Date post: | 17-Mar-2018 |
Category: |
Documents |
Upload: | phunghuong |
View: | 224 times |
Download: | 4 times |
Order in Case No. 92 of 2012
MERC, Mumbai Page 1 of 57
Before the
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION
World Trade Centre, Centre No. 1, 13th
Floor, Cuffe Parade, Mumbai - 400 005
Email: [email protected]
Website: www.mercindia.org.in /www.merc.gov.in
Case No. 92 of 2012
IN THE MATTER OF
Suo-Motu Proceeding on the Policy Review in matters related to Wind Power in
Maharashtra
Smt. Chandra Iyengar, Chairperson
Shri. Vijay L. Sonavane, Member
Stakeholders:
1. The Government of Maharashtra
2. Maharashtra State Electricity Distribution Company Limited
Prakashgadh, Plot No. G – 9,
Bandra (East), Mumbai – 400051
3. M/s. Indian Wind Power Association (Maharashtra State Council) (IWPA)
Empire House, 214, Dr. D.N. Road,
Ent. A.K. Nayak Marg,
Fort, Mumbai – 400001
4. M/s. Tata Motors Ltd.(TML)
Bombay House
24, Homi Modi Street,
Fort, Mumbai – 400001
5. Wind World (India) Ltd. (Erstwhile Enercon (India) Ltd.)
Enercon Tower,
A – 9, Veera Industrial Estate,
Veera Desai Road,
Andheri (East), Mumbai – 400053
Order in Case No. 92 of 2012
MERC, Mumbai Page 2 of 57
6. M/s. Ushdev International Ltd. & Others
i. Ushdev International Ltd.
Appejay House, 6th Floor,
130, Mumbai Samachar Marg,
Fort, Mumbai- 400001
ii. Canpex Chemicals Ltd.
123, Nana Peth,
Opposite - J.D. Transport, Pune – 02
iii. Sahyadri Industries Ltd.
Swastik House, 39/D
Gultekdi, J.N. Road,
Pune- 411037
iv. Subhash B. Mutha
123, Nana Peth,
Opp. J.D., Transport,
Pune- 411002
7. Maharashtra Energy Development Agency
MHADA Commercial Complex, II Floor,
Opp. Tridal Nagar,
Yerwada, Pune- 411 006
ORDER (SUO-MOTU)
Dated: 7 April, 2014
The Maharashtra Electricity Regulatory Commission (hereinafter referred to as the Commission
or MERC) determined Tariff for procurement of Wind Energy and wheeling for Third Party Sale
and Self Use in the State of Maharashtra vide its Order in Case No. 17(3), 3, 4 and 5 of 2002,
dated 24 November, 2003 (Wind Power Tariff Order, 2003). The said Order also classified Wind
Projects in to Group-I, Group-II and Group-III based on the date of commissioning of the
Project.
During the proceeding in Case Nos. 8, 18, 20 and 33 of 2012 in the matter of Open Access issues
related to Wind power in Maharashtra; M.D, MSEDCL vide letter dated 4 April, 2012 brought
Order in Case No. 92 of 2012
MERC, Mumbai Page 3 of 57
out various facts that could be reviewed by the Commission. The Commission in matter of these
Cases, issued a Daily Order dated 27 April, 2012 and some of relevant extracts of the Daily
Order dated 27 April, 2012 in matter related to above mentioned Case Nos. 8, 18, 20 and 33 of
2012 are as under:
“...
The Commission opined that policy making is continuous process and with
evolving scenario the policy matters have to be reviewed/modified/altered, but at
the same time in the evolving scenario, in anticipation of policy review, there
cannot be a policy vacuum. The Commission after hearing all the parties ruled as
under:
1. All the matters pertaining to Case 8 of 2012, Case 18 of 2012, Case 20 of 2012
and Case 33 of 2012, prior to the letter sent and pleadings before the Commission
before or after the above mentioned letter was sent, pertaining to the above
mentioned Petitions shall be taken up, separately and issues emanating from the
letter sent by the MD (MSEDCL) shall be taken as a part of Policy review
exercise, separately.
.....
7. Illustrative issues that may be considered for Policy review are listed below:
a. The Petitioners need to submit the details of Capital Expenditure along with
effect of various concessions for Group I/Group II & Group III wind generation
plants. The data pertaining to the recovery of investment for Group II Plants after
expiry of their EPA tenure needs to be submitted in detail, in order to arrive at
proper policy decisions.
b. Are there any gaps in existing EPAs and are some important provisions
relating to the arrangement after the expiry of tenure of Agreement, etc, provided
in the existing EPAs.
c. What is the pace of obsolescence of wind Generation technology?
Order in Case No. 92 of 2012
MERC, Mumbai Page 4 of 57
d. Objective of introducing REC mechanism, its intended beneficiaries and
whether discount on Cross Subsidy Surcharge available to Open Access
transactions from Renewable Energy generators is a preferential treatment and
whether generators getting this discount should qualify for REC benefits also.
e. Banking Charges, etc.
8. Views of State Government of Maharashtra on the letter sent by MD
(MSEDCL) will be sought.
9. Decision about Public consultation process (Public Hearing) on the policy
review will be taken by the Commission after studying the submissions by the
Petitioners & Respondents.”
Based on above mentioned decision, the Commission vide Notice dated 12 September, 2012
scheduled a Suo-motu Hearing on 19 October, 2012 and invited views/suggestion from various
Stakeholders, i.e., the Petitioners in Case Nos. 8, 18, 20 and 33 of 2012 and others who had made
submissions related to Part –II proceeding in these Cases.
Tata Motors Ltd. (TML), Indian Wind Power Association (IWPA), Wind World (India) Ltd.
(WWIL) and Arvind Cotsyn made their submissions on Affidavit in the matter on 15 October,
2012, 17 October, 2012, 19 October, 2012 and 15 October, 2012 respectively.
During the Hearing, MSEDCL made a detailed presentation regarding issues which are
pertaining to Policy Review in the matter related to Wind power in Maharashtra.
The representative from IWPA also made detailed submission during the Hearing. IWPA
submitted that the Policy Review is nothing but the complete review of various Orders.
The representative from TML submitted the details of capital cost of its Wind Projects and
confirmed that they availed concessions from Government of Maharashtra (GoM) such as Sales
Tax Benefit.
During the Hearing held on 11 January, 2013, the letter received from the GoM presenting its
view on the Policy Review matters was circulated to the parties. During the Hearing held on 31
January, 2013, all the Stakeholders in the matter were directed to file their replies on the
submission of Tata Power Company Limited on the Ancillary Services in Case No. 126 of 2012.
Order in Case No. 92 of 2012
MERC, Mumbai Page 5 of 57
During the hearing held on 15 April, 2013, all the parties present, Utilities and the Wind Energy
Association were directed to study the subject of problems caused to the grid by injection of
Renewable Energy and solution for the same.
During the hearing held on 5 June, 2013, MSEDCL was directed to contact Indian
Meteorological Department (IMD), C-WET and CPRI to study the Wind forecasting in detail
and also approach the monsoon modelling expert, Mr. Vasant Gowarikar. Further, MEDA was
directed to study the cost analysis of the balance potential of Wind power in Maharashtra.
During the hearing held on 22 July, 2013, MSEDCL was directed to carry forward the dialogue
initiated with IMD regarding Wind forecasting by meeting Dr. S.D. Attri, Director,
Environmental Monitoring and Research Centre, IMD, New Delhi.
1. ANALYSIS AND COMMISSION’S RULING
1.1 Having heard the Parties and after considering the relevant materials placed on record, the
Commission has identified following matters for its consideration:
1. Option to Sell Power Post Expiry of Energy Purchase Agreement (EPA)
2. Tenure of EPA
3. Tariff for Sale of Power Post Expiry of EPA
4. Obsolesce of Technology and Repowering of Wind Turbines
5. Objectives of Renewable Energy Certificates (RECs)
6. Eligibility for RECs
7. Banking and Banking Charges
8. Sale at Average Pooled Power Cost (APPC) and Compliance to RPO
9. Incentives
10. Miscellaneous Considerations/Suggestions
Issue No. 1: Option to sell power post expiry of Energy Purchase Agreement (EPA)
MSEDCL
1.2 MSEDCL submitted that in the existing EPAs presently there is no obligatory provision for
renewal option. The renewal of the EPA can be done by any of the party (Wind Energy
Order in Case No. 92 of 2012
MERC, Mumbai Page 6 of 57
Generators and Utility) after its expiry. The Parties to the EPA can renew the EPA by
mutual agreement on mutually agreed terms and conditions. There is no regulatory
obligation on either of the Parties to renew the EPA after the expiry of the tenure.
1.3 MSEDCL further submitted that under current Regulatory Environment, the competitive
market is available to the WEGs. However, currently, in the existing EPAs, there are no
provisions for arrangements for third party sales at what rate, cross subsidy surcharge or
any other charges as may be applicable in case the WEGs plan to sell the Wind Energy in
Open Access. Further, if the WEGs prefer to renew the EPA with MSEDCL only, there is
no provisions for the tariff at which the WEGs can sell. MSEDCL further submitted that, if
the tariff for period after expiry of the EPA is known, both parties can easily decide on
renewal of the EPAs.
1.4 MSEDCL further submitted that the provisions of refurbishment of old Wind Turbines are
also not present in the current EPAs. Many of the Wind Turbines are old and need more
O&M thereby increasing the operation cost. Breakdown of the critical components of the
Wind Turbines affects the machine availability and O&M cost for smaller capacity
Turbines. The provisions regarding timeframe for refurbishment and benefits (if any)
available to WEGs are absent in the existing EPAs.
1.5 MSEDCL submitted that following options are available with Wind Energy Generators
(WEGs) for sale of Wind energy post expiry of EPA:
(a). EPA with Distribution Licensee at Feed-in Tariff
MSEDCL submitted that WEGs have enjoyed all the benefits provided by the
State Government, the Commission and MSEDCL. Further, since the WEGs have
already recovered their entire investment with profit, the assets of these
Generators shall become the property of the State. Further, MSEDCL submitted
that post expiry of EPA, WEGs shall sell the Wind energy to MSEDCL at
discounted Tariff as may be decided by the Commission for balance life of the
Project and such purchase shall form part of Renewable Purchase Obligation
(RPO).
(b). Sale through Open Access
Order in Case No. 92 of 2012
MERC, Mumbai Page 7 of 57
MSEDCL submitted that Open Access regime provides competitive market to all
participants and accordingly requested the Commission that no special
concessions shall be allowed for sale to third party under Open Access.
(c). Sale to Utility at Average Pooled Power Cost (APPC)
MSEDCL submitted that the WEGs may also sell Wind energy to the Distribution
Licensee at a price not exceeding APPC of such Utility as approved by the
Commission and is also eligible to claim Renewable Energy Certificate (REC)
benefits. However, MSEDCL requested the Commission to allow such purchase
under APPC for fulfilment of RPO as well.
IWPA
1.6 IWPA submitted that there are no gaps in the existing EPA and the EPAs that have expired.
After the due deliberations over a period of two years and consultations with all
stakeholders including Consumer Representatives, the Wind Power Tariff Order, 2003 was
issued and the tariff philosophy was stipulated in the said Order.
1.7 IWPA further submitted that in the Wind Power Tariff Order, 2003 the Commission in
paragraph 1.5.5 of the said Order had ruled that it would not revisit the old Projects (i.e.,
Group-I and Group-II) during the review that may be undertaken after 31 March, 2007.
1.8 IWPA referred Orders in Case No. 33 of 2007 dated 20 November, 2007, Case No. 89 of
2007 dated 7 October, 2008 and Case No. 39 of 2011 dated 29 April, 2011 which stipulates
freedom to WEGs either to supply to MSEDCL or to Open Access consumers in
accordance with the MERC (Distribution Open Access) Regulations, 2005 post expiry of 8
year EPA tenure for Group II Projects and 13 year EPA tenure for Group III Projects.
1.9 IWPA further submitted that said Orders having become final with the same not contested
by MSEDCL to any higher authorities, a review provisions post expiry of the EPAs do not
arise. Further there are no errors or mistakes apparent in the said Order and hence
conclusions made by the Commission cannot be a subject matter of review.
1.10 IWPA further submitted that Commission in Order dated 29 April, 2011 in Case No.39 of
2011 in Para 1.5 has ruled that for Group-II Projects whose EPA have expired has option
Order in Case No. 92 of 2012
MERC, Mumbai Page 8 of 57
either to continue with the Commission’s preferential Tariff or opt for pricing under REC
mechanism.
1.11 IWPA further submitted that generation of power is a de-licensed activity and therefore
there cannot be any compulsion on the Generators to supply power at a specific tariff.
Further, there shall be no exclusivity to supply power to MSEDCL post expiry of the tenure
of EPA.
Tata Motors Limited
1.12 TML submitted that since the inception of the Project (except for a brief initial period) it
has been selling electricity to the third party or self consuming the electricity. TML further
referred the Commission’s Order dated 10 December, 2008 in Case No. 58 of 2008 in the
event, WEGs chose to supply to MSEDCL post expiry of EPA, the same shall be done at
the preferential tariff determined by the Commission (i.e., Rs. 2.52/kWh).
1.13 TML further submitted that prevailing law permits WEGs to enter into contract with any
Consumer and sell under Open Access and any Consumer can also select its supplier of
power. However, the Electricity Act, 2003 does not provided for regulating the sale of
power by the Generators to the Open Access Consumers.
1.14 Further, TML submitted that the Hon'ble Supreme Court in Tata Power Company Limited v
MERC & Others, 2009 ELR (SC) 246 has held that a Generator cannot be forced to enter
into an agreement to sell power from its Generating Unit to any person. Therefore, once the
term of the EPA is over, WEG is free to decide the sale of power option and therefore there
is no requirement of any Order or decision on the same in the present proceedings.
Wind World (India) Limited [Erstwhile Enercon (India) Limited]
1.15 WWIL submitted that the Hon’ble Supreme Court in the Tata Power Company Limited V/s
Reliance Energy Limited & Others (2009) 16 SCC 659 has held that a Generating
Company has freedom to sign a Power Purchase Agreement (PPA) with any person/Utility.
Further, WWIL submitted that Central Electricity Regulatory Commission’s (CERC) REC
Amendment Regulations, 2010 provides that after natural termination of PPA, WEG is
eligible for participating in the REC scheme.
Order in Case No. 92 of 2012
MERC, Mumbai Page 9 of 57
1.16 WWIL submitted that the Group-II Projects are therefore entitled to opt any of the various
selling option in Maharashtra. WWIL further submitted that incentives once provided if
taken back would create a Regulatory uncertainty in the State and would impact investment
in Wind Power.
Bajaj Finserv
1.17 Bajaj Finserv submitted that many Investors invested in wind energy from the year 2000 to
2002 to meet long term CP / TP sale requirement, even though energy realization rate was
lesser than MSEDCL's tariff and MERC's promotional tariff as per GoM's Wind Power
Policy, 1998.
1.18 Further, Bajaj Finserv submitted that in the year 2004, one time change-over from
Captive/Third Party sale to sell wind energy to Discom at promotional tariff was permitted
by the Commission vide its Order in Case No. 59 of 2003 dated 10 September, 2004. In
spite of this, Captive/Third Party sale Projects like BFS did not opt promotional tariff to sell
their power to any DISCOM presuming long term security in continuation of Captive/Third
Party sale option for further period till now.
1.19 Bajaj Finserv submitted that to promote further investment in wind energy, functioning of
old Projects should not be disturbed during its remaining life, which will only be 30% post
2013.
Commission’s Rulings:
1.20 The Commission observed that it had deliberated on the issue of option of sale of power
post expiry of EPA under its Order dated 20 November, 2007 in Case No. 33 of 2007 in the
matter of Petition filed by MSEDCL. The relevant extract of the said Order reproduced as
under:
“While the Commission reiterates that wind energy generators have freedom to
sell to any party other than MSEDCL pursuant to expiry of the existing EPA, in
case wind energy developer wishes to sell to MSEDCL (or any other distribution
licensee), the licensees and such wind energy developers need to explore alternate
commercial arrangements pursuant to expiry of existing EPA sufficiently in
Order in Case No. 92 of 2012
MERC, Mumbai Page 10 of 57
advance so that need for seeking approval for interim arrangement does not arise
at all.”
1.21 Further the Commission in its Order dated 7 October, 2008 in Case No. 89 of 2007 had
ruled as under:
“Group II projects whose EPAs expired shall be allowed to continue to inject power into
the Grid; unless such Group II project developer chooses to supply to any consumer
under open access regime subject to provisions under Section 42(2) of EA 2003 and
payment of applicable transmission charges, transmission loss, wheeling charges and
wheeling loss as determined by the Commission from time to time.”
1.22 The Commission in its Order dated 10 December, 2010 in Case No. 58 of 2008 in the
matter of Petition filed by M/s. Renewable Energy Developers Association of Maharashtra
regarding refusal of MSEDCL to make any payment to the wind farm developers of Group-
II category for the energy that is being fed to the MSEDCL Grid after the date of expiry of
the EPA’s said that:
“Wind developers were at liberty to supply to any other party other than
MSEDCL post expiry of EPA”
1.23 The Commission in its Order dated 29 April, 2011 in Case No. 39 of 2011 in the matter of
Determination of Generic Tariff for the second year of the first Control Period under
Regulation 8 of the Maharashtra Electricity Regulatory Commission (Terms and Conditions
for Determination of Renewable Energy Tariff) Regulations, 2010 had ruled as under:
“The tariff applicable to Group-II wind projects have been specified under section 3.12
of the Generic Tariff Order dated July 14, 2010, issued in Case No. 20 of 2010. Further,
beyond FY 2009-10, those Group-II wind power projects whose PPA has expired have
the option to either continue with the Commission specified preferential tariff or opt for
pricing under REC mechanism (Clause 16.1 of MERC Renewable Purchase Obligation,
its compliance and implementation of REC framework) Regulations, 2010 and in
accordance with second proviso to Regulation 3.1 of RE tariff Regulations, 2010.”
Order in Case No. 92 of 2012
MERC, Mumbai Page 11 of 57
1.24 The Commission has deliberated on this issue for option of sale of power after expiry of the
EPA with Distribution Licensee as is evident from the extracts of various Orders (i.e., Case
No. 33 of 2007, Case No. 89 of 2007, Case No. 58 of 2008, and Case No. 39 of 2011).
Therefore, the Commission is of the view that provisions of supply of power to any party
other than MSEDCL post expiry of EPA have been reiterated by the Commission through
its various Orders mentioned above and the same needs to be continued.
Issue No. 2: Tenure of Energy Purchase Agreement (EPA)
MSEDCL
1.25 MSEDCL submitted that as against the life of Wind Projects of 20 years (now 25 years),
the Commission determined the Tariff for energy purchase for 8/13 years for Group-II and
Group-III Projects respectively. While doing so the Commission considered the interest of
the WEGs and has assured that recovery of investment is made in 8/13 years as the case
may be, with assured return of 16% (now 19%-24%) on equity. Thus in case of Group-II
Projects i.e., after 8 years in FY 2010, the EPAs with these WEGs ended and as decided by
the Commission investments made in Project has been recovered.
1.26 MSEDCL submitted that therefore on expiry of such EPA, investment cost of the investors
has already been recovered along with profit.
IWPA
1.27 IWPA submitted that the Commission in its earlier Orders had approved the tenure of EPA
after due stakeholder (including MSEDCL (erstwhile MSEB)) consultation process. IWPA
further submitted that MSEB had filed a Writ Petition before the Hon’ble Bombay High
Court which was withdrawn subsequently.
1.28 IWPA further submitted that subsequently MSEDCL (erstwhile MSEB) filed a Review
Petition on 5 March, 2004 against WPTO dated 24 November, 2003 which was not
considered by the Commission for the reasons given in Order of 12 March, 2004.
Order in Case No. 92 of 2012
MERC, Mumbai Page 12 of 57
1.29 IWPA submitted that raising an issue related to tenure of EPA which has been fixed about 9
years back could impact the investment on Wind power Projects in the State of
Maharashtra.
Wind World (India) Limited [Erstwhile Enercon (India) Limited]
1.30 WWIL submitted that one of the ways to increase the Tariff predictability and security for
both the WEGs and the State DISCOM is to increase the tenure of PPA to a minimum of 20
years. WWIL further submitted that the PPA tenure of 20-25 years is provided in all other
major Wind rich States and hence requested the Commission to accept the same.
Government of Maharashtra
1.31 The GoM submitted that as per the Wind Policy, 1998 the energy from Wind Power
Projects was to be purchased by erstwhile MSEB considering the rate of Rs. 2.25 /kWh for
the base year 1994-95 and escalated at the rate of 5% per annum for subsequent years. This
escalation was provided for first 10 years and 11th
year onwards the rate was kept constant
for 3 years and from 14th
year onwards again escalation of 5% per year for remaining 7
years was provided. It further submitted that GoM Policy also expected that the wind
energy produced by wind Projects would be supplied to MSEB for 20 years. However, the
Commission in its Wind Power Tariff Order, 2003 dated 24 November, 2003 decided the
period of EPA as 8 years for Group-II Projects (Commissioned from 27 December, 1999 to
31 March, 2003) and 13 years for Group-III Projects (commissioned after 1 April, 2003)
with different rates. This energy was purchased by erstwhile MSEB and supplied to the
common consumers at the rate decided by the Commission during the EPA period of 8/13
years (less than Project life of 20 years).
Commission’s Ruling:
1.32 The Commission notes that the EPA tenure had been fixed as 8 years for Group-II and 13
years for Group-III Projects considering the loan repayment obligations. The relevant
extract of the Wind Power Tariff Order, 2003 is reproduced as under:
“Based on the policies of the main lending institution such as IREDA, the loan repayment
period has been considered as 6 years for Group II Projects and 10 years for Group III
Projects.
Order in Case No. 92 of 2012
MERC, Mumbai Page 13 of 57
In view of the possible slippage in loan repayment due to yearly variations in wind
resources within the loan repayment period considered, the tariff rate for purchase of
energy has been determined for 8 years (as against loan repayment period of 6 years) in
the case of Group II Projects from the date of commissioning, and 13 years (as against
loan repayment period of 10 years) from the date of commissioning of the Project for
Group III Projects.
The Commission also notes that the provisions of the Electricity Act (EA), 2003 that has
come in to force from 10th June 2003 are substantially different from the earlier Acts.
Specifically, the Commission notes that the new Act provides that the utilities shall have
to purchase a certain percentage of their total energy requirement from renewable
sources of energy. The Commission notes that it would take some time before the
procedures for such purchases are in place.
The Commission observes that in the light of the Act, it is essential that the duration of
the contract being entered be of minimum duration. On the other hand, it has to be kept
in mind that no Project would be financed if the duration of the agreement is shorter than
necessary for loan repayments. The Commission also notes that it is essential that some
contingency is required to be provided for in the duration of the agreement to take into
account uncertainty of wind, a natural resource, and also other commercial exigencies.
The Commission has, therefore, permitted 2 and 3 years period respectively for such
contingencies.
Therefore, the Energy Purchase Agreement Period has been determined as 8 years for
Group II Projects and 13 years for Group III Projects.
The Commission also takes a note at this point that the EA2003 has opened up a host of
opportunities for CPP and private sector generation. It also envisages the market-
oriented operation of the electricity sector. Therefore, the Commission took a conscious
decision, that, once the objective of market and technology stabilization is achieved, such
Projects must be allowed to compete in the market. This would enable the distribution
entities to source, based on competitive bidding with the benchmark of higher CUF and
consequent penalty for under-achievement, their energy requirements on commercial
basis rather than being saddled with a long-term (20 years as prescribed by MNES
policy) purchase agreement.”
Order in Case No. 92 of 2012
MERC, Mumbai Page 14 of 57
1.33 The Commission further notes that Regulation 6.1 of the MERC (Terms and Conditions for
Determination of RE Tariff) Regulations, 2010 (hereinafter referred as MERC (RE Tariff)
Regulations, 2010) stipulates that tariff period for Wind Projects as 13 years. The relevant
extract of the said Regulations is reproduced as under:
“6.1 The Tariff Period for Renewable Energy power projects except in case of Small
hydro projects upto and including 5 MW, Mini/Micro Hydro projects, Solar PV, Solar
thermal power projects, Solar rooftop PV and other small Solar power projects shall be
thirteen (13) years.”
1.34 The Commission further notes that in the Order dated 19 December, 2013 in Case No. 65 of
2013 and Miscellaneous Application No. 13 of 2013 in Case No. 65 of 2013 in the matter of
Petition filed by MSEDCL for determination of tariff by bidding process for procurement of
wind energy for FY 2013-14 within Maharashtra on the issue of competitive bidding has ruled
as under:
“The subject of competitive procurement of renewable power is a matter
deserving greater scrutiny and thus is referred to the Committee to be constituted
as per the daily Order in the present case issued by the Commission, dated 1
October, 2013. The Committee is, directed to study, inter alia, the various issues
involved in introduction of competitive framework for procurement of renewable
energy by the distribution licensees in the State and incorporate its suggestions on
the same in its report. The report shall be circulated to all the stakeholders
involved in the matter.”
1.35 The Commission further notes that other State Electricity Regulatory Commissions have
also stipulated the EPA period linked to the life of the Project (i.e., EPA period has been
defined as 20/25 years). The summary of the EPA periods as considered by various wind
rich States are stipulated as under:
CERC/SERCs EPA Period
CERC 13 Years (CERC RE Tariff Regulations, 2009 & 2012)
MERC 8/13 Years (as per Order in 2003), 13 Years (as per MERC RE
Tariff Regulations 2010)
RERC 20 Years (RERC Term & conditions Regulations 2004 & 2009),
25 Year (RERC Amendment in 2012 to RERC Term & conditions
Order in Case No. 92 of 2012
MERC, Mumbai Page 15 of 57
CERC/SERCs EPA Period
Regulations 2009)
MPERC 20 Years (Wind Order 2004, 2006 &2007), 25 years (Wind Order
2010)
GERC 20 Years (Wind Order 2006), 25 years (Wind Order 2010 &
2012)
TNERC 20 Years (Wind Order 2004, 2009 & 2012)
KERC 20 Years (Wind Order 2004 & 2009)
APERC 20 Years (As per wind Order 2009)
1.36 The Commission further notes that stakeholders have also supported for having a longer
tenure of EPA for wind Projects, however, the only concern has been raised to review the
existing EPA which has been signed long before.
1.37 The Commission further notes that after the issuance of Wind Power Tariff Order, 2003 and
notification of MERC (RE Tariff) Regulations, 2010 multiple options of sale of power are
now available for Wind Projects (i.e., third party sale, self consumption under captive route,
sale of power under REC schemes).
1.38 In view of the above, the Commission is of the view that there is a merit in
consideration of EPA period linked to life of the project for existing and new Projects.
Accordingly, the Commission rules that for Projects whose EPA have not expired may
be given an option to extend EPA to Project life. The Commission hereby further
clarifies that such extension is an option available to both Parties and is not a compulsion.
Issue No. 3: Tariff for Sale of Power after Expiry of EPA
MSEDCL
1.39 MSEDCL submitted that after expiry of EPA, the WEGs should sell the Wind energy to
MSEDCL at discounted Tariff as may be determined by the Commission for the balance
life of the Project and such purchase shall form part of Renewable Purchase Obligation
(RPO). MSEDCL, submitted that it pays only Rs. 1.65 to Rs. 2.0/kWh to Koyna Hydel
Station (set up in 1962), which is primarily to recover the lease rent and Operation &
Maintenance (O&M) expenses as the capital cost of the Dam has already been paid by the
consumers of Maharashtra. Similarly, for WEGs, the consumers of Maharashtra have paid
Order in Case No. 92 of 2012
MERC, Mumbai Page 16 of 57
for the investment and now have exclusive right over the assets and its generation, at
reasonable O&M cost.
IWPA
1.40 IWPA submitted that the Commission has determined the interim preferential tariff in
Petition filed by M/s Renewable Energy Developers Association of Maharashtra for sale of
power post expiry of EPA in Case No. 58 of 2008 as Rs. 2.52/kWh based on simple
arithmetical basis on the offer of Rs. 1.29/kWh by MSEDCL and the proposal of Rs.
3.79/kWh i.e., the last tariff rate that was applicable to Group-II Projects at the time of
expiry of tenure of EPA.
1.41 The said interim tariff for Group II projects post expiry of EPA as determined in the Order
dated 10 December, 2008 in Case No. 58 of 2008, would be subject to final tariff that may
be determined through Regulatory process. Further it was ruled that no interest shall be paid
by MSEDCL for the period from expiry of the EPA and tariff determined in the said Order
since wind farm developers were at liberty to supply to any other party other than
MSEDCL post expiry of EPA.
1.42 It was further submitted that value of wind power cannot be simple cost of generation but
the intrinsic worth of wind power contributing to reduction in pollution levels in the
atmosphere, facilitating conserving the fossil fuel, effective tool in combating Global
Warming, etc., which are all qualitative aspects and cannot be measured in absolute
monetary terms in an accurate manner.
1.43 IWPA submitted that the Karnataka Electricity Regulatory Commission (KERC) permitted
the Tariff provided at the end of tenure of EPA of preferential Tariff to be continued post
expiry of the EPA and requested to adopt the same in Maharashtra, which would be an
encouraging proposition as it takes into account the opportunity cost as reasoned by the
KERC.
1.44 IWPA submitted that as far as sale to Open Access consumers are concerned post expiry of
EPA especially for Group II Projects, the Agreement for sale of power between two private
parties being confidential agreement and its members are hesitating to disclose the rate at
which each of them are selling power to their respective Open Access consumers. IWPA
Order in Case No. 92 of 2012
MERC, Mumbai Page 17 of 57
submitted that as far as Group III Projects are concerned, since for most of them the EPA
tenure is for 13 years and would be expiring around 2016, there would be hardly any Group
III consumers opting for sale of power to Open Access consumers. Further, IWPA
submitted that the Commission had issued Regulations in the matter of implementation of
REC Framework which permits the WEGs and its Open Access consumers to opt for
bilateral agreement so that WEGs can avail RECs.
Tata Motors Limited
1.45 TML referred the Order dated 10 December, 2008 in Case No. 58 of 2008 which stipulates
for supply of power post expiry of the EPA to the Distribution Licensee at the preferential
Tariff of Rs. 2.52/kWh. TML further submitted that the Commission vide its Order dated
14 July, 2010 in Case No. 20 of 2010 in the matter of determining of generic Tariff of
Regulation 8 of The MERC (Terms and Conditions for Determination of Renewable
Energy Projects) Regulations, 2010 continued the Tariff of Rs. 2.52/kWh.
1.46 With regard to example quoted by MSEDCL of Koyna, TML submitted in the present case
there arises no occasion for a payback as Government has not funded the capital
expenditure incurred for setting up the Wind Projects.
Wind World (India) Limited [Erstwhile Enercon (India) Limited]
1.47 WWIL submitted that cost plus approach has been adopted by CERC as well as all other
State Electricity Regulatory Commissions for determination of Tariff for Wind Energy
Projects.
1.48 WWIL further submitted the calculation on cost plus Tariff under two scenarios viz.,
“Scenario 1: All parameters taken as per Wind Tariff Order dated 24 November,
2003; CUF of 20% has been considered. The Tariff computed to Rs.
5.14/kWh.
Scenario 2: All parameters taken are as per Wind Tariff Order dated 24
November, 2003; MAT and Corporation Tax, Interest on Working
Capital taken as per Wind Tariff order of 2012; CUF of 20% has
been considered. The Tariff computed to Rs. 5.19/kWh.”
Order in Case No. 92 of 2012
MERC, Mumbai Page 18 of 57
1.49 WWIL submitted that Wind Generators have earned return as determined by the
Commission and if the State enforces Group-II Power Plants to supply power solely to the
Distribution Licensee at a Tariff which is impossible to operate in, it would be much
against the spirit of the Electricity Act, 2003 besides interfering with the contracts which
have worked themselves out.
Shri S.K. Parikh’s Submission
1.50 The 1996 policy failed to bring-in the investments needed in the sector. After
considering/analysing the demography of the State, it was found that it is possible to
generate 400 MW of Wind Power in the State of Maharashtra. After studying other State
policies to encourage investment from private players Wind Policy 1998 was announced by
Maharashtra. Further main points under the Wind Power Policy, 1998 were submitted.
Shri Charbhuja Sales Corporation’s Submission dated 02 June, 2012
1.51 As per the Government of Maharashtra’s Wind Power Policy, 1998, MSEDCL should
purchase the electricity from Wind power Projects at the rate of Rs. 4.23/kWh. The
developers who would have done their computations at the rate decided in the Wind Power
Policy, 1998, would now be earning revenue at Rs. 1.72/kWh less than that originally
decided. Wind energy generation through the Project commissioned in 1998 is the same
today as was during that time and it cannot be increased.
Government of Maharashtra
1.52 The GoM submitted that MSEDCL/consumers of MSEDCL also has the share in the profit
of Wind Power Projects as they have supported these wind Projects to earn the profit (as
per the Commission’s determined rate of return) by consuming the wind energy from the
Wind Energy Projects. Further, the GoM submitted that the wind Project having availed
benefits from the Government and also from the view point of social responsibility, it is
expected that this profit should be distributed to the consumers also. Accordingly, GoM
supported the submission made by MSEDCL that the Wind Power Projects should supply
wind energy to consumers/MSEDCL at reasonable.
Order in Case No. 92 of 2012
MERC, Mumbai Page 19 of 57
1.53 The GoM submitted that in light of the profit earned by the Wind Power Projects, various
concessions availed, responsibility of MSEDCL towards consumers and the GoM’s Wind
Power Policy, the submission of the MSEDCL may be accepted by the Commission.
Commission’s Ruling:
1.54 The Commission notes that in the Order in Case No. 58 of 2008, the Commission has ruled
that the tariff on ad-interim basis for wind energy injection into the Grid by Wind Energy
developers under Group-II category post expiry of their respective EPAs, shall be Rs 2.52
per unit. For FY 2010-11 onwards, in case the Wind developer chooses to sell at
preferential Tariff, the Tariff of Rs 2.52/kWh shall be applicable.
1.55 Interim Tariff for Group-II Projects (MERC Order in Case No. 58 of 2008)
a. MSEDCL’s submission in Case No. 58 of 2008
i. Tariff proposed from Rs. 1.29/kWh to Rs. 1.96/kWh on different
assumptions of O&M expense, Profit Margin, CUF and
Contingency/Insurance/Taxes, etc.
b. REDAM’s Submission in Case No. 58 of 2008
i. Tariff at the rate of last financial of the eight year cycle determined by the
Commission under its order dated 24 November, 2003
c. Commission’s Ruling in Case No. 58 of 2008
i. Determined Tariff at Rs. 2.52 per unit, (i.e., arithmetic average of rates
proposed by both the Parties) [i.e., Rs 2.52 per unit = (Rs 1.29 per unit +
Rs 3.74 per unit)/2]
1.56 With respect to IWPA submission to refer the Karnataka Electricity Regulatory
Commission’s (KERC) Order dated 11 December, 2009 for fixation of tariff after the
expiry of EPA. The Commission has referred the relevant extract of the said Order which
stipulates as under:
“In view of the fact that, after completion of 10 years debt servicing will have
been fully met and the only increase (marginal) would be in respect of O&M
expenses, but at the same time the opportunity cost of the power has gone up, the
Commission decides to allow the rate equal to the rate at the end of the tenth
year, without escalation for the next ten years for all renewable projects. This
Order in Case No. 92 of 2012
MERC, Mumbai Page 20 of 57
tariff is also applicable to such PPAs in which ten years period is already
completed but no tariff has been determined.”
1.57 The Commission notes that the in Karnataka, Wind Energy projects prior to its Tariff Order
of 2004 were governed by the Government of Karnataka’s Policy, which had prescribed
tariff on simple escalation basis on y-o-y (year on year) basis similar kind of principle
specified in Maharashtra for Group-I Wind Energy projects were governed by Government
of Maharashtra’s Policy. Hence, the Commission rules the submission of IWPA in this
regard cannot be accepted, since, such tariff as specified in the State’s Wind Policy was
only adopted and not determined.
1.58 However, subsequent to that the KERC in the Order dated 18 January, 2005 in the matter of
determination of tariff in respect of Renewable sources of Energy had determined the tariff
for projects and was made applicable for to all the Power Purchase Agreements filed before
the Commission on and after 10 June, 2004.
1.59 The Commission notes the different tariff streams as specified by it for Wind Projects in
Maharashtra and as determined by KERC shown in the Table below:
Rs./kWh
MERC KERC
Order,
2004 Tariff Year
Commissioning Year (Group-II Projects Commissioned
After 27 Dec, 1999 and Before 31 Mar, 2003)
FY 1999-00 FY 2000-01 FY 2001-02 FY 2002-03
FY 1999-00 2.80
FY 2000-01 2.91 2.91
FY 2001-02 3.02 3.02 3.02
FY 2002-03 3.13 3.13 3.13 3.13
FY 2003-04 3.24 3.24 3.24 3.24
FY 2004-05 3.35 3.35 3.35 3.35 3.95
FY 2005-06 3.46 3.46 3.46 3.46 3.82
FY 2006-07 3.57 3.57 3.57 3.57 3.69
FY 2007-08 3.68 3.68 3.68 3.56
FY 2008-09 3.79 3.79 3.43
FY 2009-10 3.9 3.3
FY 2010-11
MERC Tariff stream is in increasing trend; while KERCs
Tariff stream is in decreasing trend.
3.18
FY 2011-12 3.05
FY 2012-13 2.93
FY 2013-14 2.80
Order in Case No. 92 of 2012
MERC, Mumbai Page 21 of 57
1.60 The Commission notes that KERC determined the tariff on cost-plus approach, accordingly
has reducing tariff at the end of 10th
year, while the Commission adopted cash flow method
and to minimise the impact of high initial tariff, front loading avoided and hence a simple
escalation on year on year was specified. Accordingly, the Commission rules that no
comparison with other States can specified to determine the tariff after expiry of the EPA.
1.61 Accordingly, the Commission rules that regulatory process for determination of tariff for
Group-II wind energy projects; upon expiry of validity of existing EPA, will have to be
undertaken in a transparent manner including participation of all key stake-holders similar
to any other tariff determination process. The Commission shall initiate such regulatory
process on suo-motu basis summarising key issues involved in tariff determination for
Group-II wind energy projects; upon expiry of validity of existing EPAs. The Commission
shall invite comments/objections/suggestions of all concerned before determining Tariff for
such projects.
1.62 However, for Group-IV Projects, i.e., the Projects for which tariff has been determined
under MERC (RE Tariff) Regulations, 2010, the Commission in Case No. 6 of 2013 has
ruled that in the matter of Determination of Generic Tariff for the fourth year of the first
Control Period under Regulation 8 of the Maharashtra Electricity Regulatory Commission
(Terms and Conditions for Determination of Renewable Energy Tariff) Regulations, 2010 on
the issue of tariff structure, PPA and useful life of Wind Power Plants had clarified as under:
“...The Commission also observes that while tariff period is specified as 13 years, the
levellisation is carried out over useful life which is 25 years and not just over 13 years,
thereby ensuring the cost recovery is spread over entire useful life which also results in
back-ending of the returns.”
1.63 Considering the fact that for Group-IV Projects, i.e., the Projects for which tariff has been
determined under MERC (RE Tariff) Regulations, 2010, the tariff is determined
considering the levellisation over the useful life of the Wind Projects, the Commission rules
that if such Projects opt to extend the EPA period from 13 years to 25 years, the tariff
determined for Wind Energy Projects for 13 years, considered from the date of commercial
operation of the Wind Project shall also be applicable from 14th
year to 25 years.
Order in Case No. 92 of 2012
MERC, Mumbai Page 22 of 57
Issue No. 4: Obsolesce of Technology and Repowering of Wind Turbines
MSEDCL
1.64 MSEDCL submitted that refurbishment of old Turbines shall be allowed only if WEGs
agree to enter EPA with MSEDCL for whole plant life of 20 years. MSEDCL further
submitted that this is necessary as the Commission had determined the Tariff for entire
plant life of 20 years and the WEGs may have availed the benefit of accelerated
depreciation in the initial period of life of the Wind Power Plant.
1.65 MSEDCL further submitted that many of the Wind Turbines in the State are old and need
more O&M expense since, breakdown of critical components of the Wind Turbines affects
the machine availability.
1.66 Further, MSEDCL submitted that if any WEG is planning for refurbishment to sell power
under Open Access, it shall be subject to the provisions of the MERC (Distribution Open
Access) Regulations, 2005. Accordingly, reduction of contract demand, energy accounting
of 15 minutes time block, installation of Special Energy Meter at both the ends along with
scheduling of generation as well as consumption shall be made compulsory for WEGs who
are planning for refurbishment and opt to sell Wind Energy under Open Access route.
IWPA
1.67 IWPA submitted that from the experience of its members, fair changes in Wind energy
technology occur in 5 to 8 year period. IWPA submitted that small changes an ongoing
process but substantial development could be seen over a longer period of 5 years. IWPA
submitted that when Wind energy development began in India, market was flooded with
225 kW to 250 kW of Wind Turbines. However, the capacities of Wind Turbines have
increased to 1.5 MW to 2 MW and beyond.
1.68 Further, IWPA submitted that the tower hub height has also increased from 25 meters to 75
meters to harness more Wind energy. IWPA submitted that the Commission may deliberate
on evolving a Policy of repowering so that more and more high capacity Wind Turbines on
taller towers could replace the existing small capacity Wind Turbines so as to harness more
energy at the same location. IWPA submitted that marked changes in the blade design and
aerodynamic technology have also facilitated the increase in generation, although with a
Order in Case No. 92 of 2012
MERC, Mumbai Page 23 of 57
higher capital cost. IWPA further highlighted the saturation of high potential land and
submitted that the potential land is available in the forest area for which the approvals from
the Forest and Environment Department requires considerable time.
1.69 IWPA submitted that few advancements over a period include uniquely designed wind
turbine blades from fiber glass with reinforced epoxy resin so as to support in terms of
optimal aerodynamics, introduction of permanent magnet generator i.e., system having
parts of conventional wind turbines and also moving parts. Conventionally people used to
increase the blade size to increase the turbine efficiency which soon turned out to be an
expensive option with limited availability of space. This resulted in the need for increase in
height of towers.
1.70 Introduction of laser system in wind mills overseas wherein the sensors monitor the wind
speed and direction in order to automatically adjust the position of turbine blades. In such a
manner the stress is reduced and more energy is generated. There are technologies of low
cost device that measures the speed and direction of the wind seconds before it hit the
turbine blades. The device is capable of receiving measurements up to 200 mts. of height.
This would also facilitate installing more turbines per acre of land. The new inventions
include Jet inspired Wind Turbines wherein the design provides for minimum wind losses.
Conventionally in a Wind Turbine half of the wind energy is spent on rotating the blades
while the other half in generating electricity. Some of these designs are yet to reach India.
Tata Motors Limited
1.71 TML submitted that refurbishment of old turbines is a welcome initiative, provided TML is
not called upon to give up any of its right available under the prevailing law. TML further
opposed to the conditional permissibility of refurbishment of old turbines i.e.,
refurbishment to be allowed only when Wind farm developers agree to enter into PPA with
MSEDCL for the whole of plant life i.e. 20 years. TML submitted that such conditions
would not be in accordance with the provisions of the Electricity Act, 2003 i.e.,
encouraging Open Access.
Order in Case No. 92 of 2012
MERC, Mumbai Page 24 of 57
Commission’s Ruling:
1.72 The summary of the installations of WTGs of various capacities over the years in the State
of Maharashtra is shown in the Table below:
*Source: Year-wise installation of WTGs data published by MEDA
1.73 It can be observed from the above Table that smaller capacities of Wind Turbine has also
been installed in FY 2011-12, therefore there appears to be no obsolescence of technology
rather there happens to be technology advancement over the period. In the later years,
installations of higher capacities have taken place.
1.74 It is noted that Re-powering deals with the replacement of first generation small capacity
Wind Turbines with modern Mega-watt and Multi-Megawatt Wind Turbines. Some of the
benefits of Re-powering is summarised as under:
(a). More efficient use of potential land, more capacity addition per unit of land area.
(b). More energy generation per unit of land area and per square meter of rotor area
with improved economics.
(c). Increase in the percentage share of wind-power in the power-generation mix
(d). Re-powering can be used as tool to achieve targets for RPO in Maharashtra
(e). More social and environmental benefits such as improved landscape, a lesser
number of turbines, a lesser footprint area utilization, use of new technology
Unit Capacity
(kW)
FY
1997-98
FY
1998-99
FY
1999-00
FY
2000-01
FY
2001-02
FY
2003-04
FY
2004-05
FY
2005-06
FY
2006-07
FY
2007-08
FY
2008-09
FY
2009-10
FY
2010-11
FY
2011-12
225 0.23 1.35 2.70 2.93 4.50 9.90 7.65 0.90
230 1.84 2.30 7.82 9.66 16.56
250 3.50 0.25 18.00 3.00 3.25 4.25
350 14.00 37.80 88.55 56.70
500 1.00 17.50
600 4.80 33.60 5.40 42.00 16.20 34.20 15.00 4.80 4.80
750 2.25 8.25 6.00 12.00 3.00
800 2.00 27.20 103.20 43.20 41.60 40.80 27.20 123.20
850 34.00
1000 53.00 2.00 48.75
1250 6.25 31.35 251.25 47.50 15.00 42.50 42.50 35.00
1500 40.50 120.00 50.08 25.50 46.50 178.50
1650 42.00 44.55 33.00 11.55 4.95 42.90
2000 2.00 32.00 10.00
2100 4.20 39.90 12.60
2500 5.00
Total (MW) 5.57 17.65 50.57 117.19 188.11 8.25 48.75 117.95 484.50 269.80 178.08 138.85 239.05 407.35
Order in Case No. 92 of 2012
MERC, Mumbai Page 25 of 57
reducing noise-levels, reduced avian mortality resulting in better technology
acceptance by communities.
(f). Better power-grid integration
(g). Reduction in risks and uncertainties for wind-energy estimation, etc.
1.75 Though there are various benefits as indicated above, however, there are certain challenges
also envisaged in the Re-powering summarised as under:
(i). Turbine ownership: Repowering will reduce the number of turbines and there may
not be one-to-one replacement. Thus, the issue of ownership needs to be handled
carefully.
(ii). Land ownership: Multiple owners of wind farm land may create complications for
repowering projects.
(iii). Power Purchase Agreement: PPAs were signed with Distribution Licensees for 13
years and the respective Distribution Licensees may not be interested in
discontinuing or revising the PPA before its stipulated time.
(iv). Electricity evacuation facilities: The current grid facilities are designed to support
present generation capacities and may require augmentation and upgrading.
(v). Additional costs: The additional decommissioning costs for old turbines (such as
transport charges) need to be assessed.
(vi). Disposal of old turbines: There are various options such as scrapping, buy–back by
the Government or manufacturer, or export.
(vii). Incentives: In order to compensate for the additional cost of repowering, appropriate
incentives may be stipulated.
(viii). Policy package: A new policy package may be developed which may include a
repowering incentive (on the lines of the recently introduced generation-based
incentive scheme by (MNRE).
Order in Case No. 92 of 2012
MERC, Mumbai Page 26 of 57
1.76 Hence, in exercise of the powers vested in it under Section 86 (2) of the Electricity Act,
2003, advises the Government of Maharashtra to formulate a Policy to encourage and
promote Re-powering of the existing small Wind Turbines within the State, which could
result in higher generation and also lead to better utilisation of existing wind sites, which
would help to encourage the investments in the State and also help to the meet the targets of
RPO. In these circumstances, considering the infirmity of Wind Power, the Government
may also consider to frame appropriate Policies for encouraging Pump-Storage Schemes
and Energy Storage Schemes.
Issue No. 5: Objective of Renewable Energy Certificate (REC)
MSEDCL
1.77 MSEDCL submitted that REC mechanism is a market based instrument to promote
Renewable Energy and facilitate compliance of Renewable Purchase Obligation (RPO).
MSEDCL submitted that the objective of REC is to address the mismatch between
availability of Renewable resources in the State and the requirement of the Obligated
Entities to meet the RPO. Through REC mechanism, it is expected that both Renewable
Energy Generators and Distribution Licensees/Consumers should get benefits and present a
win-win situation for both the Parties.
IWPA
1.78 IWPA submitted that the objective of introducing REC is that presently most States are
deficient in the availability of Renewable Energy and on account of nature of such
Renewable Energy sources, every State is endowed with only specific Renewable Energy
and at time the same is very much limited too. In the endeavor of the Central Government
and the State Governments and supported by Nodal Agencies and the Regulatory
Commissions to conserve the fossil fuel and to harness more and more Renewable Energy
and further making it mandatory for all Distribution Licensees, Captive Users and Open
Access consumers to compulsorily purchase power from Renewable Energy sources or in
its absence RECs. The respective State Electricity Regulatory Commissions have specified
only minimum qualificatory conditions on category of entities that can opt for Open Access
and avail REC benefits. IWPA further submitted that as the objective of REC is abundantly
clear, any Policy review in the matter of eligibility of REC is not called for.
Order in Case No. 92 of 2012
MERC, Mumbai Page 27 of 57
1.79 IWPA submitted that as detailed in the CERC REC Regulations, 2010, MERC RPO
Regulations and implementation of REC Framework, 2010 and the Discussion Paper of the
Consultant appointed by the Commission has made it abundantly clear that the objective of
REC which principally aims at compliance with RPO by every Obligated Entity in order to
promote generation from Renewable Energy sources.
Commission’s Ruling:
1.80 The Commission notes the following primary objectives identified for REC mechanism:
(i). Effective implementation of RPO mechanism in Maharashtra
(ii). Increased flexibility for participants to carry out RE transactions
(iii). Overcoming geographical constraints to harness available RE sources
(iv). Reduce transaction costs for RE transactions
(v). Create competition among different RE technologies
(vi). Development of all encompassing incentive mechanism
Issue No. 6: Eligibility for Renewable Energy Certificate (REC)
MSEDCL
1.81 MSEDCL submitted that a Captive Power Plant (CPP) based on Renewable Energy is not
eligible for REC, if it has availed or proposes to avail any benefit in the form of
concessional/promotional transmission or wheeling charges, banking facility benefit and
waiver of electricity duty. Even if the CPP forgoes the benefits of concessional
transmission and wheeling charges, banking facility benefit and waiver of electricity duty,
it shall become eligible for REC scheme only after a period of three years from the date of
foregoing such benefits.
1.82 MSEDCL submitted that the Commission in its Order dated 9 September, 2011 in Case No.
43 of 2010 in the matter of De-novo re-determination of Cross Subsidy Surcharge (CSS)
determined CSS as 25% of the applicable CSS for Open Access consumer purchasing
power from Renewable Energy Sources. MSEDCL submitted that such concession shall be
treated as preferential and such WEGs and Open Access consumers shall not be eligible for
benefit of REC scheme.
Order in Case No. 92 of 2012
MERC, Mumbai Page 28 of 57
1.83 MSEDCL further submitted that through REC mechanism, Renewable Generators as well
as the Distribution Licensee should be benefited. MSEDCL submitted that WEGs availing
any form of concession from GoM/MERC shall not be eligible for participation in REC
scheme and shall not be allowed to earn windfall profits.
IWPA
1.84 Further, IWPA referred the eligibility condition for the Eligible Entities for receiving RECs
as per Central Electricity Regulatory Commission (Terms and Conditions for recognition
and issuance of Renewable Energy Certificate for Renewable Energy Generation)
Regulations, 2010 dated 14 January, 2010.
1.85 IWPA submitted that both, this Commission as well as the CERC stipulate that REC
Mechanism has two components viz., electricity component and Renewable Energy
component. The ineligibility for REC is linked to preferential Tariff for sale of power to
Distribution Licensee or Tariff for sale of power to Distribution Licensee not to exceed
their APPC i.e., the reference of preferential benefit is only with respect to the electricity
component and not to the Renewable Energy component or REC which represent
environmental attributes of Renewable Energy generation.
1.86 Hence both the Regulations do not bar Renewable Energy Generator from availing REC
benefits merely because the Regulatory Commission has provided for “discounted” CSS
payable on account of the fact that the power being purchased by open access consumers is
from renewable energy sources.
1.87 Further, IWPA referred statement of objects and reasons issued by the CERC on 27
September, 2010 in the matter of CERC (Terms and Conditions for Recognition and
Issuance of Renewable Energy Certificates for Renewable Energy Generation) (First
Amendment) Regulations, 2010 stipulates that jurisdiction regarding eligibility conditions
to avail REC benefits lies with CERC only.
1.88 IWPA submitted that discount on CSS available to Open Access transactions from
Renewable Energy Generators cannot be interlinked with qualification for REC benefits.
IWPA submitted that neither RPO nor REC Framework have been linked with levy of CSS.
Order in Case No. 92 of 2012
MERC, Mumbai Page 29 of 57
1.89 IWPA submitted that the Commission in view of the infirm nature of Wind has stipulated a
lower CSS for Open Access Consumer and the same cannot be termed as a discount. IWPA
submitted that CSS is the charge or penalty on Open Access consumers who are in the high
end category and who migrate away from Distribution Licensee by purchasing power from
Parties (including Renewable Energy Generators) other than Distribution Licensee. Since
many a state controlled Distribution Licensees have certain obligations to different sector of
economy like agriculture, certain element of CSS is required to be stipulated.
1.90 IWPA further submitted that the Commission in order to encourage setting up of more
Renewable Energy Projects like wind power as sale of power from Renewable Energy
sources has provided the “discounted” CSS to Open Access.
1.91 IWPA further submitted that without prejudice to submission made as above it further
submitted that merely because certain power like Wind and Solar are infirm, CSS may not
be restricted to a preferential discount as compared to normal CSS rate. IWPA submitted
that ultimately the CSS is computed on power consumed by Open Access consumers from
sources other than the Distribution Licensee. Such levy is on the actual power consumed by
the consumer irrespective whether it is Wind power or any other Renewable power or
conventional power. Therefore, CSS has no relevance to the infirm nature of the power.
IWPA submitted that whenever any charges are linked to capacity of the plant, same scale
for conventional and non-conventional power especially infirm power like Wind Power
cannot be applied. However when charges are based on units consumed the nature or source
of power has little effect. On the basis of above reasoning, IWPA submitted that CSS is
required to be charged at the normal rate on Open Access consumers and other entities as
per Regulation at the normal rate of CSS determined by the Commission without granting
any discount and accordingly requested the Commission to take a final decision in the
matter of CSS.
Tata Motors Limited
1.92 TML submitted that, the CERC Regulations on REC framework dated 14 January, 2010 is
elaborate and clear and requires no comments as far as eligibility for REC mechanism is
concerned. TML submitted that CSS levied by the Commission is based keeping in view
Order in Case No. 92 of 2012
MERC, Mumbai Page 30 of 57
the infirm nature of the Wind energy and the same cannot be termed as a preferential
treatment.
1.93 TML submitted that presently CSS discount is available only for self use and not for third
party Wind power sale. In order to get adequate return on investment, REC mechanism
should be continued to be made available for all old & new Wind Projects for third party
sale. TML submitted that CSS levied by this Commission is based keeping in view the
infirm nature of the Wind energy and the same cannot be termed as preferential treatment.
Wind World (India) Limited [Erstwhile Enercon (India) Limited]
1.94 WWIL submitted that consumers procuring power from Renewable Energy Generating
Stations must be exempted from CSS as Renewable Generators need such exemptions in
order to compete with other generation sources in the market. WWIL submitted that CSS
on Open Access consumers is applied so that these subsidizing categories of consumers
when procure power from outside, the Tariff burden should not fall upon the subsidized
consumers. But, in case of Renewable Energy, the Open Access consumers are already
fulfilling their social obligation and supporting the promotion of Renewable Energy and
hence should not be further burdened with CSS. Further, WWIL submitted that CERC in its
REC amendment Regulations, 2010 has not stipulated discount on CSS as a concessional
benefit for non-eligibility of REC.
Commission’s Ruling:
1.95 The Commission notes the CERC in its Second Amendment to CERC (Terms and
Conditions for recognition and issuance of Renewable Energy Certificate for Renewable
Energy Generation) Regulations, 2010 (hereinafter CERC REC Regulations, 2010) has
specified the following concessional benefits for Projects which a Project has to forego in
order to avail REC benefits.
(i). Concessional/promotional transmission charges
(ii). Concessional/promotional wheeling charges
(iii). Banking facility benefit. The expression ‘banking facility benefit’ shall mean only
such banking facility whereby the CGP or any other renewable energy generator
Order in Case No. 92 of 2012
MERC, Mumbai Page 31 of 57
gets the benefit of utilizing the banked energy at any time (including peak hours)
even when it has injected into grid during off‐peak hours.
1.96 The Commission noted that CERC by way if Second Amendment to CERC REC
Regulations, 2010 had withdrawn the criteria of waiver of Electricity Duty as one of the
concessional benefits.
1.97 As regards the submissions of the stakeholders the Commission has fixed the CSS as 25%
of the applicable CSS for Open Access consumer purchasing power from for Wind Power
Projects considering infirm nature of wind generation, the Commission clarifies no such
criteria was considered. The Commission has fixed concessional CSS in order to promote
the Renewable Energy sector in the State of Maharashtra. The relevant extract of Order
dated 9 September, 2011 in Case No. 43 of 2010 is reproduced as under:
“The Commission views that increase in generation from renewable sources is also
environmentally beneficial policy and it is also the mandate of the EA 2003 as per the
provisions of Section 86 (1) (e) thereof read with Para 5.2.20 of the NEP. However,
considering the submissions of the distribution licensees and the parties representing the RE
Sector, the Commission is of the view that some CSS must be levied on OA transactions by
RE Sector instead of continuing with the exemption. Therefore, the Commission decides to fix
CSS as 25% of the applicable CSS for open access consumer purchasing power from
renewable sources of energy.. This would compensate the distribution licensees and yet not
demote promotion of RE Sector.”
1.98 As regards the submissions of the stakeholders that the CERC in its REC Regulations, 2010
and Amendment thereof has not stipulated discount on CSS as a concessional benefit for
non-eligibility of REC, the Commission has taken a note of the same. However, the
Commission is fully aware of the powers conferred to it under the Electricity Act, 2003 and
among other powers, it only has the jurisdiction to determine the CSS.
1.99 The Commission notes that with the implementation of REC mechanism, the WEGs
receives another source of income by way of selling of RECs on Power Exchanges.
However, under such schemes, a WEG would be selling only the electricity component to
the third party consumer and not the Renewable Energy. The Renewable Energy
Component is being sold on Power Exchanges in form of RECs.
Order in Case No. 92 of 2012
MERC, Mumbai Page 32 of 57
1.100 However, the Commission directs the Secretariat of the Commission to evaluate the need
of concessional benefit on CSS for open access transactions from Renewable Energy and
present it to the Commission within next 6 months of issuance of this Order.
Issue No. 7: Banking and Banking Charges
MSEDCL
1.101 MSEDCL submitted that due to infirm nature of Wind, it is very difficult to predict the
generation from Wind for a particular period. MSEDCL submitted that around 70% of the
Wind energy is generated during the period of June to September, i.e., just 4 months and
only 30% of the Wind energy is generated during the balance period. Also, most of the
Wind generation is during night i.e., off peak period and low in peak period i.e., morning.
MSEDCL submitted that this mechanism allows WEGs to inject power into the grid during
off peak low Tariff hours and consume high Tariff power during peak hours.
1.102 MSEDCL submitted that Wind Power Tariff Order, 2003 has provided that Wind Energy
generated at any given Time of Day (ToD) slot would be allowed to adjust against the
consumption at that particular ToD slot on any given day during the same financial year
and that Banking is applicable to those Wind Generators who consume power for self-use
or selling power to a third party. MSEDCL submitted that Tariffs can change not only
during the day but also during different seasons and therefore a careful examination must
be done of banking system. MSEDCL submitted that two major issues need to be examined
whether Banking system can be continued with adjustments in Tariff for the period in
which energy is injected and the period in which energy is drawn to take care of price
fluctuations over the seasons or whether it should be totally given up or not.
1.103 MSEDCL submitted that with Final Balancing and Settlement Mechanism (FBSM) in
place, it is very difficult to match drawl and schedule with provision of Banking. Therefore,
requested the Commission to not allow Banking as it would make energy accounting
complicated.
IWPA
1.104 IWPA submitted that Banking of energy is a mandatory requirement with respect to
infirm power like Wind. IWPA referred the Hon'ble Appellate Tribunal for Electricity
Order in Case No. 92 of 2012
MERC, Mumbai Page 33 of 57
(APTEL’s) Judgment dated 7 September, 2006 in Appeal 20 of 2006 in the case between
Chhattisgarh Biomass Energy 14 of 53 Appeal No. 74 of 2007 Developers Association &
Ors. Vs. CSERC.
1.105 Further, IWPA submitted that the Hon’ble APTEL had reiterated the concept of Banking
in their Order dated 21 September, 2011 in Appeal nos. 53, 94 and 95 of 2010 in Case of
Tamil Nadu Electricity Board (TNEB).
1.106 IWPA submitted that the Commission in its Wind Power Tariff Order, 2003 permitted
Banking for a period of 12 months with no specific Banking charges. IWPA further
submitted that Banking, as in Wind Power Tariff Order, 2003 be allowed to continue as it is
definitely one of the encouraging attributes for continued development of Wind Energy in
the State.
1.107 IWPA submitted that as presented by MSEDCL, only 275 MW Wind power developers
have opted for third party sale. The said 275 MW roughly translates to a mere 377 MU
which is only 0.34% of the total power in MU handled by MSEDCL. Further, the entire
quantum of 0.34% may not contribute in a mismatch of generation and consumption.
Therefore such mismatch quantum from Wind Power Open Access would be a miniscule
vis-à-vis the quantum of power handled by MSEDCL. Further, IWPA submitted that the
contention sought to be raised by MSEDCL cannot be implemented as the same is contrary
to the prevailing law in which Open Access as well as incidental Banking is required to be
encouraged.
1.108 IWPA submitted that as far as Banking is concerned, as per the Regulations in the State
such adjustments are made for the same time zone as per ToD meter. IWPA submitted that
even CERC in its Order dated 27 September, 2010 has held that since such adjustment is
based on the respective time zones, the availability of Banking cannot be considered as a
concession. MSEDCL do not raise any issue when wind farm developers sell power to
MSEDCL. Questions are raised when wind farm developers opt for Open Access.
MSEDCL had raised no issues with respect to matching generation with drawl of wind
power when wind power is sold to MSEDCL. Also 75% of the total power distributed is in
the domestic segment and another 16% is in the agricultural sector as per Statistics
provided by MSEDCL and obviously MSEDCL takes care of estimated drawls by such a
Order in Case No. 92 of 2012
MERC, Mumbai Page 34 of 57
huge segments constituting 91% (in terms of numbers and 42% in terms of MU) of the
power distribution.
Tata Motors Limited
1.109 TML submitted that banking facility is available to them till date without any charges.
TML submitted that Banking of Wind energy for at-least one year from the date of injection
should be provided as per the Commission’s Wind Power Tariff Order, 2003. TML
submitted that considering the infirm nature of Wind, GoM’s Wind Power Policy dated 12
March, 1998 read with various Orders passed by the Commission/APTEL have provided
for Banking facility.
1.110 TML presented the following to show the impact of Banking facility on the ARR of
MSEDCL:
“…
I. Let total installed capacity = 2500 MW @ 15% CUF
II. Let 1000 wind developers have installed capacity = 2000 MW @ 2MW
each (in reality it may be more)
III. Captive (Self Use) and Third Party sale to Open Access consumer
installed capacity = a-b = 500 MW approx.
IV. Let A Slot TOD Generation @30% = 197.1 MUs (Ref =
cx0.15x24x365x0.30)
V. MSEDCL have said A zone rainy season Market rate = Rs 1.50 per KWh.
VI. However MSEDCL rainy season A zone Tariff rate for HT Consumer like
TML was = Rs 5.69 (excluding Tax & duties, MD charges, etc.)
VII. Can we say that MSEDCL have earned a profit of Rs 4.19 for every unit
billed to diligent consumer like us.
VIII. MSEDCL have projected KWh requirement = 90000 MUs (for year 2010-
11)
IX. Assuming 10% increase for Year 2011-12 and power requirement =
100000 MUs approx.
X. Contribution of Wind power generation in A slot from Captive & Third
Party vis-à-vis Total Power = 0.197%
Order in Case No. 92 of 2012
MERC, Mumbai Page 35 of 57
XI. If we assumed 100% banked unit, the impact is = less than 1 paise per
unit on ARR
XII. But in reality only about 10% banking is required per year. There is no
significant impact on the ARR.
…….”
Wind World (India) Limited [Erstwhile Enercon (India) Limited]
1.111 WWIL submitted that the Commission in its Wind Power Tariff Order, 2003 permitted
ToD Banking. Further, WWIL submitted that the provisions of Banking as in WPTO are as
per the terms of Section 61 (h), 86 (1) of Electricity Act, 2003 and the provisions of Tariff
Policy and National Electricity Policy.
1.112 WWIL submitted that the Wind Industry cannot survive without the provision of
Banking. WWIL submitted that if Banking is discontinued in the State, the infirm nature of
the Wind would be an operational constraint in the balancing and settlement of Wind
energy. WWIL submitted that the Commission has to give due regard to the operational
constraints while determining wheeling charges for Open Access consumers as per
Electricity Act, 2003.
1.113 WWIL submitted that the Commission should provide Banking provision in the Open
Access Regulation itself. WWIL further referred to the Judgments of the Hon’ble APTEL
viz. Judgment in Appeal No. 98 of 2010 and Judgment in Appeal No. 53 of 2010 regarding
the Banking facility.
1.114 WWIL submitted that even Indian Electricity Grid Code (IEGC) Regulations, 2010
issued by the CERC where Wind Generators had to forecast for 15 minute time block on a
day-ahead basis have not been implemented as there are many constraints which need to be
addressed. WWIL submitted that therefore, the Commission may continue with the existing
Banking mechanism.
Arvind Cotsyn
1.115 Arvind Cotsyn submitted that the Banking facility on yearly basis must be continued.
Order in Case No. 92 of 2012
MERC, Mumbai Page 36 of 57
Shri R. B. Goenka
1.116 Shri Goenka submitted that Projects whose EPA has expired and now availing third party
sale and self-use should be charged separate banking charges apart from transmission
losses, distribution losses and cross subsidy surcharge. These banking charges may be in
form of kind i.e., some percentage of energy wheeled may be debited in the banking facility
users account. He further submitted that said energy in form of charges to be allowed to
fulfill the RPO obligation of the licensee so that the commercial interest of the licensee
shall be covered and general consumers shall also benefited.
Commission’s Analysis
1.117 The Commission notes that existing banking facility as specified in the Wind Power
Tariff Order, 2003 stipulates as under:
“In view of these considerations, the Commission has taken the following decisions:
i) Banking of energy will be permitted at any time of the day and night
ii) Balance at the end of the financial year will not be carried over to the next
year
iii) Surplus energy at the end of the financial year, limited to 10% of the energy
(kWh) fed into the grid during the financial year, will be purchased by the
utility at the lowest TOD slab rate for HT energy tariff applicable on 31st
March of the financial year in which the energy was banked.
iv) Surplus energy in excess of 10% of the energy fed into the grid during the
year due to force majeure conditions shall be purchased by the utility at a
rate equivalent to the weighted average fuel cost as determined by the
Commission in the tariff order and in force from time to time.
v) The payment for surplus energy should be made to the developer/ owner and
not to the consumer in case of third party sale.”
Order in Case No. 92 of 2012
MERC, Mumbai Page 37 of 57
1.118 The Commission has taken a note of the submissions of MSEDCL that when the banked
energy is redrawn by the Wind Generators, power has to be procured from the market at
higher rates and therefore the impacting financially to the licensee.
1.119 The Commission notes that in the Order dated 3 January, 2013 in Case No. 8 of 2012,
Case No. 18 of 2012, Case No. 20 of 2012 and Case No. 33 of 2012 considering the
submission of MSEDCL regarding commercial and financial implication of providing
banking facility to wind projects, had directed MSEDCL to carry out a detailed study based
on the historical actual generation, actual power purchase cost, incremental power purchase
cost, banking, any other relevant parameters, banking provisions provided in other States,
etc.
1.120 Accordingly, the Commission directs MSEDCL to submit the said Report and based on
such findings may file a separate Petition to review the existing provision of banking. The
Commission further rules that existing banking mechanism as stipulated in the Wind Power
Tariff Order, 2003 shall be continued.
1.121 The Commission further notes that stakeholders have opposed for levy of any banking
charges for banking facility, however, such stakeholders in other States had supported for
retaining the banking facility however with some charges.
1.122 The Commission further rules that in ad-interim basis banking charges in kind shall be
levied @5% on the energy banked at the end of every month and the same shall be reduced
from the energy banked at the end of the month. The Commission shall review the same
based on the Petition filed by MSEDCL in this regard.
Issue No. 8: Sale at Average Pooled Power Cost (APPC) and Compliance to RPO
MSEDCL
1.123 MSEDCL submitted that one of the options available with WEGs is to sell Wind energy
to Distribution Licensee at a price not exceeding the APPC of such Distribution Licensee.
MSEDCL submitted that APPC is the weighted average pooled price at which the
Distribution Licensee has purchased the electricity including cost of self generation, if any,
Order in Case No. 92 of 2012
MERC, Mumbai Page 38 of 57
in the previous year from all the long-term and short-term energy suppliers, but excluding
those based on Renewable Energy sources, as the case may be.
1.124 The energy sale at APPC as approved by the Commission from time to time is eligible to
claim the REC benefit.
1.125 MSEDCL further submitted that such energy purchase is not considered for fulfilment of
RPO and request the Commission to consider the same for RPO fulfilment.
IWPA
1.126 IWPA submitted that issue raised regarding purchase at APPC is in the domain of CERC
and if the CERC relaxes this aspect there would be savings both to State Utilities as APPC
rate is much less than the preferential tariff rate in many States and further facilitating
development of REC to make good the shortfall in availability of renewal power in
different parts of the country in the matter of obligated entities meeting the RPO
requirements. IWPA submitted that however if more entities opt for REC, it could
adversely impact the REC market and the same needs to be addressed to by the Hon’ble
CERC.
1.127 IWPA submitted that many States have given option for purchase of power at APPC and
the utilities are also entering into EPA to purchase power at APPC rate and the developer
being eligible for REC. IWPA submitted that this may work out to be more economical to
MSEDCL, and the Wind farm developers may also be inclined to sell power at APPC rate
to MSEDCL post expiry of their EPAs and further avail REC.
Wind World (India) Limited [Erstwhile Enercon (India) Limited]
1.128 WWIL submitted that under REC mechanism the electrical component of Renewable
power has to be sold by the Renewable Energy Generator at APPC of previous year.
Enercon submitted that the Commission should declare APPC of previous financial year
timely so that there is no ambiguity in the determination of cost of power under REC
mechanism.
Order in Case No. 92 of 2012
MERC, Mumbai Page 39 of 57
Tata Motors Limited
1.129 TML submitted that RPO needs to be fulfilled by MSEDCL by purchase of power at
preferential Tariff fixed by the Commission and that such purchase at APPC cannot amount
to an RPO purchase.
Commission’s Ruling:
1.130 The Commission notes that the CERC REC Regulations, 2010 stipulated that sale to host
Distribution Licensee at APPC by the Renewable Energy Project shall be considered as
eligible to participate under REC mechanism. Under the existing REC mechanism
approved by the CERC, Projects selling power at APPC to Distribution Licensee would be
selling only the electricity component and not Renewable Energy component. Hence, the
said purchase at APPC shall not be considered to meet the RPO targets under the existing
CERC REC Regulations, 2010 and amendment thereof.
1.131 As regards the submission of WWIL that APPC may be declared every year, the
Commission has taken a note of same and hereby directs all the Distribution Licensees in
the State of Maharashtra to file the details of actual Power Purchase expenses of previous
year within one month after the end of previous financial year in order to determine the
average pooled cost of power purchase.
Issue No. 9: Incentives
MSEDCL
1.132 MSEDCL submitted that the State Government provides various facilities to WEGs such
as exemption in electricity duty, infrastructure facilities like approach road, power
evacuation and equity grant. Such facilities shall be treated as concessional benefits and
hence WEGs availing any form of concession from GoM/MERC shall not be held eligible
for participation in REC scheme.
1.133 MSEDCL submitted that GoM Policy is providing many incentives to the Wind energy
developers which are not considered while computing Tariff. MSEDCL listed such benefits
as under:
Order in Case No. 92 of 2012
MERC, Mumbai Page 40 of 57
(a). Electricity Duty: exempted for captive as well as third party sale for first 10 years
(b). Octroi Tax / Entry Tax: 100% refund of Octroi Tax / Entry Tax for equipments
(c). Refund of 50% of expenses on the Evacuation Arrangement from Green Energy
Fund
(d). Refund of 100% expenditure on Approach Road as subsidy from Green Energy
Fund.
IWPA
1.134 On the issue of substantial profit being made by Wind power developers, as referred to by
MSEDCL, IWPA submitted that even if the Wind farm developers have made such profits,
such profits cannot be a matter of deliberation in respect of illustrative issues listed for
policy review. IWPA submitted that policy review or the policy formation could be
deliberated at the highest for new Projects. However, all the existing Projects for which all
the functioning is as per law cannot be questioned and cannot be the subject matter for
discussion.
1.135 On the issue of ‘concessions on certain Open Access charges’, as referred by MSEDCL,
IWPA submitted that there are no concessions enjoyed by Open Access consumers as they
are required to pay the wheeling charges, transmission charges, wheeling loss, transmission
loss as mandated by the relevant Orders of the Commission. The Open Access consumers
of Wind farm developers also pay CSS as determined by the Commission.
1.136 IWPA submitted that wind power has a number of inherent benefits which are difficult to
be quantified but the availability of benefits have been accepted world over and further
India and the State of Maharashtra stands committed for developing more and more
Renewable Energy sources. The Electricity Act, 2003, the Tariff Policy, the Nodal
Agencies in different States, the Central Electricity Regulatory Commission and State
Electricity Regulatory Commissions are all committed for generating more and more power
from Renewable Energy. IWPA further submitted that some of the incentives detailed by
MSEDCL like 50% of the expenses being refunded from Green Energy Fund or Refund of
100% expenditure on approach road, Refund of Octroi and Entry Tax, etc. would have been
considered by the Commission while determining the tariff as ultimately the net cost to the
developer is taken under capital cost.
Order in Case No. 92 of 2012
MERC, Mumbai Page 41 of 57
Wind World (India) Limited [Erstwhile Enercon (India) Limited]
1.137 WWIL submitted that almost all other States in the country except Maharashtra provide
promotional Open Access charges to Renewable Energy Generators. WWIL submitted that
the Transmission charges in Maharashtra for Renewable Generators are equivalent to short-
term Open Access transaction but in other States concessional Transmission charges have
been provided. WWIL requested the Commission to consider the promotional status given
to Renewable Energy under Section 61 (h) and 86 (1) (e) of the Electricity Act, 2003,
National Electricity Policy and Tariff Policy and provide promotional Open Access charges
to Wind Generators.
1.138 WWIL submitted that infrastructure charges provided by MSEDCL to the developers are
mostly delayed leading to loss of working capital. WWIL requested the Commission to see
that the developers are repaid the infrastructure charges on time and if not, some penalty
clause should be inserted which would deter the Distribution Licensees to delay these
payments.
Tata Motors Limited
1.139 TML submitted that being a Group II developer, following concessions were given to
them:
“Sales Tax Benefit - 1/6th
of total investment in wind power Project (excluding land cost)
was available per year to the TML as sale tax benefit for a period of 6 years. TML availed
Rs.18.25 cr per year for six years from 2001-02 to 2006-07.
Capital Subsidy – TML is eligible and entitled to claim Rs.20,00,000/- as capital subsidy.
Earlier MEDA, Respondent No.2 paid Rs. 20,00,000/- to TML towards Capital Subsidy.
However, subsequently MSEDCL, Respondent No.1 arbitrarily, without any authority and
contrary to the law has in November 2008 deducted 50% of this amount i.e.Rs.10 lacs, from
the amount payable to TML by MSEDCL on some other account. I state that TML is
entitled to receive Rs. 10,00,000/- towards Capital Subsidy as per the Order dated April 23,
2010 in Case 70 of 2009 passed by this Hon’ble Commission and the request for payment
is pending with MSEDCL.”
Order in Case No. 92 of 2012
MERC, Mumbai Page 42 of 57
1.140 TML submitted that incentives should be available for the survival of old Wind Projects.
TML submitted that the Wind Projects set-up by them are now old and to upkeep the
installations TML has to incur huge Operation and Maintenance expenses to the tune of
over Rs.20 lacs per month. TML submitted that presently Cross-subsidy surcharge discount
is available only for self use and not for third party wind power sale. Further, TML
submitted that REC mechanism should be continued to me made available for all Old &
New Wind Projects for third party Wind power sale.
Arvind Cotsyn
1.141 Arvind Cotsyn submitted that the ground reality on the allegation of undue enrichment
against Wind power generators is far different. Arvind Cotsyn submitted that the PLF of
20%, as considered for Group III Projects is on a higher side and that the Wind energy is
purchased at a rate lower than that given in the Government of Maharashtra Policy.
1.142 On the incentive of sales tax concession, Arvind Cotsyn submitted that many generators
could not avail the same as their PLF was below 12%. Arvind Cotsyn submitted that
initially, sales tax benefit was given in proportion of PLF, thereafter, the PLF, if more than
12%, was rounded off to 12% for calculating the benefit.
1.143 Arvind Cotsyn submitted that the subsidy on capital investment was disbursed to them
after a period of 5 to 7 years and MSEDCL deducted 50% of it. This shows that the
discounted value of the subsidy on receiving it was negligible. Arvind Cotsyn submitted
that the Government of Maharashtra Policy of 2004 had a clause for ‘Infrastructure
Development and Green Power Fund’. Arvind Cotsyn submitted that neither MEDA nor
MSEDCL has reimbursed any money as per this policy.
Bajaj Finserv
1.144 Bajaj Finserv submitted that WEGs earned less returns than the estimation after the
WEGs were installed during the period 2000-2002, because of non-availability of
MSEDCL's infrastructure to evacuate entire estimated wind energy. Due to this, the GoM
had given relief in eligible production of electricity for tax benefits vide GR dated 7
January, 2002 & letter dated 15 February, 2007. However, investors lost benefits of
electricity generation during that period permanently. Bajaj Finserv submitted that the same
Order in Case No. 92 of 2012
MERC, Mumbai Page 43 of 57
situation continues till today. Presently, at Vankuswade Satara site, the installed capacity of
substation is 250MVA. However, only 150 MVA is working against 185 MW generator's
load and 100 MVA is idle for want of repairs since last 2 years and loss of 35 MW of WEG
continues. Same situation exists at other major site Dhule.
Commission’s Ruling:
1.145 As regards the submission of MSEDCL regarding incentives and facilities provided by
the State Government to WEGs to be treated as concessional benefits and hence such
WEGs shall not be held eligible for participation in REC scheme, the Commission notes
that the CERC REC Regulations, 2010 does not stipulates any such concessional benefits.
1.146 The Commission notes the CERC in its Second Amendment to CERC (Terms and
Conditions for recognition and issuance of Renewable Energy Certificate for Renewable
Energy Generation) Regulations, 2010 (hereinafter CERC REC Regulations, 2010) has
specified only following concessional benefits for Projects which a Project has to forego in
order to avail REC benefits.
(i). Concessional/promotional transmission charges
(ii). Concessional/promotional wheeling charges
(iii). Banking facility benefit. The expression ‘banking facility benefit’ shall mean only
such banking facility whereby the CGP or any other renewable energy generator
gets the benefit of utilizing the banked energy at any time (including peak hours)
even when it has injected into grid during off‐peak hours.
1.147 As regards the submission of MSEDCL regarding factoring of such incentives/facilities
provided by the State Government while deciding the tariff, the Commission notes that
such clarification has already been issued in the Order dated 22 March, 2013 in Case No. 6
of 2013. The relevant extract of the said Order is reproduced as under:
“As stipulated in Regulation 22.1 of MERC RE Tariff Regulations, 2010, the
Commission observes that it shall take into consideration the incentive or subsidy
offered by the Central or State Government while determining the Tariff. The
Commission is of the view that in the absence of specific information as regards
nature of subsidy, its purpose, eligibility, applicability, concerned parties etc., the
Order in Case No. 92 of 2012
MERC, Mumbai Page 44 of 57
Commission is not inclined to pass generic ruling in the matter in the present
proceedings. The issue of sharing of such subsidies can be taken up based on
application filed by the concerned party.”
Issue No. 11: Miscellaneous Considerations/Suggestions
i. Details of Capital Expenditure as sought by the Commission
MSEDCL Submissions
1.148 MSEDCL submitted that the stakeholders have not provided any data related to capital
expenditure along with effect of various concessions for Group I/Group II Wind generating
plants as sought by the Commission. MSEDCL further submitted that it has received some
information from the WEGs and requested the Commission to give more time to study the
submissions made on capital expenditure to submit the comments/observations on the
submission made by the WEGs.
IWPA Submissions
1.149 IWPA submitted its difficulty in collating the past records as the Projects were
capitalized prior to 31 March, 2003. IWPA submitted that another Wind Power Association
viz., Renewable Energy Development Association of Maharashtra (REDAM) had already
provided the capital expenditure data to the Commission on 20 February, 2003 on an
Affidavit at the time of the Commission determining the Wind Power Tariff as part of
proceeding of the Wind Power Tariff Order, 2003.
1.150 IWPA submitted that in the Wind Power Tariff Order, 2003, the Commission had
recognised the average Project cost per MW for about 177 completed Projects at Rs.5.36
Crore/MW as filed by REDAM and Indian Wind Energy Association (InWEA). However,
the Commission considered the Project cost of Rs. 5 Crore/MW for determining the Tariff.
Tata Motors Limited Submissions
1.151 TML submitted that Wind Projects were set by the erstwhile Tata Finance Limited in the
year 2000. The Capital Expenditure made was Rs. 112.02 Crore for a total of 21.95 MW,
translating into Rs. 5.1 Crore/MW
Order in Case No. 92 of 2012
MERC, Mumbai Page 45 of 57
MEDA Submissions
1.152 MEDA submitted that according to market sources, old technology WEGs is available at
around Rs. 5 to 5.5 Crore/MW, while the Class III WEGs which have higher hub height and
bigger blade diameter are costing around Rs. 5.5 to 6 Crore/MW. These Class III WEGs
have higher efficiency than old technology WEGs. Further, there may be variation of 5 to
10% in Project cost due to site conditions.
Commission’s Ruling:
1.153 The Commission extracted the data submitted by REDAM and InWEA on 20 February,
2003 and 17 February, 2003, respectively, from its records. An analysis of the data shows
that average Capex/MW of the data submitted by REDAM was Rs. 5.86 Crore/MW and
that for InWEA was Rs. 5.12 Crore/MW. Following table shows the sale option wise
capacity and capex as provided in the mentioned data.
Capex Data Submitted by REDAM on 20.02.2003
Particulars Capacity (MW) Capex
(Rs. Crore/MW) % of Total
Self Use 24.00 5.72 18%
Third Party Sale 52.18 5.92 40%
Sale to MSEDCL 53.74 5.88 41%
Total 129.92 5.86 100%
Capex Data Submitted by IWEA on 17.02.2003
Particulars Capacity (MW) Capex
(Rs. Crore/MW) % of Total
Self Use 95.56 4.63 46%
Third Party Sale 77.83 5.71 37%
Sale to MSEDCL 35.42 5.16 17%
Total 208.80 5.12 100%
1.154 The Commission directs the Secretariat of the Commission to consider the above
mentioned issue as a separate exercise and present it to the Commission.
Order in Case No. 92 of 2012
MERC, Mumbai Page 46 of 57
ii. Pre-Commissioning PPA Signing
Wind World (India) Limited [Erstwhile Enercon (India) Limited]
1.155 WWIL submitted that currently MSEDCL signs the EPA post commissioning of the
Project. WWIL requested the Commission to give directions to MSEDCL to sign pre-
commissioning PPA which would help in the financial closure.
Commission’s Ruling:
1.156 The Commission has taken a note of the suggestion made regarding signing of EPA
before commissioning of the Plant and also notes that in the past various issues related to
EPA have been submitted by various parties including Distribution Licensees. The
Commission directs MSEDCL to file a separate Petition regarding various modifications in
the EPA.
iii. Group Captive Model
Wind World (India) Limited [Erstwhile Enercon (India) Limited]
1.157 WWIL submitted that Tamil Nadu has come up with its Group Captive model which has
been appreciated by the Distribution Licensee as well as the developers. WWIL requested
the Commission to evolve such Group Captive model in Maharashtra so that both
developers as well as the Utility benefits by attracting various Group Captive players in the
State.
Commission’s Ruling:
1.158 The Commission has taken a note of the suggestion made Group Captive model in the
State of Maharashtra and clarifies that Group Captive Model already exists in the State of
Maharashtra and no restrictions have been imposed in adopting the same. The Commission
clarifies that WEGs are free to choose the Group Captive Model subject to the provisions of
the Electricity Act, 2003 and the Electricity Rules, 2005 made thereunder.
Order in Case No. 92 of 2012
MERC, Mumbai Page 47 of 57
iv. Wind Zoning and Single Tariff across the State
MSEDCL
1.159 MSEDCL submitted that there is a need for change in procedure for classification of
Wind power Projects in Wind zone class by MEDA, as Ministry of New and Renewable
Energy (MNRE) has withdrawn the qualifying criteria of minimum Wind power density of
200 W/m2 at 50 m above ground level for establishment of Wind power Project at any site
in India. MSEDCL submitted that ascertaining the Wind zone class is a cumbersome and
tedious task considering the practical difficulties of time and labour involved. MSEDCL
submitted that considering the previous measurements and self declaration of Wind energy
generators, most of the WTGs lies in Zone I and II which are eligible for higher Tariffs.
1.160 MSEDCL submitted that there is a need of more scientific and logical approach to
establish correct Wind zone till such time Wind zone 2/3 Tariffs shall be made applicable.
Based on the above reasoning, MSEDCL requested the Commission to reconsider the zone
wise Tariff for Wind Projects in the State and determine a single Tariff for all zones.
Further, MSEDCL submitted that the Commission may incorporate the combination of
machine efficiency and the Wind velocity to decide Tariff in respect of Wind Projects.
MSEDCL submitted that most of the Wind energy potential States have only single Tariff.
IWPA
1.161 IWPA submitted that wind zones have been determined after due study by the Nodal
Agency, MEDA with assistance from Central Government Agency C-WET and also after
due discussions and deliberations with Distribution Licensees, wind farm developers and
the said approach has been approved and agreed to by MSEDCL. The classification of
zones based on available CUF has been recently concluded by MEDA by taking the views
of all the stakeholders including MSEDCL. Therefore the classification determined to be in
force for a reasonable period of 5 to 8 years before revisiting the same for any
modifications thereof.
MEDA
1.162 MEDA in its submission dated 12 April, 2013 submitted that Wind power potential of the
State is declared at central level through C-WET, which is an authority for assessment of
Order in Case No. 92 of 2012
MERC, Mumbai Page 48 of 57
wind power potential for the entire country. The bigger sized WEGs and removal of 200
watt/square meter WPD criteria will also add up to the wind potential of the State. Further,
in its submission data 17 July, 2013 MEDA submitted that MNRE / C-WET have declared
44 sites in Maharashtra which have WPD more than 200 watt per sq. meter. On these
potential windy sites, C-WET has declared potential of 5961 MW of wind power Projects
and that the installed capacity till 30 June 2013 was 3277.56 MW in the State. Further,
Wind potential of the State is estimated by the C-WET on the basis of assumption that only
2% land is available for development of wind power Project on each site. But on many
sites, land is available more than 2% and removal of 200 watt per sq. meter criteria will
increase land availability. Therefore, estimated potential of State will increase accordingly.
1.163 MEDA submitted that Wind zones have been introduced to give appropriate returns for
different wind density sites. With the introduction of wind zones, the lower Wind Power
Density (WPD) sites may also get explored. Further, MEDA submitted that the Wind Zone
classification procedure is prepared in consultation with C-WET, wind developers and all
distribution licensees. WPD of a windy site is determined on the actual wind data collection
at the site for 1-2 years and analysis of data and certification of WPD by C-WET. Project is
awarded the wind zone as per the procedure formulated by all the stakeholders. If the
Project does not fit into the parameters set in the procedure, then the Project is referred to
C-WET for Project specific WPD. Majority of the windy sites as per MEDA in the State are
low wind power density sites. Generation of electricity from any WEG is completely
dependent on availability of wind and also there is theoretical limit for conversion of wind
into electricity. New WEGs with higher hub height and higher blade diameter are designed
to convert maximum possible wind energy into electricity. Wind energy may be infirm, but
it cannot be termed inefficient.
Commission’s Rulings:
1.164 As regards the submission of MSEDCL regarding change in the procedure for wind
zoning, the Commission directs the Secretariat of the Commission to deliberate on this
issue and put up for Renewable Energy Tariff Order for FY 2014-15, considering the
submissions of MSEDCL.
Order in Case No. 92 of 2012
MERC, Mumbai Page 49 of 57
v. Renewable Purchase Obligation Target
MSEDCL
1.165 MSEDCL submitted that RPO Target should be linked with the actual potential of the
State. MSEDCL submitted that the State has Wind Energy Potential of 5439 MW of which
only 2954 MW has been achieved. Further, the actual wind generation based on installed
capacity for FY 2012 stood at around 3% of the overall energy demand as compared to the
recommended RPO of 6.75%.
IWPA
1.166 IWPA submitted that it agrees with MSEDCL that it should be linked with actual
potential of the State. Having admitted that it is only a miniscule of 3% of the overall
energy demand, MSEDCL has failed to proactively and wholeheartedly support wind
power and make efforts to control the costs emanating from the rest of the 97% of the
overall energy demand being met by conventional power. Though stipulation of RPO is
required to be realistic and probably the Commission after due deliberation has fixed the
RPO levels, the achievement of RPO levels have been further facilitated by the Hon'ble
CERC by introducing Renewable Energy Certificates and the same has been adopted at
State levels by Hon'ble MERC by stipulating that REC could be a component in bridging
the gaps, if any, in achieving the RPO obligations. IWPA further submitted that the fact of
REC in FY 2012-13 is that there are more RECs available and less takers even at the
minimum price of Rs. 1,500/- per REC. If MSEDCL is finding difficult to bridge the gap on
RPO they could very well purchase the RECs from the market. Therefore avenues do exist
in meeting the RPO obligations.
Commission’s Analysis
1.167 As regards the submission of MSEDCL regarding RPO, the Commission has given its
ruling in its Order dated 12 March, 2014 in Case No. 180 of 2013 on a similar issue
reproduced as under:
“The Commission is of the view that for realistic planning of contracting Renewable
Energy for meeting RPO, realistic CUF plays vital role. In case there is large
variation in CUF calculated by the MEDA and actual CUF achieved by Renewable
Order in Case No. 92 of 2012
MERC, Mumbai Page 50 of 57
Energy generators then it certainly affects the planning of Distribution Licensees.
Hence the Commission directs MEDA to undertake a detailed study to re-assess the
realistic Capacity Utilisation Factor (CUF) for Wind power projects in the State with
the help of reputed technical institutes within six months from the date of this Order.”
vi. Restriction on Number of WTG
MSEDCL
1.168 MSEDCL submitted that there is a need for restriction on number of WEGs per consumer
considering the consumer Contract Demand. There should be some kind of limit on how
much capacity of Wind energy generation (MW) should cater to how much contract
demand of a consumer. e.g., TML having contract demand of 55 MVA is sourcing Wind
power from 90 MW of WTGs and therefore occupying large capacity.
1.169 MSEDCL submitted that there shall be a limit of Wind power capacity say 20% more
than the contract demand or as may be determined by the Commission.
IWPA
1.170 IWPA submitted that MSEDCL has given an illustration of Tata Motors and Essar Steel
and primarily emanates from difficulties in administration. IWPA submitted that
considering the wind farm developers are small entities with few MW each, restricting their
supply of power to Open Access consumers would be a retrograde step. It is already
stipulated that only developers having 1 MW and above installation can opt for Open
Access and the same has already restricted the entry of small developers. IWPA submitted
that handling a handful of wind farm developers supplying to a single Open Access
consumer should not be an issue with the modern software system available which can
make any computations in the shortest possible time.
Tata Motors Ltd.
1.171 TML submitted that MSEDCL’s entire presentation is based on the various deterrent
clauses of their earlier Commercial Circulars 147 and 155. There is no more fresh point as
of today.
Order in Case No. 92 of 2012
MERC, Mumbai Page 51 of 57
Commission’s Analysis
1.172 As regards the submission of MSEDCL regarding restriction on number of WTGs, the
Commission directs the secretariat of the Commission to analyse the above mentioned
issue and present it to the Commission.
Summary of Rulings:
Issue No. 1: Option to sell power post expiry of Energy Purchase Agreement (EPA)
1.173 The Commission has deliberated on this issue for option of sale of power after
expiry of the EPA with Distribution Licensee as is evident from the extracts of various
Orders (i.e., Case No. 33 of 2007, Case No. 89 of 2007, Case No. 58 of 2008, and Case
No. 39 of 2011). Therefore, the Commission is of the view that provisions of supply of
power to any party other than MSEDCL post expiry of EPA have been reiterated by
the Commission through its various Orders mentioned above and the same needs to be
continued.
Issue No. 2: Tenure of Energy Purchase Agreement (EPA)
1.174 The Commission notes that other State Electricity Regulatory Commissions have
also stipulated the EPA period linked to the life of the Project (i.e., EPA period has
been defined as 20/25 years).
1.175 The Commission further notes that stakeholders have also supported for having a
longer tenure of EPA for wind Projects, however, the only concern has been raised to
review the existing EPA which has been signed long before.
1.176 The Commission further notes that after the issuance of Wind Power Tariff Order,
2003 and notification of MERC (RE Tariff) Regulations, 2010 multiple options of sale
of power are now available for Wind Projects (i.e., third party sale, self consumption
under captive route, sale of power under REC schemes).
1.177 In view of the above, the Commission is of the view that there is a merit in
consideration of EPA period linked to life of the project for existing and new Projects.
Accordingly, the Commission rules that for Projects whose EPA have not expired may
Order in Case No. 92 of 2012
MERC, Mumbai Page 52 of 57
be given an option to extend EPA to Project life. The Commission hereby further
clarifies that such extension is an option available to both Parties and is not a
compulsion.
Issue No. 3: Tariff for Sale of Power after Expiry of EPA
1.178 The Commission rules that regulatory process for determination of tariff for
Group-II wind energy projects; upon expiry of validity of existing EPA, will have to
be undertaken in a transparent manner including participation of all key stake-
holders similar to any other tariff determination process. The Commission shall
initiate such regulatory process on suo-motu basis summarising key issues involved in
tariff determination for Group-II wind energy projects; upon expiry of validity of
existing EPAs. The Commission shall invite comments/objections/suggestions of all
concerned before determining Tariff for such projects.
1.179 However, for Group-IV Projects, i.e., the Projects for which tariff has been
determined under MERC (RE Tariff) Regulations, 2010, the Commission in Case No.
6 of 2013 has ruled that in the matter of Determination of Generic Tariff for the
fourth year of the first Control Period under Regulation 8 of the Maharashtra
Electricity Regulatory Commission (Terms and Conditions for Determination of
Renewable Energy Tariff) Regulations, 2010 on the issue of tariff structure, PPA and
useful life of Wind Power Plants had clarified that while tariff period is specified as 13
years, the levellisation is carried out over useful life which is 25 years and not just over
13 years, thereby ensuring the cost recovery is spread over entire useful life which also
results in back-ending of the returns
1.180 Considering the fact that for Group-IV Projects, i.e., the Projects for which tariff
has been determined under MERC (RE Tariff) Regulations, 2010, the tariff is
determined considering the levellisation over the useful life of the Wind Projects, the
Commission rules that if such Projects opt to extend the EPA period from 13 years to
25 years, the tariff determined for Wind Energy Projects for 13 years, considered
from the date of commercial operation of the Wind Project shall also be applicable
from 14th
year to 25 years.
Order in Case No. 92 of 2012
MERC, Mumbai Page 53 of 57
Issue No. 4: Obsolesce of Technology and Repowering of Wind Turbines
1.181 In exercise of the powers vested in it under Section 86 (2) of the Electricity Act,
2003, advises the Government of Maharashtra to formulate a Policy to encourage and
promote Re-powering of the existing small Wind Turbines within the State, which
could result higher generation and also lead to better utilisation of existing wind sites,
which would help to encourage the investments in the State and also help to the meet
the targets of RPO. In these circumstances, considering the infirmity of Wind Power,
the Government may also consider to frame appropriate Policies for encouraging
Pump-Storage Schemes and Energy Storage Schemes.
Issue No. 5: Objective of Renewable Energy Certificate (REC)
1.182 The Commission notes the following primary objectives identified for REC
mechanism:
(i). Effective implementation of RPO mechanism in Maharashtra
(ii). Increased flexibility for participants to carry out RE transactions
(iii). Overcoming geographical constraints to harness available RE sources
(iv). Reduce transaction costs for RE transactions
(v). Create competition among different RE technologies
(vi). Development of all encompassing incentive mechanism
Issue No. 6: Eligibility for Renewable Energy Certificate (REC)
1.183 The Commission notes the CERC in its Second Amendment to CERC (Terms and
Conditions for recognition and issuance of Renewable Energy Certificate for
Renewable Energy Generation) Regulations, 2010 (hereinafter CERC REC
Regulations, 2010) has specified the following concessional benefits for Projects which
a Project has to forego in order to avail REC benefits.
(i). Concessional/promotional transmission charges
(ii). Concessional/promotional wheeling charges
(iii). Banking facility benefit. The expression ‘banking facility benefit’ shall mean
only such banking facility whereby the CGP or any other renewable energy
Order in Case No. 92 of 2012
MERC, Mumbai Page 54 of 57
generator gets the benefit of utilizing the banked energy at any time (including
peak hours) even when it has injected into grid during off‐peak hours.
1.184 The Commission noted that CERC by way if Second Amendment to CERC REC
Regulations, 2010 had withdrawn the criteria of waiver of Electricity Duty as one of
the concessional benefits.
1.185 The Commission notes that with the implementation of REC mechanism, the WEGs
receives another source of income by way of selling of RECs on Power Exchanges.
However, under such schemes, a WEG would be selling only the electricity component
to the third party consumer and not the Renewable Energy. The Renewable Energy
Component is being sold on Power Exchanges in form of RECs.
1.186 However, the Commission directs the secretariat of the Commission to evaluate the
need of concessional benefit on CSS for open access transactions from Renewable
Energy and present it to the Commission, within next 6 months of issuance of this
Order.
Issue No. 7: Banking and Banking Charges
1.187 The Commission notes that in the Order dated 3 January, 2013 in Case No. 8 of
2012, Case No. 18 of 2012, Case No. 20 of 2012 and Case No. 33 of 2012, considering
the submission of MSEDCL regarding commercial and financial implication of
providing banking facility to wind projects, had directed MSEDCL to carry out a
detailed study based on the historical actual generation, actual power purchase cost,
incremental power purchase cost, banking, any other relevant parameters, banking
provisions provided in other States, etc.
1.188 Accordingly, the Commission directs MSEDCL to submit the said Report and based
on such findings may file a separate Petition to review the existing provision of
banking. The Commission further rules that existing banking mechanism as stipulated
in the Wind Power Tariff Order, 2003 shall be continued.
Order in Case No. 92 of 2012
MERC, Mumbai Page 55 of 57
1.189 The Commission further notes that stakeholders have opposed for levy of any
banking charges for banking facility, however, such stakeholders in other States had
supported for retaining the banking facility however with some charges.
1.190 The Commission further rules that in ad-interim basis banking charges in kind shall
be levied @ 5% on the energy banked at the end of every month and the same shall be
reduced from the energy banked at the end of the month. The Commission shall
review the same based on the Petition filed by MSEDCL in this regard.
Issue No. 8: Sale at Average Pooled Power Cost (APPC) and Compliance to RPO
1.191 The Commission notes that the CERC REC Regulations, 2010 stipulated that sale to
host Distribution Licensee at APPC by the Renewable Energy Project shall be
considered as eligible to participate under REC mechanism. Under the existing REC
mechanism approved by the CERC, Projects selling power at APPC to Distribution
Licensee would be selling only the electricity component and not Renewable Energy
component. Hence, the said purchase at APPC shall not be considered to meet the
RPO targets under the existing CERC REC Regulations, 2010 and amendment
thereof.
1.192 As regards the submission of WWIL that APPC may be declared every year, the
Commission has taken a note of same and hereby directs all the Distribution Licensees
in the State of Maharashtra to file the details of actual Power Purchase expenses of
previous year within one month after the end of previous financial year in order to
determine the average pooled cost of power purchase.
Issue No. 9: Incentives and Promotional Open Access Charges
1.193 As regards the submission of MSEDCL regarding incentives and facilities provided
by the State Government to WEGs to be treated as concessional benefits and hence
such WEGs shall not be held eligible for participation in REC scheme, the
Commission notes that the CERC REC Regulations, 2010 does not stipulates any such
concessional benefits.
Order in Case No. 92 of 2012
MERC, Mumbai Page 56 of 57
1.194 As regards the submission of MSEDCL regarding factoring of such
incentives/facilities provided by the State Government while deciding the tariff, the
Commission notes that such clarification has already been issued in the Order dated
22 March, 2013 in Case No. 6 of 2013 that in the absence of specific information as
regards nature of subsidy, its purpose, eligibility, applicability, concerned parties etc.,
the Commission is not inclined to pass generic ruling in the matter in the present
proceedings. The issue of sharing of such subsidies can be taken up based on
application filed by the concerned party.
Issue No. 11: Miscellaneous Considerations/Suggestions
(i) Details of Capital Expenditure as sought by the Commission
1.195 The Commission directs the Secretariat of the Commission to consider the above
mentioned issue as a separate exercise and present it to the Commission.
(ii) Pre-Commissioning PPA Signing
1.196 The Commission has taken a note of the suggestion made regarding signing of EPA
before commissioning of the Plant and also notes that in the past various issues related
to EPA have been submitted by various parties including Distribution Licensees. The
Commission directs MSEDCL to file a separate Petition regarding various
modifications in the EPA.
(iii) Group Captive Model
1.197 The Commission has taken a note of the suggestion made Group Captive model in
the State of Maharashtra and clarifies that Group Captive Model already exists in the
State of Maharashtra and no restrictions have been imposed in adopting the same.
The Commission clarifies that WEGs are free to choose the Group Captive Model
subject to the provisions of the Electricity Act, 2003 and the Electricity Rules, 2005
made thereunder.
(iv) Wind Zoning and Single Tariff across the State
Order in Case No. 92 of 2012
MERC, Mumbai Page 57 of 57
1.198 As regards the submission of MSEDCL regarding change in the procedure for wind
zoning, the Commission directs the Secretariat of the Commission to deliberate on this
issue and put up for Renewable Energy Tariff Order for FY 2014-15 considering the
submissions of MSEDCL.
(v) Renewable Purchase Obligation Target
1.199 As regards the submission of MSEDCL regarding RPO, the Commission has given
its ruling in its Order dated 12 March, 2014 in Case No. 180 of 2013 on a similar issue
and has directed MEDA to undertake a detailed study to re-assess the realistic
Capacity Utilisation Factor (CUF) for Wind power projects in the State with the help
of reputed technical institutes within six months from the date of said Order.
1.200 Accordingly, with the above rulings, the Suo-Motu Petition in Case No. 92 of 2012
stands disposed of.
Sd/- Sd/-
(Vijay L. Sonavane) (Chandra Iyengar)
Member Chairperson