+ All Categories
Home > Documents > Baker Hughes - 140-LT-1001A/B/C Leak Test Work Method ...

Baker Hughes - 140-LT-1001A/B/C Leak Test Work Method ...

Date post: 24-Feb-2022
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
104
Shell Australia Baker Hughes - 140-LT-1001A/B/C Leak Test Work Method Statement Originating Company Monadelphous Document Number 2000-410-OA-6039-00010 Revision Number 02 Discipline OA - Operations Document Type 6039 Document Status IFA – Issued for Approval Project Number Purchase Order Contractor Document ID Number 57242-7075-PRO-0002 Issue Date 13/10/2021 Author D.Munian Tag Numbers Area Code Security Classification Restricted Export Classification Number Non-US content - Non Controlled REVISION HISTORY Rev Revision Purpose Date Prepared/Reviewed by Approved by 01 Issued for Review 17/08/2021 D.Munian / Baker Hughes J.O’Brien 02 Issued for Approval 13/10/2021 D.Munian / Baker Hughes J.O’Brien
Transcript

Shell Australia

Baker Hughes - 140-LT-1001A/B/C Leak

Test Work Method Statement

Originating Company Monadelphous

Document Number 2000-410-OA-6039-00010

Revision Number 02

Discipline OA - Operations

Document Type 6039

Document Status IFA – Issued for Approval

Project Number

Purchase Order

Contractor Document ID Number 57242-7075-PRO-0002

Issue Date 13/10/2021

Author D.Munian

Tag Numbers

Area Code

Security Classification Restricted

Export Classification Number Non-US content - Non Controlled

REVISION HISTORY

Rev Revision Purpose Date Prepared/Reviewed

by Approved by

01 Issued for Review 17/08/2021 D.Munian / Baker

Hughes

J.O’Brien

02 Issued for Approval 13/10/2021 D.Munian / Baker

Hughes

J.O’Brien

Baker Hughes – 140LT-1001A/B/C Leak Test Work Method Statement

UI43134 Shell Prelude FLNG Maintenance and Modifications Services Technical Execution

Monadelphous Group Limited Division:

Maintenance and Industrial Services – Oil & Gas

Document number: 2000-410-OA-6039-00010

Contractor Document number: 57242-7075-PRO-0002

Revision: 02

Document owner: John O’Brien

Revision date: 13-Oct-21

Baker Hughes – 140LT-1001A/B/C Leak Test Work Method Statement UI43134 Shell Prelude FLNG Maintenance and Modifications Services

57241-7010-FRM-0001 Rev 02 Discipline: Technical Execution

Page 2 of 4

CONTENTS

Revision History ................................................................................................................................ 3 1 Summary ................................................................................................................................. 4 2 Roles and Responsibilities ....................................................................................................... 4 2.1 Monadelphous (MEA) ......................................................................................................... 4 2.2 Baker Hughes (PPS) ........................................................................................................... 4 2.3 Shell/Technip ...................................................................................................................... 4 3 Scope Deliverables .................................................................................................................. 4 4 Appendices .............................................................................................................................. 4

Baker Hughes – 140LT-1001A/B/C Leak Test Work Method Statement

57241-7010-FRM-0001 Rev 02 Discipline: Technical Execution

Page 3 of 4

Revision History

Revision Changes Date Prepared By

0 Issued for Review 24/09/2021 D. MUNIAN

1 Issued for Approval 13/10/2021 D. MUNIAN

Baker Hughes – 140LT-1001A/B/C Leak Test Work Method Statement

57241-7010-FRM-0001 Rev 02 Discipline: Technical Execution

Page 4 of 4

1 Summary

Monadelphous (MEA) have been engaged under 2000-010-UI43134-RFP-00269 to provide High Pressure Nitrogen Leak Testing activities on the new 140LT-1001A/B/C transmitter arrangement on V-14001 (Module 1P1). MEA have engaged Baker Hughes (BH) as subject matter experts for the works and MEA will oversee all equipment and personnel readiness. Given the critical nature of the scope Baker Hughes are to manage all Nitrogen filling activities in Darwin before loading on the Prelude Supply Vessel. The leak Test will be done during the Pitstop in October 2021 in conjunction with the Production Swivel 1 HPTL.

2 Roles and Responsibilities

2.1 Monadelphous (MEA)

- Manage Temporary Equipment Inspections.

- Manage all commercial implications of Sub-Contract with Baker Hughes (PPS).

- Onboard required personnel (including training, inductions, and relevant competencies).

- MEA Offshore Delivery Coordinator (ODC) to oversee Baker Hughes offshore.

2.2 Baker Hughes (PPS)

- Develop Safe Working Procedure and Test Packs.

- Manage any Hold Points for MEA/Shell sign off.

- Supply trained and competent personnel for onshore preparation and offshore execution.

- Coordinate bulk quantities of Nitrogen and Helium from Perth/Darwin to the Prelude Supply

Vessel and Darwin Port.

- Supply all Equipment, Materials and consumables for the Nitrogen High Pressure Leak Test of

the Swivel.

2.3 Shell/Technip

- Manage all Permit/ICCs offshore for Leak Test.

- Sign off relevant inspection points and approve Leak Test.

- Approve deliverables as listed below prior to mobilisation.

3 Scope Deliverables

- Leak Detection Method Statement (Referenced in 2000-410-OA-6039-00007 - Baker Hughes -

Helium Leak Detection Test - Production Swivel 1)

- Test Packs

- High Pressure Nitrogen Leak Test Risk Assessment.

4 Appendices

- Appendix 1: C-0382-21 - Helium Leak Detection Safe Working Procedure

- Appendix 2: TP-003 - Helium Leak Detection Test Pack - 140LT-1001A/B/C Leak Test

Baker Hughes – 140LT-1001A/B/C Leak Test Work Method Statement

57241-7010-FRM-0001 Rev 02 Discipline: Technical Execution

Appendix 1: C-0382-21 - Helium Leak Detection Safe Working Procedure

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 1 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Document Title Helium Leak Detection

Safe Working Procedure-Pitstop 2021

Document Reference Number C-0382-21 / HLD / PROC / 0001

MEA Document Number 57242-7075-PRO-0001

Shell Document Number 2000-410-OA-6039-00007

Revision Number 1

Customer Monadelphous/ Shell Australia

Project Pitstop 2021- Swivel Train 1

Location / Facility Prelude FLNG

PPS Job Number C-0382-21

Customer Work Order Number WO61594382

Signatories for Current Revision Document

Signatories Company Name Job Title Signature Date

Originator Baker Hughes Zhanar Sherkeshbaeva Project Engineer

Checked by Baker Hughes Arun Mishra Project Engineer

Approved by Baker Hughes Senthil Murugesan Operations Manager

Approved by Customer Rep. #1

Approved by Customer Rep. #2

Revision History

Revision Description Baker Hughes Customer

Rep. #1

Customer

Rep.#2

Number Date Originator Reviewed Approved Approved Approved

1 21-09-2021 For Implementation after comments ZS AM SM

O 17-08-2021 For Implementation ZS AM SM

A 04-08-2021 For client review and comment. ZS AM SM

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 2 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Document Amendment Record

Item Revision No.

Section No.

Page No. Description of Change Amended

By Date

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 3 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Contents

Project Summary ................................................................................................................... 5

Acronyms, Definitions, and Units of Measure ....................................................................... 6

Acronyms and Definitions ........................................................................................... 6

Units of Measure ........................................................................................................ 7

Scope of Work ....................................................................................................................... 8

Test Systems .............................................................................................................. 8

Test Requirements and Acceptance Criteria .............................................................. 8

Applicable Codes and Standards ............................................................................... 9

Management of Change ...................................................................................................... 10

Safety .................................................................................................................................. 11

Safety Induction, Site Orientation, and Permit to Work ............................................ 11

Risk Assessment ...................................................................................................... 12

Safety Meetings ........................................................................................................ 13

Behavioural Safety ................................................................................................... 15

General Safety .......................................................................................................... 16

Emergency Response Plans .................................................................................... 19

Test System Preparation ..................................................................................................... 22

Customer Preparatory Work ..................................................................................... 22

PPS Preparatory Work ............................................................................................. 23

Over Pressure Protection ......................................................................................... 27

Pressure Monitoring ................................................................................................. 28

6.5 Test Exclusion Zone ...................................................................................................... 29

Leak Detection Method Statements .................................................................................... 30

Equipment Preparation ............................................................................................. 31

System Preparation .................................................................................................. 34

System Pressurization .............................................................................................. 35

Helium Leak Testing ................................................................................................. 39

System Depressurization .......................................................................................... 41

Project Paperwork ............................................................................................................... 43

Resources ........................................................................................................................... 44

PPS Personnel ......................................................................................................... 44

PPS Equipment ........................................................................................................ 44

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 4 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

PPS Supplied Materials ............................................................................................ 45

Customer Supplier Items and Services .................................................................... 45

Appendix A PPS Equipment ...................................................................................................... 46

Appendix B Risk Assessments .................................................................................................. 47

Appendix C Safety Data Sheets (SDS) ..................................................................................... 48

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 5 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Project Summary

Baker Hughes PPS contracted to Monadelphous (MEA) for providing Nitrogen Services for Shell Australia on their Prelude FLNG asset, during Pitstop in October 2021.

Baker Hughes PPS will undertake Nitrogen Helium Leak test operations on the scopes identified by Customer in order to leak test all disturbed joints.

This document details the safe working practices that shall be implemented for helium leak detection operations on HP Separator Train 1 and Upstream swivel No1, and all other scopes requiring N2 Leak Testing.

Test Pack documents have also been developed containing specific instructions and checklists for each system nominated for leak testing.

The purpose of the documentation is to ensure leak testing is completed in a safe, accurate, and consistent manner.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 6 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Acronyms, Definitions, and Units of Measure

Acronyms and Definitions The following acronyms and definitions apply to this document and associated Test Packs:

Term Acronym Definition Downstream d/s Term and acronym used to describe leak locations

Design pressure PD A pressure not less than the pressure at the most severe condition of coincident internal or external pressure and temperature (minimum or maximum) expected during service.

Reference: ASME B31.3 Process Piping

Full scale deflection FSD Range on an instrument gauge

Gaseous nitrogen GN2 Acronym for gaseous nitrogen

Helium He Abbreviation for helium gas

High pressure HP Acronym for high pressure

Leak rate acceptance criteria

none Maximum allowable leak rate from a single source (expressed in units of standard cubic feet per year, scf/yr) above which a flange joint, threaded connection, or other component is deemed to be leaking and in need of repair

Leak source L# Flange joint, clamp type connector, man-way door, threaded connection, instrument tubing, or other system component capable of leaking

Liquid nitrogen LN2 Acronym for liquid nitrogen

Low pressure LP Acronym for low pressure

Maximum allowable working pressure

MAWP Maximum permissible pressure at the top of a vessel (or system) in its normal operating position at the designated coincident temperature.

MAWP is determined after construction of the vessel and is equal to or greater than the design pressure.

Reference: ASME BPVC Section VIII, Division 1

Maximum operating pressure

MOP Maximum pressure expected during normal system operation.

MOP is less than design pressure or MAWP.

Ref: API 520 Sizing, Selection, & Installation of Pressure Relieving Devices

Minimum design metal temperature

MDMT The lowest expected temperature in service at a corresponding MAWP; used for pressure vessel design purposes.

Reference: ASME BPVC, Section VIII – Division 1

Non-destructive examination / testing

NDE, NDT Method of testing and inspecting welds to ensure fabrication was completed correctly and contains no flaws

Non return valve NRV Abbreviation for non return valve (check valve)

Normal operating pressure NOP Normal pressure level for standard operating conditions.

NOP is less than MOP.

Over pressure protection system

OPPS Pneumatic or electronic device used to automatically shut down a nitrogen pump unit when a pre-set trip pressure is reached in order to protect a customer’s system from over pressurization.

Set pressure PPRV Pressure level that a pressure relief valve (PRV) or pressure safety valve (PSV) initially opens.

Note: ASME BPVC compliant PRVs have +/- 3% set pressure tolerance.

Test pressure PT Final test pressure a system is pressurized to

Trip pressure POPPS Pressure level that the PPS over pressure protection system (OPPS) is activated to automatically trip the nitrogen pump unit.

Upstream u/s Term and acronym used to describe leak locations

Witness joint W# Flange joint, threaded connection, or other potential leak source which forms part of a system but could not be tested for leakage.

Table 1: Definitions and Acronyms

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 7 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Units of Measure The following units of measurement apply to this document and associated Test Packs:

Unit of Measure Description bar / bara / barg bar / absolute / gauge

bar / min. bar per minute. Rate of pressurization or depressurization.

oC Degrees Centigrade (Celsius)

dB Decibel. Acoustic reading for ultrasonic testing.

ft Foot

ft3 Cubic feet

oF Degrees Fahrenheit

kg Kilogram

kg / min. Kilogram per minute. Mass flow rate measurement.

kHz Kilohertz. Acoustic frequency reading for ultrasonic testing.

lb Pound

lb / min. Pound per minute. Mass flow rate measurement.

l Litre

m Metre

m3 Cubic metre

Pa / kPa Pascal / kilo Pascal

psi / psia / psig Pound per square inch / absolute / gauge

scf Standard cubic feet measured at +150C (+590F) and 1 atmosphere.

scf / min. Standard cubic feet per minute. Volumetric measurement for gas flow rate.

scf / hr Standard cubic feet per hour. Volumetric measurement for gas flow rate.

scf / yr Standard cubic feet per year. Volumetric measurement for leak rate.

sm3 Standard cubic meters measured at +15oC (+590F) and 1 atmosphere.

sm3 / min. Standard cubic meters per minute. Volumetric measurement for gas flow rate.

sm3 / hr Standard cubic meters per hour. Volumetric measurement for gas flow rate.

USG US gallons

% vol. Percentage concentration by volume.

Table 2: Units of Measure

All units designated ‘standard’ are measured at 150C (+590F) and 1 atmosphere.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 8 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Scope of Work

Test Systems Table 3 lists all the systems to be leak tested. The Test Packs were developed from the scope of work defined by the customer.

Test Pack Number

Test Pack Name Test Gas Required

sm3

Design / PSV Pressure

barg

Test Pressure

barg

OPPS Trip Pressure

barg

Temp. PRV Set Pressure

barg TP 001 HP Sep Train 1 and u/s Swivel 1 32000 89 75 81.6 N/A

*TP 002 Mercury Removal Unit 15000 75 67.5 68.8 71.6

TP 003 140LT-1001A/B/C 15000 75 67.5 68.8 71.6

*TP002 - Mercury Removal Unit Leak Testing has been removed from Pitstop 2021 scope

Table 3: Test Systems

Test Requirements and Acceptance Criteria Helium leak testing operations shall be carried out in accordance with the following test parameters and acceptance criteria.

Requirement

Test Pressure Test pressure will be at system working pressure at client request.

Leak Test

Pressurize the system with a 1% helium / 99% nitrogen test gas mixture.

Check all potential leak sources identified for testing for the presence of helium gas using a calibrated helium leak detector.

Compare the quantified leak rate against the maximum allowable leak rate threshold and record the results.

Acceptance

Pressure to be maintained within 10% of the nominated test pressure for the duration of the test (top up if necessary and safe to do so).

Maximum allowable leak rate threshold from any single leak source not to exceed:

Valve glands and bonnets 50 scf / yr

Pig launcher and receiver doors 100 scf / yr

All other potential leak sources 20 scf / yr

For Swivel scope the Leak Rate has been accepted as 200 scf/ yr*

Leak rates BELOW the threshold are a PASS.

Leak rates ABOVE the threshold are a FAIL.

Each occurrence above the threshold shall be quantified and the details recorded.

All identified leak sources to be repaired and re-tested until one of the following conditions is met:

i. Leak free (no helium detected)

ii. Quantified leak rate is below the maximum allowable leak rate threshold

iii. The leak is accepted as a “Witness Joint” by the Customer Representative

*The acceptance criteria have been agreed after PS2 Swivel campaign in 2020

Table 4: Test Requirements and Acceptance Criteria

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 9 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Applicable Codes and Standards The governing documents listed in Table 5 apply to this project.

Document Title Section(s) Revision Number Date

OPS_GEN_016993 Shell Prelude “Leak Testing, Inspection All 2.1 N/A

and Monitoring of Witness Joints prior to start up”

Table 5: Applicable Codes, Standards, and Project Specifications

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 10 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Management of Change All change requests initiated by either the Customer or PPS shall be dealt with promptly on a case-by-case basis in accordance with PPS management of change protocol. Each change request shall be formally documented on a change request form with the following information:

• Detailed description of the proposed change with reasons for implementation

• Expected deliverables such as documentation, personnel, equipment, or material resources

• Location for deliverables and date required

The proposed change shall then be assessed by the PPS Project Coordinator from a HSE, technical, commercial, and contractual perspective to determine:

• Technical feasibility and compliance with standard safe working practices for the service line

• Associated safety and environmental risks, and whether acceptable to both parties

• Quantification of additional resources requirements; personnel, equipment, materials, etc.

• Potential schedule and cost impact

• Whether the change request falls within the original contracted scope of work, or if a variation order and / or contract amendment is required

The results of the assessment shall be recorded by the PPS Project Manager. The information may be passed on to the PPS Operations Manager and other subject matter experts for further review, if considered necessary or required by PPS change management protocol.

The PPS Project Coordinator has the authority to approve and implement minor technical changes only. Major technical changes shall be approved by PPS area engineering. Any commercial or contractual changes shall be approved by the PPS Operations Manager prior to providing additional resources and implementing the change.

Approved changes shall be accurately documented before implementation to ensure all parties involved clearly understand the changes made and the impact on the project. For helium leak detection, document types could include new or changed job procedures, test packs, marked drawings, risk assessments, and equipment schematics. Any new or changed job documents shall be reviewed and approved by authorized PPS and Customer Representatives prior to implementing the changes.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 11 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Safety

Safety Induction, Site Orientation, and Permit to Work

Safety Induction and Permit Training All PPS crew members shall attend the customer’s safety induction training prior to carrying out any work. Any crew members nominated for requesting and / or signing permit to work documents shall also attend the customer permit to work training course.

Site Orientation Prior to undertaking any work, the PPS Project Coordinator (preferably accompanied by the Customer Representative) shall carry out a site orientation with the crew to ensure they are familiar with the work area. The orientation shall include visual inspection and confirmation of:

• Equipment lay down area

• Test systems and adjacent areas

• Emergency muster point location(s)

• Medical Centre, emergency showers, and first aid box locations

• Permit office location

• Waste disposal areas

• Other areas relevant to the test program

During the site orientation all crew members shall carry out a risk assessment review to identify any site specific risks or hazards not covered in the standard helium leak detection risk assessment. Refer to Section 5.2: Risk Assessment for further details of this process.

Permit to Work The PPS Supervisor is responsible for ensuring no work is carried out unless a valid permit to work is in place accurately describing the activities to be undertaken. The conditions of the permit shall be reviewed and discussed with the PPS crew so that all are aware of their responsibilities.

Copies of the permit shall be posted at the work site in accordance with the permit system instructions.

The permit shall be returned to the permit office and signed off upon completion of the work activities, or revalidated if work activities are expected to extend beyond the expiry time and date.

The customer’s permit to work system must prevent conflicting work activities from taking place in the same area at the same time. However, all members of the PPS crew shall be vigilant and immediately report any observed third party work activities with the potential to affect the planned testing program.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 12 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Risk Assessment

Standard Risk Assessment Appendix B contains standard risk assessments identifying the hazards and risks associated with helium leak testing operations, and the control measures to eliminate or reduce the risks to an acceptable level.

Site Specific Risks and Hazards The PPS crew shall carry out a work site assessment to identify any site specific risks or hazards not covered in the standard helium leak detection risk assessments.

Additional risks or hazards found shall be recorded on the PPS Safe to Perform (STP) form, along with proposed control measures for elimination or mitigation.

The PPS Project Coordinator shall review the standard risk assessment and the results of the site inspection at a Toolbox Talk meeting prior to undertaking any work. The Customer Representative and any other site personnel affected by the testing program shall be invited to attend.

Personnel shall be nominated to implement each proposed control measure for newly identified risks and hazards (PPS crew member, Customer Representative, or third party as appropriate).

The risk assessment and Toolbox Talk review process shall be repeated for each test.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 13 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Safety Meetings The following safety meetings shall be held and attended by the PPS Project Coordinator and leak testing crew:

• Project Safety Meetings (scheduled by the customer)

• Toolbox Talks

• Shift Handovers

Project Safety Meetings The PPS Project Coordinator and testing crew members shall attend project safety meetings upon invitation, and adequate notice, from the Customer Representative.

Safe to Perform (STP) – Toolbox Talks Prior to carrying out any leak testing work activities the PPS Project Coordinator or Shift Supervisor shall hold an initial Toolbox Talk meeting with all PPS crew members, Customer Representatives, and third party personnel affected by the helium leak detection test program.

Topics discussed shall include:

• Review of the leak testing scope of work

• Review of the standard risk assessment documents (see Section 5.2 and Appendix B)

• Personnel roles and responsibilities

• Site specific hazards and control measures not covered in the standard risk assessment

• PPE and safety equipment requirements

• Emergency response plans in the event of an incident or accident

• Incident, accident, near miss, and hazard reporting protocols

• Management of Change protocol (see Section 4)

• Any other relevant items

Rig up of equipment at the lay down area shall then commence after obtaining a permit for the work.

Subsequent Toolbox Talk meetings shall be held prior to undertaking the following tasks:

• System preparation, pressurization, leak testing, and depressurization for EACH TEST

• Rig down of equipment after completion of the final test

Minutes of each meeting shall be recorded on the PPS Safe to Perform (STP) form. All personnel present shall sign the attendance sheet to confirm understanding and agreement with all points discussed.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 14 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Shift Handovers A verbal and written handover shall be carried out at the end of each shift between the PPS incoming and outgoing Shift Supervisors, with a walk around the work site mandatory. The PPS crew shall also be in attendance to communicate any additional information to the oncoming crew.

Points discussed shall include:

• Work completed during the shift

• Work in progress

• Work planned for completion during the next shift

• Issues to be resolved

• Customer system status (customer system’s under pressure)

• Equipment and materials status

• Permit to work status

• Barriers and warning signs in place (if any)

• Procedural or system changes made under ‘Management of Change’ protocol (see Section 4)

• Safety issues or concerns

• Any other relevant information

The above information shall be recorded on a PPS Shift Handover form. This ensures a thorough handover is carried out with no ambiguity with respect to project status. The incoming and outgoing Shift Supervisors are both required to sign and date the shift handover form prior to commencement of work activities on the new shift.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 15 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Behavioural Safety The Baker Hughes enterprise HSE management system requires PPS personnel to pro-actively carry out visual inspections of their work areas and report any observed hazards, unsafe conditions, near misses, incidents or accidents. A summary of these policies is provided below.

Step Back 5 x 5 Baker Hughes Step Back 5 x 5 review is a self-evaluation risk management method that makes personnel stop and think about the task they are about to perform. Personnel are required to:

• Visually inspect the work area and surroundings

• Verify hazard controls have been implemented for the task to be carried out

• Identify any additional hazards and apply appropriate controls

• Record safety observations on the Baker Hughes SOS (Safety Observation System) card

• Stop work if appropriate controls cannot be applied (see below)

Observation & Intervention Card - (OIC) PPS personnel shall use Shell Observation and Intervention card to record any hazards observed during the Step Back 5 x 5 review. The card shall also be used to record Stop Work events.

OIC cards help communicate and report hazards before becoming potential incidents.

OIC cards are to be used as follows:

• Recognize and acknowledge others when we see a safe act or positive behavior

• Report any unsafe act or condition or near miss

• Complete and submit to PPS Supervisor or HSSE advisor

The PPS Project Coordinator shall collect the cards from crew members, review the data, and implement appropriate controls to rectify the hazardous condition reported.

Stop Work The Baker Hughes Stop Work policy empowers every individual with the responsibility and authority to stop work at any time when an observed unsafe condition or act might result in a HSE incident. The stop work protocol shall be explained to personnel during the site induction, and reiterated during Toolbox Talks.

Near Miss and Incident / Accident Reporting Any observed near miss, incident, or accident shall be reported and recorded in compliance with the customer’s and Baker Hughes reporting procedures.

In an emergency situation, PPS personnel shall follow the emergency response plan in Section 5.6 of this document. The plan shall be reviewed with personnel during a Toolbox Talk prior to commencing operations.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 16 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

General Safety The safe work practices detailed bellow shall be followed throughout the project.

Personal Protective Equipment (PPE) The PPS crew shall wear the following PPE as a minimum for helium leak testing operations:

• Safety hard hat

• Safety glasses goggles or full face shield for liquid nitrogen transfer operations

• Ear protectors operating mechanical equipment and / or high noise level areas

• Flame retardant coveralls full arm length

• Industrial / leather gloves insulated gloves for liquid nitrogen operations

• Steel toe cap boots

• Personal gas monitors Oxygen

• COVID-19 PPE face masks (if required)

The PPS Project Coordinator shall review customer safety rules, site conditions, and safety data sheets (SDS) for all materials being handled to ensure the above PPE is adequate for the planned work activities. Data sheets shall be posted at the work site and / or test cabin for reference by the crew. Any additional PPE requirements identified shall be issued to the crew.

The PPS Project Coordinator shall determine whether inclement weather requires the use of insulated coveralls, zero hoods, wet weather clothing, or other specialty PPE.

Manual Handling Cranes and other lifting aids shall be used wherever possible to eliminate manual lifts of heavy, large and awkward shaped objects. However, manual lifting shall still be required of various equipment items.

All PPS crew members have attended training for correct manual handling techniques. All manual handling lifts shall be assessed before carrying them out, and help obtained from other crew members if an equipment item is considered too heavy, large, or awkward shaped for a single person. Equipment items that fall into this category for leak testing operations include helium gas booster pumps and over pressure protection systems (OPPS). The hazards associated with lifting these items are documented in the risk assessments contained in Appendix B, and shall be reviewed as part of a Toolbox Talk meeting prior to carrying out equipment rig up or rig down activities.

The project may also require crew members to carry out manual lifts of other heavy, large, or awkward shaped items for non-standard work activities. The PPS Shift Supervisor shall carry out an assessment of each lift, then discuss potential hazards and correct lifting techniques with the relevant crew members before the work is carried out.

Hand Tool Safety Hand tools are an integral part of the helium leak detection equipment rig up. Improper maintenance, selection, and use of hand tools can easily cause first aid or more serious injuries.

All PPS crew members have attended practical training in the correct selection, use, and maintenance of hand tools.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 17 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Working at Height Helium leak detection operations often require personnel to work at height. The PPS Shift Supervisor is responsible for identifying and assessing such activities and ensuring the appropriate safety resources are provided to the crew members.

Only certified scaffolding and / or ladders erected by qualified scaffolding personnel shall be used to access high points. Harnesses and lanyards may also be required. All safety equipment used shall conform to site standards and have appropriate certification.

Lighting The Customer Representative is responsible for ensuring adequate lighting for safe working is provided at both the PPS equipment lay down area and at all customer systems nominated for testing. The PPS Supervisor shall assess the lighting provided. A request may be made for additional lighting in critical areas if the standard lighting is considered to be unsafe for working.

Confined Spaces Confined spaces can be lethal, particularly when inert gases such as helium and nitrogen are being used at the work site. Potential inert gas releases include:

• Accidental release from storage (operator error)

• Loss of containment (equipment failure)

• Leaking joints under pressure

The PPS Shift Supervisor and Customer Representative are responsible for identifying any confined spaces within close proximity of the equipment lay down area or test areas. Any work activities involving entry into a confined space shall be done in strict accordance with site permit to work conditions and safety rules. Gas checks shall be carried out to ensure oxygen levels are safe for entry. Personal oxygen monitors shall be used. Emergency breathing apparatus (B.A. sets) shall be available at the confined space work area. A buddy system is also required. Under no circumstances shall personnel enter a confined space if the potential exists for nitrogen / helium gas to be present. If in doubt STOP the job.

Radio Communications Radio communications are a critical part of any leak detection process, particularly during system pressurization. Radios shall be provided in sufficient quantities to ensure all personnel associated with the testing program, including those nominated for patrolling the test exclusion zone perimeter, are in constant communication during the job. A clear, uninterrupted communication line on a dedicated channel shall be open at all times between the nitrogen pump Operator and PPS Shift Supervisor. If the equipment operator loses contact with the Supervisor at any time during the pressurising and leak testing phases, or there is third party interference on the channel, operations shall immediately be stopped and the communication problem investigated. Testing shall only recommence once communication lines are re-established.

Correct radio protocol shall be discussed at a Toolbox Talk meeting prior to carrying out pressurization and testing operations. The protocol requires any instructions issued by a PPS Supervisor to be repeated back by the recipient to acknowledge receipt and confirm their understanding.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 18 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Housekeeping Poor housekeeping is a frequent, and avoidable, cause of first aid or more serious injuries in the oil and gas industry. Good housekeeping shall be maintained at all times:

• Hoses / temporary piping not rigged up for test shall be placed in the equipment stores area

• Valves, fittings, and equipment spares shall be placed in dedicated storage bins

• Tools shall be placed in a secure toolbox within the stores area

• Instrumentation and PRVs shall be placed in dedicated transport cases in the stores area

• Helium leak detectors and ancillary leak detection equipment shall be placed in dedicated transport cases in the test cabin when not set up for testing

• PPS crew members shall check the equipment lay down area and test system areas on a regular basis to ensure they remain clean and tidy

Waste Material Any waste materials generated by PPS during the course of the leak testing program shall be disposed of at the appropriate site waste facility provided by the customer. Potential waste materials generated include:

• Used fuel, oil, and air filters for the nitrogen pump unit

• Used oil, grease, and lubricants containers for the nitrogen pump unit

• Used barrier tape, leak detection tape, and PTFE tape

• General refuse

Inclement Weather Inclement weather may create dangerous working conditions for personnel and potentially interfere with the leak testing operations. Examples are:

• Severe rain, lightning, wind, ice, or snow can create slippery and dangerous working conditions, particularly when working at height

• Prolonged exposure of personnel to high ambient temperatures can cause dehydration, heat exhaustion, or heat stroke

• High ambient temperatures may cause expansion of the test gas and potential over-pressurization of a system

• Cold ambient temperatures may cause system components nominated for testing to enter a brittle temperature range

The PPS Shift Supervisor and Customer Representative shall monitor weather conditions and assess whether it is practical and safe for personnel to work if inclement conditions occur. If site conditions become too difficult or dangerous to work the testing shall be postponed until safe to continue.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 19 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Emergency Response Plans PPS personnel shall comply with the following emergency response plans in the event of an incident at the work site. All incidents shall be investigated and reported in compliance with Baker Hughes and Customer site policy requirements.

Personnel shall complete the actions stated only if safe to do so.

Site Emergency Response or Emergency Stop Instruction

1. Shut down the pump unit immediately, isolate, and depressurize.

2. Close the test gas injection point, if safe to do so.

Site Emergency: Proceed to the nearest up-wind muster point and await further instruction, as per site protocol.

Emergency Stop: Report to the PPS Supervisor who issued the emergency stop instruction.

Liquid Nitrogen Hose / Fitting Leak or Failure

1. Shut down the pump unit immediately (if in use at time of incident).

2. Isolate the liquid nitrogen supply, if safe to do so. Ensure personal oxygen alarms are worn.

3. Cordon off the affected area, taking note of the wind direction.

4. Apply a water hose to the liquid nitrogen, if the quantity of material is large enough to potentially damage the area it was spilled upon.

5. Quarantine the defective equipment.

6. Inform the PPS Supervisor about the spill.

Liquid Nitrogen Tank Damage

A large volume of pressurized liquid nitrogen could potentially be released in an uncontrolled manner if tank damage is severe. The following protocol should only be followed if damage to the tank is minor, and it is safe for personnel to approach the tank.

1. Cordon off the area surrounding the tank.

2. Visually assess the tank damage. Ensure personal oxygen alarms are worn.

3. Verify the quantity of liquid nitrogen remaining in the tank.

4. Remove the liquid nitrogen from the tank, using one of the two following methods:

• Transfer the liquid nitrogen to a second tank of the same capacity, if available and empty

• Vaporize and vent the liquid nitrogen directly to atmosphere at a safe location

5. Verify the liquid nitrogen tank is fully de-inventoried and depressurized.

6. Quarantine the tank and await further instruction from the PPS Supervisor.

Unconscious Person – Oxygen Deficiency / Asphyxiation

1. Raise the site alarm and direct the emergency response team to the injured crew member:

• DO NOT enter the potentially oxygen deficient area

• Only qualified emergency response personnel with correct PPE to enter the area and assist the injured person

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 20 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Cryogenic Burn or Frostbite

1. Verify symptoms and affected area:

• Skin contacted by cryogenic surface or fluid

• Pins and needles sensation followed by diminishing pain

• Hard skin with waxy and discoloured appearance

• Shock, if burn is severe

2. Escort the injured crew member promptly to the site medical facility or other safe area.

3. Flush affected area immediately and continuously with tepid water to prevent further tissue damage.

4. Cover affected area with a sterile protective dressing.

5. Move the injured crew member to a warm recovery area.

Hypothermia

1. Verify symptoms:

• Pale skin and bluing lips

• Shivering

• Slow pulse and respiratory rate

• Irrational behaviour

2. Escort the injured crew member promptly to the site medical facility or other safe area.

3. Remove any wet clothing and wrap in dry clothing and / or blankets.

4. Move the injured crew member to a warm recovery area and slowly restore their body temperature.

Pump Hydraulic Hose / Fitting Leak or Failure

1. Shut down the pump unit immediately, isolate, and depressurize.

2. Contain and clean up the spilt hydraulic oil using the spill kit.

• Ensure correct PPE is worn in compliance with SDS requirements.

3. Remove the defective components and replace with correctly specified new components (certified where applicable).

4. Service test the pump to verify the integrity of the new components fitted.

5. Obtain approval from the PPS Supervisor and Customer Representative to start operations again.

Hydraulic Oil Skin Exposure

1. Proceed to the nearest washroom facility and remove any heavily fouled clothing items (coveralls, gloves, etc.).

2. Wash the affected skin areas until free from hydraulic oil.

• Proceed to the site first aid facility for further treatment and medical advice if necessary

3. Replace the fouled clothing items with clean clothing.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 21 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Hydraulic Oil Eye Exposure

1. Escort the affected crew member immediately to the nearest eye wash station.

2. Activate the eye wash station and flush the eyes for a minimum of 15-minutes.

• Tilt head forward until the spray fully impinges the eyes

• Hold the eye lids apart while irrigating the eyes

3. Proceed to the site first aid facility for further treatment and medical advice.

Diesel Spill 1. Shut down the pump unit immediately, isolate, and depressurize (if in use at time of spill).

2. Cordon off the affected area.

3. Contain and clean up the spilt diesel using the spill kit.

• Ensure correct PPE is worn in compliance with SDS requirements.

4. Wash the area with large amounts of fresh water.

5. Dispose of the used spill kit at an approved site waste facility.

6. Inform the PPS Supervisor about the spill event.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 22 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Test System Preparation Test system preparation is a critical aspect of a helium leak testing project that must be competed accurately to ensure safe and efficient leak testing operations.

Customer Preparatory Work Before a system is prepared for testing by the PPS crew, the Customer Representative shall confirm the following activities are complete:

i. The system is mechanically complete, visually checked, all punch list items closed out, and released for testing

ii. All welds have successfully passed NDE / NDT in compliance with the applicable design code

iii. Post weld heat treatment is complete in compliance with the relevant design code

iv. All pipe supports, anchors, and associated weld attachments are complete

v. All gaskets, nuts, and bolts are correctly specified, and joints are correctly assembled

vi. All bolted flange joints, hub clamps, and other mechanical joint types are correctly tightened using torque or tension techniques specified by the applicable design code

vii. All threaded connections, compression fittings, and instrumentation that will be exposed to pressure have been checked to verify joints are correctly made up and tightened (compatible thread types, sufficient threads engaged, correctly tightened).

viii. All system components nominated for helium leak testing have successfully passed a hydrostatic strength test in accordance with the applicable design code. Alternatively, water sensitive systems have successfully passed a code compliant pneumatic strength test.

ix. Calibrated, certified system PSVs and / or bursting discs are installed as per normal plant design. Set pressure has been confirmed by visual check of tags and certification review.

x. System internal cleanliness has been verified, and no residual water or moisture is present

xi. Flange joints, threaded connections, and other potential leak sources within test limit boundaries are accessible to allow helium leak test examination. Cladding and insulation has been removed where necessary.

xii. Minimum design metal temperature (MDMT) has been confirmed for all components, and ambient temperature conditions shall be at least 17oC (30oF) above the component with the highest MDMT value for the duration of the test.

xiii. Certified scaffolding and ladders have been erected for safe access to system high points

xiv. Adequate lighting has been provided for nighttime working

xv. Actuated valves detailed on the PPS Actuated Valve Checklist have been isolated in the positions required and their motive energy sources disconnected

xvi. Action items detailed on the following PPS forms are completed (where applicable):

• PPS Mechanical Preparation

A PPS Mechanical Reinstatement form may also be issued to the customer upon completion of testing (where applicable).

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 23 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

PPS Preparatory Work

Test Pack Document A Test Pack document has been developed for each system in accordance with the drawing key, colour coding, and tagging protocol described in this section. The PPS crew shall prepare each system for testing in compliance with the marked drawings, system alignment checklists, and other work instructions contained within the Test Pack. A standard Test Pack contains the following information:

Section Title Content

N/A Cover Sheet Signature page for Test Pack review and approval process.

N/A Document Amendment Record Record of document revisions made.

A Test Pack Information • System design pressure, customer PSV set pressure, and normal operating pressure (N.O.P.)

• Incremental and final test pressures

• OPPS trip pressure

• Temporary PRV set pressure

• System free volume and test gas requirements

• Test gas injection point(s)

• Pressure monitoring points

• Depressurization (vent) points

• Maximum allowable leak rate thresholds

• Special requirements for rotating equipment (if applicable)

B Marked Drawings Test system PEFs marked up in accordance with PPS standard colour coding and tagging key. Used in conjunction with system alignment checklists to confirm the system is correctly prepared for test.

C Test System Checklists Checklists used to ensure the customer system is correctly prepared for pressurization and testing, and for safe depressurization and reinstatement.

• Punch List / Mechanical Preparation / Bill of Materials

• Test Limit Isolations Checklist

• Safety Components Checklist

• Actuated Valve Checklist

• System Depressurization Checklist

D Inspection and Test Plan (ITP) ITP used to ensure safety critical steps are completed for system preparation, testing, depressurization, and reinstatement phases.

Contents of the ITP discussed during Toolbox Talks.

E Test Results • Leak Description Report

• Leak Detection Completion Certificate

• Pressure Test Charts (or data)

• Witness Joint Register

• Other test specific forms, as required

Table 6: Test Pack Content

Test Limit Isolations Checklist

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 24 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

The PPS Test Limit Isolations Checklist identifies all test system boundaries (limits) that must be positively isolated or in the closed position prior to system pressurization, to safely contain the test gas. All test limit isolations are tagged T# and numbered sequentially. Each test limit component is listed on the checklist and cross referenced on the Test Pack P&IDs (colour coded red).

Safety Components Checklist The PPS Safety Components Checklist identifies any components, either within or outside test boundaries (limits), that have the potential to change position, prevent complete system pressurization, or cause a trapped pressure condition post-depressurization. Each identified safety component must be secured in the open position or checked for correct orientation. All safety components are tagged S# and numbered sequentially. Each component is listed on the checklist and cross referenced on the Test Pack P&IDs (colour coded green). Component types listed include:

• Actuated valves

• Check valves (non-return valves)

• Spectacle blinds and ring spacers

• Maintenance valves upstream or downstream of system PSVs, or temporarily installed PRV

• Customer isolation valves between the main test system and PPS test gas injection manifold, or OPPS pressure sensing manifold

• Critical manual valves on vent paths (double block and bleed) or system depressurization paths

• Components removed to provide direct vent paths to atmosphere (double block and bleed)

In addition to the safety components listed, all manually operated valves within test limit boundaries shall be visually checked prior to system pressurization to ensure in the open position. These valves are (typically) not listed on the checklist.

Actuated Valve Checklist The PPS Actuated Valve Checklist lists all actuated valves associated with the test (and identified on the PPS Test Limit Isolations or PPS Safety Components Checklists). The checklist is issued to the Customer Representative in advance of testing, along with the PPS Punch List, to allow advance preparation of the actuated valves by the customer’s Instrument Technician.

System Depressurization Checklist The PPS System Depressurization Checklist describes the sequential steps taken to ensure the system is completely depressurized after the system has been leak tested. The checklist identifies:

• Depressurization points to be used (location and sequence of each)

• Pressure monitoring points to be checked on the test system and vent path

• Maximum allowable depressurization rate

• Maximum allowable pressure in the vent path system

Checklist Signatories

The above mentioned checklists all require co-signature by the PPS Project Coordinator/ Shift Supervisor and Customer Representative.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 25 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Marked PEFs Key, Colour Coding, and Tagging Each Test Pack document contains a set of marked P&IDs defining the test system and cross referencing the system alignment checklists. Information contained within the marked drawings includes:

• Test gas injection manifold installation point(s)

• OPPS pressure sensing point

• Test pressure monitoring points

• Temporary PRV installation point(s)

• Depressurization points

• Vent path pressure monitoring points

• Test system check valve locations

• High pressure / low pressure piping interfaces

• Jumper hoses (if used)

• Trapped pressure sections (piping that cannot be fully depressurized post-test due to plant configuration)

The drawings are marked in accordance with the colour coding and P&ID key shown in Tables 7 and 8.

Test Limit Isolation (closed)

Safety Component (open or correctly orientated)

Test System (pressurized)

Vent Path (open to atmosphere)

Table 7: P&ID Colour Coding

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 26 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Symbol Description

T1

Test Limit Isolation (closed)

S1

Safety Component (open or correctly orientated)

L1

Leak Number

UL1

Ultrasonic Leak Number

W1

Witness Joint Number

SP1

Sample Point

Check valve (non-return valve)

Point shows direction of process flow / valve orientation.

HP LP

#

Piping specification change:

HP denotes high pressure

LP denotes low pressure

Used for highlighting:

Injection point #

Over pressure protection system (OPPS)

Temporary pressure relief valve (PRV#)

Test pressure monitoring point #

Pressure recorder

Depressurization point #

Vent path pressure monitoring point #

Caution: check valve or Caution: NRV

Jumper hose #

Trapped pressure #

Other relevant notations

Table 8: P&ID Key

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 27 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Over Pressure Protection Each test system is protected against over pressurization using a minimum of two devices:

• PPS Over Pressure Protection System (OPPS)

• Customer PSV

The OPPS takes a pressure signal from the customer system and automatically shuts down the pressurizing pump unit if a pre-set trip pressure is reached. The OPPS pressure sensor shall be installed at a non-isolatable, upstream location close to the test gas injection point (i.e. where the highest pressure is most likely to occur). The OPPS pressure sensing point is clearly identified in each Test Pack.

If a customer PSV is not present or available for a test, or additional over pressure protection is considered necessary, a temporary PRV(s) shall be installed at a non-isolatable, upstream location that provides full system protection. The PRV installation point(s) is clearly identified in each Test Pack. The PRV discharge nozzle shall be orientated to a safe location.

Each PRV provided shall be capable (at the set pressure) of relieving test gas at a flow rate greater than the pressurizing pump’s maximum flow rate capability. For lower pressure tests this approach may result in the requirement for a large diameter PRV. Installing a large diameter PRV may not be practical, and a suitable connection point may not exist. In this situation one of two options shall be implemented:

i. Install multiple smaller PRVs with the same set pressure to cumulatively achieve the required total flow rate. Each PRV shall be clearly numbered and identified in the Test Pack document.

ii. Install a single, smaller PRV at the nominated set pressure and set a maximum allowable pump rate below the PRV flow rate capability. The maximum allowable pump rate shall be recorded in the Test Pack document and communicated during a Toolbox Talk meeting prior to testing operations.

PPS standard practice is to test systems to 90% of the system design pressure or PSV set pressure.

OPPS trip pressure and temporary PRV set pressure are quantified using the rules in Table 9.

At client request system will be tested at working pressure 75 barg

System Design Pressure, PD or PSV Set Pressure

Test Pressure, PT

OPPS Trip Pressure

Temporary PRV Set Pressure

Less than or equal to 5 barg (75 psig) Discussed and agreed with the customer on a test by test basis

Greater than 5 barg (75 psig) 90% PSV / PD 102% PT 106% PT

Table 9: PPS Standard Rules for Test Pressure, OPPS, and Temporary PRV

For systems with PSV set pressure or design pressure in the range 5 barg (75 psig) or less, the margins between the above mentioned parameters are very small. The test pressure, OPPS trip pressure, and temporary PRV set pressure shall be discussed and agreed during the engineering phase for these tests.

PRV Set Pressure Tolerance ASME BPVC compliant, certified PRVs have an allowable set pressure tolerance of +/-3% under the code rules. These types of PRVs are commonly used in the industry and by the PPS group. Whilst the possibility exists that the PRVs may open at the lower end of their allowable tolerance range (+/-3%), it should not interfere with the test based upon the PPS test pressure rule.

Note: It is mandatory to install a temporary PRV for a system pressurized using an air driven gas booster pump as the OPPS automated trip is not used with this pump type.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 28 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Pressure Monitoring

Test Pressure Monitoring

The minimum test pressure monitoring requirement for each test system is:

• 1 x pressure gauge installed directly onto the test system

• 1 x pressure gauge displaying test system pressure at the pressurizing pump location

• 1 x pressure recorder

• Standard customer instrumentation on the test system

Pressure instrumentation may be analog, digital, or a combination of both. All instrumentation shall be calibrated and certified to a recognized industry standard. Analog instrumentation shall have a pressure range that falls within 50% - 90% full scale deflection (FSD) at final test pressure. Analog pressure chart recorder clocks shall be sized to match the anticipated test duration.

The test pressure monitoring instrumentation shall be installed at a non-isolatable, upstream location that provides a full system pressure reading for the pressurization, testing, and depressurization phases. Each test pressure monitoring installation point is clearly identified in the Test Pack document.

Multiple test pressure monitoring points shall be used for test systems containing single direction components such as check valves (non-return valves) to provide pressure indication upstream and downstream (where possible). This enables the test crew to check and ensure the complete system is pressurized for leak testing. The crew can also check and ensure the system is fully depressurized post testing, eliminating potential trapped pressure incidents.

The pressure instrument at the pump location enables the pump operator to continuously monitor the test pressure remotely from the test system, and react immediately to any anomalies that may occur.

Vent Path Pressure Monitoring Upon completion of leak testing each test system is depressurized to atmospheric pressure (or a residual pressure agreed with the customer). The vent path route for depressurization often has a lower pressure rating than the system under test e.g. closed drains or adjacent process system.

The depressurization rate of the test system shall be carefully monitored and controlled to ensure the vent path system is not over pressurized.

Customer system instrumentation permanently installed on the vent path route shall be used to monitor the vent path pressure, if available. If the customer system instrumentation is not available, or if additional pressure monitoring is required, PPS shall install temporary pressure instrumentation onto the vent path for pressure monitoring and recording.

The vent path pressure monitoring points are identified in the Test Pack document and clearly marked on the Test Pack drawings (see Table 8 for notation used)

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 29 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

6.5 Test Exclusion Zone After a system has been prepared for test and is ready for pressurization, barriers shall be placed around the perimeter of the agreed test exclusion zone. Warning signs shall be posted at access points and regular intervals stating:

Figure 1: Warning Sign

The test exclusion zone shall be checked for personnel immediately prior to system pressurization. Any unauthorized personnel shall be escorted outside of the barriers. A site radio announcement shall be made advising that pressurization and testing is due to commence and all barriers and warning signs must be observed.

For Shell Prelude Pitstop 2021 Pressure Testing Warning signage to include Radio Channel to be contacted for more information.

PPS personnel nominated for monitoring the perimeter shall be identified during the Toolbox Talk meeting prior to system pressurization. The test exclusion zone perimeter shall be patrolled at all times when the system is under pressure.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 30 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Leak Detection Method Statements This section contains the following standard method statements for leak testing operations:

7.1 Equipment Preparation

7.2 Test System Preparation

7.3 System Pressurization

7.4 Helium Leak Testing

7.5 System Depressurization

Additional Testing

The method statements listed above describe the preparation, pressurization, leak testing, and depressurization activities applied to each test system.

A system shall be prepared, pressurized, and tested again if:

A test is abandoned during the incremental pressure stages due to a gross leak(s) that cannot be safely isolated to allow continuation of pressurization

An initial helium leak test is completed, the system is depressurized, and all identified leaks are repaired

After completing repair work the system shall be prepared for test again, and a helium leak test carried out, as if being pressurized for the first time.

Additional testing shall continue until the system is leak free, or all potential / nominated leak sources have leak rates below the allowable threshold limit. Alternatively, a leak may be accepted by the customer as a witness joint (customer decision).

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 31 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Equipment Preparation The following activities shall be completed to prepare leak detection equipment for the testing program:

Permit to Work and Toolbox Talk

1. Obtain a current, valid permit for equipment rig up.

2. Hold a Toolbox Talk meeting with the PPS crew to discuss the risks, hazards, and control measures for safe equipment rig up. Invite other personnel affected by the work to attend also.

Position Equipment

3. Position the equipment spread at the designated lay down area:

3.1 Position the nitrogen pump unit and nitrogen tanks into the liquid nitrogen spill bund (berm).

3.2 Position the test cabin and helium gas racks adjacent to the bund area.

3.3 Ensure a charged water hose, spill kits, and fire extinguishers are available.

3.4 Earth all equipment items with spark potential (customer activity, qualified electrician).

3.5 Erect barriers and post warning signs around the circumference of the lay down area.

Utilities

4. Arrange the following utilities (customer supplied) for the nitrogen pump unit, gas booster pump, OPPS, and test cabin:

• Air 7 barg (100 psig), 4 sm3 / min (140 scf / min)

• Water Charged water hose at pump location.

• Electricity 3 Phase 32 Amp min

• Diesel 800 ltr

Inspection

5. Inspect all main equipment items to ensure no damage or loosening occurred during transit. Red tag, quarantine, and repair or replace any equipment items failing inspection.

5.1 Inspect the nitrogen pump unit and verify:

Engine oil filter, hydraulic oil filter, fuel filter, and air filter are in good condition and correctly fitted.

Pressure retaining components are tight.

A check valve is fitted to the pump discharge piping.

A calibrated, certified PRV of the correct set pressure and flow rate capability is fitted on the pump discharge to protect the unit against over pressurization.

An additional PRV of appropriate set pressure and flow rate is fitted to the pump discharge manifold to protect the temporary hose / piping used for gas transfer.

o Not required if the hose / piping is rated at or above the pumps maximum discharge pressure capability.

Note: Only certified rigging personnel are to position equipment.

Under no circumstances shall personnel walk under equipment suspended by a crane or other lifting apparatus.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 32 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

5.2 Inspect all liquid nitrogen storage tanks to ensure no damage occurred during transit:

Ensure tank PRVs are correctly aligned (not isolated).

Depressurize the tank to condition the liquid nitrogen in readiness for testing.

5.3 Check all helium gas racks for signs of damage. Pay particular attention to the discharge manifold and isolation valves.

5.4 Unload ancillary equipment from the test cabin storage area (e.g. hoses / piping, fittings kit, tool kit, helium gas booster pump, OPPS, etc.).

Take care when opening container doors as items may have moved during transit.

Arrange a crane or other lifting aids for movement of heavy equipment items.

Unavoidable manual lifts of heavy, large, or awkward shaped equipment items to be assessed for correct manual handling techniques. Lifts to be carried out by two (or more) personnel.

5.5 Carry out a visual inspection and certification audit of ancillary equipment items:

Verify the pressure retaining components of the helium gas booster and the OPPS unit are tight (no loosening during transit).

Inspect hoses and hose connectors for signs of damage.

Inspect instrumentation for signs of damage.

Quarantine any damaged items. Arrange replacements (if needed).

Rig Up and Function Test

6. Rig up and function test the equipment spread in preparation for helium leak testing operations:

6.1 Prepare the test cabin:

Ensure the main door and the emergency exit door are unobstructed.

Verify the air supply, power supply, and electrical sockets.

Function test the alarms and trips as per standard practice (if fitted).

Ensure a fire extinguisher is readily available.

Ensure the workspace is clean and tidy. Store any loose items.

6.2 Charge the radio batteries. Function test the radios on the dedicated channel (if available) to ensure working correctly.

6.3 Rig up the helium leak detector and ancillary leak testing equipment in the cabin:

Unpack all items and inspect for signs of damage during transit. Quarantine any damaged items and arrange replacements.

Set up the leak detector and calibration system in accordance with standard practice.

Use a bladder to take a gas sample from the 1% helium / 99% nitrogen gas bottle.

Calibrate the leak detector against the sample and function test to ensure responding correctly to the presence of helium gas.

Shut down the leak detection equipment.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 33 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

6.5 Rig up the air driven helium gas booster pump (as per the schematic in Appendix A):

Connect high pressure hosing between;

o Helium gas bottle rack discharge nozzle and the booster pump inlet port.

o Booster pump discharge port and the mixing tee on the nitrogen pump discharge.

Verify the hosing is carefully routed and restraint devices are used.

Connect the air supply and function test the booster pump.

6.6 Carefully route and secure the test gas injection line (hose or iron) from the nitrogen pump discharge to the nominated test gas injection point on the first test system:

Avoid access points.

Verify restraint devices are fitted and the line is secured at regular intervals.

Prepare the test gas injection manifold (check valve and double block and bleed valve configuration). Refer to Appendix C for details.

DO NOT connect the injection line to the customer system at this time.

6.7 Rig up and function test the PPS OPPS in accordance with standard practice:

Verify pressure instrumentation is of appropriate range (50% - 90% FSD at test pressure for analog instruments)

Set the OPPS trip pressure in accordance with the first Test Pack nominated for testing.

Verify the nitrogen pump unit trips at the nominated trip pressure.

6.8 Carefully route and secure the pressure sensing line from the OPPS to the nominated pressure sensing point on the first test system:

Flexible hose for pneumatic OPPS; pressure transducer and cable for electronic OPPS.

Prepare the OPPS pressure sensing point connection manifold (double block and bleed valve configuration). Refer to Appendix A for details.

DO NOT connect the pressure sensing line to the customer system at this time.

6.9 Verify the certification of all equipment used in the rig up:

All components shall be correctly rated for the test pressure and have valid certification.

Any items that are damaged, not certified, or of inadequate pressure rating shall be quarantined and replaced immediately.

Make copies of instrumentation certificates in readiness for the final leak test report.

6.10 Invite the Customer Representative to carry out an equipment inspection and certification audit. Remove and replace any items failing the inspection.

6.11 Cool down, prime, and function test the nitrogen pump unit in accordance with standard practice to ensure working correctly:

Invite the customer representative to witness the function test.

Verify the over pressure switch is correctly set and functioning.

Repeat the OPPS function test.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 34 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

System Preparation

The following activities shall be carried out to prepare each system for pressurization and leak testing:

1. Obtain customer verification that the system is mechanically complete (see Section 6.1) and action items identified on the following PPS forms are closed out:

Punch List

Mechanical Preparation

Actuated Valve Checklist

2. Obtain a current, valid permit to work for system preparation.

3. Line out the test system in accordance with the following Test Pack documents:

Marked P&IDs

Test Limit Isolations Checklist

Safety Components Checklist

4. Seal all potential leak sources with leak detection tape. For Shell Prelude Pitstop 2021 scope of Leak Testing, the compact flanges to be bagged all over including bolts.

5. Visually check and verify the test system preparation (PPS Supervisor and Customer Representative):

Test Limit Isolations

Correct isolation points have been used.

Manual valves are in the fully closed position and rated for full differential pressure.

Actuated valves are in the fully closed position, their energy source is isolated, and they are tight shut off at full differential pressure (test pressure – atmospheric pressure).

Each test limit isolation has a proven vent path to atmosphere (double block and bleed, or single block and bleed) (not applicable for positive isolations such as blind flanges).

PSVs and Burst Discs Devices are fitted as indicated on the P&IDs, and tag set pressure matches the P&ID value.

Maintenance isolation valves for the over pressure device are open, ensuring system protection.

Safety Components

Actuated valves are in the fully open position and their energy source is isolated.

Check valves (non-return valves) are correctly oriented.

Spectacle blinds and spacers are fitted open.

Manual valves within vent paths to atmosphere are in the fully open position

General All other manual valves within test limit boundaries are in the open position.

Instrumentation isolation valves are open (bleed valves closed)

Leak detection tape has been correctly applied to all potential leak sources.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 35 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

6. Sign off the system alignment checklists and relevant tasks of the Test Pack ITP once satisfied with the equipment rig up and test system alignment (PPS Supervisor and Customer Representative).

Management of change protocol shall be applied if the system cannot be aligned in accordance with the Test Pack P&IDs and system alignment checklists.

System Pressurization The following activities shall be completed to pressurize each system with a nitrogen pump unit:

1. Obtain a current, valid permit to work to pressurize and leak test the system.

2. Verify the ambient temperature and vessel / pipe wall (metal) temperature readings.

3. Hold a Toolbox Talk meeting. Ensure the following items are discussed / reviewed / confirmed:

Maximum allowable pressurization rate and associated pumping rate.

Incremental test pressures and associated hold periods.

Final test pressure.

Test gas requirements.

Leak testing acceptance criteria.

System depressurization procedure and maximum allowable depressurization rate.

Risk assessment review.

Inspection and test plan (ITP) review.

Test exclusion zone perimeter and access points.

Emergency response plan including muster points, responsible persons, and emergency contact numbers.

4. Place barriers and warning signs around the perimeter of the test exclusion zone:

Verify all potential access points to the test area are cordoned off and warning signs posted.

Check the test area. Ensure any unauthorized personnel are escorted outside the test exclusion zone boundaries. The perimeter shall be patrolled by nominated test personnel.

5. Make the final connections to the customer’s system, as detailed in the Test Pack:

5.1. Connect the test gas injection line and manifold from the nitrogen pump discharge.

5.2. Connect the OPPS pressure sensing line and manifold.

5.3. Install the pressure instrumentation (analog, digital, or a combination).

5.4. Fit the temporary PRV(s) (if applicable).

5.5. Verify the final system connections (PPS Supervisor and Customer Representative).

Note: PPS standard operating procedure requires the system metal temperature to be at least 17C (30F) above the MDMT of the pressure vessel or piping (as per ASME BPVC, Section VIII, Division 1, Pneumatic Testing requirement).

Testing may be carried out at a reduced pressure and lower temperature under management of change protocol only if approved by the customer’s technical authority.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 36 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

6. Arrange for a site radio announcement to be made stating that helium leak testing operations are due to commence, and barriers and warning signs shall be strictly observed.

7. Function test the radio communications. The PPS Pump Operator and Shift Supervisor shall maintain contact at all times during system pressurization.

8. Cool down and prime the nitrogen pump unit (allow 30 minutes for this activity).

9. Pressure test the injection line (hose / piping and manifolds) in accordance with standard practice:

9.1. Pressurize to 90% x hose / piping MAWP (maximum).

9.2. Stop pumping once test pressure is achieved and apply a hold period of 5-minutes.

9.3. Monitor for pressure drop and check for audible leaks:

Depressurize the hose / piping if leaking. Repair or replace the defective component. Re-test.

If the hose / piping is leak tight, function test the pump unit check valve in accordance with standard practice.

10. Subject to a successful pressure test, adjust the test gas injection and OPPS manifold valve positions in readiness for system pressurization.

11. Commence test gas injection (nitrogen and helium):

11.1. Inject test gas at ambient temperature and a low flow rate initially, in accordance with PPS Supervisor instructions. Monitor the system for signs of pressure increase.

If the system pressure begins to rise as expected, gradually increase the test gas injection rate.

Stop pumping if the system pressure does not rise as expected. Identify the problem and rectify.

12. Continue test gas injection until the first incremental pressure level is achieved (2 barg) (30 psig).

12.1. Stop pumping and apply a 10-minute hold period (minimum) to allow system stabilization.

12.2. Verify the pressure increment on the pressure instrumentation and ensure the reading is consistent at all pressure monitoring points. Investigate any discrepancies.

12.3. Take a gas sample from the test system and check the helium concentration using helium leak detector. Adjust helium injection rate accordingly to maintain at 1% by volume concentration.

12.4. Monitor the system pressure for signs of pressure drop.

12.5. Check for audible leaks, passing test limit isolation valves, or gas flow at the bleed points:

If the test system is found to be leaking, or pressure is passing into an adjacent system, shut down the nitrogen pump unit, assess the problem, and inform the Customer Representative.

If a leak source cannot be safely isolated to allow the test to continue, depressurize the system in accordance with the instructions in the PPS System Depressurization Checklist to enable repair work.

Note: The standard pressurization rate is 1 bar / minute (15 psi / minute).

The maximum allowable pressurization rate is 7 bar / minute (100 psi / minute).

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 37 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

If no leaks are detected and system pressure is stable, continue with system pressurization.

13. Re-commence test gas injection and continue until system pressure reaches 25% of final test pressure (second increment). Repeat steps 12.1 to 12.5.

14. Re-commence test gas injection and continue until system pressure reaches 50% of final test pressure (third increment). Repeat steps 12.1 to 12.5.

15. Re-commence test gas injection and continue until system pressure reaches 75% of final test pressure (fourth increment). Repeat steps 12.1 to 12.5.

16. Re-commence test gas injection and continue until the final test pressure (PT) is reached.

17. Stop pumping. Keep the nitrogen pump unit primed.

18. Monitor the test system for pressure drop over a 10-minute period. Ensure all pressure monitoring instrumentation is reading the same value:

If the pressure falls below the final test pressure level due to temperature stabilization of the test gas, top up the system pressure.

If the pressure falls rapidly and continuously, shut down the nitrogen pump unit and investigate the problem.

If the pressure is stable, shut down the nitrogen pump unit.

19. Isolate the test gas injection manifold and helium gas rack. Depressurize the temporary hose / piping.

20. Inform the customer representative that the system is at final test pressure (PT) and helium leak testing operations are due to commence.

Test Pressure Increments and Final Test Pressure

Steps 12 to 16 show the typical increments for pressurizing a customer system. The actual number of increments used, their associated pressures, and the final test pressure is specific to each Test Pack and directly influenced by the system design pressure / PSV set pressure, and the customer’s leak testing philosophy.

Note: Under no circumstances shall repair work be carried out while the piping system or PPS test equipment is under pressure.

Any alterations to valve alignment whilst the system is pressurized shall only be made if collectively agreed between the Customer Representative and PPS Supervisor, and the changes are recorded and approved in compliance with management of change protocol.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 38 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Refer to Table 11 for a summary.

System PSV Set Pressure, or Design Pressure, PD

Pressure Increment Test Pressure, PT

First Second Third Fourth

Less than 5 barg (75 psig)

Discussed and agreed with the customer on a test by test basis

5 barg to 20 barg (75 psig to 300 psig)

25% PT 50% PT 75% PT Not Applicable

90% PSV / PD

Greater than 20 barg (300 psig)

2 barg 30 psig

25% PT 50% PT 75% PT 90% PSV / PD

Table 11: Test Pressure Increments and Final Test Pressure

System Pressurization Using Pre-Mixed Gas Racks and an Air Driven Gas Booster

For small volume test systems, requiring less than 200 sm3 (7,000 scf) of gas to achieve test pressure, it is safer and more practical to use pre-mixed 1% helium / 99% nitrogen gas racks and an air driven gas booster for system pressurization. Installation of a temporary PRV is mandatory with this pressurization method.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 39 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Helium Leak Testing The following activities shall be completed to leak test a system that is at final test pressure (PT).

1. Take a gas sample from the test system using a bladder.

2. Calibrate the helium leak detector in accordance with standard procedure.

3. Re-check radio communications. Ensure spare batteries are charged.

4. Verify the presence of helium in the test system:

4.1. Open an instrumentation bleed valve or other suitable sample point on the test system.

4.2. Place the leak detection probe into the venting gas sample and confirm helium is detected by the helium leak detector.

4.3. Record the response time and the number of probe hoses used (latter not applicable for portable leak detectors).

5. Leak test the pressurized system in accordance with the following instructions:

5.1. Walk each line of the test system sequentially using the marked P&IDs.

5.2. Insert the leak detection probe into the first taped joint, threaded connection, or other potential leak source. Hold in a stable position for a minimum of 5 (five) seconds.

If no helium is detected, or the leak rate is below the allowable threshold limit, remove the leak detection tape and move on to the next component.

If a leak is detected above the allowable threshold limit:

i. Mark the leaking component with a tag and allocate a leak number with the notation L# (increasing sequentially).

ii. Highlight the leak on the Test Pack P&IDs, referencing the leak number.

iii. Record the following information on the PPS Leak Description Report:

o Leak number (L1, L2, L3 etc.)

o Leak rate (scf / yr)

o Drawing number

o An accurate, concise description of the leak location

6. Verify all potential leak sources have been tested. Sign the ITP as confirmation (PPS Supervisor).

7. Inform the Customer Representative that testing is complete and obtain permission to depressurize the system.

Note: If a pre-mixed gas rack is used for system pressurization a gas sample can be taken directly from the gas rack for calibration.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 40 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Witness Joints In each test system there may be a number of joints that cannot be tested for leakage.

Examples are PPS equipment tie-in points that require reinstatement after the test; flanged joints downstream of a test limit isolation valve; etc.

Untested joints shall be marked on the Test Pack P&IDs with the notation W# (numbered sequentially) and recorded on a PPS Witness Joint Register.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 41 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

System Depressurization The method statement below describes the activities to be completed for safe depressurization of each test system following completion of the leak testing process.

1. Verify the test system is correctly aligned for depressurization (PPS Supervisor and Customer Representative):

If system alignment was modified under management of change protocol, the system alignment shall be reinstated to the originally approved position prior to commencing depressurization.

If an approved change resulted in a revised or new system alignment and PPS System Depressurization Checklist, the new instructions shall be strictly followed.

2. Depressurize the entire test system to atmospheric pressure in compliance with the PPS System Depressurization Checklist:

Complete each sequential step on the checklist and sign as verification (PPS Supervisor and Customer Representative).

Ensure the initial stage of depressurization is slow by only opening the vent valve a fraction.

Monitor the vent path pressure instrumentation to ensure the maximum allowable vent system pressure is not exceeded. This takes precedence over all other parameters, including system depressurization rate.

Monitor the test system pressure continuously, adjusting the depressurization valve(s) position to maintain the depressurization rate at (or below) the agreed value. Ensure the maximum allowable depressurization rate is not exceeded.

Monitor the system piping temperature adjacent to each depressurization point to ensure excessive chilling does not occur caused by the Joule – Thomson effect. Visual warning signs are condensation on the pipe outer wall. Decrease the depressurization rate if required.

3. Check all pressure monitoring instrumentation to verify the entire system is depressurized to atmospheric pressure. Pay particular attention to pressure monitoring points upstream and downstream of single direction components such as check valves (non-return).

If repair work is to be carried out, all valves within the adjacent area shall be cycled to ensure there is no trapped pressure in the valve cavity.

4. Verify the pressure test data has been accurately recorded.

5. Ensure all leak detection tape has been removed from the system. Remove barriers and warning signs.

6. Sign off the permit, noting that the system is at atmospheric pressure (or, record the residual pressure if left under an inert blanket at the request of the Customer Representative).

Note: The standard depressurization rate is 2 bar / minute (30 psi / minute).

The maximum allowable depressurization rate is 7 bar / minute (100 psi / minute).

Regulating the depressurization rate using a valve is not required if depressurizing through a permanent restriction orifice into a flare system, vent header, or other system designed for gas service (the orifice is the regulating device).

Note: The Customer may request that residual pressure is left in the system. The vent valves (depressurization points) shall be closed when the residual pressure is reached.

The customer may also request that test gas is decanted to another system upon completion of the test. In order to ensure safe transfer of gas the receiving system shall be fully prepared and aligned for test in accordance with the instructions in Section 6.2.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 42 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

7. Present the test results to the Customer Representative.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 43 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Project Paperwork In addition to the marked Test Pack P&IDs and signed checklists, the paperwork listed in Table 12 shall be generated and placed in Section E of each Test Pack document upon successful completion of testing.

Test paperwork requires review and acceptance (signature) by the Customer Representative.

Test Pack Paperwork Distribution PPS Customer

Leak Description Report Original Copy

Leak Detection Completion Certificate Original Copy

Pressure Test Charts Original Copy

Witness Joint Register Original Copy

Nitrogen Gas Log Original Copy

Table 12: Test Pack Paperwork

The project management paperwork listed in Table 13 shall be maintained throughout the project and presented to the Customer Representative for review and acceptance (signature). Frequency for submission of the paperwork shall be discussed and agreed with the Customer Representative, and comply with contractual requirements.

Project Management Paperwork Distribution PPS Customer

Personnel Timesheets Original Copy

Equipment Schedules Original Copy

Materials and Services Original Copy

Daily Operations Report Original Copy

Monthly Charges Original Copy

Consumables Sheet Original Copy

Job Site Customer Satisfaction Survey Original Copy

Table 13: Project Management Paperwork

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 44 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Resources The following personnel, equipment, and material resources are the minimum required to complete the scope of work described in Section 3 of this document. Customer supplied items are also summarized.

Any additional resources required to support the project will be discussed and agreed with the customer under the terms of the contract, or management of change protocol.

PPS Personnel Personnel shown in Figure 2 shall be mobilized to provide 24-hr working (back-to-back 12-hour shifts).

Figure 2: PPS Personnel Crew Structure

PPS Equipment PPS shall mobilize the equipment items shown in Table 14 to the project site. Appendix A contains a standard equipment rig up drawing showing how each item is used to support the leak testing scope of work.

Equipment Description Specification Quantity Nitrogen pump unit 180k scf/hr, 690 barg

(1 x working, 1 x standby) 2

Liquid nitrogen storage tanks 8,000 litres (each) 12

Over Pressure Protection System (OPPS) 690 barg 2

Helium Gas Booster 100 scf/min, 690 barg 2

Helium Gas Racks (16 cylinders) 400 sm3, 300 barg 2

High Pressure Hose (Injection & Instrumentation) ½”, 400 barg & ¼”, 400 barg 2

Valves and Fittings Package Various 1

Pressure Instrumentation Package Various 2

Helium Leak Detector Package Mass Spectrometer 2

Test Cabin A60 1

Table 14: Main Equipment Items

Project Coordinator

(Perth Based)

Day ShiftSupervisor

2 x Day Shift Operators

Night ShiftSupervisor

2 x Night ShiftOperators

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 45 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Specification All PPS test equipment mobilized to site shall be appropriately pressure rated and certified for the leak test program. The nitrogen pump unit pressure and flow rate capabilities have been matched to project requirements, along with materials storage capacity (liquid nitrogen tanks and helium gas racks).

Preparation and Certification Prior to mobilization, all test equipment shall be inspected and function tested by the PPS workshop in accordance with PPS quality assurance procedures. The PPS Project Coordinator shall issue an equipment certification package to the Customer Representative.

PPS Supplied Materials PPS shall deliver the types and quantities of materials shown in Table 15 during the initial mobilization.

The quantities shown are based on information supplied by Shell.

Additional materials may be mobilized to support the testing program, as required.

Material Type Quantity Unit of Measure Liquid Nitrogen 90,000 litres

Helium 1248 sm3

Leak Detection Tape 30 Rolls

Leak Detection Tags 40 items

Table 15: Materials

Customer Supplier Items and Services The Customer is responsible for supplying the items and services shown in Table 16 to PPS under the contract terms.

Item or Service Description Requirement Crane and lifting services Unloading, positioning, and reloading of main equipment items

Nitrogen equipment bund (berm) Scaffolding boards to be place around the edge of the bund.

Scaffolding and ladder access Safe access to high point components that require leak testing

Lighting Adequate lighting of test systems for safe leak testing on night shift

Diesel 100 litres of diesel/hour while pumping for nitrogen pump unit

Electricity 480V, 60 Hz, 3-phase supply for A60 test cabin

Charged fire water hose Continuously available for use at the lay down area to disperse liquid nitrogen in the unlikely event of a spill

Table 16: Customer Supplied Items and Services

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 46 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Appendix A

PPS Equipment

Rev. Rev. Date Description Drawn Checked Approved

DateChecked byDateDrawn byScale

NTS

Drawing No.:

PPS-HLD-DWG-0014

Rev:Third

Angle

Projection

Helium Leak Detection

Nitrogen Pump Unit Pressurisation – Standard Offshore Rig Up

HP hose / iron

HP instrument

hosePRV #2

Gas for

calibration

Pressure

chart recorder

OPPS

PG #3

Air

PG #4

TEST SYSTEM

PRV #3

Test Gas

Injection manifold

Note 1:

Nitrogen pump valve arrangements

not shown in detail.

Note 2:

Air operated OPPS can be

substituted with electronic pressure

monitoring and trip system.

Tie in point for

hose / iron pressure

test

PRV Pressure relief valve

KEY

Ball valve

Needle valve

Check valve

PG Pressure gauge

PRV #1 : Pump protection

PRV #2 : Temporary hose / piping protection

PRV #3 : Customer system protectionPG #4 : Customer system pressure gauge

PG #1 : Liquid nitrogen pressure gauge (pump)

PG #2 : Gaseous nitrogen pressure gauge (pump)

PG #3 : OPPS pressure gauge

A 01-Jan-2014 Initial release A.Bokas G.Pike A.Barden

DieselNitrogen

pump

Heat source

To / from

liquid nitrogen

(LN2) tank

PRV 1

PG 1

Burst disc

Trip system

PG 2 TG 1

B 19-Jun-2015 Updated pump image G.Pike A.Bokas A.Barden

C A.BardenA.Bokas G.Pike23-Jan-2018 BHI logo replaced with BHGE logo

DB.Janjua 10-Feb-2020 A.Bokas 10-Feb-2020

A.BardenA.BokasB.JanjuaD 10-Feb-2020 BHGE logo replaced with Baker Hughes logo

Copyright Baker Hughes Company. All rights reserved.

Air

Gas Booster

Helium gas rack and

discharge manifold

Note 3:

Helium injection hose outlet

valve(s) must be confirmed open

before Gas Booster use to prevent

overpressurisation.

Rev. Rev. Date Description Drawn Checked Approved

DateChecked byDateDrawn byScale

NTS

Drawing No.:

PPS-HLD-DWG-0012

Rev:Third

Angle

Projection

Helium Leak Detection

Mass Spectrometer and Leak Test Probe System

Air

1% He / 99% N2

gas bottle

100 1200

Work

bench

300

He

Test

system

PG

PRV

Calibration

unit

Gas sample

bladder

Vacuum

pump

Mass

spectrometer

Electricity

Leak detection probe

Quick release

coupling

Test cabin

A

B

01-Jan-2014 First revision published A.Bokas G.Pike A.Barden

23-Jan-2018 BHI logo replaced with BHGE logo A.Bokas G.Pike A.Barden

CB.Janjua 30-Jan-2020 A.Bokas 30-Jan-2020

A.BardenA.BokasB.JanjuaC 30-Jan-2020 BHGE logo replaced with Baker Hughes logo

Copyright Baker Hughes Company. All rights reserved.

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 47 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Appendix B

Risk Assessments

Version A HSES-FM-ORA-001

OPERATIONAL RISK ASSESSMENT (ORA) FORMProcess:

Activity / Service Type:Related ORAs:Required PPE:

(Personal Protective Equipment)Location:

TASK /PROCESS STEP

THREATS / HAZARDS / ASPECTS

How can the TASK, STEP, or CHANGE go wrong?What are the potential Consequences?

What are the Gaps?

Uncontrolled RISK LEVEL

Controlled RISK LEVEL

Instrumentation installed on test system

is not rated for the test pressure,

resulting in failure due to over

pressurization:

- flying glass

- uncontrolled gas release

- personnel injury

RL1 HSE RL2 HSE

Temporary PRV selected and installed

for test has incorrect set pressure (too

high); no protection device if the test

system is over pressurized.RL1 HSE RL2 HSE

PRV / OPPS pressure sensing point /

test instrumentation installed onto wrong

point of test system, resulting in isolation

of over pressure protection devices and

no pressure monitoring capability for the

test.

RL1 HSE RL2 HSE

Temporary PRV installation point is too

small (less than the PRV inlet diameter)

causing a restricted flow rate condition

through the PRV if there is an over

pressure event. RL1 HSE RL2 HSE

Over pressurize instrumentation when

function testing the OPPS, causing flying

glass from pressure gauge / burst hose /

damaged fittings / personnel injury.RL1 HSE RL2 HSE

OPPS set to incorrect trip pressure for

test (too high); no protection device if

there is an over pressure event.

RL1 HSE RL2 HSE

Tape breaks whilst being applied to

joints causing personnel injury due to

sudden arm movement. RL2 HSE RL2 HSE

Test limit isolation missed, or incorrect

test limit isolation used, causing

pressurization / over pressurization of

adjacent system.

RL1 HSE RL2 HSE

Piping specification change missed - test

limit isolation used has inadequate

pressure rating, resulting in damage to

piping or failure during testing.

RL1 HSE RL2 HSE

Test limit isolation valves are incorrect

type and are not capable of tight shut off

under pressure, resulting in over

pressurization of adjacent system.

RL1 HSE RL2 HSE

BHC supervisor and customer representative check each

test limit isolation valve type during system alignment and

verify they are capable of tight shut off when pressurized.

Double block and bleed isolations applied where possible.

Equipment preparation

Trained, competent personnel set the OPPS trip pressure

and carry out the function test.

Gas bottle pressure regulator used for controlling the

OPPS calibration pressure.

OPPS function test witnessed and verified by the BHC

supervisor and customer representative. Test pack ITP

signed as confirmation.

Final test pressure less than the OPPS trip pressure.

Customer PSV on line and / or temporary PRV installed

onto test system as secondary over pressure protection,

and set pressure verified.

Equipment function test

Tape kept in the test cabin or warm environment prior to

use - brittle when cold. Gloves worn.

Care taken, particularly when applying tape in close

proximity to sharp edges.

H d / t i di ti f th b d

Test System Preparation

Instrumentation inspected, pressure rating verified, and

certification checked by BHC supervisor and customer

representative. Test pack ITP signed as confirmation.

Leak test hold period applied at incremental and final test

pressures, and checks made for audible leaks, prior to

personnel entering the test area.

PRV visually inspected, set pressure verified, and

certification checked by the BHC supervisor and customer

representative. Test pack ITP signed as confirmation.

OPPS is primary over pressure protection device, with

PRV mechanical back up.

All test equipment installation points verified against the

test pack drawings and system alignment checklist by the

BHC supervisor and customer representative prior to

testing. Test pack ITP signed as confirmation.

Management of Change protocol applied to:

i. Identify a new adequately sized connection point that

provides full system coverage.

ii. Or, install the PRV at the originally designated

connection point, calculate the reduced flow rate capability

at the set pressure, and restrict the test gas injection below

this value. Record the pump rate restriction in the test

pack and discuss during the toolbox talk meeting prior to

testing.

BHC supervisor and customer representative verify the test

system is correctly aligned against marked P&IDs and the

Test Limit Isolations Checklist (signed as confirmation).

BHC supervisor and customer representative check each

test limit isolation and verify they are adequately rated for

the nominated test pressure.

Process and Pipeline Services

NOTE: Additional information and guidance on Service Delivery impacts can be viewed in the Reliability Assurance

CONTROLS / BARRIERS including OPERATIONAL PROCEDURES / CONTINGENCIES

What are the CONTROLS / BARRIERS, to Control, Mitigate, Eliminate, or Prevent the identified THREAT / HAZARD / ASPECT?NOTE: Barriers can be Equipment, Process, or People

All Threats, Hazards, and Aspects are evaluated using the Five Fundamentals methodology to ensure each identified risk is appropriately mitigated.It is everyone's responsibility to "STOP WORK" when Unsafe Conditions or Conditions that do not support product quality or delivery are recognized.

NOTE: Risk Levels identified as "RL1" REQUIRE "STOP WORK" until controls are in place to reduce risk or impact.For "RL2" Risk Levels, if controls cannot be implemented the team must stop and revaluate task to determine new controls that can be implemented.

Each Threat, Hazard, and Aspect has been classified with a Risk Level. There are two Risk Level classifications (RL1 and RL2) and they are defined as:RL1 – Immediately Dangerous to Life or Health (IDLH), Life Critical, major environmental impact, Process Safety, serious injury, explosion, dropped objects, loss of well control, loss of primary containment, major property damage greater than $250,000, or a PL Reliability and Service Delivery incident classified as High Impact. RL2 – All remaining HSE not listed in RL1 and Service Delivery impacts classified as a Low or Medium Impact.

Incident Impact Definition procedure.

Leak Detection

Hard Hat, Safety Glasses/Goggles/Face Shield, Flame Retardant Coveralls, Gloves, Safety Boots

Field Operations

PPS Site Safety, PPS Nitrogen Pumping

Uncontrolled when printed. Confirm the correct revision is used.

© 2010–2016 Baker Hughes Incorporated

Baker Hughes Confidential

Revised Date: 31-May-2016

Version A HSES-FM-ORA-001

OPERATIONAL RISK ASSESSMENT (ORA) FORMProcess:

Activity / Service Type:Related ORAs:Required PPE:

(Personal Protective Equipment)Location:

TASK /PROCESS STEP

THREATS / HAZARDS / ASPECTS

How can the TASK, STEP, or CHANGE go wrong?What are the potential Consequences?

What are the Gaps?

Uncontrolled RISK LEVEL

Controlled RISK LEVEL

Process and Pipeline Services

NOTE: Additional information and guidance on Service Delivery impacts can be viewed in the Reliability Assurance

CONTROLS / BARRIERS including OPERATIONAL PROCEDURES / CONTINGENCIES

What are the CONTROLS / BARRIERS, to Control, Mitigate, Eliminate, or Prevent the identified THREAT / HAZARD / ASPECT?NOTE: Barriers can be Equipment, Process, or People

All Threats, Hazards, and Aspects are evaluated using the Five Fundamentals methodology to ensure each identified risk is appropriately mitigated.It is everyone's responsibility to "STOP WORK" when Unsafe Conditions or Conditions that do not support product quality or delivery are recognized.

NOTE: Risk Levels identified as "RL1" REQUIRE "STOP WORK" until controls are in place to reduce risk or impact.For "RL2" Risk Levels, if controls cannot be implemented the team must stop and revaluate task to determine new controls that can be implemented.

Each Threat, Hazard, and Aspect has been classified with a Risk Level. There are two Risk Level classifications (RL1 and RL2) and they are defined as:RL1 – Immediately Dangerous to Life or Health (IDLH), Life Critical, major environmental impact, Process Safety, serious injury, explosion, dropped objects, loss of well control, loss of primary containment, major property damage greater than $250,000, or a PL Reliability and Service Delivery incident classified as High Impact. RL2 – All remaining HSE not listed in RL1 and Service Delivery impacts classified as a Low or Medium Impact.

Incident Impact Definition procedure.

Leak Detection

Hard Hat, Safety Glasses/Goggles/Face Shield, Flame Retardant Coveralls, Gloves, Safety Boots

Field Operations

PPS Site Safety, PPS Nitrogen Pumping

Manual valve or actuated valve closed

within test limit boundaries, causing:

- isolation of OPPS and / or PRV

- isolation of test instrumentation

- future leaks from untested joints

- trapped pressure post testing

RL1 HSE RL2 HSE

Check valve (non return valve)

incorrectly orientated, or spectacle blind

fitted closed, within test limit boundaries

causing:

- future leaks from untested joints

- trapped pressure post testing

RL1 HSE RL2 HSE

Site conditions require change to:

- test limit isolations

- test gas injection point

- depressurization point

- pressure monitoring point

- OPPS pressure sensing point

- temporary PRV installation point

Potential for:

- pressurization of adjacent system

- untested components

- trapped pressure

- damage to rotating equipment

RL1 HSE RL2 HSE

Test exclusion zone

Access routes left open allowing

unauthorized personnel to enter the test

area and interfere with the test system. RL1 HSE RL2 HSE

Calibration issue with customer PSV /

burst disc / temporary PRV causes an

unexpected gas discharge below the set

pressure. RL2 HSE RL2 HSE

Actuated valve used for test limit

isolation changes position during the test

from closed to open, causing an

uncontrolled:

- pressure release to atmosphere

- adjacent system over-pressurized

RL1 HSE RL2 HSE

Test limit isolation passing causing

uncontrolled pressurization / over

pressurization of the adjacent system. RL1 HSE RL2 HSE

Customer system component failure

below nominated test pressure due to

incorrectly specified or defective

material, excessive erosion, corrosion,

defective welds, incorrect joint make-up,

or other cause, resulting in:

- uncontrolled gas release

- personnel injury

- equipment damage

RL1 HSE RL2 HSE

Test System Preparation

Proposed changes to the approved test pack are risk

assessed and recorded in compliance with Management of

Change protocol.

Approvals are obtained from authorized BHC and customer

representatives prior to implementation, if safe to proceed.

BHC supervisor verifies barriers and warning signs are

correctly positioned around the entire test exclusion zone.

Unauthorized personnel removed. Test exclusion zone

perimeter patrolled throughout the test. Test pack ITP

signed as verification.

BHC supervisor and customer representative check each

manual and actuated valve within test limits and verify in

the open position. Actuated valves within test limits have

their motive power source isolated (electricity / air /

hydraulic) by the customer instrument technician to ensure

the valve remains open and cannot be operated remotely.

Safety Components Checklist signed as confirmation.

BHC supervisor and customer representative visually

inspect each check valve and spectacle blind within test

limit boundaries for correct orientation.

Safety Components Checklist signed as confirmation.

Safety device tag data and set pressure verified by the

BHC supervisor and customer representative during

system preparation. Temporary PRV discharge orientated

in a safe direction, away from a walkway, access point, or

common area. If safety device lifts below set pressure, the

customer representative shall be notified immediately and

testing will stop pending investigation.

Test limit isolations used are blinds, spades, closed

spectacle blinds, and single or double block and bleed

valve isolations that protect the adjacent systems.

Bleed valves are checked and pressure is monitored in

adjacent systems during the test.

Customer representative confirms the test system is

mechanically complete, MDMT verified, and all system

components have successfully passed NDT / hydrostatic

test / pneumatic strength test / FAT in compliance with

code requirements. Test pack ITP signed as verification.

Customer to carry out wall thickness checks prior to testing

if any uncertainty about the system condition.

System pressurized in increments and checks made for

audible leaks during hold periods, prior to personnel

entering the test area.

All actuated valves used for test limits have their motive

power source isolated (electricity / air / hydraulic) by the

customer instrument technician to ensure the valve

remains closed and cannot be operated remotely.

BHC supervisor and customer representative visually

check each actuated valve is correctly isolated in the

closed position. Test Limit Isolations Checklist signed as

ifi ti i t i ti

System pressurization

Uncontrolled when printed. Confirm the correct revision is used.

© 2010–2016 Baker Hughes Incorporated

Baker Hughes Confidential

Revised Date: 31-May-2016

Version A HSES-FM-ORA-001

OPERATIONAL RISK ASSESSMENT (ORA) FORMProcess:

Activity / Service Type:Related ORAs:Required PPE:

(Personal Protective Equipment)Location:

TASK /PROCESS STEP

THREATS / HAZARDS / ASPECTS

How can the TASK, STEP, or CHANGE go wrong?What are the potential Consequences?

What are the Gaps?

Uncontrolled RISK LEVEL

Controlled RISK LEVEL

Process and Pipeline Services

NOTE: Additional information and guidance on Service Delivery impacts can be viewed in the Reliability Assurance

CONTROLS / BARRIERS including OPERATIONAL PROCEDURES / CONTINGENCIES

What are the CONTROLS / BARRIERS, to Control, Mitigate, Eliminate, or Prevent the identified THREAT / HAZARD / ASPECT?NOTE: Barriers can be Equipment, Process, or People

All Threats, Hazards, and Aspects are evaluated using the Five Fundamentals methodology to ensure each identified risk is appropriately mitigated.It is everyone's responsibility to "STOP WORK" when Unsafe Conditions or Conditions that do not support product quality or delivery are recognized.

NOTE: Risk Levels identified as "RL1" REQUIRE "STOP WORK" until controls are in place to reduce risk or impact.For "RL2" Risk Levels, if controls cannot be implemented the team must stop and revaluate task to determine new controls that can be implemented.

Each Threat, Hazard, and Aspect has been classified with a Risk Level. There are two Risk Level classifications (RL1 and RL2) and they are defined as:RL1 – Immediately Dangerous to Life or Health (IDLH), Life Critical, major environmental impact, Process Safety, serious injury, explosion, dropped objects, loss of well control, loss of primary containment, major property damage greater than $250,000, or a PL Reliability and Service Delivery incident classified as High Impact. RL2 – All remaining HSE not listed in RL1 and Service Delivery impacts classified as a Low or Medium Impact.

Incident Impact Definition procedure.

Leak Detection

Hard Hat, Safety Glasses/Goggles/Face Shield, Flame Retardant Coveralls, Gloves, Safety Boots

Field Operations

PPS Site Safety, PPS Nitrogen Pumping

Damaged / crushed / incorrectly rated

gasket fails under pressure, resulting in:

- uncontrolled gas release

- flying debris

- personnel injury RL1 HSE RL2 HSE

Loose plug / damaged threads on

system component causes failure under

pressure, resulting in:

- uncontrolled gas release

- flying projectile

- personnel injury

RL1 HSE RL2 HSE

Leaking components generate high

noise level, resulting in personnel

hearing damage.

Potential causes of leaks include:

- misaligned pipe

- scored / corroded flange face

- missing gasket

- missing bolts or loose bolts

- incorrect torque / tension settings

- valve stem leaks

- missing plug, instrument, etc.

RL1 HSE RL2 HSE

Leaking test gas creates an asphyxiation

hazard in an enclosed area.

RL1 HSE RL2 HSE

System pressurization

Inclement weather conditions (such as

heavy rain, thunderstorms, high wind

speed, heavy snow, ice, extreme cold

temperatures, extreme high

temperatures) create dangerous working

conditions causing personnel injury or

plant damage.

RL1 HSE RL2 HSE

Unauthorized personnel enter the test

area and interfere with the test system,

causing an uncontrolled pressure

release, plant damage, or personnel

injury.

RL1 HSE RL2 HSE

Joints / potential leak sources missed

during the leak test, resulting in a

hydrocarbon release during start up. RL1 HSE RL2 HSE

Customer representative requests a

leaking joint is isolated (system

alignment is changed) to enable

continuation and completion of testing.

Failure to realign the system upon

completion of testing causes a trapped

pressure event post depressurization.

RL1 HSE RL2 HSE

BHC supervisor and customer representative shall monitor

the weather conditions in advance of test and determine

whether safe for personnel to work.

If ambient temperature is anticipated to fall within 17C

(30F) of the vessel MDMT or the piping ductile - brittle

transition temperature, the test shall be postponed until

ambient temperature increases (Ref: ASME BPV).

BHC supervisor and customer representative assess the

severity of a leak and determine whether safe to isolate

and proceed with testing, or if a test shall be stopped.

Proposed changes to the approved test pack are risk

assessed and recorded in compliance with Management of

Change protocol.

Approvals are obtained from authorized BHC and customer

representatives prior to implementation, if safe to proceed.

Leak testing

Permit to work system in effect to prevent work activities

conflicts (SIMOPS).

Barriers erected, warning signs posted. Radio

announcement made.

Test exclusion zone patrolled whilst system is being

pressurized, leak tested, and depressurized.

BHC supervisor checks the system against marked P&IDs

following completion of the leak test to verify all potential

leak sources have been tested.

The test pack ITP is signed as confirmation.

Threaded connections checked to verify components are

correctly fitted prior to testing (customer responsibility).

Test Pack ITP signed by customer representative as

verification. System pressurized in increments and checks

made for audible leaks during hold periods, prior to

personnel entering the test area.

Pipe alignment tolerances verified and flange faces visually

inspected during bolted flange joint make up. BHC

supervisor and customer representative visually check the

system during system preparation and verify all

components are fitted prior to testing. Bolted flange joints

are checked to ensure nuts / bolts / gaskets are fitted, and

torque / tension tags are in place. Test Pack ITP signed by

customer representative as verification.

System pressurized in increments and checks made for

audible leaks during hold periods prior to personnel

entering the test area.

Personnel issued with hearing protection.

Test area assessed by BHC supervisor and customer

representative prior to pressurization. Enclosed area

safety controls discussed during toolbox talk.

Personal oxygen meters used. Standalone gas monitors

with audible visual alarms placed in enclosed areas.

Personnel in continuous radio contact. "Buddy" system

applied - minimum 2 x BHC personnel.

Bolted flange joints made up by qualified, competent

personnel. Correct gasket selected and visually checked

for damage prior to installation. Correct torque / tension

applied in compliance with industry standard. Joint make

up verified by flange management system. Pressurization

in increments and checks made for audible leaks during

hold periods prior to personnel entering the test area.

Personnel instructed not to stand in the line of fire when

testing flanged joints.

System pressurization

Uncontrolled when printed. Confirm the correct revision is used.

© 2010–2016 Baker Hughes Incorporated

Baker Hughes Confidential

Revised Date: 31-May-2016

Version A HSES-FM-ORA-001

OPERATIONAL RISK ASSESSMENT (ORA) FORMProcess:

Activity / Service Type:Related ORAs:Required PPE:

(Personal Protective Equipment)Location:

TASK /PROCESS STEP

THREATS / HAZARDS / ASPECTS

How can the TASK, STEP, or CHANGE go wrong?What are the potential Consequences?

What are the Gaps?

Uncontrolled RISK LEVEL

Controlled RISK LEVEL

Process and Pipeline Services

NOTE: Additional information and guidance on Service Delivery impacts can be viewed in the Reliability Assurance

CONTROLS / BARRIERS including OPERATIONAL PROCEDURES / CONTINGENCIES

What are the CONTROLS / BARRIERS, to Control, Mitigate, Eliminate, or Prevent the identified THREAT / HAZARD / ASPECT?NOTE: Barriers can be Equipment, Process, or People

All Threats, Hazards, and Aspects are evaluated using the Five Fundamentals methodology to ensure each identified risk is appropriately mitigated.It is everyone's responsibility to "STOP WORK" when Unsafe Conditions or Conditions that do not support product quality or delivery are recognized.

NOTE: Risk Levels identified as "RL1" REQUIRE "STOP WORK" until controls are in place to reduce risk or impact.For "RL2" Risk Levels, if controls cannot be implemented the team must stop and revaluate task to determine new controls that can be implemented.

Each Threat, Hazard, and Aspect has been classified with a Risk Level. There are two Risk Level classifications (RL1 and RL2) and they are defined as:RL1 – Immediately Dangerous to Life or Health (IDLH), Life Critical, major environmental impact, Process Safety, serious injury, explosion, dropped objects, loss of well control, loss of primary containment, major property damage greater than $250,000, or a PL Reliability and Service Delivery incident classified as High Impact. RL2 – All remaining HSE not listed in RL1 and Service Delivery impacts classified as a Low or Medium Impact.

Incident Impact Definition procedure.

Leak Detection

Hard Hat, Safety Glasses/Goggles/Face Shield, Flame Retardant Coveralls, Gloves, Safety Boots

Field Operations

PPS Site Safety, PPS Nitrogen Pumping

Test gas vented locally into an enclosed

space creating an asphyxiation hazard.

RL1 HSE RL2 HSE

Incorrect depressurization point used

resulting in trapped pressure

downstream of a system check valve

(non return valve). RL1 HSE RL2 HSE

Manual valve closed within test limit

boundaries resulting in trapped

pressure. RL1 HSE RL2 HSE

Incorrect depressurization point used

resulting in over pressurization of the

adjacent system. RL1 HSE RL2 HSE

Incorrect depressurization point used

resulting in accidental rotation and

damage to mechanical equipment.

RL1 HSE RL2 HSE

High depressurization rate (in excess of

agreed maximum rate) causes over

pressurization of piping and customer

equipment on the approved vent path.

RL1 HSE RL2 HSE

Excessive depressurization rate causes

chilling of piping due to Joule - Thomson

effect ( gas expansion), resulting in the

ductile - brittle transition temperature

exceeded.

RL1 HSE RL2 HSE

Excessive noise level exceeds

acceptable local HSE limits, or causes

personnel hearing damage RL1 HSE RL2 HSE

Pressure left in system at the customer's

request. Uncontrolled pressure release

and personnel injury when third party

personnel work on the system after test.RL1 HSE RL2 HSE

Piping at depressurization points closely monitored for

signs of chilling (condensation, frosting). Depressurization

rate reduced by BHC supervisor.

See additional controls above for excessive

depressurization rate.

System depressurization

System depressurization points are clearly identified in the

test pack (marked P&IDs, System Depressurization

Checklist). Only approved depressurization points are

used. Vent paths are checked by the BHC supervisor in

advance of testing to ensure test gas does not route into

an enclosed space. Flares and vent headers are used for

system depressurization wherever possible.

Temporary, secured hose used to route test gas from a

local vent point to a safe location if flare or vent header

unavailable.

Personnel oxygen meters used.

Depressurization carried out in accordance with the

System Depressurization Checklist, verified and signed off

by BHC supervisor and customer representative.

Pressure monitoring points checked upstream and

downstream of check valves to ensure the system is fully

depressurized.

BHC supervisor and customer representative verify each

manual valve within test limit boundaries is open.

Management of Change documents reviewed to ensure

any system alignment changes are identified and rectified.

Depressurization carried out in accordance with System

Depressurization Checklist and ITP, signed off by BHC

supervisor and customer representative. Adjacent

systems monitored for signs of pressure increase.

System depressurization

Depressurization rate controlled to minimize the noise level

generated in compliance with local HSE requirements.

Gas routed to the flare / vent header where possible.

Hearing protection worn by personnel.

Residual pressure level verified by the BHC supervisor and

customer representative, and recorded on the System

Depressurization Checklist, test pack ITP, and the test

permit. Customer permit office advised of system status.

Customer technical authority and OEM vendor

representative consulted regarding depressurization of

systems containing rotating mechanical equipment during

the engineering phase.

Depressurization points and maximum allowable

depressurization rates recorded in the test pack, and

discussed at a toolbox talk meeting prior to test.

Depressurization carried out in accordance with the

System Depressurization Checklist, verified and signed by

the BHC supervisor and customer representative.

Maximum allowable depressurization rate and vent path

pressure are recorded in the test pack document, and

discussed at toolbox talk meeting. Flare and vent headers,

if used, are (typically) designed for handling process flow

rates well in excess of those generated during system

depressurization. Vent path pressure instrumentation is

continuously monitored during the depressurization activity

to ensure maximum allowable vent path pressure is not

exceeded.

Uncontrolled when printed. Confirm the correct revision is used.

© 2010–2016 Baker Hughes Incorporated

Baker Hughes Confidential

Revised Date: 31-May-2016

Version A HSES-FM-ORA-001

OPERATIONAL RISK ASSESSMENT (ORA) FORMProcess:

Activity / Service Type:Related ORAs:Required PPE:

(Personal Protective Equipment)Location:

TASK /PROCESS STEP

THREATS / HAZARDS / ASPECTS

How can the TASK, STEP, or CHANGE go wrong?What are the potential Consequences?

What are the Gaps?

Uncontrolled RISK LEVEL

Controlled RISK LEVEL

Process and Pipeline Services

NOTE: Additional information and guidance on Service Delivery impacts can be viewed in the Reliability Assurance

CONTROLS / BARRIERS including OPERATIONAL PROCEDURES / CONTINGENCIES

What are the CONTROLS / BARRIERS, to Control, Mitigate, Eliminate, or Prevent the identified THREAT / HAZARD / ASPECT?NOTE: Barriers can be Equipment, Process, or People

All Threats, Hazards, and Aspects are evaluated using the Five Fundamentals methodology to ensure each identified risk is appropriately mitigated.It is everyone's responsibility to "STOP WORK" when Unsafe Conditions or Conditions that do not support product quality or delivery are recognized.

NOTE: Risk Levels identified as "RL1" REQUIRE "STOP WORK" until controls are in place to reduce risk or impact.For "RL2" Risk Levels, if controls cannot be implemented the team must stop and revaluate task to determine new controls that can be implemented.

Each Threat, Hazard, and Aspect has been classified with a Risk Level. There are two Risk Level classifications (RL1 and RL2) and they are defined as:RL1 – Immediately Dangerous to Life or Health (IDLH), Life Critical, major environmental impact, Process Safety, serious injury, explosion, dropped objects, loss of well control, loss of primary containment, major property damage greater than $250,000, or a PL Reliability and Service Delivery incident classified as High Impact. RL2 – All remaining HSE not listed in RL1 and Service Delivery impacts classified as a Low or Medium Impact.

Incident Impact Definition procedure.

Leak Detection

Hard Hat, Safety Glasses/Goggles/Face Shield, Flame Retardant Coveralls, Gloves, Safety Boots

Field Operations

PPS Site Safety, PPS Nitrogen Pumping

Leak detection tape left on the system

after final test, creating a corrosion

hazard.RL2 HSE RL2 HSE

Customer unable to start up the plant

due to test blinds / spades / closed

spectacle blinds left in test system.RL2 HSE RL2 HSE

Hydrocarbon release during start up due

to test equipment connection points and

system depressurization points being left

open directly to atmosphere upon

completion of testing.

RL1 HSE RL2 HSE

System reinstatement

Test system checked by BHC supervisor post

depressurization to verify all leak detection tape has been

removed. The test pack ITP is signed as confirmation.

Witness Joint Register and Mechanical Reinstatement

checklists issued to the customer representative after

completing testing, identifying items to be reinstated.

Witness Joint Register and Mechanical Reinstatement

checklists issued to the customer representative after

completing testing, identifying items to be reinstated.

Uncontrolled when printed. Confirm the correct revision is used.

© 2010–2016 Baker Hughes Incorporated

Baker Hughes Confidential

Revised Date: 31-May-2016

Version A HSES-FM-ORA-001

OPERATIONAL RISK ASSESSMENT (ORA) FORMProcess:

Activity / Service Type:Related ORAs:Required PPE:

(Personal Protective Equipment)Location:

TASK /PROCESS STEP

THREATS / HAZARDS / ASPECTS

How can the TASK, STEP, or CHANGE go wrong?What are the potential Consequences?

What are the Gaps?

Uncontrolled RISK LEVEL

Controlled RISK LEVEL

Personnel struck by falling objects, or

trapped underneath equipment.

RL1 HSE RL2 HSE

Large, heavy object dropped on

pressurized equipment causing:

- component failure and flying debris

- uncontrolled gas release

- personnel injury

RL1 HSE RL2 HSE

Failure of lifting device (pad-eyes, slings

/ chains, rigging equipment, hydraulic

loading equipment e.g. Hiab) causes

personnel injury and equipment damage.RL1 HSE RL2 HSE

Equipment hits and damages the

customer's plant whilst being moved into

position. RL1 HSE RL2 HSE

Spill control bund (berm) construction

Personnel injuries during construction of

the spill control bund (berm), caused by:

- trapped fingers

- slip on wet surface

- trip on uneven tarpaulin / raised side

RL2 HSE RL2 HSE

Personnel injury caused by:

- container door handle springs up

- container door swings open

- equipment falling out of storageRL2 HSE RL2 HSE

Incorrect lifting technique whilst carrying

out manual handling of large, heavy, or

awkward shaped equipment causes

personnel injury.RL2 HSE RL2 HSE

Electricity supply to equipment

incorrectly rigged up creating an

electrocution hazard.RL1 HSE RL2 HSE

Defective air hose or incorrect couplings,

results in an uncontrolled pressure

release, whipping hose, flying debris,

and personnel injury.

RL2 HSE RL2 HSE

Fuel transfer

Fuel spill during fuel tank filling operation

creates flammable hazard, and potential

fire if ignition source is present.

RL1 HSE RL2 HSE

Incorrect selection and use of hand

tools, or defective tools, cause personnel

injury and / or damage to BHC

equipment.

RL2 HSE RL2 HSE

Poor routing of hoses / iron / piping

creates trip hazard, causing personnel

injury. RL2 HSE RL2 HSE

Lifts carried out by qualified, competent third party

personnel with certified lifting equipment in compliance with

an approved lift plan (assessment of load, lift point, arc of

lift, trajectory, landing area, etc.).

Hazards of constructing a bund (berm) discussed during a

toolbox talk meeting. Bund (berm) visually checked by

BHC supervisor to ensure flat and even (no trip hazards).

Care and attention required by all personnel, particularly if

raining (slip hazard).

Personnel informed during a toolbox talk meeting to take

care when unlocking and opening storage containers.

Container doors secured / tied back prior to unloading (or

loading) equipment. Items carefully packed and secured

prior to shipment, and cargo nets used.

Lifting aids used to avoid heavy manual lifts wherever

possible. BHC personnel trained and competent in manual

handling techniques. Unavoidable heavy manual lifts

completed by two or more crew members following manual

handling assessment of the lift.

All electrical connections to BHC equipment shall be made

and verified by a qualified electrician technician, and

equipment function tested to ensure operating correctly.

Equipment checked for loose objects and all doors /

hatches secured prior to lifting. Large equipment items

shall not be used for moving smaller equipment items.

Personnel warned about overhead lifting dangers during a

toolbox talk meeting. Under no circumstances shall

personnel walk underneath suspended equipment. Lifts

carried out by qualified, competent personnel.

Customer representative informed of hazards associated

with overhead lifting above pressurized equipment.

Lifts to be eliminated wherever possible.

Unavoidable lifts carried out by qualified, competent third

party personnel with certified equipment.

Process and Pipeline Services

NOTE: Additional information and guidance on Service Delivery impacts can be viewed in the Reliability Assurance

CONTROLS / BARRIERS including OPERATIONAL PROCEDURES / CONTINGENCIES

What are the CONTROLS / BARRIERS, to Control, Mitigate, Eliminate, or Prevent the identified THREAT / HAZARD / ASPECT?NOTE: Barriers can be Equipment, Process, or People

All Threats, Hazards, and Aspects are evaluated using the Five Fundamentals methodology to ensure each identified risk is appropriately mitigated.It is everyone's responsibility to "STOP WORK" when Unsafe Conditions or Conditions that do not support product quality or delivery are recognized.

NOTE: Risk Levels identified as "RL1" REQUIRE "STOP WORK" until controls are in place to reduce risk or impact.For "RL2" Risk Levels, if controls cannot be implemented the team must stop and revaluate task to determine new controls that can be implemented.

Each Threat, Hazard, and Aspect has been classified with a Risk Level. There are two Risk Level classifications (RL1 and RL2) and they are defined as:RL1 – Immediately Dangerous to Life or Health (IDLH), Life Critical, major environmental impact, Process Safety, serious injury, explosion, dropped objects, loss of well control, loss of primary containment, major property damage greater than $250,000, or a PL Reliability and Service Delivery incident classified as High Impact. RL2 – All remaining HSE not listed in RL1 and Service Delivery impacts classified as a Low or Medium Impact.

Incident Impact Definition procedure.

PPS Site Safety

Hard Hat, Safety Glasses, Flame Retardant Coveralls, Gloves, Safety Boots

Field Operations

All PPS Product Line ORAs

Overhead lifts

Visual inspection in the workshop prior to mobilization, and

at site before use. Only certified equipment used within the

rated capacity (safety factor applied).

Manual unload / load of equipment

Utilities rig up

Air hose and couplings visually checked by the BHC

supervisor for signs of damage and to verify compatibility.

Air hose carefully routed and secured using restraint

devices prior to use.

Work area checked in advance and potential ignition

sources removed. Care taken when transferring fuel.

Correct PPE worn in accordance with SDS requirements.

BHC equipment has built in drip trays and is positioned

within spill bund (berm). Spill kit and fire extinguishers

placed at the lay down area. Spill cleaned up immediately.

Waste materials disposed of correctly in appropriate

containers. Fouled clothing removed.

BHC personnel are trained and competent in hand tool

selection and use. Tools shall be inspected, maintained

and kept clean prior to use, with defective tools removed

from the job. Gloves shall be worn (where practical).

BHC supervisor visually checks hoses / iron / piping to

verify correctly rigged up, secured, and safely routed away

from access points, common walkways and other potential

trip areas.

Uncontrolled when printed. Confirm the correct revision is used.

© 2010–2016 Baker Hughes Incorporated

Baker Hughes Confidential

Revised Date: 31-May-2016

Version A HSES-FM-ORA-001

OPERATIONAL RISK ASSESSMENT (ORA) FORMProcess:

Activity / Service Type:Related ORAs:Required PPE:

(Personal Protective Equipment)Location:

TASK /PROCESS STEP

THREATS / HAZARDS / ASPECTS

How can the TASK, STEP, or CHANGE go wrong?What are the potential Consequences?

What are the Gaps?

Uncontrolled RISK LEVEL

Controlled RISK LEVEL

Process and Pipeline Services

NOTE: Additional information and guidance on Service Delivery impacts can be viewed in the Reliability Assurance

CONTROLS / BARRIERS including OPERATIONAL PROCEDURES / CONTINGENCIES

What are the CONTROLS / BARRIERS, to Control, Mitigate, Eliminate, or Prevent the identified THREAT / HAZARD / ASPECT?NOTE: Barriers can be Equipment, Process, or People

All Threats, Hazards, and Aspects are evaluated using the Five Fundamentals methodology to ensure each identified risk is appropriately mitigated.It is everyone's responsibility to "STOP WORK" when Unsafe Conditions or Conditions that do not support product quality or delivery are recognized.

NOTE: Risk Levels identified as "RL1" REQUIRE "STOP WORK" until controls are in place to reduce risk or impact.For "RL2" Risk Levels, if controls cannot be implemented the team must stop and revaluate task to determine new controls that can be implemented.

Each Threat, Hazard, and Aspect has been classified with a Risk Level. There are two Risk Level classifications (RL1 and RL2) and they are defined as:RL1 – Immediately Dangerous to Life or Health (IDLH), Life Critical, major environmental impact, Process Safety, serious injury, explosion, dropped objects, loss of well control, loss of primary containment, major property damage greater than $250,000, or a PL Reliability and Service Delivery incident classified as High Impact. RL2 – All remaining HSE not listed in RL1 and Service Delivery impacts classified as a Low or Medium Impact.

Incident Impact Definition procedure.

PPS Site Safety

Hard Hat, Safety Glasses, Flame Retardant Coveralls, Gloves, Safety Boots

Field Operations

All PPS Product Line ORAs

Defective, damaged, or inadequately

rated equipment used in the rig up,

resulting in:

- failure / flying debris when pressurized

- personnel injury

RL1 HSE RL2 HSE

Static potential from BHC equipment

creates spark in hazardous area. RL1 HSE RL2 HSE

Poor access and inadequate working

space around the equipment causes

personnel injury due to stretching / slip /

trip / fall when rigging up, operating, or

carrying out maintenance work.

RL2 HSE RL2 HSE

Incorrect test pressure applied (too high)

during hose / iron / piping pressure test,

resulting in component failure,

uncontrolled pressure release, whipping

hoses, flying debris, and personnel

injury.

RL1 HSE RL2 HSE

Maintenance work carried out on

pressurized BHC equipment, resulting in

uncontrolled pressure release and

personnel injury.

RL1 HSE RL2 HSE

Oil / coolant liquid spill during filling or

draining maintenance work creates a slip

hazard causing personnel injury.RL2 HSE RL2 HSE

Poor housekeeping creates slip / trip /

fall hazards, causing personnel injury.RL2 HSE RL2 HSE

Poor lighting during night time working

creates slip / trip / fall hazards, causing

personnel injury.RL2 HSE RL2 HSE

Poor access whilst working at height

causes personnel injury due to fall.

RL1 HSE RL2 HSE

Pinch points on BHC equipment or

customer plant, and oily / greasy working

conditions, causes hand injuries to

personnel.

RL1 HSE RL2 HSE

Excessive noise level exceeds

acceptable local HSE limits, or causes

personnel hearing damage (BHC

equipment, customer system

depressurization, customer's plant).

RL1 HSE RL2 HSE

Equipment rig up and function test

Care taken when draining or transferring liquids. Correct

PPE worn in accordance with SDS requirements. BHC

equipment has built in drip trays and is positioned within

spill bund (berm). Spill kit available at the work site. Spills

cleaned up immediately. Waste materials disposed of in

appropriate containers. Fouled clothing removed.

Equipment maintenance

BHC supervisor visually checks the equipment rig up and

references certification to verify suitably rated for the

intended application. Defective, suspect, or low pressure

rated components shall be replaced.

All BHC equipment with spark potential shall be earthed to

the plant's grounding points and continuity checks made by

the customer's qualified electrician.

BHC crew to be present whenever possible for equipment

positioning in the lay down area. Sufficient space shall be

allowed for safe rig up, operation, and maintenance work

on equipment. Certified, appropriate work at height system

used for access to high points.

BHC supervisor confirms the test pressure to be applied

during a toolbox talk. BHC supervisor visually checks the

equipment rig up prior to testing, and cross references

certification to verify pressure rating of components.

Hose / iron / piping secured with restraint devices. PRV of

appropriate set pressure fitted to the pump discharge.

BHC personnel check to ensure the equipment is shut

down, fully depressurized to atmospheric pressure, and

isolated prior to carrying out maintenance work in

compliance with standard operating procedure.

Requirement for good housekeeping discussed at toolbox

talk meeting by BHC supervisor prior to rig up operations.

Regular inspections of the work area carried out to ensure

standards are maintained.

BHC supervisor checks lighting around the work area to

ensure adequate. Substandard lighting brought to the

immediate attention of the customer representative.

BHC supervisor and customer representative visually

inspect the work site and identify high work areas requiring

access. Only certified ladders and scaffolding, erected by

qualified scaffolders, shall be used. Personnel shall wear a

full body double lanyard harness (where required).

Hazards of working at height discussed at a toolbox talk

meeting.

Pinch points identified and work area cleaned (wherever

possible), prior to carrying work activities. Gloves worn

(where practical) and correct tools used. Guards fitted to

moving parts on BHC equipment.

Hearing protection worn by personnel.

BHC equipment designed to minimize noise output during

operations (sound proofed wherever possible).

System depressurization rate controlled to minimize the

noise level generated. Gas routed to the flare / vent

header, or temporary silencer vent.

Uncontrolled when printed. Confirm the correct revision is used.

© 2010–2016 Baker Hughes Incorporated

Baker Hughes Confidential

Revised Date: 31-May-2016

Version A HSES-FM-ORA-001

OPERATIONAL RISK ASSESSMENT (ORA) FORMProcess:

Activity / Service Type:Related ORAs:Required PPE:

(Personal Protective Equipment)Location:

TASK /PROCESS STEP

THREATS / HAZARDS / ASPECTS

How can the TASK, STEP, or CHANGE go wrong?What are the potential Consequences?

What are the Gaps?

Uncontrolled RISK LEVEL

Controlled RISK LEVEL

Process and Pipeline Services

NOTE: Additional information and guidance on Service Delivery impacts can be viewed in the Reliability Assurance

CONTROLS / BARRIERS including OPERATIONAL PROCEDURES / CONTINGENCIES

What are the CONTROLS / BARRIERS, to Control, Mitigate, Eliminate, or Prevent the identified THREAT / HAZARD / ASPECT?NOTE: Barriers can be Equipment, Process, or People

All Threats, Hazards, and Aspects are evaluated using the Five Fundamentals methodology to ensure each identified risk is appropriately mitigated.It is everyone's responsibility to "STOP WORK" when Unsafe Conditions or Conditions that do not support product quality or delivery are recognized.

NOTE: Risk Levels identified as "RL1" REQUIRE "STOP WORK" until controls are in place to reduce risk or impact.For "RL2" Risk Levels, if controls cannot be implemented the team must stop and revaluate task to determine new controls that can be implemented.

Each Threat, Hazard, and Aspect has been classified with a Risk Level. There are two Risk Level classifications (RL1 and RL2) and they are defined as:RL1 – Immediately Dangerous to Life or Health (IDLH), Life Critical, major environmental impact, Process Safety, serious injury, explosion, dropped objects, loss of well control, loss of primary containment, major property damage greater than $250,000, or a PL Reliability and Service Delivery incident classified as High Impact. RL2 – All remaining HSE not listed in RL1 and Service Delivery impacts classified as a Low or Medium Impact.

Incident Impact Definition procedure.

PPS Site Safety

Hard Hat, Safety Glasses, Flame Retardant Coveralls, Gloves, Safety Boots

Field Operations

All PPS Product Line ORAs

Unauthorized personnel enter a BHC

work area and interfere with BHC

equipment or the customer's system,

creating a hazardous working condition

(trapped pressure, uncontrolled pressure

release, etc.).RL1 HSE RL2 HSE

Inclement weather conditions (such as

heavy rain, thunderstorms, high wind

speed, heavy snow, ice, extreme cold

temperatures, extreme high

temperatures) create dangerous working

conditions, causing personnel injury or

equipment damage.

RL1 HSE RL2 HSE

Work activities require personnel to

enter an excavated pit:

- wall collapse due to poor construction

- fall injury due to poor access / egress

- potential asphyxiation hazard

RL1 HSE RL2 HSE

General work activities

Work activities require personnel to

enter an enclosed space on the

customer's plant.

Potential asphyxiation hazard.

RL1 HSE RL2 HSE

Customer system preparation / reinstatement

Customer system still pressurized whilst

installing, or removing, BHC equipment

resulting in an uncontrolled pressure

release, damage to equipment, and

personnel injury.

RL1 HSE RL2 HSE

BHC equipment still pressurized during

rig down, resulting in an uncontrolled

pressure release, damage to equipment,

and personnel injury.

RL1 HSE RL2 HSE

Customer's permit to work system strictly complied with to

prevent work activity conflicts (SIMOPS).

BHC supervisor verifies barriers and warning signs are

correctly positioned around BHC equipment and work

areas, with particular attention paid to access points. BHC

documentation signed as confirmation (ITP, work pack).

Exclusion zones patrolled by BHC personnel and

unauthorized personnel removed.

BHC supervisor and customer representative shall monitor

the weather conditions in advance of test and determine

whether safe for personnel to work.

Appropriate PPE shall be worn (e.g. thermal coveralls, zero

hoods, gloves, and safety boots for cold weather working).

Stop work will be enacted where necessary.

General work activities

Customer responsible for building a structurally safe pit

with good access and egress for personnel.

Only certified ladders erected by qualified, competent

personnel to be installed and used for pit entry and exit.

Pit wall supports to be installed where needed and

inspected prior to personnel access.

Pit wall angled to prevent potential collapse.

Buddy system applied (min. 2 x BHC personnel).

Adequate access / egress to be set up for multiple

personnel evacuation (where required).

See enclosed space entry hazard (below) for safety

controls associated with asphyxiation hazards.

All enclosed space entries shall be carried out in strict

compliance with the customer's site safety protocol, permit

to work system, and BHC standard operating procedure.

Gas analysis shall be carried out by the customer

representative to ensure safe to enter.

Under no circumstances shall BHC personnel enter

enclosed spaces that have not been identified and risk

assessed in advance.

Buddy system applied (minimum 2 x BHC personnel).

Stand alone oxygen alarms (audible and visual) shall be

strategically positioned at the work area. Personal gas

monitors shall be worn by all personnel. Emergency

breathing apparatus strategically positioned at the work

area. Air movers may be used (if required).

Potential hazards associated with enclosed space entry,

safe working procedures to be followed, and emergency

response plan in the event of an incident shall be

discussed at a toolbox talk meeting prior to starting work.

Barriers and warning signs erected around the work area

to prevent entry of unauthorized personnel.

Work activities performed under permit to work. Trapped

pressure hazards discussed during toolbox talk meeting.

System pressure gauges checked for pressure before

connection of BHC equipment. Installation points isolated

and bleed points opened before breaking any joints.

Hazards of potential trapped pressure discussed at a

toolbox talk prior to rig down activities. BHC equipment

isolated and depressurized in compliance with standard

practice. Vents checked before breaking joints.

Uncontrolled when printed. Confirm the correct revision is used.

© 2010–2016 Baker Hughes Incorporated

Baker Hughes Confidential

Revised Date: 31-May-2016

Version A HSES-FM-ORA-001

OPERATIONAL RISK ASSESSMENT (ORA) FORMProcess:

Activity / Service Type:Related ORAs:Required PPE:

(Personal Protective Equipment)Location:

TASK /PROCESS STEP

THREATS / HAZARDS / ASPECTS

How can the TASK, STEP, or CHANGE go wrong?What are the potential Consequences?

What are the Gaps?

Uncontrolled RISK LEVEL

Controlled RISK LEVEL

Process and Pipeline Services

NOTE: Additional information and guidance on Service Delivery impacts can be viewed in the Reliability Assurance

CONTROLS / BARRIERS including OPERATIONAL PROCEDURES / CONTINGENCIES

What are the CONTROLS / BARRIERS, to Control, Mitigate, Eliminate, or Prevent the identified THREAT / HAZARD / ASPECT?NOTE: Barriers can be Equipment, Process, or People

All Threats, Hazards, and Aspects are evaluated using the Five Fundamentals methodology to ensure each identified risk is appropriately mitigated.It is everyone's responsibility to "STOP WORK" when Unsafe Conditions or Conditions that do not support product quality or delivery are recognized.

NOTE: Risk Levels identified as "RL1" REQUIRE "STOP WORK" until controls are in place to reduce risk or impact.For "RL2" Risk Levels, if controls cannot be implemented the team must stop and revaluate task to determine new controls that can be implemented.

Each Threat, Hazard, and Aspect has been classified with a Risk Level. There are two Risk Level classifications (RL1 and RL2) and they are defined as:RL1 – Immediately Dangerous to Life or Health (IDLH), Life Critical, major environmental impact, Process Safety, serious injury, explosion, dropped objects, loss of well control, loss of primary containment, major property damage greater than $250,000, or a PL Reliability and Service Delivery incident classified as High Impact. RL2 – All remaining HSE not listed in RL1 and Service Delivery impacts classified as a Low or Medium Impact.

Incident Impact Definition procedure.

PPS Site Safety

Hard Hat, Safety Glasses, Flame Retardant Coveralls, Gloves, Safety Boots

Field Operations

All PPS Product Line ORAs

Liquid spill during rig down of equipment

causes environmental damage or

personnel injury.

RL1 HSE RL2 HSE

Loose items left on equipment fall off

during back-load or transit, causing

personnel injury or equipment damage.RL1 HSE RL2 HSE

Rig down equipment

Visual check of all major equipment items and trailers prior

to moving.

Hazards of liquid spills discussed at a toolbox talk meeting

prior to rig down activities. Correct PPE worn in

accordance with SDS requirements.

BHC equipment fitted with drip trays and positioned within

a spill bund (berm). BHC equipment isolated, drained, and

rigged down in compliance with standard practice.

Spill kit placed at the lay down area. Spill cleaned up

immediately. Waste materials disposed of correctly in

appropriate containers. Fouled clothing removed.

Uncontrolled when printed. Confirm the correct revision is used.

© 2010–2016 Baker Hughes Incorporated

Baker Hughes Confidential

Revised Date: 31-May-2016

Helium Leak Detection

Safe Working Procedure

BH PPS Document Number: C-0382-21 / HLD/ PROC / 0001 Page 48 of 48 Helium Leak Detection – Safe Work Procedure

MEA Document Number:

Shell Document Number:

57242-7075-PRO-0001

2000-410-OA-6039-00007

Monadelphous (Shell)

Revision: 1 Date: 21-09-2021 Pitstop 2021-Swivel 1

Copyright Baker Hughes Company. All Rights Reserved.

Appendix C

Safety Data Sheets (SDS)

1. IDENTIFICATION OF THE MATERIAL AND SUPPLIER

FOOD GRADE LIQUID NITROGEN ● LIQUID NITROGEN ● NITROGEN (REFRIGERATED)Synonyms

INDUSTRIAL APPLICATIONSUses1.2 Uses and uses advised against

1.3 Details of the supplier of the product

SUPAGASSupplier name

5 Benson Rd, Ingleburn, NSW, 2565, AUSTRALIAAddress

(02) 8788 4444Telephone

(02) 8788 4445Fax

1300 275 021Emergency

1.4 Emergency telephone numbers

http://www.supagas.net.auWebsite

1.1 Product identifier

NITROGEN (REFRIGERATED LIQUID)Product name

2. HAZARDS IDENTIFICATION

CLASSIFIED AS HAZARDOUS ACCORDING TO SAFE WORK AUSTRALIA CRITERIA

2.2 GHS Label elements

Signal word WARNING

Store in a well-ventilated place.P403Storage statements

Get immediate medical advice/attention.P315Thaw frosted parts with lukewarm water. Do not rub affected area.P336

Response statements

Wear cold insulating gloves/face shield/eye protection.P282Prevention statements

Contains refrigerated gas; may cause cryogenic burns or injury.H281Hazard statements

Pictograms

Physical Hazards

Gases Under Pressure: Refrigerated liquefied gas

Health Hazards

Not classified as a Health Hazard

Environmental Hazards

Not classified as an Environmental Hazard

2.1 Classification of the substance or mixture

SDS Date: 27 Feb 2020

Revision No: 3.1ofPage 1 6

SAFETY DATA SHEET

1. IDENTIFICATION OF THE MATERIAL AND SUPPLIER

HELIUM, COMPRESSED ● SUPAGAS COMPRESSED HELIUM ● SUPAGAS HELIUMSynonyms

BALLOON GAS ● DILUENT ● LASER APPLICATIONS ● WELDING APPLICATIONSUses1.2 Uses and uses advised against

1.3 Details of the supplier of the product

SUPAGASSupplier name

5 Benson Road, Ingleburn, NSW, 2565, AUSTRALIAAddress

(02) 8788 4444Telephone

(02) 8788 4445Fax

1300 651 106 (NSW/ACT/QLD)Emergency1300 275 021 (VIC/TAS/SA/WA/NT)Emergency

1.4 Emergency telephone numbers

http://www.supagas.net.auWebsite

1.1 Product identifier

HELIUMProduct name

2. HAZARDS IDENTIFICATION

CLASSIFIED AS HAZARDOUS (GHS ONLY) ACCORDING TO SAFE WORK AUSTRALIA CRITERIA

2.2 GHS Label elements

Signal word WARNING

Protect from sunlight. Store in a well-ventilated place.P410 + P403Storage statements

Response statements

None allocated.

Prevention statementsNone allocated.

Contains gas under pressure; may explode if heated.H280Hazard statements

Pictograms

Physical Hazards

Gases Under Pressure: Compressed gas

Health Hazards

Not classified as a Health Hazard

Environmental Hazards

Not classified as an Environmental Hazard

2.1 Classification of the substance or mixture

SDS Date: 09 Apr 2019

Version No: 3ofPage 1 6

HELIUMPRODUCT NAME

Asphyxiant. Effects are proportional to oxygen displacement.2.3 Other hazards

Disposal statementsNone allocated.

3. COMPOSITION/ INFORMATION ON INGREDIENTS

Ingredient CAS Number EC Number Content

>99.99%7440-59-7 231-168-5HELIUM

3.1 Substances / Mixtures

4. FIRST AID MEASURES

None required.4.1 Description of first aid measures

Eye

If inhaled, remove from contaminated area. To protect rescuer, use an Air-line respirator or Self ContainedBreathing Apparatus (SCBA). Apply artificial respiration if not breathing. Give oxygen if available.

Inhalation

None required.Skin

Ingestion is not considered a potential route of exposure.Ingestion

None allocated.First aid facilities

In high concentrations may cause asphyxiation. Symptoms may include loss of mobility / consciousness. Victim may not be aware ofasphyxiation.

4.2 Most important symptoms and effects, both acute and delayed

4.3 Immediate medical attention and special treatment neededTreat symptomatically.

5. FIRE FIGHTING MEASURES

Non flammable.5.2 Special hazards arising from the substance or mixture

Temperatures in a fire may cause cylinders to rupture. Cool cylinders or containers exposed to fire by applying water from a protectedlocation. Remove cool cylinders from the path of the fire. Evacuate the area if unable to keep cylinders cool. Do not approachcylinders or containers suspected of being hot.

5.3 Advice for firefighters

2T2 Fine Water Spray.T Wear full fire kit and breathing apparatus. Dilute spill and run-off.

5.4 Hazchem code

Use water fog to cool containers from protected area.5.1 Extinguishing media

6. ACCIDENTAL RELEASE MEASURES

If the cylinder is leaking, evacuate area of personnel. Inform manufacturer/supplier of leak. Use Personal Protective Equipment (PPE)as detailed in Section 8 of the SDS.

6.1 Personal precautions, protective equipment and emergency procedures

Prevent from entering sewers, basements and workpits, or any place where its accumulation can be dangerous.6.2 Environmental precautions

Carefully move material to a well ventilated remote area, then allow to discharge if safe to do so. Do not attempt to repair leaking valveor cylinder safety devices.

6.3 Methods of cleaning up

SDS Date: 09 Apr 2019

Version No: 3ofPage 2 6

HELIUMPRODUCT NAME

See Sections 8 and 13 for exposure controls and disposal.6.4 Reference to other sections

7. HANDLING AND STORAGE

Cylinders should be stored below 65°C in a secure area, upright and restrained to prevent cylinders from falling. Cylinders should alsobe stored in a dry, well ventilated area constructed of non-combustible material with firm level floor (preferably concrete), away fromareas of heavy traffic and emergency exits.

7.2 Conditions for safe storage, including any incompatibilities

No information provided.7.3 Specific end uses

7.1 Precautions for safe handling

Use of safe work practices are recommended to avoid inhalation. Do not drag, drop, slide or roll cylinders. The uncontrolled release ofa gas under pressure may cause physical harm. Use a suitable hand truck for cylinder movement.

8. EXPOSURE CONTROLS / PERSONAL PROTECTION

8.1 Control parameters

Exposure standards

Ingredient ReferenceTWA STEL

ppm mg/m³ ppm mg/m³

Helium SWA [AUS] Asphyxiant

Biological limitsNo biological limit values have been entered for this product.

PPE

Eye / Face Wear safety glasses.

Hands Wear leather gloves.

Body Wear coveralls and safety boots.

Respiratory Where an inhalation risk exists, wear Self Contained Breathing Apparatus (SCBA) or an Air-line respirator.

Provide suitable ventilation to minimise or eliminate exposure. Confined areas (e.g. tanks) should beadequately ventilated or gas tested.

8.2 Exposure controlsEngineering controls

9. PHYSICAL AND CHEMICAL PROPERTIES

9.1 Information on basic physical and chemical propertiesCOLOURLESS GASAppearanceODOURLESSOdourNON FLAMMABLEFlammabilityNOT RELEVANTFlash point-268.9°CBoiling point-272.2°C @ 26 atmMelting pointNOT AVAILABLEEvaporation rateNOT AVAILABLEpH< 1 (Air = 1)Vapour densityNOT AVAILABLESpecific gravitySLIGHTLY SOLUBLESolubility (water)NOT AVAILABLEVapour pressureNOT RELEVANTUpper explosion limit

SDS Date: 09 Apr 2019

Version No: 3ofPage 3 6

HELIUMPRODUCT NAME

9.1 Information on basic physical and chemical propertiesNOT RELEVANTLower explosion limitNOT AVAILABLEPartition coefficientNOT AVAILABLEAutoignition temperatureNOT AVAILABLEDecomposition temperatureNOT AVAILABLEViscosityNOT AVAILABLEExplosive propertiesNOT AVAILABLEOxidising propertiesNOT AVAILABLEOdour threshold

9.2 Other information100 %% Volatiles

10. STABILITY AND REACTIVITY

10.2 Chemical stability

Stable under recommended conditions of storage.

10.4 Conditions to avoid

Avoid shock, friction, heavy impact, heat, sparks, open flames and other ignition sources.

10.5 Incompatible materials

Compatible with most commonly used materials.

This material will not decompose to form hazardous products other than that already present.10.6 Hazardous decomposition products

Polymerization will not occur.

10.3 Possibility of hazardous reactions

10.1 ReactivityCarefully review all information provided in sections 10.2 to 10.6.

11. TOXICOLOGICAL INFORMATION

Based on available data, the classification criteria are not met.Acute toxicity

Not classified as a skin irritant.Skin

Not classified as an eye irritant.Eye

Not classified as causing skin or respiratory sensitisation.Sensitisation

Asphyxiant. Effects are proportional to oxygen displacement. Over exposure may result in dizziness,drowsiness, weakness, fatigue, breathing difficulties and unconsciousness.

STOT - singleexposure

Not applicable to gases and gas mixtures.Aspiration

Not classified as causing organ damage from repeated exposure.STOT - repeatedexposure

Not classified as a reproductive toxin.Reproductive

Not classified as a carcinogen.Carcinogenicity

Not classified as a mutagen.Mutagenicity

11.1 Information on toxicological effects

12. ECOLOGICAL INFORMATION

12.1 Toxicity

No ecological damage caused by this product.

12.2 Persistence and degradabilityThe product is expected to biodegrade and is not expected to persist for long periods in an aquatic environment.

12.3 Bioaccumulative potentialThis product does not bioaccumulate.

SDS Date: 09 Apr 2019

Version No: 3ofPage 4 6

HELIUMPRODUCT NAME

12.4 Mobility in soil

The substance is a gas, not applicable.

No information provided.

12.5 Other adverse effects

13. DISPOSAL CONSIDERATIONS

Cylinders should be returned to the manufacturer or supplier for disposal of contents.

13.1 Waste treatment methods

Waste disposal

Dispose of in accordance with relevant local legislation.Legislation

14. TRANSPORT INFORMATION

LAND TRANSPORT (ADG) SEA TRANSPORT (IMDG / IMO) AIR TRANSPORT (IATA / ICAO)

None allocated.

2.2 2.2

None allocated. None allocated.

2.214.3 Transporthazard class

14.4 Packing Group

HELIUM, COMPRESSED

1046

HELIUM, COMPRESSED

1046 1046

HELIUM, COMPRESSED

14.1 UN Number

14.2 ProperShipping Name

No information provided.

14.5 Environmental hazards

2THazchem code

F-C, S-VEMS

Ensure cylinder is separated from driver and that outlet of relief device is not obstructed.Other information

2C1GTEPG

14.6 Special precautions for user

CLASSIFIED AS A DANGEROUS GOOD BY THE CRITERIA OF THE ADG CODE

15. REGULATORY INFORMATION

A poison schedule number has not been allocated to this product using the criteria in the Standard for theUniform Scheduling of Medicines and Poisons (SUSMP).

15.1 Safety, health and environmental regulations/legislation specific for the substance or mixture

Poison schedule

AUSTRALIA: AICS (Australian Inventory of Chemical Substances)All components are listed on AICS, or are exempt.

Inventory listings

Safework Australia criteria is based on the Globally Harmonised System (GHS) of Classification andLabelling of Chemicals.

Classifications

16. OTHER INFORMATION

APPLICATION METHOD: Gas regulator of suitable pressure and flow rating fitted to cylinder ormanifold with low pressure gas distribution to equipment.

Additional information

SDS Date: 09 Apr 2019

Version No: 3ofPage 5 6

HELIUMPRODUCT NAME

PERSONAL PROTECTIVE EQUIPMENT GUIDELINES:The recommendation for protective equipment contained within this report is provided as a guideonly. Factors such as form of product, method of application, working environment, quantity used,product concentration and the availability of engineering controls should be considered before finalselection of personal protective equipment is made.

HEALTH EFFECTS FROM EXPOSURE:It should be noted that the effects from exposure to this product will depend on several factorsincluding: form of product; frequency and duration of use; quantity used; effectiveness of controlmeasures; protective equipment used and method of application. Given that it is impractical toprepare a report which would encompass all possible scenarios, it is anticipated that users willassess the risks and apply control methods where appropriate.

ACGIH American Conference of Governmental Industrial HygienistsCAS # Chemical Abstract Service number - used to uniquely identify chemical compoundsCNS Central Nervous SystemEC No. EC No - European Community NumberEMS Emergency Schedules (Emergency Procedures for Ships Carrying Dangerous

Goods)GHS Globally Harmonized SystemGTEPG Group Text Emergency Procedure GuideIARC International Agency for Research on CancerLC50 Lethal Concentration, 50% / Median Lethal ConcentrationLD50 Lethal Dose, 50% / Median Lethal Dosemg/m³ Milligrams per Cubic MetreOEL Occupational Exposure LimitpH relates to hydrogen ion concentration using a scale of 0 (high acidic) to 14 (highly

alkaline).ppm Parts Per MillionSTEL Short-Term Exposure LimitSTOT-RE Specific target organ toxicity (repeated exposure)STOT-SE Specific target organ toxicity (single exposure)SUSMP Standard for the Uniform Scheduling of Medicines and PoisonsSWA Safe Work AustraliaTLV Threshold Limit ValueTWA Time Weighted Average

Abbreviations

This document has been compiled by RMT on behalf of the manufacturer, importer or supplier of theproduct and serves as their Safety Data Sheet ('SDS').

It is based on information concerning the product which has been provided to RMT by themanufacturer, importer or supplier or obtained from third party sources and is believed to representthe current state of knowledge as to the appropriate safety and handling precautions for the productat the time of issue. Further clarification regarding any aspect of the product should be obtaineddirectly from the manufacturer, importer or supplier.

While RMT has taken all due care to include accurate and up-to-date information in this SDS, it doesnot provide any warranty as to accuracy or completeness. As far as lawfully possible, RMT acceptsno liability for any loss, injury or damage (including consequential loss) which may be suffered orincurred by any person as a consequence of their reliance on the information contained in this SDS.

Report status

Risk Management Technologies 5 Ventnor Ave, West Perth Western Australia 6005 Phone: +61 8 9322 1711 Fax: +61 8 9322 1794 Email: [email protected] Web: www.rmtglobal.com

Prepared by

[ End of SDS ]

SDS Date: 09 Apr 2019

Version No: 3ofPage 6 6

NITROGEN (REFRIGERATED LIQUID)PRODUCT NAME

Asphyxiant. Effects are proportional to oxygen displacement.2.3 Other hazards

Disposal statementsNone allocated.

3. COMPOSITION/ INFORMATION ON INGREDIENTS

Ingredient CAS Number EC Number Content

99.9%7727-37-9 231-783-9NITROGEN

3.1 Substances / Mixtures

4. FIRST AID MEASURES

Cold burns: Immediately flush with tepid water or with sterile saline solution. Hold eyelids apart and irrigatefor 15 minutes. Seek medical attention.

4.1 Description of first aid measures

Eye

If inhaled, remove from contaminated area. To protect rescuer, use an Air-line respirator or Self ContainedBreathing Apparatus (SCBA). Apply artificial respiration if not breathing. Give oxygen if available.

Inhalation

Cold burns: Remove contaminated clothing and gently flush affected areas with warm water (30°C) for 15minutes. It is recommended that warm water is applied to clothing before removing it so as to prevent furtherskin damage. Apply sterile dressing and treat as for a thermal burn. For large burns, immerse in warm waterfor 15 minutes. DO NOT apply any form of direct heat. Seek immediate medical attention.

Skin

Ingestion is not considered a potential route of exposure.Ingestion

Eye wash facilities and safety shower should be available.First aid facilities

In high concentrations may cause asphyxiation. Direct contact with the liquefied material or escaping compressed gas may causefrostbite injury.

4.2 Most important symptoms and effects, both acute and delayed

4.3 Immediate medical attention and special treatment neededTreat symptomatically.

5. FIRE FIGHTING MEASURES

Non flammable.5.2 Special hazards arising from the substance or mixture

Temperatures in a fire may cause cylinders to rupture. Cool cylinders or containers exposed to fire by applying water from a protectedlocation. Remove cool cylinders from the path of the fire. Evacuate the area if unable to keep cylinders cool. Do not approachcylinders or containers suspected of being hot.

5.3 Advice for firefighters

2T2 Fine Water Spray.T Wear full fire kit and breathing apparatus. Dilute spill and run-off.

5.4 Hazchem code

Use water fog to cool containers from protected area.5.1 Extinguishing media

6. ACCIDENTAL RELEASE MEASURES

If the cylinder is leaking, evacuate area of personnel. Inform manufacturer/supplier of leak. Use Personal Protective Equipment (PPE)as detailed in Section 8 of the SDS. Ventilate area where possible and eliminate ignition sources.

6.1 Personal precautions, protective equipment and emergency procedures

Prevent from entering sewers, basements and workpits, or any place where its accumulation can be dangerous.6.2 Environmental precautions

SDS Date: 27 Feb 2020

Revision No: 3.1ofPage 2 6

NITROGEN (REFRIGERATED LIQUID)PRODUCT NAME

Stop the flow of material, if this is without risk. If the leak is irreparable, move the cylinder to a safe and well ventilated area, and allowto discharge. Keep area evacuated and free from ignition sources until any leaked or spilled liquid has evaporated.

6.3 Methods of cleaning up

See Sections 8 and 13 for exposure controls and disposal.6.4 Reference to other sections

7. HANDLING AND STORAGE

Portable liquid container should be stored below 65°C in a secure area and upright to prevent from falling. Portable liquid containersshould also be stored in a dry, well ventilated area constructed of non-combustible material with firm level floor (preferably concrete),away from areas of heavy traffic and emergency exits.

7.2 Conditions for safe storage, including any incompatibilities

No information provided.7.3 Specific end uses

7.1 Precautions for safe handling

Before use carefully read the product label. Use of safe work practices are recommended to avoid eye or skin contact and inhalation.Observe good personal hygiene, including washing hands before eating. Prohibit eating, drinking and smoking in contaminated areas.

8. EXPOSURE CONTROLS / PERSONAL PROTECTION

8.1 Control parameters

Exposure standards

Ingredient ReferenceTWA STEL

ppm mg/m³ ppm mg/m³

Nitrogen SWA [AUS] Asphyxiant

Biological limitsNo biological limit values have been entered for this product.

PPE

Eye / Face Wear safety glasses.

Hands Wear leather or insulated gloves.

Body Wear coveralls.

Respiratory Where an inhalation risk exists, wear Self Contained Breathing Apparatus (SCBA) or an Air-line respirator.

Avoid inhalation. Use in well ventilated areas. Where an inhalation risk exists, mechanical explosion proofextraction ventilation is recommended.

8.2 Exposure controlsEngineering controls

9. PHYSICAL AND CHEMICAL PROPERTIES

9.1 Information on basic physical and chemical propertiesCOLOURLESS GASAppearanceODOURLESSOdourNON FLAMMABLEFlammabilityNOT RELEVANTFlash point-195.8°CBoiling point-210°CMelting pointNOT RELEVANTEvaporation rateNOT RELEVANTpH0.967 (Air = 1)Vapour densityNOT AVAILABLESpecific gravity

SDS Date: 27 Feb 2020

Revision No: 3.1ofPage 3 6

NITROGEN (REFRIGERATED LIQUID)PRODUCT NAME

9.1 Information on basic physical and chemical propertiesNOT AVAILABLESolubility (water)NOT RELEVANTVapour pressureNOT RELEVANTUpper explosion limitNOT RELEVANTLower explosion limitNOT AVAILABLEPartition coefficientNOT AVAILABLEAutoignition temperatureNOT AVAILABLEDecomposition temperatureNOT AVAILABLEViscosityNOT AVAILABLEExplosive propertiesNOT AVAILABLEOxidising propertiesNOT AVAILABLEOdour threshold

9.2 Other information-146.95°CCritical temperature808.6 kg/m³ @ 15°CDensity

10. STABILITY AND REACTIVITY

10.2 Chemical stability

Stable under recommended conditions of storage.

10.4 Conditions to avoid

Avoid heat, sparks, open flames and other ignition sources.

10.5 Incompatible materials

Compatible with most commonly used materials.

May evolve toxic gases if heated to decomposition.10.6 Hazardous decomposition products

Polymerization will not occur.

10.3 Possibility of hazardous reactions

10.1 ReactivityCarefully review all information provided in sections 10.2 to 10.6.

11. TOXICOLOGICAL INFORMATION

Based on available data, the classification criteria are not met.Acute toxicity

Not classified as a skin irritant. Contact with the liquefied material or escaping compressed gas may causefrostbite injury.

Skin

Not classified as an eye irritant. Contact with the liquefied material or escaping compressed gas may causefrostbite injury.

Eye

Not classified as causing skin or respiratory sensitisation.Sensitisation

Asphyxiant. Effects are proportional to oxygen displacement. Over exposure may result in dizziness,drowsiness, weakness, fatigue, breathing difficulties and unconsciousness.

STOT - singleexposure

Not classified as causing aspiration.Aspiration

Not classified as causing organ damage from repeated exposure.STOT - repeatedexposure

Not classified as a reproductive toxin.Reproductive

Not classified as a carcinogen.Carcinogenicity

Not classified as a mutagen.Mutagenicity

11.1 Information on toxicological effects

12. ECOLOGICAL INFORMATION

12.1 Toxicity

No information provided.

SDS Date: 27 Feb 2020

Revision No: 3.1ofPage 4 6

NITROGEN (REFRIGERATED LIQUID)PRODUCT NAME

12.2 Persistence and degradabilityNo information provided.

12.4 Mobility in soil

No information provided.

No information provided.

12.5 Other adverse effects

12.3 Bioaccumulative potentialNo information provided.

13. DISPOSAL CONSIDERATIONS

Cylinders should be returned to the manufacturer or supplier for disposal of contents.

13.1 Waste treatment methods

Waste disposal

Dispose of in accordance with relevant local legislation.Legislation

14. TRANSPORT INFORMATION

LAND TRANSPORT (ADG) SEA TRANSPORT (IMDG / IMO) AIR TRANSPORT (IATA / ICAO)

None allocated.

2.2 2.2

None allocated. None allocated.

2.214.3 Transporthazard class

14.4 Packing Group

NITROGEN, REFRIGERATEDLIQUID

1977

NITROGEN, REFRIGERATEDLIQUID

1977 1977

NITROGEN, REFRIGERATEDLIQUID

14.1 UN Number

14.2 ProperShipping Name

No information provided.

14.5 Environmental hazards

2THazchem code

F-C, S-VEmS

Transport on open top vehicles in accordance with local legislation.Other information

2C3GTEPG

14.6 Special precautions for user

CLASSIFIED AS A DANGEROUS GOOD BY THE CRITERIA OF THE ADG CODE

15. REGULATORY INFORMATION

A poison schedule number has not been allocated to this product using the criteria in the Standard for theUniform Scheduling of Medicines and Poisons (SUSMP).

15.1 Safety, health and environmental regulations/legislation specific for the substance or mixture

Poison schedule

AUSTRALIA: AICS (Australian Inventory of Chemical Substances)All components are listed on AICS, or are exempt.EUROPE:EINECS (European Inventory of Existing Chemical Substances)All components are listed on EINECS, or are exempt.

Inventory listings

Safework Australia criteria is based on the Globally Harmonised System (GHS) of Classification andLabelling of Chemicals.

Classifications

SDS Date: 27 Feb 2020

Revision No: 3.1ofPage 5 6

NITROGEN (REFRIGERATED LIQUID)PRODUCT NAME

16. OTHER INFORMATIONPERSONAL PROTECTIVE EQUIPMENT GUIDELINES:The recommendation for protective equipment contained within this report is provided as a guideonly. Factors such as form of product, method of application, working environment, quantity used,product concentration and the availability of engineering controls should be considered before finalselection of personal protective equipment is made.

HEALTH EFFECTS FROM EXPOSURE:It should be noted that the effects from exposure to this product will depend on several factorsincluding: form of product; frequency and duration of use; quantity used; effectiveness of controlmeasures; protective equipment used and method of application. Given that it is impractical toprepare a report which would encompass all possible scenarios, it is anticipated that users willassess the risks and apply control methods where appropriate.

ACGIH American Conference of Governmental Industrial HygienistsCAS # Chemical Abstract Service number - used to uniquely identify chemical compoundsCNS Central Nervous SystemEC No. EC No - European Community NumberEMS Emergency Schedules (Emergency Procedures for Ships Carrying Dangerous

Goods)GHS Globally Harmonized SystemGTEPG Group Text Emergency Procedure GuideIARC International Agency for Research on CancerLC50 Lethal Concentration, 50% / Median Lethal ConcentrationLD50 Lethal Dose, 50% / Median Lethal Dosemg/m³ Milligrams per Cubic MetreOEL Occupational Exposure LimitpH relates to hydrogen ion concentration using a scale of 0 (high acidic) to 14 (highly

alkaline).ppm Parts Per MillionSTEL Short-Term Exposure LimitSTOT-RE Specific target organ toxicity (repeated exposure)STOT-SE Specific target organ toxicity (single exposure)SUSMP Standard for the Uniform Scheduling of Medicines and PoisonsSWA Safe Work AustraliaTLV Threshold Limit ValueTWA Time Weighted Average

Abbreviations

This document has been compiled by RMT on behalf of the manufacturer, importer or supplier of theproduct and serves as their Safety Data Sheet ('SDS').

It is based on information concerning the product which has been provided to RMT by themanufacturer, importer or supplier or obtained from third party sources and is believed to representthe current state of knowledge as to the appropriate safety and handling precautions for the productat the time of issue. Further clarification regarding any aspect of the product should be obtaineddirectly from the manufacturer, importer or supplier.

While RMT has taken all due care to include accurate and up-to-date information in this SDS, it doesnot provide any warranty as to accuracy or completeness. As far as lawfully possible, RMT acceptsno liability for any loss, injury or damage (including consequential loss) which may be suffered orincurred by any person as a consequence of their reliance on the information contained in this SDS.

Report status

Risk Management Technologies 5 Ventnor Ave, West Perth Western Australia 6005 Phone: +61 8 9322 1711 Fax: +61 8 9322 1794 Email: [email protected] Web: www.rmtglobal.com

Prepared by

Additional information

[ End of SDS ]

SDS Date: 27 Feb 2020

Revision No: 3.1ofPage 6 6

Baker Hughes – 140LT-1001A/B/C Leak Test Work Method Statement

57241-7010-FRM-0001 Rev 02 Discipline: Technical Execution

Appendix 2: TP-003 - Helium Leak Detection Test Pack - 140LT-1001A/B/C Leak Test

Rev. Revision

Date

B 21-Sep-2021

A 16-Sep-2021

Copy #1

Copy #2

21-Sep-21 TP 003

Senthil Murugesan

Matthew McGonigle

Zh Sherkeshbayeva

Issued for Review

Operations Manager

Customer Rep. #1

Checked by

Description

Customer 140LT-1001A/B/C Leak Test

Distribution: Original PPS Office

PPS Job Site Prelude Pitstop Oct 2021

Copyright Baker Hughes Company. All Rights Reserved. HLD Test Pack No.:

ZS

Approved by Customer Rep. #2

Re-issued after comments

Senior Project Engineer

JSZS

Approved by

Approved by

Baker Hughes

Baker Hughes Customer

Checked by

Approved byApproved byOriginator

Revision History

Baker Hughes

Baker Hughes

Originator

Shell Australia

Prelude FLNG

C-0382-21

Prelude Pitstop Oct 2021

Project Engineer

DateSignature

Joseph Szczepaniak Project Engineer

Document Title

Customer Work Order Number

Company Job Title

Helium Leak Detection Test Pack

PPS Reference Number C-0382-21 / HLD / TP 003

Revision Number

Test Pack Name

Test Pack Number

140LT-1001A/B/C Leak Test

Customer Reference Number

TP 003

B

Customer

Project

Location / Facility

PPS Job Number

Name

Customer Contract Number

Signatories for Current Revision Document

Signatories

JS

Shell Australia

Item Revision Section Page Amended Date

1 No. No. N0. By

Yes

2

1 of 1

TP 003

Revision Date:

C-0382-21 / HLD / TP 003Document Number:

Revision Number: B

21-Sep-2021

Shell Australia

HLD Test Pack No.:Copyright Baker Hughes Company. All Rights Reserved.

Prelude Pitstop Oct 2021

140LT-1001A/B/C Leak Test

1 Document Amendment Record #1

Description of Change

1Yes

3 A1

B

C4

C5

C6

3 C7

D

E1

E2

E3

3

3

3

TP 003

Inspection and Test Plan (ITP)

Contents

Test Pack Information

Marked Drawings

Test Limit Isolations Checklist

Safety Components Checklist

Actuated Valve Checklist

System Depressurisation Checklist

Leak Description Report

Leak Detection Completion Certificate

Witness Joint Register

Document Number: C-0382-21 / HLD / TP 003 Shell Australia

Copyright Baker Hughes Company. All Rights Reserved. HLD Test Pack No.:

Revision Number: B Prelude Pitstop Oct 2021

Revision Date: 21-Sep-2021 140LT-1001A/B/C Leak Test

MetricUnit

barg

Yes barg

barg

No m3

2.0 barg 3.0 % 3.4 % 2.7 % N/A

16.9 barg 25.0 % 28.5 % 22.5 % N/A

33.8 barg 50.0 % 56.9 % 45.0 % N/A

50.6 barg 75.0 % 85.4 % 67.5 % N/A

67.5 barg 100.0 % 113.8 % 90.0 % N/A

0.0 barg

bar/min 1.0

sm3/min N/A

bar/min 0.01 sm3 Conc'n: 1.00%

sm3/min

barg

N/A barg

71.6 barg sm3/min

sm3/min

sm3/min

sm3/min

N/A sm3/min 300.0 barg

50 scf/yr

100 scf/yr

N/A scf/yr

20 scf/yr

1 1 of 2

1 TP 003

Test Pack Name N/A

% Design Press. (PD)

Normal Operating Pressure

Rotating Equipment 0.01

Increment #4

Increment #2

Number of Leak Test Joints Nominated joints

A1. Test Pack Information #1

% Test Press. (PT)Pressure

75.0

Increment #3

System Details

59.3

% System PSV

System PSV Set Pressure

Customer Ref. No. 0

System Free Volume

Increment #1

Test Pack Number System Design Pressure

Incremental Pressures and Final Test Pressure (PT)

TP 003

140LT-1001A/B/C Leak Test

% Normal Op.

System Pressurization and Depressurization Test Gas

Max. Pressurization Rate 7.0 Nitrogen Gas

Max. Volumetric Pump Rate N/A LN2 Equivalent

TEST PRESSURE (PT)

Residual Pressure Pressure left in the system upon completion of depressurisation.

litres

sm3

Max. Depressurization Rate 7.0

Max. Volumetric Vent Rate N/A Verify depressurization rate using "Test Pressure Monitoring Points"

PPS Equipment

Set Pressure PRV Relief Rate @ PRV% System PSV% Design Pressure

Helium Gas

Verify vent system pressure using "Vent Path Pressure Monitoring Points"Vent System Max. Pressure

OPPS Set Pressure Inlet Connection

Safety Equipment

Temporary PRV #2

Temporary PRV #1 95.4%

Temporary PRV #3

Temporary PRV #4

Use the PRV Calculator in PPS Toolbox to quantify PRV relief rate.

Pressurization Pump 99%N2+1%He Gas quads Max. Flow Rate Max. Pressure

Leak Test and Acceptance Criteria

Leak TestPressurize the system with 1% helium / 99% nitrogen test gas mixture to the nominated test pressure (PT).

Check all potential leak sources for leakage using a calibrated helium leak detector.

Clamp connectors

All other potential leak sources

ii. Quantified leak rate is below the maximum allowable leak rate threshold (see above).

iii. The leak is accepted as a "Witness Joint" by the Customer Representative.

Valve glands and bonnets

All identified leak sources to be repaired and re-tested until one of the following conditions is met:

C-0382-21 / HLD / TP 003Document Number:

Leak rates BELOW the threshold are a PASS. Leak rates ABOVE the threshold are a FAIL.

i. Leak free (no helium detected)

Shell Australia

Acceptance

Pressure to be maintained within 10% (preferably but not mandatory for this test) of the test pressure for the duration of the test ('top up' if necessary).

Maximum allowable leak rate threshold from any single leak source not to exceed:

Pig launcher and receiver doors

B Prelude Pitstop Oct 2021

Revision Date: 21-Sep-2021 140LT-1001A/B/C Leak Test

Copyright Baker Hughes Company. All Rights Reserved. HLD Test Pack No.:

Revision Number:

No.

#1

#2

#3

#4

#5

#6

#7

#8

#9

#10

1 2 of 2

TP 003

Injection Point #1

Temporary PRV Point #1

Depressurization Point #1

Test Pack Notes

A1. Test Pack Information #2

.

System Connection and Monitoring Points

Design Pressure

Test Component Type

U14000-PX-2365-00002-001

U14000-PX-2365-00002-001

Drawing Number

10mm Drip ring of vent flange at S1/S2/S3

Temp PRV fitted to 6-way Injection manifold

Bleed valve at 6-way Injection manifold

Location

U14000-PX-2365-00002-001

Adjacent Systems

(Adjacent System)

PDA

System Name Design Pressure

Revision Number: B Prelude Pitstop Oct 2021

Revision Date: 21-Sep-2021 140LT-1001A/B/C Leak Test

Copyright Baker Hughes Company. All Rights Reserved. HLD Test Pack No.:

The pressurisation of the test system is with N2+He Pre-mixed gas quads. The quads will be connected to BH PPS 6-way manifold.

BH PPS 6-way Manifold will be fitted with Temp PRV, pressure gauge and depressurisation valve.

6 spools (of 140LT-1001) will be pressurised via 6 Injection points at once via 6-way manifold.

Document Number: C-0382-21 / HLD / TP 003 Shell Australia

HP / LP Interface Location

( Drawing Number)Ratio (%)

PD / PDA

1 No. Type Revision No. Type Revision

No 1 PEFS 07Z 46

0 2 PEFS 06Z 47

3 PEFS 07Z 48

4 49

5 50

6 51

7 52

8 53

9 54

10 55

11 56

12 57

13 58

14 59

15 60

16 61

17 62

18 63

19 64

20 65

21 66

22 67

23 68

24 69

25 70

26 71

27 72

28 73

29 74

30 75

31 76

32 77

33 78

34 79

35 80

36 81

37 82

38 83

39 84

40 85

41 86

42 87

43 88

44 89

45 90

Note:

1 of 1

TP 003

B. Marked Drawings #1

Test Pack Drawing Numbers

U14000-PX-2365-00003-001

Drawing Number Drawing Number

U14000-PX-2365-00002-001

U14000-PX-2365-00001-001

Drawing 'Type' data entries listed as 'Plot Plan' or 'Deck Plan' represent test exclusion zone

boundary drawings and / or equipment lay down area plans.

Document Number: C-0382-21 / HLD / TP 003

Copyright Baker Hughes Company. All Rights Reserved. HLD Test Pack No.:

Shell Australia

Prelude Pitstop Oct 2021

140LT-1001A/B/C Leak Test

Revision Number: B

Revision Date: 21-Sep-2021

1501UY

1007PG

1005FFC

2810UZ

Moo3

1010TI

1003FI

2010UZ

1001LT

1009TI

2020UZ

1006PG

1001LI

1001LY

1005PG

2020UZ

1038FY

1038FC

1001LCA

2010UZ

1008TI

1001LZA

RS

TO KT-14001140011 140-00003-1

FROM E-14001/02140001 140-00001-1

TO FCV-3111140012 140-20008-1

FROM PCA-1022A140014140-00004-1

TO E-14001140004140-00001-1

TO C-14001140002 140-00004-1

TO FCV-1038140013 140-00003-1

TO C-14001140010 140-00004-1

FROM C-14001140003140-00004-1

5. NITROGEN CONNECTION FOR MAINTENANCE.

7. DELETED.

LIVIN

GQU

ARTE

R

T

F

R

3S1 2S1 1S3 1S1

4P2 3P2 2P3 1P24P1 3P1 2P2 2P1 1P1

4S1

16. DELETED.

600 MIN

MIN

11. PG TO BE READABLE FROM GLOBE VALVES.

MIN

MIN

12. PG TO BE READABLE FROM GLOBE VALVE.

BTL

2. CRYOGENIC RELIEF VALVE. FOR INSULATION DETAILS REFER TO DRAWING :2000-110-G000-GE00-G00000-PX-2365-00006-001.

14. MINIMUM PIPE LENGTH BETWEEN LAST VALVE OR LAST PIPE CONTRACTION / EXPANSION AND EQUIPMENTNOZZLE SHALL BE 10D.

4. DELETED

MIN

8. DELETED.

10. TAPPING POINT FOR PORTABLE PDI.

MIN

3. DELETED.

600 MIN

MIN

2D M

IN

MIN

MIN

20. VALVE TO BE LOCATED AT LEAST 2800MM BELOW V-14001 TANGENT LINE.

600 M

IN

MIN

9. TEMPORARY STRAINER FOR START-UP. SPOOL STRAINER TO BE RETAINED AFTER START-UP WITHOUT THE FINEMESH.

13. FEED LINE ARRIVAL PREFERENCE IS WITH LAST ELBOW IN VERTICAL PLANE.WHEN LAST ELBOW IS INHORIZONTAL PLANE, 10D MINIMUM STRAIGHT PIPE BETWEEN LAST ELBOW AND EQUIPMENT NOZZLE ISREQUIRED.

MIN

18. DELETED.

TL

600 MIN

MIN

19. PROVIDE TEMPORARY JUMPER LINE AND SPACE AROUND E-14003 HOT AND COLD SIDE FORPRE-COMMISSIONING ACTIVITIES.

MIN

15. ANCHOR FOR TWO PHASE FLOW.

6. DELETED.

600 M

IN

17. VALVE TO BE LOCATED CLOSE TO E-14003.

MIN

1. DELETED.

25

FF

I

C2

NO POCKET

C2

C2

FF

TOP CONNECTION

C2

NOTE 11

C2

C2

V-14001 V

D

TWO PHASE FLOW

50

NOTE 15

NATURAL GAS

20

250-P-140-00185-033484C2-CA

K2B

NOTE 15

450-

P-14

0-00

003-

0634

84C-

CA

C1

NOTE 20

C2

C2

150-P-140-00021-033484C2-C

C2

20

C2

NC

HH

50

FF

C2

50

NOTE 11

C3

FF

D

80-CRD-140-00083-013475F-N

I

80-CRD-140-00062-013475F-N

TSO

LO

NC

D

C2

N1

NOTES 15,24K3B

50

TWO PHASE FLOW

150-P-140-00020-063484C-CF1

C2

C2

NGL EXTRACTION COLUMN OVERHEAD

50-VT-140-00004-063484C-CF1

N4

NOTE 11

50

C1

50

RO1001

C2

C2

250-P-140-00003-063484C-CA

FEED SEPARATOR BOTTOM

C2

FF

LPT

NOTE 15

C2

LPT

50

TYPE VP205

NC

TWO PHASE FLOW

K1B

450-P-140-00023-063484C-CANO POCKET

UC

C2

D

50

80-CRD-140-00003-013475F-N

TWO PHASE FLOW

Type 4

Type 2

Type 1

Type of Modification to FEED Deliverables

FEED without change

New document

FEED + adaptations

C1

FF

2oo3

C2

V

V

LL

D

C2

UZV2811

TOP CONNECTION

I

N6

VM

20

N2

I

40

UCV1501A

NOTE 17

NATURAL GAS

NOTE 15

LCV1001

K1A

K6

FF

I

250-FDH-140-00001-013475F-N

50

NGL EXTRACTION COLUMN OVERHEAD

C3

NOTES 13, 14, 28

700

C2

C1

250-P-140-00022-063484C-CA

K3A

C2

H

C2

600-P-140-00006-033484C2-C

25

C2

C2

C1

C2

TYPE VP001

600

FF

C2

K2A

20

NOTE 15

200

NOTE 15

N5

50

C1

LPT

D

C1

600-P-140-00007-063484C-C

D

FB

450-P-140-00002-063484C-C

NATURAL GAS

NOTE 5

NOTE 5

250-P-140-00004-063484C-CA

L

150-P-140-70002-063484C-C

80-P-140-00164-011412W-N

LL

80

VE

C2

C2

50

NC

UCV1501B

HH

D

FF

40G8075.0 RV

1001A

UZV2021

50

80-P-140-00199-011412W-N

QV-1400034

QV-1400037

QV-1400029

QV-1400046

QV-1400040

QV-1400020

QV-1400015

QV-1400017

QV-1400053

QV-1400009

QV-1400042

QV-1400045

QV-1400049

QV-1400052

QV-1400003

QV-1400041

QV-1400055

QV-1400036

QV-1400043

QV-1400027

QV-1

4000

12

QV-1400047

QV-1400044

QV-1400033

QV-1400022

QV-1400019

QV-1400014

QV-1400023

QV-1400002

QV-1400016

QV-1400028

QV-1400054

QV-1400007

QV-1400051

QV-1400018

QV-1400013

QV-1400039

QV-1400050

QV-1400048

QV-1400035

QV-1400031

Rev.

12345678910111213141516

12345678910111213141516

H

G

A

B

C

D

E

F

H

G

A

B

C

D

E

F

Status Date Description Issued by Checked by Approved by

This document is restricted. The copyright is vested in Shell Global Solutions International B.V. The Hague, Netherlands,and Shell Affiliates. Recipients must obtain the written authority of the said company

before wholly or partially duplicating the contents or disclosing same to others. All right reserved.

Prelude EPCI Floating LNG PROJECT

CPYDoc. Ref.

Format:

Doc Class:

Scale:

ECCN Code:

Sheet:

Area : A1

-

Security Class:

RESTRICTED

TSCDoc. Ref.

File

nam

e:

GF00

NOTES

PROCESS ENGINEERING FLOW SCHEME

EAR99

21. DELETED.22. DELETED.

C1

C1

50D

C1UZV2013

QV-1400024C1

C225

250

SIA

C2LO

QV-1400025

C1

50D

C2

M

15C2 NOTE 10

250-P-140-00218-063484C-NNATURAL GAS SIDE NOTE 19

600-P-140-00224-063484C-NNGL EXTRACTION SIDE

TOP

OR S

IDE

CONN

ECTI

ON

MH

A1

600

15

15NOTE 10

C2

C2

QV-1400011

QV-1401975

1P1 1P2

NO P

OCKE

T

N3

QV-1401968

RS

QV-1401974

23. CAPACITY DETERMINING COMPONENT. TO BE PROVIDED WITH A RED TAG IN THE FIELD.24. LINE SUBJECT TO FLOW INDUCED VIBRATIONS.PIPING TO BE DESIGNED ACCORDINGLY.

150US

DP

PROCESS DECK A

3300

50

150

80

V

25QV-1402296

QV-1

4022

86

LCLO

C2

C2 C2

40G8075.0 RV

1001B

20

45°

150

LO

FB

QV-1402284

C2

II 250

NOTE 24

150

150

NOTE 23

RTD

900#

PROCESS DECK C

NOTE 10

NOTE 9

900#

RTD

RTD

20D

C2QV-1402295

50

NCC1

TOP CONNECTION

MIN NOTE 12TYPE VP201

1033HS

C

NOTE 25

UCQV-1402292

QV-1

4022

99

QV-1402294

QV-1402293

QV-1402285

C2

(380

0)

750

25. HS-1033 IS USED FOR SWITCHING THE CONTROL SIGNAL FC-1038 BETWEEN THE IGV VALVE ( FCV-3111 ) AND THEJT VALVE ( FCV-1038 ).

NOTE 19

50-VT-140-00022-063484C-C

QV-1402287

150-P-140-00027-063484C-N

26. DELETED.27. VALVE BODY OF UZV-2021 TO BE PFP.28. REMOVABLE SPOOL FOR CONSTRUCTABILITY PURPOSE ONLY.

I

I

LO

LO

200

MIN

NOTE 27

RS

C2

NOTE

28RS

C2(248

3) 50D

50VC2

QV-1402290

QV-1402288

E-14003

QV-1402289V

50 C2

50D

QV-1402291

C2

AMKLSMCEPCI - AS-BUILT28/02/2020ASB07ZJWHKAAMKEPCI - AS-BUILT22/05/2017ASB06ZJWHCNAMKEPCI - APPROVED FOR CONSTRUCTION16/05/2014AFC05CSRKBTAMKEPCI - APPROVED FOR CONSTRUCTION25/07/2013AFC04C

2

1 of 1

DBJWHVDCATJWHMMSRCCKAMK

\F00

1\PR0

1\140

00\14

0-00

002-

1.pid

60869M-GF00U14000-PID-0021-000022000-110-F001-PR01-U14000-PX-2365-00002-001

EPCI - APPROVED FOR CONSTRUCTION11/05/2012AFC03CEPCI - APPROVED FOR DESIGN05/08/2011AFD02AAPPROVED FOR DESIGN01/02/2011AFD01A

NGL EXTRACTION COLUMN FEED SEPARATORNGL EXTRACTION AND LIQUEFACTION UNIT

14005SPS

14036SPM

14052SPM

14052SPM

RS750QV-1402297

14006SPS

QV-1402298

15C2

NOTE 12

750

FROM TC-1184140839140-00004-1

150

CRD 140271630-10013-1

FDH 140278630-10006-2

CRD 140270630-10013-1

CRD 140425630-10013-1

DF 140424140-10002-1

DF 140162140-10002-1

bargºC

C-130.0 / 70.0 -130.0 / 70.0

- / 75.0 - / 57.7

INSULATION :DESIGN TEMP :DESIGN PRESS :

COLD SIDEHOT SIDE

E-14003NG 2ND COLD RECOVERY EXCHANGER

CF1INSULATION :

bargºC-130.0 / 70.0

- / 75.0DESIGN TEMP :DESIGN PRESS :

V-14001NGL EXTRACTION COLUMN FEED SEPARATOR

ICCA

600-P-140-00198-063484C-C

NOTE 9

750

ICAC

50I

NOTE 2

1009XA

NOTE 29HEAT TRACINGFAULT

29. HEAT TRACING FAILURE ALARM 140XA-1009 FOR 140LT-1001A/B/C PROVIDED ON DCS.

150-P-140-00026-063484C-C

Prelude FLNG Pitstop 2021 Test Pack 003 140LT-1001A/B/C Leak Test Page 1 of 3

Testing Points

T1

T2

T3

S1

S2

S3

T4

T5T6

T7

T8 T9

T10

T11

T12

S4

S5

S6

S7

TEST PACK NUMBER: TP 003 TEST PACK NAME: 140LT-1001A/B/C Leak TestPRESSURE: 67.5 bargESTIMATED VOLUME: 1.1 sm3

Open

Test Envelope

Closed

Secondary System

6-way manifold for Injection point, Temp PRV, Instrumentand depressurisation point

S8

S9

S10

1201PI

1001TC

1201PI 1003

TI

1048FI

2040UZ

1004TI

1007TI

1006TC

1105HC

1005TI

2010UZ

2010UZ

1003PDZA

2010UZ

1090FI

2770UZ

1001PG

1001TY

QT

1202PDIA

1214PG

1002PG

RS

TYPE IQP-1101A

TO E-14030140009 140-00032-1

FROM E-14003140004140-00002-1

TO K-14001140005 140-00003-1

FROM UY-1518140476140-00026-1

TO V-14001140001 140-00002-1

TO E-14007140434 140-00050-1

TO V-14020140008 140-00010-1

FROM E-14006140016140-00005-1

11. TAPPING POINT FOR PORTABLE PDI.

HOLDS

14. PROVIDE TEMPORARY JUMPER LINE AND SPACE AROUND E-14002 HOT AND COLD SIDE FORPRE-COMMISSIONING ACTIVITIES.

16. DELETED.

MIN

1. E-14002 ONLY USED FOR LOW PLANT INLET PRESSURE WITH NO DEPLETION COMPRESSOR (LPCA CASE).

MIN

10. TEMPORARY STRAINER FOR START-UP. SPOOL STRAINER TO BE RETAINED AFTER START-UP WITHOUT THE FINEMESH.

3. DELETED.

8. METHANE MAKE-UP IS INTERMITTENT.

4. DELETED.

6. PI TO BE READABLE FROM GLOBE VALVE.

MIN

600 M

IN

MIN

600 MIN

MIN

600 MIN

MIN

MIN

900#600 MIN

600 MIN

7. DELETED.

C C

900#

MIN

15. PROVIDE TEMPORARY JUMPER LINE AND SPACE AROUND E-14001 HOT AND COLD SIDE FORPRE-COMMISSIONING ACTIVITIES.

13. DELETED.12. ANCHOR FOR TWO PHASE FLOW.

2. FOR START-UP PRESSURIZATION.

LIVIN

GQU

ARTE

R

T

F

R

3S1 2S1 1S3 1S1

4P2 3P2 2P3 1P24P1 3P1 2P2 2P1 1P1

4S1

5. NITROGEN CONNECTION FOR MAINTENANCE.

9. PG TO BE READABLE FROM GLOBE VALVE.

MIN

MIN

MIN

21. DELETED.22. DELETED.23. AIR SUPPLY TO BE PROVIDED WITH A MECHANICAL LOCK.

600 M

IN

TYPE 3

140 QS-1010 : START VALIDATION140 QA-1010 GENERAL FAULT140 QB-1011 COME READ STREAM A140 QI-1011A : C1140 QI-1012A : C2140 QI-1013A : C3140 QI-1014A : iC4140 QI-1015A : nC4140 QI-1016A : C5+140 QI-1017A : N2140 QB-1014 : COME READ

VALIDATION

17. MULTISTREAM ANALYSER 140 QT-1010 WITH STREAM SWITCH 140 HS-1007.18. VALVE TO BE LOCATED AT THE EDGE OF THE FIRE ZONE.19. E-14001 IS A TWO PARALLEL CORES EXCHANGER.20. CHECK VALVE SHALL BE OF TWO DIFFERENT TYPES.

25. LINE SUBJECT TO FLOW INDUCED VIBRATIONS. PIPING TO BE DESIGNED ACCORDINGLY.24. LABORATORY SAMPLING FACILITY IS PART OF THE ANALYSER SAMPLE CONDITIONING SYSTEM.

INSULATION : N

MIN

BTL

BTL

MIN

MIN

MIN

MIN

QV-1402003

QV-1401995

50

D

800

QV-1401993

QV-1401996

QV-1401997 QV-1401998QV-1401994

800

C2

UZV2012

C2

C2

NOTE 1

C2 RS

C2

NOTE

2

NOTE

12

700-R-140-00024-063484C-C

UZVS2771

QV-1400113

QV-1400112

QV-1400152

QV-1400169C1

NOTE 8

TOP

CONN

ECTI

ON

D

C2

D

RS

C3

C1

NNF

1P1

PMR

LIQUI

D

C2

NATURAL GASNNF

LO

NATURAL GAS

NC

D

FF

200-R-140-00023-063484C-C

D

C1

C2

NATURAL GAS

50

QV-1400138

C3

NOTE 9

FF

VM

FF

NC

D

C2

700-

P-14

0-00

196-

0634

80W

-A

UC

NOTES 12, 25

C1

C2

TYPE VP105

C2

TOP CONNECTION

H

FF

150-

R-15

0-00

001-

0634

84C-

C

700-P-140-00008-033480W2-A

FF

QV-1

4019

99QV

-140

2000

FF

C2

1P1

I

450-P-140-00002-063484C-C

50

20D

C2

400-P-140-00048-093480W-N

I

I

NATU

RAL G

AS

Type 4

Type 2

Type 1

Type of Modification to FEED Deliverables

FEED without change

New document

FEED + adaptations

TOP

CONN

ECTI

ON

450

80-CRD-140-00105-013475F-N

LO

25

C2

D

C2

80-P-140-00184-011412W-N

200

BTL

PROCESS DECK B

RS

NOTE 12

FF

80-CRD-140-00002-013475F-N

TWO

PHAS

E FL

OWLPT

C2C2

HCV1105

M

600-P-140-00007-063484C-C

C250

NOTE 12

C2

C350

C350

50

900#

QV-1402179

C2

C2

MAIN DECK

MAIN DECK

MAIN DECK

40 D

C2

20

RTD

200

1P1

80-FDH-140-00064-013475F-N

200-P-140-00018-063484C-C

RS

C3

NOTE 10 700-R-140-00150-063484C-C

NC

NC50(7

30)

(242

8)

50C3

50

20 C2

D

C1

50-P-140-00194-093480W-N

C1 40

NC

C2

NOTES 11

500-

P-14

0-00

001-

0634

80W

-NTYPE VP105

300

STREAM A

50

FF

PMR VAPOUR

900#C2V50

NOTE 6

50

NATURAL GAS

UZV2011

C1

I

80-P

-140

-000

16-0

1141

2W-N

NOTE 11

RTD

C2

400-P-140-00158-063480W-N

C2

80SP

FF

80-N

L-14

0-00

013-

0114

12X-

N

C2

VE

NO POCKET

300-P-140-00203-061472W-N

150-P-140-00019-033480W2-N

20

80-CRD-140-00082-013475F-N

50C2 C250

C1

NATURAL GAS

TCV1001

50

NOTE 6

METHANE MAKE-UP

25

M

QV-1400145

NGL EXTRACTION COLUMN OVERHEAD

50

C1

QV-1400133

QV-1

4001

55

450-P-140-00013-063484C-C

C2

FF

M

C1

TOP CONNECTION

D

TWO PHASE FLOW

C2

UZVS2045

C2

C2

I

FF

C3

RTD

D

NNF

C1

NC

NOTE 5

20

FF

C2

TWO PHASE FLOW

E-14002

START-UP LINE

D

500-

P-13

5-00

001-

0614

72X-

N

C2

C3

NOTE 12

80-C

RD-1

40-0

0081

-013

475F

-N

C2

50

NC

50

NOTE 12

20

LPT

50-VT-140-00021-063484C-C

I

25D5040.0RV

1116A

NOTES 18,23

C2

C2

C2

50C2

FB

20

LO

LO

V

I

NOTE 19

100-FDH-140-00100-013475F-N

100

400

400

400

E-14001A

NOTE 27

LPT

C2D50

LO

LOC2

20C2

STRE

AM A

NOTE 17

GC

C2

50

LC

LO

FBC2

50

LO

C2

C2

C2

V

C2

D 50

C2

NOTES 18,23

QV-1

4001

18

QV-1400148

QV-1400134

QV-1400168

QV-1400126

QV-1400171

QV-1400153

QV-1400166

QV-1400123

QV-1

4001

22

QV-1400130

QV-1400139

QV-1

4001

47

QV-1350003

QV-1400119

QV-1

4001

46

QV-1400140

QV-1400137

QV-1400144

QV-1400136QV-1350001

QV-1400163

QV-1400117

QV-1350002

QV-1350007

QV-1400164

QV-1400159

QV-1350005

QV-1

4001

70

QV-1350004

QV-1400149

QV-1400116

QV-1400161

QV-1350006

QV-1400165

QV-1400154

QV-1400115

QV-1

4001

14

QV-1400120QV-1400160

QV-1400125

QV-1400157

PROCESSDECK C

50

NOTE 920

NC

UC

RTD

C2

15

15

C2

FF H

TOP CONNECTION

NOTE

15NG

L EXT

RACT

ION

SIDE

NOTE

S 10

,11

800-

P-14

0-00

223-

0634

84C-

N

450-

P-14

0-00

217-

0634

80W

-NNA

TURA

L GAS

SID

ENO

TE 15

NATU

RAL G

AS S

IDE

NOTE

14

500-

P-14

0-00

216-

0634

84C-

NNO

TE 14

700-

R-14

0-00

163-

0634

84C-

NPM

R SI

DE

RS

400

400

400

400

50

DC2

80

D

50

I

25D5040.0RV

1116B

20

C2

C2NC

QV-1

4001

28

C2

RTD

RTD

900# 350 900# 900#

350

350

(730

)

350

350

5050 C2C2

NOTE 12

700 350

350

800

RSNOTE 10

700

500

S-14008

D 50C2

800

700

QV-1400158

D

NCC2

QV-1

4001

29

50C2

QV-1402196NOTE 26

D50

C3

450-

P-14

0-00

012-

0634

84C-

C

QV-1402002

QV-1402144

QV-1402142

QV-1402141QV-1402143

QV-1402001

QV-1

4021

37QV-1402138

QV-1

4021

39

QV-1402140

QV-1

4022

04

QV-1402205

QV-1402207

QV-1

4022

09

QV-1402210

UC

QV-1402369

QV-1402370

QV-1402368

QV-1402371QV-1402374

QV-1

4023

75

QV-1402215 QV-1402216

QV-1403817

Rev.

12345678910111213141516

12345678910111213141516

H

G

A

B

C

D

E

F

H

G

A

B

C

D

E

F

Status Date Description Issued by Checked by Approved by

This document is restricted. The copyright is vested in Shell Global Solutions International B.V. The Hague, Netherlands,and Shell Affiliates. Recipients must obtain the written authority of the said company

before wholly or partially duplicating the contents or disclosing same to others. All right reserved.

Prelude EPCI Floating LNG PROJECT

CPYDoc. Ref.

Format:

Doc Class:

Scale:

ECCN Code:

Sheet:

Area : A1

-

Security Class:

RESTRICTED

TSCDoc. Ref.

File

nam

e:

GF00

NOTES

PROCESS ENGINEERING FLOW SCHEME

EAR99

26. PG TO BE READABLE FROM GLOBE VALVE.27. NON-SLAM TYPE CHECK VALVE (MOKVELD OR EQUIVALENT).

QV-1

4038

14

NOTE 26

100

LO

LOMIN

QV-1400141

NOTE 20

MIN

NOTE 24

500

C2

NOTE

12JWHKAAMKEPCI - AS-BUILT22/05/2017ASB06ZJWHCNAMKEPCI - APPROVED FOR CONSTRUCTION16/05/2014AFC05CSRKBTAMKEPCI - APPROVED FOR CONSTRUCTION25/07/2013AFC04C

2

1 of 1

DBJWHVDCATJWHMMSRCCKAMK

\F00

1\PR0

1\140

00\14

0-00

001-

1.pid

60869M-GF00U14000-PID-0021-000012000-110-F001-PR01-U14000-PX-2365-00001-001

EPCI - APPROVED FOR CONSTRUCTION11/05/2012AFC03CEPCI - APPROVED FOR DESIGN05/08/2011AFD02AAPPROVED FOR DESIGN01/02/2011AFD01A

NG 1ST COLD RECOVERY EXCHANGERNGL EXTRACTION AND LIQUEFACTION UNIT

14010SPM

14049SPC

14003SPS

14002SPS

14004SPS

C2

50

FDH 140277630-10006-2

CRD 140422630-10013-1

TO V-14010140042 150-00005-1

CRD 140275630-10013-1

DF14

0165

140-

1000

2-1

DF 140212140-10002-1

FROM

S-1

3501

1350

0113

5-00

001-

1

CRD

1404

2163

0-10

013-

1

FROM

E-1

4012

1500

0115

0-00

005-

1

FDH 140470630-10006-2

CRD 140741630-10013-1

NL14

0223

480-

1000

1-9

bargºC

C-130.0 / 70.0 -130.0 / 70.0

- / 75.0 - / 57.7

INSULATION :DESIGN TEMP :DESIGN PRESS :

COLD SIDEHOT SIDE

E-14002NGL EXTRACTION PRECOOLER

bargºC

C-130.0 / 70.0 -130.0 / 70.0

- / 75.0 - / 57.7

INSULATION :DESIGN TEMP :DESIGN PRESS :

COLD SIDEHOT SIDE

E-14001ANG 1ST COLD RECOVERY EXCHANGER

bargºC-130.0 / 70.0

- / 75.0DESIGN TEMP :DESIGN PRESS :

S-14008NG 1ST COLD RECOVERY EXCHANGER STRAINER

28. BY PASS LINE USED FOR LGHA AND LPCA CASE. TPG-2107-0

TPG-2064-0

TPG-2064-0

TPG-

2012

-0

TPG-2012-0

TPG-

2012

-0

400

TPG-2064-0

TPG-2012-0

TPG-2018-0TPG-2018-0

FROM OUTLET OF C-14001140734140-00004-1600-P-140-00052-033484C2-C

BY-PASS LINELC

C2

QV-1400026

14052SPM

TPG-2107-0

50-VT-140-00031-06340W-N TPG-2099-0

NOTE 28

TPG-2148-0

TPG-2127-0

TPG-2148-0

QV-140222740 D

C2TPG-2141-0

TPG-2410-0

TPG-2304-0

50

TPG-2275-0

TPG-2299-0

TPG-2304-0

TPG-2215-0

/ B

/ B

TPG-2215-0

TPG-

2275

-0

TPG-2410-0

IA

NTPG-2411-0

LPT

29. CONTROL VALVE SUBJECT TO ACOUSTIC INDUCED VIBRATIONS. LOW NOISE TRIM TO BE PROVIDED.

TPG-2426-0

NOTE 29

TPG-2426-0

Prelude FLNG Pitstop 2021 Test Pack 003 140LT-1001A/B/C Leak Test Page 2 of 3

T13

T14

TEST PACK NUMBER: TP 003 TEST PACK NAME: 140LT-1001A/B/C Leak TestPRESSURE: 67.5 bargESTIMATED VOLUME: 1.1 sm3

Open

Test Envelope

Closed

Secondary System

2030UZ

1511GBZ

Moo3

1011TT

1009PT

1001FY

2035GBZ

1019PI

2810UZ

1102HZA

2030UZ

1210PG

2030UZ

1009PY

1094HC

1009PZA

Moo3

1011TY

2030UZ

2030UZ

1009PIA

1514UY

1011TIA

1211PI

1011PDZA

2810UZ

1011TZA

1015PI

1601UZA

1020HC

2030UZ

2030UZ

2030UZ

1001FT

2030UZ

2010UZ

1601UZA

1016TI

1510UCA

1020GBZ

2034GBZ

1010PDIA

Moo3

1019PY

1211PI

1019PT

1601UZA

2030UZ

1001FI

1513UY

1012TI

1013TI

Moo3

2030UZ

1137HS

1138HS

2030UZ

2033GBZ

RS

RS

CRD 140300630-10012-1

CRD 140302630-10012-1

FROM E-14001140005 140-00001-1

DF 140164140-10002-1

FROM V-14001140011 140-00002-1

FDH 140280630-10006-1

FDH 140279630-10006-1

DF 140163140-10002-1

FROM FY-1038140013 140-00002-1

TO K-14002140006 140-00005-1

CRD 140301630-10012-1

TO C-14001140018 140-00004-1

CRD 140299630-10012-1

CRD 140303630-10012-1

TO SEAL GAS UNIT140727 140-20008-1

TO E-14007140433 140-00050-1

1401

138

140-

3000

2-1

MIN

600 MIN

21. FOR INTERFACE DETAILS, REFER TO PEFS NO : 2000-110-F001-PR01-U14000-PX-2365-20008-001MIN

2. NON-SLAM TYPE CHECK VALVE (MOKVELD OR EQUIVALENT).

MIN

16. DELETED.

MIN

4. DISTANCE BETWEEN ANTI-SURGE VALVE AND RECOMPRESSOR DISCHARGE TO BE MINIMIZED.

22. DELETED.23. STRAIGHT LENGTH AT INLET OF KT-14001 NG EXPANDER TO BE 3D PER VENDOR REQUIREMENT.24. CAPACITY DETERMINING COMPONENT. TO BE PROVIDED WITH A RED TAG IN THE FIELD.25. PI TO E READABLE FROM GLOBE VALVE.26. STRAIGHT LENGTH AT INLET OF K-14001 NG RECOMPRESSOR TO BE 4D PER VENDOR REQUIREMENT.

600 MIN

7. TEMPORARY STRAINER FOR START-UP. SPOOL STRAINER TO BE RETAINED AFTER START-UP WITHOUT THE FINEMESH.

18. DELETED.

MIN

13. PI TO BE READABLE FROM GLOBE VALVE.

17. ANCHOR FOR TWO PHASE FLOW.

8. DELETED.

20. DESIGN TEMPERATURE : - SUCTION : -46.0/70.0°C - DISCHARGE : -46.0/70.0°C

600 MIN

3. DISTANCE BETWEEN CHECK VALVE AND RECOMPRESSOR DISCHARGE TO BE MINIMIZED.

9. DELETED.

29. REMOVABLE SPOOL FOR CONSTRUCTABILITY PURPOSE ONLY.

MIN

5. FOR START-UP PRESSURIZATION OF EXPANDER RECOMPRESSOR.

MIN

600 MIN

MIN

12. NITROGEN CONNECTION FOR MAINTENANCE.

MIN

15. NON-SQUARE ROOT EXTRACTED VALUE USED IN SURGE PARAMETER CALCULATION.

1. RECOMPRESSOR BY-PASS FOR JT VALVE OPERATION.

10. CHECK VALVE TYPE TO BE SELECTED TO ACCEPT LOW PERMANENT PRESSURE DROP WITHOUT BACK-FLOW.

600 MIN

MIN

19. STRAIGHT LENGTH AT OUTLET OF KT-14001 NG EXPANDER TO BE 3D PER VENDOR REQUIREMENT.

MIN

600 MIN

LIVIN

GQU

ARTE

R

T

F

R

3S1 2S1 1S3 1S1

4P2 3P2 2P3 1P24P1 3P1 2P2 2P1 1P1

4S1

MIN

14. TAPPING POINT FOR PORTABLE PDI.

11. QUICK SHUT-OFF VALVE.MIN

MIN

600 MIN

6. DELETED.

MIN

MIN

MIN

27. UZV-2034 AND UZV-2035 ARE DESIGNED TO FOLLOW 063480W PIPING CLASS.28. A FLANGE TO BE PROVIDED BY TSC FOR INSTALLATION OF MANUAL VALVE AND DIFFERENTIAL PRESSURE

TRANSMITTER PROVIDED BY COMPRESSOR VENDOR.

PROCESS DECK A

VE

80

NOTE 12

NC

50

C2

700-P-140-00010-061472W-A

15C2C2

NOTE 14NOTE 14

700-P-140-00008-033480W2-A

40

20

14003SPC

O

NOTE 17

TWO PHASE FLOW

NOTE 17

HH

C3

QV-1400102

QV-1400105

QV-1400071

QV-1400083

QV-1400104QV-1400084

DUZV2035

20D

NOTES 5,27

D50

C2

14002SPC

C

L

NOTE 14

15

K-14001

80-P-140-00030-011412W-N

NOTE 1520

NATURAL GAS

14010SPS

2oo3

50

C2

C2

50

700-

P-14

0-00

232-

0614

72W

-A

NOTE

26

KT-14001

UZV2812

450-P-140-00023-063484C-CA

NOTE 17

NOTE 14

LO

80-CRD-140-00070-013475F-N

C2

NOTE 17

NC

I

V

20

D

150-FDH-140-00004-013475F-N

C1

H

700-P-140-00009-061472W-A

450

H

NOTE 13

D

NC

C2

C2

600-P-140-00029-061472W-A

50

80-CRD-140-00004-013475F-N

C2

NOTE 10

C2

UZVS2037

TOP

CONN

ECTI

ON

80-CRD-140-00069-013475F-NC1

50

NOTE 21

TYPE VP205

HSV1137

500-P-140-00024-063484C-CA

D

20

C3

LO

C2

C

50

FF

FF

H

C1

C2

NOTES 2, 3

NOTE

17

80-CRD-140-00006-013475F-N

C2

C2

NC

NOTE 1

TSO

C2

C2

EXPANDER-RECOMPRESSOR PROTECTION

50

FCV1038

D

C3

D

D

C1

C1

C1

40

C1

C2

C2

C2

C1

C2

D

TYPE VP301

C

LPT

50

M

150-FDH-140-00002-013475F-N

TYPE VP205

80

RO1003

700

HH

NOTE 24

400

20

UZVS2038

TYPE VP205

700-

P-14

0-00

028-

0334

80W

2-N

C2

450

NOTE

29

LPT

NATURAL GAS 40

NO POCKET

FF

I

TYPE VP001

FF

LL

1P2

25

SIA

C2

H

NATURAL GAS

80-P-140-00036-063484C-CA

FF

C2

HSV1138

TOP CONNECTION

20

D

TOP

CONN

ECTI

ON

500-P-140-00025-033484C2-CA

NATURAL GAS

NOTE 7

C1

NOTE 17

C1

ANTI-SURGE LINE

2oo3

HCV1020

C2

NOTE 2

25

C2

TOP

CONN

ECTI

ON

UZVS2014

C2

I

UZV2813

C2

LL

TYPE VP301

I

CCRMATRIX

FF

NOTE 13

C2

80-CRD-140-00005-013475F-N

I

NOTE

5

NOTE 17

BY-PASS LINE

NOTE 25

NOTE 17

C1

LPT

C1

C2

TYPE VP001

C1

C2

FF

V

50

TSO

FF

1P1TOP

CONN

ECTI

ON

NOTE 4

UZV2036

UCV1511

NOTE 25

50

TWO PHASE FLOW

C1

RO1002

SIA

C220

LL

NOTE 12

80-P

-140

-000

31-0

6147

2W-A

C1

I

Type 4

Type 2

Type 1

Type of Modification to FEED Deliverables

FEED without change

New document

FEED + adaptations

M

M

NOTE 21

15

QV-1400072

QV-1400056

QV-1400103

QV-1400070

QV-1

4000

86

QV-1400057

QV-1400093QV-1400091 QV-1400092

QV-1400058

QV-1400075

QV-1400088 QV-1400106

QV-1400087

QV-1400069

QV-1400094

QV-1400060

QV-1400076

QV-1400096

QV-1400107QV-1400059

QV-1400078

QV-1400098

QV-1400109

QV-1400095

QV-1400110

QV-1400063

QV-1400079

QV-1400099

QV-1400111

QV-1400097

QV-1400062

QV-1400077 QV-1400108 QV-1400067

QV-1

4001

01

15C2

400-P-140-00033-063484C-CAQV-1400065

QV-1400061

QV-1400064

QV-1400066

QV-1400081

QV-1400100

C2

400

QV-1402319

QV-1

4023

20

AMKLSMCEPCI - AS-BUILT28/02/2020ASB07ZJWHKAAMKEPCI - AS-BUILT22/05/2017ASB06ZJWHCNAMKEPCI - APPROVED FOR CONSTRUCTION16/05/2014AFC05CSRKBTAMKEPCI - APPROVED FOR CONSTRUCTION25/07/2013AFC04C

2

1 of 1

DBJWHVDCATJWHMMSRCCKAMK

\F00

1\PR0

1\140

00\14

0-00

003-

1.pid

60869M-GF00U14000-PID-0021-000032000-110-F001-PR01-U14000-PX-2365-00003-001

EPCI - APPROVED FOR CONSTRUCTION11/05/2012AFC03CEPCI - APPROVED FOR DESIGN05/08/2011AFD02AAPPROVED FOR DESIGN01/02/2011AFD01A

NG EXPANDER - RECOMPRESSORNGL EXTRACTION AND LIQUEFACTION UNIT

14001SPC

RTD

1P21P1

1P21P1

NOTE 27

15

FF

C2QV-1403812

I

C1

QV-1403811

2oo3RTD

UZV

2oo3

C2

14007SPS

NOTE 7

2oo3

RTD

RTD

NOTE

23

UZV2033

TYPE VP205NOTE 11

C1

600

I

350-P-140-00081-033480W2-NNNF NATURAL GAS

QV-1

4022

17

QV-1

4022

18

80-P-140-00035-011412W-N

500

C

NOTE 28

09TP 10

TP

07TP

08TP

C

bargºC-130.0 / 70.0

- / 75.0DESIGN TEMP :DESIGN PRESS :

KT-14001NG EXPANDER

bargºC-46.0 / 70.0

- / 86.0DESIGN TEMP :DESIGN PRESS :

K-14001NG RECOMPRESSOR

Rev.

12345678910111213141516

12345678910111213141516

H

G

A

B

C

D

E

F

H

G

A

B

C

D

E

F

Status Date Description Issued by Checked by Approved by

This document is restricted. The copyright is vested in Shell Global Solutions International B.V. The Hague, Netherlands,and Shell Affiliates. Recipients must obtain the written authority of the said company

before wholly or partially duplicating the contents or disclosing same to others. All right reserved.

Prelude EPCI Floating LNG PROJECT

CPYDoc. Ref.

Format:

Doc Class:

Scale:

ECCN Code:

Sheet:

Area : A1

-

Security Class:

RESTRICTED

TSCDoc. Ref.

File

nam

e:

GF00

NOTES

PROCESS ENGINEERING FLOW SCHEME

EAR99

Rev.

12345678910111213141516

12345678910111213141516

H

G

A

B

C

D

E

F

H

G

A

B

C

D

E

F

Status Date Description Issued by Checked by Approved by

This document is restricted. The copyright is vested in Shell Global Solutions International B.V. The Hague, Netherlands,and Shell Affiliates. Recipients must obtain the written authority of the said company

before wholly or partially duplicating the contents or disclosing same to others. All right reserved.

Prelude EPCI Floating LNG PROJECT

CPYDoc. Ref.

Format:

Doc Class:

Scale:

ECCN Code:

Sheet:

Area : A1

-

Security Class:

RESTRICTED

TSCDoc. Ref.

File

nam

e:

GF00

NOTES

PROCESS ENGINEERING FLOW SCHEME

EAR99

LPT

80-P-140-00288-063484C-CA

MIN

TO V

-440

0114

0134

440-

0000

1-1

NNF

2034

I

350-

P-14

0-00

160-

0334

80W

2-N

ICCA

I

CCA

I

IA

N

10D600#

600#

I

I

CCA

ICA

C

10D

Prelude FLNG Pitstop 2021 Test Pack 003 140LT-1001A/B/C Leak Test Page 3 of 3

T15

T16

T17

T18

TEST PACK NUMBER: TP 003 TEST PACK NAME: 140LT-1001A/B/C Leak TestPRESSURE: 67.5 bargESTIMATED VOLUME: 1.1 sm3

Open

Test Envelope

Closed

Secondary System

TypicalTSL16 S3-1

Instr.Class

100LT -1046ATag Number :

ITEM Qty Description MESC CodeVendor Code

SuppliedBy

SizeRatingMaterial

MAC1 Items

NA

20161000

shade

Nyrim

Protective shade

MAC2 Items

150 to 2500#RF

DN 80 NA

DR2.SG.AWP20.x

DRI-11

AISI 316L

Drip Ring- (10mmOD vent and drain)

INSTRUMENT HOOK-UP

CPY Doc N°

TSC Doc N°

RevSheet

13/130

Remote Mount.PIPE or CLOSED VESSEL-DPTRANS WITH DIAPHRAGM & FLUSHING RING

06Z2000-110-F001-PR01-G00000-IN-2335-00701

60869M-2S10G00000-DW-1576-00001

Remarks:

Gasket

Gasket

106110P

106110P

Note 1: SBB available from piping, refer to Vessel ISO's. Note 2: Drip Ring Vent is DN15 600# Flange Adaptor (capped) and Drip ring Drain is DN15 600# Blind flange.

Note 1

Note 1

140LT -1001A

106110P

106110P

DR2.SG.A0620.WB.11.0603A

2000-110-F001-PR01-G00000-IN-2335-00001

60869M-1P10G00000-DW-1576-00001 12/124 05Z

Note 2

Note 2

Note 2

Grafoil GHB, Graphite Gasket DP0007-0301-GF (3")

sherzha
Text Box
FOR INFORMATION ONLY

TITLE:

SCALE:

DRAWN:

DATE:

SIZE:

DRAWING NO.

EXTENSION :

SHEET

DATEDESCRIPTION

2

0

REV

1

NAME

WERK EXT.

A4 - VER

DESIGNED: WALL THICKNESS ACC. B16.34-2009DESIGNED: FLANGE SIZES ACC. B16.5-2009DESIGNED: MIM-4

DR1196S266RF16600.^BF

1 of 1

DRIPRING WITHOUT BOLTHOLES INCL. BLINDFLANGE

PS 100 - TS 450PROC.: 3" (DN80) RF, 600 LBS, SMOOTH FINISHINSTR.: 3" (DN80) RF, 600 LBS, SMOOTH FINISHVENT / DRAIN: 1/2" (DN15) 600 LBS

ALL DRAWINGS REMAIN THE INTELLECTUAL PROPERTY OF MULTI INSTRUMENTSNO PARTS MAY BE REPRODUCED IN ANY FORM

05-10-2020

FIRST CAD ISSUE 05-10-2020 W.P.D.

http://www.multi-instruments.comE-mail: [email protected]

W.P.D.

388u

O 127O 66,7

O 16

O 95,3

42

42

3" (DN80) - 600 LBS

1 1 BODY2 23 2

1/2" (DN15) RF, 600 LBS, SMOOTH FINISH1/2" (DN15) RF, 600 LBS, SMOOTH FINISH BLINDFLANGE

MATERIALITEM DESCRIPTIONQUANTITY REMARKS

1.4404 / AISI 316L (NACE)1.4404 / AISI 316L (NACE)1.4404 / AISI 316L (NACE) WEIGHT APPR.: 7,5 kg

3 2 2 3

1

Model: DR2.SG.A0620.WB.11.0603A.BF

sherzha
Text Box
FOR INFORMATION ONLY

FABRICATION MATERIALS

PTNO

COMPONENT DESCRIPTION N.S.((MM))

MESC QTY

PIPE

1 Pipe, ASME B36.19 / B36.10, PE,Seamless, Welded option is alsoacceptable, but shall be impacttested./S-40S ASTM A312 Gr. TP316/316L,

50 743623.058.F 0.1M

FITTINGS

2 Eccentric reducer, ASME B16.9, BW,Seamless, Welded option is alsoacceptable, but shall be impacttested./S-40S/S-40S ASTM A403 Gr.WP316/316L,

50 x 20 763371.635.F 1

3 Eccentric reducer, ASME B16.9, BW,Seamless, Welded option is alsoacceptable, but shall be impacttested./S-40S/S-40S ASTM A403 Gr.WP316/316L,

20 x 15 763371.566.F 1

FLANGES

4 Weldneck flange, ASME B16.5, RF, 600Lbs, -,/S-40S ASTM A182 Gr. F316/316L,

50 766580.490.1 3

5 Weldneck flange, ASME B16.5, RF, 600Lbs, -,/S-40S ASTM A182 Gr. F316/316L,

15 766580.482.1 1

6 Lap joint flange, ASME B16.5, FF, 600Lbs, -,/ ASTM A182 Gr. F316/316L,

15 766520.758.1 1

ERECTION MATERIALS

PTNO

COMPONENT DESCRIPTION N.S.((MM))

MESC QTY

GASKETS

7 Spiral wound gasket, ASME B16.20, RF asper B16.5, 600 Lbs, -, Thk = 4.5 mm,Inner AISI 316 / Outer CS, -,/ S.S. 316/ Graphite,

50 854136.414.1 3

8 Spiral wound gasket, ASME B16.20, RF asper B16.5, 600 Lbs, -, Thk = 4.5 mm,Inner AISI 316 / Outer CS, -,/ S.S. 316/ Graphite,

15 854136.404.1 1

BOLTS

9 110 mm Length:Stud bolt 2 nuts, BS 4882/ ASME B18.2.2, Full length threaded, -,-, A193 Gr. B8M Cl. 2 / A194 Gr. 8M +S1,

5/8 INS 813846.274.1 24

10 90 mm Length:Stud bolt 2 nuts, BS 4882 /ASME B18.2.2, Full length threaded, -,-, A193 Gr. B8M Cl. 2 / A194 Gr. 8M +S1,

1/2 INS 813846.159.1 4

VALVES / IN-LINE ITEMS

11 Cryo.Ball Flg RB Lp, ISO 17292, RF, 600Lbs, 2 Pieces Split Body, ExtendedBolted Bonnet, Floating Ball, Seats :RPTF/.. ASTM A351 Gr. CF8M,

50 770325.108.F 1

INSTRUMENTS

12 Lap Joint Compression Fitting for RemoteMount System, 600 Lbs

15 - 1

1 1

59.3 -58.7

75 65

82.52 P

AFC-EPCI-APPROVED FOR CONSTRUCTIONAFC-EPCI-APPROVED FOR CONSTRUCTION

/140 1P10A 50-VT-140-00004-063484C-CF1-030 25/03/13 VJ

VJ

SI SL/BH

SL/BH1 29/08/2013 AFC-EPCI-ORIGIN OF REVISION : DESIGN SK

2Z

2Z

12/08/2016 ASB-EPCI-AS BUILT MAR GGA RAV

L1

L1

N/A

N/A

/CF1

00002-001

51.3

NN

CONN. TOV-14001/K2BE 489207N 119392EL +106600

F4 G7 B9

50NS

1

50NS

F4 G7 B9

259

SELF RELIEVING

11

292

408

199

520

F4 G7 B9

250x20NS17MM OFFSET

155

320x15NS3MM OFFSET

F5 G8

98

140LT1001BL

12140LT-1001BL

F6 B10

E 489973N 119686EL +106581

411

2000-110-MP-2343-1P10A-50-VT-140-00004-063484C-CF1-03 Revision 01 Isometric Split-out Project 23/11/2020

80x50NS

14MM OFFSET

140 LT 1001BL

12

13

F5 G8 B10

2

F4 G7 B9

12

13

MOC: 106110P

Status: AFC

Date: 29/05/21

Rev: 01.01

Prepared By:

Approved By:

106110P

106110P

106110P

106110P

106110P

106110P140LT-1001BL

Dims not shown, Items fitting to fitting.

1

For gasket between flushing ring and diaphragm instrument see instrument hook up drawing 2000-110-F001-PR01-G00000-IN-2335-00001

SST-1P10A-90138

Injection Point #1

sherzha
Text Box
FOR INFORMATION ONLY

FABRICATION MATERIALS

PTNO

COMPONENT DESCRIPTION N.S.((MM))

MESC QTY

FITTINGS

1 Eccentric reducer, ASME B16.9, BW,Seamless, Welded option is alsoacceptable, but shall be impacttested./S-40S/S-40S ASTM A403 Gr.WP316/316L,

50 x 20 763371.635.F 1

2 Eccentric reducer, ASME B16.9, BW,Seamless, Welded option is alsoacceptable, but shall be impacttested./S-40S/S-40S ASTM A403 Gr.WP316/316L,

20 x 15 763371.566.F 1

FLANGES

3 Weldneck flange, ASME B16.5, RF, 600Lbs, -,/S-40S ASTM A182 Gr. F316/316L,

50 766580.490.1 1

4 Weldneck flange, ASME B16.5, RF, 600Lbs, -,/S-40S ASTM A182 Gr. F316/316L,

15 766580.482.1 1

5 Lap joint flange, ASME B16.5, FF, 600Lbs, -,/ ASTM A182 Gr. F316/316L,

15 766520.758.1 1

ERECTION MATERIALS

PTNO

COMPONENT DESCRIPTION N.S.((MM))

MESC QTY

GASKETS

6 Spiral wound gasket, ASME B16.20, RF asper B16.5, 600 Lbs, -, Thk = 4.5 mm,Inner AISI 316 / Outer CS, -,/ S.S. 316/ Graphite,

50 854136.414.1 2

7 Spiral wound gasket, ASME B16.20, RF asper B16.5, 600 Lbs, -, Thk = 4.5 mm,Inner AISI 316 / Outer CS, -,/ S.S. 316/ Graphite,

15 854136.404.1 1

BOLTS

8 110 mm Length:Stud bolt 2 nuts, BS 4882/ ASME B18.2.2, Full length threaded, -,-, A193 Gr. B8M Cl. 2 / A194 Gr. 8M +S1,

5/8 INS 813846.274.1 16

9 90 mm Length:Stud bolt 2 nuts, BS 4882 /ASME B18.2.2, Full length threaded, -,-, A193 Gr. B8M Cl. 2 / A194 Gr. 8M +S1,

1/2 INS 813846.159.1 4

VALVES / IN-LINE ITEMS

10 Cryo.Ball Flg RB Lp, ISO 17292, RF, 600Lbs, 2 Pieces Split Body, ExtendedBolted Bonnet, Floating Ball, Seats :RPTF/.. ASTM A351 Gr. CF8M,

50 770325.108.F 1

INSTRUMENTS

11 Lap Joint Compression Fitting for RemoteMount System, 600 Lbs

15 - 1

1 1

59.3 -58.7

75 65

82.52 P

AFC-EPCI-APPROVED FOR CONSTRUCTIONAFC-EPCI-APPROVED FOR CONSTRUCTION

/140 1P10A 50-VT-140-00004-063484C-CF1-040 25/03/13 VJ

VJ

SI SL/BH

SL/BH1 28/08/2013 AFC-EPCI-ORIGIN OF REVISION : PMS SK

2Z

2Z

12/08/2016 ASB-EPCI-AS BUILT MAR GGA RAV

L1

L1

N/A

N/A

/CF1

00002-001

39.8

NN

CONN. TOV-14001/K1BE 486635N 118915EL +106600

G6 B8

SELF RELIEVING

10

292

F3 G6 B8

150x20NS17MM OFFSET

1562

20x15NS3MM OFFSET

F4 G7

96

140LT1001AL

11140LT-1001AL

F5 B9

E 486076N 118915EL +106581

410

2000-110-MP-2343-1P10A-50-VT-140-00004-063484C-CF1-04 Revision 01 Isometric Split-out Project 23/11/2020

140 LT 1001AL

11

12

F4 G7 B9

1

F3 G6 B8

11

12

MOC: 106110P Status: AFC Date: 29/05/21 Rev: 01.01 Prepared By: Approved By:

80x50NS

14MM OFFSET

140LT-1001AL

106110P

106110P

106110P

106110P

106110P

106110P

Dims not shown, Items fitting to fitting.

1

For gasket between flushing ring and diaphragm instrument see instrument hook up drawing 2000-110-F001-PR01-G00000-IN-2335-00001

SST-1P10A-90137

Injection Point #2

sherzha
Text Box
FOR INFORMATION ONLY

FABRICATION MATERIALS

PTNO

COMPONENT DESCRIPTION N.S.((MM))

MESC QTY

PIPE

1 Pipe, ASME B36.19 / B36.10, PE,Seamless, Welded option is alsoacceptable, but shall be impacttested./S-40S ASTM A312 Gr. TP316/316L,

50 743623.058.F 0.2M

FITTINGS

2 Eccentric reducer, ASME B16.9, BW,Seamless, Welded option is alsoacceptable, but shall be impacttested./S-40S/S-40S ASTM A403 Gr.WP316/316L,

50 x 20 763371.635.F 1

3 45 Deg elbow LR, ASME B16.9, BW,Seamless, Welded option is alsoacceptable, but shall be impacttested./S-40S ASTM A403 Gr. WP316/316L,

50 763338.336.F 1

4 Eccentric reducer, ASME B16.9, BW,Seamless, Welded option is alsoacceptable, but shall be impacttested./S-40S/S-40S ASTM A403 Gr.WP316/316L,

20 x 15 763371.566.F 1

FLANGES

5 Weldneck flange, ASME B16.5, RF, 600Lbs, -,/S-40S ASTM A182 Gr. F316/316L,

50 766580.490.1 3

6 Weldneck flange, ASME B16.5, RF, 600Lbs, -,/S-40S ASTM A182 Gr. F316/316L,

15 766580.482.1 1

7 Lap joint flange, ASME B16.5, FF, 600Lbs, -,/ ASTM A182 Gr. F316/316L,

15 766520.758.1 1

ERECTION MATERIALS

PTNO

COMPONENT DESCRIPTION N.S.((MM))

MESC QTY

GASKETS

8 Spiral wound gasket, ASME B16.20, RF asper B16.5, 600 Lbs, -, Thk = 4.5 mm,Inner AISI 316 / Outer CS, -,/ S.S. 316/ Graphite,

50 854136.414.1 3

9 Spiral wound gasket, ASME B16.20, RF asper B16.5, 600 Lbs, -, Thk = 4.5 mm,Inner AISI 316 / Outer CS, -,/ S.S. 316/ Graphite,

15 854136.404.1 1

BOLTS

10 110 mm Length:Stud bolt 2 nuts, BS 4882/ ASME B18.2.2, Full length threaded, -,-, A193 Gr. B8M Cl. 2 / A194 Gr. 8M +S1,

5/8 INS 813846.274.1 24

11 90 mm Length:Stud bolt 2 nuts, BS 4882 /ASME B18.2.2, Full length threaded, -,-, A193 Gr. B8M Cl. 2 / A194 Gr. 8M +S1,

1/2 INS 813846.159.1 4

VALVES / IN-LINE ITEMS

12 Cryo.Ball Flg RB Lp, ISO 17292, RF, 600Lbs, 2 Pieces Split Body, ExtendedBolted Bonnet, Floating Ball, Seats :RPTF/.. ASTM A351 Gr. CF8M,

50 770325.108.F 1

INSTRUMENTS

13 Lap Joint Compression Fitting for RemoteMount System, 600 Lbs

15 - 1

1 1

59.3 -58.7

75 65

82.52 P

AFC-EPCI-APPROVED FOR CONSTRUCTIONAFC-EPCI-APPROVED FOR CONSTRUCTION

/140 1P10A 50-VT-140-00004-063484C-CF1-050 25/03/13 VJ

VJ

SI SL/BH

SL/BH1 28/08/2013 AFC-EPCI-ORIGIN OF REVISION : PMS SK

2Z

2Z

12/08/2016 ASB-EPCI-AS BUILT MAR GGA RAV

L1

L1

N/A

N/A

/CF1

00002-001

52.0

NN CONN. TOV-14001/K3BE 486687N 118548EL +106600

F5 G8 B10

50NS

1

330o

177

50

173

1

50NS

F5 G8 B10

177

SELF RELIEVING

12

292

326

339

328

F5 G8 B10

250x20NS17MM OFFSET

155

420x15NS3MM OFFSET

F6 G9

96

140LT1001CL

13140LT-1001CL

F7 B11

E 486002N 117969EL +106581

409

2000-110-MP-2343-1P10A-50-VT-140-00004-063484C-CF1-05 Revision 01 Isometric Split-out Project 23/11/2020

140 LT 1001CL 13

14

F6 G9 B11

1

F5 G8 B10

13

14

MOC: 106110P Status: AFC Date: 29/05/21 Rev: 01.01 Prepared By: Approved By:

106110P

106110P

106110P

106110P

106110P

106110P

140LT-1001CL

80x50NS

14MM OFFSET

Dims not shown, Items fitting to fitting.

1

For gasket between flushing ring and diaphragm instrument see instrument hook up drawing 2000-110-F001-PR01-G00000-IN-2335-00001

SST-1P10A-90136

Injection Point #3

sherzha
Text Box
FOR INFORMATION ONLY

FABRICATION MATERIALS

PTNO

COMPONENT DESCRIPTION N.S.((MM))

MESC QTY

FITTINGS

1 Eccentric reducer, ASME B16.9, BW,Seamless, Welded option is alsoacceptable, but shall be impacttested./S-40S/S-40S ASTM A403 Gr.WP316/316L,

50 x 20 763371.635.F 1

2 45 Deg elbow LR, ASME B16.9, BW,Seamless, Welded option is alsoacceptable, but shall be impacttested./S-40S ASTM A403 Gr. WP316/316L,

50 763338.336.F 1

3 Eccentric reducer, ASME B16.9, BW,Seamless, Welded option is alsoacceptable, but shall be impacttested./S-40S/S-40S ASTM A403 Gr.WP316/316L,

20 x 15 763371.566.F 1

FLANGES

4 Weldneck flange, ASME B16.5, RF, 600Lbs, -,/S-40S ASTM A182 Gr. F316/316L,

50 766580.490.1 1

5 Weldneck flange, ASME B16.5, RF, 600Lbs, -,/S-40S ASTM A182 Gr. F316/316L,

15 766580.482.1 1

6 Lap joint flange, ASME B16.5, FF, 600Lbs, -,/ ASTM A182 Gr. F316/316L,

15 766520.758.1 1

ERECTION MATERIALS

PTNO

COMPONENT DESCRIPTION N.S.((MM))

MESC QTY

GASKETS

7 Spiral wound gasket, ASME B16.20, RF asper B16.5, 600 Lbs, -, Thk = 4.5 mm,Inner AISI 316 / Outer CS, -,/ S.S. 316/ Graphite,

50 854136.414.1 2

8 Spiral wound gasket, ASME B16.20, RF asper B16.5, 600 Lbs, -, Thk = 4.5 mm,Inner AISI 316 / Outer CS, -,/ S.S. 316/ Graphite,

15 854136.404.1 1

BOLTS

9 110 mm Length:Stud bolt 2 nuts, BS 4882/ ASME B18.2.2, Full length threaded, -,-, A193 Gr. B8M Cl. 2 / A194 Gr. 8M +S1,

5/8 INS 813846.274.1 16

10 90 mm Length:Stud bolt 2 nuts, BS 4882 /ASME B18.2.2, Full length threaded, -,-, A193 Gr. B8M Cl. 2 / A194 Gr. 8M +S1,

1/2 INS 813846.159.1 4

VALVES / IN-LINE ITEMS

11 Cryo.Ball Flg RB Lp, ISO 17292, RF, 600Lbs, 2 Pieces Split Body, ExtendedBolted Bonnet, Floating Ball, Seats :RPTF/.. ASTM A351 Gr. CF8M,

50 770325.108.F 1

INSTRUMENTS

12 Lap Joint Compression Fitting for RemoteMount System, 600 Lbs

15 - 1

1 1

59.3 -58.7

75 65

82.52 P

AFC-EPCI-APPROVED FOR CONSTRUCTIONAFC-EPCI-APPROVED FOR CONSTRUCTION

/140 1P10A 50-VT-140-00004-063484C-CF1-060 25/03/13 VJ

VJ

SI SL/BH

SL/BH1 28/08/2013 AFC-EPCI-ORIGIN OF REVISION : PMS SK

2Z

2Z

12/08/2016 ASB-EPCI-AS BUILT MAR GGA RAV

L1

L1

N/A

N/A

/CF1

00002-001

40.1

NN

CONN. TOV-14001/K2AE 489207N 119392EL +103100

G7 B9

SELF RELIEVING

11

292

F4 G7 B9

50NS

245o

114

263

385 148

50NS35

14

32

150x20NS17MM OFFSET

77

320x15NS3MM OFFSET

F5 G8

97

140LT1001BH

12140LT-1001BH

F6 B10

E 489790N 119451EL +103081

218

2000-110-MP-2343-1P10A-50-VT-140-00004-063484C-CF1-06 Revision 01 Isometric Split-out Project 23/11/2020

140 LT 1001BH 12

13

F5 G8 B10

1

F4 G7 B9

12

13

MOC: 106110P Status: AFC Date: 29/05/21 Rev: 01.01 Prepared By: Approved By: 80x50NS

14MM OFFSET

106110P

106110P

106110P

106110P

106110P

106110P

140LT-1001BH

Dims not shown, Items fitting to fitting.

1

For gasket between flushing ring and diaphragm instrument see instrument hook up drawing 2000-110-F001-PR01-G00000-IN-2335-00001

SST-1P10A-90141

2

elbow not shown but to be included in as-built iso

Injection Point #4

sherzha
Text Box
FOR INFORMATION ONLY

FABRICATION MATERIALS

PTNO

COMPONENT DESCRIPTION N.S.((MM))

MESC QTY

FITTINGS

1 Eccentric reducer, ASME B16.9, BW,Seamless, Welded option is alsoacceptable, but shall be impacttested./S-40S/S-40S ASTM A403 Gr.WP316/316L,

50 x 20 763371.635.F 1

2 Eccentric reducer, ASME B16.9, BW,Seamless, Welded option is alsoacceptable, but shall be impacttested./S-40S/S-40S ASTM A403 Gr.WP316/316L,

20 x 15 763371.566.F 1

FLANGES

3 Weldneck flange, ASME B16.5, RF, 600Lbs, -,/S-40S ASTM A182 Gr. F316/316L,

50 766580.490.1 1

4 Weldneck flange, ASME B16.5, RF, 600Lbs, -,/S-40S ASTM A182 Gr. F316/316L,

15 766580.482.1 1

5 Lap joint flange, ASME B16.5, FF, 600Lbs, -,/ ASTM A182 Gr. F316/316L,

15 766520.758.1 1

ERECTION MATERIALS

PTNO

COMPONENT DESCRIPTION N.S.((MM))

MESC QTY

GASKETS

6 Spiral wound gasket, ASME B16.20, RF asper B16.5, 600 Lbs, -, Thk = 4.5 mm,Inner AISI 316 / Outer CS, -,/ S.S. 316/ Graphite,

50 854136.414.1 2

7 Spiral wound gasket, ASME B16.20, RF asper B16.5, 600 Lbs, -, Thk = 4.5 mm,Inner AISI 316 / Outer CS, -,/ S.S. 316/ Graphite,

15 854136.404.1 1

BOLTS

8 110 mm Length:Stud bolt 2 nuts, BS 4882/ ASME B18.2.2, Full length threaded, -,-, A193 Gr. B8M Cl. 2 / A194 Gr. 8M +S1,

5/8 INS 813846.274.1 16

9 90 mm Length:Stud bolt 2 nuts, BS 4882 /ASME B18.2.2, Full length threaded, -,-, A193 Gr. B8M Cl. 2 / A194 Gr. 8M +S1,

1/2 INS 813846.159.1 4

VALVES / IN-LINE ITEMS

10 Cryo.Ball Flg RB Lp, ISO 17292, RF, 600Lbs, 2 Pieces Split Body, ExtendedBolted Bonnet, Floating Ball, Seats :RPTF/.. ASTM A351 Gr. CF8M,

50 770325.108.F 1

INSTRUMENTS

11 Lap Joint Compression Fitting for RemoteMount System, 600 Lbs

15 - 1

1 1

59.3 -58.7

75 65

82.52 P

AFC-EPCI-APPROVED FOR CONSTRUCTIONAFC-EPCI-APPROVED FOR CONSTRUCTION

/140 1P10A 50-VT-140-00004-063484C-CF1-080 25/03/13 VJ

VJ

VJ

SI SL/BH

SL/BH

SL/BH

1 28/08/2013 AFC-EPCI-ORIGIN OF REVISION : PMS SK

SK2 28/04/2014 AFC-EPCI-ORIGIN OF REVISION : MODELREVIEW

3Z

3Z

12/08/2016 ASB-EPCI-AS BUILT MAR GGA RAV

L1

L1

N/A

N/A

/CF1

00002-001

39.8

NN

CONN. TOV-14001/K1AE 486635N 118915EL +103100

G6 B8

SELF RELIEVING

10

292

F3 G6 B8

150x20NS17MM OFFSET

1562

20x15NS3MM OFFSET

F4 G7

96

140LT1001AH

11140LT-1001AH

F5 B9

E 486076N 118915EL +103081

410

2000-110-MP-2343-1P10A-50-VT-140-00004-063484C-CF1-08 Revision 01 Isometric Split-out Project 23/11/2020

140 LT 1001AH 11

12

F4 G7 B9

1

F3 G6 B8

11

12

MOC: 106110P Status: AFC Date: 29/05/21 Rev: 01.01 Prepared By: Approved By:

80x50NS

14MM OFFSET

140LT-1001AH

106110P

106110P

106110P

106110P

106110P

106110P

Dims not shown, Items fitting to fitting.

1

For gasket between flushing ring and diaphragm instrument see instrument hook up drawing 2000-110-F001-PR01-G00000-IN-2335-00001

SST-1P10A-90140

Injection Point #5

sherzha
Text Box
FOR INFORMATION ONLY

FABRICATION MATERIALS

PTNO

COMPONENT DESCRIPTION N.S.((MM))

MESC QTY

PIPE

1 Pipe, ASME B36.19 / B36.10, PE,Seamless, Welded option is alsoacceptable, but shall be impacttested./S-40S ASTM A312 Gr. TP316/316L,

50 743623.058.F 0.2M

FITTINGS

2 Eccentric reducer, ASME B16.9, BW,Seamless, Welded option is alsoacceptable, but shall be impacttested./S-40S/S-40S ASTM A403 Gr.WP316/316L,

50 x 20 763371.635.F 1

3 45 Deg elbow LR, ASME B16.9, BW,Seamless, Welded option is alsoacceptable, but shall be impacttested./S-40S ASTM A403 Gr. WP316/316L,

50 763338.336.F 1

4 Eccentric reducer, ASME B16.9, BW,Seamless, Welded option is alsoacceptable, but shall be impacttested./S-40S/S-40S ASTM A403 Gr.WP316/316L,

20 x 15 763371.566.F 1

FLANGES

5 Weldneck flange, ASME B16.5, RF, 600Lbs, -,/S-40S ASTM A182 Gr. F316/316L,

50 766580.490.1 3

6 Weldneck flange, ASME B16.5, RF, 600Lbs, -,/S-40S ASTM A182 Gr. F316/316L,

15 766580.482.1 1

7 Lap joint flange, ASME B16.5, FF, 600Lbs, -,/ ASTM A182 Gr. F316/316L,

15 766520.758.1 1

ERECTION MATERIALS

PTNO

COMPONENT DESCRIPTION N.S.((MM))

MESC QTY

GASKETS

8 Spiral wound gasket, ASME B16.20, RF asper B16.5, 600 Lbs, -, Thk = 4.5 mm,Inner AISI 316 / Outer CS, -,/ S.S. 316/ Graphite,

50 854136.414.1 3

9 Spiral wound gasket, ASME B16.20, RF asper B16.5, 600 Lbs, -, Thk = 4.5 mm,Inner AISI 316 / Outer CS, -,/ S.S. 316/ Graphite,

15 854136.404.1 1

BOLTS

10 110 mm Length:Stud bolt 2 nuts, BS 4882/ ASME B18.2.2, Full length threaded, -,-, A193 Gr. B8M Cl. 2 / A194 Gr. 8M +S1,

5/8 INS 813846.274.1 24

11 90 mm Length:Stud bolt 2 nuts, BS 4882 /ASME B18.2.2, Full length threaded, -,-, A193 Gr. B8M Cl. 2 / A194 Gr. 8M +S1,

1/2 INS 813846.159.1 4

VALVES / IN-LINE ITEMS

12 Cryo.Ball Flg RB Lp, ISO 17292, RF, 600Lbs, 2 Pieces Split Body, ExtendedBolted Bonnet, Floating Ball, Seats :RPTF/.. ASTM A351 Gr. CF8M,

50 770325.108.F 1

INSTRUMENTS

13 Lap Joint Compression Fitting for RemoteMount System, 600 Lbs

15 - 1

1 1

59.3 -58.7

75 65

82.52 P

AFC-EPCI-APPROVED FOR CONSTRUCTIONAFC-EPCI-APPROVED FOR CONSTRUCTION

/140 1P10A 50-VT-140-00004-063484C-CF1-090 25/03/13 VJ

VJ

SI SL/BH

SL/BH1 28/08/2013 AFC-EPCI-ORIGIN OF REVISION : PMS SK

2Z

2Z

12/08/2016 ASB-EPCI-AS BUILT MAR GGA RAV

L1

L1

N/A

N/A

/CF1

00002-001

51.8

NN CONN. TOV-14001/K3AE 486687N 118548EL +103100

F5 G8 B10

50NS

1

330o

162

45

159

1

50NS

F5 G8 B10

162

SELF RELIEVING

12

292

311

330

317

F5 G8 B10

250x20NS17MM OFFSET

155

420x15NS3MM OFFSET

F6 G9

96

140LT1001CH

13140LT-1001CH

F7 B11

E 486027N 117984EL +103081

409

2000-110-MP-2343-1P10A-50-VT-140-00004-063484C-CF1-09 Revision 01 Isometric Split-out Project 23/11/2020

140 LT1001CH 14

1514

15

F6 G9 B11

2

F5 G8 B10

MOC: 106110P Status: AFC Date: 29/05/21 Rev: 01.01 Prepared By: Approved By:

80x50NS

14MM OFFSET

140LT-1001CH

106110P

106110P

106110P

106110P

106110P

106110P

Dims not shown, Items fitting to fitting. For gasket between flushing ring and diaphragm instrument see instrument hook up drawing 2000-110-F001-PR01-G00000-IN-2335-00001

1

SST-1P10A-90139

Injection Point #6

sherzha
Text Box
FOR INFORMATION ONLY

4

Yes

5

PPS HP / LP Actuated Time Date Time Date Time Date

Tag No. Interface? Valve? PPS Rep. Customer PPS Rep. Customer PPS Rep. Customer

T1

T2

T3

T4

T5

T6

T7

T8

T9 Yes

T10 Yes

T11

T12 Yes

T13

T14

T15 Yes

T16 Yes

T17

T18

TP 003

Isolate Valve to PDIA

400mm Ball Valve

N/A

RV 1001 A

QV-1402286

UZV-2811

UZV-2021

N/A

UZV-2013

QV-1400120

QV-1400126

HSV-1138

HSV-1137

PDIA

QV-1400065

80mm Ball Valve

150mm Ball Valve

150mm Ball Valve

80mm Spade

250mm Butterfly Valve

450mm Ball Valve

450mm Ball Valve

80mm Ball Valve

450mm Butterfly Valve

50mm Ball Valve

50mm Ball Valve

N/A

N/A

N/A

N/A

N/A

50mm Ball Valve

40mm RV in place

Test #3Test #2

All listed Test Limit Isolations (T#) must be in the CLOSED position.

U14000-PX-2365-00002-001

Customer Work Order No.

C-0382-21Shell Australia

Prelude Pitstop Oct 2021

Prelude FLNG

Customer

0

Test Pack Number

Test Pack Name

Checklist Number

Project 0

C4. Test Limit Isolations Checklist #1

Drawing Number

Test Limit Isolations Test #1

Location

140LT-1001A/B/C Leak Test

1 of 1

TP 003

PPS Job Number

Customer Contract No.

U14000-PX-2365-00003-001

U14000-PX-2365-00003-001

U14000-PX-2365-00002-001

U14000-PX-2365-00002-001

U14000-PX-2365-00002-001

U14000-PX-2365-00002-001

U14000-PX-2365-00002-001

U14000-PX-2365-00002-001

U14000-PX-2365-00002-001

U14000-PX-2365-00002-001

U14000-PX-2365-00001-001

U14000-PX-2365-00001-001

U14000-PX-2365-00002-001

U14000-PX-2365-00002-001

U14000-PX-2365-00002-001

U14000-PX-2365-00003-001

DescriptionCustomer

Tag No.

50mm Ball Valve

50mm Ball Valve

50mm Ball Valve

Revision Date: 21-Sep-2021

U14000-PX-2365-00003-001

B

HLD Test Pack No.:

Prelude Pitstop Oct 2021

140LT-1001A/B/C Leak Test

Document Number:

Copyright Baker Hughes Company. All Rights Reserved.

Shell AustraliaC-0382-21 / HLD / TP 003

Revision Number:

4

No

0

PPS Actuated Time Date Time Date Time Date

Tag No. Valve? PPS Rep. Customer PPS Rep. Customer PPS Rep. Customer

S1

S2

S3

S4

S5

S6

S7

S8

S9

S10

TP 003

Customer

Tag No.

N/A

N/A

N/A

QV-1402287

QV-1400002

QV-1400009

QV-1400045

N/A

N/A

N/A

Copyright Baker Hughes Company. All Rights Reserved.

Shell Australia

Prelude Pitstop Oct 2021

140LT-1001A/B/C Leak Test

HLD Test Pack No.:

Revision Number: B

Revision Date: 21-Sep-2021

Document Number: C-0382-21 / HLD / TP 003

Drawing Number

Customer Contract No.

U14000-PX-2365-00002-001

U14000-PX-2365-00002-001

U14000-PX-2365-00002-001

U14000-PX-2365-00002-001

Description

10mm drip ring of flange at K3B for Injection Point

10mm drip ring of flange at K2B for Injection Point

10mm drip ring of flange at K1B for Injection Point

80mm Ball Valve

80mm Ball Valve

50mm Ball Valve

50mm Globe Valve

10mm drip ring of flange at K3A for Injection Point

10mm drip ring of flange at K2A for Injection Point

10mm drip ring of flange at K1A for Injection Point

0

Prelude FLNG

U14000-PX-2365-00002-001

U14000-PX-2365-00002-001

U14000-PX-2365-00002-001

Test Pack Number

U14000-PX-2365-00002-001

U14000-PX-2365-00002-001

All listed Safety Components (S#) must be in the OPEN position or be CORRECTLY ORIENTATED .

All other manual valves within test limit boundaries must be in the OPEN position.

Project

Location

TP 003

Customer Work Order No. 0 Checklist Number 1 of 1

Prelude Pitstop Oct 2021

Safety Components Test #1 Test #2 Test #3

U14000-PX-2365-00002-001

C5. Safety Components Checklist #1

Customer C-0382-21 Test Pack NameShell Australia PPS Job Number 140LT-1001A/B/C Leak Test

3

Yes

6

PPS Required Instrument Time Date

Tag No. Position Technician

T9 Closed

T10 Closed

T12 Closed

T15 Closed

T16 Closed

TP 003

UZV-2021

UZV-2013

HSV-1138

HSV-1137

150mm Ball Valve

250mm Butterfly Valve

80mm Ball Valve

450mm Butterfly Valve

Document Number: C-0382-21 / HLD / TP 003 Shell Australia

Copyright Baker Hughes Company. All Rights Reserved. HLD Test Pack No.:

Revision Number: B Prelude Pitstop Oct 2021

Revision Date: 21-Sep-2021 140LT-1001A/B/C Leak Test

Project Prelude Pitstop Oct 2021 Customer Contract No. 0 Test Pack Number TP 003

U14000-PX-2365-00002-001

U14000-PX-2365-00002-001

U14000-PX-2365-00003-001

U14000-PX-2365-00002-001

U14000-PX-2365-00003-001

C6. Actuated Valve Checklist #1

Customer Shell Australia PPS Job Number C-0382-21 Test Pack Name 140LT-1001A/B/C Leak Test

1

The customer Instrument Technician is responsible for isolating the actuated valves listed in this checklist in accordance with

the instructions provided below. All valves tagged T# must be CLOSED . All valves tagged S# must be OPEN .

Actuated Valve Checklist Isolations Completed

Location Prelude FLNG

Drawing Number Comments

Test Number

Description

150mm Ball Valve

Customer

Tag No.

UZV-2811

Customer Work Order No. 0 Checklist Number 1 of 1

4

No

0

Step Time Date Time Date Time Date

No. PPS Customer PPS Customer PPS Customer

1

2

3

4

5

6

7

TP 003

Revision Date: 21-Sep-2021 140LT-1001A/B/C Leak Test

Copyright Baker Hughes Company. All Rights Reserved. HLD Test Pack No.:

Document Number: C-0382-21 / HLD / TP 003 Shell Australia

Revision Number: B Prelude Pitstop Oct 2021

fittings

Remove and sign off test charts Note date and time correct

Advise client and suspend or close (complete) the test permit.

Ensure noise levels are acceptable.

With 0.5 bar remaining in the system, confirm with customer to ensure oxygen content Check with Customer

within system is at acceptable level O2 meter level

Cycle all potential trapped pressure areas A. Test Pack Information

Refer to A. Test Pack Information for all identified trapped pressure points. Monitor system Pressure

Liaise with Customer in order to remove all PPS equipment and re-instate any removed Check with Customer

blanket is to be left in the system.

Confirm depressurisation may commence. Check with Customer

For depressurisation, open bleed valve at 6-way Injection manifold to depressurise Monitor system pressure

to safe location Monitor pipework for chilling

Monitor and control the rate of depressurisation whilst observing signs of chilling on the

pipework caused by Joules-Thomson effect.

0 Checklist Number

Complete the following instructions sequentially to safely depressurize the entire test system.

Ensure the 'Maximum Allowable Depressurization Rate' and the 'Vent System Maximum Allowable Pressure' are not exceeded.

Ensure the customer representative is informed of any unavoidable 'Trapped Pressure' areas, or residual pressure, left in the system.

System Depressurization Instructions Test #1 Test #2 Test #3

1 of 1Location Prelude FLNG Customer Work Order No.

Description Verification

Confirm with Customer if system is to be depressurised to atmospheric pressure or if an N2 Check with Customer

140LT-1001A/B/C Leak Test

Project Prelude Pitstop Oct 2021 Customer Contract No. 0 Test Pack Number TP 003

Customer Shell Australia PPS Job Number C-0382-21 Test Pack Name

C7. System Depressurisation Checklist #1

6

Yes

8

Item

No. Initial Date Initial Date

1

2

3

4

5

1 of 2

TP 003

Main equipment correctly positioned and inspected Procedure, Section 7.1 Visual Inspection / ITP PPSEquipment Preparation

Test System Preparation Test system confirmed as mechanically complete Procedure, Section 6.1 Customer Confirmation / ITP

Pressurization pumps function tested Procedure, Section 7.1 Witnessed/ ITP

OPPS trip pressure correctly set and tested Test Pack, Section A1 Witnessed / ITP

Hoses / iron pressure tested to 90% MAWP Procedure, Section 7.3 Pressure Test Data

Customer

Procedure, Section 7.2 B Marked Drawings

PPS = PPS Supervisor Customer = Customer Rep., or nominated Third Party Rep. Gray cells do not require signature.

PPS

Prelude Pitstop Oct 2021

HLD Test Pack No.:

Customer

Visual Inspection / ITP

Visual Inspection / ITP

Visual Inspection / ITP

Visual Inspection / ITP

Witnessed / ITP

Audible Test/ ITP

Party

Toolbox Talk - Preparation Toolbox talk held and risk assessment reviewed PPS & Customer

Hoses / iron safely routed and secured PPS

Visual Inspection / ITP

Test Pack, Section A1

Test Pack, Section A1

Test Pack, Section A1

Procedure, Section 7.1

Procedure, Section 7.1

Procedure, Section 5.3

Procedure, Section 7.1

Procedure, Section 7.2 C1 Punch List

PPS

Document Number:

Revision Number:

Revision Date:

Procedure, Section 7.2

Procedure, Section 7.2

Visual Inspection / ITP

C5 Safety Components

All potential leak sources taped up

Procedure, Section 7.2

C2 Mechanical Preparation

B Marked Drawings

Procedure, Section 7.2

C4 Test Limit Isolations PPS & Customer

Copyright Baker Hughes Company. All Rights Reserved.

PPS

PPS & Customer

PPS

PPS

PPS & Customer

Customer

Customer

PPS

Procedure, Section 6.5

C-0382-21 / HLD / TP 003

B

21-Sep-2021

Test Number 1

Pressure instrumentation installed correctly

Jumper hoses installed correctly

Injection manifold(s) installed correctly

Not Applicable

PPS

PPS

PPS

Temporary PRV(s) installed correctly

Certification validated for items used in rig up

Radios inspected, charged, and function tested

Mechanical preparation work for testing completed

System alignment verified prior to pressurization

Procedure, Section 7.1

Project Prelude Pitstop Oct 2021 Customer Contract No.

Location Prelude FLNG Customer Work Order No.

Customer Shell Australia PPS Job Number

D. Inspection and Test Plan (ITP) #1

Test Pack Name

Test Pack Number

Test Date

140LT-1001A/B/C Leak Test

TP 003

C-0382-21

0

Area cleared of unauthorized personnel

Test Pack, Section A1

PPS Safe to Perform (STP)

Punch list items identified and closed out

Barriers erected and warning signs postedTest Exclusion Zone

Equipment Function Test Helium leak detector correctly calibrated

Visual Inspection / ITP

140LT-1001A/B/C Leak Test

Shell Australia

0

Operation Activity Responsible PPSControlling

Document

Verification

1

Yes

15

Item

No. Initial Date Initial Date

6

7

8

9

10

11

2 of 2

TP 003

Customer Representatives

C-0382-21 Test Pack Name 140LT-1001A/B/C Leak Test

0 Test Pack Number TP 003

Customer Shell Australia PPS Job Number

1

Operation Activity

Customer Contract No.

Location Prelude FLNG

Test Number

Customer

Project Prelude Pitstop Oct 2021

Toolbox Talk - Leak Test Toolbox Talk held and risk assessment reviewed Procedure, Section 7.3 PPS Safe to Perform (STP) PPS

Verification Responsible PPS

Document Party

Procedure, Section 7.4 Witnessed / ITP PPS

0 Test Date

Controlling

System Pressurization System safely pressurized to final test pressure Test Pack, Section A1 Pressure Test Data PPS

Customer Work Order No.

System Leak Test Leak detector calibrated using system gas sample

Procedure, Section 7.5 C7 System Depressurization PPS

System Reinstatement All leak detection tape removed from test system Procedure, Section 7.5 Visual Inspection / ITPPPS

All potential leak sources tested for leakage Procedure, Section 7.4 B Marked Drawings PPS

Leaking components recorded and tagged Procedure, Section 7.4 E1 Leak Description Report PPS

System depressurized to atmospheric pressure

Copyright Baker Hughes Company. All Rights Reserved. HLD Test Pack No.:

D. Inspection and Test Plan (ITP) #1

Shell Australia

(after final test) Barriers and warning signs removed

Components removed for test have been reinstated

Prelude Pitstop Oct 2021

Procedure, Section 6.1 C8 Mechanical Reinstatement Customer

System Depressurization

140LT-1001A/B/C Leak Test

Test Pack Paperwork Test documentation issued to the customer Procedure, Section 8 ITP PPS & Customer

Comments

Note for the Leak Test Acceptance criteria:

Due to the small volume of the test system, and low assurance in primary isolation valves tightly holding the pressure, the pressure drop during the test is permitted to exceed 10%, this has been discussed and agreed by

C-0382-21 / HLD / TP 003

B

21-Sep-2021

Document Number:

Revision Number:

Revision Date:

PPS Job Number

2 Customer Contract No.

Yes Customer Work Order No.

Leak Customer

No. Tag Number Date Date Date

(L#) Test #1 Test #2 Test #3

TP 003Copyright Baker Hughes Company. All Rights Reserved.

Document Number: C-0382-21 / HLD / TP 003

PPS Representative

Customer Representative #1

HLD Test Pack No.:

Prelude Pitstop Oct 2021

Date

Shell Australia

Customer Representative #2

SignatureJob TitleName

140LT-1001A/B/C Leak TestRevision Date: 21-Sep-2021

Revision Number: B

E1. Leak Description Report #1

Project

Location

Customer Shell Australia C-0382-21

1 of 10

Test Pack Name

Test Pack Number

Report Number

140LT-1001A/B/C Leak Test

TP 003

Drawing Number

Prelude FLNG

9

Prelude Pitstop Oct 2021 0

Leak Description scf/yrCause

of Leak

1

No

0

50

100

N/A

20

barg

67.5

B

TP 003

Pressure remained within 10% (preferably but not mandatory for this test) of the test pressure for the duration of the test.

All identified leaks (> maximum allowable leak rate threshold) were recorded on the Leak Description Report.

E2. Leak Detection Completion Certificate

Leak Test

Customer

Project Information

Test Pack Information

Test Pack Name 140LT-1001A/B/C Leak Test Test Method Helium Leak Detection

C-0382-21

Project

Location

PPS Job Number

Customer Contract No.

Customer Work Order No.

Refer to the 'Witness Joint Register' for a list of components that could not be tested.

The system was repaired and re-tested a total of _ times before the acceptance criteria were met.

The system was pressurised to 67.5 barg with a 1% helium / 99% nitrogen test gas mixture.

All potential leak sources nominated for testing were checked for leakage using a calibrated helium leak detector.

Maximum allowable leak rate threshold from any single leak source did not exceed:

scf/yr

scf/yr

scf/yr

scf/yr

Acceptance

Valve glands and bonnets

Pig launcher and receiver doors

Clamp connectors

All other potential leak sources

Leak Test Results

67.5

0

0

1

Shell Australia

Prelude Pitstop Oct 2021

Prelude FLNG

Calibration Date

Instrumentation

Description Serial Number Calibration Certificate No.

Test Pack Number TP 003 Test Medium

Leak Test and Acceptance Criteria

1% Helium / 99% Nitrogen

Customer Rep. #1

140LT-1001A/B/C Leak Test

HLD Test Pack No.:Copyright Baker Hughes Company. All Rights Reserved.

Document Number: C-0382-21 / HLD / TP 003

Revision Number:

21-Sep-2021Revision Date:

Shell Australia

Prelude Pitstop Oct 2021

Customer Rep. #2

Name

PPS Rep.

Job Title DateSignature

Test Number Test Date Test Pressure Total Number of Comments

barg Joints Tested Leaks Found

2

Yes

10

Witness

Joint No.

TP 003

E3. Witness Joint Register #1

Shell Australia

Prelude Pitstop Oct 2021

Prelude FLNG

Test Pack Name

The customer is responsible for checking these components for leakage in accordance with their company protocol.

1 of 1

Witness Joints

Customer

Project

Location

Test Pack Number

Register Number

140LT-1001A/B/C Leak Test

TP 003

The system components listed below were NOT tested as part of this test pack and are 'Witness Joints'.

Drawing Number

Issued to the Customer Representative

140LT-1001A/B/C Leak Test

Time and Date

PPS Representative

Revision Date: 21-Sep-2021

Copyright Baker Hughes Company. All Rights Reserved. HLD Test Pack No.:

Document Number: C-0382-21 / HLD / TP 003

Revision Number: B

Shell Australia

Prelude Pitstop Oct 2021

Customer Rep. #2

Name Job Title Signature

Description

Customer Rep. #1

Customer

Tag Number


Recommended