Asset Information Management System (AIMS) Report
Agency Reconciliation of Maintenance Schedules
The City of New York Office of Management and Budget Mark Page, Director Fiscal Year 2007
RECONCILIATION SUMMARY 1
Introduction …….…….…….…….…….…….…….…….…….…….… 1
2008-2011 “State of Good Repair” Needs Capital Reconciliation ……. 3
2008 Maintenance Needs Expense Reconciliation ……….…………… 9
APPENDICES
“State of Good Repair” Activities Reconciliation:
New York Public Library A1 …………………………….…..... Appendix A
Brooklyn Public Library B1 ……………………………....….... Appendix B
Queens Public Library C1 ……………………………….…..… Appendix C
Department of Education D1-57 ..……………………….…..… Appendix D
City University of New York E1-3 ..……………………….….. Appendix E
Police Department F1-15 ……………………………….……... Appendix F
Fire Department G1-2 .…………………………………..….….. Appendix G
Administration for Children’s Services H1 .……………...……. Appendix H
Department of Homeless Services I1-7 .………………...…….. Appendix I
Department of Correction J1-4 ………………………………… Appendix J
Human Resources Administration K1-2 ………………....……. Appendix K
Department of Cultural Affairs L1-8 .……....……………....… Appendix L
Department of Juvenile Justice M1 .…………….…..…….….... Appendix M
Department of Small Business Services N1- 5 …....…………… Appendix N
Department of Health & Mental Hygiene O1-3 .…………..….. Appendix O
Health and Hospitals Corporation P1-11 ..…………….…..……. Appendix P
Department of Sanitation Q1-7 ……………………………...… Appendix Q
Department of Transportation R1-11 .……………………..…... Appendix R
Department of Parks and Recreation S1-13 …………….….… Appendix S
Department of Citywide Administrative Services T1-6 .……... Appendix T
Assets to be Replaced/Abandoned U1-2 .…………………….... Appendix U
Table of Contents
This page left intentionally blank.
1
Introduction
The City of New York has reported on Major Portions of the City’s Fixed Assets through the AIMS Report for Fiscal Year 2007. The Executive Summary document published in October 2006 provides financially unconstrained repair and maintenance schedules on a Citywide and on an agency basis by classes of assets and special systems. In addition, a more detailed Asset Survey Report portrays funding needs required to achieve and maintain a “State of Good Repair” on an asset basis and is available for review at the Office of Management and Budget. The methodology used to compile the condition assessment and maintenance schedules is contained in the Executive Summary.
Based on the recommended funding projections in the Asset Survey Report, participating agencies were asked to indicate their respective Capital and Expense funding for the “State of Good Repair” and maintenance activities detailed in the schedules. It is important to note that the agencies’ planned activities indicated in this Agency Reconciliation do not represent specific amounts in the Budget. The results are presented here as comparisons between agencies’ planned activities and the Executive Summary’s recommendations.
Citywide “State of Good Repair” and Major Maintenance Needs
FY 2008-2011 Capital (“State of Good Repair”)
FY 2008 Expense (Major Maintenance)
Buildings 1,607,301,000 212,984,000
Piers, Bulkheads & Marinas 422,002,000 6,703,000
Bridges & Tunnels 991,276,000 17,529,000
Parks Systems 140,424,000 2,456,000
Streets & Highways 1,933,640,000 -
Special Systems* 46,730,000 58,955,000
Total 5,141,376,000 298,629,000
* includes street lighting, traffic signal systems, ferries, vessels and Rikers Island utilities.
Reconciliation Summary
2
Items Excluded from Study
While the study is comprehensive, a number of items and considerations were excluded from the condition review & costing estimates. They were not considered directly related to the structural integrity of the asset as defined by the Charter. These include but are not limited to:
• Most equipment (fixed and movable) • Special operating systems within assets • Aesthetic considerations • Landscaping and outdoor elements • Statuary or ornamental edifices • Components not readily observable or accessible by field engineers • Fire alarm and security systems • Handicapped access requirements • Information obtained through testing or probing • Asbestos identification and removal • Programmatic needs not related to structural integrity • Efficiency improvements • Swing space/phasing costs, or premium time costs on an as-needed basis • Components deficient in code or local law compliance that do not impact on the integrity
of the asset • Assets known to be scheduled for near-term total replacement
Asset Survey Report Context
The asset condition and maintenance schedule within the AIMS Report is not a budget document, but rather a broad, unconstrained analysis of a subset of general needs. It will serve as a planning tool and resource in addressing overall Citywide funding requirements. The report does not attempt in any manner to balance the City’s asset and infrastructure requirements against other important City needs, nor does it attempt to make any funding recommendations for different agencies. There is a general prioritization presented within individual assets of the relative importance of various repairs and maintenance items in terms of preserving the assets.
Due to the complexity of the analysis, the large scale of the project, the time frame for completion, the amount of estimation required, and the necessary methodology constraints, there are inherent limitations to the level of accuracy possible at the detailed asset and component level.
In this context it should be noted that the actual cost for a project may vary substantially from the amount estimated in this report when a detailed scope of work and cost estimate is completed. Agencies will not be restricted to any asset specific number contained in the reports when planning and developing their budget requests. It is further understood that there will be work items (i.e. programmatic) excluded from this study which may require additional expenditures.
3
As an annual reconciliation effort, agencies indicate their recently performed and planned activities as compared to the activities required to bring their assets up to a “State of Good Repair” which are listed in the Asset Survey Report and defined in the Executive Summary.
Responses were based on information available for the publication of the FY 2008 January Plan. These responses, together with their footnotes, represent a characterization of the agencies’ activities to achieve a “State of Good Repair”.
Agency Planned Activities Activities as estimated in the Asset Survey Report including those that are: a) Planned for
FY 2008-2011; b) Already performed since last survey; c) Being undertaken. Cost estimate of activities is not necessarily the amount funded in the Budget.
“State of Good Repair” Need Dollar amounts represented by cost estimates from the Asset Survey Report that are required
to bring the Agency’s assets included in the survey up to a “State of Good Repair”.
Percentage Agency Planned Activities/”State of Good Repair” Need
NEW YORK PUBLIC LIBRARY (NYPL) Number of Assets 14Total Square Footage 1,537,000sfAgency Planned Activities $3,484,000State of Good Repair Need $10,127,000Percentage 34%
BROOKLYN PUBLIC LIBRARY (BPL) Number of Assets 7Total Square Footage 518,000sfAgency Planned Activities $1,975,000State of Good Repair Need $6,624,000Percentage 30%
QUEENS PUBLIC LIBRARY (QPL) Number of Assets 3Total Square Footage 328,000sfAgency Planned Activities $606,000State of Good Repair Need $892,000Percentage 68%
2008-2011 "State of Good Repair" Needs Capital Reconciliation
4
DEPARTMENT OF EDUCATION (DOE)
Number of Assets 1,123 Total Square Footage 117,101,000sf Agency Planned Activities $196,304,000 State of Good Repair Need $784,663,000 Percentage 25% * DOE's Five Year Capital Plan is $13.1 billion. There is over $4.8 billion
spent on systems and programs such as science lab, physical fitness, and auditorium upgrades, technology, accessibility, room and kitchen areas conversions, school improvements and restructuring allocation (SIRA) that address state of good repair under different criteria. If above are included, the overall reconciliation percentage would be substantially higher.
CITY UNIVERSITY OF NEW YORK (CUNY) Number of Assets 92 Total Square Footage 5,851,000sf Linear Footage of Piers/Bulkheads 4,600ft Agency Planned Activities $10,481,00 State of Good Repair Need $43,311,000 Percentage 24%
NEW YORK POLICE DEPARTMENT (NYPD) Number of Assets 112 Total Square Footage 4,867,000sf Linear Footage of Piers, Bulkheads & Marinas 4,100ft Agency Planned Activities $34,226,000 State of Good Repair Need $37,140,000 Percentage 92%
NEW YORK FIRE DEPARTMENT (FDNY) Number of Assets 31 Total Square Footage 664,000sf Linear Footage of Piers/Bulkheads 1,000ft Agency Planned Activities $5,393,000 State of Good Repair Need $11,932,000 Percentage 45%
ADMINISTRATION FOR CHILDREN’S SERVICES (ACS) Number of Assets 10 Total Square Footage 291,000sf Agency Planned Activities $334,000 State of Good Repair Need $1,455,000 Percentage 23%
5
DEPARTMENT OF HOMELESS SERVICES (DHS) Number of Assets 60Total Square Footage 4,187,000sfAgency Planned Activities $17,974,000State of Good Repair Need $34,388,000Percentage 52%
DEPARTMENT OF CORRECTION (DOC) Number of Assets 42Total Square Footage 5,120,000sfLinear Footage of Piers, Bulkheads & Marinas 20,400ftAgency Planned Activities $57,660,000State of Good Repair Need $115,507,000Percentage 50%Rikers Island Utilities Agency Planned Activities $250,000State of Good Repair Need $9,640,000Percentage 3%
HUMAN RESOURCES ADMINISTRATION (HRA) Number of Assets 17Total Square Footage 846,000sfAgency Planned Activities $2,992,000State of Good Repair Need $5,227,000Percentage 57%
DEPARTMENT OF CULTURAL AFFAIRS (DCA) Number of Assets 282Total Square Footage 10,206,000sfAgency Planned Activities $29,024,000State of Good Repair Need $60,850,000Percentage 48%
DEPARTMENT OF JUVENILE JUSTICE (DJJ) Number of Assets 3Total Square Footage 400,000sfAgency Planned Activities $3,374,000State of Good Repair Need $4,529,000Percentage 74%
6
DEPARTMENT OF SMALL BUSINESS SERVICES (DSBS) Number of Assets 246 Total Square Footage 13,636,000sf Linear Footage of Piers/Bulkheads 149,100ft Agency Planned Activities $28,775,000 State of Good Repair Need $216,130,000 Percentage 13% * Most DSBS buildings are leased facilities and tenants could be responsible
for capital improvement.
DEPARTMENT OF HEALTH & MENTAL HYGIENE (DOHMH) Number of Assets 26 Total Square Footage 1,080,000sf Agency Planned Activities $10,230,000 State of Good Repair Need $11,213,000 Percentage 91%
HEALTH & HOSPITALS CORPORATION (HHC) Number of Assets 113 Total Square Footage 17,382,000sf Agency Planned Activities $59,839,000 State of Good Repair Need $178,113,000 Percentage 34%
DEPARTMENT OF SANITATION (DSNY) Number of Assets 96 Total Square Footage 4,959,000sf Linear Footage of Piers/Bulkheads 38,500ft Agency Planned Activities $17,683,000 State of Good Repair Need $73,456,000 Percentage 24%
DEPARTMENT OF TRANSPORTATION (DOT) Bridge & Tunnels Number of Assets 121 Total Deck Area 6,227,000sf Agency Planned Activities $988,846,000 State of Good Repair Need $988,846,000 Percentage 100%
7
DEPARTMENT OF TRANSPORTATION (DOT) -- Continued Streets & Highways Miles 6,500Agency Planned Activities $887,424,000State of Good Repair Need $1,933,640,000Percentage 46%* The agency planned total represents estimates based on average cost per
lane mile for reconstruction and resurfacing projects.
Facilities, Piers & Bulkheads Number of Assets 82Total Square Footage 2,566,000sfLinear Footage of Piers/Bulkheads 30,800ftAgency Planned Activities $8,375,000State of Good Repair Need $79,871,000Percentage 10%
Ferries Number of Assets 7Agency Planned Activities $35,100,000State of Good Repair Need $35,100,000Percentage 100%
DEPARTMENT OF PARKS & RECREATION (DPR) Number of Assets 817Total Square Footage 10,471,000sfLinear Footage of Piers, Bulkheads & Marinas 243,100ftAgency Planned Activities $64,469,000State of Good Repair Need $405,914,000Percentage 16%
DEPARTMENT OF CITYWIDE ADMINISTRATIVE SERVICES (DCAS) Number of Assets 49Total Square Footage 12,072,000sfLinear Footage of Piers/Bulkheads 4,400ftAgency Planned Activities $42,531,000State of Good Repair Need $92,807,000Percentage 46%
FY 2008-2011 Citywide "State of Good Repair" Needs Capital Reconciliation Summary (Based on FY 2007 Executive Summary)
# of Total Square Linear "State of Agency ReconciliationAgency Assets Footage Footage Good Repair" recently performed & %
Buildings Piers & Needs planned (FY 2008 - 2011) Bulkheads activities
New York Public Library (NYPL) 14 1,537,000 10,127,000 3,484,000 34% Brooklyn Public Library (BPL) 7 518,000 6,624,000 1,975,000 30% Queens Public Library (QPL) 3 328,000 892,000 606,000 68%
1 Department of Education (DOE) 1,123 117,101,000 784,663,000 196,304,000 25% City University (CUNY) 92 5,851,000 4,600 43,311,000 10,481,000 24% Police Department (NYPD) 112 4,867,000 4,100 37,140,000 34,226,000 92% Fire Department (FDNY) 31 664,000 1,000 11,932,000 5,393,000 45% Admin. for Children's Services (ACS) 10 291,000 1,455,000 334,000 23% Department of Homeless Services (DHS) 60 4,187,000 34,388,000 17,974,000 52% Department of Correction (DOC) 42 5,120,000 20,400 125,147,000 57,910,000 46% Human Resources Administration (HRA) 17 846,000 5,227,000 2,992,000 57% Department of Cultural Affairs (DCA) 282 10,206,000 60,850,000 29,024,000 48% Department of Juvenile Justice (DJJ) 3 400,000 4,529,000 3,374,000 74% Dept. of Small Business Services (DSBS) 246 13,636,000 149,100 216,130,000 28,775,000 13% Dept. of Health & Mental Hygiene (DOHMH) 26 1,080,000 11,213,000 10,230,000 91% Department of Sanitation (DSNY) 96 4,959,000 38,500 73,456,000 17,683,000 24% Department of Transportation (DOT) Bridges & Tunnels 121 6,227,000 (deck area) 988,846,000 988,846,000 100%
2 Streets & Highways (6,500 miles) 1,933,640,000 887,424,000 46% Facilities, Piers & Bulkheads 82 2,566,000 30,800 79,871,000 8,375,000 10% Ferries 7 35,100,000 35,100,000 100%
3 Dept. of Parks and Recreation (DPR) 817 10,471,000 243,100 405,914,000 64,469,000 16% Dept. of Citywide Admin. Services (DCAS) 49 12,072,000 4,400 92,807,000 42,531,000 46% Health and Hospitals Corporation (HHC) 113 17,382,000 178,113,000 59,839,000 34%
4 TOTAL 3,353 220,309,000 496,000 5,141,376,000 2,507,349,000
1. DOE's facility specific state of good repair projects will continue to be identified in the 5-year Plan based on annually resurveyed conditions.2. DOT planned total represents estimates based on average cost per lane mile for reconstruction and resurfacing projects. 3. DPR assets include buildings, park arches, park walls, and boardwalks.4. Activities recommended by the survey but not planned due to asset replacement/abandonment total $30 million, which equals approximately 0.6% of the total recommended.
E - 1
9
In addition to capital reconciliation agencies also participate in Citywide response to major maintenance activities in the expense budget. Unlike repair needs which are readily identifiable during surveys, maintenance activities can only be an estimated projection influenced by the components’ current condition, standard lives, and scheduling of corrective work. In general, the recommended amount represents a basic minimum to maintain the assets in a “State of Good Repair” and assumes that the Capital work identified is carried out forthwith.
The methodology for major maintenance is documented in the Executive Summary. In general, major maintenance is defined as those activities that should be performed at intervals of at least one year or greater to maintain the useful life and integrity of the component (i.e. repointing of brick in buildings). The majority of expense projects are periodic inspections and minor repairs that are done in-house or subcontracted out. Major maintenance activities for bridges, such as cleaning and debris removal, are exceptions which include large-scale identifiable items that should not only occur regularly, but would also have a direct impact on the structural integrity of the bridge over time.
As maintenance information may not be available or documented, agencies have been asked to report on broad categories (%) closest to their experience.
NEW YORK PUBLIC LIBRARY (NYPL)
Recommended Maintenance Need $1,281,000
Percentage Reported 25%
BROOKLYN PUBLIC LIBRARY (BPL)
Recommended Maintenance Need $1,031,000
Percentage Reported 36%
QUEENS PUBLIC LIBRARY (QPL)
Recommended Maintenance Need $669,000
Percentage Reported 50%
2008 Maintenance Needs Expense Reconciliation
10
DEPARTMENT OF EDUCATION (DOE)
Recommended Maintenance Need $116,659,000
Percentage Reported 13% * DOE will spend approximately $3.6 million on elevators, $3.8 million on
HVAC, $1.5 million on electrical systems, $6.1 million on major maintenance through custodial staff and $0.6 million on maintenance done by private facility management contractors.
CITY UNIVERSITY OF NEW YORK (CUNY)
Recommended Maintenance Need $7,848,000
Percentage Reported 61%
NEW YORK POLICE DEPARTMENT (NYPD)
Recommended Maintenance Need $10,231,000
Percentage Reported 74%
NEW YORK FIRE DEPARTMENT (FDNY)
Recommended Maintenance Need $2,044,000
Percentage Reported 95%
ADMINISTRATION FOR CHILDREN’S SERVICES (ACS)
Recommended Maintenance Need $659,000
Percentage Reported 11%
DEPARTMENT OF HOMELESS SERVICES (DHS)
Recommended Maintenance Need $4,633,000
Percentage Reported 100%
11
DEPARTMENT OF CORRECTION (DOC)
Facilities, Piers & Bulkheads
Recommended Maintenance Need $3,354,000
Percentage Reported 67%
Rikers Island Utilities
Recommended Maintenance Need $1,100,000
Percentage Reported 7%
* DOC will have major Rikers Island Utility work done using capital funds where eligible.
HUMAN RESOURCES ADMINISTRATION (HRA)
Recommended Maintenance Need $1,434,000
Percentage Reported 25%
DEPARTMENT OF CULTURAL AFFAIRS (DCA)
Recommended Maintenance Need $10,326,000
Percentage Reported 0%* DCA’s maintenance items are usually undertaken by individual cultural
institutions. No City funds are spent on major maintenance.
DEPARTMENT OF JUVENILE JUSTICE (DJJ)
Recommended Maintenance Need $311,000
Percentage Reported 73%
DEPARTMENT OF SMALL BUSINESS SERVICES (DSBS)
Recommended Maintenance Need $8,843,000
Percentage Reported 58%* DBS assets are currently maintained by EDC. Maintenance activities can
be paid for through revenues gained from rental stream or through rent concessions given to tenants.
DEPARTMENT OF HEALTH & MENTAL HYGIENE (DOHMH)
Recommended Maintenance Need $2,079,000
Percentage Reported 83%
12
HEALTH & HOSPITALS CORPORATION (HHC)
Recommended Maintenance Need $12,972,000
Percentage Reported 75%
DEPARTMENT OF SANITATION (DSNY)
Recommended Maintenance Need $4,902,000
Percentage Reported 10% * DOS maintenance work is mostly in response to safety concerns.
DEPARTMENT OF TRANSPORTATION (DOT)
Bridges & Tunnels Recommended Maintenance Need $16,054,000
Percentage Reported 86% * The reconciliation above does not reflect flag repairs on bridges included
in the inventory.
Street Lighting & Traffic Signal Systems Recommended Maintenance Need $54,030,000
Percentage Reported 100%
Facilities, Piers & Bulkheads Recommended Maintenance Need $2,203,000
Percentage Reported 27%
Ferries Recommended Maintenance Need $3,400,000
Percentage Reported 100%
DEPARTMENT OF PARKS & RECREATION (DPR)
Recommended Maintenance Need $21,483,000
Percentage Reported 13%
DEPARTMENT OF CITYWIDE ADMINISTRATIVE SERVICES (DCAS)
Recommended Maintenance Need $11,053,000
Percentage Reported 37%
FY 2008 Citywide Maintenance Needs Expense Reconciliation Summary (Based on FY 2007 Executive Summary)
FACILITIES RECONCILIATION OTHER SYSTEMS RECONCILIATIONElevators/ Special Agency
Agency Arch. Ext. Arch. Int. Electrical Mechanical Escalators Misc. Piers Bulkheads Marinas Bridges Ferries Systems Funded %
New York Public Library (NYPL) 209,000 307,000 195,000 393,000 177,000 320,000 25% Brooklyn Public Library (BPL) 323,000 407,000 47,000 192,000 62,000 374,000 36% Queens Public Library (QPL) 157,000 306,000 53,000 155,000 28,000 350,000 50% Department of Education (DOE) 21,829,000 38,784,000 14,403,000 37,993,000 3,650,000 15,600,000 13% City University (CUNY) 1,797,000 2,248,000 836,000 2,277,000 576,000 25,000 88,000 4,800,000 61% Police Department (NYPD) 3,241,000 3,559,000 955,000 1,995,000 304,000 130,000 6,000 41,000 7,565,000 74% Fire Department (FDNY) 463,000 684,000 120,000 248,000 12,000 39,000 49,000 5,000 425,000 1,940,000 95% Admin. for Children's Services (ACS) 235,000 218,000 23,000 128,000 55,000 71,000 11% Department of Homeless Services (DHS) 1,547,000 1,235,000 439,000 1,084,000 329,000 4,633,000 100% Department of Correction (DOC) 417,000 726,000 473,000 1,073,000 514,000 61,000 91,000 1,100,000 2,325,000 52% Human Resources Administration (HRA) 546,000 414,000 79,000 346,000 49,000 364,000 25% Department of Cultural Affairs (DCA) 3,120,000 2,340,000 1,124,000 2,272,000 828,000 643,000 - 0% Department of Juvenile Justice (DJJ) 95,000 63,000 50,000 73,000 30,000 226,000 73% Dept. of Small Business Services (DSBS) 1,667,000 1,574,000 1,200,000 1,083,000 413,000 19,000 734,000 2,153,000 5,136,000 58% Dept. of Health & Mental Hygiene (DOHMH) 637,000 504,000 340,000 216,000 202,000 179,000 1,730,000 83% Health and Hospitals Corporation (HHC) 2,519,000 2,222,000 1,927,000 3,149,000 3,117,000 37,000 9,729,000 75% Department of Sanitation (DSNY) 1,115,000 1,195,000 615,000 1,055,000 103,000 79,000 381,000 360,000 476,000 10% Department of Transportation (DOT) 517,000 464,000 186,000 294,000 67,000 355,000 145,000 175,000 16,054,000 3,400,000 54,030,000 71,823,000 95% Dept. of Parks and Recreation (DPR) 4,646,000 3,682,000 1,740,000 2,119,000 335,000 2,810,000 339,000 1,125,000 755,000 1,475,000 2,456,000 2,759,000 13% Dept. of Citywide Admin. Services (DCAS) 682,000 1,719,000 772,000 3,521,000 4,295,000 55,000 9,000 4,047,000 37%
Citywide Reconciliation Total 134,268,000 Citywide Needs 45,762,000 62,651,000 25,577,000 59,666,000 15,146,000 4,186,000 1,894,000 4,012,000 796,000 17,529,000 3,400,000 58,011,000 298,629,000
NOTES:- DOC will have major Rikers Island Utility work done using capital funds where eligible- DCA's maintenance items are usually undertaken by individual cultural institutions. No City funds are spent on major maintenance.- DSBS receives some maintenance funds in the form of rent credits from the agency's tenants.- DOT's $16,054,000 Bridges reconciliation is 86%. This does not reflect flag repairs on bridges included in the inventory.- DOT's $54,030,000 Streets Lighting & Traffic Signal Systems reconciliation is 100%.- DOT's $3,400,000 Ferries reconciliation is 100%.- DOC Special System is Rikers Island Utilities and the reconciliation is 7%.
E - 2
This page left intentionally blank.
Appendix
FMS ID/ Budget Code
Agency Activity Year
NEW YORK PUBLIC LIBRARY
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
A
000NPL000105/29/03Date of Last Survey:42 ST. & 5TH AVE.
CENTRAL RESEARCH LIBRARY - HUMANITIES & SOCIAL SCIENCES LIB
850LHSSLFACA2007Exterior WallsArchitecture Exterior 1,593,554
850EMERFACAD2005ParapetsArchitecture Exterior 1,257,948
Total Planned activities for $2,851,502NPL0001 000
000NPL000206/27/02Date of Last Survey:515 MALCOLM X BOULEVARD
SCHOMBURG CENTER FOR RESEARCH - IN BLACK CULTURE
850L-MROOF2003RoofArchitecture Exterior 95,980
Total Planned activities for $95,980NPL0002 000
000NPL000307/09/02Date of Last Survey:40 LINCOLN CENTER PLAZA
LIBRARY FOR THE PERFORMING ARTS - LINCOLN CENTER
850LC2LPAROOF2005RoofArchitecture Exterior 188,954
Total Planned activities for $188,954NPL0003 000
000NPL000804/04/03Date of Last Survey:20 WEST 53RD ST.
DONNELL - MEDIA CENTER
850LNC003DON2005RoofArchitecture Exterior 189,993
Total Planned activities for $189,993NPL0008 000
000NPL001012/12/05Date of Last Survey:503 WEST 145TH ST.
HAMILTON GRANGE - BRANCH LIBRARY
850LNM001HGR2006WindowsArchitecture Exterior 22,548
Total Planned activities for $22,548NPL0010 000
000NPL001205/29/03Date of Last Survey:455 FIFTH AVE.
MID-MANHATTAN - BRANCH LIBRARY
LNC3MDMAN2005RoofArchitecture Exterior 127,195
Total Planned activities for $127,195NPL0012 000
000NPL001404/19/04Date of Last Survey:192 EAST BROADWAY
SEWARD PARK - BRANCH LIBRARY
037LNC3SEWPK2006Interior WallsArchitecture Interior 7,540
Total Planned activities for $7,540NPL0014 000
Total Planned Activities for : $3,483,712NEW YORK PUBLIC LIBRARY
Total Required for "State of Good Repair" for : NEW YORK PUBLIC LIBRARY $10,127,481
Page A - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
BROOKLYN PUBLIC LIBRARY
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
B
000BPL000111/19/02Date of Last Survey:GRAND ARMY PLAZA
BROOKLYN CENTRAL LIBRARY -
LBCA03CEN2005Conversion EquipmentMechanical Heating 258,366
LBCA03CEN2005DistributionMechanical Heating 123,522
LBCA05CEN2008Terminal DevicesMechanical Heating 190,772
LBCA05CEN2008Conversion EquipmentMechanical Air Conditioning 680,513
LBCA05CEN2008DistributionMechanical Air Conditioning 288,217
LBCA05CEN2008Terminal DevicesMechanical Air Conditioning 250,474
LBCA05CEN2008DistributionMechanical Ventilation 25,448
Total Planned activities for $1,817,312BPL0001 000
000BPL000401/24/01Date of Last Survey:2115 OCEAN AVE.
KINGS HIGHWAY - BRANCH LIBRARY
LBCA00KHY2006WindowsArchitecture Exterior 157,677
Total Planned activities for $157,677BPL0004 000
Total Planned Activities for : $1,974,989BROOKLYN PUBLIC LIBRARY
Total Required for "State of Good Repair" for : BROOKLYN PUBLIC LIBRARY $6,624,193
Page B - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
QUEENS PUBLIC LIBRARY
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
C
000QPL000101/11/06Date of Last Survey:89-11 MERRICK BOULEVARD
QUEENS BOROUGH PUBLIC LIBRARY - CENTRAL LIBRARY
LQQ122CLD2009Exterior WallsArchitecture Exterior 81,933
LQQ122CLD2009ParapetsArchitecture Exterior 112,973
LQQ122CLD2009RoofArchitecture Exterior 94,535
LQQ122CLD2009Interior WallsArchitecture Interior 47,223
LQQ122CLD2009CeilingsArchitecture Interior 170,440
LQQ122CLD2009WiringElectrical Under 600 Volts 53,011
LQQ122CLD2009DistributionMechanical Ventilation 46,186
Total Planned activities for $606,301QPL0001 000
Total Planned Activities for : $606,301QUEENS PUBLIC LIBRARY
Total Required for "State of Good Repair" for : QUEENS PUBLIC LIBRARY $891,766
Page C - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE000101/05/05Date of Last Survey:8 HENRY STREET
P. S. 1 - M -
A00017556/E23622007RoofArchitecture Exterior 142,172
Total Planned activities for $142,172BOE0001 000
000BOE000201/27/04Date of Last Survey:122 HENRY STREET
P. S. 2 - M -
A00005505/E23622008WiringElectrical Under 600 Volts 109,148
Total Planned activities for $109,148BOE0002 000
000BOE000310/21/02Date of Last Survey:490 HUDSON STREET
P. S. 3 - M -
A00005521/E23622006Exterior WallsArchitecture Exterior 62,557
Total Planned activities for $62,557BOE0003 000
000BOE000412/22/04Date of Last Survey:45 EAST 81 STREET
P. S. 6 - M -
A00005563/E23622005SwitchgearElectrical Under 600 Volts 78,516
A00005563/E23622005WiringElectrical Under 600 Volts 74,737
Total Planned activities for $153,253BOE0004 000
000BOE000703/04/04Date of Last Survey:2581 ADAM CLAYTON POWELL BLVD.
I. S. 10 - M (TANDEM P.S.200-M) -
EMERG2005/E23622005DistributionMechanical Heating 298,786
EMERG2005/E23622005H/C Water PipingMechanical Plumbing 127,814
Total Planned activities for $426,600BOE0007 000
000BOE000911/21/03Date of Last Survey:1573 MADISON AVENUE
J. H. S. 13 - M -
M0131B3A/E23622006WindowsArchitecture Exterior 2,008,981
M0131B3A/E23622006RoofArchitecture Exterior 448,775
A00005654/E23622005WiringElectrical Under 600 Volts 141,807
Total Planned activities for $2,599,563BOE0009 000
000BOE001001/04/05Date of Last Survey:333 EAST 4 STREET
P. S. 15 - M -
A00005672/E23622008Exterior WallsArchitecture Exterior 117,665
A00005673/E23622009WiringElectrical Under 600 Volts 70,804
Total Planned activities for $188,469BOE0010 000
000BOE001101/07/05Date of Last Survey:328 WEST 48 STREET
I. S. 17 - M -
A00005695/E23622009WiringElectrical Under 600 Volts 107,772
Total Planned activities for $107,772BOE0011 000
000BOE001210/03/02Date of Last Survey:185 1ST AVENUE
P. S. 19 - M -
Page D - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
A00017591/E23622007WindowsArchitecture Exterior 832,206
Total Planned activities for $832,206BOE0012 000
000BOE001312/08/05Date of Last Survey:166 ESSEX STREET
P. S. 20 - M -
A00017598/E23622008ParapetsArchitecture Exterior 52,267
Total Planned activities for $52,267BOE0013 000
000BOE001401/13/04Date of Last Survey:111 COLUMBIA STREET
J. H. S. 22 - M -
A00127754/E23622009WindowsArchitecture Exterior 2,301,089
Total Planned activities for $2,301,089BOE0014 000
000BOE001509/26/02Date of Last Survey:145 STANTON STREET
J. H. S. 25 - M -
M0251E5A/E23622006Exterior WallsArchitecture Exterior 38,366
Total Planned activities for $38,366BOE0015 000
000BOE001801/10/05Date of Last Survey:281 9TH AVENUE
P. S. 33 - M -
A00020436/ED0012008RoofArchitecture Exterior 566,405
A00005831/E23622007SwitchgearElectrical Under 600 Volts 91,603
A00005831/E23622007WiringElectrical Under 600 Volts 103,403
Total Planned activities for $761,411BOE0018 000
000BOE002101/31/06Date of Last Survey:319 EAST 19 STREET
P. S. 40 - M -
A00005883/E23622007WiringElectrical Under 600 Volts 68,936
Total Planned activities for $68,936BOE0021 000
000BOE002403/28/06Date of Last Survey:509 WEST 129 STREET
J. H. S. 43 - M -
A00005931/E23622008Exterior WallsArchitecture Exterior 47,455
Total Planned activities for $47,455BOE0024 000
000BOE002612/06/02Date of Last Survey:2351 1ST AVENUE
J. H. S. 45 - M -
A00005964/E23622007WiringElectrical Under 600 Volts 159,465
Total Planned activities for $159,465BOE0026 000
000BOE002911/21/03Date of Last Survey:433 EAST 100 STREET
P. S. 50 - M (UDC & ECF) -
A00017620/E23622005WindowsArchitecture Exterior 105,719
Total Planned activities for $105,719BOE0029 000
000BOE003101/05/05Date of Last Survey:650 ACADEMY STREET
I. S. 52 - M -
M0521B3A/E23622006Exterior WallsArchitecture Exterior 54,252
Page D - 2
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
A00006064/E23622006FloorsArchitecture Interior 93,752
Total Planned activities for $148,004BOE0031 000
000BOE003201/28/05Date of Last Survey:103 WEST 107 STREET
I. S. 54 - M - (J. H. S. 54 - M)
A00006078/E23622007SwitchgearElectrical Under 600 Volts 104,689
A00006078/E23622007WiringElectrical Under 600 Volts 121,243
Total Planned activities for $225,932BOE0032 000
000BOE003801/04/05Date of Last Survey:610 EAST 12 STREET
P. S. 61 - M -
A00017942/E23622007Exterior WallsArchitecture Exterior 324,402
Total Planned activities for $324,402BOE0038 000
000BOE003910/01/02Date of Last Survey:121 EAST 3 STREET
P. S. 63 - M -
A00006198/E23622009FloorsArchitecture Interior 119,241
Total Planned activities for $119,241BOE0039 000
000BOE004010/01/02Date of Last Survey:600 EAST 6 STREET
P. S. 64 - M (OL 71) -
M0646EA/E23612003Exterior WallsArchitecture Exterior 101,755
A00006213/E23622008SwitchgearElectrical Under 600 Volts 105,998
A00006213/E23622008WiringElectrical Under 600 Volts 141,807
Total Planned activities for $349,560BOE0040 000
000BOE004211/19/04Date of Last Survey:421 EAST 88 STREET
P. S. 66 - M LANG & HEAR IMPRV -
A00017536/E23622007WindowsArchitecture Exterior 272,577
Total Planned activities for $272,577BOE0042 000
000BOE004304/06/04Date of Last Survey:333 WEST 17 STREET
J. H. S. 70 - M -
EMERG2005/E23622005RoofArchitecture Exterior 68,202
Total Planned activities for $68,202BOE0043 000
000BOE004511/26/03Date of Last Survey:735 WEST END AVENUE
P. S. 75 - M -
A00006275/E23622007SwitchgearElectrical Under 600 Volts 91,603
A00006275/E23622007WiringElectrical Under 600 Volts 109,148
Total Planned activities for $200,751BOE0045 000
000BOE004611/24/04Date of Last Survey:220 WEST 121 STREET
P. S. 76 - M -
A00006292/E23622006WiringElectrical Under 600 Volts 91,914
Total Planned activities for $91,914BOE0046 000
Page D - 3
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE004712/06/02Date of Last Survey:55 EAST 120 STREET
P. S. 79 - M (MULT HANDICAP) -
A00006309/E23622006WindowsArchitecture Exterior 555,376
A00006311/E23622006WiringElectrical Under 600 Volts 45,957
Total Planned activities for $601,333BOE0047 000
000BOE004803/29/06Date of Last Survey:212 W. 120TH ST
MID MANHT ADULT TRNG CTR - M -
A00127781/E23622009WindowsArchitecture Exterior 678,248
A00006331/E23622006FloorsArchitecture Interior 163,832
Total Planned activities for $842,080BOE0048 000
000BOE005110/11/05Date of Last Survey:160 WEST 78 STREET
P. S. 87 - M -
A00006380/E23622006WindowsArchitecture Exterior 643,089
A00006382/E23622006SwitchgearElectrical Under 600 Volts 100,055
A00006382/E23622006PanelboardsElectrical Under 600 Volts 90,984
A00006382/E23622006WiringElectrical Under 600 Volts 112,944
Total Planned activities for $947,072BOE0051 000
000BOE005310/28/03Date of Last Survey:222 WEST 134 STREET
P. S. 92 - M -
A00006415/E23622007WiringElectrical Under 600 Volts 127,979
Total Planned activities for $127,979BOE0053 000
000BOE005412/29/04Date of Last Survey:216 EAST 120 STREET
P. S. 96 - M -
EMERG2006/E23622007Exterior WallsArchitecture Exterior 73,374
A00006433/E23622007WindowsArchitecture Exterior 170,878
Total Planned activities for $244,252BOE0054 000
000BOE005501/13/04Date of Last Survey:515 EAST HOUSTON STREET
P. S. 97 - M -
A00006455/E23622009WiringElectrical Under 600 Volts 55,069
Total Planned activities for $55,069BOE0055 000
000BOE005610/19/05Date of Last Survey:512 WEST 212 STREET
P. S. 98 - M -
M0981E4A/E23622005Exterior WallsArchitecture Exterior 239,156
M0981E4A/E23622005ParapetsArchitecture Exterior 57,759
Total Planned activities for $296,915BOE0056 000
000BOE005802/27/06Date of Last Survey:141 EAST 111 STREET
P. S. 101 - M -
A00062418/E23622008ParapetsArchitecture Exterior 143,702
A00017611/E23622008RoofArchitecture Exterior 147,497
Page D - 4
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
A00006516/E23622006FloorsArchitecture Interior 200,745
Total Planned activities for $491,944BOE0058 000
000BOE006002/27/06Date of Last Survey:1615 MADISON AVENUE
P. S. 108 - M -
A00006561/E23622009SwitchgearElectrical Under 600 Volts 91,603
A00006561/E23622009WiringElectrical Under 600 Volts 103,403
Total Planned activities for $195,006BOE0060 000
000BOE006311/05/04Date of Last Survey:440 WEST 53 STREET
P. S. 111 - M -
A00017618/E23622007WindowsArchitecture Exterior 1,261,305
Total Planned activities for $1,261,305BOE0063 000
000BOE006611/26/02Date of Last Survey:586 WEST 177 STREET
P. S. 115 - M -
M1151E5A/E23612004Exterior WallsArchitecture Exterior 66,487
A00006628/E23622005WindowsArchitecture Exterior 97,191
Total Planned activities for $163,678BOE0066 000
000BOE006803/15/05Date of Last Survey:240 EAST 109 STREET
J. H. S. 117 - M -
A00017627/E23622007WindowsArchitecture Exterior 2,008,981
Total Planned activities for $2,008,981BOE0068 000
000BOE007012/28/04Date of Last Survey:232 EAST 103 STREET
P. S. 38 - M -
A00006694/E23622006SwitchgearElectrical Under 600 Volts 78,516
A00006694/E23622006WiringElectrical Under 600 Volts 55,069
Total Planned activities for $133,585BOE0070 000
000BOE007603/28/06Date of Last Survey:425 WEST 130 STREET
P. S. 129 - M -
A00006794/E23622008WiringElectrical Under 600 Volts 103,403
Total Planned activities for $103,403BOE0076 000
000BOE008112/29/05Date of Last Survey:293 EAST BROADWAY
P. S. 134 - M -
A00020897/E23622006CeilingsArchitecture Interior 54,075
Total Planned activities for $54,075BOE0081 000
000BOE008312/29/05Date of Last Survey:327 CHERRY STREET
P. S. 137 - M -
A00017775/E23622007WindowsArchitecture Exterior 588,128
Total Planned activities for $588,128BOE0083 000
000BOE008412/08/05Date of Last Survey:123 RIDGE STREET
P. S. 140 - M -
Page D - 5
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
A00006951/E23622008FloorsArchitecture Interior 56,961
Total Planned activities for $56,961BOE0084 000
000BOE008609/27/04Date of Last Survey:511 WEST 182 STREET
I. S. 143 - M -
A00006985/E23622007WiringElectrical Under 600 Volts 141,807
Total Planned activities for $141,807BOE0086 000
000BOE008711/24/04Date of Last Survey:134 WEST 122 STREET
P. S. 144 - M -
A00007002/E23622007WiringElectrical Under 600 Volts 86,170
Total Planned activities for $86,170BOE0087 000
000BOE008810/07/05Date of Last Survey:150 WEST 105 STREET
P. S. 145 - M -
A00017962/E23622007RoofArchitecture Exterior 47,813
Total Planned activities for $47,813BOE0088 000
000BOE008904/11/06Date of Last Survey:421 EAST 106 STREET
P. S. 146 - M -
A00007038/E23622007WiringElectrical Under 600 Volts 103,403
Total Planned activities for $103,403BOE0089 000
000BOE009509/10/03Date of Last Survey:319 EAST 117 STREET
P. S. 155 - M -
A00007105/E23622005WindowsArchitecture Exterior 616,514
Total Planned activities for $616,514BOE0095 000
000BOE009604/28/04Date of Last Survey:1458 YORK AVENUE
P. S. 158 - M -
A00020414/D0012006FloorsArchitecture Interior 49,729
Total Planned activities for $49,729BOE0096 000
000BOE009810/07/05Date of Last Survey:163 WEST 97 STREET
P. S. 163 - M -
A00007153/E23622007WiringElectrical Under 600 Volts 62,936
Total Planned activities for $62,936BOE0098 000
000BOE010005/15/03Date of Last Survey:234 WEST 109 STREET
P. S. 165 - M -
A00007189/E23622006WindowsArchitecture Exterior 1,460,521
A00007192/E23622006Terminal DevicesMechanical Heating 109,062
A00007192/E23622006Exhaust FansMechanical Ventilation 111,808
Total Planned activities for $1,681,391BOE0100 000
000BOE010110/11/05Date of Last Survey:132 WEST 89 STREET
P. S. 166 - M -
EMERG2005/E23622006Exterior WallsArchitecture Exterior 674,484
Page D - 6
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
A00017976/E23622006WindowsArchitecture Exterior 921,909
Total Planned activities for $1,596,393BOE0101 000
000BOE010212/06/05Date of Last Survey:220 EAST 76 STREET
J. H. S. 167 - M -
A00007223/E23622009SwitchgearElectrical Under 600 Volts 117,775
A00007223/E23622009PanelboardsElectrical Under 600 Volts 37,187
A00007223/E23622009WiringElectrical Under 600 Volts 141,807
Total Planned activities for $296,769BOE0102 000
000BOE010403/18/03Date of Last Survey:19 EAST 103 STREET
P. S. 171 - M -
A00007262/E23622009WiringElectrical Under 600 Volts 103,403
Total Planned activities for $103,403BOE0104 000
000BOE010605/02/05Date of Last Survey:175 WEST 134 STREET
P. S. 175 - M (P175M-SIE VII) -
A00017846/E23622007Exterior WallsArchitecture Exterior 191,596
A00017842/E23622007WindowsArchitecture Exterior 1,178,841
A00017835/E23622007RoofArchitecture Exterior 43,184
Total Planned activities for $1,413,621BOE0106 000
000BOE010710/28/03Date of Last Survey:370 WEST 120 STREET
P. S. 180 - M -
A00007324/E23622005WiringElectrical Under 600 Volts 103,403
A00007324/E23622005DistributionMechanical Heating 49,009
A00007325/E23622005DistributionMechanical Ventilation 60,580
Total Planned activities for $212,992BOE0107 000
000BOE010812/06/05Date of Last Survey:419 EAST 66 STREET
P. S. 183 - M -
A00007346/E23622008FloorsArchitecture Interior 143,275
A00020327/E23622007SwitchgearElectrical Under 600 Volts 78,516
A00020327/E23622007WiringElectrical Under 600 Volts 70,804
Total Planned activities for $292,595BOE0108 000
000BOE011304/23/04Date of Last Survey:311 EAST 82 STREET
P. S. 290 - M -
A00017876/E23622007WindowsArchitecture Exterior 602,760
A00007416/E23622007WiringElectrical Under 600 Volts 37,470
Total Planned activities for $640,230BOE0113 000
000BOE011405/15/03Date of Last Survey:210 WEST 61 STREET
P. S. 191 - M -
A00007430/E23622006RoofArchitecture Exterior 489,900
A00007432/E23622006SwitchgearElectrical Under 600 Volts 78,516
Page D - 7
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
A00007432/E23622006PanelboardsElectrical Under 600 Volts 35,699
A00007432/E23622006WiringElectrical Under 600 Volts 70,804
Total Planned activities for $674,919BOE0114 000
000BOE011511/10/05Date of Last Survey:500 WEST 138 STREET
P. S. 192 - M -
A00127816/E23622009ParapetsArchitecture Exterior 82,894
Total Planned activities for $82,894BOE0115 000
000BOE011602/03/03Date of Last Survey:244 WEST 144 STREET
P. S. 194 - M -
A00007467/E23622006SwitchgearElectrical Under 600 Volts 78,516
A00007467/E23622006PanelboardsElectrical Under 600 Volts 44,624
A00007467/E23622006WiringElectrical Under 600 Volts 74,737
Total Planned activities for $197,877BOE0116 000
000BOE011704/28/05Date of Last Survey:625 WEST 133 STREET
I. S. 195 - M (ECF) -
A00017982/E23622008Exterior WallsArchitecture Exterior 199,782
A00018119/E23622008WindowsArchitecture Exterior 412,612
A00018139/E23622008ParapetsArchitecture Exterior 75,287
A00018140/E23622008RoofArchitecture Exterior 1,453,422
Total Planned activities for $2,141,103BOE0117 000
000BOE012010/14/05Date of Last Survey:270 WEST 70 STREET
P. S. 199 - M -
A00017988/E23622008Exterior WallsArchitecture Exterior 61,547
A00017986/E23622008WindowsArchitecture Exterior 116,921
A00017984/E23622007RoofArchitecture Exterior 256,962
A00083030/D0012007WiringElectrical Under 600 Volts 80,425
Total Planned activities for $515,855BOE0120 000
000BOE012204/14/04Date of Last Survey:E. 116 ST. & F.D.R. DRIVE
MANHATTAN CTR. FOR MATH & SCI -M -
M4351E4A/E23622005Exterior WallsArchitecture Exterior 398,228
M4351E4A/E23622005WindowsArchitecture Exterior 1,159,984
A00007682/E23622005Conversion EquipmentMechanical Heating 89,974
Total Planned activities for $1,648,186BOE0122 000
000BOE012304/06/04Date of Last Survey:351 W. 18 ST
BAYARD RUSTIN HS FOR THE HUMAN-M - CHARLES EVANS HUGHES HS HUMAN.-
M4401E4A/E23622005WindowsArchitecture Exterior 274,752
Total Planned activities for $274,752BOE0123 000
000BOE012802/26/04Date of Last Survey:145 W. 84 ST
LOUIS D. BRANDEIS HIGH SCHOOL -M -
Page D - 8
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
M4701B3A/E23622005Exterior WallsArchitecture Exterior 381,406
M4701B3A/E23622005WindowsArchitecture Exterior 592,641
M4701B3A/E23622005RoofArchitecture Exterior 148,855
Total Planned activities for $1,122,902BOE0128 000
000BOE012904/19/04Date of Last Survey:345 E. 15 ST.
HEALTH PROFESSIONS HIGH SCHOOL-M -
A00127839/E23622009WindowsArchitecture Exterior 123,127
A00007807/E23622007WiringElectrical Under 600 Volts 141,747
Total Planned activities for $264,874BOE0129 000
000BOE014004/02/03Date of Last Survey:525 W. 50 ST
PARK WEST HIGH SCHOOL - M -
SIRA6M535/E23622006Energy SourceMechanical Heating 58,826
SIRA6M535/E23622006Conversion EquipmentMechanical Heating 1,851,449
SIRA6M535/E23622006DistributionMechanical Heating 477,615
SIRA6M535/E23622006Terminal DevicesMechanical Heating 1,096,486
Total Planned activities for $3,484,376BOE0140 000
000BOE014112/12/05Date of Last Survey:WEST 135 STREET & CONVENT AVENUE
A. PHILLIP RANDOLPH CAMPUS - M -
A00083154/E23622008Exterior WallsArchitecture Exterior 201,054
A00083153/E23622008RoofArchitecture Exterior 134,500
Total Planned activities for $335,554BOE0141 000
000BOE014204/10/06Date of Last Survey:225 W. 24 STREET
H.S. OF FASHION INDUSTRIES - M -
A00017901/E23622007Exterior WallsArchitecture Exterior 220,297
A00008012/E23622007Service EquipmentElectrical Under 600 Volts 57,207
A00008012/E23622007SwitchgearElectrical Under 600 Volts 261,722
A00008012/E23622007PanelboardsElectrical Under 600 Volts 95,198
A00008012/E23622007WiringElectrical Under 600 Volts 283,491
Total Planned activities for $917,915BOE0142 000
000BOE014304/10/06Date of Last Survey:131 AVENUE OF AMERICAS
CHELSEA VOCATIONAL H.S. - M -
A00008029/E23622009WiringElectrical Under 600 Volts 45,957
Total Planned activities for $45,957BOE0143 000
000BOE015110/03/02Date of Last Survey:113 E 4 TH ST 10003
CAREER DEVELOPMENT - M (M751) -
A00008162/E23622009PanelboardsElectrical Under 600 Volts 55,532
Total Planned activities for $55,532BOE0151 000
000BOE015512/01/03Date of Last Survey:335 EAST 152 STREET
P. S. 1 - BX -
Page D - 9
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
A00013542/E23622009WiringElectrical Under 600 Volts 103,403
Total Planned activities for $103,403BOE0155 000
000BOE015703/16/05Date of Last Survey:1701 FULTON AVENUE
P. S. 4 - BX -
X0041B3A/E23622005Exterior WallsArchitecture Exterior 415,751
X0041B3A/E23622005WindowsArchitecture Exterior 1,345,838
X0041B3A/E23622005ParapetsArchitecture Exterior 53,336
A00013582/E2362005FloorsArchitecture Interior 510,319
Total Planned activities for $2,325,244BOE0157 000
000BOE015910/07/04Date of Last Survey:1000 EAST TREMONT AVENUE
P. S. 6 - BX -
X006E15A/E23622005Exterior WallsArchitecture Exterior 142,551
A00013618/E23622005FloorsArchitecture Interior 122,378
Total Planned activities for $264,929BOE0159 000
000BOE016011/29/05Date of Last Survey:3201 KINGSBRIDGE AVENUE
P. S. 7 - BX -
A00013631/E23622009SwitchgearElectrical Under 600 Volts 39,258
A00013631/E23622009WiringElectrical Under 600 Volts 59,003
Total Planned activities for $98,261BOE0160 000
000BOE016110/17/05Date of Last Survey:3010 BRIGGS AVENUE
P. S. 8 - BX -
A00013645/E23622009WiringElectrical Under 600 Volts 62,936
Total Planned activities for $62,936BOE0161 000
000BOE016210/17/05Date of Last Survey:E. 183RD ST. & RYER AVENUE
P. S. 9 - BX (OL 115) -
A00017757/E23622006Exterior WallsArchitecture Exterior 66,497
A00017758/E23622006ParapetsArchitecture Exterior 42,121
Total Planned activities for $108,618BOE0162 000
000BOE016502/12/03Date of Last Survey:3041 BRUCKNER BOULEVARD
P. S. 14 - BX -
X0141B3/E23612003Exterior WallsArchitecture Exterior 57,807
Total Planned activities for $57,807BOE0165 000
000BOE016703/11/05Date of Last Survey:502 MORRIS AVENUE
P. S. 18 - BX -
A00128382/E23622008RoofArchitecture Exterior 45,723
Total Planned activities for $45,723BOE0167 000
000BOE016811/23/04Date of Last Survey:4318 KATONAH AVENUE
P. S. 19 - BX -
X0191E5A/E23622005Exterior WallsArchitecture Exterior 127,774
Page D - 10
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
X0191E4A/E23622005WindowsArchitecture Exterior 394,374
Total Planned activities for $522,148BOE0168 000
000BOE017110/20/03Date of Last Survey:660 WEST 236 STREET
P. S. 24 - BX -
A00013834/E23622007SwitchgearElectrical Under 600 Volts 68,703
A00013834/E23622007WiringElectrical Under 600 Volts 103,403
Total Planned activities for $172,106BOE0171 000
000BOE017301/17/06Date of Last Survey:1930 ANDREWS AVENUE
P. S. 26 - BX -
A00013872/E23622009WiringElectrical Under 600 Volts 67,357
Total Planned activities for $67,357BOE0173 000
000BOE017612/01/03Date of Last Survey:758 COURTLAND AVENUE
P. S. 29 - BX -
A00017857/E23622008WindowsArchitecture Exterior 597,867
Total Planned activities for $597,867BOE0176 000
010BOE017710/20/04Date of Last Survey:577 EAST 139 STREET
P. S. 30 - BX - AX (ECF-S X ECC 2)
A00016892/E23622007WindowsArchitecture Exterior 86,003
Total Planned activities for $86,003BOE0177 010
000BOE017911/14/02Date of Last Survey:690 EAST 183 STREET
P. S. 32 - BX -
A00013959/E23622009SwitchgearElectrical Under 600 Volts 91,603
A00013959/E23622009WiringElectrical Under 600 Volts 97,659
Total Planned activities for $189,262BOE0179 000
000BOE018002/21/06Date of Last Survey:2424 JEROME AVENUE
P. S. 33 - BX -
A00013975/E23622008WiringElectrical Under 600 Volts 62,936
Total Planned activities for $62,936BOE0180 000
000BOE018103/11/05Date of Last Survey:261 EAST 163 STREET
P. S. 35 - BX -
A00013997/E23622008PanelboardsElectrical Under 600 Volts 52,061
Total Planned activities for $52,061BOE0181 000
000BOE018203/28/05Date of Last Survey:1070 CASTLE HILL AVENUE
P. S. 36 - BX -
X0361E4A-C/E23622005Exterior WallsArchitecture Exterior 277,717
X0361E4A-C/E23622005WindowsArchitecture Exterior 746,606
X0361E4A-C/E23622005ParapetsArchitecture Exterior 57,150
Total Planned activities for $1,081,473BOE0182 000
Page D - 11
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE018411/10/03Date of Last Survey:3352 OLINVILLE AVENUE
P. S. 41 - BX -
A00017561/E23622007Exterior WallsArchitecture Exterior 185,144
A00017573/E23622007WindowsArchitecture Exterior 356,706
A00017570/E23622007RoofArchitecture Exterior 289,716
Total Planned activities for $831,566BOE0184 000
000BOE018604/14/03Date of Last Survey:165 BROWN PLACE
P. S. 43 - BX -
X0431E5A/E23622005Exterior WallsArchitecture Exterior 179,036
A00014094/E23622005FloorsArchitecture Interior 378,415
Total Planned activities for $557,451BOE0186 000
000BOE018810/30/03Date of Last Survey:2502 LORILLARD PLACE
I. S. 45 - BX - (J. H. S. 45 - BX)
A00014124/E23622006WiringElectrical Under 600 Volts 94,300
Total Planned activities for $94,300BOE0188 000
000BOE018909/16/04Date of Last Survey:279 EAST 196 STREET
P. S. 46 - BX -
A00014142/E23622009WiringElectrical Under 600 Volts 55,069
Total Planned activities for $55,069BOE0189 000
000BOE019012/18/03Date of Last Survey:1794 EAST 172 STREET
P. S. 47 - BX -
A00014159/E23622006Exterior WallsArchitecture Exterior 912,485
Total Planned activities for $912,485BOE0190 000
000BOE019102/22/06Date of Last Survey:1290 SPOFFORD AVENUE
P. S. 48 - BX -
A00082734/E23622007Exterior WallsArchitecture Exterior 284,529
A00076551/E23622007ParapetsArchitecture Exterior 102,645
Total Planned activities for $387,174BOE0191 000
000BOE019205/30/06Date of Last Survey:383 EAST 139 STREET
P. S. 49 - BX -
A00128171/E23622009WindowsArchitecture Exterior 719,439
Total Planned activities for $719,439BOE0192 000
000BOE019310/07/04Date of Last Survey:1550 VYSE AVENUE
P. S. 50 - BX -
A00128172/E23622009ParapetsArchitecture Exterior 89,351
Total Planned activities for $89,351BOE0193 000
000BOE019711/10/03Date of Last Survey:341 EAST 207 STREET
P. S. 56 - BX -
A00014274/E23622008General LightingElectrical Lighting 139,935
Page D - 12
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
Total Planned activities for $139,935BOE0197 000
000BOE020002/07/06Date of Last Survey:2185 BATHGATE AVENUE
P. S. 59 - BX -
A00014313/E23622007SwitchgearElectrical Under 600 Volts 39,258
Total Planned activities for $39,258BOE0200 000
000BOE020210/07/04Date of Last Survey:1550 CROTONA PARK EAST
P. S. 61 - BX -
EMERG2005/E23622005Exterior WallsArchitecture Exterior 675,071
Total Planned activities for $675,071BOE0202 000
000BOE020303/10/05Date of Last Survey:660 FOX STREET
P. S. 62 - BX -
A00017593/E23622007Exterior WallsArchitecture Exterior 583,248
Total Planned activities for $583,248BOE0203 000
000BOE020410/19/05Date of Last Survey:1260 FRANKLIN AVENUE
P. S. 63 - BX -
A00076925/E23622008ParapetsArchitecture Exterior 41,325
Total Planned activities for $41,325BOE0204 000
000BOE020512/10/02Date of Last Survey:1425 WALTON AVENUE
P. S. 64 - BX -
A00019504/E23622005Exterior WallsArchitecture Exterior 234,101
A00019506/E23622005RoofArchitecture Exterior 169,900
A00014396/E23622008WiringElectrical Under 600 Volts 55,069
Total Planned activities for $459,070BOE0205 000
000BOE020604/14/03Date of Last Survey:677 EAST 141 STREET
P. S. 65 - BX -
A00017887/E23622007Exterior WallsArchitecture Exterior 157,810
A00082702/E23622007WindowsArchitecture Exterior 71,027
A00076983/E23622007ParapetsArchitecture Exterior 45,890
A00014413/E23622009SwitchgearElectrical Under 600 Volts 78,516
A00014413/E23622009WiringElectrical Under 600 Volts 55,069
Total Planned activities for $408,312BOE0206 000
000BOE020902/10/05Date of Last Survey:4011 MONTICELLO AVENUE
P. S. 68 - BX -
A00018921/ED0012006Interior WallsArchitecture Interior 45,645
Total Planned activities for $45,645BOE0209 000
010BOE021009/08/04Date of Last Survey:560 THERIOT AVENUE
P. S. 69 - BX - MINISCHOOL
A00016952/E23622006WindowsArchitecture Exterior 74,591
A00016952/E23622006RoofArchitecture Exterior 150,730
Page D - 13
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
Total Planned activities for $225,321BOE0210 010
000BOE021504/29/04Date of Last Survey:730 BRYANT AVENUE
I. S. 74 - BX -
A00014557/E23622007RoofArchitecture Exterior 356,092
Total Planned activities for $356,092BOE0215 000
000BOE021601/03/06Date of Last Survey:984 FAILE STREET
P. S. 75 - BX -
A00014572/E23622007Exterior WallsArchitecture Exterior 196,735
A00020083/E23622007ParapetsArchitecture Exterior 65,540
Total Planned activities for $262,275BOE0216 000
000BOE021702/28/05Date of Last Survey:900 ADEE AVENUE
P. S. 76 - BX -
A00017895/E23622007Exterior WallsArchitecture Exterior 62,546
A00017898/E23622007WindowsArchitecture Exterior 551,355
Total Planned activities for $613,901BOE0217 000
000BOE022012/29/03Date of Last Survey:125 EAST 181 STREET
P. S. 79 - BX -
A00014644/E23622007Exterior WallsArchitecture Exterior 398,141
A00014645/E23622007WiringElectrical Under 600 Volts 67,357
Total Planned activities for $465,498BOE0220 000
000BOE022204/05/05Date of Last Survey:5550 RIVERDALE AVENUE
P. S. 81 - BX -
A00128345/E23622007RoofArchitecture Exterior 88,211
Total Planned activities for $88,211BOE0222 000
000BOE022701/23/04Date of Last Survey:2756 RESERVOIR AVENUE
P. S. 86 - BX -
A00014770/E23622008WiringElectrical Under 600 Volts 107,772
Total Planned activities for $107,772BOE0227 000
000BOE022812/19/05Date of Last Survey:1935 BUSSING AVENUE
P. S. 87 - BX -
A00014786/E23622009SwitchgearElectrical Under 600 Volts 65,431
A00014786/E23622009WiringElectrical Under 600 Volts 37,470
Total Planned activities for $102,901BOE0228 000
000BOE022910/30/02Date of Last Survey:1340 SHERIDAN AVENUE
P. S. 88 - BX -
A00014802/E23622008SwitchgearElectrical Under 600 Volts 52,344
Total Planned activities for $52,344BOE0229 000
000BOE023002/19/04Date of Last Survey:980 MACE AVENUE
P. S. 89 - BX -
Page D - 14
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
A00014814/E23622009SwitchgearElectrical Under 600 Volts 91,603
A00014814/E23622009WiringElectrical Under 600 Volts 57,446
Total Planned activities for $149,049BOE0230 000
000BOE023110/30/02Date of Last Survey:1116 SHERIDAN AVENUE
P. S. 90 - BX -
A00014826/E23622009General LightingElectrical Lighting 122,276
Total Planned activities for $122,276BOE0231 000
000BOE023210/19/04Date of Last Survey:2200 AQUEDUCT AVENUE
P. S. 91 - BX -
A00014841/E23622007WiringElectrical Under 600 Volts 70,804
Total Planned activities for $70,804BOE0232 000
000BOE023301/07/04Date of Last Survey:700 EAST 179 STREET
P. S. 92 - BX -
A00020802/E23622006WindowsArchitecture Exterior 131,930
Total Planned activities for $131,930BOE0233 000
010BOE023409/08/04Date of Last Survey:1535 STORY AVENUE
P. S. 93 - BX - MINISCHOOL
A00017742/E23622007RoofArchitecture Exterior 202,982
Total Planned activities for $202,982BOE0234 010
000BOE023611/19/04Date of Last Survey:3961 HILLMAN AVENUE
P. S. 95 - BX -
A00014910/E23622006SwitchgearElectrical Under 600 Volts 82,443
A00014910/E23622006PanelboardsElectrical Under 600 Volts 83,298
A00014910/E23622006WiringElectrical Under 600 Volts 80,425
Total Planned activities for $246,166BOE0236 000
000BOE024011/13/03Date of Last Survey:800 TAYLOR AVENUE
P. S. 100 - BX -
A00082597/E23622007RoofArchitecture Exterior 51,293
Total Planned activities for $51,293BOE0240 000
000BOE024104/29/04Date of Last Survey:2750 LAFAYETTE AVENUE
J. H. S. 101 - BX -
A00014995/E23622007WiringElectrical Under 600 Volts 149,686
Total Planned activities for $149,686BOE0241 000
000BOE024310/16/03Date of Last Survey:4125 CARPENTER AVENUE
P. S. 103 - BX -
X1031B3A/E23622005WindowsArchitecture Exterior 718,455
Total Planned activities for $718,455BOE0243 000
000BOE024401/05/04Date of Last Survey:1449 SHAKESPEARE AVENUE
P. S. 104 - BX -
Page D - 15
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
A00128390/E23622007RoofArchitecture Exterior 70,175
A00015564/E23622007WiringElectrical Under 600 Volts 121,243
Total Planned activities for $191,418BOE0244 000
000BOE024603/24/05Date of Last Survey:2120 ST. RAYMOND AVENUE
P. S. 106 - BX -
A00015065/E23622007WindowsArchitecture Exterior 612,474
EMERG2005/E23622006ParapetsArchitecture Exterior 70,267
EMERG2005/E23622006RoofArchitecture Exterior 323,076
Total Planned activities for $1,005,817BOE0246 000
000BOE024910/19/04Date of Last Survey:1771 POPHAM AVENUE
P. S. 109 - BX -
A00015106/E23622009SwitchgearElectrical Under 600 Volts 78,516
A00015106/E23622009WiringElectrical Under 600 Volts 70,804
Total Planned activities for $149,320BOE0249 000
010BOE024910/19/04Date of Last Survey:1771 POPHAM AVENUE
P. S. 109 - BX - MINISCHOOL
A00017097/E23622005RoofArchitecture Exterior 44,517
Total Planned activities for $44,517BOE0249 010
000BOE025003/07/05Date of Last Survey:580 CROTONA PARK SOUTH
P. S. 110 - BX -
A00015120/E23622005WindowsArchitecture Exterior 133,228
A00015120/E23622005RoofArchitecture Exterior 48,657
Total Planned activities for $181,885BOE0250 000
000BOE025302/25/04Date of Last Survey:3710 BARNES AVENUE
I. S. 113 - BX - (J. H. S. 113 - BX)
A00078255/E23622008ParapetsArchitecture Exterior 142,213
A00078255/E23622008RoofArchitecture Exterior 58,682
Total Planned activities for $200,895BOE0253 000
000BOE025503/16/06Date of Last Survey:120 EAST 184 STREET
M.S. 319 - BX - (FORMER I.S.115-BX,OLD BX HS SCI
A00015210/E23622007WindowsArchitecture Exterior 1,077,274
A00015212/E23622007WiringElectrical Under 600 Volts 107,772
Total Planned activities for $1,185,046BOE0255 000
000BOE025604/08/05Date of Last Survey:977 FOX STREET
I. S. 116 - BX -
A00015224/E23622009General LightingElectrical Lighting 1,308,456
Total Planned activities for $1,308,456BOE0256 000
000BOE025701/13/03Date of Last Survey:1865 MORRIS AVENUE
I. S. 117 - BX - (J. H. S. 117 - BX)
Page D - 16
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
A00015235/E23622009General LightingElectrical Lighting 40,367
Total Planned activities for $40,367BOE0257 000
000BOE026001/14/04Date of Last Survey:890 CAULDWELL AVENUE
M.S. 301 - BX -
X1201B3A/E30002004WindowsArchitecture Exterior 980,877
A00015286/E23622009SwitchgearElectrical Under 600 Volts 104,689
A00015286/E23622009WiringElectrical Under 600 Volts 127,979
Total Planned activities for $1,213,545BOE0260 000
000BOE026102/28/05Date of Last Survey:2750 THROOP AVENUE
P. S. 121 - BX -
A00015301/E23622009SwitchgearElectrical Under 600 Volts 91,603
A00015301/E23622009WiringElectrical Under 600 Volts 103,403
Total Planned activities for $195,006BOE0261 000
000BOE026210/17/02Date of Last Survey:260 WEST KINGSBRIDGE ROAD
P. S. 310 - BX - (FORMER P.S. 122 - BX)
A00015320/E23612009SwitchgearElectrical Under 600 Volts 78,516
A00015320/E23612009WiringElectrical Under 600 Volts 70,804
Total Planned activities for $149,320BOE0262 000
000BOE026412/18/03Date of Last Survey:1111 PUGSLEY AVENUE
I. S. 125 - BX - (J. H. S. 125 - BX)
A00128431/E23622007RoofArchitecture Exterior 110,590
Total Planned activities for $110,590BOE0264 000
000BOE026501/05/04Date of Last Survey:175 WEST 166 STREET
P. S. 126 -BX (ECF) -
EMERG2005/E23622006WindowsArchitecture Exterior 519,650
Total Planned activities for $519,650BOE0265 000
000BOE027003/07/05Date of Last Survey:1245 WASHINGTON AVENUE
P. S. 132 - BX -
A00015448/E23622006WindowsArchitecture Exterior 702,359
A00015445/E23622009General LightingElectrical Lighting 658,044
Total Planned activities for $1,360,403BOE0270 000
000BOE027304/18/06Date of Last Survey:750 JENNINGS STREET
J. H. S. 136 - BX -
A00015499/E23622009WiringElectrical Under 600 Volts 157,564
Total Planned activities for $157,564BOE0273 000
000BOE027401/07/04Date of Last Survey:2225 WEBSTER AVENUE
M. S. 391 - BX -
X1371B3A/E23612004Exterior WallsArchitecture Exterior 92,199
X1371B3A/E23612004WindowsArchitecture Exterior 93,446
Page D - 17
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
X1371B3A/E23612004RoofArchitecture Exterior 358,428
Total Planned activities for $544,073BOE0274 000
000BOE027601/11/05Date of Last Survey:345 BROOK AVENUE
I. S. 139 - BX -
A00015541/E23622009General LightingElectrical Lighting 47,611
Total Planned activities for $47,611BOE0276 000
000BOE027702/07/05Date of Last Survey:916 EAGLE AVENUE
P. S. 140 - BX -
A00128390/E23622007RoofArchitecture Exterior 315,340
A00015564/E23622007WiringElectrical Under 600 Volts 91,914
Total Planned activities for $407,254BOE0277 000
000BOE027810/20/03Date of Last Survey:660 WEST 237 STREET
I. S. 141 - BX - (J. H. S. 141 - BX)
A00015576/E23622005Exterior WallsArchitecture Exterior 40,835
A00015575/E23622005WindowsArchitecture Exterior 1,747,600
A00018803/E23622005WiringElectrical Under 600 Volts 88,592
Total Planned activities for $1,877,027BOE0278 000
000BOE028205/15/06Date of Last Survey:1000 TELLER AVENUE
I. S. 145 - BX -
A00015655/E23622007DistributionMechanical Heating 94,130
Total Planned activities for $94,130BOE0282 000
000BOE028402/08/05Date of Last Survey:1600 WEBSTER AVENUE
I. S. 147 - BX -
A00079144/E23622008ParapetsArchitecture Exterior 54,831
Total Planned activities for $54,831BOE0284 000
000BOE028501/14/04Date of Last Survey:3630 THIRD AVENUE
I. S. 219 - BX - NEW VENTURE SCHOOL (X219)
A00082596/E23622008RoofArchitecture Exterior 41,465
Total Planned activities for $41,465BOE0285 000
000BOE028603/01/04Date of Last Survey:360 EAST 145 STREET
J. H. S. 149 - BX -
A00017665/E23622007WindowsArchitecture Exterior 1,670,007
A00082718/E23622007RoofArchitecture Exterior 103,391
Total Planned activities for $1,773,398BOE0286 000
000BOE028701/12/04Date of Last Survey:920 EAST 167 STREET
P. S. 150 - BX -
X1501E5A/E23622006Exterior WallsArchitecture Exterior 144,209
X1501E5A/E23622006WindowsArchitecture Exterior 126,224
A00015734/E23622006WiringElectrical Under 600 Volts 74,680
Page D - 18
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
Total Planned activities for $345,113BOE0287 000
000BOE029503/13/06Date of Last Survey:800 HOME STREET
I. S. 158 - BX -
A00018031/E23622007Exterior WallsArchitecture Exterior 342,249
A00018029/E23622007WindowsArchitecture Exterior 867,239
Total Planned activities for $1,209,488BOE0295 000
000BOE030001/21/04Date of Last Survey:250 EAST 164 STREET
I. S. 166 - BX -
A00128222/E23622009ParapetsArchitecture Exterior 51,864
Total Planned activities for $51,864BOE0300 000
000BOE030101/06/04Date of Last Survey:1970 WEST FARMS ROAD
P. S. 214/I. S. 200 - BX - (I. S. 167 - BX)
A00019475/E23622005Exterior WallsArchitecture Exterior 254,878
A00015965/E23622005WindowsArchitecture Exterior 76,756
A00015964/E23622005RoofArchitecture Exterior 88,492
Total Planned activities for $420,126BOE0301 000
000BOE030411/27/02Date of Last Survey:850 BAYCHESTER AVENUE
P. S. 178 - BX -
X1781B3A/E23622005Exterior WallsArchitecture Exterior 83,832
Total Planned activities for $83,832BOE0304 000
000BOE030611/27/02Date of Last Survey:800 BAYCHESTER AVENUE
I. S. 181 - BX -
A00128224/E23622009Exterior WallsArchitecture Exterior 88,932
Total Planned activities for $88,932BOE0306 000
000BOE030701/06/05Date of Last Survey:601 STICKBALL BLVD.
P. S. 182 - BX -
A00018058/E23622007RoofArchitecture Exterior 570,016
Total Planned activities for $570,016BOE0307 000
000BOE031002/25/03Date of Last Survey:650 HOLLYWOOD AVENUE
I. S. 192 - BX -
A00018064/E23622007RoofArchitecture Exterior 63,064
Total Planned activities for $63,064BOE0310 000
000BOE031310/04/04Date of Last Survey:2475 SOUTHERN BOULEVARD
P. S. 205A - BX (ECF) -
EMERG2005/E23622007RoofArchitecture Exterior 325,991
Total Planned activities for $325,991BOE0313 000
000BOE031412/29/03Date of Last Survey:2280 AQUEDUCT AVENUE
I. S. 206B - BX -
A00016191/E23622007RoofArchitecture Exterior 226,777
Page D - 19
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
Total Planned activities for $226,777BOE0314 000
000BOE031512/29/03Date of Last Survey:275 HARLEM RIVER PARK BRIDGE
P. S. 230/I. S. 229 (UDC) - BX - (P. S./I. S. 229 (UDC) - BX)
EMERG2005/E23622005Heat RejectionMechanical Air Conditioning 162,532
Total Planned activities for $162,532BOE0315 000
000BOE031803/13/06Date of Last Survey:E 166 TH ST. & BOSTON ROAD
MORRIS HIGH SCHOOL - BX -
A00020340/E23622006DistributionMechanical Heating 102,334
Total Planned activities for $102,334BOE0318 000
000BOE032003/28/05Date of Last Survey:3000 E. TREMONT AVENUE
HERBERT H. LEHMAN H.S. - BX -
A00016273/E23622007Exterior WallsArchitecture Exterior 503,029
Total Planned activities for $503,029BOE0320 000
000BOE032101/08/04Date of Last Survey:240 E. 172ND STREET
WILLIAM H. TAFT HIGH SCHOOL - BX -
X4101E4A/E23622005WindowsArchitecture Exterior 139,629
A00019142/E23622005RoofArchitecture Exterior 126,899
Total Planned activities for $266,528BOE0321 000
000BOE032402/25/04Date of Last Survey:800 E. GUN HILL RD.
EVANDER CHILDS HIGH SCHOOL - BX -
A00018068/E23622007RoofArchitecture Exterior 82,015
A00016346/E23622006FloorsArchitecture Interior 147,000
Total Planned activities for $229,015BOE0324 000
000BOE032503/19/03Date of Last Survey:196TH & RESERVOIR AVE.
WALTON HIGH SCHOOL - BX -
X4306EA/E23612003ParapetsArchitecture Exterior 59,795
Total Planned activities for $59,795BOE0325 000
000BOE032610/30/03Date of Last Survey:500 E. FORDHAM RD.
THEODORE ROOSEVELT H.S. - BX -
A00016378/E23622009WiringElectrical Under 600 Volts 265,773
Total Planned activities for $265,773BOE0326 000
000BOE032806/09/03Date of Last Survey:75 W. 205TH STREET
BRONX H.S. OF SCIENCE - BX -
X4451E4A/E23622005WindowsArchitecture Exterior 1,151,487
Total Planned activities for $1,151,487BOE0328 000
000BOE032901/26/04Date of Last Survey:1980 LAFAYETTE AVE.
ADLAI E. STEVENSON H.S. - BX -
A00016430/E23622009General LightingElectrical Lighting 55,428
Total Planned activities for $55,428BOE0329 000
Page D - 20
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE033210/29/03Date of Last Survey:WEST 230 STREET & TIBBETT AVE.
JOHN F. KENNEDY HIGH SCHOOL - BX -
A00128247/E23622009Exterior WallsArchitecture Exterior 54,042
Total Planned activities for $54,042BOE0332 000
000BOE033305/23/06Date of Last Survey:333 E. 151ST STREET
ALFRED E. SMITH HIGH SCHOOL - BX -
A00016516/E23622009WiringElectrical Under 600 Volts 283,491
Total Planned activities for $283,491BOE0333 000
000BOE033503/16/05Date of Last Survey:455 SOUTHERN BLVD.
SAMUEL GOMPERS HIGH SCHOOL - BX -
MACC2000A/E23622007WindowsArchitecture Exterior 874,491
A00017686/E23622007RoofArchitecture Exterior 494,524
Total Planned activities for $1,369,015BOE0335 000
000BOE033602/07/06Date of Last Survey:2474 CROTONA AVE.
GRACE H. DODGE HIGH SCHOOL - BX -
A00016571/E23622009SwitchgearElectrical Under 600 Volts 117,775
A00016571/E23622009WiringElectrical Under 600 Volts 141,807
Total Planned activities for $259,582BOE0336 000
000BOE034104/11/06Date of Last Survey:2375 SOUTHERN BOULEVARD
P. S. 205B (ECF)- BX -
EMERG2005/E23622006RoofArchitecture Exterior 180,415
Total Planned activities for $180,415BOE0341 000
000BOE034402/17/04Date of Last Survey:820 HANCOCK STREET
P. S. 5 - BK -
A00017503/E23622007RoofArchitecture Exterior 49,039
Total Planned activities for $49,039BOE0344 000
000BOE034709/11/03Date of Last Survey:511 7TH AVE.
P. S. 10 - BK -
A00000109/E23622009General LightingElectrical Lighting 51,170
Total Planned activities for $51,170BOE0347 000
000BOE035209/30/04Date of Last Survey:157 WILSON STREET
P. S. 16 - BK -
A00000198/E23622007SwitchgearElectrical Under 600 Volts 73,282
A00000198/E23622007WiringElectrical Under 600 Volts 94,300
Total Planned activities for $167,582BOE0352 000
000BOE035309/30/04Date of Last Survey:208 NORTH 5 STREET
P. S. 17 - BK -
A00000209/E23622006Exterior WallsArchitecture Exterior 174,538
A00020903/E23622006RoofArchitecture Exterior 37,023
Page D - 21
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
Total Planned activities for $211,561BOE0353 000
000BOE035612/17/02Date of Last Survey:225 ADELPHI STREET
P. S. 20 - BK -
A00019474/E23622009WindowsArchitecture Exterior 1,029,077
Total Planned activities for $1,029,077BOE0356 000
000BOE035812/06/05Date of Last Survey:545 WILLOUGHBY AVENUE
P. S. 23 - BK -
A00050665/E23622007ParapetsArchitecture Exterior 65,508
Total Planned activities for $65,508BOE0358 000
000BOE036003/16/05Date of Last Survey:1014 LAFAYETTE AVENUE
P. S. 26 - BK -
A00000322/E23622005WindowsArchitecture Exterior 1,491,403
Total Planned activities for $1,491,403BOE0360 000
000BOE036109/16/03Date of Last Survey:NELSON & HICKS STREETS
P. S. 27 - BK -
EMERG2005/E23622006Exterior WallsArchitecture Exterior 725,649
A00020007/E23622006RoofArchitecture Exterior 423,818
A00020006/E23622007SwitchgearElectrical Under 600 Volts 91,603
A00020006/E23622007PanelboardsElectrical Under 600 Volts 71,399
A00020006/E23622007WiringElectrical Under 600 Volts 103,403
A00020004/E23622007Conversion EquipmentMechanical Heating 37,747
Total Planned activities for $1,453,619BOE0361 000
000BOE036303/24/05Date of Last Survey:425 HENRY STREET
P. S. 29 - BK -
A00000363/E23622009SwitchgearElectrical Under 600 Volts 85,761
A00000363/E23622009WiringElectrical Under 600 Volts 77,336
Total Planned activities for $163,097BOE0363 000
000BOE036501/13/05Date of Last Survey:317 HOYT STREET
P. S. 32 - BK -
A00000395/E23622009SwitchgearElectrical Under 600 Volts 78,516
A00000395/E23622009WiringElectrical Under 600 Volts 47,202
Total Planned activities for $125,718BOE0365 000
000BOE036610/23/03Date of Last Survey:70 TOMPKINS AVENUE
I. S. 33 - BK -
A00000406/E23622008WiringElectrical Under 600 Volts 118,173
Total Planned activities for $118,173BOE0366 000
000BOE036802/17/04Date of Last Survey:272 MCDONOUGH STREET
I. S. 35 - BK - (J.H.S. 35 & P.S. 141 - BK)
A00017511/E23622009WindowsArchitecture Exterior 715,185
Page D - 22
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
Total Planned activities for $715,185BOE0368 000
000BOE036912/09/04Date of Last Survey:450 PACIFIC STREET
P. S. 38 - BK -
A00127505/E23622009WindowsArchitecture Exterior 520,178
Total Planned activities for $520,178BOE0369 000
000BOE037009/11/03Date of Last Survey:417 6TH AVENUE
P. S. 39 - BK -
A00127506/E23622009WindowsArchitecture Exterior 311,098
Total Planned activities for $311,098BOE0370 000
000BOE037102/26/04Date of Last Survey:265 RALPH AVENUE
P. S. 40 - BK -
A00000481/E23622009WindowsArchitecture Exterior 671,007
Total Planned activities for $671,007BOE0371 000
000BOE037204/25/06Date of Last Survey:411 THATFORD AVENUE
P. S. 41 - BK -
A00000502/E23622005Exterior WallsArchitecture Exterior 59,188
Total Planned activities for $59,188BOE0372 000
000BOE037303/09/05Date of Last Survey:1401 EMMONS AVENUE
I. S. 43 - BK - (I. S. 98 - BK)
A00082678/E23622007WiringElectrical Under 600 Volts 78,782
Total Planned activities for $78,782BOE0373 000
000BOE037511/01/04Date of Last Survey:84 SCHAFFER STREET
P. S. 45 - BK -
A00127509/E23622009WindowsArchitecture Exterior 156,786
A00000550/E23622005Terminal DevicesMechanical Heating 65,979
Total Planned activities for $222,765BOE0375 000
010BOE037511/01/04Date of Last Survey:1160 DECATUR STREET
P. S. 45 - BK - AX (OL BSH-RDGWD ECC1)
A00005049/E23622005RoofArchitecture Exterior 122,594
Total Planned activities for $122,594BOE0375 010
000BOE037610/26/04Date of Last Survey:100 CLERMONT AVENUE
P. S. 46 - BK -
A00018723/ED0012006WiringElectrical Under 600 Volts 91,914
Total Planned activities for $91,914BOE0376 000
000BOE037812/24/02Date of Last Survey:223 GRAHAM AVENUE
I. S. 49 - BK -
A00000599/E23622007Conversion EquipmentMechanical Heating 176,605
A00000599/E23622007DistributionMechanical Heating 379,947
A00000599/E23622007DistributionMechanical Ventilation 156,552
Page D - 23
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
A00000599/E23622007Exhaust FansMechanical Ventilation 200,527
Total Planned activities for $913,631BOE0378 000
000BOE037904/12/05Date of Last Survey:183 SOUTH 3RD STREET
J. H. S. 50 - BK -
K0501E5A/E23622005Exterior WallsArchitecture Exterior 190,572
EMERG2005/E23622005ParapetsArchitecture Exterior 58,624
K0501E1A/E34622005RoofArchitecture Exterior 39,733
A00000612/E23622005WiringElectrical Under 600 Volts 107,772
Total Planned activities for $396,701BOE0379 000
000BOE038003/04/03Date of Last Survey:350 5TH STREET
J. H. S. 51 - BK -
A00000628/E23622006SwitchgearElectrical Under 600 Volts 104,689
A00000628/E23622006WiringElectrical Under 600 Volts 121,243
Total Planned activities for $225,932BOE0380 000
000BOE038609/16/03Date of Last Survey:330 SMITH STREET
P. S. 58 - BK -
A00127518/E23622009WindowsArchitecture Exterior 66,754
A00000718/E23622008WiringElectrical Under 600 Volts 121,243
Total Planned activities for $187,997BOE0386 000
000BOE038712/06/05Date of Last Survey:211 THROOP AVENUE
P. S. 59 - BK -
A00051500/E23622007ParapetsArchitecture Exterior 72,343
A00000730/E23622007SwitchgearElectrical Under 600 Volts 64,122
A00000730/E23622007PanelboardsElectrical Under 600 Volts 71,399
A00000730/E23622007WiringElectrical Under 600 Volts 80,425
Total Planned activities for $288,289BOE0387 000
000BOE039110/26/05Date of Last Survey:51 SAINT EDWARDS STREET
P. S. 67 - BK -
A00000784/E23622007Exterior WallsArchitecture Exterior 232,066
Total Planned activities for $232,066BOE0391 000
000BOE039403/09/06Date of Last Survey:605 SHEPHERD AVENUE
P. S. 72 - BK -
A00051698/E23622008Exterior WallsArchitecture Exterior 86,772
Total Planned activities for $86,772BOE0394 000
000BOE039611/25/02Date of Last Survey:95 GROVE STREET
P. S. 75 - BK -
A00005267/E23622006WindowsArchitecture Exterior 378,575
A00005268/E23622006Terminal DevicesMechanical Heating 51,585
Total Planned activities for $430,160BOE0396 000
Page D - 24
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE040202/14/06Date of Last Survey:544 7TH AVENUE
I. S. 88 - BK - (J. H. S. 88 - BK)
A00082729/E23622007WindowsArchitecture Exterior 102,557
Total Planned activities for $102,557BOE0402 000
000BOE040612/13/05Date of Last Survey:31 NEW YORK AVENUE
P. S. 93 - BK -
A00017531/E23622007Exterior WallsArchitecture Exterior 217,523
A00052050/E23622009ParapetsArchitecture Exterior 55,566
Total Planned activities for $273,089BOE0406 000
000BOE040710/20/03Date of Last Survey:5010 6TH AVENUE
P. S. 94 - BK -
A00001014/E23622008Exterior WallsArchitecture Exterior 41,288
Total Planned activities for $41,288BOE0407 000
000BOE040804/24/06Date of Last Survey:345 VAN SICKLEN ST.
P. S. 95 - BK -
A00082977/ED0012008WiringElectrical Under 600 Volts 91,914
Total Planned activities for $91,914BOE0408 000
000BOE040912/19/02Date of Last Survey:99 AVENUE P
I. S. 96 - BK -
EMERG2004/E23612004Exterior WallsArchitecture Exterior 72,652
A00128403/E23622008WindowsArchitecture Exterior 114,917
Total Planned activities for $187,569BOE0409 000
000BOE041012/30/02Date of Last Survey:1855 STILLWELL AVE.
P. S. 97 - BK -
K0976EA/E23612004Exterior WallsArchitecture Exterior 289,905
K0976EA/E23612004Interior WallsArchitecture Interior 73,631
K0976EA/E23612004CeilingsArchitecture Interior 60,068
Total Planned activities for $423,604BOE0410 000
000BOE041209/22/03Date of Last Survey:2951 WEST 3 STREET
P. S. 100 - BK -
EMERG2004/E23612004Exterior WallsArchitecture Exterior 35,992
Total Planned activities for $35,992BOE0412 000
000BOE041610/20/03Date of Last Survey:1031 59 STREET
P. S. 105 - BK -
K1051E5A/E23622005Exterior WallsArchitecture Exterior 133,563
Total Planned activities for $133,563BOE0416 000
000BOE041802/15/06Date of Last Survey:1301 8TH AVENUE
P. S. 107 - BK -
A00083132/E23622007Exterior WallsArchitecture Exterior 161,471
Page D - 25
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
Total Planned activities for $161,471BOE0418 000
000BOE042009/30/04Date of Last Survey:124 MONITOR STREET
P. S. 110 - BK -
A00001192/E23622009WiringElectrical Under 600 Volts 47,202
Total Planned activities for $47,202BOE0420 000
000BOE042312/17/02Date of Last Survey:300 ADELPHI STREET
I. S. 113 - BK -
A00001232/E23622006RoofArchitecture Exterior 40,152
Total Planned activities for $40,152BOE0423 000
000BOE042402/08/05Date of Last Survey:1077 REMSEN AVENUE
P. S. 114 - BK -
K1141E5A/E23622006Exterior WallsArchitecture Exterior 194,822
K1141E5A/E23622006WindowsArchitecture Exterior 683,524
K1141E5A/E23622006ParapetsArchitecture Exterior 47,092
Total Planned activities for $925,438BOE0424 000
000BOE042803/16/06Date of Last Survey:3829 AVENUE K
P. S. 119 - BK -
A00127546/E23622009ParapetsArchitecture Exterior 41,695
Total Planned activities for $41,695BOE0428 000
000BOE042912/27/05Date of Last Survey:18 BEAVER STREET
P. S. 120 - BK -
A00001321/E23622006Exterior WallsArchitecture Exterior 67,841
A00001320/E23622006WindowsArchitecture Exterior 644,382
Total Planned activities for $712,223BOE0429 000
000BOE043102/09/06Date of Last Survey:100 IRVING AVENUE
P. S. 123 - BK -
A00001354/E23622007Exterior WallsArchitecture Exterior 206,597
Total Planned activities for $206,597BOE0431 000
000BOE043209/11/03Date of Last Survey:515 4TH AVENUE
P. S. 124 - BK -
A00001366/E23622009General LightingElectrical Lighting 21,990
Total Planned activities for $21,990BOE0432 000
000BOE043302/17/06Date of Last Survey:424 LEONARD STREET
J. H. S. 126 - BK -
A00001378/E23622009Exterior WallsArchitecture Exterior 100,868
Total Planned activities for $100,868BOE0433 000
000BOE043403/15/06Date of Last Survey:7805 7 AVENUE
P. S. 127 - BK -
EMERG2005/E23622005WindowsArchitecture Exterior 383,378
Page D - 26
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
Total Planned activities for $383,378BOE0434 000
000BOE043901/30/06Date of Last Survey:375 BUTLER STREET
P. S. 133 - BK -
A00127552/E23622009WindowsArchitecture Exterior 477,324
Total Planned activities for $477,324BOE0439 000
000BOE044403/15/05Date of Last Survey:315 EAST 113 STREET
P. S. 102 - M -
A00062449/E23622007Exterior WallsArchitecture Exterior 44,112
A00006530/E23622008SwitchgearElectrical Under 600 Volts 78,516
A00006530/E23622008WiringElectrical Under 600 Volts 70,804
Total Planned activities for $193,432BOE0444 000
010BOE044509/09/03Date of Last Survey:4001 18 AVE.
P. S. 134 - BK -
A00005088/E23622007WindowsArchitecture Exterior 383,378
A00005094/E23622008FloorsArchitecture Interior 210,340
Total Planned activities for $593,718BOE0445 010
020BOE044509/09/03Date of Last Survey:4001 18 AVE.
P. S. 134 - BK - MINISCHOOL
A00005032/E23622009RoofArchitecture Exterior 39,570
Total Planned activities for $39,570BOE0445 020
000BOE044609/16/03Date of Last Survey:610 HENRY STREET
J. H. S. 142 - BK -
A00001533/E23622009PanelboardsElectrical Under 600 Volts 59,499
A00001533/E23622009WiringElectrical Under 600 Volts 141,807
Total Planned activities for $201,306BOE0446 000
000BOE044810/23/03Date of Last Survey:325 BUSHWICK AVENUE
P. S. 147 - BK -
EMERG2006/E23622008Exterior WallsArchitecture Exterior 43,200
Total Planned activities for $43,200BOE0448 000
000BOE045009/15/03Date of Last Survey:364 SACKMAN STREET
P. S. 150 - BK -
A00001610/E23622006FloorsArchitecture Interior 250,404
A00001605/E23622006WiringElectrical Under 600 Volts 91,914
Total Planned activities for $342,318BOE0450 000
000BOE045203/16/06Date of Last Survey:725 EAST 23 STREET
P. S. 152 - BK -
A00128366/E23622008RoofArchitecture Exterior 43,490
Total Planned activities for $43,490BOE0452 000
Page D - 27
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE045702/06/06Date of Last Survey:850 KENT AVENUE
P. S. 157 - BK -
A00001688/E23622007Exterior WallsArchitecture Exterior 345,595
A00001689/E23622007SwitchgearElectrical Under 600 Volts 104,689
A00001689/E23622007PanelboardsElectrical Under 600 Volts 101,148
A00001689/E23622007WiringElectrical Under 600 Volts 121,243
Total Planned activities for $672,675BOE0457 000
000BOE045805/04/06Date of Last Survey:400 ASHFORD STREET
P. S. 158 - BK -
A00053462/E23622007ParapetsArchitecture Exterior 53,324
A00001707/E23622009WiringElectrical Under 600 Volts 103,403
Total Planned activities for $156,727BOE0458 000
000BOE046012/31/02Date of Last Survey:5105 FT. HAMILTON PKWY
P. S. 160 - BK -
K1606EA/E23612003WindowsArchitecture Exterior 253,787
A00018178/E23622006RoofArchitecture Exterior 165,375
Total Planned activities for $419,162BOE0460 000
000BOE046103/29/06Date of Last Survey:330 CROWN STREET
P. S. 161 - BK -
A00127569/E23622009WindowsArchitecture Exterior 949,372
A00001765/E23622008SwitchgearElectrical Under 600 Volts 78,516
A00001765/E23622008WiringElectrical Under 600 Volts 62,936
Total Planned activities for $1,090,824BOE0461 000
000BOE046303/31/03Date of Last Survey:1664 BENSON AVENUE
P. S. 163 - BK -
A00001795/E23622006RoofArchitecture Exterior 95,273
Total Planned activities for $95,273BOE0463 000
000BOE046602/10/04Date of Last Survey:800 VAN SICKLEN AVENUE
I. S. 166 - BK - (J. H. S. 166 - BK)
A0001841/E23622006WindowsArchitecture Exterior 1,795,568
A0001843/E23622006SwitchgearElectrical Under 600 Volts 105,998
A0001843/E23622006WiringElectrical Under 600 Volts 149,686
A0001837/E23622006DistributionMechanical Heating 87,775
Total Planned activities for $2,139,027BOE0466 000
000BOE046701/05/06Date of Last Survey:1025 EASTERN PKWY
P. S. 167 - BK -
A00001858/E23622007WindowsArchitecture Exterior 273,843
A00053741/E23622007ParapetsArchitecture Exterior 50,117
A00001860/E23622007SwitchgearElectrical Under 600 Volts 78,516
Page D - 28
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
A00001860/E23622007WiringElectrical Under 600 Volts 66,870
Total Planned activities for $469,346BOE0467 000
000BOE046912/10/02Date of Last Survey:7109 6TH AVE.
P. S. 170 - BK -
A0000188/E23622007General LightingElectrical Lighting 334,175
Total Planned activities for $334,175BOE0469 000
000BOE047205/04/06Date of Last Survey:574 DUMONT AVENUE
P. S. 174 - BK -
A00001925/E23622008Exterior WallsArchitecture Exterior 321,159
A00053879/E23622008ParapetsArchitecture Exterior 50,784
Total Planned activities for $371,943BOE0472 000
000BOE047412/19/02Date of Last Survey:AVE.P & WEST 1ST ST.
P. S. 177 - BK -
A00001963/E23622005Exterior WallsArchitecture Exterior 220,281
A00001963/E23622005ParapetsArchitecture Exterior 53,943
A00001963/E23622005RoofArchitecture Exterior 125,372
Total Planned activities for $399,596BOE0474 000
000BOE047503/08/06Date of Last Survey:2163 DEAN STREET
P. S. 178 - BK -
A00053990/E23622007ParapetsArchitecture Exterior 54,121
Total Planned activities for $54,121BOE0475 000
000BOE047601/09/06Date of Last Survey:202 AVENUE C
P. S. 179 - BK -
A00054019/E23622009Exterior WallsArchitecture Exterior 109,917
Total Planned activities for $109,917BOE0476 000
000BOE047712/14/05Date of Last Survey:16 AVENUE & 57 STREET
P. S. 180 - BK -
A00127589/E23622009ParapetsArchitecture Exterior 69,180
Total Planned activities for $69,180BOE0477 000
000BOE047904/25/06Date of Last Survey:76 RIVERDALE AVE.
P. S. 183 - BK -
A00017562/E23622007WindowsArchitecture Exterior 132,913
A00002044/E23622008SwitchgearElectrical Under 600 Volts 78,516
A00002044/E23622008WiringElectrical Under 600 Volts 62,936
Total Planned activities for $274,365BOE0479 000
000BOE048004/27/06Date of Last Survey:273 NEWPORT STREET
P. S. 184 - BK -
A00002064/E23622006WindowsArchitecture Exterior 961,515
Total Planned activities for $961,515BOE0480 000
Page D - 29
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE048112/10/02Date of Last Survey:8601 RIDGE BLVD
P. S. 185 - BK -
A00019472/E23622007Exterior WallsArchitecture Exterior 236,712
A00082675/E23622007RoofArchitecture Exterior 137,646
Total Planned activities for $374,358BOE0481 000
000BOE048309/22/03Date of Last Survey:3314 NEPTUNE AVENUE
P. S. 188 - BK -
A00020500/ED0012007WiringElectrical Under 600 Volts 70,804
Total Planned activities for $70,804BOE0483 000
000BOE048402/07/05Date of Last Survey:1100 EAST NEW YORK AVENUE
P. S. 189 - BK -
A00002121/E23622008SwitchgearElectrical Under 600 Volts 78,516
A00002121/E23622008WiringElectrical Under 600 Volts 62,936
Total Planned activities for $141,452BOE0484 000
000BOE048703/24/06Date of Last Survey:4715 18 AVENUE
P. S. 192 - BK -
A00017704/E23622007WindowsArchitecture Exterior 878,768
Total Planned activities for $878,768BOE0487 000
000BOE049009/30/02Date of Last Survey:131 IRWIN STREET
P. S. 195 - BK -
K1956ED/E23612003WindowsArchitecture Exterior 226,789
K1956EA/E23612003RoofArchitecture Exterior 110,887
Total Planned activities for $337,676BOE0490 000
000BOE049409/19/02Date of Last Survey:1100 ELM AVE.
P. S. 199 - BK -
A00002279/E23622005SwitchgearElectrical Under 600 Volts 78,516
A00002279/E23622005PanelboardsElectrical Under 600 Volts 53,549
A00002279/E23622005WiringElectrical Under 600 Volts 62,936
Total Planned activities for $195,001BOE0494 000
000BOE049703/09/06Date of Last Survey:982 HEGEMAN AVE.
P. S. 202 - BK -
A00054628/E23622009ParapetsArchitecture Exterior 69,180
A00002317/E23622009SwitchgearElectrical Under 600 Volts 52,344
A00002317/E23622009WiringElectrical Under 600 Volts 121,243
Total Planned activities for $242,767BOE0497 000
000BOE049802/06/03Date of Last Survey:5101 AVENUE M
P. S. 203 - BK -
K2031E4A/E23612003WindowsArchitecture Exterior 809,324
Total Planned activities for $809,324BOE0498 000
Page D - 30
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE050202/06/03Date of Last Survey:4011 FILLMORE AVE.
P. S. 207 - BK -
A00002391/E23622009Exterior WallsArchitecture Exterior 135,925
Total Planned activities for $135,925BOE0502 000
000BOE050310/03/02Date of Last Survey:4801 AVENUE D
P. S. 208 - BK -
A00127612/E23622009Exterior WallsArchitecture Exterior 83,098
A00002406/E23622007WiringElectrical Under 600 Volts 59,003
Total Planned activities for $142,101BOE0503 000
000BOE050407/22/04Date of Last Survey:AVE. Z & EAST 7TH ST.
P. S. 209 - BK -
A00020504/ED0012006WiringElectrical Under 600 Volts 70,804
Total Planned activities for $70,804BOE0504 000
000BOE050501/23/06Date of Last Survey:188 ROCHESTER AVENUE
I. S. 394/210 - BK - (I. S. 210 - BK )
EMERG2005/E23622007Exterior WallsArchitecture Exterior 492,641
A00054860/E23622008ParapetsArchitecture Exterior 36,078
Total Planned activities for $528,719BOE0505 000
000BOE050604/26/06Date of Last Survey:1001 EAST 100 STREET
I. S. 211 - BK - (J. H. S. 211 - BK)
A00002444/E23622009WiringElectrical Under 600 Volts 141,807
Total Planned activities for $141,807BOE0506 000
000BOE050703/21/06Date of Last Survey:87 BAY 49 STREET
P. S. 212 - BK -
A00127616/E23622009Exterior WallsArchitecture Exterior 349,033
Total Planned activities for $349,033BOE0507 000
000BOE050809/30/02Date of Last Survey:580 HEGEMAN AVE.
P. S. 213 - BK -
A00002480/E23622009SwitchgearElectrical Under 600 Volts 78,516
A00002480/E23622009WiringElectrical Under 600 Volts 62,936
Total Planned activities for $141,452BOE0508 000
000BOE051104/24/06Date of Last Survey:350 AVENUE X
P. S. 216 - BK -
A00002529/E23622007Exterior WallsArchitecture Exterior 319,770
Total Planned activities for $319,770BOE0511 000
000BOE051301/20/04Date of Last Survey:370 FOUNTAIN AVENUE
I. S. 218 - BK -
A00002556/E23622006WiringElectrical Under 600 Volts 126,051
A00019471/E23622006Conversion EquipmentMechanical Heating 63,936
Page D - 31
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
A00019471/E23622006DistributionMechanical Heating 91,701
Total Planned activities for $281,688BOE0513 000
000BOE051505/02/06Date of Last Survey:4812 9TH AVE.
I. S. 220 - BK - (J. H. S. 220 - BK)
EMERG2005/E23622006Exterior WallsArchitecture Exterior 39,002
Total Planned activities for $39,002BOE0515 000
000BOE051707/22/04Date of Last Survey:3301 QUENTIN ROAD
P. S. 222 - BK -
A00082993/E23622008WiringElectrical Under 600 Volts 97,659
Total Planned activities for $97,659BOE0517 000
000BOE051812/19/02Date of Last Survey:4200 16 AVENUE
I. S. 223 - BK -
K2231E5A/E23612004Exterior WallsArchitecture Exterior 143,750
K2231E4A/E23612003WindowsArchitecture Exterior 552,610
K2231E5A/E23612004ParapetsArchitecture Exterior 74,017
Total Planned activities for $770,377BOE0518 000
000BOE052203/24/06Date of Last Survey:6500 16TH AVE.
I. S. 227 - BK -
A00002703/E23622006FloorsArchitecture Interior 96,278
Total Planned activities for $96,278BOE0522 000
000BOE052403/22/05Date of Last Survey:1400 BENSON AVENUE
P. S. 229 - BK -
A00017584/E23622007WindowsArchitecture Exterior 336,763
Total Planned activities for $336,763BOE0524 000
000BOE052702/05/04Date of Last Survey:905 WINTHROP STREET
I. S. 232 - BK - (J. H. S. 232 - BK)
A00017706/E23622007Exterior WallsArchitecture Exterior 64,915
A00017710/E23622007WindowsArchitecture Exterior 297,464
A00017709/E23622007RoofArchitecture Exterior 351,029
A00002768/E23622009DistributionMechanical Heating 77,663
A00002768/E23622009Terminal DevicesMechanical Heating 119,945
A00002768/E23622009Exhaust FansMechanical Ventilation 122,966
Total Planned activities for $1,033,982BOE0527 000
000BOE052803/10/04Date of Last Survey:AVENUE B & EAST 93 STREET
P. S. 233 - BK -
A00002778/23622005WiringElectrical Under 600 Volts 110,295
Total Planned activities for $110,295BOE0528 000
000BOE053010/18/05Date of Last Survey:525 LENOX ROAD
P. S. 235 - BK -
Page D - 32
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
A00002807/E23622007Exterior WallsArchitecture Exterior 51,032
A00002808/E23622007WiringElectrical Under 600 Volts 55,069
Total Planned activities for $106,101BOE0530 000
000BOE053609/18/02Date of Last Survey:100-01 FLATLANDS AVENUE
P. S. 242 - BK - P.S. 279 - BK ANNEX
A00002905/E23622005WiringElectrical Under 600 Volts 43,269
Total Planned activities for $43,269BOE0536 000
000BOE054011/30/05Date of Last Survey:7000 21 AVENUE
P. S. 247 - BK -
EMERG2007/E23622007Exterior WallsArchitecture Exterior 54,469
Total Planned activities for $54,469BOE0540 000
000BOE054502/14/06Date of Last Survey:601 OCEAN VIEW AVENUE
P. S. 253 - BK -
A00019473/E23622007WindowsArchitecture Exterior 454,468
Total Planned activities for $454,468BOE0545 000
000BOE054609/30/02Date of Last Survey:1801 AVENUE Y
P. S. 254 - BK -
K2541E5A/E23612004Exterior WallsArchitecture Exterior 40,162
A00003042/E23622006DistributionMechanical Heating 46,480
A00003042/E23622006Terminal DevicesMechanical Heating 249,183
A00003042/E23622006Exhaust FansMechanical Ventilation 61,327
Total Planned activities for $397,152BOE0546 000
000BOE055003/21/06Date of Last Survey:141 MACON STREET
I. S. 258 - BK -
A00127642/E23622009WindowsArchitecture Exterior 1,782,929
Total Planned activities for $1,782,929BOE0550 000
000BOE055201/27/03Date of Last Survey:875 WILLIAMS AVENUE
P. S. 260 - BK -
A00003135/E23622009SwitchgearElectrical Under 600 Volts 78,516
A00003135/E23622009WiringElectrical Under 600 Volts 70,804
Total Planned activities for $149,320BOE0552 000
000BOE055302/18/05Date of Last Survey:314 PACIFIC STREET
P. S. 261 - BK -
K2611E4A/E23622005WindowsArchitecture Exterior 1,385,859
A00003151/E23622005WiringElectrical Under 600 Volts 97,659
Total Planned activities for $1,483,518BOE0553 000
000BOE055701/04/06Date of Last Survey:133 EAST 53RD STREET
P. S. 268 - BK -
A00003223/E23622009WiringElectrical Under 600 Volts 47,202
Page D - 33
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
Total Planned activities for $47,202BOE0557 000
010BOE055810/27/05Date of Last Survey:3109 NEWKIRK AVENUE
P. S. 361 - BK - FORMER P.S. 269 ANNEX (OL 89)
A00005208/E23622008FloorsArchitecture Interior 121,776
Total Planned activities for $121,776BOE0558 010
000BOE055901/09/03Date of Last Survey:241 EMERSON PLACE
P. S. 270 - BK -
EMERG2004/E23612004Exterior WallsArchitecture Exterior 47,208
Total Planned activities for $47,208BOE0559 000
000BOE056003/21/06Date of Last Survey:1137 HERKIMER STREET
I. S. 271 - BK -
A00003265/E23622006WindowsArchitecture Exterior 2,360,594
A00003271/E23622006FloorsArchitecture Interior 289,452
A00003259/E23622006DistributionMechanical Ventilation 40,908
Total Planned activities for $2,690,954BOE0560 000
000BOE056104/26/06Date of Last Survey:101-24 SEAVIEW AVENUE
P. S. 272 - BK -
A00003285/E23622006Exterior WallsArchitecture Exterior 58,048
A00003284/E23622006WindowsArchitecture Exterior 933,356
A00020912/E23622006ParapetsArchitecture Exterior 71,589
Total Planned activities for $1,062,993BOE0561 000
000BOE056205/04/06Date of Last Survey:923 JEROME ST.
P. S. 273 - BK -
A00017601/E23622008Exterior WallsArchitecture Exterior 62,401
A00056497/E23622008ParapetsArchitecture Exterior 36,602
Total Planned activities for $99,003BOE0562 000
000BOE056302/11/04Date of Last Survey:800 BUSHWICK AVENUE
P. S. 274 - BK -
A00003312/E23622006WindowsArchitecture Exterior 670,582
A00003311/E23622006RoofArchitecture Exterior 70,154
A00003312/E23622006WiringElectrical Under 600 Volts 121,243
Total Planned activities for $861,979BOE0563 000
010BOE056302/11/04Date of Last Survey:800 BUSHWICK AVENUE
P. S. 274 - BK - MINISCHOOL
A00003311/E23622006RoofArchitecture Exterior 177,860
Total Planned activities for $177,860BOE0563 010
000BOE056404/27/06Date of Last Survey:985 ROCKAWAY AVENUE
I. S. 275 - BK -
A00003324/E23622007Exterior WallsArchitecture Exterior 333,388
Page D - 34
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
Total Planned activities for $333,388BOE0564 000
000BOE056702/24/04Date of Last Survey:1925 STUART STREET
I. S. 278 - BK -
A00082971/E23622007SwitchgearElectrical Under 600 Volts 117,775
A00082971/E23622007WiringElectrical Under 600 Volts 141,807
Total Planned activities for $259,582BOE0567 000
000BOE056809/18/02Date of Last Survey:1070 EAST 104 STREET
P. S. 279 - BK -
A00003388/E23622005WiringElectrical Under 600 Volts 67,357
Total Planned activities for $67,357BOE0568 000
000BOE057102/13/03Date of Last Survey:220 WATKINS STREET
P. S. 284 - BK -
A00003432/E23622008Exterior WallsArchitecture Exterior 710,686
A00003431/E23622008WindowsArchitecture Exterior 1,121,345
Total Planned activities for $1,832,031BOE0571 000
000BOE057210/03/02Date of Last Survey:5905 BEVERLY ROAD
I. S. 285 - BK - (J. H. S. 285 - BK)
A00003448/E23622009SwitchgearElectrical Under 600 Volts 104,689
A00003448/E23622009WiringElectrical Under 600 Volts 121,243
Total Planned activities for $225,932BOE0572 000
000BOE057403/24/05Date of Last Survey:50 NAVY STREET
P. S. 287 - BK -
A00017626/E23622007RoofArchitecture Exterior 56,610
Total Planned activities for $56,610BOE0574 000
000BOE057504/17/06Date of Last Survey:2950 WEST 25 STREET
P. S. 288 - BK -
A00003489/E23622007ParapetsArchitecture Exterior 66,625
A00003489/E23622007RoofArchitecture Exterior 41,888
Total Planned activities for $108,513BOE0575 000
000BOE057902/10/04Date of Last Survey:300 WYONA STREET
I. S. 292 - BK -
A00003555/E23622008WindowsArchitecture Exterior 502,311
A00003555/E23622008ParapetsArchitecture Exterior 59,250
A00003555/E23622008RoofArchitecture Exterior 80,732
A00003562/E23622008WiringElectrical Under 600 Volts 149,686
Total Planned activities for $791,979BOE0579 000
000BOE058212/27/05Date of Last Survey:700 PARK AVENUE
P. S. 297 - BK -
A0000403603/E23622008WiringElectrical Under 600 Volts 103,403
Page D - 35
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
Total Planned activities for $103,403BOE0582 000
000BOE058802/24/03Date of Last Survey:344 MONROE STREET
P. S. 305 - BK -
A00127657/E23622009WindowsArchitecture Exterior 561,674
Total Planned activities for $561,674BOE0588 000
000BOE059102/12/04Date of Last Survey:616 QUINCY STREET
P. S. 308 - BK -
A00127659/E23622009Exterior WallsArchitecture Exterior 248,671
A00127658/E23622009WindowsArchitecture Exterior 82,195
Total Planned activities for $330,866BOE0591 000
000BOE059202/12/04Date of Last Survey:794 MONROE STREET
P. S. 309 - BK -
A00018180/E23622007WindowsArchitecture Exterior 591,236
A00082806/E23622007RoofArchitecture Exterior 357,643
Total Planned activities for $948,879BOE0592 000
000BOE059302/15/06Date of Last Survey:7103 AVENUE T
P. S. 312 - BK -
A00003778/E23622009RoofArchitecture Exterior 52,222
Total Planned activities for $52,222BOE0593 000
000BOE059512/03/02Date of Last Survey:750 CLASSON AVENUE
P. S. 316 - BK -
A00018093/E23622007WindowsArchitecture Exterior 551,351
A00003811/E23622009WiringElectrical Under 600 Volts 103,403
Total Planned activities for $654,754BOE0595 000
000BOE059803/29/06Date of Last Survey:46 MCKEEVER PLACE
I. S. 320 - BK -
A00018181/E23622007WindowsArchitecture Exterior 1,119,588
A00003844/E23622007DistributionMechanical Ventilation 33,073
Total Planned activities for $1,152,661BOE0598 000
000BOE060303/03/03Date of Last Survey:2929 WEST 30 STREET
P. S. 329 - BK -
A00057664/E23622008Exterior WallsArchitecture Exterior 80,908
Total Planned activities for $80,908BOE0603 000
000BOE060601/20/04Date of Last Survey:111 BERRIMAN STREET
P. S. 345 - BK -
A00017644/E23622007Exterior WallsArchitecture Exterior 92,882
A00057751/E23622007ParapetsArchitecture Exterior 60,405
A00017648/E23622007RoofArchitecture Exterior 612,987
Total Planned activities for $766,274BOE0606 000
Page D - 36
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE061012/23/02Date of Last Survey:355 37 STREET
P. S. 371 - BK (ALSO P.S. 231) -
A00017727/E23622007WindowsArchitecture Exterior 260,829
A00017725/E23622007RoofArchitecture Exterior 265,065
Total Planned activities for $525,894BOE0610 000
010BOE061012/23/02Date of Last Survey:360 36 STREET
BROOKLYN REGIONAL OFFICES -
K2311E4A/E23622005WindowsArchitecture Exterior 151,759
K2311E1A/E23622005RoofArchitecture Exterior 74,993
Total Planned activities for $226,752BOE0610 010
000BOE061310/28/04Date of Last Survey:1300 GREENE AVENUE
I. S. 383 - BK -
A00004064/E23622007General LightingElectrical Lighting 60,515
Total Planned activities for $60,515BOE0613 000
000BOE061903/17/03Date of Last Survey:60 EAST 94 STREET
P. S. 398 - BK (UDC) -
A00127672/E23622009WindowsArchitecture Exterior 70,416
A00127670/E23622009RoofArchitecture Exterior 40,480
Total Planned activities for $110,896BOE0619 000
000BOE062103/22/05Date of Last Survey:2630 BENSON AVE.
LAFAYETTE HIGH SCHOOL - BK -
A00017662/E23622007WindowsArchitecture Exterior 1,212,982
A00017658/E23622007RoofArchitecture Exterior 45,443
Total Planned activities for $1,258,425BOE0621 000
000BOE062212/24/03Date of Last Survey:2839 BEDFORD AVENUE
MIDWOOD HIGH SCHOOL - BK -
A00017669/E23622006Exterior WallsArchitecture Exterior 171,009
A00017671/E23622006ParapetsArchitecture Exterior 67,220
A00017672/E23622006RoofArchitecture Exterior 97,837
Total Planned activities for $336,066BOE0622 000
010BOE062212/24/03Date of Last Survey:E. 17 STREET & AVENUE L
MIDWOOD HIGH SCHOOL - BK - STADIUM / FIELDHOUSE
A00017669/E23622006Exterior WallsArchitecture Exterior 79,256
Total Planned activities for $79,256BOE0622 010
000BOE062402/04/04Date of Last Survey:5800 TILDEN AVE.
SAMUEL J. TILDEN HIGH SCHOOL -BK -
A00004244/E23622006WiringElectrical Under 600 Volts 70,873
A00004245/E23622006DistributionMechanical Heating 69,031
Total Planned activities for $139,904BOE0624 000
Page D - 37
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE062601/04/06Date of Last Survey:29 FORT GREENE PL.
BROOKLYN TECHNICAL H.S. - BK -
A00127677/E23622009RoofArchitecture Exterior 101,517
Total Planned activities for $101,517BOE0626 000
000BOE062705/31/06Date of Last Survey:400 PENNSYLVANIA AVE.
THOMAS JEFFERSON HIGH SCHOOL -BK -
A00058460/E23622009ParapetsArchitecture Exterior 53,104
A00004321/E23622009Pool Filter/TreatmentMechanical Plumbing 158,918
Total Planned activities for $212,022BOE0627 000
000BOE062802/26/03Date of Last Survey:883 CLASSON AVE.
PROSPECT HEIGHTS HIGH SCHOOL -BK -
K4406EA/E23612003Exterior WallsArchitecture Exterior 197,108
Total Planned activities for $197,108BOE0628 000
000BOE063011/22/04Date of Last Survey:850 GRAND STREET
EASTERN DISTRICT HIGH SCHOOL -BK -
A00058555/E23622007Exterior WallsArchitecture Exterior 45,728
EMERG2005/E23622005BatteriesElectrical Stand-by Power 40,552
Total Planned activities for $86,280BOE0630 000
000BOE063202/27/03Date of Last Survey:832 MARCY AVE
VARIABLE ALTERNATIVE H.S. - BK -
A00083133/E23622007WindowsArchitecture Exterior 62,069
Total Planned activities for $62,069BOE0632 000
000BOE063303/04/03Date of Last Survey:237 SEVENTH AVE
JOHN JAY HIGH SCHOOL - BK -
EMERG2005/E23622005Exterior WallsArchitecture Exterior 604,820
EMERG2005/E23622005ParapetsArchitecture Exterior 68,086
EMERG2005/E23622005RoofArchitecture Exterior 270,498
Total Planned activities for $943,404BOE0633 000
000BOE063409/17/03Date of Last Survey:911 FLATBUSH AVENUE
ERASMUS HALL HIGH SCHOOL - BK -
K4651E5A/E23622005Exterior WallsArchitecture Exterior 140,193
A00083186/E23622007WindowsArchitecture Exterior 143,183
A00082664/E23622007RoofArchitecture Exterior 160,008
Total Planned activities for $443,384BOE0634 000
000BOE063501/08/03Date of Last Survey:600 KINGSTON AVE.
GEORGE W. WINGATE HIGH SCHOOL-BK -
K4701E5A/E23622005WindowsArchitecture Exterior 2,325,992
K4701E5A/E23622005RoofArchitecture Exterior 123,142
A00004453/E23622006SwitchgearElectrical Under 600 Volts 261,722
Page D - 38
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
A00004453/E23622006PanelboardsElectrical Under 600 Volts 63,465
A00004453/E23622006WiringElectrical Under 600 Volts 318,927
A00004454/E23622006Conversion EquipmentMechanical Heating 238,097
A00004454/E23622006DistributionMechanical Heating 170,747
A00004446/E23622006Terminal DevicesMechanical Heating 75,069
A00004454/E23622006DistributionMechanical Ventilation 105,531
Total Planned activities for $3,682,692BOE0635 000
000BOE063804/12/06Date of Last Survey:1171 65TH STREET
CHRISTA MCAULIFFE SCHOOL - BK - (I.S. 187 - BK)
A00127690/E23622009Exterior WallsArchitecture Exterior 138,455
Total Planned activities for $138,455BOE0638 000
000BOE064007/22/04Date of Last Survey:3000 AVENUE X
SHEEPSHEAD BAY HIGH SCHOOL - BK -
A00004523/E23622006WiringElectrical Under 600 Volts 141,746
Total Planned activities for $141,746BOE0640 000
000BOE064410/21/03Date of Last Survey:1600 AVENUE L
EDWARD R. MURROW HIGH SCHOOL -BK -
A00004599/E23622007Exterior WallsArchitecture Exterior 406,714
A00004598/E23622007WindowsArchitecture Exterior 144,292
Total Planned activities for $551,006BOE0644 000
000BOE064709/22/03Date of Last Survey:901 CLASSON AVE
CLARA BARTON HIGH SCHOOL - BK -
K6001E4A/E23612003WindowsArchitecture Exterior 1,066,417
Total Planned activities for $1,066,417BOE0647 000
000BOE064810/22/03Date of Last Survey:50 BEDFORD AVE
AUTOMOTIVE HIGH SCHOOL - BK -
A00004672/E23622009SwitchgearElectrical Under 600 Volts 117,775
A00004672/E23622009PanelboardsElectrical Under 600 Volts 96,686
A00004672/E23622009WiringElectrical Under 600 Volts 141,807
A00004667/E23622006DistributionMechanical Heating 81,147
Total Planned activities for $437,415BOE0648 000
000BOE066012/09/02Date of Last Survey:131 LIVINGSTON STREET
BOARD OF EDUCATION ANNEX - BK -
A00059462/E23622008ParapetsArchitecture Exterior 228,121
Total Planned activities for $228,121BOE0660 000
000BOE066202/18/05Date of Last Survey:347 BALTIC STREET
COBBLE HILL/ACORN H.S. - BK - (OLD P.S. 6 - BK)
A00004862/E23622007WiringElectrical Under 600 Volts 73,290
Total Planned activities for $73,290BOE0662 000
Page D - 39
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE066502/02/06Date of Last Survey:355 PARK PLACE
DISTRICT OFFICE #13 - BK -
A00127712/E23622009WindowsArchitecture Exterior 83,665
Total Planned activities for $83,665BOE0665 000
000BOE066901/14/03Date of Last Survey:999 JAMAICA AVE.
FRANKLIN K. LANE HIGH SCHOOL -BK -
K4201E5A/E23622005Exterior WallsArchitecture Exterior 90,218
K4201E4A/E23622005WindowsArchitecture Exterior 913,583
A00004261/E23622008Energy SourceMechanical Heating 43,693
A00004261/E23622008Conversion EquipmentMechanical Heating 68,758
A00004261/E23622008DistributionMechanical Heating 98,616
A00004261/E23622008Terminal DevicesMechanical Heating 45,692
Total Planned activities for $1,260,560BOE0669 000
000BOE067201/24/03Date of Last Survey:108-35 167 STREET
J. H. S. 8 - Q -
A00008509/E23622005WindowsArchitecture Exterior 1,984,905
Total Planned activities for $1,984,905BOE0672 000
000BOE067410/05/05Date of Last Survey:31 AVE & 45 STREET
J. H. S. 10 - Q -
A00017464/E23622006WindowsArchitecture Exterior 764,547
Total Planned activities for $764,547BOE0674 000
000BOE067510/29/02Date of Last Survey:54-25 SKILLMAN AVENUE
P. S. 11 - Q -
A00019493/ED0012007SwitchgearElectrical Under 600 Volts 78,516
A00019493/ED0012007WiringElectrical Under 600 Volts 66,870
Total Planned activities for $145,386BOE0675 000
000BOE067710/06/05Date of Last Survey:55-01 94 STREET
P. S. 13 - Q -
A00066205/E23622008ParapetsArchitecture Exterior 64,430
Total Planned activities for $64,430BOE0677 000
000BOE067801/06/06Date of Last Survey:107-01 OTIS AVENUE
P. S. 14 - Q -
EMERG2005/E23622006Exterior WallsArchitecture Exterior 191,127
EMERG2005/E23622006WindowsArchitecture Exterior 313,520
EMERG2005/E23622006ParapetsArchitecture Exterior 76,332
EMERG2005/E23622006RoofArchitecture Exterior 35,779
Total Planned activities for $616,758BOE0678 000
000BOE068001/24/06Date of Last Survey:28-37 29 STREET
P. S. 17 - Q -
Page D - 40
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
EMERG2006/E23622007Exterior WallsArchitecture Exterior 109,065
Total Planned activities for $109,065BOE0680 000
000BOE068102/21/03Date of Last Survey:86-35 235 COURT
P. S. 18 - Q -
A00008631/E23622005WindowsArchitecture Exterior 628,641
Total Planned activities for $628,641BOE0681 000
000BOE068412/20/04Date of Last Survey:147-36 26 AVENUE
P. S. 21 - Q -
A00008676/E23622005Exterior WallsArchitecture Exterior 182,982
A00008674/E23622005RoofArchitecture Exterior 60,382
Total Planned activities for $243,364BOE0684 000
000BOE068511/04/05Date of Last Survey:153-33 SANFORD AVENUE
P. S. 22 - Q -
A00008684/E23622007RoofArchitecture Exterior 341,032
A00008690/E23622007WiringElectrical Under 600 Volts 74,737
Total Planned activities for $415,769BOE0685 000
000BOE069002/21/06Date of Last Survey:125-10 23 AVENUE
P. S. 29 - Q -
A00020237/E23622007Exterior WallsArchitecture Exterior 87,344
Total Planned activities for $87,344BOE0690 000
000BOE069212/05/03Date of Last Survey:211-45 46 ROAD
P. S. 31 - Q -
A00127899/E23622009Exterior WallsArchitecture Exterior 65,035
Total Planned activities for $65,035BOE0692 000
000BOE069311/25/03Date of Last Survey:171-11 35 AVENUE
P. S. 32 - Q -
A00127900/E23622009Exterior WallsArchitecture Exterior 70,001
Total Planned activities for $70,001BOE0693 000
000BOE069412/09/03Date of Last Survey:91-37 222 STREET
P. S. 33 - Q -
A00000406/E23622008WiringElectrical Under 600 Volts 94,300
Total Planned activities for $94,300BOE0694 000
000BOE069602/01/05Date of Last Survey:191-02 90 AVENUE
P. S. 35 - Q -
A00082602/E23622007WindowsArchitecture Exterior 526,681
Total Planned activities for $526,681BOE0696 000
000BOE069711/09/05Date of Last Survey:187-01 FOCH BLVD
P. S. 36 - Q -
A00008846/E23622007Exterior WallsArchitecture Exterior 43,498
Page D - 41
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
Total Planned activities for $43,498BOE0697 000
000BOE069802/21/03Date of Last Survey:179-37 137 AVENUE
P. S. 37 - Q -
Q0371E1A/E23612003RoofArchitecture Exterior 204,043
Total Planned activities for $204,043BOE0698 000
000BOE070103/01/06Date of Last Survey:214-43 35 AVENUE
P. S. 41 - Q -
A00020783/E23622007WindowsArchitecture Exterior 552,077
Total Planned activities for $552,077BOE0701 000
000BOE070212/03/03Date of Last Survey:488 BEACH 66 STREET
P. S. 42 - Q -
A00008920/E23622005SwitchgearElectrical Under 600 Volts 78,516
A00008920/E23622005WiringElectrical Under 600 Volts 70,804
Total Planned activities for $149,320BOE0702 000
000BOE070603/03/05Date of Last Survey:155-02 108 AVENUE
P. S. 48 - Q -
Q0481B3A/E23622005WindowsArchitecture Exterior 231,848
Total Planned activities for $231,848BOE0706 000
000BOE070710/24/05Date of Last Survey:79-15 PENELOPE AVENUE
P. S. 49 - Q -
A00017743/E23622007WindowsArchitecture Exterior 289,811
A00017746/E23622007RoofArchitecture Exterior 152,863
Total Planned activities for $442,674BOE0707 000
000BOE070902/15/05Date of Last Survey:GUY R. BREWER BLVD & 146 TERRACE
P. S. 52 - Q -
A00009032/E23622005WindowsArchitecture Exterior 526,327
A00009034/E23622005PanelboardsElectrical Under 600 Volts 35,699
A00009034/E23622005WiringElectrical Under 600 Volts 39,335
Total Planned activities for $601,361BOE0709 000
000BOE071102/02/05Date of Last Survey:86-02 127 STREET
P. S. 54 - Q -
Q0541B3A/E23622005WindowsArchitecture Exterior 444,176
Q0541B3A/E23622005ParapetsArchitecture Exterior 43,474
Total Planned activities for $487,650BOE0711 000
000BOE071401/29/04Date of Last Survey:132-55 RIDGEDALE STREET
I. S. 59 - Q -
A00009097/E23622007WindowsArchitecture Exterior 1,888,392
Total Planned activities for $1,888,392BOE0714 000
Page D - 42
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE071912/09/02Date of Last Survey:82-01 101 AVENUE
P. S. 64 - Q -
Q0641B3A/E23612004Exterior WallsArchitecture Exterior 155,574
Q0641B3A/E23612004WindowsArchitecture Exterior 380,569
Total Planned activities for $536,143BOE0719 000
000BOE072112/05/03Date of Last Survey:51-60 MARATHON PKWY
J. H. S. 67 - Q -
A00017755/E23622007WindowsArchitecture Exterior 1,845,460
A00017756/E23622007RoofArchitecture Exterior 64,077
Q067CC03A/ED0012004SwitchgearElectrical Under 600 Volts 117,775
Q067CC03A/ED0012004PanelboardsElectrical Under 600 Volts 44,624
Q067CC03A/ED0012004WiringElectrical Under 600 Volts 141,807
Total Planned activities for $2,213,743BOE0721 000
000BOE072211/01/05Date of Last Survey:59-09 SAINT FELIX AVENUE
P. S. 68 - Q -
A00067487/E23622009Exterior WallsArchitecture Exterior 99,735
Total Planned activities for $99,735BOE0722 000
010BOE072311/25/02Date of Last Survey:30-45 42 STREET
P. S. 70 - Q - MINISCHOOL
A00012018/E23622009RoofArchitecture Exterior 79,173
Total Planned activities for $79,173BOE0723 010
000BOE072411/10/04Date of Last Survey:77-02 37 AVENUE
P. S. 69 - Q -
Q0696EA/E23622006Exterior WallsArchitecture Exterior 337,064
Q0696EA/E23622006WindowsArchitecture Exterior 686,438
Q0696EA/E23622006ParapetsArchitecture Exterior 69,367
A00009208/E23622009General LightingElectrical Lighting 71,111
Total Planned activities for $1,163,980BOE0724 000
000BOE072511/01/05Date of Last Survey:62-85 FOREST AVENUE
P. S. 71 - Q -
A00009231/E23622009WiringElectrical Under 600 Volts 80,425
Total Planned activities for $80,425BOE0725 000
000BOE072710/15/03Date of Last Survey:70-02 54 AVE.
I. S. 73 - Q -
EMERG2005/E23622005ParapetsArchitecture Exterior 271,181
EMERG2005/E23622005RoofArchitecture Exterior 191,889
Total Planned activities for $463,070BOE0727 000
000BOE072802/23/06Date of Last Survey:61-15 OCEANIA STREET
I. S. 74 - Q -
Page D - 43
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
A00127924/E23622009Exterior WallsArchitecture Exterior 38,019
Total Planned activities for $38,019BOE0728 000
000BOE073010/05/05Date of Last Survey:36-36 10 STREET
P. S. 76 - Q -
A00127926/E23622009WindowsArchitecture Exterior 673,183
Total Planned activities for $673,183BOE0730 000
000BOE073311/06/03Date of Last Survey:559 CYPRESS AVENUE
P. S. 81 - Q -
A00009343/E23622007WindowsArchitecture Exterior 62,070
A00009344/E23622008SwitchgearElectrical Under 600 Volts 78,516
A00009344/E23622008PanelboardsElectrical Under 600 Volts 62,474
A00009344/E23622008WiringElectrical Under 600 Volts 70,804
Total Planned activities for $273,864BOE0733 000
000BOE073611/17/03Date of Last Survey:23-70 31 STREET
P. S. 85 - Q -
A00009380/E23622009SwitchgearElectrical Under 600 Volts 78,516
A00009380/E23622009WiringElectrical Under 600 Volts 70,804
Total Planned activities for $149,320BOE0736 000
000BOE073712/10/03Date of Last Survey:87-41 PARSONS BLVD
P. S. 86 - Q -
A00009389/E23622006WindowsArchitecture Exterior 102,314
A00009389/E23622006RoofArchitecture Exterior 39,333
Total Planned activities for $141,647BOE0737 000
000BOE073810/24/05Date of Last Survey:67-54 80 STREET
P. S. 87 - Q -
A00083160/E23622008Exterior WallsArchitecture Exterior 143,790
A00009411/E23622006WindowsArchitecture Exterior 701,050
A00083162/E23622008ParapetsArchitecture Exterior 60,929
Total Planned activities for $905,769BOE0738 000
000BOE073910/20/04Date of Last Survey:60-85 CATALPA AVENUE
P. S. 88 - Q -
A00017761/E23622007Exterior WallsArchitecture Exterior 253,348
A00017764/E23622007WindowsArchitecture Exterior 785,160
Total Planned activities for $1,038,508BOE0739 000
000BOE074011/20/03Date of Last Survey:85-28 BRITTON AVENUE
P. S. 89 - Q -
EMERG2005/E23622006Exterior WallsArchitecture Exterior 478,777
Total Planned activities for $478,777BOE0740 000
Page D - 44
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE074210/01/02Date of Last Survey:69 ST & CENTRAL AVENUE
P. S. 91 - Q -
A00127934/E23622009Exterior WallsArchitecture Exterior 203,953
Total Planned activities for $203,953BOE0742 000
000BOE074810/07/03Date of Last Survey:85-52 85 STREET
P. S. 97 - Q -
A00009516/E23622009WiringElectrical Under 600 Volts 68,936
Total Planned activities for $68,936BOE0748 000
000BOE075710/26/05Date of Last Survey:167-02 45 AVENUE
P. S. 107 - Q -
EMERG2005/E23622006Exterior WallsArchitecture Exterior 177,058
Total Planned activities for $177,058BOE0757 000
000BOE075912/09/03Date of Last Survey:213-10 92 AVENUE
I. S. 109 - Q -
A00020930/E23622007Exterior WallsArchitecture Exterior 183,896
A00068449/E23622007ParapetsArchitecture Exterior 72,839
Total Planned activities for $256,735BOE0759 000
000BOE076001/24/06Date of Last Survey:37-15 13 STREET
P. S. 111 - Q -
A00127944/E23622009Exterior WallsArchitecture Exterior 67,270
A00009678/E23622009SwitchgearElectrical Under 600 Volts 91,603
A00009678/E23622009WiringElectrical Under 600 Volts 103,403
Total Planned activities for $262,276BOE0760 000
000BOE076310/14/04Date of Last Survey:CRONSTON AVE & BEACH 135
P. S. 114 - Q -
A00009721/E23622009WiringElectrical Under 600 Volts 55,069
Total Planned activities for $55,069BOE0763 000
000BOE076401/24/06Date of Last Survey:80-51 261 STREET
P. S. 115 - Q -
Q1151E4A/E23622005Exterior WallsArchitecture Exterior 51,518
Q1151E4A/E23622005ParapetsArchitecture Exterior 56,847
Q1151E4A/E23622005RoofArchitecture Exterior 374,912
Total Planned activities for $483,277BOE0764 000
000BOE077310/29/02Date of Last Survey:46-02 47TH AVE.
I. S. 125 - Q -
EMERG2005/E23622006Exterior WallsArchitecture Exterior 171,636
EMERG2005/E23622006RoofArchitecture Exterior 52,412
Total Planned activities for $224,048BOE0773 000
Page D - 45
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE077410/30/03Date of Last Survey:31-51 21 STREET
I. S. 126 - Q -
A00127962/E23622009Exterior WallsArchitecture Exterior 153,116
Total Planned activities for $153,116BOE0774 000
000BOE077610/01/02Date of Last Survey:69-26 65TH DRIVE
P. S. 128 - Q -
Q1281E4A/E23622005WindowsArchitecture Exterior 136,297
Q1281E4A/E23622005RoofArchitecture Exterior 162,577
Total Planned activities for $298,874BOE0776 000
000BOE078001/17/06Date of Last Survey:218TH ST. & 132ND AVE.
P. S. 132 - Q -
EMERG2006/E23622007Exterior WallsArchitecture Exterior 40,441
Total Planned activities for $40,441BOE0780 000
000BOE078103/22/06Date of Last Survey:248-05 86 AVENUE
P. S. 133 - Q -
A00069092/E23622009ParapetsArchitecture Exterior 65,615
Total Planned activities for $65,615BOE0781 000
000BOE078211/09/05Date of Last Survey:109TH AVE. & 203RD ST.
P. S. 134 - Q -
Q1341E4A/E23622005WindowsArchitecture Exterior 576,450
Total Planned activities for $576,450BOE0782 000
000BOE078303/22/06Date of Last Survey:207-11 89 AVENUE
P. S. 135 - Q -
A00069154/E23622008ParapetsArchitecture Exterior 75,357
Total Planned activities for $75,357BOE0783 000
000BOE078512/02/04Date of Last Survey:253 ST & WELLER AVENUE
P. S. 138 - Q -
A00010049/E23622009SwitchgearElectrical Under 600 Volts 54,962
A00010049/E23622009PanelboardsElectrical Under 600 Volts 47,599
Total Planned activities for $102,561BOE0785 000
000BOE078701/25/06Date of Last Survey:116 AVE & 166 STREET
P. S. 140 - Q -
A00127971/E23622009Exterior WallsArchitecture Exterior 51,518
Total Planned activities for $51,518BOE0787 000
000BOE079010/11/05Date of Last Survey:34-74 113 STREET
P. S. 143 - Q -
A00010118/E23622008Exterior WallsArchitecture Exterior 63,127
Total Planned activities for $63,127BOE0790 000
Page D - 46
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE079212/06/04Date of Last Survey:33-34 80 STREET
I. S. 145 - Q -
A00017812/E23622007WindowsArchitecture Exterior 1,356,559
A00082673/E23622007DistributionMechanical Heating 42,967
Total Planned activities for $1,399,526BOE0792 000
000BOE079411/22/05Date of Last Survey:218-01 116 AVENUE
P. S. 147 - Q -
EMERG2006/E23622006Exterior WallsArchitecture Exterior 58,048
A00020902/E23622006ParapetsArchitecture Exterior 71,589
Total Planned activities for $129,637BOE0794 000
000BOE079511/20/03Date of Last Survey:89-02 32 AVENUE
P. S. 148 - Q -
Q1481B3A/E23622005WindowsArchitecture Exterior 143,251
Total Planned activities for $143,251BOE0795 000
000BOE079606/05/06Date of Last Survey:93-11 34 AVNEUE
P. S. 149 - Q -
A00010196/E23622007SwitchgearElectrical Under 600 Volts 91,603
A00010196/E23622007WiringElectrical Under 600 Volts 57,446
Total Planned activities for $149,049BOE0796 000
000BOE080301/17/06Date of Last Survey:229-02 137 AVENUE
P. S. 156 - Q -
A00010286/E23622007Exterior WallsArchitecture Exterior 58,048
Total Planned activities for $58,048BOE0803 000
000BOE080410/27/04Date of Last Survey:64 AVE & 102 STREET
J. H. S. 157 - Q -
A00010303/E23622006SwitchgearElectrical Under 600 Volts 94,220
A00010303/E23622006WiringElectrical Under 600 Volts 126,051
Total Planned activities for $220,271BOE0804 000
000BOE080612/05/03Date of Last Survey:205-01 33 AVENUE
P. S. 159 - Q -
A00127981/E23622009WindowsArchitecture Exterior 49,252
Total Planned activities for $49,252BOE0806 000
000BOE080812/04/03Date of Last Survey:201-02 53 AVENUE
P. S. 162 - Q -
A00010358/E23622005WindowsArchitecture Exterior 1,433,203
Total Planned activities for $1,433,203BOE0808 000
000BOE081012/16/05Date of Last Survey:138-01 77 AVENUE
P. S. 164 - Q -
A00127982/E23622009Exterior WallsArchitecture Exterior 48,693
Page D - 47
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
Total Planned activities for $48,693BOE0810 000
000BOE081112/16/05Date of Last Survey:70-35 150 STREET
P. S. 165 - Q -
A00010399/E23622005Exterior WallsArchitecture Exterior 53,237
A00010399/E23622005WindowsArchitecture Exterior 59,850
A00010399/E23622005ParapetsArchitecture Exterior 65,655
A00010399/E23622005RoofArchitecture Exterior 207,410
A00010406/E23622005SwitchgearElectrical Under 600 Volts 91,603
A00010406/E23622005PanelboardsElectrical Under 600 Volts 83,298
A00010406/E23622005WiringElectrical Under 600 Volts 103,403
Total Planned activities for $664,456BOE0811 000
000BOE081403/01/06Date of Last Survey:18-25 212 STREET
P. S. 169 - Q -
A00069992/E23622009Exterior WallsArchitecture Exterior 116,960
Total Planned activities for $116,960BOE0814 000
000BOE081511/17/03Date of Last Survey:14-14 29 AVENUE
P. S. 171 - Q -
A00010462/E23622009SwitchgearElectrical Under 600 Volts 117,775
A00010462/E23622009WiringElectrical Under 600 Volts 149,686
Total Planned activities for $267,461BOE0815 000
000BOE081601/24/06Date of Last Survey:81-14 257 STREET
J. H. S. 172 - Q -
EMERG2006/E23622006Exterior WallsArchitecture Exterior 125,895
Total Planned activities for $125,895BOE0816 000
000BOE082312/03/03Date of Last Survey:320 BEACH 104 STREET
J. H. S. 180 - Q -
A00082725/E23622006Exterior WallsArchitecture Exterior 805,523
Total Planned activities for $805,523BOE0823 000
000BOE082603/01/06Date of Last Survey:163-15 21 ROAD
P. S. 184 - Q -
A00017499/E23622007WindowsArchitecture Exterior 739,577
Total Planned activities for $739,577BOE0826 000
000BOE082803/17/03Date of Last Survey:252-12 72 AVENUE
P. S. 186 - Q -
A00082683/E23622007Exterior WallsArchitecture Exterior 52,069
A00082684/E23622007ParapetsArchitecture Exterior 72,825
Total Planned activities for $124,894BOE0828 000
000BOE082903/14/06Date of Last Survey:218-12 HARTLAND AVENUE
P. S. 188 - Q -
Page D - 48
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
A00127996/E23622009WindowsArchitecture Exterior 409,884
Total Planned activities for $409,884BOE0829 000
000BOE083111/02/05Date of Last Survey:68-17 AUSTIN STREET
J. H. S. 190 - Q -
A00010692/E23622007SwitchgearElectrical Under 600 Volts 94,220
A00010692/E23622007WiringElectrical Under 600 Volts 121,243
Total Planned activities for $215,463BOE0831 000
000BOE083201/24/06Date of Last Survey:85-15 258 STREET
P. S. 191 - Q -
A00127999/E23622009ParapetsArchitecture Exterior 86,411
Total Planned activities for $86,411BOE0832 000
000BOE083301/24/03Date of Last Survey:109-89 204 STREET
I. S. 192 - Q -
A00128000/E23622009WindowsArchitecture Exterior 2,008,981
A00010718/E23622009General LightingElectrical Lighting 104,258
Total Planned activities for $2,113,239BOE0833 000
000BOE083711/02/05Date of Last Survey:71-25 113 STREET
P. S. 196 - Q -
A00010771/E23622007SwitchgearElectrical Under 600 Volts 78,516
A00010771/E23622007WiringElectrical Under 600 Volts 70,804
Total Planned activities for $149,320BOE0837 000
000BOE084010/29/04Date of Last Survey:39-20 48TH AVE.
P. S. 199 - Q -
A00018785/ED0012006SwitchgearElectrical Under 600 Volts 78,516
A00018785/ED0012006WiringElectrical Under 600 Volts 55,069
Total Planned activities for $133,585BOE0840 000
000BOE084110/12/05Date of Last Survey:70-10 164 STREET
P. S. 200 - Q -
A00128005/23622009Exterior WallsArchitecture Exterior 158,410
A00128004/E23622009WindowsArchitecture Exterior 1,227,306
Total Planned activities for $1,385,716BOE0841 000
000BOE084402/23/06Date of Last Survey:53-11 SPRINGFIELD BLVD
P. S. 203 - Q -
A00128006/E23622009WindowsArchitecture Exterior 52,483
Total Planned activities for $52,483BOE0844 000
000BOE084510/30/03Date of Last Survey:36-41 28 STREET
J. H. S. 204 - Q -
A00128007/E23622009WindowsArchitecture Exterior 74,612
A00017834/E23622008RoofArchitecture Exterior 888,028
Page D - 49
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
Total Planned activities for $962,640BOE0845 000
000BOE084710/27/05Date of Last Survey:61-21 97 PLACE
P. S. 206 - Q -
A00010913/E23622009SwitchgearElectrical Under 600 Volts 39,258
A00010913/E23622009WiringElectrical Under 600 Volts 70,804
Total Planned activities for $110,062BOE0847 000
000BOE085612/19/05Date of Last Survey:144-39 GRAVETT ROAD
P. S. 219 - Q -
Q2191B3A/E23622005WindowsArchitecture Exterior 561,907
Total Planned activities for $561,907BOE0856 000
000BOE085712/06/04Date of Last Survey:62-10 108 STREET
P. S. 220 - Q -
A00011058/E23622009WiringElectrical Under 600 Volts 59,003
Total Planned activities for $59,003BOE0857 000
000BOE086012/09/02Date of Last Survey:121-10 ROCKAWAY BLVD
I. S. 226 - Q - (TANDEM P.S. 59 - M)
Q2261E4A/E23622005WindowsArchitecture Exterior 48,743
EMERG2005/E23622005Interior WallsArchitecture Interior 330,107
EMERG2005/E23622005CeilingsArchitecture Interior 97,635
Total Planned activities for $476,485BOE0860 000
000BOE086112/06/04Date of Last Survey:32-02 JUNCTION BLVD
I. S. 227 - Q -
A00082656/E23622007Exterior WallsArchitecture Exterior 117,376
A00011133/E23622007WindowsArchitecture Exterior 81,247
Total Planned activities for $198,623BOE0861 000
000BOE086210/24/05Date of Last Survey:67-25 51 ROAD
P. S. 229 - Q -
A00011150/E23622009WiringElectrical Under 600 Volts 94,300
Total Planned activities for $94,300BOE0862 000
000BOE086312/02/04Date of Last Survey:145-00 SPRINGFIELD BLVD
J. H. S. 231 - Q(TANDEM Q251-29) -
A00011166/E23622008Exterior WallsArchitecture Exterior 158,913
Total Planned activities for $158,913BOE0863 000
000BOE086403/04/05Date of Last Survey:153-23 83 STREET
P. S. 232 - Q -
A00017710/E23622007WindowsArchitecture Exterior 552,076
A00017709/E23622007RoofArchitecture Exterior 62,467
Total Planned activities for $614,543BOE0864 000
Page D - 50
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE086810/06/03Date of Last Survey:156-10 BAISLEY BLVD-JAMAICA
AUGUST MARTIN HIGH SCHOOL - Q -
Q4001B3A/E23622005WindowsArchitecture Exterior 503,961
Q4001B3A/E23622005RoofArchitecture Exterior 428,934
Total Planned activities for $932,895BOE0868 000
000BOE087010/14/04Date of Last Survey:100-00 BEACH CHANNEL DRIVE
BEACH CHANNEL HIGH SCHOOL - Q -
Port Auth-Non CP2006WindowsArchitecture Exterior 132,370
Total Planned activities for $132,370BOE0870 000
000BOE087301/09/06Date of Last Survey:63-25 MAIN ST. FLUSHING
JOHN BOWNE HIGH SCHOOL - Q -
Q4251E4A/E23622007WindowsArchitecture Exterior 874,955
Total Planned activities for $874,955BOE0873 000
000BOE087412/27/02Date of Last Survey:58-20 UTOPIA PKWY.-FLUSHING
FRANCIS LEWIS HIGH SCHOOL - Q -
A00011340/E23622005WindowsArchitecture Exterior 937,338
Total Planned activities for $937,338BOE0874 000
000BOE087601/23/03Date of Last Survey:67-01 110 ST.
FOREST HILLS HIGH SCHOOL - Q -
A00011373/E23622008Service EquipmentElectrical Under 600 Volts 57,207
A00011373/E23622008SwitchgearElectrical Under 600 Volts 261,722
A00011373/E23622008WiringElectrical Under 600 Volts 248,055
A00011373/E23622008Motor ControllersElectrical Under 600 Volts 40,570
Total Planned activities for $607,554BOE0876 000
000BOE087912/04/02Date of Last Survey:48-01 90TH STREET
NEWTOWN HIGH SCHOOL - Q -
A00011442/E23622007Exterior WallsArchitecture Exterior 115,485
Total Planned activities for $115,485BOE0879 000
000BOE088012/09/03Date of Last Survey:105-25 HORACE HARDING EXP.
H. S. OF ARTS & BUSINESS - Q -
EMERG2006/E23622006Exterior WallsArchitecture Exterior 45,256
Total Planned activities for $45,256BOE0880 000
000BOE088112/20/04Date of Last Survey:35-01 UNION STREET
FLUSHING HIGH SCHOOL - Q -
A00017707/E23622007Exterior WallsArchitecture Exterior 599,917
Q4601E4A/E23622005WindowsArchitecture Exterior 1,748,064
Q4601E1A/E23622005RoofArchitecture Exterior 83,059
Total Planned activities for $2,431,040BOE0881 000
Page D - 51
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE088303/09/06Date of Last Survey:167-01 GOTHIC DR.
JAMAICA HIGH SCHOOL - Q -
A00011509/E23622009WiringElectrical Under 600 Volts 248,055
Total Planned activities for $248,055BOE0883 000
000BOE088812/10/03Date of Last Survey:160-05 HIGHLAND AVE.
HILLCREST HIGH SCHOOL - Q -
A00128394/E23622007Exterior WallsArchitecture Exterior 332,029
A00128393/E23622007WindowsArchitecture Exterior 294,468
A00128391/E23622007RoofArchitecture Exterior 257,711
Total Planned activities for $884,208BOE0888 000
000BOE089001/11/05Date of Last Survey:37-02 47TH AVE.
QUEENS VOCATIONAL TECH. H.S. - Q -
A00017885/E23622007RoofArchitecture Exterior 184,756
A00011632/E23622007WiringElectrical Under 600 Volts 47,269
Total Planned activities for $232,025BOE0890 000
000BOE089212/10/03Date of Last Survey:165-65 84TH AVE.
THOMAS A. EDISON HIGH SCHOOL - Q -
A00011665/E23622009WiringElectrical Under 600 Volts 124,027
Total Planned activities for $124,027BOE0892 000
000BOE089712/01/03Date of Last Survey:976 SENECA AVENUE
I. S. 77 - Q (WITH I. S. 93 -Q) -
A00128066/E23622009Exterior WallsArchitecture Exterior 58,354
A00128065/E23622009WindowsArchitecture Exterior 237,344
Total Planned activities for $295,698BOE0897 000
000BOE089811/22/04Date of Last Survey:58 SUMMIT STREET
P. S. 1 - SI -
EMERG2005/E23622005Exterior WallsArchitecture Exterior 80,980
Total Planned activities for $80,980BOE0898 000
010BOE089811/22/04Date of Last Survey:58 SUMMIT STREET
P. S. 1 - SI - ANNEX
A00128139/E23622009Exterior WallsArchitecture Exterior 76,265
Total Planned activities for $76,265BOE0898 010
000BOE089904/26/04Date of Last Survey:333 MIDLAND AVENUE
I. S. 2 - SI -
A00012177/E23622005WiringElectrical Under 600 Volts 141,807
Total Planned activities for $141,807BOE0899 000
000BOE090103/07/06Date of Last Survey:NEDRA LANE AND ARDEN AVENUE
P. S. 4 - SI -
A00128358/E23622008RoofArchitecture Exterior 194,368
Page D - 52
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
Total Planned activities for $194,368BOE0901 000
000BOE090601/10/05Date of Last Survey:191 VERMONT AVENUE
P. S. 13 - SI -
A00020330/E23622006Exterior WallsArchitecture Exterior 192,439
Total Planned activities for $192,439BOE0906 000
000BOE090712/04/02Date of Last Survey:100 TOMPKINS AVENUE
P. S. 14 - SI -
R0141E5A/E23622005RoofArchitecture Exterior 67,651
A00012315/E23622006Conversion EquipmentMechanical Heating 65,636
A00012315/E23622006DistributionMechanical Heating 141,209
Total Planned activities for $274,496BOE0907 000
000BOE090812/08/04Date of Last Survey:80 MONROE AVENUE
P. S. 16 - SI -
R0161E5A/E23622006Exterior WallsArchitecture Exterior 60,824
R0161E5A/E23622006WindowsArchitecture Exterior 96,324
Total Planned activities for $157,148BOE0908 000
000BOE091210/14/03Date of Last Survey:168 HOOKER PLACE
P. S. 21 - SI -
A00017823/E23622007WindowsArchitecture Exterior 248,272
Total Planned activities for $248,272BOE0912 000
000BOE091303/22/06Date of Last Survey:1860 FOREST AVENUE
P. S. 22 - SI -
A00017826/E23622007WindowsArchitecture Exterior 98,009
Total Planned activities for $98,009BOE0913 000
000BOE091501/07/04Date of Last Survey:225 CLEVELAND AVENUE
I. S. 24 - SI -
A00017783/E23622007Exterior WallsArchitecture Exterior 105,087
Total Planned activities for $105,087BOE0915 000
000BOE091801/08/04Date of Last Survey:11 CLOVE LAKE PLACE
I. S. 27 - SI -
R0271B3A/E23622006Exterior WallsArchitecture Exterior 70,628
R0271B3A/E23622006WindowsArchitecture Exterior 2,008,981
R0271B3A/E23622006RoofArchitecture Exterior 95,160
Total Planned activities for $2,174,769BOE0918 000
000BOE091911/07/02Date of Last Survey:1581 VICTORY BLVD
P. S. 29 - SI -
A00083070/D0012007WiringElectrical Under 600 Volts 51,136
Total Planned activities for $51,136BOE0919 000
Page D - 53
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE092007/23/04Date of Last Survey:FISKE & LEONARD AVENUES
P. S. 30 - SI -
A00082649/D0012007WiringElectrical Under 600 Volts 55,069
Total Planned activities for $55,069BOE0920 000
000BOE092203/02/05Date of Last Survey:32 ELVERTON AVENUE
P. S. 32 - SI -
A00017848/E23622007WindowsArchitecture Exterior 110,270
A00020257/E23622007WiringElectrical Under 600 Volts 91,914
Total Planned activities for $202,184BOE0922 000
000BOE092304/15/04Date of Last Survey:ACADEMY ST & YETMAN AVENUES
I. S. 34 - SI (OL TOTVIL) -
EMERG2005/E23622005Exterior WallsArchitecture Exterior 81,444
Total Planned activities for $81,444BOE0923 000
000BOE092503/02/05Date of Last Survey:255 IONIA AVENUE
P. S. 36 - SI -
A00017788/E23622007RoofArchitecture Exterior 845,958
Total Planned activities for $845,958BOE0925 000
000BOE092701/10/05Date of Last Survey:SAND LANE & MACFARLAND AVENUE
P. S. 39 - SI -
A00083070/D0012007SwitchgearElectrical Under 600 Volts 65,431
Total Planned activities for $65,431BOE0927 000
000BOE093402/03/05Date of Last Survey:101 WARREN STREET
I. S. 49 - SI -
A00012846/E23622006FloorsArchitecture Interior 59,826
Total Planned activities for $59,826BOE0934 000
000BOE093501/06/04Date of Last Survey:200 ADELAIDE AVENUE
P. S. 50 - SI -
A00018012/E23622007WindowsArchitecture Exterior 843,053
A00018009/E23622007ParapetsArchitecture Exterior 99,428
Total Planned activities for $942,481BOE0935 000
000BOE093801/07/04Date of Last Survey:330 DURANT AVENUE
P. S. 53 - SI -
A00012914/E23622006WindowsArchitecture Exterior 445,059
Total Planned activities for $445,059BOE0938 000
000BOE094003/14/05Date of Last Survey:54 OSBORNE STREET
P. S. 55 - SI -
A00083176/E23622008WiringElectrical Under 600 Volts 97,659
Total Planned activities for $97,659BOE0940 000
Page D - 54
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE094410/13/05Date of Last Survey:144 KEATING PLACE
P. S. 69 - SI -
A00017811/E23622008RoofArchitecture Exterior 899,690
Total Planned activities for $899,690BOE0944 000
000BOE094506/01/06Date of Last Survey:33 FERNDALE AVENUE
I. S. 72 - SI -
A00128124/E23622009WindowsArchitecture Exterior 82,340
Total Planned activities for $82,340BOE0945 000
000BOE094603/07/06Date of Last Survey:HUGUENOT AVENUE & CASTOR PLACE
I. S. 75 - SI -
A00074742/E23622008ParapetsArchitecture Exterior 63,859
A00013082/E23622008RoofArchitecture Exterior 35,635
Total Planned activities for $99,494BOE0946 000
000BOE094702/15/05Date of Last Survey:465 NEW DORP LANE
NEW DORP HIGH SCHOOL - SI -
R4351B3A/E23622005ParapetsArchitecture Exterior 53,922
Total Planned activities for $53,922BOE0947 000
000BOE094811/19/03Date of Last Survey:458 CLAWSON ST.
STATEN ISLAND TECH H.S. - SI -
R4401E4A/E23622007Exterior WallsArchitecture Exterior 56,565
R4401E4A/E23622007WindowsArchitecture Exterior 797,826
R4401E4A/E23622007RoofArchitecture Exterior 512,067
A00013138/E23622007WiringElectrical Under 600 Volts 141,807
Total Planned activities for $1,508,265BOE0948 000
000BOE095001/05/04Date of Last Survey:105 HAMILTON AVE.
CURTIS HIGH SCHOOL - SI -
A00082723/E23622007Exterior WallsArchitecture Exterior 389,248
A00018089/E23622007RoofArchitecture Exterior 96,189
Total Planned activities for $485,437BOE0950 000
000BOE095102/24/04Date of Last Survey:100 LUTEN AVE
TOTTENVILLE HIGH SCHOOL - SI -
A00013190/E23622007RoofArchitecture Exterior 1,767,628
Total Planned activities for $1,767,628BOE0951 000
000BOE095203/15/05Date of Last Survey:1200 MANOR RD
SUSAN E. WAGNER HIGH SCHOOL - SI -
A00020329/E23622007Exterior WallsArchitecture Exterior 507,156
A00018187/E23622007RoofArchitecture Exterior 90,826
Total Planned activities for $597,982BOE0952 000
Page D - 55
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE095712/08/04Date of Last Survey:211 DANIEL LOW TERR.
P. S. 16 - SI ANNEX -
A00018053/E23622007Exterior WallsArchitecture Exterior 99,615
A00018061/E23622007RoofArchitecture Exterior 105,671
Total Planned activities for $205,286BOE0957 000
000BOE096002/20/04Date of Last Survey:1075 SECOND AVE
ART & DESIGN HIGH SCHOOL - M -
A00018763/ED0012006WiringElectrical Under 600 Volts 283,491
Total Planned activities for $283,491BOE0960 000
010BOE096702/16/05Date of Last Survey:25 AUGUSTA AVENUE
P. S. 42 - SI - ANNEX
EMERG2005/E23622005Exterior WallsArchitecture Exterior 36,954
A00013432/E23622006SwitchgearElectrical Under 600 Volts 52,344
Total Planned activities for $89,298BOE0967 010
000BOE097103/22/06Date of Last Survey:20 HOUSTON ST.
I. S. 51 - SI -
A00083073/D0012007WiringElectrical Under 600 Volts 133,929
Total Planned activities for $133,929BOE0971 000
000BOE097410/18/04Date of Last Survey:BROADWAY & 196TH ST.
I. S. 218 - M -
EMERG2005-C/E23622005Exterior WallsArchitecture Exterior 498,255
EMERG2005/E23622006Interior WallsArchitecture Interior 93,387
Total Planned activities for $591,642BOE0974 000
000BOE097610/21/02Date of Last Survey:3703 10TH AVE.
P. S. 5 - MANHATTAN -
A00128346/E23622008WindowsArchitecture Exterior 37,793
Total Planned activities for $37,793BOE0976 000
000BOE098512/12/02Date of Last Survey:645 MAIN ST.,
P. S./I. S. 217 - M -
A00007669/E23622007General LightingElectrical Lighting 71,738
Total Planned activities for $71,738BOE0985 000
000BOE099112/12/02Date of Last Survey:149-11 MELBOURNE AVENUE
TOWNSEND HARRIS H. S. - Q -
A00011606/E23622009General LightingElectrical Lighting 122,140
Total Planned activities for $122,140BOE0991 000
000BOE099201/21/03Date of Last Survey:150-91 87 ROAD
GATEWAY TO HEALTH SCIENCES HS-Q -
Q6801E5A/E23622005Exterior WallsArchitecture Exterior 670,378
Total Planned activities for $670,378BOE0992 000
Page D - 56
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF EDUCATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
D
000BOE102104/02/03Date of Last Survey:965 LONGWOOD AVENUE
NEW SCHOOL FOR ARTS & SCIENCES - - BX /FORMER P.S. 39 - BX
A00017191/E23622009Exterior WallsArchitecture Exterior 148,421
A00017191/E23622009RoofArchitecture Exterior 142,633
Total Planned activities for $291,054BOE1021 000
000DGS002204/20/04Date of Last Survey:283-289 ADAMS STREET
BROOKLYN FAMILY COURT -
A000020196/E23622007Exterior WallsArchitecture Exterior 955,574
A000020196/E23622007RoofArchitecture Exterior 202,301
A000020196/E23622007WiringElectrical Under 600 Volts 64,017
A000020196/E23622007DistributionMechanical Heating 35,678
Total Planned activities for $1,257,570DGS0022 000
Total Planned Activities for : $196,304,202DEPARTMENT OF EDUCATION
Total Required for "State of Good Repair" for : DEPARTMENT OF EDUCATION $784,662,528
Page D - 57
Appendix
FMS ID/ Budget Code
Agency Activity Year
CITY UNIVERSITY
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
E
010CUN000104/01/03Date of Last Survey:1150 CARROLL STREET
MEDGER EVERS COLLEGE - MAIN BLDG
ME070-0962007RoofArchitecture Exterior 102,483
ME071-0962007DistributionMechanical Heating 52,273
Total Planned activities for $154,756CUN0001 010
010CUN000204/04/03Date of Last Survey:475 GRAND CONCOURSE
HOSTOS COMMUNITY COLLEGE - A BUILDING (22002)
DASNY2007RoofArchitecture Exterior 48,257
Total Planned activities for $48,257CUN0002 010
020CUN000204/04/03Date of Last Survey:500 GRAND CONCOURSE
HOSTOS COMMUNITY COLLEGE - B BUILDING (22001)
DASNY2005RoofArchitecture Exterior 116,946
Total Planned activities for $116,946CUN0002 020
040CUN000204/04/03Date of Last Survey:460 GRAND CONCOURSE
HOSTOS COMMUNITY COLLEGE - EAST ACADEMIC COMPLEX
DASNY2005RoofArchitecture Exterior 1,116,792
Total Planned activities for $1,116,792CUN0002 040
010CUN000311/03/03Date of Last Survey:NORTH SIDE (SHEEPSHEAD BAY)
KINGSBOROUGH COMMUNITY COLLEGE - BULKHEAD
DASNY2005Sheet PilesBulkheads Structural 291,216
Total Planned activities for $291,216CUN0003 010
020CUN000311/03/03Date of Last Survey:EAST SIDE (JAMAICA BAY)
KINGSBOROUGH COMMUNITY COLLEGE - BULKHEAD
DASNY2005Coping/CurbBulkheads Structural 104,045
DASNY2005RevetmentBulkheads Structural 100,421
DASNY2005Sheet PilesBulkheads Structural 180,709
Total Planned activities for $385,175CUN0003 020
030CUN000311/03/03Date of Last Survey:SOUTH SIDE (ALTLANTIC OCEAN)
KINGSBOROUGH COMMUNITY COLLEGE - BULKHEAD
DASNY2005SurfaceBulkheads Backfill 44,357
Total Planned activities for $44,357CUN0003 030
0L0CUN000306/27/06Date of Last Survey:2000 ORIENTAL BLVD.
KINGSBOROUGH COMMUNITY COLLEGE - LIBRARY AND MEDIA CENTER - L
CA200KG032007Exterior WallsArchitecture Exterior 261,333
Total Planned activities for $261,333CUN0003 0L0
0M0CUN000306/29/06Date of Last Survey:2110 ORIENTAL BLVD.
KINGSBOROUGH COMMUNITY COLLEGE - MARINE & ACADEMIC CENTER - M
KG200-0062007RoofArchitecture Exterior 1,226,298
Total Planned activities for $1,226,298CUN0003 0M0
Page E - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
CITY UNIVERSITY
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
E
0P0CUN000306/26/06Date of Last Survey:1813 ORIENTAL BLVD.
KINGSBOROUGH COMMUNITY COLLEGE - CENTRAL SERVICES - P
KG200-0062007RoofArchitecture Exterior 496,542
Total Planned activities for $496,542CUN0003 0P0
0T0CUN000306/28/06Date of Last Survey:2001 ORIENTAL BLVD.
KINGSBOROUGH COMMUNITY COLLEGE - PERFORMING ARTS CENTER - T
CA200KG032007Exterior WallsArchitecture Exterior 78,526
Total Planned activities for $78,526CUN0003 0T0
2T0CUN000306/28/06Date of Last Survey:2065 ORIENTAL BLVD.
KINGSBOROUGH COMMUNITY COLLEGE - TEMPORARY BLDG. T2
KG126-0982007FloorsArchitecture Interior 109,875
Total Planned activities for $109,875CUN0003 2T0
4T0CUN000306/28/06Date of Last Survey:2111 ORIENTAL BLVD.
KINGSBOROUGH COMMUNITY COLLEGE - TEMPORARY BLDG. T4
DASNY2002RoofArchitecture Exterior 168,463
Total Planned activities for $168,463CUN0003 4T0
6T0CUN000306/28/06Date of Last Survey:2105 ORIENTAL BLVD.
KINGSBOROUGH COMMUNITY COLLEGE - TEMPORARY BLDG. T6
DASNY2002RoofArchitecture Exterior 66,384
Total Planned activities for $66,384CUN0003 6T0
030CUN000405/05/04Date of Last Survey:29-10 THOMSON AVENUE
LAGUARDIA COMMUNITY COLLEGE - CENTER 3 - GARAGE
CA200LG022007WindowsArchitecture Exterior 482,666
DASNY2006RoofArchitecture Exterior 645,745
Total Planned activities for $1,128,411CUN0004 030
010CUN000506/13/06Date of Last Survey:199 CHAMBERS STREET
BOR. OF MANHATTAN COMM. COLLEGE - BMCC MAIN CAMPUS BLDG
MC201-0062009Exterior WallsArchitecture Exterior 1,006,024
CA200MC042007WindowsArchitecture Exterior 239,554
CA200MC042007ParapetsArchitecture Exterior 84,605
MC201-0062009RoofArchitecture Exterior 2,112,129
Total Planned activities for $3,442,312CUN0005 010
020CUN000603/25/03Date of Last Survey:SPRG BLVD & 56 AVENUE
QUEENSBOROUGH COMMUNITY COLLEGE - TECHNOLOGY BLDG
DASNY2001Exterior WallsArchitecture Exterior 154,803
Total Planned activities for $154,803CUN0006 020
050CUN000603/24/03Date of Last Survey:SPRG BLVD & 56 AVENUE
QUEENSBOROUGH COMMUNITY COLLEGE - KENNEDY HALL
DASNY2006RoofArchitecture Exterior 135,816
Page E - 2
Appendix
FMS ID/ Budget Code
Agency Activity Year
CITY UNIVERSITY
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
E
Total Planned activities for $135,816CUN0006 050
110CUN000603/24/03Date of Last Survey:SPRG BLVD & 56 AVENUE
QUEENSBOROUGH COMMUNITY COLLEGE - ADMIN & BUSINESS BLDG
QB162-0962011DistributionMechanical Ventilation 48,076
Total Planned activities for $48,076CUN0006 110
300CUN000603/24/03Date of Last Survey:SPRG BLVD & 56 AVENUE
QUEENSBOROUGH COMMUNITY COLLEGE - HUMANITIES BLDG
DASNY2001Exterior WallsArchitecture Exterior 182,219
DASNY2001WindowsArchitecture Exterior 120,487
Total Planned activities for $302,706CUN0006 300
050CUN000703/12/03Date of Last Survey:2020 SEDGWICK AVENUE
BRONX COMMUNITY COLLEGE - COLSTON HALL
CA200BX042007WindowsArchitecture Exterior 203,152
Total Planned activities for $203,152CUN0007 050
290CUN000703/11/03Date of Last Survey:161 WEST 180th STREET
BRONX COMMUNITY COLLEGE - MEISTER HALL (TECH II)
CA200BX042007Exterior WallsArchitecture Exterior 205,786
DASNY2008RoofArchitecture Exterior 67,145
Total Planned activities for $272,931CUN0007 290
300CUN000703/11/03Date of Last Survey:171 WEST 180th ST
BRONX COMMUNITY COLLEGE - SAGE ENGINEERING
DASNY2005RoofArchitecture Exterior 136,923
Total Planned activities for $136,923CUN0007 300
560CUN000703/11/03Date of Last Survey:2205 SEDGWICK AVENUE
BRONX COMMUNITY COLLEGE - ALTSCHUL HOUSE
DASNY2003RoofArchitecture Exterior 90,786
Total Planned activities for $90,786CUN0007 560
Total Planned Activities for : $10,480,836CITY UNIVERSITY
Total Required for "State of Good Repair" for : CITY UNIVERSITY $43,311,488
Page E - 3
Appendix
FMS ID/ Budget Code
Agency Activity Year
POLICE DEPARTMENT
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
F
010DGSP00501/03/06Date of Last Survey:PIERS 35 & 36, EAST RIVER
POLICE OFFICES -
PT195-VAR2011Heat RejectionMechanical Air Conditioning 59,404
Total Planned activities for $59,404DGSP005 010
000DOT008804/30/04Date of Last Survey:103-109 PARK ROW
MANHATTAN CIVIC CENTER-GARAGE -
PO792011Exterior WallsArchitecture Exterior 72,013
PO792011General LightingElectrical Lighting 69,815
Total Planned activities for $141,828DOT0088 000
010DOT009810/30/01Date of Last Survey:W 34TH TO W 37TH STS
PIER 76 - NYPD TOW POUND
801C52322008Pile CapsPiers Structural 70,079
801C52322008Piles and BracingPiers Structural 202,859
801C52322008Wales and ChocksPiers Fender 192,579
801C52322008PilesPiers Fender 81,569
Total Planned activities for $547,085DOT0098 010
040DOT012710/30/01Date of Last Survey:W 34TH TO W 37TH STS
BULKHEAD AT PIER 76 -
801C52322008Pile Supported WallBulkheads Structural 42,741
Total Planned activities for $42,741DOT0127 040
000NYP000101/07/05Date of Last Survey:16-20 ERICSSON PLACE
1 PRECINCT/TROOP A -
PO792011RoofArchitecture Exterior 46,247
Total Planned activities for $46,247NYP0001 000
000NYP000310/04/05Date of Last Survey:233 WEST 10TH STREET
6 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 36,460
PO792011ParapetsArchitecture Exterior 58,625
PO792011FloorsArchitecture Interior 104,740
PO792011CeilingsArchitecture Interior 49,580
Total Planned activities for $249,405NYP0003 000
000NYP000401/25/06Date of Last Survey:132 BROOME STREET
7 PRECINCT/FIRE DEPT. - CO-LOCATE
PO792011Exterior WallsArchitecture Exterior 92,608
PO792011ParapetsArchitecture Exterior 69,081
PO792011FloorsArchitecture Interior 62,878
Total Planned activities for $224,567NYP0004 000
000NYP000511/02/00Date of Last Survey:321 EAST 5TH STREET
9 PRECINCT -
Page F - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
POLICE DEPARTMENT
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
F
PO792007Exterior WallsArchitecture Exterior 577,412
PO792007RoofArchitecture Exterior 38,681
PO792007FloorsArchitecture Interior 169,531
PO792007Interior WallsArchitecture Interior 91,806
PO792007CeilingsArchitecture Interior 93,803
PO792007General LightingElectrical Lighting 86,780
PO792007Conversion EquipmentMechanical Heating 72,382
PO792007DistributionMechanical Heating 96,563
PO792007Terminal DevicesMechanical Heating 603,154
PO792007Conversion EquipmentMechanical Air Conditioning 268,500
Total Planned activities for $2,098,612NYP0005 000
000NYP000612/30/04Date of Last Survey:230 WEST 20TH STREET
10 PRECINCT -
PO792007Exterior WallsArchitecture Exterior 82,206
Total Planned activities for $82,206NYP0006 000
000NYP000804/13/04Date of Last Survey:357 WEST 35TH STREET
MIDTOWN SOUTH PRECINCT -
PO792005WindowsArchitecture Exterior 329,290
PO792005RoofArchitecture Exterior 125,163
PO792005FloorsArchitecture Interior 188,404
PO792011CeilingsArchitecture Interior 92,385
PO792009GeneratorsElectrical Stand-by Power 63,856
PO792004Terminal DevicesMechanical Heating 40,602
PO792011Terminal DevicesMechanical Air Conditioning 127,939
Total Planned activities for $967,639NYP0008 000
000NYP000911/05/04Date of Last Survey:306 WEST 54TH STREET
MIDTOWN NORTH PCT & GARAGE ANNEX - (FORMER 18 PCT)
PO792011Exterior WallsArchitecture Exterior 106,158
Total Planned activities for $106,158NYP0009 000
000NYP001003/27/03Date of Last Survey:153 EAST 67TH STREET
19 PRECINCT -
PO792011WindowsArchitecture Exterior 35,387
Total Planned activities for $35,387NYP0010 000
000NYP001102/24/06Date of Last Survey:120 WEST 82ND STREET
20 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 54,200
PO792011ParapetsArchitecture Exterior 35,363
PO792011Terminal DevicesMechanical Air Conditioning 120,438
Total Planned activities for $210,001NYP0011 000
Page F - 2
Appendix
FMS ID/ Budget Code
Agency Activity Year
POLICE DEPARTMENT
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
F
000NYP001204/14/04Date of Last Survey:162 EAST 102ND STREET
23 PRECINCT / FD ENG CO. 53 - COMBINED FACILITY
PO792011Exterior WallsArchitecture Exterior 67,584
PO792011ParapetsArchitecture Exterior 69,543
PO792011CeilingsArchitecture Interior 152,261
PO792011GeneratorsElectrical Stand-by Power 63,856
Total Planned activities for $353,244NYP0012 000
000NYP001303/04/03Date of Last Survey:151 WEST 100TH STREET
24 PRECINCT/PBMN/FD - CO-LOCATE
PO792005RoofArchitecture Exterior 44,964
PO792011Conversion EquipmentMechanical Air Conditioning 51,487
Total Planned activities for $96,451NYP0013 000
000NYP001405/27/03Date of Last Survey:120 EAST 119TH STREET
25 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 68,230
PO792011WindowsArchitecture Exterior 80,359
PO792009WindowsArchitecture Exterior 654,098
PO792007Conversion EquipmentMechanical Heating 43,024
PO792011DistributionMechanical Heating 49,075
Total Planned activities for $894,786NYP0014 000
000NYP001509/14/05Date of Last Survey:520 WEST 126TH STREET
26 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 40,823
Total Planned activities for $40,823NYP0015 000
000NYP001609/14/05Date of Last Survey:2271-89 FREDERICK DOUGLASS BLVD
28 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 134,680
PO792011RoofArchitecture Exterior 134,108
Total Planned activities for $268,788NYP0016 000
000NYP001704/08/04Date of Last Survey:451 WEST 151ST STREET
30 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 57,994
PO792011WindowsArchitecture Exterior 102,753
PO792007RoofArchitecture Exterior 140,108
PO792011GeneratorsElectrical Stand-by Power 63,856
PO792011General LightingElectrical Lighting 121,210
Total Planned activities for $485,921NYP0017 000
000NYP001804/28/05Date of Last Survey:250 WEST 135TH STREET
32 PRECINCT -
Page F - 3
Appendix
FMS ID/ Budget Code
Agency Activity Year
POLICE DEPARTMENT
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
F
PO792011Exterior WallsArchitecture Exterior 38,593
PO792011RoofArchitecture Exterior 78,966
PO792011Terminal DevicesMechanical Heating 69,718
Total Planned activities for $187,277NYP0018 000
000NYP001910/31/02Date of Last Survey:4295 BROADWAY
34 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 73,587
PO792007RoofArchitecture Exterior 133,334
Total Planned activities for $206,921NYP0019 000
000NYP002009/14/04Date of Last Survey:257 ALEXANDER AVENUE
40 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 97,504
PO792007Exterior WallsArchitecture Exterior 107,909
PO792011WindowsArchitecture Exterior 190,056
PO792011RoofArchitecture Exterior 72,184
Total Planned activities for $467,653NYP0020 000
000NYP002109/16/05Date of Last Survey:1086 SIMPSON STREET
DETECTIVE BUREAU BRONX - OLD 41 PRECINCT
PO792011WindowsArchitecture Exterior 57,014
PO792011Interior WallsArchitecture Interior 128,293
Total Planned activities for $185,307NYP0021 000
000NYP002209/14/04Date of Last Survey:830 WASHINGTON AVENUE
42 PRECINCT -
PO792011WindowsArchitecture Exterior 65,247
PO792011FloorsArchitecture Interior 45,763
PO792011Interior WallsArchitecture Interior 121,444
Total Planned activities for $232,454NYP0022 000
000NYP002302/01/06Date of Last Survey:900 FTELEY AVENUE
43 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 40,829
PO792011ParapetsArchitecture Exterior 37,563
PO792011RoofArchitecture Exterior 144,093
Total Planned activities for $222,485NYP0023 000
000NYP002409/14/04Date of Last Survey:1278 SEDGWICK AVENUE
BRONX TASK FORCE (OLD 44 PCT.) -
PO792011FloorsArchitecture Interior 259,648
PO792008General LightingElectrical Lighting 66,325
Total Planned activities for $325,973NYP0024 000
Page F - 4
Appendix
FMS ID/ Budget Code
Agency Activity Year
POLICE DEPARTMENT
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
F
000NYP002503/30/05Date of Last Survey:2877 BARKLEY AVENUE
45 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 96,180
PO792011FloorsArchitecture Interior 85,417
Total Planned activities for $181,597NYP0025 000
000NYP002609/22/05Date of Last Survey:2120 RYER AVENUE
46 PRECINCT -
PO792011CeilingsArchitecture Interior 39,260
Total Planned activities for $39,260NYP0026 000
000NYP002710/16/03Date of Last Survey:4111 LACONIA AVENUE
47 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 36,588
PO792004WindowsArchitecture Exterior 337,734
PO792011GeneratorsElectrical Stand-by Power 63,856
PO792011General LightingElectrical Lighting 108,473
Total Planned activities for $546,651NYP0027 000
000NYP002809/22/05Date of Last Survey:450 CROSS BRONX EXPWY
48 PRECINCT/PBBX/FD - CO-LOCATE
PO792011ParapetsArchitecture Exterior 38,082
PO792011RoofArchitecture Exterior 56,764
PO792011Heat RejectionMechanical Air Conditioning 74,953
Total Planned activities for $169,799NYP0028 000
000NYP002909/27/05Date of Last Survey:2121 EASTCHESTER ROAD
49 PRECINCT -
PO792011WindowsArchitecture Exterior 36,692
PO792011Interior WallsArchitecture Interior 51,026
Total Planned activities for $87,718NYP0029 000
000NYP003009/28/05Date of Last Survey:3450 KINGSBRIDGE AVENUE
50 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 35,558
PO792011WindowsArchitecture Exterior 53,750
PO792011ParapetsArchitecture Exterior 38,444
Total Planned activities for $127,752NYP0030 000
000NYP003109/29/05Date of Last Survey:3016 WEBSTER AVENUE
52 PRECINCT -
PO792008Exterior WallsArchitecture Exterior 258,055
PO792008RoofArchitecture Exterior 53,821
PO792007FloorsArchitecture Interior 60,481
PO792011Conversion EquipmentMechanical Heating 40,286
Page F - 5
Appendix
FMS ID/ Budget Code
Agency Activity Year
POLICE DEPARTMENT
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
F
PO792011Terminal DevicesMechanical Heating 38,852
Total Planned activities for $451,495NYP0031 000
010NYP003109/29/05Date of Last Survey:3016 WEBSTER AVENUE
52 PRECINCT - OFFICE BUILDING
PO792011SwitchgearElectrical Under 600 Volts 43,222
Total Planned activities for $43,222NYP0031 010
000NYP003209/27/05Date of Last Survey:2 UNIONPORT ROAD
HWY PATROL #1/SS #2 -
PO792011Exterior WallsArchitecture Exterior 50,460
PO792011FloorsArchitecture Interior 51,391
PO792011Interior WallsArchitecture Interior 44,051
PO792011CeilingsArchitecture Interior 46,245
Total Planned activities for $192,147NYP0032 000
000NYP003303/09/05Date of Last Survey:2951 W 8TH STREET
60 PRECINCT - ENG. CO. 245/LAD. CO. 161
PO792011Exterior WallsArchitecture Exterior 282,753
PO792011WindowsArchitecture Exterior 258,587
PO792011ParapetsArchitecture Exterior 56,168
PO792011RoofArchitecture Exterior 190,080
PO792011CeilingsArchitecture Interior 153,759
Total Planned activities for $941,347NYP0033 000
000NYP003412/30/02Date of Last Survey:2575 CONEY ISLAND AVENUE
61 PRECINCT -
PO792011CeilingsArchitecture Interior 180,697
Total Planned activities for $180,697NYP0034 000
000NYP003509/29/05Date of Last Survey:1925 BATH AVENUE
62 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 84,207
PO792011FloorsArchitecture Interior 43,646
Total Planned activities for $127,853NYP0035 000
000NYP003604/12/05Date of Last Survey:1844 BROOKLYN AVENUE
63 PRECINCT -
PO792011General LightingElectrical Lighting 25,181
Total Planned activities for $25,181NYP0036 000
000NYP003709/29/05Date of Last Survey:5822 16TH AVENUE
66 PRECINCT -
PO792011WindowsArchitecture Exterior 106,494
Total Planned activities for $106,494NYP0037 000
Page F - 6
Appendix
FMS ID/ Budget Code
Agency Activity Year
POLICE DEPARTMENT
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
F
000NYP003809/26/05Date of Last Survey:2820 SNYDER AVENUE
67 PRECINCT - CO-LOCATE
PO792011ParapetsArchitecture Exterior 36,618
PO792011CeilingsArchitecture Interior 46,887
Total Planned activities for $83,505NYP0038 000
000NYP003909/20/05Date of Last Survey:333 65TH STREET
68 PRECINCT -
PO792008RoofArchitecture Exterior 57,599
Total Planned activities for $57,599NYP0039 000
000NYP004012/07/04Date of Last Survey:9720 FOSTER AVENUE
69 PRECINCT -
PO792007RoofArchitecture Exterior 106,134
Total Planned activities for $106,134NYP0040 000
000NYP004109/26/05Date of Last Survey:154 LAWRENCE AVENUE
70 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 119,162
PO792011FloorsArchitecture Interior 139,349
PO792011Interior WallsArchitecture Interior 39,017
PO792011CeilingsArchitecture Interior 156,184
Total Planned activities for $453,712NYP0041 000
000NYP004203/03/05Date of Last Survey:421 EMPIRE BLVD
71 PRECINCT -
PO792011General LightingElectrical Lighting 114,846
Total Planned activities for $114,846NYP0042 000
000NYP004310/22/03Date of Last Survey:830 4TH AVENUE
72 PRECINCT/SS #6 -
PO792011GeneratorsElectrical Stand-by Power 63,856
Total Planned activities for $63,856NYP0043 000
010NYP004409/19/05Date of Last Survey:1470 E NEW YORK AVENUE
73 PRECINCT - SERVICE SHOP #3
PO792011FloorsArchitecture Interior 45,632
PO792011CeilingsArchitecture Interior 82,580
Total Planned activities for $128,212NYP0044 010
000NYP004610/22/03Date of Last Survey:191 UNION STREET
76 PRECINCT -
PO792011WindowsArchitecture Exterior 195,660
PO792008GeneratorsElectrical Stand-by Power 63,856
PO792008General LightingElectrical Lighting 56,071
PO792007Heat RejectionMechanical Air Conditioning 37,121
Page F - 7
Appendix
FMS ID/ Budget Code
Agency Activity Year
POLICE DEPARTMENT
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
F
Total Planned activities for $352,708NYP0046 000
000NYP004709/19/05Date of Last Survey:127 UTICA AVENUE
77 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 168,310
PO792011WindowsArchitecture Exterior 478,735
PO792011CeilingsArchitecture Interior 36,704
Total Planned activities for $683,749NYP0047 000
000NYP004909/21/05Date of Last Survey:263 TOMPKINS AVENUE
79TH PRECINCT -
PO792011Exterior WallsArchitecture Exterior 51,089
PO792011FloorsArchitecture Interior 37,937
PO792011GeneratorsElectrical Stand-by Power 63,856
Total Planned activities for $152,882NYP0049 000
000NYP005009/21/05Date of Last Survey:30 RALPH AVENUE
81 PRECINCT/FD - CO-LOCATE
PO792011Exterior WallsArchitecture Exterior 163,814
PO792011ParapetsArchitecture Exterior 38,079
PO792011CeilingsArchitecture Interior 114,172
PO792011Heat RejectionMechanical Air Conditioning 68,142
Total Planned activities for $384,207NYP0050 000
000NYP005105/04/04Date of Last Survey:301 GOLD STREET
84 PRECINCT/ENG CO207/LAD CO110 - CO-LOCATE
PO792011Exterior WallsArchitecture Exterior 133,602
PO792011ParapetsArchitecture Exterior 54,648
PO792011GeneratorsElectrical Stand-by Power 63,856
PO792011General LightingElectrical Lighting 145,464
PO792011Heat RejectionMechanical Air Conditioning 43,247
Total Planned activities for $440,817NYP0051 000
000NYP005210/28/04Date of Last Survey:480 KNICKERBOCKER AVENUE
83 PRECINCT -
PO792007RoofArchitecture Exterior 105,836
Total Planned activities for $105,836NYP0052 000
000NYP005410/25/04Date of Last Survey:211 UNION AVENUE
90 PRECINCT/PBBN/FD - CO-LOCATE
PO792008Exterior WallsArchitecture Exterior 100,014
PO792008ParapetsArchitecture Exterior 55,926
PO792008FloorsArchitecture Interior 153,770
PO792008Terminal DevicesMechanical Heating 84,759
PO792008Heat RejectionMechanical Air Conditioning 75,480
Page F - 8
Appendix
FMS ID/ Budget Code
Agency Activity Year
POLICE DEPARTMENT
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
F
Total Planned activities for $469,949NYP0054 000
000NYP005501/09/03Date of Last Survey:100 MESEROLE AVENUE
94 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 85,108
Total Planned activities for $85,108NYP0055 000
000NYP005712/03/03Date of Last Survey:92-94 ROCKAWAY BEACH BLV
100 PRECINCT/SS #9A -
PO792011Exterior WallsArchitecture Exterior 299,724
PO792011ParapetsArchitecture Exterior 238,168
PO792011Interior WallsArchitecture Interior 94,052
PO792011GeneratorsElectrical Stand-by Power 63,856
PO792011General LightingElectrical Lighting 107,533
Total Planned activities for $803,333NYP0057 000
000NYP005810/12/04Date of Last Survey:16-12 MOTT AVENUE
101 PRECINCT -
PO792011Interior WallsArchitecture Interior 41,804
PO792011CeilingsArchitecture Interior 114,257
Total Planned activities for $156,061NYP0058 000
000NYP006110/20/04Date of Last Survey:64-02 CATALPA AVE,
104 PRECINCT -
PO792006Exterior WallsArchitecture Exterior 121,086
PO792006RoofArchitecture Exterior 59,213
Total Planned activities for $180,299NYP0061 000
000NYP006203/17/03Date of Last Survey:92-08 222ND STREET
105 PRECINCT/PBBS/FD - CO-LOCATE
PO792011Exterior WallsArchitecture Exterior 37,417
PO792007RoofArchitecture Exterior 139,888
PO792011CeilingsArchitecture Interior 38,721
PO792004Conversion EquipmentMechanical Air Conditioning 68,070
PO792011Heat RejectionMechanical Air Conditioning 72,478
Total Planned activities for $356,574NYP0062 000
000NYP006312/23/03Date of Last Survey:103-51 101ST STREET
106 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 47,439
PO792011GeneratorsElectrical Stand-by Power 63,856
Total Planned activities for $111,295NYP0063 000
000NYP006409/29/04Date of Last Survey:5-47 50TH AVENUE L.I.C.
108 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 251,907
Page F - 9
Appendix
FMS ID/ Budget Code
Agency Activity Year
POLICE DEPARTMENT
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
F
PO792007RoofArchitecture Exterior 91,777
Total Planned activities for $343,684NYP0064 000
000NYP006510/03/05Date of Last Survey:37-05 UNION STREET
109 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 54,599
Total Planned activities for $54,599NYP0065 000
000NYP006601/31/05Date of Last Survey:94-41 43RD AVENUE
110 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 76,812
PO792011Interior WallsArchitecture Interior 78,377
Total Planned activities for $155,189NYP0066 000
000NYP006809/28/05Date of Last Survey:68-40 AUSTIN STREET
112 PRECINCT -
PO792008WindowsArchitecture Exterior 51,599
PO792011ParapetsArchitecture Exterior 40,635
Total Planned activities for $92,234NYP0068 000
000NYP006905/03/05Date of Last Survey:167-02 BAISLEY BLVD
113 PRECINCT -
PO792008Exterior WallsArchitecture Exterior 140,771
PO792011CeilingsArchitecture Interior 47,314
Total Planned activities for $188,085NYP0069 000
000NYP007004/25/03Date of Last Survey:34-16 ASTORIA BLVD.
114 PRECINCT -
PO792011GeneratorsElectrical Stand-by Power 63,856
Total Planned activities for $63,856NYP0070 000
000NYP007110/03/05Date of Last Survey:92-15 NORTHERN BLVD
115 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 105,200
PO792007RoofArchitecture Exterior 130,701
Total Planned activities for $235,901NYP0071 000
000NYP007202/13/03Date of Last Survey:53-15 58TH STREET
CENTRAL MOTOR REPAIR -
PO792011WindowsArchitecture Exterior 758,505
PO792008ParapetsArchitecture Exterior 37,656
PO792008RoofArchitecture Exterior 123,291
PO792011CeilingsArchitecture Interior 66,165
PO792011General LightingElectrical Lighting 23,293
Total Planned activities for $1,008,910NYP0072 000
Page F - 10
Appendix
FMS ID/ Budget Code
Agency Activity Year
POLICE DEPARTMENT
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
F
000NYP007309/21/04Date of Last Survey:78 RICHMOND TERRACE
120 PRECINCT -
PO792009DistributionMechanical Ventilation 39,481
Total Planned activities for $39,481NYP0073 000
000NYP007411/19/03Date of Last Survey:2320 HYLAN BOULEVARD
122 PRECINCT -
PO792008WindowsArchitecture Exterior 304,063
PO792011GeneratorsElectrical Stand-by Power 63,856
PO792011Terminal DevicesMechanical Heating 45,237
Total Planned activities for $413,156NYP0074 000
010NYP007411/19/03Date of Last Survey:2320 HYLAN BLVD.
122 PRECINCT - SERVICE BLDG. & GARAGE
PO792008WindowsArchitecture Exterior 185,769
Total Planned activities for $185,769NYP0074 010
000NYP007509/26/05Date of Last Survey:116 MAIN STREET
123 PRECINCT -
PO792011Exterior WallsArchitecture Exterior 51,872
Total Planned activities for $51,872NYP0075 000
000NYP007609/28/05Date of Last Survey:59-06 LAUREL HILL BLVD.
COMBINED FACILITY - ADMIN BUILDING
PO792011Exterior WallsArchitecture Exterior 179,670
PO792011WindowsArchitecture Exterior 81,256
PO792011ParapetsArchitecture Exterior 82,153
PO792011RoofArchitecture Exterior 51,096
PO792011FloorsArchitecture Interior 158,328
PO792011Interior WallsArchitecture Interior 44,437
PO792011CeilingsArchitecture Interior 90,601
Total Planned activities for $687,541NYP0076 000
000NYP007702/11/03Date of Last Survey:47-07 PEARSON PLACE
PROPERTY CLERK WAREHOUSE -
PO792011FloorsArchitecture Interior 72,084
Total Planned activities for $72,084NYP0077 000
000NYP007807/13/05Date of Last Survey:1 POLICE PLAZA
HEADQUARTERS -
PO792011WindowsArchitecture Exterior 244,451
PO792011Interior WallsArchitecture Interior 62,426
PO792011Motor ControllersElectrical Under 600 Volts 177,697
PO792011BatteriesElectrical Stand-by Power 49,113
PO792011Egress LightingElectrical Lighting 84,776
Page F - 11
Appendix
FMS ID/ Budget Code
Agency Activity Year
POLICE DEPARTMENT
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
F
PO792011DistributionMechanical Heating 219,567
PO792011Terminal DevicesMechanical Heating 222,676
PO792011DistributionMechanical Air Conditioning 569,688
Total Planned activities for $1,630,394NYP0078 000
000NYP007910/24/02Date of Last Survey:34 1/2 E 12TH STREET
COMMUNITY AFFAIRS -
PO792011Exterior WallsArchitecture Exterior 457,207
PO792011WindowsArchitecture Exterior 335,393
PO792011ParapetsArchitecture Exterior 38,280
PO792011FloorsArchitecture Interior 294,251
PO792011Interior WallsArchitecture Interior 108,033
PO792011CeilingsArchitecture Interior 48,821
PO792011General LightingElectrical Lighting 58,650
Total Planned activities for $1,340,635NYP0079 000
000NYP008012/16/05Date of Last Survey:138 W 30TH STREET
TRAFFIC CONTROL DIVISION -
PO792011Exterior WallsArchitecture Exterior 38,072
PO792011FloorsArchitecture Interior 37,070
PO792006CeilingsArchitecture Interior 37,500
Total Planned activities for $112,642NYP0080 000
000NYP008101/31/06Date of Last Survey:235 EAST 20TH STREET
POLICE ACADEMY BUILDING - 13 PRECINCT/PBMS
PO792006Exterior WallsArchitecture Exterior 141,039
PO792006WindowsArchitecture Exterior 296,188
PO792011FloorsArchitecture Interior 305,315
PO792011Interior WallsArchitecture Interior 768,054
PO792011CeilingsArchitecture Interior 317,857
PO792011Heat RejectionMechanical Air Conditioning 139,328
PO792011DistributionMechanical Ventilation 60,623
PO792011Pool Filter/TreatmentMechanical Plumbing 1,768,900
Total Planned activities for $3,797,304NYP0081 000
000NYP008303/19/03Date of Last Survey:2 EAST 169TH ST.
NEW 44 PCT. STATIONHOUSE - SERVICE STATION #7
PO792011ParapetsArchitecture Exterior 66,364
Total Planned activities for $66,364NYP0083 000
000NYP008509/20/05Date of Last Survey:4201 FOURTH AVENUE
SUNSET PARK COURTHOUSE - RECRUITMENT SECTION
PO792011Exterior WallsArchitecture Exterior 51,496
PO792011WindowsArchitecture Exterior 550,349
Page F - 12
Appendix
FMS ID/ Budget Code
Agency Activity Year
POLICE DEPARTMENT
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
F
PO792011ParapetsArchitecture Exterior 51,838
PO792011Interior WallsArchitecture Interior 37,743
PO792011CeilingsArchitecture Interior 50,461
Total Planned activities for $741,887NYP0085 000
000NYP008609/21/05Date of Last Survey:179 WILSON AVENUE
SATCOMM BROOKLYN NORTH - OLD 83 PRECINCT
PO792011Exterior WallsArchitecture Exterior 36,695
PO792011CeilingsArchitecture Interior 38,685
Total Planned activities for $75,380NYP0086 000
000NYP008712/27/02Date of Last Survey:71-01 PARSONS BLVD.
107TH PRECINCT -
PO792011WindowsArchitecture Exterior 57,336
Total Planned activities for $57,336NYP0087 000
000NYP008810/04/05Date of Last Survey:RANDALLS ISLAND
SERVICE SHOP #9 GARAGE -
PO792011Exterior WallsArchitecture Exterior 456,630
PO792011CeilingsArchitecture Interior 98,743
Total Planned activities for $555,373NYP0088 000
000NYP009009/16/05Date of Last Survey:1035 LONGWOOD AVENUE
41 PRECINCT -
PO792011Conversion EquipmentMechanical Air Conditioning 68,840
Total Planned activities for $68,840NYP0090 000
000NYP009109/20/05Date of Last Survey:237 42ND STREET
NYPD QUARTERMASTER SECTION -
PO792011WindowsArchitecture Exterior 65,908
PO792011FloorsArchitecture Interior 69,143
PO792011CeilingsArchitecture Interior 80,209
Total Planned activities for $215,260NYP0091 000
000NYP009204/30/04Date of Last Survey:109 PARK ROW
1 POLICE PLAZA - CENTRAL - FIRE COMMUNICATIONS FACILITY
PO792011General LightingElectrical Lighting 107,059
Total Planned activities for $107,059NYP0092 000
000NYP009805/27/03Date of Last Survey:PIER 76 - HUDSON RIVER
VIOLATION TOW SERVICE - PIER 76 WAREHOUSE
PO792011Exterior WallsArchitecture Exterior 172,217
PO792011WindowsArchitecture Exterior 598,476
PO792011ParapetsArchitecture Exterior 202,331
PO792007RoofArchitecture Exterior 547,172
PO792011RoofArchitecture Exterior 342,734
Page F - 13
Appendix
FMS ID/ Budget Code
Agency Activity Year
POLICE DEPARTMENT
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
F
PO792011FloorsArchitecture Interior 63,496
PO792011Terminal DevicesMechanical Heating 612,739
Total Planned activities for $2,539,165NYP0098 000
000NYP009902/22/05Date of Last Survey:150-14 JAMAICA AVENUE
FORENSIC INVESTIGATIONS DIVISION - LABORATORY
PO792011CeilingsArchitecture Interior 165,453
PO792008General LightingElectrical Lighting 94,655
PO792011DistributionMechanical Ventilation 88,382
Total Planned activities for $348,490NYP0099 000
000NYP010005/17/04Date of Last Survey:140 58TH STREET
HARBOR CHARLIE -
PO792007DeckMarina Floating Docks 109,632
PO792011Wave AttenuatorMarina Protective Structure 55,716
Total Planned activities for $165,348NYP0100 000
000NYP010106/10/04Date of Last Survey:FOOT OF 14TH AVE @ FLUSHING BAY
HARBOR GEORGE -
PO792011Floats/FramesMarina Floating Docks 199,593
Total Planned activities for $199,593NYP0101 000
010NYP010105/02/05Date of Last Survey:FOOT OF 14TH AVE @FLUSHING BAY
BULKHEAD AT HARBOR GEORGE -
PO792009Relieving Platform TopBulkheads Structural 161,026
PO792011Piles and BracingBulkheads Structural 81,852
PO792011Sheet PilesBulkheads Structural 197,270
Total Planned activities for $440,148NYP0101 010
000NYP010211/15/04Date of Last Survey:RANDALLS ISLAND
NYPD BOAT LAUNCH & REPAIR SHOP -
PO792011Piles and BracingMarina Access Walkways 455,953
PO792011Fender Piles, Wales and ChMarina Access Walkways 38,774
PO792011Floats/FramesMarina Floating Docks 66,600
PO792011Piles and BracingMarina Launch/Haulout 44,472
PO792011Wave AttenuatorMarina Protective Structure 61,609
Total Planned activities for $667,408NYP0102 000
010NYP010205/02/05Date of Last Survey:RANDALLS ISLAND
WHARF AT NYPD BOAT LAUNCH -
PO792011Piles and BracingPiers Structural 173,672
Total Planned activities for $173,672NYP0102 010
010NYP010305/05/05Date of Last Survey:CROSS BAY BLVD & FOOT OF 159 AVE
WHARF AT HARBOR ADAM -
PO792009DeckPiers Structural 39,966
Page F - 14
Appendix
FMS ID/ Budget Code
Agency Activity Year
POLICE DEPARTMENT
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
F
Total Planned activities for $39,966NYP0103 010
Total Planned Activities for : $34,225,882POLICE DEPARTMENT
Total Required for "State of Good Repair" for : POLICE DEPARTMENT $37,140,497
Page F - 15
Appendix
FMS ID/ Budget Code
Agency Activity Year
FIRE DEPARTMENT
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
G
000DGSP00501/03/06Date of Last Survey:PIERS 35 & 36, EAST RIVER
EMS BUILDING - BATTALION 4
PT195-VAR2007WindowsArchitecture Exterior 404,685
Total Planned activities for $404,685DGSP005 000
000FIR000110/29/04Date of Last Survey:48-34 35TH STREET
MAINTENANCE GARAGE LIC -
F1755CO992007Exterior WallsArchitecture Exterior 45,314
F1755CO992007ParapetsArchitecture Exterior 12,173
F1755CO992007RoofArchitecture Exterior 57,931
F17535ST2006SwitchgearElectrical Under 600 Volts 144,331
Total Planned activities for $259,749FIR0001 000
010FIR000402/26/04Date of Last Survey:79TH STREET & TRAVERSE ROAD
COMMUNICATIONS CENTER-MANHATTAN -
F1755CO992007Exterior WallsArchitecture Exterior 721,523
F1755CO992007WindowsArchitecture Exterior 284,810
F1755CO992007ParapetsArchitecture Exterior 532,693
F1755CO992007RoofArchitecture Exterior 46,696
F1755CO992007Terminal DevicesMechanical Air Conditioning 46,666
F1755CO992007Heat RejectionMechanical Air Conditioning 52,504
Total Planned activities for $1,684,892FIR0004 010
010FIR000501/07/02Date of Last Survey:35 EMPIRE BLVD
COMMUNICATIONS CENTER - BROOKLYN -
F1755CO992007Exterior WallsArchitecture Exterior 86,533
F1755CO992007WindowsArchitecture Exterior 144,281
F1755CO992007ParapetsArchitecture Exterior 58,739
F1755CO992007RoofArchitecture Exterior 42,760
F1755CO992007Interior WallsArchitecture Interior 172,823
Total Planned activities for $505,136FIR0005 010
010FIR000601/08/02Date of Last Survey:83-98 WOODHAVEN BOULEVARD
COMMUNICATIONS CENTER-QUEENS -
F1755CO992006WindowsArchitecture Exterior 36,665
F1755CO992006ParapetsArchitecture Exterior 79,961
F1755CO992006RoofArchitecture Exterior 42,014
Total Planned activities for $158,640FIR0006 010
010FIR000701/09/02Date of Last Survey:1129 EAST 180TH STREET
COMMUNICATIONS CENTER-BRONX -
F1755CO992006Interior WallsArchitecture Interior 92,033
Total Planned activities for $92,033FIR0007 010
Page G - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
FIRE DEPARTMENT
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
G
000FIR001612/16/02Date of Last Survey:58-65 52ND ROAD
BATALLION 45 - OLD EMS STATION 46
F175RADIO2006WindowsArchitecture Exterior 247,545
F175RADIO2006RoofArchitecture Exterior 49,935
Total Planned activities for $297,480FIR0016 000
000FIR002101/01/06Date of Last Survey:BROOKLYN NAVY YARD
FIREBOAT-GOVERNOR ALFRED E SMITH -
F192SMIT72007Vessels 250,000
Total Planned activities for $250,000FIR0021 000
010FIR002101/01/06Date of Last Survey:BROOKLYN NAVY YARD
FIREBOAT - KEVIN C. KANE -
F192-KANE2008Vessels 240,000
Total Planned activities for $240,000FIR0021 010
020FIR002101/01/06Date of Last Survey:BROOKLYN NAVY YARD
FIREBOAT - JOHN D. MCKEAN -
F192KEAN62007Vessels 1,000,000
Total Planned activities for $1,000,000FIR0021 020
030FIR002101/01/06Date of Last Survey:BROOKLYN NAVY YARD
FIREBOAT - FIRE FIGHTER -
F192FFF062007Vessels 500,000
Total Planned activities for $500,000FIR0021 030
Total Planned Activities for : $5,392,615FIRE DEPARTMENT
Total Required for "State of Good Repair" for : FIRE DEPARTMENT $11,932,022
Page G - 2
Appendix
FMS ID/ Budget Code
Agency Activity Year
ADMIN. FOR CHILDREN'S SERVICES
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
H
000ACS000106/29/05Date of Last Survey:115 CHRYSTIE STREET
ADMINISTRATION BUILDING -
CAPITAL2008WindowsArchitecture Exterior 31,760
CAPITAL2009FloorsArchitecture Interior 30,411
CAPITAL2008CeilingsArchitecture Interior 19,352
2011General LightingElectrical Lighting 143,470
Total Planned activities for $224,993ACS0001 000
000ACS000406/30/05Date of Last Survey:159 BROADWAY
RICHMOND EARLY LEARNING CENTER -
068 - RICHEARLY2007Interior WallsArchitecture Interior 56,960
Total Planned activities for $56,960ACS0004 000
090HHC000106/08/06Date of Last Survey:492 FIRST AVENUE
NEW ACS CHILDREN'S CENTER - BELLEVUE HOSPITAL BLDG R-S
CAPITAL2008Exterior WallsArchitecture Exterior 52,190
Total Planned activities for $52,190HHC0001 090
Total Planned Activities for : $334,143ADMIN. FOR CHILDREN'S SERVICES
Total Required for "State of Good Repair" for : ADMIN. FOR CHILDREN'S SERVICES $1,455,326
Page H - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF HOMELESS SERVICES
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
I
000DHS000907/20/06Date of Last Survey:39 AUBURN PLACE
AUBURN FAMILY SHELTER - DORMITORY
HR115AUBX2007Exterior WallsArchitecture Exterior 660,910
HR115AUBX2005WindowsArchitecture Exterior 129,570
EXPENSE2008Interior WallsArchitecture Interior 106,222
EXPENSE2008CeilingsArchitecture Interior 90,640
EXPENSE2008WiringElectrical Under 600 Volts 78,147
Total Planned activities for $1,065,489DHS0009 000
000DHS001105/10/04Date of Last Survey:501 NEW LOTS AVENUE
LINDEN FAMILY RESIDENCE - FORMER LINDEN GENERAL HOSPITAL
HH115LINX2005Exterior WallsArchitecture Exterior 61,295
HH115LEBU2005WindowsArchitecture Exterior 87,525
Total Planned activities for $148,820DHS0011 000
000DHS001205/13/05Date of Last Survey:2155 DEAN STREET
DEAN STREET FAMILY CENTER -
HH115DEAN2006Exterior WallsArchitecture Exterior 173,145
HH115DEAN2006RoofArchitecture Exterior 119,483
Total Planned activities for $292,628DHS0012 000
000DHS001305/10/04Date of Last Survey:116 WILLIAMS AVENUE
BROOKLYN WOMEN'S SHELTER - (FORMER P.S. 63 - BK)
HH112BWFD2006WindowsArchitecture Exterior 365,127
HH115SHEL2004CeilingsArchitecture Interior 103,070
HH112SHEL2004General LightingElectrical Lighting 55,454
HH112SHEL2004Terminal DevicesMechanical Heating 293,220
HH112SHEL2004Exhaust FansMechanical Ventilation 72,166
Total Planned activities for $889,037DHS0013 000
010DHS001405/16/05Date of Last Survey:300 SKILLMAN AVENUE
BARBARA KLEIMAN RESIDENCE - BLDG. 1 - MAIN BLDG.
HH112BKXU2006Exterior WallsArchitecture Exterior 325,295
HH112BKBU2008CeilingsArchitecture Interior 101,522
HH112BKBU2008WiringElectrical Under 600 Volts 78,541
HH112BKBU2008Conversion EquipmentMechanical Air Conditioning 298,261
Total Planned activities for $803,619DHS0014 010
040DHS001405/16/05Date of Last Survey:300 SKILLMAN AVENUE
BARBARA KLEIMAN RESIDENCE - BLDGS. D & G - LAUNDRY
HH112BKXU2006WindowsArchitecture Exterior 39,726
Total Planned activities for $39,726DHS0014 040
000DHS002107/24/06Date of Last Survey:357 SUMNER AVE.
SUMNER ARMORY SHELTER - PAMOJA SUMMIT ARMORY
Page I - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF HOMELESS SERVICES
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
I
HH112SBRS2001Exterior WallsArchitecture Exterior 162,842
HH112SBRS2001ParapetsArchitecture Exterior 426,508
HH-MRBU2007RoofArchitecture Exterior 43,702
Total Planned activities for $633,052DHS0021 000
000DHS002205/13/03Date of Last Survey:85 LEXINGTON AVE.
LEXINGTON AVE. WOMEN'S SHELTER -
HH112LEXU2006WindowsArchitecture Exterior 68,874
HH112BLER2006Heat RejectionMechanical Air Conditioning 60,922
Total Planned activities for $129,796DHS0022 000
000DHS002704/29/03Date of Last Survey:78 CATHERINE STREET
METROPOLITAN FAMILY SHELTER - A.K.A. CATHERINE ST SHELTER
HR115CSCO2003Exterior WallsArchitecture Exterior 107,386
HR115CSC2/32003Exterior WallsArchitecture Exterior 171,413
HR115CSC2/32005Exterior WallsArchitecture Exterior 38,441
EXPENSE2004WindowsArchitecture Exterior 122,038
HR115CSFL2003FloorsArchitecture Interior 79,601
Total Planned activities for $518,879DHS0027 000
000DHS003007/18/06Date of Last Survey:8 EAST 3RD STREET
MEN'S SHELTER-EAST 3RD STREET -
EXPENSE2008Interior WallsArchitecture Interior 104,766
EXPENSE2008CeilingsArchitecture Interior 73,483
Total Planned activities for $178,249DHS0030 000
000DHS003305/19/05Date of Last Survey:2960 FREDRICK DOUGLAS BLVD.
HARLEM ONE - MENS RESIDENCE
HH112HMEU2006Exterior WallsArchitecture Exterior 153,610
HH112HMEU2006RoofArchitecture Exterior 168,418
HH-RECON2008SwitchgearElectrical Under 600 Volts 69,935
HH-RECON2008PanelboardsElectrical Under 600 Volts 44,516
HH-RECON2008Terminal DevicesMechanical Heating 48,056
Total Planned activities for $484,535DHS0033 000
000DHS003407/17/06Date of Last Survey:WARD'S ISLAND
CHARLES GAY SHELTER-SCHWARTZ -
HH-RECON2007FloorsArchitecture Interior 53,236
HH-RECON2007CeilingsArchitecture Interior 86,575
HH-RECON2007DistributionMechanical Ventilation 76,592
Total Planned activities for $216,403DHS0034 000
000DHS003507/17/06Date of Last Survey:WARD'S ISLAND
CHARLES GAY SHELTER-KEENER -
HH112CGKM2005Exterior WallsArchitecture Exterior 829,668
Page I - 2
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF HOMELESS SERVICES
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
I
HH112CGKF2005FloorsArchitecture Interior 232,027
EXPENSE2008Interior WallsArchitecture Interior 65,574
EXPENSE2008CeilingsArchitecture Interior 109,659
HH112CGKF2005DistributionMechanical Heating 82,277
EXPENSE2008Terminal DevicesMechanical Heating 35,325
Total Planned activities for $1,354,530DHS0035 000
000DHS004107/19/06Date of Last Survey:1122 FRANKLIN AVENUE
FRANKLIN ARMORY - SHELTER
ARMORIES2006Exterior WallsArchitecture Exterior 217,583
ARMORIES2006ParapetsArchitecture Exterior 168,705
EXPENSE2009FloorsArchitecture Interior 138,979
EXPENSE2008Interior WallsArchitecture Interior 82,246
EXPENSE2008CeilingsArchitecture Interior 45,054
Total Planned activities for $652,567DHS0041 000
000DHS004205/14/04Date of Last Survey:21-10 BORDEN AVENUE
BORDEN AVENUE MEN'S SHELTER -
HH-MRBU2008WindowsArchitecture Exterior 46,313
EXPENSE2008Conversion EquipmentMechanical Heating 52,082
CAPITAL2008Conversion EquipmentMechanical Air Conditioning 213,717
Total Planned activities for $312,112DHS0042 000
000DHS005207/19/06Date of Last Survey:346 POWERS AVENUE
PATH - POWERS FAMILY RESIDENCE -
CAPITAL2007Exterior WallsArchitecture Exterior 67,661
Total Planned activities for $67,661DHS0052 000
000DHS005305/10/04Date of Last Survey:10875 AVENUE D
FLATLANDS FAMILY RESIDENCE -
HH115FLRF2008RoofArchitecture Exterior 163,053
HH115FLAU2006FloorsArchitecture Interior 101,238
HH115FLAU2006General LightingElectrical Lighting 40,480
HH115FLAU2006Exhaust FansMechanical Ventilation 38,612
Total Planned activities for $343,383DHS0053 000
000DHS005405/18/05Date of Last Survey:50 WEST MOUNT EDEN AVE.
MOUNT EDEN SRO -
HH112MEBU2007RoofArchitecture Exterior 38,320
HH112MEBU2007Conversion EquipmentMechanical Air Conditioning 212,298
HH112MEBU2007Exhaust FansMechanical Ventilation 40,636
Total Planned activities for $291,254DHS0054 000
000DHS005605/11/05Date of Last Survey:146-80 GUY R. BREWER BLVD.
SPRINGFIELD FAMILY INN -
Page I - 3
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF HOMELESS SERVICES
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
I
HH115SPBU2005ParapetsArchitecture Exterior 39,976
HH115SPBU2005RoofArchitecture Exterior 92,901
EXPENSE2008General LightingElectrical Lighting 38,232
Total Planned activities for $171,109DHS0056 000
000DHS005705/17/05Date of Last Survey:691 EAST 138TH STREET
JACKSON FAMILY SHELTER -
HH-MRBU2008RoofArchitecture Exterior 43,513
Total Planned activities for $43,513DHS0057 000
000DHS005805/12/05Date of Last Survey:1381 EAST NEW YORK AVE.
MIRACLE MAKERS - SRO -
HH112MMRR2007RoofArchitecture Exterior 267,770
EXPENSE2008General LightingElectrical Lighting 143,891
Total Planned activities for $411,661DHS0058 000
000DHS005905/17/05Date of Last Survey:22 EAST 119TH STREET
VETERANS SRO - EAST HARLEM -
HH112VETS2006RoofArchitecture Exterior 41,695
Total Planned activities for $41,695DHS0059 000
000DHS006005/19/05Date of Last Survey:1215-1225 SENECA AVENUE
SENECA AVENUE HOUSES - EDDIE FERNANDEZ HOUSES
EXPENSE2008FloorsArchitecture Interior 52,745
Total Planned activities for $52,745DHS0060 000
000DHS006105/19/05Date of Last Survey:179-191 E 100TH STREET
JENNIE A. CLARKE RESIDENCE -
HH115JEBR2005Exterior WallsArchitecture Exterior 242,363
HH115JEBR2005WindowsArchitecture Exterior 96,581
EXPENSE2008FloorsArchitecture Interior 58,358
Total Planned activities for $397,302DHS0061 000
000DHS006205/18/05Date of Last Survey:1605 NELSON AVENUE
NELSON AVE FAMILY RESIDENCE -
HH115NELX2007RoofArchitecture Exterior 37,732
EXPENSE2008FloorsArchitecture Interior 59,578
Total Planned activities for $97,310DHS0062 000
000DHS006305/11/05Date of Last Survey:80-20 134TH STREET
BRIARWOOD FAMILY RESIDENCE -
HH-MRBU2008Exterior WallsArchitecture Exterior 99,467
EXPENSE2008General LightingElectrical Lighting 46,715
Total Planned activities for $146,182DHS0063 000
000DHS006407/17/06Date of Last Survey:WARDS ISLAND
CHARLES GAY SHELTER - CLARK THOMAS BUILDING
Page I - 4
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF HOMELESS SERVICES
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
I
HH-MRBU2008FloorsArchitecture Interior 118,811
HH-MRBU2008CeilingsArchitecture Interior 63,366
Total Planned activities for $182,177DHS0064 000
000DHS006605/18/05Date of Last Survey:338 FORBELL STREET
FORBELL ST SHELTER - 338 FORBELL STREET
EXPENSE2008Interior WallsArchitecture Interior 78,128
EXPENSE2008Conversion EquipmentMechanical Air Conditioning 66,878
Total Planned activities for $145,006DHS0066 000
000DHS006705/07/03Date of Last Survey:216 FORT WASHINGTON AVENUE
FORT WASHINGTON ARMORY - SHELTER
HH112FTXU2007Exterior WallsArchitecture Exterior 539,833
HH112FTXU2007WindowsArchitecture Exterior 632,876
HH112FTXU2007ParapetsArchitecture Exterior 455,359
HH112FTXU2007RoofArchitecture Exterior 402,959
CAPITAL2008FloorsArchitecture Interior 178,262
EXPENSE2008Conversion EquipmentMechanical Heating 97,137
EXPENSE2008Hot Water HeaterMechanical Plumbing 44,490
Total Planned activities for $2,350,916DHS0067 000
000DHS006804/28/03Date of Last Survey:333 BOWERY
KENTON HALL SHELTER - FORMER KENTON HOTEL
HH112KENT2005Exterior WallsArchitecture Exterior 123,027
Total Planned activities for $123,027DHS0068 000
000DHS006904/28/03Date of Last Survey:282 EAST 3RD STREET
EAST 3RD STREET SHELTER -
HH112EAST2003CeilingsArchitecture Interior 203,250
CAPITAL2008Heat RejectionMechanical Air Conditioning 65,144
Total Planned activities for $268,394DHS0069 000
000DHS007005/14/03Date of Last Survey:215 EAST 45TH STREET
NEW PROVIDENCE -
HH115PROVXU2007ParapetsArchitecture Exterior 119,636
Total Planned activities for $119,636DHS0070 000
000DHS007505/12/03Date of Last Survey:781 EAST 135TH STREET
WILLOW SHELTER -
HH112WLOW2005Exterior WallsArchitecture Exterior 424,708
HH112WLOW2005FloorsArchitecture Interior 380,731
HH112WLOW2005CeilingsArchitecture Interior 1,339,803
Total Planned activities for $2,145,242DHS0075 000
000DHS007805/07/03Date of Last Survey:1150 COMMONWEALTH AVENUE
COMMONWEALTH -
Page I - 5
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF HOMELESS SERVICES
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
I
HH112CWBU2005RoofArchitecture Exterior 200,317
CAPITAL2008CeilingsArchitecture Interior 205,431
EXPENSE2008General LightingElectrical Lighting 52,763
Total Planned activities for $458,511DHS0078 000
000DHS007905/12/03Date of Last Survey:1075 WEBSTER AVENUE
WEBSTER - HOUSING
HH112WEBU2005General LightingElectrical Lighting 40,994
Total Planned activities for $40,994DHS0079 000
000DHS008007/24/06Date of Last Survey:1322 BEDFORD AVENUE
(BEDFORD) ATLANTIC ARMORY -
ARMORIES2006Exterior WallsArchitecture Exterior 248,530
ARMORIES2006ParapetsArchitecture Exterior 249,531
ARMORIES2006RoofArchitecture Exterior 239,055
Total Planned activities for $737,116DHS0080 000
000DHS008107/20/06Date of Last Survey:1402 8TH AVENUE
PARK SLOPE ARMORY - WOMENS' SHELTER
ARMORIES2003Exterior WallsArchitecture Exterior 238,629
ARMORIES2003ParapetsArchitecture Exterior 400,292
HR112PS2003FloorsArchitecture Interior 333,125
HR112PS2003Interior WallsArchitecture Interior 113,630
HR112PS2003DistributionMechanical Heating 52,595
HR112PS2003DistributionMechanical Ventilation 41,157
HR112PS2003Sanitary PipingMechanical Plumbing 35,273
Total Planned activities for $1,214,701DHS0081 000
000DHS008305/08/03Date of Last Survey:829 SARATOGA AVENUE
FANNY BARNES -
HH115FANN2005Exterior WallsArchitecture Exterior 81,108
Total Planned activities for $81,108DHS0083 000
000DHS008705/01/03Date of Last Survey:175-10 88TH AVENUE
JAMAICA ASSESSMENT CENTER -
HH115JASS2005Exterior WallsArchitecture Exterior 195,231
HH115JASS2005WindowsArchitecture Exterior 79,764
Total Planned activities for $274,995DHS0087 000
010DHS008705/01/03Date of Last Survey:175-10 88TH AVENUE
JAMAICA ASSESSMENT CENTER - ANNEX
HH115JASS2005Exterior WallsArchitecture Exterior 48,668
Total Planned activities for $48,668DHS0087 010
Page I - 6
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF HOMELESS SERVICES
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
I
Total Planned Activities for : $17,973,748DEPARTMENT OF HOMELESS SERVICES
Total Required for "State of Good Repair" for : DEPARTMENT OF HOMELESS SERVICES $34,388,207
Page I - 7
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF CORRECTION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
J
010DOC000106/17/03Date of Last Survey:18-18 HAZEN ST., RIKERS ISLAND
RIKERS ISLAND FACILITIES - ANNA M. KROSS CENTER (AMKC)
072 C95-WIND2009WindowsArchitecture Exterior 4,763,172
072 C95ROOFS12006RoofArchitecture Exterior 698,960
072 C95-SECUR2006CeilingsArchitecture Interior 96,865
072 C75EGEN2007GeneratorsElectrical Stand-by Power 48,941
072 C75HOTWTR2009DistributionMechanical Heating 576,959
072 C75HOTWTR2009H/C Water PipingMechanical Plumbing 45,741
Total Planned activities for $6,230,638DOC0001 010
020DOC000106/17/03Date of Last Survey:11-11 HAZEN ST., RIKERS ISLAND
RIKERS ISLAND FACILITIES - ADOLESCENT RECEPTION DETEN. CTR.
072 C74-WIND2008WindowsArchitecture Exterior 403,853
072 C74RNDCRF2007RoofArchitecture Exterior 158,940
Total Planned activities for $562,793DOC0001 020
030DOC000106/17/03Date of Last Survey:15-15 HAZEN ST., RIKERS ISLAND
RIKERS ISLAND FACILITIES - GEORGE MOTCHAN DETENTION CENTER
072 C75WINDOW2011WindowsArchitecture Exterior 335,346
072 C75GMDCRF2007RoofArchitecture Exterior 4,014,930
072 C75HOTWTR2009DistributionMechanical Heating 258,990
Total Planned activities for $4,609,266DOC0001 030
040DOC000106/16/03Date of Last Survey:10-10 HAZEN ST., RIKERS ISLAND
RIKERS ISLAND FACILITIES - ERIC M. TAYLOR CENTER (EMTC)
072 C75WINDOW2011WindowsArchitecture Exterior 18,871,014
072 C75EGEN2007GeneratorsElectrical Stand-by Power 122,352
Total Planned activities for $18,993,366DOC0001 040
050DOC000106/17/03Date of Last Survey:14-14 HAZEN ST., RIKERS ISLAND
RIKERS ISLAND FACILITIES - JAMES A. THOMAS CENTER (JATC)
072 C75WINDOW2011WindowsArchitecture Exterior 6,449,517
072 C75JATCRC2008FloorsArchitecture Interior 794,740
072 C75JATCRC2008Interior WallsArchitecture Interior 534,517
072 C75JATCRC2008CeilingsArchitecture Interior 230,040
072 C75JATCRC2008PanelboardsElectrical Under 600 Volts 203,337
072 C75JATCRC2008WiringElectrical Under 600 Volts 228,538
072 C75JATCRC2008Motor ControllersElectrical Under 600 Volts 383,038
072 C75JATCRC2008General LightingElectrical Lighting 2,110,121
072 C75JATCRC2008Energy SourceMechanical Heating 48,950
072 C75JATCRC2008DistributionMechanical Heating 414,634
072 C75JATCRC2008Terminal DevicesMechanical Heating 1,067,299
072 C75JATCRC2008H/C Water PipingMechanical Plumbing 295,619
Page J - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF CORRECTION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
J
Total Planned activities for $12,760,350DOC0001 050
060DOC000106/18/03Date of Last Survey:16-16 HAZEN ST., RIKERS ISLAND
RIKERS ISLAND FACILITIES - OTIS BANTUM CORREC.CENTER (OBCC)
072 C75WINDOW2011WindowsArchitecture Exterior 135,790
072 C75CEIL2008CeilingsArchitecture Interior 100,188
072 C75EGEN2007GeneratorsElectrical Stand-by Power 122,352
Total Planned activities for $358,330DOC0001 060
063DOC000106/18/03Date of Last Survey:16-16 HAZEN ST., RIKERS ISLAND
RIKERS ISLAND FACILITIES - NORTH FACILITY,OBCC 300 CELL ANX
072 C75HVGRVC2007DistributionMechanical Ventilation 53,168
Total Planned activities for $53,168DOC0001 063
065DOC000106/18/03Date of Last Survey:16-16 HAZEN ST., RIKERS ISLAND
RIKERS ISLAND FACILITIES - NORTH FACILITY,OBCC 500 CELL ANX
072 C75HVGRVC2007RoofArchitecture Exterior 36,118
Total Planned activities for $36,118DOC0001 065
070DOC000106/16/03Date of Last Survey:19-19 HAZEN ST., RIKERS ISLAND
RIKERS ISLAND FACILITIES - ROSE M. SINGER CENTER RMSC
072 C75RMSCRF2007RoofArchitecture Exterior 1,062,039
072 C75HOTWTR2009DistributionMechanical Heating 150,014
Total Planned activities for $1,212,053DOC0001 070
080DOC000106/19/03Date of Last Survey:15-00 HAZEN ST., RIKERS ISLAND
RIKERS ISLAND FACILITIES - NORTH INFIRMARY CENTER (NIC)
072 C75-FCAD2007Exterior WallsArchitecture Exterior 421,409
072 C75WINDOW2011WindowsArchitecture Exterior 531,793
072 C75EGEN2007GeneratorsElectrical Stand-by Power 122,352
Total Planned activities for $1,075,554DOC0001 080
090DOC000106/18/03Date of Last Survey:16-16 HAZEN ST., RIKERS ISLAND
RIKERS ISLAND FACILITIES - POWERHOUSE
850 C130-PIPE2006Exterior WallsArchitecture Exterior 333,574
072 C75WINDOW2011WindowsArchitecture Exterior 212,500
072 C130POWER2007Conversion EquipmentMechanical Heating 513,351
850 C130PPUMP2006DistributionMechanical Heating 469,501
Total Planned activities for $1,528,926DOC0001 090
100DOC000106/19/03Date of Last Survey:16-16 HAZEN ST., RIKERS ISLAND
RIKERS ISLAND FACILITIES - TRANSPORTATION GARAGE
072 C112GARAG2007Exterior WallsArchitecture Exterior 202,863
072 C112GARAG2007WindowsArchitecture Exterior 51,731
072 C112GARAG2007RoofArchitecture Exterior 120,250
072 C75EGEN2007GeneratorsElectrical Stand-by Power 122,352
Page J - 2
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF CORRECTION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
J
072 C112GARAG2007General LightingElectrical Lighting 122,485
Total Planned activities for $619,681DOC0001 100
110DOC000106/19/03Date of Last Survey:16-16 HAZEN ST., RIKERS ISLAND
RIKERS ISLAND FACILITIES - CENTRAL STORE HOUSE
072 C75WINDOW2011WindowsArchitecture Exterior 1,312,977
Total Planned activities for $1,312,977DOC0001 110
150DOC000106/16/03Date of Last Survey:16-06 HAZEN ST., RIKERS ISLAND
RIKERS ISLAND FACILITIES - WEST FACILITY
072 C75WESTRF2007RoofArchitecture Exterior 227,140
072 C75HVACWF2008DistributionMechanical Ventilation 54,415
072 C75HOTWTR2009Hot Water HeaterMechanical Plumbing 97,824
Total Planned activities for $379,379DOC0001 150
160DOC000106/18/03Date of Last Survey:RIKERS ISLAND
RIKERS ISLAND FACILITIES - VISITORS PROCESSING CENTER
850 C114VHCIF2006Exterior WallsArchitecture Exterior 36,887
850 C114VHCIF2006FloorsArchitecture Interior 47,111
Total Planned activities for $83,998DOC0001 160
180DOC000106/18/03Date of Last Survey:09-09 HAZEN ST., RIKERS ISLAND
RIKERS ISLAND FACILITIES - GEORGE R. VIERNO CENTER GRVC
072 C75GRVCRF2007RoofArchitecture Exterior 994,014
072 C75HOTWTR2009DistributionMechanical Heating 107,378
Total Planned activities for $1,101,392DOC0001 180
182DOC000106/18/03Date of Last Survey:09-09 HAZEN ST., RIKERS ISLAND
RIKERS ISLAND FACILITIES - 200 BED FACILITY (GRVC)
072 C75HVGRVC2007Exhaust FansMechanical Ventilation 142,100
Total Planned activities for $142,100DOC0001 182
SANITDOC000101/01/06Date of Last Survey:RIKERS ISLAND
RIKERS ISLAND - SANITARY SYSTEM
072 C75-PLUMB2009Rikers Island Utilities
250,000
Total Planned activities for $250,000DOC0001 SANIT
000DOC000307/14/06Date of Last Survey:275 ATLANTIC AVENUE
BROOKLYN HOUSE OF DETENTION -
072C75EXTR2009Exterior WallsArchitecture Exterior 107,258
072 C75EXTR2008WindowsArchitecture Exterior 2,867,807
75 C114NEWF22008RoofArchitecture Exterior 39,418
76 C114NEWF22008FloorsArchitecture Interior 147,655
77 C114NEWF22008Interior WallsArchitecture Interior 71,756
78 C114NEWF22008CeilingsArchitecture Interior 67,330
Page J - 3
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF CORRECTION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
J
79 C114NEWF22008DistributionMechanical Ventilation 27,949
Total Planned activities for $3,329,173DOC0003 000
000DOC000507/06/05Date of Last Survey:125 WHITE STREET
MANHATTAN HOUSE OF DETENTION - SOUTH TOWER
072 C75EXTR2009Exterior WallsArchitecture Exterior 587,357
072 C75WINDOW2011WindowsArchitecture Exterior 213,134
Total Planned activities for $800,491DOC0005 000
000DOC000607/13/06Date of Last Survey:126-02 82ND AVENUE
QUEENS HOUSE OF DETENTION -
072 C75EXTR2009Exterior WallsArchitecture Exterior 333,676
072 C75WINDOW2011WindowsArchitecture Exterior 1,948,308
Total Planned activities for $2,281,984DOC0006 000
000DOC000907/06/05Date of Last Survey:138-40 CENTRE STREET
MANHATTAN HOUSE OF DETENTION - NORTH TOWER
072 C75-FCAD2007Exterior WallsArchitecture Exterior 70,732
C75WINDOW2011WindowsArchitecture Exterior 117,104
Total Planned activities for $187,836DOC0009 000
Total Planned Activities for : $57,909,573DEPARTMENT OF CORRECTION
Total Required for "State of Good Repair" for : DEPARTMENT OF CORRECTION $125,147,348
Page J - 4
Appendix
FMS ID/ Budget Code
Agency Activity Year
HUMAN RESOURCES ADMINISTRATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
K
000HRA002404/17/03Date of Last Survey:1001 HERKIMER STREET
BEDFORD STUY. MULTI SERVICE CTR. -
EXPENSE2008Exterior WallsArchitecture Exterior 105,941
EXPENSE2005WindowsArchitecture Exterior 169,558
EXPENSE2005RoofArchitecture Exterior 150,031
EXPENSE2007FloorsArchitecture Interior 127,871
EXPENSE2008Interior WallsArchitecture Interior 118,736
EXPENSE2009WiringElectrical Under 600 Volts 45,052
EXPENSE2008Exhaust FansMechanical Ventilation 63,440
Total Planned activities for $780,628HRA0024 000
000HRA002504/17/03Date of Last Survey:1420 BUSHWICK AVENUE
BUSHWICK MULTI SERVICE CENTER -
CDBG FUND2010Exterior WallsArchitecture Exterior 229,815
CDBG FUND2010FloorsArchitecture Interior 37,662
Total Planned activities for $267,477HRA0025 000
000HRA003604/16/03Date of Last Survey:1951 PARK AVENUE
RIVERVIEW JOB CENTER -
EXPENSE2008WindowsArchitecture Exterior 83,325
EXPENSE2003Interior WallsArchitecture Interior 134,910
EXPENSE2003CeilingsArchitecture Interior 118,687
CDBG FUND2008Terminal DevicesMechanical Heating 42,215
Total Planned activities for $379,137HRA0036 000
000HRA003704/16/03Date of Last Survey:413 EAST 120TH STREET
EAST HARLEM MULTI SERVICE CENTER -
EXPENSE2008ParapetsArchitecture Exterior 40,292
EXPENSE2008RoofArchitecture Exterior 45,242
EXPENSE2007Interior WallsArchitecture Interior 716,222
EXPENSE2009DistributionMechanical Ventilation 94,129
Total Planned activities for $895,885HRA0037 000
000HRA003807/12/05Date of Last Survey:127 WEST 127TH STREET
OBERIA D. DEMPSEY - MULTI SERVICE CTR (FORMER PS 68)
EXPENSE2007Exterior WallsArchitecture Exterior 49,936
EXPENSE2007RoofArchitecture Exterior 61,725
EXPENSE2007FloorsArchitecture Interior 36,387
EXPENSE2007General LightingElectrical Lighting 44,640
EXPENSE2009Terminal DevicesMechanical Heating 79,923
EXPENSE2009DistributionMechanical Ventilation 91,288
Total Planned activities for $363,899HRA0038 000
Page K - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
HUMAN RESOURCES ADMINISTRATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
K
010HRA003807/12/05Date of Last Survey:125 WEST 127TH STREET
OBERIA D. DEMPSEY - MULTI SERVICE CTR (ANNEX)
EXPENSE2008Exterior WallsArchitecture Exterior 97,770
Total Planned activities for $97,770HRA0038 010
000HRA004707/13/05Date of Last Survey:630 JACKSON AVENUE
HUNTS POINT MULTI SERVICE CENTER -
EXPENSE2009WindowsArchitecture Exterior 39,983
Total Planned activities for $39,983HRA0047 000
000HRA006704/21/03Date of Last Survey:217 HART STREET
HART FAMILY RESIDENCE -
EXPENSE2005Exterior WallsArchitecture Exterior 49,302
Total Planned activities for $49,302HRA0067 000
000HRA007007/26/06Date of Last Survey:1275 WESTCHESTER AVENUE
TRANSITIONAL HOUSING-NEW DAY ONE -
EXPENSE2007Exterior WallsArchitecture Exterior 117,838
Total Planned activities for $117,838HRA0070 000
Total Planned Activities for : $2,991,919HUMAN RESOURCES ADMINISTRATION
Total Required for "State of Good Repair" for : HUMAN RESOURCES ADMINISTRATION $5,227,455
Page K - 2
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF CULTURAL AFFAIRS
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
L
A00DCA000101/24/05Date of Last Survey:5TH AVE & 82ND STREET
METROPOLITAN MUSEUM OF ART - WING A
850PV022-ACR2007RoofArchitecture Exterior 507,357
Total Planned activities for $507,357DCA0001 A00
C00DCA000101/24/05Date of Last Survey:5TH AVE & 82ND STREET
METROPOLITAN MUSEUM OF ART - WING C
PV022-ACR2007Exterior WallsArchitecture Exterior 568,310
PV022-ACR2007WindowsArchitecture Exterior 539,857
PV022-ACR2007RoofArchitecture Exterior 384,982
Total Planned activities for $1,493,149DCA0001 C00
002DCA000205/21/03Date of Last Survey:W. 77TH ST. & CPW
AMERICAN MUSEUM OF NATL HISTORY - SECTION 2
850 PV034-MOD2007Exterior WallsArchitecture Exterior 201,631
850 PV034-MOD2007WindowsArchitecture Exterior 206,652
Total Planned activities for $408,283DCA0002 002
003DCA000205/21/03Date of Last Survey:W. 77TH ST. & CPW
AMERICAN MUSEUM OF NATL HISTORY - SECTION 3
850 PV034-MOD2007Exterior WallsArchitecture Exterior 312,470
850 PV034-MOD2007WindowsArchitecture Exterior 566,165
Total Planned activities for $878,635DCA0002 003
004DCA000205/22/03Date of Last Survey:W. 77TH ST. & CPW
AMERICAN MUSEUM OF NATL HISTORY - SECTION 4
850 PV034-MOD2007Exterior WallsArchitecture Exterior 256,490
850 PV034-MOD2007WindowsArchitecture Exterior 538,130
Total Planned activities for $794,620DCA0002 004
005DCA000205/21/03Date of Last Survey:W. 77TH ST. & CPW
AMERICAN MUSEUM OF NATL HISTORY - SECTION 5
850 PV034-MOD2007Exterior WallsArchitecture Exterior 396,581
850 PV034-MOD2007WindowsArchitecture Exterior 51,223
Total Planned activities for $447,804DCA0002 005
006DCA000205/22/03Date of Last Survey:W. 77TH ST. & CPW
AMERICAN MUSEUM OF NATL HISTORY - SECTION 6
850 PV034-MOD2007Exterior WallsArchitecture Exterior 396,581
850 PV034-MOD2007WindowsArchitecture Exterior 512,230
Total Planned activities for $908,811DCA0002 006
02ADCA000205/22/03Date of Last Survey:W. 77TH ST. & CPW
AMERICAN MUSEUM OF NATL HISTORY - SECTION 2A
850 PV034-MOD2007Exterior WallsArchitecture Exterior 53,398
850 PV034-MOD2007WindowsArchitecture Exterior 122,578
Page L - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF CULTURAL AFFAIRS
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
L
Total Planned activities for $175,976DCA0002 02A
02BDCA000205/21/03Date of Last Survey:W. 77TH ST. & CPW
AMERICAN MUSEUM OF NATL HISTORY - SECTION 2B
850 PV034-MOD2007Exterior WallsArchitecture Exterior 56,958
850 PV034-MOD2007WindowsArchitecture Exterior 122,578
Total Planned activities for $179,536DCA0002 02B
ELEDCA000205/21/03Date of Last Survey:W. 77TH ST. & CPW
AMERICAN MUSEUM OF NATL HISTORY - ELECTRICAL SYSTEM
850 PV034-INF2007WiringElectrical Under 600 Volts 136,947
850PV034-GEN2007GeneratorsElectrical Stand-by Power 64,580
Total Planned activities for $201,527DCA0002 ELE
010DCA000301/19/06Date of Last Survey:614 BROADWAY
STATEN ISLAND ZOOLOGICAL SOCIETY - MAIN ZOO BUILDING
850 PV175-REP2007CeilingsArchitecture Interior 39,695
850 PV175-REP2007DistributionMechanical Heating 37,744
Total Planned activities for $77,439DCA0003 010
290DCA000503/24/04Date of Last Survey:BRONX RIVER PKWY & FORDHAM RD
BRONX ZOO - LIONS HOUSE-#29
PV176-LIO2008Exterior WallsArchitecture Exterior 860,114
PV176-LIO2008WindowsArchitecture Exterior 35,548
PV176-LIO2008ParapetsArchitecture Exterior 184,679
PV176-LIO2008RoofArchitecture Exterior 1,234,982
PV176-LIO2008FloorsArchitecture Interior 792,222
PV176-LIO2008Interior WallsArchitecture Interior 560,184
PV176-LIO2008CeilingsArchitecture Interior 484,577
PV176-LIO2008General LightingElectrical Lighting 49,913
PV176-LIO2008Conversion EquipmentMechanical Heating 82,301
PV176-LIO2008DistributionMechanical Heating 110,255
PV176-LIO2008Terminal DevicesMechanical Heating 100,748
Total Planned activities for $4,495,523DCA0005 290
020DCA000901/18/05Date of Last Survey:BOARDWALK W. 8TH ST.
NY AQUARIUM - MAIN AQUARIUM
801PV230-SHA2007GeneratorsElectrical Stand-by Power 31,467
Total Planned activities for $31,467DCA0009 020
160DCA000901/01/06Date of Last Survey:BOARDWALK W. 8TH ST.
NY AQUARIUM - SHARK BUILDING
PV230-SHA2007Average Cost Method
7,296
Total Planned activities for $7,296DCA0009 160
Page L - 2
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF CULTURAL AFFAIRS
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
L
170DCA000901/01/06Date of Last Survey:BOARDWALK W. 8TH ST.
NY AQUARIUM - EXHIBIT
PV230-REC2010Average Cost Method
43,131
Total Planned activities for $43,131DCA0009 170
010DCA001002/26/03Date of Last Survey:SOUTHERN BLVD @ 200TH STREET
NEW YORK BOTANICAL GARDEN - SNUFF MILLS RESTAURANT
PV205SNUF2008Exterior WallsArchitecture Exterior 265,578
PV205SNUF2008WindowsArchitecture Exterior 108,157
PV205SNUF2008RoofArchitecture Exterior 44,895
Total Planned activities for $418,630DCA0010 010
040DCA001002/25/03Date of Last Survey:SOUTHERN BLVD @ 200TH STREET
NEW YORK BOTANICAL GARDEN - MUSEUM, OFFICES & LIBRARY
PV205HVAC2007DistributionMechanical Heating 96,669
Total Planned activities for $96,669DCA0010 040
050DCA001002/25/03Date of Last Survey:SOUTHERN BLVD @ 200TH STREET
NEW YORK BOTANICAL GARDEN - CONSERVATORY
PV205-EHC2008General LightingElectrical Lighting 37,362
PV205-EHC2008DistributionMechanical Heating 53,026
Total Planned activities for $90,388DCA0010 050
220DCA001002/26/03Date of Last Survey:SOUTHERN BLVD @ 200TH STREET
NEW YORK BOTANICAL GARDEN - PROPAGATION RANGE
PV205-HSF2008Exterior WallsArchitecture Exterior 129,861
PV205-HSF2008RoofArchitecture Exterior 1,093,912
Total Planned activities for $1,223,773DCA0010 220
010DCA001102/22/05Date of Last Survey:200 EASTERN PKWY.
BROOKLYN MUSEUM - MAIN WINGS C,D,E,F AND G
PV235-CL42007Terminal DevicesMechanical Heating 559,647
PV235-CL42007DistributionMechanical Ventilation 179,167
Total Planned activities for $738,814DCA0011 010
030DCA001102/22/05Date of Last Survey:200 EASTERN PKWY.
BROOKLYN MUSEUM - WING H
PV235-CL42007DistributionMechanical Heating 26,243
Total Planned activities for $26,243DCA0011 030
000DCA001304/10/03Date of Last Survey:1220 FIFTH AVE.
MUSEUM OF THE CITY OF NEW YORK -
PV241-REN2007RoofArchitecture Exterior 612,897
PV241-MOD2007FloorsArchitecture Interior 279,320
PV241-MOD2007Interior WallsArchitecture Interior 1,126,247
Page L - 3
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF CULTURAL AFFAIRS
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
L
PV241-MOD2007CeilingsArchitecture Interior 150,289
PV241-MOD2007General LightingElectrical Lighting 99,292
PV241-MOD2007Energy SourceMechanical Heating 331,424
PV241MOD12010Conversion EquipmentMechanical Heating 655,019
PV241-MOD2007DistributionMechanical Heating 469,735
PV241MOD12010Terminal DevicesMechanical Heating 362,740
PV241MOD12010Conversion EquipmentMechanical Air Conditioning 456,687
PV241MOD12010DistributionMechanical Ventilation 348,387
PV241MOD12010Exhaust FansMechanical Ventilation 148,749
PV241MOD12010H/C Water PipingMechanical Plumbing 40,188
PV241MOD12010Sanitary PipingMechanical Plumbing 58,456
Total Planned activities for $5,139,430DCA0013 000
000DCA001502/24/05Date of Last Survey:30 LAFAYETTE AVE.
BROOKLYN ACADEMY OF MUSIC -
850 PV264-ALT2007RoofArchitecture Exterior 52,642
Total Planned activities for $52,642DCA0015 000
050DCA001604/07/03Date of Last Survey:43-50 MAIN STREET
QUEENS BOTANICAL GARDEN - GREENHOUSE
PV272-L2007RoofArchitecture Exterior 66,037
Total Planned activities for $66,037DCA0016 050
000DCA001703/14/06Date of Last Survey:47-01 111TH STREET
NEW YORK HALL OF SCIENCE -
850 PV274-SP12007Exterior WallsArchitecture Exterior 139,882
850 PV274-SP12007RoofArchitecture Exterior 154,964
Total Planned activities for $294,846DCA0017 000
000DCA001802/23/05Date of Last Survey:130 W 56TH ST.
CITY CTR/55TH ST DANCE THEATRE -
801CITYCENTR2007WindowsArchitecture Exterior 39,600
850 PV279-FLO22007RoofArchitecture Exterior 36,221
Total Planned activities for $75,821DCA0018 000
000DCA001906/06/05Date of Last Survey:425 LAFAYETTE ST.
NEW YORK PUBLIC THEATRE -
126 PV289-REC2007Exterior WallsArchitecture Exterior 261,702
850 PV289-ROF2007ParapetsArchitecture Exterior 38,973
126 PV289-REC2007Interior WallsArchitecture Interior 205,755
126 PV289-REC2007CeilingsArchitecture Interior 301,399
126 PV289-REC2007Conversion EquipmentMechanical Air Conditioning 247,770
Total Planned activities for $1,055,599DCA0019 000
Page L - 4
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF CULTURAL AFFAIRS
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
L
000DCA002003/23/05Date of Last Survey:FLUSHING MEADOWS CORONA PARK
QUEENS MUSEUM OF ART -
PV291-QMX2008Exterior WallsArchitecture Exterior 176,390
PV291-QMX2008FloorsArchitecture Interior 55,139
Total Planned activities for $231,529DCA0020 000
110DCA002101/01/06Date of Last Survey:441 CLARKE AVENUE
STATEN ISLAND HISTORICAL SOCIETY - BOEHM HOUSE
PV341-REC2010Average Cost Method
11,108
Total Planned activities for $11,108DCA0021 110
200DCA002101/01/06Date of Last Survey:441 CLARKE AVENUE
STATEN ISLAND HISTORICAL SOCIETY - BRITTON COTTAGE
PV341-REC2010Average Cost Method
38,572
Total Planned activities for $38,572DCA0021 200
210DCA002101/01/06Date of Last Survey:441 CLARKE AVENUE
STATEN ISLAND HISTORICAL SOCIETY - KRUSER - FINLEY HOUSE
PV341-REC2010Average Cost Method
6,856
Total Planned activities for $6,856DCA0021 210
250DCA002101/01/06Date of Last Survey:441 CLARKE AVENUE
STATEN ISLAND HISTORICAL SOCIETY - CARRIAGE & WAGON MANUFACTORY
126PV341-CAR2007Average Cost Method
7,336
Total Planned activities for $7,336DCA0021 250
270DCA002101/01/06Date of Last Survey:441 CLARKE AVENUE
STATEN ISLAND HISTORICAL SOCIETY - BENNETT HOUSE
PV341-REC2010Average Cost Method
10,760
Total Planned activities for $10,760DCA0021 270
320DCA002101/01/06Date of Last Survey:441 CLARKE AVENUE
STATEN ISLAND HISTORICAL SOCIETY - STORAGE BLDG/CARRIAGE HOUSE
PV341-CAR2008Average Cost Method
9,096
Total Planned activities for $9,096DCA0021 320
330DCA002101/01/06Date of Last Survey:441 CLARKE AVENUE
STATEN ISLAND HISTORICAL SOCIETY - STORAGE SHED
PV341-REC2010Average Cost Method
9,096
Total Planned activities for $9,096DCA0021 330
Page L - 5
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF CULTURAL AFFAIRS
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
L
340DCA002104/19/05Date of Last Survey:441 CLARKE AVENUE
STATEN ISLAND HISTORICAL SOCIETY - OLD PUBLIC SCHOOL 28
126PV341PS282007WindowsArchitecture Exterior 73,907
Total Planned activities for $73,907DCA0021 340
370DCA002101/01/06Date of Last Survey:441 CLARKE AVENUE
STATEN ISLAND HISTORICAL SOCIETY - CROCHERON HOUSE
PV341-REC2010Average Cost Method
38,541
Total Planned activities for $38,541DCA0021 370
010DCA002201/31/06Date of Last Survey:675 WEST 252 STREET
WAVE HILL - WAVE HILL HOUSE
850PV464-ADA2007RoofArchitecture Exterior 82,173
850PV464-ADA2007Conversion EquipmentMechanical Heating 43,316
Total Planned activities for $125,489DCA0022 010
030DCA002404/27/05Date of Last Survey:1000 RICHMOND TERRACE
SNUG HARBOR CULTURAL CENTER - BLDG C - NEWHOUSE CENTER
850 PV490-MAT2007WindowsArchitecture Exterior 132,514
Total Planned activities for $132,514DCA0024 030
050DCA002404/27/05Date of Last Survey:1000 RICHMOND TERRACE
SNUG HARBOR CULTURAL CENTER - BLDG E
850 PV490-E2007Exterior WallsArchitecture Exterior 501,961
850 PV490-E2007ParapetsArchitecture Exterior 173,842
850 PV490-E 2007RoofArchitecture Exterior 64,119
Total Planned activities for $739,922DCA0024 050
060DCA002404/27/05Date of Last Survey:1000 RICHMOND TERRACE
SNUG HARBOR CULTURAL CENTER - BLDG F
850 PV490-FH2007DistributionMechanical Heating 50,110
Total Planned activities for $50,110DCA0024 060
190DCA002404/25/05Date of Last Survey:1000 RICHMOND TERRACE
SNUG HARBOR CULTURAL CENTER - BLDG T - MUSIC HALL
850 PV490-Q22007Exterior WallsArchitecture Exterior 46,040
850 PV490-Q22007WindowsArchitecture Exterior 60,557
850 PV490-Q22007Interior WallsArchitecture Interior 130,246
850 PV490-Q22007CeilingsArchitecture Interior 94,403
Total Planned activities for $331,246DCA0024 190
000DCA002505/07/04Date of Last Survey:37 W 65TH STREET
NEW YORK STATE THEATRE - LINCOLN CENTER
PV475-INF2007Exterior WallsArchitecture Exterior 514,523
Total Planned activities for $514,523DCA0025 000
Page L - 6
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF CULTURAL AFFAIRS
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
L
000DCA002702/23/05Date of Last Survey:881 7TH AVE
CARNEGIE HALL -
850 PV503EMER2007WindowsArchitecture Exterior 105,843
850 PV503EMER2007RoofArchitecture Exterior 105,402
Total Planned activities for $211,245DCA0027 000
010DCA002803/15/06Date of Last Survey:1000 RICHMOND TERRACE
STATEN IS. INST. ARTS & SCIENCES - BUILDING A
850 PV302-AB2007Exterior WallsArchitecture Exterior 68,844
850 PV302-F2007WindowsArchitecture Exterior 235,706
850 PV302-AB2007FloorsArchitecture Interior 643,355
850 PV302-AB2007Interior WallsArchitecture Interior 409,728
850 PV302-AB2007CeilingsArchitecture Interior 490,738
850 PV302-AB2007General LightingElectrical Lighting 80,273
Total Planned activities for $1,928,644DCA0028 010
020DCA002803/15/06Date of Last Survey:1000 RICHMOND TERRACE
STATEN IS. INST. ARTS & SCIENCES - BUILDING B
850 PV302-AB2007Exterior WallsArchitecture Exterior 111,954
850 PV302-AB2007WindowsArchitecture Exterior 215,931
850 PV302-AB2007FloorsArchitecture Interior 589,452
850 PV302-AB2007Interior WallsArchitecture Interior 398,861
850 PV302-AB2007CeilingsArchitecture Interior 449,622
850 PV302-AB2007General LightingElectrical Lighting 73,548
Total Planned activities for $1,839,368DCA0028 020
000DCA003203/21/05Date of Last Survey:FLUSHING MEADOWS CORONA PARK
QUEENS THEATRE IN THE PARK -
850 PV466-AC2007Heat RejectionMechanical Air Conditioning 43,295
Total Planned activities for $43,295DCA0032 000
000DCA003405/07/04Date of Last Survey:140 WEST 65TH ST.
LINCOLN CTR FOR PERFORMING ARTS - PLAZA AND GARAGE
PV489-IMP2008ParapetsArchitecture Exterior 104,001
PV489-IMP2008RoofArchitecture Exterior 295,703
PV489-IMP2008FloorsArchitecture Interior 538,621
PV489-IMP2008CeilingsArchitecture Interior 1,185,716
PV489-IMP2008WiringElectrical Under 600 Volts 62,562
Total Planned activities for $2,186,603DCA0034 000
010DCA003405/07/04Date of Last Survey:AMSTERDAM AVE. & W. 62ND ST.
LINCOLN CTR. FOR PERFORMING ARTS - DAMROSCH BANDSHELL
PV489-IMP2008RoofArchitecture Exterior 51,028
Total Planned activities for $51,028DCA0034 010
Page L - 7
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF CULTURAL AFFAIRS
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
L
000DCA003702/12/03Date of Last Survey:137-35 NORTHERN BLVD.
FLUSHING TOWN HALL -
PV467-FTR2008Exterior WallsArchitecture Exterior 56,613
Total Planned activities for $56,613DCA0037 000
000DGS003612/01/05Date of Last Survey:100 OLD SLIP
POLICE MUSEUM - (OLD 1ST PRECINCT)
PV467-POL2008WindowsArchitecture Exterior 392,753
PV467-POL2008ParapetsArchitecture Exterior 54,121
Total Planned activities for $446,874DGS0036 000
Total Planned Activities for : $29,023,720DEPARTMENT OF CULTURAL AFFAIRS
Total Required for "State of Good Repair" for : DEPARTMENT OF CULTURAL AFFAIRS $60,849,812
Page L - 8
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF JUVENILE JUSTICE
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
M
000DJJ000106/14/05Date of Last Survey:1221 SPOFFORD AVENUE
BRIDGES JUVENILE CENTER - INTAKE/ADMISSIONS
850BXDETCT2006WindowsArchitecture Exterior 2,704,212
850BRBOIL2007Conversion EquipmentMechanical Heating 159,586
850BRBOIL2007DistributionMechanical Heating 259,706
Total Planned activities for $3,123,504DJJ0001 000
000DJJ000206/20/05Date of Last Survey:17 BRISTOL ST.
JUVENILE DETENTION CENTER - CROSSROADS
850HZNREP2007Exterior WallsArchitecture Exterior 109,857
130 21752007RoofArchitecture Exterior 32,786
Total Planned activities for $142,643DJJ0002 000
000DJJ000306/14/05Date of Last Survey:560 BROOK AVENUE
JUVENILE DETENTION CENTER - HORIZON
850HZNREP2007Exterior WallsArchitecture Exterior 83,352
130 21752007RoofArchitecture Exterior 24,735
Total Planned activities for $108,087DJJ0003 000
Total Planned Activities for : $3,374,234DEPARTMENT OF JUVENILE JUSTICE
Total Required for "State of Good Repair" for : DEPARTMENT OF JUVENILE JUSTICE $4,528,895
Page M - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF SMALL BUSINESS SERVICES
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
N
010DBS000406/03/02Date of Last Survey:SOUTH & FULTON STS.
FORMER FULTON FISH MARKET - BUILDING 19-32
FISHMKT2003Exterior WallsArchitecture Exterior 109,985
801-FISHMKT2006WindowsArchitecture Exterior 1,063,622
Total Planned activities for $1,173,607DBS0004 010
000DBS000606/07/05Date of Last Survey:EAST RIVER AT GOUVERNEUR SLIP
PIER 42 - TERMINAL
801-EBIKEWAY2006Exterior WallsArchitecture Exterior 198,112
Total Planned activities for $198,112DBS0006 000
010DBS000610/12/01Date of Last Survey:EAST RIVER
PIER 42 -
PIER422007Piles and BracingPiers Structural 5,495,545
Total Planned activities for $5,495,545DBS0006 010
104DBS001304/15/03Date of Last Survey:39 ST BULKHEAD
SOUTH BROOKLYN MARINE TERMINAL - 39 ST BULKHEAD
CAPITAL2006Relieving Platform TopBulkheads Structural 227,684
Total Planned activities for $227,684DBS0013 104
000DBS001506/07/05Date of Last Survey:25TH STREET AT GOWANUS BAY
25TH ST. TERMINAL - WAREHOUSE - BLDG. #1
801-23STBULK2007FloorsArchitecture Interior 350,478
Total Planned activities for $350,478DBS0015 000
050DBS001606/14/05Date of Last Survey:41st - 51st STREET AND 1st AVE
BUSH TERMINAL-MASTAS - ADMIN. BLDG - OFFICES
801-BUSHMKT2006Exterior WallsArchitecture Exterior 40,312
Total Planned activities for $40,312DBS0016 050
000DBS002004/23/03Date of Last Survey:WHSE-BUILDING #1
HUNTS POINT MARKET - FRUIT AUCTION BLDGS
CAPITAL2006RoofArchitecture Exterior 1,510,766
Total Planned activities for $1,510,766DBS0020 000
090DBS002106/14/06Date of Last Survey:HALLECK STREET
NEW YORK CITY TERMINAL MARKET - BUILDING S.B. - SERVICE BRIDGE
PTHUNTEXP2003WiringElectrical Under 600 Volts 54,816
Total Planned activities for $54,816DBS0021 090
010DBS002206/15/06Date of Last Survey:FOOD CENTER DRIVE
HUNTS POINT CO-OP MARKET - BUILDING B
801-HUNT200DR2007Exterior WallsArchitecture Exterior 129,145
801-HUNT200DR2006RoofArchitecture Exterior 483,296
Total Planned activities for $612,441DBS0022 010
Page N - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF SMALL BUSINESS SERVICES
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
N
020DBS002206/15/06Date of Last Survey:FOOD CENTER DRIVE
HUNTS POINT CO-OP MARKET - BUILDING C
801-HUNT1552008Exterior WallsArchitecture Exterior 65,125
Total Planned activities for $65,125DBS0022 020
041DBS002510/26/04Date of Last Survey:E. RIVER, PIER 9 TO PIER 13
E.RIVER SOUTH SIDE PIER 9 TO 13 -
801-WATERLUMP2008Relieving Platform TopBulkheads Structural 187,122
Total Planned activities for $187,122DBS0025 041
021DBS002710/11/01Date of Last Survey:HARLEM RIVER, 147TH - 158TH ST
BULKHEAD - HARLEM RIVER - SEAWALL/REVETMENT/CRIBBING
801-HARLESPL2006SurfaceBulkheads Backfill 69,737
Total Planned activities for $69,737DBS0027 021
000DBS002805/05/06Date of Last Survey:121 WEST 125TH STREET
125TH STREET PARKING GARAGE - 5 LEVEL GARAGE
801-W125THST2005RoofArchitecture Exterior 111,930
801-W125THST2005FloorsArchitecture Interior 218,195
Total Planned activities for $330,125DBS0028 000
000DBS003204/11/06Date of Last Survey:1680 LEXINGTON AVENUE
JULIA DEBURGOS LATINO - CULTURAL CENTER
801-1680LEXAV2008WindowsArchitecture Exterior 63,357
Total Planned activities for $63,357DBS0032 000
000DBS003304/19/06Date of Last Survey:405 FRONT STREET
NAVAL STATION NEW YORK,STAPLETON - RICHMOND SUPREME COURT
CAPITAL2007CeilingsArchitecture Interior 78,334
Total Planned activities for $78,334DBS0033 000
000DBS003406/02/05Date of Last Survey:140 58TH STREET
BROOKLYN ARMY TERMINAL - BUILDING A
801-BATRAIL2008Exterior WallsArchitecture Exterior 244,060
ED373BAT22007WindowsArchitecture Exterior 511,852
801-ED373BAT22005RoofArchitecture Exterior 40,516
CAPITAL2006Interior WallsArchitecture Interior 50,510
Total Planned activities for $846,938DBS0034 000
020DBSR00210/12/01Date of Last Survey:PIER 13, 14
E.R. PLATFORM @ PIERS 13,14 - PIER/PLATFORM
STHMARINE2003Pile CapsPiers Structural 63,049
STHMARINE2007Piles and BracingPiers Structural 99,228
Total Planned activities for $162,277DBSR002 020
063DBSR02510/11/01Date of Last Survey:E. RIVER, 32ND TO 34TH STS.
WHARF AND SEAWALL - E. 32ND TO E. 34TH STS.
Page N - 2
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF SMALL BUSINESS SERVICES
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
N
801-WATERLUMP2009Wales and ChocksBulkheads Fender 182,233
Total Planned activities for $182,233DBSR025 063
066DBSR02510/21/03Date of Last Survey:E. 23RD ST. & U.N. SCHOOL
PIER - E. 23RD ST. & U.N. SCHOOL
CAPITAL2006Piles and BracingPiers Structural 352,098
Total Planned activities for $352,098DBSR025 066
013DBSR02604/17/03Date of Last Survey:SOUTH BROOKLYN MARINE TERMINAL
BULKHEAD AT 29TH STREET PIER - SHEET PILES/GRAVITY WALL
CAPITAL2006Pile Supported WallBulkheads Structural 141,364
Total Planned activities for $141,364DBSR026 013
023DBSR02604/16/03Date of Last Survey:39TH TO 52ND ST.
BUSH TERMINAL BULKHEAD - N/S PIER 4 TO N/S PIER 5
801-BUSHSTGY2008Sheet PilesBulkheads Structural 469,938
Total Planned activities for $469,938DBSR026 023
014DBSR02712/06/01Date of Last Survey:400-600 FOOD CENTER DRIVE
HUNTS POINT PENINSULA - FORMER WEDTECH SITE (SITE C)
801-HUNTBULK2006Gravity WallBulkheads Structural 1,372,486
Total Planned activities for $1,372,486DBSR027 014
015DBSR02712/06/01Date of Last Survey:600 FOOD CENTER DRIVE
HUNTS POINT PENINSULA,BOARDWALK- - SULTANA DISTRIBUTION SERVICES
801-HUNT600DR2005Coping/CurbBulkheads Structural 4,151
801-HUNT6002008Coping/CurbBulkheads Structural 62,270
Total Planned activities for $66,421DBSR027 015
000DBSR03504/21/03Date of Last Survey:HALFWAY DOWN 47TH ST, EMPTY LOT
MASPETH CREEK - RELIEVING PLATFORM
CAPITAL2006Piles and BracingBulkheads Structural 127,561
Total Planned activities for $127,561DBSR035 000
000DBSR03605/19/03Date of Last Survey:E 27ST/ QUENTIN ST & PEMBROKE ST
SHEEPSHEAD BAY MARINAS - GRAVITY WALL
CAPITAL2006Sheet PilesBulkheads Structural 665,715
Total Planned activities for $665,715DBSR036 000
020DBSR03704/21/03Date of Last Survey:119-08 29TH AVENUE
WILLIAMSBURG YACHT CLUB - PIER
CAPITAL2006DeckPiers Structural 37,988
Total Planned activities for $37,988DBSR037 020
020DBSR03804/17/03Date of Last Survey:FOOT OF 66 ST
65TH STREET RAIL YARD - TRANSFER BRIDGE PIERS
801-WATERLUMP2009PilesPiers Fender 148,214
Total Planned activities for $148,214DBSR038 020
Page N - 3
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF SMALL BUSINESS SERVICES
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
N
000DBSR04304/18/03Date of Last Survey:W 54TH ST AND HUDSON RIVER
PIER 94 - UNCONVENTION CENTER
CAPITAL2006Piles and BracingPiers Structural 398,008
Total Planned activities for $398,008DBSR043 000
010DGS004704/23/03Date of Last Survey:BTW GREENFIED AVE
NAVY HOME PORT - WHARFS, BULKHEAD, SEAWALL
PT195-VAR2005Coping/CurbBulkheads Structural 56,744
PT195-VAR2005Sheet PilesBulkheads Structural 2,848,591
Total Planned activities for $2,905,335DGS0047 010
020DGS004704/23/03Date of Last Survey:GREENFIELD AVE AND
NAVY HOME PORT - RIP-RAP
PT195-VAR2005Gravity WallBulkheads Structural 2,319,552
PT195-VAR2005RevetmentBulkheads Structural 141,031
Total Planned activities for $2,460,583DGS0047 020
030DGS004704/23/03Date of Last Survey:BTW GREENFIELD AVE AND
NAVY HOME PORT - NAVY CONCRETE PIER
PT195-VAR2005DeckPiers Structural 584,131
PT195-VAR2005BufferPiers Fender 47,009
Total Planned activities for $631,140DGS0047 030
010DGSP00310/26/04Date of Last Survey:PIER 16
PIER 16, EAST RIVER -
801-WATERLUMP2008Deck SurfacePiers Structural 53,718
801-SSSUPLAND2008Wales and ChocksPiers Fender 37,692
Total Planned activities for $91,410DGSP003 010
031DGSP00510/12/01Date of Last Survey:EAST RIVER, PIER 35
PIER 35 -
801-WATERLUMP2007Piles and BracingPiers Structural 274,944
Total Planned activities for $274,944DGSP005 031
043DGSP02510/12/01Date of Last Survey:FLETCHER ST NORTH TO BEEKMAN ST
BULKHEAD - ALONG SOUTH STREET
PT195-VAR2007PilesBulkheads Fender 43,455
PT195-VAR2007Wales and ChocksBulkheads Fender 102,595
Total Planned activities for $146,050DGSP025 043
044DGSP02510/12/01Date of Last Survey:ROBERT F. WAGNER PLACE
BULKHEAD -
PT195-VAR2007Pile Supported WallBulkheads Structural 230,814
Total Planned activities for $230,814DGSP025 044
045DGSP02510/12/01Date of Last Survey:ROBERT F. WAGNER PLACE
BULKHEAD -
Page N - 4
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF SMALL BUSINESS SERVICES
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
N
PT195-VAR2007Pile Supported WallBulkheads Structural 2,262,213
Total Planned activities for $2,262,213DGSP025 045
046DGSP02510/12/01Date of Last Survey:SOUTH STREET
BULKHEAD - GRAVITY WALL/RELIEVING PLATFORM
PT195-VAR2007Pile Supported WallBulkheads Structural 1,515,344
Total Planned activities for $1,515,344DGSP025 046
000DGSP03005/22/06Date of Last Survey:EAST 23RD ST. & EAST RIVER
23RD ST. MARINA - PARKING GARAGE
PT195-VAR2007Exterior WallsArchitecture Exterior 276,524
PT195-VAR2007RoofArchitecture Exterior 94,298
PT195-VAR2007FloorsArchitecture Interior 301,205
PT195-VAR2007CeilingsArchitecture Interior 381,107
Total Planned activities for $1,053,134DGSP030 000
067DGSPR2510/25/04Date of Last Survey:EAST RIVER, 35TH ST.
PIER - E. 35TH ST. PIER
PT195-VAR2005DeckPiers Structural 182,353
PT195-VAR2005Pile CapsPiers Structural 157,947
PT195-VAR2005Piles and BracingPiers Structural 248,581
PT195-VAR2005FacingPiers Fender 279,249
PT195-VAR2005Wales and ChocksPiers Fender 105,709
PT195-VAR2005PilesPiers Fender 44,775
Total Planned activities for $1,018,614DGSPR25 067
001DGSPR3010/21/03Date of Last Survey:23RD ST. MARINA
23RD ST. MARINA PKG. GARAGE - BUILDING FOUNDATION
PT195-VAR2007DeckPiers Structural 98,620
Total Planned activities for $98,620DGSPR30 001
002DGSPR3010/21/03Date of Last Survey:23RD ST. MARINA
23RD ST. MARINA DOCK PIER - PIER
PT195-VAR2007FacingPiers Fender 547,064
Total Planned activities for $547,064DGSPR30 002
022DGSPR3010/21/03Date of Last Survey:23RD ST. MARINA
23RD ST. MARINA DOCK - BULKHEAD
PT195-VAR2007Pile Supported WallBulkheads Structural 111,431
Total Planned activities for $111,431DGSPR30 022
Total Planned Activities for : $28,775,498DEPT. OF SMALL BUSINESS SERVICES
Total Required for "State of Good Repair" for : DEPT. OF SMALL BUSINESS SERVICES $216,129,764
Page N - 5
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF HEALTH & MENTAL HYGIENE
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
O
000HEA000106/20/06Date of Last Survey:455 FIRST AVENUE
PUBLIC HEALTH LABORATORY BLDG. -
HL82PLAZA2008Exterior WallsArchitecture Exterior 309,444
HL82PHLB2008WindowsArchitecture Exterior 2,411,146
HL82PHLB2008ParapetsArchitecture Exterior 39,655
HL82PHLB2008RoofArchitecture Exterior 375,403
HL82PHLB2008FloorsArchitecture Interior 134,756
HL82PHLB2008Interior WallsArchitecture Interior 243,665
HL82PHLB2008CeilingsArchitecture Interior 502,609
HL82PHLB2007Service EquipmentElectrical Under 600 Volts 39,288
HL82PHLB2007SwitchgearElectrical Under 600 Volts 191,693
HL82PHLB2007WiringElectrical Under 600 Volts 204,267
HL82PHLB2008General LightingElectrical Lighting 100,680
HL82PHLB2007DistributionMechanical Heating 166,352
HL82PHLB2007DistributionMechanical Air Conditioning 131,166
HL82PHLB2007Terminal DevicesMechanical Air Conditioning 113,989
HL82PHLB2007DistributionMechanical Ventilation 463,245
HL82PHLB2007Exhaust FansMechanical Ventilation 47,470
Total Planned activities for $5,474,828HEA0001 000
000HEA000205/10/05Date of Last Survey:148 EAST 115 STREET
EAST HARLEM DISTRICT HEALTH CTR -
HL82EHRLM2006Exterior WallsArchitecture Exterior 151,429
HL82EHRLM2007WindowsArchitecture Exterior 77,309
HL82EHRLM2007ParapetsArchitecture Exterior 64,130
HL82EHRLM2007General LightingElectrical Lighting 69,373
Total Planned activities for $362,241HEA0002 000
000HEA000304/24/03Date of Last Survey:600 WEST 168TH STREET
WASHINGTON HEIGHTS DIST. HEALTH -
HL82WASRF2007WindowsArchitecture Exterior 37,408
Total Planned activities for $37,408HEA0003 000
000HEA000407/05/05Date of Last Survey:1309 FULTON AVENUE
MORRISANIA DISTRICT HEALTH CTR -
HL82MORRF2007Exterior WallsArchitecture Exterior 36,231
HL82MORRF2007WindowsArchitecture Exterior 524,814
HL82MORRF2007RoofArchitecture Exterior 174,070
Total Planned activities for $735,115HEA0004 000
000HEA000707/06/05Date of Last Survey:90-37 PARSONS BOULEVARD
JAMAICA DISTRICT HEALTH CENTER -
HL82JAMCX2008Exterior WallsArchitecture Exterior 130,996
Page O - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF HEALTH & MENTAL HYGIENE
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
O
HL82JAMCX2008WindowsArchitecture Exterior 61,377
HL82JAMCX2008General LightingElectrical Lighting 67,135
Total Planned activities for $259,508HEA0007 000
000HEA000806/29/06Date of Last Survey:485 THROOP AVENUE
BEDFORD DISTRICT HEALTH CENTER -
HL82GENLM2007Exterior WallsArchitecture Exterior 102,970
Total Planned activities for $102,970HEA0008 000
000HEA000905/06/04Date of Last Survey:295 FLATBUSH AVENUE EXT.
FORT GREENE DISTRICT HEALTH CTR -
HL82FCADE2005WindowsArchitecture Exterior 158,301
Total Planned activities for $158,301HEA0009 000
000HEA001107/14/05Date of Last Survey:51-63 STUYVESANT PLACE
STATEN ISLAND DISTRICT HEALTH CR -
HL82RCMD22007WindowsArchitecture Exterior 607,565
HL82RCMD22007SwitchgearElectrical Under 600 Volts 38,339
HL82RCMD32007General LightingElectrical Lighting 65,423
Total Planned activities for $711,327HEA0011 000
000HEA001205/10/05Date of Last Survey:2238 FIFTH AVENUE
CENTRAL HARLEM DIST HEALTH CTR -
HL82DO26A2006Exterior WallsArchitecture Exterior 145,986
HL82DO26A2006WindowsArchitecture Exterior 476,057
Total Planned activities for $622,043HEA0012 000
000HEA001407/11/05Date of Last Survey:160 WEST 100TH STREET
RIVERSIDE HEALTH CENTER -
HL82RVREX2008Exterior WallsArchitecture Exterior 49,076
HL82RVREX2008WindowsArchitecture Exterior 427,753
HL82RVREX2008Interior WallsArchitecture Interior 39,640
Total Planned activities for $516,469HEA0014 000
000HEA001504/25/03Date of Last Survey:12-26 31ST AVENUE
ASTORIA DISTRICT HEALTH CENTER -
HL82ASTRA2006Exterior WallsArchitecture Exterior 59,156
HL82ASTRA2006WindowsArchitecture Exterior 220,804
HL82ASTRA2006ParapetsArchitecture Exterior 50,446
HL82ASTRA2006SwitchgearElectrical Under 600 Volts 38,339
Total Planned activities for $368,745HEA0015 000
000HEA001606/05/06Date of Last Survey:34-33 JUNCTION BOULEVARD
CORONA DISTRICT HEALTH CENTER -
HHC ID2007Exterior WallsArchitecture Exterior 68,802
Total Planned activities for $68,802HEA0016 000
Page O - 2
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF HEALTH & MENTAL HYGIENE
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
O
000HEA001911/19/01Date of Last Survey:151 MAUJER STREET
WILLIAMSBURG DISTRICT HEALTH CTR -
HL82WLLMS2005Exterior WallsArchitecture Exterior 84,759
HL82WLLMS2005WindowsArchitecture Exterior 36,462
HL82WLLMS2005Interior WallsArchitecture Interior 51,840
HL82WLLMS2005CeilingsArchitecture Interior 51,648
Total Planned activities for $224,709HEA0019 000
000HEA002201/01/06Date of Last Survey:1601 AVE. S
HOMECREST DIST. HEALTH CTR. -
HL82HCRST2007Average Cost Method
239,184
Total Planned activities for $239,184HEA0022 000
000HEA002301/01/06Date of Last Survey:18-39 42ND STREET
PRISON HEALTH WAREHOUSE -
HL82PRSN2007Average Cost Method
194,254
Total Planned activities for $194,254HEA0023 000
000HEA002601/01/06Date of Last Survey:3139 VETERANS ROAD WEST
STATEN ISLAND ANIMAL SHELTER -
HL82SIPCA2007Average Cost Method
154,544
Total Planned activities for $154,544HEA0026 000
Total Planned Activities for : $10,230,448DEPT. OF HEALTH & MENTAL HYGIENE
Total Required for "State of Good Repair" for : DEPT. OF HEALTH & MENTAL HYGIENE $11,213,167
Page O - 3
Appendix
FMS ID/ Budget Code
Agency Activity Year
HEALTH AND HOSPITALS CORP.
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
P
010HHC000102/02/04Date of Last Survey:462 FIRST AVENUE
BELLEVUE HOSPITAL - BLDG C-D
CAPITAL2009Exterior WallsArchitecture Exterior 57,536
EXPENSE2009Exterior WallsArchitecture Exterior 2,601
CAPITAL2004WindowsArchitecture Exterior 1,901,122
CAPITAL2009ParapetsArchitecture Exterior 9,951
EXPENSE2008FloorsArchitecture Interior 252,111
EXPENSE2008CeilingsArchitecture Interior 17,672
EXPENSE2008SwitchgearElectrical Under 600 Volts 7,226
EXPENSE2008SwitchgearElectrical Under 600 Volts 1,204
EXPENSE2008PanelboardsElectrical Under 600 Volts 76,052
EXPENSE2008PanelboardsElectrical Under 600 Volts 1,825
EXPENSE2008WiringElectrical Under 600 Volts 171,109
Total Planned activities for $2,498,409HHC0001 010
020HHC000102/02/04Date of Last Survey:462 FIRST AVENUE
BELLEVUE HOSPITAL - BLDG E
CAPITAL2009Exterior WallsArchitecture Exterior 25,300
CAPITAL2004WindowsArchitecture Exterior 1,419,544
EXPENSE2008SwitchgearElectrical Under 600 Volts 2,810
EXPENSE2008WiringElectrical Under 600 Volts 19,147
Total Planned activities for $1,466,801HHC0001 020
030HHC000102/02/04Date of Last Survey:462 FIRST AVENUE
BELLEVUE HOSPITAL - EMERGENCY & F BUILDING
CAPITAL2008WindowsArchitecture Exterior 119,861
CAPITAL2008RoofArchitecture Exterior 8,978
EXPENSE2008CeilingsArchitecture Interior 52,776
EXPENSE2008WiringElectrical Under 600 Volts 28,698
EXPENSE2008DistributionMechanical Heating 2,401
EXPENSE2009Conversion EquipmentMechanical Air Conditioning 90,715
Total Planned activities for $303,430HHC0001 030
040HHC000102/02/04Date of Last Survey:462 FIRST AVENUE
BELLEVUE HOSPITAL - BLDG H
EXPENSE2008WindowsArchitecture Exterior 63,517
CAPITAL2009RoofArchitecture Exterior 9,853
EXPENSE2007FloorsArchitecture Interior 42,860
EXPENSE2008CeilingsArchitecture Interior 719,649
EXPENSE2008WiringElectrical Under 600 Volts 218,820
EXPENSE2009GeneratorsElectrical Stand-by Power 13,179
EXPENSE2008BatteriesElectrical Stand-by Power 13,870
Page P - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
HEALTH AND HOSPITALS CORP.
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
P
EXPENSE2009General LightingElectrical Lighting 216,147
EXPENSE2008Conversion EquipmentMechanical Heating 4,160
EXPENSE2008DistributionMechanical Heating 93,606
EXPENSE2008Terminal DevicesMechanical Air Conditioning 522,372
EXPENSE2008Terminal DevicesMechanical Air Conditioning 341,661
EXPENSE2008Heat RejectionMechanical Air Conditioning 1,924,117
EXPENSE2008Exhaust FansMechanical Ventilation 444,627
EXPENSE2007Hot Water HeaterMechanical Plumbing 312,019
Total Planned activities for $4,940,457HHC0001 040
050HHC000102/02/04Date of Last Survey:462 FIRST AVENUE
BELLEVUE HOSPITAL - BLDG I-K
EXPENSE2007WindowsArchitecture Exterior 206,947
EXPENSE2007RoofArchitecture Exterior 151,620
EXPENSE2007CeilingsArchitecture Interior 307,194
Total Planned activities for $665,761HHC0001 050
010HHC000203/15/04Date of Last Survey:PELHAM PKWY & EAST CHESTER RD.
BRONX MUNICIPAL HOSPITAL - BLDG M - JACOBI BLDG.
EXPENSE2008RoofArchitecture Exterior 20,362
EXPENSE2008CeilingsArchitecture Interior 11,107
EXPENSE2008WiringElectrical Under 600 Volts 38,294
CAPITAL2009DistributionMechanical Heating 753,717
CAPITAL2010Conversion EquipmentMechanical Air Conditioning 801,827
Total Planned activities for $1,625,306HHC0002 010
030HHC000203/15/04Date of Last Survey:PELHAM PKWY & EAST CHESTER RD.
BRONX MUNICIPAL HOSPITAL - BLDG N - NURSES RESIDENCE
21206022006Exterior WallsArchitecture Exterior 358,799
CAPITAL2011WindowsArchitecture Exterior 1,289,494
EXPENSE2009RoofArchitecture Exterior 424,616
EXPENSE2009CeilingsArchitecture Interior 9,948
EXPENSE2009WiringElectrical Under 600 Volts 21,882
Total Planned activities for $2,104,739HHC0002 030
040HHC000203/16/04Date of Last Survey:PELHAM PKWY & EAST CHESTER RD.
BRONX MUNICIPAL HOSPITAL - BLDG F - STAFF HOUSE
EXPENSE2009WiringElectrical Under 600 Volts 4,377
Total Planned activities for $4,377HHC0002 040
090HHC000203/16/04Date of Last Survey:PELHAM PKWY & EAST CHESTER RD.
BRONX MUNICIPAL HOSPITAL - BLDG G - AUDITORIUM
EXPENSE2008Exterior WallsArchitecture Exterior 2,518
Total Planned activities for $2,518HHC0002 090
Page P - 2
Appendix
FMS ID/ Budget Code
Agency Activity Year
HEALTH AND HOSPITALS CORP.
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
P
010HHC000311/09/04Date of Last Survey:ROOSEVELT ISLAND
COLER MEMORIAL HOSPITAL - BLDG A
672001722009Exterior WallsArchitecture Exterior 86,410
672001722009RoofArchitecture Exterior 771,188
Total Planned activities for $857,598HHC0003 010
020HHC000311/09/04Date of Last Survey:ROOSEVELT ISLAND
COLER MEMORIAL HOSPITAL - BLDG B - CENTRAL BLDG
672001722007Exterior WallsArchitecture Exterior 98,323
672001722007ParapetsArchitecture Exterior 201,817
672001722007RoofArchitecture Exterior 1,941,560
Total Planned activities for $2,241,700HHC0003 020
030HHC000311/09/04Date of Last Survey:ROOSEVELT ISLAND
COLER MEMORIAL HOSPITAL - BLDG C - NORTH BLDG
672001722010Exterior WallsArchitecture Exterior 128,115
672001722010ParapetsArchitecture Exterior 81,972
672001722010RoofArchitecture Exterior 910,799
Total Planned activities for $1,120,886HHC0003 030
050HHC000311/09/04Date of Last Survey:ROOSEVELT ISLAND
COLER MEMORIAL HOSPITAL - BLDG S - SPECIAL WING
672001722010Exterior WallsArchitecture Exterior 292,772
672001722010ParapetsArchitecture Exterior 68,147
672001722010RoofArchitecture Exterior 268,356
Total Planned activities for $629,275HHC0003 050
010HHC000412/01/04Date of Last Survey:2601 OCEAN PARKWAY
CONEY ISLAND HOSPITAL - MAIN BLDG
262006022008Exterior WallsArchitecture Exterior 253,461
262006022007ParapetsArchitecture Exterior 136,847
262006022009RoofArchitecture Exterior 590,484
EXPENSE2007CeilingsArchitecture Interior 12,000
Total Planned activities for $992,792HHC0004 010
020HHC000412/01/04Date of Last Survey:2601 OCEAN PARKWAY
CONEY ISLAND HOSPITAL - HAMMETT
CAPITAL2003WiringElectrical Under 600 Volts 48,985
Total Planned activities for $48,985HHC0004 020
030HHC000412/01/04Date of Last Survey:2601 OCEAN PARKWAY
CONEY ISLAND HOSPITAL - POWER PLANT
EXPENSE2006Exterior WallsArchitecture Exterior 11,720
EXPENSE2006ParapetsArchitecture Exterior 4,090
Total Planned activities for $15,810HHC0004 030
Page P - 3
Appendix
FMS ID/ Budget Code
Agency Activity Year
HEALTH AND HOSPITALS CORP.
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
P
010HHC000512/07/04Date of Last Survey:79-01 BROADWAY
ELMHURST HOSPITAL - ZONES A,B,C,D, E, F & ER
EXPENSE2007Exterior WallsArchitecture Exterior 37,519
EXPENSE2007WindowsArchitecture Exterior 2,463,146
EXPENSE2008ParapetsArchitecture Exterior 56,075
EXPENSE2007ParapetsArchitecture Exterior 205,255
EXPENSE2007RoofArchitecture Exterior 21,350
EXPENSE2007RoofArchitecture Exterior 172,768
EXPENSE2008CeilingsArchitecture Interior 128,271
EXPENSE2007CeilingsArchitecture Interior 230,887
EXPENSE2007WiringElectrical Under 600 Volts 410,288
EXPENSE2006BatteriesElectrical Stand-by Power 77,543
EXPENSE2008Energy SourceMechanical Heating 172,948
EXPENSE2007Conversion EquipmentMechanical Heating 215,341
EXPENSE2007DistributionMechanical Heating 196,099
Total Planned activities for $4,387,490HHC0005 010
040HHC000512/08/04Date of Last Survey:79-01 BROADWAY
ELMHURST HOSPITAL - STAFF HOUSE
EXPENSE2009WiringElectrical Under 600 Volts 39,188
Total Planned activities for $39,188HHC0005 040
050HHC000512/08/04Date of Last Survey:79-01 BROADWAY
ELMHURST HOSPITAL - AMBULATORY CARE - ZONE H
CAPITAL2007RoofArchitecture Exterior 66,630
EXPENSE2007CeilingsArchitecture Interior 38,198
EXPENSE2007General LightingElectrical Lighting 97,302
Total Planned activities for $202,130HHC0005 050
010HHC000601/26/04Date of Last Survey:ROOSEVELT ISLAND
GOLDWATER MEMORIAL HOSPITAL - BLDG A
CAPITAL 2009Exterior WallsArchitecture Exterior 827,408
682001722009ParapetsArchitecture Exterior 100,301
682001722009RoofArchitecture Exterior 317,010
Total Planned activities for $1,244,719HHC0006 010
020HHC000601/26/04Date of Last Survey:ROOSEVELT ISLAND
GOLDWATER MEMORIAL HOSPITAL - BLDG B
682001722010Exterior WallsArchitecture Exterior 868,159
682001722010ParapetsArchitecture Exterior 99,395
682001722010RoofArchitecture Exterior 572,633
Total Planned activities for $1,540,187HHC0006 020
Page P - 4
Appendix
FMS ID/ Budget Code
Agency Activity Year
HEALTH AND HOSPITALS CORP.
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
P
030HHC000601/26/04Date of Last Survey:ROOSEVELT ISLAND
GOLDWATER MEMORIAL HOSPITAL - BLDG C
682001722009Exterior WallsArchitecture Exterior 776,774
682001722009ParapetsArchitecture Exterior 149,093
682001722009RoofArchitecture Exterior 36,958
Total Planned activities for $962,825HHC0006 030
040HHC000601/26/04Date of Last Survey:ROOSEVELT ISLAND
GOLDWATER MEMORIAL HOSPITAL - BLDG D
682001722008Exterior WallsArchitecture Exterior 783,861
682001722008ParapetsArchitecture Exterior 142,093
682001722008RoofArchitecture Exterior 454,797
Total Planned activities for $1,380,751HHC0006 040
050HHC000601/26/04Date of Last Survey:ROOSEVELT ISLAND
GOLDWATER MEMORIAL HOSPITAL - BLDG E
682001722008Exterior WallsArchitecture Exterior 736,719
682001722010ParapetsArchitecture Exterior 89,657
682001722010RoofArchitecture Exterior 301,085
Total Planned activities for $1,127,461HHC0006 050
060HHC000601/26/04Date of Last Survey:ROOSEVELT ISLAND
GOLDWATER MEMORIAL HOSPITAL - BLDG F
682001722008Exterior WallsArchitecture Exterior 378,818
682001722008ParapetsArchitecture Exterior 85,686
682001722008RoofArchitecture Exterior 55,525
Total Planned activities for $520,029HHC0006 060
070HHC000601/26/04Date of Last Survey:ROOSEVELT ISLAND
GOLDWATER MEMORIAL HOSPITAL - BLDG G
682001722008Exterior WallsArchitecture Exterior 88,354
682001722008ParapetsArchitecture Exterior 36,243
Total Planned activities for $124,597HHC0006 070
080HHC000601/26/04Date of Last Survey:ROOSEVELT ISLAND
GOLDWATER MEMORIAL HOSPITAL - BLDG H
682001722008Exterior WallsArchitecture Exterior 46,502
682001722008ParapetsArchitecture Exterior 36,243
682001722008RoofArchitecture Exterior 38,946
Total Planned activities for $121,691HHC0006 080
090HHC000601/26/04Date of Last Survey:ROOSEVELT ISLAND
GOLDWATER MEMORIAL HOSPITAL - BLDG J
682001722008Exterior WallsArchitecture Exterior 148,699
682001722008ParapetsArchitecture Exterior 218,761
Page P - 5
Appendix
FMS ID/ Budget Code
Agency Activity Year
HEALTH AND HOSPITALS CORP.
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
P
682001722008RoofArchitecture Exterior 305,989
Total Planned activities for $673,449HHC0006 090
010HHC000701/20/04Date of Last Survey:227 MADISON STREET
GOUVERNEUR HOSPITAL - BLDG 1
682001722008RoofArchitecture Exterior 406,350
EXPENSE2008Interior WallsArchitecture Interior 258,843
EXPENSE2008CeilingsArchitecture Interior 458,084
EXPENSE2008Terminal DevicesMechanical Air Conditioning 57,732
EXPENSE2008Non-Water PipingMechanical Plumbing 72,091
Total Planned activities for $1,253,100HHC0007 010
020HHC000701/20/04Date of Last Survey:34 SPRING STREET
GOUVERNEUR HOSPITAL - JUDSON HC - CLINIC
682001722008Exterior WallsArchitecture Exterior 88,439
682001722008ParapetsArchitecture Exterior 314,696
682001722008RoofArchitecture Exterior 129,190
Total Planned activities for $532,325HHC0007 020
010HHC000811/24/04Date of Last Survey:506 LENOX AVENUE
HARLEM HOSPITAL - M. L. KING PAVILLION
131999792007WindowsArchitecture Exterior 124,569
131999832007ParapetsArchitecture Exterior 98,193
EXPENSE2007CeilingsArchitecture Interior 459,202
EXPENSE2007WiringElectrical Under 600 Volts 136,763
EXPENSE2005DistributionMechanical Heating 410,913
EXPENSE2005Conversion EquipmentMechanical Air Conditioning 511,796
Total Planned activities for $1,741,436HHC0008 010
020HHC000811/24/04Date of Last Survey:15 WEST 136 STREET
HARLEM HOSPITAL - KOUNTZ PAVILLION
CAPITAL2007WindowsArchitecture Exterior 783,515
131999832008RoofArchitecture Exterior 304,981
EXPENSE2008WiringElectrical Under 600 Volts 76,372
EXPENSE2008Motor ControllersElectrical Under 600 Volts 47,277
132002712008DistributionMechanical Heating 129,587
Total Planned activities for $1,341,732HHC0008 020
010HHC000901/28/03Date of Last Survey:451 CLARKSON AVENUE
KINGS COUNTY HOSPITAL CENTER - MAIN BLDG. A,B,C
262006702008Exterior WallsArchitecture Exterior 2,144,796
262006702009WindowsArchitecture Exterior 992,307
262006702008ParapetsArchitecture Exterior 81,351
262006702008RoofArchitecture Exterior 574,421
Page P - 6
Appendix
FMS ID/ Budget Code
Agency Activity Year
HEALTH AND HOSPITALS CORP.
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
P
Total Planned activities for $3,792,875HHC0009 010
020HHC000901/29/03Date of Last Survey:451 CLARKSON AVENUE
KINGS COUNTY HOSPITAL CENTER - BLDG. E
KCH3/K5062006Exterior WallsArchitecture Exterior 1,026,083
292000722007RoofArchitecture Exterior 153,085
292000472007WiringElectrical Under 600 Volts 164,115
6449332007Motor ControllersElectrical Under 600 Volts 47,776
Total Planned activities for $1,391,059HHC0009 020
030HHC000901/29/03Date of Last Survey:451 CLARKSON AVENUE
KINGS COUNTY HOSPITAL CENTER - BLDG G - PSYCHIATRIC
CAPITAL2010Exterior WallsArchitecture Exterior 1,055,024
CAPITAL2010WindowsArchitecture Exterior 382,966
CAPITAL2010ParapetsArchitecture Exterior 101,658
CAPITAL2010RoofArchitecture Exterior 569,828
CAPITAL2010FloorsArchitecture Interior 73,803
CAPITAL2010WiringElectrical Under 600 Volts 95,734
EXPENSE2010General LightingElectrical Lighting 46,911
CAPITAL2010General LightingElectrical Lighting 926,738
Total Planned activities for $3,252,662HHC0009 030
100HHC000901/29/03Date of Last Survey:451 CLARKSON AVENUE
KINGS COUNTY HOSPITAL CENTER - BLDG Z - POWER HOUSE
CAPITAL 2009WindowsArchitecture Exterior 106,876
CAPITAL 2009ParapetsArchitecture Exterior 145,115
CAPITAL 2009FloorsArchitecture Interior 115,543
CAPITAL 2009Interior WallsArchitecture Interior 493,053
EXPENSE2009CeilingsArchitecture Interior 61,726
Total Planned activities for $922,313HHC0009 100
140HHC000901/29/03Date of Last Survey:451 CLARKSON AVENUE
KINGS COUNTY HOSPITAL CENTER - BLDG J - PSYCHIATRIC
CAPITAL2010Exterior WallsArchitecture Exterior 196,481
CAPITAL2010WindowsArchitecture Exterior 126,790
EXPENSE2010ParapetsArchitecture Exterior 102,981
EXPENSE2010RoofArchitecture Exterior 54,371
EXPENSE2010Interior WallsArchitecture Interior 59,116
EXPENSE2010CeilingsArchitecture Interior 58,756
EXPENSE2010GeneratorsElectrical Stand-by Power 65,897
EXPENSE2010Terminal DevicesMechanical Air Conditioning 58,992
CAPITAL2010DistributionMechanical Ventilation 252,310
Total Planned activities for $975,694HHC0009 140
Page P - 7
Appendix
FMS ID/ Budget Code
Agency Activity Year
HEALTH AND HOSPITALS CORP.
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
P
190HHC000901/30/03Date of Last Survey:451 CLARKSON AVENUE
KINGS COUNTY HOSPITAL CENTER - BLDG K5 - STAFF HOUSE
CAPITAL2009Exterior WallsArchitecture Exterior 307,482
CAPITAL2009WindowsArchitecture Exterior 509,367
CAPITAL2009ParapetsArchitecture Exterior 88,730
CAPITAL2009RoofArchitecture Exterior 86,130
CAPITAL2009Interior WallsArchitecture Interior 105,520
CAPITAL2009SwitchgearElectrical Under 600 Volts 60,217
CAPITAL2009WiringElectrical Under 600 Volts 41,987
CAPITAL2009General LightingElectrical Lighting 350,416
Total Planned activities for $1,549,849HHC0009 190
260HHC000901/30/03Date of Last Survey:451 CLARKSON AVENUE
KINGS COUNTY HOSPITAL CENTER - SUPPORT BUILDING
EXPENSE2009Exterior WallsArchitecture Exterior 55,903
Total Planned activities for $55,903HHC0009 260
270HHC000901/30/03Date of Last Survey:451 CLARKSON AVENUE
KINGS COUNTY HOSPITAL CENTER - CENTRAL KITCHEN BUILDING
EXPENSE2009Exterior WallsArchitecture Exterior 54,491
EXPENSE2009FloorsArchitecture Interior 65,012
Total Planned activities for $119,503HHC0009 270
010HHC001012/09/04Date of Last Survey:234 EAST 149TH STREET
LINCOLN HOSPITAL - MAIN HOSPITAL
CAPITAL2008Exterior WallsArchitecture Exterior 484,454
CAPITAL2008ParapetsArchitecture Exterior 76,164
EXPENSE2007RoofArchitecture Exterior 598,329
EXPENSE2007CeilingsArchitecture Interior 610,196
EXPENSE2007Motor ControllersElectrical Under 600 Volts 550,128
EXPENSE2007Arresters/CablingElectrical Lightning Protection 210,108
EXPENSE2007DistributionMechanical Heating 417,930
EXPENSE2007DistributionMechanical Air Conditioning 847,156
EXPENSE2007Sanitary PipingMechanical Plumbing 94,128
EXPENSE2007Storm Drain PipingMechanical Plumbing 60,511
Total Planned activities for $3,949,104HHC0010 010
030HHC001012/09/04Date of Last Survey:234 EAST 149TH STREET
LINCOLN HOSPITAL - GARAGE
CAPITAL2008Exterior WallsArchitecture Exterior 353,596
CAPITAL2008ParapetsArchitecture Exterior 154,116
EXPENSE2008RoofArchitecture Exterior 64,058
CAPITAL2008FloorsArchitecture Interior 355,094
Page P - 8
Appendix
FMS ID/ Budget Code
Agency Activity Year
HEALTH AND HOSPITALS CORP.
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
P
CAPITAL2008CeilingsArchitecture Interior 449,293
EXPENSE2007General LightingElectrical Lighting 103,213
Total Planned activities for $1,479,370HHC0010 030
010HHC001102/09/04Date of Last Survey:1901 FIRST AVENUE
METROPOLITAN HOSPITAL - MAIN BUILDING
372101022008Exterior WallsArchitecture Exterior 104,536
CAPITAL2005WindowsArchitecture Exterior 734,468
372001022008ParapetsArchitecture Exterior 40,076
CAPITAL2007RoofArchitecture Exterior 745,569
EXPENSE2007WiringElectrical Under 600 Volts 478,670
EXPENSE2008GeneratorsElectrical Stand-by Power 65,897
CAPITAL2008Energy SourceMechanical Heating 93,249
CAPITAL2008Conversion EquipmentMechanical Heating 120,042
Total Planned activities for $2,382,507HHC0011 010
030HHC001102/09/04Date of Last Survey:1901 FIRST AVENUE
METROPOLITAN HOSPITAL - MENTAL HEALTH
CAPITAL2005RoofArchitecture Exterior 72,190
Total Planned activities for $72,190HHC0011 030
010HHC001310/25/05Date of Last Survey:3424 KOSSUTH AVE. & 210 ST.
NORTH CENTRAL BRONX HOSPITAL -
CAPITAL2007RoofArchitecture Exterior 322,386
EXPENSE2008CeilingsArchitecture Interior 4,802
EXPENSE2008CeilingsArchitecture Interior 18,759
EXPENSE2008DistributionMechanical Ventilation 13,295
Total Planned activities for $359,243HHC0013 010
060HHC001403/09/04Date of Last Survey:82-68 164TH STREET
QUEENS HOSPITAL - NURSES SCHOOL - N
342003022008WindowsArchitecture Exterior 239,817
342003022007CeilingsArchitecture Interior 12,787
CAPITAL2007WiringElectrical Under 600 Volts 31,449
Total Planned activities for $284,053HHC0014 060
100HHC001403/08/04Date of Last Survey:82-68 164TH STREET
QUEENS HOSPITAL - POWER PLANT - E
342005012007Exterior WallsArchitecture Exterior 194,870
342005012007WindowsArchitecture Exterior 130,951
342005012007RoofArchitecture Exterior 69,261
Total Planned activities for $395,082HHC0014 100
110HHC001403/08/04Date of Last Survey:82-68 164TH STREET
QUEENS HOSPITAL - MAINTENANCE - F
Page P - 9
Appendix
FMS ID/ Budget Code
Agency Activity Year
HEALTH AND HOSPITALS CORP.
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
P
342005012008Exterior WallsArchitecture Exterior 129,441
342005012008ParapetsArchitecture Exterior 44,533
342005012008RoofArchitecture Exterior 142,813
Total Planned activities for $316,787HHC0014 110
010HHC001611/30/04Date of Last Survey:760 BROADWAY
WOODHULL MEDICAL CENTER - MAIN
EXPENSE2007Exterior WallsArchitecture Exterior 102,784
EXPENSE2007ParapetsArchitecture Exterior 54,216
6410012008FloorsArchitecture Interior 51,129
6410012007CeilingsArchitecture Interior 89,475
6410022007DistributionMechanical Heating 98,000
6410022007H/C Water PipingMechanical Plumbing 278,643
Total Planned activities for $674,247HHC0016 010
010HHC001710/26/05Date of Last Survey:100 NORTH PORTLAND AVENUE
CUMBERLAND NFCC - BLDG B
EXPENSE2008Exterior WallsArchitecture Exterior 10,182
272002702007WindowsArchitecture Exterior 569,061
272002702007ParapetsArchitecture Exterior 40,930
272002702007RoofArchitecture Exterior 126,950
EXPENSE2007Interior WallsArchitecture Interior 10,505
Total Planned activities for $757,628HHC0017 010
020HHC001710/26/05Date of Last Survey:100 NORTH PORTLAND AVENUE
CUMBERLAND NFCC - BLDG C
6410002007Interior WallsArchitecture Interior 10,408
CAPITAL2008WiringElectrical Under 600 Volts 70,917
6410002008DistributionMechanical Heating 22,836
6410002008DistributionMechanical Air Conditioning 27,774
6410002007Heat RejectionMechanical Air Conditioning 7,528
Total Planned activities for $139,463HHC0017 020
010HHC001803/01/04Date of Last Survey:1225 GERARD AVE.
MORRISIANA NFCC - MAIN BLDG.
EXPENSE2007WindowsArchitecture Exterior 87,206
CAPITAL2008GeneratorsElectrical Stand-by Power 65,897
Total Planned activities for $153,103HHC0018 010
020HHC001803/01/04Date of Last Survey:1225 GERARD AVE.
MORRISIANA NFCC - ANNEX
EXPENSE2007Exterior WallsArchitecture Exterior 104,614
Total Planned activities for $104,614HHC0018 020
Page P - 10
Appendix
FMS ID/ Budget Code
Agency Activity Year
HEALTH AND HOSPITALS CORP.
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
P
Total Planned Activities for : $59,839,203HEALTH AND HOSPITALS CORP.
Total Required for "State of Good Repair" for : HEALTH AND HOSPITALS CORP. $178,112,584
Page P - 11
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF SANITATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
Q
027DBS002510/30/01Date of Last Survey:HUDSON RIVER, WEST 57TH STREET
BULKHEAD, PIER 97 -
S216-2352005Pile Supported WallBulkheads Structural 80,345
Total Planned activities for $80,345DBS0025 027
020DGSP00501/03/06Date of Last Survey:PIERS 36, EAST RIVER
SANITATION DIST. 3/3A GARAGE -
S136-264B2010RoofArchitecture Exterior 154,035
S136-383A2010DistributionMechanical Ventilation 31,937
Total Planned activities for $185,972DGSP005 020
000DOS000104/12/04Date of Last Survey:91ST ST. & EAST RIVER
E. 91ST MARINE TRANSFER STATION -
S216-4012008RoofArchitecture Exterior 108,785
S216-4012008General LightingElectrical Lighting 42,305
Total Planned activities for $151,090DOS0001 000
010DOS000110/20/03Date of Last Survey:91ST ST. & EAST RIVER
E. 91ST MARINE TRANSFER STATION - BARGE DOCKS
S216-4012008DeckPiers Structural 38,112
S216-4012008Pile CapsPiers Structural 42,507
S216-4012008Piles and BracingPiers Structural 66,899
S216-4012008FacingPiers Fender 71,674
Total Planned activities for $219,192DOS0001 010
000DOS000803/13/02Date of Last Survey:BAY 41ST ST. AND GRAVESEND BAY
S.W.BROOKLYN MARINE TRANSFER STA -
S216-3992008Exterior WallsArchitecture Exterior 310,450
Total Planned activities for $310,450DOS0008 000
010DOS000811/03/03Date of Last Survey:BAY 41ST ST. AND GRAVESEND BAY
S.W.BROOKLYN MARINE TRANSFER STA - BARGE DOCKS
S216-3992008FacingPiers Fender 643,118
Total Planned activities for $643,118DOS0008 010
000DOS000906/02/03Date of Last Survey:HAMILTON AVE. AT GOWANUS BAY
HAMILTON AVE MARINE TRANSFER STA -
S216-4032008Exterior WallsArchitecture Exterior 172,746
S216-4032008WindowsArchitecture Exterior 163,028
S216-4032008RoofArchitecture Exterior 124,107
S216-4032008FloorsArchitecture Interior 50,877
S216-4032008General LightingElectrical Lighting 65,814
S216-4032008DistributionMechanical Ventilation 141,087
Total Planned activities for $717,659DOS0009 000
Page Q - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF SANITATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
Q
010DOS000910/23/03Date of Last Survey:HAMILTON AVE & GOWANUS BAY
HAMILTON AVENUE MTS - BARGE DOCKS
S216-4032008FacingPiers Fender 88,130
Total Planned activities for $88,130DOS0009 010
BN3DOS000B11/03/03Date of Last Survey:BAY 41ST. ST. & GRAVESEND BAY
S.W. BROOKLYN DOS FACILITY - CONCRETE WHARF
S216-3992008Sheet PilesBulkheads Structural 103,747
S216-3992008FacingBulkheads Fender 75,501
Total Planned activities for $179,248DOS000B BN3
MH3DOS000B10/22/03Date of Last Survey:GANESVOORT ST. & HUDSON RIVER
BULKHEAD -
S216-2352005Relieving Platform TopBulkheads Structural 54,183
S216-2352005SurfaceBulkheads Backfill 39,233
S216-2352005Wales and ChocksBulkheads Fender 71,185
Total Planned activities for $164,601DOS000B MH3
QN1DOS000B10/28/04Date of Last Survey:31 ST. & FLUSHING BAY CROSSWAY
NORTH SHORE MARINE TRANSFER STAT - REVETMENT
S216-4022008RevetmentBulkheads Structural 312,068
Total Planned activities for $312,068DOS000B QN1
000DOS001012/20/04Date of Last Survey:31st AVE. & FLUSHING
NORTH SHORE MARINE TRANSFER STA. -
S216-4022008Exterior WallsArchitecture Exterior 78,671
S216-4022008WindowsArchitecture Exterior 302,138
S216-4022008ParapetsArchitecture Exterior 226,644
S216-4022008RoofArchitecture Exterior 106,651
S216-4022008FloorsArchitecture Interior 76,052
S216-4022008SwitchgearElectrical Under 600 Volts 80,512
S216-4022008General LightingElectrical Lighting 59,215
Total Planned activities for $929,883DOS0010 000
010DOS001010/28/04Date of Last Survey:FLUSHING BAY
NORTH SHORE MARINE TRANSFER STA. - BARGE DOCKS
S216-4022008FacingPiers Fender 144,796
Total Planned activities for $144,796DOS0010 010
020DOS001203/22/05Date of Last Survey:S. OF VICTORY BLVD.
FRESH KILLS II - EQUIPMENT WASH BLDG.
S136-264B2011RoofArchitecture Exterior 68,499
Total Planned activities for $68,499DOS0012 020
000DOS001503/21/05Date of Last Survey:58-73 53RD AVE.
QUEENS 6 GARAGE - FORMER BETTS AVE. INCINERATOR
Page Q - 2
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF SANITATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
Q
S136-3322006ParapetsArchitecture Exterior 36,343
S136-264B2010RoofArchitecture Exterior 208,418
S136-283B2010DistributionMechanical Heating 63,443
Total Planned activities for $308,204DOS0015 000
000DOS001812/15/04Date of Last Survey:10601 AVE. D AT 105 WALK
CIOFFE REPAIR SHOP -
S136-283B2008Conversion EquipmentMechanical Heating 47,428
Total Planned activities for $47,428DOS0018 000
000DOS001902/13/03Date of Last Survey:52-07 58TH STREET
QUEENS NORTH BORO REPAIR SHOP -
S136-2642008RoofArchitecture Exterior 119,939
Total Planned activities for $119,939DOS0019 000
000DOS002003/21/05Date of Last Survey:52-35 58TH STREET
CENTRAL REPAIR SHOP -
S136-3882009Exterior WallsArchitecture Exterior 113,408
S136-264B2009RoofArchitecture Exterior 167,391
S136-383A2010Terminal DevicesMechanical Heating 79,206
S136-383A2010Conversion EquipmentMechanical Air Conditioning 241,606
S136-383A2010DistributionMechanical Ventilation 1,109,451
Total Planned activities for $1,711,062DOS0020 000
000DOS002202/14/03Date of Last Survey:120-15 31ST. AVENUE
QUEENS 7 GARAGE -
S136-3882010Exterior WallsArchitecture Exterior 78,568
S136-2642004RoofArchitecture Exterior 67,214
Total Planned activities for $145,782DOS0022 000
000DOS002305/28/03Date of Last Survey:92 BROOK STREET
STATEN ISLAND 1 GARAGE -
S136-264B2008ParapetsArchitecture Exterior 172,703
S136-264B2008RoofArchitecture Exterior 315,649
S136-3742008Energy SourceMechanical Heating 148,436
S136-3742008Conversion EquipmentMechanical Heating 58,673
S136-3742008DistributionMechanical Heating 44,291
S136-3742008Terminal DevicesMechanical Heating 94,980
Total Planned activities for $834,732DOS0023 000
000DOS002504/15/04Date of Last Survey:1000 WEST SERVICE ROAD
STATEN ISLAND 3 GARAGE -
S136-3882010Exterior WallsArchitecture Exterior 139,181
S136-264B2010RoofArchitecture Exterior 77,506
Total Planned activities for $216,687DOS0025 000
Page Q - 3
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF SANITATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
Q
000DOS002612/13/04Date of Last Survey:2500 RICHMOND AVENUE
STATEN ISLAND 2 GARAGE/BORO OFFC -
S136-3882010Exterior WallsArchitecture Exterior 151,436
S136-3852010WindowsArchitecture Exterior 53,246
S136-264B2010RoofArchitecture Exterior 340,508
Total Planned activities for $545,190DOS0026 000
000DOS002912/14/04Date of Last Survey:301 WEST 215TH STREET
MANHATTAN 12 GARAGE -
S136-3882010WindowsArchitecture Exterior 44,391
S136-264A2007RoofArchitecture Exterior 486,589
Total Planned activities for $530,980DOS0029 000
000DOS003012/14/04Date of Last Survey:5100 1ST AVENUE
BROOKLYN 7/10 GARAGE -
S136-374B2007Conversion EquipmentMechanical Heating 147,133
Total Planned activities for $147,133DOS0030 000
000DOS003402/21/03Date of Last Survey:153-67 146 AVENUE
QUEENS 13 GARAGE -
S136-264B2011RoofArchitecture Exterior 55,149
S136-283A2011DistributionMechanical Ventilation 171,815
Total Planned activities for $226,964DOS0034 000
000DOS003607/12/06Date of Last Survey:1824 SHORE PARKWAY
BROOKLYN 11 SANITATION GARAGE - BK S11
S136-3852009WindowsArchitecture Exterior 54,835
S136-383A2009DistributionMechanical Ventilation 47,626
Total Planned activities for $102,461DOS0036 000
000DOS003707/05/06Date of Last Survey:1635 EAST 233RD ST.
BRONX DIST. 12 SANITATION GARAGE -
S136-3882009Exterior WallsArchitecture Exterior 38,002
S136-264B2009ParapetsArchitecture Exterior 82,090
S136-264B2009RoofArchitecture Exterior 110,824
Total Planned activities for $230,916DOS0037 000
000DOS003902/21/03Date of Last Survey:75-05 DOUGLASTON PKWY.
QUEENS 11 GARAGE -
S136-264B2011RoofArchitecture Exterior 452,866
Total Planned activities for $452,866DOS0039 000
000DOS004007/12/06Date of Last Survey:105-01 FOSTER AVE.
BROOKLYN 17/18 SANITATION GARAGE -
S136-3852009WindowsArchitecture Exterior 69,930
S136-264B2009RoofArchitecture Exterior 173,116
Page Q - 4
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF SANITATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
Q
S136-3832008DistributionMechanical Ventilation 59,104
Total Planned activities for $302,150DOS0040 000
000DOS004104/01/03Date of Last Survey:2 BLOOMFIELD STREET
MANHATTAN 2, 4 GARAGE - GANSEVOORT
S136-2642003RoofArchitecture Exterior 165,375
Total Planned activities for $165,375DOS0041 000
000DOS004403/27/03Date of Last Survey:343 E. 99TH ST.
MANHATTAN 11 GARAGE -
S136-3322006Exterior WallsArchitecture Exterior 411,108
S136-3322006ParapetsArchitecture Exterior 144,519
S136-264B2008RoofArchitecture Exterior 35,396
S136-3322006FloorsArchitecture Interior 143,317
Total Planned activities for $734,340DOS0044 000
000DOS004802/11/03Date of Last Survey:34-28 21ST ST.
QUEENS 1 GARAGE - QW1
S136-264B2009RoofArchitecture Exterior 64,108
Total Planned activities for $64,108DOS0048 000
000DOS004902/24/03Date of Last Survey:130-23 150TH AVE.
QUEENS 8/10/12 GARAGE - BERGENLANDING
S136-264B2011RoofArchitecture Exterior 50,225
S136-383A2011DistributionMechanical Ventilation 65,017
Total Planned activities for $115,242DOS0049 000
000DOS005003/26/03Date of Last Survey:803 FORBELL ST.
BROOKLYN LOT CLEANING GARAGE -
S136-2642005RoofArchitecture Exterior 457,089
Total Planned activities for $457,089DOS0050 000
000DOS005103/25/03Date of Last Survey:127 2ND AVENUE
BROOKLYN 6 GARAGE - BK S6
S136-3852008WindowsArchitecture Exterior 181,705
S136-264B2008ParapetsArchitecture Exterior 164,105
S136-264B2008RoofArchitecture Exterior 240,909
Total Planned activities for $586,719DOS0051 000
000DOS005303/24/03Date of Last Survey:5602 19TH AVE.
BROOKLYN 12 GARAGE - MAIN BUILDING
S136-264B2011ParapetsArchitecture Exterior 386,833
S136-264B2011RoofArchitecture Exterior 158,338
S136-383A2011Terminal DevicesMechanical Heating 153,186
S136-383A2011Conversion EquipmentMechanical Air Conditioning 160,716
S136-383A2011Terminal DevicesMechanical Air Conditioning 146,941
Page Q - 5
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF SANITATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
Q
S136-383A2011Exhaust FansMechanical Ventilation 47,113
Total Planned activities for $1,053,127DOS0053 000
000DOS005403/21/03Date of Last Survey:356 WINTHROP STREET
BROOKLYN 14 GARAGE - WINTHROP ST.
S136-3322004Exterior WallsArchitecture Exterior 68,485
S136-3322004WindowsArchitecture Exterior 154,574
S136-3322004RoofArchitecture Exterior 272,770
S136-3322004FloorsArchitecture Interior 37,716
S136-3322003FloorsArchitecture Interior 160,767
S136-3322003Interior WallsArchitecture Interior 50,980
S136-3322004Terminal DevicesMechanical Heating 114,377
S136-3322004Conversion EquipmentMechanical Air Conditioning 400,359
S136-3322004Terminal DevicesMechanical Air Conditioning 62,373
Total Planned activities for $1,322,401DOS0054 000
000DOS005503/26/03Date of Last Survey:922 GEORGIA AVE.
BROOKLYN 16 GARAGE - GEORGIA AVE.
S136-3852011WindowsArchitecture Exterior 284,259
S136-2642008RoofArchitecture Exterior 175,133
S136-383A2011Arresters/CablingElectrical Lightning Protection 103,161
S136-383A2011DistributionMechanical Heating 43,881
Total Planned activities for $606,434DOS0055 000
000DOS005603/31/03Date of Last Survey:800-850 ZEREGA AVE.
BRONX 9/10 GARAGE - BRONX BOROUGH REPAIR SHOP
S136-3882011Exterior WallsArchitecture Exterior 51,567
S136-3852011WindowsArchitecture Exterior 80,587
S136-264B2011ParapetsArchitecture Exterior 315,932
S136-264B2011RoofArchitecture Exterior 367,167
S136-383A2011DistributionMechanical Heating 147,497
S136-383A2011Terminal DevicesMechanical Heating 63,260
Total Planned activities for $1,026,010DOS0056 000
010DOS005603/31/03Date of Last Survey:800-850 ZEREGA AVE.
BRONX DISTRICT GARAGE 11 -
S136-3882011Exterior WallsArchitecture Exterior 103,134
S136-264B2011ParapetsArchitecture Exterior 56,868
S136-264B2011RoofArchitecture Exterior 83,499
S136-383A2011Terminal DevicesMechanical Heating 187,589
Total Planned activities for $431,090DOS0056 010
000DOS005812/17/04Date of Last Survey:640 W. 26 ST
MANHATTAN BOROUGH REPAIR SHOP -
Page Q - 6
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPARTMENT OF SANITATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
Q
S136-264B2010RoofArchitecture Exterior 284,738
Total Planned activities for $284,738DOS0058 000
000DOS005912/21/04Date of Last Survey:48-01 58 ROAD
QUEENS - WEST DISTRICT 5 GARAGE -
S136-264B2011ParapetsArchitecture Exterior 56,690
S136-264B2011RoofArchitecture Exterior 218,726
Total Planned activities for $275,416DOS0059 000
010DOS005912/21/04Date of Last Survey:58-02 48 STREET
QUEENS WEST 5-A BROOM GARAGE -
S136-264B2011ParapetsArchitecture Exterior 52,796
S136-264B2011RoofArchitecture Exterior 72,757
Total Planned activities for $125,553DOS0059 010
000DOS006012/14/04Date of Last Survey:341 WEST 215 STREET
MANHATTAN 8 GARAGE - (FORMER INCINERATOR)
S136-264B2011ParapetsArchitecture Exterior 38,792
S136-264B2011RoofArchitecture Exterior 235,459
Total Planned activities for $274,251DOS0060 000
000DOS006205/04/06Date of Last Survey:E 93 RD ST TO NO END MARINE XFER
LOW-LEVEL RELIEVING PLATFORM - TIMBER PILE SUPPORTED BULKHEAD
S216-4012008Relieving Platform TopBulkheads Structural 43,643
Total Planned activities for $43,643DOS0062 000
Total Planned Activities for : $17,683,081DEPARTMENT OF SANITATION
Total Required for "State of Good Repair" for : DEPARTMENT OF SANITATION $73,455,648
Page Q - 7
AppendixDEPARTMENT OF TRANSPORTATION
FMS ID/ Budget Code
Agency Activity YearType of Work
Agency Activity Funding
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
R
000DOT0090QUEENS BOROUGH HALL - GARAGE - 01/23/03Date of Last Survey:80-25 126TH STREET
841 TF18-20122008Exterior WallsArchitecture Exterior 198,652
841 TF18-20122008RoofArchitecture Exterior 265,722
841 TF18-20122008FloorsArchitecture Interior 270,699
841 TF18-20122008CeilingsArchitecture Interior 222,554
841 TF18-20122008Hot Water HeaterMechanical Plumbing 35,917
Total Planned Activities for $993,544DOT0090 000
000DOT0093HARLEM RIVER BRIDGE SHOP - GARAGE 101/01/06Date of Last Survey:300 W. 206TH STREET
850 HWKF1162007Average Cost Method
1,813,791
Total Planned Activities for $1,813,791DOT0093 000
010DOT0093HARLEM RIVER BRIDGE SHOP - GARAGE 201/01/06Date of Last Survey:300 W. 206TH STREET
850 HWKF1162007Average Cost Method
666,775
Total Planned Activities for $666,775DOT0093 010
000DOT0094W. 158 ST MAINT.&REPAIR FACILITY - 04/06/06Date of Last Survey:672 W. 158TH STREET
850 HWMF0322007Exterior WallsArchitecture Exterior 519,508
850 HWMF0322007ParapetsArchitecture Exterior 181,038
850 HWMF0322007Interior WallsArchitecture Interior 110,817
Total Planned Activities for $811,363DOT0094 000
000DOT0096MASPETH VEHICLE MAINTENANCE - 01/09/04Date of Last Survey:58-50 57TH ROAD
841 HWQF0362007WindowsArchitecture Exterior 967,831
841 HWQF0362007ParapetsArchitecture Exterior 83,736
841 HWQF0362007RoofArchitecture Exterior 117,001
841 HWQF0362007FloorsArchitecture Interior 100,386
841 HWQF0362007Interior WallsArchitecture Interior 81,010
841 HWQF0362007Terminal DevicesMechanical Heating 120,152
841 HWQF0362007Conversion EquipmentMechanical Air Conditioning 42,333
Total Planned Activities for $1,512,449DOT0096 000
000DOT0097WEBSTER AVENUE FLEET SERVICES - MAINTENANCE & REPAIR SHOP06/02/04Date of Last Survey:2144 WEBSTER AVENUE
850 HWXF030A2007RoofArchitecture Exterior 36,829
Total Planned Activities for $36,829DOT0097 000
000DOT0100KEW LOOP YARD GARAGE - 01/01/06Date of Last Survey:135TH PARK DRIVE EAST
R - 1Page
AppendixDEPARTMENT OF TRANSPORTATION
FMS ID/ Budget Code
Agency Activity YearType of Work
Agency Activity Funding
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
R
841 HWQF0372007Average Cost Method
562,464
Total Planned Activities for $562,464DOT0100 000
000DOT0120JEROME 190TH ST. GARAGE - 02/19/04Date of Last Survey:JEROME AVE. & 190TH ST.
850 TF189801E2007Exterior WallsArchitecture Exterior 547,691
850 TF189801E2007WindowsArchitecture Exterior 84,897
850 TF189801E2007RoofArchitecture Exterior 190,286
850 TF189801E2007FloorsArchitecture Interior 36,113
850 TF189801E2007CeilingsArchitecture Interior 339,243
Total Planned Activities for $1,198,230DOT0120 000
020DOT0124HAMILTON AVE. ASPHALT PLANT - STORAGE01/01/06Date of Last Survey:448 HAMILTON AVENUE
841 HWKF20072007Average Cost Method
147,827
Total Planned Activities for $147,827DOT0124 020
000DOT0126GLENDALE YARD - BLDG. 1 (SHOPS & OFFICES)11/03/05Date of Last Survey:69-46 SYBILLA STREET
850 HWQF20022007WindowsArchitecture Exterior 74,607
Total Planned Activities for $74,607DOT0126 000
020DOT0126GLENDALE YARD - BLDG. 7 (GARAGE & STORAGE)11/03/05Date of Last Survey:69-46 SYBILLA STREET
850 HWQF20022007Exterior WallsArchitecture Exterior 47,495
850 HWQF20022007WindowsArchitecture Exterior 36,960
850 HWQF20022007CeilingsArchitecture Interior 41,389
Total Planned Activities for $125,844DOT0126 020
030DOT0126GLENDALE YARD - BLDG. 2 (GARAGE)11/03/05Date of Last Survey:69-46 SYBILLA STREET
850 HWQF20022007WindowsArchitecture Exterior 36,346
850 HWQF20022007RoofArchitecture Exterior 130,512
Total Planned Activities for $166,858DOT0126 030
050DOT0126GLENDALE YARD - BLDG. 601/01/06Date of Last Survey:69-46 SYBILLA STREET
841 HWQF20022007Average Cost Method
83,454
Total Planned Activities for $83,454DOT0126 050
060DOT0126GLENDALE YARD - BLDG. 501/01/06Date of Last Survey:69-46 SYBILLA STREET
841 HWQF20022007Average Cost Method
91,689
Total Planned Activities for $91,689DOT0126 060
R - 2Page
AppendixDEPARTMENT OF TRANSPORTATION
FMS ID/ Budget Code
Agency Activity YearType of Work
Agency Activity Funding
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
R
070DOT0126GLENDALE YARD - BLDG. 801/01/06Date of Last Survey:69-46 SYBILLA STREET
841 HWQF20022007Average Cost Method
60,256
Total Planned Activities for $60,256DOT0126 070
080DOT0126GLENDALE YARD - BLDG. 901/01/06Date of Last Survey:69-46 SYBILLA STREET
841 HWQF20022007Average Cost Method
28,923
Total Planned Activities for $28,923DOT0126 080
Total Planned Activities for: $8,374,903DEPARTMENT OF TRANSPORTATION Facilities
Total Required for "State of Good Repair" for: DEPARTMENT OF TRANSPORTATION Facilities $79,870,653
R - 3Page
DEPARTMENT OF TRANSPORTATIONFMS ID/ Budget Code
Agency Activity YearType of Work
Agency Activity Funding
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Appendix R
NASSAU STREET BRIDGE DOT0018278I 11/21/03Date of Last Survey:
HBKNASSAU2006Brngs,Ancr Blts,PadsAbutments 72,029Bridge Structural
HBKNASSAU2006Joint with DeckAbutments 42,835Bridge Structural
HBKNASSAU2006JointsSuperstructure 214,174Bridge Structural
HBKNASSAU2006Primary MemberSuperstructure 144,584Bridge Structural
HBKNASSAU2006Secondary MemberSuperstructure 62,152Bridge Structural
Total Planned Activities for $535,774DOT0018
GERRITSEN INLET BRIDGE DOT0021BELT SHORE PKWAY(BSP) 11/30/04Date of Last Survey:
HBK6432009Stem (breastwall)Abutments 91,523Bridge Structural
HBK6432009Pier,ColumnsPiers 1,788,367Bridge Structural
HBK6432009Stem,Solid PierPiers 1,125,385Bridge Structural
HBK6432009CurbsDeck Elements 64,006Bridge Structural
HBK6432009Sidewalks/FasciasDeck Elements 144,583Bridge Structural
HBK6432009Deck,StructuralSuperstructure 290,252Bridge Structural
HBK6432009Primary MemberSuperstructure 895,038Bridge Structural
HBK6432009Secondary MemberSuperstructure 160,845Bridge Structural
Total Planned Activities for $4,559,999DOT0021
MILL BASIN BRIDGE DOT0022BSP X-ING MILL BASIN 01/10/05Date of Last Survey:
HBK10232010Pier ProtectionStream Channel 933,230Bridge Structural
HBK10232010Cap BeamPiers 83,858Bridge Structural
HBK10232010Pier,ColumnsPiers 517,693Bridge Structural
HBK10232010Stem,Solid PierPiers 137,070Bridge Structural
HBK10232010Brngs,Ancr Blts,PadsPiers 492,878Bridge Structural
HBK10232010Sidewalks/FasciasDeck Elements 62,298Bridge Structural
HBK10232010Wearing SurfaceDeck Elements 46,253Bridge Structural
HBK10232010Deck,StructuralSuperstructure 821,620Bridge Structural
HBK10232010JointsSuperstructure 97,866Bridge Structural
HBK10232010Primary MemberSuperstructure 744,883Bridge Structural
HBK10232010Machinery BrakeDrive 84,286Bridge Electrical
HBK10232010Motor BrakeDrive 50,543Bridge Electrical
HBK10232010ConduitRaceway 207,961Bridge Electrical
HBK10232010Counter WeightBascule 434,169Bridge Mechanical
HBK10232010HousesBascule 81,636Bridge Mechanical
HBK10232010Lock BarsBascule 230,947Bridge Mechanical
HBK10232010Main Drive SystemBascule 922,864Bridge Mechanical
Total Planned Activities for $5,950,055DOT0022
R - 4Page
DEPARTMENT OF TRANSPORTATIONFMS ID/ Budget Code
Agency Activity YearType of Work
Agency Activity Funding
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Appendix R
PAERDEGAT BASIN BRIDGE DOT0023BELT SHORE PKWAY 11/21/03Date of Last Survey:
HBK10242008Pier ProtectionStream Channel 432,447Bridge Structural
HBK10242008Pier,ColumnsPiers 147,539Bridge Structural
HBK10242008Brngs,Ancr Blts,PadsPiers 1,237,927Bridge Structural
HBK10242008PedestalsPiers 122,599Bridge Structural
HBK10242008Railings/ParapetsDeck Elements 62,995Bridge Structural
HBK10242008Deck,StructuralSuperstructure 1,035,689Bridge Structural
HBK10242008JointsSuperstructure 726,124Bridge Structural
HBK10242008Primary MemberSuperstructure 356,296Bridge Structural
HBK10242008Secondary MemberSuperstructure 76,580Bridge Structural
Total Planned Activities for $4,198,196DOT0023
BROOKLYN BRIDGE DOT0036EAST RIVER - BQE 01/01/06Date of Last Survey:
BRC270C,S,T2009 281,500,000Bridge Structural
Total Planned Activities for $281,500,000DOT0036
MANHATTAN BRIDGE DOT0037EAST RIVER - BQE 01/01/06Date of Last Survey:
BRC156A,R,S22009 280,920,000Bridge Structural
Total Planned Activities for $280,920,000DOT0037
WILLIAMSBURG BRIDGE DOT0038EAST RIVER, FDR DRIVE 01/01/06Date of Last Survey:
BRC253S,CC2007 10,000,000Bridge Structural
Total Planned Activities for $10,000,000DOT0038
QUEENSBORO BRIDGE DOT0039EAST RIVER, FDR DRIVE 01/01/06Date of Last Survey:
BRC231C,S2011 201,530,000Bridge Structural
Total Planned Activities for $201,530,000DOT0039
WILLIS AVE. BRIDGE DOT0040HARLEM RIVER, WILLIS AVE. 02/02/06Date of Last Survey:
BRCR0762007Cap BeamPiers 92,637Bridge Structural
BRCR0762007Pier,ColumnsPiers 28,746Bridge Structural
BRCR0762007Pier,ColumnsPiers 111,504Bridge Structural
BRCR0762007Stem,Solid PierPiers 75,744Bridge Structural
BRCR0762007Brngs,Ancr Blts,PadsPiers 98,208Bridge Structural
BRCR0762007Mono Deck SurfaceDeck Elements 52,504Bridge Structural
BRCR0762007Railings/ParapetsDeck Elements 23,532Bridge Structural
BRCR0762007Railings/ParapetsDeck Elements 40,731Bridge Structural
R - 5Page
DEPARTMENT OF TRANSPORTATIONFMS ID/ Budget Code
Agency Activity YearType of Work
Agency Activity Funding
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Appendix R
BRCR0762007Wearing SurfaceDeck Elements 81,236Bridge Structural
BRCR0762007Deck,StructuralSuperstructure 163,184Bridge Structural
BRCR0762007Deck,StructuralSuperstructure 339,325Bridge Structural
BRCR0762007Primary MemberSuperstructure 599,880Bridge Structural
BRCR0762007Primary MemberSuperstructure 1,019,983Bridge Structural
BRCR0762007Secondary MemberSuperstructure 766,843Bridge Structural
BRCR0762007Secondary MemberSuperstructure 386,813Bridge Structural
BRCR0762007Dist Equip & Motor ControllerElectrical Power 258,604Bridge Electrical
BRCR0762007Submarine Control CablesRaceway 434,666Bridge Electrical
BRCR0762007Lighting DevicesLighting 79,511Bridge Electrical
BRCR0762007Center LatchSwing 96,426Bridge Mechanical
BRCR0762007End LiftSwing 107,338Bridge Mechanical
BRCR0762007Main Drive SystemSwing 124,839Bridge Mechanical
BRCR0762007Traffic DevicesSwing 324,000Bridge Mechanical
Total Planned Activities for $5,306,254DOT0040
THIRD AVE. BRIDGE DOT0041HARLEM RIVER, HARLEM RIV DR. 09/26/96Date of Last Survey:
HBX6632006Brngs,Ancr Blts,PadsAbutments 49,194Bridge Structural
HBX6632006Stem (breastwall)Abutments 222,976Bridge Structural
HBX6632006WallsWingwalls 83,763Bridge Structural
HBX6632006Cap BeamPiers 180,441Bridge Structural
HBX6632006Pier,ColumnsPiers 337,089Bridge Structural
HBX6632006Wearing SurfaceDeck Elements 177,371Bridge Structural
HBX6632006Deck,StructuralSuperstructure 422,474Bridge Structural
HBX6632006Primary MemberSuperstructure 795,373Bridge Structural
HBX6632006Primary MemberSuperstructure 89,883Bridge Structural
HBX6632006Secondary MemberSuperstructure 89,883Bridge Structural
HBX6632006Secondary MemberSuperstructure 167,081Bridge Structural
HBX6632006Collector RingRaceway 127,260Bridge Electrical
HBX6632006WiresRaceway 145,107Bridge Electrical
HBX6632006MotorSpan Lock 72,165Bridge Electrical
HBX6632006Traffic SignalTraffic System Electrical 190,924Bridge Electrical
HBX6632006End LiftSwing 54,976Bridge Mechanical
HBX6632006Traffic DevicesSwing 51,214Bridge Mechanical
Total Planned Activities for $3,257,174DOT0041
145TH STREET BRIDGE DOT0043HARLEM RIVER, HARLEM RIV DR. 06/05/02Date of Last Survey:
HBX10292007Bank ProtectionStream Channel 81,473Bridge Structural
HBX10292007Stem,Solid PierPiers 104,631Bridge Structural
R - 6Page
DEPARTMENT OF TRANSPORTATIONFMS ID/ Budget Code
Agency Activity YearType of Work
Agency Activity Funding
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Appendix R
HBX10292007Wearing SurfaceDeck Elements 90,575Bridge Structural
HBX10292007Primary MemberSuperstructure 538,891Bridge Structural
HBX10292007Secondary MemberSuperstructure 96,521Bridge Structural
HBX10292007WiresRaceway 145,107Bridge Electrical
HBX10292007End LiftSwing 517,914Bridge Mechanical
HBX10292007HousesSwing 897,163Bridge Mechanical
HBX10292007Main Drive SystemSwing 1,167,691Bridge Mechanical
HBX10292007Traffic DevicesSwing 623,423Bridge Mechanical
Total Planned Activities for $4,263,389DOT0043
CITY ISLAND BRIDGE DOT0046EASTCHESTER BAY, CITY ISL RD. 11/26/03Date of Last Survey:
HBX11642009WallsWingwalls 97,413Bridge Structural
HBX11642009Railings/ParapetsDeck Elements 115,179Bridge Structural
HBX11642009Wearing SurfaceDeck Elements 47,568Bridge Structural
HBX11642009Deck,StructuralSuperstructure 144,728Bridge Structural
HBX11642009Primary MemberSuperstructure 621,482Bridge Structural
HBX11642009Secondary MemberSuperstructure 445,256Bridge Structural
Total Planned Activities for $1,471,626DOT0046
ROOSEVELT AVE. BRIDGE DOT0049VAN WYCK EXPY, FLUSHING RIV. 12/26/05Date of Last Survey:
HBQ12032009Stem (breastwall)Abutments 56,307Bridge Structural
HBQ12032009WallsWingwalls 62,133Bridge Structural
HBQ12032009Cap BeamPiers 217,340Bridge Structural
HBQ12032009Pier,ColumnsPiers 121,464Bridge Structural
HBQ12032009Stem,Solid PierPiers 59,581Bridge Structural
HBQ12032009Brngs,Ancr Blts,PadsPiers 42,775Bridge Structural
HBQ12032009Wearing SurfaceDeck Elements 511,918Bridge Structural
HBQ12032009Deck,StructuralSuperstructure 142,494Bridge Structural
HBQ12032009Primary MemberSuperstructure 683,632Bridge Structural
HBQ12032009Secondary MemberSuperstructure 683,632Bridge Structural
Total Planned Activities for $2,581,276DOT0049
ROOSEVELT ISLAND BRIDGE DOT0051E RIVER, EAST CHANNEL,36 AVE 02/09/06Date of Last Survey:
HBM11172007Pier ProtectionStream Channel 149,317Bridge Structural
HBM11172007Pier,ColumnsPiers 25,507Bridge Structural
HBM11172007Wearing SurfaceDeck Elements 84,556Bridge Structural
HBM11172007Deck,StructuralSuperstructure 89,062Bridge Structural
HBM11172007Primary MemberSuperstructure 295,911Bridge Structural
HBM11172007Secondary MemberSuperstructure 295,911Bridge Structural
R - 7Page
DEPARTMENT OF TRANSPORTATIONFMS ID/ Budget Code
Agency Activity YearType of Work
Agency Activity Funding
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Appendix R
HBM11172007Vertical Lift TowerMovable Bridges 148,198Bridge Structural
HBM11172007Control ConsoleControl System Electrical 59,333Bridge Electrical
HBM11172007WiringRaceway 1,516,291Bridge Electrical
HBM11172007Counter WeightVertical Lift 47,910Bridge Mechanical
HBM11172007ElevatorsVertical Lift 92,196Bridge Mechanical
HBM11172007SheavesVertical Lift 74,461Bridge Mechanical
Total Planned Activities for $2,878,653DOT0051
RIKERS ISLAND BRIDGE DOT0052RIKERS ISL CHANNEL 11/22/04Date of Last Survey:
BRC289D2006Brngs,Ancr Blts,PadsAbutments 63,205Bridge Structural
BRC289D2006Railings/ParapetsDeck Elements 251,440Bridge Structural
BRC289D2006Wearing SurfaceDeck Elements 950,840Bridge Structural
BRC289D2006Deck,StructuralSuperstructure 1,146,825Bridge Structural
BRC289D2006JointsSuperstructure 76,497Bridge Structural
BRC289D2006Primary MemberSuperstructure 1,973,385Bridge Structural
BRC289D2006Secondary MemberSuperstructure 130,506Bridge Structural
Total Planned Activities for $4,592,698DOT0052
GRAND CONCOURSE BRIDGE DOT0062167TH ST 11/29/04Date of Last Survey:
HBX11042006BackwallAbutments 445,349Bridge Structural
HBX11042006Pier,ColumnsPiers 163,459Bridge Structural
HBX11042006Stem,Solid PierPiers 72,536Bridge Structural
HBX11042006Deck,StructuralSuperstructure 107,042Bridge Structural
HBX11042006Primary MemberSuperstructure 133,233Bridge Structural
Total Planned Activities for $921,619DOT0062
11TH AVE VIADUCT (RAMP) DOT0066WEST 33 STREET 12/08/04Date of Last Survey:
HBMC0372008Brngs,Ancr Blts,PadsAbutments 61,509Bridge Structural
HBM11862008Brngs,Ancr Blts,PadsAbutments 38,415Bridge Structural
HBM11852008Joint with DeckAbutments 57,113Bridge Structural
HBM11852008Stem (breastwall)Abutments 56,667Bridge Structural
HBM11862008Stem (breastwall)Abutments 65,198Bridge Structural
HBM11872008Cap BeamPiers 48,112Bridge Structural
HBM11202008Stem,Solid PierPiers 73,355Bridge Structural
HBM11202008Brngs,Ancr Blts,PadsPiers 165,769Bridge Structural
HBMC0372008Brngs,Ancr Blts,PadsPiers 39,485Bridge Structural
HBM11202008Sidewalks/FasciasDeck Elements 138,951Bridge Structural
HBM11202008Wearing SurfaceDeck Elements 334,302Bridge Structural
HBM11872008Deck,StructuralSuperstructure 87,049Bridge Structural
R - 8Page
DEPARTMENT OF TRANSPORTATIONFMS ID/ Budget Code
Agency Activity YearType of Work
Agency Activity Funding
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Appendix R
HBM11862008Deck,StructuralSuperstructure 168,943Bridge Structural
HBM11852008Deck,StructuralSuperstructure 125,991Bridge Structural
HBM11202008Deck,StructuralSuperstructure 968,359Bridge Structural
HBM11202008JointsSuperstructure 54,570Bridge Structural
HBM11852008Primary MemberSuperstructure 266,838Bridge Structural
HBM11202008Primary MemberSuperstructure 257,805Bridge Structural
HBMC0372008Primary MemberSuperstructure 93,280Bridge Structural
HBMC0372008Secondary MemberSuperstructure 40,098Bridge Structural
Total Planned Activities for $3,141,809DOT0066
BATTERY PARK TUNNEL DOT0082BATTERY PLACE 02/11/05Date of Last Survey:
HBM11462006WallsAbutments 1,661,750Bridge Structural
HBM11462006WallsWingwalls 5,185,362Bridge Structural
HBM11462006Sidewalks/FasciasDeck Elements 44,179Bridge Structural
HBM11462006Wearing SurfaceDeck Elements 75,088Bridge Structural
Total Planned Activities for $6,966,379DOT0082
BELTSHORE PARKWAY DOT0134BELT SHORE PKWY AT FRESH CREEK 02/09/05Date of Last Survey:
HBK10722008Bridg Seat&pedestalsAbutments 221,040Bridge Structural
HBK10722008BackwallAbutments 218,316Bridge Structural
HBK10722008Brngs,Ancr Blts,PadsAbutments 562,400Bridge Structural
HBK10722008PedestalsAbutments 45,827Bridge Structural
HBK10722008Stem (breastwall)Abutments 356,285Bridge Structural
HBK10722008WallsWingwalls 159,510Bridge Structural
HBK10722008Pier ProtectionStream Channel 375,546Bridge Structural
HBK10722008Cap BeamPiers 308,942Bridge Structural
HBK10722008Pier,ColumnsPiers 76,636Bridge Structural
HBK10722008Brngs,Ancr Blts,PadsPiers 1,109,865Bridge Structural
HBK10722008Deck,StructuralSuperstructure 484,163Bridge Structural
HBK10722008Primary MemberSuperstructure 377,565Bridge Structural
Total Planned Activities for $4,296,095DOT0134
GRAND CONCOURSE OVER E.161 ST. DOT0135GRAND CONCOURSE AND E.161 ST. 02/08/05Date of Last Survey:
HBX11042008WallsAbutments 64,478Bridge Structural
HBX11042008WallsWingwalls 484,578Bridge Structural
HBX11042008Deck,StructuralSuperstructure 1,146,881Bridge Structural
HBX11042008Primary MemberSuperstructure 4,078,616Bridge Structural
Total Planned Activities for $5,774,553DOT0135
R - 9Page
DEPARTMENT OF TRANSPORTATIONFMS ID/ Budget Code
Agency Activity YearType of Work
Agency Activity Funding
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Appendix R
MACOMBS DAM BRIDGE DOT0137E.155 ST. & HARLEM RIVER 08/03/98Date of Last Survey:
BRX2872007Bank ProtectionStream Channel 32,533,666Bridge Structural
BRX2872007Pier ProtectionStream Channel 136,874Bridge Structural
BRX2872007Sidewalks/FasciasDeck Elements 806,781Bridge Structural
BRX2872007Deck,StructuralSuperstructure 203,336Bridge Structural
BRX2872007JointsSuperstructure 538,409Bridge Structural
BRX2872007Primary MemberSuperstructure 3,007,206Bridge Structural
BRX2872007Secondary MemberSuperstructure 517,077Bridge Structural
BRX2872007WiresRaceway 145,107Bridge Electrical
BRX2872007End LiftSwing 483,859Bridge Mechanical
BRX2872007Main Drive SystemSwing 1,079,230Bridge Mechanical
BRX2872007Traffic DevicesSwing 199,514Bridge Mechanical
Total Planned Activities for $39,651,059DOT0137
HAMILTON AVENUE BRIDGE DOT0138HAMILTON AVE./GOWANUS CANAL 01/11/05Date of Last Survey:
HBK11402007Bank ProtectionStream Channel 80,159Bridge Structural
HBK11402007Bank ProtectionStream Channel 80,159Bridge Structural
HBK11402007Primary MemberSuperstructure 125,100Bridge Structural
HBK11402007Disconnect SwitchControl System Electrical 79,538Bridge Electrical
HBK11402007HousesBascule 246,061Bridge Mechanical
HBK11402007HousesBascule 375,322Bridge Mechanical
HBK11402007Lock BarsBascule 41,123Bridge Mechanical
HBK11402007Lock BarsBascule 58,182Bridge Mechanical
HBK11402007Main Drive SystemBascule 234,608Bridge Mechanical
HBK11402007Main Drive SystemBascule 1,363,590Bridge Mechanical
HBK11402007Traffic DevicesBascule 138,706Bridge Mechanical
HBK11402007TrunnionBascule 164,790Bridge Mechanical
Total Planned Activities for $2,987,338DOT0138
UNIONPORT BRIDGE DOT0140WESTCHESTER CREEK 02/02/06Date of Last Survey:
HBX11312009Pier ProtectionStream Channel 62,215Bridge Structural
HBX11312009Primary MemberSuperstructure 39,920Bridge Structural
HBX11312009Bascule SpanMovable Bridges 1,412,351Bridge Structural
HBX11312009Bascule Span PierMovable Bridges 378,265Bridge Structural
HBX11312009Lighting DevicesLighting 66,055Bridge Electrical
HBX11312009Lock BarsBascule 74,127Bridge Mechanical
HBX11312009Traffic DevicesBascule 81,747Bridge Mechanical
Total Planned Activities for $2,114,680DOT0140
R - 10Page
DEPARTMENT OF TRANSPORTATIONFMS ID/ Budget Code
Agency Activity YearType of Work
Agency Activity Funding
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Appendix R
GRAND CONCOURSE BRIDGE DOT0158GRAND CONCOURSE 11/18/03Date of Last Survey:
HBX11902009WallsWingwalls 94,721Bridge Structural
HBX11902009Deck,StructuralSuperstructure 105,775Bridge Structural
Total Planned Activities for $200,496DOT0158
Sub-Total $879,599,122DEPARTMENT OF TRANSPORTATION Bridges
Agency indicates that in addition to the above, the following amounts are budgeted : Bridge Component Repairs/Replacements FY 2008 - 2011 $105,748,000 and Bridge Protective Coating FY 2008 - 2011 $64,277,000. This increases the reconciled amount by $170,025,000. (Note: These estimates are based on the precentage of total numbers of spans represented by the bridges included in the study).
Total Planned Activities for:
For Streets and City owned Arterials, the Agency indicates the following actual and planned expenditures: (Note: These estimates are based on average $/lane mile for reconstruction, engineered resurfacing and resurfacing projects that the Agency reports it will undertake, and does not represent actual amounts in the budget).
Primary Streets FY 2008 - 2011
Secondary Streets FY 2008 - 2011
Local Streets FY 2008 - 2011
City Owned Arterials FY 2008 - 2011
Step Streets FY 2008 - 2011
Sub-Total
Sub-Total
Total Planned Activities for:
Total Planned Activities for: DEPARTMENT OF TRANSPORTATION Ferries
DEPARTMENT OF TRANSPORTATION
Total Required for "State of Good Repair" for: DEPARTMENT OF TRANSPORTATION
281,574,000
385,602,000
203,628,000
13,800,000
2,820,000
887,424,000
35,100,000
1,919,745,000
3,037,457,000
Bridge Reconciliation Sub-Total 988,846,000
R - 11Page
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF PARKS & RECREATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
S
022DBS002510/30/01Date of Last Survey:HUDSON RIVER, 41ST TO 43RD STS.
BULKHEAD, PIER 81,83 -
PT195-VAR2007Relieving Platform TopBulkheads Structural 145,208
PT195-VAR2007Gravity WallBulkheads Structural 173,024
PT195-VAR2007Piles and BracingBulkheads Structural 126,429
PT195-VAR2007Wales and ChocksBulkheads Fender 76,310
Total Planned activities for $520,971DBS0025 022
023DBS002510/30/01Date of Last Survey:HUDSON RIVER, WEST 43 TO 45 STS.
BULKHEAD, PIER 84 -
PT195-VAR2007Pile Supported WallBulkheads Structural 901,808
Total Planned activities for $901,808DBS0025 023
024DBS002510/30/01Date of Last Survey:HUDSON RIVER, 46TH STREET
BULKHEAD, PIER 86 -
PT195-VAR2007Pile Supported WallBulkheads Structural 225,557
PT195-VAR2007PilesBulkheads Fender 41,654
PT195-VAR2007Wales and ChocksBulkheads Fender 98,342
Total Planned activities for $365,553DBS0025 024
028DBS002510/30/01Date of Last Survey:HUDSON RIVER, WEST 58TH STREET
BULKHEAD, PIER 98 -
PT195-VAR2005Pile Supported WallBulkheads Structural 77,206
PT195-VAR2005PilesBulkheads Fender 43,870
PT195-VAR2005Wales and ChocksBulkheads Fender 103,574
Total Planned activities for $224,650DBS0025 028
000DGS004604/24/03Date of Last Survey:W 59TH TO W 70TH STS.,
BULKHEAD - FORMER WESTSIDE RAIL YARD
PT195-VAR2005Gravity WallBulkheads Structural 2,304,832
PT195-VAR2005RevetmentBulkheads Structural 105,102
PT195-VAR2005Sheet PilesBulkheads Structural 1,370,139
Total Planned activities for $3,780,073DGS0046 000
000DGSP00704/12/99Date of Last Survey:HUDSON RIVER W 44TH ST.
PIER 84 -
PT195-VAR2007DeckPiers Structural 125,623
PT195-VAR2007Piles and BracingPiers Structural 42,812
Total Planned activities for $168,435DGSP007 000
000DGSP00804/12/99Date of Last Survey:HUDSON RIVER W 46TH ST.
PIER 86 -
PT195-VAR2007Piles and BracingPiers Structural 37,690
PT195-VAR2007Wales and ChocksPiers Fender 303,425
PT195-VAR2007PilesPiers Fender 128,520
Page S - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF PARKS & RECREATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
S
Total Planned activities for $469,635DGSP008 000
003PAR000301/01/06Date of Last Survey:FLATBUSH, GERRITSEN, FILLMORE
MARINE PARK - FIELDHOUSE - 0003
P-213D17K2006Average Cost Method
87,622
Total Planned activities for $87,622PAR0003 003
010PAR000301/01/06Date of Last Survey:FLATBUSH, GERRITSEN, FILLMORE
MARINE PARK - FIELD HOUSE - 01C
P-213D17K2006Average Cost Method
34,128
Total Planned activities for $34,128PAR0003 010
005PAR000501/01/06Date of Last Survey:DYCKMAN ST. & PAYSON AVE.
INWOOD HILL PARK - BOATHOUSE - 0005
P-3INWOOD2005Average Cost Method
75,059
Total Planned activities for $75,059PAR0005 005
006PAR000609/06/05Date of Last Survey:RIVERSIDE DR. TO HUDSON RIVER
RIVERSIDE PARK - ROTUNDA - W.79TH ST. - 0006
P-314ROTU/P-C3802003Exterior WallsArchitecture Exterior 950,841
P-314ROTU/P-C3802003WindowsArchitecture Exterior 86,199
P-314ROTU/P-C3802003ParapetsArchitecture Exterior 94,771
P-314ROTU/P-C3802003RoofArchitecture Exterior 466,391
Total Planned activities for $1,598,202PAR0006 006
04APAR000701/01/06Date of Last Survey:WEST 155 STREET TO DYCKMAN ST.
HIGHBRIDGE PARK - COMFORT STATION - 04A
P-312HRAL2007Average Cost Method
52,923
Total Planned activities for $52,923PAR0007 04A
040PAR000801/01/06Date of Last Survey:L.I.E. TO GRAND CENTRL PKWY
CUNNINGHAM PARK - DISTRICT OFFICE - 0004
P-408CSTA2005Average Cost Method
64,722
Total Planned activities for $64,722PAR0008 040
050PAR000801/01/06Date of Last Survey:L.I.E. TO GRAND CENTRL PKWY
CUNNINGHAM PARK - PRE-SCHOOL BUILDING - 0005
P-408CSTA2005Average Cost Method
62,269
Total Planned activities for $62,269PAR0008 050
060PAR000801/01/06Date of Last Survey:L.I.E. TO GRAND CENTRL PKWY
CUNNINGHAM PARK - COMFORT STATION - 0006
Page S - 2
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF PARKS & RECREATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
S
P-408CSTA2005Average Cost Method
23,767
Total Planned activities for $23,767PAR0008 060
070PAR000801/01/06Date of Last Survey:L.I.E. TO GRAND CENTRL PKWY
CUNNINGHAM PARK - COMFORT STATION - 0007
P-408CSTA2005Average Cost Method
27,932
Total Planned activities for $27,932PAR0008 070
020PAR001001/01/06Date of Last Survey:GRAND CENTRAL PARKWAY, UNION
ALLEY POND PARK - OFFICE & COMFORT STATION - 02
P-411APE22007Average Cost Method
30,471
Total Planned activities for $30,471PAR0010 020
02APAR001001/01/06Date of Last Survey:GRAND CENTRAL PARKWAY, UNION
ALLEY POND PARK - TENNIS BLDG - 02
P-411APE22007Average Cost Method
61,509
Total Planned activities for $61,509PAR0010 02A
210PAR001109/12/05Date of Last Survey:MYRTLE AVE, UNION TPKE,
FOREST PARK - GREENHOUSE - 21
P-409FPGR2007Exterior WallsArchitecture Exterior 342,250
P-409FPGR2007RoofArchitecture Exterior 783,276
P-409FPGR2007FloorsArchitecture Interior 35,519
Total Planned activities for $1,161,045PAR0011 210
220PAR001101/01/06Date of Last Survey:MYRTLE AVE, UNION TPKE,
FOREST PARK - POLYHOUSE - 22
P-409FPGR2006Average Cost Method
56,078
Total Planned activities for $56,078PAR0011 220
250PAR001101/01/06Date of Last Survey:MYRTLE AVE, UNION TPKE,
FOREST PARK - DRY HARBOR - 25
P-409DEYH2004Average Cost Method
99,068
Total Planned activities for $99,068PAR0011 250
077PAR001804/19/05Date of Last Survey:5TH AVE. TO CENTRAL PARK W.,
CENTRAL PARK - ARSENAL BUILDING - 10
P-300PARA2007Exterior WallsArchitecture Exterior 141,018
Total Planned activities for $141,018PAR0018 077
007PAR001901/01/06Date of Last Survey:GRAND CENTRAL PARKWAY
FLUSHING MEADOWS CORONA PARK - COMFORT STATION - A007
Page S - 3
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF PARKS & RECREATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
S
P-40013BI/P-C0252001Average Cost Method
34,280
Total Planned activities for $34,280PAR0019 007
032PAR001905/18/04Date of Last Survey:GRAND CENTRAL PARKWAY
FLUSHING MEADOWS CORONA PARK - PASSARELLE - 0032
P-4PASARE2007RoofArchitecture Exterior 42,190
P-4PASARE2006Interior WallsArchitecture Interior 19,483
P-4PASARE2006General LightingElectrical Lighting 7,309
Total Planned activities for $68,981PAR0019 032
22APAR002005/11/06Date of Last Survey:FLATBUSH, OCEAN & PARKSIDE AVES.
PROSPECT PARK - MAINTENANCE BUILDING # 1
P-6DROOF62008RoofArchitecture Exterior 35,261
P-6DROOF52008RoofArchitecture Exterior 127,312
Total Planned activities for $162,573PAR0020 22A
26APAR002005/12/06Date of Last Survey:FLATBUSH, OCEAN & PARKSIDE AVES.
PROSPECT PARK - WOLLMAN ICE RINK BLDG. - 026A
P-200K01E2006WindowsArchitecture Exterior 92,584
Total Planned activities for $92,584PAR0020 26A
A0CPAR002001/01/06Date of Last Survey:FLATBUSH, OCEAN & PARKSIDE AVES.
PROSPECT PARK - ZOO WORLD OF ANIMALS - A00C
P-200C64H2006Average Cost Method
215,020
Total Planned activities for $215,020PAR0020 A0C
A0DPAR002001/01/06Date of Last Survey:FLATBUSH, OCEAN & PARKSIDE AVES.
PROSPECT PARK - ZOO ANIMAL LIFE STYLES - A00D
P-200C64H2006Average Cost Method
273,694
Total Planned activities for $273,694PAR0020 A0D
AA1PAR002001/01/06Date of Last Survey:FLATBUSH, OCEAN & PARKSIDE AVES.
PROSPECT PARK - ZOO SEA LION AREA - A0A1
P-200C64H2006Average Cost Method
112,853
Total Planned activities for $112,853PAR0020 AA1
000PAR002105/23/06Date of Last Survey:E.157TH ST. & RUPPERT PLACE
YANKEE STADIUM -
P-6CYANK52006Exterior WallsArchitecture Exterior 2,550,750
P-6CYANK52006ParapetsArchitecture Exterior 1,241,469
P-6CYANK52006RoofArchitecture Exterior 204,193
P-6CYANK52006FloorsArchitecture Interior 1,894,026
P-6CYANK52006Interior WallsArchitecture Interior 402,492
Page S - 4
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF PARKS & RECREATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
S
P-6CYANK52006CeilingsArchitecture Interior 987,050
P-6CYANK52006BatteriesElectrical Stand-by Power 80,631
P-6CYANK52006General LightingElectrical Lighting 206,784
P-6CYANK52006DistributionMechanical Ventilation 179,256
Total Planned activities for $7,746,651PAR0021 000
000PAR002205/09/06Date of Last Survey:ROOSEVELT AVE & 126TH ST
SHEA STADIUM -
P-6CSHEA52006Exterior WallsArchitecture Exterior 668,645
P-6CSHEA52006ParapetsArchitecture Exterior 1,642,668
P-6CSHEA52006RoofArchitecture Exterior 391,668
P-6CSHEA52006FloorsArchitecture Interior 717,343
P-6CSHEA52006Interior WallsArchitecture Interior 296,386
P-6CSHEA52006CeilingsArchitecture Interior 2,327,457
P-6CSHEA52006Fuel StorageElectrical Stand-by Power 40,043
P-6CSHEA52006DistributionMechanical Ventilation 213,941
P-6CSHEA52006H/C Water PipingMechanical Plumbing 201,693
Total Planned activities for $6,499,844PAR0022 000
002PAR002701/01/06Date of Last Survey:JAMAICA AVE & 153RD STS
RUFUS KING PARK - KING MANSION HISTORIC HOUSE
P-412C1902003Average Cost Method
500,366
Total Planned activities for $500,366PAR0027 002
004PAR003001/01/06Date of Last Survey:106 AVE., 173 STREET,
LIBERTY PARK - INTERMEDIATE POOL
P-6ABLDG3M2005Average Cost Method
131,431
Total Planned activities for $131,431PAR0030 004
F91PAR003105/30/01Date of Last Survey:OCEAN PROMENADE
ROCKAWAY BEACH & BOARDWALK - BOARDWALK
P-414C19W2001Underside EnclosureBoardwalks Substructure 103,181
Total Planned activities for $103,181PAR0031 F91
F92PAR003104/30/01Date of Last Survey:SHORE FRONT PKWY & BEACH
ROCKAWAY BEACH & BOARDWALK - BOARDWALK
P-414C19W2001DeckBoardwalks Superstructure 107,964
Total Planned activities for $107,964PAR0031 F92
F95PAR003104/30/01Date of Last Survey:SHORE FRONT PKWY & BEACH
ROCKAWAY BEACH & BOARDWALK - BOARDWALK
P-4 SKATE2005DeckBoardwalks Superstructure 2,107
Total Planned activities for $2,107PAR0031 F95
Page S - 5
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF PARKS & RECREATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
S
F97PAR003105/30/01Date of Last Survey:SHORE FRONT PKWY & BEACH
ROCKAWAY BEACH & BOARDWALK - BOARDWALK
P-4 SKATE2005Underside EnclosureBoardwalks Substructure 2,150
Total Planned activities for $2,150PAR0031 F97
F98PAR003105/30/01Date of Last Survey:SHORE FRONT PKWY & BEACH
ROCKAWAY BEACH & BOARDWALK - BOARDWALK
P-4 SKATE2005DeckBoardwalks Superstructure 3,944
P-4 SKATE2005GirdersBoardwalks Substructure 7,929
P-414RBFA2007Underside EnclosureBoardwalks Substructure 298,794
Total Planned activities for $310,667PAR0031 F98
N01PAR003101/01/06Date of Last Survey:BEACH 3 ST. TO BEACH 149 ST.
ROCKAWAY BEACH & BOARDWALK - COMFORT STATION
P-6CBLDG32004Average Cost Method
157,145
Total Planned activities for $157,145PAR0031 N01
N02PAR003101/01/06Date of Last Survey:BEACH 3 ST. TO BEACH 149 ST.
ROCKAWAY BEACH & BOARDWALK - COMFORT STATION
P-6CBLDG32004Average Cost Method
13,826
Total Planned activities for $13,826PAR0031 N02
001PAR003209/09/02Date of Last Survey:93-29 QUEENS BOULEVARD
LOST BATTALION HALL - RECREATION CENTER
P-406LBAT2007RoofArchitecture Exterior 40,914
P-406LBAT2007Interior WallsArchitecture Interior 53,153
Total Planned activities for $94,067PAR0032 001
01APAR003910/22/02Date of Last Survey:W145-W155-BRADHURST-EDGECOMBE
JACKIE ROBINSON PARK - RECREATION CENTER
P-6DPOOL52005Pool Filter/TreatmentMechanical Plumbing 56,494
Total Planned activities for $56,494PAR0039 01A
F06PAR003910/22/02Date of Last Survey:W145-W155-BRADHURST-EDGECOMBE
JACKIE ROBINSON PARK - DIVING POOL
P-310JROB2003Exterior WallsArchitecture Exterior 122,142
P-310JROB2003FloorsArchitecture Interior 93,718
Total Planned activities for $215,860PAR0039 F06
004PAR004710/23/02Date of Last Survey:E 120-E 124 MADISON AVENUE
MARCUS GARVEY MEMORIAL PARK - OLYMPIC POOL
P-6DPOOL52005Pool Filter/TreatmentMechanical Plumbing 70,861
Total Planned activities for $70,861PAR0047 004
Page S - 6
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF PARKS & RECREATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
S
04APAR004710/23/02Date of Last Survey:E 120-E 124 MADISON AVENUE
MARCUS GARVEY MEMORIAL PARK - BATHHOUSE BLDG.
P-307ANEX2007Interior WallsArchitecture Interior 19,302
Total Planned activities for $19,302PAR0047 04A
001PAR004809/05/02Date of Last Survey:533 WEST 59 STREET
WEST 59 STREET RECREATION CENTER - GYMNASIUM & INDOOR POOL
P-307ANEX2007Exterior WallsArchitecture Exterior 208,529
Total Planned activities for $208,529PAR0048 001
004PAR004809/05/02Date of Last Survey:533 WEST 59 STREET
WEST 59 STREET RECREATION CENTER - INTERMEDIATE OUTDOOR POOL
P-307ANEX2007FloorsArchitecture Interior 386,202
P-307ANEX2007Interior WallsArchitecture Interior 227,927
P-307ANEX2007H/C Water PipingMechanical Plumbing 117,094
P-307ANEX2007Pool Filter/TreatmentMechanical Plumbing 130,945
Total Planned activities for $862,168PAR0048 004
001PAR005810/19/98Date of Last Survey:342 EAST 54 STREET
EAST 54 STREET RECREATION CENTER - GYMNASIUM & INDOOR POOL
P-306C1242001WindowsArchitecture Exterior 156,136
P-306C1242001General LightingElectrical Lighting 41,807
P-306C1242001Conversion EquipmentMechanical Heating 39,117
P-306C1242001DistributionMechanical Heating 56,105
P-306C1242001DistributionMechanical Ventilation 41,611
Total Planned activities for $334,776PAR0058 001
001PAR005909/09/02Date of Last Survey:35 W. 134TH STREET
HANSBOROUGH RECREATION CENTER - GYMNASIUM & INDOOR POOL
P-6BRECR52005GeneratorsElectrical Stand-by Power 62,933
Total Planned activities for $62,933PAR0059 001
N01PAR006001/01/06Date of Last Survey:MONTGOMERY TO E 12TH FDR
EAST RIVER PARK - COMFORT STATION
P-EASTRV2004Average Cost Method
123,135
Total Planned activities for $123,135PAR0060 N01
N02PAR006001/01/06Date of Last Survey:MONTGOMERY TO E 12TH FDR
EAST RIVER PARK - COMFORT STATION
P-EASTRV2004Average Cost Method
28,033
Total Planned activities for $28,033PAR0060 N02
030PAR007108/31/05Date of Last Survey:JEROME AVE & MCCLELLAN ST.
JOHN MULLALY PARK - MULTIPUPOSE BUILDING
Page S - 7
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF PARKS & RECREATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
S
P-6DROOF52008RoofArchitecture Exterior 51,061
Total Planned activities for $51,061PAR0071 030
N01PAR007101/01/06Date of Last Survey:JEROME AVE & MCCLELLAN ST.
JOHN MULLALY PARK - STRUCTURE
P-6ABLDG52006Average Cost Method
65,188
Total Planned activities for $65,188PAR0071 N01
N02PAR007101/01/06Date of Last Survey:JEROME AVE & MCCLELLAN ST.
JOHN MULLALY PARK - STRUCTURE
P-6ABLDG52006Average Cost Method
48,366
Total Planned activities for $48,366PAR0071 N02
050PAR007203/18/03Date of Last Survey:EASTCHESTER BAY, HUTCHINSON
PELHAM BAY PARK - BARTOW PELL MANSION - 0005
P-110MANS2006Exterior WallsArchitecture Exterior 36,335
P-110MANS2006FloorsArchitecture Interior 53,921
P-110MANS2006CeilingsArchitecture Interior 52,258
Total Planned activities for $142,514PAR0072 050
130PAR007201/01/06Date of Last Survey:EASTCHESTER BAY, HUTCHINSON
PELHAM BAY PARK - PELHAM MAINTENANCE - 0013
P110PBPS2007Average Cost Method
77,688
Total Planned activities for $77,688PAR0072 130
140PAR007201/01/06Date of Last Survey:EASTCHESTER BAY, HUTCHINSON
PELHAM BAY PARK - H. JOHNSON DISTRICT OFFICE-0014
P110PBPS2007Average Cost Method
76,289
Total Planned activities for $76,289PAR0072 140
150PAR007201/01/06Date of Last Survey:EASTCHESTER BAY, HUTCHINSON
PELHAM BAY PARK - COMFORT STATION - 0015
P110PBPS2007Average Cost Method
15,236
Total Planned activities for $15,236PAR0072 150
420PAR007201/01/06Date of Last Survey:EASTCHESTER BAY, HUTCHINSON
PELHAM BAY PARK - RANGER & COMFORT STATION - 0042
P-110PBPS2007Average Cost Method
59,581
Total Planned activities for $59,581PAR0072 420
460PAR007203/18/03Date of Last Survey:EASTCHESTER BAY, HUTCHINSON
PELHAM BAY PARK - ORCHARD BEACH BATHHOUSE - 0046
P-1CROT202007Exterior WallsArchitecture Exterior 749,904
Page S - 8
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF PARKS & RECREATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
S
P-1CROT202007WindowsArchitecture Exterior 213,152
P-1CROT202007ParapetsArchitecture Exterior 118,394
P-110EXPA2004RoofArchitecture Exterior 286,809
Total Planned activities for $1,368,259PAR0072 460
003PAR007408/29/05Date of Last Survey:JEROME AVE, E.191 ST TO E.193 ST
ST JAMES PARK - ST. JAMES GOLDEN AGE CENTER
P-107JPSC2006Heat RejectionMechanical Air Conditioning 35,085
Total Planned activities for $35,085PAR0074 003
02APAR007408/29/05Date of Last Survey:JEROME AVE, E.191 ST TO E.193 ST
ST JAMES PARK - COMFORT & RECREATION BLDG.
P-107JPSC2006Exterior WallsArchitecture Exterior 39,419
Total Planned activities for $39,419PAR0074 02A
004PAR007509/16/02Date of Last Survey:ST. MARY'S ST. & ST. ANN'S AVE.
ST. MARY'S PARK - RECREATION CENTER
P-6ABLDG52006Exterior WallsArchitecture Exterior 274,150
P-6ABLDG62006WindowsArchitecture Exterior 72,876
P-6ABLDG72006ParapetsArchitecture Exterior 106,420
Total Planned activities for $453,446PAR0075 004
220PAR007701/01/06Date of Last Survey:W. 240 STREET TO CITY LINE
VAN CORTLANDT PARK - GREENHOUSE - 0022
P-1CROT132007Average Cost Method
372,035
Total Planned activities for $372,035PAR0077 220
02APAR007809/08/05Date of Last Survey:VAN CORTLANDT AVE. EAST
WILLIAMSBRIDGE PLAYGROUND - COMFORT AND RECREATION BLDG.
P-1CROT17A2007Exterior WallsArchitecture Exterior 112,500
P-1CROT17A2007WindowsArchitecture Exterior 37,236
Total Planned activities for $149,736PAR0078 02A
004PAR008906/22/05Date of Last Survey:FT WADSWORTH TO MILLER FIELD
FDR BOARDWALK & BEACH - MIDLAND BEACH M&W BATHHOUSES
P-5SBCOMF2006Exterior WallsArchitecture Exterior 84,316
Total Planned activities for $84,316PAR0089 004
F98PAR008902/29/04Date of Last Survey:FT WADSWORTH TO MILLER FIELD
FDR BOARDWALK & BEACH - BOARDWALK
P-5BDWK2007DeckBoardwalks Superstructure 66,876
P-5SBEACH2004BeamsBoardwalks Substructure 1,285,356
P-5SBEACH2004PiersBoardwalks Substructure 111,057
P-5SBEACH2004GirdersBoardwalks Substructure 154,046
P-5SBEACH2004Underside EnclosureBoardwalks Substructure 207,092
Page S - 9
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF PARKS & RECREATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
S
Total Planned activities for $1,824,427PAR0089 F98
F99PAR008902/29/04Date of Last Survey:FT WADSWORTH TO MILLER FIELD
FDR BOARDWALK & BEACH - BOARDWALK
P-5SBEACH2004DeckBoardwalks Superstructure 36,304
P-5SBEACH2004GirdersBoardwalks Substructure 83,625
P-5SBEACH2004Underside EnclosureBoardwalks Substructure 327,895
Total Planned activities for $447,824PAR0089 F99
001PAR009301/01/06Date of Last Survey:JOLINE AVE - HYLAN BLVD
TOTTENVILLE POOL - JOLINE POOL, INTERMEDIATE
P-6BPOOL52005Average Cost Method
140,193
Total Planned activities for $140,193PAR0093 001
N01PAR009301/01/06Date of Last Survey:JOLINE AVE - HYLAN BLVD
TOTTENVILLE POOL - SMALL POOL
P-6BPOOL52005Average Cost Method
17,165
Total Planned activities for $17,165PAR0093 N01
01APAR009711/20/02Date of Last Survey:LIVONIA-DUMONT-HOPKINSON
BETSY HEAD MEMORIAL PLAYGROUND - BATHHOUSE BLDG.
P-6BPOOL52006General LightingElectrical Lighting 49,762
Total Planned activities for $49,762PAR0097 01A
01CPAR009711/20/02Date of Last Survey:LIVONIA-DUMONT-HOPKINSON
BETSY HEAD MEMORIAL PLAYGROUND - FILTER HOUSE BLDG.
P-6BPOOL52006SwitchgearElectrical Under 600 Volts 58,974
P-6BPOOL52006General LightingElectrical Lighting 41,333
Total Planned activities for $100,307PAR0097 01C
N01PAR010001/01/06Date of Last Survey:PARK AVE-NAVY ST-N ELLIOT ST
COM JOHN BARRY PARK & PLAYGROUND - WADING POOL
P-6BPOOL52005Average Cost Method
19,908
Total Planned activities for $19,908PAR0100 N01
002PAR010510/16/03Date of Last Survey:41-44 ST & 5TH AND 7TH AVE
SUNSET PARK - OLYMPIC POOL
P-6ABLDG52006FloorsArchitecture Interior 215,223
Total Planned activities for $215,223PAR0105 002
02CPAR010510/16/03Date of Last Survey:41-44 ST & 5TH AND 7TH AVE
SUNSET PARK - FILTERHOUSE
P-6BPOOL52006General LightingElectrical Lighting 99,930
Total Planned activities for $99,930PAR0105 02C
Page S - 10
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF PARKS & RECREATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
S
001PAR010609/04/02Date of Last Survey:LAFAYETTE, TOMPKINS, MARCY AVES.
TOMPKINS PARK - VON KING CULTURAL/ARTS CENTER
P-203D0172006Exterior WallsArchitecture Exterior 40,466
P-203D0172006RoofArchitecture Exterior 174,449
Total Planned activities for $214,915PAR0106 001
02APAR011009/23/03Date of Last Survey:OSTEGO/BAY/KICKS/HALLECK AVES
RED HOOK RECREATION AREA - BATHHOUSE - BOYS AND GIRLS
P-6CWF032004Exterior WallsArchitecture Exterior 264,011
P-6CWRF032004ParapetsArchitecture Exterior 269,792
Total Planned activities for $533,803PAR0110 02A
001PAR011309/04/02Date of Last Survey:TROY-BERGEN-PROSPECT PLACE
ST JOHNS RECREATION CENTER -
P-208K11D2004Exterior WallsArchitecture Exterior 114,344
P-6CWRF03,P-208K2003ParapetsArchitecture Exterior 52,157
CNYG-1503MR2004RoofArchitecture Exterior 112,266
P-208K11D2004FloorsArchitecture Interior 37,951
Total Planned activities for $316,718PAR0113 001
01APAR011301/01/06Date of Last Survey:TROY-BERGEN-PROSPECT PLACE
ST JOHNS RECREATION CENTER - INDOOR POOL
P-208K11D2004Average Cost Method
49,475
Total Planned activities for $49,475PAR0113 01A
001PAR011601/01/06Date of Last Survey:LINDEN BLVD - HEGMAN AVE
BROWNSVILLE REC CENTER & PLYGRND - BROWNSVILLE RECREATION CENTER
P-6ARECR52005Average Cost Method
343,440
Total Planned activities for $343,440PAR0116 001
001PAR011805/03/06Date of Last Survey:SURF AVE, W. 19 ST. & BOARDWALK
ABE STARK SKATING RINK - INDOOR FACILITY
CNYG-1305M2006RoofArchitecture Exterior 199,955
Total Planned activities for $199,955PAR0118 001
009PAR012409/06/05Date of Last Survey:RANDALLS ISLAND
FIVE BORO GARAGE - CITY-WIDE FIVE BORO GARAGE
P-6DROOF52007RoofArchitecture Exterior 65,448
Total Planned activities for $65,448PAR0124 009
000PAR013205/19/03Date of Last Survey:E. 27TH ST TO POOLE LA
SHEEPSHEAD BAY PIERS 1 - 10 - 10 PIERS ON NORTH SIDE OF BAY
P-215018A2005Piles and BracingPiers Structural 126,749
Total Planned activities for $126,749PAR0132 000
Page S - 11
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF PARKS & RECREATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
S
020PAR014901/25/06Date of Last Survey:MERRICK BLVD AND 119TH AVE.
ROY WILKINS PARK - RECREATION CENTER
P-412RWPK2007Exterior WallsArchitecture Exterior 13,588
Total Planned activities for $13,588PAR0149 020
030PAR016301/01/06Date of Last Survey:155TH STREET AND 121ST AVE.
BAISLEY POND PARK - COMFORT STATION # 3
P-415BPON2007Average Cost Method
15,236
Total Planned activities for $15,236PAR0163 030
000PAR016801/01/06Date of Last Survey:NEPTUNE AVE AND WEST 29TH STREET
LEON S. KAISER PARK HOUSE -
P-213D17K2008Average Cost Method
125,004
Total Planned activities for $125,004PAR0168 000
000PARB08205/14/03Date of Last Survey:N. SIDE OF VERREZANO BRIDGE
SHORE ROAD PARKWAY - CONCRETE GRAVITY WALL
P-210SHRP2007Coping/CurbBulkheads Structural 304,165
P-210SHRP2007Pile Supported WallBulkheads Structural 12,826,379
P-210SHRP2007RevetmentBulkheads Structural 795,261
P-210SHRP2007SurfaceBulkheads Backfill 81,367
Total Planned activities for $14,007,172PARB082 000
000PARB12505/07/03Date of Last Survey:CONEY ISLAND CREEK
DREIR OFFERMAN PARK - RIP-RAP
P-213C0542008FillBulkheads Backfill 1,188,450
P-213C0542008SurfaceBulkheads Backfill 283,786
Total Planned activities for $1,472,236PARB125 000
002PARB12905/07/03Date of Last Survey:CONEY ISLAND CREEK
LEON S. KAISER PARK - PIER
P-213D0172006Piles and BracingPiers Structural 13,060
Total Planned activities for $13,060PARB129 002
001PARM03910/12/01Date of Last Survey:3RD AVE. BRIDGE TO TRIBOROUGH BR
HARLEM RIVER DR.WAY PROMENADE - SEAWALL
P-311C4752003SurfaceBulkheads Backfill 308,033
Total Planned activities for $308,033PARM039 001
000PARM04210/30/01Date of Last Survey:HUDSON RIVER
INWOOD HILL PARK - RIP-RAP
P-3INDOCK2006RevetmentBulkheads Structural 8,766
P-3INDOCK2006RevetmentBulkheads Structural 43,830
P-3INDOCK2006SurfaceBulkheads Backfill 8,732
Page S - 12
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF PARKS & RECREATION
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
S
Total Planned activities for $61,328PARM042 000
000PARM10710/28/04Date of Last Survey:WARDS ISLAND
WARDS ISLAND - SEAWALL
P-311WATT2007Gravity WallBulkheads Structural 452,118
P-311WATT2007RevetmentBulkheads Structural 180,882
P-311WATT2007SurfaceBulkheads Backfill 44,164
Total Planned activities for $677,164PARM107 000
001PARM14410/25/04Date of Last Survey:EAST RIVER PARK
EAST RIVER PARK - SEAWALL
P-3ERBULK2004Relieving Platform TopBulkheads Structural 10,919,042
Total Planned activities for $10,919,042PARM144 001
000PARX11810/20/03Date of Last Survey:SOUNDVIEW PARK
SOUNDVIEW PARK - RIP-RAP
P-109SVPT2007RevetmentBulkheads Structural 22,610
Total Planned activities for $22,610PARX118 000
000PARX12610/20/03Date of Last Survey:WESTCHESTER CREEK/EAST RIVER
FERRY POINT PARK - MARSH/RIP RAP
P-1FERRYT2008RevetmentBulkheads Structural 412,943
Total Planned activities for $412,943PARX126 000
Total Planned Activities for : $64,469,289DEPT. OF PARKS & RECREATION
Total Required for "State of Good Repair" for : DEPT. OF PARKS & RECREATION $405,913,637
Page S - 13
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF CITYWIDE ADMIN. SERV.
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
T
000DGS000201/12/06Date of Last Survey:100 CENTRE STREET
MANHATTAN CRIMINAL COURTS BLDG. -
CO283EXTR2008Exterior WallsArchitecture Exterior 2,924,892
CO283EXTR2008WindowsArchitecture Exterior 85,060
CO283EXTR2008ParapetsArchitecture Exterior 143,282
CO283ELEC2002WiringElectrical Under 600 Volts 266,124
Total Planned activities for $3,419,358DGS0002 000
000DGS000301/12/06Date of Last Survey:60 LAFAYETTE STREET
MANHATTAN FAMILY COURT -
CO285RENO2008Interior WallsArchitecture Interior 347,278
CO285RENO2008CeilingsArchitecture Interior 132,031
CO285RENO2008DistributionMechanical Heating 160,202
Total Planned activities for $639,511DGS0003 000
000DGS000409/28/04Date of Last Survey:111 CENTRE STREET
MANHATTAN CIVIL COURT -
CO284EXTR2008Exterior WallsArchitecture Exterior 374,537
CO284EXTR2007Exterior WallsArchitecture Exterior 1,514,813
CO284EXTR2007ParapetsArchitecture Exterior 71,643
Total Planned activities for $1,960,993DGS0004 000
000DGS000512/19/03Date of Last Survey:125 WORTH STREET
HEALTH BUILDING -
PW266EXTR2007WindowsArchitecture Exterior 845,495
PW266EXTR2007ParapetsArchitecture Exterior 87,641
PW266GEN2007PanelboardsElectrical Under 600 Volts 72,222
PW266GEN2007WiringElectrical Under 600 Volts 198,014
PW266GEN2007Motor ControllersElectrical Under 600 Volts 122,664
Total Planned activities for $1,326,036DGS0005 000
000DGS000610/17/02Date of Last Survey:60 CENTRE STREET
MANHATTAN SUPREME COURT -
CO304EXTR2004WindowsArchitecture Exterior 189,377
CO304EXTR2004RoofArchitecture Exterior 174,400
CO304EXTR2004FloorsArchitecture Interior 102,085
CO304BASE2007WiringElectrical Under 600 Volts 43,460
CO304CHIL2005Conversion EquipmentMechanical Heating 49,706
Total Planned activities for $559,028DGS0006 000
000DGS000701/13/06Date of Last Survey:31 CHAMBERS STREET
SURROGATE'S COURT - MUNICIPAL ARCHIVES
CO81EXTR2007Exterior WallsArchitecture Exterior 306,482
CO81EXTR2007WindowsArchitecture Exterior 271,868
Page T - 1
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF CITYWIDE ADMIN. SERV.
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
T
CO81EXTR2007ParapetsArchitecture Exterior 77,033
CO81ROOF2004RoofArchitecture Exterior 128,278
CO81RENOV2006CeilingsArchitecture Interior 371,028
PW310DHVA2008WiringElectrical Under 600 Volts 72,433
PW310DHVA2008DistributionMechanical Air Conditioning 35,086
PW310DHVA2008DistributionMechanical Ventilation 41,010
Total Planned activities for $1,303,218DGS0007 000
000DGS000806/11/02Date of Last Survey:CITY HALL PARK
CITY HALL -
PW077CHR2009FloorsArchitecture Interior 91,274
Total Planned activities for $91,274DGS0008 000
000DGS001009/28/04Date of Last Survey:346 BROADWAY
CLOCK TOWER OFFICE BUILDING -
PW79EXTRC2009Exterior WallsArchitecture Exterior 1,743,600
PW79EXTRC2009WindowsArchitecture Exterior 590,601
PW79EXTRC2009ParapetsArchitecture Exterior 293,362
PW79EXTRC2009RoofArchitecture Exterior 38,640
Total Planned activities for $2,666,203DGS0010 000
000DGS001111/15/02Date of Last Survey:137 CENTRE STREET
EXCELSIOR BUILDING -
PW77117EX2004Exterior WallsArchitecture Exterior 535,241
PW77117EX2004WindowsArchitecture Exterior 74,289
PW77117EX2004ParapetsArchitecture Exterior 79,090
PW77117EX2004RoofArchitecture Exterior 51,292
PW77117F2008WiringElectrical Under 600 Volts 37,115
PW77117F2008Terminal DevicesMechanical Heating 45,246
Total Planned activities for $822,273DGS0011 000
000DGS001206/08/06Date of Last Survey:520 FIRST AVENUE
CHIEF MEDICAL EXAMINERS BUILDING -
PW77139EX2006Exterior WallsArchitecture Exterior 117,603
PW77139EX2006WindowsArchitecture Exterior 103,856
Total Planned activities for $221,459DGS0012 000
000DGS001310/13/04Date of Last Survey:49-51 CHAMBERS STREET
ADMINISTRATION BUILDING - EMIGRANT BANK BUILDING
PW77145F2008WindowsArchitecture Exterior 164,022
PW77145TR2002General LightingElectrical Lighting 1,159,015
Total Planned activities for $1,323,037DGS0013 000
000DGS001410/17/02Date of Last Survey:280 BROADWAY
SUN BUILDING -
Page T - 2
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF CITYWIDE ADMIN. SERV.
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
T
PW-316-072003FloorsArchitecture Interior 156,644
Total Planned activities for $156,644DGS0014 000
000DGS001512/01/05Date of Last Survey:2 LAFAYETTE STREET
COURT SQUARE BUILDING - 2 LAFAYETTE
PW80EXTR2007Exterior WallsArchitecture Exterior 38,590
AG2LAFYT2008WindowsArchitecture Exterior 419,662
Total Planned activities for $458,252DGS0015 000
000DGS001604/21/04Date of Last Survey:851 GRAND CONCOURSE
MARIO MEROLA BUILDING -
CO293EXTR2007Exterior WallsArchitecture Exterior 765,900
CO293EXTR2007WindowsArchitecture Exterior 224,180
CO293EXTR2007RoofArchitecture Exterior 138,715
CO293ELEC2007SwitchgearElectrical Under 600 Volts 35,436
CO293ELEC2007WiringElectrical Under 600 Volts 65,190
CO293ELEC2007General LightingElectrical Lighting 320,278
CO293ELEC2006Terminal DevicesMechanical Heating 16,595
CO293ELEC2006DistributionMechanical Air Conditioning 30,087
CO293ELEC2006Terminal DevicesMechanical Air Conditioning 26,147
CO293MECH2007DistributionMechanical Ventilation 212,516
Total Planned activities for $1,835,043DGS0016 000
000DGS001702/09/05Date of Last Survey:215 E. 161 STREET
BRONX FAMILY/CRIMINAL COURT -
CO294EXTR2003Exterior WallsArchitecture Exterior 187,670
CO294ROOF2006ParapetsArchitecture Exterior 95,954
CO294ROOF2006RoofArchitecture Exterior 628,763
CO294BACK2009FloorsArchitecture Interior 322,002
CO294BACK2009Interior WallsArchitecture Interior 215,151
CO294BACK2009CeilingsArchitecture Interior 385,650
CO294CHIL2008Terminal DevicesMechanical Air Conditioning 3,857,633
Total Planned activities for $5,692,823DGS0017 000
000DGS001801/08/04Date of Last Survey:1932 ARTHUR AVENUE
BERGEN BUILDING -
PW77207B2006Exterior WallsArchitecture Exterior 930,673
PW77207B2006ParapetsArchitecture Exterior 56,023
Total Planned activities for $986,696DGS0018 000
000DGS001902/16/05Date of Last Survey:360 ADAMS STREET
BROOKLYN SUPREME COURT -
CO278EXTR2008Exterior WallsArchitecture Exterior 509,978
CO278EXTR2008WindowsArchitecture Exterior 290,801
Page T - 3
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF CITYWIDE ADMIN. SERV.
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
T
CO278CONV2011FloorsArchitecture Interior 301,742
CO278CONV2011CeilingsArchitecture Interior 277,386
CO278CONV2011WiringElectrical Under 600 Volts 119,274
Total Planned activities for $1,499,182DGS0019 000
000DGS002004/20/04Date of Last Survey:208-242 JORALEMON STREET
BROOKLYN MUNICIPAL BUILDING -
PW325EXTR2007Exterior WallsArchitecture Exterior 129,264
PW325EXTR2007WindowsArchitecture Exterior 309,912
PW325EXTR2007ParapetsArchitecture Exterior 132,900
PW291ROOF2007RoofArchitecture Exterior 112,701
PW325INTR2007CeilingsArchitecture Interior 192,978
PW325INTR2007WiringElectrical Under 600 Volts 330,024
PW291STM2008Conversion EquipmentMechanical Heating 92,488
PW291STM2008Terminal DevicesMechanical Heating 3,698,059
PW325COOL2007Heat RejectionMechanical Air Conditioning 54,535
Total Planned activities for $5,052,861DGS0020 000
000DGS002104/20/04Date of Last Survey:120 SCHERMERHORN STREET
BROOKLYN CENTRAL COURTS - BROOKLYN CRIMINAL COURTS
CO281EXTR2008Exterior WallsArchitecture Exterior 131,221
CO281EXTR2008RoofArchitecture Exterior 55,841
CO281K-CR2009Interior WallsArchitecture Interior 60,445
CO281TSES2010Heat RejectionMechanical Air Conditioning 73,860
Total Planned activities for $321,367DGS0021 000
000DGS002309/15/04Date of Last Survey:209 JORALEMON STREET
BROOKLYN BOROUGH HALL -
PW291ROOF2004RoofArchitecture Exterior 197,220
Total Planned activities for $197,220DGS0023 000
000DGS002510/25/04Date of Last Survey:390 KENT AVENUE
KENT AVENUE SHOPS -
PW77326EX2004WindowsArchitecture Exterior 107,545
PW77326EX2004ParapetsArchitecture Exterior 270,784
PW77326EX2004RoofArchitecture Exterior 393,241
Total Planned activities for $771,570DGS0025 000
000DGS002612/15/03Date of Last Survey:125-01 QUEENS BOULEVARD
QUEENS CRIMINAL COURTS -
CO296EXTR2008Exterior WallsArchitecture Exterior 59,153
CO296EXTR2008ParapetsArchitecture Exterior 62,201
Total Planned activities for $121,354DGS0026 000
Page T - 4
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF CITYWIDE ADMIN. SERV.
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
T
000DGS002703/03/05Date of Last Survey:88-11 SUTPHIN BOULEVARD
QUEENS SUPREME COURT -
CO300415A2007Exterior WallsArchitecture Exterior 186,489
CO300415A2007ParapetsArchitecture Exterior 156,621
Total Planned activities for $343,110DGS0027 000
000DGS002803/04/05Date of Last Survey:120-55 QUEENS BOULEVARD
QUEENS BOROUGH HALL -
CO296EXTR2007Exterior WallsArchitecture Exterior 97,601
CO296EXTR2007ParapetsArchitecture Exterior 108,476
PW77417V2009WiringElectrical Under 600 Volts 44,003
Total Planned activities for $250,080DGS0028 000
000DGS002909/29/04Date of Last Survey:25-10 COURT SQUARE
SUPREME COURT - LONG ISLAND CITY -
CO277EXTR2007Exterior WallsArchitecture Exterior 91,059
CO277EXTR2007WindowsArchitecture Exterior 167,981
CO277EXTR2007ParapetsArchitecture Exterior 224,561
CO277EXTR2007RoofArchitecture Exterior 130,107
CO277RENV2006FloorsArchitecture Interior 75,042
CO277RENV2006Interior WallsArchitecture Interior 118,235
CO277RENV2006CeilingsArchitecture Interior 77,292
CO277RENV2006WiringElectrical Under 600 Volts 37,063
Total Planned activities for $921,340DGS0029 000
000DGS003111/28/05Date of Last Survey:10 RICHMOND TERRACE
STATEN ISLAND BOROUGH HALL -
PW77501EX2007Exterior WallsArchitecture Exterior 56,763
PWR0771242008FloorsArchitecture Interior 45,864
PWR0771242007CeilingsArchitecture Interior 82,990
Total Planned activities for $185,617DGS0031 000
000DGS003412/03/02Date of Last Survey:345 ADAMS STREET
KINGS SUPREME CIVIL COURT - OFFICE BUILDING
PW3221012002WiringElectrical Under 600 Volts 132,010
PW3221012002GeneratorsElectrical Stand-by Power 58,902
Total Planned activities for $190,912DGS0034 000
000DGS003510/13/04Date of Last Survey:253-256 BROADWAY
253-256 BROADWAY - FMR HOME LIFE INSURANCE BLDG.
PW357EXTR2006Exterior WallsArchitecture Exterior 216,400
PW357EXTR2006WindowsArchitecture Exterior 1,194,349
PW357STM2008Terminal DevicesMechanical Heating 49,705
Total Planned activities for $1,460,454DGS0035 000
Page T - 5
Appendix
FMS ID/ Budget Code
Agency Activity Year
DEPT. OF CITYWIDE ADMIN. SERV.
Type of Work
Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.
Agency Activity Funding
T
000DGS003912/04/02Date of Last Survey:67 TARGEE STREET
STATEN ISLAND CRIMINAL COURT -
CO275EXTR2006Exterior WallsArchitecture Exterior 151,988
Total Planned activities for $151,988DGS0039 000
000DGS004405/17/06Date of Last Survey:100 GOLD STREET
100 GOLD STREET - OFFICE BUILDING
PW77GLDEX2008Exterior WallsArchitecture Exterior 1,413,082
PW77GLDEX2008ParapetsArchitecture Exterior 375,610
PW77GLDRF2008RoofArchitecture Exterior 128,124
PW77GLD22010FloorsArchitecture Interior 131,991
PW77GLD22010Interior WallsArchitecture Interior 132,022
PW77GLD22010CeilingsArchitecture Interior 92,549
PW77GLDAC2009DistributionMechanical Ventilation 151,743
Total Planned activities for $2,425,121DGS0044 000
068DGSP02510/25/04Date of Last Survey:EAST RIVER 38TH. TO 41ST STS.
PIER, PLATFORM -
PT195-VAR2009DeckPiers Structural 1,743,622
PT195-VAR2009Pile CapsPiers Structural 634,308
PT195-VAR2009Piles and BracingPiers Structural 237,688
PT195-VAR2009FacingPiers Fender 857,841
PT195-VAR2009Wales and ChocksPiers Fender 324,735
PT195-VAR2009PilesPiers Fender 137,546
Total Planned activities for $3,935,740DGSP025 068
000DGSP05204/06/06Date of Last Survey:W 157 TO W 160 ST TWO B&LS
HIGH-LEVEL DECK (WHARF) W/RIPRAP - & TIMBER DOLPHINS. PIER
PT195-VAR2010DeckPiers Structural 42,305
PT195-VAR2010Piles and BracingPiers Structural 839,130
PT195-VAR2010Wales and ChocksPiers Fender 38,243
Total Planned activities for $919,678DGSP052 000
056DGSPR2510/25/04Date of Last Survey:E. RIVER, E. 73RD TO 75TH ST.
PLATFORM -
PT195-VAR2009DeckPiers Structural 321,947
Total Planned activities for $321,947DGSPR25 056
Total Planned Activities for : $42,531,389DEPT. OF CITYWIDE ADMIN. SERV.
Total Required for "State of Good Repair" for : DEPT. OF CITYWIDE ADMIN. SERV. $92,807,422
Page T - 6
Asset Name / Address Asset IDFiscal Year
of Survey
AppendixAssets to be replaced/abandoned:
Report of Asset Maintenance Schedule Activities not included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report
State of Good Repair Needs
U
CITY UNIVERSITY
LAGUARDIA COMMUNITY COLLEGE28-02 SKILLMAN AVENUE 2005 $4,261,010CUN0004.040
CENTER 4
Total Assets to be Replaced/Abandoned : $4,261,010CITY UNIVERSITY
HEALTH AND HOSPITALS CORP.
BELLEVUE HOSPITAL462 FIRST AVENUE 2005 $3,980,581HHC0001.060
BLDG J
BRONX MUNICIPAL HOSPITALPELHAM PKWY & EAST CHESTER RD. 2005 $8,002,875HHC0002.020
VAN ETTEN
BRONX MUNICIPAL HOSPITALPELHAM PKWY & EAST CHESTER RD. 2005 $364,751HHC0002.070
BLDG C - LAUNDRY BLDG.
BRONX MUNICIPAL HOSPITALPELHAM PKWY & EAST CHESTER RD. 2005 $213,199HHC0002.080
BLDG B - BOILER HOUSE
HARLEM HOSPITAL15 WEST 136 STREET 2006 $251,574HHC0008.020
KOUNTZ PAVILLION
HARLEM HOSPITAL16 WEST 137 STREET 2006 $1,829,909HHC0008.030
WOMEN'S PAVILLION
HARLEM HOSPITAL16 WEST 137 STREET 2006 $1,094,664HHC0008.040
PEDIATRIC BUILDING
HARLEM HOSPITAL27 WEST 136 STREET 2006 $1,154,205HHC0008.050
NEW NURSES RESIDENCE
HARLEM HOSPITAL27 WEST 136 STREET 2006 $936,718HHC0008.060
OLD NURSES RESIDENCE
KINGS COUNTY HOSPITAL CENTER451 CLARKSON AVENUE 2004 $1,484,225HHC0009.050
BLDG H - CANCER HOSPITAL
U - 1Page
Asset Name / Address Asset IDFiscal Year
of Survey
AppendixAssets to be replaced/abandoned:
Report of Asset Maintenance Schedule Activities not included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report
State of Good Repair Needs
U
KINGS COUNTY HOSPITAL CENTER451 CLARKSON AVENUE 2004 $2,779,255HHC0009.060
BLDG U - CLINIC
KINGS COUNTY HOSPITAL CENTER451 CLARKSON AVENUE 2004 $2,398,004HHC0009.090
BLDG P - PATHLOLOGY
KINGS COUNTY HOSPITAL CENTER451 CLARKSON AVENUE 2004 $295,419HHC0009.180
BLDG AA - ANNEX 3
QUEENS HOSPITAL82-68 164TH STREET 2005 $650,631HHC0014.120
MORGUE & LABS - H
QUEENS HOSPITAL82-68 164TH STREET 2005 $63,776HHC0014.160
GARAGE - G
Total Assets to be Replaced/Abandoned : $25,499,786HEALTH AND HOSPITALS CORP.
DEPT. OF PARKS & RECREATION
FLUSHING MEADOWS CORONA PARKGRAND CENTRAL PARKWAY 2005 $618,624PAR0019.035
ALLIED BUILDING - 0035
Total Assets to be Replaced/Abandoned : $618,624DEPT. OF PARKS & RECREATION
Total Assets to be Replaced/Abandoned : $30,379,420
U - 2Page