+ All Categories
Home > Documents > Basis for Design New

Basis for Design New

Date post: 04-Apr-2018
Category:
Upload: iyanda-seun
View: 220 times
Download: 1 times
Share this document with a friend

of 56

Transcript
  • 7/31/2019 Basis for Design New

    1/56

    EpicAtlanticLimited

    Page 1

    CHESTER MEAD ASSOCI ATES LI MI TED

    BASI S FOR DESI GN

    FOR

    MI DWESTERN OI L AND GAS COMPANY PLC

    PROJECT:

    UMUSADEGE CENTRAL PROCESSI NG FACI LI TY

    ENGI NEERI NG AND PROCUREMENT SERVI CES

    CONTRACT NUMBER:

    xxxxxxxxxxxx

    DOCUMENT NUMBER:EAL/UMUCPF/GEN/DOC/001

    AO2 30/04/2012Issued forApproval

    AD KK

    Rev. Date Description Originator Released Approved (Client)

  • 7/31/2019 Basis for Design New

    2/56

    UMUSADEGE CENTRAL PROCESSING FACILITY ENGINEERING AND PROCUREMENT SERVICES

    BASIS FOR DESIGN - CMA/ UMUCPF/ MDR-GEN/ DOC/ 003Feb 28, 2012

    EpicAtlanticLimited

    Page 2

    ADDI TI ONAL AGREEMENT / APPROVAL RECORDS

    Part y Rev. I nd. Name Sign Date

    REVI SI ON PHI LOSOPHY

    All revisions for review will be issued at R01, with subsequent R02, R03, etc asrequired.

    All revisions approved for issue or design will be issued at A01, with subsequentA02, A03, etc as required.Documents approved for Construction will be issued at C01, C02, and C03respectively.Documents or drawings revised as As built will be issued as Z01, Z02 Z03 etc.Narrative sections revised from previous approved issues are to be noted in thetable below and/or highlighted in the RH margin (using the appropriate revisionstatus) thus: | A02Previous revision highlighting to be removed at subsequent issues.Drawings/diagrams revised from previous approved issues are highlighted by

    'clouding' the affected areas and by the use of a triangle containing the revisionstatus.

    REVI SI ON HI STORY

    Rev. No.Date ofI ssue

    Reason for change

    R02 IDC

    A01 28/02/12MWOG CommentsRevised Production Forecasts & Well Streams Data

    Deleted Offspec collection within CPF

  • 7/31/2019 Basis for Design New

    3/56

    UMUSADEGE CENTRAL PROCESSING FACILITY ENGINEERING AND PROCUREMENT SERVICES

    BASIS FOR DESIGN - CMA/ UMUCPF/ MDR-GEN/ DOC/ 003Feb 28, 2012

    EpicAtlanticLimited

    Page 3

    Table of Cont ent s

    GLOSSARY 8

    1.0 INTRODUCTION ............................................................................................. 151.1 Purp ose ................................................................................................ 151.2 The Umusadege Field ........................................................................ 151.3 The Field s Fac ilities Develop ment Ob jec tives .............................. 151.4 Ove rview of The Field s Existing Proc essing Fac ilities .................... 15

    2.0 KEY CONSIDERATIONS .................................................................................. 172.1 Mode .................................................................................................... 172.2 Brow n Field Eng ineering / Stra te gy Fit ............................................. 172.3 Field Life ............................................................................................... 172.4 Effic ienc y & Op timum Oil Rec overy from the Proc ess Systems .. 172.5 Dry Crud e Export ................................................................................ 172.6 Zero Effluent Emission ......................................................................... 18

    3.0 THE EXISTING FACILITIES & INFRASTRUCTURE............................................... 193.1 Surfa ce Fac ilities in Plac e .................................................................. 193.2 The Ea rly Produc tio n Fac ility ............................................................. 193.3 The Field Infra struc ture ...................................................................... 20

    4.0 DESIGN REQUIREMENTS ................................................................................ 214.1 Design Capac ities & Spec ifica tions ................................................ 214.2 Well Fluid Cha rac te ristic s and Prop erties ....................................... 224.3 Export Crude Spec ifica tion............................................................... 22

  • 7/31/2019 Basis for Design New

    4/56

    UMUSADEGE CENTRAL PROCESSING FACILITY ENGINEERING AND PROCUREMENT SERVICES

    BASIS FOR DESIGN - CMA/ UMUCPF/ MDR-GEN/ DOC/ 003Feb 28, 2012

    EpicAtlanticLimited

    Page 4

    4.4 Prod uc ed Effluent Wate r Spec ifica tion .......................................... 234.5 Cha rac te rised Well Fluid Da ta ......................................................... 234.6 Formation Wate r Ana lysis .................................................................. 244.7 Prod uc tion Start-Up ............................................................................ 244.8 Erosion Veloc ity & Noise .................................................................... 254.9 Fac ility Sta nd ards ............................................................................... 254.10 Design Simulation Software .............................................................. 25

    5.0

    THE CENTRAL PROCESSING FACILITY ........................................................... 26

    5.1 Fac ilities / Proc ess Desc ription ......................................................... 265.2 Design & Operating Philosophy ....................................................... 295.2.1 The Inlet and Intermediate / ESD Va lves Manifold ....................... 305.2.2 The Test Sepa rator .............................................................................. 315.2.3 The HP Separator ................................................................................ 315.2.4 The LP Separator ................................................................................ 315.2.5 The Gas Boot ....................................................................................... 325.3 The Crud e Export Pum ps ................................................................... 325.4 The Closed Drain System ................................................................... 325.5 Gas Hand ling ...................................................................................... 325.6 Flare System ........................................................................................ 335.7 Water Trea tment ................................................................................ 335.8 Storage Tanks ...................................................................................... 335.9 Diesel Sto rage and Dispensing ........................................................ 355.10 Servic e & Fresh Water System .......................................................... 35

  • 7/31/2019 Basis for Design New

    5/56

  • 7/31/2019 Basis for Design New

    6/56

    UMUSADEGE CENTRAL PROCESSING FACILITY ENGINEERING AND PROCUREMENT SERVICES

    BASIS FOR DESIGN - CMA/ UMUCPF/ MDR-GEN/ DOC/ 003Feb 28, 2012

    EpicAtlanticLimited

    Page 6

    9.2 LAYOUT CO NSIDERATIONS ................................................................ 4410.0 FIRE PROTECTION .......................................................................................... 46

    10.1 Fire Wate r ............................................................................................ 4610.2 Fire and Gas Dete c tion Syste m ....................................................... 46

    11.0 ELECTRICAL DESIGN BASIS ........................................................................... 4711.1 Power Generation .............................................................................. 4711.2 UPS ........................................................................................................ 48

    11.3

    Power Transmission & Distribut ion .................................................... 48

    12.0 HSE/ SD REQUIREMENTS ................................................................................. 4912.1 Safety Considerations ........................................................................ 4912.2 Environm enta l Considerations ......................................................... 4912.3 Sec urity Considerations ..................................................................... 4912.4 Risk Assessment and Mana gement ................................................ 50

    13.0 ASSET MANAGEMENT ................................................................................... 5113.1 Operating Philosop hies ..................................................................... 5113.2 Asset Reference Plan......................................................................... 51

    14.0 MANAGEMENT OF CHANGE & QUALITY ..................................................... 5214.1 Design Change .................................................................................. 5214.2 Qua lity Assuranc e and Control Requirements .............................. 52

    15.0 STATUTORY AND REGULATORY COMPLIANCE ............................................ 5315.1 Nigerian Content ............................................................................... 5315.2 Regula to ry Considerations ............................................................... 53

    16.0 APPENDICES .................................................................................................. 56

  • 7/31/2019 Basis for Design New

    7/56

    UMUSADEGE CENTRAL PROCESSING FACILITY ENGINEERING AND PROCUREMENT SERVICES

    BASIS FOR DESIGN - CMA/ UMUCPF/ MDR-GEN/ DOC/ 003Feb 28, 2012

    EpicAtlanticLimited

    Page 7

    BFD Matrix ....................................................................................................... 56Produc tion Forec ast / Well Fluid Cha rac teristics and Properties........... 56Fire and Gas Detec tion ................................................................................ 56Proposed General Layout ............................................................................ 56

  • 7/31/2019 Basis for Design New

    8/56

    EpicAtlanticLimited

    Page 8

    GLOSSARY

    The Following definitions and abbreviations have been used in this document.

    Organisational

    API American Petroleum Institute

    Client Midwestern Oil & Gas Company Plc

    Consultant Chester Mead Associates Limited

    CMA Chester Mead Associates Limited

    DPR Department of Petroleum Resources

    FME Federal Ministry of Environment

    MWOG Midwestern Oil & Gas Company Plc

    NAPIMS Nigerian Petroleum Investment Manageme

    Services

    NCD Nigerian Content Division

  • 7/31/2019 Basis for Design New

    9/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 9

    Definitions and Abbreviations (continued)

    Technical Terms

    AC Alternating Current

    AG Associated Gas

    AGG Associated Gas Gathering

    ALARP As low as reasonably practicable

    BFD Basis for Design

    B/L Bulkline

    BS&W Base Sediments & Water

    CASHES Community Affairs, Safety, Health, Environment and Security

    CITHP Closed-in Tubing Head Pressure

    CNG Compressed Natural Gas

    cP Centipoise

    CP Cathodic Protection

    CPF Central Processing Facility

    CPP Central Power Plant

    CPU Central Processing Unit

    CCR Central Control Room

    DCS Digital Control System

    D/L Delivery Line

    EIA Environmental Impact Assessment

    EPF Early Production Facility

    ESD Emergency Shutdown

    FEED Front End Engineering & Design

  • 7/31/2019 Basis for Design New

    10/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 10

    FOB Freight on Board

  • 7/31/2019 Basis for Design New

    11/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 11

    Definitions and Abbreviations (continued)

    Technical Terms (contd.)

    F&G Fire and Gas Detection System

    F/L Flowline

    F/S Flowstation

    GGF Group Gathering Facility

    GTL Gas To Liquids

    GOR Gas Oil Ratio (Surface)

    HEMP Hazard and Effects Management Process

    HMI Human Machine Interface

    HP High Pressure

    HSE Health, Safety and Environment

    HV High Voltage

    HVAC Heating, Ventilation and Air Conditioning

    IGF Induced Gas Flotation

    ITC Incoming Termination Chamber

    I/O Input/output

    LACT Lease Automated Custody Transfer

    LCR Local Control Room

    LEL Low explosion limitLER Local Equipment Room

    LPG Liquefied Petroleum Gas

    L/P Line Pipe

    LP Low Pressure

  • 7/31/2019 Basis for Design New

    12/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 12

    LV Low Voltage

    Definitions and Abbreviations (continued)

    Technical Terms (contd.)

    MCS Master Control Station

    MOC Management of Change

    M/F Manifold

    OML Oil Mining Lease

    PAS Protective Alarm System / Process Automation System

    PAGA Public Address and General Alarm

    PES Programmable Electronic Systems

    PFD Process Flow Diagrams

    PID Control Proportional-Integral-Derivative Control

    PSD Process Shutdown

    P/L Pipeline

    RAM Risk Assessment Matrix

    SD Sustainable Development

    SDV Shutdown Valve

    SIMOPS Simultaneous Operations

    SPIR Spare Parts List and Interchangeability RecordSRS Safety Requirement Specifications

    TMR Triple Modular Redundant

    TPI Tilted Plate Interceptor

  • 7/31/2019 Basis for Design New

    13/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 13

    Definitions and Abbreviations (continued)

    Units of Measurements

    BCF, bcf Billion Cubic Feet

    bpd Barrels per Day

    bopd Barrels of Oil per Day

    Bscf Billion Standard Cubic Feet

    bwpd Barrels of Water per Day

    CFM Cubic Feet per Minute

    Deg C Degree Centigrade

    ft Feet

    km Kilometer

    km/h Kilometer per Hour

    kVA Kilovolts Ampere

    m Meter

    M Thousand

    MBD Thousand Barrels per Day

    MM Million

    MMscfd Million Standard Cubic Feet per Day

    MMstb Million Stock Tank Barrels

    MMMscf Billion Standard Cubic Feetpsi Pounds per Square Inch

    ppm Parts Per Million

    scf Standard Cubic Feet

    scf/b Standard Cubic Feet per Barrel

  • 7/31/2019 Basis for Design New

    14/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 14

    USD United States Dollar

  • 7/31/2019 Basis for Design New

    15/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 15

    1.0 I NTRODUCTI ON

    1.1 Purpose

    This document establishes the design criteria, outlines the system design,

    equipment and component design features, as well as the performance

    characteristics consistent with those criteria. The document also creates the

    framework for the instruction documents and construction specifications. The

    contents of this document represent the objectives of the owner, project

    engineers, and consultants in terms of design features, systems functionality, and

    performance.

    1.2 The Umusadege Field

    Umusadege is a marginal field operated by Midwestern Oil and Gas Plc. The field

    is near Kwale in Delta State of Nigeria, and is situated in OML 56. The fields

    current potential is 20 Mbopd, but is currently producing about 9 Mbopd, through

    an early production facility within the field, with the stabilised wet crude routed to

    AGIP via existing GGF and LACT systems. Further development activities are

    planned, which will maintain the fields production at this level. However, the

    production forecasts from the new wells are yet to be reflected in the production

    forecast reference in this BFD

    1.3 The Fields Facilit ies Development Objectives

    The objective is to replace the existing 10 MBD early production facility with a 20

    MBD nominal capacity Central Processing Facility of two trains. Furthermore

    opportunity will be taken at this stage to address and re-design HSE and

    operational deficiencies to bring the fields operations to standard.

    1.4 Overview of The Fields Existing Processing Facilities

    The existing 10 MBD processing facility is a single train one-stage separation EPF,

    consisting of a 3-phase test separator, and 3-phase group separator, and related

    ancillaries. The produced crude is stored in rented tanks, from where it is pumped

    to a delivery pipeline for export through AGIP. The produced water is passed

  • 7/31/2019 Basis for Design New

    16/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 16

    through an oil skimmer tank and disposed to a pit. There is no AG facility and the

    associated gas is currently flared.

  • 7/31/2019 Basis for Design New

    17/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 17

    2.0 KEY CONSI DERATI ONSThe key considerations are presented and summarized below.

    2.1 Mode

    The CPF should be designed as a normally not manned facility. It should be able

    to operate safely under this mode, as well as being able to be shut down safely

    remotely from a PLC based control room. Its start-up has to be locally from the

    field, or remotely only with local permissive from the field.

    2.2 Brown Field Engineering / St rategy Fit

    The design will consider the existing facilities in operation, and equipment already

    ordered, and the extent to which they may be incorporated in the design, without

    prejudice to HSE, operating standards, and undue production deferment.

    2.3 Field Lif e

    The projected field life is 20 years, for which facilities life of 25 years shall be

    considered appropriate.

    2.4 Eff iciency & Optim um Oil Recovery f rom the Process System s

    Number of separation stages will be optimized in the light of surface oil recovery

    and pressure regimes of the wellhead crude. In this respect more than one-stage

    separation will be considered for the higher pressure streams, as that will improve

    their oil recovery.

    2.5 Dry Crude Export

    The design will include infield dehydration, as export will be through a 3 rd party

    facility that is willing to accept only dry crude, BSW 0.5%, and TVP 10 psia at 82o

    F.

  • 7/31/2019 Basis for Design New

    18/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 18

    2.6 Zero Effluent Emission

    The design will aim for total gas utilization and disposal of produced gas and water

    only by means approved by client.

  • 7/31/2019 Basis for Design New

    19/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 19

    3.0 THE EXI STI NG FACI LI TI ES & I NFRASTRUCTURE

    Existing processing facilities in the field are limited to the Early Production Facility

    (EPF) and rented storage tanks. There are no existing gas processing facilities.

    However, some equipment, separators, gas boots, test and production manifolds

    have been procured for the planned facilities upgrade, viz:

    1 No. Group Separator 8 x 40, 20 Mbopd / 7.5 MMscfd / 4 Mbwpd capacity

    (already procured)

    2 Nos. Gas Boot / Water Separator 3.28 x 40 (already procured)

    1 No. 6 Test Manifold

    1 No. 8 Production Manifold

    Also two storage tanks, each of 14.5 Mbbl capacity are currently being installed, and

    more may be installed later.

    3.1 Sur face Facilit ies in Place

    The surface facilities in place and in use are:

    The 10 MBD Early Production Facility

    4 Nos. Wellheads

    8 Nos. Wellhead Flowlines, with one of the flowlines hooked up directly to the

    Crude Storage Tank

    1 No. Field Manifold, complete with Bulk Flowline and Test Line.

    Group Gathering Manifold & Delivery Line

    6 Nos. Rented Crude Storage Tanks

    Crude Oil Metering System

    3.2 The Early Product ion Facilit y

    The Early Production Facility is of an ad-hoc design, of one-stage separation,

    comprising the following:

    1 No. Test Separator, complete with Inlet Manifold with 6 Header and ESD

  • 7/31/2019 Basis for Design New

    20/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 20

    1 No. Group Separator, complete with Inlet Manifold with 8 Header and ESD- One Bulk 3-Phase Separator

    3 Nos. Crude oil transfer pumps

    Oil saver skimmer / drain pit system

    Diesel system

    Instrument air system

    Flare system - complete with flare liquid knock-out vessel

    Service and fresh water system

    Chemical (de-emulsifier) injection system

    Power Generation System, - 1 No. 350 kVA & 1 No. 250 kVA Diesel Engine

    Sets

    Drain Systems, complete with 2 drain water pumps that inject water from the

    storage tanks into the drain pit.

    3.3 The Field I nfr ast ructur e

    The key field infrastructure comprise of the following:

    Custody transfer unit - 14,000 bpd capacity, complete with 6 bidirectionalloop for meter proving

    A new CAT 725 kVA Diesel Engine Set

    Utility air generation, - 2 Compressors of 375 CFM at 120 psi and a self

    support test separator instrument air compressor

    6 Nos. Crude storage tanks of 12,000 barrels total capacity

    Effluent water handling capacity of 2,500 bpd.

  • 7/31/2019 Basis for Design New

    21/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 21

    4.0 DESI GN REQUI REMENTS

    4.1 Design Capacities & Specifications

    The production profile constructed from the fields well streams forecasts is shown

    below, with potential production of 23 Mbpd as peak, declining steadily. The

    forecasts are from the present wells only, excluding future wells. The production

    potentials of the future wells are yet to be established but believed to be

    substantial to fully utilize what would be the installed capacity of the CPF.

    Productio Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

    Forecast Rate 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033

    2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033

    Oil - Mbopd 19.6 17.6 15.8 14.3 12.8 11.6 10.4 9.4 8.4 7.6 6.8 6.1 5.5 5.0 4.5 4.0 3.6 3.3 2.9 2.6 2.4 2.1 1.9

    Gas - MMscfd 3.5 7.9 8.3 10.4 10.4 9.6 8.5 6.9 5.5 4.7 4.3 3.8 3.4 3.1 2.8 2.5 2.3 2.0 1.8 1.6 1.5 1.3 1.2

    Water - Mbwpd 2.3 2.5 2.7 3.0 3.3 3.5 3.2 3.0 2.8 2.5 2.0 1.8 1.5 1.3 1.0 0.9 0.8 0.7 0.7 0.6 0.5 0.5 0.4

    Projected at 10% decline, as supplied forecast did not cover the period

    Field' s Production Forcast

    0.0

    5.0

    10.0

    15.0

    20.0

    25.0

    2 01 1 2 01 2 2 01 3 2 01 4 2 015 20 16 2 01 7 2 01 8 20 19 2 02 0 2 021 20 22 2 02 3 2 02 4 20 25 2 02 6 2 027 2 02 8 2 029 2 03 0 20 31 2 03 2 2 03 3 2 03 4 2 035 20 36

    Field'sProductionProfile ConstructedfromWellStreamsOIlProductionForecast

  • 7/31/2019 Basis for Design New

    22/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 22

    4.2 Well Fluid Characteri stics and Propert ies

    Well Reservoir / Reservo ir Bubble Oil Water Wellhead API Tank Oil

    String Datum Depth Pressure Point Viscosity Viscosity Rsi Boi CITHP FTHP Temp Tank Oil Gas SG Viscosity

    ft ss psia psia cP cP scf/ stb rb/ stb psig psig deg C SG (air = 1) cs

    1 XIIA/ 7882 3,410 108 1.41 0.00 94 1.400 650 230 96 0.83 0.84 0.00

    2 XIIB/ 7950 3,430 110 0.80 0.00 71 1.40 800 300 96 0.85 0.86 0.00

    3 IX/ 7606 2,947 116 0.73 0.00 120 1.40 500 320 130 46.00 0.00 0.00

    5 XVI/ 8145 3,410 372 0.70 0.00 100 1.12 680 420 151 44.00 0.00 0.00

    6 XIIIA/ 8105 3,408 364 0.71 0.00 140 1.12 660 340 145 40.00 0.00 0.00

    7 XIV/ 8237 3,522 570 0.64 0.00 127 1.12 780 410 140 44.00 0.00 0.00

    8 XIIC/ 8005 3,435 110 0.69 0.00 132 1.12 800 640 135 40.00 0.00 0.00

    UMU 7L

    Subsurface Conditions Wellhead / Surface Flow Conditions

    UMU 1S

    UMU 1L

    UMU 5L

    UMU 6L

    UMU 6S

    SerialN

    o.

    UMU 7S

    4.3 Export Crude Specification

    Reid Vapor Pressure (RVP) 10.0 psia

    True Vapor Pressure (TVP) 10.5 psia @ maximum storage temperature

    Basic sediment and water 0.5 volume percent

    Salt content 35 lb/kstb

    Storage Temperature 80 - 82 F

  • 7/31/2019 Basis for Design New

    23/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 23

    4.4 Produced Eff luent Water Specification

    Maximum instantaneous dispersed oil content of produced water discharges will

    be 10ppm.

    4.5 Characteri sed Well Fluid Data

    Component Mole % Specificgravity

    Molecular weight NBP (F)

    Nitrogen 0.19

    Carbon dioxide 0.14

    Hydrogen sulphide 0.00

    Methane 8.71

    Ethane 3.56Propane 7.34

    i-Butane 5.97

    n-Butane 6.80

    i-Pentane 5.19

    n-Pentane 3.61

    Hexanes 5.53

    Heptanes Plus 5.32 0.7227 96 TBD

    Octane Plus 8.28 0.7457 107 TBD

    Nonane 5.17 0.7648 121 TBD

    Decane 4.69 0.7788 134 TBD

    Undecane 3.18 0.7898 147 TBD

    Dodecane 2.60 0.8008 161 TBD

    Tridecane 2.44 0.8118 175 TBDTetradecane 2.21 0.8228 190 TBD

    Pentadecane 2.31 0.8328 206 TBD

    Hexadecane 1.92 0.8398 222 TBD

    Heptadecane 2.19 0.8478 237 TBD

    Octadecane 1.22 0.8528 251 TBD

    Nonadecane 1.19 0.8578 263 TBD

    Eicosane 0.91 0.8628 275 TBD

    Uneicosane 0.84 0.8679 291 TBD

    Doeicosane 0.80 0.8729 305 TBD

    Trieicosane 0.73 0.8779 318 TBD

    Tetraeicosane 0.60 0.8819 331 TBD

    Pentaeicosane 0.53 0.8859 345 TBD

    Hexaeicosane 0.46 0.8899 359 TBD

    Heptaeicosane 0.40 0.8939 374 TBDOctaeicosane 0.35 0.8969 388 TBD

    Nonaeicosane 0.30 0.8999 402 TBD

    Triacontane plus 4.32 0.9506 544 TBD

    Total 100

  • 7/31/2019 Basis for Design New

    24/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 24

    4.6 Form ation Water Analysis

    Source

    Umusadege6 Umusadege4(BHS @ 7,965 ft)

    Date Sampled 8th February 2011 2nd March 2007

    SG 1.0104 0.9980 @ 60oF

    pH 7.83 @ 80oF 7.96 @ 20oC

    Conductivity, s/cm @ 80oF 8,403

    Resistivity, ohm.metre @60oF

    5.900

    Total Dissolved Solids, mg/l 4,820 1,380

    Total Salinity, mg/l 4,250Total Alkalinity, mg/l 665

    Hydrogen Sulphide

    CATI ONS

    Potassium, mg/l 23

    Sodium, mg/l 1,727 295

    Calcium, mg/l 16.5 145

    Magnesium, mg/l 3.7 3.6

    Barium, mg/l 45.0 1.2

    Iron, mg/l 0.4 0.8

    Strontium, mg/l 0.7

    ANI ONS

    Chloride, mg/l 2,303 460

    Sulphate, mg/l 35 8.5

    Carbonate, mg/l 25 Nil

    Bicarbonate, mg/l 640 445

    Hydroxide, mg/l Nil Nil

    4.7 Production Start- Up

    The CPF facilities will be designed to allow facility startup using the emergency

    (diesel) generator system, as black start.

    Facility operability during turn-down to level of 20% of design rates is anticipated.

  • 7/31/2019 Basis for Design New

    25/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 25

    4.8 Erosion Velocity & Noise

    The optimum diameter for the interconnecting lines between Inlet headers and

    separators will be determined to ensure that flow velocities are within erosion

    limits and noise avoided.

    4.9 Facilit y Standards

    This is necessary only in so far as is necessary to ensure variety control as well as

    the stocking and inter-changeability of spare parts.

    4.10 Design Simu lation Soft w are

    The process design software shall be: HYSYS, Pipe Phase, Pipe Sim and Flare Net

    while the facility layout shall be designed with AUTOPLANT.

    Simulation data and results of analysis will be included in the design reports.

  • 7/31/2019 Basis for Design New

    26/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 26

    5.0 THE CENTRAL PROCESSI NG FACI LI TYThe base case concept for the Central Processing Facility is a 2 x 20 MBD capacity

    processing facility as shown in the PFD below, and will be developed with a

    provision for possible future tie-ins of additional separator(s). The 2-train system is

    driven by the objective to minimize production deferment through SIMOPS on the

    facilities installation, as well as optimal utilization of equipment already procured.

    Other related options are considered and analysed in the concept selection study

    report (with Document No. CMA/UMUCPF/MDR-GEN/DOC/004).

    The CPF systems include the following facilities: Oil processing and export facilities.

    Well test facilities.

    Utility and support systems operation.

    Produced water treatment facilities.

    5.1 Facilit ies / Process Descript ion

    The oil processing involves two trains and 3-phase separation. The trains

    configuration and installation have been planned to minimize production

    deferment at transition. In this respect, the first train, Train-1, will be designed

    and installed to start on one-stage LP separation, with provision to use mobile test

    unit for well testing (to be evaluated), while the second train, Train-2, will be

    designed and installed with the full complement of multi-stage separation,

    including a test separator. The multi-stage separation will start with two stages,

    with provision for future XHP / XXHP installation as will be dictated by the pressure

    regimes based on input information provided on well 9.

    The design for the XHP / XXHP integration is outside the current scope of work,

    and will be implemented if and when the time comes

    Crude processing will be segregated between the two trains as follows: -

    higher pressure wells to be processed via the 2-stage separation (HP + LP),

  • 7/31/2019 Basis for Design New

    27/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 27

    while the lower pressure wells will be processes through the one-stage

    separation (LP).

    Piping will be configured for flexibility to flow any well through the HP train or

    LP train, as well as connectivity between the two trains.

    The test separator, though will be installed in Train-2, will serve both trains. In

    addition valving will be designed for flexibility to use the test separator as bulk

    HP separator for Train-1.

    Figure 1: Train 1 Flow Scheme

  • 7/31/2019 Basis for Design New

    28/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 28

    Figure 2: Train 1 & 2 Flow Scheme

    Both trains will enable produced oil to be routed through three cascade tanks each

    of size 1,000 barrels before export through the LACT, or transfer to storage tanks

    with cumulative capacity of 100,000 barrels for temporary if and when the need

    arises.

    A heater currently available has been converted to function as an LP separator.

    All separation stages are placed as three phase separators, enabling water to be

    removed from each stage as well as the gas boots, for processing in a TPI facility.

    The TPI produced water is anticipated to meet DPR specifications of 10 ppm oil in

  • 7/31/2019 Basis for Design New

    29/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 29

    water before disposal in a water injection well, whose design is intended to be

    covered in a separate contract.

    In addition, given the fact that the produced water is planned to be disposed by

    injecting it into well(s), the need for treating to the high quality of 10 ppm needs

    to be discussed and confirmed with the DPR, to avoid the cost of achieving

    specifications that are unnecessary.

    The produced gas will be used as fuel gas for the CPF gas engine generator, with

    the excess available for external utilization.

    For the excess gas handling, five potential options have been compiled for

    evaluation, i.e.:

    1. LPG recovery + power generated with surplus methane stream,

    2. Power generated with whole stream of gas for export to National Grid,

    3. CNG bottles manufactured by third parties,

    4. Produced gas sold at CPF fence,

    5. Gas injected into Umusadege reservoirs. This last option is only included only

    for completeness of the records and not considered to be a serious option, as

    DPR will not approve gas disposal by re-injection.

    Any or all of the options will be examined for potential uptake by third party off-

    takes or MWOG/partners, to enable a specific recommendation. This review will be

    carried out as part of the detailed engineering scope and will be reported

    separately.

    5.2 Design & Operat ing Philosophy

    The CPF will be normally not manned

  • 7/31/2019 Basis for Design New

    30/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 30

    It should be able to operate safely under this mode, as well as being able to be

    shut down safely remotely from a local PLC based control room. The PLC will beequipped with HMI, and SCADA capability.

    Its start-up has to be locally from the field, or remotely from the control room only

    with local permissives from the field.

    TThhee operating modes outlined in this philosophy shall be developed during

    detailed engineering.

    5.2.1 The I nlet and I ntermediate / ESD Valves Manifold

    The inlet manifold will operate in bulk and test mode and both modes can be

    operated concurrently. The bulk mode will be the normal production mode in

    which wells with the same pressure regime are switched to the same header

    where they are commingled. From the header, they flow into a targeted (HP

    or LP) or in some cases test separator (when the test is being operated in

    bulk mode).

    The test mode will be the mode in which a well is put under test to determine

    its production capacity and basic composition such as GOR and BS & W. In

    this mode, the well under test will be switched to the test headers from

    where it flows into the test separator.

    The inlet headers are process lines between the ligaments and the inlet

    separators. Each well and also each inlet header will have individual

    shutdown valves, which is used primarily to isolate the ligaments (wells and

    flow lines) from the inlet separators during an operational or emergency

    shutdown. On each bypass line is a 2 inch manual globe valve. The bypass

    line is used primarily during start-up to gradually pressurize the flow station

    and the instrument fuel gas header by the use of the 2 inch globe valve.

    The flow station is first pressurized before each header ESD valve can be

    opened for the following reasons:-

    Enable the lighting of the flare.

    Prevent a pressure shock (hammer effect) on the facility.

    Prevent possible damage of the header ESD valves seat because of high

    differential pressure across them.

  • 7/31/2019 Basis for Design New

    31/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 31

    Allow a reset of the pneumatic safeguarding panel.

    Each header ESD valve will consist of a ball valve with a spring return

    actuator. A pneumatic pilot operated three-way valve operates the actuator.

    The pilot signal on the three-way valve will be controlled by a pneumatic

    relay based safeguarding system.

    Pressure gauges are installed on each header to measure the inlet pressure.

    5.2.2 The Test Separator

    The test separator operates as 3-phase. It will have two operating modes

    (test and bulk).

    When in test mode, any of the wells under test is routed to the test

    separator.

    In the bulk mode, it will be used for normal production and operates like any

    of the other two separators (LP & HP). In this mode, all producing wells

    within the same pressure regimes are switched manually through their

    individual ligament valves into the test header. From the test header they

    flow into the test separator.

    5.2.3 The HP Separator

    The HP Separator will operate between 220 to 240 psig. All producing wells

    within the same pressure regimes are switched manually through their

    individual ligament valves into the HP header. From the HP header they flow

    into the HP separator.

    In the separator, liquid and gas are separated. The flashed gas exits though

    the gas outlet, while the oil and water stream is routed to the LP separator.

    5.2.4 The LP Separator

    The LP separator will operate between 30 to 40 psig. All producing wells

    within the same pressure regimes are switched manually through their

    individual ligament valves into the LP header. From the LP header they flow

    into the LP separator. The oil, water and gas are separated. The flashed

    gas exits though the gas outlet, while the oil is routed to the gas boot / surge

    vessel.

  • 7/31/2019 Basis for Design New

    32/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 32

    The water is routed to the water treatment facility.

    5.2.5 The Gas Boot

    The gas boot is a three phase degassing / stabilizing unit, also enabling

    additional refinement of de-oiled water to be routed to the water treatment

    facility for further processing.

    Final separation of gas and liquid occurs in both cases, the flash gas exits

    through an outlet line and flows into the flare knock-out vessel. The liquid

    (oil) exits through the outlet line where it flows by gravity into the cascade

    tanks, from where it is pumped to the LACT.

    Details of pump control will be developed with vendor data during detailed

    engineering. Pump discharge pressure floats on the pipeline operation

    pressure, which is a function of the liquid export flow rate and the other

    users of the pipeline system.

    5.3 The Crude Export Pum ps

    Centrifugal pumps, with variable speed drive mechanism have been procured to

    be used. These pumps are already on the site and will be evaluated to assure

    they fit the required duty.

    5.4 The Closed Drain System

    All vessel drains are routed to the closed drain sump tank. Recovered oil is

    pumped back to the crude oil export system while removed water is routed for

    treatment. Open and closed drainage systems shall be included. Open drains will

    channel rain water and non-hazardous fluids to the open drain pit via the open

    drain header. Closed drains handling oil contaminated and hazardous liquids are

    routed to the closed drain tank via the closed drain header.

    5.5 Gas Handling

    Associated gas will be routed to an AG solution facility to enable value addition for

    sales. Options that may be considered for the AG solution facility include

    processing for direct sales, or for LPG extraction and power generation, for own

    use or for sale.

  • 7/31/2019 Basis for Design New

    33/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 33

    A fuel gas system shall be provided for supply of fuel gas to the gas turbines. The

    fuel gas system shall be sized to supply all future equipment required for theDesign Case. Supply pressure will be based on selected gas engine generator.

    A purge gas system shall be provided for purging and supply to flare pilots and

    ignition system. Critical control valves shall be spared to ensure availability of

    supply.

    5.6 Flare System

    In line with DPR regulations, routine process flaring will not be permitted.

    However a full facility flare will be included for use under emergency conditions.The existing flare will be evaluated to determine capacity for the forecast

    production. A flare header / flare system will be provided to collect and safely

    dispose of produced hydrocarbon gases. As a minimum, the system will consist of

    flare headers, a flare knockout drum, and a continuously ignited pilot flare. In

    addition, the system will be designed to safely and continuously flare the produced

    gas capacity of the CPF and to depressurize all of the production flow lines in the

    shortest possible practicable time. Discharges from pressure relief valves and

    other hydrocarbon streams as required by the CPF Facility Specifications will be

    routed to the flare system. The flare system will be equipped with meters to

    measure flare volumes to within an accuracy of 2%.

    5.7 Water Treatment

    Produced water will be routed to a TPI (Tilted Plate Interceptor) Facility ahead of

    disposal. The ultimate disposal route will be via re-injection into an aquifer.

    The TPI produced water shall be made to meet DPR specifications of 10 ppm oil in

    water before disposal by injection into an aquifer. Before the installation of the

    water injection plant, water will be disposed off in the existing pond.

    The design of the injection facility is outside the scope of this Basis for Design,

    and will be covered in a separate contract.

    5.8 Storage Tanks

    The tables below summarise the tanks that will be installed:

  • 7/31/2019 Basis for Design New

    34/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 34

    Table 1 : Crude Oil Tanks

    Tank Designation Capacit y

    Processed (dead) Crude 2 x 14,500 barrels

    Processed (dead) Crude 2 x 35,000 barrels (Anticipated)

    Crude Settlement 3 x 1,000 bbl Cascade Tanks

    Table 2: Other Tanks

    Tank Designat ion Capacit y

    Produced Water 1,000 bbl as part of re-injection phase.

    Firewater 5,000 barrels

    Chemical (one per chemical type) TBD

    Diesel 500 barrels (10 days endurance)

    The crude oil tanks will be fitted with a stripping system to permit removal of

    water that has settled out of the crude oil. The storage system will be capable of

    receiving stabilized crude from the production facilities. The offloading system will

    be capable of discharging at a rate and pressure such that it can flow into the GGF.Fiscal metering of the exported crude will be based upon the use of the existing

    LACT system at GGF since the existing facility is in-place and is reliable. The tank

    shall be fitted with local flow meters (or gauge).

    The facility and associated systems will be designed to remain on site for entire

    design life and with minimal maintenance and repair (e.g., no major steel, coating,

    and piping or equipment renewals) which might result in interruption of production

    operations. This will be achieved mainly from material selection.

    There will an automated and manual level control system on each tank. Motorised

    valves will be interlocked to allow one tank filling at a time. Two 14,500 barrel

    crude oil tanks shall be used for storage and settlement. Additional two 35,000

    barrels capacity are anticipated for future expansion.

    The storage tank inlet motorized valves are controlled by the Level Switch High on

    the storage tank to prevent overfilling of the crude oil. The motorized valves are

    also at interlock with each other with the philosophy that only one tank can be

  • 7/31/2019 Basis for Design New

    35/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 35

    filled at a time. The closure of one motorized valve gives an advent of the opening

    of the next motorized valve on priority. The Level Switch Low on the tank controlthe motorized valve on the outlet section of the tank in safeguarding the operation

    of the pumps.

    The final logic of the tank filling operation shall be done by the detailed

    engineering contractor which shall be implemented by the Vendor of the

    Programmable Logic Controller.

    5.9 Diesel Storage and Dispensing

    Diesel is required for the emergency power supply system. Specific care will bemade to ensure that the supplied quality meets equipment requirements and that

    adulterated products are not supplied.

    5.10 Service & Fresh Wat er System

    Potable water system will be included for use in engine cooling system as well as

    fire water storage. The borehole supply pump will be powered by electric motor.

    5.11 Chemical I nj ect ion System

    Chemical Injection points will be included where needed. Such chemicals as

    corrosion and scale inhibitors are potentially required.

    5.12 Pneumatic Control & Automation System

    Dry instrument air will be provided to the process facilities. CMA will determine

    the required pressure and capacity of the instrument air and provide 2 or 1 electric

    motor driven air compressors. CMA shall consider the cooling demands of

    generator when assessing the instrument air demand. An air filtration (leaning)regulator system will be provided.

    5.13 Eart hing System

    An earth ring main will be designed to provide earthing source for all the facilities

  • 7/31/2019 Basis for Design New

    36/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 36

    5.14 Cathodic Protect ion System

    Cathodic protection will be provided for buried flowlines & delivery line and also

    for vessels and storage tanks.

  • 7/31/2019 Basis for Design New

    37/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 37

    6.0 MWOG PROCURED EQUI PMENT

    The following equipment items have been procured and, as much as is feasible, will

    be included in the design.

    Table 1 : Pre-Ordered Equipment I tem s

    Tag Dimensions MAWP Design

    Temperature

    Test Separator 1.1m by 3.1m 655 psig 200OF

    L.P Separator 8ft OD x 40 ft s/s 50 psig 140F

    H.P Separator 5ft OD x 20ft s/s 740 psig 200F

    Gas Boot 1 m x 14m 20 psig 140F

    Test Manifold 6 in header 1,400 psig 120OF

    Production

    Manifold

    8 in header 1,400 psig 120OF

    Storage Tanks 65ft dia x 24 ft 5 psig Ambient

    Pump 67.6 HP

    (Rating)

    187 psi

    (Differential)

    Technical information on these items of equipment are available and will be applied

    in the design checks.

  • 7/31/2019 Basis for Design New

    38/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 38

    7.0 CI VI L WORKSThe scope of civil works covers the following aspects:

    1. Determine the facility area including fence lines, roads and footprints of facility

    components.

    This shall be based on survey maps and as-built drawings provided by MWOG,

    which shall be verified during site visits.

    2.Appraise existing drainage lines and reconcile with new routing required.

    3. The topography of the new CPF area shall be reviewed to ascertain the extent of

    cut and fill that will be required.

    4. Output from topography review shall form basis for recommending heights of

    supporting structures; e.g. pipe supports, tanks, vessels and gas boots

    foundations, steel columns, and walkways.

    5. Detailed design of all applicable foundations including oil tank foundations,

    control room, buildings, skids, bundwalls .

    Results of the borehole sampling will be reflected in the design work and shall

    form the basis of foundation design.

    6. Detailed instructions on materials to be used, method of application, expected

    results or outputs and technical development for constructing the works stated in

    item 5 shall be adequately provided.

    7. Recommend any other structural component required for a resilient structure;

    e.g. platforms, walkways etc.

    8. The Construction Scope of Work. These items relating to the execution and

    completion of construction works shall be quantified and priced as input to the

    project cost estimate. It is expected that any modifications and change orders

    from the client shall be incorporated as civil works progress, if agreed and

    accepted by parties.

  • 7/31/2019 Basis for Design New

    39/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 39

    8.0 I NSTRUMENTATI ON

    Overall control of the liquid production system is through the Process Automation

    System (PAS). This extends over the pump stations, tank farm and the CPF. The

    facility will be normally not manned. Normal monitoring of plant performance,

    verification of set-points and starting/stopping of equipment, etc, will take place

    from the Control Centre located at base.

    TThhee Flowstation oil production system will be maintained in stable operation by a

    number of factors, including manually set flowlines choke valves that will maintain

    the overall station production

    8.1 Test Separator I nstrum entati on

    The test separator instrumentation will be designed to provide a means to initiate

    and carry out well testing locally, and in line with API 14C will have the following

    features:

    Back Pressure Control

    High Pressure Safeguarding

    Level Control

    Low & High Level Safeguarding

    Level & Pressure Measurement

    Gas Outlet Measurement

    Liquid Outlet Measurements

    Temperature Measurement

    8.1.1 Back Pressure Cont rol

    The test separator will be designed to operate at either LP or HP separator

    pressure, and in test or bulk mode. Hence, it will not have a dedicated back

    pressure control system, but will share with that of the LP separator (when in

    LP mode) or the HP separator (when in HP mode). This sharing shall be

    implemented by connecting the test separator gas outlet line to both the LP

    or HP header where their back pressure control systems are installed.

    The back pressure control will comprise a pneumatic pressure controller and

    pressure control valve. The pressure controller measures the process

  • 7/31/2019 Basis for Design New

    40/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 40

    pressure and produces a standard pneumatic output signal, which drives a

    back pressure control valve.

    8.1.2 Level Control

    The level control will comprise the following:

    a. Displacer type controller / transmitter

    b. Level control valve

    c. Test / Bulk mode selector switch

    d. Level Measurement

    Displacer Type Contr oller / Transmit ter

    The displacer type pneumatic transmitter receives change in fluid level

    through change in buoyant force exerted by the fluid on the sensor

    displacer, and consequently produces a standard pneumatic output signal

    that drives the control valve.

    Test / Bulk Mode Selector Sw it ch

    The liquid outlets will be divided into two, - a 2 and a 4 line, with a

    level control valve installed in each line, with both lines recombined into a

    4 line downstream of the control valves. The required liquid outlet line(2 for test mode, and 4 for bulk mode) is selected by manually opening

    of the ball valves upstream and downstream of the level control valve,

    while the control valve selection is by use of a manual pneumatic switch.

    The pneumatic selector switch connects the standard output signal of the

    level transmitter / controller to the selected valve.

    The liquid outlet will be divided into oil & water to achieve metering

    separately.

    8.1.3 Level Measurement

    The only level indication will be that directly on the vessel by the use of sight

    glass.

    There will be no direct level measurement and display on the test separator

    except level measurement by the displacer type transmitter / controller used

  • 7/31/2019 Basis for Design New

    41/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 41

    in the level control loop. The level control loop will be primarily field located

    with no form of indication.

    8.1.4 Low and High Level Safeguarding

    The test separator will be equipped with a duplex type transmitter and

    controller that will provide dual function of level control and high / low level

    safeguarding.

    The safeguarding instrumentation will consist of high and low level displacer

    type pneumatic switches, connected to a pneumatic relay panel used for

    plant safeguarding. The safeguarding logic is implemented in the relay panel

    such that for a high level in bulk mode, all the inlet valves and the liquid

    outlet valve are closed. In the test mode, the inlet valve applicable will be

    that of the well on test. In the event of low level, the liquid outlet valve will

    be forced down.

    Other safeguarding functions will be conducted in accordance with the

    flowstations cause and effects diagrams

    8.1.5 High Pressure Safeguarding

    The test separator high pressure safeguarding will comprise a high pressure

    pneumatic switch that will initiate the shutdown. When the pressure switch

    senses a high pressure, it sends a signal to the pneumatic safeguarding relay

    panel, where the shutdown logic is implemented in accordance with the

    cause & effects diagram.

    The objective is to close the inlet shutdown valve to the separator so as to

    prevent further entry of hydrocarbon.

    8.1.6 Pressure Measurement

    All pressure measurement will be by pressure gauges only.

    8.1.7 Gas Out let Flow Measurem ent

    A senior Daniel orifice or ultrasonic meter will be installed to measure all

    outlet gas rates.

  • 7/31/2019 Basis for Design New

    42/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 42

    8.1.8 Liquid Out let Flow Measurem ent

    Oil & water will be metered separately. The oil will be measured usingturbine meters for accuracy that will be in line with DPR requirement.

    8.1.9 Temperature Measurement

    All temperature measurements will be by temperature gauges only.

    8.2 HP Separator I nstrum entati on

    The instrumentation and safeguarding functions on the HP separator will be

    similar to the test separator, except that there will be no liquid measurement, -

    only gas.

    Similar to the test separator, it will have a duplex type level instrument, which will

    provide both level control and high high level safeguarding function.

    8.3 LP Separator I nstrum entat ion

    Also, the instrumentation and safeguarding functions on the HP separator will be

    similar to the test separator, except that there will be no liquid measurement, -

    only gas.

    Similar to the test separator, it will have a duplex type level instrument, which will

    provide both level control and high high level safeguarding function.

    8.4 Crude Oil Export Pump I nstrum entati on

    The crude oil pump will have a pneumatic governor, which will be used to vary the

    speed of the pump gas engine driver as part of the level control system of the

    surge vessel. When the level in the surge vessel goes high, the speeds of the

    pumps are set to maximum by the surge vessel controller. At low level, the

    pumps are set to minimum speed. In the event that the level drops further, the

    recirculation valve begins to open so as to recycle the liquid to the surge vessel.

    Pressure gauges will be installed on the pump suction and discharge lines.

  • 7/31/2019 Basis for Design New

    43/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 43

    8.5 Flare Knockout Vessel I nstrum entati on

    The knockout vessel will have four level switches. Three of the switches will be

    electric, while the fourth will be pneumatic two of the electric switches will be used

    for level control, while the third will be used to shutdown the pump on low low

    level detection. The pneumatic switch will be connected to the pneumatic relay

    panel for shutdown on high high level in the flare knockout vessel.

    The level control system for the pump will consist of a stand-alone electric relay

    logic control panel.

  • 7/31/2019 Basis for Design New

    44/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 44

    9.0 EQUI PMENT LAYOUT

    The facility equipment shall be laid out to fit within the CPF land boundary, bearing

    in mind the limitations created by the position of the new storage tanks under

    construction and right of way.

    9.1 AREA CLASSI FI CATI ON

    Adequate safe distances for all equipment will be considered in accordance with

    area classification requirements that will be firmed up at detail design stage. The

    layout shows access roads with provision for drainage lines. Inter-connecting

    piping from the process area to storage tanks will be buried at road-crossings; i.e.

    piping at other areas will be above ground.

    The allocation of functional spaces in the layout was based on the following

    parameters:

    Flare zone: North-West, due to prevailing wind directions

    Utility area: North, in the proximity of the administration building, considered

    as a safe area

    Tank farm: South-West, in the largest free space to accommodate tanks

    Process area: South-East, in near proximity to in-coming lines and inlet

    manifolds

    Fencing: Perimeter of property, and seal-off of restricted areas.

    Accesses: Gates to control service accesses into restricted areas

    A conceptual layout is included as Appendix to this document.

    9.2 LAYOUT CONSI DERATI ONS

    1.All equipment will be placed optimally, satisfying the optimum orientation for all

    processes, utility and instrument equipment items.

    2. The cost of construction will be minimized, e.g. by adopting a layout that gives

    the shortest run of connecting piping between equipment.

    3. Sufficient working space and headroom will be provided to allow easy access to

    equipment.

  • 7/31/2019 Basis for Design New

    45/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 45

    4. Equipment such as pumps that require dismantling for maintenance will be

    placed under rain/sun cover.5. Equipment will be located so that it can be conveniently tied in with any future

    expansion of the process, e.g. future gas off-take.

    6.Additional space will be left along the pipe racks to accommodate future piping

    needs.

    7. The gas flare that is included for emergency use will be located as far as

    possible from the process vessels, in line with safe area classification

    requirements.

    8. The EPF will be tied-in to the new storage tanks via temporary transfer lines that

    would be disconnected before commissioning the CPF.

    9. The general plant arrangement and orientation will be consistent with the

    prevailing atmospheric and site conditions such as wind direction as well as

    hazardous area requirements.

    10.Adequate allowance will be left for drainage and fire fighting facilities. Access

    ways will be provided within the facility for access to items that require removal

    for off-site repair.

  • 7/31/2019 Basis for Design New

    46/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 46

    10.0 FI RE PROTECTI ON

    10.1 Fire Water

    Fire water storage tank shall be installed with a capacity suitable to meet

    firefighting needs for a minimum period of four hours, as determined by the

    period for arrival of firefighting support equipment from nearby locations.

    A diesel fuel pump and electrical Jockey pump are included. The critical areas shall

    be covered with a pressurized ring main that feeds a series of hydrants each with

    hoses located at strategic positions in the CPF.

    10.2 Fire and Gas Detection System

    A Fire and Gas Detection System shall consist of three parts:

    a) Detection

    b) Control Logic

    c)Active Protection

    Fire and Gas Detection devices and Manual Call Points shall be provided.

    The System shall provide voting capability (2oo3 and where there is failure in one

    of the applicable detectors, it recourses to 1oo2) where multiple detectors have

    been installed to minimize nuisance shutdowns. For a large area with multiple

    zones (without a barrier), cross zone voting within adjacent zones may be used.

    Process shutdown actions initiated by the Fire and Gas Detection System shall be

    executed via interlocks to the ESD/PSD systems. Other actions (e.g., release of

    fire suppressant systems, fire water pump starts, etc.) may be executed directly

    from the F&G System.

    The Fire and Gas Detection System shall be designed so that it can be functionally

    tested and individual detectors can be calibrated without affecting CPF processes

    and equipment operation.

    The system configuration for F&G Systems shall comprise centrally located logic

    solvers in the control room and either centrally or remotely located I/O systems.

  • 7/31/2019 Basis for Design New

    47/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 47

    Further details on the proposed fire protection system are contained in a separate

    document in the Appendix.

    11.0 ELECTRI CAL DESI GN BASI S

    Power will be generated using gas engine generators fired by the produced gas. A

    diesel engine set will be retained for emergency power. Furthermore, solar power

    will also be considered as that will have prime use for critical installation such as the

    CP system or the telemetry system for communications between the wells and the

    CPF.

    11.1 Pow er Generati on

    Power will be generated on site with two adequately sized Gas engine generator

    operated in an N+1 sparing philosophy and sized to cater for 100% total plant

    peak load, covering the CPF, GGF, Campsite, and Satellites. The required for

    future facilities, e.g. water injection plant and AG solution facility will be addressed

    separately, when the time comes.

    In addition to the gas engine generators, a diesel engine generator shall be

    provided for emergency service and cold start of the CPF. The emergencygenerator shall be adequately sized to supply power for vital and agreed essential

    services and to start and run a minimum of one oil export pump.

    The vital services refer to those services which, when they fail in operation or

    when called upon, can cause an unsafe condition of the process and / or electrical

    installation, jeopardize life, or cause major damage to the installation; while the

    essential services refer to those that when they fail in operation or when called

    upon, will affect the continuity, quality or quantity of the product.

    The emergency and critical loads will be defined and agreed, and reflected in the

    load list. The load list will form the basis for load segregation, as well as sizing

    main equipment such as:

    1. Main gas engine generators

    2. Emergency diesel generators

    3. HV switchboards

    4. LV switchboards

    5. Protective circuit breakers etc.

  • 7/31/2019 Basis for Design New

    48/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 48

    11.2 UPS

    AC and DC uninterruptible power supply shall be provided complete with battery

    banks for the vital loads at the CPF and outlying flowstations. The uninterruptible

    power supplies shall use Nickel Cadmium batteries. Each power supply shall be

    equipped with two 100% duty chargers capable of both charging batteries and

    supporting the maximum load. All batteries shall be 2 x 100% sized, and capable

    of supporting their for 30 minutes.

    11.3 Pow er Transmission & Dist ribut ion

    Power transmission will not be required because the low voltage distribution can

    be used.

    Main power distribution within the facility will be at 415/220 volt, 50Hz, TPN

    (Triple Phase and Neutral) in accordance with local power authority (PHCN)

    standard distribution. Power will be distributed to electrical equipment by

    adequately sized cables via cable trays or trench.

    Adequate protections will be provided to electrical equipment and personnel on

    site through a well-designed earthing network that will tie into the existing

    earthing system. Other deliverables will be generated in line with the approved

    MDR.

  • 7/31/2019 Basis for Design New

    49/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 49

    12.0 HSE/ SD REQUI REMENTSHSE issues are those which result from the interaction of the proposed facility with

    the environment and safety related issues that need to be addressed as part of

    Human Factors Engineering in design and also, during project implementation in the

    Umusadege field. CMAs CASHES Plan has been consistently applied in our work

    execution, enabling safe working practices and minimum impact on the environment

    or damage to human life. Documents created as part of the design activities will

    reflect these perspectives.

    12.1 Safety Considerati ons

    The general approach adopted during design development and the requirement

    for further design stages will identify and eliminate hazards as an integral part of

    the design process.

    12.2 Environmental Considerations

    The PMT and HSE regulatory teams will work closely together to assure

    environmental issues are considered in the design process, following the

    applicable regulations and guidelines listed in section 15.2. An Environmental

    Impact Assessment study has been conducted on the facility and all its

    recommendations shall be implemented. All new facilities will be installed under

    the existing MWOG operating permit.

    12.3 Securi t y Considerations

    CMA / MWOG are committed to a dynamic, visible security program, which

    addresses the threats in the major following areas:

    Protection of assets

    Office and Residential Security

    Personnel Transportation/Travel

    Communication/Information Security

  • 7/31/2019 Basis for Design New

    50/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 50

    12.4 Risk Assessment and Managem ent

    The CPF project has a number of inherent risks and uncertainties. These will range

    from sub-surface uncertainties that may affect the production forecast, to

    technical and commercial risks, but also include a number of socio-political risks,

    especially during the project execution phase at Umusadege. A risk register has

    been compiled with 80 items listed. Mitigation factors will be developed and

    implemented.

    This project will follow standard guidelines for Engineering Managed Modifications

    (EMM) as part of the process for managing any associated risk. A Design Risk

    Assessment shall be conducted before the detailed design is concluded.

    As part of risk assessment, a specific perspective is the need to carry out a

    SIMOPS exercise during detailed design. Consideration will be given to

    simultaneous operation of the EPF in parallel with the installation of the CPF. A

    SIMOPS Study will be carried out to assess the risks and develop the right

    approach for risk mitigation during the installation CPF stage.

  • 7/31/2019 Basis for Design New

    51/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 51

    13.0 ASSET MANAGEMENT

    13.1 Operat ing Philosophies

    Operating philosophy envisages that the facility is not normally manned.

    Maintenance will aim at preventive maintenance through a computerized

    management system. Other features include the following:

    a. Field production will continue un-hindered during the installation of the

    expanded facility. Aspects include placement and tie-in of processing vessels

    and piping works in tandem with systems in operation.

    b. Considering that the Umusadege is a marginal field, sparing of equipment

    items will be minimized. Also for this reason, high integrity systems will be

    included for process safety control. Moderate level of automation for process

    control is desired, with process control equipment placed in a purpose-built

    office.

    c. The facility will operate 365 days a year with shut-down only in the event of

    an emergency procedure or for statutory inspections on relief systems and

    vessel internals.

    13.2 Asset Reference Plan

    The ARP that will be created by others at the end of detailed design will aim to

    utilize the Operations Readiness and Assurance report to:

    Define the boundaries of the asset.

    Optimize asset planning and operations with respect to previously completed

    sub-surface studies, facilities design and equipment selection and

    specifications Integrate business process strategies,

    All these actions are aimed at optimizing value of the asset for benefit of MWOG,

    its partners, and other stakeholders.

  • 7/31/2019 Basis for Design New

    52/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 52

    14.0 MANAGEMENT OF CHANGE & QUALI TY

    14.1 Design Change

    All changes that interface with MWOG operations will be captured, using the CMA

    Management of Change (MOC) process. This would ensure that potential changes

    are properly assessed, approved and documented so that risks remain at

    acceptable levels while project objectives are met. All necessary approvals will be

    secured before any deviation / change is carried out.

    14.2 Qualit y Assurance and Cont rol Requirem ents

    CMAs Quality Assurance process will be applied through the concept of

    competence in work disciplines and the attitude and commitment that mandates

    all staff to follow best practices.

  • 7/31/2019 Basis for Design New

    53/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 53

    15.0 STATUTORY AND REGULATORY COMPLI ANCE

    This design shall follow the guidelines and standards set by Midwestern Oil and Gas,

    Department of Petroleum Resources (DPR) and International Codes of Practice as

    applicable in the oil industry. Safety standards shall follow the regulations from the

    Occupational Safety and Health Act (OSHA) and other Nigerian regulations.

    15.1 Nigerian Cont ent

    The work shall be done in accordance with the Nigerian Content Development

    Regulation passed by the National Assembly in 2010. Nigerian contractors will

    fabricate and install, in most cases using Nigerian personnel.

    15.2 Regulatory Considerati ons

    The Umusadege project will be developed in compliance with all applicable

    Nigerian laws and regulations. The project will also be guided by Scope of work

    specifications and International Codes and standards referenced therein. The

    Nigerian Department of Petroleum Resources (DPR) is the responsible government

    entity for regulating petroleum development in Nigeria. Other pertinent

    government agencies involved directly or indirectly, in engineering, procurement,construction, and installation activities in oil and gas development include:

    Federal Ministry of Environment (FME)

    Nigerian National Petroleum Corporation (NNPC)

    Nigerian Petroleum Investment Management Services (NAPIMS)

    Applicable Regulations and Guidelines related to oil and gas exploration and

    exploitation activities include but are not limited to the following:

    MWOG joint Operating Agreement

    Petroleum (Drilling & Production) Act 1969

    Mineral Oils (Safety) Regulations 1997

    Guidelines and Procedures for Construction, Operation and Maintenance of Oil

    and Gas Pipelines and Ancillary Facilities issued by DPR

    Environmental Guidelines and Standards issued by DPR, 2002

  • 7/31/2019 Basis for Design New

    54/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 54

    The design shall reference industry and international codes and standards. The

    engineering work carried out in this project complies with applicable government

    regulations, industry standards including, but not limited to those listed in

    Appendix 1, and are deemed most applicable to the scope of this project. In all

    cases the latest edition of the codes shall be used except otherwise stated for

    older/existing components. CMA will operate within the tenets of Companys

    standards. Drawings for all new facilities shall comply with all applicable

    international standard.

    Specifically;

    MWOG Project scope of work and other documents from MWOG

    MWOG Design instructions from MWOG staff

    MWOG Information gathered during facilities site visit

    Nigeria All applicable Nigerian Codes and Standards

    Unfired PressureVessels

    ASME Boiler & Pressure Vessel Code (Section II, SectionSection VIII, Div. 1 or Div. 2, and Section IX)

    Process Facilities All applicable API RP (e.g. API RP 14E, 12J etc).

    Relief Valves ASME Section VIII, API 520, 521, 526, 527

    Piping ANSI B31.3, Code for Chemical Plant and Petroleum Refin

    Pressure Piping

    ANSI/ASME B16.5 Steel Pipe Flanges and Flanged Fittings

    ANSI/ASME B16.9 Wrought Steel Butt welding Fittings

    ANSI/ASME

    B16.11

    Steel Socket Weld Fittings

    ANSI/ASME

    B16.20

    Metallic Gaskets for Pipe Flanges - Ring Joint, Spiral Wou

    and Jacketed

    ANSI/ASME Valves - Flanged, Threaded and Weld End

  • 7/31/2019 Basis for Design New

    55/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    EpicAtlanticLimited

    Page 55

    B16.34

    API 598 Valve Inspection and Testing

    API 600 Steel Gate Valves - Flanged and Butt welding Ends

    API 602 Compact Steel Gate Valves

    API 650 Welded Tanks

    API 12B Bolted Tanks

    ASME 8 Boiler and Pressure Vessel Code

    Electrical All apparatus shall bear the CSA label

    All installations shall be in accordance with the CSA Natio

    Electrical Code, latest edition.

    API RP 500 Recommended Practice for Classification of Locations f

    Electrical Installation at Petroleum Facilities

    NFPA National Fire Protection Association

    NFPA 10 Fire Extinguishers

    NFPA 12 CO2 Extinguishing System

    NFPA 13 Sprinkler System

    NFPA 14 H2O Spray fixed system

    NFPA 14 Standpipe and Hose system

    NFPA 20 Fire Pumps

    Other NFPA are; 16, 15, 22, 72, 30, 54 and 101

  • 7/31/2019 Basis for Design New

    56/56

    CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004

    June 9, 2012

    16.0 APPENDI CES

    BFD Matr ix

    BFD Matrix.pdf

    Product ion Forecast / Well Fluid Character isti cs and Propert ies

    Production Forecast& Profile Picture.xls

    Fire and Gas Detection

    Fire and GasDetection System.do

    Proposed General Layout

    Proposed GeneralLayout.pdf


Recommended