+ All Categories
Home > Documents > Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset...

Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset...

Date post: 10-Aug-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
62
Attachment 5 Asset management and governance 30 June 2017 201823 Water and Sewerage Price Proposal
Transcript
Page 1: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Attachment 5

Asset management and governance

30 June 2017

2018–23 Water and Sewerage Price Proposal

Page 2: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page i

© 2017 Icon Water Limited (ABN 86 069 381 960)

This publication is copyright and is the property of Icon Water Limited.

Page 3: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page ii

Table of contents

1 Overview ............................................................................................................. 1

2 Asset management capability............................................................................ 2

3 Asset management system ................................................................................ 6

3.1 Customer and stakeholder needs ......................................................................................... 7

3.2 Statement of Corporate Intent .............................................................................................. 8

3.3 Asset management policy .................................................................................................... 8

3.4 Strategic Asset Management Plan ....................................................................................... 9

3.5 Asset management plans ................................................................................................... 13

3.6 Performance monitoring ..................................................................................................... 28

4 Governance ....................................................................................................... 29

4.1 Integrated organisational management system ................................................................. 29

4.2 Responsibilities and authorities for key functions ............................................................... 31

4.3 Investment planning and delivery ....................................................................................... 34

5 Asset management system improvements ..................................................... 39

5.1 Summary of target improvements ...................................................................................... 40

Appendix 1 Identified performance gaps.................................................................... 42

Appendix 2 Strategic Asset Management Plan .......................................................... 44

Appendix 3 Collect Water Asset Management Plan ................................................... 45

Appendix 4 Treat Water Asset Management Plan ..................................................... 46

Appendix 5 Distribute Water Asset Management Plan .............................................. 47

Appendix 6 Collect Sewerage Asset Management Plan ............................................ 48

Appendix 7 Treat Sewerage Asset Management Plan .............................................. 49

Appendix 8 Discharge Sewerage Asset Management Plan ....................................... 50

Appendix 9 Land and Buildings Asset Management Plan......................................... 51

Appendix 10 Vehicles and Plant Asset Management Plan .......................................... 52

Appendix 11 ICT Asset Management Plan.................................................................... 53

Page 4: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page iii

List of tables

Table 3-1: Information systems and functions................................................................................ 26

Table 4-1: Asset management, governance processes and supporting documents ..................... 30

Table 4-2: Investment process governance structure .................................................................... 33

Table 4-3: Project types and approval path criteria ........................................................................ 35

Table 4-4: Documentation for the capital planning process ........................................................... 36

Table 5-1: Icon Water IAM’s asset management subject maturity target state .............................. 39

List of figures

Figure 2-1: Icon Water's integrated organisational management system ......................................... 2

Figure 2-2: The IAM Asset Management Maturity Framework .......................................................... 3

Figure 2-3: Asset management capabilities improvements since 2013 ............................................ 4

Figure 3-1: Icon Water's Asset management system ........................................................................ 6

Figure 3-2: Icon Water’s strategic objectives ..................................................................................... 8

Figure 3-3: ISO 55001 Roles and Responsibilities ............................................................................ 9

Figure 3-4: Icon Water's asset management objectives drivers ...................................................... 10

Figure 3-5: Asset Management Objectives Hierarchy ..................................................................... 10

Figure 3-6: Tier 1 asset management objectives ............................................................................ 11

Figure 3-7: Projected greenfield developments in the ACT ............................................................. 12

Figure 3-8: Asset investment decision factors ................................................................................. 13

Figure 3-9: Icon Water's asset value chain decomposition ............................................................. 14

Figure 3-10: Icon Water asset breakdown by criticality ..................................................................... 15

Figure 3-11: Icon Water asset condition ............................................................................................ 16

Figure 3-12: Investment initiation key considerations ....................................................................... 18

Figure 3-13: Primary and secondary project criteria prioritisation ..................................................... 19

Figure 3-14: Asset delivery activities ................................................................................................. 21

Figure 3-15: Example of estimation framework ................................................................................. 23

Figure 3-16: Main elements of integrated asset support ................................................................... 24

Figure 3-17: Asset management information system ........................................................................ 26

Figure 4-1: Organisational structure and asset management responsibilities ................................ 32

Figure 4-2: Guiding principle focus areas for Icon Water’s IPaD .................................................... 34

Figure 4-3: Investment planning and delivery lifecycle .................................................................... 35

Figure 4-4: Icon Water Sustainability Scorecard Factors ................................................................ 37

Figure 5-1: Institute of Asset Management Conceptual Model for Asset Management .................. 39

Figure 5-2: Asset management system improvements ................................................................... 41

List of boxes

Box 1-1: ICRC Act 1997 price direction provisions ............................................................................. 1

Box 2-1: ISO 55000 series of international standards ........................................................................ 3

Page 5: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset
Page 6: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 1

1 Overview

It is widely accepted that effective implementation of a robust asset management framework

maximises the value that an organisation produces from its assets. Accordingly, a number of national

and international regulators have linked the extent of regulation oversight to an organisation’s asset

management maturity. In the ACT, a review of the key elements of a robust asset management

framework is required by the Independent Competition and Regulatory Commission Act 1997

(ICRC Act) (see Box 1-1).

Box 1-1: ICRC Act 1997 price direction provisions1

Section 20 Directions about prices

(2) In making a decision under subsection (1), the commission must have regard to—

(b) standards of quality, reliability and safety of the regulated services; and

(e) the cost of providing the regulated services

Source: ACT Government (1997): s20(2).

Icon Water’s asset management system enables reliable and cost effective service delivery.

Management of our assets achieves business goals and creates value for the business and our

community by investing sustainably in the water and sewerage network.

The business operations of Icon Water are maturing in response to changes in customer

expectations, commercial pressures and the regulatory environment. The business transformation

initiatives undertaken since 2013 have significantly improved Icon Water’s ability to manage its water

and sewerage assets efficiently and effectively and provided a foundation for Icon Water to move to

international best practice.

Our asset management system considers our current and future asset performance and risks and

implements cost effective programs that provide the appropriate balance between each of these

criteria. Investment planning and delivery is reliant on the efficient whole of asset life cost solution.

1 Act Government, 1997. Extract from ICRC Act 1997. R23. Effective: 1 September 2016.

Page 7: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 2

2 Asset management capability

Icon Water is an asset intensive company, with over $2 billion in water and sewerage assets. The

management of these assets through their lifecycle influences the financial, environmental and social

performance of our organisation significantly. In addition, our community, customers, shareholders

and regulators expect us to manage and operate these assets as efficiently as any comparable

business.

Asset management is a core business function undertaken as a subset of an integrated organisational

management system as illustrated in Figure 2-1. Facets of the integrated organisational management

systems such as leadership, culture, risk, safety and environment align, guide and support Icon

Water’s asset management system.

Figure 2-1: Icon Water's integrated organisational management system

Source: Icon Water.

A new operating model has been progressively employed during the 2013-18 regulatory period to

enhance asset management capability throughout the organisation. Icon Water’s approach to asset

management is developing to align with the recent International Organization for Standardization

(ISO) 55000 series of international standards for the management of infrastructure assets (ISO 2014)

and the Institute of Asset Management’s (IAM) Asset Management Maturity Framework (2015) (see

Box 2-1 and Figure 2-2). Together these frameworks build on well-established asset management

practices and incorporate the latest international contemporary thinking on best practice holistic asset

management.

Integrated Organisational

Management System

Asset management System

Asset Portfolio

Page 8: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 3

Box 2-1: ISO 55000 series of international standards

The ISO is a worldwide federation of national standards bodies. The ISO 55000 series of

international standards represent common practices that can be applied in a management system for

asset management, including:

ISO 55000 - Asset management–Overview, principles and terminology: provides an overview

of the subject of asset management and standard terms and definitions.

ISO 55001 - Asset management– Requirements: details requirements specification for an

integrated, effective management system for asset management.

ISO 55002 - Asset management–Guidelines on the application of ISO 55001: provides

guidance for the implementation of such a management system.

Source: ISO 5500, 55001, 55002.

Figure 2-2: The IAM Asset Management Maturity Framework

Source: Asset Management Maturity Framework (2015).

During 2013–18, planning and service delivery asset management capabilities in Icon Water have

improved in response to changes in our operating environment and future demands. The initiatives to

improve practices form part of our organisational structure and our asset management system. Key

elements of the enhanced asset management capability implemented in 2013–18 are detailed below

and shown in Figure 2-3.

People

Senior leadership have demonstrated support for the importance of asset management within

the organisation by the creation and implementation of a dedicated asset management strategy

and policy.

Icon Water has invested in our people and culture during the 2013–18 period to enhance our

asset management capability to support our progression towards target state asset

management maturity.

Processes

Since 2013 Icon Water mapped internal processes to align to ISO 55000 and the IAM Asset

Management Maturity Framework (2015). This work has resulted in a revised asset management

system and framework that:

Page 9: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 4

balances cost, risk and performance to optimise decisions on the capital works program

begins to work with our customers to understand and adjust our service level to respond to their

stated preferences with prudent consideration of the balance between cost and sustainable

levels of service (refer to Attachment 3: Service standards)

formalises asset maintenance to depend on stated function and required system reliability

provides industry leading capital works planning (section 3.5.7), delivery (section 3.5.13) and

governance processes (section 4).2

Technology

implemented programs to replace aging information technology assets that will assist in

improved work delivery packaging and scheduling and improve asset data availability and

accuracy

implemented a number of data analytical tools to aid in the understanding of complex

relationships between asset data to inform asset planning decisions

developed a prioritisation tool for consideration of the balance of cost and levels of service to

inform projects and program priorities.

Figure 2-3: Asset management capabilities improvements since 2013

Source: Icon Water.

2 Icon Water’s investment planning and delivery process was acknowledged by other water utilities as an example of a Leading Practice in the recent WSAA asset management benchmarking.

Page 10: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 5

In a recent review of capital expenditure governance and prioritisation the consultant3 made the

following comments:

“It is evident that the organisational changes have been supported by cultural change with an

increased consideration across the business to ensure that capital expenditure is justified and is

able to be linked to service delivery.”

“We have seen considerable uplift across Icon Water in capital expenditure development arising

from the redesign of the asset management framework. Particularly, a cultural change as to the

importance of rigorously justifying expenditure and challenging the status quo is evident. “

“Icon Water’s efforts to have a robust and consistent capital program for the forward regulatory

period demonstrates that it is committed to the regulatory process.”

Icon Water is committed to continuously improving our asset management system; details for future

improvement are included in section 5 of this attachment.

3 2017, Cardno, Review of Icon Water capital expenditure governance and prioritisation.

Page 11: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 6

3 Asset management system

This attachment explains how Icon Water’s asset management system facilitates efficient capital (refer to

Attachment 6: Capital expenditure) and operating (Attachment 7: Operating expenditure) investment

programs. This attachment explains our asset management system and the application of our internal

capabilities for planning and service delivery.

As shown in Figure 2-1, Icon Water’s asset management system is incorporated into the existing integrated

organisational management system that enables certification to AS/NZS ISO 9001 (quality), AS/NZS ISO

14001 (environment), AS/NZS 4801 (safety) and the Codex Alimentarius (drinking water quality).

Icon Water is committed to operating and continually improving a suitably resourced asset management

system that aligns with the ISO55001:2014 Asset management – Management systems: Requirements (ISO

55001).

The asset management system describes the interlinked processes and the series of artefacts that support

and document asset management objectives and decision-making throughout the asset lifecycle. Figure 3-1

shows the relationship between the key elements of Icon Water’s asset management system.

Figure 3-1: Icon Water's Asset management system

The following section describes the key elements of the asset management system in the order presented in

Figure 3-1.

Page 12: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 7

3.1 Customer and stakeholder needs

The value proposition offered by Icon Water’s assets differs depending on the perspective of the

varied stakeholders of the organisation. Customers demand a reliable high quality drinking water

service that provides sufficient pressure and flow, and technical regulations support this. Customers

also require the provision of environmentally responsible sanitation services. Our shareholders are

interested in meeting all its technical obligations an industry comparable and sustainable rate of return

(amongst other things).

Therefore, Icon Water must consider a variety of stakeholder values when determining the right

balance between levels of service and cost across its asset base.

3.1.1 Customer needs

Customer engagement represents an integral component of our approach to service delivery, and

consequently shapes decision making on asset performance. We engage with customers using

market research and willingness-to-pay surveys and through the Community Consultative Forum to

understand their needs and what they value. The top five things our customers told us they value, in

order of priority are:

These values inform the setting of our asset management objectives. Attachment 3: Service

standards describes how we engage with our customers and how we are increasingly using this

research to influence asset management decisions.

3.1.2 Legislation and regulation

Icon Water manages assets within a complex regulatory framework that includes ACT, NSW and

Commonwealth requirements (74 acts and codes). Details of the legislative framework are included in

Attachment 1: Context and background.

The key Acts that are considered in the development of asset management objectives are listed

below.

Environment Protection Act 1997 (ACT)

Independent Competition and Regulatory Commission Act 1997 (ACT)

Protection of the Environment (Operations) Act 1997 (NSW)

Public Health Act 1997 (ACT)

Territory-owned Corporations Act 1990 (ACT)

Utilities Act 2000 (ACT)

Utilities (Technical Regulation) Act 2014 (ACT)

Water and Sewerage Act 2000 (ACT)

Water Resources Act 2007 (ACT).

Page 13: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 8

3.2 Statement of Corporate Intent

Icon Water’s Statement of Corporate Intent (SCI) (sets the overarching strategic goal and objectives

for the organisation founded on the objectives of the Territory-owned Corporations Act 1990 (ACT).

Our strategic goal to be the premier, most trusted water utility represents an ambitious, long-term

outcome that relies on coordinated collective effort from across the organisation.

To become premier and trusted means putting customers at the centre of everything we do.

Understanding customer needs and expectations involves continually improving business processes

to deliver value to customers. This will only be achieved through developing our people whilst

improving our processes and technology. 3-2 illustrates Icon Water’s strategic objectives and

outcomes detailed in the SCI.

Figure 3-2: Icon Water’s strategic objectives

Source: Icon Water.

Further context on Icon Water’s mission, objectives and service standards is provided in

Attachment 1: Context and background and Attachment 3: Service standards.

3.3 Asset management policy

The Asset management policy (Icon Water 2014) documents Icon Water’s commitment to asset

management. It identifies asset management principles and gives high-level direction on asset

management practices. The policy sets out requirements for the asset management system which

align to ISO 55001 and defines the key roles and responsibilities of Asset Owner, Asset Manager and

Asset Service Provider as shown in Figure 3-3.

Page 14: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 9

Figure 3-3: ISO 55001 Roles and Responsibilities

3.4 Strategic Asset Management Plan

Icon Water’s Strategic Asset Management Plan (SAMP) (Icon Water, 2017) describes the principles,

governance, systems and objectives of asset management which have been adopted by Icon Water.

The purpose of the SAMP is to provide a clear framework for strategic asset decision making that

aligns with achievement of wider corporate performance objectives and targets set out in the SCI. The

SAMP will ensure that strategic asset decisions follow clear and comprehensive processes that reflect

best practice asset management principles and practices.

This SAMP defines the major processes and procedures used for the planning, development,

operation, maintenance and disposal of Icon Water assets. Furthermore, the SAMP also provides

guidance on the continuous improvement initiatives for the asset management system.

This will ensure that Icon Water’s strategic asset decision-making processes achieve an agreed

balance of cost, risk and asset performance that meets customer service delivery expectations.

The SAMP is provided at Appendix 2 to this attachment.

3.4.1 Asset management objectives

Icon Water has developed asset management objectives derived from:

1. Customer values

2. The strategic goals and objectives set out in the SCI

3. Specific goals set out within the Enterprise Asset Management Strategy (Icon Water 2017)

4. Adherence to relevant legislation, codes, licenses and technical standards

5. Demand requirement forecasts

6. Application of Icon Water corporate risk appetite

7. Analysis of current and future business drivers and impacts from the operating environment.

Page 15: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 10

Figure 3-4: Icon Water's asset management objectives drivers

Figure 3-5 demonstrates the processes of analysing competing requirements and converting them

into asset management objectives for water and sewerage assets. These are described in terms of a

tiered hierarchy that is based on a logical decomposition of the assets. The functional hierarchical

approach establishes specific cost, risk and performance requirements at each level which are used

as the foundation for asset decisions on capital, maintenance and operating plans.

Embedded within the cascading asset management objectives are the requirements and support of

Icon Water’s integrated organisational management system (section 4.1).

Figure 3-5: Asset Management Objectives Hierarchy

Customer Values, SCI, Legislation, Demand, Risk

Appetite, Business Drivers, Operating Environment

Asset management objectives

Page 16: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 11

Figure 3-6: Tier 1 asset management objectives

Cost Risk Performance

Water Supply

Deliver a sustainable

financial return

Comply with corporate

Risk Management

Framework including

personnel and energy

al safety requirements

Meet water quality,

demand, pressure and

flow requirements as per

Acts, Codes, Licences

and customer

requirements

Sewerage System

Deliver a sustainable

financial return

Comply with corporate

Risk Management

Framework including

personnel and

environmental safety

requirements

Meet network flow

capacity, licenced

discharge and

environmental protection

requirements and

availability requirements

as per Acts, codes and

licences and customer

requirements

3.4.2 Operating environment

Icon Water’s assets consistently deliver safe drinking water and reliable sewerage services to a

growing community of over 393,000 people. We continue to ensure the effectiveness of our asset

base both to meet current need, and to support future requirements based on predicted population

growth, varying climate scenarios, ageing infrastructure and other factors considered as part of our

annual external environmental scan.

Attachment 1: Context and background outlines our current operating environment and some of the

key challenges facing Icon Water over the next five years and into the future. As we continue to

transform our business to becoming more customer-centric, we will become more reliant on real-time

data to enable efficient asset management planning to drive cost efficiencies across the business.

3.4.3 Long-term demand

Icon Water regularly updates demand and supply forecasts for water and sewerage assets to ensure

the ability to meet service requirements now and into the future. These forecasts consider multiple

data sets such as population projections, climate forecasts, technology change and government

policy and strategy.The ACT Government projects urban population growth to continue at around 1.5

per cent per annum to 2036, with a focus on the development fronts shown in Figure 3-7.

Personnel Safety

Page 17: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 12

Figure 3-7: Projected greenfield developments in the ACT

Source: ACT Government EPSDD (2012).

The ACT Government intend to supply around half of the required new housing via greenfield

development with the remaining half to be delivered through an increased focus on urban

intensification in town centres and major transport routes. In particular, the increased focus on infill

(brownfield) developments will place greater capacity constraints on Icon Water’s existing assets that

will trigger capacity augmentations over time.

In general, overall per capita water usage continues to decline although population growth continues

to match this, leading to predicted slow increases in both required water and sewage treatment

demand over the medium to long term.

Icon Water reviews available data sets and makes a determination whether the current asset base

can accommodate the demand for water and sewerage services.

Page 18: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 13

3.5 Asset management plans

Our asset management planning involves defining the optimal balance of cost, risk and performance

to maximise customer value of our assets. Icon Water’s asset management plans provide an

overview of the lifecycle asset activities required to maintain customer service levels. Figure 3-8

shows the key factors that are considered in the determination of the optimal balance of investment

across our asset portfolio.

Figure 3-8: Asset investment decision factors

Source: Icon Water.

3.5.1 Asset portfolio overview

Icon Water is one of the few large water utilities in Australia that manage a vertically integrated asset

portfolio for the provision of drinking water supply and sewerage services. The major components of

the diverse array of assets within Icon Water’s portfolio are shown in Figure 3-9. This figure shows the

interconnectedness of Icon Water’s asset portfolio and their role in the provision of water and

sewerage services.

Icon Water’s asset management system recognises nine separate asset classes: six related to its

water and sewerage assets, with a further three relating to ‘common assets.’ Common assets are our

mobile plant and vehicles, land and buildings, and information and communication technology (ICT)

assets. Asset management plans for each asset class contain information on the prudent and efficient

plans to manage that specific grouping of assets through its lifecycle.

Copies of the nine asset management plans are provided to the ICRC as appendices 3 to 9 of this

Attachment as commercial-in-confidence documents.

3.5.2 Asset criticality

Icon Water’s asset portfolio has a varying level of importance on individual assets dependent on their

function in the provision of our services to our customers. It is for this reason that we intimately

Page 19: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 14

understand the relative importance of individual assets within our system and assign them varying

levels of criticality.

At Icon Water, this criticality (or risk to service provision) is defined as availability and reliability

targets. This classification is a key factor in deciding on the level of investment (either maintenance,

operations, renewal or augmentation) undertaken on assets. Assets with higher criticality will have a

greater impact (and therefore risk) on our ability to maintain our level of service to our customers and

therefore require a greater level of investment.

Figure 3-9: Icon Water's asset value chain decomposition

By way of example, Figure 3-10 shows the relative level of asset criticality across our three of our

water and sewerage asset classes.

Page 20: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 15

Figure 3-10: Icon Water asset breakdown by criticality

3.5.3 Asset condition

Knowledge of the current condition of our asset portfolio is an important consideration in determining

whether our assets can meet and will continue to maintain our customer service levels. Icon Water

undertakes comprehensive condition assessment and monitoring for selected asset classes that

provide a detailed understanding of the condition of our asset base.

The methodology for inspections follows the Institute of Public Works Engineering Australasia (2012)

practice note and preamble.

Asset monitoring and inspection methods vary with the type of assets involved, their criticality,

accessibility and the inspection methodology. Assets are given a condition score between 1 (good

condition) to 5 (poor condition and unsupported). Figure 3-11 shows the condition of the overall water

and sewerage asset systems.

Page 21: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 16

Figure 3-11: Icon Water asset condition

Source: Icon Water (2017).

3.5.4 Asset performance

Icon Water undertakes assessments to determine whether our assets can meet current and future

asset performance requirements. In doing so, future demand, levels of service and regulatory

requirements are considered and these are informed by Icon Water’s strategic planning (section

3.4.1). The capital works program shown in Attachment 6: Capital expenditure details Icon Water’s

plans to resolve identified performance gaps as detailed in Appendix 1.

3.5.5 Predictive modelling

Icon Water utilises a number of advanced data analytics tools to aid in the understanding of complex

relationships between asset data to inform asset planning decisions. Examples where predictive

modelling is used to inform asset planning decisions include:

• Forward projections on water storage levels to help inform when new

water sources will be required and to understand current and future water

security scenarios.

• Operational decisions on which water source to utilise by balancing cost to

customers (a combination of operating costs and the cost to the

community of water restrictions) and the risk to overall urban water

security.

• Understanding the complex relationships between cost and levels of

service of our water reticulation assets. This enabled Icon Water to make

informed decisions regarding customer preference influences on the water

mains renewal program (refer to Attachment 3: Service standards).

0%

20%

40%

60%

80%

1 2 3 4 5

% o

f W

ater

an

d S

ewer

Ass

et B

ase

Asset Condition Rating

Asset Condition

Assets in GoodCondition

Assets in Poor

Condition

0%

5%

10%

15%

20%

5

15

25

35

45

55

65

75

85

95

>1

00

% o

f W

ater

an

d S

ewer

Ass

et B

ase

Assessed Remaining Life (years)

Remaining Life

Page 22: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 17

• Utilisation of award winning predictive modelling to understand the

complex relationships between cost and levels of service of our sewerage

reticulation assets.4 This enabled Icon Water to make informed decisions

regarding customer preference influences on our proactive sewerage

reticulation maintenance and capital programs (refer to Attachment 3:

Service standards).

3.5.6 Lifecycle costing

Maintaining our level of service requires appropriate investment across the whole of the asset

lifecycle. Icon Water recognises the importance of managing its assets from a ‘whole of asset life’

perspective. Our investments are planned and monitored from the initial planning through design,

construction, maintenance, renewal until final decommissioning and disposal. For example, the

operating, maintenance and integrated support costs are considered in the asset acquisition phase

(not just the capital cost) as part of the overall assessment of the most prudent and efficient project

solution.

3.5.7 Capital works planning

The key factors identified in Figure 3-12 are considered in the determination of whether there is a

need to modify, augment or construct a new asset. The factors that are considered differ depending

on the capital investment driver. Capital works are undertaken only when there is not a cost-effective

lifecycle operational alternative available.

4 Asset Management Council, 2017: Cost Risk Performance Award.

Page 23: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 18

Figure 3-12: Investment initiation key considerations

Capital investment decisions involve identifying, quantifying and influencing the current and desired

levels of costs, risks, and performance. Alternative options (including do nothing, maintenance and

operating options) for achieving the desired set of asset management objectives are analysed and

evaluated. The option that best represents the appropriate balance of lifecycle cost, risk and impacts

on established performance measures. This forms the basis of our initial capital works program. The

initial capital works program is then prioritised (section 3.5.8) and then run against a series of

scenarios (section 3.5.11) prior to finalisation of the most prudent and efficient program that provides

the appropriate balance of cost and levels of service for Icon Water’s asset portfolio.

Legislative Requirements

Customer Engagement

Investment Factors

Investment Drivers

Growth Investment Plans

Renewal Investment Plans

Efficiency Investment Plans

Regulation Investment Plans

Operation & Maintenance

Investment Plans

Demand

Land Releases

Asset Criticality

Asset Condition

Price Changes

Regulations Changes

Asset Performance

Asset Criticality

Asset Condition

Asset Performance

Predictive Modelling

Predictive Modelling

Quality Drinking Water

Reliable supply

Affordable Pricing

Customer Service

Environmental Sustainabilty

Technology

Risk

Predictive Modelling

Asset Performance

Asset Criticality

Asset Condition

Predictive Modelling

Asset Management Plans Program

of work

Scen

ario

Mo

del

ling

Pru

den

cy &

Eff

icie

ncy

Te

stin

g

Page 24: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 19

3.5.8 Investment prioritisation

Icon Water uses a quantitative prioritisation tool to identify all potential projects that contribute to the

prudence and efficiency of its works program.

The tool requires a panel of assessors (subject matter experts) to discuss and rank the priority of

projects by categorising projects by capex driver and then applying a set of criteria based on the

driver to each project. The criteria and scoring are aligned with the consequence definitions and

ratings from the Icon Water risk assessment tables. Cross-business input is sought in the prioritisation

of projects.

The results of the selection of projects is again assessed for primary and secondary criteria by a

separate group with input from across the business. This verification is used to update earlier priority

scoring where variance is encountered.

The Investment Review Committee (IRC) has oversight and responsibility for the prioritisation of the

works program. This approach to investment planning aligns with the ISO 55000 series of

international standards for the management of infrastructure assets.

Figure 3-13: Primary and secondary project criteria prioritisation

3.5.9 Maintenance planning

Icon Water identifies its planned maintenance works through a proactive inspection schedule. This

involves assessing the condition of the asset (including historical failure information) against

documented level of service criteria and prioritising, scheduling and actioning the work to be

undertaken within documented time frames.

Asset reliability strategy, maintenance standards and procedures have been developed for defect

elimination, analysis of failures, condition monitoring, and improvement to maintenance strategies.

These are routinely updated to continuously improve cost efficiency, plant reliability and performance.

Icon Water undertakes comprehensive condition assessment and monitoring for selected asset

classes that provide a detailed understanding of the condition and performance of our assets. Asset

monitoring and inspection methods reflect functional criticality of assets and asset age. The approach

promotes proactive maintenance rather than reliance on manufacturer specifications for maintenance.

Operating and maintenance requirements are determined to reduce the severity of the effect of

specific failure modes, which involves:

identifying potential failure modes for a product or process;

assessing the risk associated with those failure modes, to rank the issues in terms of

importance; and

determining and carrying out corrective actions to address the most serious concerns.

Page 25: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 20

The method identifies weak areas in asset design, the safety-critical components, or critical

maintenance and test procedures. The process enables the best maintenance to be determined to

achieve design reliability at minimum cost.

Figure 3-13 summarises at a high level the key factors that are considered in the determination of the

maintenance investment program.

Icon Water is currently renewing its works management system. The renewed system will provide a

greater data granularity and this will inform enhanced asset maintenance investment decisions.

3.5.10 Operations planning

The efficient and effective operation of water and sewerage assets is a core function for Icon Water.

To enable this throughout the asset lifecycle, a process operating plan (POP) is developed for asset

systems.

The POP is developed by defining the asset management objectives including function, performance

requirements, functional significance, consequences of asset failure, maximum outage times for asset

per functional area, operating parameters and limitations (summarised in section 3.6 and Figure

3-12). The POP also considers interactions with capital project delivery work that may have an impact

on the process performance and could require temporary flows or parameter changes.

The POP provides direction to treatment and network operations personnel, defining the operational

parameters, required operational activities and guidance for planned responses to abnormal events

(wet weather events). The operators use the POP in planning the delivery of their daily operating

activities.

Lessons learnt from process trend analysis and asset performance during abnormal events are

captured as feedback to continuously improve the POP and optimise the performance envelope for

the assets.

3.5.11 Investment scenario modelling

High cost projects (those with a forecast spend of over $2.5 million per annum) across all asset

classes and expenditure types are analysed through the program of works balance model.

This model is based on the outcomes of facilitated workshops with subject matter experts to map

projects to their impacts on Icon Water (levels of service measured against key performance

indicators (KPIs) and risk. The model develops optimised cost-saving scenarios at a minimum impact

to risk or KPIs.

The scenarios are provided to the IRC to determine the appropriate investment that balances cost,

risk and performance against Icon Water’s entire asset portfolio. The outcome of the IRC is then the

basis of the program of work that is included in asset management plans.

3.5.12 Asset delivery

Icon Water’s primary role is to deliver cost-effective, quality safe drinking water and collect and treat

sewage for its customers. These services utilise assets and it is our fundamental requirement that an

efficient and effective approach to the management of these assets is applied through the asset

lifecycle activities that is acquisition, maintenance, operation through to disposal as shown in Figure

3-14.

Page 26: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 21

Figure 3-14: Asset delivery activities

3.5.13 Asset acquisition

Icon Water acquires assets through three main mechanisms:

developers construct and pay for the assets and gift them to Icon Water,

third parties construct assets and Icon Water pay for them,

Icon Water constructs the asset.

Irrespective of the delivery, the following processes are applied to ensure that all assets met the

requirements of Icon Water and will enable Icon Water to continue to provide reliable service to

customers:

The asset acquisition process is aligned to the international Project Management

Body of Knowledge (Project Management Institute, 1996) framework. To embed this

with the business, a program management office has been created. This office provides

greater efficiency in project delivery by standardisation of approaches and templates. A

tiered governance approach to is followed to ensure that the level of governance matches

the complexity and business risk of the project. The project management office regularly

benchmarks Icon Water’s project delivery process and systems with other organisations.

Icon Water also participates in Water Services Association Australia (WSAA) and utility

benchmarking.

Page 27: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 22

The design of all assets is considered and accepted by the business prior to

construction. The design of new assets is guided and reviewed using standard engineering

design tools to identify and minimise safety and operability hazards5 at several points as the

design evolves. To ensure ongoing efficiency in maintenance and operations and to achieve

efficiency during asset creation, technical standards, and preferred equipped lists are utilised

as much as possible. The standards used to govern project design reduce complexity and

minimise costs of managing assts. Technical codes set out requirements for the design,

operation and maintenance of the water supply and sewerage assets, for customer protection

and for emergency management For larger, complex projects, specific value management

studies are included.

Asset is accepted and integrated within the business: The construction of the asset is

monitored to ensure that the quality, reliability and safety requirements of Icon Water are met.

During commissioning of the asset, it is tested to ensure that it meets the ongoing requirements

of the system. After commissioning, the asset is integrated into the standard operations and

maintenance of the business.

The majority (over 80 per cent value of new assets)

of asset acquisition is managed by Icon Water with

dedicated business areas responsible for this

function. All acquisition managed by Icon Water

occurs as per Icon Water’s investment planning and

delivery (IPaD) process described in section 4.3.

This gated process ensures that the full budget on a

project is not finally approved and released until

appropriate planning is in place and there is budget

certainty. This allows for scrutiny of procurement

methods.

Once a project is justified to be implemented, the

method by which it is delivered is decided in order to

efficiently manage time, cost and quality constraints

for optimal delivery performance. Each project will

be assessed for opportunities to leverage off

existing investments or operational dependencies in

addition to optimising resource requirements.

This evaluation of delivery method and allocation of

resources includes:

Project bundling to reduce management

overheads.

Project ‘unpacking’ where components of

scope are removed or planned to be delivered in

isolation for either efficiency or risk management

purposes.

Delivery allocated to the team with the relevant expertise.

5 Icon Water use both Hazard and Operability Assessments (HAZOP) and Construction Hazard Assessment Implication Reviews (CHAIRs) through the design of assets.

Example of why monitoring asset

installation is important: (Water Meters)

Ensuring customers can isolate

supply in case of a change to internal

plumbing

Ongoing access by the meter reader

which enables correct meter reads

Safer and faster meter replacement,

which decreases outage time

Incorrect installation could lead to

damage to meter, vehicles or

creation of a pedestrian hazard.

Adequate Installation

Poor Installation

Page 28: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 23

Icon Water has recently implemented an estimation framework to support the investment planning

and development (IPaD) process in order to provide a consistent approach to project estimation and

provide guidance on the level of detail that is expected in each stage of the project (see

).

This can include external peer review of estimates on larger projects.

Figure 3-15: Example of estimation framework

Each project stage has an estimate accuracy percentage that is a guideline for realistic expectations.

This includes guidelines on calculating contingency. If the percentage of contingency requested falls

outside this guideline then additional justification is expected to be provided.

A contingency management guideline has been developed to assist in communicating the definition of

contingency management as well as describing its usage and controls in the IPaD process. It

proposes that contingency management is developed based on quantifiable analysis that is in enough

detail relevant to the project complexity. Contingency can only be accessed after approval from the

Page 29: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 24

appropriate manager. Access to higher levels of contingency via a management reserve are at the

discretion of the IRC.

3.5.14 Integrated asset support

Icon Water applies a structured approach in the integration of elements that are essential to support

assets throughout their lifecycle. The approach focusses on early consideration of risk mitigation in

the asset lifecycle and provides:

the support needed for the system design to be effective and efficient

a structured approach to increase efficiency of maintenance & operations

reduced cost of providing support by preplanning all aspects of support.

The main elements of integrated asset support are shown in Figure 3-16.

Figure 3-16: Main elements of integrated asset support

3.5.15 Operation

Icon Water is accountable for the appropriate operation of all water and sewerage assets, this

includes monitoring the assets functionality against licence requirements and operation plans. The

performance of the network is also monitored and appropriate stakeholders are notified in the event of

unplanned outages or interruption events.

Given the specialised knowledge, training and competencies associated with running the water and

sewerage assets, and the associated regulatory obligations; Icon Water prioritises training and

upskilling of our staff. Processes are in place to ensure this training follows a tailored competency

framework. Where possible, work is scheduled to minimise resourcing constraints and conflicts

although it is still necessary to operate multiple significant sites. The total number of operations staff is

based on assessment on licence requirements with regard to resourcing peak demands and

emergency responses through rostering and overtime management.

Icon Water treatment and network operations personnel strive for continuous improvement in all areas

of operational expenditure. Regular reviews of high-value cost inputs associated with labour,

chemicals, energy and fuel usage are undertaken, with an emphasis placed on operational

efficiencies in decision-making and process optimisation for cost avoidance through reduced input

consumption. This process allows Icon Water Operations to target a cost-efficient delivery model. An

example is maximising the value from process waste. Agri-ash from our sewer treatment plant

incineration process is provided for beneficial reuse as a soil conditioner, this also reduces the impact

on our environment by reducing reliance on land fill and avoids additional operating costs.

Icon Water continues to improve its energy management practices through regular management

reviews and reporting. Icon Water continues to participate in industry-wide energy performance

benchmarking studies for our pump stations and sewage treatment plants. The benchmarking results

combined with more detailed asset performance reviews allows Icon Water to target energy efficiency

initiatives. These initiatives form part of Icon Water’s broader Energy Strategy (Icon Water 2015) and

energy management program and are described in Attachment 6: Capital expenditure.

Training and competencies

Chemicals and energy

Tooling and special

equipment

Data management

Inventory management

Safety management

Environmental management

Page 30: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 25

3.5.16 Maintenance

Icon Water safely maintains assets in compliance with legislative requirements, specifications,

procedures and drawings. Maintenance is scheduled to ensure continuity of critical operations and to

reduce planned and unplanned downtime time events. Work is packaged and delivered in accordance

with the business activity model work management processes.

The number of maintenance staff and other direct costs are determined by the requirement to

complete planned maintenance and respond to unplanned events. Staffing levels include a range of

skilled trades, supervision, planning and engineering to meet the maintenance demand. Staff

numbers are reviewed as part of the annual planning process. Unlike some other utilities our staff are

multi-skilled in that they are competent to work on both our water and sewer assets. This provides us

with a degree of operational efficiency and allows cost savings to be achieved by consolidating crews.

Competency is verified for individual maintainers to ensure the safe performance of their duties and

that they are performed in accordance with site standards and procedures and competency

framework.

Icon Water continuously reviews the most efficient and effective balance of internal and external

resources in the delivery of our maintenance program. A recent example of this assessment resulted

in a decision to move from an outsourcing to an insource delivery model specifically for our water and

sewer pump stations.

Resource allocation, optimisation and sustainability are also considered to provide efficient and

effective maintenance outcomes. An example that illustrates this point is a program that was

established to stockpile, sort and reuse (where possible) the reclaimed material that is excavated

during maintenance activities. This program has provided increased efficiency (travel time for crews

and material costs) and reduced the volumes and the associated impacts (cost and environmental) of

land fill disposal.

Icon Water is in the process of renewing its works management system to ensure water and

sewerage services continue to be delivered to customers as efficiently as possible.

3.5.17 Asset disposal

Icon Water considers the ongoing need of assets within our portfolio to meet current and future levels

of levels of service. If the asset is no longer able to perform its inherent function and cannot be

upgraded or modified; or there is a change in the system that no longer requires that asset then a

decision may be made for disposal.

Multiple options are considered to maximise the residual value of an asset during the disposal stage

and where practical assets are reused or sold. When an asset is disposed of then the appropriate

adjustment is made on the regulatory asset base and any residual value is recognised as operational

expenditure.

An example is the treatment of Icon Water’s high security water entitlements. Since the Millennium

Drought ended, the ACT is in a position of high water security. There has also been a sustained

per-capita reduction in water consumption. This prompted a review of how to maximise value for Icon

Water’s investment in high security water entitlements. Weather forecasts trends in the middle of

June 2016 predicted a La Nina event and the water trading market have historically responded to this

by a fall in market values. To maximise asset value (the balance between level of service and cost) it

was decided that the prudent and efficient course of action was the sale of the entitlements.

3.5.18 Asset information management

ICT is a key enabler to improve productivity, efficiencies and timely decision making. Information

about assets and program delivery is required to be of adequate quality and availability. ICT and its

incorporation into business processes and decision making are essential to efficiently analyse,

Page 31: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 26

manage and optimise our asset network for the benefit of consumers and stakeholders. Icon Water

relies on information management to:

ensure the effectiveness of the asset management system and asset management activities

support investment decision making and planning processes.

Icon Water manages a subset of its ICT assets through the support of core operational technology

(OT) systems as shown in Figure 3-17 and listed in the table below.

Figure 3-17: Asset management information system

Supporting IT Infrastructure(Servers, Databases, Switches, Security)

Information Technology (IT) Applications Operational Technology (OT) Applications

Managed by ActewAGL

through the CSA

Managed by ActewAGL

through the CSCSAManaged by Icon Water

Supporting OT Infrastructure (Virtualised cloud-based IaaS)(Servers, Databases, Switches, Security)

Managed by third party

Office Equipment(PC’s, Laptops, Printers, Phones, Tablets, Switches, Cables)

Geographic

Information System(Esri ArcGIS)

Asset

Analytics

Works

Management(Oracle WAM)

Customer

Management

Asset

Management(Oracle WAM)

Enterprise Data

Warehouse

Business

AnalyticsDigital

Customer

Icon Customers

Water & wastewater network assets

Technical

Drawing(AutoCad)

Building

ManagementCCTV

Drawing

Management(Meridian)

Building

Access Control

Advanced Metering

Infrastructure (AMI)

Time Series

Historian(Schneider Wonderware)

Industrial Control

System (SCADA)(Schneider Citect)

Industrial Internet

of Things (IIoT)(PLC’s, RTU’s, Sensors)

Telemetry Bus

Risk

Management(Guardian)

Customer

Billing(Gentrack Velocity)

Directory

Management(Active Directory)

Firewall

Human

Resources(Aurion)

Financial

Management(Oracle EBS)

Directory

Management(Active Directory)

PC

Management(Win10, MS/Office)

Email

Management(MS/Exchange)

Icon

Intranet (SharePoint)

Records

Management (RecordPoint)

Project

Management (PMIS)

Enterprise Service Bus (ESB / ETL)

Document

Management(MS/SharePoint)

Mobility

Management(Vmware/AirWatch)

Source: Icon Water.

Table 3-1: Information systems and functions

Key Information System Function

Work management system Provides asset management and associated work management and costing functions for water and sewerage assets, contains asset information, maintenance programs, asset failure information.

Spatial information system The spatial information system is used to manage and disseminate asset information relating to water, sewer and effluent networks to its stakeholders including staff and customers.

Drawing management system

The drawing management system is a document control system of information in the form of drawing files or raster images relevant to the operation and maintenance of water and sewerage assets

Fixed assets accounting system

Manages financial information relating to Icon Water Assets

Dispatch system Managing and reporting of water and sewerage network reactive jobs, contains asset failure information and performance information in response to faults.

Page 32: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 27

Water meter database Database containing the asset information for customer water meters.

Supervisory control and data acquisition (SCADA)

System for monitoring and controlling operation of infrastructure.

Many of these OT systems are reaching end of life and shall be either upgraded, replaced, retired or

integrated to capture efficiency improvements in asset management. Integrating our OT systems will

improve our asset data quality and availability that will enrich our customer interactions, work delivery

processes, asset planning decisions and asset management monitoring and control.

A key objective of the ICT strategy is to renew Icon Water’s ageing OT capabilities and to achieve an

integrated, robust, scalable and secure technology platform. This business change will be led through

a number of strategic programs that address technology, process, data quality, governance and

sustainability and business capability.

3.5.19 Procurement

The procurement process for assets in Icon Water is predicated on achieving the best value for

money. This means that numerous cost and non-cost factors are considered when goods and

services are procured. These include factors such as the reliability of suppliers, quality of the product

and/or service, assessment of after sales service, assessment of previous experience and

assessment of the product and/or service to meet the inherent requirements. The cost and non-cost

criteria are considered by a pre-agreed weighting that results in an objective assessment of value for

money. Procurement processes are scalable depending on the complexity and level of risk and are

designed to:

ensure transparency and probity by market testing procurement submissions using individual

project-specific assessment criteria and conflict of interest governance

facilitate the management of project, commercial and technical risk.

Supply is arranged through a number of processes depending on the circumstances, from sole

supplier to public competitive tender. Depending on the complexity, a procurement plan is prepared

that sets out the process used and defines a probity plan that is agreed in advance. This plan

objectively defines the factors to be taken into account by placing a weighting on their importance.

The following list of examples demonstrates Icon Water’s commitment to gaining value for money

through our procurement within a variety of section of the asset management lifecycle:

Analysis of the appropriate procurement strategies for delivery of the capital work program

identified that a collaborative contracting procurement strategy was the most appropriate

methodology to manage the risk portfolio of the major program of work activity occurring at Icon

Water’s main sewer treatment plant. Accordingly, Icon Water assessed the various

collaborative contracting models and decided that tailoring the existing Alliance agreement with

Downer represented the best value for money for this program of work. This alliance has

enabled Icon Water to achieve efficiencies and reduce program risk through the engagement of

short term resources with specialised project management and delivery capabilities.

Projects currently being delivered via the Downer Program Alliance will continue through to

completion (estimated at up to $37 million during the 2013–18 regulatory period). Alternative

delivery mechanisms to augment Icon Water project delivery capability into the next regulatory

period are currently being evaluated to ensure prudent and efficient delivery of the program.

The development of a design panel was the most appropriate procurement strategy to manage

the risks and effectiveness of the majority of design work undertaken throughout the

organisation. This has enabled an expedited procurement process for design services in

Page 33: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 28

addition to increasing consistency, quality and performance. An increasing volume of design is

being managed through the panel since its inception.

A complete review of the process requirements, supply chain security and lifecycle cost of

many of Icon Water’s chemical supply contracts have been assessed and revised. A result from

one of the reviews is the decision to commence the transition to a different chemical with

greater process effectiveness and supply chain security at comparable cost (that is greater

value for money).

Icon Water has reviewed and renegotiated many of the service contracts provided throughout

the period to maximise value for money. Examples of these are:

- Hydraulic data collection services contract renegotiations have resulted in the provision of

service at a lower cost.

- - Customer and corporate services delivered through contracts with ActewAGL continue to

be reviewed so that Icon Water can leverage the maximum benefit from the shared

economies of scale. The forecast for customer and corporate services in the next regulatory

period assumes that ActewAGL will deliver further efficiency improvements over time to be

passed through to Icon Water (see Attachment 7: Operating expenditure).

3.6 Performance monitoring

Icon Water has a number of Key Performance Indicators (KPI’s) in place for performance monitoring

at varying levels in the asset management system. These KPI’s range from internally set performance

indicators through to indicators set by governing bodies. These indicators have generally been in

place for many years and work is continuously being carried out to strategically align to the asset

management system.

Icon Water reports both internally and externally on a variety of KPIs. Some of this reporting is based

on specific assets whilst other reporting is for entire systems such as legislation, codes and licences.

Furthermore, Icon Water participates in utility wide performance monitoring programs such as the

National Performance Report and the National Water Accounts. Icon Water is continuously

developing and implementing a systematic approach to measure the performance for the entire asset

management system.

Icon Water has processes in place to detect and diagnose performance issues for individual asset

classes. An example is the monitoring system used by Icon Water for water quality. Icon Water uses

Codex Alimentarius based framework for drinking water quality that identifies key limits, control points

and parameters throughout the water supply system are routinely controlled, monitored and audited.

Page 34: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 29

4 Governance

This section outlines Icon Water’s governance framework, including our:

integrated organisational management system

organisational structure which allows for clear allocation of responsibilities and accountability

and enables cross-functional representation and oversight

investment planning and delivery method

central business area which enables consistency of analysis for investment and a scalable

approach for project delivery

reporting and audit processes.

4.1 Integrated organisational management system

The integrated organisational management system enables the business to monitor and improve

organisational strategy. The integrated organisational management system defines the governance

framework, and management operating system. Further, the integrated organisational management

system characterises the linkages between the direction and control of the business, and the way we

manage our assets.

Table 4-1 lists the key asset management and governance documents, processes and enablers that

underpin the integrated organisational management system. The documents describe the conduct

and management of key business functions, and enable or support the integrated organisational

management system requirements.

Page 35: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 30

Table 4-1: Asset management, governance processes and supporting documents

Asset management system

Asset Management Policy

Strategic Asset Management Plan (SAMP)

Asset management plans (AMPs)

Asset management processes, procedures and work instructions.

Capital governance process and supporting documents

Investment Review Committee (IRC) Charter

Investment Planning and Delivery Guide (IPaD)

Detailed IPaD Process Map

IPaD Submission Review Enabler

IPaD Stage Work Instructions

IPaD Templates

Minor Works Form

Short Form Concept Development Statement (SFCDS)

Concept Development Statement (CDS)

Short Form Technical Report (SFTR)

Technical Report (TR)

Develop Stage Proposal (DSP)

Execute Stage Proposal (ESP)

Closure Report

Project Change Request (PCR)

IPaD Tools

Prioritisation tool

Tier Classification tool

Project Initiation tool

Project Estimation Guide

Page 36: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 31

Key enablers for the governance of the asset management system

Risk Management Framework and Policy

Quality Management Framework and Policy

Environmental Management Framework and Policy

Safety Management Framework and Policy

Structures, authorities and responsibilities

Stakeholder committees and operational forums

Content management, documentation and records

Asset information management

Risk management

Change management

Procurement

Compliance

Audit

System improvements

Consumer engagement, including willingness-to-pay surveys of customer preferences.

Source: Icon Water.

4.2 Responsibilities and authorities for key functions

This section provides an explanation of how internal structures and processes support the

functionality of asset management and oversight of project and service delivery.

4.2.1 Structures and authorities for key functions

The roles and responsibilities for asset ownership and asset management are clearly defined. Figure

4-1 maps the organisational structure and asset management responsibilities.

Page 37: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 32

Figure 4-1: Organisational structure and asset management responsibilities

Source: Icon Water.

4.2.2 Executive governance structure

Each member of the executive takes responsibility for a portion of the asset portfolio. Icon Water staff

within each business group are responsible for the management of those assets. Table 4-2 outlines

the governance structure for the approval and oversight of investment projects.

Page 38: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 33

Table 4-2: Investment process governance structure

Responsible person Role and responsibility

Icon Water Board The Board is responsible for the governance of Icon Water and approval projects over $10 million.

Managing Director Icon Water’s Managing Director is responsible for approving expenditure on capital works and cost increases and variations for projects greater than $3 million and less than $10 million.

Investment Review Committee (IRC)

The role of the IRC includes the prioritisation and endorsement of all stage gate submissions and change requests for Tier 1 and Tier 2 projects. Membership includes: Chief Financial Officer; General Manager, Asset Management; General Manager, Project Delivery Operations and Maintenance; General Manager, Business Services; General Manager Strategic Projects and Technology.

Project Executive Sponsor

The Icon Water executive that is recommending the project and accountable for its implementation and benefits realisation. The Sponsor is also responsible for approving the Envisage, Evaluate and Accept stage gate submissions for Tier 3 projects.

Project Sponsor Delegate (PSD)

Assigned for Project Executive Sponsor to lead the preparation of the initiation documents and to engage with subject matter experts and stakeholders across the business to ensure that the project’s impacts across the business are given due attention. Responsible for:

• reviewing all relevant stage gate submissions and change

requests

• representing submissions at the IRC

• endorsing project scope statements and accepting

handover deliverables.

Program Management Office (PMO)

Provides decision support information to the Board, IRC, PSD and delivery teams. The PMO provides:

• governance

• transparency

• delivery and project initiation support

• traceability

• standardisation of process.

Project Delivery Team

Manage the delivery of projects in the category specific to their specialisation or expertise. The lead the projects from evaluation to completion and are responsible for:

• project deliverables

• stage gate submissions (plan stage onward)

• procurement and contract management

• stakeholder management

• site management and commissioning planning.

Page 39: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 34

4.3 Investment planning and delivery

The Investment Planning and Delivery Manual (provided as confidential Appendix 12 to this

attachment) describes the processes for the initiation and approval of all significant investment

projects. These governance processes ensure that only projects that are efficient, prudent, and

benefit the community and stakeholders are approved. Icon Water’s IPaD process was acknowledged

by other water utilities as an example of Leading Practice in the recent WSAA asset management

benchmarking. Five guiding principles are applied across the organisation for decision making and

project planning. Figure 4-2 illustrates the guiding principles and focus areas for investment planning

and delivery.

Figure 4-2: Guiding principle focus areas for Icon Water’s IPaD

4.3.1 Gating process

The governance framework depends on a thorough and end-to-end gated process that:

achieves consistent and repeatable decision making

identifies and manages risks

achieves efficiency of project delivery

controls the progressive release of funding based on stage by stage justification.

The gating process is a system where each ‘gate’ requires authority for a project to proceed according

to the investment planning and delivery lifecycle. Figure 4-3 illustrates how the gating process

corresponds to the investment planning and delivery lifecycle.

Excellence

(How well)

Developing prudent,

innovative and cost efficient

solutions

Assuring sustainability, safety, quality

and fit for purpose

Strategic Alignment

(What/When)

Achieving business

objectives and goals

Prioritising projects and

analysing portfolio

decisions

Collaboration

(Who)

Engaging and consulting all stakeholders

Considering viable options

Benefits

(Why)

Realising project

outcomes

Measuring success (post

delivery)

Governance

(How)

Ensuring project & program

performance

Ensuring project & program

conformance

Page 40: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 35

Figure 4-3: Investment planning and delivery lifecycle

The lifecycle consists of three main phases: Initiate, Implement and Integrate. Each of the seven

stages of the project lifecycle - Envisage, Evaluate, Plan, Develop, Execute, Accept and Monitor -

corresponds to a stage gate for assessing the prudence and efficiency of investment decisions.

Prudency and efficiency objectives are incorporated throughout the project lifecycle. Evaluation of the

current risks at each stage of the project lifecycle underpins our decisions to proceed with a project

compared with the ‘do-nothing’ option. Project classification involves defining the scope, cost, and

complexity at the initiation stage of project planning. Assessments determine the risk profile of the

project. Table 4-3 outlines the project types and associated criteria defined in the Investment Planning

and Delivery Manual, and which define the approval path for project endorsement.

Table 4-3: Project types and approval path criteria

Project Type Criteria

Path 1 - Major Projects More than one option to be assessed as a solution.

Concept design and full project planning required.

Path 2 - Expedited Projects

Only one option to be assessed as solution.

<1 week concept design work as complexity is low.

Path 3 - Minor Works <$75 000 total project cost.

Only one option to be assessed with minimal design.

Path 4 - Emergency Projects

Relate to reactive action required to resolve a critical interruption to service provision. These are usually classified with a priority score of 8 or above.

Can only be classed as ‘Emergency’ as approved by the Project Executive Sponsor.

Source: IPAD Manual, Icon Water, 2017.

The path that is allocated to a project determines the relevant gating process. For example, the ‘Major

Project’ path involves more comprehensive and relevant stage gate reviews. This risk-based

approach defines the commercial decisions for project approval. Consistent with the risk based

Initiate Phase

Gate 1

Envisage Stage

Gate 2

Evaluate Stage

Gate 3

Plan Stage

Gate 4

Develop Stage

Gate 5

Execute Stage

Gate 6

Accept Stage

Gate 7

Monitor Stage

The problem

and need

are

identified.

Project is

registered

and

prioritised.

Stakeholders

are

Potential

solutions to

resolve

problems are

identified and

evaluated

Concept

design is

performed.

An option is

Project scope

is detailed.

Project

Management

Plan is

developed.

Detail design

is performed.

Approach to

market

Handover is

planned.

Construction

/ Build

activities.

Project

handover

acceptance.

Post-

implementati

on reviews

are

performed.

Project

closure

documentati

on is

developed.

Defects

management

.

Benefits

realisation

Formal

closure.

Implement Phase Integrate Phase

Page 41: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 36

approach, higher value projects have stricter governance requirements to support decision making for

prudence and efficiency of investment. Table 4- describes the standard documentation developed for

project planning and delivery.

Table 4-4: Documentation for the capital planning process

Planning document Description Purpose

Short-form concept

development statement

(SCDS)

Developed for new projects commencing more than 24 months from current date.

To articulate the problem and risk to the business, including preliminary cost estimates.

Concept development

statement (CDS)

All projects with > 1 week concept design and > 1 feasible option. Developed at project commencement.

To articulate the problem and risk to the business, includes preliminary cost estimates to resolve problem. Recommends approach to evaluate options and obtain funding to perform evaluation and concept design activities.

Technical report (TR) Prepared for all projects with total project cost >$100 000 which are not an emergency.

Note that the assessment detail is scaled to the level of the project.

To evaluate and recommend options and to set out all capital cost considerations. Recommends an option and obtains funding for initial project planning.

Development stage proposal

(DSP)

Describes detailed design for new projects and preliminary project plan to manage the project.

To determine requirements for the tender process and obtain funding for detailed design and procurement.

Execution stage proposal

(ESP)

Describes project design and/or construction phase and project plan.

To obtain funding for construction and implementation activities.

Source: Icon Water.

4.3.2 Investment Review Committee

The IRC operates as a centralised governance body which has oversight of our investment programs.

The function of the IRC is to provide consistency of analysis and decision making across the

investment program, including by:

identifying priorities for the investment program

integrating decision making across the business and minimising fragmentation

taking into account business and strategic objectives as well as the acceptable balance of cost,

risk and performance.

The IRC is central to the business’ project initiation, delivery and approval processes, and addressing

considerations of proportionality of the scale and complexity of capital expenditure (capex) projects.

All Tier 1 and Tier 2 projects are considered by the IRC.

Page 42: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 37

In assessing and prioritising projects the IRC has regard to:

Icon Water’s stated business and strategic objectives

governance principles

capex and other budgets approved by the Icon Water Board.

The IRC enables investment decisions to be based on a whole-of-business perspective.

4.3.3 Sustainability Scorecard

Icon Water has incorporated a sustainability assessment via a scorecard in the evaluation of projects.

This enables the balancing of the Territory Owned Corporations Act 1990 objectives at a project level

for environmental and social responsibilities. The scorecard enables the current situation and each

option under consideration to be given a score (where a lower score is less sustainable). The

inclusion of this scorecard was recognised at the Infrastructure Sustainability Council of Australia

awards in 2015.6

The factors that are evaluated in the scorecard are listed in Figure 4-4. These factors assist Icon

Water to consider the balance of financial health, environmental sustainability, cultural vitality and

social responsibility to meet the needs of the present without compromising the ability for future

generations to meet their own needs. Two projects – Cotter Dam and Googong Water Treatment

Plant Chemical upgrade have achieved commended national ratings by the Infrastructure

Sustainability Council of Australia.7

Figure 4-4: Icon Water Sustainability Scorecard Factors

Source: Icon Water.

6 Icon Water received the Highly Commended award at the Infrastructure Sustainability Council of Australia for Organisational Leadership in 2015.

7 Infrastructure Sustainability Council of Australia, 2015 Infrastructure Sustainability Update https://isca.org.au/images/publications/2015ISCAAnnualUpdate_PartA.pdf

Resources

•Energy Use

•Water Use

•Materials

•Land Use

Environment

•Discharges

•Waste

•EcologyClimate Change

People and Place

•Community

•Heritage

•Urban & Landscape

•Workforce

Page 43: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 38

4.3.4 Benefits framework

Icon Water has developed a benefits management framework to identify, plan, manage and report all

potential benefits at a program level. This is currently being piloted across the business

transformation projects and will be rolled out across all projects after the trial. This benefits realisation

framework will be embedded into the investment planning and delivery process.

In a recent review of capital expenditure governance and prioritisation the consultant8 made the

following comments:

“Icon Water’s planned approach to benefits realisation is relatively sophisticated when

compared with other organisations in Australia responsible for significant capital expenditure.”

4.3.5 Reporting and audit process

Monthly reporting on the progress of the investment program includes information about project status

and expenditure. Consistent reporting enables comparison of the expenditure program over time, and

includes:,

Pipeline Report

Project Traffic Light Report

Projects In Distress Report

Schedule Status Report

Program Financial Report.

Furthermore, for water and sewerage projects, monthly project implementation reviews are conducted

between project managers and the Manager Projects Delivery, supported by the Program

Management Office.

Communication of information about program status to the IRC enables corporate oversight, and

management of changing expectations for the budgeting process. Changes to the scope, cost or

timing of a project must be endorsed by the IRC or Project Executive Sponsor via a project change

request. The audit process provides assurance that changes to the works program, including in terms

of cost or scope, are positive, proactive, prudent and efficient decisions of the business.

8 2017, Cardno, Review of Icon Water capital expenditure governance and prioritisation.

Page 44: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 39

5 Asset management system improvements

Icon Water subscribes to continual improvement in asset management system and governance to

align with our strategic goal to be the premier, most trusted water utility. The organisational strategy

involves further developing our enterprise-wide asset management and governance, and to continue

to translate strategic planning and goal setting into operational actions.

In 2018–23, Icon Water will continue to implement the Enterprise Asset Management Strategy, which

will enable alignment with ISO 55001 and deliver the appropriate level of maturity across the IAM’s

asset management subjects shown in Table 5-1 and Figure 5-1. Icon Water has assessed the

appropriate target maturity level with regard to our levels of service impact on customers and our

organisation’s scale, complexity and operating environment.

Table 5-1: Icon Water IAM’s asset management subject maturity target state

IAM asset management subject IAM asset management target maturity

Strategy and planning

Asset management decision making Excellent

Lifecycle delivery Excellent

Asset information Optimising

Organisation and people Optimising

Risk and review Excellent

Source: Icon Water.

Figure 5-1: Institute of Asset Management Conceptual Model for Asset Management

Source: Asset Management Landscape, Institute for Asset Management (2011).

Page 45: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 40

5.1 Summary of target improvements

Leadership

The Asset Owner (Icon Water Executive) will have improved data to enable more informed

asset management decision.

People

Continue to invest in our people to refine our capabilities and provide a culture that supports

our target state asset management maturity.

Processes

Refine our processes and operating models to enable compliance with ISO 55001 and IAM

asset management subject target maturity levels.

Continue to work with our customers to understand and adjust our services to respond to their

stated preferences with prudent consideration of the balance between cost and sustainable

levels of service.

Technology

Refine and integrate our asset data and information systems, including through renewal of the

asset and works management system.

Enhance our data analytics capability to provide deeper insights into our asset data to optimise

our asset planning decisions.

Develop systems to enhance our interaction and service with our customers.

The key initiatives planned for 2018–23 to reinforce processes and refine asset management are

illustrated in Figure 5-2.

Page 46: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 41

Figure 5-2: Asset management system improvements

Source: Icon Water.

Page 47: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 42

Appendix 1 Identified performance gaps

9 Some of these projects have been identified, but the funding arrangements are under negotiation.

10 Capital Contributions projects.

Asset Class Current or near Future Performance Gaps Projects planned or in progress to

resolve gap9

Water Sources

Security of critical infrastructure compared with Commonwealth Standards

Safe and clear access to assets

Upgrade to fencing and intruder detection

Bendora Dam Spill way bridge and various work and heights improvements

Water Treatment

Ability to continue to comply with Codex Alimentarius (drinking water quality guidelines) due to aging infrastructure

Security of Chlorine supplier and equipment

Renewal to Googong Clarifiers

Disinfection system upgrade (in progress)

Water Distribution

Small percentage of network unable to meet current ACT fireflow requirements

Ongoing meter accuracy to National Measurement Institute requirements

Smart metering & customer access to data

Water Mains replacement (hydraulic failure)

Meter Replacement

Monitoring triggers to determine appropriate investment timing

Sewer Collection & Transfer

High levels of blockages and chokes compared with other similar sized utilities

Urban infill leading to several transfers mains at capacity

Urban encroachment leading to need for additional ventilation

Potential changes in EPA air emission standards

Sewer Mains replacement & Maintenance programs

Multiple sewer main augmentation projects10

Multiple upgrades to ventilation at several sites (in progress)

Ongoing odour studies

Sewer Treatment

Approaching capacity limit for Nitrogen removal

Inability to consistently meet emissions licence at LMWQCC

Upgrade Bioreactors

Solids Handling and Furnace Upgrade

Land & Buildings

Operational buildings at key sites do not meet contemporary requirements of a modern workforce and have legacy issues (for example asbestos)

Upgrades to administration and control centres at several sites

Page 48: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 43

ICT

The majority of Icon Water’s operational technology systems are at end of life. That is, they are either no longer supported by the vendor, do not have a vendor supported product development roadmap, or are based on aged technologies that are not well used in the current technology environment.

A number of ICT systems are also at end of life, requiring renewal or replacement to shift the capability on to a contemporary technology platform. This will assist in the management of any current and future security risks to these systems and the associated data.

The existing suite of end of life systems are not able to support the implementation of our strategies without significant expense and risk to customise system functionality.

Implementation of a new Asset Management and Maintenance System

Upgrade of the existing geo-spatial system to a supported version

Retirement of legacy citrix applications and implementation of a supported SharePoint platform.

Enhanced security controls over critical ICT systems.

Implementation of asset modelling tools.

Page 49: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 44

Appendix 2 Strategic Asset Management Plan

This appendix contains Icon Water’s Strategic Asset Management Plan, which is attached as a pdf file.

Page 50: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 45

Appendix 3 Collect Water Asset Management Plan

This appendix contains Icon Water’s Collect Water Asset Management Plan, which is attached as a confidential pdf file.

Page 51: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 46

Appendix 4 Treat Water Asset Management Plan

This appendix contains Icon Water’s Treat Water Asset Management Plan, which is attached as a confidential pdf file.

Page 52: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 47

Appendix 5 Distribute Water Asset Management Plan

This appendix contains Icon Water’s Distribute Water Asset Management Plan, which is attached as a confidential pdf file.

Page 53: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 48

Appendix 6 Collect Sewerage Asset Management Plan

This appendix contains Icon Water’s Collect Sewerage Asset Management Plan, which is attached as a confidential pdf file.

Page 54: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 49

Appendix 7 Treat Sewerage Asset Management Plan

This appendix contains Icon Water’s Treat Sewerage Asset Management Plan, which is attached as a confidential pdf file.

Page 55: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 50

Appendix 8 Discharge Sewerage Asset Management Plan

This appendix contains Icon Water’s Discharge Sewerage Asset Management Plan, which is attached as a confidential pdf file.

Page 56: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 51

Appendix 9 Land and Buildings Asset Management Plan

This appendix contains Icon Water’s Land and Buildings Asset Management Plan, which is attached as a confidential pdf file.

Page 57: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 52

Appendix 10 Vehicles and Plant Asset Management Plan

This appendix contains Icon Water’s Vehicles and Plant Asset Management Plan, which is attached as a confidential pdf file.

Page 58: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 53

Appendix 11 ICT Asset Management Plan

This appendix contains Icon Water’s Information and Communication Asset Management Plan, which is attached as a confidential pdf file.

Page 59: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 54

Appendix 12 IPaD Manual

This appendix contains Icon Water’s Investment Planning and Delivery Manual, which is attached as a confidential pdf file.

Page 60: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 55

Abbreviations and acronyms

ABS Australian Bureau of Statistics

ACT Australian Capital Territory

ADWG Australian Drinking Water Guidelines

AMP Asset management plan

AMS Asset management system

AMSRC Asset Management System Review Committee

CCF Community Consultative Forum

CDS Concept development statement

EAM Enterprise asset management

DSP Development stage proposal

ESP Execution stage proposal

IAM Institute of Asset Management

ICRC Independent Competition and Regulatory Commission

ICRC Act Independent Competition and Regulatory Commission Act 1997

ICT Information and communication technology

IMS Integrated management system

IPaD Investment planning and development manual

IRC Investment Review Committee

ISO 55001 ISO 55001:2014 Asset management – Management systems: Requirements

MOO Maintenance & Operations Optimisation Project

MRA Maintenance requirements analysis

OT Operational technology

POP Process operating plan

QMS Quality management system

SAMP Strategic asset management plan

SCADA Supervisory control and data acquisition

Page 61: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 56

SCI Statement of Corporate Intent 2017-–18 to 2020–21

TOC Territory-owned Corporations Act 1990 (ACT)

TR Technical report

WSAA Water Services Association of Australia

Page 62: Attachment 5 - Icon Waterourprices.iconwater.com.au/...asset-management... · Source: Asset Management Maturity Framework (2015). During 2013–18, planning and service delivery asset

Icon Water Page 57

References

ACT Government (1990). Territory-owned Corporations Act 1990 (ACT).

ACT Government (1997). Independent Competition and Regulatory Commission Act 1997. A1997-77.

A. P. Counsel. Canberra, ACT Government.

Global Forum on Maintenance & Asset Management, (2014). The Asset Management Landscape.

IAM (2015). Asset Management Maturity Framework.

Icon Water (2014). Asset Management Policy.

Icon Water (2015). Energy Strategy.

Icon Water (2017). Investment Planning and Delivery manual.

Icon Water (2017). Benefits Management Framework.

Icon Water (2017). Strategic Asset Management Plan.

Institute for Public Works Engineering Australia (2012). Preamble to condition assessment practice

note.

Project Management Institute (1996). A Guide to the Project Management Body of Knowledge.

Standards Australia (2014). ISO55001.

WHO and FAO (2003). Codex Alimentarius Alinorm: 2003/13A (HACCP) and Good Manufacturing Practice (GMP).


Recommended