ASMAR WOOD WAREHOUSE ZAHLE, LEBANON

Date post: 26-Mar-2022
Category:
Upload: others
View: 6 times
Download: 0 times
Share this document with a friend
1
Asmar Wood has been supplying lumber products to the Lebanese since 1958. As an importer of products from around the world, the company maintains extensive storage facilities. One such storage depot is a 15,000 m 2 warehouse which comprises 5,500 m 2 slab on grade and 9,500 m 2 suspended slabs. CCL’s specialist Surface team was engaged to carry out a value engineering exercise on an existing reinforced concrete (RC) slab design. This produced a crack-free, joint-free, flat and level post-tensioned (PT) floor slab solution. Reengineering the RC slab as a PT slab on grade eliminated the need for the screed topping and provided cost savings of 30%. The CCL team also undertook installation of the slab, which involved a continuous concrete pour of 2,200 m 2 over 16 hours. The project was completed in 75 days. ASMAR WOOD WAREHOUSE ZAHLE, LEBANON CCL Client: Asmar Wood Consultant: Ziad Germany Main Contractor: NSE for Contracting Project Date: April 2017 Surface Jointless Flooring System - DHPPB T: +961 (0) 9 22 60 44 F: +961 (0) 9 22 60 77 E: [email protected] W: www.cclint.com
Transcript

Asmar Wood has been supplying lumber products to the Lebanese since 1958. As an importer of products from around the world, the company maintains extensive storage facilities. One such storage depot is a 15,000 m2 warehouse which comprises 5,500 m2 slab on grade and 9,500 m2 suspended slabs.

CCL’s specialist Surface team was engaged to carry out a value engineering exercise on an existing reinforced concrete (RC) slab design. This produced a crack-free, joint-free, flat and level post-tensioned (PT) floor slab solution. Reengineering the RC slab as a PT slab on grade eliminated the need for the screed topping and provided cost savings of 30%.

The CCL team also undertook installation of the slab, which involved a continuous concrete pour of 2,200 m2 over 16 hours. The project was completed in 75 days.

ASMAR WOODWAREHOUSEZAHLE, LEBANONCCL Client: Asmar WoodConsultant: Ziad Germany Main Contractor: NSE for ContractingProject Date: April 2017