ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
PROGRESS MASTER SCHEDULE of CONSTRUCTIONPIPINGPOWER BLOCKGAS TURBINE COMMONPIPINGFUEL OIL SUPPLY SYSTEMPIPING 130010101 Carry In/Temporary Laydown 0 15 15NOV10* 29NOV10 15NOV10* 29NOV10 0.14 0.00 166.00 0.00 125.70
130010102 Fit-up Welding 0 30 17NOV10 16DEC10 17NOV10 16DEC10 0.21 0.00 1,538.00 0.00 188.55
130010103 Fit-up Screw ( Included Ti 0 5 17DEC10 21DEC10 17DEC10 21DEC10 0.10 0.00 0.00 0.00 94.28
130010104 Fit-up Flange ( Included T 0 20 22DEC10 10JAN11 22DEC10 10JAN11 0.10 0.00 148.00 0.00 94.28
130010105 Welding 0 35 18NOV10 22DEC10 18NOV10 22DEC10 0.42 0.00 1,538.00 0.00 377.10
130010106 NDT 0 30 25NOV10 24DEC10 25NOV10 24DEC10 0.04 0.00 0.00 0.00 37.71
130010108 Support 0 45 15NOV10 29DEC10 15NOV10 29DEC10 0.21 0.00 0.00 0.00 188.55
130010109 Pressure Test 0 30 30DEC10 28JAN11 30DEC10 28JAN11 0.04 0.00 0.00 0.00 37.71
130010110 Flushing 0 105 15JUN11* 27SEP11 15JUN11* 27SEP11 0.03 0.00 0.00 0.00 25.14
FUEL GAS SUPPLY SYSTEMPIPING 130020101 Carry In/Temporary Laydown 0 20 25DEC10 13JAN11 25DEC10 13JAN11 0.03 0.00 38.00 0.00 31.40
130020102 Fit-up Welding 0 30 27DEC10 25JAN11 27DEC10 25JAN11 0.05 0.00 376.00 0.00 47.10
130020104 Fit-up Flange ( Included T 0 30 26JAN11 24FEB11 26JAN11 24FEB11 0.03 0.00 172.00 0.00 23.55
130020105 Welding 0 35 28DEC10 31JAN11 28DEC10 31JAN11 0.10 0.00 376.00 0.00 94.20
130020106 NDT 0 35 30DEC10 02FEB11 30DEC10 02FEB11 0.01 0.00 0.00 0.00 9.42
130020108 Support 0 45 25DEC10 07FEB11 25DEC10 07FEB11 0.05 0.00 0.00 0.00 47.10
130020109 Pressure Test 0 20 08FEB11 27FEB11 08FEB11 27FEB11 0.01 0.00 0.00 0.00 9.42
130020110 Flushing 0 30 15MAR11* 13APR11 15MAR11* 13APR11 0.01 0.00 0.00 0.00 6.28
INSTRUMENT AIR SYSTEMPIPING 130050101 Carry In/Temporary Laydown 0 15 01NOV10 15NOV10 04NOV10 18NOV10 0.14 0.00 349.00 0.00 125.68
130050102 Fit-up Welding 0 30 01NOV10 30NOV10 04NOV10 03DEC10 0.21 0.00 1,057.00 0.00 188.52
130050103 Fit-up Screw ( Included Ti 0 10 01DEC10 10DEC10 04DEC10 13DEC10 0.10 0.00 3.00 0.00 94.26
130050104 Fit-up Flange ( Included T 0 10 11DEC10 20DEC10 14DEC10 23DEC10 0.10 0.00 58.00 0.00 94.26
130050105 Welding 0 30 02NOV10 01DEC10 05NOV10 04DEC10 0.42 0.00 1,057.00 0.00 377.04
130050106 NDT 0 45 10NOV10 24DEC10 13NOV10 27DEC10 0.04 0.00 0.00 0.00 37.70
130050108 Support 0 45 02NOV10 16DEC10 05NOV10 19DEC10 0.21 0.00 0.00 0.00 188.52
130050109 Pressure Test 0 15 17DEC10 31DEC10 20DEC10 03JAN11 0.04 0.00 0.00 0.00 37.70
130050110 Flushing 0 15 01MAR11 15MAR11 01MAR11 15MAR11 0.03 0.00 0.00 0.00 25.14
CIRCULATING WATER SYSTEMPIPING 130110101 Carry In/Temporary Laydown 0 21 16SEP10* 06OCT10 04NOV10* 24NOV10 0.14 0.00 0.00 0.00 125.68
130110102 Fit-up Welding 0 16 21OCT10 05NOV10 09DEC10 24DEC10 0.21 0.00 0.00 0.00 188.52
130110103 Fit-up Screw ( Included Ti 0 16 06OCT10 21OCT10 24NOV10 09DEC10 0.10 0.00 0.00 0.00 94.26
130110104 Fit-up Flange ( Included T 0 18 04JAN11* 21JAN11 21JAN11* 07FEB11 0.10 0.00 0.00 0.00 94.26
130110105 Welding 0 31 23OCT10 22NOV10 11DEC10 10JAN11 0.42 0.00 0.00 0.00 377.04
130110106 NDT 0 31 28OCT10 27NOV10 16DEC10 15JAN11 0.04 0.00 0.00 0.00 37.70
130110108 Support 0 78 16SEP10 02DEC10 04NOV10 20JAN11 0.21 0.00 0.00 0.00 188.52
130110109 Pressure Test 0 16 15JUN11* 30JUN11 15JUN11* 30JUN11 0.04 0.00 0.00 0.00 37.70
130110110 Flushing 0 1 15JUL11* 15JUL11 15JUL11* 15JUL11 0.03 0.00 0.00 0.00 25.14
CLOSED COOLING WATER SYSTEMPIPING 130130101 Carry In/Temporary Laydown 0 30 22NOV10* 21DEC10 22NOV10* 21DEC10 0.07 0.00 19.00 0.00 66.70
130130102 Fit-up Welding 0 35 24NOV10 28DEC10 22NOV10 26DEC10 0.11 0.00 53.00 0.00 100.05
130130103 Fit-up Screw ( Included Ti 0 10 18JAN11 27JAN11 16JAN11 25JAN11 0.06 0.00 0.00 0.00 50.03
130130104 Fit-up Flange ( Included T 0 20 29DEC10 17JAN11 27DEC10 15JAN11 0.06 0.00 8.00 0.00 50.03
130130105 Welding 0 45 26NOV10 09JAN11 24NOV10 07JAN11 0.22 0.00 53.00 0.00 200.10
2010 2011APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 1
Primavera Systems, Inc.
Start Date 30APR10Finish Date 01NOV11Data Date 04NOV10Run Date 08NOV10 13:27
Early Bar
Target Bar
Progress Bar
Critical Activity
GFPP
PLN TANJUNG PRIOK GFPPEP 740 MW
GFPPEP
PPSS for Piping Schedule Level 6
Sheet 1 of 30Date Revision Checked Approved
Sheet 2 of 30
ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
130130106 NDT 0 45 03DEC10 16JAN11 01DEC10 14JAN11 0.02 0.00 0.00 0.00 20.01
130130108 Support 0 45 22NOV10 05JAN11 22NOV10 05JAN11 0.11 0.00 0.00 0.00 100.05
130130109 Pressure Test 0 20 06JAN11 25JAN11 06JAN11 25JAN11 0.02 0.00 0.00 0.00 20.01
130130110 Flushing 0 30 01JUL11 30JUL11 01JUL11 30JUL11 0.01 0.00 0.00 0.00 13.34
SERVICE AIR SYSTEMPIPING 130160101 Carry In/Temporary Laydown 0 104 22OCT10* 02FEB11 04NOV10* 15FEB11 0.14 0.00 138.00 0.00 125.68
130160102 Fit-up Welding 0 103 24OCT10 03FEB11 06NOV10 16FEB11 0.21 0.00 517.00 0.00 188.52
130160103 Fit-up Screw ( Included Ti 0 9 08FEB11 16FEB11 21FEB11 01MAR11 0.10 0.00 0.00 0.00 94.26
130160104 Fit-up Flange ( Included T 0 44 27DEC10 08FEB11 09JAN11 21FEB11 0.10 0.00 14.00 0.00 94.26
130160105 Welding 0 103 26OCT10 05FEB11 08NOV10 18FEB11 0.42 0.00 517.00 0.00 377.04
130160106 NDT 0 103 22OCT10 01FEB11 04NOV10 14FEB11 0.04 0.00 0.00 0.00 37.70
130160108 Support 0 117 28OCT10 21FEB11 10NOV10 06MAR11 0.21 0.00 0.00 0.00 188.52
130160109 Pressure Test 0 1 15FEB11 15FEB11 28FEB11 28FEB11 0.04 0.00 0.00 0.00 37.70
130160110 Flushing 0 21 15MAR11* 04APR11 15MAR11* 04APR11 0.03 0.00 0.00 0.00 25.14
WATER INJECTION SYSTEMPIPING 130200101 Carry In/Temporary Laydown 0 20 30NOV10* 19DEC10 30NOV10* 19DEC10 0.06 0.00 0.00 0.00 50.40
130200102 Fit-up Welding 0 20 02DEC10 21DEC10 02DEC10 21DEC10 0.08 0.00 0.00 0.00 75.60
130200103 Fit-up Screw ( Included Ti 0 10 22DEC10 31DEC10 22DEC10 31DEC10 0.04 0.00 0.00 0.00 37.80
130200104 Fit-up Flange ( Included T 0 10 01JAN11 10JAN11 01JAN11 10JAN11 0.04 0.00 0.00 0.00 37.80
130200105 Welding 0 30 03DEC10 01JAN11 03DEC10 01JAN11 0.17 0.00 0.00 0.00 151.20
130200106 NDT 0 30 08DEC10 06JAN11 08DEC10 06JAN11 0.02 0.00 0.00 0.00 15.12
130200108 Support 0 45 30NOV10 13JAN11 30NOV10 13JAN11 0.08 0.00 0.00 0.00 75.60
130200109 Pressure Test 0 15 17JAN11 31JAN11 17JAN11 31JAN11 0.02 0.00 0.00 0.00 15.12
130200110 Flushing 0 30 01MAY11* 30MAY11 01MAY11* 30MAY11 0.01 0.00 0.00 0.00 10.08
CO2 FIRE FIGHTING SYSTEMPIPING 130240101 Carry In/Temporary Laydown 0 20 25DEC10 13JAN11 25DEC10 13JAN11 0.04 0.00 0.00 0.00 37.60
130240102 Fit-up Welding 0 40 25DEC10 02FEB11 25DEC10 02FEB11 0.06 0.00 0.00 0.00 56.40
130240103 Fit-up Screw ( Included Ti 0 20 03FEB11 22FEB11 03FEB11 22FEB11 0.03 0.00 0.00 0.00 28.20
130240104 Fit-up Flange ( Included T 0 30 23FEB11 24MAR11 23FEB11 24MAR11 0.03 0.00 0.00 0.00 28.20
130240105 Welding 0 60 02JAN11 02MAR11 02JAN11 02MAR11 0.13 0.00 0.00 0.00 112.80
130240106 NDT 0 60 19JAN11 19MAR11 19JAN11 19MAR11 0.01 0.00 0.00 0.00 11.28
130240108 Support 0 85 27DEC10 21MAR11 27DEC10 21MAR11 0.06 0.00 0.00 0.00 56.40
130240109 Pressure Test 0 20 13APR11* 02MAY11 13APR11* 02MAY11 0.01 0.00 0.00 0.00 11.28
130240110 Flushing 0 15 15JUL11* 29JUL11 15JUL11* 29JUL11 0.01 0.00 0.00 0.00 7.52
INSULATION & PAINTINGFUEL OIL SUPPLY SYSTEMPAINTING 130010201 Painting 0 30 29JAN11 27FEB11 29JAN11 27FEB11 0.03 0.00 0.00 0.00 25.14
FUEL GAS SUPPLY SYSTEMPAINTING 130020301 Painting 0 45 28FEB11 13APR11 28FEB11 13APR11 0.01 0.00 0.00 0.00 6.28
INSTRUMENT AIR SYSTEMPAINTING 130050301 Painting 0 20 31DEC10 19JAN11 03JAN11 22JAN11 0.03 0.00 0.00 0.00 25.14
CIRCULATING WATER SYSTEMPAINTING 130110301 Painting 0 308 16SEP10 20JUL11 04NOV10 07SEP11 0.03 0.00 0.00 0.00 25.14
CLOSED COOLING WATER SYSTEMPAINTING 130130301 Painting 0 20 26JAN11 14FEB11 26JAN11 14FEB11 0.01 0.00 0.00 0.00 13.34
SERVICE AIR SYSTEMPAINTING 130160301 Painting 0 117 22OCT10 15FEB11 04NOV10 28FEB11 0.03 0.00 0.00 0.00 25.14
WATER INJECTION SYSTEMPAINTING 130200301 Painting 0 10 01FEB11 10FEB11 01FEB11 10FEB11 0.01 0.00 0.00 0.00 10.08
CO2 FIRE FIGHTING SYSTEMPAINTING 130240301 Painting 0 10 04MAY11 13MAY11 04MAY11 13MAY11 0.01 0.00 0.00 0.00 7.52
2010 2011APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 1
Sheet 2 of 30
Sheet 3 of 30
ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
GAS TURBINE BUILDING UNIT 1PIPINGFUEL OIL SUPPLY SYSTEMPIPING 131010101 Carry In/Temporary Laydown 0 20 30NOV10* 19DEC10 30NOV10* 19DEC10 0.13 0.00 244.00 0.00 120.00
131010102 Fit-up Welding 0 30 02DEC10 31DEC10 02DEC10 31DEC10 0.20 0.00 242.50 0.00 180.00
131010103 Fit-up Screw ( Included Ti 0 10 01JAN11 10JAN11 01JAN11 10JAN11 0.10 0.00 0.00 0.00 90.00
131010104 Fit-up Flange ( Included T 0 30 11JAN11 09FEB11 11JAN11 09FEB11 0.10 0.00 177.50 0.00 90.00
131010105 Welding 0 50 03DEC10 21JAN11 03DEC10 21JAN11 0.40 0.00 242.50 0.00 360.00
131010106 NDT 0 46 06DEC10 20JAN11 06DEC10 20JAN11 0.04 0.00 0.00 0.00 36.00
131010108 Support 0 60 30NOV10 28JAN11 30NOV10 28JAN11 0.20 0.00 0.00 0.00 180.00
131010109 Pressure Test 0 30 29JAN11 27FEB11 29JAN11 27FEB11 0.04 0.00 0.00 0.00 36.00
131010110 Flushing 0 105 15JUN11* 27SEP11 15JUN11* 27SEP11 0.03 0.00 0.00 0.00 24.00
FUEL GAS SUPPLY SYSTEMPIPING 131020101 Carry In/Temporary Laydown 0 15 14JAN11 28JAN11 14JAN11 28JAN11 0.03 0.00 67.00 0.00 31.40
131020102 Fit-up Welding 0 20 14JAN11 02FEB11 14JAN11 02FEB11 0.05 0.00 72.00 0.00 47.10
131020104 Fit-up Flange ( Included T 0 15 03FEB11 17FEB11 03FEB11 17FEB11 0.03 0.00 194.00 0.00 23.55
131020105 Welding 0 30 15JAN11 13FEB11 15JAN11 13FEB11 0.10 0.00 72.00 0.00 94.20
131020106 NDT 0 30 14JAN11 12FEB11 14JAN11 12FEB11 0.01 0.00 0.00 0.00 9.42
131020108 Support 0 30 14JAN11 12FEB11 14JAN11 12FEB11 0.05 0.00 0.00 0.00 47.10
131020109 Pressure Test 0 10 13FEB11 22FEB11 13FEB11 22FEB11 0.01 0.00 0.00 0.00 9.42
131020110 Flushing 0 30 15MAR11* 13APR11 15MAR11* 13APR11 0.01 0.00 0.00 0.00 6.28
AIR AND FLUE GAS SYSTEMPIPING 131030101 Carry In/Temporary Laydown 0 30 30NOV10* 29DEC10 30NOV10* 29DEC10 0.14 0.00 382.00 0.00 125.80
131030102 Fit-up Welding 0 30 03DEC10 01JAN11 03DEC10 01JAN11 0.21 0.00 977.00 0.00 188.70
131030103 Fit-up Screw ( Included Ti 0 10 02JAN11 11JAN11 02JAN11 11JAN11 0.10 0.00 19.50 0.00 94.35
131030104 Fit-up Flange ( Included T 0 10 12JAN11 21JAN11 12JAN11 21JAN11 0.10 0.00 1,368.50 0.00 94.35
131030105 Welding 0 35 08DEC10 11JAN11 08DEC10 11JAN11 0.42 0.00 977.00 0.00 377.40
131030106 NDT 0 45 15DEC10 28JAN11 15DEC10 28JAN11 0.04 0.00 0.00 0.00 37.74
131030108 Support 0 50 30NOV10 18JAN11 30NOV10 18JAN11 0.21 0.00 0.00 0.00 188.70
131030109 Pressure Test 0 15 19JAN11 02FEB11 19JAN11 02FEB11 0.04 0.00 0.00 0.00 37.74
131030110 Flushing 0 30 15MAR11* 13APR11 15MAR11* 13APR11 0.03 0.00 0.00 0.00 25.16
GT WASHING AND DRAIN SYSTEMPIPING 131040101 Carry In/Temporary Laydown 0 20 20NOV10* 09DEC10 20NOV10* 09DEC10 0.15 0.00 268.00 0.00 139.20
131040102 Fit-up Welding 0 30 22NOV10 21DEC10 22NOV10 21DEC10 0.23 0.00 289.50 0.00 208.80
131040103 Fit-up Screw ( Included Ti 0 10 22DEC10 31DEC10 22DEC10 31DEC10 0.12 0.00 35.00 0.00 104.40
131040104 Fit-up Flange ( Included T 0 10 01JAN11 10JAN11 01JAN11 10JAN11 0.12 0.00 74.00 0.00 104.40
131040105 Welding 0 50 24NOV10 12JAN11 24NOV10 12JAN11 0.46 0.00 289.50 0.00 417.60
131040106 NDT 0 50 26NOV10 14JAN11 26NOV10 14JAN11 0.05 0.00 0.00 0.00 41.76
131040107 PWHT 0 1 12FEB11* 12FEB11 12FEB11* 12FEB11 0.00 0.00 8.00 0.00 0.00
131040108 Support 0 50 20NOV10 08JAN11 20NOV10 08JAN11 0.23 0.00 0.00 0.00 208.80
131040109 Pressure Test 0 15 09JAN11 23JAN11 09JAN11 23JAN11 0.05 0.00 0.00 0.00 41.76
131040110 Flushing 0 30 30APR11* 29MAY11 30APR11* 29MAY11 0.03 0.00 0.00 0.00 27.84
INSTRUMENT AIR SYSTEMPIPING 131050101 Carry In/Temporary Laydown 0 20 20NOV10* 09DEC10 20NOV10* 09DEC10 0.14 0.00 57.00 0.00 125.68
131050102 Fit-up Welding 0 30 20NOV10 19DEC10 20NOV10 19DEC10 0.21 0.00 29.50 0.00 188.52
131050103 Fit-up Screw ( Included Ti 0 10 20DEC10 29DEC10 20DEC10 29DEC10 0.10 0.00 8.00 0.00 94.26
131050104 Fit-up Flange ( Included T 0 10 30DEC10 08JAN11 30DEC10 08JAN11 0.10 0.00 14.00 0.00 94.26
131050105 Welding 0 30 20NOV10 19DEC10 20NOV10 19DEC10 0.42 0.00 29.50 0.00 377.04
131050106 NDT 0 30 20NOV10 19DEC10 20NOV10 19DEC10 0.04 0.00 0.00 0.00 37.70
131050108 Support 0 45 29NOV10 12JAN11 29NOV10 12JAN11 0.21 0.00 0.00 0.00 188.52
131050109 Pressure Test 0 15 13JAN11 27JAN11 13JAN11 27JAN11 0.04 0.00 0.00 0.00 37.70
131050110 Flushing 0 15 01MAR11* 15MAR11 01MAR11* 15MAR11 0.03 0.00 0.00 0.00 25.14
PURGE AIR SYSTEMPIPING 131060101 Carry In/Temporary Laydown 0 10 10DEC10* 19DEC10 10DEC10* 19DEC10 0.09 0.00 0.00 0.00 76.80
131060102 Fit-up Welding 0 10 10DEC10 19DEC10 10DEC10 19DEC10 0.13 0.00 0.00 0.00 115.20
131060103 Fit-up Screw ( Included Ti 0 10 20DEC10 29DEC10 20DEC10 29DEC10 0.06 0.00 0.00 0.00 57.60
2010 2011APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 1
Sheet 3 of 30
Sheet 4 of 30
ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
131060104 Fit-up Flange ( Included T 0 10 30DEC10 08JAN11 30DEC10 08JAN11 0.06 0.00 0.00 0.00 57.60
131060105 Welding 0 30 13DEC10 11JAN11 13DEC10 11JAN11 0.26 0.00 0.00 0.00 230.40
131060106 NDT 0 24 20DEC10 12JAN11 20DEC10 12JAN11 0.03 0.00 0.00 0.00 23.04
131060108 Support 0 40 10DEC10 18JAN11 10DEC10 18JAN11 0.13 0.00 0.00 0.00 115.20
131060109 Pressure Test 0 15 19JAN11 02FEB11 19JAN11 02FEB11 0.03 0.00 0.00 0.00 23.04
131060110 Flushing 0 30 02MAY11* 31MAY11 02MAY11* 31MAY11 0.02 0.00 0.00 0.00 15.36
NITROGEN GAS SYSTEMPIPING 131150101 Carry In/Temporary Laydown 0 15 20DEC10 03JAN11 20DEC10 03JAN11 0.01 0.00 0.00 0.00 9.00
131150102 Fit-up Welding 0 40 20DEC10 28JAN11 20DEC10 28JAN11 0.01 0.00 0.00 0.00 13.50
131150103 Fit-up Screw ( Included Ti 0 10 29JAN11 07FEB11 29JAN11 07FEB11 0.01 0.00 0.00 0.00 6.75
131150104 Fit-up Flange ( Included T 0 10 08FEB11 17FEB11 08FEB11 17FEB11 0.01 0.00 0.00 0.00 6.75
131150105 Welding 0 50 20DEC10 07FEB11 20DEC10 07FEB11 0.03 0.00 0.00 0.00 27.00
131150106 NDT 0 50 20DEC10 07FEB11 20DEC10 07FEB11 0.00 0.00 0.00 0.00 2.70
131150108 Support 0 50 20DEC10 07FEB11 20DEC10 07FEB11 0.01 0.00 0.00 0.00 13.50
131150109 Pressure Test 0 15 08FEB11 22FEB11 08FEB11 22FEB11 0.00 0.00 0.00 0.00 2.70
131150110 Flushing 0 15 01JUL11* 15JUL11 01JUL11* 15JUL11 0.00 0.00 0.00 0.00 1.80
SERVICE AIR SYSTEMPIPING 131160101 Carry In/Temporary Laydown 0 15 29OCT10* 12NOV10 04NOV10* 18NOV10 0.01 0.00 0.00 0.00 11.20
131160102 Fit-up Welding 0 20 01NOV10 20NOV10 07NOV10 26NOV10 0.02 0.00 0.00 0.00 16.80
131160103 Fit-up Screw ( Included Ti 0 10 21NOV10 30NOV10 27NOV10 06DEC10 0.01 0.00 0.00 0.00 8.40
131160104 Fit-up Flange ( Included T 0 20 01DEC10 20DEC10 07DEC10 26DEC10 0.01 0.00 0.00 0.00 8.40
131160105 Welding 0 50 04NOV10 23DEC10 10NOV10 29DEC10 0.04 0.00 0.00 0.00 33.60
131160106 NDT 0 46 08NOV10 23DEC10 14NOV10 29DEC10 0.00 0.00 0.00 0.00 3.36
131160108 Support 0 50 08NOV10 27DEC10 14NOV10 02JAN11 0.02 0.00 0.00 0.00 16.80
131160109 Pressure Test 0 15 28DEC10 11JAN11 03JAN11 17JAN11 0.00 0.00 0.00 0.00 3.36
131160110 Flushing 0 15 01MAR11* 15MAR11 01MAR11* 15MAR11 0.00 0.00 0.00 0.00 2.24
SERVICE WATER SYSTEMPIPING 131170101 Carry In/Temporary Laydown 0 15 05DEC10 19DEC10 05DEC10 19DEC10 0.02 0.00 0.00 0.00 18.00
131170102 Fit-up Welding 0 20 07DEC10 26DEC10 07DEC10 26DEC10 0.03 0.00 0.00 0.00 27.00
131170103 Fit-up Screw ( Included Ti 0 10 27DEC10 05JAN11 27DEC10 05JAN11 0.01 0.00 0.00 0.00 13.50
131170104 Fit-up Flange ( Included T 0 10 06JAN11 15JAN11 06JAN11 15JAN11 0.01 0.00 0.00 0.00 13.50
131170105 Welding 0 40 09DEC10 17JAN11 09DEC10 17JAN11 0.06 0.00 0.00 0.00 54.00
131170106 NDT 0 36 13DEC10 17JAN11 13DEC10 17JAN11 0.01 0.00 0.00 0.00 5.40
131170108 Support 0 50 09DEC10 27JAN11 09DEC10 27JAN11 0.03 0.00 0.00 0.00 27.00
131170109 Pressure Test 0 15 28JAN11 11FEB11 28JAN11 11FEB11 0.01 0.00 0.00 0.00 5.40
131170110 Flushing 0 15 02MAY11* 16MAY11 02MAY11* 16MAY11 0.00 0.00 0.00 0.00 3.60
POTABLE WATER SYSTEMPIPING 131180101 Carry In/Temporary Laydown 0 15 05DEC10* 19DEC10 05DEC10* 19DEC10 0.07 0.00 0.00 0.00 63.20
131180102 Fit-up Welding 0 30 07DEC10* 05JAN11 07DEC10* 05JAN11 0.11 0.00 0.00 0.00 94.80
131180103 Fit-up Screw ( Included Ti 0 10 21JAN11* 30JAN11 21JAN11* 30JAN11 0.05 0.00 0.00 0.00 47.40
131180104 Fit-up Flange ( Included T 0 15 06JAN11* 20JAN11 06JAN11* 20JAN11 0.05 0.00 0.00 0.00 47.40
131180105 Welding 0 35 14DEC10* 17JAN11 14DEC10* 17JAN11 0.21 0.00 0.00 0.00 189.60
131180106 NDT 0 30 23DEC10* 21JAN11 23DEC10* 21JAN11 0.02 0.00 0.00 0.00 18.96
131180108 Support 0 40 16DEC10* 24JAN11 16DEC10* 24JAN11 0.11 0.00 0.00 0.00 94.80
131180109 Pressure Test 0 15 25JAN11* 08FEB11 25JAN11* 08FEB11 0.02 0.00 0.00 0.00 18.96
131180110 Flushing 0 15 16JUL11* 30JUL11 16JUL11* 30JUL11 0.01 0.00 0.00 0.00 12.64
WASTE WATER SYSTEMPIPING 131190101 Carry In/Temporary Laydown 0 30 30JAN11* 28FEB11 30JAN11* 28FEB11 0.02 0.00 0.00 0.00 20.80
131190102 Fit-up Welding 0 35 02FEB11 08MAR11 02FEB11 08MAR11 0.03 0.00 0.00 0.00 31.20
131190103 Fit-up Screw ( Included Ti 0 10 09MAR11 18MAR11 09MAR11 18MAR11 0.02 0.00 0.00 0.00 15.60
131190104 Fit-up Flange ( Included T 0 10 19MAR11 28MAR11 19MAR11 28MAR11 0.02 0.00 0.00 0.00 15.60
131190105 Welding 0 35 01FEB11 07MAR11 01FEB11 07MAR11 0.07 0.00 0.00 0.00 62.40
131190106 NDT 0 35 06FEB11 12MAR11 06FEB11 12MAR11 0.01 0.00 0.00 0.00 6.24
131190108 Support 0 45 30JAN11 15MAR11 30JAN11 15MAR11 0.03 0.00 0.00 0.00 31.20
131190109 Pressure Test 0 30 16MAR11 14APR11 16MAR11 14APR11 0.01 0.00 0.00 0.00 6.24
2010 2011APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 1
Sheet 4 of 30
Sheet 5 of 30
ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
WATER INJECTION SYSTEMPIPING 131200101 Carry In/Temporary Laydown 0 20 20DEC10 08JAN11 26DEC10 14JAN11 0.06 0.00 81.00 0.00 50.40
131200102 Fit-up Welding 0 10 20DEC10 29DEC10 26DEC10 04JAN11 0.08 0.00 108.00 0.00 75.60
131200103 Fit-up Screw ( Included Ti 0 10 30DEC10 08JAN11 05JAN11 14JAN11 0.04 0.00 1.00 0.00 37.80
131200104 Fit-up Flange ( Included T 0 10 09JAN11 18JAN11 15JAN11 24JAN11 0.04 0.00 61.50 0.00 37.80
131200105 Welding 0 40 20DEC10 28JAN11 26DEC10 03FEB11 0.17 0.00 108.00 0.00 151.20
131200106 NDT 0 40 30DEC10 07FEB11 05JAN11 13FEB11 0.02 0.00 0.00 0.00 15.12
131200108 Support 0 45 30DEC10 12FEB11 05JAN11 18FEB11 0.08 0.00 0.00 0.00 75.60
131200109 Pressure Test 0 15 13FEB11 27FEB11 19FEB11 05MAR11 0.02 0.00 0.00 0.00 15.12
131200110 Flushing 0 30 01MAY11* 30MAY11 01MAY11* 30MAY11 0.01 0.00 0.00 0.00 10.08
GT LUBE OIL SYSTEMPIPING 131210101 Carry In/Temporary Laydown 0 115 20OCT10* 11FEB11 04NOV10* 26FEB11 0.04 0.00 380.00 0.00 37.60
131210102 Fit-up Welding 0 112 26OCT10 14FEB11 10NOV10 01MAR11 0.06 0.00 909.25 0.00 56.40
131210103 Fit-up Screw ( Included Ti 0 45 02NOV10 16DEC10 17NOV10 31DEC10 0.03 0.00 8.00 0.00 28.20
131210104 Fit-up Flange ( Included T 0 114 26OCT10 16FEB11 10NOV10 03MAR11 0.03 0.00 679.50 0.00 28.20
131210105 Welding 0 112 28OCT10 16FEB11 12NOV10 03MAR11 0.13 0.00 909.25 0.00 112.80
131210106 NDT 0 112 02NOV10 21FEB11 17NOV10 08MAR11 0.01 0.00 0.00 0.00 11.28
131210108 Support 0 115 20OCT10 11FEB11 04NOV10 26FEB11 0.06 0.00 0.00 0.00 56.40
131210109 Pressure Test 0 32 28FEB11 31MAR11 15MAR11 15APR11 0.01 0.00 0.00 0.00 11.28
131210110 Flushing 0 31 31MAR11 30APR11 15APR11 15MAY11 0.01 0.00 0.00 0.00 7.52
LUBE OIL SYSTEMPIPING 131220101 Carry In/Temporary Laydown 0 30 15NOV10* 14DEC10 15NOV10* 14DEC10 0.07 0.00 0.00 0.00 59.20
131220102 Fit-up Welding 0 30 18NOV10 17DEC10 18NOV10 17DEC10 0.10 0.00 0.00 0.00 88.80
131220103 Fit-up Screw ( Included Ti 0 10 18DEC10 27DEC10 18DEC10 27DEC10 0.05 0.00 0.00 0.00 44.40
131220104 Fit-up Flange ( Included T 0 30 28DEC10 26JAN11 28DEC10 26JAN11 0.05 0.00 0.00 0.00 44.40
131220105 Welding 0 70 20NOV10 28JAN11 20NOV10 28JAN11 0.20 0.00 0.00 0.00 177.60
131220106 NDT 0 70 25NOV10 02FEB11 25NOV10 02FEB11 0.02 0.00 0.00 0.00 17.76
131220108 Support 0 70 15NOV10 23JAN11 15NOV10 23JAN11 0.10 0.00 0.00 0.00 88.80
131220109 Pressure Test 0 15 24JAN11 07FEB11 24JAN11 07FEB11 0.02 0.00 0.00 0.00 17.76
131220110 Flushing 0 30 16MAY11* 14JUN11 16MAY11* 14JUN11 0.01 0.00 0.00 0.00 11.84
CONTROL OIL SYSTEMPIPING 131230101 Carry In/Temporary Laydown 0 20 30NOV10* 19DEC10 30NOV10* 19DEC10 0.02 0.00 67.00 0.00 15.20
131230102 Fit-up Welding 0 20 02DEC10 21DEC10 02DEC10 21DEC10 0.03 0.00 49.50 0.00 22.80
131230103 Fit-up Screw ( Included Ti 0 10 22DEC10 31DEC10 22DEC10 31DEC10 0.01 0.00 3.38 0.00 11.40
131230104 Fit-up Flange ( Included T 0 20 01JAN11 20JAN11 01JAN11 20JAN11 0.01 0.00 37.50 0.00 11.40
131230105 Welding 0 50 04DEC10 22JAN11 04DEC10 22JAN11 0.05 0.00 49.50 0.00 45.60
131230106 NDT 0 50 15DEC10 02FEB11 15DEC10 02FEB11 0.01 0.00 0.00 0.00 4.56
131230108 Support 0 50 30NOV10 18JAN11 30NOV10 18JAN11 0.03 0.00 0.00 0.00 22.80
131230109 Pressure Test 0 15 19JAN11 02FEB11 19JAN11 02FEB11 0.01 0.00 0.00 0.00 4.56
131230110 Flushing 0 30 16MAY11* 14JUN11 16MAY11* 14JUN11 0.00 0.00 0.00 0.00 3.04
CO2 FIRE FIGHTING SYSTEMPIPING 131240101 Carry In/Temporary Laydown 0 20 15NOV10* 04DEC10 15NOV10* 04DEC10 0.04 0.00 0.00 0.00 37.60
131240102 Fit-up Welding 0 35 17NOV10 21DEC10 17NOV10 21DEC10 0.06 0.00 0.00 0.00 56.40
131240103 Fit-up Screw ( Included Ti 0 10 22DEC10 31DEC10 22DEC10 31DEC10 0.03 0.00 0.00 0.00 28.20
131240104 Fit-up Flange ( Included T 0 10 01JAN11 10JAN11 01JAN11 10JAN11 0.03 0.00 0.00 0.00 28.20
131240105 Welding 0 55 20NOV10 13JAN11 20NOV10 13JAN11 0.13 0.00 0.00 0.00 112.80
131240106 NDT 0 55 26NOV10 19JAN11 26NOV10 19JAN11 0.01 0.00 0.00 0.00 11.28
131240108 Support 0 60 15NOV10 13JAN11 15NOV10 13JAN11 0.06 0.00 0.00 0.00 56.40
131240109 Pressure Test 0 15 14JAN11 28JAN11 14JAN11 28JAN11 0.01 0.00 0.00 0.00 11.28
131240110 Flushing 0 15 15JUL11* 29JUL11 15JUL11* 29JUL11 0.01 0.00 0.00 0.00 7.52
FIRE FIGHTING SYSTEMPIPING 131250101 Carry In/Temporary Laydown 0 30 31OCT10* 29NOV10 04NOV10* 03DEC10 0.09 0.00 0.00 0.00 82.70
131250102 Fit-up Welding 0 30 02NOV10 01DEC10 06NOV10 05DEC10 0.14 0.00 0.00 0.00 124.05
131250103 Fit-up Screw ( Included Ti 0 10 02DEC10 11DEC10 06DEC10 15DEC10 0.07 0.00 0.00 0.00 62.03
131250104 Fit-up Flange ( Included T 0 10 12DEC10 21DEC10 16DEC10 25DEC10 0.07 0.00 0.00 0.00 62.03
131250105 Welding 0 40 05NOV10 14DEC10 09NOV10 18DEC10 0.27 0.00 0.00 0.00 248.10
2010 2011APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 1
Sheet 5 of 30
Sheet 6 of 30
ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
131250106 NDT 0 40 10NOV10 19DEC10 14NOV10 23DEC10 0.03 0.00 0.00 0.00 24.81
131250108 Support 0 40 31OCT10 09DEC10 04NOV10 13DEC10 0.14 0.00 0.00 0.00 124.05
131250109 Pressure Test 0 15 10DEC10 24DEC10 14DEC10 28DEC10 0.03 0.00 0.00 0.00 24.81
131250110 Flushing 0 15 02MAY11* 16MAY11 02MAY11* 16MAY11 0.02 0.00 0.00 0.00 16.54
SEAL OIL SYSTEMPIPING 131260101 Carry In/Temporary Laydown 0 20 30NOV10 19DEC10 04DEC10 23DEC10 0.05 0.00 0.00 0.00 44.00
131260102 Fit-up Welding 0 30 02DEC10 31DEC10 06DEC10 04JAN11 0.07 0.00 0.00 0.00 66.00
131260103 Fit-up Screw ( Included Ti 0 10 01JAN11 10JAN11 05JAN11 14JAN11 0.04 0.00 0.00 0.00 33.00
131260104 Fit-up Flange ( Included T 0 10 11JAN11 20JAN11 15JAN11 24JAN11 0.04 0.00 0.00 0.00 33.00
131260105 Welding 0 50 03DEC10 21JAN11 07DEC10 25JAN11 0.15 0.00 0.00 0.00 132.00
131260106 NDT 0 46 15DEC10 29JAN11 19DEC10 02FEB11 0.01 0.00 0.00 0.00 13.20
131260108 Support 0 50 10DEC10 28JAN11 14DEC10 01FEB11 0.07 0.00 0.00 0.00 66.00
131260109 Pressure Test 0 30 29JAN11 27FEB11 02FEB11 03MAR11 0.01 0.00 0.00 0.00 13.20
131260110 Flushing 0 45 16APR11* 30MAY11 16APR11* 30MAY11 0.01 0.00 0.00 0.00 8.80
HYDROGEN GAS SYSTEMPIPING 131270101 Carry In/Temporary Laydown 0 15 22FEB11* 08MAR11 22FEB11* 08MAR11 0.01 0.00 0.00 0.00 12.80
131270102 Fit-up Welding 0 30 23FEB11 24MAR11 23FEB11 24MAR11 0.02 0.00 0.00 0.00 19.20
131270103 Fit-up Screw ( Included Ti 0 10 25MAR11 03APR11 25MAR11 03APR11 0.01 0.00 0.00 0.00 9.60
131270104 Fit-up Flange ( Included T 0 10 04APR11 13APR11 04APR11 13APR11 0.01 0.00 0.00 0.00 9.60
131270105 Welding 0 50 24FEB11 14APR11 24FEB11 14APR11 0.04 0.00 0.00 0.00 38.40
131270106 NDT 0 46 28FEB11 14APR11 28FEB11 14APR11 0.00 0.00 0.00 0.00 3.84
131270108 Support 0 50 22FEB11 12APR11 22FEB11 12APR11 0.02 0.00 0.00 0.00 19.20
131270109 Pressure Test 0 15 13APR11 27APR11 13APR11 27APR11 0.00 0.00 0.00 0.00 3.84
131270110 Flushing 0 15 01JUL11* 15JUL11 01JUL11* 15JUL11 0.00 0.00 0.00 0.00 2.56
CHEMICAL DOSING & SAMPLING PIPING SYSTEMPIPING 131300101 Carry In/Temporary Laydown 0 15 01FEB11* 15FEB11 01FEB11* 15FEB11 0.05 0.00 0.00 0.00 48.80
131300102 Fit-up Welding 0 35 02FEB11 08MAR11 02FEB11 08MAR11 0.08 0.00 0.00 0.00 73.20
131300103 Fit-up Screw ( Included Ti 0 20 09MAR11 28MAR11 09MAR11 28MAR11 0.04 0.00 0.00 0.00 36.60
131300104 Fit-up Flange ( Included T 0 20 29MAR11 17APR11 29MAR11 17APR11 0.04 0.00 0.00 0.00 36.60
131300105 Welding 0 45 03FEB11 19MAR11 03FEB11 19MAR11 0.16 0.00 0.00 0.00 146.40
131300106 NDT 0 60 10FEB11 10APR11 10FEB11 10APR11 0.02 0.00 0.00 0.00 14.64
131300108 Support 0 50 01FEB11 22MAR11 01FEB11 22MAR11 0.08 0.00 0.00 0.00 73.20
131300109 Pressure Test 0 30 23MAR11 21APR11 23MAR11 21APR11 0.02 0.00 0.00 0.00 14.64
131300110 Flushing 0 30 01SEP11* 30SEP11 01SEP11* 30SEP11 0.01 0.00 0.00 0.00 9.76
INSULATION & PAINTINGFUEL OIL SUPPLY SYSTEMPAINTING 131010301 Painting 0 45 28FEB11 13APR11 28FEB11 13APR11 0.03 0.00 0.00 0.00 24.00
FUEL GAS SUPPLY SYSTEMPAINTING 131020301 Painting 0 30 23FEB11 24MAR11 23FEB11 24MAR11 0.01 0.00 0.00 0.00 6.28
AIR AND FLUE GAS SYSTEMPAINTING 131030301 Painting 0 45 09FEB11 25MAR11 09FEB11 25MAR11 0.03 0.00 0.00 0.00 25.16
GT WASHING AND DRAIN SYSTEMPAINTING 131040301 Painting 0 10 24JAN11 02FEB11 24JAN11 02FEB11 0.03 0.00 0.00 0.00 27.84
INSTRUMENT AIR SYSTEMPAINTING 131050301 Painting 0 20 28JAN11 16FEB11 28JAN11 16FEB11 0.03 0.00 0.00 0.00 25.14
PURGE AIR SYSTEMPAINTING 131060301 Painting 0 30 03FEB11 04MAR11 03FEB11 04MAR11 0.02 0.00 0.00 0.00 15.36
NITROGEN GAS SYSTEMPAINTING 131150301 Painting 0 20 23FEB11 14MAR11 23FEB11 14MAR11 0.00 0.00 0.00 0.00 1.80
SERVICE AIR SYSTEMPAINTING 131160301 Painting 0 20 12JAN11 31JAN11 18JAN11 06FEB11 0.00 0.00 0.00 0.00 2.24
2010 2011APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 1
Sheet 6 of 30
Sheet 7 of 30
ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
SERVICE WATER SYSTEMPAINTING 131170301 Painting 0 20 12FEB11 03MAR11 12FEB11 03MAR11 0.00 0.00 0.00 0.00 3.60
POTABLE WATER SYSTEMPAINTING 131180301 Painting 0 20 09FEB11 28FEB11 09FEB11 28FEB11 0.01 0.00 0.00 0.00 12.64
WATER INJECTION SYSTEMPAINTING 131200301 Painting 0 30 28FEB11 29MAR11 06MAR11 04APR11 0.01 0.00 0.00 0.00 10.08
GT LUBE OIL SYSTEMPAINTING 131210301 Painting 0 62 28FEB11 30APR11 15MAR11 15MAY11 0.01 0.00 0.00 0.00 7.52
LUBE OIL SYSTEMPAINTING 131220301 Painting 0 30 08FEB11 09MAR11 08FEB11 09MAR11 0.01 0.00 0.00 0.00 11.84
CONTROL OIL SYSTEMPAINTING 131230301 Painting 0 30 03FEB11 04MAR11 03FEB11 04MAR11 0.00 0.00 0.00 0.00 3.04
CO2 FIRE FIGHTING SYSTEMPAINTING 131240301 Painting 0 20 29JAN11 17FEB11 29JAN11 17FEB11 0.01 0.00 0.00 0.00 7.52
FIRE FIGHTING SYSTEMPAINTING 131250301 Painting 0 20 25DEC10 13JAN11 29DEC10 17JAN11 0.02 0.00 0.00 0.00 16.54
SEAL OIL SYSTEMPAINTING 131260301 Painting 0 20 28FEB11 19MAR11 04MAR11 23MAR11 0.01 0.00 0.00 0.00 8.80
HYDROGEN GAS SYSTEMPAINTING 131270301 Painting 0 20 28APR11 17MAY11 28APR11 17MAY11 0.00 0.00 0.00 0.00 2.56
CHEMICAL DOSING & SAMPLING PIPING SYSTEMPAINTING 131300301 Painting 0 20 22APR11 11MAY11 22APR11 11MAY11 0.01 0.00 0.00 0.00 9.76
GAS TURBINE BUILDING UNIT 2PIPINGFUEL OIL SUPPLY SYSTEMPIPING 132010101 Carry In/Temporary Laydown 0 30 20DEC10* 18JAN11 20DEC10* 18JAN11 0.14 0.00 275.00 0.00 128.00
132010102 Fit-up Welding 0 30 22DEC10 20JAN11 22DEC10 20JAN11 0.21 0.00 388.50 0.00 192.00
132010103 Fit-up Screw ( Included Ti 0 10 21JAN11 30JAN11 21JAN11 30JAN11 0.11 0.00 0.00 0.00 96.00
132010104 Fit-up Flange ( Included T 0 30 31JAN11 01MAR11 31JAN11 01MAR11 0.11 0.00 181.50 0.00 96.00
132010105 Welding 0 50 23DEC10 10FEB11 24DEC10 11FEB11 0.43 0.00 388.50 0.00 384.00
132010106 NDT 0 46 27DEC10 10FEB11 28DEC10 11FEB11 0.04 0.00 0.00 0.00 38.40
132010108 Support 0 60 20DEC10 17FEB11 20DEC10 17FEB11 0.21 0.00 0.00 0.00 192.00
132010109 Pressure Test 0 30 18FEB11 19MAR11 18FEB11 19MAR11 0.04 0.00 0.00 0.00 38.40
132010110 Flushing 0 105 15JUN11* 27SEP11 15JUN11* 27SEP11 0.03 0.00 0.00 0.00 25.60
FUEL GAS SUPPLY SYSTEMPIPING 132020101 Carry In/Temporary Laydown 0 15 29JAN11* 12FEB11 29JAN11* 12FEB11 0.03 0.00 67.00 0.00 31.40
132020102 Fit-up Welding 0 20 01FEB11 20FEB11 29JAN11 17FEB11 0.05 0.00 72.00 0.00 47.10
132020104 Fit-up Flange ( Included T 0 15 21FEB11 07MAR11 18FEB11 04MAR11 0.03 0.00 194.00 0.00 23.55
132020105 Welding 0 30 03FEB11 04MAR11 31JAN11 01MAR11 0.10 0.00 72.00 0.00 94.20
132020106 NDT 0 30 03FEB11 04MAR11 31JAN11 01MAR11 0.01 0.00 0.00 0.00 9.42
132020108 Support 0 30 03FEB11 04MAR11 31JAN11 01MAR11 0.05 0.00 0.00 0.00 47.10
132020109 Pressure Test 0 10 05MAR11 14MAR11 02MAR11 11MAR11 0.01 0.00 0.00 0.00 9.42
132020110 Flushing 0 30 15MAR11 13APR11 12MAR11 10APR11 0.01 0.00 0.00 0.00 6.28
AIR AND FLUE GAS SYSTEMPIPING 131030107 PWHT 0 116 07NOV10* 02MAR11 07NOV10* 02MAR11 0.00 0.00 43.00 0.00 0.00
132030101 Carry In/Temporary Laydown 0 30 30DEC10* 28JAN11 30DEC10* 28JAN11 0.14 0.00 382.00 0.00 125.80
132030102 Fit-up Welding 0 30 04JAN11 02FEB11 04JAN11 02FEB11 0.21 0.00 977.00 0.00 188.70
132030103 Fit-up Screw ( Included Ti 0 10 03FEB11 12FEB11 03FEB11 12FEB11 0.10 0.00 19.50 0.00 94.35
2010 2011APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 1
Sheet 7 of 30
Sheet 8 of 30
ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
132030104 Fit-up Flange ( Included T 0 10 13FEB11 22FEB11 13FEB11 22FEB11 0.10 0.00 1,368.50 0.00 94.35
132030105 Welding 0 35 08JAN11 11FEB11 08JAN11 11FEB11 0.42 0.00 977.00 0.00 377.40
132030106 NDT 0 45 15JAN11 28FEB11 15JAN11 28FEB11 0.04 0.00 0.00 0.00 37.74
132030108 Support 0 50 30DEC10 17FEB11 30DEC10 17FEB11 0.21 0.00 0.00 0.00 188.70
132030109 Pressure Test 0 15 18FEB11 04MAR11 18FEB11 04MAR11 0.04 0.00 0.00 0.00 37.74
132030110 Flushing 0 30 15MAR11* 13APR11 15MAR11* 13APR11 0.03 0.00 0.00 0.00 25.16
GT WASHING AND DRAIN SYSTEMPIPING 132040101 Carry In/Temporary Laydown 0 20 10DEC10* 29DEC10 10DEC10* 29DEC10 0.15 0.00 268.00 0.00 139.50
132040102 Fit-up Welding 0 30 10DEC10 08JAN11 10DEC10 08JAN11 0.23 0.00 289.50 0.00 209.25
132040103 Fit-up Screw ( Included Ti 0 10 09JAN11 18JAN11 09JAN11 18JAN11 0.12 0.00 35.00 0.00 104.63
132040104 Fit-up Flange ( Included T 0 10 19JAN11 28JAN11 19JAN11 28JAN11 0.12 0.00 74.00 0.00 104.63
132040105 Welding 0 50 13DEC10 31JAN11 13DEC10 31JAN11 0.46 0.00 289.50 0.00 418.50
132040106 NDT 0 50 15DEC10 02FEB11 15DEC10 02FEB11 0.05 0.00 0.00 0.00 41.85
132040107 PWHT 0 1 06MAR11* 06MAR11 06MAR11* 06MAR11 0.00 0.00 8.00 0.00 0.00
132040108 Support 0 50 05DEC10 23JAN11 05DEC10 23JAN11 0.23 0.00 0.00 0.00 209.25
132040109 Pressure Test 0 15 24JAN11 07FEB11 24JAN11 07FEB11 0.05 0.00 0.00 0.00 41.85
132040110 Flushing 0 30 30APR11* 29MAY11 30APR11* 29MAY11 0.03 0.00 0.00 0.00 27.90
INSTRUMENT AIR SYSTEMPIPING 132050101 Carry In/Temporary Laydown 0 20 11DEC10* 30DEC10 11DEC10* 30DEC10 0.02 0.00 146.00 0.00 14.40
132050102 Fit-up Welding 0 30 23DEC10* 21JAN11 23DEC10* 21JAN11 0.02 0.00 97.50 0.00 21.60
132050103 Fit-up Screw ( Included Ti 0 10 22JAN11 31JAN11 22JAN11 31JAN11 0.01 0.00 11.00 0.00 10.80
132050104 Fit-up Flange ( Included T 0 10 01FEB11 10FEB11 01FEB11 10FEB11 0.01 0.00 14.00 0.00 10.80
132050105 Welding 0 30 23DEC10 21JAN11 23DEC10 21JAN11 0.05 0.00 97.50 0.00 43.20
132050106 NDT 0 30 27DEC10 25JAN11 27DEC10 25JAN11 0.00 0.00 0.00 0.00 4.32
132050108 Support 0 45 28DEC10 10FEB11 28DEC10 10FEB11 0.02 0.00 0.00 0.00 21.60
132050109 Pressure Test 0 15 11FEB11 25FEB11 11FEB11 25FEB11 0.00 0.00 0.00 0.00 4.32
132050110 Flushing 0 15 01MAR11 15MAR11 01MAR11 15MAR11 0.00 0.00 0.00 0.00 2.88
PURGE AIR SYSTEMPIPING 132060101 Carry In/Temporary Laydown 0 10 20DEC10 29DEC10 20DEC10 29DEC10 0.09 0.00 0.00 0.00 76.80
132060102 Fit-up Welding 0 10 25DEC10 03JAN11 25DEC10 03JAN11 0.13 0.00 0.00 0.00 115.20
132060103 Fit-up Screw ( Included Ti 0 10 04JAN11 13JAN11 04JAN11 13JAN11 0.06 0.00 0.00 0.00 57.60
132060104 Fit-up Flange ( Included T 0 10 14JAN11 23JAN11 14JAN11 23JAN11 0.06 0.00 0.00 0.00 57.60
132060105 Welding 0 30 27DEC10 25JAN11 27DEC10 25JAN11 0.26 0.00 0.00 0.00 230.40
132060106 NDT 0 26 04JAN11 29JAN11 04JAN11 29JAN11 0.03 0.00 0.00 0.00 23.04
132060108 Support 0 40 25DEC10 02FEB11 25DEC10 02FEB11 0.13 0.00 0.00 0.00 115.20
132060109 Pressure Test 0 15 03FEB11 17FEB11 03FEB11 17FEB11 0.03 0.00 0.00 0.00 23.04
132060110 Flushing 0 30 01JUN11 30JUN11 01JUN11 30JUN11 0.02 0.00 0.00 0.00 15.36
CLOSED COOLING WATER SYSTEMPIPING 132130101 Carry In/Temporary Laydown 0 30 21JAN11* 19FEB11 21JAN11* 19FEB11 0.07 0.00 170.00 0.00 66.70
132130102 Fit-up Welding 0 35 24JAN11 27FEB11 21JAN11 24FEB11 0.11 0.00 1,970.00 0.00 100.05
132130103 Fit-up Screw ( Included Ti 0 10 28FEB11 09MAR11 25FEB11 06MAR11 0.06 0.00 0.00 0.00 50.03
132130104 Fit-up Flange ( Included T 0 20 10MAR11 29MAR11 07MAR11 26MAR11 0.06 0.00 244.00 0.00 50.03
132130105 Welding 0 45 26JAN11 11MAR11 23JAN11 08MAR11 0.22 0.00 1,970.00 0.00 200.10
132130106 NDT 0 45 28JAN11 13MAR11 25JAN11 10MAR11 0.02 0.00 0.00 0.00 20.01
132130108 Support 0 45 21JAN11 06MAR11 21JAN11 06MAR11 0.11 0.00 0.00 0.00 100.05
132130109 Pressure Test 0 20 15MAR11 03APR11 12MAR11 31MAR11 0.02 0.00 0.00 0.00 20.01
132130110 Flushing 0 30 01JUL11* 30JUL11 01JUL11* 30JUL11 0.01 0.00 0.00 0.00 13.34
NITROGEN GAS SYSTEMPIPING 132150101 Carry In/Temporary Laydown 0 15 04JAN11* 18JAN11 04JAN11* 18JAN11 0.01 0.00 0.00 0.00 9.00
132150102 Fit-up Welding 0 40 04JAN11 12FEB11 04JAN11 12FEB11 0.01 0.00 0.00 0.00 13.50
132150103 Fit-up Screw ( Included Ti 0 10 13FEB11 22FEB11 13FEB11 22FEB11 0.01 0.00 0.00 0.00 6.75
132150104 Fit-up Flange ( Included T 0 10 23FEB11 04MAR11 23FEB11 04MAR11 0.01 0.00 0.00 0.00 6.75
132150105 Welding 0 50 04JAN11 22FEB11 04JAN11 22FEB11 0.03 0.00 0.00 0.00 27.00
132150106 NDT 0 50 04JAN11 22FEB11 04JAN11 22FEB11 0.00 0.00 0.00 0.00 2.70
132150108 Support 0 50 11JAN11 01MAR11 11JAN11 01MAR11 0.01 0.00 0.00 0.00 13.50
132150109 Pressure Test 0 15 02MAR11 16MAR11 02MAR11 16MAR11 0.00 0.00 0.00 0.00 2.70
132150110 Flushing 0 15 01JUL11 15JUL11 01JUL11 15JUL11 0.00 0.00 0.00 0.00 1.80
2010 2011APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 1
Sheet 8 of 30
Sheet 9 of 30
ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
SERVICE AIR SYSTEMPIPING 132160101 Carry In/Temporary Laydown 0 15 16NOV10* 30NOV10 16NOV10* 30NOV10 0.01 0.00 0.00 0.00 12.60
132160102 Fit-up Welding 0 20 18NOV10 07DEC10 18NOV10 07DEC10 0.02 0.00 0.00 0.00 18.90
132160103 Fit-up Screw ( Included Ti 0 10 12DEC10 21DEC10 13DEC10 22DEC10 0.01 0.00 0.00 0.00 9.45
132160104 Fit-up Flange ( Included T 0 10 22DEC10 31DEC10 23DEC10 01JAN11 0.01 0.00 0.00 0.00 9.45
132160105 Welding 0 40 20NOV10 29DEC10 20NOV10 29DEC10 0.04 0.00 0.00 0.00 37.80
132160106 NDT 0 36 29NOV10 03JAN11 30NOV10 04JAN11 0.00 0.00 0.00 0.00 3.78
132160108 Support 0 50 22NOV10 10JAN11 22NOV10 10JAN11 0.02 0.00 0.00 0.00 18.90
132160109 Pressure Test 0 15 11JAN11 25JAN11 11JAN11 25JAN11 0.00 0.00 0.00 0.00 3.78
132160110 Flushing 0 15 01MAR11* 15MAR11 01MAR11* 15MAR11 0.00 0.00 0.00 0.00 2.52
SERVICE WATER SYSTEMPIPING 132170101 Carry In/Temporary Laydown 0 15 20DEC10* 03JAN11 20DEC10* 03JAN11 0.02 0.00 0.00 0.00 18.00
132170102 Fit-up Welding 0 20 22DEC10 10JAN11 22DEC10 10JAN11 0.03 0.00 0.00 0.00 27.00
132170103 Fit-up Screw ( Included Ti 0 10 11JAN11 20JAN11 11JAN11 20JAN11 0.01 0.00 0.00 0.00 13.50
132170104 Fit-up Flange ( Included T 0 10 21JAN11 30JAN11 21JAN11 30JAN11 0.01 0.00 0.00 0.00 13.50
132170105 Welding 0 40 24DEC10 01FEB11 24DEC10 01FEB11 0.06 0.00 0.00 0.00 54.00
132170106 NDT 0 36 27DEC10 31JAN11 27DEC10 31JAN11 0.01 0.00 0.00 0.00 5.40
132170108 Support 0 50 20DEC10 07FEB11 20DEC10 07FEB11 0.03 0.00 0.00 0.00 27.00
132170109 Pressure Test 0 15 08FEB11 22FEB11 08FEB11 22FEB11 0.01 0.00 0.00 0.00 5.40
132170110 Flushing 0 15 02MAY11* 16MAY11 02MAY11* 16MAY11 0.00 0.00 0.00 0.00 3.60
POTABLE WATER SYSTEMPIPING 132180101 Carry In/Temporary Laydown 0 15 20DEC10 03JAN11 20DEC10 03JAN11 0.07 0.00 0.00 0.00 63.20
132180102 Fit-up Welding 0 30 22DEC10 20JAN11 22DEC10 20JAN11 0.11 0.00 0.00 0.00 94.80
132180103 Fit-up Screw ( Included Ti 0 5 05FEB11 09FEB11 05FEB11 09FEB11 0.05 0.00 0.00 0.00 47.40
132180104 Fit-up Flange ( Included T 0 15 21JAN11 04FEB11 21JAN11 04FEB11 0.05 0.00 0.00 0.00 47.40
132180105 Welding 0 35 20DEC10 23JAN11 20DEC10 23JAN11 0.21 0.00 0.00 0.00 189.60
132180106 NDT 0 35 30DEC10 02FEB11 30DEC10 02FEB11 0.02 0.00 0.00 0.00 18.96
132180108 Support 0 50 22DEC10 09FEB11 22DEC10 09FEB11 0.11 0.00 0.00 0.00 94.80
132180109 Pressure Test 0 15 14FEB11 28FEB11 14FEB11 28FEB11 0.02 0.00 0.00 0.00 18.96
132180110 Flushing 0 15 16JUL11 30JUL11 16JUL11 30JUL11 0.01 0.00 0.00 0.00 12.64
WASTE WATER SYSTEMPIPING 132190101 Carry In/Temporary Laydown 0 30 01MAR11 30MAR11 01MAR11 30MAR11 0.02 0.00 0.00 0.00 20.80
132190102 Fit-up Welding 0 35 03MAR11 06APR11 03MAR11 06APR11 0.03 0.00 0.00 0.00 31.20
132190103 Fit-up Screw ( Included Ti 0 10 07APR11 16APR11 07APR11 16APR11 0.02 0.00 0.00 0.00 15.60
132190104 Fit-up Flange ( Included T 0 10 17APR11 26APR11 17APR11 26APR11 0.02 0.00 0.00 0.00 15.60
132190105 Welding 0 35 05MAR11 08APR11 05MAR11 08APR11 0.07 0.00 0.00 0.00 62.40
132190106 NDT 0 35 19MAR11 22APR11 19MAR11 22APR11 0.01 0.00 0.00 0.00 6.24
132190108 Support 0 45 01MAR11 14APR11 01MAR11 14APR11 0.03 0.00 0.00 0.00 31.20
132190109 Pressure Test 0 30 15APR11 14MAY11 15APR11 14MAY11 0.01 0.00 0.00 0.00 6.24
WATER INJECTION SYSTEMPIPING 132200101 Carry In/Temporary Laydown 0 20 09JAN11 28JAN11 09JAN11 28JAN11 0.06 0.00 86.00 0.00 50.40
132200102 Fit-up Welding 0 10 11JAN11 20JAN11 11JAN11 20JAN11 0.08 0.00 122.00 0.00 75.60
132200103 Fit-up Screw ( Included Ti 0 10 21JAN11 30JAN11 21JAN11 30JAN11 0.04 0.00 1.00 0.00 37.80
132200104 Fit-up Flange ( Included T 0 10 31JAN11 09FEB11 31JAN11 09FEB11 0.04 0.00 61.50 0.00 37.80
132200105 Welding 0 40 09JAN11 17FEB11 09JAN11 17FEB11 0.17 0.00 122.00 0.00 151.20
132200106 NDT 0 40 19JAN11 27FEB11 19JAN11 27FEB11 0.02 0.00 0.00 0.00 15.12
132200108 Support 0 45 09JAN11 22FEB11 09JAN11 22FEB11 0.08 0.00 0.00 0.00 75.60
132200109 Pressure Test 0 15 23FEB11 09MAR11 23FEB11 09MAR11 0.02 0.00 0.00 0.00 15.12
132200110 Flushing 0 30 01MAY11* 30MAY11 01MAY11* 30MAY11 0.01 0.00 0.00 0.00 10.08
GT LUBE OIL SYSTEMPIPING 132210101 Carry In/Temporary Laydown 0 119 17NOV10* 15MAR11 17NOV10* 15MAR11 0.04 0.00 359.00 0.00 37.60
132210102 Fit-up Welding 0 119 23NOV10 21MAR11 23NOV10 21MAR11 0.06 0.00 849.25 0.00 56.40
132210103 Fit-up Screw ( Included Ti 0 69 09DEC10* 15FEB11 09DEC10* 15FEB11 0.03 0.00 8.00 0.00 28.20
132210104 Fit-up Flange ( Included T 0 119 21NOV10 19MAR11 21NOV10 19MAR11 0.03 0.00 679.50 0.00 28.20
132210105 Welding 0 119 25NOV10 23MAR11 25NOV10 23MAR11 0.13 0.00 849.25 0.00 112.80
132210106 NDT 0 119 30NOV10 28MAR11 30NOV10 28MAR11 0.01 0.00 0.00 0.00 11.28
2010 2011APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 1
Sheet 9 of 30
Sheet 10 of 30
ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
132210108 Support 0 119 17NOV10 15MAR11 17NOV10 15MAR11 0.06 0.00 0.00 0.00 56.40
132210109 Pressure Test 0 17 15MAR11 31MAR11 15MAR11 31MAR11 0.01 0.00 0.00 0.00 11.28
132210110 Flushing 0 16 15APR11* 30APR11 15APR11* 30APR11 0.01 0.00 0.00 0.00 7.52
LUBE OIL SYSTEMPIPING 132220101 Carry In/Temporary Laydown 0 30 15DEC10* 13JAN11 15DEC10* 13JAN11 0.07 0.00 27.00 0.00 59.20
132220102 Fit-up Welding 0 60 17DEC10 14FEB11 17DEC10 14FEB11 0.10 0.00 98.00 0.00 88.80
132220103 Fit-up Screw ( Included Ti 0 10 15FEB11 24FEB11 15FEB11 24FEB11 0.05 0.00 0.00 0.00 44.40
132220104 Fit-up Flange ( Included T 0 10 25FEB11 06MAR11 25FEB11 06MAR11 0.05 0.00 0.00 0.00 44.40
132220105 Welding 0 60 20DEC10 17FEB11 20DEC10 17FEB11 0.20 0.00 98.00 0.00 177.60
132220106 NDT 0 66 23DEC10 26FEB11 23DEC10 26FEB11 0.02 0.00 0.00 0.00 17.76
132220108 Support 0 60 19JAN11 19MAR11 19JAN11 19MAR11 0.10 0.00 0.00 0.00 88.80
132220109 Pressure Test 0 15 20MAR11 03APR11 20MAR11 03APR11 0.02 0.00 0.00 0.00 17.76
132220110 Flushing 0 30 01MAY11* 30MAY11 01MAY11* 30MAY11 0.01 0.00 0.00 0.00 11.84
CONTROL OIL SYSTEMPIPING 132230101 Carry In/Temporary Laydown 0 15 20DEC10* 03JAN11 20DEC10* 03JAN11 0.02 0.00 67.00 0.00 15.20
132230102 Fit-up Welding 0 30 21DEC10 19JAN11 20DEC10 18JAN11 0.03 0.00 49.50 0.00 22.80
132230103 Fit-up Screw ( Included Ti 0 10 20JAN11 29JAN11 19JAN11 28JAN11 0.01 0.00 3.38 0.00 11.40
132230104 Fit-up Flange ( Included T 0 10 30JAN11 08FEB11 29JAN11 07FEB11 0.01 0.00 37.50 0.00 11.40
132230105 Welding 0 50 22DEC10 09FEB11 21DEC10 08FEB11 0.05 0.00 49.50 0.00 45.60
132230106 NDT 0 50 28DEC10 15FEB11 27DEC10 14FEB11 0.01 0.00 0.00 0.00 4.56
132230108 Support 0 60 20DEC10 17FEB11 19DEC10 16FEB11 0.03 0.00 0.00 0.00 22.80
132230109 Pressure Test 0 30 18FEB11 19MAR11 17FEB11 18MAR11 0.01 0.00 0.00 0.00 4.56
132230110 Flushing 0 30 16MAY11* 14JUN11 16MAY11* 14JUN11 0.00 0.00 0.00 0.00 3.04
CO2 FIRE FIGHTING SYSTEMPIPING 132240101 Carry In/Temporary Laydown 0 20 05DEC10* 24DEC10 05DEC10* 24DEC10 0.04 0.00 0.00 0.00 37.60
132240102 Fit-up Welding 0 35 07DEC10 10JAN11 07DEC10 10JAN11 0.06 0.00 0.00 0.00 56.40
132240103 Fit-up Screw ( Included Ti 0 10 11JAN11 20JAN11 11JAN11 20JAN11 0.03 0.00 0.00 0.00 28.20
132240104 Fit-up Flange ( Included T 0 10 21JAN11 30JAN11 21JAN11 30JAN11 0.03 0.00 0.00 0.00 28.20
132240105 Welding 0 55 09DEC10 01FEB11 08DEC10 31JAN11 0.13 0.00 0.00 0.00 112.80
132240106 NDT 0 55 22DEC10 14FEB11 22DEC10 14FEB11 0.01 0.00 0.00 0.00 11.28
132240108 Support 0 60 05DEC10 02FEB11 05DEC10 02FEB11 0.06 0.00 0.00 0.00 56.40
132240109 Pressure Test 0 15 03FEB11 17FEB11 03FEB11 17FEB11 0.01 0.00 0.00 0.00 11.28
132240110 Flushing 0 15 15JUL11* 29JUL11 15JUL11* 29JUL11 0.01 0.00 0.00 0.00 7.52
FIRE FIGHTING SYSTEMPIPING 132250101 Carry In/Temporary Laydown 0 30 01OCT10* 30OCT10 04NOV10* 03DEC10 0.09 0.00 0.00 0.00 82.40
132250102 Fit-up Welding 0 30 04OCT10 02NOV10 07NOV10 06DEC10 0.14 0.00 0.00 0.00 123.60
132250103 Fit-up Screw ( Included Ti 0 10 03NOV10 12NOV10 07DEC10 16DEC10 0.07 0.00 0.00 0.00 61.80
132250104 Fit-up Flange ( Included T 0 10 13NOV10 22NOV10 17DEC10 26DEC10 0.07 0.00 0.00 0.00 61.80
132250105 Welding 0 40 14OCT10 22NOV10 17NOV10 26DEC10 0.27 0.00 0.00 0.00 247.20
132250106 NDT 0 36 18OCT10 22NOV10 21NOV10 26DEC10 0.03 0.00 0.00 0.00 24.72
132250108 Support 0 44 10OCT10 22NOV10 13NOV10 26DEC10 0.14 0.00 0.00 0.00 123.60
132250109 Pressure Test 0 15 23NOV10 07DEC10 27DEC10 10JAN11 0.03 0.00 0.00 0.00 24.72
132250110 Flushing 0 15 02MAY11* 16MAY11 02MAY11* 16MAY11 0.02 0.00 0.00 0.00 16.48
SEAL OIL SYSTEMPIPING 132260101 Carry In/Temporary Laydown 0 20 20DEC10* 08JAN11 20DEC10* 08JAN11 0.05 0.00 0.00 0.00 44.00
132260102 Fit-up Welding 0 30 27DEC10 25JAN11 27DEC10 25JAN11 0.07 0.00 0.00 0.00 66.00
132260103 Fit-up Screw ( Included Ti 0 10 26JAN11 04FEB11 26JAN11 04FEB11 0.04 0.00 0.00 0.00 33.00
132260104 Fit-up Flange ( Included T 0 10 05FEB11 14FEB11 05FEB11 14FEB11 0.04 0.00 0.00 0.00 33.00
132260105 Welding 0 50 29DEC10 16FEB11 29DEC10 16FEB11 0.15 0.00 0.00 0.00 132.00
132260106 NDT 0 46 08JAN11 22FEB11 08JAN11 22FEB11 0.01 0.00 0.00 0.00 13.20
132260108 Support 0 50 25DEC10 12FEB11 25DEC10 12FEB11 0.07 0.00 0.00 0.00 66.00
132260109 Pressure Test 0 30 13FEB11 14MAR11 13FEB11 14MAR11 0.01 0.00 0.00 0.00 13.20
132260110 Flushing 0 45 16APR11* 30MAY11 16APR11* 30MAY11 0.01 0.00 0.00 0.00 8.80
HYDROGEN GAS SYSTEMPIPING 132270101 Carry In/Temporary Laydown 0 15 09MAR11* 23MAR11 09MAR11* 23MAR11 0.01 0.00 0.00 0.00 12.80
132270102 Fit-up Welding 0 30 11MAR11 09APR11 11MAR11 09APR11 0.02 0.00 0.00 0.00 19.20
2010 2011APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 1
Sheet 10 of 30
Sheet 11 of 30
ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
132270103 Fit-up Screw ( Included Ti 0 10 10APR11 19APR11 10APR11 19APR11 0.01 0.00 0.00 0.00 9.60
132270104 Fit-up Flange ( Included T 0 10 20APR11 29APR11 20APR11 29APR11 0.01 0.00 0.00 0.00 9.60
132270105 Welding 0 50 14MAR11 02MAY11 14MAR11 02MAY11 0.04 0.00 0.00 0.00 38.40
132270106 NDT 0 46 21MAR11 05MAY11 21MAR11 05MAY11 0.00 0.00 0.00 0.00 3.84
132270108 Support 0 50 09MAR11 27APR11 09MAR11 27APR11 0.02 0.00 0.00 0.00 19.20
132270109 Pressure Test 0 15 28APR11 12MAY11 28APR11 12MAY11 0.00 0.00 0.00 0.00 3.84
132270110 Flushing 0 15 01JUL11* 15JUL11 01JUL11* 15JUL11 0.00 0.00 0.00 0.00 2.56
CHEMICAL DOSING & SAMPLING PIPING SYSTEMPIPING 132300101 Carry In/Temporary Laydown 0 15 16FEB11 02MAR11 16FEB11 02MAR11 0.05 0.00 0.00 0.00 48.80
132300102 Fit-up Welding 0 35 18FEB11 24MAR11 18FEB11 24MAR11 0.08 0.00 0.00 0.00 73.20
132300103 Fit-up Screw ( Included Ti 0 20 25MAR11 13APR11 25MAR11 13APR11 0.04 0.00 0.00 0.00 36.60
132300104 Fit-up Flange ( Included T 0 20 14APR11 03MAY11 14APR11 03MAY11 0.04 0.00 0.00 0.00 36.60
132300105 Welding 0 45 21FEB11 06APR11 21FEB11 06APR11 0.16 0.00 0.00 0.00 146.40
132300106 NDT 0 45 25FEB11 10APR11 25FEB11 10APR11 0.02 0.00 0.00 0.00 14.64
132300108 Support 0 50 16FEB11 06APR11 16FEB11 06APR11 0.08 0.00 0.00 0.00 73.20
132300109 Pressure Test 0 30 07APR11 06MAY11 07APR11 06MAY11 0.02 0.00 0.00 0.00 14.64
132300110 Flushing 0 30 01SEP11 30SEP11 01SEP11 30SEP11 0.01 0.00 0.00 0.00 9.76
INSULATION & PAINTINGFUEL OIL SUPPLY SYSTEMPAINTING 132010301 Painting 0 20 28MAR11* 16APR11 28MAR11* 16APR11 0.03 0.00 0.00 0.00 25.60
FUEL GAS SUPPLY SYSTEMPAINTING 132020301 Painting 0 15 15MAR11 29MAR11 12MAR11 26MAR11 0.01 0.00 0.00 0.00 6.28
AIR AND FLUE GAS SYSTEMPAINTING 132030301 Painting 0 45 05MAR11 18APR11 05MAR11 18APR11 0.03 0.00 0.00 0.00 25.16
GT WASHING AND DRAIN SYSTEMPAINTING 132040301 Painting 0 20 21FEB11* 12MAR11 21FEB11* 12MAR11 0.03 0.00 0.00 0.00 27.90
INSTRUMENT AIR SYSTEMPAINTING 132050301 Painting 0 20 26FEB11 17MAR11 26FEB11 17MAR11 0.00 0.00 0.00 0.00 2.88
PURGE AIR SYSTEMPAINTING 132060301 Painting 0 20 18FEB11 09MAR11 18FEB11 09MAR11 0.02 0.00 0.00 0.00 15.36
CLOSED COOLING WATER SYSTEMPAINTING 132130301 Painting 0 20 04APR11 23APR11 04APR11 23APR11 0.01 0.00 0.00 0.00 13.34
NITROGEN GAS SYSTEMPAINTING 132150301 Painting 0 20 17MAR11 05APR11 17MAR11 05APR11 0.00 0.00 0.00 0.00 1.80
SERVICE AIR SYSTEMPAINTING 132160301 Painting 0 20 26JAN11 14FEB11 26JAN11 14FEB11 0.00 0.00 0.00 0.00 2.52
SERVICE WATER SYSTEMPAINTING 132170301 Painting 0 20 28FEB11* 19MAR11 28FEB11* 19MAR11 0.00 0.00 0.00 0.00 3.60
POTABLE WATER SYSTEMPAINTING 132180301 Painting 0 20 01MAR11 20MAR11 01MAR11 20MAR11 0.01 0.00 0.00 0.00 12.64
WASTE WATER SYSTEMPAINTING 132190301 Painting 0 20 15MAY11 03JUN11 15MAY11 03JUN11 0.00 0.00 0.00 0.00 4.16
WATER INJECTION SYSTEMPAINTING 132200203 Painting 0 20 10MAR11 29MAR11 10MAR11 29MAR11 0.01 0.00 0.00 0.00 10.08
GT LUBE OIL SYSTEMPAINTING 132210301 Painting 0 31 31MAR11 30APR11 31MAR11 30APR11 0.01 0.00 0.00 0.00 7.52
2010 2011APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 1
Sheet 11 of 30
Sheet 12 of 30
ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
LUBE OIL SYSTEMPAINTING 132220301 Painting 0 20 04APR11 23APR11 04APR11 23APR11 0.01 0.00 0.00 0.00 11.84
CONTROL OIL SYSTEMPAINTING 132230301 Painting 0 20 04APR11 23APR11 04APR11 23APR11 0.00 0.00 0.00 0.00 3.04
CO2 FIRE FIGHTING SYSTEMPAINTING 132240301 Painting 0 20 18FEB11 09MAR11 18FEB11 09MAR11 0.01 0.00 0.00 0.00 7.52
FIRE FIGHTING SYSTEMPAINTING 132250301 Painting 0 20 08DEC10 27DEC10 11JAN11 30JAN11 0.02 0.00 0.00 0.00 16.48
SEAL OIL SYSTEMPAINTING 132260301 Painting 0 20 15MAR11 03APR11 15MAR11 03APR11 0.01 0.00 0.00 0.00 8.80
HYDROGEN GAS SYSTEMPAINTING 132270301 Painting 0 20 13MAY11 01JUN11 13MAY11 01JUN11 0.00 0.00 0.00 0.00 2.56
CHEMICAL DOSING & SAMPLING PIPING SYSTEMPAINTING 132300301 Painting 0 20 07MAY11 26MAY11 07MAY11 26MAY11 0.01 0.00 0.00 0.00 9.76
STEAM TURBINE COMMONPIPINGMAIN STEAM SYSTEMPIPING 120070101 Carry In/Temporary Laydown 0 93 21DEC10* 23MAR11 21DEC10* 23MAR11 0.14 0.00 21.00 0.00 127.00
120070102 Fit-up Welding 0 93 23DEC10 25MAR11 23DEC10 25MAR11 0.21 0.00 55.00 0.00 190.50
120070103 Fit-up Screw ( Included Ti 0 9 04APR11 12APR11 04APR11 12APR11 0.11 0.00 0.00 0.00 95.25
120070104 Fit-up Flange ( Included T 0 11 25MAR11 04APR11 25MAR11 04APR11 0.11 0.00 0.00 0.00 95.25
120070105 Welding 0 93 25DEC10 27MAR11 25DEC10 27MAR11 0.42 0.00 55.00 0.00 381.00
120070106 NDT 0 93 31DEC10 02APR11 31DEC10 02APR11 0.04 0.00 22.00 0.00 38.10
120070108 Support 0 103 21DEC10 02APR11 21DEC10 02APR11 0.21 0.00 0.00 0.00 190.50
120070109 Pressure Test 0 11 02APR11 12APR11 02APR11 12APR11 0.04 0.00 0.00 0.00 38.10
120070110 Flushing 0 31 05MAY11* 04JUN11 05MAY11* 04JUN11 0.03 0.00 0.00 0.00 25.40
ST FLASH TANK & DRAIN SYSTEMPIPING 120090101 Carry In/Temporary Laydown 0 20 21DEC10 09JAN11 21DEC10 09JAN11 0.22 0.00 37.00 0.00 198.00
120090102 Fit-up Welding 0 40 22DEC10 30JAN11 22DEC10 30JAN11 0.33 0.00 154.00 0.00 297.00
120090103 Fit-up Screw ( Included Ti 0 10 31JAN11 09FEB11 31JAN11 09FEB11 0.16 0.00 0.00 0.00 148.50
120090104 Fit-up Flange ( Included T 0 30 10FEB11 11MAR11 10FEB11 11MAR11 0.16 0.00 25.00 0.00 148.50
120090105 Welding 0 70 20DEC10 27FEB11 20DEC10 27FEB11 0.66 0.00 154.00 0.00 594.00
120090106 NDT 0 70 10JAN11 20MAR11 10JAN11 20MAR11 0.07 0.00 14.00 0.00 59.40
120090108 Support 0 70 04JAN11 14MAR11 04JAN11 14MAR11 0.33 0.00 0.00 0.00 297.00
120090109 Pressure Test 0 20 15MAR11 03APR11 15MAR11 03APR11 0.07 0.00 0.00 0.00 59.40
CONDENSATE WATER SYSTEMPIPING 120100101 Carry In/Temporary Laydown 0 98 09OCT10* 14JAN11 04NOV10* 09FEB11 0.00 0.00 152.00 0.00 79.60
120100102 Fit-up Welding 0 98 11OCT10 16JAN11 06NOV10 11FEB11 0.00 0.00 439.00 0.00 119.40
120100103 Fit-up Screw ( Included Ti 0 16 16JAN11 31JAN11 11FEB11 26FEB11 0.00 0.00 0.00 0.00 59.70
120100104 Fit-up Flange ( Included T 0 98 15OCT10 20JAN11 10NOV10 15FEB11 0.00 0.00 142.00 0.00 59.70
120100105 Welding 0 98 13OCT10 18JAN11 08NOV10 13FEB11 0.00 0.00 1,203.00 0.00 238.80
120100106 NDT 0 98 19OCT10 24JAN11 16NOV10 21FEB11 0.00 0.00 0.00 0.00 23.88
120100108 Support 0 98 11OCT10 16JAN11 06NOV10 11FEB11 0.00 0.00 0.00 0.00 119.40
120100109 Pressure Test 0 80 15FEB11* 05MAY11 27FEB11* 17MAY11 0.00 0.00 0.00 0.00 23.88
120100110 Flushing 0 123 15MAR11* 15JUL11 15MAR11* 15JUL11 0.00 0.00 0.00 0.00 15.92
INSULATION & PAINTINGMAIN STEAM SYSTEMPAINTING 120070301 Painting 0 103 21DEC10 02APR11 21DEC10 02APR11 0.03 0.00 0.00 0.00 25.40
INSULATIO 120070201 Insulation 0 21 12APR11 02MAY11 12APR11 02MAY11 0.16 0.00 0.00 0.00 140.00
2010 2011APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 1
Sheet 12 of 30
Sheet 13 of 30
ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
ST FLASH TANK & DRAIN SYSTEMPAINTING 120090301 Painting 0 20 04APR11 23APR11 04APR11 23APR11 0.04 0.00 0.00 0.00 39.60
CONDENSATE WATER SYSTEMPAINTING 120100301 Painting 0 72 05MAY11 15JUL11 17MAY11 27JUL11 0.00 0.00 0.00 0.00 15.92
INSULATIO 120100201 Insulation 0 80 15FEB11 05MAY11 27FEB11 17MAY11 0.00 0.00 0.00 0.00 23.88
STEAM TURBINE BUILDINGPIPINGINSTRUMENT AIR SYSTEMPIPING 121050101 Carry In/Temporary Laydown 0 15 31DEC10* 14JAN11 31DEC10* 14JAN11 0.02 0.00 55.00 0.00 15.00
121050102 Fit-up Welding 0 20 31DEC10* 19JAN11 31DEC10* 19JAN11 0.02 0.00 46.00 0.00 22.50
121050103 Fit-up Screw ( Included Ti 0 10 20JAN11* 29JAN11 20JAN11* 29JAN11 0.01 0.00 6.00 0.00 11.25
121050104 Fit-up Flange ( Included T 0 10 30JAN11* 08FEB11 30JAN11* 08FEB11 0.01 0.00 0.00 0.00 11.25
121050105 Welding 0 30 31DEC10* 29JAN11 31DEC10* 29JAN11 0.05 0.00 46.00 0.00 45.00
121050106 NDT 0 25 08JAN11* 01FEB11 08JAN11* 01FEB11 0.00 0.00 0.00 0.00 4.50
121050108 Support 0 45 31DEC10* 13FEB11 31DEC10* 13FEB11 0.02 0.00 0.00 0.00 22.50
121050109 Pressure Test 0 14 14FEB11* 27FEB11 14FEB11* 27FEB11 0.00 0.00 0.00 0.00 4.50
121050110 Flushing 0 15 01MAR11* 15MAR11 01MAR11* 15MAR11 0.00 0.00 0.00 0.00 3.00
MAIN STEAM SYSTEMPIPING 121070101 Carry In/Temporary Laydown 0 40 02NOV10* 11DEC10 04NOV10* 13DEC10 0.14 0.00 472.00 0.00 127.00
121070102 Fit-up Welding 0 80 08NOV10 26JAN11 10NOV10 28JAN11 0.21 0.00 4,546.50 0.00 190.50
121070103 Fit-up Screw ( Included Ti 0 10 11JAN11 20JAN11 13JAN11 22JAN11 0.11 0.00 0.00 0.00 95.25
121070104 Fit-up Flange ( Included T 0 30 21JAN11 19FEB11 23JAN11 21FEB11 0.11 0.00 76.00 0.00 95.25
121070105 Welding 0 90 10NOV10 07FEB11 12NOV10 09FEB11 0.42 0.00 4,546.50 0.00 381.00
121070106 NDT 0 90 10NOV10 07FEB11 12NOV10 09FEB11 0.04 0.00 216.00 0.00 38.10
121070108 Support 0 100 01NOV10 08FEB11 04NOV10 11FEB11 0.21 0.00 99.00 0.00 190.50
121070109 Pressure Test 0 20 09FEB11 28FEB11 12FEB11 03MAR11 0.04 0.00 0.00 0.00 38.10
121070110 Flushing 0 30 03OCT11* 01NOV11 03OCT11* 01NOV11 0.03 0.00 0.00 0.00 25.40
AUXILIARY / GLAND STEAM SYSTEMPIPING 121080101 Carry In/Temporary Laydown 0 20 01DEC10* 20DEC10 01DEC10* 20DEC10 0.14 0.00 630.00 0.00 124.00
121080102 Fit-up Welding 0 20 01DEC10 20DEC10 01DEC10 20DEC10 0.21 0.00 2,269.00 0.00 186.00
121080103 Fit-up Screw ( Included Ti 0 10 21DEC10 30DEC10 21DEC10 30DEC10 0.10 0.00 29.88 0.00 93.00
121080104 Fit-up Flange ( Included T 0 10 31DEC10 09JAN11 31DEC10 09JAN11 0.10 0.00 624.50 0.00 93.00
121080105 Welding 0 40 02DEC10 10JAN11 02DEC10 10JAN11 0.41 0.00 2,269.00 0.00 372.00
121080106 NDT 0 40 12DEC10 20JAN11 12DEC10 20JAN11 0.04 0.00 189.00 0.00 37.20
121080107 PWHT 0 135 28NOV10 11APR11 28NOV10 11APR11 0.00 0.00 386.00 0.00 0.00
121080108 Support 0 40 12DEC10 20JAN11 12DEC10 20JAN11 0.21 0.00 0.00 0.00 186.00
121080109 Pressure Test 0 20 21JAN11 09FEB11 21JAN11 09FEB11 0.04 0.00 0.00 0.00 37.20
121080110 Flushing 0 30 01OCT11* 30OCT11 01OCT11* 30OCT11 0.03 0.00 0.00 0.00 24.80
ST FLASH TANK & DRAIN SYSTEMPIPING 121090101 Carry In/Temporary Laydown 0 20 21DEC10* 09JAN11 21DEC10* 09JAN11 0.22 0.00 127.00 0.00 198.00
121090102 Fit-up Welding 0 40 22DEC10 30JAN11 22DEC10 30JAN11 0.33 0.00 521.00 0.00 297.00
121090103 Fit-up Screw ( Included Ti 0 10 31JAN11 09FEB11 31JAN11 09FEB11 0.16 0.00 0.00 0.00 148.50
121090104 Fit-up Flange ( Included T 0 30 10FEB11 11MAR11 10FEB11 11MAR11 0.16 0.00 92.00 0.00 148.50
121090105 Welding 0 70 20DEC10 27FEB11 20DEC10 27FEB11 0.66 0.00 521.00 0.00 594.00
121090106 NDT 0 70 10JAN11 20MAR11 10JAN11 20MAR11 0.07 0.00 104.00 0.00 59.40
121090108 Support 0 70 04JAN11 14MAR11 04JAN11 14MAR11 0.33 0.00 0.00 0.00 297.00
121090109 Pressure Test 0 20 15MAR11 03APR11 15MAR11 03APR11 0.07 0.00 0.00 0.00 59.40
CONDENSATE WATER SYSTEMPIPING 121100101 Carry In/Temporary Laydown 0 35 01DEC10* 04JAN11 01DEC10* 04JAN11 0.09 0.00 649.00 0.00 79.60
121100102 Fit-up Welding 0 45 04DEC10 17JAN11 04DEC10 17JAN11 0.13 0.00 2,885.50 0.00 119.40
121100103 Fit-up Screw ( Included Ti 0 30 18JAN11 16FEB11 18JAN11 16FEB11 0.07 0.00 29.50 0.00 59.70
121100104 Fit-up Flange ( Included T 0 30 17FEB11 18MAR11 17FEB11 18MAR11 0.07 0.00 519.00 0.00 59.70
121100105 Welding 0 80 09DEC10 26FEB11 09DEC10 26FEB11 0.26 0.00 2,885.50 0.00 238.80
121100106 NDT 0 80 16DEC10 05MAR11 16DEC10 05MAR11 0.03 0.00 75.00 0.00 23.88
2010 2011APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 1
Sheet 13 of 30
Sheet 14 of 30
ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
121100108 Support 0 90 10DEC10 09MAR11 10DEC10 09MAR11 0.13 0.00 0.00 0.00 119.40
121100109 Pressure Test 0 20 21MAR11 09APR11 21MAR11 09APR11 0.03 0.00 0.00 0.00 23.88
121100110 Flushing 0 60 01AUG11* 29SEP11 01AUG11* 29SEP11 0.02 0.00 0.00 0.00 15.92
CIRCULATING WATER SYSTEMPIPING 121110101 Carry In/Temporary Laydown 0 20 03JAN11* 22JAN11 03JAN11* 22JAN11 0.23 0.00 664.00 0.00 205.00
121110102 Fit-up Welding 0 30 03JAN11 01FEB11 03JAN11 01FEB11 0.34 0.00 1,518.00 0.00 307.50
121110103 Fit-up Screw ( Included Ti 0 5 22FEB11 26FEB11 22FEB11 26FEB11 0.17 0.00 2.00 0.00 153.75
121110104 Fit-up Flange ( Included T 0 20 02FEB11 21FEB11 02FEB11 21FEB11 0.17 0.00 6,802.50 0.00 153.75
121110105 Welding 0 45 03JAN11 16FEB11 03JAN11 16FEB11 0.68 0.00 1,518.00 0.00 615.00
121110106 NDT 0 50 17JAN11 07MAR11 17JAN11 07MAR11 0.07 0.00 0.00 0.00 61.50
121110108 Support 0 50 04JAN11 22FEB11 04JAN11 22FEB11 0.34 0.00 0.00 0.00 307.50
121110109 Pressure Test 0 20 23FEB11 14MAR11 23FEB11 14MAR11 0.07 0.00 0.00 0.00 61.50
121110110 Flushing 0 20 01SEP11* 20SEP11 01SEP11* 20SEP11 0.05 0.00 0.00 0.00 41.00
FEED WATER SYSTEMPIPING 121120101 Carry In/Temporary Laydown 0 40 01DEC10* 09JAN11 01DEC10* 09JAN11 0.14 0.00 632.00 0.00 127.00
121120102 Fit-up Welding 0 45 04DEC10 17JAN11 04DEC10 17JAN11 0.21 0.00 3,060.50 0.00 190.50
121120103 Fit-up Screw ( Included Ti 0 10 22FEB11 03MAR11 22FEB11 03MAR11 0.11 0.00 4.00 0.00 95.25
121120104 Fit-up Flange ( Included T 0 35 18JAN11 21FEB11 18JAN11 21FEB11 0.11 0.00 207.00 0.00 95.25
121120105 Welding 0 90 06DEC10 05MAR11 06DEC10 05MAR11 0.42 0.00 3,060.50 0.00 381.00
121120106 NDT 0 90 15DEC10 14MAR11 15DEC10 14MAR11 0.04 0.00 60.00 0.00 38.10
121120107 PWHT 0 90 01DEC10 28FEB11 01DEC10 28FEB11 0.21 0.00 56.00 0.00 190.50
121120108 Support 0 100 01DEC10 10MAR11 01DEC10 10MAR11 0.04 0.00 0.00 0.00 38.10
121120109 Pressure Test 0 20 11MAR11 30MAR11 11MAR11 30MAR11 0.03 0.00 0.00 0.00 25.40
121120110 Flushing 0 60 01AUG11 29SEP11 01AUG11 29SEP11 0.16 0.00 0.00 0.00 140.00
CLOSED COOLING WATER SYSTEMPIPING 121130101 Carry In/Temporary Laydown 0 30 29DEC10* 27JAN11 29DEC10* 27JAN11 0.07 0.00 444.00 0.00 66.60
121130102 Fit-up Welding 0 40 31DEC10 08FEB11 31DEC10 08FEB11 0.11 0.00 2,006.50 0.00 99.90
121130103 Fit-up Screw ( Included Ti 0 10 09FEB11 18FEB11 09FEB11 18FEB11 0.06 0.00 0.00 0.00 49.95
121130104 Fit-up Flange ( Included T 0 30 19FEB11 20MAR11 19FEB11 20MAR11 0.06 0.00 878.50 0.00 49.95
121130105 Welding 0 75 03JAN11 18MAR11 03JAN11 18MAR11 0.22 0.00 2,006.50 0.00 199.80
121130106 NDT 0 80 08JAN11 28MAR11 08JAN11 28MAR11 0.02 0.00 0.00 0.00 19.98
121130108 Support 0 90 03JAN11 02APR11 03JAN11 02APR11 0.11 0.00 0.00 0.00 99.90
121130109 Pressure Test 0 15 03APR11 17APR11 03APR11 17APR11 0.02 0.00 0.00 0.00 19.98
121130110 Flushing 0 30 01JUL11* 30JUL11 01JUL11* 30JUL11 0.01 0.00 0.00 0.00 13.32
NITROGEN GAS SYSTEMPIPING 121150101 Carry In/Temporary Laydown 0 15 01DEC10* 15DEC10 01DEC10* 15DEC10 0.01 0.00 0.00 0.00 9.80
121150102 Fit-up Welding 0 20 03DEC10 22DEC10 03DEC10 22DEC10 0.02 0.00 0.00 0.00 14.70
121150103 Fit-up Screw ( Included Ti 0 10 23DEC10 01JAN11 23DEC10 01JAN11 0.01 0.00 0.00 0.00 7.35
121150104 Fit-up Flange ( Included T 0 20 02JAN11 21JAN11 02JAN11 21JAN11 0.01 0.00 0.00 0.00 7.35
121150105 Welding 0 35 06DEC10 09JAN11 06DEC10 09JAN11 0.03 0.00 0.00 0.00 29.40
121150106 NDT 0 40 08DEC10 16JAN11 06DEC10 14JAN11 0.00 0.00 0.00 0.00 2.94
121150108 Support 0 50 01DEC10 19JAN11 01DEC10 19JAN11 0.02 0.00 0.00 0.00 14.70
121150109 Pressure Test 0 15 20JAN11 03FEB11 20JAN11 03FEB11 0.00 0.00 0.00 0.00 2.94
121150110 Flushing 0 15 01JUL11* 15JUL11 01JUL11* 15JUL11 0.00 0.00 0.00 0.00 1.96
SERVICE AIR SYSTEMPIPING 121160101 Carry In/Temporary Laydown 0 15 01DEC10* 15DEC10 01DEC10* 15DEC10 0.01 0.00 91.00 0.00 12.40
121160102 Fit-up Welding 0 30 02DEC10 31DEC10 01DEC10 30DEC10 0.02 0.00 364.00 0.00 18.60
121160103 Fit-up Screw ( Included Ti 0 10 01JAN11 10JAN11 31DEC10 09JAN11 0.01 0.00 0.00 0.00 9.30
121160104 Fit-up Flange ( Included T 0 10 11JAN11 20JAN11 10JAN11 19JAN11 0.01 0.00 0.00 0.00 9.30
121160105 Welding 0 40 03DEC10 11JAN11 02DEC10 10JAN11 0.04 0.00 364.00 0.00 37.20
121160106 NDT 0 45 08DEC10 21JAN11 07DEC10 20JAN11 0.00 0.00 0.00 0.00 3.72
121160108 Support 0 50 08DEC10 26JAN11 07DEC10 25JAN11 0.02 0.00 0.00 0.00 18.60
121160109 Pressure Test 0 14 01FEB11 14FEB11 31JAN11 13FEB11 0.00 0.00 0.00 0.00 3.72
121160110 Flushing 0 15 01MAR11* 15MAR11 01MAR11* 15MAR11 0.00 0.00 0.00 0.00 2.48
SERVICE WATER SYSTEMPIPING 121170101 Carry In/Temporary Laydown 0 44 01DEC10 13JAN11 01DEC10 13JAN11 0.07 0.00 8.00 0.00 66.60
2010 2011APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 1
Sheet 14 of 30
Sheet 15 of 30
ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
121170102 Fit-up Welding 0 44 03DEC10 15JAN11 01DEC10 13JAN11 0.11 0.00 32.00 0.00 99.90
121170103 Fit-up Screw ( Included Ti 0 5 25JAN11 29JAN11 23JAN11 27JAN11 0.06 0.00 0.00 0.00 49.95
121170104 Fit-up Flange ( Included T 0 11 15JAN11 25JAN11 13JAN11 23JAN11 0.06 0.00 0.00 0.00 49.95
121170105 Welding 0 44 05DEC10 17JAN11 03DEC10 15JAN11 0.22 0.00 32.00 0.00 199.80
121170106 NDT 0 44 10DEC10 22JAN11 08DEC10 20JAN11 0.02 0.00 0.00 0.00 19.98
121170108 Support 0 77 01DEC10 15FEB11 01DEC10 15FEB11 0.11 0.00 0.00 0.00 99.90
121170109 Pressure Test 0 11 15FEB11 25FEB11 15FEB11 25FEB11 0.02 0.00 0.00 0.00 19.98
121170110 Flushing 0 1 15MAR11* 15MAR11 15MAR11* 15MAR11 0.01 0.00 0.00 0.00 13.32
WASTE WATER SYSTEMPIPING 121190101 Carry In/Temporary Laydown 0 30 31MAR11* 29APR11 31MAR11* 29APR11 0.03 0.00 0.00 0.00 30.00
121190102 Fit-up Welding 0 30 31MAR11 29APR11 31MAR11 29APR11 0.05 0.00 0.00 0.00 45.00
121190103 Fit-up Screw ( Included Ti 0 10 30APR11 09MAY11 30APR11 09MAY11 0.02 0.00 0.00 0.00 22.50
121190104 Fit-up Flange ( Included T 0 10 10MAY11 19MAY11 10MAY11 19MAY11 0.02 0.00 0.00 0.00 22.50
121190105 Welding 0 50 02APR11 21MAY11 02APR11 21MAY11 0.10 0.00 0.00 0.00 90.00
121190106 NDT 0 50 08APR11 27MAY11 02APR11 21MAY11 0.01 0.00 0.00 0.00 9.00
121190108 Support 0 60 31MAR11 29MAY11 25MAR11 23MAY11 0.05 0.00 0.00 0.00 45.00
121190109 Pressure Test 0 20 30MAY11 18JUN11 24MAY11 12JUN11 0.01 0.00 0.00 0.00 9.00
LUBE OIL SYSTEMPIPING 121220101 Carry In/Temporary Laydown 0 20 01DEC10* 20DEC10 01DEC10* 20DEC10 0.07 0.00 909.00 0.00 59.50
121220102 Fit-up Welding 0 35 03DEC10 06JAN11 03DEC10 06JAN11 0.10 0.00 2,121.50 0.00 89.25
121220103 Fit-up Screw ( Included Ti 0 10 07JAN11 16JAN11 07JAN11 16JAN11 0.05 0.00 50.25 0.00 44.63
121220104 Fit-up Flange ( Included T 0 20 17JAN11 05FEB11 17JAN11 05FEB11 0.05 0.00 296.50 0.00 44.63
121220105 Welding 0 45 06DEC10 19JAN11 06DEC10 19JAN11 0.20 0.00 2,121.50 0.00 178.50
121220106 NDT 0 47 01DEC10 16JAN11 01DEC10 16JAN11 0.02 0.00 932.00 0.00 17.85
121220108 Support 0 60 01DEC10 29JAN11 01DEC10 29JAN11 0.10 0.00 0.00 0.00 89.25
121220109 Pressure Test 0 20 30JAN11 18FEB11 30JAN11 18FEB11 0.02 0.00 0.00 0.00 17.85
121220110 Flushing 0 105 15JUN11* 27SEP11 15JUN11* 27SEP11 0.01 0.00 0.00 0.00 11.90
CONTROL OIL SYSTEMPIPING 121230101 Carry In/Temporary Laydown 0 20 04JAN11* 23JAN11 04JAN11* 23JAN11 0.02 0.00 0.00 0.00 16.00
121230102 Fit-up Welding 0 30 06JAN11 04FEB11 06JAN11 04FEB11 0.03 0.00 0.00 0.00 24.00
121230103 Fit-up Screw ( Included Ti 0 10 05FEB11 14FEB11 05FEB11 14FEB11 0.01 0.00 0.00 0.00 12.00
121230104 Fit-up Flange ( Included T 0 10 15FEB11 24FEB11 15FEB11 24FEB11 0.01 0.00 0.00 0.00 12.00
121230105 Welding 0 45 08JAN11 21FEB11 08JAN11 21FEB11 0.05 0.00 0.00 0.00 48.00
121230106 NDT 0 35 17JAN11 20FEB11 17JAN11 20FEB11 0.01 0.00 0.00 0.00 4.80
121230108 Support 0 50 04JAN11 22FEB11 04JAN11 22FEB11 0.03 0.00 0.00 0.00 24.00
121230109 Pressure Test 0 20 23FEB11 14MAR11 23FEB11 14MAR11 0.01 0.00 0.00 0.00 4.80
121230110 Flushing 0 30 16MAY11* 14JUN11 16MAY11* 14JUN11 0.00 0.00 0.00 0.00 3.20
FIRE FIGHTING SYSTEMPIPING 121250101 Carry In/Temporary Laydown 0 30 30NOV10* 29DEC10 30NOV10* 29DEC10 0.09 0.00 0.00 0.00 82.40
121250102 Fit-up Welding 0 45 03DEC10 16JAN11 03DEC10 16JAN11 0.14 0.00 0.00 0.00 123.60
121250103 Fit-up Screw ( Included Ti 0 20 17JAN11 05FEB11 17JAN11 05FEB11 0.07 0.00 0.00 0.00 61.80
121250104 Fit-up Flange ( Included T 0 20 06FEB11 25FEB11 06FEB11 25FEB11 0.07 0.00 0.00 0.00 61.80
121250105 Welding 0 45 03DEC10 16JAN11 03DEC10 16JAN11 0.27 0.00 0.00 0.00 247.20
121250106 NDT 0 50 03DEC10 21JAN11 03DEC10 21JAN11 0.03 0.00 0.00 0.00 24.72
121250108 Support 0 80 03DEC10 20FEB11 03DEC10 20FEB11 0.14 0.00 0.00 0.00 123.60
121250109 Pressure Test 0 30 21FEB11 22MAR11 21FEB11 22MAR11 0.03 0.00 0.00 0.00 24.72
121250110 Flushing 0 15 02MAY11* 16MAY11 02MAY11* 16MAY11 0.02 0.00 0.00 0.00 16.48
SEAL OIL SYSTEMPIPING 121260101 Carry In/Temporary Laydown 0 20 09JAN11* 28JAN11 09JAN11* 28JAN11 0.05 0.00 0.00 0.00 44.00
121260102 Fit-up Welding 0 30 17JAN11 15FEB11 17JAN11 15FEB11 0.07 0.00 0.00 0.00 66.00
121260103 Fit-up Screw ( Included Ti 0 10 16FEB11 25FEB11 16FEB11 25FEB11 0.04 0.00 0.00 0.00 33.00
121260104 Fit-up Flange ( Included T 0 10 26FEB11 07MAR11 26FEB11 07MAR11 0.04 0.00 0.00 0.00 33.00
121260105 Welding 0 60 19JAN11 19MAR11 19JAN11 19MAR11 0.15 0.00 0.00 0.00 132.00
121260106 NDT 0 60 28JAN11 28MAR11 28JAN11 28MAR11 0.01 0.00 0.00 0.00 13.20
121260108 Support 0 70 14JAN11 24MAR11 14JAN11 24MAR11 0.07 0.00 0.00 0.00 66.00
121260109 Pressure Test 0 20 25MAR11 13APR11 25MAR11 13APR11 0.01 0.00 0.00 0.00 13.20
121260110 Flushing 0 45 16APR11 30MAY11 16APR11 30MAY11 0.01 0.00 0.00 0.00 8.80
2010 2011APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 1
Sheet 15 of 30
Sheet 16 of 30
ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
HYDROGEN GAS SYSTEMPIPING 121270101 Carry In/Temporary Laydown 0 15 24MAR11* 07APR11 24MAR11* 07APR11 0.01 0.00 0.00 0.00 12.80
121270102 Fit-up Welding 0 20 26MAR11 14APR11 26MAR11 14APR11 0.02 0.00 0.00 0.00 19.20
121270103 Fit-up Screw ( Included Ti 0 10 15APR11 24APR11 15APR11 24APR11 0.01 0.00 0.00 0.00 9.60
121270104 Fit-up Flange ( Included T 0 20 25APR11 14MAY11 25APR11 14MAY11 0.01 0.00 0.00 0.00 9.60
121270105 Welding 0 50 26MAR11 14MAY11 26MAR11 14MAY11 0.04 0.00 0.00 0.00 38.40
121270106 NDT 0 50 28MAR11 16MAY11 28MAR11 16MAY11 0.00 0.00 0.00 0.00 3.84
121270108 Support 0 60 24MAR11 22MAY11 24MAR11 22MAY11 0.02 0.00 0.00 0.00 19.20
121270109 Pressure Test 0 15 23MAY11 06JUN11 23MAY11 06JUN11 0.00 0.00 0.00 0.00 3.84
121270110 Flushing 0 15 01JUL11* 15JUL11 01JUL11* 15JUL11 0.00 0.00 0.00 0.00 2.56
CHEMICAL DOSING & SAMPLING PIPING SYSTEMPIPING 121300101 Carry In/Temporary Laydown 0 15 03MAR11* 17MAR11 03MAR11* 17MAR11 0.05 0.00 0.00 0.00 46.80
121300102 Fit-up Welding 0 30 05MAR11 03APR11 05MAR11 03APR11 0.08 0.00 0.00 0.00 70.20
121300103 Fit-up Screw ( Included Ti 0 10 04APR11 13APR11 04APR11 13APR11 0.04 0.00 0.00 0.00 35.10
121300104 Fit-up Flange ( Included T 0 20 14APR11 03MAY11 14APR11 03MAY11 0.04 0.00 0.00 0.00 35.10
121300105 Welding 0 35 07MAR11 10APR11 07MAR11 10APR11 0.16 0.00 0.00 0.00 140.40
121300106 NDT 0 30 15MAR11 13APR11 15MAR11 13APR11 0.02 0.00 0.00 0.00 14.04
121300108 Support 0 45 03MAR11 16APR11 03MAR11 16APR11 0.08 0.00 0.00 0.00 70.20
121300109 Pressure Test 0 30 17APR11 16MAY11 17APR11 16MAY11 0.02 0.00 0.00 0.00 14.04
121300110 Flushing 0 30 01SEP11 30SEP11 01SEP11 30SEP11 0.01 0.00 0.00 0.00 9.36
INSULATION & PAINTINGINSTRUMENT AIR SYSTEMPAINTING 121050301 Painting 0 20 16MAR11* 04APR11 16MAR11* 04APR11 0.00 0.00 0.00 0.00 3.00
MAIN STEAM SYSTEMPAINTING 121070301 Painting 0 20 06APR11 25APR11 09APR11 28APR11 0.03 0.00 0.00 0.00 25.40
INSULATIO 121070201 Insulation 0 36 01MAR11 05APR11 04MAR11 08APR11 0.16 0.00 0.00 0.00 140.00
AUXILIARY / GLAND STEAM SYSTEMPAINTING 121080301 Painting 0 20 14FEB11 05MAR11 14FEB11 05MAR11 0.03 0.00 0.00 0.00 24.80
INSULATIO 121080201 Insulation 0 36 14FEB11 21MAR11 14FEB11 21MAR11 0.16 0.00 0.00 0.00 140.00
ST FLASH TANK & DRAIN SYSTEMPAINTING 121090301 Painting 0 20 04APR11 23APR11 04APR11 23APR11 0.04 0.00 0.00 0.00 39.60
CONDENSATE WATER SYSTEMPAINTING 121100301 Painting 0 30 10APR11 09MAY11 10APR11 09MAY11 0.02 0.00 0.00 0.00 15.92
INSULATIO 121100201 Insulation 0 30 10APR11 09MAY11 10APR11 09MAY11 0.03 0.00 0.00 0.00 23.88
CIRCULATING WATER SYSTEMPAINTING 121110301 Painting 0 20 15MAR11 03APR11 15MAR11 03APR11 0.05 0.00 0.00 0.00 41.00
FEED WATER SYSTEMPAINTING 121120301 Painting 0 20 06MAY11 25MAY11 06MAY11 25MAY11 0.00 0.00 0.00 0.00 0.00
INSULATIO 121120201 Insulation 0 36 31MAR11 05MAY11 31MAR11 05MAY11 0.03 0.00 0.00 0.00 25.40
CLOSED COOLING WATER SYSTEMPAINTING 121130301 Painting 0 35 18APR11 22MAY11 18APR11 22MAY11 0.01 0.00 0.00 0.00 13.32
NITROGEN GAS SYSTEMPAINTING 121150301 Painting 0 20 04FEB11 23FEB11 04FEB11 23FEB11 0.00 0.00 0.00 0.00 1.96
SERVICE AIR SYSTEMPAINTING 121160301 Painting 0 20 15FEB11 06MAR11 14FEB11 05MAR11 0.00 0.00 0.00 0.00 2.48
2010 2011APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 1
Sheet 16 of 30
Sheet 17 of 30
ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
SERVICE WATER SYSTEMPAINTING 121170301 Painting 0 58 20DEC10 15FEB11 20DEC10 15FEB11 0.01 0.00 0.00 0.00 13.32
WASTE WATER SYSTEMPAINTING 121190301 Painting 0 20 20JUN11 09JUL11 14JUN11 03JUL11 0.01 0.00 0.00 0.00 6.00
LUBE OIL SYSTEMPAINTING 121220301 Painting 0 20 19FEB11 10MAR11 19FEB11 10MAR11 0.01 0.00 0.00 0.00 11.90
CONTROL OIL SYSTEMPAINTING 121230301 Painting 0 20 15MAR11 03APR11 15MAR11 03APR11 0.00 0.00 0.00 0.00 3.20
FIRE FIGHTING SYSTEMPAINTING 121250301 Painting 0 20 27MAR11* 15APR11 27MAR11* 15APR11 0.02 0.00 0.00 0.00 16.48
SEAL OIL SYSTEMPAINTING 121260301 Painting 0 20 02MAY11* 21MAY11 02MAY11* 21MAY11 0.01 0.00 0.00 0.00 8.80
HYDROGEN GAS SYSTEMPAINTING 121270301 Painting 0 20 07JUN11 26JUN11 07JUN11 26JUN11 0.00 0.00 0.00 0.00 2.56
CHEMICAL DOSING & SAMPLING PIPING SYSTEMPAINTING 121300301 Painting 0 20 17MAY11 05JUN11 17MAY11 05JUN11 0.01 0.00 0.00 0.00 9.36
HRSG UNIT 1PIPINGINSTRUMENT AIR SYSTEMPIPING 111050101 Carry In/Temporary Laydown 0 15 01NOV10* 15NOV10 04NOV10* 18NOV10 0.02 0.00 0.00 0.00 16.80
111050102 Fit-up Welding 0 18 04NOV10 21NOV10 04NOV10 21NOV10 0.03 0.00 0.00 0.00 25.20
111050103 Fit-up Screw ( Included Ti 0 10 24NOV10 03DEC10 24NOV10 03DEC10 0.01 0.00 0.00 0.00 12.60
111050104 Fit-up Flange ( Included T 0 15 04DEC10 18DEC10 04DEC10 18DEC10 0.01 0.00 0.00 0.00 12.60
111050105 Welding 0 30 08NOV10 07DEC10 08NOV10 07DEC10 0.06 0.00 0.00 0.00 50.40
111050106 NDT 0 30 13NOV10 12DEC10 13NOV10 12DEC10 0.01 0.00 0.00 0.00 5.04
111050108 Support 0 35 01NOV10 05DEC10 04NOV10 08DEC10 0.03 0.00 0.00 0.00 25.20
111050109 Pressure Test 0 15 06DEC10 20DEC10 09DEC10 23DEC10 0.01 0.00 0.00 0.00 5.04
111050110 Flushing 0 15 01MAR11* 15MAR11 01MAR11* 15MAR11 0.00 0.00 0.00 0.00 3.36
MAIN STEAM SYSTEMPIPING 111070101 Carry In/Temporary Laydown 0 40 12DEC10* 20JAN11 12DEC10* 20JAN11 0.13 0.00 291.00 0.00 117.10
111070102 Fit-up Welding 0 80 12DEC10 01MAR11 12DEC10 01MAR11 0.19 0.00 1,877.00 0.00 175.65
111070103 Fit-up Screw ( Included Ti 0 10 02MAR11 11MAR11 02MAR11 11MAR11 0.10 0.00 0.00 0.00 87.83
111070104 Fit-up Flange ( Included T 0 30 12MAR11 10APR11 12MAR11 10APR11 0.10 0.00 114.00 0.00 87.83
111070105 Welding 0 90 15DEC10 14MAR11 15DEC10 14MAR11 0.39 0.00 1,877.00 0.00 351.30
111070106 NDT 0 90 25DEC10 24MAR11 25DEC10 24MAR11 0.04 0.00 15.00 0.00 35.13
111070108 Support 0 100 12DEC10 21MAR11 12DEC10 21MAR11 0.19 0.00 4.00 0.00 175.65
111070109 Pressure Test 0 20 22MAR11 10APR11 22MAR11 10APR11 0.04 0.00 0.00 0.00 35.13
111070110 Flushing 0 30 03OCT11* 01NOV11 03OCT11* 01NOV11 0.03 0.00 0.00 0.00 23.42
FEED WATER SYSTEMPIPING 111120101 Carry In/Temporary Laydown 0 30 15DEC10 13JAN11 15DEC10 13JAN11 0.19 0.00 746.00 0.00 172.00
111120102 Fit-up Welding 0 60 20DEC10 17FEB11 20DEC10 17FEB11 0.29 0.00 3,049.50 0.00 258.00
111120103 Fit-up Screw ( Included Ti 0 5 20MAR11 24MAR11 20MAR11 24MAR11 0.14 0.00 6.00 0.00 129.00
111120104 Fit-up Flange ( Included T 0 30 18FEB11 19MAR11 18FEB11 19MAR11 0.14 0.00 64.00 0.00 129.00
111120105 Welding 0 80 24DEC10 13MAR11 24DEC10 13MAR11 0.57 0.00 3,049.50 0.00 516.00
111120106 NDT 0 90 15DEC10 14MAR11 15DEC10 14MAR11 0.06 0.00 24.00 0.00 51.60
111120107 PWHT 0 80 24DEC10 13MAR11 24DEC10 13MAR11 0.04 0.00 104.00 0.00 34.40
111120108 Support 0 100 15DEC10 24MAR11 15DEC10 24MAR11 0.29 0.00 0.00 0.00 258.00
111120109 Pressure Test 0 20 25MAR11 13APR11 25MAR11 13APR11 0.06 0.00 0.00 0.00 51.60
111120110 Flushing 0 60 01AUG11* 29SEP11 01AUG11* 29SEP11 0.04 0.00 0.00 0.00 34.40
2010 2011APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 1
Sheet 17 of 30
Sheet 18 of 30
ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
CLOSED COOLING WATER SYSTEMPIPING 111130101 Carry In/Temporary Laydown 0 20 28DEC10* 16JAN11 28DEC10* 16JAN11 0.07 0.00 0.00 0.00 66.80
111130102 Fit-up Welding 0 30 28DEC10 26JAN11 28DEC10 26JAN11 0.11 0.00 0.00 0.00 100.20
111130103 Fit-up Screw ( Included Ti 0 10 27JAN11 05FEB11 27JAN11 05FEB11 0.06 0.00 0.00 0.00 50.10
111130104 Fit-up Flange ( Included T 0 10 06FEB11 15FEB11 06FEB11 15FEB11 0.06 0.00 0.00 0.00 50.10
111130105 Welding 0 50 28DEC10 15FEB11 28DEC10 15FEB11 0.22 0.00 0.00 0.00 200.40
111130106 NDT 0 61 28DEC10 26FEB11 28DEC10 26FEB11 0.02 0.00 0.00 0.00 20.04
111130108 Support 0 50 28DEC10 15FEB11 28DEC10 15FEB11 0.11 0.00 0.00 0.00 100.20
111130109 Pressure Test 0 30 16FEB11 17MAR11 16FEB11 17MAR11 0.02 0.00 0.00 0.00 20.04
111130110 Flushing 0 30 01JUL11* 30JUL11 01JUL11* 30JUL11 0.01 0.00 0.00 0.00 13.36
NITROGEN GAS SYSTEMPIPING 111150101 Carry In/Temporary Laydown 0 20 19JAN11* 07FEB11 19JAN11* 07FEB11 0.01 0.00 0.00 0.00 9.80
111150102 Fit-up Welding 0 30 21JAN11 19FEB11 21JAN11 19FEB11 0.02 0.00 0.00 0.00 14.70
111150103 Fit-up Screw ( Included Ti 0 10 20FEB11 01MAR11 20FEB11 01MAR11 0.01 0.00 0.00 0.00 7.35
111150104 Fit-up Flange ( Included T 0 10 02MAR11 11MAR11 02MAR11 11MAR11 0.01 0.00 0.00 0.00 7.35
111150105 Welding 0 35 22JAN11 25FEB11 22JAN11 25FEB11 0.03 0.00 0.00 0.00 29.40
111150106 NDT 0 35 28JAN11 03MAR11 28JAN11 03MAR11 0.00 0.00 0.00 0.00 2.94
111150108 Support 0 40 19JAN11 27FEB11 19JAN11 27FEB11 0.02 0.00 0.00 0.00 14.70
111150109 Pressure Test 0 15 28FEB11 14MAR11 28FEB11 14MAR11 0.00 0.00 0.00 0.00 2.94
111150110 Flushing 0 15 01JUL11* 15JUL11 01JUL11* 15JUL11 0.00 0.00 0.00 0.00 1.96
SERVICE AIR SYSTEMPIPING 111160101 Carry In/Temporary Laydown 0 15 16DEC10* 30DEC10 16DEC10* 30DEC10 0.02 0.00 0.00 0.00 18.90
111160102 Fit-up Welding 0 30 18DEC10 16JAN11 18DEC10 16JAN11 0.03 0.00 0.00 0.00 28.35
111160103 Fit-up Screw ( Included Ti 0 10 17JAN11 26JAN11 17JAN11 26JAN11 0.02 0.00 0.00 0.00 14.18
111160104 Fit-up Flange ( Included T 0 10 27JAN11 05FEB11 27JAN11 05FEB11 0.02 0.00 0.00 0.00 14.18
111160105 Welding 0 50 20DEC10 07FEB11 20DEC10 07FEB11 0.06 0.00 0.00 0.00 56.70
111160106 NDT 0 50 23DEC10 10FEB11 23DEC10 10FEB11 0.01 0.00 0.00 0.00 5.67
111160108 Support 0 50 20DEC10 07FEB11 20DEC10 07FEB11 0.03 0.00 0.00 0.00 28.35
111160109 Pressure Test 0 15 08FEB11 22FEB11 08FEB11 22FEB11 0.01 0.00 0.00 0.00 5.67
111160110 Flushing 0 15 01MAR11 15MAR11 01MAR11 15MAR11 0.00 0.00 0.00 0.00 3.78
SERVICE WATER SYSTEMPIPING 111170101 Carry In/Temporary Laydown 0 15 04JAN11* 18JAN11 04JAN11* 18JAN11 0.02 0.00 0.00 0.00 16.80
111170102 Fit-up Welding 0 20 06JAN11 25JAN11 06JAN11 25JAN11 0.03 0.00 0.00 0.00 25.20
111170103 Fit-up Screw ( Included Ti 0 10 26JAN11 04FEB11 26JAN11 04FEB11 0.01 0.00 0.00 0.00 12.60
111170104 Fit-up Flange ( Included T 0 20 05FEB11 24FEB11 05FEB11 24FEB11 0.01 0.00 0.00 0.00 12.60
111170105 Welding 0 50 06JAN11 24FEB11 06JAN11 24FEB11 0.06 0.00 0.00 0.00 50.40
111170106 NDT 0 50 10JAN11 28FEB11 10JAN11 28FEB11 0.01 0.00 0.00 0.00 5.04
111170108 Support 0 50 04JAN11 22FEB11 04JAN11 22FEB11 0.03 0.00 0.00 0.00 25.20
111170109 Pressure Test 0 20 23FEB11 14MAR11 23FEB11 14MAR11 0.01 0.00 0.00 0.00 5.04
111170110 Flushing 0 15 02MAY11* 16MAY11 02MAY11* 16MAY11 0.00 0.00 0.00 0.00 3.36
WASTE WATER SYSTEMPIPING 111190101 Carry In/Temporary Laydown 0 20 21DEC10* 09JAN11 21DEC10* 09JAN11 0.03 0.00 350.00 0.00 23.40
111190102 Fit-up Welding 0 30 22DEC10 20JAN11 22DEC10 20JAN11 0.04 0.00 1,407.00 0.00 35.10
111190103 Fit-up Screw ( Included Ti 0 10 21JAN11 30JAN11 21JAN11 30JAN11 0.02 0.00 0.00 0.00 17.55
111190104 Fit-up Flange ( Included T 0 10 31JAN11 09FEB11 31JAN11 09FEB11 0.02 0.00 40.00 0.00 17.55
111190105 Welding 0 50 30DEC10 17FEB11 30DEC10 17FEB11 0.08 0.00 1,407.00 0.00 70.20
111190106 NDT 0 50 30DEC10 17FEB11 30DEC10 17FEB11 0.01 0.00 16.00 0.00 7.02
111190108 Support 0 60 22DEC10 19FEB11 22DEC10 19FEB11 0.04 0.00 0.00 0.00 35.10
111190109 Pressure Test 0 15 20FEB11 06MAR11 20FEB11 06MAR11 0.01 0.00 0.00 0.00 7.02
INSULATION & PAINTINGINSTRUMENT AIR SYSTEMPAINTING 111050301 Painting 0 20 21DEC10 09JAN11 24DEC10 12JAN11 0.00 0.00 0.00 0.00 3.36
MAIN STEAM SYSTEMPAINTING 111070301 Painting 0 20 01JUN11 20JUN11 01JUN11 20JUN11 0.03 0.00 0.00 0.00 23.42
2010 2011APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 1
Sheet 18 of 30
Sheet 19 of 30
ActivityID
ActivityDescription
%Comp
OrigDur
PPSSStart
PPSSFinish
PlanStart
PlanFinish
%WF
%Comp
QTYPlan
QTYAct
MDY
INSULATIO 111070201 Insulation 0 75 11APR11 24JUN11 11APR11 24JUN11 0.33 0.00 0.00 0.00 297.50
FEED WATER SYSTEMPAINTING 111120301 Painting 0 35 14APR11* 18MAY11 14APR11* 18MAY11 0.04 0.00 0.00 0.00 34.40
INSULATIO 111120201 Insulation 0 75 18APR11* 01JUL11 18APR11* 01JUL11 0.33 0.00 0.00 0.00 297.50
CLOSED COOLING WATER SYSTEMPAINTING 111130301 Painting 0 20 14AUG11* 02SEP11 14AUG11* 02SEP11 0.01 0.00 0.00 0.00 13.36
NITROGEN GAS SYSTEMPAINTING 111150301 Painting 0 20 15MAR11 03APR11 15MAR11 03APR11 0.00 0.00 0.00 0.00 1.96
SERVICE AIR SYSTEMPAINTING 111160301 Painting 0 20 23FEB11 14MAR11 23FEB11 14MAR11 0.00 0.00 0.00 0.00 3.78
SERVICE WATER SYSTEMPAINTING 111170301 Painting 0 20 15MAR11 03APR11 15MAR11 03APR11 0.00 0.00 0.00 0.00 3.36
WASTE WATER SYSTEMPAINTING 111190301 Painting 0 20 07MAR11 26MAR11 07MAR11 26MAR11 0.01 0.00 0.00 0.00 4.68
HRSG UNIT 2PIPINGINSTRUMENT AIR SYSTEMPIPING 112050101 Carry In/Temporary Laydown 0 15 16NOV10 30NOV10 19NOV10 03DEC10 0.02 0.00 1.00 0.00 14.40
112050102 Fit-up Welding 0 18 21NOV10 08DEC10 25NOV10 12DEC10 0.02 0.00 0.00 0.00 21.60
112050103 Fit-up Screw ( Included Ti 0 10 09DEC10 18DEC10 13DEC10 22DEC10 0.01 0.00 0.00 0.00 10.80
112050104 Fit-up Flange ( Included T 0 15 19DEC10 02JAN11 23DEC10 06JAN11 0.01 0.00 0.00 0.00 10.80
112050105 Welding 0 30 21NOV10 20DEC10 25NOV10 24DEC10 0.05 0.00 0.00 0.00 43.20
112050106 NDT 0 30 25NOV10 24DEC10 29NOV10 28DEC10 0.00 0.00 0.00 0.00 4.32
112050108 Support 0 35 21NOV10 25DEC10 25NOV10 29DEC10 0.02 0.00 0.00 0.00 21.60
112050109 Pressure Test 0 15 26