VSC-HVDC Availability Analysis
Antony Beddard
Dr Mike Barnes
November 2011
Revision 2.1
Table of Contents
1 Introduction ................................................................................................................................ 1
2 Radial System Overview .............................................................................................................. 1
3 Methodology ............................................................................................................................... 2
4 Component Availability ............................................................................................................... 3
4.1 Converter Reactor ............................................................................................................... 6
4.2 MMC, Cooling System and Ventilation System ................................................................... 6
4.3 Control System .................................................................................................................... 7
4.4 Transformer and GIS ........................................................................................................... 7
4.5 DC Switchyard ..................................................................................................................... 8
4.6 DC Cable .............................................................................................................................. 9
5 Radial VSC-HVDC Scheme availability analysis ......................................................................... 10
5.1 Offshore system availability analysis ................................................................................ 10
5.2 Onshore system availability analysis................................................................................. 12
5.3 DC system availability analysis .......................................................................................... 13
5.4 Radial VSC-HVDC Availability ............................................................................................ 14
6 Regional HVDC Grid .................................................................................................................. 16
7 Cost-benefit analysis ................................................................................................................. 21
8 Summary ................................................................................................................................... 23
9 Conclusion ................................................................................................................................. 24
10 References ............................................................................................................................ 25
1
1 Introduction
The UK government has signed a legally binding contract for 15% of its energy consumption to be
produced from renewable energy sources by 2020[1]. The government’s 2009 Renewable energy
strategy has identified that to met this target 30% of the UK’s electricity generation must come from
renewable energy sources, of which nearly half is likely to come from offshore wind[1]. This
translates to nearly 15% of the UK’s electricity generation being produced from offshore wind in less
than 9 years. Therefore the reliability of the offshore windfarms and their connection which
facilitates the power transfer back to shore are extremely important.
The connection for the offshore windfarm can be via either a high voltage alternating current (HVAC)
transmission system or a high voltage direct current (HVDC) transmission system. The choice of
transmission system is largely dependent upon how far the windfarm is located from shore.
Generally speaking HVDC technology is more favourable for windfarms located more than 50km
from shore. This is primarily because in a HVAC system a large proportion of a cable’s current
carrying capacity is required to charge and discharge the cable’s capacitance every cycle. Whereas in
a HVDC system, once the cable is charged almost its entire current carrying capacity is available for
real power transfer.
Current Source Converters (CSC) and Voltage Source Converters (VSC) are the two main types of
converter technology used in HVDC transmission systems. VSC-HVDC is more suited for offshore
windfarms because it does not require a strong AC system and has a smaller footprint in comparison
to CSC-HVDC. Therefore this research focuses on assessing the availability of the VSC-HVDC link.
2 Radial System Overview
National Grid has presented three different strategies for the connection of the UK’s Round 3
offshore windfarms in their Offshore Development Information Statement (ODIS)[2, 3]. The radial
strategy requires more than twenty five 1000MW VSC-HVDC point-to-point schemes. A simplified
diagram for the offshore connection design of a Round 3 windfarm employing a 1000MW VSC-HVDC
point-to-point scheme is shown in Figure 1.
Wind Farm
500MW AC
Substation
500MW AC
Substation
1000MW VSC-
HVDC Scheme
400kV AC Grid
220kV AC
36kV AC
Figure 1 – 1000MW VSC-HVDC point-to-point offshore connection diagram
This paper assesses the availability of the VSC-HVDC link which is shown in Figure 2. Proposed
1000MW VSC-HVDC schemes as shown in Figure 1 have HVDC cable lengths ranging approximately
60km to 275km with an average cable length of approximately 165km [2]. Therefore the DC cable
length will be 165km for this study.
2
All of the three major HVDC manufacturers offer a VSC-HVDC product. Siemens and Alstom Grid’s
VSC-HVDC technology is based on a multi-modular converter (MMC); whereas ABB’s current VSC-
HVDC product utilizes a two-level converter topology. However ABB have developed a VSC-HVDC
product which employs a form of MMC known as a cascaded two-level converter (CTL). The CTL is
likely to be first used on the Dolwin 2 project which is expected to be commissioned in 2015.
Therefore it is fair to say all future orders for VSC-HVDC schemes will employ a MMC. Hence the
availability analysis in this paper will be based on a MMC VSC-HVDC scheme.
Figure 2 – point to point VSC-HVDC scheme
MMC VSC-HVDC schemes produce a very low harmonic content and as such no AC filters are
required in most MMC schemes[4]. It is also unlikely any DC filtering would be required1. Therefore
no filters are employed in this scheme. An MCC can operate without a phase reactor. However they
do require limb/converter reactors which are connected in series to each arm of the converter but
are normally located outside the valve hall. In this availability analysis the converter reactor and
MMC are analysed as separate components. The AC converter voltage is likely to be in the vicinity of
275kV2. A transformer steps this voltage up to 400kV onshore as shown in Figure 2.
3 Methodology
The VSC-HVDC transmission scheme is broken down into three subsystems as shown in Figure 2 and
Figure 3. The scheme can only facilitate power transmission if all of the three subsystems are in
service. The failure of any one of the series connected subsystems results in an outage. This is the
concept of series dependent systems.
Subsystem 2 -
DC System
Subsystem 3 -
Onshore System
Subsystem 1 –
Offshore System
VSC-HVDC Availability Diagram
Figure 3 – VSC-HVDC Reliability Model
1 Harmonic content in most cases is likely to be so low that no DC filter would be required. Also in [5] there are
no DC filters shown for the HVDC Plus converter. 2 This value is based on the peak AC converter voltage being 0.75 times half the DC voltage (0.75*300kV) which
gives a converter side line-to-line voltage of 275.57kV rms. The 0.75 is based on simulation results from the
Trans Bay cable project which has a peak AC converter voltage of 150kV and a DC voltage of ±200kV[4].
3
The overall availability of the VSC-HVDC scheme can be calculated by multiplying the availability of
the three subsystems together. In order to do this the availability of each component in each
subsystem must be calculated. The availability of each component can be calculated directly from
equation (1.1).
MTTF
AMTTF MTTR
=+
(1.1)
Equation (1.1) requires the mean time to failure (MTTF) and mean time to repair (MTTR) of each
component. The MTTF and MTTR values for each component have been estimated from several
sources of information.
4 Component Availability
A brief explanation of each component and their reliability indices will be discussed here. A thorough
explanation for the derivation of the MTTF and MTTR of each component is contained in the
appendix. The components in the offshore system are very similar to the components in the onshore
system. The key difference is that the transformers and gas insulated switchgear (GIS) bays for the
onshore are connected to the 400kV grid whereas the offshore transformer and GIS bays are
connected at 220kV as shown in Figure 2. The voltage rating of equipment could affect their
likelihood to fail and the time it takes to repair the component in the event of a failure. This is taken
into consideration in this availability analysis.
The crucial difference between a component being located offshore or onshore is the take it takes to
repair the component. This is because it takes longer to access the offshore platform. The time it
takes varies significantly depending on the following factors:-
• Method of transport (small vessel/large vessel/helicopter)
• Availability of transport
• Weather conditions
• Location of offshore platform
• Location of air field/port/offshore maintenance platform
• Availability of required personnel
The access time could be as little as one day (24 hours) based on travel via a helicopter in good
weather conditions with the correct administration procedures in place to enable rapid deployment
of personnel and equipment. However it could also be as long as three months or more due to very
bad weather conditions and unavailability of a large suitable vessel.
The mean time to access the offshore platform (MTTAOP) with different sized components or spare
parts has been estimated as shown in Table 1. Pictures of the example components/spare parts in
Table 1 are shown below to give an indication for their size.
Table 1 – Mean Time to Access the Offshore Platform with Different Sized Components / Spare Parts
Component/Spare Part Size Example Component / Spare Part MTTAOP (hr) Transportation Method
Small MMC Submodule 48 Helicopter/small vessel
Medium Gas-insulated Switchgear 168 Medium Vessel
Large Transformer 504 Large Vessel
4
In order to accurately estimate the MTTR for an offshore component, the size of the spare part the
component would require in the event of a failure must be estimated. From estimating the size of
spare parts a component is likely to require in the event of a failure, the mean offshore access time
(MOAT) for the component can be calculated. Calculating the MTTR for a component located
offshore is not as simple as adding the MTTR for the component located onshore together with the
MOAT for that component. This is because some tasks which affect the MOAT may be performed in
parallel with tasks included in the MTTR for the onshore component. To give greater clarity to these
two aspects consider the following example.
In this availability analysis it is estimated that 70% of GIS failures require a small sized part and 30%
require a medium sized part. From Table 1 the mean offshore access time (MOAT) to repair a GIS
switchbay would be 84 hours (70% helicopter/small vessel and 30% medium vessel). The MTTR for a
GIS bay located onshore is estimated to be 120 hours. It is estimated that 20 hours of the offshore
access time is spent performing administration related tasks which could be done concurrently with
the time spent obtaining spare parts (included in the onshore MTTR). Therefore the MTTR of an
offshore GIS is the MTTR of an onshore GIS switchbay plus the MOAT minus the mean time spent
performing concurrent tasks (MTPCT) (i.e. 120+84-20). Further information is contained in the
appendix.
Figure 4 – MMC sub-module from [6]
The MMC sub-module is approximately 0.6x1.5x0.3m (HxWxD) and weighs approximately 165kg [6].
5
Figure 5 – Picture of a 245kV Gas Insulated Switchgear (GIS) from [7]
A 245kV gas insulated switchgear bay has a footprint of about 12m2 and weighs approximately 5-6
tonnes [8].
Figure 6 – 150kV 140MVA offshore transformer modified from [9]
6
A 150kV 140MVA transformer as shown in is a relatively small transformer in terms of its rating, but
still weighs approximately 90 tonnes[8]. Larger transformers are significantly heavier.
4.1 Converter Reactor
The converter reactors also known as limb reactors are connected in series with each arm of the
MMC. There is only one MMC currently in operation (commissioned 2010) and it is not for an
offshore system and therefore reliability indices for converter reactors are non-existent. Det Norske
Veritas (DNV) is the only known source to have published reliability indices for a VSC-HVDC
converter reactor. These reliability indices are likely to be for the converter reactors employed on
two-level voltage source scheme. Never the less the reliability indices for the reactor are taken to be
similar to the converter reactors used in MMC VSC-HVDC schemes. The reliability indices published
by DNV was used to estimate the reliability indices for a converter reactor as given in Table 2.
Table 2 - Estimated Reliability Indices for Converter Reactors
4.2 MMC, Cooling System and Ventilation System
The cooling system is required to ensure the components within the MMC such as the IGBT’s do not
exceed their rated temperature. The ventilation system amongst other functions is needed to ensure
the valve hall temperature and moisture does not exceed set limits. Failure of either the cooling
system or ventilation system is likely to result in the converter being tripped fairly quickly. It is for
these reasons critical parts in the cooling system are duplicated [10].
As mentioned previously, failure statistics for MMCs are non-existent because there is only one MCC
HVDC scheme in operation which was commissioned in 2010. The first two-level VSC-HVDC scheme
was commissioned in 1997 and since then many more schemes have been commissioned. That said
no VSC-HVDC schemes have been included in the Cigre world survey of HVDC schemes which is
published biannually. There are a small number of sources which have published reliability indices
for HVDC VSC’s3. One of these sources estimated the VSC’s reliability indices based on data from the
Cigre survey of LCC-HVDC schemes. This survey publishes reliability indices for the HVDC converter
with the cooling system and the ventilation system included. It is expected although not explicitly
stated that reliability indices for the converter from the other sources included the cooling system
and the ventilation system. Therefore estimating the reliability indices for the MMC from these
sources would also include the cooling system and the ventilation system. The disadvantage of this,
would be that the individual effect of the cooling system and ventilation system on the schemes
availability would be obscured.
A paper published by industry did analyse the converter, cooling system and ventilation system as
individual components [11]. However the components used in the offshore cooling system and
onshore cooling system seemed to be somewhat inconsistent with each other and with a real
cooling system. As an example the offshore cooling system did not account for instrumentation
whereas the onshore cooling system did and neither accounted for the failure rates of the cooling
3 Although it is not stated explicitly it appears that the reliability indices are for two-level VSC’s.
Component MTTF (yr) MTTR (hr) Availability
Onshore Converter Reactor 7 24 0.99961
Offshore Converter Reactor 7 192 0.99688
7
systems control system. The same inconsistency seems to apply to the ventilation systems. There
may well be very good reasons to explain these inconsistencies. However without this knowledge it
would be unwise to use the data from this paper for the cooling system and ventilation system as
the resultant availability could be very inaccurate. It is therefore believed more accurate reliability
indices would be obtained by estimating the MTTF and MTTR for the MMC from the other sources
which have factored in the cooling system and ventilation system4. It is for these reasons the cooling
system and ventilation system will be factored into the reliability indices for the MCC as one
component.
Table 3 - Estimated Reliability Indices for MMC, Ventilation System and Cooling System
4.3 Control System
The HVDC control system is fully duplicated to ensure a high level of reliability. The reliability indices
for HVDC control systems used in academic and industry publications are for two-level VSC-HVDC
schemes and LCC-HVDC schemes. The control algorithms for MCC VSC-HVDC schemes are more
complex than other HVDC schemes. The hardware, with the exception of the valve based
electronics, is similar. These were two of the factors which were taken into consideration when
estimating the MTTF and MTTR for the control system.
Table 4 - Estimated Reliability Indices for Control System
4.4 Transformer and GIS
Figure 7 – Subsystem 4
The reliability indices for the GIS have been mainly estimated from the GIS failure statistics from the
1996 Cigre GIS survey. Cigre surveys for AC circuit breakers and reliability indices for AC circuit
breakers from other sources were also used. GIS failure statistics are categorised based on the
voltage rating of the equipment. The GIS voltage ratings are determined by the busbar to which they
4 Sources 1 and 2 have not explicitly stated they have included the cooling and ventilation system. However it
is very likely they were included.
Component MTTF (yr) MTTR (hr) Availability
MMC Onshore 1.9 12 0.99928
MMC Offshore 1.9 60 0.99641
Component MTTF (yr) MTTR (hr) Availability
Onshore Control System 1.6 3 0.99979
Offshore Control System 1.6 17 0.99879
GISSwitchbay
500MW
500MW
1000MW
T1
T2
GIS 1
GIS 3
GIS 2
GIS 4
Busbar 1
Busbar 2
8
are connected. The offshore GIS connected to the windfarm side (busbar1) would need to be rated
at 220kV whereas the GIS connected to the converter side (busbar2) would need to be rated at
about 275kV. This places the offshore GIS in the 200-300kV category.
Figure 8 – Subsystem 5
The onshore GIS connected to the converter side (busbar3) would need to be rated at about 275kV
whereas the GIS connected to the AC grid (busbar 4) would need to be rated at 400kV. Therefore the
GIS connected to busbar1 are in the 200-300kV category and the GIS connected to busbar 4 are in
the 300-500kV category.
Table 5 – Estimated Reliability Indices for GIS
The reliability indices for the power transformer have been estimated from a number of sources
including Cigre surveys, academic and industry publications. The failure statistics are categorised
based on the transformer’s highest winding voltage. The highest winding voltage for the offshore
transformers is within the 100-300kV category irrespective of whether a delta or star connected
transformer is employed. However a delta connected onshore transformer would have a winding
voltage of 400kV, whereas a star connected transformer would have a winding voltage of
approximately 230kV. This availability analysis assumes the onshore transformer is connected to the
grid via a star winding. This also places the onshore transformers in the 100-300kV category.
Table 6 - Estimated Reliability Indices for Transformers
4.5 DC Switchyard
The major equipment in a DC VSC switchyard consists of HV capacitor banks, line reactors,
measurement transducers and switchgear[12]. The major equipment in a LCC DC switchyard consists
of DC harmonic filters, smoothing reactors, measurement transducers and switchgear[13].
GISSwitchbay
1000MW1000MW
T1
T2
GIS 1
GIS 3
GIS 2
GIS 4
Busbar 3
Busbar 4
Component MTTF (yr) MTTR(hr) Availability
Offshore switchbay 250 184 0.99992
400kV onshore switchbay 100 120 0.99986
275kV onshore switchbay 250 120 0.99995
Component MTTF(yr) MTTR(hr) Availability
Offshore Transformer 95.00 1512.00 0.99819
Onshore Transformer 95.00 1008.00 0.99879
9
Figure 9 – MMC VSC DC Switchyard (left, modified from[12]) LCC DC Switchyard (right modified from[14])
Since there is significant similarity between the DC switchyards, the failure statistics from the world
HVDC survey (LCC) is used to estimate the reliability indices for the MMC VSC-HVDC DC switchyard.
The latest World HVDC survey was published in 2010 for data collected on LCC-HVDC schemes
during 2007-2008. Back-to-back HVDC schemes do not normally require smoothing reactors or DC
filters [13]. Therefore only the data from transmission schemes is considered. The estimated
reliability indices for a DC switchyard are given in Table 7.
Table 7 - Estimated Reliability Indices for DC Switchyard
4.6 DC Cable
Submarine cable failures rates are very subjective. They are heavily influenced by many factors
including, fishing activity, installation protection method, awareness of cable routes, water depth,
and hardness of the sea bed. Therefore reliability indices for submarine cables should be used with a
high level of caution and ideally estimated on a case by case basis.
The latest survey for failures of submarine cables was published in 2009 by Cigre for data collected
between 1990 and 2005. Unfortunately failure rates for the most common type of submarine cable
used in VSC-HVDC schemes (DC-XLPE) was not given in the report. The very high majority of known
cable failures were due to external damage, which is likely to be independent of cable type and
voltage rating5. Therefore the average failure rate of all cable types and voltages was used to
estimate failure for DC-XLPE submarine cable. The average failure rate of submarine cable with some
form of installation protection was calculated to be 0.096. Based on this figure and the value given
by DNV it was estimated that the annual failure of a submarine cable is 0.07 failures per 100km. The
circuit length in this report is defined as the distance between the onshore and offshore converter
(i.e. 165km not 330km).
5 Only 4 of the 49 reported failures were classed as internal failures which were all for one type of cable
(SCOF).
Componenet MTTF(yr) MTTR(hr) Availability
Onshore DC Switchyard 4.02 26.06 0.99926
Offshore DC Switchyard 4.02 98.06 0.99723
Line Reactor
10
The average repair time for submarine cables in the Cigre survey was approximately 60 days which is
the same as the MTTR used by DNV in their availability analysis. Therefore a MTTR of 60 days will be
assumed in this report.
Table 8 – Estimated Submarine Cable Reliability Indices
5 Radial VSC-HVDC Scheme availability analysis
The availability for the radial VSC-HVDC scheme will be calculated in this section.
5.1 Offshore system availability analysis
The offshore system is broken down into subsystems and components. The offshore system has
series dependency as shown in Figure 10. The failure of any one component from subsystem 4 to the
control system will result in the failure of the offshore system and therefore the failure of the
transmission scheme. Subsystem 4 can operate at 100% or 50% capacity. Due to the series
dependency if subsystem 4 is operating at 50% capacity the offshore subsystem and consequently
the transmission scheme can only operate at 50% capacity.
Figure 10 – Reliability Model for Subsystem 1
The availability of all the components in the offshore subsystem is given in Table 9.
Table 9– Availability of offshore components
The simplified offshore subsystem availability diagram is shown in Figure 11.
Figure 11 – Reliability Model for Subsystem 1
Component Failure rate (occ/yr/100km) Circuit Length (km) MTTF (yr) MTTR (hr) Availability
DC Cable 0.07 165 8.493625 1440 0.98101
Component MTTF(yr) MTTR(hr) Availability
Offshore GIS switchbay 250 184 0.99992
Offshore Transformer 95 1512 0.99819
Offshore Converter Reactor 7 192 0.99688
MMC Offshore 1.9 60 0.99641
Offshore Control System 1.6 17 0.99879
11
Subsystem 4 contains two parallel branches as shown in Figure 2 and Figure 12 . If both branches are
in service subsystem 4 operates at full capacity. If only one branch is in service subsystem 4 operates
at 50% capacity.
Figure 12 – Subsystem 4
The protection of the equipment before, and including, busbar1 is assumed to be the responsibility
of the AC substation manufacturer. Therefore the failure of this equipment will not be included in
this availability analysis. It is also assumed permanent faults on busbar2 are very rare and can
therefore be neglected.
There are many components which make up a GIS switchbay including circuit breakers,
disconnectors and instrumentation. The component which fails and the mode in which that
component has failed determines the available capacity of the system. To demonstrate this three
example GIS failure modes and consequences are shown in Table 10.
Table 10 – Example GIS failure modes and consequences
There are many different failure modes of a GIS switchbay. In order to take into account each failure
mode and its effect on the capacity of the system complex analysis could be conducted. However
without accurate failure mode input data even the most sophisticated availability analysis method
will produce inaccurate results.
Data to determine the failure rate of a GIS switchbay as a single unit is limited. In fact for this report
the failure data for a GIS switchbay was estimated from a number of sources some of which were
15-25 years old and others which were for AC circuit breaker rather than a GIS switchbay. The data
used to estimate with any real degree of accuracy what component within a 2011 GIS switchbay and
how that component will fail is near enough non-existent. It is worth noting that in [15] there is
some data from the Cigre 1996 GIS survey for the symptoms of GIS failures. This includes symptoms
such as “loss of mechanical function” and “failure to operate switching device”. However such
symptoms do not indicate the failure mode of the GIS. The biggest single failure symptom (>30%)
was an insulation breakdown to earth, which indicates the third failure mode in Table 10. It is also
worth noting the survey was for GIS which was commissioned some 15-25 years ago and therefore
failure symptoms of modern day GIS could be very different.
GISSwitchbay
500MW
500MW
1000MW
T1
T2
GIS 1
GIS 3
GIS 2
GIS 4
Busbar 1
Busbar 2
Failure Mode Immediate effect Branches Effected Capacity Outage (MW)
Disconnector opens inadvertently Isolates the connected branch 1 500
Circuit fails to open on command Cannot clear transformer fault 2 1000
Insulation breakdown to earth Short circuit connected busbar 2 1000
12
Due to the lack of any credible failure mode statistics for GIS and that the biggest single failure
symptom for GIS was a “breakdown to earth” it is assumed the failure of any GIS switchbay results in
full capacity outage, which is the worst case scenario. There are 64 possible combinations of
components in Figure 12 considering each component as being available and unavailable. Rather
than go through each possible combination it is significantly less time consuming to go through any
combination of component which results in some available capacity. This is because the very high
majority of the combinations result in zero available capacity due to the assumption that any GIS
failure results in full capacity outage.
In order to operate at full capacity all the components (GIS1-4 and T1-2) must be available. The
failure of any one transformer providing all the GIS switchbays are available would result in an
available capacity of 500MW. All other component combinations result in full capacity outage.
Table 11 – Available capacity table for subsystem 4
From equation(1.2) the available capacity of subsystem 1 can be calculated.
1(100%) 4(100%) Re (100%) (100%) (100%)
1(50%) 4(50%) Re (100%) (100%) (100%)
1(0%) 1(100%) 1(50%)1
Sub Sub actor MMC Control
Sub Sub actor MMC Control
Sub Sub Sub
A A A A A
A A A A A
A A A
= × × ×
= × × ×
= − −
(1.2)
Table 12 – Available Capacity Table for the Offshore Subsystem (Subsystem 1)
Table 12 shows the offshore subsystem is operating at full capacity approximately 98.8% of the time,
half capacity 0.4% of the time and completely out of service 0.8% of the time.
5.2 Onshore system availability analysis
The analysis of the onshore system is the same as the offshore system. The availability of all the
components in the onshore system is given in Table 13.
Available Capacity GIS1 GIS2 GIS3 GIS4 T1 T2 Probability Availability
100% 1 1 1 1 1 1 0.99604 0.99604
1 1 1 1 1 0 0.00181
1 1 1 1 0 1 0.00181
0 0.00034 0.00034
50% 0.00362
All other combinations
1= available, 0= unavailable
Capacity Availability
100% 0.98817
50% 0.00359
0% 0.00824
Subsystem 1
13
Table 13 - Availability of onshore components
The available capacity of subsystem 5 is given in Table 14.
Table 14 - Available capacity of subsystem5
From equation(1.3) the available capacity of subsystem 3 can be calculated.
3(100%) 5(100%) Re (100%) (100%) (100%)
3(50%) 5(50%) Re (100%) (100%) (100%)
3(0%) 3(100%) 3(50%)1
Sub Sub actor MMC Control
Sub Sub actor MMC Control
Sub Sub Sub
A A A A A
A A A A A
A A A
= × × ×
= × × ×
= − −
(1.3)
Table 15 – Available Capacity Table for the Onshore System (Subsystem 3)
Table 15 shows the onshore system is operating at full capacity approximately 99.6% of the time,
half capacity 0.2% of the time and completely out of service 0.2% of the time.
5.3 DC system availability analysis
The DC system is broken down into three series dependent components as shown in Figure 13.
Figure 13 – Reliability Model of Subsystem 2
Component MTTF(yr) MTTR(hr) Availability
400kV onshore switchbay 100 120 0.99986
275kV onshore switchbay 250 120 0.99995
Onshore Transformer 95 1008 0.99879
Onshore Converter Reactor 7 24 0.99961
MMC Onshore 1.9 12 0.99928
Onshore Control System 1.6 3 0.99979
Available Capacity GIS1 GIS2 GIS3 GIS4 T1 T2 Probability Availability
100% 1 1 1 1 1 1 0.99720 0.99720
1 1 1 1 1 0 0.00121
1 1 1 1 0 1 0.00121
0% 0.00038 0.00038
50% 0.00242
All other combinations
1= available, 0= unavailable
Capacity Availability
100% 0.99588
50% 0.00241
0% 0.00171
Subsystem 3
Offshore DC Switchyard
(100%)DC Cable (100%)
Onshore DC Switchyard
(100%)
14
Subsystem 2 operates at full capacity if all three series dependent components are in service. If any
one component is out of service, subsystem 2 is completely unavailable.
Table 16 - Available Capacity Table for the DC System (Subsystem 2)
5.4 Radial VSC-HVDC Availability
The availability diagram of the VSC-HVDC scheme is shown in Figure 14. The available capacity of the
overall VSC-HVDC scheme is calculated in Table 17.
Figure 14 – Reliability Model of the VSC-HVDC Scheme
Table 17 - Available capacity of Radial VSC-HVDC Scheme
The radial VSC-HVDC scheme operates at full capacity approximately 96.2% of the time, half capacity
0.6% of the time and zero capacity 3.2% of the time. Therefore the schemes energy availability is
approximately 96.5%6. The target annual scheduled outage for maintenance is typically 0.82% (72
hours) for a VSC-HVDC scheme7. Therefore the overall energy availability for the VSC-HVDC scheme
analysed in this report would be approximately 95.7%8. The only known VSC-HVDC availability
statistics for VSC-HVDC schemes are for the Murraylink and Cross Sound Cable project. The average
energy availability for the Murraylink and Cross Sound Cable project are 96.5 and 96.9% respectively
[16]. These figures include forced and scheduled outages. Considering that the VSC-HVDC scheme in
this report was for an offshore windfarm, an overall energy availability of 95.7% seems rational.
The key component which influences the availability of the scheme can be assessed by calculating
the unavailability of each subsystem9.
6 “Energy Availability” is defined in this paper as “the maximum amount of energy which could have been
transmitted except for forced outages”. 7 The manufacturers target scheduled outage rate for the VSC-HVDC Cross Sound Cable project was 0.82%[16].
8 (0.964935-0.0082)*100=95.67%
9 The reader should be aware that adding the individual unavailability in hours (outage) for subsystems 1-3 is
not equal to the total VSC-HVDC scheme outage. This is because outages of individual subsystems can overlap.
Furthermore the unavailability of subsystem1 and subsystem 3 is calculated based on its equivalent energy
Capacity Availability
100% 0.97757
0% 0.02243
Subsystem 2
Capacity (%) Subsystem1 Subsystem 2 Subsystem 3 Probability Availability
100 1 1 1 0.96202 0.96202
0.5 1 1 0.00350
1 1 0.5 0.00233
0.5 1 0.5 0.00001
0 0.03215 0.03215Any Other Combination
50 0.00583
15
Figure 15 – Pie chart to show each subsystem’s unavailability
Figure 15 clearly shows that the DC system (subsystem 2) has the least availability. Therefore the
unavailability of each component in subsystem 2 is calculated and the results are displayed in Figure
16.
Figure 16 - Pie chart to show each component’s unavailability in subsystem 2
Figure 16 shows the DC cable has the greatest effect on the availability of subsystem2 and
subsequently the VSC-HVDC. As mentioned previously the failure rate of submarine cables is
dependent upon many factors. The annual failure rate used in this availability analysis was 0.07
failures per 100km circuit. The effect of the submarine cable failure rate on the energy availability of
the VSC-HVDC scheme excluding scheduled maintenance is shown in Table 18 .
Table 18 – Cable Sensitivity Analysis
availability. Therefore the subsystems energy unavailability is equal to the probability of the subsystem having
no capacity plus 0.5 times the probability of the subsystem operating at 50% capacity.
28%
64%
8%
Subsystem Unavailability
Subsystem 1 Subsystem 2 Subsystem 3
12%
85%
3%
Unavailability of Subsystem 2
Components
Offshore DC Switchyard DC Cable Onshore DC Switchyard
Cable Failure Rate (occ/yr/100km) Energy Availability (%)
0.007 98.2
0.07 96.5
0.7 79.7
16
Table 18 indicates that if the true failure rate of submarine VSC-HVDC cables is in the vicinity of 0.7
failures per 100km of circuit then VSC-HVDC schemes for the connections of the UKs Round 3
offshore windfarms are commercially unviable. This would in fact make the Round 3 windfarms
altogether unviable as any technology which requires submarine cables would have a similar
availability.
6 Regional HVDC Grid
Many potential benefits have been identified from interconnecting offshore windfarms via a multi-
terminal DC (MTDC) network. These benefits include a reduction in the volume of assets installed
offshore, improved operational flexibility and network security. A simplified diagram of the HVDC
grid which will be analysed in this report is shown in Figure 17.
Figure 17 – Regional HVDC Grid
The three offshore nodes are rated at 600MW each, giving a total grid capacity of 1800MW. This is
the maximum infeed loss permitted by NETS SQSS10
[3]. A fault on the DC grid could temporally
cause the entire 1800MW to be disconnected from the AC grid, while the faulty section of the grid is
isolated. The installation of HVDC circuit breakers would enable DC faults to be cleared without de-
energising the entire DC grid and therefore the grid’s maximum capacity could be greater than
1800MW. However there are currently no HVDC circuit breakers commercially available. Therefore
the HVDC grid analysed in this report does not contain HVDC circuit breakers and hence its
maximum capacity is limited to 1800MW.
The DC cables connected between the onshore and offshore converters have a length of 165km. This
length of cable is approximately the average straight line connection distance for the radial HVDC
10
NETS SQSS is the National Electricity Transmission System Security and Quality of Supply Standard.
Wind
Farm 3
165km DC Cable
AC Grid
Wind
Farm 1
DC
Shore
Wind
Farm 2
165km DC Cable
600MW Offshore
AC Substation
600MW Offshore
AC Substation
600MW Offshore
AC Substation
600MW Offshore
Node C (OFNC)
600MW Offshore
Node B (OFNB)
600MW Offshore
Node A (OFNC)
Onshore Node A
(OFNC)
Onshore Node B
(OFNC)
60km DC Cable
60km DC Cable
17
schemes outlined in ODIS. The offshore converters are connected together via 60km of DC cable.
This length of DC cable was chosen as it may be more suitable to connect the windfarms together
using HVAC for connection distances less than 60km.
This paper assesses the availability of the HVDC grid shown in Figure 17 and Figure 19. This analysis
neglects the grid’s downtime due to isolating a DC side fault, as this time is insignificant for the
calculation of grid’s availability.
Each offshore node consists of an offshore DC switchyard connected in series with subsystem 1 and
each onshore node contains an onshore DC switchyard connected in series with subsystem 3, as
shown in Figure 18.
Figure 18 – Onshore and Offshore Nodes
Figure 19 –Block Diagram of Regional HVDC Grid
The onshore nodes and their series connected DC cable can be combined into a single subsystem as
shown in Figure 20. The offshore nodes as well as subsystem 6 and subsystem 7 can be in one of
three states (100%, 50% or 0%), due to the dual transformers in subsystems 1 and 3. The DC cables
(C1 and C2) can be in one of two states (100% or 0%). Therefore the HVDC grid as shown in figure 4
has 972 (5 23 2× ) possible states. Simplifying these nodes/subsystems to two states would reduce
the number of possible HVDC grid states to 128 (27). The probability that subsystem 1 or subsystem
3 is operating at 50% capacity is very small. Therefore in this case, the 50% state may be eliminated
without introducing any significant error in the overall availability analysis of the HVDC grid. The
18
probability of the subsystem operating at 100% capacity is increased accordingly to account for the
exclusion of the 50% state. As an example subsystem 1 which has three states will be simplified to
two states of equivalent available capacity.
Table 19 – Equivalent Available Capacity Table for Subsystem 1
Subsystem 1 in the MTDC grid is rated at 600MW. Therefore the equivalent capacity of subsystem 1
can be calculated as follows:-
3
2
1 600 0.988167 300 0.003591 593.978
1 600 0.98996 593.978
Cap State
Cap State
Sub MW MW MW
Sub MW MW
= × + × =
= × = (1.4)
Equation (1.4) shows that there is no difference between the 3 state and the simplified 2 state
model in terms of the overall capacity of subsystem 1. Therefore the energy transmitted through
subsystem 1 when considered as a standalone system is exactly the same whether it is represented
by a 3 state model or a 2 state model. However the calculated availability of a system containing
several 3 state models is not strictly equal to the calculated availability of a system with equivalent
simplified 2 state models. Nevertheless since the probability of the node/subsystem operating in
the eliminated state is very small, the error is insignificant for the cases analysed in this report.
Figure 20 – Simplified Block Diagram of an HVDC Grid
The simplified two state capacity availability tables for the offshore node as well as subsystem 6 and
subsystem 7 are shown in Table 20.
Capacity Availability Equivalent Availability
100% 0.988167 0.989963
50% 0.003591
0% 0.008242 0.010037
Subsystem 1
19
Table 20 – Available Capacity Tables
The seven components/nodes/subsystems in Figure 20 operate in one of two states giving a possible
128 grid states. VBA code was written in excel to produce a 7x128 truth table. Only the first four
states are shown here. The full table is contained in the appendix.
Table 21 – Truth Table for Regional HVDC Grid
Each ‘1’ and ‘0’ in the truth table is replaced with the probability of that subsystem/node being
available (100%) and unavailable (0%) respectively. The probability of each state is then calculated
by multiplying the seven columns together.
Table 22 – Probability Table for The First Four Grid States
In order to calculate the HVDC grid’s overall availability, the grid’s capacity associated with each of
the 128 states must be deduced. VBA code was written to calculate the grid’s capacity for each of
the 128 states. Table 23 shows the grids available capacity for the first 4 states with subsystem 6 and
subsystem 7 having a capacity rating of 900MW each.
Table 23 – Capacity Table for Regional HVDC Grid with Sub6=Sub7=900MW
Summing the probabilities of each state for each grid capacity level gives the grid’s available capacity
as shown in Table 24.
Capacity Availability
100% 0.98721
0% 0.01279
Offshore Node
Capacity Availability
100% 0.99635
0% 0.00365
Onshore Node
Capacity Availability
100% 0.97743
0% 0.02257
Subsystem 6 and7
State OFNA OFNB OFNC C1 C2 Sub 6 Sub 71 1 1 1 1 1 1 12 1 1 1 1 1 1 03 1 1 1 1 1 0 14 1 1 1 1 1 0 0
State OFNA OFNB OFNC C1 C2 Sub 6 Sub 7 Probability1 0.98721 0.98721 0.98721 0.99310 0.99310 0.97743 0.97743 0.906542 0.98721 0.98721 0.98721 0.99310 0.99310 0.97743 0.02257 0.020933 0.98721 0.98721 0.98721 0.99310 0.99310 0.02257 0.97743 0.020934 0.98721 0.98721 0.98721 0.99310 0.99310 0.02257 0.02257 0.00048
State OFNA OFNB OFNC C1 C2 Sub 6 Sub 7 Capacity (MW)1 1 1 1 1 1 1 1 18002 1 1 1 1 1 1 0 9003 1 1 1 1 1 0 1 9004 1 1 1 1 1 0 0 0
20
Table 24 – Capacity Availability Table for Regional HVDC Grid with Sub6=Sub7=900MW
The HVDC grid shown in Figure 20 with each path to shore (sub6 & sub7) rated at 900MW has an
energy availability of 0.96302 compared to a energy availability of 0.964935 for a radial HVDC link.
This indicates that three 600MW radial links would have a higher energy availability than an
1800MW HVDC grid with each path to shore rated at 900MW. Upgrading subsystem 6 and 7 to
1200MW increases the grid’s availability as shown in Table 25.
Table 25– Capacity Availability Table for Regional HVDC Grid with Sub6=Sub7=1200MW
The grids availability can be increased further by rating each path to shore, equal to the grid’s
maximum capacity as shown in Table 26.
Table 26 - – Capacity Availability Table for Regional HVDC Grid with Sub6=Sub7=1800MW
The reader should be aware that the availability figures given in Table 26 are calculated from
component reliability indices for a DC voltage of ±300kV however it is likely any 1800MW VSC-HVDC
scheme will be built at a voltage greater than this. However data on such systems is even sparser
than for ±300kV systems.
Capacity (MW) Availability Energy Availability1800 0.90654 0.963021500 0.012601200 0.03560900 0.04395600 0.000790 0.00052
Sub 6&7 =900MW
Capacity (MW) Availability Energy Availability1800 0.91915 0.972441200 0.07954600 0.000790 0.00052
Sub6 & Sub 7 = 1200MW
Capacity (MW) Availability Energy Availability1800 0.96101 0.986401200 0.03768600 0.000790 0.00052
Sub 6 & Sub 7=1800MW
21
7 Cost-benefit analysis
This section of the document compares the required capital investment against the calculated
availability of each of the following schemes:-
1. 1800MW Regional HVDC grid with each path to shore rated at 900MW
2. Three 600MW radial HVDC links
3. 1800MW Regional HVDC grid with each path to shore rated at 1200MW
Since the schemes are being compared with one another, the components which are common to all
schemes can be ignored as the cost of these components would be the same for each scheme. All of
the schemes require three 600MW offshore nodes; hence the cost of these items is neglected. The
costs of components used in this cost benefit analysis are from the ODIS 2011 annex and are for
indicative purposes only.
Table 27 – VSC Converter Costs11
Table 28 – HVDC Extruded Cable Costs12
Table 29 – Cable Installation Costs
From the above tables the cost of the three transmission schemes (excluding the offshore nodes)
can be estimated. The required cross sectional area for HVDC submarine cable of different power
ratings was estimated from data given in [17]. It is estimated that the 600MW, 900MW and
11
It is assumed the VSC converter cost is for a single converter including AC and DC switchyard. 12
It is assumed the cost is per km of cable not per km of route (i.e one radial link requires 2x165km of cable).
Rating Min Max Average
300kV 500MW 65 80 72.5
320kV 850MW 85 105 95
500kV 1250MW 105 130 117.5
500kV 2000MW 125 175 150
VSC Converter Costs (£m)
Cross sec Area
Min Max Average Min Max Average
1200 200 400 300 300 450 375
1500 250 400 325 300 450 375
1800 300 450 375 300 500 400
2000 300 500 400 350 550 450
±150kV ±320kV
HVDC Extruded Cable Costs (£k/km)
Cable Installation Type Min Max Average
Twin Cable in Single Trench 0.5 0.9 0.7
Cable Installation Costs (£m/km)
22
1200MW cable would require cross sectional area of about 630mm2, 1400mm
2 and 2200mm
2
respectively13
. The costs of each scheme excluding the offshore nodes are given in Table 30.
Table 30 – HVDC transmission Scheme Costs Excluding Offshore Nodes
The HVDC grid with each path back to shore rated at 900MW (scheme 1) is the least expensive
scheme, but also has the lowest energy availability. The radial scheme (scheme 2) and the HVDC grid
with each path back to shore are rated at 1200MW (scheme 3) are more expensive than scheme 1,
but their energy availability is higher. Since higher availability equates to greater revenue, it may
make more economic sense to invest a greater amount of capital to obtain a scheme with a higher
availability.
The amount of revenue lost each year due to a transmission scheme being unavailable can be
calculated using equation(1.5).
8760( )R F pLoss U P C hrs S= × × × × (1.5)
£ /
R
F p
U Unavailability P Rated power in MW
C Capacity factor S Electricty sale pricein MW
− −− −
The capacity factor for the three schemes is assumed to be 0.414
. This means that over the course of
the year the transmission scheme is only required to operate at 40% of its rated power. The
electricity sale price is assumed to be £150/MWh15
.
The annual saving for scheme 2 and scheme 3 is calculated by subtracting the annual loss of that
scheme from the annual loss of scheme 1.
13
Figures are based on a ±300kV submarine cable with a copper conductor in a moderate climate spaced
closely together. These figures are indicative only. 14
Capacity factors of 0.35-0.45 are typical for offshore windfarms. 15
This figure is based on one MWh of energy generated by an offshore windfarm being equal to the electricity
wholesale price plus two renewable obligations certificates (ROC) plus one levy exemption certificate (LEC).
The electricity wholesale price is approximately £60/MWh [18]. Accredited offshore windfarms are currently
awarded 2 ROC’s per MWh [19], where each ROC is worth £38.69 plus 10% for headroom [20]. One LEC has a
value of £4.85 [21].
Scheme Item Cost £m Total Cost £m
240km ±300kV 1200MW Cable 114
660km ±300kV 900MW Cable 247.5
Cable Installation 315
2 x 900MW Onshore Converter 200
990km ±300kV 600MW Cable 321.75
Cable Installation 346.5
3 x 600MW Onshore Converter 240
900km ±300kV 1200MW Cable 427.5
Cable Installation 315
2 X1200MW Onshore Converter 240
2. Radial 908.25
3. 1200MW 982.5
1. 900MW 876.50
23
Table 31 – Economic Cost Benefit Analysis
Dividing the additional capital investment of a scheme by that scheme’s additional annual revenue is
one way to calculate the number of years it takes to repay the investment. If the number of years to
repay the investment is less that the life expectancy of the scheme, then it may be worth investing
the additional capital.
HVDC schemes can have a life expectancy in excess of 40 years [22]. Therefore this cost-benefit
availability analysis indicates that scheme 3 offers the best potential return for the investor.
Variations in capital costs, capacity factor and electricity price could significantly impact on these
results. This type of economic cost-benefit analysis is simplistic and should only be used as an
indication. An extensive cost-benefit analysis would need to consider the projected inflation rates,
interest rates, and electricity prices over the next 40 years as well as taxation, exchange rates and
commodity prices such as copper. This type of economic forecasting is at best loose and out of the
scope of this report.
The purpose of this cost-benefit availability analysis is to clearly show the strong link between
transmission schemes availability and its economic feasibility. Other factors such as system losses
must be taken into consideration when evaluating which transmission scheme configuration offers
the greatest financially reward.
8 Summary
The most suitable transmission technology for the connection of large offshore windfarms located
more than approximately 50km from shore is VSC-HVDC. The technical and commercial viability of
connecting vast amounts of the UK’s generating capacity long distances from shore is dependent
upon the availability of VSC-HVDC schemes.
A radial VSC-HVDC scheme has been constructed for the purpose of performing availability analysis.
The scheme was based on the potential radial VSC-HVDC designs outlined in National Grid’s ODIS, to
ensure the scheme represents a typical VSC-HVDC link. Availability analysis, independent of
methodology, can only ever be as good as the input data. Unfortunately there are no true failure
statistics for VSC-HVDC components available in the public domain. Therefore the reliability indices
for each component within the scheme have been estimated based on the most credible
information available.
The availability analysis for the radial VSC-HVDC scheme has shown the energy availability due to
forced outages to be approximately 96.5%. The DC submarine cable was identified to be the key
component which affects the availability of the transmission scheme. Therefore every effort must
be made to ensure failures of submarine cables are minimised.
Availability analysis was carried out on a regional HVDC grid with each of its two paths back to shore
rated at 900, 1200 and 1800MW. This analysis shown that the availability of the grid was highly
Scheme Capital Cost £m Availability Loss £m/yr Saving £m /yr Additional Capital Cost £m Payback (yr)
1 876.5 0.963 34.990 0 0 0
2 908.25 0.965 33.174 1.816 31.75 17
3 982.5 0.972 26.073 8.917 106 12
24
dependent upon the rating of the grid’s paths back to shore and that the grid with paths rated at
1200MW and 1800MW had a significantly higher availability than an equivalent radial system.
The strong link between a HVDC transmission schemes availability and economic feasibility has also
been established in this report.
9 Conclusion
Connecting large amounts of offshore wind far from the shore is a sure way to increase renewable
energy generation. However if the availability of the transmission systems which facilitates the
power transfer back to shore is poor, the cost of energy to the consumer will increase and have a
negative impact on the economy. Therefore work to ensure a high availability of these transmission
schemes is of paramount importance. Availability analysis is a good tool to calculate the availability
of these schemes and to identify key components which have the greatest impact on the scheme.
This would allow mitigation strategies to improve the schemes availability to be put in place before
the schemes are built. However with the current lack of reliability data for VSC-HVDC components
conclusive availability analysis cannot be performed, although the key importance of the cable’s
availability is highlighted. Furthermore HVDC grids with additional capacity have been shown to
have a higher availability than an equivalent radial HVDC scheme and consequently could provide a
more cost-effective solution for the connection offshore windfarms.
25
10 References
[1] The Crown Estate, "Offshore wind: Opportunities for the composites industry", 2011, http://www.thecrownestate.co.uk/opportunities_composites_industry.pdf [accessed: July 2011]
[2] National Grid, "2010 Offshore Development Information Statement " 2010.
[3] National Grid, "Offshore Development Information Statement," 2011.
[4] Siemens, "HVDC PLUS – Basics and Principle of Operation," Siemens, 2008.
[5] K. Friedrich, "Modern HVDC Plus application of VSC in Modular Multilevel Converter Topology," 2010.
[6] N. MacLeod, "HVDC Max Sine : VSC Demonstrator," 2011.
[7] ABB, "Product Brochure - Gas-insulated Switchgear ELK-14, 245kV," 2011.
[8] National Grid, "2011 Offshore Development Information Statement Appendices," 2011.
[9] ABB, "Liquid-filled power transformers," 2009.
[10] Alstom, "Voltage Source Converter - Cooling Plant", 2010, http://www.alstom.com/assetmanagement/DownloadAsset.aspx?ID=a5030f88-1638-4874-a92f-b51cc294d9d2&version=9978ae5698e8433aa9283c2bee3ca94a1.pdf&lang=1036 [accessed:
[11] C. Ö. Ø. Rui, J. Solvik, J. Thon, K. Karijord, T. Gjengedal, "Design, operation and availability analysis of a multi-terminal HVDC grid - A case study of a possible Offshore Grid in the Norwegian Sea " in IEEE Trondheim PowerTech, 2011.
[12] Alstom, "Voltage Source Converter Switchyard," 2011.
[13] Alstom, HVDC - Connecting to the future: Alstom, 2010.
[14] Alstom, "HVDC for beginners and beyond," 2009.
[15] F. H. T.M. Chan, D. Kopejtkova*, P. O’Connell, J.-P. Taillebois, I. Welch, "Report on the second International Survey on High Voltage Gas Insulated Substations (GIS) Service Experience," 1998.
[16] S. Dodds, B. Railing, K. Akman, B. Jacobson, T. Worzyk, and B. Nilsson, "HVDC VSC (HVDC light) transmission – operating experiences," Cigre 2010, 2010.
[17] ABB, "Its time to connect," 2008.
[18] Ofgem, "Electricity and Gas Supply Market Report," Oct 2011.
[19] Department of Energy and Climate Change, "Eligible renewable sources and banding levels", http://www.decc.gov.uk/en/content/cms/meeting_energy/renewable_ener/renew_obs/eligibility/eligibility.aspx [accessed: Novemeber 2011]
26
[20] Ofgem, "The Renewables Obligation Buy-Out price and Mutualisation Ceiling 2011-2012," 2011.
[21] Ofgem, "Climate Change Levy: Renewables Exemption", http://www.ofgem.gov.uk/Sustainability/Environment/cclrenexem/Pages/CCLRenewablesExemption.aspx [accessed: November 2011]
[22] J. E. Skog, "HVDC Transmission and Lifetime Expectancy," 2004.
[23] S. Zadkhast, M. Fotuhi-Firuzabad, F. Aminifar, R. Billinton, S. O. Faried, and A.-A. A. Edris, "Reliability Evaluation of an HVDC Transmission System Tapped by a VSC Station," IEEE Transactions on Power Delivery, 2010.
[24] K. Linden, B. Jacobson, M. H. J. Bollen, and J.Lundquist, "Reliability study methodology for HVDC grids," Cigre 2010, 2010.
[25] ABB, "The evolution of GIS (Gas Insulated Switchgears)", 2011, http://www.abb.com/cawp/db0003db002698/38508bb5b1291fa7c12572ec003304ca.aspx [accessed: 20/10/11]
[26] ABB, "ABB Review - Extreme maintenance", http://www05.abb.com/global/scot/scot271.nsf/veritydisplay/e01a592d15046c26c1256f030033b6bc/$file/abb%20sp%204-04.pdf [accessed:
[27] ABB, "ABB’s on-site transformer repair service provides rapid return to full production for Corus’ Scunthorpe steelworks ", http://www.abb.co.uk/cawp/seitp202/0786ec54259901cec12576b3003a2d67.aspx [accessed: 20/10/11]
[28] R. V. Narinder S. Dhaliwal* and M. H. Astrid Keste, Peter Kuffel, , "Nelson River Pole 2 Mercury Arc Valve Replacement," Cigre, 2004.
[29] R. D. R.-C. U. Cigre Working Group B1.10, "Update of Service Experience of HV Underground and Submarine Cable Systems," 2009.
[30] National Grid, "2010 Offshore Development Information Statement Appendices," 2010.
[31] R. A. R. Billinton, Reliability Evaluation of Engineering Systems - Concepts and Techniques: Plenum Press, 1992.
[32] S. Stanley, "MTBF, MTTR, MTTF & FIT Explanation of Terms," IMC Networks, 2011.
27
Appendix A
Component Reliability Indices
Reliability statistics for the components in a VSC-HVDC scheme are extremely sparse. The following
papers/reports produced by academic institutions and industry will be used as the basis for the
derivation of reliability statistics for the VSC-HVDC scheme used in this report:-
1. LCC-HVDC data from academic paper [23] [Billinton et al, “Reliability Evaluation of an HVDC
Transmission System Tapped by a VSC Station"]
2. VSC-HVDC data from academic paper [23]
3. VSC-HVDC data from industrial paper report [11] [Statnett and DNV, “Design, operation and
availability analysis of a multi-terminal HVDC grid - A case study of a possible Offshore Grid
in the Norwegian Sea”]
4. VSC-HVDC data from Cigre paper [24] [ ABB and STRI, “Reliability study methodology for
HVDC grids”]
Source 1 and 2 are recent IEEE transactions paper produced by respected authors in the area of
power systems reliability including Roy Billinton. The third source is a report produced by Statnett
and Det Norske Veritas (DNV). The fourth source is a Cigre paper written by authors from ABB and
STRI. Therefore the data from these papers is expected to be credible. Due to the limited data
available some degree of estimation is unavoidable. Where this has been done the rational used is
explained.
Gas Insulated Switchgear (GIS) Failure Statistics
Unfortunately sources 1-4 only gave failure statistics for an AC circuit breaker. However since the
circuit breaker is the main component of a GIS switchbay, it is worth analysing the failure statistics
used in sources 1-4 to give an indication of the failure statistics for the GIS.
Table 32 shows the reliability statistics for AC circuit breakers given in academic and industrial
papers.
Table 32 – Circuit Breaker MTTF and MTTR values given in Academic and Industrial Papers
It is clear from Table 32 that the circuit breaker reliability statistics used for reliability studies in
academic and industrial papers varies very significantly. Source 3 and 4 reference Cigre publications
Source MTTF(yr) MTTR(hr) Scheme
1 66.7 50 500kV
2 1000 40 500kV
3 405 190 132kV Offshore
4 50 200 >500kV
28
for their reliability statistics. The last known high voltage circuit breaker survey was published by
Cigre in 1994. This publication presented results from two surveys one conducted between 1974 and
1977 (all circuit breaker technologies) and the other conducted between 1988 and 1991 (only SF6).
Table 33 – Cigre High Voltage Circuit Breaker Reliability Data
The MTTF values for the survey conducted in 1988-1991 survey are more than 3 times higher than
the values from the 1974-1977 survey. This increase in MTTF for the circuit breakers in the 1988-
1991 survey is thought to be due to improvements in circuit breaker technology and due to the
utilities doing a better job of collecting statistics. The increase in downtime for the MTTR for circuit
breakers in the 1988-1991 survey was cited as being primarily due to the time taken to obtain a
specific spare part, for the SF6 circuit breakers.
According to the ODIS 2011 document, gas insulated switchgear (GIS) bays will be installed on all
offshore platforms and onshore platforms located less than 5km from the sea. The final results for
two surveys on the reliability of gas insulated substations have been published. The first
international survey was circulated in 1991 and the second survey was circulated in 1996 [15]. The
major failure statistics results from the 2nd
international survey for GIS commissioned after 1985 are
shown in Table 34.
Table 34 –Failure statistics from the 1996 survey for GIS commissioned after 198516
Comparing the values from the Cigre 1988-1991 survey in Table 33 with Table 34, it is clear that a
GIS bay tends to take longer to repair than an AC circuit breaker and that the higher voltage (300-
500kV) GIS has a shorter MTTF than an AC circuit breaker. This is not particularly surprising
considering a GIS bay contains an AC circuit breaker as well as other equipment such as
disconnectors.
The data given in Table 32, Table 33 and Table 34 can be used to estimate the failure statistics for a
220/275kV GIS switchbay and a 400kV switchbay commissioned in 2011. It is fair to assume that the
MTTF of a GIS switchbay in 2011 would be much higher than a GIS switchbay commissioned
between 1985 and 1996. In fact the MTTF from the 1996 survey for 200-300kV GIS commissioned
after 1985 was 45% higher than the GIS commissioned after 1985 from the 1991 survey. The MTTF
for AC circuit breakers 1988 survey was more than 300% higher than the values given in the 1974
16
MTTF is calculated by taking the reciprocal of the failure rate. It is assumed the failure rate is based on the
number of Circuit breaker bay-years in service. (I.e. the reciprocal of the failure rate is the MTTF not the
MTBF). In any case difference between MTTF and MTBF will be very small.
Survey Voltage(kV) MTTF (yr) MTTR(hr)
200-300 38.760 58.5
300-500 21.978 83.8
200-300 122.850 54.6
300-500 82.645 162.5
Cigre 1974-1977
Cigre 1988-1991
Component MTTF (yr) MTTR(hr)
200-300kV GIS 149 192
300-500kV GIS 39 192
29
survey. Therefore it is justifiable to assume the MTTF for a 220/275kV GIS switchbay and a 400kV
switchbay commissioned in 2011 would be 250 years and 100 years respectively. These figures lie
within reasonable ranges as shown by the figures used in academic and industrial papers in Table 32.
It is also worth mentioning that ABB have quoted a mean time between failure (MTBF) figure of up
to 1000 bay-years for their gas insulated switchgear[25].
Based on the assumption that GIS today would be somewhat easier to fix than 15-25 years ago and
that the spare parts are more readily available, the MTTR values will be reduced. Furthermore the
supply chain is computerised with modern telecoms which would help to improve service levels.
Therefore the MTTR for modern GIS is assumed to be 120 hours.
As mentioned previously access times for offshore platforms vary massively depending on a number
of factors. The 1996 GIS survey stated at about 70% of repairs could be carried out on site and
required a spare part and/or enclosure [15]. It is assumed that the high majority of spare parts could
be transported by helicopter. Therefore the time to access the offshore platform to repair a GIS
switchbay is taken as 84 hours (70% helicopter, 30% medium vessel). Approximately 40% of 192
hours down time (Table 34) is the time it takes to get spare parts and tools. It is estimated about 20
hours of the offshore access time is spent performing administration related tasks which could be
done concurrently with the time spent obtaining spare parts. Therefore the MTTR for the offshore
gas insulated switchgear offshore used is 184 hours.
Figure 21 – Estimated Reliability Values for GIS
Transformer Failure Statistics
Table 35 shows the reliability statistics for transformers given in academic and industrial papers.
Table 35 – Transformer Failure Statistics given in Academic and Industrial Papers
The transformers used in LCC-HVDC schemes (source1) are more complex and experience greater
stress than the transformers in the VSC-HVDC schemes (source 2). This would explain the better
reliability statistics for the transformer from source 2.
The reliability statistics provided by source 4 are from the latest transformer failure statistics survey
published by Cigre in 1983 for transformers between 300-700kV. After analysing the 1983 report it is
clear that the statistics from source 4 are based on an autotransformer with and without an on load
tap changer (OLTC). Analysis of the 1983 report shows that for an autotransformer with an OLTC the
Component MTTF (yr) MTTR(hr)
Offshore switchbay 250 184
400kV onshore switchbay 100 120
275kV onshore switchbay 250 120
Source MTTF (yr) MTTR (hr) Scheme
1 14.29 1200 500kV
2 20 1000 500kV
3 225 672 132kV Offshore
4 41.67 2160 >500kV
30
MTTF is 98.33 years and for an autotransformer without OLTC the MTTF is 17.2 years17
. This is
somewhat surprising and the report noted that the abnormally high failure rate of autotransformers
without OLTC could be in part explained by the failure of the transformers belonging to a certain
network. In other words the MTTF of 17.2 years for an autotransformer without OLTC should be
used with a degree of caution and therefore the figure with and without OLTC as used in source 4
should also be used with a degree of caution. In any case HVDC schemes use transformers with an
OLTC and tend not to use autotransformers, because they cannot provide galvanic isolation between
the AC and DC sides. Therefore the statistic given in source 4 may not be representative of a
transformer used in an HVDC scheme.
The 1983 Cigre report also gave statistics for substation station transformers. The MTTF for a 100-
300kV substation transformer with an OLTC and a 300-700kV transformer is 62.5 years and 50.85
years respectively. Considering the survey was conducted more than 30 years ago. It is reasonable to
suggest the MTTF for a modern transformer is much improved. Therefore an estimated MTTF of 95
years for 100-300kV transformer and 80 years a 300-700kV transformer will be used in this
availability analysis. These values are still much less than the estimated values given by DNV.
Unfortunately the 1983 Cigre report did not publish the mean downtime for non-autotransformers
in the 300-700kV range as it was deemed not significant. However the mean downtime with a 95%
confidence level for a 100-300kV transformer with an OLTC was reported as being between 46 and
76 days. Therefore the MTTR is taken as the mean, 61 days (1464 hrs). Considering it is now more
than 30 years since the survey was conducted, an estimated MTTR value of 42 days (1008 hrs) will be
assumed. This figure is based on the assumption that technology today allows a quicker diagnosis
and repair of the transformer failure.
In the event a transformer fails it is normally shipped back to the factory for repair [26]. There have
been situations where it is so difficult to send the transformer back to the factory that a fully
equipped workshop has been constructed on site. It is difficult to send an offshore transformer back
to the factory, but due to the lack of space on an offshore platform it would be extremely rare if not
impossible to construct a workshop on the platform. Therefore in the event a transformer fails it is
expected it would need to be shipped back to the factory for repair.
In this report the time it takes to access an offshore platform with a transformer has been estimated
at 3 weeks (504 hours) as shown in Table 1. This figure was based on the transportation of a large
item such as a transformer to the offshore platform. The offshore access time required for repairing
an offshore transformer would be split into two parts. The first part would be to transport the
transformer back to shore. The second part would occur once the transformer is repaired and must
be transported back to the offshore platform. Therefore the offshore access time for repairing the
transformer must at least be greater than 3 weeks. A significant portion of the three weeks access
time would be due to delays in acquiring the large vessel at very short notice. However the vessel
could be booked well in advance for returning the transformer back to the offshore platform.
Therefore the access time to transport the transformer to the offshore platform will be reduced to
17
MTTF is calculated by taking the reciprocal of the failure rate. According to the Cigre report the failure rate is
calculated based on the number of transformer-years in service (i.e. the reciprocal of the failure rate is the
MTTF not the MTBF).
31
one week. Therefore the total access time to repair the offshore transformer is estimated to be 4
weeks.
It is assumed one week of the MTTR for the onshore transformer is spent sourcing spare parts. It is
feasible that the transformer could be diagnosed using non-invasive tests on the offshore platform
[27]. This would allow the spare part to be sourced while the transformer is being transported back
to the factory. Therefore the MTTR for the offshore transformer will be 3 weeks longer than the
MTTR for the onshore transformer. For comparison DNV increased the MTTR for the offshore
transformer by 3 weeks in their availability analysis.
Table 36 – Reliability Values for Transformer
Converter Reactor Failure Statistics
Table 37 shows the reliability statistics for phase reactors given in academic and industrial papers.
Table 37 – Converter reactor reliability values given in Academic and Industrial Papers
Only source 3 has stated reliability values for the converter reactor. Unfortunately there no other
known author publications which have given reliability values for the converter phase reactor. It is
worth noting that availability statistics for the Murraylink VSC-HVDC scheme have been published by
ABB in a Cigre paper [16] as shown in Table 38.
Table 38 – Murraylink Energy Availability
The very low availability of the scheme in 2007 was due to a fault in the phase reactor, which was
most likely caused by a fault in an external light fitting which lead to a fire on the reactor. It was
noted that one of the reasons the repair took so long was because the building was not designed to
accommodate an easy replacement. That said the Murray link went into service in 2003 and it is
expected new schemes would be designed to allow easy replacement of components.
The values from DNV seem reasonable, after all DNV is a well respected risk management company
and therefore their values are expected to be credible. The only slight concern is that the MTTR
values for both the onshore and offshore converters are the same. In the event a converter reactor
fails it is assumed it would need to be replaced rather than repaired on site because it is a single unit
and has no moving parts. A converter reactor is too large to be shipped via a helicopter therefore a
medium sized vessel would be required. The offshore access time for the converter reactor is 168
Component MTTF(yr) MTTR(hr)
Offshore Transformer 95.00 1512.00
Onshore Transformer 95.00 1008.00
Source MTTF (yr) MTTR (hr)
3 7 24
Energy 2003 2004 2005 2006 2007 2008 2009 Average
Total 95.18 97.08 95.39 98.92 90.56 99.17 99.37 96.52429
Scheduled 96.49 98.77 97.96 98.51 97.91 99.12 99.13 98.27
Forced 98.21 98.04 97.11 99.33 90.98 99.86 100 97.64714
Murray Link
32
hours. It is expected that a converter reactor is readily available to allow replacement within 24
hours. Since there is no time delay in sourcing the component the offshore MTTR is equal to the
onshore MTTR plus the offshore access time.
Table 39 – Phase Reactor Reliability Values
MMC Failure Statistics
Table 40 shows the reliability statistics for MMCs given in academic and industrial papers.
Table 40 – MMC Failure Statistics given in Academic and Industrial Papers
It is unclear if sources 1 and 2 have included the control and protection (C&P) systems as well as the
cooling and ventilation systems in the reliability values for the converter. However it is assumed they
have since these systems are not considered separately and the converter would be the most
appropriate component in which to include these systems. Sources 2 and 3 do not explicitly state
that their reliability statistics are for a two level VSC converter, however, since both systems include
AC filters it is fair to assume they are for a two-level converter. Source 3 has considered the C&P as
well as the cooling and ventilation systems separately. Therefore the values given by source are
purely for the IGBT converter system.
The reliability statistics given for a voltage source converter in source 4 are based on actual forced
outage statistics collected for LCC-HVDC schemes between 2005 and 2006 [24]. However the value
for source 4 given in Table 40 is a combined value for the converter, C&P and DC equipment. Based
on the same analysis method used in source 4 the MTTF and MTTR for only the converter is 2.1 years
and 3 hours respectively. These values account for the cooling and ventilation systems, but not the
C&P and DC equipment.
There has been no actual reliability statistics published for converters used in VSC-HVDC schemes.
However based on the values given in Table 40 it is assumed that the MTTF and MTTR for a two-level
VSC are 2 years and 12 hours respectively. The MMC has a significantly higher component count
than a two-level VSC, which is likely to reduce the reliability of the converter. However it does not
suffer the high stress of switching all IGBTs in the valve simultaneously. It is reasonable to assume
that the MMC at this time will be slightly less reliable than the two-level converter due to the lack of
Component MTTF (yr) MTTR (hr)
Onshore Converter Reactor 7 24
Offshore Converter Reactor 7 192
Source MTTF (yr) MTTR (hr) Comment
1 1 5 LCC
2 2 4 2-level VSC
3 2 24 2-level VSC
4 0.71 4.1 VSC*
*Value based on LCC and includes the C&P and the DC Equipment
33
experience with this type of converter in HVDC schemes and the higher component count. Therefore
the MTTF will be reduced to 1.9 years as a placeholder to reflect the expected increase in failure
rates for MMC. The MTTR will be kept the same at 12 hours for an onshore converter. The reliability
indices for the MMC account for the cooling and ventilation systems.
The failure of a MMC is likely to require a sub-module replacing. It is justifiably assumed that spare
sub-modules would be readily available since they require minimum storage space and are critical
for converter operation. Sub-modules are fairly small components and could be transported by a
helicopter with the engineer. Since the reliability indices for the MMC includes the cooling and
ventilation systems, the size of spare parts for these systems must also be taken into account. The
critical components which have high failure rates in a cooling plant are electrical motors. It is
expected that electrical motors could be transported by helicopter/small vessel. The offshore access
time for such a component has been estimated at 48 hours (Table 1) and as such the MTTR for the
offshore converter is 60 hours.
Table 41 – MMC Reliability Values
Control System
Table 42 shows the reliability statistics for the control system given in academic and industrial
papers.
Table 42 – Control and Protection Failure Statistics given in Academic and Industrial Papers
The reliability statistics from source 3 are a DNV internal estimate for a single VSC control system.
The control and protection systems for HVDC schemes are normally duplicated [13]. Therefore the
availability of the duplicated control system must be calculated.
Table 43 – Availability of DNV duplicated control system
Providing the repair time for the DNV duplicated C&P system is fixed at 9 hours the MTTF for the
duplicated control system would be approximately 930 years. This value has been calculated by
rearranging equation (1.1)
Component MTTF (yr) MTTR (hr)
MMC Onshore 1.9 12
MMC Offshore 1.9 60
Source MTTF (yr) MTTR (hr)
3 1 9
4 1.60 3
Capacity Control 1 Control 2 Probability Availability
1 1 0.99795
1 0 0.00103
0 1 0.00103
0 0 0 0.00000 0.0000011
100% 0.9999989
34
(1 )
(1 )
MTTFA
MTTF MTTRMTTF
MTTF MTTRA
MTTF A A MTTR
A MTTRMTTF
A
=+
= +
− = ××=
−
(1.6)
0.9999989 9
8181809 930(1 0.9999989)
hrs or yrs× ≈
− (1.7)
The values given in source 4 are from the actual forced outage statistics collected for LCC-HVDC
schemes between 2005 and 2006. Therefore the MTTF statistic is actually the mean time to failure
of both C&P systems as the scheme could operate if only one of the two C&P systems failed.
Therefore the availability of the duplicated C&P system is 0.99979 which is significantly less than the
availability of the duplicated control system from the DNV reliability data. This is further highlighted
by the difference between the calculated MTTF value from the DNV data and the MTTF value from
source 4. It is expected the reliability data given in source 4 is more realistic than source 3 since this
is actual HVDC C&P failure data.
The hardware for the C&P system for a LCC-HVDC system is similar to an MMC VSC-HVDC system.
Therefore the data given in source 4 would provide a good basis for estimating the reliability indices
for the MMC VSC-HVDC C&P system. The MMC valve based electronics (VBE), the interface between
the C&P system and the converter, is different from that of an LCC-HVDC scheme due to the higher
number of levels. The software is also more complex, because the control system must balance the
capacitor voltages in the MMC valve and turn each level on and off individually. However it is
expected that a modern C&P system would be more reliable than an older C&P system. The world
HVDC survey obtains data from many schemes using C&P systems of different ages. Therefore all
things considered a MTTF and MTTR of 1.6 years and 3 hours will be used in this availability analysis.
It is assumed many control system faults could be solved without attending the site (i.e. via remote
access). In the event that the problem cannot be solved via remote access an engineer would have
to attend site. Spare parts for controls systems such as digital signal processing cards are very small
and therefore access via helicopter is suitable. It is assumed that 30 % of faults on the offshore
control system require an on-site visit. Therefore the MTTR of the offshore control system is equal to
MTTR for the onshore control system plus 30% of the time required to access the offshore platform
with a small component (3+48*0.3=17hours).
Table 44 – Control System Reliability Values
Component MTTF (yr) MTTR (hr)
Onshore Control System 1.6 3
Offshore Control System 1.6 17
35
DC Switchyard
Table 45 contains the reliability indices for the DC equipment from sources 1-4.
Table 45 – DC Equipment Failure Statistics given in Academic and Industrial Papers
There is significant difference between the DC filter reliability indices between sources 1 and 2. The
DC filters are for different schemes but it is unlikely that the VSC DC filter is 400 times more reliable
than an LCC filter based on the MTTF. The DNV (source 3) reliability indices for the VSC DC filter
appear to be more realistic than source 2. Sources 1-3 have appear to have included what they
consider the key components for their analysis, whereas source 4 has accounted for an entire DC
switchyard. Source 4 has accounted for all the VSC DC equipment by analysing the failure statistics
for DC equipment in the 2006-2007 world HVDC survey (LCC) published in 2008.
The major equipment in a MMC DC VSC switchyard consists of HV capacitor banks, line reactors,
measurement transducers and switchgear [12]. The major equipment in a LCC DC switchyard
consists of DC harmonic filters, smoothing reactors, measurement transducers and switchgear [13].
Figure 22 – MMC VSC DC Switchyard (left, modified from[12]) LCC DC Switchyard (right modified from[14])
Since there is significant similarity between the DC switchyards, the failure statistics from the world
HVDC survey (LCC) could be used to estimate the reliability indices for the MMC VSC-HVDC DC
switchyard. The latest World HVDC survey was published in 2010 for data collected on LCC-HVDC
schemes during 2007-2008. Back-to-back HVDC schemes do not normally require smoothing
reactors or DC filters [13]. Therefore only the data for transmission schemes should be considered.
In the 2007-2008 HVDC survey data was collected from 18 transmission schemes (8 monopole and
Source MTTF (yr) MTTR (hr) Scheme
20 300 Smoothing Reactor
2.5 12 LCC DC Filter
1 4 VSC HVDC Switch/breaker
1000 5 VSC DC Filter
7 24 HV DC Bus
6 24 VSC DC Filter
4 3.333 6.4 Based on Data from 2005-2006 LCC Survey
1
2
3
Line Reactor
36
10 bipole). Monopole schemes have one DC switchyard at each end of the scheme, whereas bipole
schemes have the equivalent of two DC switchyards at each end of the scheme. The failure rate for a
single DC switchyard can be calculated by summing the number of failures for the 18 transmission
schemes and dividing by the number of DC switchyards (56). The MTTR is obtained by dividing the
total number of outage hours by the number of failures. The reciprocal of the failure rate is the
mean time between failures (MTBF). The MTTF is the MTBF minus the MTTR. The average MTTF and
MTTR has been calculated and is shown in Table 46.
Table 46 – Analysis of the DC equipment failure statistics from the world 2007-2008 HVDC survey
Comparing the MTTF and MTTR calculated here from the 2007-2008 with the reliability indices
calculated in source 4 from the 2005-2006 shows some significant difference. However source 4
calculated the reliability indices for a DC switchyard from both back-to-back and transmission
schemes. Source 4 also assumed that 50% of the HVDC schemes in the 2005-2006 were monopole
and 50% were bipole. Since the 2007-2008 survey is the most recent and the analysis of the
reliability indices is more accurate for a transmission scheme these indices will be used in this report.
It is worth noting that although there are 18 transmission schemes which would normally equate to
56 converters (8*2+4*10) further analysis of the data shows that there are actually 80 converters.
This is because a number of schemes contain more than 1 converter per pole. Nelson River BP 2 for
example has 3 six-pulse converters connected in series per pole giving 12 converters for the bipole
instead of the usual 4 [28]. This is unlikely to affect the reliability indices for DC switchyards as there
should still be about the same amount of DC equipment for standard HVDC schemes with one
converter per pole. However calculating the reliability indices for the HVDC converters from the
world HVDC surveys should take the number of converters per pole into consideration to ensure a
high degree of accuracy.
In order to adjust the MTTR for the offshore DC switchyard, the most common types of repair and
size of spare parts would be needed. Unfortunately the HVDC surveys do not give this level of detail.
However by analysing the outage statistics due to DC equipment failures it may be possible to get an
indication of the size of component required for the most common failures. In 2007 there were 12
DC Equipment failures causing a total of 368 outage hours of which a single failure accounted for
314 hours. Therefore the MTTR excluding the single major failure was only 4.9 hours. Such a small
repair time is likely to indicate that only small parts which were readily available if any were
required. The 314 hour outage indicates the repair required a large component. The 314 hour
Parameters 2007 2008 Average
No of schemes 19 19
Number of monopoles 9 9
Number of bipoles 10 10
No of Failures 12 18
Failure per scheme year 0.63 0.95
Failures per Switchyard 0.21 0.31
MTBF (yr) 4.8333 3.22 4.03
Repair time (hr) 367.50 386.80
MTTR (hr) 30.63 21.49 26.06
MTTF (yr) 4.83 3.22 4.02
37
outage was due to a smoothing reactor failure, which is a large component as shown in Figure 22.
Only five of the 18 failures in 2008 required a repair time in excess of 10 hours. This analysis
indicates that the high majority of DC switchyard repairs require a small spare part if any and that
the spare part is readily available. Therefore it is estimated 80% of offshore DC switchyard repair
could be carried out via helicopter/small vessel and the remaining 20% via a small vessel18
.
Furthermore since the analysis indicates the majority of spare parts are readily available it is
assumed very little time could be saved performing parallel tasks and it is therefore neglected.
Hence the MTTR for the offshore DC switchyard is the MTTR for the onshore DC switchyard plus the
offshore access time for the DC switchyard. From Table 1 the offshore access time to the DC
switchyard is estimated to be 72 hours. (0.8*48+0.2*168).
Table 47 – Estimated reliability indices for DC switchyard
DC Cable
Only source 3 contained reliability indices for cables as shown in Table 48.
Table 48 - DC Cable Failure Statistics given in Academic and Industrial Papers
The results from the latest reliability survey for cable systems were published by Cigre in 2009 [29].
The survey ended in 2005 and was for a 15 year period. At the end of 2005 approximately 7000
circuit km of submarine cable was identified as being in service.
DC-XLPE cable is the type of cable which is most likely to be used for VSC-HVDC schemes.
Unfortunately the failure rates for DC-XLPE cables were not given in the report. The failure rates for
all submarine cable types with the exception of DC self contained oil filled (SCOF) cables due to
internal faults was zero. Therefore the failure rate due to internal faults for DC-XLPE cable will be
assumed to be zero.
The average failure rate for all types of cable technology and voltage ratings due to
external/unknown damage gives a failure rate of 0.217 failures per year per 100km of circuit.
Approximately 55% of these submarine cable failures were reported to be at a location where the
cable was unprotected19
. Submarine HVDC cables are normally buried at depths of 1m to offer
protection [30]. For cable routes where direct burial is unsuitable due to the sea bed conditions (e.g.
solid rock) other protection methods such as concrete mattressing may be employed [30].
Considering that HVDC submarine cables will have installation protection, the failure rate is
calculated to be 0.096 failures per year per 100km circuit. This failure rate is nearly double the
18
Based on the assumption that an outage time of less than 10 hours for a single fault indicates a small spare
was required. In 2007, 2 of the 12 failures caused outages in excess of 10 hours while in 2008, 5 of the 18
failures caused outages in excess of 10 hours. Therefore approximately 80% of failures required a small part. 19
There were a total of 49 submarine cable failures recorded of which 4 were internal failures. 25 of the 45
(55%) external/unknown failures occurred at a location the cable was unprotected.
Componenet MTTF(yr) MTTR(hr)
Onshore DC Switchyard 4.02 26.06
Offshore DC Switchyard 4.02 98.06
Component Failure rate (occ/yr/100km) MTTR (hr)
DC Cable 0.05 1440
38
failure rate used in the DNV report. It is important to note that submarine cable failures rates are
very subjective. They are heavily influenced by many factors including, fishing activity, installation
protection method, awareness of cable routes, water depth, and hardness of the sea bed. In this
availability analysis it will be assumed the annually failure rate is 0.07 failures per 100km of circuit.
This is a reasonable assumption based on the data from the DNV report and the Cigre survey.
The offshore converter and onshore converter are located 165km apart. Therefore the total cable
length is 330km, but the circuit length/route length is assumed to be 165km20
. The average repair
time for submarine cables in the Cigre 2009 was 60 days [29] which is the same as the DNV MTTR.
Therefore this availability analysis will assume a MTTR of 60 days (1440hrs) for submarine cables.
Table 49 – Estimated Reliability Indices for Submarine Cable21
20
The questionnaire for the Cigre survey gives an example of how the circuit length is calculated. “A 5 km long
double-circuit connection with 3 phases and two cables per phase should be reported as 10 circuit km even
though it has 60 km of cable core”. Therefore from this example 330km of core cable has a circuit length of
165km.
21 The reciprocal of the failure rate was assumed to be the MTBF. MTTF=MTBF-MTTR.
Component Failure rate (occ/yr/100km) Circuit Length (km) MTTF (yr) MTTR (hr)
DC Cable 0.07 165 8.493625 1440
39
Appendix B
Reliability Concepts & Definitions
Reliability – is the probability of a device performing its purpose adequately for the period of time
intended under the operating conditions encountered [31].
Maintainability – is the probability that a component/device/system will be retained or restored to
specified working condition.
Mean Time To Failure – is the average time from the instance a component/device/system enters a
working state until a component/device/system enters a failed state. This may also be defined as the
component/device/systems uptime.
Mean Time To Repair - is the average time it takes to restore a component/device/system to a
specified working condition from the instance the component/device/system failed. This may also
be defined at the component/device/systems downtime.
Mean Time Between Failures – is the average time elapsed between a component/device/system
entering a working state until component/device/system re-enters a working state. This may also be
defined as the cycle time, which is the uptime plus the downtime.
Availability – is the probability of finding the component/device/system in the operating state at
some time into the future [31]. The availability of a component with two states can be calculated by
equation (1.8).
Uptime MTTF MTTF
AUptime Downtime MTTF MTTR MTBF
= = =+ +
(1.8)
Failure rate – is the number of times a component/device/system is expected to fail per unit of time
or the number of times a component/device/system is expected to fail per unit of time the
component/device/system is in a working condition. The failure rate in this report has two
definitions because different reliability surveys determine the failure rate from one of two methods.
Some surveys record the number of failures for a sample of components for a specified period time
without suspending time for a component upon failure, whereas other surveys suspend time when a
component enters a failed state.
As an example, consider a fictitious reliability survey which collected failure statistics from 10
transformers for 10 years during their useful life, giving 100 transformer-years of data. The survey
concluded that there were 4 failures in that time and that the average time to repair each failure
was 3 months. The number of times a transformer is expected to fail per unit of time is calculated as
follows:-
4
0.04( / )10 10
occ yrλ = =×
(1.9)
40
Equation (1.9) states that the failure rate for a transformer is 0.04 failures per year. However this
method for determining the failure rate did not stop suspend time when each transformer was in a
failed condition. The number of times the transformer is expected to fail per unit of time when the
transformer is in a working condition is calculated as follows:-
4
0.0404040( / )10 10 (4 3 )
occ yrmonth
λ = =× − ×
(1.10)
Failure rates in this report are assumed to be constant (see bath-tub curve). The reciprocal of
equation (1.9) is the MTBF whereas the reciprocal of equation (1.10) is the MTTF.
Therefore the MTTF and MTBF:-
1
24.750.0404040
MTTF years= = (1.11)
1
250.04
MTBF years= = (1.12)
24.75 3 25MTBF MTTF MTTR months years= + = + = (1.13)
Reliability surveys normally specify the failure rate and MTTR. Therefore if the reliability survey has
calculated the failure rate for a component without suspending time for failed components, the
MTTF may be obtained from equation(1.14).
1
MTTF MTTRλ
= − (1.14)
It is not always clear which method the reliability survey has used to calculate the failure rate.
However, in many cases this will not significantly impact on the calculated availability of the
component since the MTTF is typically much greater than the MTTR.
Bath-tub Curve
The lifecycle of a product can be described by three distinct phases as shown by the bath-tub curve
in Figure 23. The infant mortality phase is characterized by a high failure rate which decreases with
MTBF
MTTR
MTTF time
1
0
41
time, and could be due to manufacturing errors or improper design. Product failures in the second
region (useful life) occur purely by chance and as such the failure rate is constant. The third region
(end of life) of the bath-tub curve shows the product is wearing out.
Figure 23 – Product Lifecycle from [32]
The failures rates in this report are assumed to be constant with time (i.e. phase 1 and 3 are
neglected). This is a fair assumption since components go through an extensive testing process
before they are installed at site and it is expected that the life of the product has been designed to
be equal to or less than the useful life of the product. In other words, it is expected that
manufacturing errors or improper design issues would be discovered in the testing phase and that if
a product is expected to be in operation for 25 years the manufacture would have designed the
product to have a useful life of at least 25 years.
Mean Time to Access Offshore Platform – is the average estimated time it takes to reach an
offshore platform with a component of a particular size.
Mean Offshore Access Time – is the average estimated offshore access time for a particular
component.
Mean Time Performing Concurrent Tasks – is the average time spent performing tasks associated
with repairing a component located onshore which can be conducted in parallel with tasks related to
the MOAT for the component.
42
Example
A GIS switchbay located onshore has an estimated MTTR of 120 hours. It is estimated that 70% of
GIS failures require a small sized spare part and 30% require a medium sized spare part (see Table 1).
0.7 ( ) 0.3 ( )
0.7 48 0.3 168 84
MOAT MOTTAOP small MOTTAOP medium
MOAT hours
= × + ×= × + × =
(1.15)
In addition it is estimated that 20 hours of the MOAT is spent on administration related tasks which
can be performed in parallel with the time spent obtaining spare parts (accounted for in the onshore
MTTR).
20MTPCT hours= (1.16)
120 84 20 184offshore onshoreMTTR MTTR MOAT MTPCT hours= + − = + − = (1.17)
43
Appendix C
Cost-benefit Analysis
The full truth table for 7 variables is shown below:-
State OFNA OFNB OFNC C1 C2 Sub 6 Sub 7
1 1 1 1 1 1 1 12 1 1 1 1 1 1 03 1 1 1 1 1 0 14 1 1 1 1 1 0 05 1 1 1 1 0 1 16 1 1 1 1 0 1 07 1 1 1 1 0 0 18 1 1 1 1 0 0 09 1 1 1 0 1 1 110 1 1 1 0 1 1 011 1 1 1 0 1 0 112 1 1 1 0 1 0 013 1 1 1 0 0 1 114 1 1 1 0 0 1 015 1 1 1 0 0 0 116 1 1 1 0 0 0 017 1 1 0 1 1 1 118 1 1 0 1 1 1 019 1 1 0 1 1 0 120 1 1 0 1 1 0 021 1 1 0 1 0 1 122 1 1 0 1 0 1 023 1 1 0 1 0 0 124 1 1 0 1 0 0 025 1 1 0 0 1 1 126 1 1 0 0 1 1 027 1 1 0 0 1 0 128 1 1 0 0 1 0 029 1 1 0 0 0 1 130 1 1 0 0 0 1 031 1 1 0 0 0 0 132 1 1 0 0 0 0 033 1 0 1 1 1 1 134 1 0 1 1 1 1 035 1 0 1 1 1 0 136 1 0 1 1 1 0 037 1 0 1 1 0 1 138 1 0 1 1 0 1 039 1 0 1 1 0 0 140 1 0 1 1 0 0 041 1 0 1 0 1 1 142 1 0 1 0 1 1 043 1 0 1 0 1 0 144 1 0 1 0 1 0 045 1 0 1 0 0 1 146 1 0 1 0 0 1 047 1 0 1 0 0 0 148 1 0 1 0 0 0 049 1 0 0 1 1 1 150 1 0 0 1 1 1 051 1 0 0 1 1 0 152 1 0 0 1 1 0 053 1 0 0 1 0 1 154 1 0 0 1 0 1 055 1 0 0 1 0 0 156 1 0 0 1 0 0 057 1 0 0 0 1 1 158 1 0 0 0 1 1 059 1 0 0 0 1 0 160 1 0 0 0 1 0 061 1 0 0 0 0 1 162 1 0 0 0 0 1 063 1 0 0 0 0 0 164 1 0 0 0 0 0 0
44
65 0 1 1 1 1 1 166 0 1 1 1 1 1 067 0 1 1 1 1 0 168 0 1 1 1 1 0 069 0 1 1 1 0 1 170 0 1 1 1 0 1 071 0 1 1 1 0 0 172 0 1 1 1 0 0 073 0 1 1 0 1 1 174 0 1 1 0 1 1 075 0 1 1 0 1 0 176 0 1 1 0 1 0 077 0 1 1 0 0 1 178 0 1 1 0 0 1 079 0 1 1 0 0 0 180 0 1 1 0 0 0 081 0 1 0 1 1 1 182 0 1 0 1 1 1 083 0 1 0 1 1 0 184 0 1 0 1 1 0 085 0 1 0 1 0 1 186 0 1 0 1 0 1 087 0 1 0 1 0 0 188 0 1 0 1 0 0 089 0 1 0 0 1 1 190 0 1 0 0 1 1 091 0 1 0 0 1 0 192 0 1 0 0 1 0 093 0 1 0 0 0 1 194 0 1 0 0 0 1 095 0 1 0 0 0 0 196 0 1 0 0 0 0 097 0 0 1 1 1 1 198 0 0 1 1 1 1 099 0 0 1 1 1 0 1
100 0 0 1 1 1 0 0101 0 0 1 1 0 1 1102 0 0 1 1 0 1 0103 0 0 1 1 0 0 1104 0 0 1 1 0 0 0105 0 0 1 0 1 1 1106 0 0 1 0 1 1 0107 0 0 1 0 1 0 1108 0 0 1 0 1 0 0109 0 0 1 0 0 1 1110 0 0 1 0 0 1 0111 0 0 1 0 0 0 1112 0 0 1 0 0 0 0113 0 0 0 1 1 1 1114 0 0 0 1 1 1 0115 0 0 0 1 1 0 1116 0 0 0 1 1 0 0117 0 0 0 1 0 1 1118 0 0 0 1 0 1 0119 0 0 0 1 0 0 1120 0 0 0 1 0 0 0121 0 0 0 0 1 1 1122 0 0 0 0 1 1 0123 0 0 0 0 1 0 1124 0 0 0 0 1 0 0125 0 0 0 0 0 1 1126 0 0 0 0 0 1 0127 0 0 0 0 0 0 1128 0 0 0 0 0 0 0
45
The capacity probability table for the HVDC grid with each path to shore rated at 900MW is shown
below:-
State OFNA OFNB OFNC C1 C2 Sub 6 Sub 7 Probability Capacity1 0.98721 0.98721 0.98721 0.99310 0.99310 0.97743 0.97743 0.90654 18002 0.98721 0.98721 0.98721 0.99310 0.99310 0.97743 0.02257 0.02093 9003 0.98721 0.98721 0.98721 0.99310 0.99310 0.02257 0.97743 0.02093 9004 0.98721 0.98721 0.98721 0.99310 0.99310 0.02257 0.02257 0.00048 05 0.98721 0.98721 0.98721 0.99310 0.00690 0.97743 0.97743 0.00630 15006 0.98721 0.98721 0.98721 0.99310 0.00690 0.97743 0.02257 0.00015 9007 0.98721 0.98721 0.98721 0.99310 0.00690 0.02257 0.97743 0.00015 6008 0.98721 0.98721 0.98721 0.99310 0.00690 0.02257 0.02257 0.00000 09 0.98721 0.98721 0.98721 0.00690 0.99310 0.97743 0.97743 0.00630 150010 0.98721 0.98721 0.98721 0.00690 0.99310 0.97743 0.02257 0.00015 60011 0.98721 0.98721 0.98721 0.00690 0.99310 0.02257 0.97743 0.00015 90012 0.98721 0.98721 0.98721 0.00690 0.99310 0.02257 0.02257 0.00000 013 0.98721 0.98721 0.98721 0.00690 0.00690 0.97743 0.97743 0.00004 120014 0.98721 0.98721 0.98721 0.00690 0.00690 0.97743 0.02257 0.00000 60015 0.98721 0.98721 0.98721 0.00690 0.00690 0.02257 0.97743 0.00000 60016 0.98721 0.98721 0.98721 0.00690 0.00690 0.02257 0.02257 0.00000 017 0.98721 0.98721 0.01279 0.99310 0.99310 0.97743 0.97743 0.01174 120018 0.98721 0.98721 0.01279 0.99310 0.99310 0.97743 0.02257 0.00027 90019 0.98721 0.98721 0.01279 0.99310 0.99310 0.02257 0.97743 0.00027 90020 0.98721 0.98721 0.01279 0.99310 0.99310 0.02257 0.02257 0.00001 021 0.98721 0.98721 0.01279 0.99310 0.00690 0.97743 0.97743 0.00008 90022 0.98721 0.98721 0.01279 0.99310 0.00690 0.97743 0.02257 0.00000 90023 0.98721 0.98721 0.01279 0.99310 0.00690 0.02257 0.97743 0.00000 024 0.98721 0.98721 0.01279 0.99310 0.00690 0.02257 0.02257 0.00000 025 0.98721 0.98721 0.01279 0.00690 0.99310 0.97743 0.97743 0.00008 120026 0.98721 0.98721 0.01279 0.00690 0.99310 0.97743 0.02257 0.00000 60027 0.98721 0.98721 0.01279 0.00690 0.99310 0.02257 0.97743 0.00000 60028 0.98721 0.98721 0.01279 0.00690 0.99310 0.02257 0.02257 0.00000 029 0.98721 0.98721 0.01279 0.00690 0.00690 0.97743 0.97743 0.00000 60030 0.98721 0.98721 0.01279 0.00690 0.00690 0.97743 0.02257 0.00000 60031 0.98721 0.98721 0.01279 0.00690 0.00690 0.02257 0.97743 0.00000 032 0.98721 0.98721 0.01279 0.00690 0.00690 0.02257 0.02257 0.00000 033 0.98721 0.01279 0.98721 0.99310 0.99310 0.97743 0.97743 0.01174 120034 0.98721 0.01279 0.98721 0.99310 0.99310 0.97743 0.02257 0.00027 90035 0.98721 0.01279 0.98721 0.99310 0.99310 0.02257 0.97743 0.00027 90036 0.98721 0.01279 0.98721 0.99310 0.99310 0.02257 0.02257 0.00001 037 0.98721 0.01279 0.98721 0.99310 0.00690 0.97743 0.97743 0.00008 120038 0.98721 0.01279 0.98721 0.99310 0.00690 0.97743 0.02257 0.00000 60039 0.98721 0.01279 0.98721 0.99310 0.00690 0.02257 0.97743 0.00000 60040 0.98721 0.01279 0.98721 0.99310 0.00690 0.02257 0.02257 0.00000 041 0.98721 0.01279 0.98721 0.00690 0.99310 0.97743 0.97743 0.00008 120042 0.98721 0.01279 0.98721 0.00690 0.99310 0.97743 0.02257 0.00000 60043 0.98721 0.01279 0.98721 0.00690 0.99310 0.02257 0.97743 0.00000 60044 0.98721 0.01279 0.98721 0.00690 0.99310 0.02257 0.02257 0.00000 045 0.98721 0.01279 0.98721 0.00690 0.00690 0.97743 0.97743 0.00000 120046 0.98721 0.01279 0.98721 0.00690 0.00690 0.97743 0.02257 0.00000 60047 0.98721 0.01279 0.98721 0.00690 0.00690 0.02257 0.97743 0.00000 60048 0.98721 0.01279 0.98721 0.00690 0.00690 0.02257 0.02257 0.00000 049 0.98721 0.01279 0.01279 0.99310 0.99310 0.97743 0.97743 0.00015 60050 0.98721 0.01279 0.01279 0.99310 0.99310 0.97743 0.02257 0.00000 60051 0.98721 0.01279 0.01279 0.99310 0.99310 0.02257 0.97743 0.00000 60052 0.98721 0.01279 0.01279 0.99310 0.99310 0.02257 0.02257 0.00000 053 0.98721 0.01279 0.01279 0.99310 0.00690 0.97743 0.97743 0.00000 60054 0.98721 0.01279 0.01279 0.99310 0.00690 0.97743 0.02257 0.00000 60055 0.98721 0.01279 0.01279 0.99310 0.00690 0.02257 0.97743 0.00000 056 0.98721 0.01279 0.01279 0.99310 0.00690 0.02257 0.02257 0.00000 057 0.98721 0.01279 0.01279 0.00690 0.99310 0.97743 0.97743 0.00000 60058 0.98721 0.01279 0.01279 0.00690 0.99310 0.97743 0.02257 0.00000 60059 0.98721 0.01279 0.01279 0.00690 0.99310 0.02257 0.97743 0.00000 060 0.98721 0.01279 0.01279 0.00690 0.99310 0.02257 0.02257 0.00000 061 0.98721 0.01279 0.01279 0.00690 0.00690 0.97743 0.97743 0.00000 60062 0.98721 0.01279 0.01279 0.00690 0.00690 0.97743 0.02257 0.00000 60063 0.98721 0.01279 0.01279 0.00690 0.00690 0.02257 0.97743 0.00000 064 0.98721 0.01279 0.01279 0.00690 0.00690 0.02257 0.02257 0.00000 0
46
65 0.01279 0.98721 0.98721 0.99310 0.99310 0.97743 0.97743 0.01174 120066 0.01279 0.98721 0.98721 0.99310 0.99310 0.97743 0.02257 0.00027 90067 0.01279 0.98721 0.98721 0.99310 0.99310 0.02257 0.97743 0.00027 90068 0.01279 0.98721 0.98721 0.99310 0.99310 0.02257 0.02257 0.00001 069 0.01279 0.98721 0.98721 0.99310 0.00690 0.97743 0.97743 0.00008 120070 0.01279 0.98721 0.98721 0.99310 0.00690 0.97743 0.02257 0.00000 60071 0.01279 0.98721 0.98721 0.99310 0.00690 0.02257 0.97743 0.00000 60072 0.01279 0.98721 0.98721 0.99310 0.00690 0.02257 0.02257 0.00000 073 0.01279 0.98721 0.98721 0.00690 0.99310 0.97743 0.97743 0.00008 90074 0.01279 0.98721 0.98721 0.00690 0.99310 0.97743 0.02257 0.00000 075 0.01279 0.98721 0.98721 0.00690 0.99310 0.02257 0.97743 0.00000 90076 0.01279 0.98721 0.98721 0.00690 0.99310 0.02257 0.02257 0.00000 077 0.01279 0.98721 0.98721 0.00690 0.00690 0.97743 0.97743 0.00000 60078 0.01279 0.98721 0.98721 0.00690 0.00690 0.97743 0.02257 0.00000 079 0.01279 0.98721 0.98721 0.00690 0.00690 0.02257 0.97743 0.00000 60080 0.01279 0.98721 0.98721 0.00690 0.00690 0.02257 0.02257 0.00000 081 0.01279 0.98721 0.01279 0.99310 0.99310 0.97743 0.97743 0.00015 60082 0.01279 0.98721 0.01279 0.99310 0.99310 0.97743 0.02257 0.00000 60083 0.01279 0.98721 0.01279 0.99310 0.99310 0.02257 0.97743 0.00000 60084 0.01279 0.98721 0.01279 0.99310 0.99310 0.02257 0.02257 0.00000 085 0.01279 0.98721 0.01279 0.99310 0.00690 0.97743 0.97743 0.00000 60086 0.01279 0.98721 0.01279 0.99310 0.00690 0.97743 0.02257 0.00000 60087 0.01279 0.98721 0.01279 0.99310 0.00690 0.02257 0.97743 0.00000 088 0.01279 0.98721 0.01279 0.99310 0.00690 0.02257 0.02257 0.00000 089 0.01279 0.98721 0.01279 0.00690 0.99310 0.97743 0.97743 0.00000 60090 0.01279 0.98721 0.01279 0.00690 0.99310 0.97743 0.02257 0.00000 091 0.01279 0.98721 0.01279 0.00690 0.99310 0.02257 0.97743 0.00000 60092 0.01279 0.98721 0.01279 0.00690 0.99310 0.02257 0.02257 0.00000 093 0.01279 0.98721 0.01279 0.00690 0.00690 0.97743 0.97743 0.00000 094 0.01279 0.98721 0.01279 0.00690 0.00690 0.97743 0.02257 0.00000 095 0.01279 0.98721 0.01279 0.00690 0.00690 0.02257 0.97743 0.00000 096 0.01279 0.98721 0.01279 0.00690 0.00690 0.02257 0.02257 0.00000 097 0.01279 0.01279 0.98721 0.99310 0.99310 0.97743 0.97743 0.00015 60098 0.01279 0.01279 0.98721 0.99310 0.99310 0.97743 0.02257 0.00000 60099 0.01279 0.01279 0.98721 0.99310 0.99310 0.02257 0.97743 0.00000 600
100 0.01279 0.01279 0.98721 0.99310 0.99310 0.02257 0.02257 0.00000 0101 0.01279 0.01279 0.98721 0.99310 0.00690 0.97743 0.97743 0.00000 600102 0.01279 0.01279 0.98721 0.99310 0.00690 0.97743 0.02257 0.00000 0103 0.01279 0.01279 0.98721 0.99310 0.00690 0.02257 0.97743 0.00000 600104 0.01279 0.01279 0.98721 0.99310 0.00690 0.02257 0.02257 0.00000 0105 0.01279 0.01279 0.98721 0.00690 0.99310 0.97743 0.97743 0.00000 600106 0.01279 0.01279 0.98721 0.00690 0.99310 0.97743 0.02257 0.00000 0107 0.01279 0.01279 0.98721 0.00690 0.99310 0.02257 0.97743 0.00000 600108 0.01279 0.01279 0.98721 0.00690 0.99310 0.02257 0.02257 0.00000 0109 0.01279 0.01279 0.98721 0.00690 0.00690 0.97743 0.97743 0.00000 600110 0.01279 0.01279 0.98721 0.00690 0.00690 0.97743 0.02257 0.00000 0111 0.01279 0.01279 0.98721 0.00690 0.00690 0.02257 0.97743 0.00000 600112 0.01279 0.01279 0.98721 0.00690 0.00690 0.02257 0.02257 0.00000 0113 0.01279 0.01279 0.01279 0.99310 0.99310 0.97743 0.97743 0.00000 0114 0.01279 0.01279 0.01279 0.99310 0.99310 0.97743 0.02257 0.00000 0115 0.01279 0.01279 0.01279 0.99310 0.99310 0.02257 0.97743 0.00000 0116 0.01279 0.01279 0.01279 0.99310 0.99310 0.02257 0.02257 0.00000 0117 0.01279 0.01279 0.01279 0.99310 0.00690 0.97743 0.97743 0.00000 0118 0.01279 0.01279 0.01279 0.99310 0.00690 0.97743 0.02257 0.00000 0119 0.01279 0.01279 0.01279 0.99310 0.00690 0.02257 0.97743 0.00000 0120 0.01279 0.01279 0.01279 0.99310 0.00690 0.02257 0.02257 0.00000 0121 0.01279 0.01279 0.01279 0.00690 0.99310 0.97743 0.97743 0.00000 0122 0.01279 0.01279 0.01279 0.00690 0.99310 0.97743 0.02257 0.00000 0123 0.01279 0.01279 0.01279 0.00690 0.99310 0.02257 0.97743 0.00000 0124 0.01279 0.01279 0.01279 0.00690 0.99310 0.02257 0.02257 0.00000 0125 0.01279 0.01279 0.01279 0.00690 0.00690 0.97743 0.97743 0.00000 0126 0.01279 0.01279 0.01279 0.00690 0.00690 0.97743 0.02257 0.00000 0127 0.01279 0.01279 0.01279 0.00690 0.00690 0.02257 0.97743 0.00000 0128 0.01279 0.01279 0.01279 0.00690 0.00690 0.02257 0.02257 0.00000 0
47
Acronyms
HVDC - High Voltage Direct Current
VSC – Voltage Source Converter
LCC - Line Commutated Converter
ODIS - Offshore Development Information Statement
MMC – Multi-modular Converter
Subsystem 1 – Offshore System
Subsystem 2 – DC System
Subsystem 3 – Onshore System
MTTF – Mean time to failure
MTBF – Mean time between failures
MTTR – Mean time to repair
GIS – Gas Insulated Switchgear
DNV – Det Norske Veritas
XLPE – Cross Linked Polyethylene
SCOF – Self Contained Oil Filled
MTTAOP – Mean time to Access offshore platform
MOAT – Mean Offshore Access Time
MTPCT - Mean Time Performing Concurrent Tasks