+ All Categories
Home > Documents > ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS...

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS...

Date post: 24-Feb-2020
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
96
ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.1 5.0 EVALUATION OF IMPACTS AND MITIGATION MEASURES Evaluation of the likely adverse impacts of pollution from the project during construction and regular operation and mitigation measures to be adopted are detailed below. 5.1 Assessment of Any Environmental Impact on Local Population and the Environment during Construction and Operational Phase. The proposed project site is situated in rain fed agriculture area with mining area located in perennial grazing, short grasses, bushes/shrubs and scrubs. Details about the human settlements in the area are given in the Chapter - 4, Section 4.4. Nearest town is Choa Saidan Shah, which also Tehsil headquarter. Three cement plants are location in the Project area. In view of the strict environmental management measures to be adopted during construction and operation of the plant, there will not be any adverse impacts on the population and environment around. A systematic account of the environmental issues and their solutions is provided hereunder. During construction and operation phases of the project pollutants like effluent, gaseous emissions, particulate matter, solid wastes and noise will be generated. The likely impacts of pollutants, in case environmental controls are not put in place for their mitigation, are discussed here. Details are also given as how environmental management practices to be adopted will help to undo adverse environmental impacts on all segments of the environment. 5.1.1 Environmental Adverse Impacts and Remedies -During Construction The likely adverse environmental impacts to occur due to the project activity during construction phase are described as below
Transcript
Page 1: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.1

5.0 EVALUATION OF IMPACTS AND MITIGATION MEASURES

Evaluation of the likely adverse impacts of pollution from the project duringconstruction and regular operation and mitigation measures to be adopted are detailedbelow.

5.1 Assessment of Any Environmental Impact on Local Population and the Environmentduring Construction and Operational Phase.The proposed project site is situated in rain fed agriculture area with mining arealocated in perennial grazing, short grasses, bushes/shrubs and scrubs.

Details about the human settlements in the area are given in the Chapter - 4, Section4.4. Nearest town is Choa Saidan Shah, which also Tehsil headquarter.

Three cement plants are location in the Project area. In view of the strict environmentalmanagement measures to be adopted during construction and operation of the plant,there will not be any adverse impacts on the population and environment around. Asystematic account of the environmental issues and their solutions is providedhereunder.

During construction and operation phases of the project pollutants like effluent,gaseous emissions, particulate matter, solid wastes and noise will be generated. Thelikely impacts of pollutants, in case environmental controls are not put in place for theirmitigation, are discussed here. Details are also given as how environmentalmanagement practices to be adopted will help to undo adverse environmental impactson all segments of the environment.

5.1.1 Environmental Adverse Impacts and Remedies -During ConstructionThe likely adverse environmental impacts to occur due to the project activity duringconstruction phase are described as below

Page 2: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.2

Excavation, construction activities, moving vehicles, machinery & materials transportactivity and plant installation are the likely main sources of pollution during constructionphase.

The pollutants during construction will be emissions including sulphur dioxide (SO2),nitrogen oxides (NOx), carbon monoxide (CO); particulate matter (PM); noise frommachinery and vehicles and sewage from the work force. Dust (PM) will also begenerated especially during leveling, excavations of the land for civil construction,moving machines and transport.

Construction activities will be carried out according to a well-planned action plan basedon sound environmental management and controls principles. The construction plan willbe prepared also keeping in view avoiding maximum use of machinery at the same time.Rather, the minimum number of machines and execution of minimum number ofoperations/construction/plant installations jobs at a time will be followed. Under allthese construction and other operations gaseous emissions, particulate matter andnoise from the machinery and vehicles will be minimized and curtailed within limitedarea of the project. Therefore, pollution factor will be further reduced at source. As faras possible construction work will be carried out during day time.

Frequency of the vehicles to visit the site, carrying plant machinery and other materialswill be regulated to avoid rush on the public roads and at the project site. Rather theirvisit will be regulated under a well considered plan. They will approach the project siteat different intervals of time and in limited number. As far as possible, well maintainedvehicles will be engaged for the project work. Therefore, all type of pollutants includinggaseous, PM, noise levels and so on will be curtailed through these programming andmanagement mechanisms of number and time of visits of the vehicles.

Domestic sewage to be generated will be treated according to standard method. Thetreated sewage will be used within the four walls of the project site for irrigation ofvegetation and plants and sprinkling on the dusty roads to suppress dust and thusminimize PM pollution from the roads also. If some volume were left unused it will bedischarged in proper way.

Page 3: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.3

The project area will be declared “No Horn Zone”. This will drastically further reduceunnecessary noise levels.

Even during plant machinery installation period the best environmental managementpractices are to be strictly followed according to a plan encompassing environmentalelement.

Blasting is not predicted during construction phase however if required legal permissionwill be obtained. No hazardous chemicals will be used during construction without therequired health safety and environmental plan in place. All construction machinery willbe kept clean to avoid any oil and grease.

To keep noise levels within the prescribed limits of the NEQS Pakistan, powermechanical equipment will be used with low sound power, whenever possible.Construction machinery will be well maintained & regularly serviced. Constructionactivities will be scheduled in such a way that noise intensive operations side by sidewith an increased net noise levels are avoided. Workers will be required to use earplugs or ear muffs to avoid damage to hearing besides ensuring adoption of safe workpractices.

Further, the area subject to excavation or construction is devoid of any fauna life. Assuch there is no sensitivity of environment within the area of influence of the projectactivity. Construction activities will be carried under controlled measures to avoid anydamage to nearby waters or any element of environment in the area of influence of theproject during construction. And last but not the least, the entire phase of constructionis short lived, accordingly the likely minor addition of sediments to nearby waters havingextremely large dilution capacity will hardly matter from environmental point of view.

The main direct ecological impact resulting from the construction phase of the projectwill be the loss of vegetation associated with the “clearance” at the quarry areas, andthe access road alignments. At the quarry about 1 - 3 meters of topsoil at surface,including vegetation will be removed. These will be store in a designated area for futurere-vegetation purposes. Any trees in the plant & quarry area will be cut and supplied tothe local community as firewood.

Page 4: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.4

However, APML shall establish forest nurseries in association with this project. Treeseedlings are used (i) to provide physical screening of quarries and cement plant sitesand (ii) for subsequent site restoration. The establishment of nursery should assist withshort-term mitigation and longer term on and off-site restoration of damaged habitat.

5.1.2 Environmental Adverse Impacts, During Operation Stage and Their UltimateCompliance Status:

The potential effects of the proposed development during operation can be divided asfollows:

• Impacts on air quality as a result of emissions from the cement productionprocess and dust from the quarry activities and crushing and grinding processes.Also, international scale impacts as a result of the emissions of greenhouse gasesfrom the production process.

• Impacts associated with noise, particularly the impact of noise on nearby humanreceptors.

• Impacts of the plant and quarries by changes to the landscape and visualimpacts.

• Impacts on the local ecology by the loss of habitat taken by the development andimpacts associated with the operations on the surrounding ecology.

• Impact on the surface water regime (hydrology) by changes to the naturaldrainage of the landscape within the development area and potential emissionsof fine particles (suspended solids) into the water as a result of the industrialactivities. Potential release of contaminated effluents into the surface waterdrainage. Also, impact on the underground water, called groundwater(hydrogeology) as a result of extraction of raw materials for use in the industrialprocess.

• Use of significant volumes of raw materials and the production of waste on anindustrial scale.

• Impacts of transport.

Each of these potential issues is addressed in the following sections.

Page 5: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.5

5.1.2.1 Pollutants and Wastes:During regular plant operations the following pollutants/wastes will accrue:

i- Stack: If not controlled, they may cause various diseases among human beings,pollute nearby waters, damage aquatic life, change pH of soil and thus maydamage it. It may damage trees, plants, vegetation, structures and anything thatcomes under its influence.

The levels of their emissions into the air will be controlled well within the limitingvalues of the environmental standards of the NEQs Pakistan by employing/using:

ii- Combustion controls to minimize the formation of CO.

iii- The use of low NOx burners technologyto reduce NOx, a Greenhouse Gas (GHG),will also be in the spirit of Kyoto Protocol and practical demonsration ofadoption of Cleaner Development Mechanism (CDM).

iv- A bag filters and ESP’s for control of PM emissions..

The stack emissions concentrations of these gases and the PM will correspond to therequired limits of the NEQs Pakistan:

5.1.2.2 Air Dispersion Modeling (ADM):The design and operational criteria for the facility have been based upon guidelinesprovided the World Bank/IFC. The European Union standard relates to the main aspectsof industrial design and operation and sets out the Best Available Techniques (BAT) forprevention and control of pollution. The BAT is detailed for each major industrialactivity in a series of documents called the EU BAT Reference (BREF) notes. There is aspecific BREF note for the production of cement, which details the suitable design andoperational standard for this industrial sector. Similarly, the World Bank Group throughthe IFC have issued the EHS Guidelines which detail the requirements for the design andoperation of industrial facilities. Within these guidelines are guidelines for the cementindustry. This is the main standard adopted by the IFC investment partner. The two setsof guidance are complementary.

Page 6: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.6

Of particular importance to this project are emissions to air and assurance that the plantwill comply with the appropriate benchmarks for emissions to air. Oxides of nitrogen areof particular importance when controlling emissions from cement plants. APML hasstated that the plant will be designed and operated to meet World Bank/IFC emissionfrom stack limit standards as stated in the EHS Guidelines for Cement & LimeManufacturing, April 30, 2007. Table-1 of the guideline is reproduced below as areference:

Table – 5.1

Page 7: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.7

These levels should be achieved, without dilution, at least 95 percent of the time thatthe plant or unit is operating, to be calculated as a proportion of annual operatinghours.

These emission limits are comparable with the emission limits required in the EU BREFwith the exception of Oxides of Nitrogen. The BAT emission limit for Oxides of Nitrogenas stated in the EU BREF is stated as 500 – 800 mg/Nm3, dependent on the controlsused.

Controls on all other pollutants also have to adhere to the guidelines laid out in the forementioned standard. For all pollutants the maximum concentrations have to beachieved without dilution (i.e. main stack to contain only process gases), at least 95% ofthe time that the plant or unit is operating, to be calculated as a proportion of annualoperating hours.

In contrast to the cement plant, there are no official standards published by the EU orWorld Bank for quarrying activities. A key document useful in this respect is entitledGood Environmental Practice in “The European Extractive Industry: A Reference Guide”.

In addition to the use of international design standards for the cement plant, APML willoperate the quarries to the same standards as its parent company does with its quarriesin other countries, taking into account local sensitivities in its operational activities.

The proposed design and operation provided by the APML indicates that the plant,quarries and associated infrastructure developments will comply with the appropriateWorld Bank/IFC design and operational standards. With regards to emissions of oxidesof nitrogen the plant will operate in line with the requirements of Pakistan NEQS and IFCStandards. It is expected that APML will operate within the World Bank/IFC limitswithout the need for NO abatement technologies.

Page 8: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.8

Air Dispersion Modeling of Proposed Cement Plant:

i. IntroductionThe air dispersion of the emissions from the power plant have been estimated withthe help of widely used Air Dispersion Model “Screen – 3”.

ii. Air EmissionsThe main emissions from chimney/stack include sulfur dioxide, oxides of nitrogen,carbon monoxide, and particulate matter.

iii. Methodology:USA Clean Air Act allows the use of air dispersion modeling to determine or predictground level concentration of pollutants from point, area, volume and open pitsources as well as from line sources. The adoption of air dispersion models in thelocal scenario is most suitable to determine CO, SO2. NOx, and Particulate matter andtheir ambient concentrations from source emissions. ADM has been carried out onkiln stack located at a height of 115 meters.

iv. Modeling Scenarios:

a) Hourlyb) 24 hourly Dispersions of emissionsc) Yearly dispersion of emissions

Air dispersion modeling of NOx, SO2, CO and PM10 based hourly, 24-Hourly, andAnnual Averages of meteorological parameters for the proposed Cement Plant hasbeen carried out and the modeling output tabulated in the form of air quality tablesbelow. Appendices 5.2, 5.3, 5.4, and 5.5 present model run data for NOx, SO2, COand PM10 respectively.

v - Conclusions

The following tables based on the Air Dispersion Modeling data (show thatestablishment of the proposed Cement Plant; would have minimum environmental

Page 9: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.9

adverse impact on the air shed from the emissions of pollutants from the Kiln Stackas they remain within the prescribed limiting values set by the NEQS Pakistan andIFC Standards. Results of Air Dispersion Model run are presented below:

Table – 5.2APML - Air Dispersion Model - Data

Exhaust Gases Characteristics Emissions

CO, mg/Nm3 29

SO2, mg/Nm3 200NOx, mg/Nm3 400

PM10, mg/Nm3 30

Table – 5.3APML - ADM Input

Emission Rate

NOx, g/s 56.58

SO2, g/s 28.29

CO, g/s 4.10

PM, g/s 4.24

Stack Height, meters 115

Exhaust Temp, o C 150

Average Ambient Air Temp, o C 30

Exhaust Velocity, m/s 20.01

Volume Flow Rate, m3/s 141.46

Stack Cross-Section Area, m2 7.07

Stack Inside Diameter, meter 3.00

Page 10: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.10

Table – 5.4APML - AIR DISPERSION MODEL - RESULTS SUMMARY

Kiln StackParameters NOx SO2 CO PMA - Air Dispersion Model - Input Data- Source Type Point Point Point Point- Stack Height, meters 115.00 115.00 115.00 115.00- Stack Diameter, meters 3.00 3.00 3.00 3.00- Volume Flow Rate, Nm3/s 141.46 141.46 141.46 141.46- Emission Rate, gm/s 56.58 28.29 4.10 4.24- Stack Gas Temperature, oK 423.00 423.00 423.00 423.00- Ambient Air Temperature, oK 303.00 303.00 303.00 303.00- Rural/Urban Option Rural Rural Rural RuralB - Air Dispersion Model - Output Data- Final Stable Plume Height, meters 509.59 509.59 509.59 509.59- Stack Velocity, M/S 20.01 20.01 20.01 20.01- Buoyancy Flux, M4/S3 125.25 125.25 125.25 125.25- Momentum Flux, M4/S2 645.33 645.33 645.33 645.33- Terrain Simple Simple Simple Simple

- Maximum 1- Hour Concentration, µg/m3 101.50 50.76 7.36 7.61- Maximum 24- Hours Concentration, µg/m3, See Note(**) 40.60 20.30 2.94 3.04

- Max. Annual Ave. Concentration, µg/m3, See Note (**) 8.12 4.06 0.59 0.61- Distance to Maximum, meters 982.00 982.00 982.00 982.00IFC/WHO, Stack Emissions , mg/Nm3, (*) See Note 600.00 400.00 (***) 100 30Pakistan - NEQS, Concentration in Ambient Air,µg/Nm3

- Annual Average 40.00 80.00 (2) 5.00 120.00

- 24 Hours 80.00 120.00 (3) 10.00 150.00

(*) - Note: IFC - General EHS Guidelines April 2007, Air Emissions & Ambient Air Quality

(**) - Using US EPA conversion factor for Screen3

(***) - WHO Guideline Value for CO is 100 milligram/cubic metre for 15 minutes or 30 mg/m3 for one Hour

(1) - NOx as NO2

(2) - NEQS CO - 8 hours

(3) - NEQS CO - 1 hr

Page 11: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.11

Air impact modelling assessment indicates that there will not be an adverse impact onlocal air quality as a result of the proposed emissions of NOx, SO2, CO & PM.

It is concluded that at all sensitive receptors, the maximum changes in NOx, sulphurdioxide, carbon monoxide, and particulate matter concentrations due to plant operationare a small fraction of the relevant air quality criteria, and future air quality will remainwell within these criteria. The principal emission from the cement kiln is oxides ofnitrogen. Given the likely very good existing background air quality in these largely rurallocations, air quality will remain well within the limit value.

The overall conclusion from the dispersion modelling study is that when the plant is inoperation future air quality will be well within the Pakistan NEQS, World Bank/IFC &WHO guidelines specified for the protection of human health. These limits are set wellbelow the levels at which there are any observable effects on human health orrespiratory function in order to protect vulnerable individuals within the population. Onthat basis, it is concluded that there will be no adverse health effects on the localpopulation due to the operation of the proposed Cement Plant.

5.1.2.2 All Waste WatersThe Cement Plant produced wastewater, sanitary & sewage water and oily waste water,etc., will be treated as: neutralized, flocculated, bio-contact oxidation technologyprocessing and oil-water separators respectively. After treatment the wastewater isexpected to meet Pakistan NEQS effluent standard and will be reused.

5.1.2.3 Equipment NoiseIt will be controlled using conventional noise control measures, such as insulation,lagging, and enclosures as needed to comply with the NEQS Pakistan {85 dB (A)}:

Page 12: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.12

Maximum Allowable Log Equivalent (hourly measurements), in dB(A)Day Night

Receptor (07:00-22:00) (22:00-07:00)Residential,Institutional,Educational 55 45

Industrial,Commercial 70 70

5.1.2.4 Solid Wastes,Main solid wastes anticipated and their disposal methodology are given hereunder:

- Metal/wooden waste: Metal and wooden waste to be sold in the marketfor reuse.

- Empty drums or containers: Empty drums/containers will be returned tothe suppliers for recycling/reuse at their end.

- Cotton rags: Waste cotton rags to be generated after cleaning ofequipment will be incinerated in an incinerator to be installed on theproject site.

- Dispensary wastes: All dispensary wastes will be incinerated inincinerator.

- Miscellaneous waste: Miscellaneous solid waste including redundanttires, tubes, batteries, belts, nylon strips, filters, scrap wood, steel scrap,etc., will be sold in the market through contractors.

Solid wastes to be generated from the project production activities will be sold in themarket for their recycling & reuse. Some of them will be used on site.

However, while disposing any solid waste material, all environmental aspects/impacts ofsuch wastes will be communicated clearly to the concerned contractor. Record of allsuch sales will be maintained for later use if and when required.

Page 13: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.13

Environmental pollution on all accounts from the project activity on regular basis shallbe managed by strict compliance with the Environmental Management Plan (EMP) andEnvironmental Monitoring Plan (EMtP) as recommended in this EIA Report, andfollowing environmentally sustainable practices/cleaner production practices under thefive (5) “R” concept- Reduce, Recycle, Reuse, Retrofit and Refurbish.

5.2 The Relevant Environmental Data and Predictive Methods Used and Any UnderlyingAssumptions Made

5.2.1 Base line Environmental Data:In order to know about the existing status of environment on the project site, baselineenvironmental monitoring was carried out. The ambient monitored data regardingSulphur dioxide (SO2), Nitrogen Oxides (NOx), Carbon monoxide (CO), PM, noise levelsand water quality are exhibited in following sections. These data are necessary for anyfurther reference and for its use by EPA Punjab or the project proponent for a variety oftheir end uses.

5.2.1.1 Ambient Air Quality-AmbientDetails of the status of ambient gaseous pollutants and particulates are reportedhereunder:

Table – 5.5Ambient Air Monitored Data

REFERENCEPOINT DATE TIME

HOURSSO2

(µg/m3)NO2

(µg/m3)CO

(mg/Nm3)PM10

(μg/m3)

Near Proposed

Plant Site

28.09.2015 06:00 31.2 32.5 1.3 33.9

28.09.2015 09:00 34.1 31.2 2.5 41.7

28.09.2015 12:00 35.8 36.7 2.6 42.5

28.09.2015 15:00 36.1 37.2 0.1 43.1

28.09.2015 18:20 35.7 25.3 1.8 42.8

28.09.2015 21:30 31.1 12.3 2.5 33.8

Page 14: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.14

REFERENCEPOINT DATE TIME

HOURSSO2

(µg/m3)NO2

(µg/m3)CO

(mg/Nm3)PM10

(μg/m3)

28.09.2015 24:00 31.0 22.2 2.3 33.7

29.09.2015 03:00 30.9 21.9 1.0 42.1

29.09.2015 06:00 31.0 22.1 1.1 43.1

Pak NEQS 80µg/m3

80µg/m3 10 mg/m3 150

µg/m3

NEQS = National Environmental Quality Standards for Ambient Air.* High concentration of air pollutants are associated with burring of the post waste from cultivated land, andmovement of Bicycle and Heavy Tractors during the monitoring hours.

5.2.1.2 Noise LevelsNoise levels monitoring was done at the project site to have background environmentaldata. The monitored data are reported in the Table – 5.6.

Table 5.6Noise Levels Monitored Data

REFERENCEPOINT DATE TIME

HOURS dB(A) LEQ /AVERAGE

Main RoadNear Katas

28.09.2015 06:00 45 46 46 46 47 45 47 47 45 46.0

28.09.2015 09:00 61 63 63 62 68 70 70 61 66 64.88

28.09.2015 12:00 70 68 68 68 61 59 59 60 61 63.77

28.09.2015 15:00 62 69 72 62 60 61 60 59 60 62.77

28.09.2015 18:20 64 63 63 62 68 73 74 61 63 65.66

28.09.2015 21:30 45 46 49 49 48 45 41 42 42 45.22

28.09.2015 24:00 35 36 36 36 37 35 37 37 35 36.0

29.09.2015 03:00 34 33 31 31 31 32 33 31 32 32.0

29.09.2015 06:00 45 46 46 46 47 45 47 47 45 46.0

Page 15: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.15

5.2.1.3 Water QualityAnalysis of ground water sample collected Tatral Village, Dulmial Village and Near KatasTemple are presented in Tables 5.7, 5.8 and 5.9.

Table – 5.7

SR.NO.

PARAMETERS UNITS NDWQS RESULTS REMARKS

1. pH – 6.5–8.5 7.7

--

2. Taste & Odor – NonObjectionable Objectionable

3. Color TCU <15 11

4. Turbidity NTU <5 12

5. Total Coliform Number/100 mL 0 Number/100mL

10

6. E–Coli Number /100 mL

0 Number /100 mL 0

7. Total DissolvedSolids (TDS) mg/L <1000 330

8. Total Hardness mg/L <500 68

9. Nitrate mg/L ≤50 1.2

10. Nitrite mg/L ≤3 0.001

11. Ammonia mg/L – 0.01

12. Arsenic mg/L <0.05 N.D.

13. Antimony mg/L <0.005 N.D.

14. Barium mg/L 0.7 N.D.

15. Chloride mg/L 250 34

16. Fluoride mg/L <1.5 0.3

17. Aluminum mg/L ≤0.2 N.D.

18. Manganese mg/L ≤0.5 N.D.

Page 16: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.16

SR.NO.

PARAMETERS UNITS NDWQS RESULTS REMARKS

19. Mercury mg/L 0.001 N.D.

20. Iodine mg/L – 0.08

21. Zinc mg/L 5 0.14

22. Boron mg/L 0.7 N.D.

23. Chromium mg/L ≤0.05 N.D.

24. Selenium mg/L ≤0.5 N.D.

N.D = Not DetectedSampling Source = Hand Pump Water near Tatral

Table – 5.8

SR.NO. PARAMETERS UNITS NDWQS RESULTS REMARKS

1. pH – 6.5–8.5 7.4

--

2. Taste & Odor – NonObjectionable

Objectionable

3. Color TCU <15 6

4. Turbidity NTU <5 4

5. Total Coliform Number/100 mL 0 Number/100mL

0

6. E–Coli Number /100 mL

0 Number /100 mL 0

7. Total DissolvedSolids (TDS)

mg/L <1000 290

8. Total Hardness mg/L <500 53

9. Nitrate mg/L ≤50 1.1

10. Nitrite mg/L ≤3 0.001

11. Ammonia mg/L – 0.01

Page 17: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.17

SR.NO.

PARAMETERS UNITS NDWQS RESULTS REMARKS

12. Arsenic mg/L <0.05 N.D.

13. Antimony mg/L <0.005 N.D.

14. Barium mg/L 0.7 N.D.

15. Chloride mg/L 250 30

16. Fluoride mg/L <1.5 0.3

17. Aluminum mg/L ≤0.2 N.D.

18. Manganese mg/L ≤0.5 N.D.

19. Mercury mg/L 0.001 N.D.

20. Iodine mg/L – 0.08

21. Zinc mg/L 5 0.11

22. Boron mg/L 0.7 N.D.

23. Chromium mg/L ≤0.05 N.D.

24. Selenium mg/L ≤0.5 N.D.

N.D = Not DetectedSampling Source = Hand Pump Water near Dulmial

Table – 5.9

SR.NO.

PARAMETERS UNITS NDWQS RESULTS REMARKS

1. pH – 6.5–8.5 8.1

--2. Taste & Odor – Non

Objectionable Objectionable

3. Color TCU <15 21

4. Turbidity NTU <5 18

Page 18: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.18

SR.NO.

PARAMETERS UNITS NDWQS RESULTS REMARKS

5. Total Coliform Number/100 mL 0 Number/100mL

45

6. E–Coli Number /100 mL

0 Number /100 mL +ve

7. Total DissolvedSolids (TDS) mg/L <1000 390

8. Total Hardness mg/L <500 73

9. Nitrate mg/L ≤50 2.1

10. Nitrite mg/L ≤3 0.001

11. Ammonia mg/L – 0.01

12. Arsenic mg/L <0.05 N.D.

13. Antimony mg/L <0.005 N.D.

14. Barium mg/L 0.7 N.D.

15. Chloride mg/L 250 63

16. Fluoride mg/L <1.5 13

17. Aluminum mg/L ≤0.2 N.D.

18. Manganese mg/L ≤0.5 N.D.

19. Mercury mg/L 0.001 N.D.

20. Iodine mg/L – 0.18

21. Zinc mg/L 5 0.14

22. Boron mg/L 0.7 N.D.

23. Chromium mg/L ≤0.05 N.D.

24. Selenium mg/L ≤0.5 N.D.

N.D = Not DetectedSampling Source = Hand Pump Water near Katas Temple

Page 19: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 5, Evaluation of Impacts & Mitigation Measures Page – 5.19

5.3 Compliance with Relevant Environmental Standards:The plant will operate in compliance with the National Environmental Quality Standards(NEQS) Pakistan.

5.4 Assessed Significance of the Impact Stating the Standards or Criteria used as a Basisfor Judgment:Pollutants of all sorts to be generated due to plant operations have been discussed inthe preceding section. Assessment as to their remaining within the NEQS limiting valueshas also been given therein. The levels of emissions of all kinds will conform to theNEQS.

5.5 Potential socio-economic impactsPotential socio-economic impacts to accrue from the project activity are described asunder:

The proposed Project will provide jobs to about 1500 - 2000 workers at peakconstruction and about 300 - 400 workers during regular operations of theproposed Cement Plant.

Both provincial and Federal Governments will receive taxes and duties onrecurring basis.

Basic infrastructure of the area will improve. Supply of vendors’ services is yet another opportunity of earnings for the people

of the area. Supply of edibles like fruit, milk and other food items will be other source of

income. Price of the land will be appreciated which is another benefit to its owners. Addition to the awareness of the people will set trend in getting education

among the people of the project area. It will improve their social status thusbringing a lot of tangible change in the overall life style of the people.

Page 20: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 6, Comparative Evaluation of Alternative Page – 6.1

6.0 COMPARATIVE EVALUATION OF SITE ALTERNATIVES AND IDENTIFICATION OF THEPREFFERED OPTION

6.1 Siting

Site selection requires careful, well thought out and wise decision. Any over sight maylead to major failure. Among various other major factors, the following are the mostimportant ones taken into consideration for site selection regarding the cement plantunder reference:

This Chapter presents a systematic comparison of feasible project alternatives, in termsof both the project (i.e., technology, design, operation, etc.) and site selection. Theassessment of project alternatives and site selection includes environmental and socialfactors and include a no action (i.e., without the project) scenario.

The assessment must clearly state and justify the selected alternative. Alternativesinclude location as well as approach to design, process, and construction technology aswell as the country chosen.

The main alternatives for the establishment of a grass root cement manufacturingfacility can be summarized in following sections.

6.2 Do Nothing Alternative

The ‘Do Nothing’ alternative means as economic development accelerates, due to CPEC,public sector development programmes and various public & private projects (especiallymega dams projects), and the country will have to import cement to meet its futureneeds and will be mostly dependent on world market fluctuations. At the same timeexport of cement (a substantial foreign exchange earner) will end. With shortage ofcement in the country the prices of cement will go up thus increasing construction costs.Pakistan has abundant natural resources and especially high quality and easilyextractable limestone and clay/laterite reserves which make the best location in PunjabProvince for a cement plant. This single source alternative if not utilized will resort todependence on cement imports, but that could also very easily result in the cement

Page 21: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 6, Comparative Evaluation of Alternative Page – 6.2

supply shortages. Shortage of building material like cement will cause cement prices torise.According to Market Study of the Project, by Year 2020-21 there will a shortfall indomestic demand of 4.0 million to 7.0 million tonnes of cement, which is likely toincrease further in subsequent years. “Do Nothing” alternative will place Pakistan’sdependency on cement imports or slow down its economic growth.

The ease of availability to basic building materials is needed to further develop country’seconomy. The ‘Do Nothing’ alternative does not seem plausible given the legitimacy ofthe proposed project rationale and the benefits to be derived. Pakistan’s trade deficitwill increase, and the country will remain susceptible to high cement prices.

Though it has minor social and environmental impacts, the proposed cement plant isexpected to provide about 350 job opportunities during its operation phase andadditional job and economic opportunities through development of supply/distributionchain and trucking. In addition, there will be a transfer of technology associated withinstallation, operation of the equipment and maintenance and savings on foreignexchange, hence the alternative of establishing cement plant was chosen.

The investment potential of US Dollar 470 million, as proposed by the ProjectProponents, will not be utilized with “Do Nothing” option.

6.3 Project Site Option

Given that limestone and clay represent over 94% of the raw materials from whichcement is manufactured, the availability of these unexploited raw materials is anotherprimary criterion for determining potential sites for a new cement plant. The proposedplant site in Chakwal District located close to south of large reserve of good qualitylimestone deposit with availability of clay in the vicinity. Shorter distance location of theplant from the limestone and clay deposit will reduce the transportation cost and in turnwill lower the cost of cement production as well as minimize generation of greenhousegases due to transport movement over shorter distance from quarry to plant site.

Page 22: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 6, Comparative Evaluation of Alternative Page – 6.3

The proposed plant site is to be located in an area which is devoid of any biodiversityincluding forestry, wildlife, migratory birds, game reserves (flora and fauna), orprotected species of fauna & flora; fishery or aquatic biology; watershed. There is nocultural or any other heritage in the proposed Plant site area.

There is only one very small village namely “Rupper” Village with 32 houses having apopulation of 175 people. Population of this village will be relocated/resettled.

There is no environmental sensitivity in the project area. These factors are also stronglysupportive of the proposed project site.

The limestone deposit is unexploited and is situated along with proposed plant site inarea of environmentally insignificant. Most of the area has vegetation in the form ofvery small bushes, of no value from any angle.

All raw materials, with the exception of gypsum, will be extracted from the proposedmining lease area. This option entails the execution of the proposed project, whichinvolves mining limestone and clay from a dedicated quarry.

The proposed location was determined to be the most convenient location in closeproximity to the limestone and clay reserves. The proposed site has least environmental& social impacts.

The site has proximity to Motorway M-2. A 132 KV High Tension Line passes close to theproposed site. These factors are also very much supportive of the project at theproposed site.

6.4 Mine Options

Two options can be considered for limestone mining, within the proposed site, i.e., sub-surfaced Open Cast Mining and Underground Mining. Sub-surface open cast mining hasbeen considered as most efficient and suitable for mining operation. The method ofmining is considered to be safer and economical.

Page 23: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 6, Comparative Evaluation of Alternative Page – 6.4

6.5 Technology Options

The technology being considered to be ‘state of the art’ in terms of being environmentfriendly, energy efficiency and modern plant & process design for similar capacityplants.

Dry process technology has been preferred over wet or semi-dry technologies as moreeconomical in power consumption as well as heat and manpower requirement andbeing less capital intensive.

The new plant will be built according to the applicable Best Available Technologies (BAT)defined for the cement industry, which include the adoption of pre-calcining technologyin the clinker production and de-dusting bag filters for gases.

6.6 Process Options

The grinding efficiency of a ball mill is only half as efficient as a vertical roller mill,therefore, for this project, APML has proposed vertical roller mills for raw materialgrinding, cement finishing grinding and solid fuel (coal) grinding. Ball mills result insignificantly higher specific power consumption. In addition, the noise level of a verticalroller mill is significantly lower than that of a ball mill.

APML has proposed 5-Stage preheater with pre-calciner. The preheater configurationselected offers an optimal solution with respect to heat economy and powerconsumption taking into account the moisture content of the raw materials as well asthe height of the preheater tower.

In comparison with conventional kiln systems (without pre-calciner) the selectedinstallation offers a considerable reduction in kiln dimension and a high degree of pre-calcination. Concerning the operational costs, the uniform operation and low brickconsumption are favorable aspects of the pre-calciner kiln.

The kiln burner is a two-channel burner with low primary air consumption, normally inthe region of 6-8%. The primary air is supplied by a high pressure fan (up to 250 mbar).

Page 24: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 6, Comparative Evaluation of Alternative Page – 6.5

Coal mill installations are designed to meet International standards, which will befollowed for factory installations, where the risk of explosion is possible.

Several air pollution control technologies suitable for the proposed project wereconsidered, the main equipment include bag house, ESP and cyclones.

6.7 Construction Technology Options

The proposed project site is not exposed to any natural hazards. The highest structure inthe cement plant is the preheater tower at approximately 110 meters in height. In thisrespect, concrete construction will be applied in the foundation and lower level of thepre-heater tower. The middle and top levels of the pre-heater tower are expected touse structural steel. Alternatives, such as the use of fewer pre-heater stages, to lowerthe height of the structure would compromise, unfortunately, negatively impact the fuelefficiency of the plant and therefore the increase environmental emissions. Therefore,good engineering practices need to be implemented within the context of the preferredtechnology.

A thorough investigation of construction technology options will therefore depend onsound engineering design as well as field investigations (such as weather, climate, soilbearing capacity, the availability of construction materials locally and local labor skills).During the design phase, the EPC Contractor will choose the construction technologywhich best meets the Project schedule, safety, and quality as well as the economicbenefit to the local community.

The proposed project site is located in the “Minor to Moderate Zone of SeismicActivity”.

Page 25: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.1

7.0 ENVIRONMENTAL MANAGEMENT PLAN, ENVIRONMENTAL MITIGATION MEASURES,MONITORING PLAN, SOCIAL MANAGEMENT PLAN AND PROPOSED TRAINING

As desired by the matrix/mandate of the officially approved EIA Repot guidelinesAppendix – 1.5, the Environmental Management Plan (EMP) presented in this sectionhighlights the followings:

i- Mitigation / Compensation Measures during Construction Phaseii- Mitigation / Compensation Measures during Operation Phaseiii- Environmental Monitoring:

Ambient Air Quality Stack Emissions Noise Assigning responsibility for implementation (by name or position) Reporting and reviewing procedures

iv- Training Needs

7.1 Environmental Management Plan

Environmental Management Plan (EMP) is presented in this section. Mitigation andcompensation measures to address the environmental issues during construction of theproject are discussed in Section-7.2. The mitigation and compensation measures essentialto meet the requirement during operation of the proposed project are described inSection - 7.3 of this Chapter. Section – 7.4 presents the impacts and mitigation measuresduring decommissioning phase.

In Section-7.8, monitoring recommendations are presented for documenting thecompliance of the project to the NEQS Pakistan and the World Bank EnvironmentalGuidelines.

7.2 Mitigation / Compensation Measures during Construction PhaseThese are presented in Table – 7.1 below.

Page 26: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.2

7.3 Mitigation / Compensation Measures during Operation PhaseThese are presented in Table – 7.2 below.

Mitigation Measures during Construction PhaseTable - 7.1

AIR QUALITYEnvironmental Impact Proposed Mitigation Residual Impact Residual Impact

RatingAir quality:- dust emissions duringconstruction and groundworks.

Development ofprocedures for:-water spraying roads anddusty materialsstockpiles- covering vehiclescarrying dusty materialson leaving the site toprevent materialsbeing blown from thevehicles-speed limits on unpavedsurfaces on site to limitdust.

Dust propagation will belimited to construction areaand will not influence localcommunity. Workers willbe supplied with dustmasks.

Minor adverse

GROUND & WATEREnvironmental Impact Proposed Mitigation Residual Impact Residual Impact

RatingImportation of pollutantsalready presentwithin the materials to beused for fillingand site levellingoperations

Ensure that pollutants arenot present in materialsimported onto the site byappropriate selection ofsource material by theContractors and chemicalanalysis by APML ifrequired.

Potential for importation ofpollutants in the materialwill be minimized throughAPML’s specifications toContractors and monitoringby APML project team.

Minor adverse

Accidental release of fuels,oils, chemicals, hazardousmaterials, etc., to theground, especially in theconstruction lay-downarea, during delivery to thesite.

Appropriate proceduresand protocols to beestablished and monitoredfor materials delivery andhandling to ensure thereare no spills.

Potential for accidentalrelease during delivery ofmaterials to the site will beminimized via writtenprocedures and protocols.

Minor adverse

Accidental release of fuels,oils, chemicals, liquidwaste, hazardous materials,etc., to the ground,especially in theconstruction lay-downarea, during storage.

All storage areas will haveappropriate environmentalsecurity measures toprevent accidental releaseto ground.

Potential for accidentalrelease of materials duringstorage on the site will beminimized.

Minor adverse

Page 27: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.3

GROUND & WATER [continued]Environmental Impact Proposed Mitigation Residual Impact Residual Impact

RatingAccidental release of fuels,oils, chemicals, hazardousmaterials, etc., to theground, especially in theconstruction lay-downarea, during transport tothe area of use.

Appropriate proceduresand protocols to beestablished and monitoredfor materials transport andhandling whilst on the site.

Potential for accidentalrelease of materials duringtransport within andhandling on the site will beminimized.

Minor adverse

Accidental release of fuels,oils, chemicals, hazardousmaterials, etc., to theground, during use, [forexample, re-fuelling,maintenance, etc.]

Appropriate proceduresand protocols to beestablished and monitoredfor materials handling anduse. Where possible, re-fuelling and maintenanceareas will include someform of secondarycontainment.

Potential for accidentalrelease of materials duringuse will be minimized.

Minor adverse

Accidental release of liquidwastes during removalfrom site.

Appropriate proceduresand protocols to beestablished and monitoredfor waste materialsremoval.

Potential for accidentalrelease of waste duringremoval from the site willbe minimized.

Minor adverse

Accidental discharge ofsanitary wastewater toground and groundwaterfrom the workers camp.

Sanitary waste will not bedischarged to the ground.Contractors will provideappropriate SewageTreatment Facilities.

None Negligible/Nil

Contamination of localwater ways from proposedeffluent plant discharge.

Ensure that the plantcomplies with IFCstandards and otherinternational guidelines.Final effluent should haveno significant negativeimpact on the receivingwater. The plant will bedesigned for the full loadduring construction.

Potential for release ofharmful of effluent if thefacility is underspecified ornot managed correctly.

Minor adverse

Discharge of pollutants inwater used for plant,equipment and vehiclewashing to ground.

Washing activities willtake place on areas withappropriate containmentand procedures andprotocols will beestablished and monitoredto ensure that thepreventative measures aresufficient to meet theeffluent standards.

Potential for accidentalrelease of pollutants to theground during washingactivities will beminimized.

Minor adverse

Page 28: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.4

GROUND & WATER [continued]Environmental Impact Proposed Mitigation Residual Impact Residual Impact

RatingIncrease of sediment loadin natural aquatic receptorsresulting from direct run-off disposal.

Minimization ofexcavations face duringConstruction. Temporarydrainage grooves andsedimentation ponds forsurface run-off collection.The topography is nearlyflat.

None Negligible

Natural aquatic receptorsdegradation due to directdisposal of domestic typewastewater.

Construction of appropriatesewage system andwastewater treatmentfacility by Contractor.Effluent if any will meetthe standards.

None Negligible

Groundwatercontamination fromleakage of pollutingsubstances.

Usage of non-hazardousconstruction materials forhuman health andenvironmental protection.Storage of potentialpolluting materials inappropriate areas,including secondarycontainment.Any contaminated landoccurred duringconstruction will bedirectly removed anddisposed of in accordancewith local regulations forwaste disposal.

None Negligible

MATERIAL USE & WASTE MANAGEMENTEnvironmental Impact Proposed Mitigation Residual Impact Residual Impact

RatingWaste generation. Introduction of waste

storage and controlproceduresSegregation and recyclingof waste by EPCContractor into metalcomponents, plastics, glassseparately.

Waste for disposal will bedisposed of at an approvedwaste disposal site.

Negligible

Page 29: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.5

ECOLOGYEnvironmental Impact Proposed Mitigation Residual Impact Residual Impact

RatingPlant & Mine SiteLoss of vegetation on site.Clearance.

Vegetation loss cannot beavoided, but clearance withsuccessful restoration,improvement and longterm management of thesurrounding areas forconservation andproductive uses willprovide significantcompensation.

Negligible

Further land take over(habitat loss) for temporaryConstruction Camp.

Build temporaryconstruction camp on landthat in due course be re-used for APML for otheractivities.Contractors/APML willalso restore, whereverpossible to green areassuch as the planting ofgrass, shrubs & trees.

No additional impact sinceis visualized.

Not significant

Destruction of fauna andhabitat (mammals, birds,reptiles, amphibians,invertebrates).

Further ecological/faunasurvey at appropriateseasons and translocationsmonitored by the APMLspecialist.

Moving fauna toneighbouring sites mayhelp short-term survival,but not medium-term ifthese sites are alreadyoccupied. In long termpopulations may recoveron restored sites.

Not significant

Increase in exploitativepressures on habitatsneighbouring the sites.

Conduct and implementfurther “Habitat Surveyand Management Study”,in close consultation withlocal officials &communities.

With co-operation ofofficials & localcommunity and projectproviding alternativesource of income, habitatsshould be improved.

Moderate to substantialbeneficial.

On ecology of surroundingarea by temporaryworkforce as a result ofremoval of vegetation andthe displacement ofwildlife.

Education, monitoring andenforcement program.Adequate wastemanagement and sanitationfacilities. No permits willbe provided to Contractorsfor any burning.

Implementation may bedifficult and some impactcan be expected.

Minor adverse (subject toimplementation andenforcement).

LANDSCAPE AND VISUALEnvironmental Impact Proposed Mitigation Residual Impact Residual Impact

RatingDamage to the landscapecharacter and visualamenity due toIntroduction ofincongruous features andactivities.

Sensitive planning of siteworks and worker’scompound. Advancedstructure planning.Minimize lighting andnight time workings.

Some exposure toalteration of the landscapecharacter and loss of visualamenity, predominantlydue to out-of-site activity.

Minor adverse impact.

Page 30: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.6

NOISE & VIBRATION [Incorporating Transport]Environmental Impact Proposed Mitigation Residual Impact Residual Impact

RatingNoise from construction ofnew plant/mine and linkroads.

Good site management;Appropriate choice ofmachinery; Methods ofworking; Hours ofworking; efficient materialhandling.

A baseline noise studyneeds to be carried out. Butfurther study may be Theneed to predict whetherthere may be noiseincreases at nearbyvillages.

Minor adverse

Noise from traffic relatingto construction usingexisting roads throughlocal residential areas &cities

Define access routes to thesite with the smallestnumber of properties inproximity to it. Keepvehicle movements to aminimum. Once link roadsare completed, allconstruction traffic to/fromthe site should only use thelink roads.

There may be noiseincreases at residentialproperties in proximity tothe chosen access route,and then from the link roadonce completed.

Not significant

SOCIALEnvironmental Impact Proposed Mitigation Residual Impact Residual Impact

RatingWorker - industrialemergency

Prearranged qualitycurative treatment inHospitals at Choa SaidanShah, Kallar Kahar andChakwal for allemergencies.

Depends on nature ofemergency

Minor adverse

Non-local worker livingconditions and quality oflife. Utility and serviceprovision impacts on localvillages.

Contractors will providedetailed specification ofcamp layout, facilities, andutility provision (anddisposal) in accordancewith identifiedinternational standards.APML to monitor healthand safety and terms andconditions of employment.

Depends on individualworker susceptibility. Ifconditions are poormultitude of issues couldarise in camp and spill intolocal communities.

Minor / Moderate adverse

Disturbance and conflict incamp

In-camp codes of conductand enforcement of keybehaviours shall berequired.

None identified Minor adverse

Page 31: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.7

SOCIAL [continued]Environmental Impact Proposed Mitigation Residual Impact Residual Impact

RatingDisturbance and /orconflict with localpopulation.

Camp code of conductupheld by workers andenforced by camp.Provision of employmentand opportunities to localpopulation to minimizehostility.

Some residual impactexpected but scale limitedby worker free time, andlocal interaction withcamp, especially if“Liaison Committee” isformed early.

Minor / Moderate adverse

Potential for increasedincidence of transferabledisease (TD) in localpopulations and amongstworkers.

Preventative healthawareness campaigns forTDs provided to workersand targeted at key locallocations / groups.Contractors will providehealth checks andimmunizations beforemovement to site.

Difficult to identify causeor source of such disease.However some diseasemay be spread and curativetreatment may be requiredfor the different diseases.

Moderate adverse

Page 32: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.8

MITIGATION MEASURES DURING OPERATION PHASE

Table 7.2AIR QUALITYEnvironmental Impact Proposed Mitigation Residual Impact Residual Impact

RatingRelease of combustiongas emissions from thekiln stack

Equipment design andprimary operationalmanagement controltechniques

Local air emissions willbe based on IFCGuidelines for theprotection of humanhealth at all emissionpoint sources. On thatbasis, it is concludedthat there will be noadverse health effects inthe local population dueto the operation of thecement plant.

Not significant

Release of particulateemissions from the kiln,the clinker cooler, thecoal mill and the cementmill.

Bag filters – dustabatement using verystringent 30 mg/Nm3

standard and ESP 100mg/Nm3 standard.

Local air quality will bevirtually unaffected inProject area &surroundings, and willbe based IFC Guidelinesfor the protection ofhuman health.

Negligible

Release of dustemissions from thequarry operations.

Use of best practicemanagement techniquesduring extraction andloading of raw materials.

It is unlikely that therewill be any discernibleadverse effect due todust deposition at anyresidential properties.

Not significant

Release of combustionemissions from transportassociated with transportof materials to and fromthe site.

Use of new, efficientvehicles, driver trainingto minimize emissions(e.g. prevention of overrevving, shut off engineswhen vehicles not inuse), propermaintenance,rationalization of trafficmanagement system tooptimize transportefficiency.

Localized minor effectson air quality at anyproperties very close tocertain roads, butincrements a very smallfraction of air qualitycriteria. Given thevolume of trucks,however, impact isModerately adverse.

Moderate.

Page 33: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.9

Surface Water and Ground WaterEnvironmental Impact Proposed Mitigation Residual ImpactIncrease of sediment content insurface due to fugitive dustdispersion.

For cement plant: Storm watermanagement through ditchesand or gutters and settlementponds.For mines: Mine face will bekept minimal. Gradualrehabilitation (throughlandscaping and planting) oflocations where extractionworks have been completed.Storm water managementthrough peripheral ditches andsettlement pond.

None

Degradation of surface watersquality due to process waterdirect disposal or leakage ofpolluting materials.

For cement plant: Processwater circulation is closedcircuit including settlementtank for treatment. Storage offuels for cement production inenclosed storage area. Tidyingthe plant on regular basis withmechanical sweepersremoving dust collected on thestreets and gutters. Thoroughwashing of surfaces in case ofpolluting materials spillagesand further processing ofcollected washings as specialwaste.For mines specialconsiderations for clay quarry.Preventative maintenance ofquality equipment, protocolsand procedures.

None. Appropriate collection andtransportation of potential pollutingmaterials (e.g. spent oil, lubricants,etc.)

Pollution of surface water dueto release of harmful/untreatedsewage.

The sewage treatment systemwill be sized for peak demandduring operation phase. Nohazardous liquids will bereleased on to the sewagetreatment system. Theprovision of a large balancingtank before industrial use willact as a storage unit in theevent of accidental release intothe sewage system.

None

Page 34: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.10

Soil Erosion. For cement plant: EPContractor to design properdrainage system consistentwith seasonal winds.For mines: Proper Drainagedesign by the Contractor aswell as gradual rehabilitationof location where extractionworks have been completed.

Soil erosion will be limited on-site thequarries.

Ground and Groundwatercontamination.

For cement plant and mines:Secondary containment forpotential polluting materials.Any contaminated landremoval and disposal inaccordance with local andgeneral internationalrequirements.

Potential contamination will be limitedon-site.

LAND QUALITYEnvironmental Impact Proposed Mitigation Residual Impact Residual Impact

RatingAccidental release offuels, oils, chemicals,hazardous materials,etc., to the groundduring delivery to thesite.

Appropriate proceduresand protocols to beestablished andmonitored for materialsdelivery and handling.APML will have, at alltimes, clean up kitsavailable.

Potential for accidentalrelease during deliveryof materials to the sitewill be minimized.

Minor adverse.

Accidental release offuels, oils, chemicals,liquid waste, hazardousmaterials, etc., to theground during storage.

All storage areas willhave appropriateenvironmental securitymeasures to preventaccidental release toground. EP Contractorto design the plant forberms/detrimentalretainer walls that aredesigned for 1.5 timesthe capacity of any suchstorage tank.

Potential for accidentalrelease of materialsduring storage on thesite will be minimized.

Minor adverse.

Accidental release offuels, oils, chemicals,liquid waste, hazardousmaterials, etc., to theground during transportto the area of use.

Appropriate proceduresand protocols to beestablished andmonitored for materialstransport and handlingwhilst on the site.

Potential for accidentalrelease of materialsduring transport withinand handling on the sitewill be minimized.

Minor adverse.

Accidental release offuels, oils, chemicals,liquid waste, hazardousmaterials, etc., to theground during use, for

Appropriate proceduresand protocols to beestablished andmonitored for materialshandling and use. Wherepossible, re-fuelling and

Potential for accidentalrelease of materialsduring use will beminimized.

Minor adverse.

Page 35: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.11

example, re-fueling,maintenance, etc.

maintenance areas willinclude some form ofsecondary containment.

Accidental release ofliquid wastes duringremoval from site.

Appropriate proceduresand protocols to beestablished andmonitored for liquidwaste materials removal.

Potential for accidentalrelease of waste duringremoval from the sitewill be minimized.

Minor adverse.

Accidental discharge ofsanitary wastewater andwastewater to ground.

Sanitary wastewater willnot be discharged to theground. Wastewatersumps and pits will beproperly designed. Pipe-work will be inspectedperiodically by APMLand recycle waterwherever possible.

None Negligible/Nil.

Discharge of pollutantsin water used for plant,equipment and vehiclewashing to ground.

Washing activities willtake place on areas withproper drainage systemswith containment andtreatment. Effluent, ifany, will meet thestandards.

Potential for accidentrelease of pollutants tothe ground duringwashing activities willbe minimized by properdesign and use byAPML.

Minor adverse.

ENERGY AND GREENHOUSE GAS BALANCEEnvironmental Impact Proposed Mitigation Residual ImpactUse of solid fuels and direct andindirect greenhouse gasemissions.

Ensure that combustion andprocessing is as efficient and infull compliance with IFCrequirements for cement plantand maintenance and monitoringby APML.

Emissions of greenhouse gases.[Refer to separate note, in latersection of this Chapter-7.]

MATERIAL USE AND WASTEWATER MANAGEMENTEnvironmental Impact Proposed Mitigation Residual ImpactStorage of solid and liquidwastes.

Inspection of all waste storageareas to ensure appropriateidentification, segregation andcontainment.

Potential release into theenvironment.

Waste management Establishment of wastemanagement disposal/recyclingtechniques and appropriatechoice/negotiation of EPCcontractor by APML.Establishment of filter dusthandling procedures and choiceof the contractors. Hazardouswaste disposal techniques to beestablished. Review of wasteminimization and recyclingoptions for all waste will beexhaustive

Waste management will becovered by internal proceduresand will be regulated throughlocal regulations. Increasedquantity of waste will be disposedof off-site. APML will monitor itsprocedures to increase ormaximize recycling/reuse of anywaste generated, including firingin the cement manufacturingprocess and composting.

Page 36: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.12

ECOLOGY, Cement Plant and Mine Sites.Environmental Impact Proposed Mitigation Residual Impact Residual Impact

RatingDust deposition onleaves leading to loss ofvegetation productivityand health.

The planting of tree linesby Contractors duringthe construction phase toprovide local screeningin accordance withecology expert’srecommendation as amean to reduce dustemissions at the sourceduring operation. APMLwill ensure that the treesare planted to aid in theprevention of dustaccumulation on foliageoutside the plant.

Some dust emissions atthe quarry sites,associated withexcavation, etc., areinevitable, but emissionsand impacts can be keptto an acceptable level byuse of latesttechnologies and bestworking practices.Mining plan andprocedures to beimplemented per therecommendations andapproval by ecologyexpert.

Minor Adverse.

Productivity and qualityof vegetation forherbivores reduced.

In-plant road will bepaved. Mine accessroads will be clay andwill be periodicallywetted to minimize anyimpact.

Some impact isinevitable, but APMLwill make it a priority.

Minor Adverse.

Disturbance of wildlifeby noise.

Reduced at source andless than 60 dB at theplant fence.

The project site does nothave any sensitivespecies.

Not significant

Disturbance of wildlifeby human presence andactivities.

Environmentaleducational program.On-site ecologist byAPML.

There should be somehabituation to humanpresence by some non-sensitive wildlife.

Not significant

Page 37: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.13

LANDSCAPE AND VISUALEnvironmental Impact Proposed Mitigation Residual Impact Residual Impact

RatingDamage to the landscapecharacter and visualamenity due tointroduction ofincongruous features andactivities

Proper design of lightsources by establishingand effective balancebetween safety/securityand environmentalsensitivity. Sensitive anduniform (paintspecifications)coloration of cementplant and vehicles.Minimize the timebetween working andrestoration phase ofquarry

Some exposure toalternation of thelandscape character andloss of visual amenity,predominantly due tooff-site quarry activities.

Minor to moderateadverse impact

TRAFFIC AND TRANSPORTEnvironmental Impact Proposed Mitigation Residual Impact Residual Impact

RatingIncreased heavy vehiclestraffic both locally andnationally.

Maximize the use of therail network, whenavailable, for bulkdeliveries and abnormalloads. Restrictingdelivery hours to reducenoise nuisance; avoidheavy truck movementsin the night hours willbe considered whetherdeliveries should bescheduled to avoid peaktimes to reducecongestion; heavyconstruction traffic willbe subject to a trafficmanagement plan, asnecessary.

The traffic has thepotential to contribute tocongestion and lead tocomplaints due tonoise/vibration nuisanceon a local basis.However, the studyindicates that there willnot be a significantimpact.

Minor Adverse.

NOISE AND VIBRATIONEnvironmental Impact Proposed Mitigation Residual Impact Residual Impact

RatingNoise from cement plant None recommended

unless the plant andvarious installationdiffer significantly fromsimilar establishedcement plants used as areference. IFCguidelines for noise willbe followed by APML.

None expected Nil. Less than 60 dBA.

Page 38: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.14

Noise from miningactivities

Good site management;appropriate choice ofmachinery; methods ofworking; hours ofworking; efficientmaterial handling.

None expected Minor Adverse.

SOCIALEnvironmental Impact Proposed Mitigation Residual Impact Residual Impact

RatingIncreased Employment.(Positive Change)

Measures to maximizelocal employment.Recommended:

Local recruitmentand training.

Prioritization ofemployment ofProject AffectedPeople (PAP’s)

Identification oftargets of localpeople to beemployed by skilllevels.

This depends on skillsof the people. Enhancedapprenticeship/trainingfor some local peoplewhose skills could beimproved includingRecruitment Policy toextend in future tolimited sponsorship forworkers / local peoplechildren.

Major beneficial.

Increased National taxand budget (PositiveChange).

Assistance to villagersto formulate projectsand strengthenadvocacy. Money fromimproved budget can beused to realize theseobjectives. APML mayoffer skills training forimproved planning &project formulation.

Increased Regional &National Budget andsecondary impact onlocal Communities.Residual impact willdepend on effectivenessof allocation process infavour of affectedvillages. An ineffectiveprocess would causeconflict / discontent.

Major beneficial.

Electrical and otherinfrastructureimprovements (neutralor positive if realized).

APML will be self-sufficient from theNational Grid so there isno mitigation.

Potential positive impacton visual impacts due toinfrastructureimprovement.

Neutral/Minorbeneficial.

Extended and improvedroad and implicationsfor local economy(minor/moderatebeneficial).

Regulations relating toroadside andcommercial activities tobe adhered to bybusiness persons andenforced byCommunity. Monitoringof health, road safetyissue. Curative andpreventive action to betaken if issues identifiedby monitoring.

Improved opportunitiesshould be seen inincreased opportunitiesand wealth of villages. Itmay be difficult toapportion this only tothe new road or cementworks given the currentincreasingly dynamiceconomic environment.

Minor beneficial.

Page 39: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.15

Loss of Land andproperty “RUPPER”Village household andcompensation (minorbenefit/minor adverse)

An appropriatecompensation plan willbe developed and agreedupon. CompensationPlan & FrameworkDocuments will beprepared.

No negative residualimpact should beincurred by PAP’s. Theassessment shouldinclude all applicableentitlements. Monitoringprocess to review andreport.

Negligible / minorbeneficial.

Hazards associated withdevelopment of newroads from mainHighway to the cementplant and from thequarry to the cementplant.

With regards toidentified ‘high’ risks: Design measures to

ensurelandslips/falling rocksdo not cause accidents

Inclusions ofpedestrian walkwaysand crossings

Lighting, particularlyat intersections.

Planned access andparking. Risk ofaccident shall bereduced byimplementation ofeducation (road safetyawareness) programsand liaison with thelocal communities aswell as driver trainingprograms andimplementation ofnear-miss/accidentreporting procedures.Communities toconsider the need foradditional safetybylaws.

Some residual impact isexpected, but should belimited byimplementation ofaforementionedmitigation measures.

Moderate adverse –possibility severeadverse if there isdisregard for safetyissues by the road users.

7.4 Impacts during Decommissioning Phase:

Detailed assessment of environmental impacts associated with decommissioning cannotbe made at present. The plant has an expected lifespan of over 50 years and so onlygeneral principles can be established at the present time.

7.4.1 Broad the process of decommissioning is likely to give rise to impacts similar to thoseexperienced during construction phase. The methods and techniques selected are

Page 40: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.16

expected to be in accordance with national and international standards prevailing at thetime of decommissioning.

7.4.2 Decommissioning will involve following activities: Removal of all surface equipment and units; Potential removal of hard standing and surface cover; Abandonment of sub-surface utilities or filling and abandonment as appropriate; Reinstatement of the site and all project areas to pre-construction conditions. With

regards to the rehabilitation of the quarries during operation, the works shall beconducted on an on-going basis in accordance with the accepted timetable set out inthe planning proposals to the Jamaican authorities.

For the cement plant, APML will develop a site closure plan during the later stages ofproject design and maintain the plan throughout the life of the development. The planshould include arrangements for decommissioning the plant in a manner which avoidsany pollution and return the site to an acceptable state. In addition anydecommissioning plan should take into account the social and economic impacts andinclude mitigation measures where necessary.

The opportunities the site provides for long term biodiversity conservation purposesshould be investigated as part of the site closure plan. There are no identified sites ofecological significance outside the main development areas that should be affectedby decommissioning activities, though consideration will need to be given as to thelong term use of the access roads to the mines. This will depend on their future use.It may be necessary to remove the roads and “re-instate” the ground and vegetation,but maintaining vehicle access or foot access only are also possibilities.

The site closure plan and preceding rehabilitation plans will need to be reviewed andupdated in the light of experience with implementing the ecological mitigation andcompensation measures – especially the “Habitat Restoration” proposals. Thesehabitat restoration activities will need to be monitored, during the course of theproject, so that lessons can be learned and applied prior to and at the time of finalsite closure.

Overall, decommissioning activities are transitory, and are likely to be similar inmagnitude to construction impacts.

Page 41: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.17

Rehabilitation of the mine area will take place in stages during the development ofthe mine. When an area of the mine has been exploited, rehabilitation works willfollow and the success of the rehabilitation/restoration monitored so that the besttechniques can be adopted for future stages of restoration.

The decommission activities relating to the mine sites will be significantly lessintensive that those of the cement plant due to the lack of onsite plant and permanentstructures and hard-standing to be removed. It is anticipated that thedecommissioning activities will have no noticeable effect beyond that which theoperational phases experienced. Giving consideration to the effect of noise from theoperation of the mine on the landscape character, the ceasing of excavation activitiesin itself will abate the negative effects of the quarries. As such the decommissioningof the mines is anticipated to have a minor adverse effect on the landscape resources.

The restoration programmes for the mine sites, as with the cement plant, has thepotential to contribute to landscape enhancements to the baseline landscapecondition. This may involve the reforestation of the area, ground re-modelling, andpotentially the addition of landscape amenities such as the conversion of the mineinto a water body. As such, the restoration phase of the mines will have a minorbeneficial effect of the landscape resources.

Environmental Impact Proposed Mitigation Residual Impact Residual ImpactRating

Emission Prevention Development of siteclosure plan.

Undated information onrisks and requirements isavailable at site closure.

Minor beneficial

Dust emission duringground works

Water spraying of roads.Covering of vehiclescarrying dusty materials.Speed limits of vehiclesmovement.Dust emission monitoringat selected points

Dust propagation will belimited to demolition areaand not influence the localcommunity.However, workers shouldbe supplied with dustmasks.

Minor adverse

Discharge of silty orcontaminated water tosurface water.Ground contamination ofleakages from machines.

Potentially pollutingmaterials will be stored indedicated storage areas.Machines & equipmentcondition to be reviewedperiodically.Machines & equipmentwill be sited on hardsurfaces.

Ground and storm watercontamination will belimited on site by properhandling and storage ofmaterials and equipment.Storm water will be treatedin sedimentation ponds, theimpact on overall qualityof wastewater will beminor.

Minor adverse

Page 42: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.18

All storm water will go viasedimentation ponds & oilseparation.Procedures for locatingcontaminated materialduring evacuation will beestablished.Covering and damping ofexcavated materials.Appropriate storage ofcontamination material iffound

Some loss of flora & faunathat are re-colonizing themine area.

Mine Restoration Planincorporating habitatcreation and use of nativespecies

Depending on proposedfuture use of mine habitatcreation could lead tosignificant improvementfor biodiversity over valuewhen used as an activequarry.

Moderate to substantialbeneficial

Damage to the landscapecharacter and visualamenity due to introductionof incongruous featuresand activities

Restoration of the plantand mine sites including areforestation programme

Return of sites to existingto better than existingcondition

Minor beneficial

Solid waste generation Segregation and recyclingof waste and proper storagein isolation from theground

Solid waste will be passedto contractors and disposedaccording to their permits.

Minor adverse

Noise and emissiongenerated by vehicles

Traffic management plan. Local traffic congestionproblems avoided

Moderate adverse

Noise fromdecommissioning of plantand mines

Good site management;Good choice of machinery;Methods of working,including sequentialblasting;Hours of working;Efficient material handling;Construction of noisebarriers or baffle mound;Maximizing separationdistances

Until further details areknown, it is not possible topredict whether there maybe noise increase at nearbyresidential properties

N/A

Emergency situationsduring decommissioningworks

Local fire and emergencysquads available on-site.Availability of APML andcontractors inspectors onsite.

Plans to re-deploy workerswill be developed

Moderate adverse

Social Impacts – There willbe no job losses

An exit strategy should bedevised to minimize lossesand assist deployment. Itshould include options forretraining / early retirement/ assistance to job searchesand positioning /identification of jobswithin the group andpossible relocationassistance.

Plans to re-deploy workerswill be developed

Moderate adverse

Page 43: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.19

7.5 Other Mitigation Measures

7.5.1 Waste Minimization and Treatment & Disposal MeasuresThese have been discussed in Sections 7.1 and 7.2, above.

7.5.2 Natural Resource ManagementThese have been discussed in Sections 7.1 and 7.2, above.

7.5.3 Mitigation of Human Impacts

A) Economic Environment

The Project could have both positive and negative impacts on theeconomic environment.

Whilst there is significant potential for positive economic benefits of theProject, the extent to which it is likely to lead to economic developmentand or inflation depends on the Project approach to providing services toits workers (e.g. transport, canteen services, and in-house medical care).

Mitigation: The Company needs to consider the Socio-economic baselinecontext and consult community leaders and civil society when makingeconomic development agreements.

B) Employment, Livelihoods and Income Generating ActivitiesAccess to Project Employment is a key priority for local stakeholders.

In both construction and operational phases there is an opportunity formaximizing positive impacts of the Company on local employment throughinvolving unskilled (and where possible skilled) labour from all Projectcommunities. However, although the generation of employmentopportunities resulting from Project activities is expected as a positiveimpact, there is a risk that conflicts could arise between local inhabitantsand new comers or outsiders over such employment opportunities.Furthermore there is high risk that, unless Project employment by theCompany and contractors is managed appropriately, nepotism wouldinfluence the recruitment procedure, meaning that people without

Page 44: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.20

connections would not get access to Project opportunities – namelyemployment and other livelihood benefits. This could lead to a moderaterisk of social conflict.

Mitigation Measures:The Company should work actively to promote local access to Projectemployment in both the construction and the operations phases.

The Company needs to identify the skills that it needs for its constructionand operations phases that could be provided as part of a community skillsdevelopment program providing basic vocational training in thecommunities.

7.5.4 Occupational Safety & Health Measures

Construction and operational activities could expose workers to health andsafety risks. In particular, the following activities could have negativehealth impacts: noise and dust; working with heavy equipment (strains andaccidents); working in confined spaces (fumes could mean respiratoryimpacts), heavy lifting, storage, handling and use of dangerous substancesand waste (strains and accident risks), and working under noisy conditions(hearing and stress/psychological impacts). Excavations andtransportation of materials may cause further health and safety negativeimpacts.

Occupational health and emergency health services for both theconstruction labour force and operations employees will be at risk ofnegative health impacts which cannot be quantified, until clear plansemerge. The need for an ongoing, proactive workers health and safety planapplies for the full Life Cycle of the Project, particularly with regard to theoperational phase for the employees.

Without an operational/fully functional Health and Safety plan and healthtraining for workers the risks for worker health and safety are high.

Page 45: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.21

Mitigation Measures:The Company needs to demonstrate a best practice occupational healthscheme, and share plans for the health maintenance and emergencyservices for their employees so that local health infrastructure capacity isnot put under greater strain. An important mitigation is the forming ofpartnerships of understanding and relationship building with local healthcare providers.

Company’s contractors should adopt strict construction and operationpractices with best technology and health and safety training to ensure thesafety of its workers.

7.6 Mitigation Measures for Green House Gases

The Carbon dioxide (CO2) emissions from Portland cement manufacturing are generatedby two mechanisms. As with most high-temperature, energy-intensive industrialprocesses, combustion of fuels to generate process energy releases substantial quantitiesof CO2. Substantial quantities of CO2 also are generated through calcining of limestone orother calcareous material. This calcining process thermally decomposes CaCO3 to CaO andCO2. Typically, Portland cement contains the equivalent of about 63.5 percent CaO.

Consequently about 1.135 units of CaCO3 are required to produce 1 unit of cement, andthe amount of CO2 released in the calcining process is about 500 kilograms (kg) per tonneof Portland cement produced. Total CO2 emissions from the pyro-process depend onenergy consumption and generally fall in the range of 0.85 to 1.35 tonnes of CO2 per tonneof clinker. IFC EHS Guidelines for Cement and Lime Manufacturing (April 30, 2007), inTable-7.3 (presented below) indicates the range of CO2 output from cement plant.

Page 46: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.22

Table – 7.3

The other sources of CO2 emissions stemming from cement manufacturing operationsinclude transportation equipment used in the mining and transport of raw and finishedmaterials. The direct CO2 emission intensity of fuels depends on the carbon content ofthe fuel which varies by type of fuel and further may vary within a given fuel type. Theemission intensity of coals, for example, will vary depending on its geologic source.

In general, emissions of CO2 from the cement manufacturing sector can be reduced by:

• Improving the energy efficiency of the process,• Shifting to a more energy efficient process (e.g. from wet to dry process and use

of preheater/precalciner process),• Replacing high carbon fuels with low carbon fuels,• Applying lower clinker/cement ratio (increasing the ratio additives/cement):

blended cements, etc.

The technology to be used by APML is efficient, for the plant capacity, using dry processand preheater/precalciner process. Coal will be used as fuel.

Page 47: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.23

Forests are both a part of the global warming problem and part of the solution. Unlikeother emission sectors, forests have the unique capacity to remove carbon dioxide (CO2)from the atmosphere and store this gas as carbon for long periods of time in their biomass(e.g., trunks, branches, leaves, roots, etc.).

While forests are a natural CO2 reservoir, or “sink”, they are also a source of CO2

emissions. On a global level, forests are responsible for roughly 20 – 25% of overall CO2

emissions, largely due to conversion of forestland and the associated depletion of carbonstocks. When forests are disturbed through events such as conversion to development oragriculture, fire or harvest, the carbon that is stored in tree biomass is emitted to theatmosphere. When harvested for timber, a percentage of forest carbon is stored in woodproducts for periods of time. These wood products decay over time, releasing CO2 at anaverage decay rate of 2% annually.

The Project can reduce greenhouse gas emission through activities that increase forestcarbon stocks on the landscape in concession area.

In order to mitigation GHG generation, APML can support afforestation project inconcession area through the Divisional Forest Department, by developing nurseries andprovision of samplings.

7.7 Coal Transportation

Coal unloading at Port Qasim and transportation to cement plant site has the potential togenerate fugitive dust. The fugitive dust can be reduced by:

Importing coal without fines and in larger sizes. Importing coal with moisture content ranging at 7% to 8%. This will also

lessen fire hazard. Using tarpaulin or other covers during transportation.

Page 48: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.24

7.8 Environmental Monitoring

7.8.1 Ambient Air QualityA continuous ambient air quality monitoring system and program should be installed atleast 2-3 months prior to the start of main construction activities.

It is recommended that the monitoring program should cover as a minimum, the chemicalparameters under the environmental legal requirement.

Meteorological data should be recorded in parallel to air quality monitoring at the samereference location.

Monitoring parameters and frequency are to be carried out according to the requirementof Pakistan Environment Protection Act, 1997, under Category-A “Guidelines for Self-Monitoring and Reporting by Industry (SMART), [Copy attached as Appendix – 7.1].Ambient air quality monitoring should be carried out biannually, at least.

Monitoring methods are presented in Appendix – 7.1. Recommended monitoringequipment and instruments (including costs) and recommended monitoring methods arepresented in Appendix – 7.1.

7.8.2 Stack EmissionsArrangement for regular stack monitoring of NOx, SO2, CO and PM should be in place

7.8.3 NoiseAn ambient noise measurement program should be instituted upon commissioning of theproject. The monitoring program should consider the noise limits during day-time andnight-time at the closest point of public contact.

7.8.4 Wastewater/Thermal DischargeTreated wastewater and cooling water will be monitored as required by applicableenvironmental regulations.

Page 49: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.25

7.8.5 Assigning responsibility for implementation (by name or position)In order to ensure implementation and effective operation of the EnvironmentalManagement Plan (EMP), it is of utmost importance that responsibilities be fixed tospecific persons so that each one of them should be answerable in case of lapse ormishap. Accordingly, hereunder the same responsibilities have been described:

Official Concerned Responsibility

1- Works Manager

i- Ultimate in-charge and responsible for all the

operations of Environmental Management Plan

(E.M.P) set up.

ii- He will be responsible to ensure smooth

functioning of the E.M.P system.

iii- Daily progress on the state of the

environmental status will be reported to him in

writing by the Shift Production Foremen.

iv- All other E.M.P matters, issues and problems

will be reported to him (for rectification) by the

Shift Production Foremen.

v- He will work as bridge between the

Government concerned authorities and the

senior most management of the project.

vi- He will be answerable to the higher

management in all matters relating to E.M.P.

and report at least monthly about the state of

the E.M.P. operations.

2- Shift Production Foremen

i- During his shift timings, he will be responsible to

ensure smooth functioning of the entire E.M.P.

ii- He will be responsible to rectify any problem

regarding environmental matter.

iii- He will directly report to the Plant Manager. All

matters relating to E.M.P. on daily basis.

Page 50: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.26

3- Plant Operator

i- He will be responsible to operate effluent

treatment plant and look after gaseous,

Production Manager and sound levels monitoring

systems.

ii- He will maintain all records of monitoring of the

entire elements of the E.M.P.

iii- He will report to the Shift Production Foremen

about matters relating to EM.P. Operations on

daily basis and earlier if so required.

4- Laboratory Chemist

i- He will be responsible to carry out all laboratory

testing of waste water at all levels.

ii- He will perform all other lab. testing as may be

required from time to time in the interest of

effective operation of the E.M.P.

iii- He will maintain records of the entire E.M.P.

operations.

He will daily report to the Shift Engineer/In-charge

about the matters relating to the E.M.P. operations.

7.7.6 Reporting and Reviewing ProceduresEnvironmental monitoring program, as described above, will be the guiding principle andreporting will be done regularly on monthly basis according to the formats of the SMARTprogram as annexed Appendix – 7.1.

At the plant level all the monitored data will be reviewed and scrutinized at the level ofProduction Manager & Risk Manager and on monthly basis at the Works Manager level.The same review of the data will be done twice at the level of the Managing Director. Thedata will be documented according to appropriate format at the plant level. Discrepancieswill be duly addressed to.

Page 51: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.27

For presentation of the data to the concerned agencies - Environmental ProtectionDepartment, Government of Punjab, Lahore and Environmental Protection Agency,Government of Pakistan, Islamabad; format presented as Appendix – 7.1, will be used

7.9 Training Needs

In order to effectively operate the EMP all the staff to be engaged in this activity shouldbe trained extensively.

All the environment management staff to be engaged for operating effluents treatmentplant, monitoring and testing should be duly trained. Laboratory chemist should betrained in all operations of laboratory testing of the effluents and other relevantmaterials/samples. He should be trained in applying analytical methods/techniques oftesting, data processing, interpretation and reporting. He should know the local laws,rules and regulations as applicable to the testing of effluents.

The person to monitor gaseous emissions, PM and noise levels should be extensivelytrained to handle his job capably. Training program should include use of monitoringinstruments, data generation, processing, interpretation, recording and presentation.

7.10 Social Management Plan

7.10.1 Recommendations and Mitigation Measures(The following recommendations are made preliminary and will be adjusted based on theresults of the Social Impact Assessment process.)

Based on the initial benchmark study, the following preliminary recommendations will befurther adjusted according to the results of the Social Impact Assessment process to beconducted at a later stage:

The management of the Project can capitalize on the positive attitude of thepeople of area towards proposed Project by offering them maximum employmentopportunities at the construction stage and any stage of operational phase of thepower plant.

Page 52: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 7, Environmental & Social Management Plan Page – 7.28

Insufficient and inadequate socio-economic structure of the community of thearea also provides ample opportunities to Company management to winsympathies of local people in their favour, by introducing meaningful andmanageable plan of community development.

Aggressive and comprehensive plantation plan can also lessen fear of local peopletowards environmental issues.

Plant management can explore direct or indirect chances of female employmentopportunities. Such efforts can be fruitful to minimize negative social impacts.

Sustainable development approach through conservation of natural resourceswould be the best strategy to compensate negative socio- environmental impacts.

Plant management should offer technical training opportunities to the local youth,if possible, to remove relative sense of deprivation.

Social responsible attitude and stewardship of company management towardslocal people and resources can make project people friendly.

Prior to action of the Project installation a comprehensive awareness campaignmay be launched at masses level to avoid any conflict.

To avoid any political, ethnic and value conflict, the administration of the plantmay win the confidence of local powerful elites, authorities, leaders and interestgroups by adopting informal confidence building measures.

On the basis of the findings of this study, it is concluded that the proposed Cement Plantwill not have any adverse impacts on the local population, or any segment ofenvironment or aquatic environment around provided the recommendations made andrecommended mitigation measures are implemented by the Plant Management inletter and spirit.

Twice annual all out environmental monitoring of the facility by a third party will winconfidence of public, EPA, and all other stakeholders about the environmentally safepractices to be followed during regular operations of the cement plant.

Page 53: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 8, Grievance Redressal Mechanism & Resettlement Action Plan Page – 8.1

8.0 ENVIRONMENT PROTECTION & GRIEVANCE REDRESSING MECHANISM-FORMAL ANDINFORMAL CHANNELS AND RESETTMENT ACTION PLAN

8.1 Formal Channel

8.1.1 Environmental LegislationThe Pakistan Environmental Act (PEPA) -1997, after amendment by the ProvincialAssembly of the Punjab vide its Bill No. 56 of 2011 now called “The Punjab EnvironmentalProtection (Amendment) Act 2011”, provides a complete code of conduct for addressinggrievances stemming from damages to any sector of the environment from the projectactivities.

The project is required to operate at least 95 % of its operational period in strictcompliance with the required emission standards of Pakistan as provided in the PakistanEnvironmental Protection Act 1997 and the National Environmental Quality Standards.This ensures that the project proponent is legally bound to observe all legal requirementsto avoid damaging the environment around the project.

8.1.2 Pakistan Environmental Act and Environmental ManagementThe Punjab Environmental Protection (Amendment) Act 2011 covers aspects related tothe protection, conservation, rehabilitation and improvement of the environment and theprevention, control of pollution and promotion of sustainable development. The PunjabEnvironmental Protection (Amendment) Act [PEP(A)A] 2011, establishes completeregulatory and monitoring bodies, policies, rules, regulations and national environmentalquality standards. To ensure enforcement, the act establishes regulating bodies i.e.Punjab Environmental Protection Council (PEPC) and responsible bodies i.e. PunjabEnvironmental Protection Department (Punjab EPA) at Provincial level. The act extendsto the whole of Punjab Province.

Punjab EPD has the power to arrest without warrant any person against whom reasonablesuspicion exists of his having been involved in an offence under the [PEP(A)A] 2011, andenter, inspect and search without warrant any premises, vehicle or vessel. It also provides

Page 54: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 8, Grievance Redressal Mechanism & Resettlement Action Plan Page – 8.2

for seizing any plant, machinery, equipment, vehicle or substance, record or document.[PEP(A)A] 2011 also provides the power to summon and enforce the attendance of anyperson and issuance of Environmental Protection Order, PO 16, an EnvironmentalProtection Order (EPO), in relation to a person who is contravening a provision of the[PEP(A)A] 2011.

8.1.3 Enforcement of Pakistan Environmental Protection Act 1997 and The PunjabEnvironmental Protection (Amendment) Act [PEP(A)A ] 2011 and LiabilityThe Government of Pakistan is bound to protect the environment in accordance with itsinternational commitments under various conventions and treaties it has signed orratified. The Pakistan Environmental Protection Act (PEPA)-1997 translates thesecommitments into a compliance programme for the industrial establishments. Non-compliance to these commitments may results in loss of credibility, popularity and evenfinancial aid from the international forums.

The Pak-EPA is directly responsible for enforcement of rules and regulation relating toenvironmental management/protection in the areas controlled by the FederalGovernment including Islamabad and FATA. While the Punjab EPD, after the 18th

Amendment in the Constitution of Pakistan and of late under The Punjab EnvironmentalProtection (Amendment) Act [PEP(A)A] 2011 is responsible for implementation of theseRules and Regulations within the province.

Environmental Protection Agencies shall exist at the Provincial level. The [PEP(A)A ] 2011requires:

That no person (including companies) under its purview will discharge or emit anyeffluent or noise in contravention of the National Environmental QualityStandards.

That no proponent of a project shall commence construction or operation unlesshe has filed with the PEPA, an Environmental Assessment Report according to thesensitivity of the project or where the project is likely to cause an adverseenvironmental impact.

Page 55: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 8, Grievance Redressal Mechanism & Resettlement Action Plan Page – 8.3

That no person may dispose of waste on public land or on highway on or a landowned or administrated by a local council, unless done in accordance with theprovisions of The Punjab Environmental Protection (Amendment) Act [PEP(A)A ]2011.

The following section of the [PEP(A)A] 2011 further clarifies the mechanism ofEnvironmental Management and Grievance Redress Mechanism.

Section 11:“Prohibition of certain discharges or emissions.(1) Subject to the provisions of this Act and the rules and regulations no person shalldischarge or emit or allow the discharge or emission of any effluent or waste or airpollutant or noise in an amount, concentration or level which is in excess of the NationalEnvironmental Quality Standards or, where applicable, the standards established undersub-clause (I) of clause (g) of sub-section (1) of section 6.”

“(2) The Provincial Government may levy a pollution charge on any person whocontravenes or fails to comply with the provisions of sub-section (1), to be calculated atsuch rate, and collected in accordance with such procedure as may be prescribed.”

Section 12:“Initial environmental examination and environmental impact assessment.(1) No proponent of a project shall commence construction or operation unless he hasfiled with the PEPA an environmental impact assessment, and has obtained from thisGovernment Agency approval in respect thereof”.

Section 16:

Environmental Protection Order“(1) Where the PEPA is satisfied that the discharge or emission of any effluent, waste, airpollutant or noise, or the disposal of waste, or the handling of hazardous substances, orany other act or omission is likely to occur, or is occurring, or has occurred, in violation ofthe provisions of this Act, rules or regulations or of the conditions of a license, and is likelyto cause, or is causing or has caused an adverse environmental effect, the PEPA may, after

Page 56: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 8, Grievance Redressal Mechanism & Resettlement Action Plan Page – 8.4

giving the person responsible for such discharge, emission, disposal, handling, act oromission an opportunity of being heard, by order direct such person to take suchmeasures that the Agency may consider necessary within such period as may be specifiedin the order.”“(2) In particular and without prejudice to the generality of the foregoing power, suchmeasures may include;

(a) immediate stoppage, preventing, lessening or controlling the discharge, emission,disposal, handling, act or omission, or to minimize or remedy the adverseenvironmental effect;

(b) installation, replacement or alteration of any equipment or thing to eliminate,control or abate on a permanent or temporary basis, such discharge, emission,disposal, handling, act or omission;

(c) action to remove or otherwise dispose of the effluent, waste, air pollutant, noise, orhazardous substances; and

(d) action to restore the environment to the condition existing prior to such discharge,disposal, handling, act or omission, or as close to such condition as may bereasonable in the circumstances, to the satisfaction of the Agency.”

Section 17:Penalties:“(1) Whoever contravenes or fails to comply with the provisions of Sections 11, 12, 13 orSection 16 or any order issued there under shall be punishable with fine which may extendto five million rupees, and in the case of a continuing contravention or failure, with anadditional fine which may extend to five hundred thousand rupees for every day duringwhich such contravention or failure continues:

Provided that if contravention of the provisions of section 11 also constitutescontravention of the provisions of section 15, such contravention shall bepunishable under sub-section (2) only.”

“(2) Whoever contravenes or fails to comply with the provisions of section 14 or 15 or anyrule or regulation or conditions of any license, any order or direction, issued by the PunjabEnvironmental Protection Council or the Provincial Agency, shall be punishable with finewhich may extend to five hundred thousand rupees, and in case of continuing

Page 57: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 8, Grievance Redressal Mechanism & Resettlement Action Plan Page – 8.5

contravention or failure with an additional fine which extend to five thousand rupees forevery day during which such contravention or failure continues.

Contraventions of the provisions of the Punjab Environmental Protection(Amendment) Act [PEP(A)A ] 201 is punishable with imprisonment extending upto five years, or with fine extending up to one million or with both. Where anoffence is committed by a company every Chief Executive Officer (CEO) and thecompany shall be deem guilty of the offence. Action can even be taken againstGovernment Agencies and Local Authorities.”

Government may also constitute an Environmental Tribunal to hear cases relating to thePEPA-1997. The tribunal may only hear cases when the complaint is made in writing byPak-EPA, or Local Council or any aggrieved person who has given at least thirty days noticeto PEPA of the offence and of his intension to make a complaint to the Tribunal. TheTribunal may also hear appeals from the Agency and appeals from the tribunal shall go tothe High Court.

In order to resolve the disputes relating to the environment issues, EnvironmentalTribunal Rules 1999 have been promulgated. In trying the offences, the tribunal has tofollow the Code of Criminal Procedures 1898. The tribunal shall send the copies of hisorders to the parties concerned and the Director General of the PEPA. The Tribunal shalldispose of its proceedings within 60 days. An appeal to the Tribunal, accompanying a copyof the impugned order, copies of the documents relied and prescribed fees, shall be sentto the Registrar by the appellant. Generally the proceedings of the Tribunal shall be open.“

8.2 Grievance Redress Mechanism- Informal

8.2.1 Procedure for Redress of Grievances

Suggested procedures to be adopted for the redress of the grievances are given below:

Project affectee will submit his/her application to the Field Implementation Unit for

Page 58: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 8, Grievance Redressal Mechanism & Resettlement Action Plan Page – 8.6

consideration. Within 15 days of the receipt of the complaint, action will be taken upfor redressal of the grievance. Wherever policy matters are involved, the case will bereferred to the appropriate authority or committee appointed by the Project, todecide the matter.

In case some response on the complaint is not received within 15 days of the receiptof the complaint, the complainant may also send a reminder with 15 days notice totake legal remedial measures.

In case the matter has been decided but the complainant is not satisfied, he/she maygo to the court of law.

In case of such eventualities, all affected persons should be exempted from legal andadministrative fees made/paid/incurred pursuant to the grievance redressalprocedures.

All complaints received in writing or written when received verbally will be properlyrecorded and documented.

8.2.2 Proposed Mechanism for Grievance RedressUnder the Project the following will be established or appointed to ensure timely andeffective handling of grievances:

A Public Complaints Unit (PCU), which will be responsible to receive, log, and resolvecomplaints; and,

A Grievance Redress Committee (GRC), responsible to oversee the functioning of thePCU as well as the final non-judicial authority on resolving grievances that cannot beresolved by PCU;

Grievance Focal Points (GFPs) having educated people from each community that canbe approached by the community members for their grievances against the Project.The GFPs will be provided training by the Project in facilitating grievance redress.

Details of the proposed mechanism are given below.

Page 59: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 8, Grievance Redressal Mechanism & Resettlement Action Plan Page – 8.7

PCU – Function and StructurePCU will be set up as part of the Risk Management Department of the Project. A seniorofficial with experience in community and public liaison will lead the unit. Two assistants,one male and one female will be responsible for coordinating correspondence andpreparing documentation work and will assist the senior official. The senior official will beresponsible to review all documentation. The PCU will be responsible to receive, log, andresolve grievances. Given that the female community members have restricted mobilityoutside of their homes, the female PCU staff will be required to undertake visits to thelocal communities. The frequency of visits will depend on the nature and magnitude ofactivity in an area and the frequency of grievances.

GRC – Function and StructureThe GRC will function as an independent body that will regulate PCU and the grievanceredress process. It will comprise of:

Works Manager of the Project. Senior Engineer that is responsible to oversee the contractors. Two literate representatives from the communities residing near the project site; A representative of the local government. Senior member from the local civil society with experience in community relations. A female member from the local civil society.

The GRC will meet once every three months to review the performance of the PCU; thefrequency can be changed depending on the nature and frequency of grievances received.The performance will be gauged in terms of the effectiveness and the timeliness withwhich grievances were managed. In case there are any unresolved or pending issues, theGRC will deliberate on mechanisms to resolve those and come up with solutionsacceptable to all concerned.

Grievance Focal PointsThe GFPs will be literate people from each community that will facilitate their communitymembers in reporting grievances from the Project. The GFPs will be provided training by

Page 60: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 8, Grievance Redressal Mechanism & Resettlement Action Plan Page – 8.8

the Project in facilitating grievance redress. Each community will have a male and femaleGFP appointed for this purpose.

Procedure of Filing and Resolving GrievancesGrievances will be logged and resolved in the following steps:

Step 1: Receive and Acknowledge ComplaintOnce the PCU receives a complaint, which could be the complainant giving it inperson, via letter or email, through phone call, or through a GFP, an acknowledgementof receipt of the complaint has to be sent within two working days to the complainant.The complainant will be issued a unique complaint tracking number for their andPCU’s record.

Step 2: InvestigationPCU will work to understand the cause of the grievance for which the PCU may needto contact the complainant again and obtain details. The PCU will be required tocomplete preliminary investigations within five working days of receiving thecomplaint and send a response to the complainant documenting the results of theirinvestigations and what the PCU plans to do ahead.

Step 3: Resolution through PCUOnce the PCU have investigated a grievance, it will share with the complainant theproposed course of action to resolve the complaint, should PCU believe any to benecessary. If the complainant considers the grievance to be satisfactorily resolved, thePCU will log the complaint as resolved in their records. In case the grievance remainsunresolved it will be reassessed and GRC will have further dialogue with thecomplainant to discuss if there are any further steps, which may be taken to reach amutually agreed resolution to the problem.

For minor grievances, Steps 1, 2 and 3 or Steps 2 and 3 can be merged.

Step 4: Resolution through GRCIn case the PCU is unable to resolve the issue, the matter will be referred to GRC. Allcomplaints that could not be resolved within four weeks will by default be referred to

Page 61: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 8, Grievance Redressal Mechanism & Resettlement Action Plan Page – 8.9

GRC. However, the complainant or the PCU can convene the GRC at any point in time,depending on the nature and urgency of the issue.

8.2.3 Operating Principles for PCUThe PCU will operate on the principles of transparency, approachability andaccountability. To achieve these, the PCU will be required to:

Be equipped to handle grievances in the local languages. Be equipped to work through all possible modes of communication, such as, emails,

surface mail and face-to-face meetings at project site or requiring visits. Employ female staff, preferably from the nearby communities, to oversee complaints

and issues of the female community members. Maintain a log of all grievances, with record of the date and time of the complaint

logged and stakeholder information, such as, name, designation and contact details; Provide opportunity to the stakeholder to revert with their comments on the

proposed plan of action. Keep the stakeholder informed of the progress in grievance resolution. Obtain stakeholder consent on the mechanism proposed to redress the grievance and

document consent, and, Maintain confidentiality of the stakeholder, if requested so.

Stages of GrievancesOnce a grievance is logged with the PCU, it could acquire the following stages:

Stage 1: it is resolved by the PCU or if not PCU, by the GRC;Stage 2: If the stakeholders are still not satisfied, they can proceed through localjudicial proceedings.

AwarenessThe stakeholders will be informed of the establishment of the PCU, GRC and GFPs througha short and intensive awareness campaign. Under the awareness campaign, theproponent will share:

Page 62: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 8, Grievance Redressal Mechanism & Resettlement Action Plan Page – 8.10

Objective, function and the responsibilities of the PCU, GRC and GFPs; Means of accessing the PCU and the mechanics of registering a grievance at the

PCU, GRC and GFPs; Operating principles of the PCU, GRC and GFPs; and, Contact details. Additional awareness campaigns may be organized, if necessary

8.3 Compensation for Environmental Damages

First, according to The Punjab Environmental Protection (Amendment) Act[PEP(A)A] 2011, the likely damages to be caused to any sector of the environmentor property or else will be paid to the affected parties.

Second, under The Punjab Environmental Protection (Amendment) Act [PEP(A)A]2011, the PEPA and the Environment Tribunal can legally prosecute the projectproponent for the damages to occur from the pollution generation from theproject.

There is complete legal cover to address issues related to compensation for anyenvironmental damage arising out of project activity. However, to address any such issuesmore expeditiously, the project administration will have a local committee as an InformalMechanism.

This informal mechanism will provide convenient, quick and cost effective decisions forcompensation against any environmental damages that occur from the project activity.This informal mechanism will also build confidence between the project administrationand public and safeguard the interests of both the project and the public at large.

Page 63: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 8, Grievance Redressal Mechanism & Resettlement Action Plan Page – 8.11

8.4 Resettlement Action Plan (RAP)

This section describes the Resettlement Action Plan (RAP) for the APML cement project.The RAP provides a framework for addressing and reviewing compliance with agreedroles, responsibilities and activities related to resettlement.

This resettlement definition reflects the World Bank terminology whereby resettlementcovers all direct economic and social losses resulting from land taking and restriction ofaccess by the project. The underlying assumption for the RAP is that efforts will be madeto improve the livelihoods and standards of living for all projects affected persons or atleast to restore them to pre-project levels.

8.5 Resettlement Principles and Objectives

The main resettlement principles and procedures that are applicable to the Project arethe following:

Resettlement will be minimized as much as possible. Where land acquisition isunavoidable, the project will be designed to minimizee adverse impacts on thepoorest.

Project Affected People (PAP) will be compensated or at least restored to pre-projectlevels. All the PAPs residing in, or cultivating land, or having rights over resourceswithin the project area will be entitled to compensation. All previous claims andunresolved issues related to resettlement or compensation in the area of eachcontract package, including outstanding claims arising, will be resolved in accordancewith applicable Pakistan Laws and regulations, prior to initiating any new landacquisition measures on the respective contract package. In all cases the World Bank’sOperational Directive 4.12 will supersede national laws in resolving issues relating tocompensation:

Lack of formal legal land title is not a bar to compensation or rehabilitationassistance under the Project.

Page 64: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 8, Grievance Redressal Mechanism & Resettlement Action Plan Page – 8.12

Land for Land is an option for compensation in the case of loss of land. In theabsence of replacement land, cash compensation for the property acquired willbe paid at its replacement value in addition to any transaction costs.

Each PAP is entitled to receive assistance to restore income and livelihood to apre-project standard, and all vulnerable affected people are entitled to assistanceto improve their income and livelihood.

All PAPs will be informed and consulted on compensation and other entitlements,relocation programs and income restoration assistance.

Compensation and income restoration programs will be carried out with equalconsideration for women and men. Particular attention will be paid to the rightsof women, widows, orphans, the elderly, other vulnerable people and group suchas indigenous people and religious and cultural minorities. Appropriate andsufficient assistance will be provided to help them improve their socioeconomicstatus.

PAPs social and cultural institution will be protected along with common propertyresources. Community and public services will be provided to relocatedcommunities.

The resettlement transition period will be minimized and case compensation willbe provided to the PAPs prior to the expected start data of works in the relevantcontract package/s.

It is recommended that proponent (APML) should establish a committee for theResettlement/Compensation of Project Affected Persons, conforming of the following:

APML Country Manager or an authorized representative of APML District Environmental Officer Deputy Director of Mines & Minerals, Chakwal Concerned Revenue Officer of the District

Page 65: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 8, Grievance Redressal Mechanism & Resettlement Action Plan Page – 8.13

Representative of the Affected Persons Elected Councilor of the Area

The committee will recommend all entitlements (in totality) to be made to the ProjectAffected Persons (PAPs) in connection with resettlement / compensation before the cut-off date.

Page 66: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 9, Public Consultation Page – 9.1

9.0 PUBLIC/STAKEHOLDRS CONSULTATIONS (PCs)

Public/Stakeholder consultation is a means of involving all primary and secondarystakeholders in the project’s decision-making process in order to address their concerns,improve project design, and give the project legitimacy. Stakeholder consultation, ifconducted in a participatory and objective manner, is a means of enhancing projectsustainability. Community input (both of knowledge and values) on socioeconomic andenvironmental issues can greatly enhance the quality of decision-making. Stakeholderconsultation was therefore conducted in the project area not only to satisfy the legalrequirements of the EIA process but also to improve and enhance the social andenvironmental design of the project.

To determine the cultural and social factors associated with the construction andoperation of the proposed limestone quarry/mine and cement plant, members of thecommunities in the general vicinity of the project were interviewed. These wereundertaken to ascertain information to satisfy the following factors:

9.1 Objectives of Stakeholders Consultations

The process of public participation and consultation was endorsed in the United NationsConference on the Environment and Development (UNCED) in 1992, through one of thekey documents of the conference named as Agenda 21. Agenda 21 is a comprehensivestrategy for global action on sustainable development and deals with issues regardinghuman interaction with the environment. It emphasizes the role of public participation inenvironmental decision-making for the achievement of sustainable development.

The study was carried out with the broad objective to evaluate the impact of the projecton the local population through public consultation process. The specific impactassessment aims were:

Promote better understanding of the project, its objective, and its likely impact. Identify and address concerns of all interested and affected parties of project area.

Page 67: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 9, Public Consultation Page – 9.2

Provide a means to identify and resolve issues before plans are finalized andpotentially costly delays development commences, thus avoiding public anger andresentment.

Encourage transparency and inculcate trust among various stakeholders to promotecooperation and partnership with the communities and local leadership.

9.2 Punjab Environmental Protection Act 1997 (Amended 2012)

Public Consultation is mandated under Pakistan’s Environmental Law. The ProvincialAgency, under Regulation-6 of the IEE-EIA Regulations 2000, has issued a set of guidelinesof general applicability and sectorial guidelines indicating specific assessmentrequirements. This includes Guidelines for Public Consultation, 1997 (the ‘Guidelines’),that are summarized below:

Objectives of Public InvolvementTo inform stakeholders about the proposed project, to provide an opportunity forthose otherwise unrepresented to present their views and values, providing bettertransparency and accountability in decision making, creating a sense of ownershipwith the stakeholders;

StakeholdersPeople who may be directly or indirectly affected by a proposal will clearly be thefocus of public involvement. Those who are directly affected may be projectbeneficiaries, those likely to be adversely affected, or other stakeholders. Theidentification of those indirectly affected is more difficult, and to some extent it willbe a subjective judgment. For this reason it is good practice to have a very widedefinition of who should be involved and to include any person or group who thinksthat they have an interest. Sometimes it may be necessary to consult with arepresentative from a particular interest group. In such cases the choice ofrepresentative should be left to the group itself. Consultation should include not onlythose likely to be affected, positively or negatively, by the outcome of a proposal, butshould also include those who can affect the outcome of a proposal.

Page 68: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 9, Public Consultation Page – 9.3

In particular of this project all the stakeholders were consulted during theconsultation process.

MechanismProvide sufficient relevant information in a form that is easily understood by non-experts (without being simplistic or insulting), allow sufficient time for stakeholdersto read, discuss, consider the information and its implications and to present theirviews, responses should be provided to issues and problems raised or commentsmade by stakeholders, selection of venues and timings of events should encouragemaximum attendance.

In particular of this project all the stakeholders were well informed for individual andgroup discussions.

Timing and FrequencyPlanning for the public consultation program needs to begin at a very early stage;ideally it should commence at the screening stage of the proposal and continuethroughout the EIA process;

Consultation ToolsSome specific consultation tools that can be used for conducting consultationsinclude; focus group meetings, needs assessment, semi-structured interviews;community meetings and workshops;

Important ConsiderationsThe development of a public involvement program typically involved consideration ofthe following issues:

objectives of the proposal and the study; identification of stakeholders; identification of appropriate techniques to consult with the stakeholders; identification of approaches to ensure feedback to involved stakeholders; and mechanisms to ensure stakeholders consideration are taken into account.

Page 69: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 9, Public Consultation Page – 9.4

9.3 Consultation Process

Primary stakeholders were consulted during informal and formal meetings held in theproject area. The consultation process was carried out in the Urdu language. During thesemeetings a simple, non-technical, description of the project was given, with an overviewof the project’s likely human and environmental impact. This was followed by an opendiscussion allowing participants to voice their concerns and opinions. In addition toproviding communities with information on the proposed project, their feedback wasdocumented during the primary stakeholder consultation. The issues and suggestionsraised were recorded in field notes for analysis, and interpretation.

By reaching out to a wider segment of the population and using various communicationtools such as participatory needs assessment, community consultation meetings, focusgroup discussions, in-depth interviews, and participatory rural appraisal EIA involved thecommunity in active decision-making. This process will continue even after this EIA hasbeen submitted, as well as during future EIA in which similar tools will be used to createconsensus among stakeholders on specific environmental and social issues.

In the Secondary stakeholder consultations were more formal as they involvedgovernment representatives and local organizations, consulted during face-to-facemeetings. They were briefed on the EIA process, the project design, and the potentialnegative and positive impact of the project on the area’s environment and communities.It was important not to raise community expectations unnecessarily or unrealisticallyduring the stakeholder consultation meetings in order to avoid undue conflict withcommunity’s leaders or local administrators. The issues recorded in the consultationprocess were examined, validated, and addressed in the EIA report.

9.4 Points Discussed

Following points were discussed during the public consultations:

Project components, its activities and impacts. Needs, priorities and reactions of the affected population regarding the

proposed Project.

Page 70: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 9, Public Consultation Page – 9.5

Grievances redress procedures. Compensation framework for the Project affectees. Role of the affectees in implementation of the project.

9.5 Stakeholder Consultation Technique and Results/ Comments

In recognition of the diversity of views within any community, it is very important toobtain a clear understanding of the different stakeholders and to analyze their capacityand willingness to be involved in some or all of the project and its planning process. It isimportant to be aware of how different relations can distort participation. It is alsoimportant to examine how community skills, resources, and ‘local knowledge’ can beapplied to improve project design and implementation. All of this can be achieved bycareful use of the various tools of Stakeholder Consultation.

In the consultation process for EIA, following key stakeholders were consulted: Local communities, Men Community’s elders attended meetings.

Participants from following four (4) villages were consulted:Table – 9.1

VILLAGES INVOLVED FOR PUBLIC CONSULTANTION

Village Population BoysSchool

GirlsSchool Collage Vocational

InstituteDispensary/

Hospital

Khajula 15,000 Present NO NO NO Present

Dulmial 20,000 Present Present Privatecollage NO Present

Tatral 9,000 NO NO NO NO NO

Maghal 6,000 NO NO NO NO NO

Meetings with stakeholders consisted of community consultation meetings, focus groupdiscussions, and in-depth interviews and limited focus-group discussions. The location ofthe meetings, the process followed, and the outcomes are discussed in this section.

Page 71: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 9, Public Consultation Page – 9.6

Table – 9.2

Name of VillageLevel of Awareness

(%)

High +ve Medium +ve Low +veDulmial 80 12 8Tatral Kahoon 71 19 10Khajula 79 16 5Maghal 75 14 11

Note: +ve means positive

Table – 9.3Number of Stakeholders Participed

Sr. No. Date Location/Venue No. of Participants

1. 14-09-15 Dulmial 72

2. 15-09-15 Tatral Kahoon 83

3. 16-09-15 Khajula & Maghal 22

Table – 9.4Participants during the Public Consultations & Concern

Date Location/Venue

Names of MajorParticipants

Occupations of theMajor Participants Feedback/Concerns

14-09-15 Village Dulmial Mr. Gul Zaman Private job I am satisfied with the project. However,relocation or compensation should be asper the requirements of the affectees.

14-09-15 Village Dulmial Mr. FaisalAbbas

Agricultural Farmer Relocation or compensation should be asper the requirements of the affectees.Lucrative land against land should beprovided.

14-09-15 Village Dulmial Mr. DilawarKhan

Head of the UC(Namberdar)

People are mostly satisfied with theproject.He also demanded from the projectproponents to install the latesttechnologies for pollution control.He also believes on overall basis, this is agood project because it will help toimprove basic infrastructure of area.

Page 72: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 9, Public Consultation Page – 9.7

Date Location/Venue

Names of MajorParticipants

Occupations of theMajor Participants Feedback/Concerns

14-09-15 Village Dulmial Mr. YounasFaheem

Private Job It is a good project that will improvethe infrastructure of the area.

14-09-15 Village Dulmial Captain FatehMuhammad

RetiredGovernmentOfficial

He also demanded from the projectproponents to install the latesttechnologies for pollution control.He also believes on overall basis, this is agood project because it will help toimprove basic infrastructure of area

14-09-15 Village Dulmial Mr. UsmanAzam

Private Job He appreciated the project.

14-09-15 Village Dulmial Mr. AmirBashir

Farmer It is a good project that will create jobopportunities.

14-09-15 Village Dulmial Mr. GulistanKhan

Farmer It is a good project that will create jobopportunities.

14-09-15 Village Dulmial Mr. JalilAhmad

Private Job He welcomed the project

14-09-15 Village Dulmial Mr. HassanFahim

Farmer He also demanded from the projectproponents to install the latesttechnologies for pollution control.

14-09-15 Village Dulmial Mr. ZainKafeel

Farmer He also demanded from the projectproponents to install the latesttechnologies for pollution control.

14-09-15 Village Dulmial Mr. RashidAwan

Private Business It is a good project that will create the joband business opportunities.

14-09-15 Village Dulmial Mr. GhulamNazar

Farmer/PrivateBusiness

He welcomed the project perceiving thedevelopment of the project area

14-09-15 Village Dulmial Mr. GhulamAbbasDhalon

Farmer He demanded the proper compensation forthe lands

14-09-15 Village Dulmial Mr. AshiqMuhammad

Private Business He demanded the proper compensation forthe lands for people displaced.

14-09-15 Village Dulmial Mr. NabiBukhsh

ConstructionMaterial Dealer

He also believes on overall basis, this is agood project because it will help toimprove basic infrastructure of area

14-09-15 Village Dulmial Mr. ShoibNazer

Private Business He welcomed the project

14-09-15 Village Dulmial Mr.MuhammadAsgherArien

Farmer It is a good project that will create the joband business opportunities.

14-09-15 Village Dulmial Mr. NaeemGunjua

Shopkeeper He demanded from the project proponentsto conduct their project activities inenvironment friendly manners.

14-09-15 Village Dulmial Mr. HassanGanjua

Student He perceived the project as good for localarea.

14-09-15 Village Dulmial Mr.WaseemAsgher

Student It is a good project that will create the joband business opportunities.

14-09-15 Village Dulmial Mr. UmarArien

Private Business He also perceived the project as good forlocal area.

Page 73: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 9, Public Consultation Page – 9.8

Date Location/Venue

Names of MajorParticipants

Occupations of theMajor Participants Feedback/Concerns

14-09-15 Village Dulmial Mr. NaeemSherazi

Shop Keeper The project should operate environmentfriendly manners.

14-09-15 Village Dulmial Mr. ShahidAsgher

Private Business The project should operate environmentfriendly manners.

Date Location/Venue

Names of MajorParticipants

Occupations of theMajor Participants Feedback/Concerns

15-09-15 Village TatralKahoon

Mr. TahirMehmood

Private Business I am satisfied with the project. However,relocation or compensation should be asper the requirements of the affectees.

15-09-15 Village TatralKahoon

Mr. AmjadMehmood

Agricultural Farmer Relocation or Compensation should be asper the requirements of the affectees.Lucrative Land against land should beprovided.

15-09-15 Village TatralKahoon

Mr. NaaikMuhammad

GovernmentEmployee

People are mostly satisfied with theproject. He also demanded from theproject proponents to install the latesttechnologies for pollution control.He also believes on overall basis, this is agood project because it will help toimprove basic infrastructure of area.

15-09-15 Village TatralKahoon

Mr. RizwanAfzal

Private Job It is a good project that will improvethe infrastructure of the area.

15-09-15 Village TatralKahoon

Captain FatehMuhammad

RetiredGovernmentOfficial

He demanded from the project proponentsto install the latest technologies forpollution control.He also believes on overall basis, this is agood project because it will help toimprove basic infrastructure of area

15-09-15 Village TatralKahoon

Mr.MehboobAlam

Private Job He appreciated the project.

15-09-15 Village TatralKahoon

PirZafarullahShah

Namberdar It is a good project that will create the jobopportunities. People are mostly satisfiedwith the project. He also demanded fromthe project proponents to install the latesttechnologies for pollution control.He also believes on overall basis, this isa good project because it will help toimprove basic infrastructure of area.

15-09-15 Village TatralKahoon

Mr. BashirAhmad

Farmer It is a good project that will create thejob opportunities.

15-09-15 Village TatralKahoon

Mr. MuhammadKhan

PrivateJob/Farmer

He welcomed the project

15-09-15 Village TatralKahoon

Mr. HassanFahim

Farmer He also demanded from the projectproponents to install the latesttechnologies for pollution control andproper compensation.

Page 74: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 9, Public Consultation Page – 9.9

Date Location/Venue

Names of MajorParticipants

Occupations of theMajor Participants Feedback/Concerns

15-09-15 Village TatralKahoon

Mr. ZainKafeel

Farmer He also demanded from the projectproponents to install the latesttechnologies for pollution control.

15-09-15 Village TatralKahoon

Mr. Azam Private Business He criticized the operation of existingcement units in the area and expectedbetter and advance pollution controltechnology.

15-09-15 Village TatralKahoon

Mr. Hameed Farmer/PrivateBusiness

He welcomed the project perceiving thedevelopment of the project area

15-09-15 Village TatralKahoon

Mr. Gulraiz Farmer He demanded the proper compensation ofthe lands

15-09-15 Village TatralKahoon

Mr.ShamraizKhan

Private Business He demanded the proper compensation ofthe lands

15-09-15 Village TatralKahoon

Mr.Abdullah

School Teacher He welcomed the project activities.

15-09-15 Village TatralKahoon

Mr. Ishaq Private Business He welcomed the project. He also believeson overall basis, this is a good projectbecause it will help to improve basicinfrastructure of area

15-09-15 Village TatralKahoon

Mr. AshrafKhan

Farmer It is a good project that will create the joband business opportunities.

15-09-15 Village TatralKahoon

Mr. ArshadHussain

Shopkeeper He demanded from the project proponentsto conduct their project activities inenvironment friendly manners.

15-09-15 Village TatralKahoon

Mr. ArifMalik

Army Employee He argued about the project as good forlocal area.

15-09-15 Village TatralKahoon

Mr. IlahiBukhsh

GovernmentEmployee

It is a good project that will create the joband business opportunities.

15-09-15 Village TatralKahoon

Mr. UsmanAsgher

Private Business He also perceived the project as good forlocal area.

15-09-15 Village TatralKahoon

Mr. PervaizKhan

Shop Keeper The project should operate environmentfriendly manners.

15-09-15 Village TatralKahoon

Mr. Zaheer Arian Private Business The project should operate in environmentfriendly manners.

Date Location/Venue

Names of MajorParticipants

Occupations of theMajor Participants Feedback/Concerns

16-09-15 Village Khajula Mr.Rehan Farmer He strongly opposed the project by arguingthat it will create the huge pollution in thearea.

16-09-15 Village Khajula Mr. IjazHussani

Agricultural Farmer He appreciated the project. Relocation orCompensation should be as per therequirements of the affectees. LucrativeLand against land should be provided.

16-09-15 Village Khajula Mr. MuhammadZubair

Agricultural Farmer People are mostly satisfied with theproject.He also demanded from the projectproponents to install the latesttechnologies for pollution control.

Page 75: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 9, Public Consultation Page – 9.10

Date Location/Venue

Names of MajorParticipants

Occupations of theMajor Participants Feedback/Concerns

He also believes on overall basis, this is agood project because it will help toimprove basic infrastructure of area.

16-09-15 Village Khajula Mr. YounasFaheem

Private Job It is a good project that will improvethe infrastructure of the area.

16-09-15 Village Khajula Mr. MuhammadWalait

RetiredGovernmentOfficial

He also demanded from the projectproponents to install the latesttechnologies for pollution control.He also believes on overall basis, this is agood project because it will help toimprove basic infrastructure of area

16-09-15 Village Khajula Mr. RajaMuhammadJavaid

Namberdar/Farmer

He appreciated the project. Relocationor Compensation should be as per therequirements of the affectees.Lucrative Land against land should beprovided.

16-09-15 Village Khajula Mr. ArbabKamal

Farmer It is a good project that will create thejob opportunities.

16-09-15 Village Khajula Mr.TabbasamMunawar

Farmer It is a good project that will create thejob opportunities.

16-09-15 Village Khajula Mr. RajaAttaMuhammad

Private Job He welcomed the project

16-09-15 Village Khajula Mr. NajeebAsghar

Farmer He also demanded from the projectproponents to install the latesttechnologies for pollution control.

16-09-15 Village Khajula Mr. Malik Nasir Farmer He also demanded from the projectproponents to install the latesttechnologies for pollution control and paytimely compensation.

16-09-15 Village Khajula Mr. AtifMalik

Private Business It is a good project that will create job andbusiness opportunities.

16-09-15 Village Khajula Mr. GhulamRasool

Farmer/PrivateBusiness

He welcomed the project perceiving thedevelopment of the project area

16-09-15 Village Khajula Mr. GhulamAbbasDhalon

Farmer He demanded the proper compensation ofthe lands

16-09-15 Village Khajula Mr. AshiqMuhammad

Private Business He demanded the proper compensation ofthe lands

Date Location/Venue

Names of MajorParticipants

Occupations of theMajor Participants Feedback/Concerns

16-09-15 Village Maghal Mr. Yousaf Farmer He appreciated the project Relocation orCompensation should be as per therequirements of the affectees. LucrativeLand against land should be provided

16-09-15 Village Maghal Mr. KhudaBukhsh

Farmer He strongly opposed the project by arguingthat it will create the huge pollution in thearea

Page 76: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 9, Public Consultation Page – 9.11

Date Location/Venue

Names of MajorParticipants

Occupations of theMajor Participants Feedback/Concerns

16-09-15 Village Maghal Ali Abbas Farmer People are mostly satisfied with theproject.He also demanded from the projectproponents to install the latesttechnologies for pollution control.He also believes on overall basis, this is agood project because it will help toimprove basic infrastructure of area.

16-09-15 Village Maghal Mr. RashoolChihan

Private Job It is a good project that will improvethe infrastructure of the area.

16-09-15 Village Maghal Mr. MuhammadKhan

GovernmentEmployee

He also demanded from the projectproponents to install the latesttechnologies for pollution control.He also believes on overall basis, this is agood project because it will help toimprove basic infrastructure of area

16-09-15 Village Maghal Mr. RajaWaeem

Namberdar/Farmer

He appreciated the project Relocationor Compensation should be as per therequirements of the affectees.Lucrative Land against land should beprovided.

16-09-15 Village Maghal Mr. AkbarAli

Farmer It is a good project that will create thejob opportunities.

16-09-15 Village Maghal Mr.MunawarHussain

Zamindar It is a good project that will create jobopportunities.

16-09-15 Village Maghal Mr.MuhammadAtta

Private Job He welcomed the project activities

16-09-15 Village Maghal Mr. AzadMuhammad

Businessman He demanded from the project proponentsto install the latest technologies forpollution control.

16-09-15 Village Maghal Mr. Malik Javaid Farmer He demanded from the project proponentsto install the pollution control technologiesfor pollution prevention and pay timelycompensation.

16-09-15 Village Maghal Mr. AllahDad

Private Business It is a good project that will create the joband business opportunities.

16-09-15 Village Maghal Mr. ImtiazNaqvi

Private Business He welcomed the project perceiving thedevelopment of the project area

16-09-15 Village Maghal Mr. RajaShamsheer

Farmer He demanded the proper compensation ofthe lands

16-09-15 Village Maghal Mr. Ishtiaq Private Business He demanded the proper compensation ofthe lands

Page 77: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 9, Public Consultation Page – 9.12

Photo Log of the consultation process is presented in Appendix – 9.1 and signed copiesof the participants interviewed are presented in Appendix – 9.2.

Government RepresentativesThe consultations were carried out with the local government officials and officials of thefollowing departments:

Mines & Mineral Department Environment Protection Department (EPA) Forestry/Fisheries Tehsil Municipal Administration (TMA) Irrigation Wild Life

The officials of TMA, Wildlife and Forest Department perceived that the employmentopportunities and business development would be a positive impact on the communityand people during the construction phase of the proposed project. Among the perceivednegative impacts during construction phase of the project include especially roadblockage, dust emissions, noise and nuisance due to heavy traffic. All officials of projectstudy area were in favour of the project. They expect many positive, conducive andconstructive impacts on socio-economic life of local community regarding jobs, businessopportunity and social structure development. They were of opinion that project wouldimprove area’s development through development of existing infrastructure etc. Theproject will also raise their level of awareness, initiate cultural diffusion, activate socialmobility and bring social change regarding various aspects of their life.

The officials from Fisheries and Irrigation Departments appreciated the proposed activity.They also expressed that jobs and business opportunities for the local community will beincreased due to project activities and that infrastructure will develop that automaticallywill lead to the development of the project area. They also expressed the concern thatmost of the unskilled and skill jobs should be provided for the local communities.

Page 78: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 9, Public Consultation Page – 9.13

9.6 Stakeholder Concerns and Recommendations

The findings of the Community consultations are given below. All these have beenaddressed in various sections of the EIA, and the mitigation plans have been incorporatedinto the EMP.

The summary of the various stakeholder consultations is given below.

The people foresee positive impacts like employment opportunities, business,development of the area etc.

Study findings depict that the people of the study area perceive overall positiveimpacts as a result of cement plant sitting. Therefore, their attitude towards theproject establishment is quite positive.

As far as the EIA is concerned, positive social impacts are dominant over hardlyconceived any negative social impacts observed during the study.

The people have high expectations and hope from the project activity and itsmanagement.

They correlate their positive attitude towards the project with many socio-economic opportunities and benefits.

The people believe that the project in the area will open up vast employmentopportunities which in turn follow a chain of indirect socio-economic benefits.

They also perceive accelerated economic activity due to the businessopportunities likely to emerge in the area. Directly or indirectly, hundreds of thelocal people are expected to get employment and business from the project e.g.,shopkeepers, traders, suppliers, contractors, transporters, technicians, etc.

People foresee many socio-cultural and psychological positive impacts on theirlives and the community.

They feel that the cement plant and its related activities will provide a strong basefor social change.

They reckon that enhancement of investment and technology in the area willimprove the quality of life of the people. It will also improve the level of generalawareness of the people about different aspects of life.

Page 79: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 9, Public Consultation Page – 9.14

From the above facts it can be concluded that many positive economic and social impactswill appear in the quality of the lives of the people of the Study Area due to the proposedproject. These positive impacts include improvement in female status, employment andbusiness opportunities, infrastructure development, reducing rural urban migration,generating income resources and improving quality of life.

9.7 Summary of Findings of Public Consultations

9.7.1 Socio-economic Baseline Conditions

Socio-economic status of the people of the project area are described hereunder:

Drinking water availability and educational and medical facilities in the villagesunder reference of this study are not fully established.

Public transport is also readily available. In villages major source of income is agriculture. Old social order of life prevails and by and large, social harmony prevails. Elders are very much respected and they have great say in decision making. Traditional type of conservative society and for that matter traditional socio-

cultural values are dominant in every walk of life. Though print and electronicmedia have started bringing a change in the overall pattern of life style.

Joint family system is the order of the day. Some women the area help in agriculture activities while others are restricted to

house-keeping. Majority of the older generation is limited education. But younger generation is

showing interest in getting better and higher education.

On the overall basis it is concluded that socio-economic conditions of the people stillneeds drastic improvement. People do face hardship regarding basic amenities,education, health and employment.

Page 80: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 9, Public Consultation Page – 9.15

9.7.2 Community Awareness and Perceptions about the Project

People of the area are well aware of installation of the project. Virtually all of themhave positive attitude about the project.

They are well aware that the project installation will provide them jobopportunities.

Their perception is that the Plant in the area will be very beneficial for thecommunity and the area.

They foresee positive impacts out of it, like employment opportunities, business,development of the area etc.

The people perceive overall positive social impacts by the installation of the Plant.They have highly positive attitude towards the project installation.

They are apprehensive of environmental aspects of the project.

At the same time they foresee that the project management will feel their, social, moraland legal obligation and bring in Environmental Management Order whereby theenvironment will not be tempered.

9.7.2.1 Social ImpactsIt can be safely concluded that social and economic impacts clearly dominate any fewnegative impacts of environment.

9.7.2.2 Positive Impacts The conclusions of the study prove that the positive economic and social impacts

of the Plant are far too dominant. People foresee employment opportunities for them. These employment opportunities will follow a chain of indirect benefits also i.e.

the young people of these communities will get employment and business. They feel that the Plant and its related activities would provide a strong base for

social change. This trend will enhance family protection, socialization of the family members. Set trend for more industry to be installed around. Commercially viable project and long term sustainability

Page 81: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 9, Public Consultation Page – 9.16

Improved and mechanized services for the community.

From the above discussion, one can conclude that positive impacts includingimprovement in employment, generating income resources and business opportunities.

9.7.2.3 Negative ImpactsMajor concern of the consulted people of the area is generation of air pollution. For whichthey feel that APML should undertake extensive mitigation measures to safe-guardagainst air pollution. They feel that the project should adhere to International Standards.

9.8 Recommendations and Mitigation Measures

APML have discussed the possibility of relocation of village “Rupper”, with inhabitants/residents. This is a small dhoke/village comprising of 32 house with population of 175people. They are willing to be shifted to another nearby place. APML is negotiating acomprehensive agreement with then for purchase of land and exploring the possibility attwo different nearby locations to relocate them.

APML will use its reasonable endeavours to support and develop the local community andwill construct and maintain an appropriate hospital and girl school for the area as part ofits ongoing Corporate Social Responsibility programme. APML will also build an accessroad/path and water supply for the Khajula Village.

APML is also in consultation with the Pakistan Railways to extend their railway networkto near the plant site. When implemented this will reduce freight congestion on roadnetwork as well as provide passenger service to local community.

Page 82: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 9, Public Consultation Page – 9.17

As result of the PCs the following recommendations are made:

The management of the Project should measure up to the positive expectations of thepeople of the area and offer them maximum employment opportunities.

Environmental protection according to the legal national & internationalrequirements should be ensured throughout the project operational life thusguaranteeing protection of the environment and human health.

Sustainable development approach through conservation of natural resourcesmanagement would be the best strategy.

The plant management should offer technical training opportunities to the local youthif possible.

Implementation of the Environmental Management Plan and EnvironmentalMonitoring Plan, as recommended in this report, should be ensured.

Page 83: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 10, References Page – 10.1

10.0 REFERENCES

Listed below are some of the documents, reports and other references consulted duringthe preparation of this report:

a. Information and data provided by project proponents;

b. Project Pre-feasibility Study Report;

c. Technical Design Data related to the project.

d. Information gathered through discussions with the project related persons of theproject proponent;

e. Discussion with concerned government officials;

f. Information collected from the Technical documents of various suppliers ofmachinery/equipment.

g. Guidelines for Self- Monitoring and Reporting by the Industry (SMART),” FinalReport, March 1998, approved by Pakistan Environmental Protection Council(PEPC), August 1999;

h. National Environment Quality Standards for Municipal and Liquid IndustrialEffluents, Statutory Notification (S.R.O.), Government of Pakistan, Ministry ofEnvironment, Local Government and Rural Development, S.R.O.549 (1)/2000,Islamabad, the 8th August 2000;

i. National Environment Quality Standards for Ambient Air November 2010;

j. National Environment Quality Standards Noise Levels November 2010;

k. National Environment Quality Standards for Drinking Water November 2010:;

l. Pakistan Environmental Protection Act, 1997;

m. The Punjab Environmental Protection (Amendment) Act 2011 covers aspectsrelated to: the protection, conservation, rehabilitation and improvement of the

environment and the prevention, control of pollution and promotion ofsustainable development;

Page 84: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 10, References Page – 10.2

establishing complete regulatory and monitoring bodies, policies, rules,regulations and national environmental quality standards; and

to ensure enforcement, the act establishes regulating bodies i.e. PunjabEnvironmental Protection Council (PEPC) and responsible bodies i.e. PunjabEnvironmental Protection Agency (Punjab EPA) at Provincial level.

a. Land Use Policies and Environmental Legal Framework including;

b. Environment related Laws in Pakistan and the Province of Punjab;

c. The Pakistan National Conservation Strategy, Environment and Urban Affairs’Division (presently- Ministry of Environment, Urban Affairs and Wild Life),Government of Pakistan, Islamabad;

d. Standard Methods for the Examination of Water and Wastewater, 19th Edition,1995, Prepared and published jointly by: American Public Health Association,American Water Works Association, Water Environment Federation; Publicationoffice: American Public Health Association, 1015 Fifteenth Street, NWWashington, DC 2005;

e. International Finance Commission (IFC) Environmental, Health and SafetyGuidelines, Environmental and Social Guidelines for Occupational Health & Safety(December 2012);

f. Government of Pakistan, Pakistan Environmental Protection Agency, Policy andProcedures for Filing, Review and Approval of Environmental Assessment, 2000;

g. The Canal and Drainage Act, 1873;

h. Environmental Assessment Requirements and Environmental Review Proceduresof the Asian Development Bank, 1993;

i. GOOGLE EARTH, maps.

j. Guidelines for Public Consultations - These guidelines cover: Consultation, involvement and participation of Stakeholders Techniques for public consultation (principles, levels of involvements, tools,

building trust) Effective public consultation (planning, stages of EIA where consultation is

appropriate). Consensus building and dispute resolution.

Page 85: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 10, References Page – 10.3

k. Factories Act, 1934;

l. Applicable International Environmental and Occupational Safety and Health Lawsand Regulations;

m. Applicable International Environmental and Occupational Safety and Health Lawsand Regulations;

n. Pollution Prevention and Abatement Handbook, The World Bank, 1998;

o. International Finance Corporation’s Policy on Energy and Social Sustainability,January 1, 2012;

p. National Resettlement Policy (Draft), Government of Pakistan, March 2002.

Page 86: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 11, Sources of Data & Information Page – 11.1

11.0 SOURCES OF DATA AND INFORMATION AND LIST OF REFERENCE MATERIAL USED

The Baseline data regarding ambient air quality, water sample analysis, etc., was gatheredduring detailed site. Data was collected and analyzed by Integrated EnvironmentConsultants, Lahore at their laboratory.

Data for Air Dispersion Modelling was based on pollutants emission data provided byAPML and compared with Pakistan NEQS, IFC EHS Guidelines and WHO Guidelines.

Detailed references of documents & reports consulted during preparation of this reportis presented in Chapter-10.

Page 87: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 12, Consultant’s Team Members Page – 12.1

12.0 CONSULTANTS KEY TEAM MEMBERS FOR THE STUDY AND PREPARATION OF THE EIAREPORT

Team members who participated in various activities of this study and preparation of thisreport are listed hereunder with their qualifications, experience and assignment carriedout by each one of them.

1. AFTAB AHMAD, Chief Executive, Aftec (Pvt.) Limited, - TEAM LEADER

General Experience:Specialist on conduct of EIA and SEIA studies and preparation of reports; process,production and waste treatment plants designing; project feasibility studiesspecialist; HAZOP studies, Energy Auditing and HSE specialist. Technical Expert onFertilizer, Cement & Power Plants; and Public Consultations.- M.Sc. (Hons.) Chem. Technology, 1956 (Punjab University.).- Ex. Managing Director, Pak Arab Fertilize Corporation, Multan;- EX. Managing Director Milkpak Limited (now Nestle Pakistan).

Related Experience:- Involved in survey and conduct over 40 EIA Reports.- Preparation and conduct of about 15 SEIA Reports.- Preparation of Resettlement Plans.

2. AHTASHAM RAZA, Principle Environmentalist, Integrated Environment Consultants- Ph.D Scholar (Environmental Sciences), University of the Punjab, Lahore,

Pakistan 2010 - 13)- M.Phil, (Environmental Sciences), GC University, Lahore, Pakistan (2007-2009)- M.Sc. (Industrial Process Chemistry), GC University, Lahore, Pakistan (2004-06)- B.Sc. (Botany, Zoology, Chemistry), University of the Punjab, Lahore Pakistan

(2002-04)

- Other Training: One Week Training for Environmental Regulatory ComplianceAuditing, EEI Corporation, Rockville, MD 20850-USA.

- Area of Specialization: Preparation of Environmental and Social ImpactAssessment (ESIA) reports according to International Finance Corporation (IFC)Performance Standards under Equator Principles, the World Bank, Asian

Page 88: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 12, Consultant’s Team Members Page – 12.2

Development Bank and Pakistan Standards. Environmental RegulatoryCompliance Auditing. Environment, Health & Safety (EHS) Auditing. LaboratoryTesting services; a wide variety of samples are tested for NEQS- Pakistan, theWorld Bank, IFC and Levis etc. requirements. Hazardousness and Operability(HAZOP) analysis. Auditor (external) for Environmental Regulatory Compliancefor and on behalf of EEI Corporation, Rockville, MD 20850-USA. EnvironmentalMonitoring/Audits (including ambient and stacks monitoring, POPs monitoring,soil, sludge, ground water and treated effluents analysis) and Air DispersionModelling, Published 8 scientific research papers in different internationaljournals.

- Employment Record

Page 89: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 12, Consultant’s Team Members Page – 12.3

- Work Undertaken that Best Illustrates Capability to Handle the Tasks AssignedActivities

Page 90: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 12, Consultant’s Team Members Page – 12.4

Page 91: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 12, Consultant’s Team Members Page – 12.5

Page 92: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 12, Consultant’s Team Members Page – 12.6

Page 93: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 12, Consultant’s Team Members Page – 12.7

- During the Preparation of Environmental Impact Assessment (EIA) Report theBaseline Environmental Monitoring and data collection was done of thefollowing assignments:- Grand Office Plaza, Opposite to 7-up Guru Mangat Road, Gulberg Lahore.- Johar Public Schooling System, Johar Town, Lahore.- Best Way Cement Company, Kallar Kahar-Choa Saidan Shah Road, District

Chakwal.- Madina Height, M.S.A. Road, Lahore.- Aashiana Shopping Center, Gulberg-III, Lahore

Page 94: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 12, Consultant’s Team Members Page – 12.8

- Lahore University of Management Sciences Installation of Waste Wate- LakeCity, Raiwind Road, Lahore

- 25-MW Waste Heat Recovery Power Plant at Bestway Cement, Kallar-Nippon paint Ware House in Lahore for Storage of Paint materials/produc-Bahria Town, Islamabad and Rawalpindi

- Dadu-Khuzdar 120 KV Transmission Line According to World Bank F- 80 MWPower Plant, PakArab Fertilizer, Multan

- Descon Oxychem (Pvt) Limited, 18- Km, Sheikupura Road, Lahore.

- Environmental Monitoring for process emission and effluent analysis werecarried out of various industries in Pakistan the major one are- Sitara Textiles. Faisalabad- Packages Limited, Lahore- Nishat Dyeing, Lahore- Century Paper Mills- Fauji Corn Complex, Jahangira, Kyber Pakhtunkhuwaha- Pak Arab Fertilizer Ltd, Multan- Crescent Bahuman Limited- Cotton Web Pvt. Limited, Lahore- Elemtec Pvt. Limited- Pak Arab Refinery Company Limited (PARCO) etc

- 14. Detailed Tasks Assigned- Prepare the environmental screening to classify the subprojects in

consultation with the- Provincial Environmental Protection Agency (EPA).- Conducting environmental assessment study based on the classification of

the sub project with adequate consultation with affected people. ForCategory-A (in line with agreed Client guidelines) subproject carry out twostep consultation with affected people.

- For category B project (according to Client guidelines), assist eachimplementing agency responsible for submitting the environmental

Page 95: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 12, Consultant’s Team Members Page – 12.9

screening and environmental assessment report and its summary to theNWFP, EPA for review in order to obtain an environmental clearance forexecution of the subprojects.

- For category A project, in addition to following the procedure as stated inClient project document (RRP), the specialist will assist the implementingagency to submit EIA report and its summary to Client as soon as possible tomeet the 120 days public disclosure prior to obtaining a Client approval forsuch subproject.

- Ensuring that the contract document for implementing each subprojectincludes: (a )environmental monitoring and management plan taken fromthe environmental assessment report, and (b) the environmental clearancecertificate and its conditions.

- Facilitate environmental clearance certificate from KPK, EPA, prior togranting contract award.

- Monitoring the implementation of environmental management planthroughout the whole project implementation stage particularly duringpreparation of detail engineering design and construction stage andpreparing the report in monitoring the implementation of environmentalmanagement plan (optional – may be undertaken by RE depending upon thecomplication of the requirements of environmental plan).

- Undertaking remedial action in close consultation with respective EPA andClient to handle unexpected environmental impacts.

- Submitting the monitoring report on EMP to the relevant agencies andClient.

2. Dr. Rub Nawaz, Ph.D (Environmental Sciences), Asian Institute of technology (AIT),Thailand.M.Sc (Hons)/ B.Sc (Hons), University of Agriculture, Faisalabad,

3. Mr. Zeeshan, M.Sc. Environmental SciencesM.B.A (QC& QA /Environmental Economist)

Page 96: ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT … Main EIA... · ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT Chapter – 5, Evaluation of Impacts & Mitigation

ASIAN PRECIOUS MINERALS LIMITED – EIA REPORT CEMENT PROJECT

Chapter – 12, Consultant’s Team Members Page – 12.10

4. Mr. Asher AzadM.Sc. (Chemical Engineering)M.Sc. Chemistry –USA

5. Aftab RehmanMasters in Social Science, University of The Punjab,Sociologist

6. Syeda Hina GillaniM.Sc (Environmental Sciences)


Recommended