+ All Categories
Home > Documents > Assessing Operational Flexibility in Systems with...

Assessing Operational Flexibility in Systems with...

Date post: 18-Oct-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
46
© 2015 Electric Power Research Institute, Inc. All rights reserved. Aidan Tuohy, PhD Project Manager/Technical Leader, EPRI Grid Operations and Planning University of Illinois Dept of Electrical and Computing Engineering Feb 22, 2015 Assessing Operational Flexibility in Systems with Increased Penetration of Variable Generation
Transcript
  • © 2015 Electric Power Research Institute, Inc. All rights reserved.

    Aidan Tuohy, PhD

    Project Manager/Technical Leader, EPRI

    Grid Operations and Planning

    University of Illinois Dept of Electrical

    and Computing Engineering

    Feb 22, 2015

    Assessing

    Operational Flexibility

    in Systems with

    Increased Penetration

    of Variable Generation

  • 2© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Grid Operations, Planning & Integration Area

    Grid Operations &

    Planning

    Bulk Integration Variable

    Generation

    Integration of Distributed

    Renewables

    Information & Comm.

    Technologies

    Transmission & Subs

    P162 HVDC

    PS-D HVDC Planning PS-A Modeling/Simulation

  • 3© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Control Center

    Bulk Renewable Integration R&D Focus

    Schedule, Dispatch

    & ReservesVoltage &

    Frequency Control

    Monitoring

    Analysis

    Decision Support

    Control

    New Methods/Tools

    Reliable & EfficientOperation

    Modeling &

    Protection

    0 20 40 60 80 100 1201.9

    2

    2.1

    Time (seconds)

    Vfd

    (pu

    )

    0 20 40 60 80 100 1200.95

    0.96

    Vt

    (pu)

    0 20 40 60 80 100 1201.95

    2

    Ifd

    (pu)

    Measured

    Fitted

    Variability & System

    Flexibility

    Conventional Gen

    Emerging Flexible Resources

    VG Power Management

  • 4© 2015 Electric Power Research Institute, Inc. All rights reserved.

    US Installed Solar PV

    Source: NREL Open PV Project; Bloomberg

    Total US: 16 GW

    2014 Install Est.: 6.5 GW

    CAISOWG Capacity = 5.8 GW

    PV Capacity = 8+ GW

    Peak Load = 48 GW

    HECOWG Capacity = 100 MW

    PV Capacity = 254 MW

    Peak Load = 1200 MW

    ERCOTWG Capacity = 11.2 GW

    PV Capacity = 250 MW

    Peak Load = 56 GW

  • 5© 2015 Electric Power Research Institute, Inc. All rights reserved.

    How much PV and Wind Is Possible?

    DOE SunShot Initiative Scenarios…

    Source: NREL, “Sensitivity of Rooftop PV Projections in the SunShot Vision Study to Market Assumptions”

    Optimistic, but policy objective PV assumptions, leads to

    Rooftop PV of 120 GW in 2030 & 240 GW in 2050.

  • 6© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Wind & PV Variability/Uncertainty Increases the Need for

    System Flexibility

    • It’s the Wind Ramp,

    Not the Ripple!

    • Forecasting Is Key

    • System must have

    ramping & cycling

    capabilities

    Source: Constructed from EIRGRID online data (www.eirgrid.com).

  • 7© 2015 Electric Power Research Institute, Inc. All rights reserved.

    0

    10.000

    20.000

    30.000

    40.000

    50.000

    60.000

    70.000

    80.000

    EE D

    Installiert EE D

    Jahres-Mittel EE

    MW

    PDE max. RE*: 37.642MW

    wind: 23.574MW

    PV: 14.069MW

    approx. 53% (14.04.2014)

    min. RE*: 148MW

    wind: 148MW

    PV: 0MW

    approx. 0,2% (17.02.2013)

    h-Values

    Renewable Energy

    Installed Capacity

    yearly average

    Sourc

    e: A

    mprion G

    mbH

    Germany - Installed Renewable Capacity versus

    Real Infeed Capacity since 2011

    Source: Amprion GmbH - CIGRE Session 2014 - Opening Panel | Klaus

    Kleinekorte | 25th August 2014 | © Amprion

  • 8© 2015 Electric Power Research Institute, Inc. All rights reserved.

    VER Integration Impacts

    Integration Issue Bulk Renewables

    (Wind and Solar)

    Distributed Resources

    (incl. rooftop PV)

    Scheduling & Dispatch

    Reserves & Frequency

    Regulation

    Resource Adequacy &

    System Flexibility

    Generation Cycling &

    Retirement

    System Voltage and

    Frequency Impacts

    Distribution Feeder

    Impacts

    Bulk Impacts of DER

    Utility Revenue &

    Business Models

  • 9© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Ensuring Sufficient System Flexibility

  • 10© 2015 Electric Power Research Institute, Inc. All rights reserved.

    The “Duck” Curve

    0

    500

    1.000

    1.500

    2.000

    2.500

    00

    .00

    01

    .00

    02

    .00

    03

    .00

    04

    .00

    05

    .00

    06

    .00

    07

    .00

    08

    .00

    09

    .00

    10

    .00

    11

    .00

    12

    .00

    13

    .00

    14

    .00

    15

    .00

    16

    .00

    17

    .00

    18

    .00

    19

    .00

    20

    .00

    21

    .00

    22

    .00

    23

    .00

    MW - Lunedì, 30 Agosto 2010

    MW - Lunedì, 29 Agosto 2011

    MW - Lunedì, 27 Agosto 2012

    Source: ENEL – Measured Data from Southern Italy

    Increased requirement for

    downward ramping capability in

    the morning

    More upward ramping

    capability is required when

    sun goes down

    Need lower minimum generation

    levels to avoid over-generation

    Not Just Resource Adequacy but the Adequacy of Resource of the Right Type

  • 11© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Flexibility Considerations & Metrics

    Many Regions (Regulators + ISO+ Utilities) Considering Future Flexibility Needs Now – Planning and Operations time frame

    Other systems experiencing similar needs (Renewables and/or Retirements)– Germany, Spain, New York, Hawaii etc.

    New flexible resources now becoming deployable in the bulk system

    California

    •Flexible Resource Adequacy

    •Flexi-Ramp Market Product

    •Long Term Procurement Plan

    Ireland

    • Long Term Flexibility Incentives

    Oregon

    • Integrated Resource Planning

    Process

    MISO

    • Market Rule Changes to

    Incentivize Flexibility

  • 12© 2015 Electric Power Research Institute, Inc. All rights reserved.

    EPRI Flexibility Metrics for system planning

    Multi-Level Approach– Levels 1 and 2 screening metrics– Levels 3 and 4 detailed metrics

    Four detailed metrics for planning time frame:– Periods of Flexibility Deficit – Expected Unserved Ramping – Well-being analysis – Insufficient Ramping Resource

    Expectation

    Post-processed metrics based on production cost study or historical data

    White paper available on epri.com

    Level 1

    • Variability Analysis & Flexibility Requirement

    Level2

    • Resource Flexibility Calculation

    Level 3

    • System Flexibility Metrics

    Level 4

    • Transmission and Fuel Constrained Flexibility

  • 13© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Level 2: What flexibility is available?

    Determine Ramping Available in Each Hour of the YearDifferent time scales, need to make assumptions

    about intertie and energy limited resources

  • 14© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Need to consider operational aspects…

    How you operate the system – including reserves – impacts on the availability of flexible capacity

  • 15© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Level 3: What is the net flexibility after ramps?

    Examine either net available flexibility or against extreme ramps

  • 16© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Level 3: Metric 1: Periods of Flexibility Deficit

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    0 2 4 6 8 10 12 14 16

    Pe

    rio

    ds

    of

    Fle

    xib

    ilit

    y D

    efi

    cit

    (%

    )

    Time Horizon (Hours)

    Example for extreme ramping requirements (97th percentile)

  • 17© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Level 3: Metric 2. Expected Ramping Deficit

    Expected value of ramping deficit values observed in each direction and time horizon

    8760

    1

    /,0||/,8760

    1 i

    i

    DCit iDeficitERD

  • 18© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Example Conclusions from Studies

    “Flexibility shortages seen over 60 minute interval”

    – Higher resolution data would be beneficial

    “Peak at 540 minutes indicates that the system may need to add additional capacity”

    – Unlikely that system leaves long start units offline when available

    – In that case the system had interties assumed inflexible

    Assumptions on intertie flexibility may alleviate issue

    Frequency of shortages for

  • 19© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Time of Day and Year

    Example Ramp Rates

    1 2 3 4 5 6 7 8 9 101112131415161718192021222324

    Jan

    Feb

    Mar

    Apr

    May

    Jun

    Jul

    Aug

    Sep

    Oct

    Nov

    Dec

    0

    200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    Flexibility resources will need to be available at different times of day and year depending on system requirements

    Max 1 hour up ramps for each hourly interval in a given month

    Based on example data from Northwest US

    Calculate for different time intervals, up and down ramping

  • 20© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Demand Response as Flexible Resource

    Types of Loads:– What will be available and when?

    – How long will it be available for?

    – How is it controlled?

    – Will be examined in this project and quantified for case studies

    – Can contribute to system operators assessment of DR as a resource for providing operational flexibility

    DR operations:– Ramp limits

    – Call rate limits

    – Energy limits

    – Duration limits

    – Time of day/week/year availability

    – Efficiency of pre-loading & make up energy

    System Operators will need to be able to characterize if and how DR can provide operational flexibility

  • 21© 2015 Electric Power Research Institute, Inc. All rights reserved.

    What about storage?

    Storage is a very flexible resource

    But also very expensive and inefficient

    Need to identify key places where storage will play a role in aiding integration of VG

    Still in progress – as more VG comes online, storage becomes more attractive

  • 22© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Today

    Energy

    Capacity

    Ancillary Services

    Future ?

    Energy

    Capacity

    Ancillary Services

    Central Station Energy StorageDemand Response

    Value of Capacity and Services

    Variable Generation

  • 23© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Increased variation in system conditions

    7,2

    50

    8,0

    00

    8,7

    50

    9,5

    00

    10,2

    50

    11,0

    00

    11,7

    50

    12,5

    00

    13,2

    50

    14,0

    00

    14,7

    50

    15,5

    00

    16,2

    50

    17,0

    00

    17,7

    50

    18,5

    00

    19,2

    50

    20,0

    00

    20,7

    50

    21,5

    00

    1

    10

    100

    1000

    0

    800

    1,600

    2,400

    3,200

    4,000

    4,800

    5,600

    6,400

    Region Load (MW)

    Frequency of Occurence

    Renewable Output (MW)

    100-1000

    10-100

    1-10

    Low probability,

    high impact events

    Low probability,

    high impact events

    Average system conditions

  • 24© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Ongoing and future work

    Impact of transmission constraints on system flexibility adequacy

    – Working with Ecco International to demonstrate how metrics can consider flexibility and how transmission can be a flexibility resource

    Flexibility from Energy Limited Resources

    – How do demand response, storage, hydro etc provide flexibility?

    Case Studies to demonstrate framework and ‘baseline’ flexibility

    Potential future directions:

    – Gas network and interaction with gas markets

    – Transmission planning interaction with resource adequacy

    – Operational versus planning issues – making sense of why there is insufficient flexibility

    – Markets for incentivizing flexibility (see next section)

  • 25© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Managing Uncertainty in Operations

    Forecasting Solar and Operational Tools for Reserve Procurement

  • 26© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Responding to Variability

    Frequency

    Droop

    AGCCapacity

    Reserves

    Operating

    Reserve

    Spinning

    Reserve

    Va

    riabili

    ty &

    Uncert

    ain

    ty (

    MW

    )

    1 day 4 hr 30 min 5 min 10 s 0 s

    Energy Storage

    Intelligent Distribution Devices

    Demand Response

    Inertia

    Governor Response

    Regulating Units

    Hydro

    Simple-Cycle GT

    Combined Cycle

    Warm ST

    Cold ST

    Source: Russ Philbrick, PES General Meeting, Detroit, July 2011

  • 27© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Solar Forecasting – Texas solar plants

  • 28© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Daily Mean Absolute Percentage Error

    Many other metrics could be calculated – research needed

    the best ways to assess forecast accuracy and value

    Weekly MAE shows range of performance of individual and combined forecasts

    Difficult to forecast distributed PV, but may have some geographic diversity?

  • 29© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Operating With Increased Uncertainty

    Source: Pierre Pinson, DTU, Denmark

    Average day ahead error: 8%-10% for wind farm, 4% for system

    Ramp error: Over 50% for large ramps

  • 30© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Ancillary Services/ Reserves – Industry Rethink

    FlexiRamp

    – Reserving flexible capacity for use in real time

    – New methods to quantify requirements

    Ramp Product & Look Ahead Dispatch

    – Similar requirement to California ISO

    Ancillary Service Review

    – Wide scale reorganization of ancillary services

    Cooperative balancing in Europe, CAISO /Pacificorp

    Other methods being developed in BPA, HECO, etc

  • 31© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Flexible ramping reserves

    Requirements

    based on short-

    time variability

    and uncertainty

    – Confidence

    intervals inform

    requirements

    – Demand

    curves for

    flexibility

    31

    Based on offline analysis will be included in markets soon

  • 32© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Reserve Determination for VG - Survey

    • Many areas already considering wind and/or PV

    • Multiple manners to consider:

    • Static versus dynamic

    • Forecasted versus historical

    • Scheduling & dispatch practices also matter

    Broad Spectrum of Approaches Being Used

  • 33© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Methods for managing uncertainty

    Static

    Reserve

    Dynamic

    Reserve

    No

    Reserve

    Stochastic

    UC

    Re

    liab

    ility

    /effic

    ien

    cy im

    pro

    vem

    en

    t

    Computation time

  • 34© 2015 Electric Power Research Institute, Inc. All rights reserved.

    EXISTING

    NEW

    EPRI project - Stochastic Reserve Procurement Process

    System

    Data

    Hour-Ahead (HA)

    Deterministic

    Commitment

    Intra-Day

    (ID)Determinist

    ic Commitment

    Forecast

    Probabilistic

    Data

    Real Time

    (RT) Dispatch

    (ID_ST)

    Reserve

    Determination

    Integrate probabilistic information into existing deterministic processes

    Day-Ahead (DA)

    Deterministic

    Commitment

  • 35© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Overview of multi cycle modeling

    Updated information in each cycle data requirement

    Updated unit schedules as time progresses

    Fewer options available to meet errors

    Models consumption of load following type reserve

    Source: Russ Philbrick, Utility Variable Generation Working Group, April 16, 2012, San Diego

    Cycle 1: ~4 HA

    Cycle 2: 90 MA

    Cycle 3: Real time

  • 36© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Stochastic Scenario Development

    Step 1: Probabilistic

    Site Forecasts

    Step 2: Probabilistic

    Aggregate Forecast

    Step 3: Forecast

    Trajectories

    MW

    MW

    MW

    MW

    Time

    Prob.

    Prob.

    Prob.

    Coherent scenarios with

    trajectory for each site

  • 37© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Stochastic Multi Cycle

    LFU and LFD Procurement

    Load Following procurement seen to follow solar forecast uncertainty.

  • 38© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Findings from Stochastic and Multi-Cycle Modeling

    1. Important to replicate the time constraints associated with each

    type of resource on multiple time horizons

    – As uncertainty is realized, dispatch and commitments may need to

    change.

    2. Choose reserve procurement policies which cover the

    uncertainty at each time

    – E.g. load following reserve should be held by online units as

    commitment is not possible when the reserve is to be released

    – Choices relating to when and how to reserve are released can also

    impact on energy prices.

    3. Stochastic Modeling is achievable and realistic

    – May want to use stochastic methods to inform deterministic process

    at first to improve operators understanding and comfort

  • 39© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Overview of the Integrated

    Grid Benefit/Cost

    Framework

    An

    Integrated

    Grid

  • 40© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Integrated Approach to Deploying DER

    Consistent, transparent framework for

    assessing benefits/costs of

    transitioning to an Integrated Grid.

    An

    Integrated

    Grid

  • 41© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Strategic Planning with DER

    Value of

    Solar?

    Storage

    Deployment?

    Community

    Solar?

    Smart Inverter

    Cost/Benefit?

    Proactively

    Upgrade?

    Research Questions Core Assumptions

    Study

    Timeframe

    Regulatory

    Framework

    Resource Mix

    Expected DER

    Growth

    Environmental

    Impact

    Analytical process must be consistent, repeatable, and transparent

  • 42© 2015 Electric Power Research Institute, Inc. All rights reserved.

    EPRI’s Integrated Grid Benefit-Cost Framework

    Hosting

    CapacityEnergy

    Thermal

    Capacity

    Distribution System

    Bulk System

    Customer or

    Owner

    Cost/Benefits

    Societal

    Costs/Benefits

    Benefit/Cost

    1 4

    5

    3

    2

    6

    Core Assumptions

    Adoption/

    Deployment

    Scenarios

    Market

    Conditions

    Resource

    Adequacy

    Flexibility

    Operational Practices &

    Simulation

    Transmission

    Performance

    Transmission

    Expansion

    System

    Net Costs

    System

    Benefits

    Reliability

  • 43© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Hosting

    CapacityEnergy

    Thermal

    Capacity

    Distribution System

    Bulk System

    Customer or

    Owner

    Cost/Benefits

    Societal

    Costs/Benefit

    s

    Benefit/Cost

    1 4

    5

    3

    2

    6

    Core Assumptions

    Adoption/

    Deployment

    Scenarios

    Market

    Conditions

    Resource

    Adequacy

    Flexibility

    Operational Practices & Simulation

    Transmission

    Performance

    Transmission

    Expansion

    System

    Net Costs

    System

    Benefits

    Reliability

    Integrated Grid Benefit Cost Framework

    B

    Feeder Performance Characterization

    Feeder Hosting Capacity Analysis

    Feeder Clustering Based on Hosting

    Feeder Clustering Based on Energy

    Impacts

    Capacity Analysis

    Energy Analysis on Select Feeders

    Losses/Consumption Results Extrapolated

    to System

    Mitigation Evaluation

    Benefit/Cost Analysis

    Bulk System Analysis

    Feeder Models

    Load Data

    Hosting Capacity Analysis

    Energy Analysis

    Capacity Analysis

    Asset Deferral

    DER Performance Characterization

    DER Data

    Optimal Hosting Capacity Location

    B

    C

    D

    Reliability Analysis

    Reliability Analysis

    E

    Substation – Level Hosting Capacity for

    DER

    Feeder-Specific Hosting Capacity for

    DER

    A

    Transmission System

    Performance Studies

    DER Scenarios

    Resource Adequacy

    Existing SystemModel(s)

    Load Forecasts

    Variability Profiles

    Existing Generation

    Existing Network Model

    Resource Epxansion

    LOLE/Reserve Margin & Capacity

    Credit

    New Resources/Expansion

    Plan

    Thermal / Voltage Impacts

    Operational Simulations

    Resource Dispatches

    Transmission System

    Upgrades

    Technology options

    Transmission Expansion

    Losses

    Reliability Impacts

    Reserve & Operational

    Changes

    LOLE/Reserve Margin & Capacity

    Credit

    New Reserve & Operational

    Modes

    Integrated Grid

    Bulk System

    Analysis

    Framework

    Costs of new resources

    Production Costs & Marginal

    Costs

    Costs of mitigation/upgrades

    Cost of Losses

    Cost of Base Case

    Cost of Scenario

    System Flexibility

    Assessment

    Flexibility Metrics

    Line Type Legend

    Data Input

    Final Result

    Feed-Forward Result

    Feed Back Result

    Frequency Impacts

    Hosting Capacity PV & Demand

    Profiles (See Fig. 5.3)

    PQ & Protection Impacts

  • 44© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Transmission System

    Performance Studies

    DER Scenarios

    Resource Adequacy

    Existing SystemModel(s)

    Load Forecasts

    Variability Profiles

    Existing Generation

    Existing Network Model

    Resource Epxansion

    LOLE/Reserve Margin & Capacity

    Credit

    New Resources/Expansion

    Plan

    Thermal / Voltage Impacts

    Operational Simulations

    Resource Dispatches

    Transmission System

    Upgrades

    Technology options

    Transmission Expansion

    Losses

    Reliability Impacts

    Reserve & Operational

    Changes

    LOLE/Reserve Margin & Capacity

    Credit

    New Reserve & Operational

    Modes

    Integrated Grid

    Bulk System

    Analysis

    Framework

    Costs of new resources

    Production Costs & Marginal

    Costs

    Costs of mitigation/upgrades

    Cost of Losses

    Cost of Base Case

    Cost of Scenario

    System Flexibility

    Assessment

    Flexibility Metrics

    Line Type Legend

    Data Input

    Final Result

    Feed-Forward Result

    Feed Back Result

    Frequency Impacts

    Hosting Capacity PV & Demand

    Profiles (See Fig. 5.3)

    PQ & Protection Impacts

    Integrated Grid: Bulk System Analysis

    1 RESOURCE ADEQUACY

    2 FLEXIBILITY3 OPERATIONAL

    SIMULATION

    4 TRANSMISSION PERFORMANCE

    5 TRANSMISSION EXPANSION

  • 45© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Summary/Conclusions

    Large penetrations of variable generations already being seeing and will continue to grow– Much of it is distributed which adds particular challenges

    Planning time frames will need to ensure sufficient operational flexibility is available– Need methods and metrics to assess flexibility adequacy

    – Consider demand response, energy storage, VG itself and transmission as well as conventional generation

    Operational planning and market operations will see increased uncertainty– Requires additional operating reserves to manage wind/solar in appropriate time

    scales

    – New methods for scheduling and dispatch stochastic or other

    Frameworks to assess the impacts and benefits of new technologies– Consider distribution, transmission and economics

    – Fully integrate rather than just interconnect new resources

  • 46© 2015 Electric Power Research Institute, Inc. All rights reserved.

    Together…Shaping the Future of Electricity


Recommended