+ All Categories
Home > Documents > ASD HART Mini Pre-Engineered Pipe Design Guide

ASD HART Mini Pre-Engineered Pipe Design Guide

Date post: 18-Nov-2014
Category:
Upload: xingnong1
View: 186 times
Download: 3 times
Share this document with a friend
19
Hart Mini Pipe Design Guide Hart Mini Pre-Engineered Pipe Design Guide Manual No: TM0086 It is important to select suitable pipework for the environment requiring protection. This must be designed and installed specifically for each site condition to meet the performance specification that is required. Kidde Fire Protection recommends and supplies Red ABS SnifferPipe and fittings. Other pipe types may also be used dependant upon the type of application being monitored.
Transcript
Page 1: ASD HART Mini Pre-Engineered Pipe Design Guide

Hart Mini Pipe Design Guide

Hart MiniPre-Engineered

Pipe DesignGuide

Manual No: TM0086

It is important to select suitable pipework for the environment requiring protection.This must be designed and installed specifically for each site condition to meet theperformance specification that is required.

Kidde Fire Protection recommends and supplies Red ABS SnifferPipe and fittings.Other pipe types may also be used dependant upon the type of application beingmonitored.

Page 2: ASD HART Mini Pre-Engineered Pipe Design Guide

Hart Mini Pipe Design GuideTABLE OF CONTENTS

Para Page

1 Aspirating Pipework Design1.1 Pipework Layout1.1.1 Response Time1.1.2 Ventilation of the Area1.2 Air Sampling Systems1.2.1 Duct Sampling1.2.2 Installation of a duct sampling pipe system1.2.3 Air Handling Unit Sampling1.2.4 Installation of Air Handling Unit (AHU) Sampling Pipework1.2.5 Distributed Air Sampling1.2.6 Closed Ended (Balanced) Distributed Pipework Systems1.2.7 Hole Sensitivity Of Balanced Systems1.2.8 Pipework Junctions1.2.9 Remote Sample Points

2 Special Design Considerations2.1 Elutriator2.2 Stratification2.3 Pressure Differentials

3 System Examples3.1 System Design D3.2 System Design I

4 Installation4.1 Pipe Warning Label4.2 Sample Point Labels4.3 Mini Sample Point Label

Appendices

A 1 Hole Size Drill Guide (BS6266)A 2 Hole Size Drill Guide (BS5839)

LIST OF ILLUSTRATIONS

FIGURE TITLE Page1-1 Single Pipe System 2-11-2 Two Pipe System 2-21-3 Four Pipe System 2-21-4 Duct Sampling 2-41-5 Duct Sampling Installation 2-51-6 Air Handling Unit Sampling 2-61-7 AHU Installation 2-71-8 AHU Typical Installation 2-81-9 Distributed Air Sampling 2-91-10 Remote sample points 2-112-1 Elutriator 3-12-2 Stratification 3-23-1 System Design D 5-13-2 System Design I 5-23-3 Alternative System Design I 5-34-1 Sampling Pipe Support 6-1

Page 3: ASD HART Mini Pre-Engineered Pipe Design Guide

Hart Mini Pipe Design Guide

Issue 1 Page 6-1

1. ASPIRATING PIPEWORK DESIGN

HART Mini has been designed to provide many years of service with minimalmaintenance. However, an HSSD system is only effective if the sampling pipework has been designed and installed correctly.

1.1 PIPEWORK LAYOUT

The sampling pipe network is the most crucial aspect of the design of an HSSDsystem and there are two important factors to consider: -

• Response time• Ventilation of the area.

1.1.1 Response Time

The response time of the detector is the means by which the overall HSSD system isassessed. It is affected by the environmental conditions and the design of the pipenetwork.

The response time is separated into two parts - the time allowed for the smoke toreach the sampling point and the transport time, which is the maximum time forsmoke to be carried from the furthest sampling point to the detector. For systemsdesigned to BFPSA code of practice for design, commissioning, installation &maintenance of HSSD systems, the transport time should be within 120 seconds.The maximum transport time can be directly affected by the installed pipe design(see figures 1-1, 1-2 and 1-3). The 4 pipe branch design will provide the shortesttransport time (fig 1-3).

Figure 1-1 Single Pipe

DetectionUnit

SamplePipe

DetectionUnit

SamplePipe

Page 4: ASD HART Mini Pre-Engineered Pipe Design Guide

Hart Mini Pipe Design Guide

Issue 1 Page 6-2

Figure 1-2 Two-Pipe System

Figure 1-3 Four Pipe System

Note: Should the transport time be greater than 120 seconds, an acceptable timeshould be agreed with the client prior to commissioning.

1.1.2 Ventilation of the Area

The ventilation of the protected area affects the time it takes for smoke to reach thesample points. In applications without ventilation detection can be carried out atceiling level using the Secondary Detection principle, ie the air sampling points aresited and spaced to satisfy BS5839 part 1 or BS6266 requirements.

In areas with forced ventilation, air handling units (AHUs) or some other form of airextraction system, smoke may be prevented from reaching ceiling level samplepoints. In this instance it is recommended that Primary Detection be used, ie thepipework and air sampling points are mounted directly in the airflow. This type ofsystem is usually regarded as supplementary to other forms of detection due to itslimited response capability once the air movement ceases.

1.2 AIR SAMPLING SYSTEMS

There are three basic types of sampling system design:

1. Duct Sampling (Primary Detection).2. Air handling unit sampling (Primary Detection).3. Distributed air sampling (Secondary Detection).

1.2.1 Duct Sampling

Within this type of application there are a number of issues to be considered indesigning the HSSD system. These being:

• Pressure equalisation• Maintenance accessibility (eg flexible joints to allow the pipe to be removed)• Monitoring upstream or downstream of filters

Duct detection is considered as primary detection. However, the area should also bemonitored by secondary detection to provide protection in the event of the ductairflow shutting down. Monitoring is achieved by installing sample pipe within the

DetectionUnit

SamplePipe

Page 5: ASD HART Mini Pre-Engineered Pipe Design Guide

Hart Mini Pipe Design Guide

Issue 1 Page 6-3

duct. To maintain the pressure balance, the exhaust air is returned to the ductdownstream of the monitoring sample pipe.

The use of a union socket is recommended to allow easy access for commissioningand maintenance purposes. Typically, as ducts have different pressures, it isrecommended that only a single HART Mini is used to monitor a single duct.

Where possible the sampling pipe should be installed in the centre of the airflow andaway from bends. It should also be installed close to inspection hatches formaintenance purposes. Due to the use of high efficiency particle filters within HVACsystems, it is recommended that monitoring be carried out before the filter as it mayremove smoke particles.

Fig. 1-4 Duct Sampling

1.2.2 Installation of a duct sampling pipe system

1. The sampling pipe must be inserted approximately half of the height into theduct and should be supported and sealed. It should penetrate at least 80% ofthe width of the duct.

2. In order to be able to maintain and test the HART Mini, the sample pipeshould span the width of the duct, protrude the opposite side and be closed-off using a removable end cap.

3. The sample points should be positioned at an angel of 45O off centre in theairflow. There should be one sample point for each 0.4m2 of the duct’s crosssectional area.

DetectionUnit

SamplingPipe

ReturnAir Pipe

Airflow

Page 6: ASD HART Mini Pre-Engineered Pipe Design Guide

Hart Mini Pipe Design Guide

Issue 1 Page 6-4

4. Exhaust air from the HART Mini should be returned to the duct by fitting theoutlet adaptor, which is supplied as standard with the detector.

5. The return holes into the duct should face downstream and be inserted atleast 1 metre downstream of the sampling pipe and be positioned at 1/3height of the duct.

Fig 1-5 shows the set-up required for duct sampling.

Fig. 1-5 Duct Sampling Installation

UnionSocket

End Cap

GrommetSeal

SamplePipe

ReturnPipe

Direction ofAirflow

Direction ofAirflow

Sample Hole

Page 7: ASD HART Mini Pre-Engineered Pipe Design Guide

Hart Mini Pipe Design Guide

Issue 1 Page 6-5

1.2.3 Air Handling Unit Sampling

For applications that include AHUs, a number of issues to be considered in designingthe HSSD system. These are;

• High Airflow• Lack of smoke energy• Resultant low smoke temperature• Dilution caused by airflow velocities• Addition of clean air by ventilation systems

Sampling the air inlets of AHUs is a highly effective way of detecting small levels ofsmoke quickly. Fig 1-6 shows an example.

When monitoring AHUs:

1. Ensure that external air velocities are less than 6 metres per second toprevent venturi effects occurring at the sampling holes.

2. Sample only over the air inlets, as many AHU's have HEPA filters which willremove smoke particles.

3. A maximum of 2 AHU's (dependent upon air movement and size) can becovered by one HART Mini.

Fig. 1-6 Air Handling Unit Sampling

DetectionUnit

SamplingPipe

Page 8: ASD HART Mini Pre-Engineered Pipe Design Guide

Hart Mini Pipe Design Guide

Issue 1 Page 6-6

1.2.4 Installation of Air Handling Unit (AHU) sampling pipework.

When the pipework is to be installed to monitor an AHU:

1. The sampling pipe should be fitted across the middle of the air grille.

2. There should be one sample point for each 0.4m2 of the grille’s area.

3. The sample points should be positioned in the airflow at an angel of 45O offcentre.

4. A union socket should be used to allow easy access for maintenance.

Fig. 1-7 AHU Installation

Page 9: ASD HART Mini Pre-Engineered Pipe Design Guide

Hart Mini Pipe Design Guide

Issue 1 Page 6-7

Fig. 1-8 AHU Typical Installation

1.2.5 Distributed Air Sampling

A distributed sampling system consists of a pipe network throughout the area - seefig 1-9. This is typically combined with AHU sampling to provide extra cover in theevent of failure in the AHU by providing secondary detection. In small areas a singledetector is capable of providing both primary and secondary detection.

Ceiling and floor void monitoring should also be considered. The system should bedesigned so that the sample point spacing meets the design requirements ofBS5839 part 1 or BS6266 or any other local requirements, depending upon theapplication.

Fig. 1-9 Distributed Air Sampling

Detection

SamplingPipe

False Floor

Union

Page 10: ASD HART Mini Pre-Engineered Pipe Design Guide

Hart Mini Pipe Design Guide

Issue 1 Page 6-8

1.2.6 Balanced (Closed Ended) Distributed Pipe Work Systems

A balanced system is one in which the sampling points are sized such that they allprovide the same airflow. The sampling pipe network may be configured to matchenvironmental conditions, holes may be spaced at critical intervals and at unevenspacing. This will provide maximum protection at risk locations. If necessary differentpipe diameters may be combined to decrease transport time and so increase theresponse of the system. All pipe segments should be capped. Typically the lastsampling point will be within 150mm from the end cap.

The pipe designs provided in the appendices have been pre-engineered to producea balanced system.

1.2.7 Hole Sensitivity of Balanced System

In a balanced system design the sensitivity at each sample point hole is the same.The effective sensitivity can be determined by multiplying the sensitivity of thedetector by the number of sampling holes in the system.

Example: - The Relative sensitivity of a sample point with a detector headsensitivity setting of 0.1%/m, which is connected to a sampling pipenetwork using 40 sampling points can be calculated as follows:

0.1%/m x 40 = 4% relative sensitivity per hole

1.2.8 Pipework Junctions

HART Mini has an air inlet for a single pipe connection. For systems requiring morethan one branch to the pipework the network can incorporate Tee pieces and bends. The pre-engineered systems in the appendices have been designed specificallyusing a maximum of 2 branches. If more than two branches are needed, pleasecontact Kidde Fire Protection.

1.2.9 Remote Sample Points

If the area being protected has ceiling voids or false ceilings, run the main pipenetwork within the voids out of sight. To do this, drop a small length of pipe throughthe ceiling into the protected area with the sampling hole drilled in the end cap orsampling point. These are known as extended sampling points and varyingdiameters of pipe can be used, e.g. from 10mm capillary to 25mm OD pipe.

The type of extension would depend upon application requirements. Figure 1-10shows typical examples.

Page 11: ASD HART Mini Pre-Engineered Pipe Design Guide

Hart Mini Pipe Design Guide

Issue 1 Page 6-9

Fig 1-10 Remote sample points

2. SPECIAL DESIGN CONSIDERATIONS

2.1 ELUTRIATOR

The HART Mini has been specifically designed to operate in most environments fromclean rooms to underground railway stations. However, in areas where the detectormay be subjected to large particles such as dust or fibres or to atomised liquids orsteam, a build up of contamination can occur in the detector or false alarms mayoccur.

The Elutriator is an optional item and can be used if the protected area is expectedto have heavy amounts of non-combustion particulate. An Elutriator should beinstalled to prevent build-up of material within the Detector. The Elutriator is aninertial particle separator that allows air to flow freely through it while separating outlarge particulate by allowing them to accumulate on an impact plate. It has anoptional foam insert that can be fitted in place of the impact plate and screens forapplications where if the detector is likely to be exposed to any atomised liquids orsteam.

The airflow travels into the Elutriator and hits the impactor momentarily slowing theairflow. This slowing of the airflow causes the larger, heavier particles to drop outallowing the smaller, lighter smoke particles to travel through the slots to thedetector.

FlushSample Point

Mini SamplePoint

End CappedSample Point

Page 12: ASD HART Mini Pre-Engineered Pipe Design Guide

Hart Mini Pipe Design Guide

Issue 1 Page 6-10

Fig 2-1 Elutriator (union adaptors omitted for clarity)

The main benefit of the Elutriator is to allow the HART Mini to operate within areaswhere background contamination may be a problem. It should be checked andcleaned regularly to ensure correct operation.

2.2 STRATIFICATION

Stratification is an important issue, which needs to be considered when designing thepipework layout. It occurs were there are differing temperature gradients within aprotected area and it is commonly associated with high ceiling rooms, atria orwarehouses - particularly where above ground heating or sky lighting are installed.

The air temperature within the area increases with height and this can create athermal barrier preventing the smoke rising up to the sampling point. Aspiratingsystems can compensate for this by sampling at various levels within the room. Thisis done by dropping vertical sample pipes, having sample points spaced at 3 metres,see figure 2-2.

Consideration needs to be given to the practical installation of vertical pipework.Ideally sample pipe should be within the racking. Care needs to be taken to ensurethe pipework is not obstructed or damaged. Alternatively, horizontal pipes can be runat different heights within the racking.

Page 13: ASD HART Mini Pre-Engineered Pipe Design Guide

Hart Mini Pipe Design Guide

Issue 1 Page 6-11

Fig 2-2 Stratification

2.3 PRESSURE DIFFERENTIALS

It is important when installing a HART Mini to take the pressure within the protectedarea into consideration particularly where the unit is installed outside of the area ofprotection or where more than one area is covered by one detector.

The HART Mini unit should always be installed in an area where the pressure is thesame or negative with respect to the protected area. Where the unit is located in apositive air pressure relative to the protected area, the detector should be exhaustedback into the protected area.

3. SYSTEM EXAMPLES

This manual has covered the design information and applications for the HART MiniHSSD system. This chapter details examples of typical system designs. Theexamples used here are taken from the pre-engineered designs shown in appendixA.

3.1 System Design ‘D’

System D is a typical standard sampling pipe network used in ceilings and roof andfloor void applications. The example design has been configured using a single pipedesign with three sampling points.

Page 14: ASD HART Mini Pre-Engineered Pipe Design Guide

Hart Mini Pipe Design Guide

Issue 1 Page 6-12

Fig 3-1 System Design D

SamplePoint

Location

SamplePoint size

1 6mm2 7mm3 7mm

NOTE

• For ceiling, roof and floor void sampling, the sample holes need to be positionedfacing down.

• All sampling pipe and sample points should be identified using an appropriatelabel such as provided in Kidde Fire Protection’s SnifferPipe range.

3.2 System Design ‘I’

System I is based on a double pipe design complete with 3 sampling holes on eachsample pipe run covering an area of 150m².

Sampling Pipe

Sample Point Location

DetectionUnit

2.5M

1

2

3

5M

5M

2.5M

5M

Page 15: ASD HART Mini Pre-Engineered Pipe Design Guide

Hart Mini Pipe Design Guide

Issue 1 Page 6-13

Fig 3-2 System Design I

SamplePoint

Location

SamplePoint size

1 6mm2 7mm3 7mm

NOTE

• For ceiling, roof and floor void sampling, sampling holes need to be positionedfacing down.

• All sampling pipe and sample points should be identified using an appropriatelabel such as provided in Kidde Fire Protection’s SnifferPipe range.

Alternatively a two pipe system design, such as System I, can be used to cover aroom and a floor void, as shown below.

Sampling Pipe

1 2 3

2.5M

5M 5M 2.5M

DetectionUnit

2.5

5M

2.5

Sample Point Location

Page 16: ASD HART Mini Pre-Engineered Pipe Design Guide

Hart Mini Pipe Design Guide

Issue 1 Page 6-14

Fig 3-3 Alternative System Design I

4. INSTALLATION

The sampling pipe network is an arrangement of pipes within the protected areathrough which air is drawn back to the HART Mini to be sampled. Piping may bemetallic or non-metallic. The designs provided within this design guide are based onusing 25mm pipe such as Kidde Fire Protection’s red ABS SnifferPipe, fittings andaccessories. Pipe and fittings in 32mm ABS are also available.

It is important to ensure that all joints are airtight and cemented to prevent anyleakage, as this would affect system performance. Joint integrity is greatly reduced ifsurfaces are not properly prepared and absolutely clean before cementing.

The pipework must be supported by appropriate pipe clips. The supports must bespaced to give adequate support to the pipework and long, straight sections must besupported at least every 1.5 metres. Short straight lengths of pipes between bendsmust be supported at least once. Pipework supports must not penetrate the pipewall.

DetectionUnit2.5

M1

2

3

5

5M

2.5

5M

Floor Void

Sampling

Sample Point Location

Sampling Pipe in Floor Void

Page 17: ASD HART Mini Pre-Engineered Pipe Design Guide

Hart Mini Pipe Design Guide

Issue 1 Page 6-15

Figure 4-1 Sampling Pipe Support

4.1 Warning Labels

All sampling pipe and sample points should be identified using appropriate labels,such as provided in Kidde Fire Protection’s SnifferPipe range. If the pipe is notalready pre-printed, identification labels should be applied every 2 to 3 Metres. Asample point warning label should be attached at each sample point.

1.5 Metres

Pipe Clip Pipe Socket Pipe Clip

Sample Pipe

Page 18: ASD HART Mini Pre-Engineered Pipe Design Guide

Pre

-Eng

inee

red

Pip

e D

esig

nG

uide

APPE

ND

IX A

Not

e: T

his

is b

ased

upo

n us

ing

BS

6266

sys

tem

des

ign

requ

irem

ents

(e.g

. 5 m

etre

spa

cing

)

12

34

56

78

910

1112

1314

1516

12

34

56

78

910

A1

S1

8.5

B2

S2

7.0

7.0

C2

D1+

17.

07.

0D

3S

36.

07.

07.

0E

4S

45.

56.

07.

07.

0F

4D

2+2

7.0

7.0

7.0

7.0

G5

S5

4.0

5.5

6.0

6.5

7.0

H6

S6

4.0

4.0

5.0

5.5

6.5

7.0

I6

D3+

36.

07.

07.

06.

07.

07.

0J

7S

73.

04.

04.

05.

05.

56.

06.

5K

8S

83.

03.

03.

04.

04.

55.

05.

56.

0L

8D

4+4

5.5

6.0

6.5

7.0

5.5

6.0

6.5

7.0

M9

S9

2.5

3.0

3.0

3.0

4.0

4.0

4.5

5.0

5.0

N10

S10

2.5

2.5

3.0

3.0

3.0

3.0

4.0

4.0

4.5

5.0

O10

D5+

54.

05.

06.

06.

06.

54.

05.

06.

06.

06.

5P

11S

112.

52.

52.

53.

03.

03.

03.

04.

04.

04.

04.

5Q

12S

122.

52.

52.

52.

52.

53.

03.

03.

03.

54.

04.

04.

5R

12D

6+6

3.5

4.0

4.5

5.0

6.0

6.0

3.5

4.0

4.5

5.0

6.0

6.0

S13

S13

2.0

2.5

2.5

2.5

2.5

2.5

3.0

3.0

3.0

3.5

3.5

4.0

4.5

T14

S14

2.0

2.0

2.0

2.5

2.5

2.5

2.5

2.5

3.0

3.0

3.0

3.5

3.5

4.5

U14

D7+

73.

03.

54.

04.

04.

55.

05.

53.

03.

54.

04.

04.

55.

05.

5V

15S

152.

02.

02.

02.

02.

52.

52.

52.

52.

53.

03.

03.

03.

03.

54.

5W

16S

162.

02.

02.

02.

02.

02.

02.

52.

52.

52.

52.

53.

03.

03.

03.

04.

5X

16D

8+8

2.5

3.0

3.0

3.5

4.0

4.0

4.5

5.0

2.5

3.0

3.0

3.5

4.0

4.0

4.5

5.0

Y18

D9+

92.

02.

52.

53.

03.

54.

04.

04.

04.

52.

02.

52.

53.

03.

54.

04.

04.

04.

5Z

20D

10+1

02.

52.

52.

53.

03.

03.

03.

04.

04.

04.

02.

52.

52.

53.

03.

03.

03.

04.

04.

04.

0

Pipe

2 H

ole

num

ber a

nd s

ize

(mm

) at 5

m s

paci

ngPi

pe 1

Hol

e nu

mbe

r and

siz

e (m

m) a

t 5m

spa

cing

SYST

EM

Tota

l No

of

Sam

ple

Hole

s

Sing

le o

r Do

uble

Pi

pe

Sam

ple

hole

s /

pipe

Page 19: ASD HART Mini Pre-Engineered Pipe Design Guide

Note: Based on using BS5839 system design requirements (e.g. 10 metre spacing).

Total No of

Sample Holes

Single or Double

Pipe

Sample holes / pipe

1 2 3 4 5 6 7 8 1 2 3 41 S 1 8.52 S 2 8.0 8.52 D 1+1 7.0 7.03 S 3 6.0 8.0 8.53 D 2+1 6.5 7.0 7.04 S 4 5.0 6.0 7.5 8.04 D 3+1 5.5 6.5 7.0 4.54 D 2+2 6.5 7.0 6.5 7.05 S 5 4.0 4.5 5.5 6.5 7.55 D 4+1 4.5 5.5 6.0 7.0 3.55 D 3+2 5.5 6.5 7.0 4.5.55.06 S 6 3.0 4.0 4.0 5.0 6.0 6.56 D 5+1 3.5 4.0 5.0 6.0 6.5 3.06 D 4+2 5.5 6.5 7.0 8.0 5.0 5.06 D 3+3 5.5 6.5 7.0 5.5 6.5 7.07 S 7 3.0 3.0 3.5 4.0 4.5 5.0 6.07 D 6+1 3.0 3.5 4.0 4.5 5.5 6.0 3.07 D 5+2 4.5 5.0 6.0 7.0 7.5 4.0 4.07 D 3+4 4.5 5.5 6.0 7.0 4.5 5.5 6.0 7.08 S 8 3.0 3.0 3.0 3.5 4.0 4.0 4.5 5.08 D 7+1 3.0 3.0 3.0 3.5 4.0 4.5 5.5 3.08 D 6+2 4.0 4.5 5.0 5.5 6.0 7.0 3.5 3.58 D 5+3 4.5 5.0 6.0 7.0 7.5 4.0 4.0 4.58 D 4+4 4.0 5.0 6.0 7.0 4.0 5.0 6.0 7.0

Pipe 2 Hole number and size (mm)

Pipe 1 Hole number and size (mm)


Recommended