+ All Categories
Home > Documents > Auditor General Report_2008-English

Auditor General Report_2008-English

Date post: 30-May-2018
Category:
Upload: ollieace
View: 221 times
Download: 0 times
Share this document with a friend

of 40

Transcript
  • 8/14/2019 Auditor General Report_2008-English

    1/40

  • 8/14/2019 Auditor General Report_2008-English

    2/40

    i

    CONTENTS

    Page

    THE FEDERAL GOVERNMENTS FINANCIAL STATEMENT AND FINANCIALMANAGEMENT OF THE FEDERAL MINISTRIES/DEPARTMENTS

    Preface 3

    Part I - Certification Of The Federal Governments Financial StatementFor The Year Ended 31 December 2008

    6

    Part II - Financial Management Of The Federal Government 6

    - Overall Financial Management Performance 6- Financial Management At Federal Ministries And Departments

    Level6

    ACTIVITIES OF THE FEDERAL MINISTRIES/ DEPARTMENTS AND THEMANAGEMENT OF GOVERNMENT COMPANIES

    Preface 11

    Part I - Implementation Of Activities By The Federal Ministries/Departments 13

    PRIME MINISTERS DEPARTMENTAttorney Generals Chambers- Handling Of Civil And Prosecution Cases By State Legal

    Advisor Offices13

    MINISTRY OF FINANCE- Public Infrastructure Maintenance Programme, Basic

    Infrastructure Programme And Parliamentary ConstituencyRural Development Projects

    13

    Inland Revenue Board- Management Of Individual Tax Assessment For Salaried

    Income Under Self Assessment System

    14

    Inland Revenue Board- Management Of Refunds For Overpaid Income Tax 15

    Royal Customs Department Of Malaysia- Management Of Customs Duty Assessment On Imported

    Goods16

    MINISTRY OF AGRICULTURE AND AGRO-BASED INDUSTRY- Infrastructure Development Programme For Crop

    Diversification17

    - Construction Of Tanjung Manis Integrated Deep Sea FishingPort, Mukah,Sarawak

    18

  • 8/14/2019 Auditor General Report_2008-English

    3/40

    ii

    Page

    MINISTRY OF RURAL AND REGIONAL DEVELOPMENT- Management Of Infodesa Programme 18

    MINISTRY OF WORKS

    - Construction Of The Federal Government AdministrativeCentre, Muadzam Shah, Kedah

    19

    Public Works Department Sabah- Construction Of Sapulut - Kalabakan Road, Sabah 20

    MINISTRY OF TRANSPORT- Electrified Double TrackProject Between Rawang And Ipoh 20

    MINISTRY OF SCIENCE, TECHNOLOGY AND INNOVATION- Management Of Human Capital Development Programme In

    Science, Technology And Innovation21

    MINISTRY OF FEDERAL TERRITORYCity Hall Kuala Lumpur- Enforcement Of Trading Activities, The Department Of Safety

    And Enforcement22

    MINISTRY OF EDUCATION MALAYSIA- Maintenance Of School Buildings 23

    - Project To Supply Clean Water To Rural Schools In Sabah 24

    MINISTRY OF HEALTH MALAYSIA- Construction Of Pekan Hospital, Pahang 24

    - Management Of Prevention And Control Of Dengue Fever 25

    - Management Of Harm Reduction Programme 26

    MINISTRY OF HOUSING AND LOCAL GOVERNMENTTown And Country Planning Department, Peninsular Malaysia- Management Of Local Planning 27

    MINISTRY OF INFORMATION, COMMUNICATION ANDCULTURENational Library Department- Management Of Rural Libraries 28

    Department Of Broadcasting

    - Management Of Procurement Of External Broadcasting VanWith Broadcasting System And Digital Radio Production

    29

    MINISTRY OF HUMAN RESOURCES- Management Of Educational Equipments In Training Institutes,

    Manpower Department30

    MINISTRY OF HIGHER EDUCATION- Management Of Procurement Of Course Equipments For

    Community Colleges30

    MINISTRY OF HOME AFFAIRS- Construction And Management Of The Ministry Of Home

    Affairs Complex, Perak31

  • 8/14/2019 Auditor General Report_2008-English

    4/40

    iii

    Page

    Royal Malaysian Police- Management Of Red Light Surveillance Camera System And

    The Issuance Of Summons32

    VARIOUS MINISTRIES AND DEPARTMENTS- Management Of Emolument For Civil Servants 33

    Part II - Management Of Government Companies 34

    - Export - Import Bank Of Malaysia Berhad 34

    - Syarikat Prasarana Negara Berhad 35

    - JKP Sdn. Bhd. 36

    - Kumpulan Modal Perdana Sdn. Bhd. 37

    - Hotel Chains Of Seri Malaysia Sdn. Bhd. 38

    - Malaysia Venture Capital Management Berhad 39

  • 8/14/2019 Auditor General Report_2008-English

    5/40

    SYNOPSIS

    AUDITOR GENERALS REPORT 2008

    ON THE FEDERAL GOVERNMENTSFINANCIAL STATEMENT AND

    FINANCIAL MANAGEMENT OF THE

    FEDERAL MINISTRIES/DEPARTMENTS

  • 8/14/2019 Auditor General Report_2008-English

    6/40

    3

    PREFACE

    1. Article 106 and 107 of the Federal Constitution and Audit Act 1957 require the

    Auditor General to audit the Federal Governments Financial Statement, financial

    management as well as its activities and submit his Reports to the King and obtain his

    consent before tabling the Audit Reports in Parliament. To fulfil these responsibilities,

    the National Audit Department needs to carry out 3 types of audits as follows:

    1.1. Attestation Audits to give an opinion as to whether the Federal

    Governments Financial Statement for the year concerned shows a true and fair

    view as well as its accounting records were maintained properly and updated

    accordingly.

    1.2. Compliance Audits to determine whether the financial management in

    Ministries/Departments is in accordance with relevant financial laws and regulations.

    1.3. Performance Audits to ascertain whether Government activities have

    been carried out efficiently and economically to achieve its desired objectives/goals.

    2. Similar to the year 2007, audit findings on the Federal Governments Financial

    Statement and financial management are reported separately from the audit findings onthe activities of the Federal Ministries/Departments as well as management of

    Government companies. This separation allows easy reference and to ensure a greater

    impact on the issues raised as each has a different scope of objective and management

    technique. My Report on the Federal Governments Financial Statement and financial

    management for the year 2008 includes the followings:

    Part I : Certification On The Federal Governments FinancialStatement For The Year Ended 31 December 2008

    Part II : Financial Management Of The Federal Government

    Part III : Involvement of The National Audit Department In VariousActivities To Enhance Public Fund Management AndAccountability

    Part IV : General Matters

    3. The audit on the Federal Governments Financial Statement for the year ended 31

    December 2008 revealed that the Statement generally reflects a true and fair view on

    the financial position of the Federal Government, operational outputs and cash flow for

    the year concerned as well as accounting records were maintained properly andupdated accordingly. As for the financial management of the Federal Government,

  • 8/14/2019 Auditor General Report_2008-English

    7/40

    4

    auditing revealed the non-compliance of various financial regulations. Several

    weaknesses due to insufficient manpower, lack of training in financial management,

    inadequate supervision and lax of monitoring continue to occur.

    4. All matters reported had been brought to the attention of the respective Controlling

    Officers/Heads of Department for confirmation. The National Audit Department has

    taken various measures to assist the Federal Ministries/Departments in rectifying the

    weaknesses in financial management. Among the measures taken were as follows:

    4.1. Implementing the star rating system based on the Accountability Index.

    Through this system, marks will be given for compliance of regulations of 6 main

    elements in financial management. The 6 elements are management control,

    budgetary control, revenue control, expenditure control, management of trust funds

    and deposits as well as management of assets and stores. The Federal

    Ministries/Departments rated as excellent can become a role model to others. Thiswould motivate Federal Ministries/Departments to diligently improve to enhance their

    financial management.

    4.2. Published the book Excellent Financial Management From The Perspective

    Of The National Audit Department. This is one of the proactive steps introduced to

    enhance Governments financial management. Therefore, it is hoped that the Heads

    of Department/Agency will be guided by examples of common weaknesses

    identified during the course of audit in order to achieve an excellent rating under the

    Accountability Index System. It is also hoped that the book will be used as a

    reference in Government training institutes and public institutions of higher learning.

    4.3. Treasury Instructions require the Heads of Department to ensure the

    responsible officers safeguard public money, stamps or other valuable items in

    safety boxes, vaults, cash boxes or other receptacles. Heads of Department should

    also ensure complete and updated records being maintained and periodic

    inspections carried out by senior officers. To ensure the implementation of these

    instructions, the National Audit Department has carried out surprise inspections in

    98 Federal Departments/Offices throughout the country.

    4.4. The Agency Adoption Programme was introduced in 2003. Under this

    programme, selected offices with weaknesses in financial management were given

    continuous guidance and advice to assist them in rectifying weaknesses especially

    with regard to the maintenance of accounting records. In 2008, this programme was

    implemented in 5 Government offices. Generally, financial management at the

    selected offices have improved and showed significant positive results.

    4.5. Carrying out special evaluations on the performance of Premier Grade

    Officers on financial management as part of their confirmation exercise. A total of 92

    Heads of Department were evaluated from January 2008 to May 2009. Theseevaluations have indirectly contributed towards the enhancement of the financial

  • 8/14/2019 Auditor General Report_2008-English

    8/40

    5

    management as promotion of Heads of Department would only be considered by the

    Public Services Department after the National Audit Department had confirmed that

    the officers had taken corrective actions on the weaknesses on financial

    management.

    4.6. Officers from the National Audit Department have participated in discussions

    on the development of computerised systems at various Federal

    Ministries/Departments to ensure internal controls were adequate to safeguard the

    integrity of data and reliability of the systems. It is felt that such involvement is

    necessary as huge expenditure has been spent in developing computerised

    systems. Thus, it is appropriate that these systems should be implemented properly

    to meet the desired objectives.

    5. I wish to express my thanks to all the officers in the various Federal

    Ministries/Departments who have given their full cooperation to my officers during the

    audit. I also wish to record my appreciation and thanks to my officers who have worked

    diligently and for their totalcommitment to complete this Report.

    ( TAN SRI DATO SETIA HAJI AMBRIN BIN BUANG )

    Auditor General of Malaysia

    Putrajaya

    17 June 2009

  • 8/14/2019 Auditor General Report_2008-English

    9/40

    6

    SYNOPSIS

    PART I - CERTIFICATION OF THE FEDERAL GOVERNMENTSFINANCIAL STATEMENT FOR THE YEAR ENDED 31DECEMBER 2008

    1. The Federal Governments Financial Statement for the year ended 31 December

    2008 as a whole reflected a true and fair view of the financial position of the Federal

    Government and the accounting records were also properly maintained and kept up-to-

    date.

    PART II - FINANCIAL MANAGEMENT OF THE FEDERAL GOVERNMENT

    Overall Financial Management Performance

    2. For the year 2008, the Government had approved RM152.01 billion for operating

    expenditure in the government sector. However, a total of RM153.50 billion was spent

    during the year whereby exceeding approved allocation amounting to RM1.49 billion.

    Nine Ministries had spent more than the approved allocation for emolument, services

    and supplies, acquisition of capital assets, subsidies and fixed charges. Whereas a total

    of RM42.85 billion (91.2%) was spent out of RM46.98 billion as approved under the

    development allocation for the implementation of 1,111 projects. The Government had

    received revenue totalling RM159.79 billion as compared to RM139.89 billion for the

    year 2007. There were 56 Federal Ministries/Departments with arrears of revenue

    totalling RM23.19 billion for the year 2008 as compared to RM14.08 billion for the year

    2007. The significant increase was due to the requirement in the Treasury Circular No. 3

    Year 2008 which was issued in the beginning of the year 2008 by the Ministry of

    Finance whereby all outstanding loan and other debts should be considered as

    Receivable Account.

    Financial Management At Federal Ministries And Departments Level

    3. The National Audit Department had carried out audits in 27 Federal Ministries

    and 33 Departments in the year 2008 in order to ascertain whether financial

    management at these Ministries and Departments were being managed according to

    established laws and financial regulations. The result of the audit showed that some of

    the Federal Ministries and Departments were not serious to improve their performance

    in financial management even though such weaknesses had been repeatedly reported

    and brought up to their attention by the National Audit Department. As an effort to

    motivate the Federal Ministries and Departments to further improve and strengthen their

    performance in financial management, the National Audit Department has introduced

  • 8/14/2019 Auditor General Report_2008-English

    10/40

    7

    the Accountability Index for financial management. Federal Ministries and Departments

    rated as excellent can become a role model to others. From the assessments carried

    out, the financial management performance of 4 Ministries and 2 Departments were

    rated as excellent; 20 Ministries and 10 Departments as good and the remaining 3

    Ministries and 10 Departments as satisfactory. Besides that, the Headquarters and 14state branches of the Royal Malaysian Customs Department as well as 11 Malaysian

    Representative Offices abroad under the Ministry of Foreign Affairs were also audited.

    4. The Controlling Officers/Heads of Department must ensure that the responsible

    officers safeguard public money, stamps or other valuable of any kind in safety boxes,

    vaults, cash boxes or other receptacles as stated under the Treasury Instructions. They

    must also ensure that all records are properly maintained, up-to-date and examined by

    senior officers periodically. In order to ensure that such duties were carried out by the

    Controlling Officers/Heads of Department, the National Audit Department has carried

    out surprise inspections in 98 Federal Departments/Offices. The audit revealed that

    there were some instances where public money and other valuable items were not kept

    safely, delays in banking-in collections and cash balances in hand differ from records.

    5. Besides conducting mandatory audits as provided under the laws, the National

    Audit Department also implements the Adoption Programme and special evaluations on

    the financial management performance of Premier Grade Officers from various

    Ministries/Departments/Agencies. In 2008, the National Audit Department had carried

    out the Adoption Programme at 5 Federal Department whereas from January 2008 to

    May 2009, a total of 92 Premier Grade Officers had been evaluated.

  • 8/14/2019 Auditor General Report_2008-English

    11/40

    SYNOPSIS

    AUDITOR GENERALS REPORT 2008

    ON ACTIVITIES OF THE

    FEDERAL MINISTRIES/DEPARTMENTS

    AND THE MANAGEMENT OF

    GOVERNMENT COMPANIES

  • 8/14/2019 Auditor General Report_2008-English

    12/40

    11

    PREFACE

    1. Article 106 and 107 of the Federal Constitution and Audit Act 1957 require the

    Auditor General to audit the Federal Governments Financial Statement, financial

    management as well as its activities and submit his Reports to the King and obtain his

    consent before tabling the Audit Reports in Parliament. To fulfil these responsibilities,

    the National Audit Department needs to carry out 3 types of audits as follows:

    1.1. Attestation Audits to give an opinion as to whether the Federal

    Governments Financial Statement for the year concerned shows a true and fair

    view as well as its accounting records were maintained properly and updated

    accordingly.

    1.2. Compliance Audits to determine whether the financial management in

    Ministries/Departments is in accordance with relevant financial laws and regulations.

    1.3. Performance Audits to ascertain whether Government activities have

    been carried out efficiently and economically to achieve its desired objectives/goals.

    2. Starting from 2006, my Report on performance audits on the implementation of

    activities of the Federal Ministries/Departments and the management of Government

    companies are prepared separately from the Report on the Financial Statement and

    financial management of the Federal Government for the year 2008. This is for easy

    reference and to ensure greater impact on the issues highlighted. My Report on the

    implementation of activities of the Federal Government as well as the management of

    the Government Companies for the year 2008 includes the followings:

    Part I : Implementation Of Activities By The Federal Ministries/

    Departments

    Part II : Management Of Government Companies

    Part III : Follow-up Actions Being Undertaken/Not Carried Out By The

    Ministries/Departments/Government Companies On Matters

    Highlighted In The Auditor Generals Reports For The Year 2006

    And 2007

    3. Section 6(d) Audit Act 1957 requires the Auditor General to conduct audits to

    ascertain whether Government activities have been managed efficiently, economically

    and in accordance with the objectives of these activities. The audits were conducted on

    various activities among others, project constructions, maintenance works, law

    enforcements, procurements, asset management, taxations as well as social economy

    enhancement programmes. This Report contains matters observed from the audits on

    32 activities/projects undertaken by various Ministries/Departments/Governmentcompanies. Generally, the Ministries/Departments/Government companies have

  • 8/14/2019 Auditor General Report_2008-English

    13/40

    12

    planned well for the implementation of these activities/projects. However there were

    several weaknesses in the execution of these activities/projects due to shortage of

    manpower and expertise, insufficient funds, lack of close supervision and ineffective

    monitoring.

    4. As in previous years, auditing had also been carried out on companies which

    Government owned more than 50% equity. This is to ascertain whether the respective

    company have carried out its activities effectively, prudently and in accordance with its

    established objectives. This Report comprises the analysis of financial performance of

    48 Government companies based on their Financial Statements for the year 2007 and

    matters observed from the audits on the management of activities carried out by 6

    Government companies. Audit analysis revealed that 27 of these companies reported a

    profit before tax amounting to RM78 billion for the year 2007 whereas 21 companies

    had incurred losses totalling RM0.87 billion. However, only 14 out of the 27 profitable

    companies paid dividends totalling RM72.21 billion to the Government and taxesamounting to RM24.37 billion were collected from 30 companies. Generally, the audit

    on the management of activities by the companies revealed that the activities were well

    planned. However, there were several weaknesses in the execution of these activities

    that needs to be rectified especially those related to internal controls on financial

    management.

    5. To assist the Ministries/Departments/Government companies to overcome the

    weaknesses highlighted in the Auditor Generals Report for the year 2007, a total of 360

    recommendations were proposed. Follow-up audits conducted up to 1 April 2009

    revealed that the respective Ministries/Departments/Government companies had takenaction on 338 (93.9%) recommendations. As for the Auditor Generals Report for the

    year 2006, actions on 201 (93.9%) from 214 recommendations have been taken. The

    13 and 22 recommendations for year 2006 and 2007 respectively are either being

    undertaken or has not been carried out yet.

    6. I wish to express my thanks to all the officers in the various Federal

    Ministries/Departments who have given their full cooperation to my officers during the

    audit. I also wish to record my appreciation and thanks to my officers who have worked

    diligently and for their totalcommitment to complete this Report.

    ( TAN SRI DATO SETIA HAJI AMBRIN BIN BUANG )

    Auditor General of Malaysia

    Putrajaya

    17 June 2009

  • 8/14/2019 Auditor General Report_2008-English

    14/40

    13

    SYNOPSIS

    PART I - IMPLEMENTATION OF ACTIVITIES BY THE FEDERAL MINISTRIES/

    DEPARTMENTS

    PRIME MINISTERS DEPARTMENT

    Attorney Generals Chambers

    - Handling Of Civil And Prosecution Cases By State Legal Advisor Offices

    The State Legal Advisor Office (SLAO) is responsible for drafting and vetting laws to be

    tabled at the State Legislative Assembly, provides legal advice to the State Government

    in all aspects of administration, relationship between Federal and State Governments as

    well as the private sector and to conduct prosecutions on criminal and civil proceedings.

    The audit revealed that there is room for improvement in conducting criminal andcivil

    proceedingsas there were cases where SLAO had taken up to 183 days to review a

    civil case and up to 1,149 days for a criminal case. Among the factors which caused

    such delays were the difficulties faced in seeking further information from other law

    enforcement agencies, heavy workload, unstipulated time frame to complete certain

    work processes and the frequency of transferring officers involved in on-going cases. As

    such, it is recommended that the Attorney Generals Chambers considers the following

    matters:

    Ensure work processes involving civil and criminal cases are completed by

    SLAO within the time frame as stipulated in the High Court Rules 1980,

    Subordinate Court Rules 1980 and Limitation Act 1953. As for work processes

    without a stipulated time frame, the Attorney Generals Chambers should

    determine the time frame and ensure all SLAO complies with it.

    Review staffing in SLAO to deal with the increasing workload.

    Standardise a Management Information System to be used by all SLAO in order

    to facilitate references/reviews and to further improve the monitoring on handling

    of cases.

    MINISTRY OF FINANCE

    - Public Infrastructure Maintenance Programme, Basic InfrastructureProgramme And Parliamentary Constituency Rural Development Projects

    From 2005 to November 2008, a total of 92,687 projects under the Public Infrastructure

    Maintenance Programme, Basic Infrastructure Programme and Parliamentary

    Constituency Rural Development Projects involving RM4.59 billions were implemented.

    Generally, the audit revealed that certain programmes/projects were not satisfactorily

    implemented such as delays in project completion, work done not in accordance with

  • 8/14/2019 Auditor General Report_2008-English

    15/40

    14

    the original scope of works, increased project cost due to the inclusion of procurements

    of equipment and asset in the scope of works, unutilised facilities upon completion,

    improper payment made for works not done and shortages of officers in project

    supervision. To ensure the objectives of these programmes/projects are achieved and

    Government gets value for money, it is recommended that the Federal Treasury,

    Implementation and Coordination Unit (ICU) in the Prime Minister's Department and

    State Development Offices (SDO)/District Offices consider the following matters:

    The Letter of Offer should clearly state the date of commencement and

    completion of works and also the provisions relating to penalties for delays so

    that SDO/District Offices can initiate action against contractors who failed to

    execute their works accordingly.

    ICU should ensure each and every project is implemented as planned and

    utilised optimally to avoid wastage of public funds.

    The SDO of the Federal Territory of Kuala Lumpur should investigate improper

    payments and if there are any irregularities, appropriate actions must be taken

    against those involved.

    The Federal Treasury should review the post of technicians and assistant

    technicians emplaced at each SDO by taking into account the present workload.

    SDO should then ensure specific trainings to be given to enable them to carry

    out their duties efficiently and effectively.

    MINISTRY OF FINANCE

    Inland Revenue Board

    - Management Of Individual Tax Assessment For Salaried Income Under SelfAssessment System

    The Self Assessment System is based on Assess, Pay and File concept where a

    taxpayer is required to make his/her own assessment/tax computation by referring to

    guidelines/regulations issued, make payment and submit Income Tax Form (BE Form)

    to Inland Revenue Board (IRB). Generally, the audit revealed that the Self Assessment

    System for salaried income is useful as it reduces the workload of IRB officers. However,

    there were some weaknesses in its implementation that could cause non/undercollection of income tax. Among the weaknesses were BE Forms could not be sent to

    taxpayers, non/late submission of BE Forms by taxpayers and no penalties imposed,

    mistakes/inaccurate information in BE Forms as well as Tax Deduction Schedules were

    not prepared by employers and notices not issued by IRB to employers to deduct

    employees salary with tax arrears. The IRB must immediately solve the problems

    regarding BE Forms as it can affect the collection of Government revenue. As such, IRB

    is advised to take the following actions:

    Provide continuous explanations to taxpayers by desk officers at public places

    such as shopping malls and office buildings.

  • 8/14/2019 Auditor General Report_2008-English

    16/40

    15

    For cases to be audited by the Desk Audit Unit (Salaried Income), all supporting

    documents must be obtained from taxpayers and filed accordingly.

    Penalties must be imposed on taxpayers for non/late submission of BE Forms.

    Ensure employers prepare Tax Deduction Schedules for employees with a

    monthly salary exceeding RM2,551.

    Issue a Tax Deduction Instruction to ensure employee salaries are deducted to

    settle their tax arrears.

    Strengthen manpower in the Desk Audit Unit (Salaried Income) as over 50% of

    the BE Forms audited by the Unit revealed taxes were either over or under

    collected.

    MINISTRY OF FINANCE

    Inland Revenue Board

    - Management Of Refunds For Overpaid Income Tax

    In accordance with Section 111 Income Tax Act 1967, the Inland Revenue Board (IRB)

    is responsible to refund overpaid income tax to taxpayers. Auditing on samples of

    refund of overpaid income tax involving RM648.70 million revealed that majority of the

    refunds were delayed between 10 days to 2 years for manual cases and up to a year for

    e-Filingcases. Among the reasons for the delay were due to the implementation by

    stages of the Self Assessment System, incomplete/doubtful information/document

    submitted by taxpayers and the incapability of IRB to solve this problem as responsible

    officers were required to manage other assignments. In addition, some of the overpaid

    income taxes were not refunded correctly resulting in losses to the Government. As the

    collection of income tax is of uttermost importance to Government revenue, it is

    recommended that IRB considers and takes immediate actions on the following matters:

    To enhance its delivery system, the IRD should comply with the time frame for

    repayment of overpaid income taxes as stipulated in the Client Charter.

    The Client Charter on repayment of overpaid income taxes should be clearly and

    specifically stated. In relation to this, taxpayers need to be informed of their

    responsibility in ensuring the correctness of income tax assessment informationfor all the relevant years of assessment, the original dividend vouchers attached

    are complete, overpaid income tax for the concerned assessment year to be

    offsetted with the income tax due from other years of assessment, outstanding

    real property gains tax and debts due to Government for companies if the

    Compared Total exceeds the Compared Aggregate for purpose of dividend

    payment.

    Simplify the tax payment codes through discussion with the Federal Treasury.

    This is important to prevent taxpayers from filling the wrong transaction code due

    to the confusion over the numerous existing codes which have resulted in

    payment transactions been recorded in the unrelated assessment year.

  • 8/14/2019 Auditor General Report_2008-English

    17/40

    16

    Review the manpower requirement in every Collection Branch/Unit by taking into

    consideration the existing workload.

    Prepare a complete checklist on computation for repayment of overpaid income

    tax in order to ensure only correct amounts are refunded accordingly. Items to

    be listed for checking are tax increase under subsection 107B(3)/107C(9),subsection 107B(4)/107C(10), subsection 103(3) and 103(4) of Income Tax Act

    1967, debts under section 108 of Income Tax Act 1967, outstanding real

    property gains tax and proof of confirmation of dividend vouchers for tax

    deduction.

    Prepare a standardised Computation of Excess Income Tax Statement for every

    refund to be used by all IRD Branches and sent to taxpayers involved. The

    statement should contain detailed information such as the date and income tax

    assessment for each assessment year, date and income tax imposed, date and

    income tax payable and amount due to Government (involves dividend and real

    property gains tax) to facilitate taxpayers to carry out checking on the

    computation of the refund of overpaid income tax.

    Overpayment of refunds should be collected immediately from taxpayers

    involved.

    The Fund For Income Tax RefundStatement should to be prepared for auditing

    purpose as stipulated in the Trust Deed.

    Determine the amount of funds required under the Fund For Income Tax Refund

    so as to ensure all refunds are made accordingly to taxpayers.

    Royal Customs Department Of Malaysia

    - Management Of Customs Duty Assessment On Imported Goods

    From 2006 to 2008, the Royal Customs Department of Malaysia had collected an

    average of RM6.38 billion a year on import duty, excise duty (import) and sales tax

    (import). The audit revealed several weaknesses such as delay in declaring imported

    goods and payment of import duties/taxes by forwarding agents/importers, errors in

    classification and valuation by Assessing Officers, poor handling of Custom Declaration

    Forms, shortcomings in the Customs Information System that accept multiple import

    declaration of the same goods and poor interface with Gate Control System. Toovercome these weaknesses which among others were due to manpower shortage and

    weakness in monitoring, it is recommended that the Royal Customs Department takes

    the following actions:

    Prepare a guideline on the rate of compound/fine to prevent the imposition of low

    rates of compound/fine that are incompatible for offences committed and non-

    uniformity between custom stations. The Royal Customs Department should

    increase monitoring and enforcement to ensure importers complies with the laws

    and regulations.

    Follow-up on the application for additional post of Assessing Officers that had

    been submitted to the Public Service Department to ensure posts created are

  • 8/14/2019 Auditor General Report_2008-English

    18/40

    17

    compatible with the heavy workload and to reduceclassification and valuation

    errors of imported goods. In addition, approved posts should be filled

    immediately.

    Carry out surprise checks and enforce disciplinary action to ensure proper

    management of declaration forms and to prevent any infringement.

    Ensure the Price Monitoring And Classification Committee holds periodical

    meetings to enhance its functions as a supervisory body to resolve issues and

    problems of assessment and classification at station and state level effectively.

    Collect arrears of revenue zealously to prevent losses on Government revenue.

    Ensure the integrity of data in the Customs Information System and the system

    is able to interface with the Gate Control System to substantiate payment of

    import duties/taxes. For cases whereby Gate Control System does not work, the

    Customs Officers stationed at check points should inspect documents and goodsphysically.

    Prepare annual training programme to ensure each and every officer attends

    course/training for at least 7 days a year as stipulated under Service Circular No.

    6 of 2005 in order to increase his/her skill and efficiency especially related to

    their line of work.

    MINISTRY OF AGRICULTURE AND AGRO-BASED INDUSTRY

    - Infrastructure Development Programme For Crop Diversification

    As at December 2008, the Government has incurred a total of RM182.93 million to carry

    out the Infrastructure Development Programme For Crop Diversification. Generally, the

    implementation and monitoring of constructing agricultural infrastructure were

    satisfactory whereby 92.5% of the projects were implemented as planned. However,

    there were weaknesses in maintaining the completed infrastructure and implementation

    of agricultural activities. To ensure continuous benefit on the implementation of this

    programme, it is recommended that the Ministry consider the following matters:

    Take immediate action to complete the abandoned project in order to benefit the

    project participants as planned.

    Prepare a periodical maintenance plan and provide sufficient allocation for such

    maintenance.

    Ensure areas chosen are suitable before approving a project so that agricultural

    activities can be carried out throughout the year.

    Apart from close monitoring and continuous guidance, prepare a strategic plan

    to assist farmers to market their crops as this is crucial in encouraging them to

    actively cultivate the crops.

  • 8/14/2019 Auditor General Report_2008-English

    19/40

    18

    MINISTRY OF AGRICULTURE AND AGRO-BASED INDUSTRY

    - Construction Of Tanjung Manis Integrated Deep Sea Fishing Port, Mukah,Sarawak

    The construction of Tanjung Manis Integrated Deep Sea Fishing Port, Mukah, Sarawak

    was implemented at a cost of RM313.62 million. The audit revealed severalweaknesses such as project delay, unsatisfactory work quality and some basic facilities

    were not constructed or completed. Thus the main objective of the project could not be

    completely achieved. To overcome these weaknesses and also to prevent the

    recurrence of the same weaknesses in other projects, it is recommended that the

    Ministry of Agriculture and Agro-based Industry, the Ministry of Finance, Public Works

    Department and Fisheries Development Authority of Malaysia consider the following

    matters:

    The contractor should not be allowed to postpone any repair works until the

    completion of phase 3 of the project as damages/defects can become moreserious if immediate remedial actions are not taken.

    For a fast track project implemented by design and build concept and approval

    by the Ministry of Finance on a multi-phase contract price, the Ministry of

    Finance should approve the contract price for each phase in sequence to the

    implementation stages as suggested by the Ministry/Department concerned.

    This is vital to prevent disruption of the implementation of the project.

    The Ministry of Finance should approve sufficient allocation to complete all basic

    facilities/components of the project to ensure a fully functional Integrated Deep

    Sea Fishing Port and thus ensure the achievement of its objective.

    MINISTRY OF RURAL AND REGIONAL DEVELOPMENT

    - Management Of Infodesa Programme

    The Infodesa Programme aims to bridge the digital divide between urban and rural

    communities. As at 31 December 2008, a total of RM68.38 million was incurred for this

    programme and 41,298 participants were given ICT training. The audit revealed several

    weaknesses such as delay in project completion as well as delay in operating the

    completed Infodesa Centres (MID) due to delay in procuring equipments and filling up

    the post of MID managers. In addition, a total of 156 MID constructed by the Federal

    Government were situated on land that has yet to be registered in the name of the

    Federal Land Commissioner. To overcome these problems and to ensure that the

    objective of this programme is achieved, it is recommended that the Ministry of Rural

    and Regional Development considers the following matters:

    As this is a costly programme that has been implemented since the Eighth

    Malaysia Plan, the Ministry should create a permanent post for MID managers to

    facilitate the appointment process and ensure the MID managers commitment.

    Ensure that each MID establishes a Management Board to assist in its functions.

    As District Officers are too busy to chair the board meeting, a representative

    from the District Office could be appointed as chairman.

  • 8/14/2019 Auditor General Report_2008-English

    20/40

    19

    Close monitoring of projects to ensure they are implemented within the

    stipulated time frame. In this regard, the implementing agency should submit

    monthly progress report and to clarify if any delays were to occur.

    Ensure MID managers abide all financial rules and regulations on procurement

    and management of assets. Related records and registers should be maintainedand updated regularly. The Ministry must also conduct regular spot checks on

    MID to confirm compliance with the related rules and regulations. To ensure MID

    managers perform their responsibility competently and effectively, management

    training including financial management should be given.

    Increase the number of computer users in MID to ensure ICT equipments are

    used optimally and to achieve the objective of bridging the digital divide between

    urban and rural communities. For this purpose, the Ministry should increase

    awareness among the local and neighbouring communities of the facilities

    available in MID.

    Ensure all MID project sites are registered in the name of the Federal Land

    Commissioner in order to continue its activities even if a change of the ruling

    party of the state Government occurs.

    Adequate allocation for maintenance of equipments and buildings should be

    budgeted for to ensure continuity of this programme.

    Perform regular reviews to determine the achievements of the programme and to

    carry out further improvements.

    MINISTRY OF WORKS

    - Construction Of The Federal Government Administrative Centre, MuadzamShah, Kedah

    As at 31 December 2008, 95% of the Federal Government Administrative Centre,

    Muadzam Shah, Kedah project was completed and a total of RM243.53 million was

    spent. The audit revealed several weaknesses such as the appointment of the

    contractor and project implementation method that caused project delay, unsatisfactory

    contract management, delay/not occupying completed building and poor quality

    construction works. This complex could have been utilised earlier if effective co-

    ordination between the Prime Ministers Department, Public Works Department (PWD)and other involved agencies exist and efficient consultants were appointed. To

    overcome these problems, it is recommended that PWD as the Project Superintending

    Officer and user departments/agencies consider the following matters:

    Procurement of furniture should be synchronized with construction work

    progress. In this regard, furniture should be procured when the progress of

    construction work achieved 80% so that the complex could be utilised upon

    completion.

    For a common-user building, user departments/agencies should be identified

    and finalized at the planning stage of the project to prevent changes in building

    plans that could cause delays.

  • 8/14/2019 Auditor General Report_2008-English

    21/40

    20

    User requirements should be considered during the design stage to prevent a

    completed building being left unoccupied for not fulfilling their needs and

    additional cost for renovations.

    To safeguard Government's interests, PWD should comply with rules and

    regulations on contract management. In this regard, the contract should besigned within 4 months after the issuance of Letter of Acceptance. Stern action

    needs to be taken to ensure contractor rectify all defects reported before the end

    of the Defects Liability Period.

    Close supervision and monitoring to prevent project delay and ensure stipulated

    work specifications are fully complied.

    PUBLIC WORKS DEPARTMENT SABAH

    - Construction Of Sapulut - Kalabakan Road, Sabah

    The Sapulut - Kalabakan Road, Sabah was constructed by Konsortium FA Irama Duta

    Sdn. Bhd. (contractor) under the design and build concept at a total cost of RM563.33

    million. The contractor was appointed by the Ministry of Finance through direct

    negotiation. The audit revealed that even though the original plan was to construct a

    paved road for a distance of 145 kilometers, only a gravel road was built due to

    insufficient allocation caused by the problem of the contractors obligation to remove

    substantial amount of unsuitable material from the project site. The problem of

    unsuitable soil was not identified prior to project implementation due to inadequate soil

    investigation. Monitoring of the implementation and maintenance of this project was

    unsatisfactory resulting in poor quality workmanship. In this regard, it is recommendedthat the Public Works Department Sabah considers the following matters:

    Ensure the contractor repairs damaged road and drains as well as slope failures

    to prevent the situation from getting worst until the whole road gets damaged

    before the expiry of the Defects Liability Period and thus putting road users' lives

    at risk.

    Enhance monitoring to ensure the contractor carries out quality maintenance

    according to schedule and stipulated terms and conditions of the contract.

    Apply sufficient allocation under the Tenth Malaysia Plan to pave the road.

    Ensure adequate soil investigations are carried out by responsible parties for

    future road construction projects so that a suitable design can be prepared

    before commencement of the project.

    MINISTRY OF TRANSPORT

    - Electrified Double TrackProject Between Rawang And Ipoh

    The Electrified Double Track Project Between Rawang And Ipoh was implemented at a

    cost of RM5.77 billion through 2 packages namely the Infrastructure Package andSystem Package. The main contractor for the Infrastructure Package is DRB-Hicom

  • 8/14/2019 Auditor General Report_2008-English

    22/40

    21

    Berhad (DRB-Hicom) while Mitsui-MTS Konsortium (Mitsui) is the contractor for the

    System Package. The audit revealed the objective of the project was not fully achieved

    due to several weaknesses such as delay in project completion that resulted in an

    estimated cost overrun of RM1.43 billion, procurement of excess equipments and non-

    coordination of train procurement with infrastructure development. In addition, there is a

    possibility of the Government bearing part of the losses estimated at RM1.14 billion.

    This is due to a maximum liability of RM257.99 million that could be claimed from the

    contractor as stipulated in terms and conditions of the contract between DRB-Hicom

    (original contractor) and the Government. To ensure Government gets value for money

    and also to prevent the recurrence of the same weaknesses in other projects, it is

    recommended that the Ministry of Transport (Ministry), Keretapi Tanah Melayu Berhad

    (KTMB) and related central agencies consider the following matters:

    The Ministry should impose penalties amounting to RM80.88 million (RM164,727

    per day) on DRB-Hicom for failing to complete the project on time.

    Five sets of Automatic Fare Collection System which are still kept in the store

    should be distributed to commuter stations that require them to avoid wastage.

    The Ministry/KTMB should ensure all defects are rectified by contractors during

    the Defects Liability Period so that the Government will not incur additional cost

    for repairs.

    Procurements of related equipments and facilities should be synchronized with

    the infrastructure and system development. In this regard, equipments and

    facilities should be procured when the progress of construction work achieved

    80% so that the infrastructure could be fully utilised upon completion.

    As stipulated in terms and conditions of the contract, the Ministry should report

    to the Ministry of Finance to terminate the service of the project manager who

    failed to perform.

    Central Agencies should allocate sufficient funds to procure equipments/facilities

    that are components of the project to enable a completed project to function

    according to plan.

    MINISTRY OF SCIENCE, TECHNOLOGY AND INNOVATION- Management Of Human Capital Development Programme In Science,

    Technology And Innovation

    From 2006 to 2008, a total of RM153.73 million was spent to carry out the Human

    Capital Development Programme. The audit revealed several weaknesses such as

    targets of schemes not fully achieved, payments made to unqualified recipients, several

    important elements to safeguard Governments interest were not included in the

    contract, delay in distributing allocations and failure to comply with terms and conditions

    of contract as well as inefficient monitoring and evaluation of the programme. In this

    regard, it is recommended that the Ministry of Science, Technology and Innovation(Ministry) considers the following matters:

  • 8/14/2019 Auditor General Report_2008-English

    23/40

    22

    Intensify publicity of the Human Capital Development Programme especially

    among students/lecturers of institutions of higher learning and also officers of

    Ministry/agencies involved in the field of science and technology.

    Ensure all important elements are included in the contract such as the

    requirement for all recipients to submit examination results/research progressreports and to present oneself after the end of the study/research. In addition,

    monitoring should also be carried out by the Ministry to ensure that the above

    terms and conditions are fully complied with and to impose penalties on those

    who fail to comply.

    Evaluate the Human Capital Development Programme to ascertain whether the

    programme has achieved its intended objective and consequently take remedial

    actions on any weaknesses that could affect the achievement of its objective.

    MINISTRY OF FEDERAL TERRITORYCity Hall Kuala Lumpur

    - Enforcement Of Trading Activities, The Department Of Safety AndEnforcement

    Generally, the audit revealed that the enforcement on the trading activities by the

    Department of Safety and Enforcement is unsatisfactory. Among the weaknesses

    observed were the Enforcement Action Reports were inconsistent with the Yearly

    Performance Target, delays in carrying out follow-up actions on KEJAs (obstruction by

    chairs and tables) operations, inefficiency in managing public complaints and Notice of

    Offence and Compound (Notice of Offence) as well as confiscated items were not kept

    properly. To overcome the above weaknesses, the City Hall Kuala Lumpur (City Hall) is

    recommended to consider the following matters:

    Ensure the Enforcement Action Report is prepared in consistent with the related

    Yearly Performance Target to enable evaluations be carried out on the

    performance of the enforcement activities by the Department of Safety and

    Enforcement.

    The Work Procedure Manual and the Client Charter for enforcement of trading

    activities need to be concise and clear. As such, City Hall needs to determine

    the time frame for carrying out follow-up action after issuance of Notice ofOffence/informing verbally to the petty traders to remove the chairs and tables

    that caused obstruction. In addition, the time frame for managing the public

    complaints as stated in the Work Procedure Manual and the Client Charter

    should be standardized. City Hall also needs to maintain a comprehensive and

    up-to-date Record of Complaints for the purpose of monitoring and enhancing its

    efficiency on delivery system.

    Enhance the methodology in managing compound collections by overcoming the

    problems relating to PADU System (Laws Database System). Besides that, City

    Hall needs to monitor the status of every Notice of Offence that was issued and

    prepare a Report on Arrears of Compound as well as to ensure that all Notice of

    Offence are filed properly.

  • 8/14/2019 Auditor General Report_2008-English

    24/40

    23

    Reduce time frame for claiming back confiscated goods from 3 months to 1

    month to enable earlier action to write-off the confiscated goods and thus

    overcome the problem of storage congestion and further depreciation of its value.

    MINISTRY OF EDUCATION MALAYSIA

    - Maintenance Of School Buildings

    A total of 47 private consultants were awarded contracts worth RM22.18 million to

    identify maintenance/repair works in schools that need to be carried out, supervise/

    monitor and certify the actual works done by contractors before payments are made by

    the Ministry of Education Malaysia (Ministry). The audit revealed that unsatisfactory

    maintenance works on some school infrastructure/buildings had resulted in poor/

    unconducive situation that could endanger the safety of its users. The weaknesses in

    the maintenance and repair works were due to the Ministry not being allocated sufficient

    funds and technical manpower. The Ministry on its part had not monitored the

    performance of the consultants which resulted in some consultants who fail to carryout

    their responsibilities effectively. In addition, the required monitoring on the works that

    supposedly carried out by the Ministry/State Education Departments (SED)/District

    Education Offices (DEO)/schools was not done. To overcome the above weaknesses, it

    is recommended that the Ministry considers the following matters:

    Prepare a scheduled maintenance plan that includes preventive and corrective

    maintenance for all schools in the country based on General Circular Letter No.

    2 of 1995. For this purpose, sufficient financial allocation must be provided.

    Prepare a clear and measurable scope for maintenance/repair works for easy

    reference by contractors and officers who supervise the related works.

    Enhance monitoring/supervision on maintenance/repair works carried out by

    contractors. For this purpose, the Ministry should closely monitor the

    performance of the consultants to ensure that they carry out their responsibility

    effectively as stipulated in the contract. Teachers stationed at SED/DEO/schools

    should not be given the task of managing maintenance works. Such

    responsibility should be given to those with technical knowledge and expertise.

    In relation to this, sufficient technical posts must be created and TechnicalAssistants Grade J36 which are still vacant in some SED must be filled

    immediately. To enhance monitoring on maintenance/repair works, a monitoring

    register should be maintained in each school.

    Take appropriate actions against those who were proven to have certified works

    as completed which actually has not been completed or not done at all as this is

    an improper payment. If the certification was done by a public officer, disciplinary

    action or surcharge must be imposed. If this involved a consultant, the company

    concerned should be blacklisted and the offence reported to the relevant

    professional bodies for further action.

  • 8/14/2019 Auditor General Report_2008-English

    25/40

    24

    Restructure the various divisions responsible for maintenance of school

    buildings by placing them under one unit to ensure maintenance/repair works

    could be planned and managed efficiently and effectively.

    Ensure all concerned parties involved in maintenance/repair works comply with

    the relevant financial regulations. Market surveys must be carried out to ensureGovernment gets value for money for all procurements. Financial management

    training should also be given to those involved.

    MINISTRY OF EDUCATION MALAYSIA

    - Project To Supply Clean Water To Rural Schools In Sabah

    The Ministry of Education Malaysia (Ministry) had implemented projects to supply clean

    water to rural schools in Sabah through the Rain Water Harvesting System, well tube,

    gravity water tube reticulation system and supplying treated water project. As at

    December 2008, a total of RM174.32 million had been spent for supplying clean water

    through Rain Water Harvesting System. The audit revealed that the implementation of

    phase 3 of this project was not satisfactory. There were weaknesses such as delays in

    project completion, work specifications not fully met, no maintenance of the pipe water

    system by contractors and project modifications done without approval by the

    Department of Federal Development of Sabah. To ensure the targeted group benefits

    from this project, it is recommended that the Sabah Project Team (SPT) who has taken

    over the function of the Department of Federal Development of Sabah and the Ministry

    consider the following matters:

    SPT should closely monitor the work carried out by contractors and ensure

    periodical maintenance of the pipe water system is carried out. In this regard, the

    school authorities, the Ministry, SPT and the contractors should coordinate by

    having regular meetings to discuss and overcome maintenance problems of this

    project.

    The Ministry should allocate funds for maintenance of the project after the expiry

    of the Defects Liability Period for its continuous benefits.

    SPT should ensure school authorities obtain approval before modification works

    are carried out so that the said modification would not affect the function of the

    water tank.

    SPT should determine total penalties that could be imposed on contractors and

    ensure that they settle the amount concerned.

    MINISTRY OF HEALTH MALAYSIA

    - Construction Of Pekan Hospital, Pahang

    The audit revealed that the implementation of this project at a total cost of

    RM96.45 million was not satisfactory resulting in the Government incurring losses as

    well as facilities provided could not be utilised for the benefit

    of the

    public. Among the

    weaknesses observed were the issuance of Certificate of Practical Completion (CPC)

  • 8/14/2019 Auditor General Report_2008-English

    26/40

    25

    even though certain portion of the works had not been completed and equipments not

    fully supplied by the contractor, delays in project completion resulting in cost overrun,

    unsuitable/poor quality construction works and equipments/facilities not been used

    optimally. To rectify the weaknesses, the Ministry of Health (Ministry) and the Public

    Works Department (PWD) need to consider the following matters:

    PWD should speed up the process of signing the contract to safeguard

    Governments interest and to enforce contract terms and specifications.

    Performance Bond and all insurance policies should also be submitted within the

    stipulated time.

    PWD should not issue CPC before completion of project and all equipments are

    supplied by contractor.

    The Ministry should ensure the 2 years warranty period for equipments received

    after the issuance of CPC is set from the actual date of equipments received andnot from 31 January 2009.

    The Ministry should expedite repair works on all detected defects/damages so

    that the hospital can operate effectively. In addition, the Rehabilitation and

    Pharmaceutical Unit should operate as soon as possible to ensure equipments

    procured could be utilised optimally.

    The Ministry should claim penalty from the supplier for the late supply of 2 units

    of ambulance immediately.

    The Ministry should maintain an Asset Register to record all assets procured.

    The Ministry should enhance the monitoring process to ensure quality works are

    completed according to schedule.

    MINISTRY OF HEALTH MALAYSIA

    - Management Of Prevention And Control Of Dengue Fever

    The audit revealed that the activities to prevent and control dengue fever by the Ministry

    of Health Malaysia (Ministry) were not effective in decreasing the incidence and

    mortality rate of dengue fever but instead keeps increasing every year. According to the

    Ministrys record there were 49,335 cases of dengue and dengue haemorrhagic fever

    with 112 deaths in 2008 as compared to 38,556 cases and 92 deaths in 2006. Among

    the factors that could have caused such increase were weaknesses in enforcements

    and controls such as inspections of premises were not done according to plan, failure to

    follow-up inspections on premises that could not be inspected during the previous visits,

    vector detection index not fully used, delay in notifying dengue cases and incomplete

    blood test. These weaknesses among others were due to lack of manpower and

    facilities as well as lack of cooperation from the public in the prevention and control of

    this disease. In relation to this, it is recommended that the Ministry considers the

    following matters:

  • 8/14/2019 Auditor General Report_2008-English

    27/40

    26

    Create specific posts and special units at the Ministry, State Health Departments

    and District Health Offices to prevent and control dengue fever as incidence and

    mortality rate of dengue fever kept on increasing yearly. With the creation of

    such unit, the Ministry should consider taking over this activity from local

    authorities to ensure proper and comprehensive planning and implementation.

    Use of the Vector Detection Index to ensure detection of infection risk level/

    dengue epidemic is implemented at all districts. In addition, the prevention and

    control of Aedes mosquitoes should be implemented at all identified high risk

    localities.

    Create a mechanism to overcome problems that has contributed to the delay in

    sending notices of dengue fever cases. Early notification is essential to ensure

    the inspection of premises and fogging to be done as soon as possible in the

    affected areas to prevent an epidemic from happening.

    Ensure inspections are carried out according to plan as the inspection ofpremises to detect the reproduction of Aedes mosquitoes is one of the important

    controls to reduce the incidence of dengue fever.

    Ensure follow-up inspections are carried out on premises which were not

    inspected during the previous visit so that the potential reproduction habitat for

    Aedes mosquitoes are identified and early eradication carried out. For this

    purpose, the Ministry should intensify the awareness campaign regarding the

    importance of publics cooperation in making the prevention and control of

    dengue fever a success. In relation to this, involvement by public groups such as

    community societies, youth clubs, non-governmental organisations and voluntary

    groups should also be encouraged.

    Ensure serology tests carried out are recorded properly. This test is to establish

    whether an individual has been infected with dengue fever so that treatment can

    be given and affected premises and localities be identified earlier to prevent the

    epidemic.

    Determine a reasonable time frame and ensure it is complied with to prevent any

    delay in the issuance of compound notices which will affect enforcements

    effectiveness. In addition, action should be taken on all unsettled compound

    cases by referring to the Deputy Public Prosecutor.

    Distribute unused equipments to other District Health Offices that require them to

    prevent obsolescence and wastage. Besides that, a plan to increase the number

    of transportation vehicles should be prepared.

    MINISTRY OF HEALTH MALAYSIA

    - Management Of Harm Reduction Programme

    The Harm Reduction Programme implemented by the Ministry of Health Malaysia

    (Ministry) since 2006 consists of 2 components, namely Methadone Replacement

    Therapy as well as Needle and Syringe Exchange Activity with the objective of

    preventing the spread of Human Immunodeficiency Virus (HIV). Generally, the audit

  • 8/14/2019 Auditor General Report_2008-English

    28/40

    27

    revealed that this programme has helped in reducing the addiction level, minimize risky

    lifestyle behaviors and improve the quality of an addicts life. However there were

    several weaknesses that need to be rectified such as the number of addicts treated did

    not reach the targeted goals due to either lack of medical personnel or required basic

    facilities, improper procurement of methadone that resulted in Government incurring

    losses, improper records of needles in hand and ineffective monitoring on the

    performance of the programme. In this regard, it is recommended that the Ministry

    considers the following matters:

    Create special posts and ensure the availability of sufficient basic facilities in all

    hospitals or health clinics that are involved in this programme as the

    effectiveness of the Methadone Replacement Therapy requires the involvement

    of health personnel on a full time basis and sufficient basic facilities.

    Ensure financial aid is provided to the Malaysian AIDS Council and other

    responsible non-governmental organisations under the Needle and Syringe

    Exchange Activitybefore such activity commences.

    Enhance the Needle and Syringe Exchange Activity by increasing the coverage

    areas through the Outreach activity as this programme is able to create

    awareness among the addicts on the risk of HIV infections through sharing

    needles. Besides this, co-operation with the police and locals must be improved.

    Impose penalties on suppliers who do not comply with the terms and conditions

    of contract for supplying methadone. In future, the Ministry should immediately

    inform and submit a copy of the agreement to hospitals to prevent purchases ofmethadone outside contract at a higher cost.

    Ensure all parties involved in the procurement, recording and storage of needles

    comply with relevant regulations.

    Ensure the MyMMT system (My Methadone Maintenance Therapy System)

    functions as planned and the Malaysian AIDS Council submits report on its

    achievement of activities organised within the stipulated time in order to enhance

    monitoring of the Harm Reduction Programme. With information obtained from

    the above sources, the Ministry should then carry out analysis to evaluate the

    effectiveness of the programme.

    MINISTRY OF HOUSING AND LOCAL GOVERNMENT

    Town And Country Planning Department, Peninsular Malaysia

    - Management Of Local Planning

    Local Planning (LP) is an important reference document to ensure systematic

    development of a particular area. It contains among others, explanation regarding the

    use of land, environment, infrastructure and utility, landscape and traffic of a particular

    area. The audit revealed several weaknesses such as delay in gazetting the LP thatresulted in a shorter execution period, approval of development based on a draft LP and

  • 8/14/2019 Auditor General Report_2008-English

    29/40

    28

    benefits could not be enjoyed by the public fully. Besides that, compliance to the LP was

    not closely monitored. In this regard, it is recommended that the Town and Village

    Planning Department, State and Local Authorities who are directly involved in the

    preparation/usage of the LP consider the following matters:

    All involved parties should collectively prepare a comprehensive guideline on

    preparation, gazetting, printing, distribution and enforcement of the LP to ensure

    it could be adhered to by all concerned parties. Among others, the guidelines

    should state the responsible party to manage the printing, the number of LP to

    be printed and distributed as well as records to be maintained in relation to the

    preparation, distribution and monitoring of its usage. In addition, a time frame

    should also be determined for each related work process.

    The Ministry of Finance should review the process of appointing consultants and

    the cost involved to prepare the draft LP as the present process takes a long

    time.

    The local authorities should consistently monitor the relevant areas and take

    necessary actions against parties who do not abide by the LP to ensure that the

    development is done in accordance with the gazetted LP. This is required to

    ensure a systematic development of the area does not threaten life or the

    environment and the Government gets value for money for costs incurred in

    preparing the LP.

    MINISTRY OF INFORMATION, COMMUNICATION AND CULTURE

    National Library Department

    - Management Of Rural Libraries

    As at 31 December 2008, a total of 425 rural libraries were operating in the country.

    They were established to be the catalyst to cultivate the reading habit and reduce

    disparities of illiteracy among the rural folks and the urbanites. The audit revealed

    several weaknesses such as delay in completing construction/renovation of buildings,

    works did not comply with agreed specifications/scopes, unsatisfactory maintenance of

    buildings, improper records of books and penalties were not imposed on suppliers who

    failed or delayed the supply of books/reading materials. In this regard, it is

    recommended that the National Library Department considers the following matters:

    Monitor construction of rural libraries or renovations on public buildings as rural

    libraries to ensure project specifications/scopes are fully complied with by

    implementing agencies. In addition, the National Library Department should

    review the number of officers required to carry out supervision as currently it has

    only one assistant technician to supervise the construction of all rural libraries in

    the country. The same officer is also involved in other development projects

    managed by the National Library Department.

    Carry out periodical maintenance of rural libraries to ensure they are always in

    good physical condition and safe to use. For this purpose, sufficient funds should

    be allocated.

  • 8/14/2019 Auditor General Report_2008-English

    30/40

    29

    Monitor the performance of suppliers of books and ensure they comply with the

    terms and conditions of contract and impose penalties if they fail to do so. A

    mechanism should be created to enable rural libraries to procure the latest

    magazines.

    Synchronize procurement of books and library accessories with completion dateof construction/renovations of rural libraries to ensure they could operate and

    benefit the public upon completion.

    Ensure all rural libraries continuously implement activities of cultivating reading

    habits as these can increase the interest of reading among the local

    communities. For this purpose, a guideline on Implementing Rural Libraries

    Activities should be issued to relevant parties to explain the implementation

    procedures/processes of such activities.

    Review whether a minimum fine could be imposed on book borrowers to reduce

    the rate of lost/unreturned books.

    MINISTRY OF INFORMATION, COMMUNICATION AND CULTURE

    Department Of Broadcasting

    - Management Of Procurement Of External Broadcasting Van WithBroadcasting System And Digital Radio Production

    a. The Ministry of Information (Ministry) had spent not less than RM40 million for the

    procurement of External Broadcasting Van with Broadcasting System and Digital

    Radio Production in order to increase broadcasting coverage of Radio Television

    Malaysia (RTM). However, there were several weaknesses in the said procurement

    such as delays in the supply of the specific van/equipments, contract conditions not

    complied with and improper payments. To ensure the objectives of the procurement

    are achieved and the Government gets value for money, it is recommended that the

    Ministry considers the following matters:

    Ensure the contractor supplies the External Broadcasting Van and Broadcasting

    Equipments that have yet to be delivered. In relation to this, the Ministry should

    ensure the contractor renews the Performance Bond which had expired on 3rd

    March 2009 and renews the warranty for the undelivered van and equipments.

    For the case where payment has been made for unsupplied equipments,

    investigation should be carried out to identify the responsible parties and if found

    guilty, surcharge must be taken against them.

    RTM should inform their stations that received the equipments on its warranty

    and manufacturers guarantee in order to benefit from these facilities.

    b. To safeguard Governments interest, it is recommended that the Ministry should

    improve its procurement management by taking the following steps:

    Contracts must be signed within 4 months from the date of issuance of the Letterof Acceptance.

  • 8/14/2019 Auditor General Report_2008-English

    31/40

    30

    Ensure the Performance Bond is valid until all repairs on defects are completed

    by the contractor to prevent the Government from bearing the cost of repairs.

    Any application to modify the specification or equipment schedule should only be

    approved after a price adjustment and contract cost survey has been carried out.

    The contractor should also submit a confirmation of quality assurancecomparable to the original specification.

    MINISTRY OF HUMAN RESOURCES

    - Management Of Educational Equipments In Training Institutes, ManpowerDepartment

    Under the Eighth Malaysia Plan, the Ministry of Human Resources (Ministry) has spent

    not less than RM441.33 million to provide educational equipments to 7 Industrial

    Training Institutes throughout the country. The audit revealed several weaknesses in the

    management of the equipments which resulted in Government not getting value for

    money and adversely affected the academic activities. Among the weaknesses were

    equipments procured at a much higher cost than market value, not less than RM3.66

    million worth of equipments not utilised or underutilised and improper maintenance of

    equipments. These weaknesses among others were the result of poor planning for

    procurement/maintenance of equipments and the failure to carry out market price

    surveys. In this regard, it is recommended that the Ministry considers the following

    matters:

    Ensure contract price is based on negotiated price of each type of equipment

    and agreed between the supplier and the Ministry and not based on the

    approved allocation for the procurement. In relation to this, market price surveys

    should be carried out as a reference in determining the price of the equipments

    as well as verify the price offered by the supplier.

    Carry out detailed planning of the procurement and obtain views from lecturers/

    trainers to ensure only compatible and required equipments are procured.

    Review the rate of penalty imposed on suppliers for delays in the supply of

    equipments as the present rate is too low.

    Determine time frame for every relevant work process in the maintenance/repairs of equipments and ensure that the time allocated is complied with to

    prevent delays in maintenance/repairs. In addition, the Ministry should take

    action on suppliers who delay maintenance/repairs by imposing a penalty or

    confiscate the Performance Bond.

    MINISTRY OF HIGHER EDUCATION

    - Management Of Procurement Of Course Equipments For Community Colleges

    From 2006 to 2008, the Ministry of Higher Education (Ministry) had spent a total of

    RM80.07 million to provide course equipments for community colleges. The audit

    revealed several weaknesses such as required equipments were not provided,

  • 8/14/2019 Auditor General Report_2008-English

    32/40

    31

    equipments not used optimally due to oversupply/not required/not suitable equipments,

    delays in supply, payments made though equipments has not been tested/

    commissioned, equipments kept at an unsuitable/unsafe location as well as asset

    records not maintained properly nor updated. In this regard, it is recommended that the

    Ministry considers the following matters:

    Obtain views from relevant lecturers to ensure equipments procured are suitable

    for the courses. For cases where suppliers failed to deliver, the Ministry should

    take immediate actions to acquire unsupplied equipments by appointing new

    suppliers. Whereas for the oversupplied equipments, it should be distributed to

    other community colleges which require the said equipments.

    Take action to ensure that all remaining equipments that have not been received

    by the relevant community colleges are delivered by suppliers immediately.

    The relevant community colleges should urgently apply for funds from the

    Ministry to improve its security. Community colleges should also be perceptive

    regarding the suitable placement of the equipments and to immediately obtain

    certification from the Department of Occupational Safety and Health Malaysia for

    specific equipments that require such certification.

    Maintain proper and up-to-date asset records for easy reference. Such records

    should also be regularly checked by responsible officers and used for the

    purpose of physical verification.

    Carry out investigation to determine all payments were vouched with supporting

    documents. If misappropriation of funds occurs, disciplinary action or surcharge

    must be taken against the responsible parties.

    Training should be given to officers involved in the procurement of equipments

    and the maintenance of the asset records especially for officers of the

    community colleges.

    MINISTRY OF HOME AFFAIRS

    - Construction And Management Of The Ministry Of Home Affairs Complex,Perak

    This complex was completed in April 2005 at a cost of RM41.83 million. The auditrevealed several weaknesses such as the As-Built Plan together with the Operational

    and Maintenance Manual were only furnished by the contractor 3 years after project

    completion, delay in handing over the As-Built Plan had caused the consultant to face

    difficulties in certifying the quality of the construction works and remedial works were not

    fully carried out by the contractor during Defects Liability Period. In addition, work areas

    were not up to the standards set by the Malaysian Administrative Modernisation and

    Management Planning Unit and also did not take into consideration areas for additional

    staff as well as facilities such as the Day Nursery, Library, Sports and Recreation Room

    were not utilised. In this regard, it is recommended that the Ministry considers the

    following matters:

  • 8/14/2019 Auditor General Report_2008-English

    33/40

    32

    Prepare a comprehensive manual on managing this complex that includes all

    aspects of managing a common user building such as financial requirement,

    usage of areas/facilities and the security of the building.

    Settle all issues on remedial works immediately by urging the contractor to

    complete unfinished works and to issue the Certificate of Making Good Defectsas well as to finalise the closing account of the project as soon as possible.

    The Complex Maintenance Management Committee which was formed in July

    2008 must take assertive and immediate actions to settle complaints from

    employees and the public regarding the facilities in the complex.

    As a short term solution, renovate and modify all underutilised areas such as

    Day Nursery, Library, Sports and Recreation Room to be converted into work

    areas for departments facing critical shortage in office space. For long term

    measure, the Ministry should plan to relocate certain departments that do not

    deal with the public in different buildings/locations as the surrounding areas of

    the complex are limited.

    The Ministry and management of the complex should take immediate action to

    increase its level of security to ensure the safety of assets and users.

    MINISTRY OF HOME AFFAIRS

    Royal Malaysian Police

    - Management Of Red LightSurveillance Camera System And The Issuance Of

    Summons

    The Red Light Surveillance Camera System was developed by the Royal Malaysian

    Police (RMP) at a cost of RM8.98 million with the intention to increase awareness of

    road users to abide the traffic lights rules, thereby reducing the accident rate at road

    junctions. The contract for maintenance, repairs and supply of spare parts for this

    system valued at RM5.46 million was signed between the Ministry of Internal Security

    and Commercial Circle (M) Sdn. Bhd. for the period from 2004 to 2009. As at 31

    December 2008, the contractor has been paid a total of RM3.21 million. The audit

    revealed that the management and monitoring of the system and its equipments were

    not satisfactory. There were several weaknesses that could adversely affect theeffectiveness of the system such as equipments not being fully utilised, faulty

    equipments that remain unrepaired and without proper maintenance, placing

    equipments at unsuitable locations and inefficient issuance of summons. To rectify the

    weaknesses and to ensure the Government achieves the objective of installing the

    system and to get value for money, it is recommended that the Ministry of Home Affairs

    and RMP take the following remedial actions:

    Create a mechanism to collect data on the number of accidents due to violation

    of the traffic light rules and accidents at junctions which have been installed with

    the system for the purpose of evaluating the effectiveness of the system in

    achieving its objective.

  • 8/14/2019 Auditor General Report_2008-English

    34/40

    33

    Ensure fully functional system/equipments are installed at suitable locations. For

    this purpose, continuous supervision must be carried out to ensure maintenance

    of the system/equipments are done according to schedule and breakdowns

    repaired immediately. Besides this, the Ministry/RMP should co-operate with the

    relevant local authorities to ensure construction/road widening/development

    activities do not affect the effectiveness of the system.

    Designate police personnel to manage the system and train them to operate the

    system especially in film handling to ensure there are no faulty recordings which

    will jeopardise the issuance of summons.

    Determine a time frame for each process from the date of offence until the

    issuance of summons to ensure there is no delay in issuing summons to

    offenders.

    VARIOUS MINISTRIES AND DEPARTMENTS

    - Management Of Emolument For Civil Servants

    Based on data in the Human Resources Management Information System (HRMIS), a

    total of 1,257,426 posts of various grades have been approved by the Public Services

    Department of which 1,013,532 posts have been filled up as at 31 December 2008. The

    total filled up posts do not include 206,652 personnel in the armed forces and police.

    For 2008, a total of RM41.01 billion has been spent on emoluments. At ministries/

    departments, there were several weaknesses in the management of emolument that

    resulted in over/under payments due to mistakes/carelessness by/of the officers while

    processing payments, lack of co-ordination among divisions involved, lack of

    supervision on collections of overpaid emoluments and service records not updated. To

    overcome the weaknesses, it is recommended that ministries/departments consider the

    following matters:

    Impose surcharge against careless officers who caused over/under payments of

    emoluments in accordance with Section 18 Financial Procedures Act.

    Establish co-ordination among involved parties at all levels to ensure existing

    regulations are complied with and timely updating of information could be done

    whenever there is a change in officers status especially involving transfers andpromotions.

    Ensure responsible officers carry out detail checking before approving any

    changes in the emolument of officers to avoid over/under payments.

    Issue delegation of power to officers who approve the Statement of Changes of

    Officers Salary (Form Fin. 8).

    Provide regular training to officers who manage emolument payment to increase

    their awareness in existing and latest regulations. The National Public

    Administration Institute should be requested to organise courses related to the

    management of emolument. In addition, officers should refer to the process of

    managing emolument as stated in the Manual Work Procedures.

  • 8/14/2019 Auditor General Report_2008-English

    35/40

    34

    The Accountant General's Department Malaysia should expedite interfacing of

    the Government Financial And Management Accounting System (GFMAS) and

    Human Resource Management Information System (HRMIS). Heads of

    department should ensure all required information is updated in HRMIS and its

    accuracy verified.

    Internal Audit/Inspectorate Unit in each ministry/department should randomly

    check service records of officers every 6 months to ensure these records are

    complete and updated. Errors detected from such checking could be rectified

    immediately.

    PART II - MANAGEMENT OF GOVERNMENT COMPANIES

    As at 31 December 2008, the Government has invested RM24.21 billion in 99

    companies. A total of RM22.51 billion was invested in 50 companies where theGovernment holds more than 50% equity. The objectives of these investments are to

    obtain reasonable returns, maintain Governments interest in strategic sectors and to

    invest in sectors that lack investments from the private sectors. Audit analysis on the

    income for 2007 of 48 companies revealed that 27 companies earned pre-tax profit of

    RM78 billion whereas the remaining 21 companies incurred losses amounting to

    RM0.87 billion. However, only 14 out of the 27 profitable companies paid dividends

    totalling RM72.21 billion to the Government. A total of 30 companies paid tax amounting

    to RM24.37 billion to the Government. The audit revealed that the activities of these

    companies were well planned. However there were weaknesses in the implementationof these activities especially with regards to internal controls of financial management.

    - MANAGEMENT OF EXPORT- IMPORT BANK OF MALAYSIA BERHAD

    Export-Import Bank of Malaysia Berhad (EXIM Bank) is wholly owned by the

    Government with a paid up capital of RM2.71 billion. The main objective of EXIM Bank

    is to arrange for credit facilities to increase the capabilities of Malaysian companies to

    export products/services and carry out investment projects overseas. From 2006 to

    2008, EXIM Bank approved 115 loans/guarantees totalling RM3.30 billion. The audit

    revealed that the management of lending activities of EXIM Bank were not satisfactory

    such as approval of loans which does not meet the established criteria or without liquid

    assets or bank/corporate guarantees, loose process in the release of loans, ineffective

    performance monitoring of the borrowers and increase in non-performing loans (NPLs).

    In this regard, it is recommended that the Board of Directors and the management of

    EXIM Bank consider the following matters:

    The management should ensure appropriate loan securities are determined by

    considering the risk level of every borrower by giving priority to securities such

    as cash/cash and equivalents or bank/corporate guarantees.

  • 8/14/2019 Auditor General Report_2008-English

    36/40

    35

    The Board and management should monitor and supervise closely the

    performance of borrowers and carry out post mortem review on all NPLs in

    accordance to the policies of EXIM Bank. This is to ensure NPLs do not

    continue to increase. In addition, loan performance status should be made a

    compulsory agenda and to be presented/discussed at every Boards meeting.

    The management should ensure dividends be paid from profits to the

    Government, who as a shareholder entitles for such returns on the investments.

    - MANAGEMENT OF SYARIKAT PRASARANA NEGARA BERHAD

    Syarikat Prasarana Negara Berhad (Prasarana) is wholly owned by the Government

    with a paid up capital of RM3.80 billion. The company is responsible to manage the

    infrastructure of public transportation in Klang Valley and Penang. As at


Recommended