Application of the IAEA INPRO method to
EU-DEMO Plant Concept Selection
R. Brown
First IAEA Technical Meeting (TM) on the Safety, Design and Technology of Fusion Power Plants
4th May 2016
Content
• Programme Background
• EU-DEMO Development Strategy Update
• Definition of Alternative Plant Concepts
• IAEA INPRO Assessment Methodology
• Implementation for EU-DEMO
• Contributions from Industry
• Conclusions
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 2
Emphasis on: • Central role of ITER: assumption in original Roadmap ITER comes in operation in early 2020’s
• Concept design of a DEMOnstration Fusion Power Plant to follow ITER, capable of generating
several 100MW of net electricity and operating with a closed fuel-cycle
• DEMO as a single step to commercial fusion power plants
• Electricity production demonstration around middle of the century
• An ambitious roadmap implemented by a Consortium of Fusion Labs (EUROfusion)
• Support to facilities based on the joint exploitation.
• Focus around 8 Missions
DEMO
IPH
IPH
1. Plasma Operation
2. Heat Exhaust
3. Neutron resistant Materials
4. Tritium-self sufficiency
5. Safety
6. Integrated DEMO Design
7. Competitive Cost of Electricity
8. Stellarator
Background
EU Fusion Roadmap to Fusion Electricity
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 3
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 4
PPPT PMU
L. ZANI (CEA) WPMAG
L. BOCCACCINI (KIT) WPBB
J. H. YOU (IPP Ga) WPDIV
A. LOVING (CCFE) WPRM
W. BIEL (FZJ) WPDC
M. GRATTAROLA (Ansaldo) WPBOP
C. DAY (KIT) WPTFV
M. Q. TRAN (EFPL) WPHCD
M. RIETH (KIT) WPMAT
A.IBARRA (CIEMAT) WPENS
N. TAYLOR (CCFE) WPSAE
Project control/ coordination
System & Design Integration
Physics Integration
G. FEDERICI WPPMI
Background
EU-DEMO Programme Organisation
EU DEMO Development Strategy Update
A proposed re-examination and re-working of the EU-DEMO Design
Implementation Strategy has been triggered by the following:
• Anticipated ITER delay: In light of the anticipated delays to ITER, DEMO
PPPT PMU has explored possible adaptations of the development strategy
in order to minimise the impacts of the ITER delay on the EUROFusion
2050 Mission to realise Fusion electricity.
• A recommendation from EU-DEMO Stakeholders to investigate &
assess alternative plant concepts: Engagements with Stakeholders have
highlighted the need to investigate the attractiveness of alternative plant
concepts to: • Substantiate that the eventual plant concept represents an optimised decision.
• Provide mitigation to known shortcomings/technical risk in the baseline concept design.
• Ensure that the concept selection is aligned to stakeholder requirements.
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 5
Management of Design Variants
DEMO Design Option 2
DEMO Design Option 3
DEMO Design Option 4
DEMO Design Option 5
Pre-Conceptual Design Conceptual Design Engineering Design
DEMO Design Option 2 DEMO Design
Option 2DEMO Design Option 4
DEMO Design Option 1
2020 2027En
gin
ee
rin
g P
rogr
amm
eR
ese
arch
Pro
gram
me
Focus: Answer critical questions
Critical questions
Focus: De-risk concept
Baseline
Key risks
RisksSolutions /
Opportunities
Solutions / Opportunities
Focus: Mitigate key risks
Solutions / Opportunities
Architecture selected
2024-2025
Management of Design Variants in Programme Phases:
• The programme will maintain a ‘Baseline’ design to keep the design effort focused.
• Design variants must be managed through the design phases, with the number of variants generally
being reduced as the programme matures.
• Concept down-selection should be managed through a traceable decision making framework
(Decision Analysis).
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 6
Example Candidate Plant Concepts
DEMO Candidate Plant Concepts earmarked for investigation and assessment:
• DEMO1-SN: Single Null (SN) configuration based heavily on extrapolations from ITER
design/technology (more detailed systems and integration studies to continue e.g Aspect Ratio,
No. Coils, RM etc.). Assessment of Water and He as options for primary coolant.
• DEMO1-DN: A Double Null (DN) diminishes the problems of the plasma position detection and
active control, and de-risks the design of the first wall. Remote Maintenance solution not yet
established.
• DEMO1 with an extended pulse (e.g., > 4 hrs): Maintains similar physics and technology
assumptions to baseline, but with pulse length extended by a factor of 2 to 4 in an inductive
device. Impact on Central Solenoid and BoP design to be assessed.
• DEMO2: Steady State operation with optimistic (but realistic) physics & technology assumptions.
e.g. 1.5 MeV NB technology, >90% radiation fraction.
• DEMO3: Steady State operation with advanced physics & technology assumptions. eg. ODS
Eurofer, HTS, advance divertor configuration.
These must be defined by a common set of artefacts to a level to allow meaningful
comparison and assessment.
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 7
Alternative Concepts Definition & Assessment Process
Concept & Motivations
Plant definition
• Cardinal plant/physics parameters
• Operational concept
• Plant architecture
Systems definitions
• System parameters
• System architecture
• System technology assumptions
Synthesis
Informed Decision Making
Plant Assessment Framework
Concept Definition
PROCESS runs
Plant Param. Outputs
CAD & Geometry
Iterate to check motivations are valid
and refine parameters
Evaluation
• Technical Performance
• Safety, Environment & waste Management
• Economics
• Technical Risk
• Schedule & Deployment
Impact Assessments
• Safety analyses
• Plasma Physics aspects
• Maintenance
• TBR analysis
• CS impact
• First Wall/Divertor Loads
• Technology Readiness
• etc…
Technical Impact Assessment Assess impact relative to baseline design on engineering & physics aspects including:
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 8
Define criteria upfront to guide analysis and development
Decision Analysis Process
• The assessment of the plant concept are difficult because they include numerous
stakeholders, multiple competing objectives, substantial uncertainty, and
significant consequences.
• Down-selection of Plant and System Concepts is a necessary feature of the EU-
DEMO programme. It must be handled with an objective, robust, traceable
processes.
• Decisions Analysis Process; “…to provide a structured, analytical framework
for objectively identifying, characterizing and evaluating a set of alternatives for a
decision at any point in the life cycle and select the most beneficial course of
action.”(ISO/IEC/IEEE 15288)
• The methodology for making decisions must have the capacity for accepting and
quantifying human subjective inputs;
• Cumulative wisdom provided by experienced personnel is essentional for
integrating technical & non-technical factor to produce sound decisions.
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 9
IAEA INPRO Methodology
• The process of DEMO plant concept selection should as closely as possible follow
established concept selection processes from Nuclear Fission and other highly
regulated fields.
• IAEA International Project on Innovative Nuclear Reactors and Fuel Cycles (INPRO)
was established in 2000.
• INPRO Methodology for nuclear energy system assessment – a comprehensive set
of internationally agreed basic principles, requirements and criteria in important areas
of: Economics, safety, waste management, proliferation resistance, physical
protection, environment and infrastructure.
Image Credit - IAEA
• How can these approach be applied and if
necessary adapted to Fusion?
• Are there other approaches that DEMO should
consider?
• How to define and assess appropriate criteria?
• How to compare a variety of criteria in a single
‘value’ space?
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 10
INPRO Methodology Overview
Basic Principlesa
User Requirementsb
Key Indicators
Criteriac
aCorresponds to the term Goal in Generation IV Interational Forum (GIF)
bCorresponds to the term Criterion in GIF
cCorresponds to the term Metrics in GIF
• Statement of a general goal that is to be achieved.
• Basic Principle (BP) is achieved through meeting the related User
Requirements
• User Requirements (UR) define the means of achieving the goal
set out in the basic principles.
• URs are the conditions that should me met to achieve Stakeholder
Acceptance.
• Criterion (CR) enable the assessment to asses how well a
given UR is being met.
• It consists of an Indicator (IN) and Acceptance Limit (AL)
Key Indicators (KI) are a subset of CRs that are the focus of
evaluation and assessment.
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 11
The DEMO Context & Implementation
Fission/INPRO Context:
• INPRO methodology as applied in the assessment of Fission INS, addresses a primary
objective to ensure that Fission INS development follows a sustainablea path generically
applicable to multiple programmes.
• INPRO methodology is a generic tool that has been developed to assist Member States in their
assessment of INS options to fulfil their objectives – taking into account their regional
constraints.
• Fission INS represent (relative to Fusion) evolutions of existing technologies/plant designs for
which there is already a strong technical and commercial precedent.
DEMO Programme Context
• DEMO is a demonstration project – not a fully fledge deployable commercial reactor solution.
• The DEMO programme has defined timescales and goals, as defined by the Fusion Roadmap
and is therefore constrained programmatically.
• Fusion Technology Readiness and Integrated Plant Design are substantially less mature
compared to Fission INS.
• Focus during pre-concept on screening and comparison between DEMO concepts.
aSustainable as defined in INPRO manual, is considered along the dimensions of: economic, environmental, social and institutional factors
• There are parallels between Fission/INPRO methodology as applied to the assessment of the
sustainability of Innovative Nuclear Systems (INS) and the assessment of DEMO plant concepts.
• There are also distinctions that necessitate tailoring of the method for application to DEMO architecture
evaluation:
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 12
Exploring application of INPRO to DEMO
1. Establish a standard process for definition of plant concepts that generates
the artefacts required for objective evaluation of concepts.
2. Define Basic Principles and User Requirements in a value hierarchy: • Review of INPRO URs for applicability.
• Incorporate the DEMO Stakeholder Requirements.
3. Define Key Indicators that are:
• Measurable
• Discriminatory
• Applicable
4. Rank User Requirements in terms of priorities with DEMO stakeholders.
5. Complete KI scoring assessments, integrating:
• Expert judgement from subject matter experts.
• Measured values (models and simulations).
6. Synthesis and analysis of results.
During an early design phase
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 13
Definition of Basic Principles for DEMO
Basic Principle
Themes
Criteria
Applicability
for DEMO
Comments on suitability for DEMO Plant Concept selection
Safety Strong alignment with DEMO safety principles – but could be
made more specific for Fusion.
Economics Must be adapted to reflect that EU-DEMO is a demonstration
device.
Environment Must be adapted to reflect fusion environment & waste
management issues. Waste Management
Proliferation
Resistance
Proliferation risks for fusion are considered to be significantly
reduced for Fusion.
Physical Protection Physical protection strategies not well defined at pre-concept
stage.
Infrastructure Operational concept has high impact on infrastructure
compatibility.
Plant Performance DEMO must demonstrate all the relevant technology for a power
plant.
Deployment
Timescales
EU Fusion Roadmap has defined timescales - this must be
accounted for in concept selection.
Programmatic Risk DEMO integrates many unproven technological elements into a
single device. High programmatic risk must be accounted for.
Overview of INPRO BP themes and initial indicative assessment of applicability to DEMO plant concept evaluation.
IAE
A IN
PR
O B
asic
Prin
cip
les
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 14
Which Safety User Requirements can be meaningfully assessed at an early design
stage to enable differentiation between concepts?
• Robustness (Margins & Simplicity of Design)
• Safety Basis (experience and precedent of technology)
• Minimisation of hazards
• Design Basis Accidents (frequency of occurrence)
• Minimisation of dose risk to workers & public
• Prevention of releases into the environment
• Independence of DID
• Detection & Interception
• Human machine interfaces
Early stage
Later stage
DE
MO
Co
nce
pt
Eva
lua
tio
n S
pe
cific
Risk-Informed Decision Analysis
• The decision analysis should not only focus on technical or performance
assessment.
• With DEMO whilst more technically advanced concepts might offer improved
performance, the technology developed and associated technical/cost/schedule risk
may increased substantially.
• There must be integration of decision analysis with risk analysis, to ensure that
programmatic constraints are also taken account in decisions.
Programme Delivery Risk
(technical, schedule, cost)
Technology Readiness
DEMO-C1
DEMO-C2
DEMO-C3
Technology and Physics Performance
Fig 2: Representation of the relationship between technology readiness and programme delivery risks
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 15
Demonstrate the Technical Feasibility of Fusion Power in accordance with the
Fusion Roadmap
Technical Performance
Maximise plant availability
Demonstrate net electricity production
Demonstrate close tritium fuel
cycle
Safety, Environment &
Waste Management
Minimise risk to the public &
workers
Minimise radiological
waste
Minimise inherent safety
risk
Minimise radiological
releases
Economics
Development Cost
Facilities Cost
Operations Cost
Decomm. Cost
Deployment timescale
Development schedule
Operations schedule
Programmatic Risk
Tech. Dev. Risk
Cost Risk.
Schedule Risk.
Establishing & value hierarchy
Inputs:
• DEMO Stakeholder Requirements Document
• Fusion Roadmap
• INPRO internationally agreed basic principles
Basic Principles organised in a value hierarchy for EU-DEMO: Risk Informed
Decision
Making
The implementation of the method will likely require an evolution of this hierarchy!
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 16
User Requirement Definition
Expanding Technical performance as an example -
immediately it becomes difficult to decompose the
value hierarchy into User Requirements without
overlap.
DEMO Mission
Technical performance
Maximise availability
Plant operational lifetime
Planned
availability
Maintenance times of key components
Inherent reliability
Demonstrate closed tritium cycle
Provide tritium breeding over operational life
Provide T to start another device
Demonstrate net electricity production
Net electricity production
Predictability of supply
Basic
Principles
User Req.
How to agree on the level of decomposition?
• Each User Requirement must be of intrinsic interest to
stakeholders/relevant to INPRO .
• Each user requirement should be interpretable by
stakeholders.
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 17
Example criteria definition
Plant performance basic principle BP1 (): The DEMO plant shall demonstrate a closed tritium fuel cycle
User Requirements (UR) Criteria
Indicators (IN) Acceptance Limits (AL)
The DEMO FPP shall breed
sufficient tritium to; (i)
Guarantee its planned
operational life; (ii) Provide
adequate back-up storage in
case of unforeseen losses"
CR 1.5.1: Tritium start-up requirement
IN 1.5.1: Quantity of tritium required for plant
start-up. AL 1.5.1: TBD
CR 1.5.2: Plant tritium breeding ratio
IN 1.5.2: Plant tritium breeding ratio AL1.5.2: 1.1
CR 1.5.3 Maintain Tritium breeding ratio over blanket life
IN 1.5.3: Degradation in tritium breeding
performance over FPY AL 1.5.3: TBD
CR 1.5.4 Minimise foreseen Tritium loses from the fuel inventory
IN 1.5.4 Rate of tritium loss from the fuel cycle AL 1.5.4: TBD
CR 1.5.5: Provide adequate back-up in case of unforeseen loses
IN 1.5.5: Time to accumulate backup AL 1.5.4: TBD
To be reviewed with subject matter experts in 2016.
Considering the UR: ‘The DEMO plant shall demonstrate a closed tritium fuel cycle’ as an example
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 18
Key Indicators and Desirable Target Values
No Potential Potential
Acceptance
Limit Desired
Target Value
Key Indicator-1
Key Indicator-2
DEMO-C1
DEMO-C2
A Desired Target Value (DTV)
• Defined for each KI, the DTV represents the ultimate value of a KI that could practically be achieved
through R&D.
• The DTV represents a stretch target for a KI that is judged to be eventually or ultimately achievable by
appropriate R&D.
Range of uncertainty
Acceptance Limit (AL)
• The acceptance limit represent the minimum value for stakeholder or technical acceptance.
• As there is high uncertainty in an early stage assessment, failing to meet the acceptance limit would
not result in default exclusion, but this KI must be closely monitored and tracked.
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 19
Acceptance Limits and Desired Target Values
Representation of Acceptance Limits and Desired Target Values for Key Indicators
0102030405060708090
100
KI-1
KI-2
KI-3
KI-4
KI-5
KI-6
KI-7
KI-8
Acceptancce Limit
Desired Target Value
Key Indicator representation for a single Basic Principle
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 20
Acceptance Limits and Desired Target Values
Representation of DEMO Concept Evaluations mapped against Acceptance Limits and Desired Target Values for Key
Indicators
0102030405060708090
100
KI-1
KI-2
KI-3
KI-4
KI-5
KI-6
KI-7
KI-8
DEMO-C2
DEMO-C1
Acceptancce Limit
Desired Target Value
Key Indicator representation for a single Basic Principle
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 21
Synthesis of multiple KI maps
Safety, Environment &
Waste Management
Technical
Performance
Economic Factors
Technical Risk
Deployment Timescale
Synthesis into an
overall ranking
• In order to obtain an overall ranking, all KI maps must be synthesised through a process of establishing
Stakeholder priorities.
• Not an exact science – important to maintain traceability and visibility in the process.
• Analytical Hierarchy Process can be applied to structure this process.
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 22
Mapping KIs to Relative Benefit Index
KI value
A suitable function defined that
maps the perceived ‘benefit’ to
the physical design space.
RBI = 100
RBI = 0
Acceptance
Limit Desired Target
Value
RBI Design Space
Va
lue
Sp
ace
Concept of Relative Benefit Index (RBI) maps the KI value to the ‘benefit’ as perceived by
stakeholders or subject matter experts.
The relative importance of each KI can be compared through assigning weighting factors
(wi) to each RBI – based on importance assessed be stakeholders.
This allows the evaluation and trade-off between multiple criteria in a single ‘value space’
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 23
DEMO-C2
DEMO-C1
x2 x1
RBI1
RBI2
KI to RBI value function
1.5.2 KI
RBI = 100
RBI = 0
Acceptance
Limit
1.20
1.5.2 RBI Design Space
Valu
e S
pace
No Solution Suboptimal Design
Space
1.10
Desired Target
Value
1.25
“Unacceptance”
Limit
RBI_DN = 20
RBI_DN = 90
DEMO-DN
DEMO-SN
1.12 1.19
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 24
Example of a possible value function for tritium breeding ratio (indicative numbers):
CR 1.5.2: Plant tritium breeding ratio
IN 1.5.2: Plant tritium breeding ratio AL1.5.2: 1.1 DTV 1.5.2 1.2
TBR estimate taken from: G. Federeci et al. “Overview of the design approach and prioritization of R&D activities towards an EU DEMO”, 2015
Not to scale
Concept KI1.5.2 RBI1.5.2
DEMO-SN 1.19 90
DEMO-DN 1.12 20
KI Synthesis - Analytical Hierarchy Process
DEMO
PLANT
OPTIONS
Technical
Performance
Safety,
Environment &
Waste Mang.
Economic
Factors
Technical
Risk
Deployment
Timescales
TBR
Availability
Pass. V stab.
Waste
…
1 RBIn
Decomposition of the decision process
into the decision criteria and sub-criteria
clusters
Comparative Judgements
of all criteria and alternative
combination in the cluster
Ranking and
comparison of
global
performance
Synthesis of the weighted KI to
overall alternative ranking
Technical
Performance
Safety,
Environment &
Waste Mang.
Economic
Factors
Technical
Risk
Deployment
Timescales
• Pairwise Comparisons: Stakeholders asked to judge each KI with respect to all other criteria to
obtain measure of relative importance.
• KIs are aggregated to obtain overall ranking of alternatives.
• Consistency of assessments is assessed.
N/A
FW margin
R0
Differential sub-criteria
Availability
×
× ×
× ×
×
×
×
0.9
RBIn
RBIn
RBIn
RBIn
RBIn
RBIn
RBIn
0.3
0.2
0.5
w
0.8
1
0.2
→ →
→ →
→ →
→
→ +
+
+
+
TBR
Availability
Pass. V stab.
Waste
…
N/A
FW margin
R0
Availability
RBIn
RBIn
RBIn
RBIn
RBIn
RBIn
RBIn
RBIn
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 25
Industry Technology Maturity Assessments
Industry Task
Technology Option
• Technology description
• System performance parameters
Industry Contribution
• Industry can contribute through developing schedule & cost estimates – but
assessment scope and inputs must be well defined.
• TRL assessments are a useful starting point – but should be developed into
quantitative estimates.
• NASA has developed non-linear mapping functions between the TRL level and cost
and schedule uncertainty through historical analysis of project records that might
support this activity1.
TRL
Assessments
Cost: Development Cost Estimates
Schedule: Development Schedule
Estimates
Technical Risk: Technology Development
Risks
1NASA Cost Estimating Handbook Version 4.0
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 26
Mapping KI improvement to Time, Cost & Risk
KI Value AL DTV
Co
st
AL DTV
Tim
es
ca
le
KI Value
AL DTV
Te
ch
nic
al R
isk
KI Value
Industry Task Objectives
The industry task aims to map KI improvement to relative cost,
timescale and development risk:
• Relative Cost – Normalised to baseline cost.
• Relative Timescale – Normalised to baseline schedule.
• Relative Risk – Comparative Risk assessments
considering TRL.
Since the same design points are assessed (derived from
DEMO concepts), the time, cost and risk estimates can be
mapped to the associated RBI for each KI.
Design Points Design Points
Design Points
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 27
RBI vs. Cost, Time, Risk
• An aggregate RBIagg can be obtained for by combing the RBIs for each KI with the weighting factor wi
obtained from AHP.
• Similarly aggregate values for Cost, Schedule and Risk could be obtained and plotted against RBIagg
to obtain maps for Cost, Time and Risk vs. Benefit.
• Sensitivity analysis can be performed to understand how the design strategy may need to respond to
changes in external factors (stakeholder preferences) and uncertainties in assumptions.
RB
I ag
g
DEMO-C1 DEMO-C2
DEMO-C3
RCIagg
RB
I ag
g
DEMO-C1
DEMO-C2
DEMO-C3
RTIagg
RB
I ag
g
DEMO-C1
DEMO-C2
DEMO-C3
RRIagg
Benefit vs. Cost Benefit vs. Time Benefit vs. Risk
RCI/RBI <1 RTI/RBI <1 RRI/RBI <1
RCI/RBI >1 RTI/RBI >1 RRI/RBI >1
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 28
Plan for Implementation
2016 – Framework & Concept Definition
- Define value hierarchy
- Define plant concepts
- Review INPRO criteria
- Establish Key Indicators
- Launch industry task
- Establish mechanics of the framework
2017 – Concept Technical Assessment
- Refine plant concepts
- Perform technical & safety assessments
- Review Key Indicators
- Launch Industry TRL assessments
- Initial scoring assessments
2018 – Concept Evaluation
- Industry cost & schedule estimates
- Plant concept assessment
- Synthesis and evaluation of results
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 29
Summary
• Presented is a first proposal for a concept evaluation framework for EU-
DEMO.
• Our aspiration is to ensure that we have a robust and traceable concept
evaluation framework that assesses designs against a diverse range of
requirements & objectives.
• A full INPRO assessment is unlikely to be feasible or warranted at this
stage, but a lighter INPRO based screening approach is more realistic.
• INPRO criteria to be reviewed with experts for applicability to EU-DEMO
concept evaluation.
• Program aspects (time, cost & risk) must be considered in the evaluation.
• We welcome suggestions and look forward to your input.
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 30
Appendix Slides
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 31
Criteria Definition
Safety
Minimise inherent safety risk
Robustness of design (margins)
Robustness of design (simplicity)
Design basis accident severity
Triggering event frequency
Can a sub-set of safety related criteria for early stage
assessment be derived that are:
(a) Measurable
(b) Discriminatory
(c) Representative
Coolant inventories
Operating pressure
Operating temperature
Resultant pressurisation (in-vessel LOCA)
Resultant pressurisation (ex- vessel LOCA)
Plasma disturbance frequency
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 32
Parameter uncertainties
Continuous distributions from expert judgements
• In case where expert elicitation is relied upon, it is more informative to obtain ranges
rather than single discrete values.
• Three point estimation technique is a convenient technique for obtaining continuous
distributions if probability distribution is assumed to approximate a normal distribution.
• best-case estimate (5th percentile) = = xi,5th • best judgement (median) = xi,50 • worst-case estimate (95th percentile) = xi,95th
Expert Elicitation
Continuous distributions from quantitative models
• Monte Carlo analysis can be applied to obtain continuous distributions from
quantitative models.
• Continuous distributions shall provide a clearer picture of the levels of uncertainty
associated with parameter estimates. This is particularly important when values are
near to acceptance limits.
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 33
DEMO Stakeholder requirements
• Engagements with a group of EU-DEMO stakeholders have taken place in
2015 and 2016.
• This group includes experts from Industry, the grid, EC and ITER/F4E.
• One of the objectives of the engagement is to capture a set of high level
requirements for the project, referred to as the Stakeholder Requirements.
• DEMO PMU has captured these requirements in the Stakeholder
Requirements Document.
• Stakeholder requirements captured in aspects of: • Plant Performance
• Safety, Environment & Waste Management
• Economic Aspects
• Project Risk
The current SHRD should not be assumed to be complete and exhaustive –
and a thorough review of the INPRO assessment criteria may yield other
relevant requirements.
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 34
Dealing with risk & uncertainties
“Uncertainties do need to be considered when performing comparative assessments, in setting RD&D
goals, and in deciding whether or not to initiate or continue a development program” IAEA INPRO
Risk – the chance of an unfavourable event occurring. A risk is characterised by a probability of
an event occurring.
Uncertainty – indefiniteness about an estimate or assumption. Uncertainty is characterised by a
probability distribution and represents our fundamental inability to perfectly predict the outcome of a
future event.
• The Technical Risk term applied here, is taken to mean the risk
that a major objective or requirement can not be met due to the
uncertainty that we have in future performance of technology or
physics that is not yet realised.
• Initially, it is proposed to assessed the Technical Risk through
assessment of the Technology Readiness Levels and Systems
Readiness Levels or of the main constituent systems or physics
assumptions.
• This can be refined to more specific estimates as the method
matures.
Technical Risk & TRL
R. Brown | IAEA Technical Meeting | Vienna | 04/05/2016 | Page 35