Atlantic Yards B2 FOIL, AY STV Report - 5-23-14 - Proposed Redactions_Redacted

Date post: 07-Aug-2018
Category:
Upload: norman-oder
View: 214 times
Download: 0 times
Share this document with a friend

of 6

Transcript
  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 5-23-14 - Proposed Redactions_Redacted

    1/12

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 5-23-14 - Proposed Redactions_Redacted

    2/12

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 5-23-14 - Proposed Redactions_Redacted

    3/12

      STV Construction, Inc.

    Project Date 5/19/2014Location Weekday Monday

    Client Report # 319

    Contract # Weather  

    Project # Temp. L/H 49-70

    STV Representative: Phil Amicone Wind Speed

    Work hours 7:30-4:30 Precip

    117 113 1.0

    930 0.126

    Tower Crane - Inactive for 26th weekday in a row

    Module Transportation - 0 mods delivered to site.

    Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 113 workdays = 1 mod per day so far. FCR informed on 5/13 that restart of mod installation pushed back to June 9 from June 2 and that it is expected

    installation will halt again after installation of the 6th-8th floors, possibly the 9th floor, waiting for another 3-floor backlog to be manufactured.

    Module Fabrication - Ongoing at Navy Yard, presumably, working on 7th floor mods with 142-man workforce. FCR reported on 5/2 that6th floor mods were all done, per schedule. On 5/13, a number of mods observed sitting outside Bldg 293 at the Navy Yard along with a host

    of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced production on 4/18 and will be

    finished by 5/14 but FCR informed on 5/13 that are running late and on 5/14 reported they will be finished the week of 5/21 and that the 8th

    floor mods have begun production.

    MEP - Sprinkler on 2nd/3rd and storm pipe on 1st floor as well as electrical conduit continued in basement levels, primarily upper level.

    Additional New Observations: Spraying on fireproofing (SOFP) continued behind curtains on west side of ground floor. No particulateescape observed.

    DAILY CONSTRUCTION REPORT

    Atlantic YardsB2ESD

    6717 Sunny, Clear  

    2114659

    Summary of Construction Activities

    5 mph gusting to 20 mph+

      0"

    Other -

    New Information received:

    New Information requested:

     At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog

    of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of

    erection so there will be no downtime during mod erection at the B2 site.

    Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.

    Previous Information received: Mod installation now not starting until June 9 per FCR. 7th floor mods due to be finished now the week

    of 5/21. FCR reiterates that 6th, 7th & 8th floors and Skanska adds poss bly the 9th floor will be installed after which job will shut down again.

    Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.

     Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th

    floor where mods are to be uninstalled.

    Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches tothe façade; interior: lack of completeness of mods.

    1/20/14 -

    y.

    Information previously requested: 5/1/14 -

    2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.

    4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.

    1 of 2

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 5-23-14 - Proposed Redactions_Redacted

    4/12

      STV Construction, Inc.

    Manpower on Site 10-20Navillus 0

    Stearns 0

    J SuporTrucking 0

    MEP trades 5-10

    Other 5-10

    Philip Amicone  5/19/2014 Date

    Manpower figure is rough approximation by STV.

    Potain Tower Crane (I)

    Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

    Special instruction(s) given:

    Prepared by Philip Amicone

    Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed

    Major Equipment on site (I = Inactive)

    2 of 2

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 5-23-14 - Proposed Redactions_Redacted

    5/12

      STV Construction, Inc.

    Project Date 5/20/2014Location Weekday Tuesday

    Client Report # 320

    Contract # Weather  

    Project # Temp. L/H 55-78

    STV Representative: Phil Amicone Wind Speed

    Work hours 7:30-4:30 Precip

    117 114 1.0

    930 0.126

    2114659

    Summary of Construction Activities

    5 mph gusting to 15 mph+

      0"

    Other -

    DAILY CONSTRUCTION REPORT

    Atlantic YardsB2ESD

    6717 Sunny, Clear  

    Tower Crane - Inactive for 27th weekday in a row

    Module Transportation - 0 mods delivered to site.

    Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 114 workdays = 1 mod per day so far. FCR informed on 5/13 that restart of mod installation pushed back to June 9 from June 2 and that it is expected

    installation will halt again after installation of the 6th-8th floors, possibly the 9th floor, waiting for another 3-floor backlog to be manufactured.

    Module Fabrication - Ongoing at Navy Yard, presumably, working on 7th floor mods with 142-man workforce. FCR reported on 5/2 that6th floor mods were all done, per schedule. On 5/13, a number of mods observed sitting outside Bldg 293 at the Navy Yard along with a host

    of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced production on 4/18 and will be

    finished by 5/14 but FCR informed on 5/13 that are running late and on 5/14 reported they will be finished the week of 5/21 and that the 8th

    floor mods have begun production.

    MEP - Sprinkler on 2nd/3rd and storm pipe on 1st floor as well as electrical conduit continued in basement levels, primarily upper level.

    Additional New Observations: Spraying on fireproofing (SOFP) continued behind curtains on west side of ground floor. No particulateescape observed. Removal of water damaged sheetrock in units continues.

    Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.

     Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th

    floor where mods are to be uninstalled.

    Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches tothe façade; interior: lack of completeness of mods.

    1/20/14 -

    Information previously requested: 5/1/14 -.

    2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.

    4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.

    New Information received:

    New Information requested:

     At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog

    of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of

    erection so there will be no downtime during mod erection at the B2 site.

    Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.

    Previous Information received: Mod installation now not starting until June 9 per FCR. 7th floor mods due to be finished now the week

    of 5/21. FCR reiterates that 6th, 7th & 8th floors and Skanska adds poss bly the 9th floor will be installed after which job will shut down again.

    1 of 2

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 5-23-14 - Proposed Redactions_Redacted

    6/12

      STV Construction, Inc.

    Manpower on Site 10-20Navillus 0

    Stearns 0

    J SuporTrucking 0

    MEP trades 5-10

    Other 5-10

    Philip Amicone  5/20/2014 Date

    Potain Tower Crane (I)

    Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

    Special instruction(s) given:

    Prepared by Philip Amicone

    Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed

    Major Equipment on site (I = Inactive)

    Manpower figure is rough approximation by STV.

    2 of 2

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 5-23-14 - Proposed Redactions_Redacted

    7/12

      STV Construction, Inc.

    Project Date 5/21/2014Location Weekday Wednesday

    Client Report # 321

    Contract # Weather  

    Project # Temp. L/H 64-74

    STV Representative: Phil Amicone Wind Speed

    Work hours 7:30-4:30 Precip

    117 115 1.0

    930 0.126

    2114659

    Summary of Construction Activities

    3 mph gusting to 7 mph+

      1/4"

    Other -

    DAILY CONSTRUCTION REPORT

    Atlantic YardsB2ESD

    6717 Cloudy

    Tower Crane - Inactive for 28th weekday in a row

    Module Transportation - 0 mods delivered to site.

    Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 115 workdays = 1 mod per day so far. FCR informed on 5/13 that restart of mod installation pushed back to June 9 from June 2 and that it is expected

    installation will halt again after installation of the 6th-8th floors, possibly the 9th floor, waiting for another 3-floor backlog to be manufactured.

    Module Fabrication - Ongoing at Navy Yard, presumably, working on 7th floor mods with 142-man workforce. FCR reported on 5/2 that6th floor mods were all done, per schedule. On 5/13, a number of mods observed sitting outside Bldg 293 at the Navy Yard along with a host

    of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced production on 4/18 and will be

    finished by 5/14 but FCR informed on 5/13 that are running late and on 5/14 reported they will be finished the week of 5/21 and that the 8th

    floor mods have begun production.

    MEP - Sprinkler on 2nd/3rd and storm pipe on 1st floor as well as electrical conduit continued in basement levels, primarily upper level.

    Additional New Observations: Spraying on fireproofing (SOFP) continued behind curtains on west side of ground floor. No particulateescape observed. Removal of water damaged sheetrock in units on 2nd floor continues.

    Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.

     Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th

    floor where mods are to be uninstalled.

    Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches tothe façade; interior: lack of completeness of mods.

    1/20/14 -

    Information previously requested: 5/1/14 -

    2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.

    4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.

    New Information received:

    New Information requested:

     At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog

    of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of

    erection so there will be no downtime during mod erection at the B2 site.

    Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.

    Previous Information received: Mod installation now not starting until June 9 per FCR. 7th floor mods due to be finished now the week

    of 5/21. FCR reiterates that 6th, 7th & 8th floors and Skanska adds poss bly the 9th floor will be installed after which job will shut down again.

    1 of 2

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 5-23-14 - Proposed Redactions_Redacted

    8/12

      STV Construction, Inc.

    Manpower on Site 10-20Navillus 0

    Stearns 0

    J SuporTrucking 0

    MEP trades 5-10

    Other 5-10

    Philip Amicone  5/21/2014 Date

    Potain Tower Crane (I)

    Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

    Special instruction(s) given:

    Prepared by Philip Amicone

    Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed

    Major Equipment on site (I = Inactive)

    Manpower figure is rough approximation by STV.

    2 of 2

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 5-23-14 - Proposed Redactions_Redacted

    9/12

      STV Construction, Inc.

    Project Date 5/22/2014Location Weekday Thursday

    Client Report # 322

    Contract # Weather  

    Project # Temp. L/H 59-66

    STV Representative: Phil Amicone Wind Speed

    Work hours 7:30-4:30 Precip

    117 116 1.0

    930 0.126

    2114659

    Summary of Construction Activities

    5 mph gusting to 7 mph+

      Trace

    Other -  No Con Ed. No Navillus (reportedly ran out of material). No sprinkler subcontractor.

    DAILY CONSTRUCTION REPORT

    Atlantic YardsB2ESD

    6717 Overcast with occasional showers

    Tower Crane - Inactive for 29th weekday in a row

    Module Transportation - 0 mods delivered to site.

    Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 116 workdays = 1 mod per day so far. FCR informed on 5/13 that restart of mod installation pushed back to June 9 from June 2 and that it is expected

    installation will halt again after installation of the 6th-8th floors, possibly the 9th floor, waiting for another 3-floor backlog to be manufactured.

    Module Fabrication - Ongoing at Navy Yard, presumably, working on 7th floor mods with 142-man workforce. FCR reported on 5/2 that6th floor mods were all done, per schedule. On 5/13, a number of mods observed sitting outside Bldg 293 at the Navy Yard along with a host

    of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced production on 4/18 and will be

    finished by 5/14 but FCR informed on 5/13 that are running late and on 5/14 reported they will be finished the week of 5/21 and that the 8th

    floor mods have begun production.

    MEP - Sprinkler on 2nd/3rd and storm pipe on 1st floor as well as electrical conduit continued in basement levels, primarily upper level.

    Additional New Observations: Spray-n fireproofing (SOFP) continued behind curtains on west side of ground floor until noon. Noparticulate escape observed. Primary machine broke down at approximately noon. Backup machine did not function adequately. Operator

    said the backup machine was not breaking the dry SOFP small enough and there was not enough pressure to properly spray the material on

    Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.

     Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th

    floor where mods are to be uninstalled.

    Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to

    the façade; interior: lack of completeness of mods.

    1/20/14 -

    Information previously requested: 5/1/14 -.

    2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.

    4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.

    New Information received:

    New Information requested:

     At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog

    of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of

    erection so there will be no downtime during mod erection at the B2 site.

      . .

    2nd floor continues.

    Previous Information received: Mod installation now not starting until June 9 per FCR. 7th floor mods due to be finished now the weekof 5/21. FCR reiterates that 6th, 7th & 8th floors and Skanska adds poss bly the 9th floor will be installed after which job will shut down again.

    1 of 2

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 5-23-14 - Proposed Redactions_Redacted

    10/12

      STV Construction, Inc.

    Manpower on Site 10-20

    Navillus 0

    Stearns 0

    J SuporTrucking 0

    MEP trades 5-10

    Other 5-10

    Philip Amicone 5/22/2014 Date

    Potain Tower Crane (I)

    Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

    Special instruction(s) given:

    Prepared by Philip Amicone

    Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed

    Major Equipment on site (I = Inactive)

    Manpower figure is rough approximation by STV.

    Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.

    2 of 2

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 5-23-14 - Proposed Redactions_Redacted

    11/12

      STV Construction, Inc.

    Project Date 5/23/2014Location Weekday Friday

    Client Report # 323

    Contract # Weather  

    Project # Temp. L/H 56-71

    STV Representative: Phil Amicone Wind Speed

    Work hours 7:30-4:30 Precip

    117 117 1.0

    930 0.126

    2114659

    Summary of Construction Activities

    2 mph gusting to 6 mph+

      1"

    Other -

    DAILY CONSTRUCTION REPORT

    Atlantic YardsB2ESD

    6717 Overcast with occasional showers

    Tower Crane - Inactive for 30th weekday in a row

    Module Transportation - 0 mods delivered to site.

    Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 117 workdays = 1 mod per day so far. FCR informed on 5/13 that restart of mod installation pushed back to June 9 from June 2 and that it is expected

    installation will halt again after installation of the 6th-8th floors, possibly the 9th floor, waiting for another 3-floor backlog to be manufactured.

    Module Fabrication - Ongoing at Navy Yard, presumably, working on 7th floor mods with 142-man workforce. FCR reported on 5/2 that6th floor mods were all done, per schedule. On 5/13, a number of mods observed sitting outside Bldg 293 at the Navy Yard along with a host

    of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced production on 4/18 and will be

    finished by 5/14 but FCR informed on 5/13 that are running late and on 5/14 reported they will be finished the week of 5/21 and that the 8th

    floor mods have begun production.

    MEP - Sprinkler on 2nd/3rd and storm pipe on 1st floor as well as electrical conduit continued in basement levels, primarily upper level.

    Additional New Observations: Spray-on fireproofing (SOFP) stopped for the week at approximately noon on Thursday. No sprayingoperation today. Resetting the containment tarps for spraying to continue moving east. Spraying expected to start again on Tuesday.

    Removal of water damaged sheetrock in units on 2nd floor continues.

    Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.

     Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th

    floor where mods are to be uninstalled.

    Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches tothe façade; interior: lack of completeness of mods.

    1/20/14 -

    Information previously requested: 5/1/14 -.

    2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.

    4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.

    New Information received:

    New Information requested:

     At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog

    of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of

    erection so there will be no downtime during mod erection at the B2 site.

    Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.

    Previous Information received: Mod installation now not starting until June 9 per FCR. 7th floor mods due to be finished now the weekof 5/21. FCR reiterates that 6th, 7th & 8th floors and Skanska adds poss bly the 9th floor will be installed after which job will shut down again.

    1 of 2

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 5-23-14 - Proposed Redactions_Redacted

    12/12

      STV Construction, Inc.

    Manpower on Site 10-20

    Navillus 0

    Stearns 0

    J SuporTrucking 0

    MEP trades 5-10

    Other 5-10

    Philip Amicone  5/23/2014 Date

    Potain Tower Crane (I)

    Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

    Special instruction(s) given:

    Prepared by Philip Amicone

    Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed

    Major Equipment on site (I = Inactive)

    Manpower figure is rough approximation by STV.


Recommended