
802,300 kW
LHV+Sensible Heat (kJ/kg)
LHV+Sensible Heat (kJ/kg)
LHV+Sensible Heat (kJ/kg)
Net Specific Energy
Preliminary Heat and Mass Balance Diagramof 800MW Natural Gas Fired Combined Cycle Power Plant
with Forced Draft Direct Air Cooled Condenser
at Site Conditions
HP SH
RHTR
IP SH LP SHHP EVA IP EVA LP EVAHP ECO IP ECO LP ECO
HPT IPT LPTTurbine Air Compessor
Combustor
from Gland Seals
TCACoole
Fuel GasHeater
Fuel GasComp
from NO.2 HRSG
to NO.2 HRSG
from NO.2 HRSG
Steam Turbine to NO.2 HRSG
Steam Turbine GeneratorNO.1 Gas Turbine Generator
NO. 1 Gas Turbine
NO. 1 HRSG
from NO.2 HRSG
Air Cooled Condenser
Condensate Drain Pot
Figure b-3 Combined Heat Balance
Source: JICA Study Team
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―32
1.3 Basic Plan of the Coal-fired Thermal Power Plant
(1) Rated output and mode of power generation
The plant will be planned assuming rated output of 600 MW at the transmission end and
subcritical pressure equipment (steam pressure 16 MPa, steam temperature 538℃) as the mode of
power generation. The main reasons for selecting subcritical pressure equipment are as follows:
Base load operation with operating factor of around 80 percent entailing few starts and
stops and load change commands will be planned for.
When adopting supercritical pressure (22.1 MPa or higher) for the plant steam conditions,
since there is no specific gravity disparity between steam and water and water cannot be
circulated in water-cooled walls, inevitably a through flow boiler is adopted. In the case
of a through flow boiler, because no drum for separating steam and water is installed, it is
not possible to blow impurities from the feed water as in the case of a drum boiler. In
order to prevent steam containing impurities being conveyed to the turbine, in the case of
a through flow boiler, it is necessary to comply with strict water quality standards such as
preparing extremely high purity boiler feed water.
In supercritical pressure equipment, high plant efficiency can be obtained, however,
compared to subcritical pressure equipment, construction costs are more expensive due to
the use of expensive materials and installation of a condensate demineralizer.
In supercritical pressure equipment, sophisticated technology is required for conducting
the welding repair of high temperature high pressure materials.
Subcritical pressure equipment is numerously proven and entails easy operation and
maintenance.
(2) Equipment Composition
(a) Outline of boiler equipment
The equipment will be planned as a pulverized coal-fired subcritical pressure forced
circulating drum-type boiler. For the burner, a low NOx burner will be adopted, the ventilation
method will be balanced ventilation, and smoke tunnel equipment will comprise major fans
such as primary air fan, forced draft fan and induced draft fan as well as air preheater, electric
dust collector, desulfurization equipment and other environmental instruments, etc. As for the
fuel-related equipment, a coal pulverizer, coal bunker, coal feeder and belt conveyor
equipment, etc. will be installed.
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―33
Boiler type: Pulverized coal-fired forced circulating drum-type boiler
Steam flow rate: 1,800 t/h
Superheater outlet steam: 17MPa/541℃
Reheater outlet steam: 3.5MPa/300℃
Burner type: Pulverized coal-fired low NOx burner
Furnace outlet temperature: This shall be at least 50℃ lower than the used fuel ash
melting temperature.
Boiler efficiency: Approximately 80 percent
Soot blowers: Install in the furnace, superheater, reheater, coal economizer and air
preheater.
Coal pulverizer: Install six units with 50 t/h capacity, and use one of these for standby
purposes.
Air and combustion gas equipment: Install balanced ventilation, electric dust collector
and desulfurization equipment.
(b) Outline of turbine equipment
The turbine is composed of the turbine generator unit, condenser equipment, condensing
equipment, feedwater superheater equipment, feedwater pump equipment, cooling water
equipment, seawater system equipment, sealed oil equipment and stator cooling equipment, etc.
Concerning the turbine unit, a tandem compound condensing turbine comprising four cylinders, i.e.
high pressure cylinder, medium pressure cylinder and two low pressure cylinders, will be adopted.
The four-flow type will be adopted for low-pressure air exhaust. For governor control, electronic
hydraulic control will be adopted and high-pressure and low-pressure turbine bypass devices will
be equipped. The feedwater superheater system will comprise three low pressure feedwater
superheaters and three high pressure feedwater superheaters. For the condenser cooling water
pipes, super stainless pipes will be adopted. The condenser will be a surface contact type with one
path and two chambers, and a continuous washing unit will be installed. Moreover, the turbine
drive system will be adopted for the feedwater pump and this will be used during normal operation,
while a powered water feed pump will be used at times of equipment starting and stopping.
The generators will be cooled by the hydrogen cooling method. As accessories, stator cooling
equipment, sealed oil equipment and hydrogen ventilation equipment will be installed. Moreover,
for adjustment of the generator voltage, an AVR (automatic voltage regulator) system will be
adopted and a PSS (power system stabilizer) will be used to stabilize the power system.
Steam turbine: 4 cylinder, reheat condensing extraction turbine
Output: 600MW
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―34
Revolutions: 3,000rpm
Governor control system: Electronic hydraulic governor
Condenser: Horizontal, surface cooling, 1 path, double partition of water chamber,
continuous washing unit
Turbine bypass system: High pressure and low pressure turbine bypass system
(c) Outline of water treatment equipment
Because there is no large freshwater resource close to the power plant, a desalination plant
utilizing river water will be installed. The water making capacity will be approximately 2,000
cubic meters per day. This freshwater will be planned so that it can be used not only in the
power generating equipment but also for making coal slurry in the desulfurization equipment.
Concerning the desalination process, either the evaporation method or the reverse osmotic
membrane method can be adopted, however, the latter one will be adopted here.
(d) Outline of coal equipment and coal unloading, storage and transporting equipment
The coal equipment and coal unloading, storage and transporting equipment will be designed
based on the transportation method, heating value of coal, density of coal, unloading speed
and conveyance speed, etc. The equipment will comprise the coal receiving jetty, coal storage
yard and the belt conveyor for linking these items of equipment. In terms of coal lifting
capacity, there will be two lines with capacity of approximately 800 tons per hour, while
concerning the coal conveyance capacity, it is planned to install two lines with capacity of
approximately 500 tons per hour. Capacity of the coal yard will depend on the coal
transportation method, however, it is desirable that enough capacity for around 60 days will be
secured.
Coal unloader (continuous): 800t/h x 2 units
Receiving conveyor: 800t/h x 2 lines
Stacker and reclaimer: 800t/h x units
Issuing conveyor: 800t/h x 2 lines
(e) Ash treating equipment
Ash that is melted in the coal combustion will fall into the hopper and will be collected underneath
the boiler furnace. This ash is known as clinker. Generally speaking, around 5~15 percent of the
entire ash quantity will be captured. The clinker ash that is discharged from the bottom of the
boiler will be carried by truck to the ash dump. Meanwhile, the combustion ash that is captured by
the electric dust collector will be collected in the hopper underneath the dust collector. This
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―35
combustion ash is known as fly ash. Roughly 80~90 percent of the total ash volume will be
collected here. After the fly ash is carried to the silo by compressed air, it will be carried to the ash
dump by truck. The capacity of the ash dump will be enough to hold the ash generated over the
service life of the power plant. The combustion ash from the coal-fired thermal plant and gypsum
generated in the desulfurization equipment has the potential to be used as mineral resources, and
approximately 50 percent of coal ash in Japan is utilized in the cement field.
Furnace bottom ash equipment: 1 unit
Ash collection equipment: 1 unit
Fly ash storage and issue equipment: 1 unit
(f) Water intake equipment
The water intake equipment will be composed of water intake pipes, intake equipment, screen
equipment and water circulation equipment. Two circulating pumps with 50 percent capacity each
will be installed.
(g) Wastewater treatment equipment
The wastewaters that are generated on both a routine basis and non-routine basis in coal-fired
thermal power will undergo physical and chemical treatment to ensure that they satisfy
wastewater standards. Wastewater from coal-fired thermal power includes the following.
Living wastewater from hand washing and toilets, etc.
Wastewater from coal handling equipment such as unloading, transporting and storage
equipment
Wastewater from ash treating equipment generated in handling of clinker and ash from
the electric dust collector
Wastewater from the smoke exhaust plant comprising air preheater, electric dust collector
and desulfurization equipment
Power plant waste water from the boilers, turbines and condensing system
(h) Desulfurization equipment
The desulfurization equipment will be installed downstream of the electric dust collector. The
wet limestone–gypsum method is widely used throughout the world. The desulfurization
equipment will be composed of four processes, namely the limestone supply process, which
supplies the limestone (an alkaline absorption agent), the absorption process for removing
SO2 from exhaust gases, the gypsum recovery process for recovering the byproduct gypsum,
Appendix
Study for Updating Syrian Electricity Sector in Syrian Arab Republic (Draft Final Report)
B―36
and the ventilation process which introduces exhaust gas and reheats the gas. The SO2 in the
exhaust gas will react with the limestone and will be oxidized by oxygen in the air, thereby
producing gypsum. The system will be designed in combination with related equipment such
as electric dust collector to ensure that the dust concentration of exhaust gas is within the
designated standard and the gypsum concentration is 95 percent or higher based on data such
as the coal characteristics and limestone concentration and so on.
Oxidation air compressor: 50 percent x 3 units
Service water pump and associated equipment: 100 percent x 2 units
Mist eliminator: 1 set
Limestone slurry system: 1 set
Dewatering equipment and vacuum filter system: 1 set
(i) Limestone and gypsum equipment
Following unloading, limestone will be carried to the limestone storage yard by belt conveyor.
From the storage yard, the limestone will be carried by bulldozer to the plant limestone
storage silo. Assuming that the S content of limestone is 1 percent, the required amount of
limestone will be approximately 250 tons per day, and it will be necessary to design the
limestone and gypsum equipment in consideration of this point.
Limestone unloader: 1 unit
Limestone receiving conveyor: 1 unit
Limestone storage silo: 1 unit
Gypsum issuing equipment: 1 unit