+ All Categories
Home > Documents > Balchik Integrated Water Project in Bulgaria ISPA Measure 2002 BG 17 P PE 017 WWTP BALCHIK.

Balchik Integrated Water Project in Bulgaria ISPA Measure 2002 BG 17 P PE 017 WWTP BALCHIK.

Date post: 05-Jan-2016
Category:
Upload: eugene-maurice-mason
View: 220 times
Download: 0 times
Share this document with a friend
14
Balchik Integrated Water Project in Bulgaria ISPA Measure 2002 BG 17 P PE 017 WWTP BALCHIK
Transcript
Page 1: Balchik Integrated Water Project in Bulgaria ISPA Measure 2002 BG 17 P PE 017 WWTP BALCHIK.

Balchik Integrated Water Project in Bulgaria

ISPA Measure 2002 BG 17 P PE 017

WWTP BALCHIK

Page 2: Balchik Integrated Water Project in Bulgaria ISPA Measure 2002 BG 17 P PE 017 WWTP BALCHIK.

Works ContractWWTP Balchik

• Commencement Date: 28thJune 2006

• Completion Date: 10th March 2010

• Physical Execution: 100 %

• Contract Price: 3 868 061.09 Euro

• WWTP became operational on 10th March 2010

Page 3: Balchik Integrated Water Project in Bulgaria ISPA Measure 2002 BG 17 P PE 017 WWTP BALCHIK.

Taking –over of the Works and Sections ofWWTP Balchik

Page 4: Balchik Integrated Water Project in Bulgaria ISPA Measure 2002 BG 17 P PE 017 WWTP BALCHIK.

WWTP BALCHIK

Aeration tank Sludge tank

Page 5: Balchik Integrated Water Project in Bulgaria ISPA Measure 2002 BG 17 P PE 017 WWTP BALCHIK.

WWTP BALCHIK

Main Tanks

Page 6: Balchik Integrated Water Project in Bulgaria ISPA Measure 2002 BG 17 P PE 017 WWTP BALCHIK.

Scroober installation at

Chlorination Building

WWTP BALCHIK

Page 7: Balchik Integrated Water Project in Bulgaria ISPA Measure 2002 BG 17 P PE 017 WWTP BALCHIK.

Balchik Water Supply& Sewerage Network ConnectionsWorks Contract

ISPA Measure 2002 BG 17 P PE 017

• Commencement Date: 07th January 2008

• Completion Date: 23th December 2011

• Physical Execution: 100%

• Contract Price: 8 658 308.34 Euro

• The Water Supply and Sewerage networks became operational on 23th December 2011

Page 8: Balchik Integrated Water Project in Bulgaria ISPA Measure 2002 BG 17 P PE 017 WWTP BALCHIK.

Balchik Water Supply& Sewerage Network Connections

Information boards

Page 9: Balchik Integrated Water Project in Bulgaria ISPA Measure 2002 BG 17 P PE 017 WWTP BALCHIK.

Balchik Water Supply&Sewerage Network Connections

Main sewerage and house connections

Compaction as layer on sewer line , Part III, Section F

Page 10: Balchik Integrated Water Project in Bulgaria ISPA Measure 2002 BG 17 P PE 017 WWTP BALCHIK.

Backdrop Manhole, Part IV, Section A

Balchik Water Supply&Sewerage Network Connections

Excavation on water supply main pipe, Part IV, Section A

Page 11: Balchik Integrated Water Project in Bulgaria ISPA Measure 2002 BG 17 P PE 017 WWTP BALCHIK.

Balchik Water Supply& Sewerage Network Connections

Excavation on Water Main – G. Milev Street

Page 12: Balchik Integrated Water Project in Bulgaria ISPA Measure 2002 BG 17 P PE 017 WWTP BALCHIK.

Balchik Water Supply& Sewerage Network Connections

Covering pipe for pressure under the Kavarna motorway

Page 13: Balchik Integrated Water Project in Bulgaria ISPA Measure 2002 BG 17 P PE 017 WWTP BALCHIK.

Balchik Water Supply& Sewerage Network Connections

Main to Reservoir (Tsarichino) excavation

Page 14: Balchik Integrated Water Project in Bulgaria ISPA Measure 2002 BG 17 P PE 017 WWTP BALCHIK.

Balchik Water Supply& Sewerage Network Connections

Welding activities on Tsarichino main pressure conduit


Recommended