Date post: | 04-Apr-2018 |
Category: |
Documents |
Upload: | iyanda-seun |
View: | 220 times |
Download: | 1 times |
of 56
7/31/2019 Basis for Design New
1/56
EpicAtlanticLimited
Page 1
CHESTER MEAD ASSOCI ATES LI MI TED
BASI S FOR DESI GN
FOR
MI DWESTERN OI L AND GAS COMPANY PLC
PROJECT:
UMUSADEGE CENTRAL PROCESSI NG FACI LI TY
ENGI NEERI NG AND PROCUREMENT SERVI CES
CONTRACT NUMBER:
xxxxxxxxxxxx
DOCUMENT NUMBER:EAL/UMUCPF/GEN/DOC/001
AO2 30/04/2012Issued forApproval
AD KK
Rev. Date Description Originator Released Approved (Client)
7/31/2019 Basis for Design New
2/56
UMUSADEGE CENTRAL PROCESSING FACILITY ENGINEERING AND PROCUREMENT SERVICES
BASIS FOR DESIGN - CMA/ UMUCPF/ MDR-GEN/ DOC/ 003Feb 28, 2012
EpicAtlanticLimited
Page 2
ADDI TI ONAL AGREEMENT / APPROVAL RECORDS
Part y Rev. I nd. Name Sign Date
REVI SI ON PHI LOSOPHY
All revisions for review will be issued at R01, with subsequent R02, R03, etc asrequired.
All revisions approved for issue or design will be issued at A01, with subsequentA02, A03, etc as required.Documents approved for Construction will be issued at C01, C02, and C03respectively.Documents or drawings revised as As built will be issued as Z01, Z02 Z03 etc.Narrative sections revised from previous approved issues are to be noted in thetable below and/or highlighted in the RH margin (using the appropriate revisionstatus) thus: | A02Previous revision highlighting to be removed at subsequent issues.Drawings/diagrams revised from previous approved issues are highlighted by
'clouding' the affected areas and by the use of a triangle containing the revisionstatus.
REVI SI ON HI STORY
Rev. No.Date ofI ssue
Reason for change
R02 IDC
A01 28/02/12MWOG CommentsRevised Production Forecasts & Well Streams Data
Deleted Offspec collection within CPF
7/31/2019 Basis for Design New
3/56
UMUSADEGE CENTRAL PROCESSING FACILITY ENGINEERING AND PROCUREMENT SERVICES
BASIS FOR DESIGN - CMA/ UMUCPF/ MDR-GEN/ DOC/ 003Feb 28, 2012
EpicAtlanticLimited
Page 3
Table of Cont ent s
GLOSSARY 8
1.0 INTRODUCTION ............................................................................................. 151.1 Purp ose ................................................................................................ 151.2 The Umusadege Field ........................................................................ 151.3 The Field s Fac ilities Develop ment Ob jec tives .............................. 151.4 Ove rview of The Field s Existing Proc essing Fac ilities .................... 15
2.0 KEY CONSIDERATIONS .................................................................................. 172.1 Mode .................................................................................................... 172.2 Brow n Field Eng ineering / Stra te gy Fit ............................................. 172.3 Field Life ............................................................................................... 172.4 Effic ienc y & Op timum Oil Rec overy from the Proc ess Systems .. 172.5 Dry Crud e Export ................................................................................ 172.6 Zero Effluent Emission ......................................................................... 18
3.0 THE EXISTING FACILITIES & INFRASTRUCTURE............................................... 193.1 Surfa ce Fac ilities in Plac e .................................................................. 193.2 The Ea rly Produc tio n Fac ility ............................................................. 193.3 The Field Infra struc ture ...................................................................... 20
4.0 DESIGN REQUIREMENTS ................................................................................ 214.1 Design Capac ities & Spec ifica tions ................................................ 214.2 Well Fluid Cha rac te ristic s and Prop erties ....................................... 224.3 Export Crude Spec ifica tion............................................................... 22
7/31/2019 Basis for Design New
4/56
UMUSADEGE CENTRAL PROCESSING FACILITY ENGINEERING AND PROCUREMENT SERVICES
BASIS FOR DESIGN - CMA/ UMUCPF/ MDR-GEN/ DOC/ 003Feb 28, 2012
EpicAtlanticLimited
Page 4
4.4 Prod uc ed Effluent Wate r Spec ifica tion .......................................... 234.5 Cha rac te rised Well Fluid Da ta ......................................................... 234.6 Formation Wate r Ana lysis .................................................................. 244.7 Prod uc tion Start-Up ............................................................................ 244.8 Erosion Veloc ity & Noise .................................................................... 254.9 Fac ility Sta nd ards ............................................................................... 254.10 Design Simulation Software .............................................................. 25
5.0
THE CENTRAL PROCESSING FACILITY ........................................................... 26
5.1 Fac ilities / Proc ess Desc ription ......................................................... 265.2 Design & Operating Philosophy ....................................................... 295.2.1 The Inlet and Intermediate / ESD Va lves Manifold ....................... 305.2.2 The Test Sepa rator .............................................................................. 315.2.3 The HP Separator ................................................................................ 315.2.4 The LP Separator ................................................................................ 315.2.5 The Gas Boot ....................................................................................... 325.3 The Crud e Export Pum ps ................................................................... 325.4 The Closed Drain System ................................................................... 325.5 Gas Hand ling ...................................................................................... 325.6 Flare System ........................................................................................ 335.7 Water Trea tment ................................................................................ 335.8 Storage Tanks ...................................................................................... 335.9 Diesel Sto rage and Dispensing ........................................................ 355.10 Servic e & Fresh Water System .......................................................... 35
7/31/2019 Basis for Design New
5/56
7/31/2019 Basis for Design New
6/56
UMUSADEGE CENTRAL PROCESSING FACILITY ENGINEERING AND PROCUREMENT SERVICES
BASIS FOR DESIGN - CMA/ UMUCPF/ MDR-GEN/ DOC/ 003Feb 28, 2012
EpicAtlanticLimited
Page 6
9.2 LAYOUT CO NSIDERATIONS ................................................................ 4410.0 FIRE PROTECTION .......................................................................................... 46
10.1 Fire Wate r ............................................................................................ 4610.2 Fire and Gas Dete c tion Syste m ....................................................... 46
11.0 ELECTRICAL DESIGN BASIS ........................................................................... 4711.1 Power Generation .............................................................................. 4711.2 UPS ........................................................................................................ 48
11.3
Power Transmission & Distribut ion .................................................... 48
12.0 HSE/ SD REQUIREMENTS ................................................................................. 4912.1 Safety Considerations ........................................................................ 4912.2 Environm enta l Considerations ......................................................... 4912.3 Sec urity Considerations ..................................................................... 4912.4 Risk Assessment and Mana gement ................................................ 50
13.0 ASSET MANAGEMENT ................................................................................... 5113.1 Operating Philosop hies ..................................................................... 5113.2 Asset Reference Plan......................................................................... 51
14.0 MANAGEMENT OF CHANGE & QUALITY ..................................................... 5214.1 Design Change .................................................................................. 5214.2 Qua lity Assuranc e and Control Requirements .............................. 52
15.0 STATUTORY AND REGULATORY COMPLIANCE ............................................ 5315.1 Nigerian Content ............................................................................... 5315.2 Regula to ry Considerations ............................................................... 53
16.0 APPENDICES .................................................................................................. 56
7/31/2019 Basis for Design New
7/56
UMUSADEGE CENTRAL PROCESSING FACILITY ENGINEERING AND PROCUREMENT SERVICES
BASIS FOR DESIGN - CMA/ UMUCPF/ MDR-GEN/ DOC/ 003Feb 28, 2012
EpicAtlanticLimited
Page 7
BFD Matrix ....................................................................................................... 56Produc tion Forec ast / Well Fluid Cha rac teristics and Properties........... 56Fire and Gas Detec tion ................................................................................ 56Proposed General Layout ............................................................................ 56
7/31/2019 Basis for Design New
8/56
EpicAtlanticLimited
Page 8
GLOSSARY
The Following definitions and abbreviations have been used in this document.
Organisational
API American Petroleum Institute
Client Midwestern Oil & Gas Company Plc
Consultant Chester Mead Associates Limited
CMA Chester Mead Associates Limited
DPR Department of Petroleum Resources
FME Federal Ministry of Environment
MWOG Midwestern Oil & Gas Company Plc
NAPIMS Nigerian Petroleum Investment Manageme
Services
NCD Nigerian Content Division
7/31/2019 Basis for Design New
9/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 9
Definitions and Abbreviations (continued)
Technical Terms
AC Alternating Current
AG Associated Gas
AGG Associated Gas Gathering
ALARP As low as reasonably practicable
BFD Basis for Design
B/L Bulkline
BS&W Base Sediments & Water
CASHES Community Affairs, Safety, Health, Environment and Security
CITHP Closed-in Tubing Head Pressure
CNG Compressed Natural Gas
cP Centipoise
CP Cathodic Protection
CPF Central Processing Facility
CPP Central Power Plant
CPU Central Processing Unit
CCR Central Control Room
DCS Digital Control System
D/L Delivery Line
EIA Environmental Impact Assessment
EPF Early Production Facility
ESD Emergency Shutdown
FEED Front End Engineering & Design
7/31/2019 Basis for Design New
10/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 10
FOB Freight on Board
7/31/2019 Basis for Design New
11/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 11
Definitions and Abbreviations (continued)
Technical Terms (contd.)
F&G Fire and Gas Detection System
F/L Flowline
F/S Flowstation
GGF Group Gathering Facility
GTL Gas To Liquids
GOR Gas Oil Ratio (Surface)
HEMP Hazard and Effects Management Process
HMI Human Machine Interface
HP High Pressure
HSE Health, Safety and Environment
HV High Voltage
HVAC Heating, Ventilation and Air Conditioning
IGF Induced Gas Flotation
ITC Incoming Termination Chamber
I/O Input/output
LACT Lease Automated Custody Transfer
LCR Local Control Room
LEL Low explosion limitLER Local Equipment Room
LPG Liquefied Petroleum Gas
L/P Line Pipe
LP Low Pressure
7/31/2019 Basis for Design New
12/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 12
LV Low Voltage
Definitions and Abbreviations (continued)
Technical Terms (contd.)
MCS Master Control Station
MOC Management of Change
M/F Manifold
OML Oil Mining Lease
PAS Protective Alarm System / Process Automation System
PAGA Public Address and General Alarm
PES Programmable Electronic Systems
PFD Process Flow Diagrams
PID Control Proportional-Integral-Derivative Control
PSD Process Shutdown
P/L Pipeline
RAM Risk Assessment Matrix
SD Sustainable Development
SDV Shutdown Valve
SIMOPS Simultaneous Operations
SPIR Spare Parts List and Interchangeability RecordSRS Safety Requirement Specifications
TMR Triple Modular Redundant
TPI Tilted Plate Interceptor
7/31/2019 Basis for Design New
13/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 13
Definitions and Abbreviations (continued)
Units of Measurements
BCF, bcf Billion Cubic Feet
bpd Barrels per Day
bopd Barrels of Oil per Day
Bscf Billion Standard Cubic Feet
bwpd Barrels of Water per Day
CFM Cubic Feet per Minute
Deg C Degree Centigrade
ft Feet
km Kilometer
km/h Kilometer per Hour
kVA Kilovolts Ampere
m Meter
M Thousand
MBD Thousand Barrels per Day
MM Million
MMscfd Million Standard Cubic Feet per Day
MMstb Million Stock Tank Barrels
MMMscf Billion Standard Cubic Feetpsi Pounds per Square Inch
ppm Parts Per Million
scf Standard Cubic Feet
scf/b Standard Cubic Feet per Barrel
7/31/2019 Basis for Design New
14/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 14
USD United States Dollar
7/31/2019 Basis for Design New
15/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 15
1.0 I NTRODUCTI ON
1.1 Purpose
This document establishes the design criteria, outlines the system design,
equipment and component design features, as well as the performance
characteristics consistent with those criteria. The document also creates the
framework for the instruction documents and construction specifications. The
contents of this document represent the objectives of the owner, project
engineers, and consultants in terms of design features, systems functionality, and
performance.
1.2 The Umusadege Field
Umusadege is a marginal field operated by Midwestern Oil and Gas Plc. The field
is near Kwale in Delta State of Nigeria, and is situated in OML 56. The fields
current potential is 20 Mbopd, but is currently producing about 9 Mbopd, through
an early production facility within the field, with the stabilised wet crude routed to
AGIP via existing GGF and LACT systems. Further development activities are
planned, which will maintain the fields production at this level. However, the
production forecasts from the new wells are yet to be reflected in the production
forecast reference in this BFD
1.3 The Fields Facilit ies Development Objectives
The objective is to replace the existing 10 MBD early production facility with a 20
MBD nominal capacity Central Processing Facility of two trains. Furthermore
opportunity will be taken at this stage to address and re-design HSE and
operational deficiencies to bring the fields operations to standard.
1.4 Overview of The Fields Existing Processing Facilities
The existing 10 MBD processing facility is a single train one-stage separation EPF,
consisting of a 3-phase test separator, and 3-phase group separator, and related
ancillaries. The produced crude is stored in rented tanks, from where it is pumped
to a delivery pipeline for export through AGIP. The produced water is passed
7/31/2019 Basis for Design New
16/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 16
through an oil skimmer tank and disposed to a pit. There is no AG facility and the
associated gas is currently flared.
7/31/2019 Basis for Design New
17/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 17
2.0 KEY CONSI DERATI ONSThe key considerations are presented and summarized below.
2.1 Mode
The CPF should be designed as a normally not manned facility. It should be able
to operate safely under this mode, as well as being able to be shut down safely
remotely from a PLC based control room. Its start-up has to be locally from the
field, or remotely only with local permissive from the field.
2.2 Brown Field Engineering / St rategy Fit
The design will consider the existing facilities in operation, and equipment already
ordered, and the extent to which they may be incorporated in the design, without
prejudice to HSE, operating standards, and undue production deferment.
2.3 Field Lif e
The projected field life is 20 years, for which facilities life of 25 years shall be
considered appropriate.
2.4 Eff iciency & Optim um Oil Recovery f rom the Process System s
Number of separation stages will be optimized in the light of surface oil recovery
and pressure regimes of the wellhead crude. In this respect more than one-stage
separation will be considered for the higher pressure streams, as that will improve
their oil recovery.
2.5 Dry Crude Export
The design will include infield dehydration, as export will be through a 3 rd party
facility that is willing to accept only dry crude, BSW 0.5%, and TVP 10 psia at 82o
F.
7/31/2019 Basis for Design New
18/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 18
2.6 Zero Effluent Emission
The design will aim for total gas utilization and disposal of produced gas and water
only by means approved by client.
7/31/2019 Basis for Design New
19/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 19
3.0 THE EXI STI NG FACI LI TI ES & I NFRASTRUCTURE
Existing processing facilities in the field are limited to the Early Production Facility
(EPF) and rented storage tanks. There are no existing gas processing facilities.
However, some equipment, separators, gas boots, test and production manifolds
have been procured for the planned facilities upgrade, viz:
1 No. Group Separator 8 x 40, 20 Mbopd / 7.5 MMscfd / 4 Mbwpd capacity
(already procured)
2 Nos. Gas Boot / Water Separator 3.28 x 40 (already procured)
1 No. 6 Test Manifold
1 No. 8 Production Manifold
Also two storage tanks, each of 14.5 Mbbl capacity are currently being installed, and
more may be installed later.
3.1 Sur face Facilit ies in Place
The surface facilities in place and in use are:
The 10 MBD Early Production Facility
4 Nos. Wellheads
8 Nos. Wellhead Flowlines, with one of the flowlines hooked up directly to the
Crude Storage Tank
1 No. Field Manifold, complete with Bulk Flowline and Test Line.
Group Gathering Manifold & Delivery Line
6 Nos. Rented Crude Storage Tanks
Crude Oil Metering System
3.2 The Early Product ion Facilit y
The Early Production Facility is of an ad-hoc design, of one-stage separation,
comprising the following:
1 No. Test Separator, complete with Inlet Manifold with 6 Header and ESD
7/31/2019 Basis for Design New
20/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 20
1 No. Group Separator, complete with Inlet Manifold with 8 Header and ESD- One Bulk 3-Phase Separator
3 Nos. Crude oil transfer pumps
Oil saver skimmer / drain pit system
Diesel system
Instrument air system
Flare system - complete with flare liquid knock-out vessel
Service and fresh water system
Chemical (de-emulsifier) injection system
Power Generation System, - 1 No. 350 kVA & 1 No. 250 kVA Diesel Engine
Sets
Drain Systems, complete with 2 drain water pumps that inject water from the
storage tanks into the drain pit.
3.3 The Field I nfr ast ructur e
The key field infrastructure comprise of the following:
Custody transfer unit - 14,000 bpd capacity, complete with 6 bidirectionalloop for meter proving
A new CAT 725 kVA Diesel Engine Set
Utility air generation, - 2 Compressors of 375 CFM at 120 psi and a self
support test separator instrument air compressor
6 Nos. Crude storage tanks of 12,000 barrels total capacity
Effluent water handling capacity of 2,500 bpd.
7/31/2019 Basis for Design New
21/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 21
4.0 DESI GN REQUI REMENTS
4.1 Design Capacities & Specifications
The production profile constructed from the fields well streams forecasts is shown
below, with potential production of 23 Mbpd as peak, declining steadily. The
forecasts are from the present wells only, excluding future wells. The production
potentials of the future wells are yet to be established but believed to be
substantial to fully utilize what would be the installed capacity of the CPF.
Productio Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Forecast Rate 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033
Oil - Mbopd 19.6 17.6 15.8 14.3 12.8 11.6 10.4 9.4 8.4 7.6 6.8 6.1 5.5 5.0 4.5 4.0 3.6 3.3 2.9 2.6 2.4 2.1 1.9
Gas - MMscfd 3.5 7.9 8.3 10.4 10.4 9.6 8.5 6.9 5.5 4.7 4.3 3.8 3.4 3.1 2.8 2.5 2.3 2.0 1.8 1.6 1.5 1.3 1.2
Water - Mbwpd 2.3 2.5 2.7 3.0 3.3 3.5 3.2 3.0 2.8 2.5 2.0 1.8 1.5 1.3 1.0 0.9 0.8 0.7 0.7 0.6 0.5 0.5 0.4
Projected at 10% decline, as supplied forecast did not cover the period
Field' s Production Forcast
0.0
5.0
10.0
15.0
20.0
25.0
2 01 1 2 01 2 2 01 3 2 01 4 2 015 20 16 2 01 7 2 01 8 20 19 2 02 0 2 021 20 22 2 02 3 2 02 4 20 25 2 02 6 2 027 2 02 8 2 029 2 03 0 20 31 2 03 2 2 03 3 2 03 4 2 035 20 36
Field'sProductionProfile ConstructedfromWellStreamsOIlProductionForecast
7/31/2019 Basis for Design New
22/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 22
4.2 Well Fluid Characteri stics and Propert ies
Well Reservoir / Reservo ir Bubble Oil Water Wellhead API Tank Oil
String Datum Depth Pressure Point Viscosity Viscosity Rsi Boi CITHP FTHP Temp Tank Oil Gas SG Viscosity
ft ss psia psia cP cP scf/ stb rb/ stb psig psig deg C SG (air = 1) cs
1 XIIA/ 7882 3,410 108 1.41 0.00 94 1.400 650 230 96 0.83 0.84 0.00
2 XIIB/ 7950 3,430 110 0.80 0.00 71 1.40 800 300 96 0.85 0.86 0.00
3 IX/ 7606 2,947 116 0.73 0.00 120 1.40 500 320 130 46.00 0.00 0.00
5 XVI/ 8145 3,410 372 0.70 0.00 100 1.12 680 420 151 44.00 0.00 0.00
6 XIIIA/ 8105 3,408 364 0.71 0.00 140 1.12 660 340 145 40.00 0.00 0.00
7 XIV/ 8237 3,522 570 0.64 0.00 127 1.12 780 410 140 44.00 0.00 0.00
8 XIIC/ 8005 3,435 110 0.69 0.00 132 1.12 800 640 135 40.00 0.00 0.00
UMU 7L
Subsurface Conditions Wellhead / Surface Flow Conditions
UMU 1S
UMU 1L
UMU 5L
UMU 6L
UMU 6S
SerialN
o.
UMU 7S
4.3 Export Crude Specification
Reid Vapor Pressure (RVP) 10.0 psia
True Vapor Pressure (TVP) 10.5 psia @ maximum storage temperature
Basic sediment and water 0.5 volume percent
Salt content 35 lb/kstb
Storage Temperature 80 - 82 F
7/31/2019 Basis for Design New
23/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 23
4.4 Produced Eff luent Water Specification
Maximum instantaneous dispersed oil content of produced water discharges will
be 10ppm.
4.5 Characteri sed Well Fluid Data
Component Mole % Specificgravity
Molecular weight NBP (F)
Nitrogen 0.19
Carbon dioxide 0.14
Hydrogen sulphide 0.00
Methane 8.71
Ethane 3.56Propane 7.34
i-Butane 5.97
n-Butane 6.80
i-Pentane 5.19
n-Pentane 3.61
Hexanes 5.53
Heptanes Plus 5.32 0.7227 96 TBD
Octane Plus 8.28 0.7457 107 TBD
Nonane 5.17 0.7648 121 TBD
Decane 4.69 0.7788 134 TBD
Undecane 3.18 0.7898 147 TBD
Dodecane 2.60 0.8008 161 TBD
Tridecane 2.44 0.8118 175 TBDTetradecane 2.21 0.8228 190 TBD
Pentadecane 2.31 0.8328 206 TBD
Hexadecane 1.92 0.8398 222 TBD
Heptadecane 2.19 0.8478 237 TBD
Octadecane 1.22 0.8528 251 TBD
Nonadecane 1.19 0.8578 263 TBD
Eicosane 0.91 0.8628 275 TBD
Uneicosane 0.84 0.8679 291 TBD
Doeicosane 0.80 0.8729 305 TBD
Trieicosane 0.73 0.8779 318 TBD
Tetraeicosane 0.60 0.8819 331 TBD
Pentaeicosane 0.53 0.8859 345 TBD
Hexaeicosane 0.46 0.8899 359 TBD
Heptaeicosane 0.40 0.8939 374 TBDOctaeicosane 0.35 0.8969 388 TBD
Nonaeicosane 0.30 0.8999 402 TBD
Triacontane plus 4.32 0.9506 544 TBD
Total 100
7/31/2019 Basis for Design New
24/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 24
4.6 Form ation Water Analysis
Source
Umusadege6 Umusadege4(BHS @ 7,965 ft)
Date Sampled 8th February 2011 2nd March 2007
SG 1.0104 0.9980 @ 60oF
pH 7.83 @ 80oF 7.96 @ 20oC
Conductivity, s/cm @ 80oF 8,403
Resistivity, ohm.metre @60oF
5.900
Total Dissolved Solids, mg/l 4,820 1,380
Total Salinity, mg/l 4,250Total Alkalinity, mg/l 665
Hydrogen Sulphide
CATI ONS
Potassium, mg/l 23
Sodium, mg/l 1,727 295
Calcium, mg/l 16.5 145
Magnesium, mg/l 3.7 3.6
Barium, mg/l 45.0 1.2
Iron, mg/l 0.4 0.8
Strontium, mg/l 0.7
ANI ONS
Chloride, mg/l 2,303 460
Sulphate, mg/l 35 8.5
Carbonate, mg/l 25 Nil
Bicarbonate, mg/l 640 445
Hydroxide, mg/l Nil Nil
4.7 Production Start- Up
The CPF facilities will be designed to allow facility startup using the emergency
(diesel) generator system, as black start.
Facility operability during turn-down to level of 20% of design rates is anticipated.
7/31/2019 Basis for Design New
25/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 25
4.8 Erosion Velocity & Noise
The optimum diameter for the interconnecting lines between Inlet headers and
separators will be determined to ensure that flow velocities are within erosion
limits and noise avoided.
4.9 Facilit y Standards
This is necessary only in so far as is necessary to ensure variety control as well as
the stocking and inter-changeability of spare parts.
4.10 Design Simu lation Soft w are
The process design software shall be: HYSYS, Pipe Phase, Pipe Sim and Flare Net
while the facility layout shall be designed with AUTOPLANT.
Simulation data and results of analysis will be included in the design reports.
7/31/2019 Basis for Design New
26/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 26
5.0 THE CENTRAL PROCESSI NG FACI LI TYThe base case concept for the Central Processing Facility is a 2 x 20 MBD capacity
processing facility as shown in the PFD below, and will be developed with a
provision for possible future tie-ins of additional separator(s). The 2-train system is
driven by the objective to minimize production deferment through SIMOPS on the
facilities installation, as well as optimal utilization of equipment already procured.
Other related options are considered and analysed in the concept selection study
report (with Document No. CMA/UMUCPF/MDR-GEN/DOC/004).
The CPF systems include the following facilities: Oil processing and export facilities.
Well test facilities.
Utility and support systems operation.
Produced water treatment facilities.
5.1 Facilit ies / Process Descript ion
The oil processing involves two trains and 3-phase separation. The trains
configuration and installation have been planned to minimize production
deferment at transition. In this respect, the first train, Train-1, will be designed
and installed to start on one-stage LP separation, with provision to use mobile test
unit for well testing (to be evaluated), while the second train, Train-2, will be
designed and installed with the full complement of multi-stage separation,
including a test separator. The multi-stage separation will start with two stages,
with provision for future XHP / XXHP installation as will be dictated by the pressure
regimes based on input information provided on well 9.
The design for the XHP / XXHP integration is outside the current scope of work,
and will be implemented if and when the time comes
Crude processing will be segregated between the two trains as follows: -
higher pressure wells to be processed via the 2-stage separation (HP + LP),
7/31/2019 Basis for Design New
27/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 27
while the lower pressure wells will be processes through the one-stage
separation (LP).
Piping will be configured for flexibility to flow any well through the HP train or
LP train, as well as connectivity between the two trains.
The test separator, though will be installed in Train-2, will serve both trains. In
addition valving will be designed for flexibility to use the test separator as bulk
HP separator for Train-1.
Figure 1: Train 1 Flow Scheme
7/31/2019 Basis for Design New
28/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 28
Figure 2: Train 1 & 2 Flow Scheme
Both trains will enable produced oil to be routed through three cascade tanks each
of size 1,000 barrels before export through the LACT, or transfer to storage tanks
with cumulative capacity of 100,000 barrels for temporary if and when the need
arises.
A heater currently available has been converted to function as an LP separator.
All separation stages are placed as three phase separators, enabling water to be
removed from each stage as well as the gas boots, for processing in a TPI facility.
The TPI produced water is anticipated to meet DPR specifications of 10 ppm oil in
7/31/2019 Basis for Design New
29/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 29
water before disposal in a water injection well, whose design is intended to be
covered in a separate contract.
In addition, given the fact that the produced water is planned to be disposed by
injecting it into well(s), the need for treating to the high quality of 10 ppm needs
to be discussed and confirmed with the DPR, to avoid the cost of achieving
specifications that are unnecessary.
The produced gas will be used as fuel gas for the CPF gas engine generator, with
the excess available for external utilization.
For the excess gas handling, five potential options have been compiled for
evaluation, i.e.:
1. LPG recovery + power generated with surplus methane stream,
2. Power generated with whole stream of gas for export to National Grid,
3. CNG bottles manufactured by third parties,
4. Produced gas sold at CPF fence,
5. Gas injected into Umusadege reservoirs. This last option is only included only
for completeness of the records and not considered to be a serious option, as
DPR will not approve gas disposal by re-injection.
Any or all of the options will be examined for potential uptake by third party off-
takes or MWOG/partners, to enable a specific recommendation. This review will be
carried out as part of the detailed engineering scope and will be reported
separately.
5.2 Design & Operat ing Philosophy
The CPF will be normally not manned
7/31/2019 Basis for Design New
30/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 30
It should be able to operate safely under this mode, as well as being able to be
shut down safely remotely from a local PLC based control room. The PLC will beequipped with HMI, and SCADA capability.
Its start-up has to be locally from the field, or remotely from the control room only
with local permissives from the field.
TThhee operating modes outlined in this philosophy shall be developed during
detailed engineering.
5.2.1 The I nlet and I ntermediate / ESD Valves Manifold
The inlet manifold will operate in bulk and test mode and both modes can be
operated concurrently. The bulk mode will be the normal production mode in
which wells with the same pressure regime are switched to the same header
where they are commingled. From the header, they flow into a targeted (HP
or LP) or in some cases test separator (when the test is being operated in
bulk mode).
The test mode will be the mode in which a well is put under test to determine
its production capacity and basic composition such as GOR and BS & W. In
this mode, the well under test will be switched to the test headers from
where it flows into the test separator.
The inlet headers are process lines between the ligaments and the inlet
separators. Each well and also each inlet header will have individual
shutdown valves, which is used primarily to isolate the ligaments (wells and
flow lines) from the inlet separators during an operational or emergency
shutdown. On each bypass line is a 2 inch manual globe valve. The bypass
line is used primarily during start-up to gradually pressurize the flow station
and the instrument fuel gas header by the use of the 2 inch globe valve.
The flow station is first pressurized before each header ESD valve can be
opened for the following reasons:-
Enable the lighting of the flare.
Prevent a pressure shock (hammer effect) on the facility.
Prevent possible damage of the header ESD valves seat because of high
differential pressure across them.
7/31/2019 Basis for Design New
31/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 31
Allow a reset of the pneumatic safeguarding panel.
Each header ESD valve will consist of a ball valve with a spring return
actuator. A pneumatic pilot operated three-way valve operates the actuator.
The pilot signal on the three-way valve will be controlled by a pneumatic
relay based safeguarding system.
Pressure gauges are installed on each header to measure the inlet pressure.
5.2.2 The Test Separator
The test separator operates as 3-phase. It will have two operating modes
(test and bulk).
When in test mode, any of the wells under test is routed to the test
separator.
In the bulk mode, it will be used for normal production and operates like any
of the other two separators (LP & HP). In this mode, all producing wells
within the same pressure regimes are switched manually through their
individual ligament valves into the test header. From the test header they
flow into the test separator.
5.2.3 The HP Separator
The HP Separator will operate between 220 to 240 psig. All producing wells
within the same pressure regimes are switched manually through their
individual ligament valves into the HP header. From the HP header they flow
into the HP separator.
In the separator, liquid and gas are separated. The flashed gas exits though
the gas outlet, while the oil and water stream is routed to the LP separator.
5.2.4 The LP Separator
The LP separator will operate between 30 to 40 psig. All producing wells
within the same pressure regimes are switched manually through their
individual ligament valves into the LP header. From the LP header they flow
into the LP separator. The oil, water and gas are separated. The flashed
gas exits though the gas outlet, while the oil is routed to the gas boot / surge
vessel.
7/31/2019 Basis for Design New
32/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 32
The water is routed to the water treatment facility.
5.2.5 The Gas Boot
The gas boot is a three phase degassing / stabilizing unit, also enabling
additional refinement of de-oiled water to be routed to the water treatment
facility for further processing.
Final separation of gas and liquid occurs in both cases, the flash gas exits
through an outlet line and flows into the flare knock-out vessel. The liquid
(oil) exits through the outlet line where it flows by gravity into the cascade
tanks, from where it is pumped to the LACT.
Details of pump control will be developed with vendor data during detailed
engineering. Pump discharge pressure floats on the pipeline operation
pressure, which is a function of the liquid export flow rate and the other
users of the pipeline system.
5.3 The Crude Export Pum ps
Centrifugal pumps, with variable speed drive mechanism have been procured to
be used. These pumps are already on the site and will be evaluated to assure
they fit the required duty.
5.4 The Closed Drain System
All vessel drains are routed to the closed drain sump tank. Recovered oil is
pumped back to the crude oil export system while removed water is routed for
treatment. Open and closed drainage systems shall be included. Open drains will
channel rain water and non-hazardous fluids to the open drain pit via the open
drain header. Closed drains handling oil contaminated and hazardous liquids are
routed to the closed drain tank via the closed drain header.
5.5 Gas Handling
Associated gas will be routed to an AG solution facility to enable value addition for
sales. Options that may be considered for the AG solution facility include
processing for direct sales, or for LPG extraction and power generation, for own
use or for sale.
7/31/2019 Basis for Design New
33/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 33
A fuel gas system shall be provided for supply of fuel gas to the gas turbines. The
fuel gas system shall be sized to supply all future equipment required for theDesign Case. Supply pressure will be based on selected gas engine generator.
A purge gas system shall be provided for purging and supply to flare pilots and
ignition system. Critical control valves shall be spared to ensure availability of
supply.
5.6 Flare System
In line with DPR regulations, routine process flaring will not be permitted.
However a full facility flare will be included for use under emergency conditions.The existing flare will be evaluated to determine capacity for the forecast
production. A flare header / flare system will be provided to collect and safely
dispose of produced hydrocarbon gases. As a minimum, the system will consist of
flare headers, a flare knockout drum, and a continuously ignited pilot flare. In
addition, the system will be designed to safely and continuously flare the produced
gas capacity of the CPF and to depressurize all of the production flow lines in the
shortest possible practicable time. Discharges from pressure relief valves and
other hydrocarbon streams as required by the CPF Facility Specifications will be
routed to the flare system. The flare system will be equipped with meters to
measure flare volumes to within an accuracy of 2%.
5.7 Water Treatment
Produced water will be routed to a TPI (Tilted Plate Interceptor) Facility ahead of
disposal. The ultimate disposal route will be via re-injection into an aquifer.
The TPI produced water shall be made to meet DPR specifications of 10 ppm oil in
water before disposal by injection into an aquifer. Before the installation of the
water injection plant, water will be disposed off in the existing pond.
The design of the injection facility is outside the scope of this Basis for Design,
and will be covered in a separate contract.
5.8 Storage Tanks
The tables below summarise the tanks that will be installed:
7/31/2019 Basis for Design New
34/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 34
Table 1 : Crude Oil Tanks
Tank Designation Capacit y
Processed (dead) Crude 2 x 14,500 barrels
Processed (dead) Crude 2 x 35,000 barrels (Anticipated)
Crude Settlement 3 x 1,000 bbl Cascade Tanks
Table 2: Other Tanks
Tank Designat ion Capacit y
Produced Water 1,000 bbl as part of re-injection phase.
Firewater 5,000 barrels
Chemical (one per chemical type) TBD
Diesel 500 barrels (10 days endurance)
The crude oil tanks will be fitted with a stripping system to permit removal of
water that has settled out of the crude oil. The storage system will be capable of
receiving stabilized crude from the production facilities. The offloading system will
be capable of discharging at a rate and pressure such that it can flow into the GGF.Fiscal metering of the exported crude will be based upon the use of the existing
LACT system at GGF since the existing facility is in-place and is reliable. The tank
shall be fitted with local flow meters (or gauge).
The facility and associated systems will be designed to remain on site for entire
design life and with minimal maintenance and repair (e.g., no major steel, coating,
and piping or equipment renewals) which might result in interruption of production
operations. This will be achieved mainly from material selection.
There will an automated and manual level control system on each tank. Motorised
valves will be interlocked to allow one tank filling at a time. Two 14,500 barrel
crude oil tanks shall be used for storage and settlement. Additional two 35,000
barrels capacity are anticipated for future expansion.
The storage tank inlet motorized valves are controlled by the Level Switch High on
the storage tank to prevent overfilling of the crude oil. The motorized valves are
also at interlock with each other with the philosophy that only one tank can be
7/31/2019 Basis for Design New
35/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 35
filled at a time. The closure of one motorized valve gives an advent of the opening
of the next motorized valve on priority. The Level Switch Low on the tank controlthe motorized valve on the outlet section of the tank in safeguarding the operation
of the pumps.
The final logic of the tank filling operation shall be done by the detailed
engineering contractor which shall be implemented by the Vendor of the
Programmable Logic Controller.
5.9 Diesel Storage and Dispensing
Diesel is required for the emergency power supply system. Specific care will bemade to ensure that the supplied quality meets equipment requirements and that
adulterated products are not supplied.
5.10 Service & Fresh Wat er System
Potable water system will be included for use in engine cooling system as well as
fire water storage. The borehole supply pump will be powered by electric motor.
5.11 Chemical I nj ect ion System
Chemical Injection points will be included where needed. Such chemicals as
corrosion and scale inhibitors are potentially required.
5.12 Pneumatic Control & Automation System
Dry instrument air will be provided to the process facilities. CMA will determine
the required pressure and capacity of the instrument air and provide 2 or 1 electric
motor driven air compressors. CMA shall consider the cooling demands of
generator when assessing the instrument air demand. An air filtration (leaning)regulator system will be provided.
5.13 Eart hing System
An earth ring main will be designed to provide earthing source for all the facilities
7/31/2019 Basis for Design New
36/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 36
5.14 Cathodic Protect ion System
Cathodic protection will be provided for buried flowlines & delivery line and also
for vessels and storage tanks.
7/31/2019 Basis for Design New
37/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 37
6.0 MWOG PROCURED EQUI PMENT
The following equipment items have been procured and, as much as is feasible, will
be included in the design.
Table 1 : Pre-Ordered Equipment I tem s
Tag Dimensions MAWP Design
Temperature
Test Separator 1.1m by 3.1m 655 psig 200OF
L.P Separator 8ft OD x 40 ft s/s 50 psig 140F
H.P Separator 5ft OD x 20ft s/s 740 psig 200F
Gas Boot 1 m x 14m 20 psig 140F
Test Manifold 6 in header 1,400 psig 120OF
Production
Manifold
8 in header 1,400 psig 120OF
Storage Tanks 65ft dia x 24 ft 5 psig Ambient
Pump 67.6 HP
(Rating)
187 psi
(Differential)
Technical information on these items of equipment are available and will be applied
in the design checks.
7/31/2019 Basis for Design New
38/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 38
7.0 CI VI L WORKSThe scope of civil works covers the following aspects:
1. Determine the facility area including fence lines, roads and footprints of facility
components.
This shall be based on survey maps and as-built drawings provided by MWOG,
which shall be verified during site visits.
2.Appraise existing drainage lines and reconcile with new routing required.
3. The topography of the new CPF area shall be reviewed to ascertain the extent of
cut and fill that will be required.
4. Output from topography review shall form basis for recommending heights of
supporting structures; e.g. pipe supports, tanks, vessels and gas boots
foundations, steel columns, and walkways.
5. Detailed design of all applicable foundations including oil tank foundations,
control room, buildings, skids, bundwalls .
Results of the borehole sampling will be reflected in the design work and shall
form the basis of foundation design.
6. Detailed instructions on materials to be used, method of application, expected
results or outputs and technical development for constructing the works stated in
item 5 shall be adequately provided.
7. Recommend any other structural component required for a resilient structure;
e.g. platforms, walkways etc.
8. The Construction Scope of Work. These items relating to the execution and
completion of construction works shall be quantified and priced as input to the
project cost estimate. It is expected that any modifications and change orders
from the client shall be incorporated as civil works progress, if agreed and
accepted by parties.
7/31/2019 Basis for Design New
39/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 39
8.0 I NSTRUMENTATI ON
Overall control of the liquid production system is through the Process Automation
System (PAS). This extends over the pump stations, tank farm and the CPF. The
facility will be normally not manned. Normal monitoring of plant performance,
verification of set-points and starting/stopping of equipment, etc, will take place
from the Control Centre located at base.
TThhee Flowstation oil production system will be maintained in stable operation by a
number of factors, including manually set flowlines choke valves that will maintain
the overall station production
8.1 Test Separator I nstrum entati on
The test separator instrumentation will be designed to provide a means to initiate
and carry out well testing locally, and in line with API 14C will have the following
features:
Back Pressure Control
High Pressure Safeguarding
Level Control
Low & High Level Safeguarding
Level & Pressure Measurement
Gas Outlet Measurement
Liquid Outlet Measurements
Temperature Measurement
8.1.1 Back Pressure Cont rol
The test separator will be designed to operate at either LP or HP separator
pressure, and in test or bulk mode. Hence, it will not have a dedicated back
pressure control system, but will share with that of the LP separator (when in
LP mode) or the HP separator (when in HP mode). This sharing shall be
implemented by connecting the test separator gas outlet line to both the LP
or HP header where their back pressure control systems are installed.
The back pressure control will comprise a pneumatic pressure controller and
pressure control valve. The pressure controller measures the process
7/31/2019 Basis for Design New
40/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 40
pressure and produces a standard pneumatic output signal, which drives a
back pressure control valve.
8.1.2 Level Control
The level control will comprise the following:
a. Displacer type controller / transmitter
b. Level control valve
c. Test / Bulk mode selector switch
d. Level Measurement
Displacer Type Contr oller / Transmit ter
The displacer type pneumatic transmitter receives change in fluid level
through change in buoyant force exerted by the fluid on the sensor
displacer, and consequently produces a standard pneumatic output signal
that drives the control valve.
Test / Bulk Mode Selector Sw it ch
The liquid outlets will be divided into two, - a 2 and a 4 line, with a
level control valve installed in each line, with both lines recombined into a
4 line downstream of the control valves. The required liquid outlet line(2 for test mode, and 4 for bulk mode) is selected by manually opening
of the ball valves upstream and downstream of the level control valve,
while the control valve selection is by use of a manual pneumatic switch.
The pneumatic selector switch connects the standard output signal of the
level transmitter / controller to the selected valve.
The liquid outlet will be divided into oil & water to achieve metering
separately.
8.1.3 Level Measurement
The only level indication will be that directly on the vessel by the use of sight
glass.
There will be no direct level measurement and display on the test separator
except level measurement by the displacer type transmitter / controller used
7/31/2019 Basis for Design New
41/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 41
in the level control loop. The level control loop will be primarily field located
with no form of indication.
8.1.4 Low and High Level Safeguarding
The test separator will be equipped with a duplex type transmitter and
controller that will provide dual function of level control and high / low level
safeguarding.
The safeguarding instrumentation will consist of high and low level displacer
type pneumatic switches, connected to a pneumatic relay panel used for
plant safeguarding. The safeguarding logic is implemented in the relay panel
such that for a high level in bulk mode, all the inlet valves and the liquid
outlet valve are closed. In the test mode, the inlet valve applicable will be
that of the well on test. In the event of low level, the liquid outlet valve will
be forced down.
Other safeguarding functions will be conducted in accordance with the
flowstations cause and effects diagrams
8.1.5 High Pressure Safeguarding
The test separator high pressure safeguarding will comprise a high pressure
pneumatic switch that will initiate the shutdown. When the pressure switch
senses a high pressure, it sends a signal to the pneumatic safeguarding relay
panel, where the shutdown logic is implemented in accordance with the
cause & effects diagram.
The objective is to close the inlet shutdown valve to the separator so as to
prevent further entry of hydrocarbon.
8.1.6 Pressure Measurement
All pressure measurement will be by pressure gauges only.
8.1.7 Gas Out let Flow Measurem ent
A senior Daniel orifice or ultrasonic meter will be installed to measure all
outlet gas rates.
7/31/2019 Basis for Design New
42/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 42
8.1.8 Liquid Out let Flow Measurem ent
Oil & water will be metered separately. The oil will be measured usingturbine meters for accuracy that will be in line with DPR requirement.
8.1.9 Temperature Measurement
All temperature measurements will be by temperature gauges only.
8.2 HP Separator I nstrum entati on
The instrumentation and safeguarding functions on the HP separator will be
similar to the test separator, except that there will be no liquid measurement, -
only gas.
Similar to the test separator, it will have a duplex type level instrument, which will
provide both level control and high high level safeguarding function.
8.3 LP Separator I nstrum entat ion
Also, the instrumentation and safeguarding functions on the HP separator will be
similar to the test separator, except that there will be no liquid measurement, -
only gas.
Similar to the test separator, it will have a duplex type level instrument, which will
provide both level control and high high level safeguarding function.
8.4 Crude Oil Export Pump I nstrum entati on
The crude oil pump will have a pneumatic governor, which will be used to vary the
speed of the pump gas engine driver as part of the level control system of the
surge vessel. When the level in the surge vessel goes high, the speeds of the
pumps are set to maximum by the surge vessel controller. At low level, the
pumps are set to minimum speed. In the event that the level drops further, the
recirculation valve begins to open so as to recycle the liquid to the surge vessel.
Pressure gauges will be installed on the pump suction and discharge lines.
7/31/2019 Basis for Design New
43/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 43
8.5 Flare Knockout Vessel I nstrum entati on
The knockout vessel will have four level switches. Three of the switches will be
electric, while the fourth will be pneumatic two of the electric switches will be used
for level control, while the third will be used to shutdown the pump on low low
level detection. The pneumatic switch will be connected to the pneumatic relay
panel for shutdown on high high level in the flare knockout vessel.
The level control system for the pump will consist of a stand-alone electric relay
logic control panel.
7/31/2019 Basis for Design New
44/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 44
9.0 EQUI PMENT LAYOUT
The facility equipment shall be laid out to fit within the CPF land boundary, bearing
in mind the limitations created by the position of the new storage tanks under
construction and right of way.
9.1 AREA CLASSI FI CATI ON
Adequate safe distances for all equipment will be considered in accordance with
area classification requirements that will be firmed up at detail design stage. The
layout shows access roads with provision for drainage lines. Inter-connecting
piping from the process area to storage tanks will be buried at road-crossings; i.e.
piping at other areas will be above ground.
The allocation of functional spaces in the layout was based on the following
parameters:
Flare zone: North-West, due to prevailing wind directions
Utility area: North, in the proximity of the administration building, considered
as a safe area
Tank farm: South-West, in the largest free space to accommodate tanks
Process area: South-East, in near proximity to in-coming lines and inlet
manifolds
Fencing: Perimeter of property, and seal-off of restricted areas.
Accesses: Gates to control service accesses into restricted areas
A conceptual layout is included as Appendix to this document.
9.2 LAYOUT CONSI DERATI ONS
1.All equipment will be placed optimally, satisfying the optimum orientation for all
processes, utility and instrument equipment items.
2. The cost of construction will be minimized, e.g. by adopting a layout that gives
the shortest run of connecting piping between equipment.
3. Sufficient working space and headroom will be provided to allow easy access to
equipment.
7/31/2019 Basis for Design New
45/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 45
4. Equipment such as pumps that require dismantling for maintenance will be
placed under rain/sun cover.5. Equipment will be located so that it can be conveniently tied in with any future
expansion of the process, e.g. future gas off-take.
6.Additional space will be left along the pipe racks to accommodate future piping
needs.
7. The gas flare that is included for emergency use will be located as far as
possible from the process vessels, in line with safe area classification
requirements.
8. The EPF will be tied-in to the new storage tanks via temporary transfer lines that
would be disconnected before commissioning the CPF.
9. The general plant arrangement and orientation will be consistent with the
prevailing atmospheric and site conditions such as wind direction as well as
hazardous area requirements.
10.Adequate allowance will be left for drainage and fire fighting facilities. Access
ways will be provided within the facility for access to items that require removal
for off-site repair.
7/31/2019 Basis for Design New
46/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 46
10.0 FI RE PROTECTI ON
10.1 Fire Water
Fire water storage tank shall be installed with a capacity suitable to meet
firefighting needs for a minimum period of four hours, as determined by the
period for arrival of firefighting support equipment from nearby locations.
A diesel fuel pump and electrical Jockey pump are included. The critical areas shall
be covered with a pressurized ring main that feeds a series of hydrants each with
hoses located at strategic positions in the CPF.
10.2 Fire and Gas Detection System
A Fire and Gas Detection System shall consist of three parts:
a) Detection
b) Control Logic
c)Active Protection
Fire and Gas Detection devices and Manual Call Points shall be provided.
The System shall provide voting capability (2oo3 and where there is failure in one
of the applicable detectors, it recourses to 1oo2) where multiple detectors have
been installed to minimize nuisance shutdowns. For a large area with multiple
zones (without a barrier), cross zone voting within adjacent zones may be used.
Process shutdown actions initiated by the Fire and Gas Detection System shall be
executed via interlocks to the ESD/PSD systems. Other actions (e.g., release of
fire suppressant systems, fire water pump starts, etc.) may be executed directly
from the F&G System.
The Fire and Gas Detection System shall be designed so that it can be functionally
tested and individual detectors can be calibrated without affecting CPF processes
and equipment operation.
The system configuration for F&G Systems shall comprise centrally located logic
solvers in the control room and either centrally or remotely located I/O systems.
7/31/2019 Basis for Design New
47/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 47
Further details on the proposed fire protection system are contained in a separate
document in the Appendix.
11.0 ELECTRI CAL DESI GN BASI S
Power will be generated using gas engine generators fired by the produced gas. A
diesel engine set will be retained for emergency power. Furthermore, solar power
will also be considered as that will have prime use for critical installation such as the
CP system or the telemetry system for communications between the wells and the
CPF.
11.1 Pow er Generati on
Power will be generated on site with two adequately sized Gas engine generator
operated in an N+1 sparing philosophy and sized to cater for 100% total plant
peak load, covering the CPF, GGF, Campsite, and Satellites. The required for
future facilities, e.g. water injection plant and AG solution facility will be addressed
separately, when the time comes.
In addition to the gas engine generators, a diesel engine generator shall be
provided for emergency service and cold start of the CPF. The emergencygenerator shall be adequately sized to supply power for vital and agreed essential
services and to start and run a minimum of one oil export pump.
The vital services refer to those services which, when they fail in operation or
when called upon, can cause an unsafe condition of the process and / or electrical
installation, jeopardize life, or cause major damage to the installation; while the
essential services refer to those that when they fail in operation or when called
upon, will affect the continuity, quality or quantity of the product.
The emergency and critical loads will be defined and agreed, and reflected in the
load list. The load list will form the basis for load segregation, as well as sizing
main equipment such as:
1. Main gas engine generators
2. Emergency diesel generators
3. HV switchboards
4. LV switchboards
5. Protective circuit breakers etc.
7/31/2019 Basis for Design New
48/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 48
11.2 UPS
AC and DC uninterruptible power supply shall be provided complete with battery
banks for the vital loads at the CPF and outlying flowstations. The uninterruptible
power supplies shall use Nickel Cadmium batteries. Each power supply shall be
equipped with two 100% duty chargers capable of both charging batteries and
supporting the maximum load. All batteries shall be 2 x 100% sized, and capable
of supporting their for 30 minutes.
11.3 Pow er Transmission & Dist ribut ion
Power transmission will not be required because the low voltage distribution can
be used.
Main power distribution within the facility will be at 415/220 volt, 50Hz, TPN
(Triple Phase and Neutral) in accordance with local power authority (PHCN)
standard distribution. Power will be distributed to electrical equipment by
adequately sized cables via cable trays or trench.
Adequate protections will be provided to electrical equipment and personnel on
site through a well-designed earthing network that will tie into the existing
earthing system. Other deliverables will be generated in line with the approved
MDR.
7/31/2019 Basis for Design New
49/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 49
12.0 HSE/ SD REQUI REMENTSHSE issues are those which result from the interaction of the proposed facility with
the environment and safety related issues that need to be addressed as part of
Human Factors Engineering in design and also, during project implementation in the
Umusadege field. CMAs CASHES Plan has been consistently applied in our work
execution, enabling safe working practices and minimum impact on the environment
or damage to human life. Documents created as part of the design activities will
reflect these perspectives.
12.1 Safety Considerati ons
The general approach adopted during design development and the requirement
for further design stages will identify and eliminate hazards as an integral part of
the design process.
12.2 Environmental Considerations
The PMT and HSE regulatory teams will work closely together to assure
environmental issues are considered in the design process, following the
applicable regulations and guidelines listed in section 15.2. An Environmental
Impact Assessment study has been conducted on the facility and all its
recommendations shall be implemented. All new facilities will be installed under
the existing MWOG operating permit.
12.3 Securi t y Considerations
CMA / MWOG are committed to a dynamic, visible security program, which
addresses the threats in the major following areas:
Protection of assets
Office and Residential Security
Personnel Transportation/Travel
Communication/Information Security
7/31/2019 Basis for Design New
50/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 50
12.4 Risk Assessment and Managem ent
The CPF project has a number of inherent risks and uncertainties. These will range
from sub-surface uncertainties that may affect the production forecast, to
technical and commercial risks, but also include a number of socio-political risks,
especially during the project execution phase at Umusadege. A risk register has
been compiled with 80 items listed. Mitigation factors will be developed and
implemented.
This project will follow standard guidelines for Engineering Managed Modifications
(EMM) as part of the process for managing any associated risk. A Design Risk
Assessment shall be conducted before the detailed design is concluded.
As part of risk assessment, a specific perspective is the need to carry out a
SIMOPS exercise during detailed design. Consideration will be given to
simultaneous operation of the EPF in parallel with the installation of the CPF. A
SIMOPS Study will be carried out to assess the risks and develop the right
approach for risk mitigation during the installation CPF stage.
7/31/2019 Basis for Design New
51/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 51
13.0 ASSET MANAGEMENT
13.1 Operat ing Philosophies
Operating philosophy envisages that the facility is not normally manned.
Maintenance will aim at preventive maintenance through a computerized
management system. Other features include the following:
a. Field production will continue un-hindered during the installation of the
expanded facility. Aspects include placement and tie-in of processing vessels
and piping works in tandem with systems in operation.
b. Considering that the Umusadege is a marginal field, sparing of equipment
items will be minimized. Also for this reason, high integrity systems will be
included for process safety control. Moderate level of automation for process
control is desired, with process control equipment placed in a purpose-built
office.
c. The facility will operate 365 days a year with shut-down only in the event of
an emergency procedure or for statutory inspections on relief systems and
vessel internals.
13.2 Asset Reference Plan
The ARP that will be created by others at the end of detailed design will aim to
utilize the Operations Readiness and Assurance report to:
Define the boundaries of the asset.
Optimize asset planning and operations with respect to previously completed
sub-surface studies, facilities design and equipment selection and
specifications Integrate business process strategies,
All these actions are aimed at optimizing value of the asset for benefit of MWOG,
its partners, and other stakeholders.
7/31/2019 Basis for Design New
52/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 52
14.0 MANAGEMENT OF CHANGE & QUALI TY
14.1 Design Change
All changes that interface with MWOG operations will be captured, using the CMA
Management of Change (MOC) process. This would ensure that potential changes
are properly assessed, approved and documented so that risks remain at
acceptable levels while project objectives are met. All necessary approvals will be
secured before any deviation / change is carried out.
14.2 Qualit y Assurance and Cont rol Requirem ents
CMAs Quality Assurance process will be applied through the concept of
competence in work disciplines and the attitude and commitment that mandates
all staff to follow best practices.
7/31/2019 Basis for Design New
53/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 53
15.0 STATUTORY AND REGULATORY COMPLI ANCE
This design shall follow the guidelines and standards set by Midwestern Oil and Gas,
Department of Petroleum Resources (DPR) and International Codes of Practice as
applicable in the oil industry. Safety standards shall follow the regulations from the
Occupational Safety and Health Act (OSHA) and other Nigerian regulations.
15.1 Nigerian Cont ent
The work shall be done in accordance with the Nigerian Content Development
Regulation passed by the National Assembly in 2010. Nigerian contractors will
fabricate and install, in most cases using Nigerian personnel.
15.2 Regulatory Considerati ons
The Umusadege project will be developed in compliance with all applicable
Nigerian laws and regulations. The project will also be guided by Scope of work
specifications and International Codes and standards referenced therein. The
Nigerian Department of Petroleum Resources (DPR) is the responsible government
entity for regulating petroleum development in Nigeria. Other pertinent
government agencies involved directly or indirectly, in engineering, procurement,construction, and installation activities in oil and gas development include:
Federal Ministry of Environment (FME)
Nigerian National Petroleum Corporation (NNPC)
Nigerian Petroleum Investment Management Services (NAPIMS)
Applicable Regulations and Guidelines related to oil and gas exploration and
exploitation activities include but are not limited to the following:
MWOG joint Operating Agreement
Petroleum (Drilling & Production) Act 1969
Mineral Oils (Safety) Regulations 1997
Guidelines and Procedures for Construction, Operation and Maintenance of Oil
and Gas Pipelines and Ancillary Facilities issued by DPR
Environmental Guidelines and Standards issued by DPR, 2002
7/31/2019 Basis for Design New
54/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 54
The design shall reference industry and international codes and standards. The
engineering work carried out in this project complies with applicable government
regulations, industry standards including, but not limited to those listed in
Appendix 1, and are deemed most applicable to the scope of this project. In all
cases the latest edition of the codes shall be used except otherwise stated for
older/existing components. CMA will operate within the tenets of Companys
standards. Drawings for all new facilities shall comply with all applicable
international standard.
Specifically;
MWOG Project scope of work and other documents from MWOG
MWOG Design instructions from MWOG staff
MWOG Information gathered during facilities site visit
Nigeria All applicable Nigerian Codes and Standards
Unfired PressureVessels
ASME Boiler & Pressure Vessel Code (Section II, SectionSection VIII, Div. 1 or Div. 2, and Section IX)
Process Facilities All applicable API RP (e.g. API RP 14E, 12J etc).
Relief Valves ASME Section VIII, API 520, 521, 526, 527
Piping ANSI B31.3, Code for Chemical Plant and Petroleum Refin
Pressure Piping
ANSI/ASME B16.5 Steel Pipe Flanges and Flanged Fittings
ANSI/ASME B16.9 Wrought Steel Butt welding Fittings
ANSI/ASME
B16.11
Steel Socket Weld Fittings
ANSI/ASME
B16.20
Metallic Gaskets for Pipe Flanges - Ring Joint, Spiral Wou
and Jacketed
ANSI/ASME Valves - Flanged, Threaded and Weld End
7/31/2019 Basis for Design New
55/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
EpicAtlanticLimited
Page 55
B16.34
API 598 Valve Inspection and Testing
API 600 Steel Gate Valves - Flanged and Butt welding Ends
API 602 Compact Steel Gate Valves
API 650 Welded Tanks
API 12B Bolted Tanks
ASME 8 Boiler and Pressure Vessel Code
Electrical All apparatus shall bear the CSA label
All installations shall be in accordance with the CSA Natio
Electrical Code, latest edition.
API RP 500 Recommended Practice for Classification of Locations f
Electrical Installation at Petroleum Facilities
NFPA National Fire Protection Association
NFPA 10 Fire Extinguishers
NFPA 12 CO2 Extinguishing System
NFPA 13 Sprinkler System
NFPA 14 H2O Spray fixed system
NFPA 14 Standpipe and Hose system
NFPA 20 Fire Pumps
Other NFPA are; 16, 15, 22, 72, 30, 54 and 101
7/31/2019 Basis for Design New
56/56
CMA-MWOG UMUSADEGE CPF ENGINEERING DESIGN AND PROCUREMENT SERVICESBASIS FOR DESIGN - CMA/UMUCPF/MDR-GEN/DOC/004
June 9, 2012
16.0 APPENDI CES
BFD Matr ix
BFD Matrix.pdf
Product ion Forecast / Well Fluid Character isti cs and Propert ies
Production Forecast& Profile Picture.xls
Fire and Gas Detection
Fire and GasDetection System.do
Proposed General Layout
Proposed GeneralLayout.pdf