+ All Categories
Home > Documents > Application of a Level 2 PSA to Advanced Gas-cooled...

Application of a Level 2 PSA to Advanced Gas-cooled...

Date post: 07-Apr-2019
Category:
Upload: dothien
View: 213 times
Download: 0 times
Share this document with a friend
47
Application of a Level 2 PSA to Advanced Gas-cooled Reactors: A Hunterston B Power Station pilot study Dr Charles Shepherd & Andrew Butcher
Transcript

Application of a Level 2 PSA to

Advanced Gas-cooled Reactors:

A Hunterston B Power Station pilot

study

Dr Charles Shepherd & Andrew Butcher

2

Background

March 2011 - Fukushima Daiichi Nuclear disaster

following earthquake and tsunami.

September 2011 - Dr Weightman report on the

implications for the UK nuclear reactors.

– Specifically Recommendation FR4 related to

PSAs

September 2013 – To support EDF Energy’s

response to FR4, CRA develops the UK’s first

Level 2 PSA for an Advance Gas-cooled Reactor.

Introduction

This presentation with be in two parts:

The methodology developed by CRA to

produce the UK’s first Level 2 PSA for an

AGR.

The application of this methodology to the

development of a pilot Level 2 PSA for

Hunterston B Power Station.

3

Development of the Level 2 PSA

Methodology for the AGRs

Dr Charles Shepherd, BSc (Hons), MSc, Phd

Chief Consultant, CRA

5

Level 2 PSA

methodology

LEVEL 2 PSA

Input from Level 1 PSA

1. Plant Familiarisation

2. Grouping into Plant Damage States

3. Accident Sequence Modelling/ Event Trees

Output to Level 3 PSA

4. Containment/ PCPV Performance Analysis

5. Grouping into Release Categories

6. Source Term Analysis

7. Quantification of the Analysis

8. Uncertainty Analysis and Sensitivity Studies

9. Use of the Results of the Level 2 PSA

10. Documentation of the Analysis

An

aly

sis

to s

up

port

Lev

el 2

PS

A

6

Aims of the Level 2 PSA for the AGRs

• To gain insights into how severe accidents progress, the operator

actions that could be carried out to mitigate the consequences and the

physical events that could occur

• To identify the accident sequences that make a significant

contribution to a large release of radioactive material to the

environment

• To identify plant specific vulnerabilities

• To determine whether there are sufficient provisions to manage

severe accidents

• To investigate the effectiveness of the Severe Accident Guidelines

(SAGs) and suggest improvements

7

PWR severe accidents

Core melt, relocation in vessel

H2 / steam explosion in reactor pressure vessel

Vessel failure/ high pressure melt ejection

H2 / steam explosion in containment

Molten core-concrete interaction

Operation of safety systems

• Containment isolation, H2 igniters/ re-combiners,

containment coolers/ sprays, filtered containment vent

• Molten core catcher/ cooling system

Challenges to barriers to release

• Reactor pressure vessel

• Containment building

8

AGR severe accidents

Prompt criticality

• Positive moderator coefficient/ recriticality at

about 1150oC with all control rods in

• Failure of core support structures/ reactivity

addition if control rods remain suspended

Steam explosion

• Following boiler tube leakage where there is

water in basement of pressure vessel

Molten core-concrete interaction

Challenges to PCPV

• Failure of penetrations

• Gross failure under pressure

9

Plant Damage States - PWR

PDSs form the interface between Level 1 PSA and Level 2 PSA

• Level 1 PSA identifies accident sequences that would lead to core damage

• Starting point/ boundary conditions for progression of severe accident

PDSs defined in terms of attributes

• Type of initiating event (intact circuit, LOCA, containment bypass)

• Primary system pressure at time of core damage (high, low)

• Status of the safety systems (SG feed, emergency core cooling) and support

systems (electrical power, cooling water)

• Status of containment systems (isolation, fan coolers, spray, H2 systems)

• Integrity of the containment (intact, failed, bypassed)

Used to define full set of PDSs; grouped/ condensed into set used in

analysis

10

Plant Damage States - AGR

Level 1 PSA identifies accident sequences that would lead to a Dose

Band 5 (DB5) release

PDSs defined in terms of attributes

• Type of initiating event (intact circuit, depressurisation fault, boiler tube leakage)

• Operation of reactor trip/ shutdown/ hold-down systems

• Operation of boiler feed systems for post trip cooling

• Availability of equipment (gas circulators, pressure vessel cooling, boiler

depressurisation)

Used to define full set of PDSs; grouped/ condensed into set used in

analysis

• 10 PSA attributes identified; 60 PDSs defined by attributes; grouped/ 15 APETs

produced

11

Containment Event Trees - PWR

Nodes presented in time sequence

• Core melt before vessel failure; at vessel failure; shortly after vessel failure;

longer term; very long term

Number of nodes

• Needs to be sufficient to model all mitigating actions/ physical events

• Small CETs with 20 to 30 nodes; Large CETs with >30 nodes

Operator actions to mitigate severe accident

• RPV depressurised in timeframe x

• Containment filtered vent operated in timeframe y

Occurrence of physical events

• Does a steam explosion in timeframe z (in-vessel or ex-vessel)

12

Differences between analysis for PWR and AGR

Endpoints of Level 1 PSA different

• PWR – core damage

• AGR – sequence would lead to a DB5 release

– Need to take account of other possibilities to restore post trip cooling

– Equipment stored off-site that can be brought in following the declaration of a

site incident; includes pumps and power supplies

Barriers to the release of radioactive material for a severe accident

• PWRs have two barriers and protection for these barriers

– Reactor pressure vessel: primary circuit depressurisation; flooding vessel cavity

to prevent vessel failure/ in-vessel retention

– Containment: fan coolers; sprays; H2 control; filtered containment vent

• AGRs have one barrier – concrete pressure vessel

– Protection depends on core cooling and primary circuit depressurisation

13

Accident Progression Event Trees – AGR (1)

Possible operator actions identified from SAGs

• {Plant integrity management} close gas domes to protect boilers

• {Restore PTC using on-site equipment} by identification/ recovery of operator

errors

• {Restore operation of the pressure vessel cooling water system} to protect the

penetrations

• {Depressurisation of primary circuit} to protect the pre-stressed concrete

pressure vessel

• {Water injection into the primary circuit and steam venting} to provide core

cooling and protect boiler supports

Operator actions that are not possible

• Feed and bleed cooling using CO2 or N2 – heat removal rate not high enough

• All methods of inserting negative reactivity

14

Accident Progression Event Trees – AGR (2)

Physical events identified from SAGs/ BDB analysis

• <Stuck open SRV> opened due to accident sequence being modelled

• <Prompt criticality>

• <Failure of core support structures>

• <Steam explosion>

• <Molten core-concrete interaction> which would occur in the long term

following core relocation to basement of PCPV

• <Failure of the PCPV> where the possible outcomes are PCPV intact, pre-

existing depressurisation fault, penetration failure, gross failure

Physical events not included

• Combustible gas explosion inside or outside the PCPV

• Graphite fire

15

Accident Progression Event Trees – AGR (3)

APETs presented in two parts

APET1 Timeframe 1 – from start of accident sequence to irrecoverable loss of core

cooling

Operator actions: restoration of core cooling

Physical events: failure of boiler supports/ boiler penetration failure

APET2 Timeframe 2 – from irrecoverable loss of core cooling to substantial core

relocation

Timeframe 3 – long term after core relocation

Operator actions: none

Physical events: prompt criticality (T2), steam explosion (T2), molten core-

concrete interaction (T3), failure of pressure vessel (T2/T3)

16

Release Categories/ Source Term Analysis - PWR

Endpoints of the CETs grouped into Release Categories (RCs)

Aim is to define the quantity of radioactive material and the

characteristics of the release for each of the RCs

Attributes used to define the RCs

• Time at which the release starts; retention of radioactive material

• Mode and time of failure of the RPV/ containment

• Operation of the active mitigating systems/ passive mitigating systems

• Duration of the release; release rate; location of the release; energy content (for

Level 3 PSA)

Full set of RCs condensed into the set used for the analysis

Source term analysis carried out for one or more bounding/

representative sequence in each RC

Source Term Analysis done using one of the integral codes – MAAP,

MELCOR, ASTEC

17

Source Term/ Release Categories - AGR

Endpoints of the APETs grouped into Release Categories (RCs)

Attributes used to define the RCs

• Accident sequence type: failure to shutdown, total loss of all core cooling

• PCPV failure mode: intact, pre-existing breach, penetration failure, gross failure

• Energetic event: prompt criticality, steam explosion inside PCPV

• Molten core-concrete interaction

Attributes define 32 RCs; grouped into 5 RC Groups • PCPV intact

• PCPV failed/ no energetic events/ no MCCI

• PCPV failed/ energetic event occurs/ no MCCI

• PCPV failed/ no energetic events/ MCCI occurs

• PCPV failed/ energetic event occurs/ MCCI occurs

RC attributes/ RCs/ RC Groups defined using judgement

No Source Term Analysis has been carried out for the severe accident

sequences identified by the APETs

18

Analysis to support the Level 2 PSA - PWRs

Integral codes available - MAAP, MELCOR, ASTEC

Able to model all aspects of the severe accident behaviour in an

integrated analysis

• Thermal-hydraulic response of the reactor, heat-up of the core

• Fuel damage/ melting/ relocation

• Containment loadings/ response

• Release of radioactive material from the fuel, transport through reactor coolant

system/ containment, release to the environment

19

Analysis to support the Level 2 PSA - AGRs

No integral codes

Limited analysis for the accident sequences identified in the APETs

Depends on existing analysis for severe/ Beyond Design Basis accidents

Expert Judgements made in many areas:

• Steam explosion is possible after a boiler tube leakage fault and is “likely” to cause

gross failure of the PCPV

• Probability of core slump before moderator temperature heats and causes prompt

criticality is 0.5

• Prompt criticality would lead to a rapid release of energy and gross failure of the

PCPV

20

Expert judgement - PWR

Formal structured process used for NUREG-1150

Used for issues where uncertainties large, no widely accepted models,

risk significant including:

• Probability of temperature-induced reactor coolant hot leg failure and SGTR

• Magnitude of in-vessel hydrogen generation

• Mode of temperature-induced reactor vessel bottom head failure

• Containment pressure increase at reactor vessel breach;

Steps in the process:

• Selection of issues; selection of experts; training

• Presentation of material; review/ analysis by experts

• Elicitation of expert’s conclusions; derivation of probability distributions;

documentation

Current practice is to use an expert judgement process

21

Expert judgement - AGR

Used extensively due to large uncertainties in severe accident

phenomena/ possibilities for mitigating consequences

Expert judgement fora include:

• AGR PSA Level 2 Extension Expert Judgement Panel

• EDF/CRA Level 2 PSA Workshops

• CRA internal model development meetings

Issues addressed by EDF Expert Panel include:

• Beyond design basis initiating events and internal/ external hazards

• Recovery of pressure vessel cooling system

• Feasibility of accident mitigating actions included in Severe Accident Guidelines

• Water injection into the reactor following irrecoverable loss of core cooling

Judgements documented with reasoning in minutes of meetings/

analysis reports

Development of a pilot Level 2 PSA for

Hunterston B Power Station

Andrew Butcher, BSc, MSc, CPhys

Consultant, CRA

Level 1 PSA Overview

Design Basis Faults >1E-7 per reactor year.

Beyond Design Basis Faults <1E-7 per

reactor year.

Current HNB Level 1 PSA only models

Design Basis Faults.

A number of new Beyond Design Basis

Level 1 ETs have been created so that

these faults can be included in the Level 2

PSA.

23

Level 1 PSA Event Tree Fundamentals

Fault Schedule => Bounding Fault Schedule.

Level 1 PSA model has an Event Tree per

Bounding Fault.

24

Example of fault schedule??

Forced Gas Circulation

(FGC) Based PTC

Natural Circulation

(NC) Based PTC

BF01.0 1.1 1.87E+00 2 2.09E+00

1.2 3.39E-02

1.3 1.50E-01

3.3(a)(i) 1.40E-03

5.1(a)(i) 1.00E-04

5.1(b)(i) 2.00E-02

6.4 2.00E-02

10.8.1 1.74E-03

2011 PSA

Update

Bounding

Fault

Frequency

Bounding

Fault

Bounding

Fault Title

Criteria for Successful

Reactor Trip and

Shutdown used for

the PSA

2011 PSA

Update

Estimated

Error

Factor

Fault Freq.

(pry)

(see App

C&E, Table 1)

Faults

Bounded

Criteria for Successful Post Trip Cooling (PTC) used for

the PSA Availability and Configuration of

Post-trip Cooling Systems

Modelled in the Event Tree

All quadrants available for PTC.

FGC provided by RSSE/ operator

initiated ‘No.2’ GCs.

FGC provided by operator

initiated ‘No.1’ GCs.

Boiler feed provided by the HP

feed system or LP feed system,

or BUCS.

Operator action to reduce HP

and LP feed flow to 2 quadrants

at 1 hour has also been credited

in order to conserve feed stocks.

The Station Fire Tender Pump

manually connected to the BUCS

pumphouse is available to be

commissioned within recovery

timescales.

Spurious

trip.

Not applicable - for

faults bounded by this

bounding fault the

main guardlines have

already been tripped

following the

initiating event.

With PVCW available:

RSSE/operator

establishes FGC by at

least one gas circulator

(GC) with the IGVs

correctly set, in a

quadrant supplied with

HP or emergency LP feed

within 60 minutes of

reactor trip (RT) to

prevent the lifting of the

lowest set CPV SRV.

With PVCW available:

NC of CO2 gas in at least 1

quadrant fed by HP, LP feed

or BUCS within 90 minutes

of RT to prevent the lifting

of the lowest set CPV SRV.

NC of CO2 gas in at least 1

quadrant fed by the Station

Fire Tender Pump within 8

hours of RT with the lowest

set CPV SRV reseating

following successful l ift.

CPV SRV reseat failure

requires manual isolation

within 90 minutes to

maintain successful NC

PTC.

Bounding Fault 01.1 Spurious Trip

Fautls

25

Integrating the Level 1 and 2 PSAs

The Level 1 PSA simply assigns a Doseband

5 (DB5) consequence to the end of the

accident sequences (assumed releases > 1

Sievert), without making any distinction of the

size of this DB5 release.

The Level 2 PSA examines how these

releases could come about to understand the

nature and magnitude of these releases.

26

First step is to assign a Plant Damage State

(PDS) to each DB5 sequence.

The PDSs are the input to the Level 2 PSA

APETs and form the boundary between the

Level 1 and 2 PSAs.

27

Linking the Level 1 – Level 2 PSAs (1)

28

Linking the Level 1 – Level 2 PSAs (1)

Scale of the PSAs

APET1 a

APET1 b

APET1 c

APET1 g

APET1 h

29

~200 BF ETs ~15 APET1s ~10 APET2s

BF01.0

BF02.0

BF02.1

BF03.0

….

….

BF45.0

BF46.0

APET2 a

APET2 b

APET2 d

APET1s – Recovery APETs

APET1s consider the recovery actions that

may be claimed to limit the accident

progression.

Operator recovery actions are fundamental

for this stage of the accident progression.

Existing plant systems are claimed along

with off-site back up emergency equipment.

30

Level 2 APET1 – Example 1

APET1 (IN).(C)

– All Intact Circuit Faults, e.g. Spurious trip,

electrical faults, feed faults, etc.

– Trip & Shutdown Successful

– Total loss of Post Trip Cooling

– Pressure Vessel Cooling Water Available

31

Level 2 APET1 – Example 1

The focus of APET1 (IN).(C) is to:

Blowdown the reactor and prevent failure of

the Pressure Vessel.

And

Re-establish core cooling to control core

temperatures and prevent fuel/clad melt or

failure of the core support structures.

32

Level 2 APET1 - Example 2

APET1 (DVSB).(C)

– Depressurisation Fault

– Trip & Shutdown Successful

– Post Trip Cooling Failure

– Very Small Breach

34

Level 2 APET1 - Example 2

The focus of APET1 (DVSB).(C) is to:

Seal the breach and contain any radioactive

release from the primary circuit.

And

Re-establish core cooling to control core

temperatures and prevent fuel/clad melt or

failure of the core support structures.

35

APET (DSVB).(C)

36

APET1 Sequence Consequences

The end-points of the APET1 sequences have been

assigned new consequences.

Where the severe accident has been:

– mitigated by successful recovery actions, the

sequence is assigned DB1 to DB4;

– limited by some successful recovery actions, the

sequence is assigned ‘FML’ or Fuel Melt Limited.

These sequences are terminated at this point;

Where the severe accident has resulted in an

irrecoverable loss of core cooling, the accident

progression is continued in the APET2s.

37

38

Linking the APET1s and APET2s

APET2s – Physical APETs

APET2s consider the physical phenomena that

may occur in the core.

No operator recovery actions are considered

effective at this stage of the accident progression.

Split fractions are assigned to the sequence

branch points to provide a judgement, in the

absence of any other information, on how likely the

phenomena will be to occur.

E.g. Highly Likely (0.99), Likely (0.75), Medium

(0.5), Unlikely (0.25) etc.

39

APET2 Example 1

APET2 (I-A-D)

– Pressure Vessel Intact

– Reactor at Atmospheric Pressure (Depressurised)

– Total Loss of Core Cooling

– No In-Vessel Water (Dry)

40

APET2 Example 1

APET2 (I-P-W)

– Pressure Vessel Intact

– Reactor Pressurised

– Total Loss of Core Cooling

– In-Vessel Water (applicable for Boiler Tube

Leakage faults)

42

Release Categories

Each sequence end-point in the APET2s has been

assigned a Release Category consequence.

A total of 32 Release Categories have been

identified.

The 5 Release Category Groups will be used to

assess the likelihood, for these severe accidents, of:

– PCPV intact

– PCPV failed/ no energetic events/ no MCCI

– PCPV failed/ energetic event occurs/ no MCCI

– PCPV failed/ no energetic events/ MCCI occurs

– PCPV failed/ energetic event occurs/ MCCI occurs

44

Insights from the HNB Level 2 PSA

Provides an understanding of how severe accidents

progress.

Identifies the important recovery actions, the physical

events and potential vulnerabilities.

Provides an input to the future development of:

– The Symptom Based Emergency Response

Guidelines (SBERGs), and;

– The Severe Accident Guidelines (SAGs).

Identifies areas where there is a high level of uncertainty

and a lack of knowledge about how severe accidents

would progress.

45

Conclusions

CRA has produced the UK’s first Level 2 PSA

for an AGR.

Supporting EDF Energy in responding to the

UK Regulator’s FR4 recommendation.

46

47

OUR MISSION:

To be the premier risk management consultancy

of the 21st century and beyond.


Recommended