+ All Categories
Home > Documents > Assam Schedule VII : Form No. 132sonitpurjudiciary.gov.in/Judgement/11-08_TITLE SUIT NO.10...Assam...

Assam Schedule VII : Form No. 132sonitpurjudiciary.gov.in/Judgement/11-08_TITLE SUIT NO.10...Assam...

Date post: 04-Apr-2020
Category:
Upload: others
View: 5 times
Download: 0 times
Share this document with a friend
19
Assam Schedule VII : Form No. 132 HIGH COURT FORM NO.(J) 2. HEADING OF JUDGMENT IN ORIGINAL SUIT / CASE IN THE COURT OF THE CIVIL JUDGE TEZPUR, SONITPUR Present: Smti Munmun B.Sarma Civil Judge Tezpur, Sonitpur 11 th August2017 TITLE SUIT NO.10/2013 ITP Limited Registered Office - 17, R.N. Mukherjee Road, Kishore Bhawan, Kolkatta 700001, Owner of - Monmohinipur Tea Estate, PO Darrang Panbari 784111 Mouza Dhekiajuli, District Sonitpur, Assam ......... Plaintiff -Vs - Assam Power Distribution Company Ltd 1. The Managing Director Assam Power Distribution Company Ltd. Bijuli Bhawan, Paltan Bazar, Guwahati 781001, Assam 2. The General Manager Assam Power Distribution Company Ltd. Tezpur 784001, Mouza - Mahabhairab Sonitpur, Assam 3. The Area Manager Industrial Revenue Collection Area
Transcript

Assam Schedule VII : Form No. 132

HIGH COURT FORM NO.(J) 2.

HEADING OF JUDGMENT IN ORIGINAL SUIT / CASE

IN THE COURT OF THE CIVIL JUDGE

TEZPUR, SONITPUR

Present: Smti Munmun B.Sarma

Civil Judge

Tezpur, Sonitpur

11th August‟2017

TITLE SUIT NO.10/2013

ITP Limited

Registered Office -

17, R.N. Mukherjee Road, Kishore Bhawan,

Kolkatta 700001,

Owner of -

Monmohinipur Tea Estate,

PO – Darrang Panbari – 784111

Mouza – Dhekiajuli,

District – Sonitpur, Assam ......... Plaintiff

-Vs -

Assam Power Distribution Company Ltd

1. The Managing Director

Assam Power Distribution Company Ltd.

Bijuli Bhawan, Paltan Bazar,

Guwahati – 781001, Assam

2. The General Manager

Assam Power Distribution Company Ltd.

Tezpur – 784001, Mouza - Mahabhairab

Sonitpur, Assam

3. The Area Manager

Industrial Revenue Collection Area

Page 2 of 19

Assam Power Distribution Company Ltd.

Kamarchuburi, Tezpur – 784001,

Mouza – Bhairabpad, Sonitpur, Assam

........ Defendant(s).

This suit for declaration that an amount of Rs.2,65,774/- (Rupees Two Lakhs

Six Five Thousand Seven Hundred Seventy Four Only) is not recoverable from

the plaintiff by the defendants vide bill No.351/05 dated 30-03-2013 and for

permanent injunction came-up for final hearing on 14-07-2017

Counsel for Plaintiff : Sri Ananta Goswami

Counsel for Defendant : Sri P.K.Dutta

JUDGMENT

1) This suit for declaration that an amount of Rs.2,65,774/- (Rupees Two

Lakhs Six Five Thousand Seven Hundred Seventy Four only) is not

recoverable by the defendants (vide bill No.351/05 dated 30-03-2013) from

the plaintiff and for permanent injunction.

Plaintiff’s Case:

2) The plaintiff is a company known as ITP, incorporated and registered

under the Companies Act, 1956 & carries on business of plantation,

manufacture and sell of tea as a tea planter. The plaintiff has its registered

office at Kolkata & carries on business as the owner of Manmohinipur Tea

Estate. Defendant Assam Power Distribution Company Ltd (hereinafter

referred to as APDCL) supplies power to Manmohini T.E. bearing No.

009000001031, category I. R. T. E.-LQ-161/DHI. Plaintiff has been marking

regular payment of energy bills to the defendant No.3 at Tezpur without any

Page 3 of 19

default. The electricity consumption in respect of labour quarters are recorded

in separate meters and bill is raised from this meter.

3) On 30-03-2013 the defendant No.3 forwarded a bill for Rs.2,65,734/-

(Rupees Two Lakhs Six Five Thousand Seven Hundred Thirty Four only) only

vide Bill No.351/05 dated 30-03-2013 to the plaintiff-Monmohinipur Tea

Estate therein “Audit objection bill against short realization of demand

charges” with “NB – Enclosed Audit Report”. The enclosed audit report

revealed about “revised bill” and period pertained to “28-02-10 to 31-10-10”.

The audit report spoke about less billing in the labour quarter metering of the

mentioned period, but silent about how it could happen in as much as the

responsibility of recording meter reading vis-à-vis preparation of monthly

energy bill/s is always a prerogative of the office of the defendant No.3

thorough his subordinate officer/engineer and the auditor being non-technical

person/s has no say in the matter alleged of. The energy supplier company

raised the bill dated 30-03-2013 in old stationery of ASEB.

4) The static meter No.07432177 of LT type metering was supplied and

installed by the energy supplier company & is defendant company‟s

prerogative and consumer does not have any access to it. The plaintiff‟s

garden used to receive energy bills to the extent of its use and used to make

regular payments thereof without any default nor any arrear was shown in

the said monthly energy bills. There is no concept of adhoc bill or audit

objection bill in the Electricity Act and Rules & the instant bill of Rs.2,65,734/-

against labor quarter electricity consumption is a reflection of mismanaged bill

system.

Page 4 of 19

5) It was further prayed in the plaint that the defendant company has no

right to raise the aforesaid revised bill dated 30-03-2013 for the period

February, 2010 to October, 2010 amounting to Rs.2,65,734/- & therefore,

the defendant company is not entitled to any amount whatsoever under the

alleged “revised bill” basing on so called “Audit objection”. Furthermore, the

purported bill not having been raised within the statutory period of 2 years

from the date when such sum became due & not being shown continuously

recoverable in the monthly energy bills as an arrear, has become time barred

and not recoverable from the plaintiff under the specific provisions u/s 56 (2)

of the Electricity Act, 2003. Thus, the present suit was filed with the following

prayers:

a) Declaration that the revised bill No.351/05 dated 30-03-2013 for

the period February, 2010 to October, 2010 for Rs.2,65,734/- is

not lawfully due and recoverable & time barred u/s 56(2)

Electricity Act;

b) Permanent Injunction prohibiting the defendant & their men and

agents from recovering Rs.2,65,734/- or any part thereof from the

plaintiff garden Monmohinipur Tea Estate & from disconnecting the

electricity connection/ power supply from the plaintiff‟s garden

Monmohinipur Tea Estate;

c) All costs of the suit against the defendants;

d) All other relief/s as the court may deem fit and proper.

Defendant’s Case:

6) The defendants contested the suit & filed written statement. They

raised the objections that the plaint was not signed & verified by duly

Page 5 of 19

authorized person & therefore is not maintainable & barred by law. That the

suit is not filed complying with the provisions of Order 29 of CPC and hence,

deserves to be dismissed. The suit is also hit by principles of waiver

acquiescence and estoppel. It was also prayed that the plaintiff is not a

company incorporated under the Companies Act, 1956 and hence, the suit is

not maintainable.

7) It was further claimed that no regular payment was ever received by

the consumer /plaintiff & every month there was a huge amount remained as

balance. Due to non-payment of regular electricity bill the service connection

was disconnected on 16-05-2012 and afterwards part payment was accepted

to reduce balance. It was further stated that the revised bill was served as

per audit report in line of AERC Guide Lines Code 4.2.2.4. The bill dated 30-

03-2013 was legally and validly served on the plaintiff company and the

plaintiff is liable under law to pay the same. AERC guide lines Code 4.2.2.4. is

procedure for assessment of consumption in case of incorrect and stopped

meter. In the event of any meter reading found prima facie incorrect, where

actual errors of reading cannot be ascertained, the assessed quantity of

energy consumed shall be determined by taking the average consumption for

the previous months, succeeding the date of which the defect was detected

or the next three months after correction whichever is higher and bill is

prepared and presented accordingly. The defendant No.3 complied with the

provisions of AERC guidelines & prepared the bill and served to the plaintiff.

There was no mismanagement in the billing system & due to defects detected

in the meter average bill was prepared/served as per rule w.e.f 28-02-2010 to

31-08-2010. Furthermore, the plaintiff misread and misapplied the provision

Page 6 of 19

of s.56(2) Electricity Act & as per law an amount becomes first due when it is

qualified and claimed by raising a bill. As such the revised bill dated 30-03-

2013 become first due on 30-03-2013 and as such the bill is well within time

and not time barred as per provision of Section 56 (2) of EC Act. Hence,

defendants prayed for dismissal of the suit.

8) Upon perusal of the pleadings of both parties and hearing learned

advocates of both sides, the following issues are settled:

1. Whether there is any cause of action for the suit?

2. Whether the suit is maintainable in its present form?

3. Whether the defendant Company has any right to raise the Audit

objection Bill dated 30-03-2013 No.35105 for Rs.2,65,774/- against

the plaintiff?

4. Whether the suit is barred by limitation more particularly u/s 56

(2) of the Electricity Act, 2003?

5. Whether the plaintiff is entitled to the decree, as prayed for?

6. To what other relief (s) the parties are entitled?

9) During trial, the plaintiff examined Sri Parminder Singh as PW-1 and

exhibited 10 documents, as mentioned in the appendix. The defendant-side

also examined Mir Rafiul Amin as DW-1 and 3 documents were exhibited.

DISCUSSION, DECISION AND REASONS THEREOF :-

10) I have gone through the pleadings minutely and also perused the

documents submitted by both the sides. Also heard the arguments forwarded

by the ld. counsel for the plaintiff and the defendants. Thus, based on the

Page 7 of 19

rival contentions the issues are discussed herein below. Pertinent to mention

that for easier appreciation of evidence and for sake of brevity, the issues

might not be discussed chronologically.

Issue no. 1: Whether there is any cause of action for the suit?

11) This issue was framed because all the defendants challenged that

there is no cause of action for the suit. Even though none of the parties

forwarded any argument in this regard, this issue is discussed so that it

doesn‟t become a point of contention on a future date.

My Decision & Reasons Thereof:

12) For a cause of action to exist it is essential for the plaintiff to mention

such particulars in his plaint as to enable the defendant and the Court to

ascertain whether in fact or law the cause of action did arise as alleged or

not. As can be understood from the perusal of the plaint and a written

statement, the plaintiff is a consumer of the power supplied by defendant

company APDCL. The defendant raised a revised bill, which the plaintiff

challenges in this suit, as they believe that the revised bill is illegal, in valid &

also time-barred. However, the defendants claim that the revised bill has

been rightly raised as per laid procedure and the suit is not time-barred.

Thus, it appears that there is a probable cause of action for the suit. Thus,

issue no. 1 is settled in favour of the plaintiff.

Issue no. 2: Whether the suit is maintainable in its present form?

13) This issue was framed because the defendants claimed that the suit is

not maintainable. Defendant challenged the maintainability of the suit on the

Page 8 of 19

point that the plaintiff claim themselves to be a company incorporated,

however, they have not complied with the provisions of Order 29 of CPC.

Argument on Behalf of Plaintiff:

14) The plaintiff had submitted written-argument and had mentioned that

the suit has been instituted by duly authorized, person same being PW1

Parmender Singh, and therefore the provisions of law has been complied

with. It was also submitted that the plaintiff company has submitted all

necessary documents to prove that they are competent to file this suit and

that the suit is maintainable.

Argument on Behalf of Defendants:

15) On the other hand, it was argued on behalf of the defendant that

plaintiff company must prove that it is a juristic person & capable of filing the

suit or contesting it, but plaintiff failed to do so. Ext.1 is the 2nd Certificate of

Incorporation of the company & PW1 accepted that the 1st Incorporation

Certificate has not been submitted. If that is the case, how can it be believed

that it is actually an incorporated company? Plaintiff also failed to prove that

it is a registered company & if not registered then it is barred from instituting

this suit. Furthermore, the plaint & the evidence-in-affidavit of PW-1 show

that it has been signed as Manager of Monmohinipur Tea Estate & not as for

the company. PW1 Parmender Singh claimed he obtained Power of Attorney

from Monmohinipur Tea Estate to file the suit but not directly from the

company. Furthermore, the Power of Attorney was given by ITP Ltd. and

mentioned Monmohinipur Tea Estate as factory lessee (Ext.3). No company

resolution was ever taken to file this suit or any authority given to anyone to

Page 9 of 19

file the suit & this fact was admitted by PW1. Thus, when PW1 has not been

authorized to file the suit then how can this suit be maintainable?

16) It was also argued on behalf of the defendant that Ext.2 is the

Memorandum of Association & Article of Association of ITP Ltd., but it is only

a single sheet of page. Thus, this document has no legal value itself. It was

also argued that the plaint is not clear as how the ITP Ltd. came into

existence and even the documents are not sufficient to prove it. Furthermore,

PW1 has no idea as to how ITP Ltd. was formed & explains the relation

between ITP Ltd. & the Tea Estate. Under such circumstances, it is clear that

the plaintiff couldn‟t prove its existence itself, leave alone the question of

proving their other claims. Thus, it is clear that O.29 r.1 CPC has not been

complied with & therefore, the suit not maintainable.

My Decision & Reasons Thereof:

17) As per law, all suits of civil nature are maintainable, unless it has been

specifically barred by statute. Defendant has taken-up two line of defence to

claim that the suit is not maintainable – (1) Plaintiff couldn‟t proof that it is a

incorporated company (2) Non-compliance of O.29 r.1 CPC. I have gone

through the Incorporation certificate ITP Ltd. (Ext.1), Memorandum of

Association and Articles of Association (Ext.2) & Power of Attorney dated 03-

01-2008 (Ext.3).

18) It is true, as pointed out by ld. counsel for the defendant, that Ext.1 is

the 2nd Certificate of Incorporation of the company & the 1st Incorporation

Certificate has not been submitted and there are writing & overwriting on

Page 10 of 19

Ext.1. It is also true that Ext.2 is the 1st sheet of Memorandum of Association

& Article of Association of ITP Ltd. However, the question that arises is

whether this technical matter goes to the root of the case and makes it not

maintainable? My answer would be an emphatic „no‟. O.29 CPC. O.29 r.1 CPC

reads as follows, “In suits by or against a corporation, any pleading may be

signed and verified on behalf of the corporation by the secretary or by any

director or „other principal officer of the corporation who is able to depose to

the facts other case.” Here the word „corporation‟ has not been used in a

restricted sense and is for means legal persons. My view finds support in the

decisoin in Hakam Singh v. Gammon (India) Ltd., (1971) 1 SCC 286 where a

division bench of Hon‟ble Apex Court held that, “The Code of Civil Procedure

uses the expression “corporation” as meaning a legal person and includes a

company registered under the Indian Companies Act. Order 29 of the Code of

Civil Procedure deals with suits by or against a corporation and there is

nothing in the Code of Civil Procedure that a corporation referred to under

Order 20 means only a statutory corporation and not a company registered

under the Indian Companies Act.”Pertinent to mention that in this said

decision the Hon‟ble Court was dealing with a registered company and

therefore used it as an example and the main operative word here is the

observation that “The Code of Civil Procedure uses the expression

“corporation” as meaning a legal person…”Thus, it is clear that irrespective of

the fact when and how the company was incorporated or not, the plainitff

company can be considered a „corporation‟ u/O.29 r.1 CPC.

Page 11 of 19

19) Coming to question whether PW-1 has a proper Power of Attorney &

whether he has been authorized to institute the suit. The Ext.3 is the Power

of Attorney and it reveals that PW-1 has been given the Power of Attorney &

M/s ITP Ltd. metions itself to be the „lessee‟ of Monmohinipur T.E. I have

considered the objections raised by the defendant side that PW-1 Parmender

Singh has no authority to institute this suit and the Ext.3 is not a valid

document authorising him to institute the suit against the defendants. A

Division Bench of Hon‟ble Supreme Court in the case of United Bank Of India

Vs Naresh Kumar & Ors., (1996) 6 SCC 660 dealt with a similar matter where

there was dispute regarding the Power of Attorney issued and a objection

was raised regarding non-compliance of O.29 CPC. Hon‟ble Apex Court held

that, “Reading Order 6 Rule 14 together with Order 29 Rule 1 of the Code of

Civil Procedure it would appear that even in the absence of any formal letter

of authority or power of attorney having been executed a person referred to

in Rule 1 of Order 29 can, by virtue of the office which he holds, sign and

verify the pleadings on behalf of the corporation. In addition thereto and

dehors Order 29 Rule 1 of the Code of Civil Procedure, as a company is a

juristic entity, it can duly authorise any person to sign the plaint or the written

statement on its behalf and this would be regarded as sufficient compliance

with the provisions of Order 6 Rule 14 of the Code of Civil Procedure. A

person may be expressly authorised to sign the pleadings on behalf of the

company, for example by the Board of Directors passing a resolution to that

effect or by a power of attorney being executed in favour of any individual. In

absence thereof and in cases where pleadings have been signed by one of its

officers a corporation can ratify the said action of its officer in signing the

Page 12 of 19

pleadings. Such ratification can be express or implied. The court can, on the

basis of the evidence on record, and after taking all the circumstances of the

case, specially with regard to the conduct of the trial, come to the conclusion

that the corporation had ratified the act of signing of the pleading by its

officer.” Thus, we can safely say that PW-1 was authorized to institue the suit

and pursue the same on behalf of the plaintiff company.

20) Another pertinent point I deem it necessary to state is that I don‟t see

any justifiable ground why an employee (PW-1 Parmender Singh) will institute

a suit and fight a legal battle against a giant like APDCL on his own choice

and without authority from the company & it can be presumed that he has

been authorized to file the plaint & fight the legal battle or his act has been

ratified by the company. My view finds support in the decision of Apex Court

in United Bank Of India Vs Naresh Kumar & Ors., (Supra) wherein the Court

observed that, “The suit had been filed in the name of the appellant

company; full amount of court fee had been paid by the appellant-Bank;

documentary as well as oral evidence had been led on behalf of the appellant

and the trial of the suit continued for years. It is difficult, in these

circumstances, even to presume that the suit had been filed and tried without

the appellant having authorised the institution of the same. The only

reasonable conclusion which we can come to is that the person who instituted

the suit must have been authorised to sign the plaint and, in any case, it must

be held that the appellant had ratified his action in signing the plaint and

thereafter it continued with the suit.”

Page 13 of 19

21) In view of the above discussions I hold that the suit is maintainable &

hence, Issue no. 2 is settled in favour of the plaintiff.

Issue no. 3: Whether the defendant Company has any right to raise

the Audit Objection Bill dated 30-03-2013 No.35105 for

Rs.2,65,774/- against the plaintiff?

AND

Issue no.4: Whether the suit is barred by limitation more

particularly u/s 56 (2) of the Electricity Act, 2003?

22) Both these issues has been taken-up together as they are inter-related

and decision on them are based on same set of law & fact. The plaintiff have

challenged that the defendant company cannot raise an Audit Objection Bill &

that it is liable to be cancelled, mainly when, it is barred u/s 56 (2) of the

Electricity Act as it was not raised within the statutory period of 2 years from

the date when such sum became due & not being shown continuously

recoverable in the monthly energy bills as an arrear.

Arguments By Plaintiff Side:

23) It was argued on behalf of the plaintiff that defendant No.3 admitted

in written-statement that the bill in question was served on the plaintiff

garden on 30-03-2013 & it was in connection with arrear from 28-02-2010.

Thus, it is clearly time-barred. Furthermore, guidelines of AERC Code 4.2.2.4.

speak of procedure for assessment of consumption in case of incorrect and

stopped meter. However, the meter of plaintiff was neither incorrect nor

stopped because defendants official were regularly visiting the garden to

obtain the readings and thereafter bills were raised and accordingly payment

were made at the relevant point of time. Furthermore, it is not at all possible

for the auditors to detect the defect in the meter after 3 years. Evidences

Page 14 of 19

clearly revealed that the audit objection bill dated 30-03-2013 is for the

period February‟2010 to October‟2010 and there was failure on the part of the

defendant APDCL to show this „Audit Objection Bill‟ as an arrear in the current

bills, which ought to have been shown right from the month of March‟2010.

Moreover, there is no provision under the Electricity Act for „Audit Objection

Bill‟ or ad-hoc bill. Hence, it is illegal and unsustainable. It was also argued on

behalf of plaintiff that the defendant-side produced DW-1 Mr. Mir Rafiul Amin

Dewan, Area Manager, IRCA. He neither filed the written-statement, nor knew

anything about how this audit objection was raised by APDCL and he was not

a signatory to the current bills and „Audit Objection Bill‟.

24) It was further argued that it is a clear case within the popular maxim

„vigilantibus et non dormeintibus, jura subvermiunt‟ meaning „law always

assists the vigilant and not those who sleep over their right‟. In support of

their claim plaintiff relied on the decision of Hon‟ble Gauhati High Court in

Manipur Tea Company Vs. Assam State Electricity Board & Ors., (2015) 5 GLR

72. In the said decision the division bench of Hon‟ble Gauhati High Court

discussed s.56 (2) & s.185 (5) of the Electricity Act, 2003 & also the s.6

General Clauses Act, 1897. It was held that s.185 (5) Electricity Act read with

s.6 General Clauses Act saves the liability incurred by the petitioner under the

repealed Act. It was further held that s.56 (2) Electricity Act protects the

consumer from any amount due after a period of two years & it is not

recoverable unless continuously shown in monthly bills as arrears.

Arguments By Defenadant Side:

Page 15 of 19

25) It was argued on behalf of the defendants that the plaintiff was

always irregular in making payment of their dues and huge arrear is already

standing against them & hence, s.56 (2) Electricity Act has been complied

with & it has been shown as arrear. Furthermore, the revised bill has been

prepared as per laid procedure and there is no ambiguity in it and the

defendant company has right to claim the dues rightly payable to them.

My Decision & Reasons Thereof:

26) I firstly start by considering the objection raised by the plaintiff that

there is no provision under the Electricity Act for „Audit Objection Bill‟ or ad-

hoc bill, hence, it is illegal and unsustainable. Perusal of the written-

statement shows that the revised bill was served as per audit report in line of

AERC Guide Lines Code 4.2.2.4. & it lays down the procedure for assessment

of consumption in case of incorrect and stopped meter. In the event of any

meter reading found prima facie incorrect, where actual errors of reading

cannot be ascertained, the assessed quantity of energy consumed shall be

determined by taking the average consumption for the previous months,

succeeding the date of which the defect was detected or the next three

months after correction whichever is higher and bill is prepared and presented

accordingly. Due to defects detected in the meter, average bill was

prepared/served as per rule w.e.f 28-02-2010 to 31-08-2010. Thus, what can

be understood is that the energy company has a laid down procedure for

detection of incorrect and stopped meter & assessment of consumption. It is

seen Electricity Act and its corresponding Rules covers all matters relating to

power consumption, including calculation mechanism, correction of incorrect

meters & defects, etc. The term „Audit Objection Bill‟ per se may not find

expression in the Electricity Act or the Rules, however, what is implies that

Page 16 of 19

during Audit the defect was detected and subsequently this bill was raised.

However, use of a mis-norm doesn‟t invalidate a revised bill generated on a

defect being detected. Hence, this objection of the plaintiff is not sustainable.

27) Coming to the question whether the arrears has been shown

continuously in the bills, I have gone through the evidence of PW-1 and also

perused the documents submitted. The monthly bills for the Oct‟2012 to

Mar‟2013 has been submitted by the plaintiff and exhibited as Ext.5 – 10.

Perusal of these bills shows that each one of these bills shows arrears running

to lakhs of rupees and the plaintiff choose to pay only a meager part of it. For

e.g., monthly bill dated 12-11-2012 shows arrear (principal + surcharge) as

Rs.50,97,987/- & the total monthly bill coming to Rs.53,70,204/-, however,

the defendant choose to pay only Rs.2,27,833/-. Similar fate is seen in all the

other monthly bills submitted by the plaintiff. There is nothing on record to

show that plaintiff made any communication with defendants regarding non-

payment of these huge arrears. The monthly bills submitted by the plaintiff

(Ext.5 – 10) shows that each one of these bills shows arrears running to lakhs

of rupees & the burden was on the plaintiff to prove that the arrears reflected

in the monthly bills (Ext.5 – 10) doesn‟t relate to the dues of Feb‟2010 to

Sep‟2010, however, the plaintiff failed to discharge this burden. I‟ve also gone

through the documents annexed with Ext.4 (audit bill), which shows that it

reflects how the revised calculation was done. Pertinent to mention that the

plaintiff tried to mislead the Court by claiming that the plaintiff has paid all

dues regularly and no arrear pending. Thus, it appears that the plaintiff has

not come to the Court with clean hands.

Page 17 of 19

28) The Hon‟ble Gauhati High Court decision in Manipur Tea Company Vs.

Assam State Electricity Board & Ors. (supra) is a very relevant judgment

when it comes to s.56 (2) Electricity Act, but we have to understand that this

decision was purely on whether „sums due‟. However, the legal position is

different when it comes to revised bills or bills raised on some defect being

detected in the consumption. In the case of M/s Sheo Shakti Cement

Industries, Jharkhand–vs- Jharkhand Urga Vikas Nigam Limited & Ors, AIR

2016 Jharkhand 98 it was observed that, “Sub-section (2) makes it clear that

expression “no sum due” in sub-section (2) is confined to Section 56 only.

Thus, the sum due from the consumer is the amount for charge of electricity

which the consumer has neglected to pay. Section 56(2) refers to only such

amount which was within the knowledge of the Electricity Board/Nigam.

Moreover, it is well settled that a mistake in calculation no doubt can be

rectified at a subsequent stage.”

29) In view of the above discussions it is cleat that there can be no bar on

the defendant company from raising a revised bill on these unchallenged

arrears, as paying these bills is a statutory obligation of the consumer. Thus, I

have no hesitation in holding that defendant Company has right to raise the

Audit Objection Bill dated 30-03-2013 No.35105 for Rs.2,65,774/- against the

plaintiff & it is not time-barred u/s 56 (2) Electricity Act. Issue no.3 & 4 is

accordingly settled against the plaintiff.

Issue no. 5: Whether the plaintiff is entitled to the decree, as prayed for?

30) In view of the discussions above and from a discrete scrutiny of the

entire evidence on record, both oral and documentary, it appears that the

Page 18 of 19

plaintiff failed to prove that the defendant Company didn‟t have any right to

raise the Audit Objection Bill dated 30-03-2013 No.35105 for Rs.2,65,774/-

against the plaintiff & that it is not time-barred u/s 56 (2) Electricity Act.

Hence, it is held that the plaintiff is not entitled to the decree, as prayed for.

Hence, issue no.5 is decided against the plaintiff.

ORDER

THE suit is hereby dismissed. The parties will bear their own cost. Prepare a

decree accordingly.

Given under my hand & seal of the Court on the 11th August‟2017.

(Munmun B.Sarma)

Civil Judge

Tezpur, Sonitpur

Dictated and corrected by me.

(Munmun B.Sarma)

Civil Judge

Tezpur, Sonitpur

Dictation taken and transcribed be me:

(J. K Muru)

Steno.

Page 19 of 19

APPENDIX

Plaintiff Witness:

1) PW-1 : Sri Parminder Singh

Plaintiff Exhibits:

1) Ext.1 : Incorporation certificate ITP Ltd. 14-08-2007

2) Ext.2 : Memorandum of Association and Articles of Association

3) Ext.3 : Power of Attorney in favour of Mr. P.S. Seihra, 03-01-2008

4) Ext.4 : Audit related bill Rs.2,65,734/- with annexure, 30-03-2013

5) Ext.5 : Monthly bill Rs.2,19,640/- with money receipt, 14-10-2012

6) Ext.6 : Monthly bill Rs.2,27,833/- with money receipt, 12-11-2012

7) Ext.7 : Monthly bill Rs.3,33,059/- with money receipt, 14-12-2012

8) Ext.8 : Monthly bill Rs.2,89,559/- with money receipt, 16-01-2013

9) Ext.9 : Monthly bill Rs.2,59,397/- with money receipt, 13-02-2013

10) Ext.10 : Monthly bill Rs.2,52,759/- with money receipt, 15-03-2013

Defendant Witness:

1) PW-1 : Mir Rafiul Amin

Defendant Exhibits:

1) Ext.A : Payment status of Monmohinipur TE A.C.L.G.

2) Ext.B : Revised bill for consumption of Electrical energy.

3) Ext.C : Extract of Assam Gazette Extraordinary

(Munmun B.Sarma)

Civil Judge

Tezpur, Sonitpur


Recommended