+ All Categories
Home > Documents > B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of...

B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of...

Date post: 02-Sep-2021
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
83
Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL - MCQ SUBJECT CODE: 2180909 Questions 1 to 4 refer to the figures given below: Theinput-outputcurvesfortwounitswithsupplyinparallelacommonloadareshowninthe figure Q1. Whenaloadof10MWisequallysharedbythetwogenerators,thecombined input mustbe (A) 250x10 5 kcal/hr (B) 350x10 5 kcal/hr (C) 500x10 5 kcal/hr (D) 600x10 5 kcal/hr
Transcript
Page 1: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

B.E. 8 th SEMESTER

POWER SYSTEM OPERATION AND CONTROL - MCQ

SUBJECT CODE: 2180909

Questions 1 to 4 refer to the figures given below:

Theinput-outputcurvesfortwounitswithsupplyinparallelacommonloadareshowninthe figure

Q1. Whenaloadof10MWisequallysharedbythetwogenerators,thecombined input mustbe

(A) 250x105kcal/hr

(B) 350x105kcal/hr

(C) 500x105kcal/hr

(D) 600x105kcal/hr

Page 2: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q2. Ifthetwogeneratorshaveindividualratingsof10MWeach,asystemloadof16 MW should be sharedas

(A) 8 MW on eachgenerator (B) 10MWonAand6MWonB

(C) 10MWonBand6MWonA (D) 9MWonAand7MWonB

Q3.Loadsheddingisdone

(A) To reduce heatdemand

(B) To improve powerfactor

(C) Toruntheequipmentefficiency

(D) To repair themachine

Q4. Ifbothgeneratorshave2MWloadeachthenwhichofthefollowingstatementsis correct?

(A) GeneratorArunsathigherspeedascomparedtogeneratorB (B) GeneratorBrunsmoreefficientlyascomparedtogeneratorA

(C) InputtogeneratorAislessthan75%oftheinputtogeneratorB

(D) InputtogeneratorBislessthantheinputtogeneratorAbyabout23%

Questions 5 and 6 refer to the data given below:

AbulksupplywastakenbyalargeindustrialconsumerattherateofRs80perKWplus2 5 paisa perKWh

Q5. TheaveragechargeperKWhwhentheloadfactoris20% willbe

(A) 3cents

(B) 5cents

(C) 7cents

(D) cannotbedeterminedonthebasisoftheinformationprovided

Q6. TheaveragechargesperKWhwillbeleastwhentheplantloadfactoris (A)100%

(B)75%

(C)50%

(D)20%

Page 3: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q7. Whichstatementaboutthedailyloadcurveisvalid?

(A) Theareaunderthecurvegivestheaveragedemand

(B) Theratiooftheareaunderthecurvestothetotalareaofrectangleinwhichitis

containedgivestheloadfactorfortheday

(C) Thepeakofthecurvegivesthe'installedcapacityoftheplant

(D) Theareaofthecurvesdividedbythenumberofhoursgivesloadfactor

Q8. AnEquipmentpurchasedforRs10,000twoyearsagohasamarketvalueofRs

12500atpresent.Itcanbeconcludedthat

(A) thevaluehasdepreciatedaccordingtostraightlinemethod

(B) thevaluehasdepreciatedaccordingtodiminishingvaluemethod

(C) thevaluehasdepreciatedaccordingtosinkingfundmethod

(D) thevaluehasappreciatedwiththetime

Q9. Inasteampowerplantwhichcomponentneedsmaximummaintenanceattention?

(A) Condenser

(B) Boiler

(C) Turbine

(D) Water treatment plant

Page 4: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

FourloadsasshowninfiguregivenbelowareconnectedtoapowerstationAbsciseistimefrom

0to24hrsinallcases,OrdinaterepresentstheloadinKW

Q10. Whichloadhasthelowestaveragedemand?

LoadA

LoadB

LoadC

LoadD

Q11. Whichloadsoffertheidenticalaverageload?

(A) AandB

(B) BandC

(C) CandD

(D) A, B andD

Q12. Thepeakloadontheplantis

Page 5: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(A) 3000KW

(B) 3500KW

(C) 4000KW

(D) 4250KW

Q13. Theloadfactoroftheplantsupplyingpowertotheseloadswillbenearly

(A)11%

(B)15%

(C)18%

(D)21%

Q14. Thediversityfactoroftheplantsupplyingtheseloadswillbe

(A)0.5

(B)1.0

(C)1.5

(D) 0.2 Define

Q 15.

n

∑PGi−PD −PLoss=0 i=1

(A) Real Power balanceconstraints

(B) Generation capacity constraint

(C) Both A andB

(D) None ofthem

Page 6: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Gi Gi Gi

Q16. Pmin≤P≤Pmax,i=1,2,…….,

(A) Real Power balanceconstraints

(B) Generation capacity constraint

(C) Both A andB

(D) None ofthem

Q17. Sli≤ Smaxli, i = 1, ...,NL

(A) Real Power balanceconstraints

(B) Generation capacityconstraint

(C) Securityconstraints

(D) None ofthem

Q18. F(P N

)=∑a+bP +c P2 Wherei=1, .......................... ,N Gi i i Gi

i=0 i Gi

(A) Real Power balanceconstraints

(B) Generation capacity constraint

(C) Security constraints

(D) None ofthem

Q19. Followingpowerplanthasinstantstarting

(A) nuclear powerplant

(B) hydro powerplant

(C) diesel powerplant

(D) both (b) and(c)

Page 7: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q20. Whichofthefollowinggeneratingstationhasminimumruiningcost?

(A) Nuclear

(B) Hydro

(C) Thermal

(D) Diesel

Q21. This curve isshowing?

(A) Increment Fuel CostCurve

(B) Input OutputCurve

(C) Operating costcurve

(D) None ofthese

Q22. Optimal system operationinvolved

(A) Economy ofoperation

(B) Systemsecurity

(C) Emissionsatcertainfossil-fuelplants

(D) All ofabove

Q23. Optimalsystemoperationmaysayas

(A) Economy of operation of PowerSystem

(B) Emission of operation of PowerSystem

Page 8: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(C) BothAandB

(D) None ofthem

Q24. Theeconomicdispatchproblemisusetocalculate

(A) Minimizethetotalcostofgeneratingrealpower

(B) Minimizethetotalcostofgeneratingreactivepower

(C) BothAandB

(D) None ofthem

Q25. Optimal system operationinvolved

(A) Economy ofoperation

(B) Systemsecurity

(C) BothAandB

(D) None ofthem

Q26. Which power plant is neglecting operatingcost

(A) Hydroplant

(B) Thermalplants

(C) Nuclearplant

(D) None ofthem

Q27. Which power plant is considering operatingcost

(A) Hydroplant

(B) Thermalplants

(C) Nuclearplant

(D) BothBandC

Page 9: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q28. Input-outputcurveofageneratingunitdrawinbetween

(A) Operating cost and powergeneration

(B) PowerGenerationAndOperatingCost

(C) Both OfAbove

(D) None OfThese

Q29. Operating cost consistof

(A) Fuelcost

(B) Maintenancecost

(C) BothAandB

(D) OnlyA

Q30. Incremental cost curveis

(A) Slope of Input outputcurve

(B) Slope of loadcurve

(C) BothAandB

(D) None ofabove

Q31. Ageneratingstationisnoteconomicalat

(A) AbovethePGimin

(B) Equal to thePGi

(C) BelowthePGimax

(D) BelowthePGimi

Q32. Ageneratingstationisnoteconomicalat

(A) EqualtothePGimin

(B) Equal to thePGi

(C) AbovethePGimax

(D) AbovethePGimin

Q33. Ageneratingstationiseconomicalat

(A) EqualtothePGimin

(B) Equal to thePGi

(C) BelowthePGimax

Page 10: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(D) All theabove

Q34. Incrementalfuelcost(IC)defineas

(A) IC= dCi

d PGi

(B) IC=dPGi

d Ci N

(C) IC=∑ a + b P+c P2

i i Gi iGi

i=0

(D) None ofthese

Q35. The system constraintare

(A) EqualityConstraint

(B) Inequalityconstraint

(C) BothAandB

(D) None ofthese

Q36. IncrementtheICvaluebyΔICincaseof

n

(A) ∑PGi−PD<0 i=1

n

(B) ∑PGi−PD >0 i=1

n

(C) ∑PGi−PD=0 i=1

(D) None ofthese

Q37. IncrementtheICvaluebyΔICincaseof

n

(A) ∑PGi−PD <0 i=1

n

(B) ∑PGi−PD>0 i=1

n

(C) ∑PGi−PD=0 i=1

(D) None ofthese

Page 11: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Y

Y

Y

Y

= ∧ =

Q38.“Itsloadingfromnowonisheldfixedatthisvalueandthebalanceloadisthen

sharedbetweentheremaininggeneratorsonequalincrementalcostbasis.”Thistheory knows

(A) Patton’s securitytheory

(B) Kuhn-Tuckertheory

(C) BothAandB

(D) None ofthese

Q39. IncrementalfuelcostsinrupeesperMWhforaplantconsistingoftwounitsare:

IC1=0.20PG1+40

IC2=0.25PG2+30

Where PG1 and PG2(inMW)arepowergeneratedbyboththeunitsforatotaldemandof

250MW,Thetotalsharedbythetwounitsare

(A) P

350 P

G1 3 400

G2 3

(B) PG 1=100∧ PG2=250

(C) PG 1=125∧ PG2=125

(D) PG 1=150∧ PG2=100

Q40.“Itsloadingfromnowonisheldfixedatthisvalueandthebalanceloadisthen

sharedbetweentheremaininggeneratorsonequalincrementalcostbasis.”Thistheory knows

(A) Patton’s securitytheory

(B) Kuhn-Tuckertheory

(C) BothAandB

(D) None ofthese

Q41. Dynamicprogrammingmethodequationis

(A) FN

(B) FN

(x)=min{F

(x)=min{F

(y)+F

(y)+F

N−1

N−1

( x− y ) }

( x+ y )}

(C) FN (x)=min{F

N−1 (y)+FN ( x− y ) }

(D) FN (x) )=min{F (y)+F N+1 ( x− y )}

Questions 42 to 44 refer to the data given below:

N

N

N

Page 12: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Theinput-outputcurveofa0.5MWgeneratingstationsisdefinedby I=30+0.8L+0.5L2

Where I is in MKcal and L is in megawatts

Q42. Theinputwhentheplantwasrunningonnoloadwas

(A) 0.5kcal

(B) 31.3kcal

(C) 30 x 106kcal

(D) zero

Q43. Totalinputwhentheplantwasgenerating35MWwas

(A) 181x106kcal/hr

(B) 250x106kcal/hr

(C) 362.5 x 106kcal/hr

(D) 582xl26kcal/hr

Q44. Whentheloadonthegeneratorwas25MWtheheatrateinkcal/MWhrwas nearly

(A)16x106

(B)20x106

(C)30x106

(D) 31.3 x 106

Questions 45 to 48 refer to the data given below:

ManufacturerAoffershisequipmentcostingRs150,000+45xKW the equipmentis

guaranteedtogivethefollowingoperatingcostRs18+0.007KWh

ManufacturerBoffershisequipmentcostingRs1,12000+50xKWTheoperatingcostis guaranteed as Rs 16.50 +

0.0072KWh

Page 13: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

KW indicates machine rating and KWh indicates output

Q45. Whichmachineischeapertoownin5000KWrange

(A) MachinesuppliedbymanufacturerA

(B) MachinesuppliedbymanufacturerB

(C) Both have identical initialcost

(D) Both have identical operatingcost

Q46. AtwhatKWratingtheinitialcostofthetwomachineswillbeidentical?

(A) 5500KW

(B) 6000KW

(C) 7600KW

(D) 8500KW

Q47. AtwhatratinginKWhthetwosetswillbeequallyeconomicaltooperate?

(A) 5000KWh

(B) 7500KWh

(C) 75000KWh

(D)50,000 KWh

Q48. Power factor is givenby

(A) KWh /KW

(B) activepower/reactivepower

(C) reactivepower/activepower

(D) KW /KWh

Q49. Forthesamecylinderdimensionsandspeed,whichenginewillproduceleast power?

(A) Petrolengine

Page 14: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(B) Dieselengine

(C) Super chargedengine

(D) All will produce samepower

Q50. ForunderwatermovementSubmarinesarepoweredby?

(A) Dieselengines

(B) Airmotors

(C) Batteries

(D) Steamaccumulators

Q51. Ships are generally poweredby

(A) Dieselengines

(B) Hydraulicturbines

(C) Nuclear powerplants

(D) Steamaccumulators

Q52. Aturbojetaeroplanehas

(A) Noblades

(B) Twoblades

(C) Threeblades

(D) Fourblades

Q53. Aninterconnectedsystemhasthefollowingplants I

runofftheriverplant

II Nuclearpowerplant

III Steampowerplant

IV Hydro-electric plant withstorage

Page 15: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

V Diesel engineplant

Which two plants can be exclusively used for base load?

(A) I andII

(E) II andIII

(F) IIandIV

(G) II andV

Q54. Whichplantcanbeusedexclusivelyforpeakload?

(A) I

(B) III

(C) IV

(D) V

Q55. Directconversionofbeatintoelectricalenergyispossiblethrough

(A) Magneto hydrodynamicgenerators

(B) Solarcells

(C) Fuelcells

(D) notpossible

Q56. Inafuelcellelectricityisproducedby

(A) Combustionoffuelinabsenceofoxygen

(B) Oxidation offuel

(C) Thermionicaction

(D) Any of theabove

Q57.AcertainplanthasfixedcostofRs40,000andasalvagevalueofRs4000atthe

endofausefullifeof20yearsThedepreciatedvalueoftheplantattheendof10years

willbeleast(interestratebeing6%compoundedannually)whencalculatedby

(A) Straight linemethod

(B) Sinking fundmethod

Page 16: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(C) Diminishing valuemethod

Q58. Intheaboveproblemthevaluewillbehighestwhencalculatedby

(A) Straight linemethod

(B) Sinking fundmethod

(C) Diminishing valuemethod

Q59. Lowpowerfactorisusuallynotdueto

(A) Incandescentlamp

(B) Inductionmotors

(C) Arclamps

(D) Fluorescenttubes

Q60. WhichtypeofplanthastheleastrunningcostperKWhofenergygenerated?

(A) Hydro-electricplant

(B) Thermal powerplant

(C) Nuclear powerplant

(D) Diesel powerplant

Q61. Base load plantshave

(A) Highcapitalcost,highoperatingcostandhighloadfactor

(B) Highcapitalcost,lowoperatingcostandhighloadfactor

(C) Lowcapitalcost,lowoperatingcostandlowloadfactor

(D) Lowcapitalcost,highoperationcostandhighloadfactor

Page 17: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q62. Whichalternatorwillhavemorenumberofpoles

(A) Coupled to hydraulicturbine

(B) Coupled to steamturbine

(C) Coupled to gasturbine

(D) Allwillhavesamenumberofpoles

Q63. Whichalternatorusuallyrunsatslowspeedascomparedtoothers

(A) Coupled to gasturbine

(B) Coupled to steamturbine

(C) Coupled to hydraulicturbine

(D) Coupled to dieselengine

Q64. Inathermalpowerstationofmoderatesize,theelectricalpowerisgeneratedata voltageof

(A) 115V

(B) 230V

(C) 440V

(D) 11kV

Q65. Theresistanceofthedryskinofhumanbody,betweenthetipofthelefthand

fingerandrighthandfinger,isoftheorderof

(A) 100ohms

(B) 1000ohms

Page 18: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(C) 10,000ohms

(D) 100,000 ohms

Q66. Iftheresistanceofdryskinofhumanbodyis100,000ohms,theresistanceofthe wet body willbe

(A) 100,000 ohms

(B) 200,000 ohms (C)

5000,000 ohms

(D) 5000ohms

Q67. Theeffectofelectricshockonhuman,bodydependson

(A) Voltage

(B) Current

(C) Duration ofcontact

(D) All of theabove

Q68. Acurrentof10millamperesthroughhumanbody

(A) Will cause mildsensation

(B) Will affect musclecontrol

(C) Will affectbreathing

(D) Will causedeath

Q69. Deathisalmostcertainwhenthecurrentthroughhumanbodyis

(A) 10 millamperes

Page 19: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(B) 20 millamperes

(C) 40 millamperes

(D) 100milliamperes

Q70. For extinguishing electricalfires

(A) Water should beused

(B) Carbondioxidefireextinguishershouldbeused

(C) Foamtypefireextinguishershouldbeused

(D) Carbontetrachloridefireextinguishershouldbeused

Q71. Firstaidforelectricshockvictimis

(A) Bandage

(B) Massage

(C) Pouring water onbody

(D) Artificialrespiration

Multiple Choice Questions of Economics of Power Generation (168-182):

Q72. Whenapowerplantisnotabletomeetthedemandofconsumersitwillresortto

(A) Penalizinghighloadconsumersbyincreasingthechargesforelectricity

(B) Power factor improvement at thegenerators

(C) Efficient plantoperation

(D) Loadshedding.

Q73. Load shedding is possiblethrough

(A) Voltagereduction

(B) Frequencyreduction

(C) Switching off theloads

Page 20: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(D) Any of theabove.

Q74. Whichofthefollowingpowerplantscangeneratepoweratunpredictableor uncontrollabletimes?

(A) Wind powerplant

(B) Tidal powerplant

(C) Solar powerplant

(D) Anyoftheabove.

Q75. Directconversionofheatintoelectricalpowerispossiblethrough

(A) Thermionicconverter

(B) Fuelcell

(C) Batteries

(D) all of theabove.

Q76. Inafuelcellpositiveelectrodeisof

(A) Oxygen

(B) Ammonia

(C) Hydrogen

(D) Carbonmonoxide.

Q77. AllofthefollowingaresourcesofborrowingmoneyEXCEPT

(A) Debentures

(B) Bonds

(C) Share

(D) Fixeddeposits.

Page 21: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q78. Ideallydepreciatedvalueoftheplantplustheaccumulationinthedepreciation fund should be equalto

(A) Salvagevalue

(B) Obsolescencerate

(C) Sinkingfund

(D) Original investedcapital.

Q79. Inpowerplantsinsurancecoverisprovidedfor

(A) Equipmentonly

(B) Skilled workersonly

(C) Unskilled workersonly

(D) all of theabove.

Q80. Debenture :Interest::

(A) Capital:Depreciation

(B) Insurance:Mishap

(C) Sinking fund:Amortization

(D) Shares:Dividend.

Q81. Maximumdemandtariffisgenerallynotappliedtodomesticconsumersbecause

(A) They cannot affordtoday

(B) They consume lesspower

(C) Their load factor islow

Page 22: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(D) Their maximum demand islow.

Q82. Howmuchmustbedepositedattheendofeachyearinasinkingfundfor15

yearstoaccumulateRs1000ifinterestisat5percent?

(A) Rs46.34

(B) Rs54.55

(C) Rs 59.50

(D) Rs 60.00.

Q83. IfRs.50weredepositedattheendofeachyearfor12yearsinasinkingfund

earning6%,thetotalaccumulationwouldbe

(A) Rs 1000 (B)

Rs 925.50 (C) Rs

843.50 (D)

Rs799.75.

Q84. Anadvantageofstaticcapacitorforpowerfactorimprovementis

(A) Lowlosses

(B) Little maintenancecost

(C) Case ininstallation

(D) All of theabove.

Q85. AllofthefollowingarerepayableaftersometimeEXCEPT

(A) Bonds

Page 23: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(B) Shares

(C) Cashcertificates

(D) Fixeddeposits

Q86. The usual valueof

(A) Diversityfactorislessthanoneanddemandfactorismorethanone

(B) Diversityfactormorethanoneanddemandfactorislessthanisone

(C) Diversityfactoraswellasdemandfactorislessthandemand

(D) Diversityfactoraswellasdemandfactorismorethanone.

Multiple Choice Questions of Economics of Power Generation (183-197)

Q87. Theamountrepaidtoapersonattheendof15years,whoinvestsRs12,000at4

percentinterestcompoundedannually,willbe

(A) Rs12,400

(B)Rs16,120

(C)Rs21,612

(D) Rs 26,121.

Q88. WhatisthepresentworthofreceivingRs1000twentyyearsfromnowifmoney

canearn5%interestcompoundedannually?

(A) Rs376.93

(B)Rs445.50

(C)Rs500.00

(D) Rs 617.27.

Page 24: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Questions 185 to 187 refer to data given below:

Rs 10,000 are invested for 20 years at 6 percent.

Q89. Theamountaccumulated,whentheinterestiscompoundedannuallywillbe (A) Rs27,020

(B)Rs30,270

(C)Rs32,070

(D) Rs 35,600.

Q90. Theamountaccumulatedwhentheinterestiscompoundedsemi-annuallywillbe (A) Rs32,070

(B)Rs32,474

(C)Rs,32,620

(D)Rs32,888.

Q91. Theamountaccumulatedwhentheinterestiscompoundedmonthlywillbe (A) Rs32,070

(B)Rs32,620

(C)Rs32,898

(D) Rs 33,100.

Q92. Astheloadfactorapproachesunity,theshapeofloaddurationcurvewillbe nearly

Page 25: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(A) Lshaped

(B) Inverted Tshaped

(C) Triangular

(D) Rectangular.

Q93. Whenmaximumandaverageloadsareequal,theloadfactorwillbe

(A) Zero

(B) 0.01

(C)0.5

(D)1.0

Q94. Whichofthefollowingrelationisincorrect?

(A) Capacityfactor=UtilizationfactorxLoadfactor

(B) LoadfactorxMaximumload=Averageload

(C) DemandfactorxConnectedload=Maximumdemand

(D) None of theabove.

Q95. Capacityfactorandloadfactorbecomeidenticalwhen

(A) Peakloadisequaltothecapacityoftheplant

(B) Averageloadishalfthecapacityoftheplant

(C) Averageloadissameaspeakload

(D) Groupdiversityfactorisequaltopeakdiversityfactor.

Q96. Alowutilizationfactorforaplantindicatesthat

Page 26: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(A) Plant is undermaintenance

(B) Plantisusedforbaseloadonly

(C) Plantisusedforstandbypurposeonly

(D) Plantisusedforpeakloadaswellasbaseload.

Questions 95 to 96 refer to the following data:

Power plants considered are

I. Diesel

II. Thermal

III. Hydro

IV. Nuclear.

Q97. PlantsinascendingorderofcapitalcostperMWare

(A) I, II, III,IV

(B) II,III,IV,I

(C) III,IV,I,II

(D) IV.III,I,II

Q98. Plantsindescendingorderoftheirexpectedusefullifeare

(A) I,III,II,IV

(B) II,I,III,IV

(C) III,II,IV,I

(D) IV, I, II,III.

Page 27: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q99. PlantsinascendingorderoftheiroperatingcostperMWHgeneratedare

(A) IV,I,II,III

(B) III,II,IV,I

(C) II,I,III,IV

(D) I,III,II,IV

Q100. Sinking fundis

(A) Initialvalue-Salvagevalue

(B) Capitalcost-Operatingcost

(C) Periodicalmaintenance-Breakdownmaintenance

(D) Capital cost / Usefullife.

Page 28: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

1 D 21 A 41 A 61 B 81 D

2 B 22 D 42 C 62 A 82 A

3 A 23 A 43 C 63 C 83 C

4 C 24 A 44 A 64 D 84 D

5 C 25 C 45 B 65 D 85 B

6 A 26 A 46 C 66 D 86 B

7 D 27 D 47 C 67 D 87 C

8 D 28 A 48 B 68 A 88 A

9 B 29 C 49 A 69 D 89 C

10 C 30 A 50 C 70 D 90 C

11 D 31 D 51 A 71 D 91 D

12 D 32 C 52 A 72 D 92 D

13 A 33 D 53 A 73 D 93 D

14 B 34 A 54 D 74 D 94 D

15 A 35 C 55 A 75 A 95 A

16 B 36 A 56 B 76 A 96 C

17 C 37 B 57 C 77 C 97 A

18 C 38 B 58 B 78 D 98 C

19 D 39 A 59 A 79 D 99 B

20 B 40 B 60 A 80 D 100 A

Page 29: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Unit -2

Q101. Load curve helps indeciding

(A) Sizes of the generationunits

(B) Totalinstalledcapacityoftheplant

(C) Operating schedule of generatingunits

(D) all of theabove.

Multiple Choice Questions of Economics of Power Generation (91-106):

Q102. Majorshareofpowerproducedisthrough

(A) Thermal powerplants

(B) Hydro electric powerplants

(C) Nuclear powerplants

(D) Diesel powerplants

Q103. Essentialrequirementofpeakloadplant

(A) Itshouldbecapableofstandingquickly

(B) It should be run at highspeed

(C) Itshouldprovideathighvoltage

(D) Itshouldbesmallinsize

Q104. Whichofthefollowingplantsisalmostinevitablyusedasbaseloadplant?

(A) Gas turbineplant

(B) Diesel engineplant

(C) Pumped storageplant

(D) Nuclear powerplant

Q105. Athermalpowerstationwasdesignedtobumcoalcontaining12%ash

Whentheplantactuallystartedoperatingcoalhaving22%ashwasmadeavailable

Whichunitoftheplantwillneedmajormodifications?

(A) Water treatmentplant

Page 30: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(B) Pulverizingunit

(C) Ash handlingunit

(D) Coolingtowers

Q106. Efficiencyissecondaryconsiderationincaseof

(A) peak loadplants

(B) Base loadplants

(C) Bothpeakloadandbaseloadplants

(D) None of theabove

Q107. Whichofthefollowingplantswilltakeleasttimeinstartingfromcoldconditions to full

loadoperation?

(A) Nuclear powerplant

(B) Steam powerplants

(C) Hydro-electricplant

(D) Gas turbineplant

Q108. During loadshedding

(A) System voltage isreduced

(B) System frequency isreduced

(C) Some loads are switchedoff

(D) System power factor ischanged

Q109. Forthesameplantsize,initialcostofwhichplantisthehighest?

(A) Steampowerplant

(B) Diesel engineplant

(C) Nuclear powerplant

Page 31: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(D) Gas turbineplant

Q110.Aconsumertakesasteadyloadof200kWatapowerfactorof0.85laggingfor8

hoursperdayand315daysperannum.TheannualpaymentunderthetariffofRs80per

annumperkAplus10centsperkWhwillbe

(A) Rs 5040 (B)

Rs 50,400 (C) Rs

69,200 (D)

Rs88,400

Questions 111 to 115 refer to the data given below:

Theestimatedtotalannualoperatingcostandcapitalchargesfortwoproposedpowerstations

aregivenbythefollowingexpressions

AnnualcostofstationA=Rs(600,000+3.0kW+0.015kWhr)AnnualcostofstationB=Rs

(750,000+5.0kW+0.014kWhr)

WherekWrepresentsthecapacityofthestationandkWhrepresentsthetotalannualoutput

Loaddurationcurveoftheplantisshowninthefiguregivenbelow

Q111. Whichstationmaybeselectedforbaseload?

(A) StationA

(B) StationB

Page 32: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(C) Any of theabove

Q112. Baseloadplantshouldbeoperatedannuallyfor

(A) 500hrs

(B) 1000hrs

(C) 2000hrs

(D) 5000hrs

Q113. Thecapacityofthebaseloadplantshouldnotbelessthan

(A) 3860kW

(B) 4180kW

(C) 5000kW

(D) 5500kW

Q114. TotalkWhsuppliedbytheplantis (A) 10.l

x106

(B)15x106

(C)18x106

(D) 21.9 x 106

Q115. TotalkWhtobesuppliedbybaseplantmustbe (A) 19 .76

x106

(B) 15.34 x 106

(C)14.1x106

(D)10.3x106

Page 33: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q116. Foraloadflowsolutionthequantitiesnormallyspecifiedatavoltagecontrolled busare:

(A) P andQ

(B) PandIVI

(C) QandIVI

(D) P andᵟ

Q117. Fora15-buspowersystemwith3voltagecontrolledbus,thesizeofJacobian

matrixis(a)11x11(b)12x12(c)24x24(d)28x28.

In the solution of load-flow equation, Newton-Raphon (NR) method is superior to the Gauss-

Seidal (GS) method, because the

(A) timetakentoperformoneiterationintheNRmethodislesswhencomparedto

thetimetakenintheGSmethod

(B) numberofiterationrequiredintheNRmethodismorewhencomparedtothatin the GSmethod

(C) numberofiterationsrequiredisnotindependentofthesizeofthesysteminthe NRmethod

(D) convergencecharacteristicoftheNRmethodarenotaffectedbytheselectionof slackbus.

Q118. Whichoneofthefollowingmatricesrevealsthetopologyofthepowersystem network?

(A) Bus incidencematrix

(B) Primitive impedancematrix

(C) Primitive admittancematrix

(D) Bus impedancematrix.

Q119. Inload-flowanalysis,theloadatabusisrepresentedas

Page 34: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(A) aconstantcurrentdrawnfromthebus

(B) aconstantimpedanceconnectedatthebus

(C) constantrealandreactivepowersdrawnfromthebus

(D) avoltage-dependentimpedanceatthebus. (E)

Q120. InGauss-Seidelmethodofpowerflowproblem,thenumberofiterationsmaybe re-

ducedifthecorrectioninvoltageateachbusismultipliedby

(A) Gaussconstant

(B) Acceleration constant

(C) Deceleration constant

(D) Blockingfactor.

Q121. Considerthefollowingstatements:1.ItiseasiertoconstructtheYBusmatrixas

comparedtoZBus.2.ZBusisafullmatrixwhileYbusissparse.3.Y-buscanbeeasily

modifiedwheneverthenetworkchangesascomparedtotheZBus.Whichofthese statements are correct?

(A) 1and2

(B) 2and3

(C) 1and3

(D) 1, 2 and3.

Q122. Inloadflowstudiesofapowersystem,avoltagecontrolbusisspecifiedby Real power and

reactivepower

Real power and voltage magnitude Voltage

and voltage phase angle

Page 35: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Reactive power and voltagemagnitude.

Q123. Atslackbus,whichoneofthefollowingcombinationsofvariablesisspecified?

(A) I VI,ᵟ

(B) P,Q

(C) P, I VI

(D) Q,IVI.

Q124. Considerthefollowingquantities:1.Realpower3.Powerfactor5.Busvoltage magnitude

2. Reactive power 4. Input current 6. Bus voltage phase-angle.

Forthepurposeoftheloadflowstudiesofapowersystem,eachbusornodeisassociatedwith

whichoneofthecombinationsoftheabovefourquantities?

(A) 1, 3, 4 and 5

(B) 1, 2, 3 and 4

(C) 2,3,5and6

(D)1,2,5and6.

Q125. Normally ZBUSmatrix isa

(A) Nullmatrix

(B) Fullmatrix

(C) Sparsematrix

(D) Unitymatrix.

Q126. Gausss-Seideliterativemethodcanbeusedforsolvingasetof

(A) Linear differential equationsonly

Page 36: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(B) Linear algebraic equationsonly

(C) Bothlinearandnonlinearalgebraicequations

(D) Bothlinearandnonlineardifferentialequations

Q127. Apowersystemconsistsof300busesoutofwhich20busesaregeneratorbuses,

25busesaretheoneswithreactivepowersupportand15busesaretheoneswithfixed

shuntcapacitors.Alltheotherbusesareloadbuses.Itisproposedtoperformaloadflow

analysisforthesystemusingNewton-Raphsonmethod.ThesizeoftheNewton-

Raphson Jacobian matrix is (a)

553 x553

(b)540x540

(c)555x555

(d)554x554

Q128. Inload-flowanalysis,theloadatabusisrepresentedas

(a) Aconstantcurrentdrawnfromthebus

(b) Aconstantimpedanceconnectedatthebus

(c) Constantrealandreactivepowersdrawnfromthebus

(d) Avoltage-dependentimpedanceatthebus

Q129. Economicschedulingofgenerationisperformedforaperiodof

(a) 1/2hr

(b) 24hr

(c) 1sec

(d) 1week

Q130. Theinput-outputcharacteristicisplotted

Page 37: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(a) Fuel input Vs poweroutput

(b) Fuel input Vstime

(c) Fuel rate Vs poweroutput

(d) Fuel rate Vs energyoutput

Q131. Hearratecurveisplottedin

(a) k-cal/kwhr VsKW

(b) K-cal/hr VsKW

(c) k-cal/KW VsKw

(d) K-cal VsKW

Q132. Incrementalproductioncostandincrementalfuelcostare

(a) both thesame

(b) IPC>IFC

(c) IPC<IFC

(d) They are notrelated

Q133. Inpowersystemeachbusisassociatedwithhowmanyquantities.

(a) 4

(b) 3

(c) 5

(d) none

Q134. Ifrealandreactivepowercomponentsarespecifiedthenitiswhichtypeofbus.

(a) PQbus

Page 38: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(b) PVbus

(c) slackbus

(d) none

Q135. Forwhichbusinthepowersystemthevoltagemagnitudecorrespondingtothe

generationvoltageandrealpowercorrespondingtoitsratingsarespecified.

(a) PQbus

(b) PVbus

(c) slackbus

(d) none

Q136. Whichbusisinthepowersystemismadetotakeadditionalrealandreactive power to supply

transmissionlosses.

(a) PQbus

(b) PVbus

(c) slackbus

(d) none

Q137. Forwhichbuswehavetofindoutthevoltagemagnitudeandphaseangleofthe

busthroughtheloadflowsolution.

(a) PQbus

(b) PVbus

(c) slackbus

(d) none

Q138. Forwhichbuswehavetofindoutthereactivepowergenerationandphaseangle of the bus through the load

flowsolution

(a) PQbus

(b) PVbus

Page 39: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(c) slackbus

(d) none

Q139. DiagonalelementoftheYBUSmatrixisselfadmittance.

(a) True

(b) false

Q140. IBUS=YBUSVBUS,istheequationfornbussystem,inthisthematixsizeofYBUSisnXn.

(A) True

(B) False

(C) Nonepossible

Q141. IBUS=YBUSVBUS,istheequationfornbussystem,inthisthematixsizeofYBUSisnX1.

(a) True

(b) False

Q142. IBUS=YBUSVBUS,istheequationfornbussystem,inthisthematixsizeofYBUSis

(a) nXn

(b) 1Xn

(c) nX1

(d) 1X1

Q143. IBUS=YBUSVBUS,istheequationfornbussystem,inthisthematixsizeofIBUSis

(A) nXn

Page 40: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(B) 1Xn

(C) nX1

(D) 1X1

Q144. IBUS=YBUSVBUS,istheequationfornbussystem,inthisthematixsizeof VBUSis

(a) nXn

(b) 1Xn

(c) nX1

(d) 1X1

Q145. YBUSisthenXnmatrix,wherenisthenumberofbuses.

(a) true

(b) false

Q146. YBUSisthesymmetricmatrix

(a) true

(b) false

Q147. DiagonalelementoftheYBUSmatrixis

(a) selfadmittance

(b) transferadmittance

(c) both

(d) none

Q148. off-DiagonalelementoftheYBUSmatrixis

(a) selfadmittance

(b) transferadmittance

(c) both

Page 41: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(d) none

Q149. ZBUSisafullmatrix

(a) true

(b) false

Q150. Forconveniencewhichbusisconsideredasslackbus.

(a) Firstbus

(b) lastbus

(c) middlebus

(d) none.

Q151. SlackbusisalsocalledSwingbus

(a) true

(b) false

Q152. slackbusisalsocalledReferencebus

(a) true

(b) false

Q153. LoadbusisalsocalledPVbus

(a) true

(b) false

Q154. LoadbusisalsocalledPQbus

(a) true

(b) false

Q155. generator bus is also called PQbus

(a) true

(b) false

Page 42: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q156. generator bus is also called PVbus

(a) true

(b) false

Q157. Loadflowsolutionisthesolutionunderwhichcondition

(a) steady statecondition

(b) transientcondition

(c) both

(d) none

Q158. Loadflowsolutionforpowernetworkcanbeworkedoutoperationunder

(a) balancedcondition

(b) unbalancedcondition

(c) both

(d) none

Q159. Inpowersystemeachbusisassociatedwith

(a) fourquantities

(b) threequantities

(c) fivequantities

(d) none

Q160. Ifrealandreactivepowercomponentsarespecifiedthenitiswhichtypeofbus.

(a) loadbus

(b) generatorbus

(c) slackbus

(d) none

Page 43: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q161. Forwhichbusinthepowersystemthevoltagemagnitudecorrespondingtothe

generationvoltageandrealpowercorrespondingtoitsratingsarespecified

(a) loadbus

(b) generatorbus

(c) slackbus

(d) none

Q162. Whichbusisinthepowersystemismadetotakeadditionalrealandreactive power to supply

transmissionlosses.

(a) loadbus

(b) generatorbus

(c) slackbus

(d) none

Q163. Forwhichbuswehavetofindoutthevoltagemagnitudeandphaseangleofthe

busthroughtheloadflowsolution.

(a) loadbus

(b) generatorbus

(c) slackbus

(d) none

Q164. Forwhichbuswehavetofindoutthereactivepowergenerationandphaseangle of the bus through the load

flowsolution

(a) loadbus

(b) generatorbus

(c) slackbus

(d) none

Q165. slackbusisinthepowersystemismadetotakeadditionalrealandreactive power to supply

transmissionlosses.

Page 44: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(a) true

(b) false

Q166. Forgeneratorbuswehavetofindoutthevoltagemagnitudeandphaseangleof

thebusthroughtheloadflowsolution

(a) True

(b) False

Q167. Forgeneratorbuswehavetofindoutthereactivepowergenerationandphase angle of the bus through

the load flowsolution.

a) true

b) false

Q168. Thevoltagecontrolledbusistreatedasaloadbusinsubsequentiterationwhenits Voltage limit isviolated.

(a) True

(b) False

Q169. Thevoltagecontrolledbusistreatedasaloadbusinsubsequentiterationwhen

its:activepowerlimitisviolated.

(a) true

(b) false

Q170. TheloadflowsolutionisalwaysassuredincaseofNewton-Raphsonmethod.

(a) True

(b) False

Q171. Thebusadmittancematrix(Ybus)ofapowersystemisSymmetricmatrix.

(a) true

(b) false

Page 45: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q172. Thebusadmittancematrix(Ybus)ofapowersystemisSparsematrix.

a) true

b) false

Q173. Thebusadmittancematrix(Ybus)ofapowersystemisequaltoZbusmatrix.

(a) True

(b) False

Q174. Thevoltagecontrolledbusistreatedasaloadbusinsubsequentiterationwhen its:

a) Voltage limit isvoilated

b) active power limit isvoilated

c) Reactive power limit isvoilated

d) Phase angle limit isvoilated

Q175. Theloadflowsolutionisalwaysassuredincaseof:

(a) Newton-Raphsonmethod

(b) Gaussmethod

(c) Gauss -Seidelmethod

(d) None of these methodguarantees

Q176.ComparedtoGauss-Seidelmethod,Newton-Raphsonmethodtakes: (a)less number

ofiterations

(b)morenumberofiterations

(c)equalnumberofiterations none

ofthese

Page 46: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q177.ComparedtoGauss-Seidelmethod,Newton-Raphsonmethodtakes: (a)less time

periteration

(b) moretimeperiteration

(c)equaltimeperiteration

(d)none ofthese

Q178. Atslackbus,whichoneofthefollowingcombinationofvariablesisspecified?

(a) |V|,δ

(b) P,θ

(c) P,|V|

(d) θ,|V|

Q179. AtGeneratorbus,whichoneofthefollowingcombinationofvariablesis specified?

(a) |V|,δ

(b) P,|V|

(c) P,θ

(d) θ,|V|

Q180. AtLoadbus,whichoneofthefollowingcombinationofvariablesisspecified?

(a) P,θ

(b) θ,|V|

(c) |V|,δ

(d) P,Q

Q181. Whichofthefollowingquantityisassociatedwitheachbusornodeforthe

purposeofloadflowstudiesofapowersystem

Page 47: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(a) Realpower

(b) powerfactor

(c) Inputcurrent

(d) frequency

Q182. Thebusadmittancematrix(Ybus)ofapowersystemisnot

(a) Symmetric

(b) a squarematrix

(c) a fullmatrix

(d) generallyhavingdominantdiagonalelements

Q183. Ifavoltagecontrolledbusistreatedasloadbus,thenwhichofthefollowing limits would

beviolated?

(a) Volatge

(b) Activepower

(c) Reactivepower

(d) phaseangle

Q184. Fora15-buspowersystemwith3voltagecontrolledbus,thesizeofJacobian matrixis

(a)11X11

(b)12X12

(c)24X24

(d)28X28

Q185. Thediagonalelementsofanodaladmittancematrixarestrengthenbyadding

Page 48: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(a) Shuntinductances

(b) shuntcapacitances

(c) loads

(d) Generators

Q186. Theloadflowsolutionisalwaysassuredincaseof:

a. Newton-Raphsonmethod

b. Gaussmethod

c. Gauss-Seidelmethod

d. Noneofthesemethodsguarantees

Q187. Inwhichofthefollowingmethodsofloadflowanalysistheconvergenceof

solutiondoesnotdependuponchoiceofslackbus

a. Newton-Raphsonmethod

b. Gaussmethod

c. Gauss-Seidel

d. none ofthese

Q188. InaYbusmatrixthediagonalelementofeachnodeisobtainedby

a. Multiplying the admittances connected toit

b. Adding the admittances connected toit

c. Subtracting the admittances connected toit

d. None ofthese

Page 49: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q189. Whichfundamentallawisappliedateachnodeinamultibussystemtoobtain Ybusmatrix

a. KVL

b. KCL

c. both

d. one of theabove

Q190. Inalargesystemof100nodes,thenon-zeroelementsmaybeassmallas a.20%

b.22%

c. 2%

d. 9%

Q191. TheBusadmittancematrixYbusis

a. Singularmatrix

b. Symmetricmatrix

c. Sparsematrix

d. All of theabove

Q192. Inloadflowstudiesofapowersystem,avoltagecontrolbusisspecifiedby

a. Realpowerandreactivepower

b. Realpowerandvoltagemagnitude

c. Voltage and voltage phaseangle

d. Reactivepowerandvoltagemagnitude

Q193. InGauss-Seidelmethodofpowerflowproblem,thenumberofiterationsmaybe

reducedifthecorrectioninvoltageateachbusismultipliedby

Page 50: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

a. Gaussconstant

b. Acceleration constant

c. Deceleration constant

d. Blockingfactor

Q194. Loadflowstudyiscarriedoutfor

a. Faultcalculations

b. stabilitystudies

c. Systemplanning

d. Load frequencycontrol

Q195. Transientinelectriccircuitsnormallydisappearswithinatimeequalto

(a) 4 * timeconstant

(b) 2* timeconstant

(c) 8* timeconstant

(d) timeconstant

Q196. TheconvergencecharacteristicoftheNetwon–Rophsonmethodofsolvinga load flow problemis

a)quadratic b)linear

C)geometric d)cubic

Q197. Busesforloadflowstudiesareclassifiedas

1. Loadbus

2. PVbus(b)

3. Slackbus

Q 198.

Page 51: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q199. Theprincipalinformationobtainedfromloadflowstudiesinapowersystemare

1. magnitudeandphaseangleofthevoltageateachbus

2. reactiveandrealpowerflowsineachofthelines

3. totalpowerlossinthenetwork

4. transientstabilitylimitofthesystem

Select the correct answer using the codes given below :

(A) 1and2

(B) 3and4

(C) 1, 2 and3

(D) 2 and4

Page 52: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q200. Direction:Thefollowingtwoitemsconsistoftwostatements,onelabelledas

Assertion‘A’andtheotherlabelledasReason‘R’.Youaretoexaminethesetwo

statementscarefullyanddecideiftheAssertionAandtheReasonRareindividuallytrue

andifso,whethertheReasonisacorrectexplanationoftheAssertion.Selectyour

answerstotheseitemsusingthecodesgivenbelow.

Codes :

(A) BothAandRaretrueandRisthecorrectexplanationofA

(B) BothAandRaretruebutRisNOTthecorrectexplanationofA

(C) AistruebutRisfalse

(D) AisfalsebutRistrue

Assertion (A) : Bus admittance matrix is a sparse matrix.

Reason (R) : In load flow studies, one of the buses is take as a slack bus.

Consider the following statements in respect of load flow studies in power systems :

1. Busadmittancematrixisasparsematrix

2. Gauss-SeidelmethodispreferredoverNewton-Raphsonmethodforloadflowstudies

3. Oneofthebusesistakenasslackbusinloadflowstudies

Which of the statements given above are correct ?

(A) 1, 2 and3

(B) 1and2

(C) 1and3

(D) 2and3

Page 53: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

101 D 121 B 141 A 161 A 181 D

102 A 122 D 142 A 162 B 182 A

103 A 123 B 143 A 163 C 183 C

104 D 124 A 144 C 164 A 184 C

105 C 125 D 145 A 165 B 185 D

106 A 126 B 146 A 166 A 186 A

107 D 127 B 147 A 167 B 187 D

108 C 128 B 148 A 168 A 188 A

109 C 129 C 149 B 169 B 189 B

110 C 130 A 150 A 170 A 190 B

111 B 131 A 151 A 171 B 191 C

112 C 132 A 152 A 172 A 192 D

113 A 133 B 153 A 173 A 193 B

114 D 134 A 154 B 174 B 194 B

115 A 135 A 155 A 175 B 195 C

116 B 136 B 156 B 176 D 196 C

117 D 137 C 157 A 177 A 197 A

118 D 138 A 158 A 178 B 198 B

119 A 139 B 159 C 179 A 199 C

120 C 140 A 160 A 180 B 200 C

Page 54: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Unit- 3

Q 201.

.

Q202. TheYBUSmatrixofa100-businterconnectedsystemis90%sparse.Hencethe

numberoftransmissionlinesinthesystemmustbe

(A) 450

Page 55: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q204.

Q204.

Ataparticularunbalancednode,therealpowersspecified are: Leaving the

node 20 MW, 25 MW

Enteringthenode60MW,30MWThe

balancing power will be:

(a)30MWleavingthenode

(B) 500

(C) 900 (D)

1000

Q 203.

(b) 45MWleavingthenode

(c) 45 MW entering thenode

(d) 22.5MWenteringthenodeand22.5MWleavingthenode.

Q205. Thelosscoefficientsforatwo-bussystemaregivenasfollows:]

(a)B11=0.02,B22=0.05,B12=0.01,B21=0.015.

(b) B11= 0.02, B22= 0.04, B12= -0.01, B21= - 0.001.

(c)B11 = 0.03, B22= 0.005, B12= - 0.001, B2I= - 0.001.

(d) B11= 0.03, B22= 0.05, B12= 0.001, B21= - 0.001.

Page 56: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q206. Foreconomicoperation,thegeneratorwithhighestpositiveincremental

transmission•losswilloperateat:

(a) Thelowestpositiveincrementalcostofproduction

(b) Thelowestnegativeincrementalcostofproduction

(c) Thehighestpositiveincrementalcostofproduction

(d) None of theabove.

Q207. Themaximumpermissiblechangeinpowerfrequencyis

(A) ±5Hz

(B) ±0.5Hz

(C) ±0.6Hz

(D) ± 0.05 Hz

Q208. automaticgenerationandvoltageregulationequipmentisinstalledoneach generator

(A) Loadfrequency

(B) Excitationvoltage

(C) BothAandB

(D) None ofthese

Q209. theytakecareofsmallchangesinloaddemand

(A) Without change in frequency andvoltage

(B) Without change in Power andvoltage

(C) WithoutchangeinRealPowerandReactivepower

(D) None ofthese

Page 57: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q210. Thechangeinloaddemand,thiswillchangeinalternator

(A) Powerangle

(B) Excitationangle

(C) Firingangle

(D) None ofthese

Q211. Thechangeinloaddemand,thiswillmeetoutbyalternator

(A) Excitationvoltage

(B) Speed ofturbine

(C) BothAandB

(D) None ofthem

Q212. Thechangeinloaddemand,thiswillchangeinalternator

(A) Excitationvoltage

(B) Speed ofturbine

(C) BothAandB

(D) None ofthem

Q213.Maintainnetworkfrequencyconstantsothatthepowerssothatthepowerstation

aresatisfactorilyparallelonthesystemrunatthedesiredspeedcorrecttimeisobtained from

(A) Synchronoscope

(B) Two lampmethod

(C) Threemethod

(D) None ofthese

Q214. Poweranglewillchangeincontrolledformet

Page 58: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(A) MomentarilySmallchangeinspeed

(B) Large change inspeed

(C) Medium change inspeed

(D) None ofthem

Q215. powerfrequencycontrolisslowdueto

(A) turbineandgeneratormomentofinertia

(B) turbine and generatortroque

(C) turbine and generatorforce

(D) All of theabove

Q216. Changeinloaddemandcanbeidentifiedas

(A) slowvaryingchangesinmeandemand

(B) fast random variations around themean

(C) A andB

(D) None ofthem

Q217. Whatshouldbeatquestionmarkfrompicture

(A) frequency

(B) Voltage

(C) Realpower

(D) Speed

Q218. Pilot piston is usedfor

(A) Providingtohelpchangeinmainpiston

?

Page 59: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(B) Providing change in mainValve

(C) Providingtoflowinhydraulicoil

(D) All ofthem

Q219. These are part of LFCsystem

(A) Fly ball speedgovernor

(B) Hydraulicamplifier

(C) Linkagemechanism

(D) All ofthem

Q220. Flyballspeedgovernorisusedfor

(A) frequency

(B) Voltage

(C) Realpower

(D) Speed

Q221. This modal may namedas

(A) TurbineModel

(B) ModelofSpeedGoverningSystem

(C) generator-loadmodel

(D) All ofthem

Q222. This modal may namedas

Page 60: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(A) TurbineModel

(B) Model of Speed GoverningSystem

(C) generator-loadmodel

(D) All ofthem

Q223. This modal may namedas

(A) TurbineModel

(B) Model of Speed GoverningSystem

(C) generator-loadmodel

(D) All ofthem

Give the answer all below questions

Page 61: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q224. Thevalueatposition“1”inabovemodal

(A) ∆Pc(s)

(B) ∆PD(s)

(C) ∆PG(s)

(D) ∆F(s)

Q225. Thevalueatposition“2”inabovemodal

(A) ∆Pc(s)

(B) ∆PD(s)

(C) ∆PG(s)

(D) ∆F(s)

Q226. Thevalueatposition“3”inabovemodal

(A) ∆Pc(s)

(B) ∆YE(s)

(C) ∆PG(s)

(D) ∆F(s)

Q227. Thevalueatposition“4”inabovemodal

(A) ∆Pc(s)

(B) ∆PD(s)

(C) ∆PG(s)

(D) ∆F(s)

Q228. Thevalueatposition“6”inabovemodal

(A) ∆Pc(s)

(B) ∆PD(s)

Page 62: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(C) ∆PG(s)

(D) ∆F(s)

Q229. Thefinalvalueatabovemodal

(A) ∆Pc(s)

(B) ∆PD(s)

(C) ∆PG(s)

(D) ∆F(s)

Q230. Theinputvalueatabovemodal

(A) ∆Pc(s)

(B) ∆PD(s)

(C) ∆PG(s)

(D) ∆F(s)

Q231. speed regulation of thegovernor

(A) K1KC/K2

(B) K1KCK3/K4

(C) 1/K5K4

(D) none ofthem

Q232. gain of speedgovernor

(A) K1KC/K2

(B) K1KCK3/K4

(C) 1/K5K4

(D) none ofthem

Page 63: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

R

R

R

Q233. time constant of speedgovernor

(A) K1KC/K2

(B) K1KCK3/K4

(C) 1/K5K4

(D) none ofthem

Q234. The droop slope may defineas

−1

(A) B+(1)

(B) B+(1)

(C) (1)

(D) None of them

Q235. For250MWmachinewithanoperatingloadof125MW.letthechangeinload be1%for1%

changeinfrequency(scheduledfrequency=50Hz).Then ∂P

∂ f

(A) 2.5MW/Hz

(B) 5.0MW/Hz

(C) 2.6MW/Hz

(D) 3.5MW/Hz

Q236. For250MWmachinewithanoperatingloadof125MW.letthechangeinload be1%for1%

changeinfrequency(scheduledfrequency=50Hz).Then ∂P

∂ f

(A) 0.001 puMW/Hz

(B) 0.01 puMW/Hz

(C) 0.1 puMW/Hz

Page 64: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(D) 1 puMW/Hz

Q237. A100MVAsynchronousgeneratoroperatesonfullloadatfrequencyof50Hz.

Theloadissuddenlyreducedto50MW.Duetotimelagingovernorsystem,thesteam

valvebeginstocloseafter0.4seconds.GivenH=5kW-sec/KVAofgeneratorcapacity.

Determinethechangeinfrequencythatoccursinthistime.

(A) 51Hz

(B) 50Hz

(C) 48Hz

(D) 49Hz

Q238. A100MVAsynchronousgeneratoroperatesonfullloadatfrequencyof50Hz.

Theloadissuddenlyreducedto50MW.Duetotimelagingovernorsystem,thesteam

valvebeginstocloseafter0.4seconds.GivenH=5kW-sec/KVAofgeneratorcapacity.

Determine Excess power input to generator

(A) 50MW

(B) 52MW

(C) 53MW

(D) 40MW

Q239. A100MVAsynchronousgeneratoroperatesonfullloadatfrequencyof50Hz.

Theloadissuddenlyreducedto50MW.Duetotimelagingovernorsystem,thesteam

valvebeginstocloseafter0.4seconds.GivenH=5kW-sec/KVAofgeneratorcapacity.

Determine Kinetic energy stored in rotating parts of generator and turbine

(A) 0.5MW

(B) 5.0MW

(C) 3.0MW

(D) 1.6MW

Q240. A100MVAsynchronousgeneratoroperatesonfullloadatfrequencyof50Hz.

Theloadissuddenlyreducedto50MW.Duetotimelagingovernorsystem,thesteam

Page 65: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

valve begins to close after 0.4 seconds. Given H = 5 kW-sec/KVA of generator capacity.

Determine Excess energy input to rotating parts in 0.4 sec

(A) 21000KW-Sec

(B) 20000KW-Sec

(C) 19000KW-Sec

(D) Notcalculated

Q241. Twogeneratorsrated200MWand400MWareoperatinginparallel.Thedroop

characteristicsoftheirgovernorsare4%and5%,respectivelyfromnoloadtofullload.

Assumingthatthegeneratorsareoperatingat50Hzatnoload,Assumefreegovernor

operation,howwouldaloadof600MWbesharedbetweenthem?

(A)230,370

(B)229,371

(C) 231,369

(D) Not calculated

Q242.Twogeneratorsrated200MWand400MWareoperatinginparallel.Thedroop

characteristicsoftheirgovernorsare4%and5%,respectivelyfromnoloadtofullload.

Assumingthatthegeneratorsareoperatingat50Hzatnoload,Whatwillbethesystem

frequencyatthisload?Assumefreegovernoroperation.

(A)51.59 Hz

(B) 47.69Hz

(C)48.99Hz

(D)49.00Hz

Q243. This modal isshowing

(A) 1storder LFCmodal

(B) 2ndorder LFCmodal

(C) Multiple order LFCmodal

Page 66: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(D) None ofthese

Q244. centraleconomicdispatchcomputerisabbreviated

(A) CEDC

(B) CEC

(C) EDC

(D) None ofthem

Q245. synchronizing coefficient is (A)

|V1||V2|

PX

(B) |V1||V2|

sin(δ0−δ0)

Pr 1 1 1

12

(C) |V1||V2|

sin(δ1−δ2) P

(D) None of them

Q246.Maintainnetworkfrequencyconstantsothatthepowerssothatthepowerstation

aresatisfactorilyparallelonthesystemrunatthedesiredspeedcorrecttimeisobtained from

(A) Synchronoscope

(B) Two lampmethod

(C) Threemethod

(D) None ofthese

Q247. Poweranglewillchangeincontrolledformat

(A) MomentarilySmallchangeinspeed

(B) Large change inspeed

(C) Medium change inspeed

X

Page 67: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(D) None ofthem

Q248. powerfrequencycontrolisslowdueto

(A) turbineandgeneratormomentofinertia

(B) turbine and generatortroque

(C) turbine and generatorforce

(D) All of theabove

Q249. Two area controlmeans

(A) One power system areinvolved

(B) twoormorepowersystemareinvolved

(C) A andB

(D) None ofthem

Q250. Thisequationshows Ksg

1+Tsgs

(A) TurbineModel

(B) Model of Speed GoverningSystem

(C) generator-loadmodel

(D) All ofthem

Q251. Thisequationshows Kt

1+T ts

(A) TurbineModel

(B) Model of Speed GoverningSystem

(C) generator-loadmodel

(D) All ofthem

Q252. Thisequationshows Kps

1+T pss

Page 68: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(A) TurbineModel

(B) Model of Speed GoverningSystem

(C) generator-loadmodel

(D) All ofthem

201 D 221 B 241 C

202 C 222 A 242 B

203 C 223 C 243 A

204 B 224 B 244 A

205 C 225 A 245 B

206 A 226 B 246 A

207 B 227 C 247 A

208 C 228 D 248 A

209 A 229 D 249 B

210 A 230 A 250 C

211 C 231 B 251 C

212 C 232 B 252 C

Page 69: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

213 A 233 C

214 A 234 A

215 A 235 A

216 C 236 B

217 A 237 A

218 D 238 A

219 D 239 A

220 A 240 B

Page 70: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Unit=4

Q253. Zeropowerfactormethodofanalternatorisusedtofindits

(A) fieldresistance

(B) armatureresistance

(C) efficiency

(D) voltageregulation

Q254. Thepowerfactorofanalternatorisobtainedfromits

(A) excitation

(B) speed

(C) load

(D) noneoftheabove

Q255. Forparalleloperation,alternatorsmusthave

(A) samespeed

(B) same kvarating

(C) same voltagerating

(D) none of theabove

Q256. Foralternationhavingfractionalpitchof5/6thecoilspanis

(A) 90°

(B) 120°

(C) 150°

(D) 180°

Q257. Fractionalpitchtoeliminate7thharmonicfromalternatoremfis

(A)7/6

(B)6/7

(C)6/5

(D)3/5

Page 71: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q 258.Consider the following statements about a three-phase synchronous generator

synchronizedtoaninfinitebuswhenitsmechanicalinputisincreasedgraduallywith field current

heldconstant:

1 Thepowerfactorofthecurrentsuppliedbecomesmorelagging

2 Thepowerfactorofthecurrentsuppliedimproves

3 The power factor remainsunity

4 Theloadangleisincreased Of

thesestatements

(A) 1 alone iscorrect

(B) 2 alone iscorrect

(C) 2and4arecorrect

(D) 3and4arecorrect

Q259. A 3-phase synchronous generator, with its armature resistance and the leakage

reactancebeingneglected,issynchronizedtoaninfinitebusanditsfieldexcitationis keptconstantthereafter

NowthemachineisloadedbySupplyingmechanicalinput totheshaftsothattheload-

angleδreachesavalueof60°Underthiscondition,the operating power-factor wouldbe

(A) 0.866leading

(B) 0.866lagging

(C) 0 .5leading

(D) 0.5lagging

Q260.Aroundrotorsynchronousgeneratorhasaleakagereactanceof10%,armature

reactionreactanceof90%andnegligiblearmatureresistancewiththemachineinitially

runningatratedspeedandterminalvoltageof1.0pu,a3-phaseshort-circuitisapplied

Thesustainedarmaturecurrentwillbe

(A) 1.25pu

(B) 1.11pu

(C) 1.0pu

(D) 0.9pu

Q261. Followingasuddenshort-circuitattheterminalsofa3-phaseunloaded

synchronousgenerator,theinitialeffectofthepole-facedamperwindings,isto

Page 72: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(A) establishthearmaturefluxthroughthedirect-axismagneticcircuitofthe machine

(B) allowonlypartiallinkageofthearmaturefluxwiththemainfieldwinding

(C) confinethearmaturefluxtocompletelylinkthedamperwinding

(D) repelthearmaturefluxandconfineittotheleakagefluxpathintheair-gap Q262.

Inasynchronousgeneratoroperatingatzeropflagging,theeffectofarmature

reaction is

(A) magnetizing

(B) demagnetizing

(C) cross-magnetizing

(D) both magnetizing andcross-magnetizing

Q263. Whichofthefollowinglimitthereactivepoweroutputofasynchronous generator?

1 Armaturecurrent

2 Fieldcurrent

3 Loadangle

4 Prime moverinput

Select the correct answer using the codes given below:

Codes

(A) 1 and2

(B) 2and3

(C) 3and4

(D) 1and4

Q264. Thesteady-statestabilitylimitofasynchronousgeneratorcanbeincreasedby

(A) an increase in itsreactance

(B) anincreaseintheexcitationofthemachine

(C) adecreaseinthemomentofinertiaofthemachine

(D) anincreaseinthemomentofintertiaofthemachine

StatewhetherthefollowingstatementsrelatedtoSynchronousGeneratoraretrue(T)or false(F):

Page 73: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q265. Synchronousreactancecanbedeterminedfromopencircuitandshortcircuittests

(A) TRUE

(B) FALSE

(C) NotPossible

(D) None ofthese

Q266. Voltageregulationcanbedeterminedbysynchronousimpedancemethod

(A) TRUE

(B) FALSE

(C) NotPossible

(D) None ofthese

Q267. Percentageresistanceistheresistancedropatratedcurrentandfrequency

expressedasthepercentageoftheratedvoltage

(A) TRUE

(B) FALSE

(C) NotPossible

(D) None ofthese

Q268. MMFmethodforregulationdoesnotusedataavailablefromopencircuitand short circuittests

(A) TRUE

(B) FALSE

(C) NotPossible

(D) None ofthese

Q269. Inshort-pitchwindingsfractionalnumberofslotsperpolecanbeused

(A) TRUE

(B) FALSE

Page 74: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(C) NotPossible

(D) None ofthese

Q270. Oneoftheadvantageofshortpitchwindingsissavingincopper

(A) TRUE

(B) FALSE

(C) NotPossible

(D) None ofthese

Q271. Largescalepowergenerationisdonebysynchronousgenerators

(A) TRUE

(B) FALSE

(C) NotPossible

(D) None ofthese

Q272. TheanglebetweenEgandVtiscalledthepowerangle

(A) TRUE

(B) FALSE

(C) NotPossible

(D) None ofthese

Q273. Synchronousreactanceisdeterminedbysynchronousreactancemethod

(A) TRUE

(B) FALSE

(C) NotPossible

(D) None ofthese

Q274. Synchronousgeneratormustoperateatthecorrectspeedasitdeterminesthe

frequencysincethenumberofpolesisfixedforanygivenmachine

Page 75: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(A) TRUE

(B) FALSE

(C) NotPossible

(D) None ofthese

Q275. Thevoltageregulationofanacgeneratorisdefinedastheriseinvoltagewhen

theloadisreducedfromfull-ratedloadvaluetozero,speedandfieldcurrentremaining constant

(A) TRUE

(B) FALSE

(C) NotPossible

(D) None ofthese

Q276. Armaturereactioninanalternatoraffectsgeneratedvoltage/phase

(A) TRUE

(B) FALSE

(C) NotPossible

(D) None ofthese

Q277. Armaturereactioninanalternatorismagnetizingatlaggingloads

(A) TRUE

(B) FALSE

(C) NotPossible

(D) None ofthese

Q278. Maximumdemandonapowerplantis

(A) Thegreatestofall"shorttimeintervalaveraged"demandduringaperiod

(B) InstantaneousmaximumvalueofKVAsuppliedduringaperiod

Page 76: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(C) Both (a) or(b)

(D) None of theabove

Q279. Inanalternator,thefrequencyperrevolutionisequalto

(A) Number ofpoles

(B) Number of pairs ofpoles

(C) Number of armatureconductors

(D) Forty

Q280. Squirrelcagebarsplacedintherotorpolefacesofanalternatorhelpreduce hunting

(A) Above synchronous speedonly

(B) Below synchronous speedonly

(C) Aboveandbelowsynchronousspeedsboth

(D) None of theabove

Q281. Stationaryalternatorshouldnotbeconnectedtolivebus-barsbecauseit

(A) Islikelytorunassynchronousmotor

(B) Willgetshort–circuited

(C) Willdecreasebus-barvoltagethoughmomentarily

(D) Willdisturbgeneratedemf'sofotheralternatorsconnectedinparallel

Q282. Withaunityloadp f,theeffectofarmaturereactiononthemainfieldflux of an

alternatoris

(A) Distortional

(B) Magnetizing

(C) Demagnetizing

(D) Nominal

Page 77: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

Q283. Atlaggingloads,armaturereactioninanalternatoris

(A) Cross-magnetising

(B) Demagnetizing

(C) Non-effective

(D) Magnetizing

Q284. Thefrequencyofvoltagegeneratedbyanalternatorhaving4polesandrotatingat 1800 rpmis

(A) 60Hz

(B) 7200Hz

(C) 120Hz

(D) 450Hz

Q285. Themaindisadvantagesofusingshortpitchwindinginalternatorsisthatit

(A) Reducesharmonicsinthegeneratedvoltage

(B) Reducesthetotalvoltagearoundthearmaturecoils

(C) Producesasymmetryinthethreephasewindings

(D) IncreasesCuofendconnections

Q286. Zeropowerfactormethodofanalternatorisusedtofindits

(A) Efficiency

(B) Voltageregulation

(C) Armatureresistance

(D) Synchronousimpedance

Q287. Armaturereactioninanalternatormainlyaffects

(A) Rotorspeed

Page 78: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(B) Terminal voltage perphase

(C) Frequency ofarmaturecurrent

(D) Generated voltage perphase

Q288. Theeffectofincreasingairgaplengthintheinductionmotorwillincreasethe

(A) Powerfactor

(B) Speed

(C) Magnetizingcurrent

(D) Air gapflux

Q289. Theprincipleofoperationofa3phaseinductionmotorismostsimilartothatofa

(A) Synchronousmotor

(B) Repulsion start inductionmotor

(C) Transformerwithashortedsecondary

(D) Capacitor start, induction runmotor

Q290. Squirrelcagebarsplacedintherotorpolefacesofanalternatorhelpreduce hunting

(A) Above synchronous speedonly

(B) Below synchronous speedonly

(C) Aboveandbelowsynchronousspeedsboth

(D) None of theabove

Q291. Thestationaryalternatorshouldnotbeconnectedtolivebus-barsbecauseit

(A) Islikelytorunassynchronousmotor

(B) Willgetshort–circuited

(C) Willdecreasebus-barvoltagethoughmomentarily

Page 79: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(D) Willdisturbgeneratedemf'sofotheralternatorsconnectedinparallel

Q292. Withaunityloadpf,theeffectofarmaturereactiononthemainfieldfluxofan alternatoris

(A) Distortional

(B) Magnetizing

(C) Demagnetizing

(D) Nominal

Q293. Atlaggingloads,armaturereactioninanalternatoris

(A) Cross-magnetising

(B) Demagnetizing

(C) Non-effective

(D) Magnetizing

Q294. Thefrequencyofvoltagegeneratedbyanalternatorhaving4polesandrotatingat 1800 rpmis

(A) 60Hz

(B) 7200 Hz

(C) 120Hz

(D) 450Hz

Q295. Themaindisadvantagesofusingshortpitchwindinginalternatorsisthatit

(A) Reducesharmonicsinthegeneratedvoltage

(B) Reducesthetotalvoltagearoundthearmaturecoils

(C) Producesasymmetryinthethreephasewindings

(D) IncreasesCuofendconnections

Q296. Zeropowerfactormethodofanalternatorisusedtofindits

Page 80: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(A) Efficiency

(B) Voltageregulation

(C) Armatureresistance

(D) Synchronousimpedance

Q297. Armaturereactioninanalternatormainlyaffects

(A) Rotorspeed

(B) Terminal voltage perphase

(C) Frequency ofarmaturecurrent

(D) Generated voltage perphase

Q298. Theeffectofincreasingairgaplengthintheinductionmotorwillincreasethe

(A) Powerfactor

(B) Speed

(C) Magnetizingcurrent

(D) Air gapflux

Q299. Theprincipleofoperationofa3phaseinductionmotorismostsimilartothatofa

(A) Synchronousmotor

(B) Repulsion start inductionmotor

(C) Transformerwithashortedsecondary

(D) Capacitor start, induction runmotor

Q300. Twoalternatorsareparalleled

(A) So that one isn'toverworked

Page 81: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

(B) Becauseofarisingloaddemand

(C) To ease the workload

(D) Becauseofthedecliningloaddemand

Page 82: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

253 D 273 A 293 D

254 C 274 A 294 A

255 C 275 A 295 B

256 C 276 A 296 B

257 B 277 B 297 D

258 B 278 A 298 C

259 B 279 A 299 C

260 B 280 C 300 B

261 B 281 B

262 B 282 A

263 B 283 D

264 B 284 A

265 A 285 B

266 A 286 B

267 A 287 D

268 B 288 C

269 A 289 C

270 A 290 C

271 A 291 B

272 A 292 A

Page 83: B.E. 8 th SEMESTER POWER SYSTEM OPERATION ......Faculty of Degree Engineering - 083 Department of Electrical Engineering -09 B.E. 8 th SEMESTER POWER SYSTEM OPERATION AND CONTROL -

Faculty of Degree Engineering - 083 Department of Electrical Engineering -09

ELECTRICAL MACHINE-1 –(3140913)

GUIDED BY: PROF. RUSHIKESH V. PANDYA


Recommended