Procedure for how to take Background MRP Run
1.0 PURPOSE :
To understand how to take MRP Run in Background for All Network Plants, using Transaction Code:-MDBT.
2.0 SCOPE:
To view Background MRP List.
3.0 METHOD:
Please follow the procedure as given below:
Transaction code MDBTMenu Path SAP menu Logistics Production MRP Planning Total
Planning MDBT--Background MRP
1
Enter T. code:- MDBT
Or Select easy access
Procedure for how to take Background MRP Run
2
Click here to Create Planning Variant
Enter Name of Planning Variant
Procedure for how to take Background MRP Run
3
Select All Selection Screens
Click Here
Procedure for how to take Background MRP Run
After filling information please click on Attributes. Here you need to do configuration for Scope of Planning (Tcode: OM0E) or you can select single plant also. In Scope of planning you take multiple plants.
4
Select Scope of Planning
Select Processing Key: NETCH, Create Purchase Req: 1, Schedule Line: 1 No Schedule Line, Create MRP List: 1 MRP List,Planning Mode: 3 Delete & recreate planning data, Scedulling: 2 Lead Time Scheduling and Capacity Planning,Planning Date: Blank
Select 001-Deterministic MRP run (Materials with MRP type 'PD')
Click Here
Procedure for how to take Background MRP Run
Here you select different option as per your requirement like protect variant.After Saving Variant you will get Variant SCM VB Saved.
we need to start our background MRP Run through Tcode- MDBT.
5
Enter Meaning Full Description
Save It (Ctrl S)
See here New Planning Variant Created.
Procedure for how to take Background MRP Run
Then go Tcode: SM37- Job Overview
6
Click here to start immediately Background MRP Run
Here you will see Planning Variant is Started
Enter User ID from which you have started Background MRP
Execute
Procedure for how to take Background MRP Run
After Successful completion of Background Job, please select the Job & then Click on Spool
7
Click on Spool
Select Background Job (RMMRP000)
Click here to see MRP List
Procedure for how to take Background MRP Run
Here you will MRP list generated through Background MRP Job. This list will show which materials are planned with Plant & their exception group.
8