+ All Categories
Home > Documents > Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why...

Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why...

Date post: 07-Aug-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
35
Barton CSO Project – Green Stormwater Infrastructure (GSI) Sunrise Heights & Westwood Community Meeting February 8, 2012
Transcript
Page 1: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Barton CSO Project – Green Stormwater Infrastructure (GSI)

Sunrise Heights &

Westwood

Community Meeting

February 8, 2012

Page 2: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Meeting Agenda

• Project background (Mary Wohleb)

• Update on fieldwork, findings, and how they inform project design (Peg Staeheli & Curtis Koger)

• Considerations for bioretention swale locations (Peg Staeheli)

• Next steps and community involvement in design phase (Mary Wohleb)

• Hear community perspectives, concerns, and questions (Team)

• Break-out Sessions: one-on-one opportunities

Page 3: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

What is a Combined Sewer Overflow (CSO)?

• Currently averages 4 overflows per year

• Dept. of Ecology requires no more than 1 overflow per year by 2015.

Page 4: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Barton Basin Description and Requirements

• 1,111 acres

• Five sub-basins

• Historically surface

water flowed south

and east

• Constructed

Combined Sewer

system conveyed

flows to the Barton

Pump station then

on to West Point

Treatment Plant

Murray CSO

Barton CSO

Approximate location of Longfellow Creek

Page 5: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Contribution to the Combined Sewer System

• 45% of stormwater flows entering the combined sewer come from the project area

• Stormwater runoff from the streets drain to combined sewer

PROJECT AREA

Page 6: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Project Area Connection • 170 acres in the

Sunrise Heights and

Westwood

communities is

connected to the

CSS

• Reduce overall

volume of stormwater

entering the CSS

through GSI

Page 7: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

What is Green Stormwater Infrastructure (GSI)?

Engineered

infrastructure to

manage stormwater

quantity and quality

using soils and

vegetation (sometimes

in combination with

decentralized storage)

to capture, infiltrate,

evaporate or reuse

stormwater.

Page 8: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

GSI for CSO Control

High Point, Seattle Port Townsend

Page 9: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Why this Neighborhood? • Predominately connected

• 45% flow contribution

• Initial high level analysis appears there were enough blocks connected to meet the CSO control target

• Many flat or slightly sloping streets

• Wide planter strips on many streets

• Can be constructed in the Right of Way

Project scope:

• Construct bioretention swales in the planter strips in the city owned right of way on up to 40 blocks to control CSOs

Page 10: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial
Page 11: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

What We’ve Heard from You

• Existing Drainage Concerns

• Parking

• Access

• Vegetation and Trees

• Maintenance

Page 12: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Setting the Stage for Design

• Research

• Select a Consultant Team

• Gather Data

• Develop Models

• Start Permitting Process

Page 13: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Understanding the Conditions of Your Neighborhood

Page 14: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Overview of Field Reconnaissance

• Understanding Above- and Below-Ground Features

• Geotechnical Testing

• Initial Land Survey

• Data Review

image courtesy Google

Page 15: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Neighborhood Geology

• Soil types

• Soil layers

• How and where water flows underground

• Water table characteristics

Page 16: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Testing Sites and Equipment

Page 17: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

What We Found Underground

Page 18: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Initial Geotechnical Findings

• Surface soils have low infiltration (drainage) rates

• There are deeper soils that are excellent for conveying water in the Vashon advance outwash for stormwater infiltration

Page 19: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial
Page 20: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Bioretention Swale in Infiltrative Soils

Page 21: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Bioretention with Pit Drains Design

Page 22: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Bioretention with Deep Well Infiltration Design

Page 23: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Bringing Together the Data

• Right-of-way (ROW) location

• Geotechnical combined with field survey

• Field reconnaissance

• Underground utilities

• Parking placement and use

• Community survey

• Assessment of trees and

vegetation

• Existing surface conditions

Page 24: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Field Reconnaissance

Page 25: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Catchment Areas and Modeling

SvR to ADD GRAPHIC:

showing block level

catchments.

Page 26: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Evaluation of the Streets

32nd Ave SW (Webster to Holden) 31st Ave SW (Webster to Holden)

SW Kenyon St (34th to 31st) 34nd Ave SW (Trenton to Henderson)

Page 27: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Characteristics We’re Looking For

• Residential Streets (not arterials)

• Right-of-way (ROW) location

• Wider Planters

• Flatter Roads

• Utility Locations

• Service Utilities

• Open Areas Without Mature Trees

• Existing Vegetation

• Fewer Driveways

• Cross Slope of Road (“Thrown” vs. “Crowned”)

• Bigger Catchment Areas

• On-Street Parking

• No Impact on Cultural Resources

• No Impact to Existing Drainage Conditions

• Suitable Soils

• Community Survey

• Access to Sidewalks

Page 28: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial
Page 29: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial
Page 30: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Design Process

Survey Modeling

Geotechnical

Testing

Field

Recon.

Public

Feedback Design

&

Permitting

Page 31: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Design and Permitting Process

• Perform Field Reconnaissance

• Develop Conceptual Layout for Streets

• Fit Bioretention Cells Into Planting Strips

• Begin Street Improvement Process with Seattle Dept. of Transportation (SDOT) & Seattle Public Utilities (SPU)

• Gather Community Input

• Design for Operations & Maintenance

• Design for Wise Use of Public Funds

• Prepare Bid Documents for Construction

Page 32: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Next Steps

• Modeling to determine the number of blocks needed to control the CSO

• Select the blocks

• Notify selected blocks

• Work with some homeowners on further land surveying or locating utilities

• Community meeting in late March on block selection and begin work on final design

Page 33: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial
Page 34: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

Break Out Sessions

• Geology

• Design Considerations

• Basin Drainage

• General Project Questions

Page 35: Barton CSO Project Green Stormwater Infrastructure (GSI)...High Point, Seattle Port Townsend . Why this Neighborhood? •Predominately connected •45% flow contribution •Initial

For More Information

• Kristine Cramer, King County Community Relations

Email: [email protected]

Phone: (206) 263-3184

• Mary Wohleb, King County Project Manager

Email: [email protected]

Phone: (206) 296-8028

• Web: www.kingcounty.gov/environment/wtd/ construction/seattle/bartonCSO-GSI.aspx


Recommended