Infrastructure Improvement Priorities August 10, 2017 Chris Cornelison
Transcript
Page 1: August 10, 2017 Chris Cornelison...Infrastructure Projects FY 2016/17 Project Location Stage Cost Tangerine Rd. - La Cañada Dr. to Shannon Rd. Under Construction Regional Partnering

Infrastructure Improvement Priorities

August 10, 2017

Chris Cornelison

Page 2: August 10, 2017 Chris Cornelison...Infrastructure Projects FY 2016/17 Project Location Stage Cost Tangerine Rd. - La Cañada Dr. to Shannon Rd. Under Construction Regional Partnering

Infrastructure Projects FY 2016/17

Project Location Stage Cost

Tangerine Rd. - La Cañada Dr. to Shannon Rd.Under ConstructionRegional Partnering $2,860,000

Lambert Ln. - La Cañada Dr. to Rancho Sonora Dr. Under Construction $6,500,000

La Cholla Widening – Overton Rd. to Tangerine Rd. Finishing Design $2,000,000

Traffic Signal at La Cañada Drive and Community

Center entranceDesign under contract $250,000

La Cañada Drive and Moore Rd intersection study Study started in

FY16/17$50,000

Page 3: August 10, 2017 Chris Cornelison...Infrastructure Projects FY 2016/17 Project Location Stage Cost Tangerine Rd. - La Cañada Dr. to Shannon Rd. Under Construction Regional Partnering

Regional partnerships

Tangerine Rd. from La Cañada Dr. to Shannon Rd.

$2.86 million budget

Tangerine Road Widening – Marana lead agency

Final Design - late 2015

Utilities clearing and relocation - fall 2015

Start roadway construction - spring 2016

Finish roadway construction - late 2018

Page 4: August 10, 2017 Chris Cornelison...Infrastructure Projects FY 2016/17 Project Location Stage Cost Tangerine Rd. - La Cañada Dr. to Shannon Rd. Under Construction Regional Partnering

Lambert Ln. from La Cañada Dr. to Rancho Sonora Dr.

$6.5 million budget

This is a safety improvement with emphasis in lowering the roadway profile between La Cañada Dr. and Rancho Sonora Dr. to enhance sight distance.

Start construction October 3, 2016; Substantial completion September 2017

4-lanes to RS Dr., multi-use path, sidewalk, and drainage improvements

Remove 60,000 cubic yards of dirt

Aesthetic value – Bighorn sheep’s horn in soil nail wall

Page 5: August 10, 2017 Chris Cornelison...Infrastructure Projects FY 2016/17 Project Location Stage Cost Tangerine Rd. - La Cañada Dr. to Shannon Rd. Under Construction Regional Partnering

Regionally significant

La Cholla Blvd. from Overton Rd. to Tangerine Rd. - Design

$2 million budget design

Project costs estimated at $23 million total

Resume final design phase

Project information website www.LaChollaImprovements.info

AECOM consultant contracted by the TownFinal design by end of 2017

Proposed improvements:4-lane divided desert parkway corridorDrainage facilitiesMulti-use pathResidential frontage road2 animal crossings

Page 6: August 10, 2017 Chris Cornelison...Infrastructure Projects FY 2016/17 Project Location Stage Cost Tangerine Rd. - La Cañada Dr. to Shannon Rd. Under Construction Regional Partnering

La Cañada Dr. Traffic Study and Signal

La Cañada Dr. Traffic Signal - $250,000Entrance of Community & Recreation Center

RTA funded

La Cañada Rd./Moore Rd. intersection study (currently 4-way stop) - $50,000

PAG funded

Either signalized intersection or roundabout (determined after study completed)

To be completed in next few months

Page 7: August 10, 2017 Chris Cornelison...Infrastructure Projects FY 2016/17 Project Location Stage Cost Tangerine Rd. - La Cañada Dr. to Shannon Rd. Under Construction Regional Partnering

Projects Completed

Completed FY 2016 Highlights

Rancho Vistoso and Vistoso Highlands Traffic Signal$500,000 budget for traffic signal; $20,000 budget for sidewalk

Includes sidewalk and pedestrian enhancements along Rancho Vistoso Boulevard from Vistoso Highlands Dr. to Morning Vista Dr.

Naranja Dr. from La Cholla Blvd. to Ironwood High School $2 million budget

Three lane roadway, drainage structures, multi-use path, sidewalk, curb, multi-use lanes

Page 8: August 10, 2017 Chris Cornelison...Infrastructure Projects FY 2016/17 Project Location Stage Cost Tangerine Rd. - La Cañada Dr. to Shannon Rd. Under Construction Regional Partnering

Upcoming CIP

Naranja Park - Constructing 2 new multi-use fields w/ lightsCost = $1 million

Naranja Dr. widening to 3 lanes at entrance (Cost = $458,000)• Adding a 2-way left-turn lane

Tangerine Rd. access into Safeway at 1st Ave. ($250,000)

Palisades Rd. multi-use path ($284,000)

Page 9: August 10, 2017 Chris Cornelison...Infrastructure Projects FY 2016/17 Project Location Stage Cost Tangerine Rd. - La Cañada Dr. to Shannon Rd. Under Construction Regional Partnering

In Review Process

Residential Subdivisions

Rancho Vistoso Parcel 5G, K, & V (Mattamy) – East side of Rancho Vistoso Blvd along new Moore Road extension to be constructed; 150 total lots

Rancho Vistoso Parcel 6B (Mattamy) – SE corner of Rancho Vistoso Blvd. and Moore Road; 36 total lots

Sanctuary at Silverhawke (Meritage) – East side of 1st

Avenue at Naranja Rd. intersection; 44 total lots

Villages at Silverhawke (Meritage) – East side of 1st

Avenue, north of Palisades Road; 211 total lots

Page 10: August 10, 2017 Chris Cornelison...Infrastructure Projects FY 2016/17 Project Location Stage Cost Tangerine Rd. - La Cañada Dr. to Shannon Rd. Under Construction Regional Partnering

Under Construction

Residential Subdivisions

Eagle’s Rest (Lennar) – north side of Moore between La Canada/Rancho Vistoso Blvd.; 75 total lots

La Canada Ridge (Insight) – west side of La Canada and south of Moore; 12 total lots

Meritage at Stone Canyon 8 – New area north of existing Tortolita Mountain Circle; 36 total lots

Rancho Vistoso Parcel 5F (Mattamy) – NE corner of Rancho Vistoso Blvd./Moore Road; 116 total lots

Page 11: August 10, 2017 Chris Cornelison...Infrastructure Projects FY 2016/17 Project Location Stage Cost Tangerine Rd. - La Cañada Dr. to Shannon Rd. Under Construction Regional Partnering

Now Open and Selling

Residential Subdivisions

Center Pointe Vistoso (Maracay) – north end of La Canada Blvd; 344 total lotsDiscovery at Vistoso Reserve (Lennar) – SW corner of Rancho Vistoso Blvd and Vistoso Highlands intersection; 27 total lotsEnclave at Stone Canyon (Mattamy & Fairfield) – southeast of new clubhouse; 36 total lotsEstates at Capella (Meritage) – south side of Naranja, east of Ironwood Ridge HS; 120 total lotsRancho del Cobre (Maracay) – east side of La Cholla Blvd, south of Tangerine Rd; 68 total lots

Page 12: August 10, 2017 Chris Cornelison...Infrastructure Projects FY 2016/17 Project Location Stage Cost Tangerine Rd. - La Cañada Dr. to Shannon Rd. Under Construction Regional Partnering

Amphitheater K-5 STEM School

New Elementary School

Science, technology, engineering and math

Recently Completed for 2017/18 school year

Approximately 500 students

Located northeast of La Cañada Dr. and Moore Rd. intersection, off of Desert Fairways Dr.

Page 13: August 10, 2017 Chris Cornelison...Infrastructure Projects FY 2016/17 Project Location Stage Cost Tangerine Rd. - La Cañada Dr. to Shannon Rd. Under Construction Regional Partnering

Oro Valley Leman Academy

New Elementary School

Located west of La Cañada Dr. and north of Tangerine Rd.

Recently opened w/ Temporary Certificate of Occupancy

Kindergarten through 6th grade, w/ pre-kinder program

Plan to end with a K-8 by 2019

Page 14: August 10, 2017 Chris Cornelison...Infrastructure Projects FY 2016/17 Project Location Stage Cost Tangerine Rd. - La Cañada Dr. to Shannon Rd. Under Construction Regional Partnering

Town of Oro Valley

Questions

Chris Cornelison

Assistant Town Manager

[email protected]