Auk North Field Development
The Production & Development Conference & ExhibitionAberdeen Exhibition and Conference Centre
12th May 2011
Auk North Field Development 12th May 2011 2
Auk North Field Development: Outline
• Background
• Appraisal
• Development Concept
• Field Determination
• Project Execution
• Current Status
• Summary
Auk North Field Development 12th May 2011 3
Background: Location
Aberdeen
United
Kingdom
Auk Field
Quad 30
Block 16
• Auk North is the northern part of the
Auk field
• The Auk field is located approximately
250 km east-south-east of Aberdeen in
Block 30/16
• The Auk field was discovered in 1971
• First production from the Auk field
occurred in 1975
• Talisman acquired the Auk field in
December 2006
Auk North Field Development 12th May 2011 4
Background: Overview of Auk Field
• The reservoir consists of Zechstein carbonates and Rotliegend sandstones containing a low gas-oil ratio (GOR) oil
• Areal extent: 60 km2
• Reservoir depth: 7300-7750’ ft TVD(SS)
• Auk North undeveloped at time of acquisition (beyond reach of platform drilling rig)
PLATFORM
Oil
Water
LINE OF SECTION
Zechstein ExtentN2
N1
N3A
N4N4Z
Devonian
Zechstein
Triassic
Chalk
Rot 1
2000
2500
3000
msT
WT A25 30/16-9A3Z30/16-2
Rot 3, 4 & 5
0.5 km
Rot 2 O.W.C
W E
Rot 2
Rot 3, 4 & 5
Devonian
Zechstein
Triassic
Chalk
Rot 1
2000
2500
3000
msT
WT A25 30/16-9A3Z30/16-2
Rot 3, 4 & 5
0.5 km0.5 km
Rot 2 O.W.C
W E
Rot 2
Rot 3, 4 & 5
Auk
Auk North
Top Rotliegend Depth Structure Map
Auk North Field Development 12th May 2011 5
Background: Auk Field Production History
• First oil in December 1975
• Initial development focus
was on Zechstein
• Production peaked in May
1977
• Production mechanism is depletion drive with aquifer support
Auk Historical Production
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
Dec-7
5
Dec-7
7
Dec-7
9
Dec-8
1
Dec-8
3
Dec-8
5
Dec-8
7
Dec-8
9
Dec-9
1
Dec-9
3
Dec-9
5
Dec-9
7
Dec-9
9
Dec-0
1
Dec-0
3
Dec-0
5
Dec-0
7
Dec-0
9
Oil P
roduction R
ate
[stb
/d]
0
20
40
60
80
100
120
140
160
Cum
. O
il [M
Mstb
]
Zechstein Rotliegend Conventional Rotliegend Horizontal Cum.Oil.
Rotliegend horizontal wells
transformed Auk after decline in Zechstein
• Normally pressured reservoir with jet pumps and ESP’s used for artificial lift
• Development focus switched to Rotliegend in the 1990’s with application of
horizontal well technology
Auk North Field Development 12th May 2011 6
Background: Geology
ROT2
ROT3
ROT4
ROT5
Ripple laminated & slipface sands
Slipface sands
Slipface sands
Waterlain conglomerates & sands
ROT1 Slumped & waterlainsands
Anhydrite (A06 only)Shales and anhydrite residue
Vuggy dolomite
Kupfercheifer shale
Devonian
ROT2
ROT3
ROT4
ROT5
Ripple laminated & slipface sands
Slipface sands
Slipface sands
Waterlain conglomerates & sands
ROT1 Slumped & waterlainsands
Anhydrite (A06 only)Shales and anhydrite residue
Vuggy dolomite
Kupfercheifer shale
Devonian
Kupferschiefer Shale
~200-400ft
~30ft
Aeolian
Marine
Aeolian
Generalised StratigraphyReservoir Summary
Zechstein
Rotliegend
Lower
Permian
Upper
Permian
~30ft
Devonian
Kupferschiefer Shale
ROT2
ROT1
ROT3
ZECHSTEIN
� Original justification for Auk development
� Leached dolomitised platform carbonates
� Vugs, solution channels and fractures dominate fluid flow
� Erosionally truncated towards the east
� Communication with Rotliegend reservoir below
ROT1
� Dominated by waterlain mass-flow sandstones, probably
reworked dune sands
� Variable reservoir development with some better quality
homogeneous intervals
ROT2
� Dominant oil-bearing interval in the Auk Field
� Aeolian sandstones, with both wind ripple and slipface sands
� Complex heterogeneous system of good quality slipface
sands (linear dune slipface) enclosed within poor quality wind
ripple sands (linear dune plinth and sandsheets)
ROT3
� Dominated by a thick succession of slipface sands
� Best reservoir quality rock in the Rotliegend but predominantly
in the water-leg, with only a small oil leg in the crest of the
field
Auk North Field Development 12th May 2011 7
Background: Rotliegend Depositional Model
Sand flat
Higher wind velocities in upper portions of linear dunes result in winnowed, better sorted sands (reworked wind rippled sands)
(wind ripple sand)
Laterally impersistent slipfaces developed at all levels on flanks of large linear dunes
Small barchanoid dunes on flanks of linear dunes or draa result in
preserved slipfaces even on lower plinths of linear dunes
Patchy preservation of upper reworked wind ripple sand facies
Preservation threshold controlled by angle of climb of dune
Small barchanoid dune field in interdune corridor associated with sand flat and lower plinth areas
Auk North Field Development 12th May 2011 8
Background: Auk Rotliegend Unit 2 Geological Variability
Re-worked Wind Ripple Sand Slipface SandWind Ripple SandUV LightPlain Light
Rotliegend Core Showing Red Stained (Non-Oil Bearing) Wind Rippled Sands and Bleached (Oil-Bearing) Re-worked Wind Ripple and Slipface sands (Coarser Grained and More Permeable Sands)
Rotliegend facies proportions:
• Slipface Sand: 10-15%
• Re-worked Wind Ripple
Sand: 20-30%
• Wind Ripple Sand: approx.
60%
Auk North Field Development 12th May 2011 9
Appraisal: Programme Objectives
• Existing appraisal well data in Auk North insufficient to reduce uncertainty in factors influencing STOIIP:
− Depth of top structure on flank
− Net-to-gross tends
• Existing seismic data unable to be used to map net-to-gross trends
• Recognised that several well penetrations would be required to reduce the uncertainty in the STOIIP
• Appraisal programme consisted of:
− Vertical well with deviated side-track (30/16-
15/15Z)
− Vertical well with deviated side-track and
horizontal side-track (30/16-16/16Z/16Y)
• Appraisal wells drilled between September 2007 and February 2008
30/16-15Z
30/16-16
30/16-16Z
30/16-16Y
Zechstein
Triassic
Chalk
Rot 2/3/4
Devonian
12 13Z 13 15Z 15WSW ENE
2000
2500
ms
TW
T
1 km3000
Zechstein
Triassic
Chalk
Rot 2/3/4
Devonian
12 13Z 13 15Z 15WSW ENE
2000
2500
ms
TW
T
1 km1 km3000
LINE OF SECTION
30/16-15
Top Rotliegend Depth Structure Map
Auk North Field Development 12th May 2011 10
Appraisal: Well Results
• Results incorporated into geological model
• Revised range of STOIIP indicated that there was sufficient volume in place to
warrant development of Auk North
30/16-16Y30/16-15 30/16-15Z 30/16-1630/16-16Z
Rotliegend
Rot 3
Wind Ripple
Re-worked
Slipface
?
Auk North Field Development 12th May 2011 11
Development Concept
Production Pipeline
ESP Power Cable
EH/CI Umbilical
Production Pipeline
ESP Power Cable
EH/CI Umbilical
Subsea Manifold and
Wells
Subsea Manifold and
Wells
Fulmar Riser
Fulmar Riser
Fulmar Topsides Facilities
Fulmar Topsides Facilities
• Three options were considered for the development of Auk North:
− Extended reach drilling from the Auk platform
− Subsea wells drilled from a mobile rig tied back to the Auk platform
− Subsea wells drilled from a mobile rig tied back to the Fulmar platform
• On the basis of feasibility and cost the option selected was a subsea tie-back to the Fulmar platform with ESPs being used as the means of artificial lift
Auk North Field Development 12th May 2011 12
Field Determination
• Auk field subject to Petroleum Revenue Tax (PRT)
• The Auk North project under a PRT paying environment would not be sanctioned as it would not meet Talisman's economic criteria to achieve project sanction
• However, the project would meet Talisman’s economic criteria to achieve project sanction if the Auk North development area was determined to be a new field and therefore not subject to PRT
• Talisman liaised closely with DECC and HM Treasury to demonstrate that this was the case:
− Open discussion on Talisman’s economic criteria required to sanction projects
• Auk North project sanctioned by Talisman Board in October 2008, conditional on Auk North being determined as a new field and therefore not subject to PRT
• Auk North determined as a new, separate field in January 2009:
− Re-determination of oil field boundaries on economic grounds (document issued November 2008)
• Development consent for the Auk North field received in January 2009
Platform
Auk North
Auk
Auk South
Top Rotliegend Depth Structure Map
New Auk North Field
Determination (and
Development) Area
Revised Auk Field
Determination (and
Development) Area
Auk North Field Development 12th May 2011 13
Project Execution: Drilling
• Three development wells drilled and completed between January 2009 and August 2009 and between September 2010 and November 2010
• Issues during drilling:
− Losses incurred while drilling the reservoir section of well N1 after encountering an area of intersecting faults
− Well paths of subsequent wells revised to avoid areas where faults intersect (identified using seismic attribute data)
N3A N1 N2
Wind Ripple
Re-worked
Slipface
Rot 1
Rot 1
Rot 2
Top Rotliegend Depth Structure Map
Zechstein Edge
N4ZN4
N3A
N1
N2
Auk North Field Development 12th May 2011 14
Project Execution: Completion
• Lower completion:− Sand screens and swell packers in reservoir section
• Upper completion:− Dual ESPs:
� 684 hp motor
� 140 stage centrifugal pump
� Non-return valve to prevent back-flow through pump
� Separate cables to surface for each pump
− Use of subsea horizontal tree necessitated new penetrator design for cables through the tubing hanger that still provided a dual barrier
• Expected completion run life of four years
• Key challenge was sizing pump to cater for a wide range of well productivities
ESP Pump Curves - FBHP versus Rate
P.I. = 40
P.I. = 15
P.I. = 3.5
P.I. = 2P.I. = 1P100 SXD
63 P100 SXD max. freq.
0
500
1000
1500
2000
2500
3000
3500
4000
0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000 11000 12000 13000 14000 15000
Liquid Rate [stb/d]
FB
HP
[p
si]
ESP Packer
Y-Tool
Non-Return Valve (NRV)
Monitoring Discharge Unit
Pump
Seal
Motor
ESP Monitoring Gauge
Pump Support sub
Bypass Isolation Plug
Perforated pipe
Sump or liner top packer / PBR
Auk North Field Development 12th May 2011 15
Project Execution: Well Results
Auk North Development Well PBU Log/Log Plot
0.001
0.01
0.1
1
0.001 0.01 0.1 1 10 100
Elapsed Time (hours)
Delt
a P
/Delt
a Q
(p
si/
b/d
)
N1 pressure
N1 derivative
N2 pressure
N2 derivative
N3A pressure
N3A derivative
Auk North Development Well Transient P.I.
0
10
20
30
40
50
60
70
80
90
100
0 5 10 15 20 25 30 35 40
Time (hours)
P.I
. (s
tb/d
/psi)
N1 Transient P.I.
N2 Transient P.I.
N3A Transient P.I.
Auk North Field Development 12th May 2011 16
Project Execution: Topsides and Subsea Facilities
• Subsea manifold:
− Designed for three wells with tie-in for future expansion
• Subsea pipeline:− Eight inch diameter and 10.5 km long
− Insulated to a U value of 4 W/M2k
• Electro-hydraulic/chemical injection subsea controls umbilical and an ESP power cable
• Conductor riser:− Containing two risers and two J-tubes
− Installed in redundant well slot
• Process facilities:− Utilised existing ‘B’ train 1st stage separator
− Methanol and wax inhibitor injection system
− Modules containing variable speed drives (VSDs) for ESPs
• Work on installing the topsides and subsea facilities took place between January 2009 and November 2010
Auk North Field Development 12th May 2011 17
Current Status
• First oil occurred on 17th November 2010
• Peak oil production rate in excess of
20,000 stb/d
• The results of the initial phase of the
project has resulted in a fourth
development well being sanctioned
• Well N4/N4Z spudded on 21st March 2011
• Currently running lower completion
Top Rotliegend Depth Structure Map
Zechstein Edge
N4ZN4
N3A
N1
N2
Auk North Field Development 12th May 2011 18
Summary
• Auk North began production in November 2010, some eighteen years after initial appraisal
• The appraisal programme carried out in 2007-2008 showed that there was sufficient volume in place to warrant development of Auk North
• However, the development costs meant that the project had marginal economics in a PRT paying environment
• Talisman liaised closely with DECC and HM Treasury to facilitate the development of Auk North – this was achieved by having Auk North being determined as a new field and therefore not subject to PRT
• The success of the initial phase of the project has resulted in a fourth development well being sanctioned