Autothermal Cyclic Reforming and H2 Refueling System
Ravi Kumar, Court Moorefield, ParagKulkarni, Boris Eiteneer, John Reinker,and Vladimir ZamanskyGE Global ResearchMike ManningPraxair
DOE Project ReviewPhiladelphia, PAMay 2004This presentation does not include any proprietary or confidential information
Autothermal Cyclic Reforming & H2 Refueling2
Outline• Objectives• Project Timeline & Budget• DOE Targets• Accomplishments over last year• Safety Status• Project Plan for Next Year• Summary
Autothermal Cyclic Reforming & H2 Refueling3
Objectives• Overall
> Design a reformer based refueling system that can meet the DOE cost (<$2.50/kg) target
> Fabricate and operate an integrated 60 kg of H2/day reforming and refueling system
• Last Year> Design, fabricate and operate reformer and pressure swing
adsorber pilot-scale sub-systems> Design the prototype reformer and pressure swing adsorber> Design the compression, storage and dispensing system and
collect data on sub-systems
Autothermal Cyclic Reforming & H2 Refueling4
Project Timeline – Major Milestones
Phase I Phase II Phase III01/02 - 12/02 01/03 - 12/04 01/05 - 09/05
• Phase I – Design and Analysis1. Completed conceptual design2. Completed economic analysis
• Phase II – Subsystem Development3. Operated pilot-scale reformer and PSA 4. Completed prototype reformer and PSA design5. Fabrication and shakedown of prototype reformer and PSA
• Phase III – Integrated System Operation6. Integration of ACR with PSA 7. Complete bench-scale catalyst durability testing8. Integration of H2 generator with H2 compressor and dispenser9. Operation of ACR based hydrogen refueling system
21 3 4 5 6 7 8 9
Autothermal Cyclic Reforming & H2 Refueling5
Budget
• Total: $4.8 Million
• Industry: $2.1 Million
• DOE: $2.7 Million
• FY04 Funding: $0.6 Million
Autothermal Cyclic Reforming & H2 Refueling6
Technical Barriers and Targets• Distributed H2 Production from Natural Gas Barriers
> A. Fuel Processor Capital Costs> B. Operation & Maintenance Issues> D. Carbon Dioxide Emissions> E. Control & Safety> Z. Catalysts> AB. H2 Separation & Purification
• Targets
625.02003
7568Efficiency (LHV)1.53.0Cost ($/kg)20102005
Autothermal Cyclic Reforming & H2 Refueling7
Prototype Hydrogen Generating & Dispensing System
H2, CO, CO2,CH4
Recycle Fuel
H2
Com
p.
Storage Tanks
H2
Reformer
Shift Reactor
Pressure
Swing
Adsorber
Vent
DispenserAir
Natural Gas
Water
Praxair
GE Hydro-Pac
Fueling Technologies
Autothermal Cyclic Reforming & H2 Refueling8
Exergy of Reformers for H2 Generation
60%
70%
80%
90%
100%
SMR/ACR ATR
H2
Product (efficiency)
Exergydestruction in Reformer+ HX + Shift
Exergydestruction in Vent + Misc.
H2
Production Exergy
ExergyDestruction in Reformer + HX + Shift
ExergyDestruction in Vent + Misc.
SMR – Steam Methane ReformingACR – Autothermal Cyclic ReformingATR – Conventional Autothermal Reforming
Autothermal Cyclic Reforming & H2 Refueling9
Reformer Choice Depends on Application
75%65%75%Efficiency
Good
Good
Natural Gas, Propane, Diesel Fuel, Biogas
Low
40-50%Conv. ATR
GoodPoorTurndown
GoodPoorSulfur Tolerance
Natural Gas, Propane, Diesel Fuel, Biogas
Natural Gas, Propane
Fuel Flexibility
LowHighCapital Cost
70%70%%H2 from reformer
ACRConv. SMR
Autothermal Cyclic Reforming & H2 Refueling10
Stable Operation of Low-Pressure Pilot-Scale ACR
0
5
10
15
20
25
30
35
40
45
50
0 50 100 150 200 250 300Time (minutes)
CH
4 (%
vol
. dry
)
0
10
20
30
40
50
60
70
80
90
100
H2
and
CO
(% v
ol. d
ry)
CO%
H2%
CH4%
Autothermal Cyclic Reforming & H2 Refueling11
500550600650700750800850900950
1000
0 50 100
150
200
250
300
350
400
450
500
550
600
650
700
Time, minutes
Tem
p, C
Stable Operation of Low-Pressure Pilot-Scale ACR
ACR Reactor Temp
Autothermal Cyclic Reforming & H2 Refueling12
Shift Reactor TestingSpecification: %CO < 1%
0
50
100
150
200
250
0 20 40 60 80 100 120Time, minutes
Tem
pera
ture
, C
0
1
2
3
4
5
CO
, %
Shift Temperature
Shift Outlet CO%
Autothermal Cyclic Reforming & H2 Refueling13
Reformer Testing Accomplishments
• Operated system with about 30 start-stop cycles
• Operated system continuously for up to 30 hours using automated controls several times.
• Demonstrated less than 0.5% CO at exit of shift reactor
• Operated system from 55 kg/day to 15 kg/day (3.5:1 load change)
• Lab scale tests for 2,000 hrs
Autothermal Cyclic Reforming & H2 Refueling14
High Pressure Reformer Reactor: 3-D Stress & Thermal Modeling
3.4Total< 5.0Specification
0.3Bottom2.7Side0.4Top
Heat Loss, kWReformer Zones
> 1,000,000Outer Shell> 1,000Specification
> 90,000Hottest Internal
Cold-Start Cycles to failure
Critical welds
Autothermal Cyclic Reforming & H2 Refueling15
Praxair PSA Pilot Plant Meets Requirements
Design Goals: 60 kg/day, 99.99% H2 purity, 75% recovery
4 bed design> Shortened bed height > Reduced amount of sieve required > Improved recovery
3 bed design> Advanced sieve material> Proprietary 12-step cycle> Lowered feed pressure requirements
Autothermal Cyclic Reforming & H2 Refueling16
• Skid design 75% complete
• Adsorbent - on order
• Logged 300,000 cycles on valves > No detectable leaks using He @ 150
psig
Praxair PSA Prototype Skid Status
Autothermal Cyclic Reforming & H2 Refueling17
~ 100 ppm~ 100 ppm< 2%O2, N2 & Ar< 10 ppm< 10 ppm< 100 ppmHydrocarbons< 1 ppm< 10 ppm< 1 ppmAmmonia< 10 ppb< 50 ppb< 10 ppbSulfur< 5 ppm< 10 ppm< 100 ppmCO2< 1 ppm< 5 ppm< 1 ppmCO
~ 99.9999% dry basis
99.99% dry basis
98% dry basisH2
Status with Future Development
Current StatusDOE TargetsComponent in
the Product
H2 Purity Status
Autothermal Cyclic Reforming & H2 Refueling18
Hydro-Pac Hydraulic H2 Compressor
• Praxair’s LAX project provided an opportunity to gain experience needed for the ACR program
• Measured incoming power and calculated the compressor efficiency during factory run test on helium
67.8%ηadiabatic =
Autothermal Cyclic Reforming & H2 Refueling19
150 psig H2 from Reformer
Stage 1 & 2 Intensifier
Stage 3/ Filling Intensifier
6500 psig H2 to FC vehicle
Dispenser
400-700 psig low P storage bank
1000-6500 psig mid-high P storage bank
Hydraulic fluid reservoir
• Requires 1/3 the amount of storage than cascade dispensing
• Added low pressure storage bank to maximize utilization
• Requires only one “modified” packaged compressor by separating functionality of each intensifier during fill
> Stages 1 & 2 fill low pressure bank
> Stage 3 acts as fill pump
• Small scale testing to begin in 2nd quarter of 2004
Fill Pump Dispensing with Added Low Pressure Bank (Patent Pending)
Autothermal Cyclic Reforming & H2 Refueling20
Stationary Storage
ASME STEEL CYLINDERS
• Plan to use ASME Section VIII, Division 1 Coded seamless steel cylinders
> Designed with a safety factor of 3.0
> Praxair has a perfect safety record when employing these vessels for H2 service
• Work with ASME to develop new rules for composite vessels
> Praxair working with ASME and is actively participating in the H2Steering Committee for storage and transport of H2
Autothermal Cyclic Reforming & H2 Refueling21
Praxair is working with Fueling Technologies on Dispenser
PRIORITY SEQUENCING PANEL
DISPENSER ISLAND
• Safety
• Additions> A vibration switch terminates the fill
operation in the event of vehicle contact and remains locked out until reactivated
> A shear frame assembly and automatic shutoff valves as a safeguard against a more severe vehicular collision
> FTI provided new connections to allow the use of N2 for purging both the enclosure in an LEL shut-down event and for continuously purging the dispenser H2 vent header
Autothermal Cyclic Reforming & H2 Refueling22
Project Safety
REV MAY2002
Likelihood Wt. = 0 Likelihood Wt. = 6 Likelihood Wt. = 3 Likelihood Wt. = 7 Likelihood Wt. = 7
0 PFac 4.20609E-06 PFac 5.76003E-07 PFac 0.000638468 PFac 0.000465474 PFac
F D E C CLikelihood Wt. = 7
0.001108724 PFac
C
% = Likelihood Wt. = 6 Likelihood Wt. = 7 Likelihood Wt. = 3 % = 20 Likelihood Wt. = 3 9 = Severity Wt.
0.001001343 PFac 1.3279E-07 PFac 3.37844E-10 PFac 1.77878E-13 PFac 3.55756E-14 PFac 3.55756E-14 PFac
N/A D C E N/A E E
% = Likelihood Wt. = 3 Likelihood Wt. = 3 Likelihood Wt. = 9 Likelihood Wt. = 7 Likelihood Wt. = 3 % = 20
5.26385E-07 PFac 7.05114E-13 PFac 9.4453E-19 PFac 4.22008E-19 PFac 1.07367E-21 PFac 5.65297E-25 PFac 1.13059E-25 PFac
N/A E E B C E N/A
% = Likelihood Wt. = 7 % = 50 Likelihood Wt. = 3 9 = Severity Wt.
2.63193E-07 PFac 6.69613E-10 PFac 3.34806E-10 PFac 3.34806E-10 PFac Single Unit = N/A C N/A E Entire Fleet =
% = Likelihood Wt. = 6 % = 20 Likelihood Wt. = 3 9 = Severity Wt.
2.63193E-07 PFac 3.49025E-11 PFac 6.98051E-12 PFac 6.98051E-12 PFac Single Unit = N/A D N/A E Entire Fleet =
% = Likelihood Wt. = 7 % = 20 Likelihood Wt. = 3 9 = Severity Wt.
5.26385E-07 PFac 1.33923E-09 PFac 2.67845E-10 PFac 2.67845E-10 PFac Single Unit = N/A C N/A E Entire Fleet =
% = Likelihood Wt. = 3 Likelihood Wt. = 7 Likelihood Wt. = 7 Likelihood Wt. = 9 % = 20 Likelihood Wt. = 3 9
5.21112E-05 PFac 6.98051E-11 PFac 1.77598E-13 PFac 4.51843E-16 PFac 7.93491E-14 PFac 1.58698E-14 PFac 1.58698E-14 PFac
N/A E C C B N/A E
% = Likelihood Wt. = 3 Likelihood Wt. = 6 % = 20 Likelihood Wt. = 3 9 = Severity Wt.
5.26385E-07 PFac 7.05114E-13 PFac 6.98051E-11 PFac 1.3961E-11 PFac 1.3961E-11 PFac Single Unit = N/A E D N/A E Entire Fleet =
% = Likelihood Wt. = 3 Likelihood Wt. = 6 % = 20 Likelihood Wt. = 3 9 = Severity Wt.
5.26385E-07 PFac 7.05114E-13 PFac 9.35068E-17 PFac 1.87014E-17 PFac 1.87014E-17 PFac Single Unit = N/A E D N/A E Entire Fleet =
% = Likelihood Wt. = 3 % = 50 Likelihood Wt. = 3 9 = Severity Wt.
5.26376E-05 PFac 7.05102E-11 PFac 3.52551E-11 PFac 3.52551E-11 PFac Single Unit = N/A E N/A E Entire Fleet =
Safety Score 6.5797E-091.64492E-07
Safety Score 3.49025E-8.72564E-
Node Description 27 Estimated Events
Safety Score 2.60556E-06.5139E-08
Node Description 27 Estimated Events
Node Description 27 Estimated Events
Safety Score 4.99882E-081.24971E-06
Node DescriptionIgnition Source
Safety Score 1.30278E-093.25695E-08
Node Description 27 Estimated Events
1.56213E-06
Node Description 27 Estimated Events
Node Description 27 Estimated Events
Safety Score
Ignition SourceInlet Valve Failure
Ignition Source
Air Pressue Drop Valves Closing at Different Times
NG Release
Ignition SourceExplosive Mixture
Residual Gases in System Ignition Source
0.04747665% of failures thatlead to chain X
Vibration During Transport
Valve Position Changing
% of failures thatlead to chain X Purge Failure
NG Accumulation
4.70010562% of failures thatlead to chain X Slow Air Leak
0.04747665% of failures thatlead to chain X
No Flame in Reformer Reactor
4.74758227
0.04747665% of failures thatlead to chain X H2 Fitting/Piping Leak
Ignition Source
Ignition Source
% of failures thatlead to chain X NG Fitting/Piping Leak NG Release
Hydrogen Release
0.02373833% of failures thatlead to chain X
External Impact of NG Line
0.02373833
0.04747665% of failures thatlead to chain X Inlet Valve Failure Air Into Shift &/or
Ox Reactor T Sensor Failure T Increase in Reactor
T/P Buildup in Reactor
Release of H2 and CO
Control Software Failure
Total DefectLikelihood
90.3149288
% of failures thatlead to chain 1 T/P Sensor Failure
Hydrogen Generator (eNPP 01-39.1)Explosion ASR
DesignInadequate
ManufacturingDefect
InstallationDefect
OperationalDefect
MaintenanceDefect
Ignition Source
Control Software Failure Ignition Source
Control Software Failure
Release of H2 and CO
Air Mixing with H2 or NG
Node Description 27
Safety Score 6.24853E-08
and/or and/or and/or and/or
• System Component FMEA’s
• Preliminary Hazard Assessment
• Haz Op (with independent review)
• Accident Scenario Review (performed review on any medium scoring item on Haz Op)
Autothermal Cyclic Reforming & H2 Refueling23
# Task Name
1Low pressure reformer operation
2High pressure reformer designand fabrication
3Catalyst durability testing4PSA design and fabrication5Installation in UCI
6Design of H2 compressor, storageand dispenser
7High pressure ACR reactorshakedown
8High pressure reformer start-upand operation
9Integration with PSA10Integration with PEM fuel cell
11Integration with H2 compressor,storage and dispenser
D J F M A M J J A S O N D J F M A M J J A S O NQ4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q
2004 2005
• Increased Reliability in Startups• Extended Operation
• ASME Codes• Modeling Stress due
to Reformer Cycles
• Catalyst Durability test for 3000 hrs
• Codes & Standards• Safety Reviews
ACR Project Plan for 2004-5
Autothermal Cyclic Reforming & H2 Refueling24
Significant Reviewer Comments• Excellent implementation of economics; Economic analysis should
include reformers from other manufacturers> Working on DOE H2A panel> Supporting DOE on an apples-to-apples comparison of
different reforming technologies• Little innovation outside of GE reformer evident
> Praxair submitted patents on PSA and refueling system recently
> Novel 3-bed and 4-bed designs> Some of the innovation is confidential and will be presented to
DOE • Excellent component developed and test plans; Future plans are
weak> Included a detailed project plan for next year
Autothermal Cyclic Reforming & H2 Refueling25
Summary• Low-pressure pilot-scale ACR operation
> Stabilized for extended periods of time > 30 start-stop cycles
• High pressure prototype reformer design is complete
• Prototype reformer and PSA will be fabricated and operated this year
• Reformer will be integrated with PSA, compressor and storage tanks
• Operation of integrated system in 2005
Autothermal Cyclic Reforming & H2 Refueling26
Ackowledgements
• Department of Energy> Mark Paster, Peter Devlin and Sig Gronich
California Energy Commission> Avtar Bining and Mike Batham
• California Air Resources Board> Steve Church
Autothermal Cyclic Reforming & H2 Refueling27
Questions?