Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street. Public Informational Meeting July 22, 2014. Introductions. Doug Helt , P.E. City of Tulsa Transportation Lead Brooke Caviness, P.E. City of Tulsa Senior Engineer / Project Manager Tim Morgan, P.E. - PowerPoint PPT Presentation
Popular Tags:
18
Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street Public Informational Meeting July 22, 2014
Transcript
Page 1: Arterial Street Rehabilitation for Riverside Drive 24 th  Street to 35 th  Street

Arterial Street Rehabilitation for Riverside Drive24th Street to 35th Street

Public Informational MeetingJuly 22, 2014

Page 2: Arterial Street Rehabilitation for Riverside Drive 24 th  Street to 35 th  Street

Introductions

• Doug Helt, P.E. City of TulsaTransportation Lead

• Brooke Caviness, P.E.City of TulsaSenior Engineer / Project Manager

• Tim Morgan, P.E.HNTB CorporationProject Manager

Page 3: Arterial Street Rehabilitation for Riverside Drive 24 th  Street to 35 th  Street

Project Location Map

Page 4: Arterial Street Rehabilitation for Riverside Drive 24 th  Street to 35 th  Street

Overview

• Roadway Improvements

• Stormwater Improvements

• Water Main Improvements

• Sanitary Sewer Improvements

• Anticipated Project Schedule

• Questions

Page 5: Arterial Street Rehabilitation for Riverside Drive 24 th  Street to 35 th  Street

Roadway Improvements

Roadway Geometry Improved = Safer Drive

Page 6: Arterial Street Rehabilitation for Riverside Drive 24 th  Street to 35 th  Street

Roadway Improvements

• 35 mph Speed Limit

• Median Separation Through Park

• Lane Widths Increased

• New Lighting (LED)

Page 7: Arterial Street Rehabilitation for Riverside Drive 24 th  Street to 35 th  Street

Roadway Improvements

Page 8: Arterial Street Rehabilitation for Riverside Drive 24 th  Street to 35 th  Street

Stormwater Improvements

• Travis Park RCB System

• Swan Creek RCB System

• Crow Creek Bridge Replaced

• Riverside Drive Storm System Upgraded

Page 9: Arterial Street Rehabilitation for Riverside Drive 24 th  Street to 35 th  Street

Stormwater Improvements

Pre-Project Storm Conveyance System

Page 10: Arterial Street Rehabilitation for Riverside Drive 24 th  Street to 35 th  Street

Stormwater Improvements

Post-Project Storm Conveyance System

Page 11: Arterial Street Rehabilitation for Riverside Drive 24 th  Street to 35 th  Street

Water Main Improvements

• Riverside Drive 12” Water Main

• Gathering Place 8” Water Main

• Creating Looped Water Main Systems

• Improved Function and Flow in Neighborhoods

Page 12: Arterial Street Rehabilitation for Riverside Drive 24 th  Street to 35 th  Street

Water Main Improvements

Pre Project Water Main Network

Page 13: Arterial Street Rehabilitation for Riverside Drive 24 th  Street to 35 th  Street

Water Main Improvements

Post Project Water Main Network

Page 14: Arterial Street Rehabilitation for Riverside Drive 24 th  Street to 35 th  Street

Sanitary Sewer Improvements

• Existing Systems are 60-100 years old

• Reconstruction of Major Sanitary Mains

• High Strength Fiberglass for New Systems

• No Impact to Users

Page 15: Arterial Street Rehabilitation for Riverside Drive 24 th  Street to 35 th  Street

Sanitary Sewer Improvements

Pre-Project Sanitary Sewer Network

Page 16: Arterial Street Rehabilitation for Riverside Drive 24 th  Street to 35 th  Street

Sanitary Sewer Improvements

Sanitary Sewer Replacements

Page 17: Arterial Street Rehabilitation for Riverside Drive 24 th  Street to 35 th  Street

Anticipated Project Schedule

• Fall 2014 - Construction Contract Award

• Winter 2014/2015 - Construction Begins

• Spring 2015 - Riverside Drive Closure

• 2016 - Riverside Drive Pavement Construction

• 2017 - Project Completed

Page 18: Arterial Street Rehabilitation for Riverside Drive 24 th  Street to 35 th  Street

Questions?