+ All Categories
Home > Documents > Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Date post: 02-Jan-2017
Category:
Upload: phungthuan
View: 219 times
Download: 0 times
Share this document with a friend
27
Arsenic Removal from Groundwater using a PRB of BOF Slag at the DuPont East Chicago (IN) Site John Wilkens, Stephen H. Shoemaker, William B. Bazela; DuPont Company Alan P. Egler, Rajiv Sinha; URS Diamond Jeff G. Bain, University of Waterloo RTDF PRB Action Team Meeting Niagara Falls, October 16, 2003
Transcript
Page 1: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Arsenic Removal from Groundwater using a PRB of BOF Slag at the DuPont East Chicago (IN) Site

John Wilkens, Stephen H. Shoemaker, William B. Bazela; DuPont Company

Alan P. Egler, Rajiv Sinha; URS Diamond

Jeff G. Bain, University of Waterloo

RTDF PRB Action Team Meeting Niagara Falls, October 16, 2003

Page 2: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Overview

Site Background

Laboratory Scouting

Field Demonstration

PRB Installation

Post-Installation Monitoring & Joint Research

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 2

Page 3: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

East Chicago Site Site History • DuPont purchased from Grasselli Corp. in 1928

– Diversified chemical manufacturing facility

– 440 acres, some undeveloped

• DuPont sold plant in 2000 IL IN

Chicago

East Chicago

– Retained land & environmental responsibility

PRB Driving Force • Achieve “YES” status for EI-750 metric as a GPRA baseline facility

– Demonstrate adequate groundwater migration control

PRB Development • Program initiated in late 1990s

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 3

Page 4: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Arsenic in Groundwater - EC North Side0.15

Ars

enic

Con

cent

ratio

n, p

pm

Below Detection Limit of 0.01ppm

EC MW-22 March 1997

Arsenic Groundwater Profile General Shape DMLS Sampler

0.1

0.05

0

0 5 10 15 20 25 30 Depth, ft.

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 4

Page 5: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Ars

enic

Con

cent

ratio

n, p

pm

PRB for Arsenic Removal: Material Scouting

4

Scouting

3

Iron Oxide - D Iron Oxide - A Iron Oxide - BIron Oxide - C Treated Steel SlagIron & Oxides Iron Filings Feed 3 ppmFeed 1 ppm Steel SlagIron Slag

ag Iron Filings

Representative By-Product Materials

Batch Scouting Tests

IneffectiveIneffective

Steel Slag FurtherFurther StudyStudy

• Focus: iron by-products

• EC water 2 – As spiked

• Batch tests 1 – screening

• Kinetic runs

0 • Best materials reduced As

0 0.05 0.1 0.15 to < 10 ppb Weight Ratio, Material / Water

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 5

Page 6: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Field Demonstration

Best materials from lab chosen • Zero-valent iron (Peerless) -- 5 wt. % in pure silica sand

• Basic Oxygen Furnace (BOF) slag -- 30 and 100 wt. %

• Iron oxide -- 5 and 20 wt. %

• Control -- pure silica sand

Laboratory Experiments -- limitations

• Arsenic content

• Dissolved oxygen

• Redox potential

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 6

Page 7: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Reactive Test Wells

Field Demonstration -- Reactive Test Wells • Potential for high data quality, technical certainty

• Actual groundwater chemistry

• Simulate “real-time” PRB

• No contaminant losses

• Ease of operation -- passive

• Long-term monitoring

Application • Installed in high-arsenic area of potential PRB

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 7

Page 8: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Reactive Test Wells at EC

GROUND LEVEL

REACTIVE COLUMN 12-IN. DIAM.

SLOTTED WELL PIPE

SAMPLING

GROUND-WATER

IN-GROUND TEST COLUMNS• Columns filled with reactive

material mixtures • Passive flow of groundwater

through columns • 12-in diameter, 35 feet deep,

keyed into clay • Two, One-inch sampling wells

– Two-foot slotted sections

SAMPLING • Low-flow • Bi-level: shallow, deep

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 8

Page 9: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Reactive Test Wells -- Installation Rotasonic drilling

Centralized sampling

pipe

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 9

Page 10: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

RTW Results: Arsenic Concentrations @ 7 Months

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 10

Material Sand -- Control 42 % 1000 %

Iron - 5% ND = 3,100 %

Iron by-product - 5% * 30 = 3000 %

Iron by-product - 20% 400 & 1,100 = BOF Slag - 30% ND = ND = BOF Slag - 100% ~ND = ~ND =

Arsenic concentrations in ppb MDL = 5 ppb; PQL = 10 ppb

Arrows indicate trends since 4-month sampling * sampling terminated at 4-months

Shallow Deep

Page 11: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

BOF Slag

Slag source:Bethlehem Steel, Burns Harbor, INvia The Levy Company, Portage, IN

Component Wt. Pct. Fe forms Σ

Fe0 (est) FeO (est) Fe2O3 (est)

27 3

21 3

CaO 41 SiO2 12 MgO 9 MnO 5 Al2O3 5 P2 O5 1 TiO2 0.5 K2O 0.05 Zn forms 0.02

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 11

Page 12: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

PRB Specifications Performance • Treat 1-3 ppm arsenic to below 10 ppb

• 20 year life

Material • 100% Basic Oxygen Furnace (BOF) slag

– Bethlehem Steel, provided by The Levy Company

Dimensions • 2000 ft. long

• 30 in. wide minimum

• 37+/- ft. deep

• Begin below waste/ash at 5-ft. below ground surface Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 12

Page 13: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

PRB InstallationSite Challenges • Sandy material restricts open, unsupported trench • PRB to be located beneath waste layer • Relatively high groundwater table

Bioslurry -- not feasible • High pH of BOF slag reduces guar gum bioslurry viscosity • Enzyme breaker less effective at high pH • Overall: significant uncertainty

Trenching -- chosen option • Simple, no additional chemicals • Trenching through homogenous sands, devoid of obstructions • 25 ft depth limitation overcome by phased construction Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 13

Page 14: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

PRB Layout North Wall

Two parallel PRBs • 2000 ft. long • ~ 15 ft. centers separation • To ~ 37 ft. depth

South Wall

N

South wall • Upper & lower sections

Groundwater Flow

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 14

Page 15: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

PRB Cross SectionSouth NorthWall Wall

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 15

Silty Clay Sand

Natural Sand

Existing Waste Ash

Key 2-ft. min. depth

BOF Slag 19-ft. min. depth

BOF Slag 18-ft. min. depth 22-24-in. wide (both walls)

BOF Slag 10-ft. min.depth 44-46-in. wide

Clean natural sand backfill

Groundwater

~ 15 ft.

Page 16: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Dewatering

1,000,000 gallons/day

• Stabilized flowing sands • Enabled trenching

• Avoided “lake”

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 16

Page 17: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Benching

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 17

Shallow: Deep:

105,000 cubic yards excavated

Enable 25-ft. trencher to reach 40-ft. depth • Benching • Phased construction

5 ft. bgs 18-20 ft. bgs

Page 18: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Trencher

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 18

Custom trencher • DeWind Environmental • 25-ft. working depth

Page 19: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Trenching

Continuous trenching • Ongoing refill

BOF Slag Installed • 26,500 cubic yards • 43,000 tons

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 19

Page 20: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Trenchbox to “Top” South Wall

Trenchbox • Add section to top of wall • 10 ft. deep x 44-46-in. wide

Procedure efficient • Fill bench to base of ash • Dig new trench for box

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 20

Page 21: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

And at Completion...

Restored site

Completion • Three month

process • One week early

SAFETY prevailed:5,000 safe contractor work hours

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 21

Page 22: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Post-Installation Monitoring

Collaboration with Waterloo University • Prof. David Blowes

– Jeff Bain, graduate student

– David Smyth

• Joint monitoring and analysis

– Monitoring by both groups

– Cores by Waterloo

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 22

Page 23: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago SitePage 23

Monitoring Wells & Cores

DuPont - ExistingDuPont - NewWaterloo

Wells & Cores

C

PRBNGroundwater

Flow

CC

C

CC

C

Page 24: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Path Forward

Monitoring • Performance measurement

Analysis • Performance assessment

• Geochemical and reactive transport modeling

• Mechanism elucidation

• Recommendations

Program • Monitoring in progress

• First public report spring 2004

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 24

Page 25: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 25

At the End of the Rainbow… a PRB

Double rainbow over East Chicago, IN following PRB field test - September 2001

Page 26: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...
Page 27: Arsenic Removal from Groundwater using a PRB of BOF Slag at the ...

AbstractA DuPont site in East Chicago, Indiana is the first full-scale application of basic oxygen furnace (BOF) slag to remove arsenic from groundwater. To remediate a 1 to 2 mg/L arsenic plume, a 2000-ft. long by 35-ft. deep permeable reactive barrier (PRB) was installed in 2002.

Development began with laboratory scouting of materials for a PRB using site groundwater. Performance under actual site conditions was considered critical because of the difficulties in simulating site groundwater conditions in the laboratory, particularly such parameters as arsenic content, redox potential and dissolved oxygen. To test the best materials under actual site conditions, several reactive test wells (RTW) were installed. The RTWs incorporated proposed PRB materials as packing in 12-inch diameter, uncased wells with internal sampling points. Data were collected regularly over a nine-month period, and significant differences in material performance were observed.

Based on the RTW results and hydrological modeling, a full-scale PRB was installed, 2000-feet long and 35-ft. deep, consisting of 100% BOF slag. To achieve the desired wall thickness, the PRB comprised two parallel, two-foot-wide trenches plus a unique two-level design. The hydrogeologic conditions at the site include a 35-ft. deep fine sand aquifer overlying thick clay aquitard, with groundwater velocity in the sand of 0.25 ft. per day. The installation was particularly challenging due to flowing sands and the presence of a high water table. Deep benching and extensive dewatering allowed a trenching machine to install the PRB in two passes followed by trench-box installation of an upper level of reactive material.

DuPont and the University of Waterloo are collaborating on field monitoring and analysis of the PRB performance. Eight multilevel bundle piezometers were installed, crossing the two PRB sections along the centerline. Measurements indicate that the hydraulic conductivity of the PRB material is higher than that of the surrounding materials, favoring groundwater flow through the PRB.

Arsenic Removal using PRB of BOF Slag at DuPont East Chicago Site Page 27


Recommended